Daily Work Report Format
Daily Work Report Format
REPORT NO.:
PROJECT NO:
WORK ORDER NO:
PROJECT TITLE :
Contractor:
Department:
Al Jalhami Contracting and Trad. Co.
Site Engineer:
Incharge :
Signature:
Signature:
WORK DESCRIPTION
DATE:
LOCATION:
MSS
DATE:
WORK PROGRESS
0%
WORK PLANNED:
No. of
Hours
0
QA/QC Engineer
Safety Supervisor
Mech. Foreman
Civil Foreman
Mechanic
Equipment Operator
Work Permit
N/A
Sand blasters
Information
N/A
Painter
Inspection
N/A
Welder
Other Trades
N/A
Electrician
Subcontractors
N/A
Mechanical technicians
Other Reasons
N/A
Scaffolder
Laborers
Masons
Cement Finishers
Piping technician/Fitters
Driver
Work Force
Site Supervisor
Other:
TOTAL
Subcontractors
TOTAL
No. of
No. of
Men
Hours
NO
NO
Describe:
Tests/Inspections
Inspectors-Names
Representing
Representing
HT 003 SS11
AL JALHAMI CONT.EST.
DATE:
SITE ENGINEER :
THIVAKAR
SIGNATURE
_______________________
1.12.2013
SIGNATURE :
______________________
Overall Progress = 35.09%
A MFL INSPECTION:
1 Awaitting for ESD inspection report.
B BOTTOM PLATE.
C CIVIL WORKS;
1 Continue the chipping of pipe sleepers for ESD inspection.
=
=
=
=
=
=
=
=
1
0
1
1
1
1
2
0
Civil Foreman
Mason
Electrician
Fitter
Welder
Scaffolder
Driver
Labour/Helper
0
0
1
0
0
0
1
8
7
TOTAL
= 17
Working Hours:7:00 AM -6.00 PM
Site Supervisor
QA/QC Engineer
Safety Supervisor
Mech. Foreman
Mechanic
Crane Optr.
Sand blasters
Painter
=
=
=
=
=
=
=
=
1
0
1
1
1
1
2
0
Civil Foreman
Mason
Electrician
Fitter
Welder
Scaffolder
Driver
Labour/Helper
=
=
=
=
=
=
=
=
7
TOTAL =
Working Hours: 7:00 AM - 6:00 PM
No. MSSD/13/163
____
09%
:00 PM
0
0
1
0
0
0
1
8
17