Datasheet API Standard 53
Datasheet API Standard 53
Standard
53
Edition
4th Edition,
Nov. 2012
Section
Inquiry #
Question
6.3.1.1
7.3.1.1
7.4.1.1
53-01-13
Reply
The intent is that compliance with the normative references applies
at the time the rig is built and/or the BOP system or components
are installed. This can also be affected by a contractual
agreement or regulatory requirements.
53
4th Edition,
Nov. 2012
6.2.3.2.2
53-09-13
Section 6.2.3.2.2 a) advises what the minimum nominal I.D. for choke
lines by pressure rating only. For pressure rated systems 10K and
above, is a 3 in. nominal I.D. choke line required for 4-inch. and 7-inch.
through-bore BOP equipment?
4th Edition,
Nov. 2012
6.2.3.2.2
53-02-14
Referring to Section 6.2.3.2.2, can you please clarify further the meaning
of the size range shown and your interpretation of nominal diameter?
4th Edition,
Nov. 2012
6.3.5
53-12-13
Is API 53, Sections 6.3.5.4 and 6.3.5.5 saying that the pumps need to be
checked on the initial test and the subsequent tests, only on the initial
test, or only when the equipment owners PM program requires it?
Yes; the intent of 6.3.5.4 and 6.3.5.5 is to conduct the test at predeployment, initial latch-up, and not-to-exceed six months. Any
other testing is at the discretion of the equipment owner or other
applicable requirements that fall outside of API 53.
Page 1 of 7
Standard
53
Edition
4th Edition,
Nov. 2012
Section
Inquiry #
Question
6.3.11.2.5
7.3.13.2.5
7.4.8.2.5
7.3.13.2.5
53-03-13
A drilling contractor has a new rig with a subsea MUX stack and subsea
conventional stack (for weight on older wellheads). They have stated
that the drape hose are below the moonpool and that the shielding is
more for wave motion than fire rating. The moon pool conduit lines are
hard pipe.
Sections 6.3.11.2.5, 7.3.13.2.5, 7.4.8.2.5, and 7.3.13.2.5 are ambiguous
with respect to the requirement of fire retardant hoses. It is our
understanding that the requirement in 7.3.13.2.5 takes precedence and
hence the hoses should not be fire retardant.
The note in Std 53 indicates that the API requirement assumes that a fire
in the moonpool would burn out the conduit hoses and hence trigger the
deadman system if the electrical signals are also lost. For our deepwater
semis however, it is not likely that the hoses are affected by a fire in the
moonpool as the hoses are hanging below bottom box of the rig. There
is no requirement in the API of how short time the hose should sustain a
fire, and hence the design will not be a proper form of weak link design.
Can you clarify if a fire retarded hose for the conduit line and hot line will
fulfil the requirements in Std 53?
53
53
4th Edition,
Nov. 2012
6.3.8
53-16-14
4th Edition,
Nov. 2012
6.5.3
53-01-14
4th Edition,
Nov. 2012
6.5.3.4.1
53-05-13
Reply
Keep in mind that API 16D is the specification for control systems;
do not confuse the requirements of API 16D with those of API 16C
(choke and kill systems). Additionally, Section 6.3.11.2.5 applies
only to surface BOPs.
The intent in API 53 is to provide a weak link between the control
system and the BOP because the fire retardant properties would
be counter to the intended purpose of the emergency system.
Since there are many vessel designs in operation it is not practical
to have a different option for each. Sections 7.3.18 and 7.3.19
require floating rigs to have an autoshear and deadman
respectively, therefore should be interpreted as: Rigid conduit and
hot line supply hoses between the control system and the BOP
shall NOT be fire retardant.
Page 2 of 7
Standard
53
Edition
4th Edition,
Nov. 2012
Section
Inquiry #
6.5.3.6.2
53-08-13
Question
Background: Section 6.5.3.6.2 states analog pressure measurements
shall be made at not less than 25% and not more than 75% of the full
pressure span of the gauge. We currently have chart recorder with a
range of 30,000 psi and would like to perform pressure test of 3,000 psi,
which represent 10% of the maximum range of our chart recorder. These
tests are to perform integrity test of our operating chambers of various
equipments. Our customer refers to Section 6.5.3.6.2 regarding the
pressure test and does not want to pursue the test and require
replacement of the chart recorder.
Reply
Yes, only if the chart recorder is electronic (e.g. uses a pressure
transducer), and the test pressures are within the manufacturers
specified range, it conforms to API 53.
4th Edition,
Nov. 2012
7.2.2.18
53-04-14
Page 3 of 7
Standard
53
Edition
4th Edition,
Nov. 2012
Section
Inquiry #
Question
7.2.3.1.1
53-11-13
Page 4 of 7
Reply
Reply1: Yes.
Reply 2: Yes.
Reply 3: No.
Standard
53
Edition
4th Edition,
Nov. 2012
Section
Inquiry #
7.2.3.2.9
53-10-13
Question
Background: Regarding Section 7.2.3.2.9, I would like to address the
issue of the 12 inch spools between the choke and kill valve bodies and
the BOP body. The spool pieces were originally added by the
manufacturer to extend the position of the choke and kill bodies away
from the BOP. This added length prevented damage to the valves and
BOP bonnet doors during maintenance. Without the spool pieces the
doors could not be opened fully, thus adding the potential to damage the
door face during ram block installation and removal. Since the original
design of the BOP the manufacturer has manufactured an extended neck
valve body design. But, it must be noted there are problems with this
design. With the addition of a welded spool to the valve body alignment
becomes critical. If the welded extension is not square to the flange and
to the valve body, proper alignment can never be achieved. This also
adds the probability that the valves are no longer interchangeable within
the system. Example; if the lower inner and outer choke body is
prepared and fitted in place; potentially it could not be moved to a
different valve position without remanufacturing the associated choke
and kill pipework. If the valve in fact is moved to a different position and
the original pipework is utilized, it could allow the associated flanges to
be out of position and over stressed after installation. We believe the use
of the short spools is the better solution, and reduces the exposure to
leak via a ring gasket, due to possible over stress of the flange
connections, if a valve is replaced.
Reply
API does not grant deviations to the requirements stated in its
standard; we can only issue interpretations in response to
questions concerning the meaning of the requirements. Your
comments have been forwarded to the task group responsible for
API 53 for consideration as a future revision to the standard.
53
4th Edition,
Nov. 2012
7.2.3.2.9
53-14-13
Yes; API 53 does not allow for use of spools between the BOP
outlet and the choke and kill valves.
53
4th Edition,
Nov. 2012
7.3.10
53-02-13
Background: A particular rig with casing shear rams has response time
of 51 seconds. When asked about the required closing time in API 53 for
subsea casing shear rams, I stated 45 seconds, the same as pipe
rams. Rig personnel believed that the requirements in 7.2.10 do not
apply to casing shear rams because they do not seal and thus are not
considered a BOP.
Question: Are casing shear rams required to comply with the closing
times stated in 7.3.10?
Page 5 of 7
Standard
53
Edition
4th Edition,
Nov. 2012
Section
Inquiry #
7.4.16.2.2
53-04-13
Question
Background: I have a four-ram stack (one blind shear and three pipe
rams). I have an acoustic pod that closes the blind shear rams, closes a
hang-off ram, and disconnects the LMRP. The acoustic pod is capable of
operating critical functions, just not all of them.
Reply
No; this provision is implemented with a should and therefore is a
recommendation.
4th Edition,
Nov. 2012
7.5.6.1
53-07-13
Question: Are the blind shear ram closing times stated in Table 7 to
mean if pipe is in the BOP it must shear and seal in 45seconds, and if
drill pipe is not in the BOP, the ram must close in 45 seconds with
sufficient pressure that could have sheared the drill pipe had it been in
the BOP?
53
4th Edition,
Nov. 2012
7.6.8.3
53-15-13
Reply 3: Yes.
Question 4: If well hopping, does the test at initial landing only have to
be completed after connection to the first well?
Page 6 of 7
Standard
53
Edition
4th Edition,
Nov. 2012
Section
Inquiry #
7.6.9.3.3
53-03-14
Question
Background: Section 7.6.9.3.3 states certain equipment shall undergo a
critical inspection (internal/external visual, dimensional, NDE, etc.)
annually, or upon recovery if exceeding 1 year: e.g. shear blades, bonnet
bolts (or other bonnet/door locking devices), ram shaft button/foot,
welded hubs, ram cavities, and ram blocks. The actual dimensions shall
be verified against the manufacturers allowable tolerances.
Question 1: Was this meant to be a requirement for the listed example
equipment?
Question 2: Does API 53 specify who determines which inspection
method is used?
53
4th Edition,
Nov. 2012
7.6.11.7.6
53-01-12
Reply
Page 7 of 7