0% found this document useful (0 votes)
72 views6 pages

CT Measuremnt CSK 14-15 CSK Only

This document provides instructions for a coursework assignment on surveying and construction technology. It describes two tasks: Task 1 involves analyzing construction methods for building an underground car park basement, including differentiating bottom-up and top-down construction approaches. Students must select a method and provide details of formwork, concrete work, and sequencing for the reinforced concrete frame above ground. Task 2 requires taking off quantities for formwork and concrete only from provided drawings, and producing a bill of quantities in CEMM4 format. Submissions must be electronically through Turnitin, include all working, follow prescribed formatting, and attribute references properly. Late submissions within 24 hours receive a 5% penalty, while later work receives zero marks

Uploaded by

Jay Say
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
72 views6 pages

CT Measuremnt CSK 14-15 CSK Only

This document provides instructions for a coursework assignment on surveying and construction technology. It describes two tasks: Task 1 involves analyzing construction methods for building an underground car park basement, including differentiating bottom-up and top-down construction approaches. Students must select a method and provide details of formwork, concrete work, and sequencing for the reinforced concrete frame above ground. Task 2 requires taking off quantities for formwork and concrete only from provided drawings, and producing a bill of quantities in CEMM4 format. Submissions must be electronically through Turnitin, include all working, follow prescribed formatting, and attribute references properly. Late submissions within 24 hours receive a 5% penalty, while later work receives zero marks

Uploaded by

Jay Say
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

SCHOOL OF ARCHITECTURE, COMPUTING &

ENGINEERING

Work to be submitted via the Turnitin Link located on the EG4104 Moodle site.
All work to be included in ONE Word or pdf document including tables photographs,
and diagrams, scanned in electronically where required..
Any work submitted beyond the deadline will receive the same penalties as a normal
hardcopy submission.

Module code

EG4104

Module title

Surveying & Construction Technology

Module leader

Richard Latham

Assignment tutor

Mike Hurst / Ian Lemon

Assignment title

Construction Technology & Measurement Report

Assignment number

Component 1 - Construction Report

Weighting

30% Module
tbc

Handout date
Submission date
Learning outcomes
assessed by this
assignment

Mon 20th April 2015 at 10pm - Online Submission only via Turnitin
Only.

Turnitin submission
requirement
Other electronic system
used?
Additional information

Describe main types / methods of construction technologies used in the


production of modern buildings / structures
Describe main types/ methods of construction technologies used for
simple and civil engineering projects
Take off quantities in accordance with CESMM4, measure work and
prepare a simple bill of quantities

Yes
Turnitin GradeMark feedback
used?
No
Are submissions / feedback totally yes
electronic?
Electronic Submission at 10:00pm by Turnitin only There will be
no hardcopy submission required.
Feedback will be available online through Turnitin @ 3-4 weeks
later.
Yes

Form of assessment:
Individual work

Group work

For group work assessment which requires members to submit both individual and group work
aspects for the assignment, the work should be submitted as:
Consolidated single document

Separately by each member

Number of assignment copies required:


1

Other

Assignment to be presented in the following format:


On-line submission
Stapled once in the top left-hand corner
Glue bound
Spiral bound
Placed in a A4 ring bound folder (not lever arch)
Note:

To students submitting work on A3/A2 boards, work has to be contained in suitable


protective case to ensure any damage to work is avoided.

Soft copy:
CD (to be attached to the work in an envelope or purpose made wallet adhered to
the rear)
USB (to be attached to the work in an envelope or purpose made wallet adhered to
the rear)
Soft copy not required

University of East London


School of Architecture Computing & Engineering
EG4104 Surveying & Construction Technology
Task 1 Scenario
Further accommodation is required for teaching facilities to the rear of the new Business
School at the (Docklands Campus). This will require the construction of a 4 storey r.c.
framed building with a basement car park to be built next to the west of the existing
Library. The floors, columns and beams are to reinforced insitu concrete above ground
level with non-loadbearing brick cladding and sealed unit double glazed windows.
See Figure 1 : Site Layout Plan for details
Two trial holes were taken which revealed sandy clay down to 12m overlain by made
ground and building debris/old shallow strip foundations. The water table was located at
a depth of 1.5 m below ground level.
Task 1
i)

Differentiate between the following two methods of basement construction in how


they are built and where each would be used:
(1) Bottomup construction
(2) Top-down construction
10 Marks

ii) Select a suitable method to build the new basement as described in the scenario above
including all required temporary works. Produce a neat accurate labelled vertical
section through the underground car park to illustrate your construction methods.
Include details of the dewatering method to be used. Clearly explain the sequence of
works required.
20 Marks
iii) Describe and explain with the use of neat labelled diagrams the sequence, techniques
and temporary works needed to construct the r.c. frame elements, namely:
(1) The columns
(2) The beams
(3) The floors
Ensure that you describe good formwork and concrete practices that should be
used in each case.
Task 2

30 Marks
With references to the drawing issued for your Constructionarium field project, either the
Gurkin Tower or the Donn Valley Stadium, you are required to :
Take off all the quantities of your project for the formwork and concrete works only to
CEMM4 on standard dimension paper only. You will exclude excavation works, backfilling
and reinforcement. Pictorials can be used to aid the process, ensure all waste calculations
are shown clearly along with classification numbers.
Note that all formwork will be fair faced finished, all concrete C40. From the taking off
produce a priced Bill of Quantities to CEMM4 order, with correct collection and summary
pages clearly labelled. Costs can be taken from the CEMM3/4 pricing manuals or Laxtons
pricing books from the library (read only). All descriptions must be clear, follow taking off
methods used in the class lectures.
40 marks

Submission of Coursework
1.
2.

3.
5.
6.
7.
8
9.

All the work must be the students own.


Work is to be word processed and this should be in a clear legible typeface and
double line spaced, single sided. Calculations must be logically laid out so that
they can be easily checked. Sketches can be in pencil with inked notes, CAD or
Word, but must be scanned and included in electronic submission. All pages should
be clearly numbered.
Submissions must be properly structured, this involves pre-planning your work. A
conclusion will be expected.
The work must have a bibliography and/or a list of references used, properly cited
within the text. All referenced to CITE THEM RIGHT.
In industry presentation of information is of paramount importance. Marks will be
awarded for the quality of the presentation skills used.
All work submitted electronically via the Turnitin Link provided only. No other
form of submission paper based or electronic will be accepted.
If the file is too large to upload in its original form e.g. Word or PowerPoint then
the work should be saved as a pdf which should compress pictures and scans.
The information to be included on the front sheet of the assignment is as follows:
a)
b)
c)
d)
e)
f)

10.

The University and Department Titles.


Students full name, course title and year.
The Unit/Unit Number and Title.
The Title of the piece of work.
The date.
The assignment brief does not need to be submitted

Work which is submitted after the due date (or such extended date as agreed) but
within 24 hours of original submission time will receive a 5% penalty. Any work
received after 24 hours of the due date will receive zero marks. Students who
make an attempt at any part of the coursework will be deemed to have taken an
opportunity as described in the student handbook.

DOWN

Public Highway (location of all existing mains services)

Possible temp. vehicular access

Pavement / verge

NORTH

Proposed Access Ramp to basement car park


Site Boundary
Knowledge Dock

New
Teaching
Block with basement
& Library

Royal Albert Dock

0m

30m

Approx. Scale

Fig 1: Site Layout Plan

You might also like