Daily Work Report Format

The daily work report provides status updates for project number HT 003 SS11, the general maintenance of crude oil storage tank TK-130. Work completed on December 1st included fabrication of a roof leg support plate and chipping of pipe sleepers for inspection. The planned progress was 34.80% with actual progress of 35.09%. On December 2nd, the same tasks continued with a workforce of 17 people, including site supervisors, safety personnel, mechanics, laborers and others. No work stoppages or delays were reported.
Copyright
© © All Rights Reserved
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
369 views

Daily Work Report Format

The daily work report provides status updates for project number HT 003 SS11, the general maintenance of crude oil storage tank TK-130. Work completed on December 1st included fabrication of a roof leg support plate and chipping of pipe sleepers for inspection. The planned progress was 34.80% with actual progress of 35.09%. On December 2nd, the same tasks continued with a workforce of 17 people, including site supervisors, safety personnel, mechanics, laborers and others. No work stoppages or delays were reported.
Copyright
© © All Rights Reserved
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 3

DAILY WORK REPORT

REPORT NO.:
PROJECT NO:
WORK ORDER NO:
PROJECT TITLE :
Contractor:
Department:
Al Jalhami Contracting and Trad. Co.
Site Engineer:
Incharge :
Signature:
Signature:
WORK DESCRIPTION

DATE:
LOCATION:
MSS

DATE:

WORK PROGRESS

0%

WORK PLANNED:

REMARKS/ CONCERNS IF ANY:


No. of
Men
4

No. of
Hours
0

QA/QC Engineer

Safety Supervisor

Mech. Foreman

Civil Foreman

Mechanic

Equipment Operator

Work Permit

N/A

Sand blasters

Information

N/A

Painter

Inspection

N/A

Welder

Other Trades

N/A

Electrician

Subcontractors

N/A

Mechanical technicians

Other Reasons

N/A

Scaffolder

Laborers

Masons

Cement Finishers

Piping technician/Fitters

Driver

Work Force
Site Supervisor

Other:
TOTAL
Subcontractors

TOTAL

No. of

No. of

Men

Hours

Was work stoppage ordered in writing/verbally?

NO

Was work delayed because of :

NO

Describe:

Tests/Inspections
Inspectors-Names

Representing

SITE VISITS / JOINT INSPECTION / WALK THROUGH


Visitors-Names

Representing

DAILY WORK REPORT

HT 003 SS11

W/O No. MSSD/13/163

GENERAL MAINTAINENCE OF CRUDE OIL STORAGE TANK TK-130


CONTRACTOR:

AL JALHAMI CONT.EST.

DATE:

SITE ENGINEER :

THIVAKAR

KJO IN-CHARGE : MSS

SIGNATURE

_______________________

Planned Progress = 34.80%

1.12.2013

SIGNATURE :

______________________
Overall Progress = 35.09%

A MFL INSPECTION:
1 Awaitting for ESD inspection report.
B BOTTOM PLATE.

1 Continue the fabrication of Roof Leg support plate.

C CIVIL WORKS;
1 Continue the chipping of pipe sleepers for ESD inspection.

Used Manpower (01/12/2013)


Site Supervisor
QA/QC Engineer
Safety Supervisor
Mech. Foreman
Mechanic
Crane Opt.
Sand blasters
Painter

=
=
=
=
=
=
=
=

1
0
1
1
1
1
2
0

Civil Foreman
Mason
Electrician
Fitter
Welder
Scaffolder
Driver
Labour/Helper

Today Manpower (02/12/2013)


=
=
=
=
=
=
=
=

0
0
1
0
0
0
1
8

7
TOTAL
= 17
Working Hours:7:00 AM -6.00 PM

Site Supervisor
QA/QC Engineer
Safety Supervisor
Mech. Foreman
Mechanic
Crane Optr.
Sand blasters
Painter

=
=
=
=
=
=
=
=

1
0
1
1
1
1
2
0

Civil Foreman
Mason
Electrician
Fitter
Welder
Scaffolder
Driver
Labour/Helper

=
=
=
=
=
=
=
=

7
TOTAL =
Working Hours: 7:00 AM - 6:00 PM

No. MSSD/13/163

____

09%

:00 PM

0
0
1
0
0
0
1
8
17