1.1 Purpose of The Risk Management Plan
1.1 Purpose of The Risk Management Plan
1.1
INTRODUCTION
PURPOSE OF THE RISK MANAGEMENT PLAN
[Provide the purpose of the Risk Management Plan.]
A risk is an event or condition that, if it occurs, could have a positive or negative effect on
a projects objectives. Risk Management is the process of identifying, assessing,
responding to, monitoring, and reporting risks. This Risk Management Plan defines how
risks associated with the project will be identified, analyzed, and managed. It outlines how
risk management activities will be performed, recorded, and monitored throughout the
lifecycle of the project and provides templates and practices for recording and prioritizing
risks.
The Risk Management Plan is created by the project manager in the Planning Phase of the
CDC Unified Process and is monitored and updated throughout the project.
The intended audience of this document is the project team, project sponsor and
management.
2
2.1
2.2
RISK IDENTIFICATION
Risk identification will involve the project team, appropriate stakeholders, and will include
an evaluation of environmental factors, organizational culture and the project management
plan including the project scope. Careful attention will be given to the project deliverables,
assumptions, constraints, WBS, cost/effort estimates, resource plan, and other key project
documents.
A Risk Management Log will be generated and updated as needed and will be stored
electronically in the project library located at <file location>.
2.3
RISK ANALYSIS
All risks identified will be assessed to identify the range of possible project outcomes.
Qualification will be used to determine which risks are the top risks to pursue and respond
to and which risks can be ignored.
2.3.1
Impact
High Risk that has the potential to greatly impact project cost,
project schedule or performance
Medium Risk that has the potential to slightly impact project
cost, project schedule or performance
Low Risk that has relatively little impact on cost, schedule or
performance
Impact
H
M
L
L
M H
Probabili
ty
Risks that fall within the RED and YELLOW zones will have risk response planning which
may include both a risk mitigation and a risk contingency plan.
2.3.2
2.4
2.5