User Manual PM02 - Maintenance OrderCycle
User Manual PM02 - Maintenance OrderCycle
User manual
Maintenance Order
Cycle
Prepared
by:Chandan
Kumar
09Sept 2014
BCML
Table of Contents
Scenario
1.1.1
1.1.2
1.1.3
Responsibility
1.1.4
Screen capture
12
1.2.1
12
1.2.2
12
1.2.3
Responsibility
12
16
1.3.1
16
1.3.2
16
1.3.3
Responsibility
16
1.3.4
Screen capture
16
19
1.4.1
19
1.4.2
19
1.4.3
Responsibility
19
1.4.4
Screen capture
19
21
21
1.5.2
21
1.5.3
Responsibility
21
1.5.4
Screen capture
22
24
1.6.1
24
1.6.2
25
1.6.3
Responsibility
25
1.6.4
Screen capture
25
PwC
28
28
Page 2 of 40
BCML
1.7.2
28
1.7.3
Responsibility
29
1.7.4
Screen capture
29
31
1.8.1
31
1.8.2
31
1.8.3
Responsibility
31
1.8.4
Screen capture
32
33
33
33
2.1.2
34
2.1.3
Responsibility
34
2.1.4
Screen capture
34
3 Appendix
36
3.1 Table
PwC
36
3.1.1
36
3.1.2
36
3.1.3
PM Activity type
36
3.1.4
37
Page 3 of 40
BCML
Scenario
Maintenance order will be created in system to plan and execute the maintenance work required in
Season and Off season. Maintenance order will have information of dates, operations, material and
WBS required for the maintenance work.
The Maintenance order will always be created with a WBS element attached to it. Budget check will
happen on the material and services cost when user tries to save the order. Budget check can
refuse, allow or allow with warning as per the amount available in the WBS budget.
Select the appropriate type of Maintenance order for the purpose. Maintenance order can be created
from the Notification as a continuation of the incident reported, or directly in system.
These Maintenance order types that will be used in case of Season maintenance are
PM01- Breakdown Maintenance Unplanned maintenance order getting created from M2/ZS
type Notification created in section 3.2 above.
ZRM1 Seasonal Routine Maintenance Order will be created manually by the maintainer
and it will have no reference to any notification. It will be created to capture the following
activities (evaporator cleaning, general maintenance of standby equipment). To create this
type of maintenance order, the equipment should exist in the SAP system.
In case of Off Season Maintenance, user will create only ZM03 type of Maintenance order.
The following linkages are configured in system for the Notification type and order types and system
automatically proposes the correct Order type when user tries to create Order from Notification.
Notification type
M1 preventive/ Scheduled
M2 Breakdown
M3 Corrective
ZM Opportunity
PwC
Order type
PM03 Scheduled Maintenance
PM01 Critical/ Breakdown Maintenance
PM02 Corrective Maintenance
-
Page 4 of 40
BCML
ZS Equipment Stoppage
1..1
Order can be created along with the Notification from t-code IW22. When notification is finally saved
maintenance order is generated along with notification. Two numbers are generated, one for
Maintenance order number and another for Notification number.
1..1
Menu Path and Transaction code
SAP R/3 menu
SAP Menu > Logistics >Plant Maintenance>Maintenance processing
>Notification> Create(General)
Transaction code
1..2
IW21
Responsibility
1..3
Screen capture
Fill the details for Notificaiton screen entry fields as explained in User manul PM01 sec 1.1.4. After entering the
details for notificaiton click on the icon
The next popup window takes the correct order type by default and asks you to confirm to take the process
forward to create maintenance order. The planning plant, Main work center gets auto filled based on the
reference object (Equipment/FL) selected in the notification.
PwC
Page 5 of 40
BCML
PwC
Page 6 of 40
BCML
Input Field
Mandatory/Optional
Available Values
Order type
Mandatory
Auto Fill
Planning plant
Mandatory
Auto Fill
Work Centre
Mandatory
Auto Fill
New screen appear for Maintenance order creation. Fill in the details in the maintenance order as shown
below. Note that you are working in the Header tab of the MO(Maintenance Order). Similarly you need to fill
the details in the other tabs like Operation and Components. You need to fill the WBS information in the
Additonal Data tab.
Rest other tabs like Cost, Objects, Location, Planning, Control displays the data which gets autofilled.
PwC
Page 7 of 40
BCML
These are the stesps in the processing of a maintenance order as mentioned below. Remember that the
maintenance order can be created through an Notification or directly(IW31). In both cases the processing steps
of MO remains the same.
There are some mandatory fields in the MO which must be filled to save an order. Like WBS element field in the
Additonal data tab and simlar other where system prompts you with a warning for data entry and doesnt lets
you go to further step.
Operation planning in MO
Material Planning in MO
Release of MO(REL)
Material Issue to MO
PwC
Page 8 of 40
BCML
Operation confirmation in MO
TECO(Technical Confirmation) of MO
Settlement of MO
The maintenace order shows the system status in the status bar which indicated the present status of the order.
This helps you to determine the next process required to be done to further complete the MO cycle.
Header Data:
Input Field
Person Responsible-Planner grp,
PwC
Mandatory/Optional
Optional
Input Values
Select the correct value for Planner
Page 9 of 40
BCML
Mandatory
Optional
Mandatory
Optional
Mandatory
Mandatory
Optional
Optional
Optional
PwC
Page 10 of 40
BCML
Account Assignment:
Enter the WBS in the Additonal Data field, this is required for selecting component against a particular
WBS(work breakdown structure) related to that plant and section. Use search help to select the correct WBS for
PwC
Page 11 of 40
BCML
the job. Each WBS element is aggined a budget in the Project Sysem(PS) module and Budget Check happens at
the time of save.
1.2.2
Menu Path and Transaction code
SAP R/3 menu
SAP Menu > Logistics >Plant Maintenance>Maintenance processing
PwC
Page 12 of 40
BCML
>Notification> Create(General)
Transaction code
1.2.3
IW21
Responsibility
Selecting the correct component (Material) in the Components tab of the MO:
User will run a search to select the material or directly enter the material code if known in the Component
column undet the Components.
Press F4 or click in the component field and run search
PwC
Page 13 of 40
BCML
Selec the Special stock indicator as required, explained above. By default , the Special Stock Indicator is fixed at
Plant stock (Normal stock)= blank, you will be required to select Spl Stk Ind =2.
A reservation number in generated in the system for material (component) selected in the MO. To get the
reservation number against the component selected in the order, select the component line item and click on
the Gen Data icon below.
PwC
Page 14 of 40
BCML
PwC
Page 15 of 40
BCML
This Reservation number is required in the MM module to trace the origin of Material issue request and
associted account assignement. That is to say the Reservation number carries information about the MO
number, and account posting information for the material issue and cost calculation.
System confirm the saving of Notification with Order and generates identification numbers to them.
Once the maintenance Order is saved and a particular number assigned, it is ready to be released.
The following activities are only carried out further when the order gets the status released, REL in
the system status bar.
PwC
Page 16 of 40
BCML
1.3.2
Menu Path and Transaction code
SAP R/3 menu
SAP Menu > Logistics >Plant Maintenance>Order> Change
Transaction code
1.3.3
IW32
Responsibility
1.3.4
PwC
Screen capture
Page 17 of 40
BCML
When the order is opened in the Change mode and has status CRTD, it can be released by clicking on the
green flag icon as shown below.
A message in the below status bar appears that Order 6000XXX will be released after update. Save the order
and it gets released.
PwC
Page 18 of 40
BCML
The system status of the MO changes to REL. The released order is now available to MM and FI department
for material issue, services PR (Purchase Request), and filling service entry sheet.
The Order cant be un- released once marked REL.
Input Field
Mandatory/Optional
Available Values
Event
Mandatory
PwC
Page 19 of 40
BCML
1.4.3
IW32/33
Responsibility
1.4.4
PwC
Screen capture
Page 20 of 40
BCML
Estimated cost is fixed as entered at the time of creation, planned cost and actual cost get updated when user
makes changes in the component or crates an external service request.
Input Field
Mandatory/Optional
Available Values
Envent
Display
After feeding the above inputs, press Enter to move to the next screen.
Document Flow:
When documents (material and financial or costing) are generated by system due to the transactions made
against the MO, they gets updated in the order and can be viewed from inside the MO. For example when
Material component is issued for the reservation number(created from Order), it generates a material issue
document in system, this material document is then visible in the Document Flow of the order.
PwC
Page 21 of 40
BCML
Click in the icon as shown above. The detailed page shows the documents generated against the Order.
PwC
Page 22 of 40
BCML
1.5Confirm Operation
1.5.1 Definition and Prerequisites
When the work activity is complete, the operations in the MO should be confirmed in system. The actual time
taken to complete the work activity must be entered in the confirmation screen (IW41) against the order
number and operation selection.
When all the operations of the MO are confirmed, the order status changes to CNF. In case not all the
operations are confirmed, and at least one is confirmed, the status order changes to PCNF.
1.5.2
Menu Path and Transaction code
SAP R/3 menu
SAP Menu > Logistics >Plant Maintenance>Order> Change/Display
Transaction code
1.5.3
IW41
Responsibility
1.5.4
PwC
Screen capture
Page 23 of 40
BCML
The time duration in field work is entered at the time of creating the order as a planned value. These
operation duration is confirmed and actual time taken to complete the operation is entered against the order
number in the confirmation screen.
Go to the transaction IW41 and enter the MO number. Press Enter
Select the Operations to be confirmed from the list of operations of the MO. Click on icon Actual Data or
press F8.
PwC
Page 24 of 40
BCML
Order operation confirmation screen is opened to fill the actual time taken to complete the operations. Fill the
Actual data for the operation number of the Order.
Save the entries, use keyboard short cut Cntrl+S or press icon
CNF after all the operations are confirmed as shown below.
PwC
Page 25 of 40
BCML
1.6.1
Definition and Prerequisites
When all the field activities for the operations in the MO are complete from technical (Plant Maintenance) point
of view, the order status can be set to Technically complete. The system updates and assigns a system status
of MO as TECO.
After TECO the following financial posting activities can still be performed on the MO
Invoice posting for the External services taken
Invoice posting for the Material(component) purchased
Settlement of MO cost to cost centre
The following activities are not possible on MO after its status has been set to TECO
PwC
Page 26 of 40
BCML
1.6.2
Menu Path and Transaction code
SAP R/3 menu
SAP Menu > Logistics >Plant Maintenance>Order> Change
Transaction code
1.6.3
IW32
Responsibility
1.6.4
Screen capture
System asks for the settlement rule for the MO at the time of TECO if not entered earlier. Enter the settlement
rule with the parameter shown. The cost centre must be selected appropriately (using F4 search help) where
the cost of the maintenance order should be booked.
The settlement Cost Centre = Cost Centre in the Location tab of the Equipment/Functional location .
PwC
Page 27 of 40
BCML
System presents a Pop up window to confirm the Reference date and time of TECO. Confirm the information,
select Breakdown and Notification Completion if required and press enter.
PwC
Page 28 of 40
BCML
The MO system status now set to TECO and no further changes can be done in the order from maintenance
point of view.
PwC
Page 29 of 40
BCML
In case some change must be made or to open the order again after month end settlement, the MO can be
reversed from TECO status.
To change the status back to REL, select the path in the change mode (IW32) of Order.
OrderFunctionCompleteCancel technical completion
The MO status changes to REL again and further maintenance related activities can be performed on the same
order.
PwC
Page 30 of 40
BCML
1.7.1
Definition and Prerequisites
Maintenance orders will be settled periodically (monthly) to settle all the actual costs accumulated on the order.
The purpose for carrying out settlement is to send the actual cost on the MO to the correct receiving Cost
Center.
This transaction will be carried out in FICO module and maintenance orders will be settled in mass as part of
the month end activity.
However, to settle a single order if required can be carried out using the following process by PM user also.
1.7.2
Menu Path and Transaction code
SAP R/3 menu
SAP Menu >Accounting>Controlling>Internal Orders>Period-End
Closing>Single Functions>Settlement>Individual processing
Transaction code
1.7.3
KO88
Responsibility
1.7.4
Screen capture
Go to tcode KO88. Enter the details for Order number and posting timeline. Select default setting for
Processing type = Automatic.
PwC
Page 31 of 40
BCML
Settlement can be run in test mode also to check the Sender, Receiver and amount settled. To actually settle
remove the Test Run tick mark in the check box and execute
PwC
Page 32 of 40
BCML
PwC
Page 33 of 40
BCML
1.8.1
Business closure (CLSD)of a maintenance order will be carried out at the end when the order is already TECO,
settlement executed and there are no pending FI (invoice) posting on the order.
This transaction will be carried out by the FICO users to close the PM orders along with other internal orders on
a periodic basis.
However, to close a single order if required can be carried out using the following process by PM user also.
CLSD orders can be revoked for processing again.
1.8.3
IW32
Responsibility
PwC
Page 34 of 40
BCML
To revoke the status of CLSD, open the order in change mode and select the path shown below to cancel the
business completion of the MO
PwC
Page 35 of 40
BCML
PwC
Page 36 of 40
BCML
2.1.2
Menu Path and Transaction code
SAP R/3 menu
SAP Menu >Logistics>Plant Maintenance>Maintenance
Processing>Order>Create(General)
Transaction code
2.1.3
IW31
Responsibility
2.1.4
Screen capture
Fill the details on the entry screen for creating order. Select the order type, Priority, Equipment, functional
location, planning plant and Business area. The Business area is the same as the Planning Plant.
PwC
Page 37 of 40
BCML
Press enter and a pop up window appears to provide information about the Breakdown reported, notification
and order created for the Object (Equipment/Functional location).
The Next screen is the same screen for creation of Order as explained earlier in section 1.1 onwards.
PwC
Page 38 of 40
BCML
Fill the details for objects, account assignment, material and service request, WBS and save the order.
Depending upon the order type system might ask to fill the Breakdown date time details to fill the information
in the Notification that would be generated along with the order.
3 Appendix
3.1
Table
The following tables help in selecting the correct value in the for the Key Data structures. The values shown are
3.1.1
PwC
Engineering
Page 39 of 40
BCML
GEN
PRO
3.1.2
3.1.3
3.1.4
PwC
General
Process
PM Activity type
All Plants
Mechanical
Electrical
Instrumentation
CIVIL
GENL
Civil
General
101
102
103
Inspection
AMC
Repair
104
105
106
107
108
Service
Modify
NR jobs- Capitalize
Replacement
Routine
P01
P02
P03
Assembly
Calibration
P04
P05
P06
P07
P08
P09
P10
P11
P12
P13
P14
P15
P16
P17
P18
Dismantling
Erection
Fabrication
Fitting
Inspection
Insulation
Laying of cables
Miscellaneous
Painting
Repair
Rewinding
Sheeting
Shifting
Testing
White washing
Cleaning
Page 40 of 40