Determining Activity Durations: Purpose
Determining Activity Durations: Purpose
32R-04
2 of 12
Completed Activity
Completed Project 1
Completed Project 2
Actual
(Days)
10
5
Duration
3 of 12
8
6
Assume that these original activity durations are normally distributed, to compute a
confidence interval on the mean duration. This is better than just taking an average since
it gives a range of values instead of a single number. Details on calculating confidence
intervals can be found in many texts. The confidence interval for the above example
would be roughly 7 Days 2
Days. This means that the next duration could be
anywhere from 5 to 9 days. This calculation gives the shortest and longest probable
activity original durations based on historical data.
3. Professional judgment may be used to help determine an activitys estimated duration. Often,
key project team members can provide their experience related to particular types of work
activities. Their knowledge may reveal that doing work in certain geographical areas or under
specific climatic conditions generally takes shorter or longer than anticipated. Utilizing the opinion
of an experienced professional helps identify known working restrictions to consider when
assigning original durations to those activities.
Phase II Adjust Activity Duration Based on Constraint Impact
Once a well thought out and developed plan has been prepared using the unconstraint activity durations
determined on phase 1, and the scheduler has understood the dynamics the effect of activity durations
have on the plan as a whole, then it should proceed to consider any effects that constraints (i.e. site,
location, seasons, etc.) might have on the activity durations.
The impact of constraints on activity duration must be considered and accounted for when estimating
activity duration. Some constraints may only affect certain activities and not others. The proposed
method suggests creating a list of possible constraints. The list should include any known or anticipated
constraint that could adversely affect activity duration. The list should then be cross referenced against
each activity to determine if the constraint could potentially affect that particular activity. Factors to
consider include:
Resource availability
Factors affecting productivity
Nature of the work / scope of work
Labor & Equipment productivity (means and methods) planned
Management Skill / Constraints
Material & Equipment availability
Seasonal / Location considerations
Work Restrictions (Union vs. Non-Union, Work rules & constraints, etc.)
Quality of Work (contract specifications requirements)
Subcontractor & Vendor considerations
Engineering deliverables / Client, Third-Party influences and deliverables
Fast Tracking / Concurrency of work
If the constraint has the potential to affect an activity, the scheduler should create a calendar that takes
into consideration the constraints that affect any of the activity resources or the activity scope per se. Not
all constraints can be modeled through resource and activity calendars. In such instances, it is critical to
fully document all assumptions and activity duration modifications.
An example of a constraint might be equipment availability. Suppose a portion of a project includes
machining secondary parts on an existing milling machine during the month of January. It is also known
that January is generally a high production time and that the milling machine generally runs high priority
parts during this period. Since we may not be able to run all of our parts at once, assign a calendar to the
Copyright 2009 AACE International, Inc.
4 of 12
5 of 12
January 27, 2009
6 of 12
January 27, 2009
7 of 12
January 27, 2009
8 of 12
iii. If an AS date is missing and a valid actual finish of the activity (AF) date is given, remaining durations
and percent completes are ignored and the activity (revised) duration is determined on the basis of the AF
and the specified duration.
iv. If AS and AF dates are missing the activity (revised) duration is determined on the basis of the
remaining duration and percent complete.
Duration relation with start and finish dates
The following conventions usually apply when either actual start (AS) and/or finish (AF) dates are
specified for an activity:
i. If both AS and AF dates are specified, the activity (revised) duration is computed as the time
period, between the AS and the AF, excluding non working periods.
ii. If AS is specified without an AF the activity (revised) duration is computed as the sum of the elapsed
duration and the remaining duration.
iii. If AS is specified and both an AF and an RD are missing the activity (revised) duration is computed on
the basis of the elapsed duration and the percent complete.
iv. If AS is specified and AF, remaining duration or percent complete are not specified, the activity
duration is not revised.
v. If the time elapse between the AS and the time now is greater than or equal to the duration of the
activity, the activity is assume to have finished at the appropriate time.
Risk and activity duration variability
Several alternatives have been devised to take into consideration risk when determining the activity
duration. As mentioned at the beginning of this RP in the P.E.R.T. is a probabilistic or stochastic network
model that uses three duration estimates; variations to the three point estimate have been derived using
weighted average for triangular and beta distributions. For example:
i.
9 of 12
5.1.b
10 of 12
Design WBS
(Figure 1)
Activity 1
Estimated
Hrs
to
Complete
Crew Size
20
100
10
1
2
1
Activity 2
Estimated
Hrs
to
Complete
Crew Size
30
50
45
2
1
1
Once this table has been created for each activity the duration can be estimated for the activities
using the following formula:
Where,
R1, R2...Rn = the resources needed to complete each portion of an activity.
Crew Size = the number of each resource used to complete the activity.
11 of 12
Each resource (R1, R2, R3,etc.) work only on their portion of the activity (no cross-trained
resources)
Resources DO NOT work in parallel to accomplish the work
The schedule logic is correct.
Design WBS
Activity 1
Estimated
Hrs
to
Complete
Crew
Size
Duration
(Days)
Workload
Factor
(number of units)
New
Duration
(Days)
20
100
10
1
2
1
2.5
6.25
1.25
2.0
3.0
2.0
Activity Duration
5
18.75
2.5
26.25
Activity 2
Estimated
Hrs
to
Complete
Crew
Size
Duration
(Days)
Workload
Factor
(number of units)
New
Duration
(Days)
40
60
40
2
1
1
2.5
7.5
5.0
2.0
3.0
2.0
Activity Duration
5.0
22.5
10.0
37.5
For resources working in parallel the MAXIMUM duration calculated between resources would be used.
For example, the total duration for Activity 1 would be nineteen (18.75 rounded) days instead of twentytwo (26.25) days. Activity 2 would be twenty-three (22.5 days rounded) rather than thirty-eight days (37.5
days rounded).
While this model provides a way to determine activity original durations, it should not be used as the sole
basis for deciding original durations. As the flowchart shows, all data should be merged to make a
decision on an activitys duration. By using more than one approach to determine original durations, the
scheduler can get a much better idea of how the work will be performed. Ultimately this results in a
project schedule which has a greater opportunity for successful completion.
TERMS, ACRONYMS AND DEFINITIONS
Note: Upon acceptance of this RP, these terms and definition will be removed and incorporated
into AACEs Recommended Practice 10S-90 Cost Engineering Terminology
Workload Factor - The amount of work assigned to or expected from a worker during a specified time
period expressed as a multiplier of the standard crews productivity with 1.0 equal to the same
productivity and 2.0 equal to one half of the standard productivity.
12 of 12
January 27, 2009
WORK DAY
Activity Duration
Calendar
REFERENCES
1. AACE International, Recommended Practice No. 10S-90, Cost Engineering Terminology, AACE
International, Morgantown, WV, (latest revision).
2. AACE International Recommended Practice No. 29R-03 Forensic Schedule Analysis, (Section 2.3
Schedule Updates: Validation, Rectification, and Reconstruction (SVP 2.3), D. Special Procedures, b.
Blinders Method, page 27; and Section 4.3 Critical Path and Float, pages 93-94), AACE International,
Morgantown, WV, (latest revision).
3. Thomas E. Glavinich, Construction Planning and Scheduling, The Associated General Contractors of
America, 2nd Edition, 2004.
4. Burman, Peter J, Precedence Networks for Project Planning and Control, (Chapter 7 Estimates of
Duration, pages 73-85), Reprinted in USA by Blitz Publishing Company with permission from
McGraw-Hill Book Company (UK) Limited and the author, 1980.
5. Hollmann, John K., Editor, Total Cost Management Framework: An Integrated Approach to Portfolio,
Program, and Project Management, (Chapter 7.2 Schedule Planning and Development), AACE
International, Morgantown WV, 2006.
CONTRIBUTORS
Rey F. Diaz, PE (Author)
Edward E. Douglas, III CCC PSP
Donald F. McDonald, Jr. PE CCE PSP
Dr. David T. Hulett