Impact of WAMS Malfunction On Power System Reliability Assessment
Impact of WAMS Malfunction On Power System Reliability Assessment
AbstractMonitoring/control infrastructures are often assumed to be fully reliable in power system reliability studies.
However, recent investigations on blackouts have revealed the
crucial impacts of monitoring/control system malfunctions. This
paper addresses the impact of situational awareness and controllability on power system reliability assessment. A methodology is
proposed to simulate a situation in which a limitation of either
or both monitoring and control functions could spread the consequence of power system events throughout the grid. It is assumed
that the monitoring/control infrastructure is based on a wide-area
measurement system (WAMS). While the proposed methodology
is applicable to a variety of strategies for grid operations, certain
assumptions are made for the simulation purposes. The Monte
Carlo simulation is applied and a scenario reduction technique is
considered for overcoming computational burdens. The performance of the proposed approach is simulated and analyzed on
9-bus and the IEEE 57-bus systems.
Index TermsComposite system reliability assessment, observability analysis, phasor measurement unit (PMU), wide-area measurement system (WAMS).
NOMENCLATURE
Capacity of line .
Unit index.
Line index.
Bus index.
Scenario index.
Scenario index for power system.
Set of buses.
Set of lines.
in scenario .
in scenario .
I. INTRODUCTION
Synchrophasor measurement technology (SMT) was recognized as a promising alternative for enhancing the situational
awareness. It provides an unprecedented insight on the realtime state of power systems with a wide-area coverage [1][3].
Phasor measurement units (PMUs) are the building block of
SMT [3]. SMT, which is also referred to as wide-area measurement system (WAMS), is presently accounted for monitoring
and control of static and dynamic power systems.
In the literature, few studies focused on the role of monitoring/control infrastructures in the probabilistic power system
reliability assessment. Reference [4] reported a probabilistic
case study on the overall reliability of control center facilities in
Ontario Hydro. The paper considered failures in control center
equipment; however, it did not study malfunctions associated
with the supervisory control and data acquisition (SCADA)
system and their impacts on power system performance. A
joint SCADA and power system model was considered in [5]
in which the impact of SCADA failures on power system load
curtailments was analyzed. The idea was valuable; however,
the approach was not elaborated on its details. The paper
presented limitations on controllability but did not incorporate
observability deficits in power system analyses.
The WAMS applications were examined in [6] using simple
examples. The probability of successful operations was calculated based on the availability of WAMS elements. However,
the probabilistic power system analyses were preliminary. Reference [7] conducted the calculation of multiple reliability indices for a regional network of WAMS. The outages of PMUs
and communication links were considered, while those of other
key components such as measuring transformers or transmission lines were excluded. The authors extended their works in
[8] by presenting a quantitative reliability evaluation method for
the communication network of WAMS and the overall WAMS
from a hardware reliability perspective.
In [9], the observability of WAMS-based power networks was
analyzed from a probabilistic viewpoint. A probabilistic observability index was introduced for buses associated with a PMU
placement configuration. The average of bus indices represented
a system index with an insight on the overall network observability. The proposed model in [9] was extended in [10]; however, both studies were devised with the intention of PMU placement in power systems. References [6][10] studied the WAMS
performance as a single system; however, they did not investigate the impact of WAMS failures on power system performance analyses.
In this paper, the proposed methodology considers WAMS as
a viable monitoring/control infrastructure in electric power systems. This assumption is due to straightforward observability
rules embedded in the WAMS model. The WAMS application
to the enhancement of power system operation is discussed
and requirements for the joint reliability assessment of WAMS
and power system infrastructures are identified. As reliability
analyses assess the performance of static power systems, the
WAMS capability in monitoring power system dynamics is
not modeled here. This feature makes the proposed framework
applicable in the SCADA-based power systems where the
supply-demand balance and transmission system loading are
just monitored. A set of assumptions in the proposed study
represent the complexity of the problem which is, in turn, due
to miscellaneous infrastructures deployed across the world.
1303
1304
Fig. 2. Proposed algorithm for joint reliability evaluation of power system and WAMS.
given line current offers an indirect voltage measurement associated with the line other end. The
observability rules are summarized as: i) a PMU
located at a given bus would make itself and adjacent buses observable; ii) a transmission line
with observable terminals is observable since its
current and power flow could be calculated. The
addition of PMUs and the provision of redundant communication channels would enhance the
power system observability. Note as well that for
SCADA-equipped power systems, this step merely
represents the state estimation (SE). Assuming
WAMS for both monitoring and control, this step
will also identify uncontrollable parameters. In the
event of any WAMS failures, the communication
path between the control center and system buses
could become partially unavailable. Accordingly,
certain system variables would become uncontrollable. However, if the WAMS is only responsible for
the system monitoring, we assume that the system
is fully controllable for the sake of this study.
1305
A. Formulation
The OLS problem, in Step 5, is formulated in (1)(8).
(1)
Subject to
(2)
(3)
(4)
(5)
(6)
(7)
(8)
TABLE II
SYSTEM DEMAND DISTRIBUTION
TABLE III
TRANSMISSION SYSTEM DATA
Here, the joint scenario set for power system and WAMS comand
as
prises scenario sets
(9)
and
is an ordered pair of scenarios for
where
WAMS and power system.
In each scenario, the objective is to minimize the load shedding in (1). The line flow calculation (2) has a binary parameter
where 0 stands for the state of lines on outage making the
power flow of such lines equal to 0. In (3), the bus-level power
balance is considered and the units on outage are excluded by in. The load shedding varicorporating the binary parameter
is considered in the power balance equation to make
able
the problem feasible. The set of constraints (4) compels observable line flows to be within limits. The range of possible redispatch associated with controllable and uncontrollable generating units are determined by (5) and (7), respectively. Sets
of constraints (6) and (8) declare the range of deployable load
shedding associated with controllable and uncontrollable demands.
If WAMS is merely in charge of monitoring and the system
control is managed through other media such as telephone lines,
1306
TABLE IV
WAMS COMPONENTS RELIABILITY DATA
TABLE V
CASE 1: RELIABILITY INDICES
Fig. 4. Case 2, Contingency 3: load flow following line 67 outage. (a) Precascading outage. (b) Postcascading outage.
TABLE VI
CASE 2: LOAD CURTAILMENTS OF CONTINGENCIES 14
1307
TABLE IX
RELIABILITY INDICES FOR VARIOUS PLACEMENT SCHEMES OF 4 PMUS
TABLE VII
COMPARISON OF RELIABILITY INDICES IN CASES 1 AND 3
TABLE X
AVAILABILITY OF GENERATING UNITS
TABLE VIII
RELIABILITY INDICES WITH A RELIABLE WAMS
Hence, buses with large units and/or loads are better candidates for the PMU installation. However, if the value of lost
load (VOLL) or synonymously interrupted energy assessment
rate (IEAR) is considered in the power system reliability assessment, the buses serving economical or critical loads are suited
for enhancing the observability.
V. CASE STUDY AND DISCUSSION: IEEE 57-BUS SYSTEM
In this section, the proposed reliability evaluation methodology is tested on the IEEE 57-bus system [9], [10], [13]. The
system has 80 transmission lines, 7 generating units with 1975
MW generation capacity, and 42 bulk loads with 1250 MW demand. The data for the base case power flow solution are available at [19]. Generating units data are taken from [19] and their
availabilities are given in Table X. Line capacities are presented
in Table XI and their availability data are taken from [9].
Fig. 5 depicts the IEEE 57-bus system and 17 PMUs for the
WAMS network. The reliability data considered for the WAMS
components are the same as those given in Table IV. The numerical simulations consist of the following cases:
Case 1: Power system contingencies with a reliable
WAMS.
Case 2: All contingencies of power system and WAMS.
Case 3: Same as Case 2 but the controllability is fully reliable.
Table XII shows the system reliability index associated with
the three case studies. The CPU time for the calculation of Case
2 was about 30 minutes on a Core i7 1.60-GHz processor and 4
GB of RAM.
in Case 1 represents the system reliability based on
the conventional evaluation analysis.
in Case 2 shows
a 41% increase as compared with that of Case 1. So incorporating the malfunction of WAMS components, as expected, provides a more comprehensive system reliability index. In Case 3,
it is assumed that WAMS is just in charge of system monitoring
and control actions are rendered through another media which
is not affected by WAMS failures. As expected, in this case, the
is greater than that of Case
system reliability index
1308
TABLE XI
CAPACITY OF TRANSMISSION LINES
TABLE XII
SYSTEM
TABLE XIII
MAJOR LOAD POINT RELIABILITY INDICES IN CASE 2
1. This is due to incorporating the observability deficits associated with WAMS malfunctions. On the contrary, comparison
of Cases 2 and 3 reveals that accounting controllability deficits
would further deteriorate the system reliability.
The following discussion is limited to Case 2 which is the
major case study. Due to the large dimensions, it is not possible
to present the results at all load points. So the major load point
buses, with demands greater than 25 MW, are adopted and their
respective reliability indices are detailed in Table XIII. For the
reliability index is employed since
sake of comparison,
load shedding amount directly influences this index. As shown
of all buses, except bus 12, are in a same
in Table XIII,
order of magnitude. The reason can be declared through analysis of the measurement robustness associated with buses 8, 9,
and 12 as those serve largest loads. As depicted in Fig. 5, bus 8
is redundantly observable through two paths, namely PMUs at
buses 6 and 9. Also, bus 9 is equipped with its own PMU and
its observability is independent on the network topology. However, bus 12 is neither furnished with a PMU nor does it have
redundant observability sources. So the probability of observability [10] of this bus is significantly lower than those of buses
8 and 9.
As a cascading event, the concurrent outages of PMU at bus
9 and line 117 is considered. Here, buses 9, 10, 11, 12, and 55
and all linking lines are unobservable. So the overloaded line
1216 will trip. Thereafter, the overloaded line 1213 will trip.
The cascading event is ended when lines 89, 910, 911, 912,
and 1012 trip.
VI. CONCLUSIONS
contribute to load shedding and simulate major changes in reliability assessments. These events are usually overlooked in
conventional reliability evaluation studies. Numerical analyses
show that buses with large generating units and loads should be
candidates for PMU installations. It was deduced that, due to
very long execution times, a few shortcuts should be devised
to speed up the process. Scenario reduction was the approach
adopted here while other alternatives such as parallel processing
or running over pre-selected contingencies would also be possible. These studies underlined the indisputable role of information infrastructure on the power system adequacy evaluation.
Other infrastructures such as the natural gas network and water
resources could influence the problem as well and the joint analysis of all these systems should be considered in future studies.
REFERENCES
[1] Real-time application of synchrophasors for improving reliability,
North American Electric Reliability Corporation, 2010.
[2] V. Terzija, G. Valverde, C. Deyu, P. Regulski, V. Madani, J. Fitch, S.
Skok, M. M. Begovic, and A. Phadke, Wide-area monitoring, protection, and control of future electric power networks, Proc. IEEE, vol.
99, no. 1, pp. 8093, Jan. 2011.
[3] G. Phadke and J. S. Thorp, Synchronized Phasor Measurements and
Their Applications. New York: Springer, 2008.
[4] L. Wang, P. P. Gelberger, and N. Ramani, Reliability assessment of
the operational functions of a power system control center, Proc. IET
Prob. Methods Appl. Electr. Power Syst., pp. 229234, Jul. 1991.
[5] A. G. Bruce, Reliability analysis of electric utility SCADA systems,
IEEE Trans. Power Syst., vol. 13, no. 3, pp. 844849, Aug. 1998.
[6] M. Zima, M. Larsson, P. Korba, C. Rehtanz, and G. Andersson,
Design aspects for wide-area monitoring and control systems, Proc.
IEEE, vol. 93, no. 5, pp. 970996, May 2005.
[7] Y. Wang, W. Li, J. Lu, and H. Liu, Evaluating multiple reliability
indices of regional networks in wide area measurement system, Electr.
Power Syst. Res., vol. 73, no. 10, pp. 13531359, Oct. 2009.
[8] Y. Wang, W. Li, and J. Lu, Reliability analysis of wide-area measurement system, IEEE Trans. Power Del., vol. 25, no. 3, pp. 14831491,
Jul. 2010.
[9] F. Aminifar, M. Fotuhi-Firuzabad, M. Shahidehpour, and A. Khodaei,
Observability enhancement by optimal PMU placement considering
random power system outages, Energy Syst., vol. 2, no. 1, pp. 4565,
Mar. 2011.
[10] F. Aminifar, M. Fotuhi-Firuzabad, M. Shahidehpour, and A. Khodaei,
Probabilistic multistage PMU placement in electric power systems,
IEEE Trans. Power Del., vol. 26, no. 2, pp. 841849, Apr. 2011.
[11] A. J. Wood and B. F. Wollenberg, Power Generation, Operation, and
Control, 2nd ed. New York: Wiley, 1996.
[12] J. Dupacov, N. Grwe-Kuska, and W. Rmisch, Scenario reduction
in stochastic programming: An approach using probability metrics,
Math. Program., vol. A 95, pp. 493511, 2003.
[13] F. Aminifar, A. Khodaei, M. Fotuhi-Firuzabad, and M. Shahidehpour,
Contingency-Constrained PMU placement in power networks, IEEE
Trans. Power Syst., vol. 25, no. 1, pp. 516523, Feb. 2010.
[14] F. Aminifar, C. Lucas, A. Khodaei, and M. Fotuhi-Firuzabad, Optimal
placement of phasor measurement units using immunity genetic algorithm, IEEE Trans. Power Del., vol. 24, no. 3, pp. 10141020, Jul.
2009.
[15] F. Aminifar, S. Bagheri-Shouraki, M. Fotuhi-Firuzabad, and M.
Shahidehpour, Reliability modeling of PMUs using fuzzy sets,
IEEE Trans. Power Del., vol. 25, no. 4, pp. 23842391, Nov. 2010.
[16] M. J. Rice and G. T. Heydt, The measurement outage table and state
estimation, IEEE Trans. Power Syst., vol. 23, no. 2, pp. 353360, May
2008.
1309
[17] Performance requirements task team (PRTT), performance requirements, Part II, Targeted applications: State estimation, Eastern Interconnection Phasor Project, 2005.
[18] H. Pham, Handbook of Reliability Engineering. New York: Springer,
2003.
[19] MATPOWER [Online]. Available: http://www.pserc.cornell.edu/matpower
Farrokh Aminifar (S07M11) received the M.Sc.
and Ph.D. degrees in electrical engineering from
Sharif University of Technology, Tehran, Iran, in
2007 and 2010, respectively.
He worked with the Electrical and Computer
Engineering Department at Illinois Institute of
Technology, Chicago, as a Research Associate.
Currently, he is a Postdoctoral Fellow with the
Electrical Engineering Department Sharif University
of Technology, Iran. His research interests include
wide-area measurement system, reliability modeling
and assessment, and smart grid technologies.
Dr. Aminifar is the Guest Editor of a Special Issue on Microgrids of the IEEE
TRANSACTIONS ON SMART GRID. He received the IEEE Best Ph.D. Dissertation
Award from Iran Section for his research on the probabilistic schemes for the
placment of phasor measurement units.