Package B - Fourth Lane Widening

This document outlines the schedule for a proposed fourth lane widening project on the North-South Expressway between Bukit Lanjan (KM 22.0) and Jalan Duta Toll Plaza (KM 29.0) in Package B. Key aspects of the schedule include: - The project will be completed by July 5, 2014 and involves various stages including site clearance and fencing, earthworks, and construction of structures. - Site clearance and fencing work is broken into sections by chainage and will be completed between September 2012 to September 2013. - Earthworks for the project are scheduled to take place from September 2012 to September 2013. - Numerous milestones and completion dates are outlined
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
193 views13 pages

Package B - Fourth Lane Widening

This document outlines the schedule for a proposed fourth lane widening project on the North-South Expressway between Bukit Lanjan (KM 22.0) and Jalan Duta Toll Plaza (KM 29.0) in Package B. Key aspects of the schedule include: - The project will be completed by July 5, 2014 and involves various stages including site clearance and fencing, earthworks, and construction of structures. - Site clearance and fencing work is broken into sections by chainage and will be completed between September 2012 to September 2013. - Earthworks for the project are scheduled to take place from September 2012 to September 2013. - Numerous milestones and completion dates are outlined
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 13

NORTH-SOUTH EXPRESSWAY (PLUS)

PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Activity ID

Activity Name

Original Early Start


Duration

PACKAGE B : FOURTH LANE WIDENING


Milestones

Early Finish

Late Start

Late Finish

Total
Float

593 06-Jul-12

05-Jul-14

06-Jul-12

05-Jul-14

593 06-Jul-12

05-Jul-14

06-Jul-12

05-Jul-14

2013
Jul
1

Aug
2

Sep
3

Oct
4

Nov
5

Dec
6

Jan
7

Feb
8

Mar
9

Apr
10

May
11

Jun
12

Jul
13

Aug
14

Sep
15

Oct
16

Nov
17

Dec
18

Jan
19

Feb
20

Mar
21

2014
Apr
May
22
23

Jun
24

Jul
Aug
25
26
05-Jul-14, PACKAGE B : FOURTH LANE WID
05-Jul-14, Milestones

BA1000

Letter of Award

0 06-Jul-12

BA1010

Site Possession

0 06-Jul-12

BA1060

Section Completion of Package B Section 1 (East Bound) Work

05-Oct-13

05-Jul-14

221

BA1150

Section Completion of Package B Section 2 (West Bound) Work

05-Jul-14

05-Jul-14

Section Completion of Package B Section 2 (W

BA2000

Completion of PLUS Package B

05-Jul-14

05-Jul-14

Completion of PLUS Package B

05-Jul-14

375 01-Apr-13

Section 2 (West Bound)


BA4000

Commencement Stage 1

0 01-Apr-13

BA4010

Completion Stage 1

BA4020

Commencement Stage 2

0 15-Apr-14

BA4030

Completion Stage 2

0
372 06-Jul-12

Section 1 (East Bound)


BA3000

Commencement Stage 1

0 06-Jul-12

BA3010

Completion Stage 1

BA3020

Commencement Stage 2

0 06-Jun-13

BA3030

Completion Stage 2

0
588 06-Jul-12

General Items

06-Jul-12

2012
Jun
-1

06-Jul-12

05-Jul-14

05-Jul-14
05-Jul-14

14-Apr-14

05-Oct-13

05-Jul-14

05-Jul-14

06-Jul-12

Section Completion of Package B Section 1 (East Bound) Work

05-Jul-14, Section 2 (West Bound)


Completion Stage 1

68

Commencement Stage 2

221
593

Completion Stage 2
05-Oct-13, Section 1 (East Bound)
Commencement Stage 1

321

Completion Stage 1

321

Commencement Stage 2

05-Jul-14

221

05-Jul-14

30-Jun-14, General Items

Preliminaries Start

0 06-Jul-12

BB1010

Initial Site Survey

50 06-Jul-12

06-Sep-12

06-Jul-12

06-Sep-12

Initial Site Survey

BB1020

Mobilisation

50 06-Jul-12

06-Sep-12

12-Jul-12

12-Sep-12

Mobilisation

BB1030

Preliminaries Finish

05-Jul-14

Preliminaries Finish

BB4000

Testing of Materials and Works

Testing of Materials and Works

30-Jun-14

Completion Stage 2

BB1000

06-Jul-12

Commencement Stage 1

68

05-Jul-14

05-Jul-14
30-Jun-14

Site Possession

05-Jul-14

05-Oct-13

05-Jul-14
05-Jul-14

05-Jun-13

Letter of Award

375

05-Jul-14
05-Jul-14

542 03-Sep-12

30-Jun-14

06-Sep-12

03-Jul-14

578 18-Jul-12

30-Jun-14

24-Jul-12

05-Jul-14

Construction Plant

575 18-Jul-12

26-Jun-14

27-Jul-12

05-Jul-14

Contractor's Accommo dation an d Build in gs

578 18-Jul-12

30-Jun-14

24-Jul-12

05-Jul-14

35 18-Jul-12

30-Aug-12

24-Jul-12

06-Sep-12

24 03-Jun-14

Method Related Items


BB3030
BB3000

Establishment of the Contractor's Offices

BB3010

Removal of the Contractor's Offices

BB3020

Maintenance of the Contractor's Offices

Preliminaries Start

30-Jun-14, Method Related Items


Construction Plant

30-Jun-14, Contractor's Accommodation and Bui


Establishment of the Contractor's Offices

30-Jun-14

09-Jun-14

05-Jul-14

575 18-Jul-12

26-Jun-14

24-Jul-12

02-Jul-14

Maintenance of the Contractor's Offices

Removal of the Contractor's Offices

575 18-Jul-12

26-Jun-14

27-Jul-12

05-Jul-14

26-Jun-14, Temporary Works

BB3100

Temporary Access and Haul Roads

575 18-Jul-12

26-Jun-14

27-Jul-12

05-Jul-14

Temporary Access and Haul Roads

BB3110

Temporary Facilities

575 18-Jul-12

26-Jun-14

27-Jul-12

05-Jul-14

BB3120

Project Signboard

24-Jul-12

27-Jul-12

02-Aug-12

BB3130

Metal Deck Hoardings

575 18-Jul-12

26-Jun-14

27-Jul-12

05-Jul-14

578 18-Jul-12

30-Jun-14

24-Jul-12

05-Jul-14

Temporary Works

6 18-Jul-12

Specified Requirements

Temporary Facilities
Project Signboard
Metal Deck Hoardings
30-Jun-14, Specified Requirements

BB2000

Progress Reports

575 18-Jul-12

26-Jun-14

24-Jul-12

02-Jul-14

Progress Reports

BB2010

Progress Photographs

575 18-Jul-12

26-Jun-14

27-Jul-12

05-Jul-14

Progress Photographs

BB2020

Progress Videos

575 18-Jul-12

26-Jun-14

27-Jul-12

05-Jul-14

Progress Videos

BB2030

As-Built Drawings

46 06-May-14

30-Jun-14

12-May-14

05-Jul-14

BB2040

Operation & Maintenance Manual (O&M)

46 06-May-14

30-Jun-14

12-May-14

05-Jul-14

BB2050

Occupational, Safety adn Health Requirements

575 18-Jul-12

26-Jun-14

27-Jul-12

05-Jul-14

BB2060

Setting Out

575 18-Jul-12

26-Jun-14

27-Jul-12

05-Jul-14

52 06-Jul-12

08-Sep-12

18-Sep-12

04-Dec-12

70

08-Sep-12, Land Acquisition

Land Acquisition

As-Built Drawings
Operation & Maintenance Manual (O&M)
Occupational, Safety adn Health Requirements
Setting Out

BB5000

Access from Desa Park City to Edinburgh Estate CH.3380

52 06-Jul-12

08-Sep-12

02-Oct-12

04-Dec-12

70

Access from Desa Park City to Edinburgh Estate CH.3380

BB5010

Segambut Dalam Encumbrances at CH.5480

52 06-Jul-12

08-Sep-12

18-Sep-12

20-Nov-12

58

Segambut Dalam Encumbrances at CH.5480

320 03-Sep-12

28-Sep-13

03-Sep-12

05-Jul-14

227

317 03-Sep-12

25-Sep-13

03-Sep-12

05-Jul-14

230

05-Jul-14

230
75

Phase 1 (East Bound)


Site Clearance and Fencing (EB)
BC1005

Site Clearance and Fencing Start (EB)

0 03-Sep-12

BC1015

Site Clearance and Fencing Finish (EB)

Site Clearing and Fencing (CH.0-CH.1400)

03-Sep-12
25-Sep-13

206 03-Sep-12

10-May-13

03-Sep-12

12-Aug-13

28-Sep-13, Phase 1 (East Bound)


25-Sep-13, Site Clearance and Fencing (EB)
Site Clearance and Fencing Start (EB)
Site Clearance and Fencing Finish (EB)
10-May-13, Site Clearing and Fencing (CH.0-CH.1400)

BC1000

Site Clearing & Demolition Works

38 03-Sep-12

17-Oct-12

03-Sep-12

17-Oct-12

BC1010

Demolition Works

38 03-Sep-12

17-Oct-12

26-Jun-13

12-Aug-13

243

Site Clearing & Demolition Works


Demolition Works

BC1020

Relocation & Installation of Temporary Signage & Gantry

38 03-Sep-12

17-Oct-12

26-Jun-13

12-Aug-13

243

Relocation & Installation of Temporary Signage & Gantry

BC1030

Fencing and Gate

37 28-Mar-13

10-May-13

03-Apr-13

16-May-13

BC1040

Miscellaneous Dismantling, Demolition and Excavation

38 03-Sep-12

17-Oct-12

26-Jun-13

12-Aug-13

243

Fencing and Gate


Miscellaneous Dismantling, Demolition and Excavation

205 18-Oct-12

25-Jun-13

18-Oct-12

27-Sep-13

76

BC1100

Site Clearing & Demolition Works

38 18-Oct-12

04-Dec-12

18-Oct-12

04-Dec-12

BC1110

Demolition Works

38 18-Oct-12

04-Dec-12

13-Aug-13

27-Sep-13

243

Demolition Works

BC1120

Relocation & Installation of Temporary Signage & Gantry

38 18-Oct-12

04-Dec-12

13-Aug-13

27-Sep-13

243

Relocation & Installation of Temporary Signage & Gantry

BC1130

Fencing and Gate

37 11-May-13

25-Jun-13

17-May-13

01-Jul-13

BC1140

Miscellaneous Dismantling, Demolition and Excavation

38 18-Oct-12

04-Dec-12

13-Aug-13

27-Sep-13

243

Site Clearing and Fencing (CH.1400-CH.2800)

25-Jun-13, Site Clearing and Fencing (CH.1400-CH.2800)


Site Clearing & Demolition Works

Fencing and Gate


Miscellaneous Dismantling, Demolition and Excavation

204 05-Dec-12

10-Aug-13

05-Dec-12

14-Nov-13

77

BC1200

Site Clearing & Demolition Works

38 05-Dec-12

19-Jan-13

05-Dec-12

19-Jan-13

BC1210

Demolition Works

38 05-Dec-12

19-Jan-13

28-Sep-13

14-Nov-13

243

Demolition Works

BC1220

Relocation & Installation of Temporary Signage & Gantry

38 05-Dec-12

19-Jan-13

28-Sep-13

14-Nov-13

243

Relocation & Installation of Temporary Signage & Gantry

BC1230

Fencing and Gate

37 26-Jun-13

10-Aug-13

02-Jul-13

16-Aug-13

BC1240

Miscellaneous Dismantling, Demolition and Excavation

38 05-Dec-12

19-Jan-13

28-Sep-13

14-Nov-13

243

Site Clearing and Fencing (CH.2800-CH.4200)

10-Aug-13, Site Clearing and Fencing (CH.2800-CH.4200)


Site Clearing & Demolition Works

Fencing and Gate


Miscellaneous Dismantling, Demolition and Excavation

203 21-Jan-13

25-Sep-13

21-Jan-13

31-Dec-13

78

BC1300

Site Clearing & Demolition Works

38 21-Jan-13

07-Mar-13

21-Jan-13

07-Mar-13

Site Clearing & Demolition Works

BC1310

Demolition Works

38 21-Jan-13

07-Mar-13

28-Jan-13

13-Mar-13

Demolition Works

BC1320

Relocation & Installation of Temporary Signage & Gantry

38 21-Jan-13

07-Mar-13

28-Jan-13

13-Mar-13

Relocation & Installation of Temporary Signage & Gantry

BC1330

Fencing and Gate

37 12-Aug-13

25-Sep-13

17-Aug-13

01-Oct-13

Site Clearing and Fencing (CH.4200-CH.5600)

Remaining Work

Summary

25-Sep-13, Site Clearing and Fencing (CH.4200-CH.5600)

Fencing and Gate

1 of 13

Critical Remaining Work


Milestone

WORK PROGRAMME

Date
30-Jul-12
11-Sep-12

Revision
Rev.0
Rev.1

Checked

Approved

NORTH-SOUTH EXPRESSWAY (PLUS)


PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Activity ID

Activity Name

BC1340

Original Early Start


Duration

Miscellaneous Dismantling, Demolition and Excavation

Earthworks (EB)
BD0010

Earthwork Start (EB)

BD0020

Earthwork Finish (EB)

Early Finish

Late Finish

Total
Float

38 21-Jan-13

07-Mar-13

15-Nov-13

31-Dec-13

243

309 15-Sep-12

28-Sep-13

22-Sep-12

05-Jul-14

227

0 15-Sep-12
0

Stage 1

Late Start

08-Nov-12
28-Sep-13

05-Jul-14

227

175 15-Sep-12

16-Apr-13

22-Sep-12

14-Oct-13

147

61 18-Dec-12

02-Mar-13

12-Jan-13

28-Aug-13

147

Excavate to Toe of Slo pe (CH.2800-CH.4200)

38 18-Dec-12

02-Feb-13

05-Jul-13

21-Aug-13

164

BD1210

Fill to Formation Level (CH.2800-CH.4200)

38 07-Jan-13

21-Feb-13

12-Jan-13

27-Feb-13

BD1220

Turfin g

38 16-Jan-13

02-Mar-13

18-Mar-13

30-Apr-13

50

BD1230

Instrumentation and Monitoring

44 07-Jan-13

28-Feb-13

05-Jul-13

28-Aug-13

149

BD1240

Soil Investigation

38 18-Dec-12

02-Feb-13

05-Jul-13

21-Aug-13

164

61 15-Sep-12

29-Nov-12

22-Sep-12

27-May-13

147

CH.0-CH.1400
BD1000

Excavate to Toe of Slo pe (CH.0-CH.1400)

38 15-Sep-12

31-Oct-12

22-Sep-12

06-Nov-12

BD1010

Fill to Formation Level (CH.0-CH.1400)

38 04-Oct-12

20-Nov-12

10-Oct-12

26-Nov-12

BD1020

Turfin g

38 13-Oct-12

29-Nov-12

14-Dec-12

30-Jan-13

50

BD1030

Instrumentation and Monitoring

44 04-Oct-12

27-Nov-12

04-Apr-13

27-May-13

149

BD1040

Soil Investigation

38 15-Sep-12

31-Oct-12

04-Apr-13

18-May-13

164

61 01-Nov-12

15-Jan-13

27-Nov-12

11-Jul-13

147
164

CH.1400-CH.2800

Jul
1

Aug
2

Sep
3

Oct
4

Nov
5

Dec
6

Jan
7

2013
Mar
Apr
May
Jun
Jul
Aug
Sep
9
10
11
12
13
14
15
Miscellaneous Dismantling, Demolition and Excavation

Feb
8

Soil Investigation
29-Nov-12, CH.0-CH.1400
Excavate to Toe of Slo pe (CH.0-CH.1400)
Fill to Formation Level (CH.0-CH.1400)
Turfin g
Instrumentation and Monitoring
Soil Investigation
15-Jan-13, CH.1400-CH.2800

Fill to Formation Level (CH.1400-CH.2800)

38 21-Nov-12

05-Jan-13

27-Nov-12

11-Jan-13

Turfin g

38 30-Nov-12

15-Jan-13

31-Jan-13

16-Mar-13

50

BD1130

Instrumentation and Monitoring

44 21-Nov-12

12-Jan-13

20-May-13

11-Jul-13

149

BD1140

Soil Investigation

38 01-Nov-12

17-Dec-12

20-May-13

04-Jul-13

164

61 04-Feb-13

16-Apr-13

28-Feb-13

14-Oct-13

147

16-Apr-13, CH.4200-CH.5600

164

Excavate to Toe of Slo pe (CH.4200-CH.5600)

Fill to Formation Level (CH.4200-CH.5600)

38 22-Feb-13

06-Apr-13

28-Feb-13

12-Apr-13

BD1320

Turfin g

38 04-Mar-13

16-Apr-13

02-May-13

17-Jun-13

50

BD1330

Instrumentation and Monitoring

44 22-Feb-13

13-Apr-13

22-Aug-13

14-Oct-13

149

BD1340

Soil Investigation

Stage 2
CH.4200-CH.5600

38 04-Feb-13

20-Mar-13

22-Aug-13

07-Oct-13

164

142 08-Apr-13

28-Sep-13

30-Apr-13

07-Feb-14

104

46 02-Aug-13

28-Sep-13

27-Aug-13

07-Feb-14

104

BD2300

Removal of Existing Pavement

32 02-Aug-13

11-Sep-13

27-Aug-13

04-Oct-13

19

BD2310

Turfin g (Remaining Works)

32 21-Aug-13

28-Sep-13

28-Dec-13

07-Feb-14

104

BD2320

Treatment of Existing Subsoil Dr ain

32 13-Aug-13

20-Sep-13

19-Dec-13

28-Jan-14

104

46 16-May-13

10-Jul-13

10-Jun-13

18-Nov-13

104

BD2100

Removal of Existing Pavement

32 16-May-13

24-Jun-13

10-Jun-13

16-Jul-13

19

BD2110

Turfin g (Remaining Works)

32 04-Jun-13

10-Jul-13

09-Oct-13

18-Nov-13

104

BD2120

Treatment of Existing Subsoil Dr ain

32 25-May-13

02-Jul-13

01-Oct-13

09-Nov-13

104

CH.1400-CH.2800

46 25-Jun-13

20-Aug-13

17-Jul-13

27-Dec-13

104

BD2200

Removal of Existing Pavement

32 25-Jun-13

01-Aug-13

17-Jul-13

26-Aug-13

19

BD2210

Turfin g (Remaining Works)

32 11-Jul-13

20-Aug-13

19-Nov-13

27-Dec-13

104

BD2220

Treatment of Existing Subsoil Dr ain

32 03-Jul-13

12-Aug-13

11-Nov-13

18-Dec-13

104

CH.2800-CH.4200

Excavate to Toe of Slo pe (CH.1400-CH.2800)


Fill to Formation Level (CH.1400-CH.2800)
Turfin g
Instrumentation and Monitoring
Soil Investigation

Fill to Formation Level (CH.4200-CH.5600)


Turfin g
Instrumentation and Monitoring
Soil Investigation
28-Sep-13, Stage 2
28-Sep-13, CH.4200-CH.5600
Removal of Existing Pavement
Turfin g (Remaining Works)
Treatment of Existing Subsoil Dr ain
10-Jul-13, CH.1400-CH.2800
Removal of Existing Pavement
Turfin g (Remaining Works)
Treatment of Existing Subsoil Dr ain
20-Aug-13, CH.2800-CH.4200
Removal of Existing Pavement
Turfin g (Remaining Works)
Treatment of Existing Subsoil Dr ain

46 08-Apr-13

03-Jun-13

30-Apr-13

08-Oct-13

104

BD2000

Removal of Existing Pavement

32 08-Apr-13

15-May-13

30-Apr-13

08-Jun-13

19

BD2010

Turfin g (Remaining Works)

32 24-Apr-13

03-Jun-13

30-Aug-13

08-Oct-13

104

Turfin g (Remaining Works)

BD2020

Treatment of Existing Subsoil Dr ain

32 16-Apr-13

23-May-13

22-Aug-13

30-Sep-13

104

Treatment of Existing Subsoil Dr ain

309 15-Sep-12

28-Sep-13

10-Nov-12

05-Jul-14

227

CH.0-CH.1400

Drainage Works (EB)


BE0010

Drainage Works Start (EB)

BE0030

Drainage Works Finish (EB)

0 15-Sep-12

28-Sep-13, Drainage Works (EB)

46

Drainage Works Start (EB)

05-Jul-14

227

Drainage Works Finish (EB)

28-Sep-13

10-Nov-12

05-Jul-14

227

28-Sep-13, Stage 1

Pipe Culverts Extensions

250 28-Nov-12

28-Sep-13

02-Sep-13

05-Jul-14

227

Culvert 4 (CH.1293)

25 28-Feb-13

28-Mar-13

03-Dec-13

03-Jan-14

227

11 28-Feb-13

12-Mar-13

03-Dec-13

16-Dec-13

227

3 13-Mar-13

15-Mar-13

17-Dec-13

19-Dec-13

227

11 16-Mar-13

28-Mar-13

20-Dec-13

03-Jan-14

227

25 28-Nov-12

27-Dec-12

02-Sep-13

01-Oct-13

227

11 28-Nov-12

10-Dec-12

02-Sep-13

13-Sep-13

227

3 11-Dec-12

13-Dec-12

14-Sep-13

18-Sep-13

227

11 14-Dec-12

27-Dec-12

19-Sep-13

01-Oct-13

227

25 28-Dec-12

28-Jan-13

02-Oct-13

31-Oct-13

227

11 28-Dec-12

10-Jan-13

02-Oct-13

14-Oct-13

227

BE3300

Pipe Culvert Extension

BE3310

RC Box Joints

BE3320

Inlet/Outlet Structures

Culvert 1 (CH.94)
BE3000

Pipe Culvert Extension

BE3010

RC Box Joints

BE3020

Inlet/Outlet Structures

Culvert 2 (CH.625)
BE3100

Pipe Culvert Extension

BE3110

RC Box Joints

BE3120

Inlet/Outlet Structures

Culvert 3 (CH.927)
BE3200

Pipe Culvert Extension

BE3210

RC Box Joints

BE3220

Inlet/Outlet Structures

Culvert 5 (CH.2365)
BE3400

Pipe Culvert Extension

BE3410

RC Box Joints

BE3420

Inlet/Outlet Structures

Culvert 6 (CH.2926)
BE3500

Pipe Culvert Extension

Remaining Work

Summary

28-Sep-13

03-Jun-13, CH.0-CH.1400
Removal of Existing Pavement

309 15-Sep-12

Stage 1

10-Nov-12

3 11-Jan-13

14-Jan-13

16-Oct-13

18-Oct-13

227

11 15-Jan-13

28-Jan-13

19-Oct-13

31-Oct-13

227

25 29-Jan-13

27-Feb-13

01-Nov-13

02-Dec-13

227

11 29-Jan-13

09-Feb-13

01-Nov-13

15-Nov-13

227

3 12-Feb-13

14-Feb-13

16-Nov-13

19-Nov-13

227

11 15-Feb-13

27-Feb-13

20-Nov-13

02-Dec-13

227

25 29-Mar-13

26-Apr-13

04-Jan-14

05-Feb-14

227

11 29-Mar-13

10-Apr-13

04-Jan-14

17-Jan-14

227

3 11-Apr-13

13-Apr-13

18-Jan-14

21-Jan-14

227

11 15-Apr-13

26-Apr-13

22-Jan-14

05-Feb-14

227

25 27-Apr-13

28-May-13

06-Feb-14

07-Mar-14

227

11 27-Apr-13

10-May-13

06-Feb-14

19-Feb-14

227

28-Sep-13, Pipe Culverts Extensions


28-Mar-13, Culvert 4 (CH.1293)
Pipe Culvert Extension
RC Box Joints
Inlet/Outlet Structures
27-Dec-12, Culvert 1 (CH.94)
Pipe Culvert Extension
RC Box Joints
Inlet/Outlet Structures
28-Jan-13, Culvert 2 (CH.625)
Pipe Culvert Extension
RC Box Joints
Inlet/Outlet Structures
27-Feb-13, Culvert 3 (CH.927)
Pipe Culvert Extension
RC Box Joints
Inlet/Outlet Structures
26-Apr-13, Culvert 5 (CH.2365)
Pipe Culvert Extension
RC Box Joints
Inlet/Outlet Structures
28-May-13, Culvert 6 (CH.2926)
Pipe Culvert Extension

2 of 13

Critical Remaining Work


Milestone

Jul
25

Turfing

BD1120

BD1310

Jun
24

Instrumentation and Monitoring

BD1110

07-Oct-13

2014
Apr
May
22
23

Fill to Formation Level (CH.2800-CH.4200)

04-Jul-13

22-Aug-13

Mar
21

02-Mar-13, CH.2800-CH.4200

20-May-13

20-Mar-13

Feb
20

Excavate to Toe of Slo pe (CH.2800-CH.4200)

17-Dec-12

38 04-Feb-13

Jan
19

Earthwork Finish (EB)

38 01-Nov-12

Excavate to Toe of Slo pe (CH.4200-CH.5600)

Dec
18

16-Apr-13, Stage 1

Excavate to Toe of Slo pe (CH.1400-CH.2800)

BD1300

Nov
17

Earthwork Start (EB)

BD1100

CH.4200-CH.5600

Oct
16

28-Sep-13, Earthworks (EB)

44

BD1200

CH.2800-CH.4200

2012
Jun
-1

WORK PROGRAMME

Date
30-Jul-12
11-Sep-12

Revision
Rev.0
Rev.1

Checked

Approved

Aug
26

NORTH-SOUTH EXPRESSWAY (PLUS)


PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Activity ID

Activity Name

BE3510

RC Box Joints

BE3520

Inlet/Outlet Structures

Culvert 7 (CH.3640)
BE3600

Pipe Culvert Extension

BE3610

RC Box Joints

BE3620

Inlet/Outlet Structures

Culvert 8 (CH.4196)
BE3700

Pipe Culvert Extension

BE3710

RC Box Joints

BE3720

Inlet/Outlet Structures

Culvert 9 (CH.4628)
BE3800

Pipe Culvert Extension

BE3810

RC Box Joints

BE3820

Inlet/Outlet Structures

Culvert 10 (CH.4906)
BE3900

Pipe Culvert Extension

BE3910

RC Box Joints

BE3920

Inlet/Outlet Structures

Drainage (CH.0-CH.1400)

Original Early Start


Duration

Early Finish

Late Start

Late Finish

Total
Float

3 11-May-13

14-May-13

20-Feb-14

22-Feb-14

227

11 15-May-13

28-May-13

24-Feb-14

07-Mar-14

227

25 29-May-13

27-Jun-13

08-Mar-14

05-Apr-14

227

11 29-May-13

11-Jun-13

08-Mar-14

20-Mar-14

227

3 12-Jun-13

14-Jun-13

21-Mar-14

24-Mar-14

227

11 15-Jun-13

27-Jun-13

25-Mar-14

05-Apr-14

227

25 28-Jun-13

27-Jul-13

07-Apr-14

06-May-14

227

11 28-Jun-13

10-Jul-13

07-Apr-14

18-Apr-14

227

3 11-Jul-13

13-Jul-13

19-Apr-14

22-Apr-14

227

11 15-Jul-13

27-Jul-13

23-Apr-14

06-May-14

227

25 29-Jul-13

28-Aug-13

07-May-14

06-Jun-14

227

11 29-Jul-13

12-Aug-13

07-May-14

20-May-14

227

3 13-Aug-13

15-Aug-13

21-May-14

23-May-14

227

11 16-Aug-13

28-Aug-13

24-May-14

06-Jun-14

227

25 29-Aug-13

28-Sep-13

07-Jun-14

05-Jul-14

227

11 29-Aug-13

11-Sep-13

07-Jun-14

19-Jun-14

227

3 12-Sep-13

14-Sep-13

20-Jun-14

23-Jun-14

227

11 17-Sep-13

28-Sep-13

24-Jun-14

05-Jul-14

227

43 15-Sep-12

06-Nov-12

10-Nov-12

03-Jan-13

46

BE1000

Excavation

33 15-Sep-12

24-Oct-12

10-Nov-12

20-Dec-12

46

BE1010

Laying of Drain

33 22-Sep-12

31-Oct-12

19-Nov-12

27-Dec-12

46

BE1020

Backfilling

33 28-Sep-12

06-Nov-12

24-Nov-12

03-Jan-13

46

43 07-Nov-12

29-Dec-12

04-Jan-13

25-Feb-13

46

Drainage (CH.1400-CH.2800)

2012
Jun
-1

Jul
1

Aug
2

Sep
3

Oct
4

Nov
5

Dec
6

Jan
7

Feb
8

28-Sep-13, Culvert 10 (CH.4906)


Pipe Culvert Extension
RC Box Joints
Inlet/Outlet Structures
06-Nov-12, Drainage (CH.0-CH.1400)
Excavation
Laying of Drain
Backfilling
29-Dec-12, Drainage (CH.1400-CH.2800)

22-Dec-12

10-Jan-13

19-Feb-13

46

Laying of Drain

29-Dec-12

16-Jan-13

25-Feb-13

46

Backfilling

43 31-Dec-12

21-Feb-13

26-Feb-13

16-Apr-13

46

15-Feb-13

04-Mar-13

10-Apr-13

46

33 12-Jan-13

21-Feb-13

09-Mar-13

16-Apr-13

46

43 22-Feb-13

12-Apr-13

17-Apr-13

08-Jun-13

46

Drainage (CH.4200-CH.5600)
BE1300

Excavation

33 22-Feb-13

01-Apr-13

17-Apr-13

27-May-13

46

BE1310

Laying of Drain

33 28-Feb-13

06-Apr-13

23-Apr-13

03-Jun-13

46

BE1320

Backfilling

33 06-Mar-13

12-Apr-13

29-Apr-13

08-Jun-13

46

128 13-Apr-13

18-Sep-13

03-Feb-14

05-Jul-14

236

128 13-Apr-13

18-Sep-13

03-Feb-14

05-Jul-14

236

Stage 2
Drains (Remaining Works) and Kerbs
BE1500

CH.0-CH.1400

32 13-Apr-13

21-May-13

03-Feb-14

12-Mar-14

236

BE1510

CH.1400-CH.2800

32 22-May-13

29-Jun-13

13-Mar-14

18-Apr-14

236

BE1520

CH.2800-CH.4200

32 01-Jul-13

07-Aug-13

19-Apr-14

28-May-14

236

BE1530

CH.4200-CH.5600

32 10-Aug-13

18-Sep-13

29-May-14

05-Jul-14

236

158 20-Mar-13

28-Sep-13

11-May-13

05-Jul-14

227

Sub-Base, Roadbase and Pavement (EB)


BF0010

Sub-Base, Roadbase and Pavement Start (EB)

BF0020

Sub-Base, Roadbase and Pavement Finish (EB)

Stage 1

0 20-Mar-13
0

11-May-13
28-Sep-13

05-Jul-14

227

12-Jul-13

13-Mar-14

05-Jul-14

289

BF0500

Saw Cut of CRCP - CH.0-CH.1400

24 20-Mar-13

16-Apr-13

13-Mar-14

09-Apr-14

289

BF0510

Saw Cut of CRCP - CH.1400-CH.2800

24 17-Apr-13

15-May-13

10-Apr-14

08-May-14

289

BF0520

Saw Cut of CRCP - CH.2800-CH.4200

24 16-May-13

14-Jun-13

09-May-14

07-Jun-14

289

BF0530

Saw Cut of CRCP - CH.4200-CH.5600

24 15-Jun-13

12-Jul-13

09-Jun-14

05-Jul-14

289

158 20-Mar-13

28-Sep-13

11-May-13

05-Jul-14

227

140 20-Mar-13

06-Sep-13

11-May-13

30-Oct-13

44

Stage 2
BF3000

Sub-surface Drainage Improvement (East Bound)

Excavation

21-Feb-13, Drainage (CH.2800-CH.4200)


Excavation
Laying of Drain
Backfilling
12-Apr-13, Drainage (CH.4200-CH.5600)
Excavation
Laying of Drain
Backfilling
18-Sep-13, Stage 2
18-Sep-13, Drains (Remaining Works) and Kerbs
CH.0-CH.1400
CH.1400-CH.2800
CH.2800-CH.4200
CH.4200-CH.5600
28-Sep-13, Sub-Base, Roadbase and Pavement (EB)

44

96 20-Mar-13

Sub-Base, Roadbase and Pavement Start (EB)


Sub-Base, Roadbase and Pavement Finish (EB)
12-Jul-13, Stage 1
Saw Cut of CRCP - CH.0-CH.1400
Saw Cut of CRCP - CH.1400-CH.2800
Saw Cut of CRCP - CH.2800-CH.4200
Saw Cut of CRCP - CH.4200-CH.5600
28-Sep-13, Stage 2
Sub-surface Drainage Improvement (East Bound)

38 18-Apr-13

04-Jun-13

11-May-13

16-Apr-14

256

BF1010

Sub-Grade and Prepare Formation

24 18-Apr-13

16-May-13

11-May-13

10-Jun-13

19

Sub-Grade and Prepare Formation

BF1020

Laying of Lower Sub-Base

24 20-Apr-13

18-May-13

14-May-13

12-Jun-13

19

Laying of Lower Sub-Base

BF1030

Laying of Lower Upper-Base

24 23-Apr-13

21-May-13

16-May-13

14-Jun-13

19

Laying of Lower Upper-Base

BF1040

Laying of CBM

22 25-Apr-13

21-May-13

18-May-13

14-Jun-13

19

Laying of CBM

BF1050

Laying of WMM

22 27-Apr-13

23-May-13

01-Nov-13

28-Nov-13

152

Laying of WMM

BF1060

Laying of DBM

22 30-Apr-13

27-May-13

06-Nov-13

30-Nov-13

152

Laying of DBM

BF1070

Laying of ACBC

22 03-May-13

29-May-13

08-Nov-13

03-Dec-13

152

Laying of ACBC

BF1075

Regulating

22 04-May-13

30-May-13

22-Mar-14

16-Apr-14

259

Regulating

BF1080

Laying of ACWC

22 06-May-13

31-May-13

11-Nov-13

05-Dec-13

152

Laying of ACWC

BF1090

Laying of SMA

22 08-May-13

04-Jun-13

13-Nov-13

07-Dec-13

152

Laying of SMA

BF1100

Dismantle Guardrail, NJB Installation & Misc. Works

32 25-Apr-13

04-Jun-13

18-May-13

26-Jun-13

19

BF1110

Temporay Road Marking & Traffic Diversion/Contra Flow

32 25-Apr-13

04-Jun-13

04-Feb-14

13-Mar-14

227

38 05-Jul-13

21-Aug-13

29-Jul-13

05-Jul-14

258

Sub-Base upto Pavement (CH.0-CH.1400)

Sub-Base upto Pavement (CH.2800-CH.4200)

04-Jun-13, Sub-Base upto Pavement (CH.0-CH.1400)

Dismantle Guardrail, NJB Installation & Misc. Works


Temporay Road Marking & Traffic Diversion/Contra Flow
21-Aug-13, Sub-Base upto Pavement (CH.2800-CH.4200)

BF1410

Sub-Grade and Prepare Formation

24 05-Jul-13

02-Aug-13

29-Jul-13

27-Aug-13

19

BF1420

Laying of Lower Sub-Base

24 08-Jul-13

05-Aug-13

31-Jul-13

29-Aug-13

19

Laying of Lower Sub-Base

BF1430

Laying of Lower Upper-Base

24 10-Jul-13

07-Aug-13

02-Aug-13

02-Sep-13

19

Laying of Lower Upper-Base

BF1440

Laying of CBM

22 12-Jul-13

07-Aug-13

05-Aug-13

02-Sep-13

19

Laying of CBM

BF1450

Laying of WMM

22 15-Jul-13

12-Aug-13

08-May-14

04-Jun-14

239

Laying of WMM

BF1460

Laying of DBM

22 17-Jul-13

14-Aug-13

10-May-14

06-Jun-14

239

Laying of DBM

BF1470

Laying of ACBC

22 19-Jul-13

16-Aug-13

14-May-14

09-Jun-14

239

Laying of ACBC

BF1475

Regulating

22 20-Jul-13

17-Aug-13

15-May-14

10-Jun-14

239

Regulating

BF1480

Laying of ACWC

22 22-Jul-13

19-Aug-13

09-Jun-14

03-Jul-14

258

Laying of ACWC

Remaining Work

Summary

Sub-Grade and Prepare Formation

3 of 13

Critical Remaining Work


Milestone

Jul
25

Inlet/Outlet Structures

33 21-Nov-12

33 07-Jan-13

Jun
24

RC Box Joints

33 14-Nov-12

Backfilling

2014
Apr
May
22
23

28-Aug-13, Culvert 9 (CH.4628)

Backfilling

Laying of Drain

Mar
21

Pipe Culvert Extension

Laying of Drain

BE1220

Feb
20

Inlet/Outlet Structures

BE1120

BE1210

Jan
19

RC Box Joints

BE1110

46

Dec
18

27-Jul-13, Culvert 8 (CH.4196)

46

04-Apr-13

Nov
17

Pipe Culvert Extension

13-Feb-13

26-Feb-13

Oct
16

Inlet/Outlet Structures

04-Jan-13

08-Feb-13

Sep
15

RC Box Joints

17-Dec-12

33 31-Dec-12

Aug
14

27-Jun-13, Culvert 7 (CH.3640)

33 07-Nov-12

Excavation

2013
May
Jun
Jul
11
12
13
RC Box Joints

Pipe Culvert Extension

Excavation

BE1200

Apr
10

Inlet/Outlet Structures

BE1100

Drainage (CH.2800-CH.4200)

Mar
9

WORK PROGRAMME

Date
30-Jul-12
11-Sep-12

Revision
Rev.0
Rev.1

Checked

Approved

Aug
26

NORTH-SOUTH EXPRESSWAY (PLUS)


PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Activity ID

Activity Name

Original Early Start


Duration

Early Finish

Late Start

Late Finish

Total
Float

BF1490

Laying of SMA

22 24-Jul-13

21-Aug-13

11-Jun-14

05-Jul-14

BF1500

Dismantle Guardrail, NJB Installation & Misc. Works

32 12-Jul-13

21-Aug-13

05-Aug-13

13-Sep-13

19

BF1510

Temporay Road Marking & Traffic Diversion/Contra Flow

32 12-Jul-13

21-Aug-13

21-Apr-14

29-May-14

227

37 15-Aug-13

28-Sep-13

07-Sep-13

05-Jul-14

227

Sub-Base upto Pavement (CH.4200-CH.5600)

2012
Jun
-1

2013
Jul
1

Aug
2

Sep
3

Oct
4

Nov
5

Dec
6

Jan
7

Feb
8

Mar
9

Apr
10

May
11

Jun
12

Jul
13

Aug
14

Sep
Oct
15
16
Laying of SMA

258

Nov
17

Dec
18

Jan
19

12-Sep-13

07-Sep-13

05-Oct-13

19

Sub-Grade and Prepare Formation

BF1620

Laying of Lower Sub-Base

24 17-Aug-13

14-Sep-13

10-Sep-13

08-Oct-13

19

Laying of Lower Sub-Base

BF1630

Laying of Lower Upper-Base

24 20-Aug-13

18-Sep-13

12-Sep-13

10-Oct-13

19

Laying of Lower Upper-Base

BF1640

Laying of CBM

22 22-Aug-13

18-Sep-13

14-Sep-13

10-Oct-13

19

Laying of CBM

BF1650

Laying of WMM

22 24-Aug-13

20-Sep-13

04-Jun-14

28-Jun-14

228

Laying of WMM

BF1660

Laying of DBM

22 27-Aug-13

23-Sep-13

06-Jun-14

01-Jul-14

228

Laying of DBM

BF1670

Laying of ACBC

22 29-Aug-13

25-Sep-13

09-Jun-14

03-Jul-14

228

Laying of ACBC

BF1675

Regulating

22 30-Aug-13

26-Sep-13

11-Jun-14

05-Jul-14

229

Regulating

BF1680

Laying of ACWC

22 30-Aug-13

26-Sep-13

10-Jun-14

04-Jul-14

228

Laying of ACWC

BF1690

Laying of SMA

22 02-Sep-13

27-Sep-13

11-Jun-14

05-Jul-14

228

Laying of SMA

BF1700

Dismantle Guardrail, NJB Installation & Misc. Works

31 22-Aug-13

28-Sep-13

14-Sep-13

22-Oct-13

19

BF1710

Temporay Road Marking & Traffic Diversion/Contra Flow

31 22-Aug-13

28-Sep-13

30-May-14

05-Jul-14

227

38 28-May-13

11-Jul-13

20-Jun-13

05-Jul-14

290

Temporay Road Marking & Traffic Diversion/Contra Flow


11-Jul-13, Sub-Base upto Pavement (CH.1400-CH.2800)

Sub-Grade and Prepare Formation

24 28-May-13

25-Jun-13

20-Jun-13

17-Jul-13

19

Sub-Grade and Prepare Formation

BF1220

Laying of Lower Sub-Base

24 30-May-13

27-Jun-13

22-Jun-13

19-Jul-13

19

Laying of Lower Sub-Base

BF1230

Laying of Lower Upper-Base

24 03-Jun-13

29-Jun-13

25-Jun-13

22-Jul-13

19

Laying of Lower Upper-Base

BF1240

Laying of CBM

22 05-Jun-13

29-Jun-13

27-Jun-13

22-Jul-13

19

Laying of CBM

BF1250

Laying of WMM

22 07-Jun-13

02-Jul-13

11-Apr-14

07-May-14

249

Laying of WMM

BF1260

Laying of DBM

22 10-Jun-13

04-Jul-13

14-Apr-14

09-May-14

249

Laying of DBM

BF1270

Laying of ACBC

22 12-Jun-13

06-Jul-13

16-Apr-14

12-May-14

249

Laying of ACBC

BF1275

Regulating

22 13-Jun-13

08-Jul-13

17-Apr-14

14-May-14

249

Regulating

BF1280

Laying of ACWC

22 14-Jun-13

09-Jul-13

09-Jun-14

03-Jul-14

290

Laying of ACWC

BF1290

Laying of SMA

22 17-Jun-13

11-Jul-13

11-Jun-14

05-Jul-14

290

Laying of SMA

BF1300

Dismantle Guardrail, NJB Installation & Misc. Works

32 05-Jun-13

11-Jul-13

27-Jun-13

03-Aug-13

19

BF1310

Temporay Road Marking & Traffic Diversion/Contra Flow

32 05-Jun-13

11-Jul-13

14-Mar-14

19-Apr-14

227

73 01-Jul-13

28-Sep-13

07-Jan-14

05-Jul-14

227

0 01-Jul-13

BG0020

Road Furniture Finish (EB)

Stage 2
CH.4200-CH.5600

07-Jan-14
28-Sep-13

Dismantle Guardrail, NJB Installation & Misc. Works


Temporay Road Marking & Traffic Diversion/Contra Flow
28-Sep-13, Road Furniture (EB)

152

Road Furniture Start (EB)

05-Jul-14

227

Road Furniture Finish (EB)

73 01-Jul-13

28-Sep-13

07-Jan-14

05-Apr-14

152

28-Sep-13, Stage 2

18 07-Sep-13

28-Sep-13

17-Mar-14

05-Apr-14

152

28-Sep-13, CH.4200-CH.5600
Traffic Signs

BG1300

Traffic Signs

18 07-Sep-13

28-Sep-13

17-Mar-14

05-Apr-14

152

BG1310

Road Markings

18 07-Sep-13

28-Sep-13

17-Mar-14

05-Apr-14

152

Road Markings

BG1320

Ancillary Finishings

18 07-Sep-13

28-Sep-13

17-Mar-14

05-Apr-14

152

Ancillary Finishings

18 23-Jul-13

15-Aug-13

30-Jan-14

22-Feb-14

152

15-Aug-13, CH.1400-CH.2800

BG1100

Traffic Signs

18 23-Jul-13

15-Aug-13

30-Jan-14

22-Feb-14

152

Traffic Signs

BG1110

Road Markings

18 23-Jul-13

15-Aug-13

30-Jan-14

22-Feb-14

152

Road Markings

BG1120

Ancillary Finishings

18 23-Jul-13

15-Aug-13

30-Jan-14

22-Feb-14

152

Ancillary Finishings

CH.1400-CH.2800

18 16-Aug-13

06-Sep-13

24-Feb-14

15-Mar-14

152

06-Sep-13, CH.2800-CH.4200

BG1200

Traffic Signs

18 16-Aug-13

06-Sep-13

24-Feb-14

15-Mar-14

152

Traffic Signs

BG1210

Road Markings

18 16-Aug-13

06-Sep-13

24-Feb-14

15-Mar-14

152

Road Markings

BG1220

Ancillary Finishings

18 16-Aug-13

06-Sep-13

24-Feb-14

15-Mar-14

152

Ancillary Finishings

CH.2800-CH.4200

19 01-Jul-13

22-Jul-13

07-Jan-14

29-Jan-14

152

22-Jul-13, CH.0-CH.1400

BG1000

Traffic Signs

19 01-Jul-13

22-Jul-13

07-Jan-14

29-Jan-14

152

Traffic Signs

BG1010

Road Markings

19 01-Jul-13

22-Jul-13

07-Jan-14

29-Jan-14

152

Road Markings

BG1020

Ancillary Finishings

19 01-Jul-13

22-Jul-13

07-Jan-14

29-Jan-14

152

Ancillary Finishings

222 02-Jan-13

28-Sep-13

10-Jan-13

05-Jul-14

227

CH.0-CH.1400

Utilities and Services (EB)


BH0100

Utilities and Services Start (EB)

BH0110

Utilities and Services Finish (EB)

Overall Stage 1
BH0020

Testing and Commissioning

CH.0-CH.1400
BH1030

Temporary Works for Existin g Utili ties

Telecommunication System
BH1000

Lay Duct

CH.1400-CH.2800
BH2030

Temporary Works for Existin g Utili ties

Telecommunication System

0 02-Jan-13
0

10-Jan-13
28-Sep-13

05-Jul-14

227

Utilities and Services Finish (EB)

28-Sep-13

10-Jan-13

05-Jul-14

227

28-Sep-13, Overall Stage 1

94 06-Jun-13

28-Sep-13

12-Jun-13

04-Oct-13

122 02-Jan-13

28-May-13

10-Jan-13

05-Jul-14

327

104 23-Jan-13

28-May-13

04-Mar-14

05-Jul-14

327

36 02-Jan-13

14-Feb-13

10-Jan-13

22-Feb-13

Lay Duct

36 02-Jan-13

14-Feb-13

10-Jan-13

22-Feb-13

12-Jun-13

12-Feb-13

05-Jul-14

315

90 25-Feb-13

12-Jun-13

20-Mar-14

05-Jul-14

315

60 02-Feb-13

13-Apr-13

12-Feb-13

11-Jun-13

47

36 02-Feb-13

16-Mar-13

12-Feb-13

25-Mar-13

Relocation of OFC

36 18-Feb-13

30-Mar-13

13-Apr-13

27-May-13

47

BH2020

ITS System

36 04-Mar-13

13-Apr-13

27-Apr-13

11-Jun-13

47

108 06-Mar-13

12-Jul-13

14-Mar-13

05-Jul-14

289

90 27-Mar-13

12-Jul-13

20-Mar-14

05-Jul-14

289

60 06-Mar-13

15-May-13

14-Mar-13

11-Jun-13

21

Telecommunication System
BH3000

Lay Duct

36 06-Mar-13

16-Apr-13

14-Mar-13

24-Apr-13

BH3010

Relocation of OFC

36 20-Mar-13

30-Apr-13

13-Apr-13

27-May-13

21

BH3020

ITS System

36 03-Apr-13

15-May-13

27-Apr-13

11-Jun-13

21

202 02-Jan-13

04-Sep-13

13-Apr-13

05-Jul-14

247

104 29-Apr-13

04-Sep-13

04-Mar-14

05-Jul-14

247

70 02-Jan-13

26-Mar-13

09-Oct-13

04-Jan-14

230

CH.4200-CH.5600
BH4030

Temporary Works for Existin g Utili ties

BH4040

Water works, Relocation of Water Mains (CH.5450)

Remaining Work

Summary

Temporary Works for Existin g Utili ties


14-Feb-13, Telecommunication System

Lay Duct

Temporary Works for Existin g Utili ties

Testing and Commissioning


28-May-13, CH.0-CH.1400

BH2010

BH3030

Utilities and Services Start (EB)

222 02-Jan-13

BH2000

CH.2800-CH.4200

28-Sep-13, Utilities and Services (EB)

108 02-Feb-13

12-Jun-13, CH.1400-CH.2800
Temporary Works for Existing Utilities
13-Apr-13, Telecommunicatio n System
Lay Duct
Relocation of OFC
ITS System
12-Jul-13, CH.2800-CH.4200
Temporary Works for Existin g Utilities
15-May-13, Telecommunication System
Lay Duct
Relocation of OFC
ITS System
04-Sep-13, CH.4200-CH.5600
Temporary Works for Existin g Utilities
Water works, Relocation of Water Mains (CH.5450)

4 of 13

Critical Remaining Work


Milestone

Jul
25

Dismantle Guardrail, NJB Installation & Misc. Works

BF1210

Road Furniture Start (EB)

Jun
24

28-Sep-13, Sub-Base upto Pavement (CH.4200-CH.5600)

24 15-Aug-13

BG0010

2014
Apr
May
22
23

Temporay Road Marking & Traffic Diversion/Contra Flow

Sub-Grade and Prepare Formation

Road Furniture (EB)

Mar
21

Dismantle Guardrail, NJB Installation & Misc. Works

BF1610

Sub-Base upto Pavement (CH.1400-CH.2800)

Feb
20

WORK PROGRAMME

Date
30-Jul-12
11-Sep-12

Revision
Rev.0
Rev.1

Checked

Approved

Aug
26

NORTH-SOUTH EXPRESSWAY (PLUS)


PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Activity ID

Activity Name

Original Early Start


Duration

Early Finish

Late Start

Late Finish

Total
Float

48 08-Apr-13

05-Jun-13

13-Apr-13

11-Jun-13

BH4000

Lay Duct

36 08-Apr-13

20-May-13

13-Apr-13

27-May-13

BH4010

Relocation of OFC

36 15-Apr-13

28-May-13

20-Apr-13

04-Jun-13

BH4020

ITS System

36 22-Apr-13

05-Jun-13

27-Apr-13

11-Jun-13

286 15-Sep-12

30-Aug-13

20-Oct-12

05-Jul-14

250

Telecommunication System

Bridge Widening (EB)


BJ1000

Bridge Widening Start (EB)

BJ1010

Bridge Widening Finish (EB)

Bridge Extension Over Jalan Damansara (BR B.1)


Section 1 - East Bound
East Abu tment

0 15-Sep-12
0

20-Oct-12
30-Aug-13

2012
Jun
-1

Jul
1

Aug
2

Sep
3

Oct
4

Nov
5

Dec
6

Jan
7

Feb
8

Mar
9

Apr
10

2013
Jun
Jul
Aug
Sep
Oct
12
13
14
15
16
05-Jun-13, Telecommunication System

May
11

05-Jul-14

250

Bridge Widening Finish (EB)

238 14-Nov-12

30-Aug-13

19-Dec-12

21-Jun-14

238

30-Aug-13, Bridge Extension Over Jalan Damansara (BR B.1)

238 14-Nov-12

30-Aug-13

19-Dec-12

21-Jun-14

238

52 03-Jan-13

06-Mar-13

29-Apr-13

01-Jul-13

97

29-Apr-13

20-May-13

97

Pile Cap Construction

13-Feb-13

21-May-13

10-Jun-13

97

Abutment Wall

BJ2160

Wing Wall & Curtail Wall

10 14-Feb-13

25-Feb-13

11-Jun-13

21-Jun-13

97

BJ2170

Approach Slab

8 26-Feb-13

06-Mar-13

22-Jun-13

01-Jul-13

97

40 21-Mar-13

07-May-13

16-Jul-13

04-Sep-13

97

07-May-13, Bridge Deck

40 21-Mar-13

07-May-13

16-Jul-13

04-Sep-13

97

Bridge Deck Construction

106 23-Apr-13

30-Aug-13

21-Aug-13

21-Jun-14

238

26 23-Apr-13

23-May-13

21-Aug-13

21-Sep-13

97

BJ2430

Installation of Movement Joints in Bridge Deck and Approach Slab

12 17-Aug-13

30-Aug-13

09-Jun-14

21-Jun-14

238

12 07-Mar-13

20-Mar-13

02-Jul-13

15-Jul-13

97

12 07-Mar-13

20-Mar-13

02-Jul-13

15-Jul-13

97

40 14-Nov-12

02-Jan-13

19-Dec-12

27-Apr-13

97

BJ2400

Launching of Pre-tensioned Concrete Beams

Piling
BJ2000

Temporary Sheet Piling

BJ2005

Bored Piling

West Abutment

6 14-Nov-12

21-Nov-12

19-Dec-12

26-Dec-12

29

26 01-Dec-12

02-Jan-13

29-Mar-13

27-Apr-13

97

52 08-Dec-12

09-Feb-13

24-Apr-13

01-Jul-13

117

Wing Wall & Curtail Wall


Approach Slab

30-Aug-13, Miscellaneous
Bridge Parapet, Lining to Abutment and Service Ducts
Installation of Movement Joints in Bridge Deck and Approach Slab
20-Mar-13, Precast Beams
Launching of Pre-tensioned Concrete Beams
02-Jan-13, Piling
Temporary Sheet Piling
Bored Piling
09-Feb-13, West Abutment

BJ2100

Pile Cap Construction

18 08-Dec-12

29-Dec-12

24-Apr-13

15-May-13

113

BJ2110

Abutment Wall

16 31-Dec-12

18-Jan-13

21-May-13

10-Jun-13

117

BJ2120

Wing Wall & Curtail Wall

10 19-Jan-13

31-Jan-13

11-Jun-13

21-Jun-13

117

BJ2130

Approach Slab

8 01-Feb-13

09-Feb-13

22-Jun-13

01-Jul-13

117

Approach Slab

48 11-Dec-12

07-Feb-13

04-May-13

01-Jul-13

119

07-Feb-13, Pier 1

Pier 1
BJ2200

Pile Cap Construction

22 11-Dec-12

07-Jan-13

04-May-13

30-May-13

119

BJ2210

Column Construction

26 08-Jan-13

07-Feb-13

31-May-13

01-Jul-13

119

54 11-Dec-12

15-Feb-13

26-Apr-13

01-Jul-13

113
113

Pier 2
BJ2220

Pile Cap Construction

22 11-Dec-12

07-Jan-13

26-Apr-13

22-May-13

BJ2230

Column Construction

32 08-Jan-13

15-Feb-13

23-May-13

01-Jul-13

113

62 15-Dec-12

01-Mar-13

17-Apr-13

01-Jul-13

101

Pier 3
BJ2240

Pile Cap Construction

22 15-Dec-12

11-Jan-13

17-Apr-13

13-May-13

101

BJ2250

Column Construction

40 12-Jan-13

01-Mar-13

14-May-13

01-Jul-13

101

26 18-Dec-12

18-Jan-13

31-May-13

01-Jul-13

135

Pier 4

Pile Cap Construction


Abutment Wall
Wing Wall & Curtail Wall

Pile Cap Construction


Column Construction
15-Feb-13, Pier 2
Pile Cap Construction
Column Construction
01-Mar-13, Pier 3
Pile Cap Construction
Column Construction
18-Jan-13, Pier 4

BJ2260

Pile Cap Construction

22 18-Dec-12

14-Jan-13

31-May-13

26-Jun-13

135

Pile Cap Construction

BJ2270

Column Construction

4 15-Jan-13

18-Jan-13

27-Jun-13

01-Jul-13

135

Column Construction

48 20-Dec-12

18-Feb-13

04-May-13

01-Jul-13

111

22 20-Dec-12

16-Jan-13

04-May-13

30-May-13

111

Pier 5
BJ2280

Pile Cap Construction

BJ2290

Column Construction

Bridge Extension Over Segambut Dalam (BR B.2)


Section 1 - East Bound
Piling
BJ3000

Temporary Sheet Piling

BJ3005

Bored Piling

West Abutment

26 17-Jan-13

18-Feb-13

31-May-13

01-Jul-13

111

236 15-Oct-12

29-Jul-13

21-Nov-12

21-Jun-14

264

236 15-Oct-12

29-Jul-13

21-Nov-12

21-Jun-14

264

38 15-Oct-12

30-Nov-12

21-Nov-12

28-Mar-13

97

6 15-Oct-12

20-Oct-12

21-Nov-12

27-Nov-12

29

26 30-Oct-12

30-Nov-12

27-Feb-13

28-Mar-13

97

52 03-Nov-12

07-Jan-13

16-Apr-13

18-Jun-13

134

BJ3100

Pile Cap Construction

18 03-Nov-12

26-Nov-12

16-Apr-13

07-May-13

134

BJ3110

Abutment Wall

16 27-Nov-12

14-Dec-12

08-May-13

27-May-13

134

BJ3120

Wing Wall & Curtail Wall

10 15-Dec-12

27-Dec-12

28-May-13

08-Jun-13

134

BJ3130

Approach Slab

8 28-Dec-12

07-Jan-13

10-Jun-13

18-Jun-13

134

48 08-Nov-12

07-Jan-13

20-Apr-13

18-Jun-13

134

Pier 1
BJ3180

Pile Cap Construction

22 08-Nov-12

05-Dec-12

20-Apr-13

16-May-13

134

BJ3190

Column Construction

26 06-Dec-12

07-Jan-13

17-May-13

18-Jun-13

134

62 14-Nov-12

29-Jan-13

04-Apr-13

18-Jun-13

116

Pier 2
BJ3200

Pile Cap Construction

22 14-Nov-12

10-Dec-12

04-Apr-13

29-Apr-13

116

BJ3210

Column Construction

40 11-Dec-12

29-Jan-13

30-Apr-13

18-Jun-13

116

62 20-Nov-12

02-Feb-13

04-Apr-13

18-Jun-13

112

Pier 3

18-Feb-13, Pier 5
Pile Cap Construction
Column Construction
29-Jul-13, Bridge Extension Over Segambut Dalam (BR B.2)
29-Jul-13, Section 1 - East Bound
30-Nov-12, Piling
Temporary Sheet Piling
Bored Piling
07-Jan-13, West Abutment
Pile Cap Construction
Abutment Wall
Wing Wall & Curtail Wall
Approach Slab
07-Jan-13, Pier 1
Pile Cap Construction
Column Construction
29-Jan-13, Pier 2
Pile Cap Construction
Column Construction
02-Feb-13, Pier 3

BJ3220

Pile Cap Construction

22 20-Nov-12

14-Dec-12

04-Apr-13

29-Apr-13

112

BJ3230

Column Construction

40 15-Dec-12

02-Feb-13

30-Apr-13

18-Jun-13

112

Column Construction

56 24-Nov-12

31-Jan-13

11-Apr-13

18-Jun-13

114

31-Jan-13, Pier 4

Pier 4
BJ3240

Pile Cap Construction

22 24-Nov-12

19-Dec-12

11-Apr-13

07-May-13

114

BJ3250

Column Construction

34 20-Dec-12

31-Jan-13

08-May-13

18-Jun-13

114

52 01-Dec-12

02-Feb-13

16-Apr-13

18-Jun-13

112

East Abu tment

Pile Cap Construction

Pile Cap Construction


Column Construction
02-Feb-13, East Abutment

BJ3140

Pile Cap Construction

18 01-Dec-12

21-Dec-12

16-Apr-13

07-May-13

112

Pile Cap Construction

BJ3150

Abutment Wall

16 22-Dec-12

11-Jan-13

08-May-13

27-May-13

112

Abutment Wall

BJ3160

Wing Wall & Curtail Wall

10 12-Jan-13

23-Jan-13

28-May-13

08-Jun-13

112

BJ3170

Approach Slab

8 25-Jan-13

02-Feb-13

10-Jun-13

18-Jun-13

112

12 04-Feb-13

18-Feb-13

19-Jun-13

02-Jul-13

112

18-Feb-13, Precast Beams

12 04-Feb-13

18-Feb-13

19-Jun-13

02-Jul-13

112

Launching of Post-tensioned Concrete Beams

Precast Beams
BJ3410

Launching of Post-tensioned Concrete Beams

Remaining Work

Summary

Wing Wall & Curtail Wall


Approach Slab

5 of 13

Critical Remaining Work


Milestone

Jul
25

30-Aug-13, Section 1 - East Bound

23-Jan-13

Bridge Parapet, Lining to Abutment and Service Ducts

Jun
24

06-Mar-13, East Abutment

16 25-Jan-13

BJ2420

2014
Apr
May
22
23

Bridge Widening Start (EB)

18 03-Jan-13

Precast Beams

Mar
21

30-Aug-13, Bridge Widening (EB)

29

Pile Cap Construction

Miscellaneous

Feb
20

ITS System

Abutment Wall

Bridge Deck Construction

Jan
19

Relocation of OFC

BJ2150

BJ2410

Dec
18

Lay Duct

BJ2140

Bridge Deck

Nov
17

WORK PROGRAMME

Date
30-Jul-12
11-Sep-12

Revision
Rev.0
Rev.1

Checked

Approved

Aug
26

NORTH-SOUTH EXPRESSWAY (PLUS)


PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Activity ID

Activity Name

Original Early Start


Duration

Bridge Deck
BJ3420

Bridge Deck Construction

Miscellaneous
BJ3430

Bridge Parapet, Lining to Abutment and Service Ducts

BJ3440

Installation of Movement Joints in Bridge Deck and Approach Slab

Extension of Viaduct at Edinburgh Estate (BR B.3)


Section 1 - East Bound
Piling
BJ4000

Temporary Sheet Piling

BJ4005

Bored Piling

West Abutment

Early Finish

Late Start

Late Finish

Total
Float

40 19-Feb-13

05-Apr-13

03-Jul-13

21-Aug-13

40 19-Feb-13

05-Apr-13

03-Jul-13

21-Aug-13

112

106 23-Mar-13

29-Jul-13

06-Aug-13

21-Jun-14

264

26 23-Mar-13

22-Apr-13

06-Aug-13

07-Sep-13

112

Aug
14

Sep
15

29-Oct-12

20-Oct-12

26-Feb-13

97

07-Aug-13, Section 1 - East Bound


29-Oct-12, Piling

6 15-Sep-12

22-Sep-12

20-Oct-12

27-Oct-12

29

Temporary Sheet Piling

30 24-Sep-12

29-Oct-12

21-Jan-13

26-Feb-13

97

Bored Piling

58 01-Oct-12

10-Dec-12

13-Apr-13

22-Jun-13

160
160
160

BJ4130

Approach Slab

10 29-Nov-12

10-Dec-12

12-Jun-13

22-Jun-13

160

40 03-Oct-12

21-Nov-12

06-May-13

22-Jun-13

176

BJ4200

Pile Cap Construction

22 03-Oct-12

29-Oct-12

06-May-13

31-May-13

176

BJ4210

Column Construction

18 30-Oct-12

21-Nov-12

03-Jun-13

22-Jun-13

176

48 05-Oct-12

03-Dec-12

25-Apr-13

22-Jun-13

166

BJ4220

Pile Cap Construction

22 05-Oct-12

31-Oct-12

25-Apr-13

21-May-13

166

BJ4230

Column Construction

26 01-Nov-12

03-Dec-12

22-May-13

22-Jun-13

166

58 08-Oct-12

17-Dec-12

13-Apr-13

22-Jun-13

154

BJ4240

Pile Cap Construction

22 08-Oct-12

02-Nov-12

13-Apr-13

09-May-13

154

BJ4250

Column Construction

36 03-Nov-12

17-Dec-12

10-May-13

22-Jun-13

154

68 10-Oct-12

02-Jan-13

02-Apr-13

22-Jun-13

142

BJ4260

Pile Cap Construction

22 10-Oct-12

05-Nov-12

02-Apr-13

26-Apr-13

142

BJ4270

Column Construction

46 06-Nov-12

02-Jan-13

27-Apr-13

22-Jun-13

142

68 12-Oct-12

04-Jan-13

02-Apr-13

22-Jun-13

140

BJ4280

Pile Cap Construction

22 12-Oct-12

07-Nov-12

02-Apr-13

26-Apr-13

140

BJ4290

Column Construction

46 08-Nov-12

04-Jan-13

27-Apr-13

22-Jun-13

140

68 15-Oct-12

07-Jan-13

02-Apr-13

22-Jun-13

138

BJ4300

Pile Cap Construction

22 15-Oct-12

09-Nov-12

02-Apr-13

26-Apr-13

138

BJ4310

Column Construction

46 10-Nov-12

07-Jan-13

27-Apr-13

22-Jun-13

138

72 17-Oct-12

14-Jan-13

28-Mar-13

22-Jun-13

132

BJ4320

Pile Cap Construction

22 17-Oct-12

12-Nov-12

28-Mar-13

22-Apr-13

132

BJ4330

Column Construction

50 14-Nov-12

14-Jan-13

23-Apr-13

22-Jun-13

132

72 19-Oct-12

16-Jan-13

28-Mar-13

22-Jun-13

130

BJ4340

Pile Cap Construction

22 19-Oct-12

16-Nov-12

28-Mar-13

22-Apr-13

130

BJ4350

Column Construction

50 17-Nov-12

16-Jan-13

23-Apr-13

22-Jun-13

130

58 22-Oct-12

02-Jan-13

13-Apr-13

22-Jun-13

142

BJ4360

Pile Cap Construction

22 22-Oct-12

19-Nov-12

13-Apr-13

09-May-13

142

BJ4370

Column Construction

36 20-Nov-12

02-Jan-13

10-May-13

22-Jun-13

142

48 24-Oct-12

21-Dec-12

25-Apr-13

22-Jun-13

150

BJ4380

Pile Cap Construction

22 24-Oct-12

21-Nov-12

25-Apr-13

21-May-13

150

BJ4390

Column Construction

26 22-Nov-12

21-Dec-12

22-May-13

22-Jun-13

150

58 30-Oct-12

09-Jan-13

13-Apr-13

22-Jun-13

136

10-Dec-12, West Abutment


Pile Cap Construction
Abutment Wall
Wing Wall & Curtail Wall
Approach Slab
21-Nov-12, Pier 1
Pile Cap Construction
Column Construction
03-Dec-12, Pier 2
Pile Cap Construction
Column Construction
17-Dec-12, Pier 3
Pile Cap Construction
Column Construction
02-Jan-13, Pier 4
Pile Cap Construction
Column Construction
04-Jan-13, Pier 5
Pile Cap Construction
Column Construction
07-Jan-13, Pier 6
Pile Cap Construction
Column Construction
14-Jan-13, Pier 7
Pile Cap Construction
Column Construction
16-Jan-13, Pier 8
Pile Cap Construction
Column Construction
02-Jan-13, Pier 9
Pile Cap Construction
Column Construction
21-Dec-12, Pier 10
Pile Cap Construction
Column Construction
09-Jan-13, East Abutment

BJ4150

Pile Cap Construction

22 30-Oct-12

26-Nov-12

13-Apr-13

09-May-13

136

Pile Cap Construction

BJ4160

Abutment Wall

18 27-Nov-12

17-Dec-12

10-May-13

31-May-13

136

Abutment Wall

BJ4170

Wing Wall & Curtail Wall

12 13-Dec-12

27-Dec-12

28-May-13

11-Jun-13

136

BJ4180

Approach Slab

10 28-Dec-12

09-Jan-13

12-Jun-13

22-Jun-13

136

16 17-Jan-13

05-Feb-13

24-Jun-13

11-Jul-13

130

05-Feb-13, Precast Beams

16 17-Jan-13

05-Feb-13

24-Jun-13

11-Jul-13

130

Launching of Post-tensioned Concrete Beams

46 06-Feb-13

01-Apr-13

12-Jul-13

07-Sep-13

130

01-Apr-13, Bridge Deck

46 06-Feb-13

01-Apr-13

12-Jul-13

07-Sep-13

130

Bridge Deck Construction

118 19-Mar-13

07-Aug-13

24-Aug-13

14-Jun-14

250

32 19-Mar-13

24-Apr-13

24-Aug-13

02-Oct-13

130

18 17-Jul-13

07-Aug-13

24-May-14

14-Jun-14

250

173 01-Oct-12

27-Apr-13

08-Dec-12

05-Jul-14

351

05-Jul-14

351

Slope Improvement Works Finish (EB)

Miscellaneous
BJ4420

Bridge Parapet, Lining to Abutment and Service Ducts

BJ4430

Installation of Movement Joints in Bridge Deck and Approach Slab

Slope Improvement Works (EB)


BL0010

Slope Improvement Works Start (EB)

0 01-Oct-12

BL0020

Slope Improvement Works Finish (EB)

Overall Stage 1
Fill Area
Slope Improvement - Retaining Wall (CH.4300-CH.4540)

08-Dec-12
27-Apr-13

Slope Improvement Works Start (EB)

04-Apr-14

275

27-Apr-13, Overall Stage 1

40 13-Mar-13

27-Apr-13

18-Feb-14

04-Apr-14

275

27-Apr-13, Fill Area

40 13-Mar-13

27-Apr-13

18-Feb-14

04-Apr-14

275

18-Feb-14

19-Mar-14

275

BL2320

Construction of Wall Base

26 20-Mar-13

18-Apr-13

25-Feb-14

26-Mar-14

275

BL2330

Construction of Retaining Wall

26 25-Mar-13

23-Apr-13

01-Mar-14

31-Mar-14

275

BL2340

Backfill

26 29-Mar-13

27-Apr-13

06-Mar-14

04-Apr-14

275

172 01-Oct-12

26-Apr-13

08-Dec-12

04-Jul-13

56

172 01-Oct-12

26-Apr-13

08-Dec-12

04-Jul-13

56

BL1000

Installation of Horizontal Drain (CH.0-CH.1400)

43 01-Oct-12

22-Nov-12

08-Dec-12

30-Jan-13

56

BL1010

Installation of Horizontal Drain (CH.1400-CH.2800)

43 23-Nov-12

14-Jan-13

31-Jan-13

22-Mar-13

56

BL1020

Installation of Horizontal Drain (CH.2800-CH.4200)

43 15-Jan-13

07-Mar-13

23-Mar-13

13-May-13

56

BL1030

Installation of Horizontal Drain (CH.4200-CH.5600)

43 08-Mar-13

26-Apr-13

14-May-13

04-Jul-13

56

Summary

Installation of Movement Joints in Bridge Deck and Approach Slab


27-Apr-13, Slope Improvement Works (EB)

08-Dec-12

11-Apr-13

Remaining Work

07-Aug-13, Miscellaneous
Bridge Parapet, Lining to Abutment and Service Ducts

27-Apr-13

26 13-Mar-13

Slope Improvement - Horizontal Drain

Approach Slab

173 01-Oct-12

Excavation

Cut Area

Wing Wall & Curtail Wall

56

BL2300

27-Apr-13, Slope Improvement - Retaining Wall (CH.4300- CH.4540)


Excavation
Construction of Wall Base
Construction of Retaining Wall
Backfill
26-Apr-13, Cut Area
26-Apr-13, Slope Improvement - Horizontal Drain
Installation of Horizontal Drain (CH.0-CH.1400)
Installation of Horizontal Drain (CH.1400-CH.2800)
Installation of Horizontal Drain (CH.2800-CH.4200)
Installation of Horizontal Drain (CH.4200-CH.5600)

6 of 13

Critical Remaining Work


Milestone

Jul
25

29-Jul-13, Miscellaneous

36 15-Sep-12

11-Jun-13

Jun
24

Bridge Parapet, Lining to Abutment and Service Ducts


07-Aug-13, Extension of Viaduct at Edinburgh Estate (BR B.3)

31-May-13

2014
Apr
May
22
23

Bridge Deck Construction

250

28-May-13

Bridge Deck Construction

Mar
21

14-Jun-14

10-May-13

BJ4410

Feb
20

20-Oct-12

28-Nov-12

Bridge Deck

Jan
19

07-Aug-13

19-Nov-12

Launching of Post-tensioned Concrete Beams

Dec
18

268 15-Sep-12

12 14-Nov-12

BJ4400

Nov
17

Installation of Movement Joints in Bridge Deck and Approach Slab

18 27-Oct-12

Precast Beams

Oct
16

250

Wing Wall & Curtail Wall

East Abu tment

2013
Apr
May
Jun
Jul
10
11
12
13
05-Apr-13, Bridge Deck

264

Abutment Wall

Pier 10

Mar
9

14-Jun-14

BJ4120

Pier 9

Feb
8

21-Jun-14

BJ4110

Pier 8

Jan
7

20-Oct-12

160

Pier 7

Dec
6

09-Jun-14

09-May-13

Pier 6

Nov
5

07-Aug-13

13-Apr-13

Pier 5

Oct
4

29-Jul-13

25-Oct-12

Pier 4

Sep
3

12 15-Jul-13

22 01-Oct-12

Pier 3

Aug
2

268 15-Sep-12

Pile Cap Construction

Pier 2

Jul
1

112

BJ4100

Pier 1

2012
Jun
-1

WORK PROGRAMME

Date
30-Jul-12
11-Sep-12

Revision
Rev.0
Rev.1

Checked

Approved

Aug
26

NORTH-SOUTH EXPRESSWAY (PLUS)


PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Activity ID

Activity Name

Original Early Start


Duration
168 07-Sep-12

Ground Treatment Works (EB)


BM0010

Ground Treatment Works Start (EB)

0 07-Sep-12

BM0020

Ground Treatment Works Finish (EB)

Stage 1
Ground Treatment (CH.4200-CH.5600)

Early Finish

30-Mar-13

Late Start

13-Sep-12

Late Finish

05-Jul-14

375

05-Jul-14

375

13-Sep-12
30-Mar-13

Total
Float

2012
Jun
-1

Jul
1

Aug
2

Sep
3

168 07-Sep-12

30-Mar-13

13-Sep-12

20-May-13

42

42 09-Feb-13

30-Mar-13

01-Apr-13

20-May-13

42

Oct
4

Nov
5

Dec
6

Jan
7

Feb
8

2013
Apr
May
Jun
Jul
Aug
10
11
12
13
14
30-Mar-13, Ground Treatment Works (EB)

Mar
9

01-Apr-13

06-May-13

42

Excavation of Unsuitable Material

BM1310

Laying of Geotextile Separator

30 15-Feb-13

21-Mar-13

05-Apr-13

10-May-13

42

Laying of Geotextile Separator

BM1320

Laying of Outlet Drain

30 20-Feb-13

26-Mar-13

10-Apr-13

15-May-13

42

BM1330

Backfilling with Compacted Soil / hardcore Material

30 25-Feb-13

30-Mar-13

15-Apr-13

20-May-13

42

42 29-Oct-12

18-Dec-12

19-Dec-12

08-Feb-13

42

30 29-Oct-12

04-Dec-12

19-Dec-12

25-Jan-13

42

Excavation of Unsuitable Material

Laying of Geotextile Separator

30 02-Nov-12

08-Dec-12

24-Dec-12

30-Jan-13

42

Laying of Geotextile Separator

BM1120

Laying of Outlet Drain

30 07-Nov-12

13-Dec-12

29-Dec-12

04-Feb-13

42

BM1130

Backfilling with Compacted Soil / hardcore Material

30 12-Nov-12

18-Dec-12

04-Jan-13

08-Feb-13

42

42 19-Dec-12

08-Feb-13

09-Feb-13

30-Mar-13

42

08-Feb-13, Ground Treatment (CH.2800-CH.4200)

30 19-Dec-12

25-Jan-13

09-Feb-13

16-Mar-13

42

Excavation of Unsuitable Material

BM1210

Laying of Geotextile Separator

30 24-Dec-12

30-Jan-13

15-Feb-13

21-Mar-13

42

Laying of Geotextile Separator

BM1220

Laying of Outlet Drain

30 29-Dec-12

04-Feb-13

20-Feb-13

26-Mar-13

42

BM1230

Backfilling with Compacted Soil / hardcore Material

30 04-Jan-13

08-Feb-13

25-Feb-13

30-Mar-13

42

42 07-Sep-12

27-Oct-12

13-Sep-12

02-Nov-12

Laying of Outlet Drain


Backfilling with Compacted Soil / hardcore Material
27-Oct-12, Ground Treatment (CH.0-CH.1400)

BM1000

Excavation of Unsuitable Material

30 07-Sep-12

12-Oct-12

13-Sep-12

18-Oct-12

Excavation of Unsuitable Material

BM1010

Laying of Geotextile Separator

30 12-Sep-12

17-Oct-12

19-Sep-12

23-Oct-12

Laying of Geotextile Separator

BM1020

Laying of Outlet Drain

30 18-Sep-12

22-Oct-12

24-Sep-12

29-Oct-12

BM1030

Backfilling with Compacted Soil / hardcore Material

30 22-Sep-12

27-Oct-12

28-Sep-12

02-Nov-12

219 05-Jan-13

28-Sep-13

09-Oct-13

05-Jul-14

Electrical Works for Street Lighting Finish (EB)

Overall Stage 1
BN0100

Testing and Commissioning

CH.1400-CH.2800

28-Sep-13

Laying of Outlet Drain


Backfilling with Compacted Soil / hardcore Material

227

28-Sep-13, Electrical Works for Street Lighting (EB)

227

Electrical Works for Street Lighting Start (EB)

05-Jul-14

227

Electrical Works for Street Lighting Finish (EB)

219 05-Jan-13

28-Sep-13

09-Oct-13

05-Jul-14

227

28-Sep-13, Overall Stage 1

60 16-Jul-13

28-Sep-13

24-Apr-14

05-Jul-14

227

37 20-Feb-13

03-Apr-13

25-Nov-13

09-Jan-14

227

03-Apr-13, CH.1400-CH.2800
High Mast

Testing and Commissioning

BN1100

High Mast

37 20-Feb-13

03-Apr-13

25-Nov-13

09-Jan-14

227

BN1110

Street Lighting

37 20-Feb-13

03-Apr-13

25-Nov-13

09-Jan-14

227

Street Lighting

37 05-Jan-13

19-Feb-13

09-Oct-13

23-Nov-13

227

19-Feb-13, CH.0-CH.1400

CH.0-CH.1400
BN1000

High Mast

37 05-Jan-13

19-Feb-13

09-Oct-13

23-Nov-13

227

High Mast

BN1010

Street Lighting

37 05-Jan-13

19-Feb-13

09-Oct-13

23-Nov-13

227

Street Lighting

37 04-Apr-13

17-May-13

10-Jan-14

26-Feb-14

227

17-May-13, CH.2800-CH.4200

CH.2800-CH.4200
BN1200

High Mast

37 04-Apr-13

17-May-13

10-Jan-14

26-Feb-14

227

High Mast

BN1210

Street Lighting

37 04-Apr-13

17-May-13

10-Jan-14

26-Feb-14

227

Street Lighting

37 18-May-13

02-Jul-13

27-Feb-14

10-Apr-14

227

02-Jul-13, CH.4200-CH.5600

CH.4200-CH.5600
BN1300

High Mast

37 18-May-13

02-Jul-13

27-Feb-14

10-Apr-14

227

High Mast

BN1310

Street Lighting

37 18-May-13

02-Jul-13

27-Feb-14

10-Apr-14

227

Street Lighting

370 01-Apr-13

01-Jul-14

01-Apr-13

05-Jul-14

370 01-Apr-13

01-Jul-14

01-Apr-13

05-Jul-14

Phase 2 (West Bound)


Site Clearance and Fencing (WB)
BC3000

Site Clearance and Fencing Start (WB)

BC3010

Site Clearance and Fencing Finish (WB)

Site Clearing and Fencing (CH.4200-CH.2800)

0 01-Apr-13

05-Jul-14

0 01-Jul-14

01-Jul-14, Phase 2 (West Bound)


01-Jul-14, Site Clearance and Fencing (WB)

375

05-Jul-14

Site Clearance and Fencing Start (WB)

242 04-Jun-13

29-Mar-14

21-Jun-13

04-Apr-14

Site Clearance and Fencing Finish (WB)


29-Mar-14, Site Clearing and Fencing (CH.4200-CH.2800)

BC2100

Site Clearing & Demolition Works

52 04-Jun-13

03-Aug-13

21-Jun-13

23-Aug-13

15

Site Clearing & Demolition Works

BC2110

Demolition Works

38 20-Jun-13

03-Aug-13

13-Aug-13

27-Sep-13

43

Demolition Works

BC2120

Relocation & Installation of Temporary Signage & Gantry

38 20-Jun-13

03-Aug-13

20-Feb-14

04-Apr-14

195

BC2130

Fencing and Gate

38 13-Feb-14

29-Mar-14

20-Feb-14

04-Apr-14

BC2140

Miscellaneous Dismantling, Demolition and Excavation

38 20-Jun-13

03-Aug-13

20-Feb-14

04-Apr-14

195

256 01-Apr-13

12-Feb-14

01-Apr-13

19-Feb-14

BC2000

Site Clearing & Demolition Works

52 01-Apr-13

03-Jun-13

01-Apr-13

03-Jun-13

BC2010

Demolition Works

38 17-Apr-13

03-Jun-13

26-Jun-13

12-Aug-13

57

BC2020

Relocation & Installation of Temporary Signage & Gantry

38 17-Apr-13

03-Jun-13

02-Jan-14

19-Feb-14

209

BC2030

Fencing and Gate

38 26-Dec-13

12-Feb-14

02-Jan-14

19-Feb-14

BC2040

Miscellaneous Dismantling, Demolition and Excavation

38 17-Apr-13

03-Jun-13

02-Jan-14

19-Feb-14

209

Site Clearing and Fencing (CH.5600-CH.4200)

Relocation & Installation of Temporary Signage & Gantry


Fencing and Gate
Miscellaneous Dismantling, Demolition and Excavation
12-Feb-14, Site Clearing and Fencing (CH.5600-CH.4200)
Site Clearing & Demolition Works
Demolition Works
Relocation & Installation of Temporary Signage & Gantry
Fencing and Gate
Miscellaneous Dismantling, Demolition and Excavation

228 05-Aug-13

15-May-14

24-Aug-13

21-May-14

BC2200

Site Clearing & Demolition Works

52 05-Aug-13

08-Oct-13

24-Aug-13

26-Oct-13

15

Site Clearing & Demolition Works

BC2210

Demolition Works

38 23-Aug-13

08-Oct-13

28-Sep-13

14-Nov-13

29

Demolition Works

BC2220

Relocation & Installation of Temporary Signage & Gantry

38 23-Aug-13

08-Oct-13

05-Apr-14

21-May-14

181

BC2230

Fencing and Gate

38 31-Mar-14

15-May-14

05-Apr-14

21-May-14

BC2240

Miscellaneous Dismantling, Demolition and Excavation

38 23-Aug-13

08-Oct-13

05-Apr-14

21-May-14

181

Site Clearing and Fencing (CH.2800-CH.1400)

15-May-14, Site Clearing and Fencing (CH.2800-CH.1400)

Relocation & Installation of Temporary Signage & Gantry


Fencing and Gate
Miscellaneous Dismantling, Demolition and Excavation

214 09-Oct-13

30-Jun-14

28-Oct-13

05-Jul-14

BC2300

Site Clearing & Demolition Works

52 09-Oct-13

12-Dec-13

28-Oct-13

31-Dec-13

15

Site Clearing & Demolition Works

BC2310

Demolition Works

38 26-Oct-13

12-Dec-13

15-Nov-13

31-Dec-13

15

Demolition Works

BC2320

Relocation & Installation of Temporary Signage & Gantry

38 26-Oct-13

12-Dec-13

15-Nov-13

31-Dec-13

15

Relocation & Installation of Temporary Signage & Gantry

BC2330

Fencing and Gate

38 16-May-14

30-Jun-14

22-May-14

05-Jul-14

BC2340

Miscellaneous Dismantling, Demolition and Excavation

38 26-Oct-13

12-Dec-13

22-May-14

05-Jul-14

167

341 02-May-13

26-Jun-14

02-May-13

05-Jul-14

Site Clearing and Fencing (CH.1400-CH.0)

Earthworks (WB)
BD6500

Earthwork Start (WB)

BD6510

Earthwork Finish (WB)

0 02-May-13
0
133 16-Jan-14

Stage 2

Remaining Work

Summary

05-Jul-14
26-Jun-14
26-Jun-14

16-Jan-14

30-Jun-14, Site Clearing and Fencing (CH.1400-

Fencing and Gate


Miscellaneous Dismantling, Demolition and Excavation

26-Jun-14, Earthworks (WB)

349
05-Jul-14

05-Jul-14

Earthwork Start (WB)


Earthwork Finish (WB)
26-Jun-14, Stage 2

7 of 13

Critical Remaining Work


Milestone

Aug
26

Backfilling with Compacted Soil / hardcore Material

Excavation of Unsuitable Material

BN0020

Jul
25

Laying of Outlet Drain

BM1200

09-Oct-13

Jun
24

Backfilling with Compacted Soil / hardcore Material

Excavation of Unsuitable Material

0 05-Jan-13

2014
Apr
May
22
23

Mar
21

18-Dec-12, Ground Treatment (CH.1400-CH.2800)

BM1110

Electrical Works for Street Lighting Start (EB)

Feb
20

Laying of Outlet Drain

BM1100

BN0010

Jan
19

30-Mar-13, Ground Treatment (CH.4200-CH.5600)

16-Mar-13

Electrical Works for Street Lighting (EB)

Dec
18

30-Mar-13, Stage 1

30 09-Feb-13

Ground Treatment (CH.0-CH.1400)

Nov
17

Ground Treatment Works Finish (EB)

Excavation of Unsuitable Material

Ground Treatment (CH.2800-CH.4200)

Oct
16

Ground Treatment Works Start (EB)

BM1300

Ground Treatment (CH.1400-CH.2800)

Sep
15

WORK PROGRAMME

Date
30-Jul-12
11-Sep-12

Revision
Rev.0
Rev.1

Checked

Approved

NORTH-SOUTH EXPRESSWAY (PLUS)


PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B

42 26-Feb-14

15-Apr-14

05-Mar-14

24-Apr-14

2014
Apr
May
Jun
Jul
Aug
22
23
24
25
26
15-Apr-14, CH.4200-CH.2800

BD7100

Removal of Existing Pavement

32 26-Feb-14

03-Apr-14

05-Mar-14

10-Apr-14

Removal of Existing Pavement

BD7110

Turfin g (Remaining Works)

32 10-Mar-14

15-Apr-14

19-Mar-14

24-Apr-14

BD7120

Treatment of Existing Subsoil Dr ain

32 04-Mar-14

09-Apr-14

19-Mar-14

24-Apr-14

13

Activity ID

Activity Name

Original Early Start


Duration

CH.4200-CH.2800

Early Finish

Late Start

Late Finish

Total
Float

42 04-Apr-14

24-May-14

11-Apr-14

04-Jun-14

BD7200

Removal of Existing Pavement

32 04-Apr-14

12-May-14

11-Apr-14

20-May-14

BD7210

Turfin g (Remaining Works)

32 16-Apr-14

24-May-14

25-Apr-14

04-Jun-14

BD7220

Treatment of Existing Subsoil Dr ain

32 10-Apr-14

19-May-14

25-Apr-14

04-Jun-14

13

CH.2800-CH.1400

42 16-Jan-14

08-Mar-14

16-Jan-14

18-Mar-14

BD7000

Removal of Existing Pavement

32 16-Jan-14

25-Feb-14

16-Jan-14

25-Feb-14

BD7010

Turfin g (Remaining Works)

32 28-Jan-14

08-Mar-14

08-Feb-14

18-Mar-14

BD7020

Treatment of Existing Subsoil Dr ain

32 22-Jan-14

03-Mar-14

03-Feb-14

12-Mar-14

CH.5600-CH.4200

2012
Jun
-1

2013
Jul
1

Aug
2

Sep
3

Oct
4

Nov
5

Dec
6

Jan
7

Feb
8

Mar
9

Apr
10

May
11

Jun
12

Jul
13

Aug
14

Sep
15

Oct
16

Nov
17

Dec
18

Jan
19

Feb
20

Mar
21

Turfin g (Remaining Works)


Treatment of Existing Subsoil Dr ain
24-May-14, CH.2800-CH.1400
Removal of Existing Pavement
Turfin g (Remaining Works)
Treatment of Existing Subsoil Dr ain
08-Mar-14, CH.5600-CH.4200
Removal of Existing Pavement
Turfing (Remaining Works)
Treatment of Existing Subsoil Dr ain

37 14-May-14

26-Jun-14

21-May-14

05-Jul-14

26-Jun-14, CH.1400-CH.0

BD7300

Removal of Existing Pavement

27 14-May-14

14-Jun-14

21-May-14

21-Jun-14

Removal of Existing Pavement

BD7310

Turfin g (Remaining Works)

27 26-May-14

26-Jun-14

05-Jun-14

05-Jul-14

BD7320

Treatment of Existing Subsoil Dr ain

27 20-May-14

20-Jun-14

05-Jun-14

05-Jul-14

13

233 02-May-13

17-Feb-14

02-May-13

05-Jul-14

116

77 02-May-13

02-Aug-13

02-May-13

26-Dec-13

116

CH.1400-CH.0

Stage 1
CH.5600-CH.4200
BD6000

Excavate to Toe of Slo pe (CH.5600-CH.4200)

52 02-May-13

03-Jul-13

02-May-13

03-Jul-13

BD6010

Fill to Formation Level (CH.5600-CH.4200)

52 22-May-13

23-Jul-13

29-May-13

30-Jul-13

BD6020

Turfin g

52 03-Jun-13

02-Aug-13

18-Jun-13

20-Aug-13

13

BD6030

Instrumentation and Monitoring

58 22-May-13

31-Jul-13

16-Oct-13

26-Dec-13

118

BD6040

Soil Investigation

52 02-May-13

03-Jul-13

23-Oct-13

26-Dec-13

141

77 07-Sep-13

10-Dec-13

07-Sep-13

03-May-14

116

CH.2800-CH.1400
BD6200

Excavate to Toe of Slo pe (CH.2800-CH.1400)

52 07-Sep-13

11-Nov-13

07-Sep-13

11-Nov-13

BD6210

Fill to Formation Level (CH.2800-CH.1400)

52 28-Sep-13

30-Nov-13

14-Oct-13

17-Dec-13

13

BD6220

Turfin g

52 08-Oct-13

10-Dec-13

24-Oct-13

27-Dec-13

13

BD6230

Instrumentation and Monitoring

58 28-Sep-13

07-Dec-13

25-Feb-14

03-May-14

118

BD6240

Soil Investigation

52 07-Sep-13

11-Nov-13

04-Mar-14

03-May-14

141

77 04-Jul-13

07-Oct-13

04-Jul-13

03-Mar-14

116

CH.4200-CH.2800
BD6100

Excavate to Toe of Slo pe (CH.4200-CH.2800)

52 04-Jul-13

06-Sep-13

04-Jul-13

06-Sep-13

BD6110

Fill to Formation Level (CH.4200-CH.2800)

52 24-Jul-13

27-Sep-13

12-Aug-13

12-Oct-13

13

BD6120

Turfin g

52 03-Aug-13

07-Oct-13

21-Aug-13

23-Oct-13

13

BD6130

Instrumentation and Monitoring

58 24-Jul-13

04-Oct-13

19-Dec-13

03-Mar-14

118

BD6140

Soil Investigation

52 04-Jul-13

06-Sep-13

27-Dec-13

03-Mar-14

141

77 12-Nov-13

17-Feb-14

12-Nov-13

05-Jul-14

116

CH.1400-CH.0
BD6300

Excavate to Toe of Slo pe (CH.1400-CH.0)

52 12-Nov-13

15-Jan-14

12-Nov-13

15-Jan-14

BD6310

Fill to Formation Level (CH.1400-CH.0)

52 02-Dec-13

06-Feb-14

18-Dec-13

22-Feb-14

13

BD6320

Turfin g

52 12-Dec-13

17-Feb-14

28-Dec-13

04-Mar-14

13

BD6330

Instrumentation and Monitoring

58 02-Dec-13

13-Feb-14

26-Apr-14

05-Jul-14

118

BD6340

Soil Investigation

52 12-Nov-13

15-Jan-14

05-May-14

05-Jul-14

141

318 04-Jun-13

30-Jun-14

10-Jun-13

05-Jul-14

Drainage Works (WB)


BE4040

Drainage Works Start (WB)

BE4050

Drainage Works Finish (WB)

Stage 1

0 04-Jun-13
0

05-Jul-14
30-Jun-14

Turfin g (Remaining Works)


Treatment of Existing Subsoil Dr ain
17-Feb-14, Stage 1
02-Aug-13, CH.5600-CH.4200
Excavate to Toe of Slo pe (CH.5600-CH.4200)
Fill to Formation Level (CH.5600-CH.4200)
Turfin g
Instrumentation and Monitoring
Soil Investigation
10-Dec-13, CH.2800-CH.1400
Excavate to Toe of Slope (CH.2800-CH.1400)
Fill to Formation Level (CH.2800-CH.1400)
Turfing
Instrumentation and Monitoring
Soil Investigation
07-Oct-13, CH.4200-CH.2800
Excavate to Toe of Slo pe (CH.4200-CH.2800)
Fill to Formation Level (CH.4200-CH.2800)
Turfing
Instrumentation and Monitoring
Soil Investigation
17-Feb-14, CH.1400-CH.0
Excavate to Toe of Slo pe (CH.1400-CH.0)
Fill to Formation Level (CH.1400-CH.0)
Turfin g
Instrumentation and Monitoring
Soil Investigation
30-Jun-14, Drainage Works (WB)

323
05-Jul-14

188 04-Jun-13

22-Jan-14

10-Jun-13

28-Jan-14

Drainage Works Start (WB)


Drainage Works Finish (WB)
22-Jan-14, Stage 1

47 04-Jun-13

29-Jul-13

10-Jun-13

03-Aug-13

BE2000

Excavation

33 04-Jun-13

11-Jul-13

10-Jun-13

17-Jul-13

BE2010

Laying of Drain

33 12-Jun-13

19-Jul-13

18-Jun-13

26-Jul-13

Laying of Drain

BE2020

Backfilling

33 20-Jun-13

29-Jul-13

26-Jun-13

03-Aug-13

Backfilling

47 30-Jul-13

26-Sep-13

05-Aug-13

02-Oct-13

Drainage (CH.5600-CH.4200)

Drainage (CH.4200-CH.2800)

29-Jul-13, Drainage (CH.5600-CH.4200)


Excavation

26-Sep-13, Drainage (CH.4200-CH.2800)

BE2100

Excavation

33 30-Jul-13

09-Sep-13

05-Aug-13

14-Sep-13

BE2110

Laying of Drain

33 07-Aug-13

18-Sep-13

15-Aug-13

24-Sep-13

Laying of Drain

BE2120

Backfilling

33 17-Aug-13

26-Sep-13

23-Aug-13

02-Oct-13

Backfilling

47 27-Sep-13

23-Nov-13

03-Oct-13

29-Nov-13

Drainage (CH.2800-CH.1400)

Excavation

23-Nov-13, Drainage (CH.2800-CH.1400)

BE2200

Excavation

33 27-Sep-13

07-Nov-13

03-Oct-13

13-Nov-13

BE2210

Laying of Drain

33 05-Oct-13

15-Nov-13

11-Oct-13

21-Nov-13

Laying of Drain

BE2220

Backfilling

33 14-Oct-13

23-Nov-13

21-Oct-13

29-Nov-13

Backfilling

47 25-Nov-13

22-Jan-14

30-Nov-13

28-Jan-14

Drainage (CH.1400-CH.0)

Excavation

22-Jan-14, Drainage (CH.1400-CH.0)

BE2300

Excavation

33 25-Nov-13

04-Jan-14

30-Nov-13

10-Jan-14

BE2310

Laying of Drain

33 03-Dec-13

13-Jan-14

09-Dec-13

20-Jan-14

Laying of Drain

BE2320

Backfilling

33 12-Dec-13

22-Jan-14

18-Dec-13

28-Jan-14

Backfilling

130 23-Jan-14

30-Jun-14

29-Jan-14

05-Jul-14

130 23-Jan-14

30-Jun-14

29-Jan-14

05-Jul-14

Stage 2
Drains (Remaining Works) and Kerbs

Excavation

30-Jun-14, Stage 2

30-Jun-14, Drains (Remaining Works) and Kerb

BE4000

CH.5600-CH.4200

32 23-Jan-14

04-Mar-14

29-Jan-14

10-Mar-14

BE4010

CH.4200-CH.2800

32 05-Mar-14

10-Apr-14

11-Mar-14

16-Apr-14

BE4020

CH.2800-CH.1400

33 11-Apr-14

21-May-14

17-Apr-14

27-May-14

BE4030

CH.1400-CH.0

33 22-May-14

30-Jun-14

28-May-14

05-Jul-14

CH.1400-CH.0

143 06-Jan-14

28-Jun-14

27-Jan-14

05-Jul-14

28-Jun-14, Sub-Base, Roadbase and Pavement

Sub-Base, Roadbase and Pavement (WB)


BF3020

Sub-Base, Roadbase and Pavement Start (WB)

0 06-Jan-14

BF3030

Sub-Base, Roadbase and Pavement Finish (WB)

Stage 2
BF3010

Sub-surface Drainage Improvement (West Bound)

Sub-Base upto Pavement (CH.5600-CH.4200)

Remaining Work

Summary

05-Jul-14
28-Jun-14

CH.5600-CH.4200
CH.4200-CH.2800
CH.2800-CH.1400

149
05-Jul-14

143 06-Jan-14

28-Jun-14

27-Jan-14

05-Jul-14

130 06-Jan-14

13-Jun-14

29-Jan-14

05-Jul-14

19

38 27-Jan-14

14-Mar-14

27-Jan-14

18-Apr-14

30

Sub-Base, Roadbase and Pavement Start (WB)

Sub-Base, Roadbase and Pavement Finish (WB)


28-Jun-14, Stage 2
Sub-surface Drainage Improvement (West Bound)
14-Mar-14, Sub-Base upto Pavement (CH.5600-CH.4200)

8 of 13

Critical Remaining Work


Milestone

WORK PROGRAMME

Date
30-Jul-12
11-Sep-12

Revision
Rev.0
Rev.1

Checked

Approved

NORTH-SOUTH EXPRESSWAY (PLUS)


PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B

BF2010

Sub-Grade and Prepare Formation

24 27-Jan-14

26-Feb-14

27-Jan-14

26-Feb-14

2014
Mar
Apr
May
Jun
21
22
23
24
Sub-Grade and Prepare Formation

BF2020

Laying of Lower Sub-Base

24 29-Jan-14

28-Feb-14

29-Jan-14

28-Feb-14

Laying of Lower Sub-Base

BF2030

Laying of Lower Upper-Base

24 03-Feb-14

03-Mar-14

03-Feb-14

03-Mar-14

Laying of Lower Upper-Base

BF2040

Laying of CBM

22 05-Feb-14

03-Mar-14

05-Feb-14

03-Mar-14

Laying of CBM

BF2050

Laying of WMM

22 07-Feb-14

05-Mar-14

07-Feb-14

05-Mar-14

Laying of WMM

BF2060

Laying of DBM

22 10-Feb-14

07-Mar-14

10-Feb-14

07-Mar-14

Laying of DBM

BF2070

Laying of ACBC

22 12-Feb-14

10-Mar-14

12-Feb-14

10-Mar-14

Laying of ACBC

BF2075

Regulating

22 13-Feb-14

11-Mar-14

13-Feb-14

11-Mar-14

Regulating

BF2080

Laying of ACWC

22 14-Feb-14

12-Mar-14

14-Feb-14

12-Mar-14

Laying of ACWC

BF2090

Laying of SMA

22 18-Feb-14

14-Mar-14

18-Feb-14

14-Mar-14

Laying of SMA

BF2100

Dismantle Guardrail, NJB Installation & Misc. Works

32 05-Feb-14

14-Mar-14

13-Mar-14

18-Apr-14

30

Dismantle Guardrail, NJB Installation & Misc. Works

BF2110

Temporay Road Marking & Traffic Diversion/Contra Flow

32 05-Feb-14

14-Mar-14

13-Mar-14

18-Apr-14

30

Temporay Road Marking & Traffic Diversion/Contra Flow

38 08-Mar-14

21-Apr-14

02-Apr-14

05-Jul-14

62

Activity ID

Activity Name

Original Early Start


Duration

Sub-Base upto Pavement (CH.4200-CH.2800)

Early Finish

Late Start

Late Finish

Total
Float

2012
Jun
-1

2013
Jul
1

Aug
2

Sep
3

Oct
4

Nov
5

Dec
6

Jan
7

Feb
8

Mar
9

Apr
10

May
11

Jun
12

Jul
13

Aug
14

Sep
15

Oct
16

Nov
17

Dec
18

Jan
19

Feb
20

Jul
25

Aug
26

21-Apr-14, Sub-Base upto Pavement (CH.4200-CH.2800)

BF2210

Sub-Grade and Prepare Formation

24 08-Mar-14

04-Apr-14

02-Apr-14

29-Apr-14

21

BF2220

Laying of Lower Sub-Base

24 11-Mar-14

07-Apr-14

04-Apr-14

02-May-14

21

Laying of Lower Sub-Base

BF2230

Laying of Lower Upper-Base

24 13-Mar-14

09-Apr-14

07-Apr-14

05-May-14

21

Laying of Lower Upper-Base

BF2240

Laying of CBM

22 15-Mar-14

09-Apr-14

09-Apr-14

05-May-14

21

Laying of CBM

BF2250

Laying of WMM

22 18-Mar-14

11-Apr-14

11-Apr-14

07-May-14

21

Laying of WMM

BF2260

Laying of DBM

22 20-Mar-14

14-Apr-14

14-Apr-14

09-May-14

21

Laying of DBM

BF2270

Laying of ACBC

22 22-Mar-14

16-Apr-14

16-Apr-14

12-May-14

21

Laying of ACBC

BF2275

Regulating

22 24-Mar-14

17-Apr-14

17-Apr-14

14-May-14

21

Regulating

BF2280

Laying of ACWC

22 25-Mar-14

18-Apr-14

09-Jun-14

03-Jul-14

62

Laying of ACWC

BF2290

Laying of SMA

22 27-Mar-14

21-Apr-14

11-Jun-14

05-Jul-14

62

Laying of SMA

BF2300

Dismantle Guardrail, NJB Installation & Misc. Works

32 15-Mar-14

21-Apr-14

19-Apr-14

28-May-14

30

Dismantle Guardrail, NJB Installation & Misc. Works

BF2310

Temporay Road Marking & Traffic Diversion/Contra Flow

32 15-Mar-14

21-Apr-14

19-Apr-14

28-May-14

30

Temporay Road Marking & Traffic Diversion/Contra Flow

38 15-Apr-14

30-May-14

28-Apr-14

05-Jul-14

30

Sub-Base upto Pavement (CH.2800-CH.1400)

Sub-Grade and Prepare Formation

30-May-14, Sub-Base upto Pavement (CH.2800-CH.1400

BF2410

Sub-Grade and Prepare Formation

24 15-Apr-14

14-May-14

28-Apr-14

27-May-14

11

Sub-Grade and Prepare Formation

BF2420

Laying of Lower Sub-Base

24 17-Apr-14

16-May-14

30-Apr-14

29-May-14

11

Laying of Lower Sub-Base

BF2430

Laying of Lower Upper-Base

24 19-Apr-14

19-May-14

03-May-14

31-May-14

11

Laying of Lower Upper-Base

BF2440

Laying of CBM

22 22-Apr-14

19-May-14

06-May-14

31-May-14

11

Laying of CBM

BF2450

Laying of WMM

22 24-Apr-14

21-May-14

08-May-14

04-Jun-14

11

Laying of WMM

BF2460

Laying of DBM

22 26-Apr-14

23-May-14

10-May-14

06-Jun-14

11

Laying of DBM

BF2470

Laying of ACBC

22 29-Apr-14

26-May-14

14-May-14

09-Jun-14

11

Laying of ACBC

BF2475

Regulating

22 30-Apr-14

27-May-14

15-May-14

10-Jun-14

11

Regulating

BF2480

Laying of ACWC

22 02-May-14

28-May-14

09-Jun-14

03-Jul-14

30

Laying of ACWC

BF2490

Laying of SMA

22 05-May-14

30-May-14

11-Jun-14

05-Jul-14

30

Laying of SMA

BF2500

Dismantle Guardrail, NJB Installation & Misc. Works

32 22-Apr-14

30-May-14

29-May-14

05-Jul-14

30

Dismantle Guardrail, NJB Installation & Misc. Works

BF2510

Temporay Road Marking & Traffic Diversion/Contra Flow

32 22-Apr-14

30-May-14

29-May-14

05-Jul-14

30

Temporay Road Marking & Traffic Diversion/Contra Flow

35 19-May-14

28-Jun-14

26-May-14

05-Jul-14

Sub-Base upto Pavement (CH.1400-CH.0)

28-Jun-14, Sub-Base upto Pavement (CH.1400-C

BF2610

Sub-Grade and Prepare Formation

24 19-May-14

16-Jun-14

26-May-14

23-Jun-14

Sub-Grade and Prepare Formation

BF2620

Laying of Lower Sub-Base

24 20-May-14

17-Jun-14

27-May-14

24-Jun-14

Laying of Lower Sub-Base

BF2630

Laying of Lower Upper-Base

24 21-May-14

18-Jun-14

28-May-14

25-Jun-14

Laying of Lower Upper-Base

BF2640

Laying of CBM

22 24-May-14

19-Jun-14

31-May-14

26-Jun-14

Laying of CBM

BF2650

Laying of WMM

22 26-May-14

20-Jun-14

03-Jun-14

27-Jun-14

Laying of WMM

BF2660

Laying of DBM

22 27-May-14

21-Jun-14

04-Jun-14

28-Jun-14

Laying of DBM

BF2670

Laying of ACBC

22 29-May-14

24-Jun-14

06-Jun-14

01-Jul-14

Laying of ACBC

BF2675

Regulating

22 30-May-14

25-Jun-14

11-Jun-14

05-Jul-14

Regulating

BF2680

Laying of ACWC

22 31-May-14

26-Jun-14

09-Jun-14

03-Jul-14

Laying of ACWC

BF2690

Laying of SMA

22 04-Jun-14

28-Jun-14

11-Jun-14

05-Jul-14

Laying of SMA

BF2700

Dismantle Guardrail, NJB Installation & Misc. Works

30 24-May-14

28-Jun-14

31-May-14

05-Jul-14

Dismantle Guardrail, NJB Installation & Misc. Wor

BF2710

Temporay Road Marking & Traffic Diversion/Contra Flow

30 24-May-14

28-Jun-14

31-May-14

05-Jul-14

Temporay Road Marking & Traffic Diversion/Cont

75 01-Apr-14

30-Jun-14

01-Apr-14

05-Jul-14

Road Furniture (WB)


BG3000

Road Furniture Start (WB)

0 01-Apr-14

BG3010

Road Furniture Finish (WB)

Stage 2
CH.5600-CH.4200

05-Jul-14
30-Jun-14

30-Jun-14, Road Furniture (WB)

80

Road Furniture Start (WB)

05-Jul-14

75 01-Apr-14

30-Jun-14

01-Apr-14

05-Jul-14

Road Furniture Finish (WB)

19 01-Apr-14

22-Apr-14

01-Apr-14

28-Apr-14

22-Apr-14, CH.5600-CH.4200

30-Jun-14, Stage 2

BG2000

Traffic Signs

19 01-Apr-14

22-Apr-14

01-Apr-14

22-Apr-14

Traffic Signs

BG2010

Road Markings

19 01-Apr-14

22-Apr-14

07-Apr-14

28-Apr-14

Road Markings

BG2020

Ancillary Finishings

19 01-Apr-14

22-Apr-14

07-Apr-14

28-Apr-14

Ancillary Finishings

19 23-Apr-14

16-May-14

23-Apr-14

22-May-14

16-May-14, CH.4200-CH.2800

CH.4200-CH.2800
BG2100

Traffic Signs

19 23-Apr-14

16-May-14

23-Apr-14

16-May-14

Traffic Signs

BG2110

Road Markings

19 23-Apr-14

16-May-14

29-Apr-14

22-May-14

Road Markings

BG2120

Ancillary Finishings

19 23-Apr-14

16-May-14

29-Apr-14

22-May-14

Ancillary Finishings

19 17-May-14

09-Jun-14

17-May-14

14-Jun-14

09-Jun-14, CH.2800-CH.1400

CH.2800-CH.1400
BG2200

Traffic Signs

19 17-May-14

09-Jun-14

17-May-14

09-Jun-14

Traffic Signs

BG2210

Road Markings

19 17-May-14

09-Jun-14

23-May-14

14-Jun-14

Road Markings

BG2220

Ancillary Finishings

19 17-May-14

09-Jun-14

23-May-14

14-Jun-14

Ancillary Finishings

18 10-Jun-14

30-Jun-14

10-Jun-14

05-Jul-14

30-Jun-14, CH.1400-CH.0

CH.1400-CH.0
BG2300

Traffic Signs

18 10-Jun-14

30-Jun-14

10-Jun-14

30-Jun-14

Traffic Signs

BG2310

Road Markings

18 10-Jun-14

30-Jun-14

16-Jun-14

05-Jul-14

Road Markings

BG2320

Ancillary Finishings

18 10-Jun-14

30-Jun-14

16-Jun-14

05-Jul-14

Ancillary Finishings

221 01-Oct-13

30-Jun-14

07-Oct-13

05-Jul-14

Utilities and Services (WB)


BH0120

Utilities and Services Start (WB)

Remaining Work

Summary

0 01-Oct-13

05-Jul-14

30-Jun-14, Utilities and Services (WB)

226

Utilities and Services Start (WB)

9 of 13

Critical Remaining Work


Milestone

WORK PROGRAMME

Date
30-Jul-12
11-Sep-12

Revision
Rev.0
Rev.1

Checked

Approved

NORTH-SOUTH EXPRESSWAY (PLUS)


PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Activity ID

Activity Name

BH0130

Original Early Start


Duration

Utilities and Services Finish (WB)

Overall Stage 1
BH0010

Testing and Commissioning

CH.5600-CH.4200

Early Finish

Late Start

Late Finish

Total
Float

05-Jul-14

30-Jun-14

07-Oct-13

05-Jul-14

30-Jun-14, Overall Stage 1

63 15-Apr-14

30-Jun-14

21-Apr-14

05-Jul-14

71 01-Oct-13

27-Dec-13

07-Oct-13

19-Apr-14

92

30-Jun-14

Temporary Works for Existin g Utili ties

71 01-Oct-13

27-Dec-13

24-Jan-14

19-Apr-14

92

Water works, Relocation of Water Mains (CH.5450)

70 01-Oct-13

26-Dec-13

07-Oct-13

02-Jan-14

60 01-Oct-13

13-Dec-13

07-Oct-13

22-Jan-14

31

BH5000

Lay Duct

36 01-Oct-13

14-Nov-13

07-Oct-13

20-Nov-13

BH5010

Relocation of OFC

36 16-Oct-13

28-Nov-13

23-Nov-13

07-Jan-14

31

BH5020

ITS System

36 30-Oct-13

13-Dec-13

07-Dec-13

22-Jan-14

31

71 15-Nov-13

12-Feb-14

21-Nov-13

19-Apr-14

56

71 15-Nov-13

12-Feb-14

24-Jan-14

19-Apr-14

56

60 15-Nov-13

28-Jan-14

21-Nov-13

08-Mar-14

31

BH6030

Temporary Works for Existin g Utili ties

Telecommunication System
BH6000

Lay Duct

36 15-Nov-13

28-Dec-13

21-Nov-13

04-Jan-14

BH6010

Relocation of OFC

36 29-Nov-13

13-Jan-14

08-Jan-14

22-Feb-14

31

BH6020

ITS System

36 14-Dec-13

28-Jan-14

23-Jan-14

08-Mar-14

31

71 30-Dec-13

27-Mar-14

06-Jan-14

19-Apr-14

20

71 30-Dec-13

27-Mar-14

24-Jan-14

19-Apr-14

20

60 30-Dec-13

14-Mar-14

06-Jan-14

19-Apr-14

31

CH.2800-CH.1400
BH7030

Temporary Works for Existin g Utili ties

Telecommunication System

Jul
1

Aug
2

Sep
3

Oct
4

Nov
5

Dec
6

Jan
7

Feb
8

Mar
9

Apr
10

May
11

Jun
12

Jul
13

Aug
14

Sep
15

Oct
16

Nov
17

Dec
18

Jan
19

Feb
20

2014
Apr
May
22
23

221 01-Oct-13

BH5040

CH.4200-CH.2800

2013

Jul
Aug
25
26
Utilities and Services Finish (WB)

BH5030

Telecommunication System

2012
Jun
-1

Mar
21

Testing and Commissioning


27-Dec-13, CH.5600-CH.4200
Temporary Works for Existin g Utili ties
Water works, Relocation of Water Mains (CH.5450)
13-Dec-13, Telecommunication System
Lay Duct
Relocation of OFC
ITS System
12-Feb-14, CH.4200-CH.2800
Temporary Works for Existin g Utili ties
28-Jan-14, Telecommunication System
Lay Duct
Relocation of OFC
ITS System
27-Mar-14, CH.2800-CH.1400
Temporary Works for Existin g Utili ties
14-Mar-14, Telecommunication System

BH7000

Lay Duct

36 30-Dec-13

13-Feb-14

06-Jan-14

20-Feb-14

BH7010

Relocation of OFC

36 15-Jan-14

28-Feb-14

24-Feb-14

05-Apr-14

31

Relocation of OFC

BH7020

ITS System

36 29-Jan-14

14-Mar-14

10-Mar-14

19-Apr-14

31

ITS System

65 14-Feb-14

02-May-14

21-Feb-14

05-Jul-14

53

65 14-Feb-14

02-May-14

18-Apr-14

05-Jul-14

53

50 14-Feb-14

14-Apr-14

21-Feb-14

19-Apr-14

CH.1400-CH.0
BH8030

Temporary Works for Existin g Utili ties

Telecommunication System

Jun
24

Lay Duct

02-May-14, CH.1400-CH.0
Temporary Works for Existing Utili ties
14-Apr-14, Telecommunicatio n System

BH8000

Lay Duct

36 14-Feb-14

28-Mar-14

21-Feb-14

03-Apr-14

BH8010

Relocation of OFC

36 22-Feb-14

04-Apr-14

28-Feb-14

10-Apr-14

Relocation of OFC

BH8020

ITS System

36 04-Mar-14

14-Apr-14

10-Mar-14

19-Apr-14

ITS System

31-May-14

05-Aug-13

05-Jul-14

29

271 01-Jul-13

Bridge Widening (WB)


BJ1020

Bridge Widening Start (WB)

BJ1030

Bridge Widening Finish (WB)

Bridge Extension Over Jalan Damansara (BR B.1)


Pier 2

0 29-Aug-13
0

05-Jul-14
31-May-14

31-May-14, Bridge Widening (WB)

252
05-Jul-14

29

223 29-Aug-13

31-May-14

14-Oct-13

05-Jul-14

29

54 03-Oct-13

07-Dec-13

14-Nov-13

22-Jan-14

35

BJ2760

Pile Cap Construction

22 03-Oct-13

29-Oct-13

14-Nov-13

09-Dec-13

33

BJ2770

Column Construction

32 30-Oct-13

07-Dec-13

13-Dec-13

22-Jan-14

35

48 05-Oct-13

03-Dec-13

16-Nov-13

22-Jan-14

39

Pier 1

Lay Duct

Bridge Widening Start (WB)


Bridge Widening Finish (WB)

31-May-14, Bridge Extension Over Jalan Damansara (BR


07-Dec-13, Pier 2
Pile Cap Construction
Column Construction
03-Dec-13, Pier 1

BJ2780

Pile Cap Construction

22 05-Oct-13

31-Oct-13

16-Nov-13

12-Dec-13

33

BJ2790

Column Construction

26 01-Nov-13

03-Dec-13

20-Dec-13

22-Jan-14

39

12 17-Dec-13

31-Dec-13

23-Jan-14

07-Feb-14

29

31-Dec-13, Precast Beams

12 17-Dec-13

31-Dec-13

23-Jan-14

07-Feb-14

29

Launching of Pre-tensioned Concrete Beams

40 02-Jan-14

21-Feb-14

08-Feb-14

27-Mar-14

29

40 02-Jan-14

21-Feb-14

08-Feb-14

27-Mar-14

29

40 29-Aug-13

17-Oct-13

14-Oct-13

22-Nov-13

29

Precast Beams
BJ2900

Launching of Pre-tensioned Concrete Beams

Bridge Deck
BJ2910

Bridge Deck Construction

Piling
BJ2500

Temporary Sheet Piling

BJ2505

Bored Piling

Miscellaneous

6 29-Aug-13

05-Sep-13

14-Oct-13

21-Oct-13

37

26 17-Sep-13

17-Oct-13

22-Oct-13

22-Nov-13

29

95 07-Feb-14

31-May-14

14-Mar-14

05-Jul-14

29

BJ2940

Bridge Parapet, Lining to Abutment and Service Ducts

26 07-Feb-14

10-Mar-14

14-Mar-14

12-Apr-14

29

BJ2950

Installation of Movement Joints in Bridge Deck and Approach Slab

12 19-May-14

31-May-14

23-Jun-14

05-Jul-14

29

48 26-Sep-13

23-Nov-13

31-Oct-13

22-Jan-14

47

Pier 5
BJ2700

Pile Cap Construction

22 26-Sep-13

22-Oct-13

31-Oct-13

27-Nov-13

29

BJ2710

Column Construction

26 23-Oct-13

23-Nov-13

20-Dec-13

22-Jan-14

47

62 28-Sep-13

13-Dec-13

02-Nov-13

22-Jan-14

31

Pier 4
BJ2720

Pile Cap Construction

22 28-Sep-13

24-Oct-13

02-Nov-13

29-Nov-13

29

BJ2730

Column Construction

40 25-Oct-13

13-Dec-13

03-Dec-13

22-Jan-14

31

62 01-Oct-13

16-Dec-13

07-Nov-13

22-Jan-14

29

Pier 3
BJ2740

Pile Cap Construction

22 01-Oct-13

26-Oct-13

07-Nov-13

02-Dec-13

29

BJ2750

Column Construction

40 28-Oct-13

16-Dec-13

03-Dec-13

22-Jan-14

29

52 08-Oct-13

10-Dec-13

19-Nov-13

22-Jan-14

33

West Abutment

Pile Cap Construction


Column Construction

21-Feb-14, Bridge Deck


Bridge Deck Construction
17-Oct-13, Piling
Temporary Sheet Piling
Bored Piling
31-May-14, Miscellaneous
Bridge Parapet, Lining to Abutment and Service Ducts

Installation of Movement Joints in Bridge Deck and Approa


23-Nov-13, Pier 5
Pile Cap Construction
Column Construction
13-Dec-13, Pier 4
Pile Cap Construction
Column Construction
16-Dec-13, Pier 3
Pile Cap Construction
Column Construction
10-Dec-13, West Abutment

BJ2640

Pile Cap Construction

18 08-Oct-13

29-Oct-13

19-Nov-13

09-Dec-13

33

Pile Cap Construction

BJ2650

Abutment Wall

16 30-Oct-13

19-Nov-13

10-Dec-13

30-Dec-13

33

Abutment Wall

BJ2660

Wing Wall & Curtail Wall

10 20-Nov-13

30-Nov-13

31-Dec-13

11-Jan-14

33

BJ2670

Approach Slab

8 02-Dec-13

10-Dec-13

13-Jan-14

22-Jan-14

33

52 24-Sep-13

26-Nov-13

29-Oct-13

22-Jan-14

45

East Abu tment


BJ2600

Pile Cap Construction

18 24-Sep-13

14-Oct-13

29-Oct-13

20-Nov-13

29

BJ2610

Abutment Wall

16 16-Oct-13

02-Nov-13

10-Dec-13

30-Dec-13

45

BJ2620

Wing Wall & Curtail Wall

10 06-Nov-13

16-Nov-13

31-Dec-13

11-Jan-14

45

BJ2630

Approach Slab

8 18-Nov-13

26-Nov-13

13-Jan-14

22-Jan-14

45

232 30-Jul-13

14-May-14

12-Sep-13

05-Jul-14

44

38 30-Jul-13

14-Sep-13

12-Sep-13

21-Oct-13

29

Bridge Extension Over Segambut Dalam (BR B.2)


Piling
BJ3500

Temporary Sheet Piling

BJ3505

Bored Piling

East Abu tment


BJ3600

Pile Cap Construction

Remaining Work

Summary

6 30-Jul-13

05-Aug-13

12-Sep-13

19-Sep-13

35

26 15-Aug-13

14-Sep-13

20-Sep-13

21-Oct-13

29

62 22-Aug-13

07-Nov-13

16-Oct-13

18-Jan-14

58

22 22-Aug-13

18-Sep-13

16-Oct-13

12-Nov-13

44

Wing Wall & Curtail Wall


Approach Slab
26-Nov-13, East Abutment
Pile Cap Construction
Abutment Wall
Wing Wall & Curtail Wall
Approach Slab
14-May-14, Bridge Extension Over Segambut Dalam (BR B.2)
14-Sep-13, Piling
Temporary Sheet Piling
Bored Piling
07-Nov-13, East Abutment
Pile Cap Construction

10 of 13

Critical Remaining Work


Milestone

WORK PROGRAMME

Date
30-Jul-12
11-Sep-12

Revision
Rev.0
Rev.1

Checked

Approved

NORTH-SOUTH EXPRESSWAY (PLUS)


PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Activity ID

Activity Name

Original Early Start


Duration

Early Finish

Late Start

Late Finish

Total
Float

2012
Jun
-1

2013
Jul
1

Aug
2

Sep
3

Oct
4

Nov
5

Dec
6

Jan
7

Feb
8

Mar
9

Apr
10

May
11

Jun
12

Jul
13

Aug
14

Sep
15

Oct
Nov
Dec
16
17
18
Abutment Wall

BJ3610

Abutment Wall

18 19-Sep-13

09-Oct-13

29-Nov-13

20-Dec-13

58

BJ3620

Wing Wall & Curtail Wall

12 10-Oct-13

24-Oct-13

21-Dec-13

06-Jan-14

58

BJ3630

Approach Slab

10 25-Oct-13

07-Nov-13

07-Jan-14

18-Jan-14

58

Approach Slab

56 27-Aug-13

02-Nov-13

21-Oct-13

18-Jan-14

60

02-Nov-13, Pier 4

Pier 4
BJ3700

Pile Cap Construction

22 27-Aug-13

23-Sep-13

21-Oct-13

16-Nov-13

44

BJ3710

Column Construction

34 24-Sep-13

02-Nov-13

06-Dec-13

18-Jan-14

60

62 29-Aug-13

14-Nov-13

23-Oct-13

18-Jan-14

52

Pier 3
BJ3720

Pile Cap Construction

22 29-Aug-13

25-Sep-13

23-Oct-13

19-Nov-13

44

BJ3730

Column Construction

40 26-Sep-13

14-Nov-13

29-Nov-13

18-Jan-14

52

40 09-Dec-13

28-Jan-14

05-Feb-14

24-Mar-14

44

40 09-Dec-13

28-Jan-14

05-Feb-14

24-Mar-14

44

62 02-Sep-13

16-Nov-13

25-Oct-13

18-Jan-14

50

Bridge Deck
BJ3920

Bridge Deck Construction

Pier 2
BJ3740

Pile Cap Construction

22 02-Sep-13

27-Sep-13

25-Oct-13

21-Nov-13

44

BJ3750

Column Construction

40 28-Sep-13

16-Nov-13

29-Nov-13

18-Jan-14

50

62 09-Sep-13

23-Nov-13

01-Nov-13

18-Jan-14

44

West Abutment

28-Jan-14, Bridge Deck


Bridge Deck Construction
16-Nov-13, Pier 2
Pile Cap Construction
Column Construction
23-Nov-13, West Abutment

44

Pile Cap Construction

BJ3650

Abutment Wall

18 05-Oct-13

26-Oct-13

29-Nov-13

20-Dec-13

44

Abutment Wall

BJ3660

Wing Wall & Curtail Wall

12 28-Oct-13

12-Nov-13

21-Dec-13

06-Jan-14

44

BJ3670

Approach Slab

10 13-Nov-13

23-Nov-13

07-Jan-14

18-Jan-14

44

48 04-Sep-13

31-Oct-13

28-Oct-13

18-Jan-14

62

30-Sep-13

28-Oct-13

23-Nov-13

44

26 01-Oct-13

31-Oct-13

17-Dec-13

18-Jan-14

62

98 15-Jan-14

14-May-14

11-Mar-14

05-Jul-14

44

Miscellaneous

Wing Wall & Curtail Wall


Approach Slab
31-Oct-13, Pier 1
Pile Cap Construction
Column Construction
14-May-14, Miscellaneous

BJ3930

Bridge Parapet, Lining to Abutment and Service Ducts

26 15-Jan-14

17-Feb-14

11-Mar-14

09-Apr-14

44

BJ3940

Installation of Movement Joints in Bridge Deck and Approach Slab

12 29-Apr-14

14-May-14

23-Jun-14

05-Jul-14

44

12 25-Nov-13

07-Dec-13

20-Jan-14

04-Feb-14

44

07-Dec-13, Precast Beams

12 25-Nov-13

Launching of Post-tensioned Concrete Beams

Precast Beams
BJ3910

Launching of Post-tensioned Concrete Beams

Extension of Viaduct at Edinburgh Estate (BR B.3)


Piling
BJ4500

Temporary Sheet Piling

BJ4505

Bored Piling

East Abu tment

07-Dec-13

20-Jan-14

04-Feb-14

44

260 01-Jul-13

19-May-14

05-Aug-13

05-Jul-14

40

36 01-Jul-13

14-Aug-13

05-Aug-13

19-Sep-13

29

Bridge Parapet, Lining to Abutment and Service Ducts

Installation of Movement Joints in Bridge Deck and Approach Sl

19-May-14, Extension of Viaduct at Edinburgh Estate (BR B.3


14-Aug-13, Piling

6 01-Jul-13

06-Jul-13

05-Aug-13

13-Aug-13

29

Temporary Sheet Piling

30 08-Jul-13

14-Aug-13

14-Aug-13

19-Sep-13

29

Bored Piling

62 15-Jul-13

30-Sep-13

04-Sep-13

20-Dec-13

66

30-Sep-13, East Abutment

BJ4600

Pile Cap Construction

22 15-Jul-13

12-Aug-13

04-Sep-13

30-Sep-13

40

Pile Cap Construction

BJ4610

Abutment Wall

18 13-Aug-13

03-Sep-13

01-Nov-13

23-Nov-13

66

Abutment Wall

BJ4620

Wing Wall & Curtail Wall

12 04-Sep-13

18-Sep-13

25-Nov-13

07-Dec-13

66

BJ4630

Approach Slab

10 19-Sep-13

30-Sep-13

09-Dec-13

20-Dec-13

66

Approach Slab

48 19-Jul-13

18-Sep-13

09-Sep-13

20-Dec-13

76

18-Sep-13, Pier 10

Pier 10
BJ4700

Pile Cap Construction

22 19-Jul-13

16-Aug-13

09-Sep-13

04-Oct-13

40

BJ4710

Column Construction

26 17-Aug-13

18-Sep-13

20-Nov-13

20-Dec-13

76

58 22-Jul-13

02-Oct-13

11-Sep-13

20-Dec-13

64

Pier 9
BJ4720

Pile Cap Construction

22 22-Jul-13

19-Aug-13

11-Sep-13

07-Oct-13

40

BJ4730

Column Construction

36 20-Aug-13

02-Oct-13

08-Nov-13

20-Dec-13

64

72 24-Jul-13

22-Oct-13

13-Sep-13

20-Dec-13

48

Pier 8
BJ4740

Pile Cap Construction

22 24-Jul-13

21-Aug-13

13-Sep-13

09-Oct-13

40

BJ4750

Column Construction

50 22-Aug-13

22-Oct-13

21-Oct-13

20-Dec-13

48

72 27-Jul-13

24-Oct-13

17-Sep-13

20-Dec-13

46

Pier 7

Wing Wall & Curtail Wall

Pile Cap Construction


Column Construction
02-Oct-13, Pier 9
Pile Cap Construction
Column Construction
22-Oct-13, Pier 8
Pile Cap Construction
Column Construction
24-Oct-13, Pier 7

BJ4760

Pile Cap Construction

22 27-Jul-13

23-Aug-13

17-Sep-13

11-Oct-13

40

BJ4770

Column Construction

50 24-Aug-13

24-Oct-13

21-Oct-13

20-Dec-13

46

Column Construction

68 30-Jul-13

22-Oct-13

19-Sep-13

20-Dec-13

48

22-Oct-13, Pier 6

Pier 6
BJ4780

Pile Cap Construction

22 30-Jul-13

26-Aug-13

19-Sep-13

14-Oct-13

40

BJ4790

Column Construction

46 27-Aug-13

22-Oct-13

25-Oct-13

20-Dec-13

48

68 01-Aug-13

24-Oct-13

21-Sep-13

20-Dec-13

46

Pier 5
BJ4800

Pile Cap Construction

22 01-Aug-13

28-Aug-13

21-Sep-13

17-Oct-13

40

BJ4810

Column Construction

46 29-Aug-13

24-Oct-13

25-Oct-13

20-Dec-13

46

68 03-Aug-13

26-Oct-13

24-Sep-13

20-Dec-13

44

Pier 4
BJ4820

Pile Cap Construction

22 03-Aug-13

30-Aug-13

24-Sep-13

19-Oct-13

40

BJ4830

Column Construction

46 02-Sep-13

26-Oct-13

25-Oct-13

20-Dec-13

44

58 06-Aug-13

17-Oct-13

26-Sep-13

20-Dec-13

52

Pier 3
BJ4840

Pile Cap Construction

22 06-Aug-13

03-Sep-13

26-Sep-13

22-Oct-13

40

BJ4850

Column Construction

36 04-Sep-13

17-Oct-13

08-Nov-13

20-Dec-13

52

48 10-Aug-13

07-Oct-13

28-Sep-13

20-Dec-13

60

Pier 2
BJ4860

Pile Cap Construction

22 10-Aug-13

05-Sep-13

28-Sep-13

24-Oct-13

40

BJ4870

Column Construction

26 06-Sep-13

07-Oct-13

20-Nov-13

20-Dec-13

60

40 13-Aug-13

30-Sep-13

01-Oct-13

20-Dec-13

66

Pier 1
BJ4880

Pile Cap Construction

22 13-Aug-13

07-Sep-13

01-Oct-13

26-Oct-13

40

BJ4890

Column Construction

18 09-Sep-13

30-Sep-13

29-Nov-13

20-Dec-13

66

62 17-Aug-13

31-Oct-13

05-Oct-13

20-Dec-13

40

West Abutment

Pile Cap Construction

Pile Cap Construction


Column Construction
24-Oct-13, Pier 5
Pile Cap Construction
Column Construction
26-Oct-13, Pier 4
Pile Cap Construction
Column Construction
17-Oct-13, Pier 3
Pile Cap Construction
Column Construction
07-Oct-13, Pier 2
Pile Cap Construction
Column Construction
30-Sep-13, Pier 1
Pile Cap Construction
Column Construction
31-Oct-13, West Abutment

BJ4640

Pile Cap Construction

22 17-Aug-13

12-Sep-13

05-Oct-13

31-Oct-13

40

Pile Cap Construction

BJ4650

Abutment Wall

18 13-Sep-13

04-Oct-13

01-Nov-13

23-Nov-13

40

Abutment Wall

BJ4660

Wing Wall & Curtail Wall

12 05-Oct-13

19-Oct-13

25-Nov-13

07-Dec-13

40

BJ4670

Approach Slab

10 21-Oct-13

31-Oct-13

09-Dec-13

20-Dec-13

40

16 01-Nov-13

21-Nov-13

21-Dec-13

10-Jan-14

40

21-Nov-13, Precast Beams

16 01-Nov-13

21-Nov-13

21-Dec-13

10-Jan-14

40

Launching of Post-tensioned Concrete Beams

Precast Beams
BJ4900

Launching of Post-tensioned Concrete Beams

Remaining Work

Summary

Wing Wall & Curtail Wall


Approach Slab

11 of 13

Critical Remaining Work


Milestone

Aug
26

Column Construction

28-Nov-13

22 04-Sep-13

Jul
25

14-Nov-13, Pier 3

01-Nov-13

Column Construction

Jun
24

Pile Cap Construction

04-Oct-13

Pile Cap Construction

2014
Apr
May
22
23

Column Construction

22 09-Sep-13

BJ3770

Mar
21

Pile Cap Construction

Pile Cap Construction

BJ3760

Feb
20

Wing Wall & Curtail Wall

BJ3640

Pier 1

Jan
19

WORK PROGRAMME

Date
30-Jul-12
11-Sep-12

Revision
Rev.0
Rev.1

Checked

Approved

NORTH-SOUTH EXPRESSWAY (PLUS)


PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Activity ID

Activity Name

Bridge Deck
BJ4910

46 22-Nov-13

18-Jan-14

11-Jan-14

10-Mar-14

40

2014
Feb
Mar
Apr
May
20
21
22
23
18-Jan-14, Bridge Deck

46 22-Nov-13

18-Jan-14

11-Jan-14

10-Mar-14

40

Bridge Deck Construction

110 04-Jan-14

19-May-14

25-Feb-14

05-Jul-14

40

32 04-Jan-14

13-Feb-14

25-Feb-14

02-Apr-14

40

18 26-Apr-14

19-May-14

16-Jun-14

05-Jul-14

40

268 03-Jun-13

28-Apr-14

10-Aug-13

05-Jul-14

56

Original Early Start


Duration

Bridge Deck Construction

Miscellaneous
BJ4920

Bridge Parapet, Lining to Abutment and Service Ducts

BJ4930

Installation of Movement Joints in Bridge Deck and Approach Slab

Slope Improvement Works (WB)


BL0030

Slope Improvement Works Start (WB)

0 03-Jun-13

BL0040

Slope Improvement Works Finish (WB)

Early Finish

Late Start

Late Finish

05-Jul-14
28-Apr-14

Total
Float

56

Cut Area

268 03-Jun-13

28-Apr-14

10-Aug-13

05-Jul-14

56

76 14-Dec-13

19-Mar-14

05-Apr-14

05-Jul-14

90

BL3500

Excavation

58 14-Dec-13

26-Feb-14

05-Apr-14

14-Jun-14

90

BL3510

Construction of Wall Base

58 21-Dec-13

05-Mar-14

12-Apr-14

21-Jun-14

90

BL3520

Construction of Retaining Wall

58 30-Dec-13

12-Mar-14

19-Apr-14

28-Jun-14

90

BL3530

Backfill

58 07-Jan-14

19-Mar-14

26-Apr-14

05-Jul-14

90

268 03-Jun-13

28-Apr-14

10-Aug-13

05-Jul-14

56

BL3000

Installation of Horizontal Drain (CH.5600-CH.4200)

67 03-Jun-13

22-Aug-13

10-Aug-13

30-Oct-13

56

BL3010

Installation of Horizontal Drain (CH.4200-CH.2800)

67 23-Aug-13

14-Nov-13

31-Oct-13

23-Jan-14

56

BL3020

Installation of Horizontal Drain (CH.2800-CH.1400)

67 15-Nov-13

07-Feb-14

24-Jan-14

15-Apr-14

56

BL3030

Installation of Horizontal Drain (CH.1400-CH.0)

67 08-Feb-14

28-Apr-14

16-Apr-14

05-Jul-14

56

54 24-Jun-13

28-Aug-13

02-May-14

05-Jul-14

252

54 24-Jun-13

28-Aug-13

02-May-14

05-Jul-14

252

BL4000

Excavation

30 24-Jun-13

29-Jul-13

02-May-14

07-Jun-14

252

BL4020

Construction of Wall Base

30 08-Jul-13

14-Aug-13

17-May-14

21-Jun-14

252

BL4030

Construction of Retaining Wall

30 15-Jul-13

21-Aug-13

24-May-14

28-Jun-14

252

BL4040

Backfill

30 22-Jul-13

28-Aug-13

31-May-14

05-Jul-14

252

208 15-May-13

28-Jan-14

21-May-13

05-Jul-14

130

BM0030

Ground Treatment Works Start (WB)

BM0040

Ground Treatment Works Finish (WB)

Stage 1
Ground Treatment (CH.5600-CH.4200)

0 15-May-13
0

05-Jul-14
28-Jan-14

Nov
5

Dec
6

Jan
7

Feb
8

Mar
9

Apr
10

May
11

Jun
12

Jul
13

Aug
14

Sep
15

Oct
16

Dec
18

Jan
19

Installation of Movement Joints in Bridge Deck and Approach S


Slope Improvement Works Start (WB)

28-Apr-14, Cut Area


19-Mar-14, Slope Improvement - Retaining Wall (CH.2300-CH.2080)
Excavation
Construction of Wall Base
Construction of Retaining Wall
Backfill
28-Apr-14, Slope Improvement - Horizontal Drain
Installation of Horizontal Drain (CH.5600-CH.4200)
Installation of Horizontal Drain (CH.4200-CH.2800)
Installation of Horizontal Drain (CH.2800-CH.1400)
Installation of Horizontal Drain (CH.1400-CH.0)
28-Aug-13, Fill Area
28-Aug-13, Slope Improvement - Retaining Wall (CH.5380-CH.5280)
Excavation
Construction of Wall Base
Construction of Retaining Wall
Backfill
28-Jan-14, Ground Treatment Works (WB)

338
05-Jul-14

130

208 15-May-13

28-Jan-14

21-May-13

05-Jul-14

130

52 15-May-13

16-Jul-13

21-May-13

22-Jul-13

Ground Treatment Works Start (WB)


Ground Treatment Works Finish (WB)
28-Jan-14, Stage 1
16-Jul-13, Ground Treatment (CH.5600-CH.4200)

46 15-May-13

09-Jul-13

21-May-13

15-Jul-13

Excavation of Unsuitable Material

Laying of Geotextile Separator

46 17-May-13

11-Jul-13

23-May-13

17-Jul-13

Laying of Geotextile Separator

BM2020

Laying of Outlet Drain

46 20-May-13

13-Jul-13

27-May-13

19-Jul-13

Laying of Outlet Drain

BM2030

Backfilling with Compacted Soil / hardcore Material

46 22-May-13

16-Jul-13

29-May-13

22-Jul-13

52 17-Jul-13

20-Sep-13

27-Dec-13

03-Mar-14

130

Backfilling with Compacted Soil / hardcore Material


20-Sep-13, Ground Treatment (CH.4200-CH.2800)

BM2100

Excavation of Unsuitable Material

46 17-Jul-13

12-Sep-13

27-Dec-13

24-Feb-14

130

Excavation of Unsuitable Material

BM2110

Laying of Geotextile Separator

46 19-Jul-13

14-Sep-13

30-Dec-13

26-Feb-14

130

Laying of Geotextile Separator

BM2120

Laying of Outlet Drain

46 22-Jul-13

18-Sep-13

02-Jan-14

28-Feb-14

130

Laying of Outlet Drain

BM2130

Backfilling with Compacted Soil / hardcore Material

46 24-Jul-13

20-Sep-13

04-Jan-14

03-Mar-14

130

Backfilling with Compacted Soil / hardcore Material

52 21-Sep-13

23-Nov-13

04-Mar-14

03-May-14

130

23-Nov-13, Ground Treatment (CH.2800-CH.1400)

BM2200

Excavation of Unsuitable Material

46 21-Sep-13

16-Nov-13

04-Mar-14

25-Apr-14

130

Excavation of Unsuitable Material

BM2210

Laying of Geotextile Separator

46 24-Sep-13

19-Nov-13

06-Mar-14

28-Apr-14

130

Laying of Geotextile Separator

BM2220

Laying of Outlet Drain

46 26-Sep-13

21-Nov-13

08-Mar-14

30-Apr-14

130

Laying of Outlet Drain

BM2230

Backfilling with Compacted Soil / hardcore Material

46 28-Sep-13

23-Nov-13

11-Mar-14

03-May-14

130

Backfilling with Compacted Soil / hardcore Material

52 25-Nov-13

28-Jan-14

05-May-14

05-Jul-14

130

28-Jan-14, Ground Treatment (CH.1400-CH.0)

BM2300

Excavation of Unsuitable Material

46 25-Nov-13

21-Jan-14

05-May-14

28-Jun-14

130

Excavation of Unsuitable Material

BM2310

Laying of Geotextile Separator

46 27-Nov-13

23-Jan-14

07-May-14

01-Jul-14

130

Laying of Geotextile Separator

BM2320

Laying of Outlet Drain

46 29-Nov-13

25-Jan-14

09-May-14

03-Jul-14

130

Laying of Outlet Drain

BM2330

Backfilling with Compacted Soil / hardcore Material

46 02-Dec-13

28-Jan-14

12-May-14

05-Jul-14

130

219 03-Oct-13

30-Jun-14

09-Oct-13

05-Jul-14

Electrical Works for Street Lighting (WB)


BN0030

Electrical Works for Street Lighting Start (WB)

BN0040

Electrical Works for Street Lighting Finish (WB)

Overall Stage 1
BN0200

Testing and Commissioning

CH.5600-CH.4200

0 03-Oct-13
0

05-Jul-14
30-Jun-14

Backfilling with Compacted Soil / hardcore Material

30-Jun-14, Electrical Works for Street Lighting (W

224

Electrical Works for Street Lighting Start (WB)

05-Jul-14

Electrical Works for Street Lighting Finish (WB)

219 03-Oct-13

30-Jun-14

09-Oct-13

05-Jul-14

30-Jun-14, Overall Stage 1

60 18-Apr-14

30-Jun-14

24-Apr-14

05-Jul-14

48 03-Oct-13

30-Nov-13

09-Oct-13

06-Dec-13

30-Nov-13, CH.5600-CH.4200

Testing and Commissioning

BN2000

High Mast

48 03-Oct-13

30-Nov-13

09-Oct-13

06-Dec-13

High Mast

BN2010

Street Lighting

48 03-Oct-13

30-Nov-13

09-Oct-13

06-Dec-13

Street Lighting

48 02-Dec-13

30-Jan-14

07-Dec-13

07-Feb-14

30-Jan-14, CH.4200-CH.2800

CH.4200-CH.2800
BN2100

High Mast

48 02-Dec-13

30-Jan-14

07-Dec-13

07-Feb-14

High Mast

BN2110

Street Lighting

48 02-Dec-13

30-Jan-14

07-Dec-13

07-Feb-14

Street Lighting

48 03-Feb-14

31-Mar-14

08-Feb-14

05-Apr-14

31-Mar-14, CH.2800-CH.1400

CH.2800-CH.1400

Aug
26

28-Apr-14, Slope Improvement Works (WB)

Excavation of Unsuitable Material

Ground Treatment (CH.1400-CH.0)

Jul
25

19-May-14, Miscellaneous

BM2010

Ground Treatment (CH.2800-CH.1400)

Jun
24

Bridge Parapet, Lining to Abutment and Service Ducts

BM2000

Ground Treatment (CH.4200-CH.2800)

Nov
17

28-Apr-14, Overall Stage 1

05-Jul-14

Ground Treatment Works (WB)

Oct
4

Slope Improvement Works Finish (WB)

10-Aug-13

Slope Improvement - Retaining Wall (CH.5380-CH.5280)

Sep
3

56

28-Apr-14

Fill Area

Aug
2

324

268 03-Jun-13

Slope Improvement - Horizontal Drain

2013
Jul
1

05-Jul-14

Overall Stage 1
Slope Improvement - Retaining Wall (CH.2300-CH.2080)

2012
Jun
-1

BN2200

High Mast

48 03-Feb-14

31-Mar-14

08-Feb-14

05-Apr-14

High Mast

BN2210

Street Lighting

48 03-Feb-14

31-Mar-14

08-Feb-14

05-Apr-14

Street Lighting

48 01-Apr-14

28-May-14

07-Apr-14

04-Jun-14

28-May-14, CH.1400-CH.0

CH.1400-CH.0
BN2300

High Mast

48 01-Apr-14

28-May-14

07-Apr-14

04-Jun-14

High Mast

BN2310

Street Lighting

48 01-Apr-14

28-May-14

07-Apr-14

04-Jun-14

Street Lighting

02-Jul-14

06-Sep-12

05-Jul-14

544 03-Sep-12

Prime Cost and Provisional Sums


BP1000

Provisional Sums Start

BP1010

Provisional Sums Finish

0 01-Oct-12
0

Prime Cost

05-Jul-14
02-Jul-14

05-Jul-14

Provisional Sums Finish

02-Jul-14

06-Sep-12

05-Jul-14

02-Jul-14, Prime Cost

Traffic Management

544 03-Sep-12

02-Jul-14

06-Sep-12

05-Jul-14

BP3300

Landscaping Works

70 01-Apr-14

24-Jun-14

12-Apr-14

05-Jul-14

10

Summary

Provisional Sums Start

544 03-Sep-12

BP3100

Remaining Work

02-Jul-14, Prime Cost and Provisional Sums

524

Traffic Management
Landscaping Works

12 of 13

Critical Remaining Work


Milestone

WORK PROGRAMME

Date
30-Jul-12
11-Sep-12

Revision
Rev.0
Rev.1

Checked

Approved

NORTH-SOUTH EXPRESSWAY (PLUS)


PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Activity ID

Activity Name

Original Early Start


Duration

Early Finish

Late Start

Late Finish

Total
Float

2012
Jun
-1

2013
Jul
1

Aug
2

Sep
3

Oct
4

Nov
5

Dec
6

Jan
7

Feb
8

Mar
9

Apr
10

May
11

Jun
12

Jul
13

Aug
14

Sep
15

Oct
16

Nov
17

Dec
18

Jan
19

Feb
20

Mar
21

2014
Apr
May
22
23

Jun
24

Jul
Aug
25
26
24-Jun-14, Provisional Sums

514 01-Oct-12

24-Jun-14

17-Oct-12

05-Jul-14

10

BP1100

Protection to All Services and Utilities

510 01-Oct-12

19-Jun-14

17-Oct-12

05-Jul-14

14

Protection to All Services and Utilities

BP1250

Environmental Management

510 01-Oct-12

19-Jun-14

17-Oct-12

05-Jul-14

14

Environmental Management

BP1300

Authority Fee

510 01-Oct-12

19-Jun-14

17-Oct-12

05-Jul-14

14

Authority Fee

BP1450

Rock Fences

70 01-Apr-14

24-Jun-14

12-Apr-14

05-Jul-14

10

Rock Fences

BP1550

Slope Protection

510 01-Oct-12

19-Jun-14

17-Oct-12

05-Jul-14

14

Slope Protection

BP1600

Piled Embankment

510 01-Oct-12

19-Jun-14

17-Oct-12

05-Jul-14

14

Piled Embankment

BP1700

Telecommunication Services

510 01-Oct-12

19-Jun-14

17-Oct-12

05-Jul-14

14

Telecommunication Services

BP1800

ITS System

510 01-Oct-12

19-Jun-14

17-Oct-12

05-Jul-14

14

ITS System

BP1900

Utilities Relocation Works Under the Bridges

510 01-Oct-12

19-Jun-14

17-Oct-12

05-Jul-14

14

Utilities Relocation Works Under the Bridges

BP2050

Relocation Works

510 01-Oct-12

19-Jun-14

17-Oct-12

05-Jul-14

14

Relocation Works

BP2100

Dayworks

510 01-Oct-12

19-Jun-14

17-Oct-12

05-Jul-14

14

Dayworks

273 02-Aug-13

05-Jul-14

05-May-14

05-Jul-14

52 02-Aug-13

05-Oct-13

05-May-14

05-Jul-14

221

05-Oct-13, Section 1 - East Bound

Provisional Sums

Project Completion
Section 1 - East Bound

05-Jul-14, Project Completion

BQ1000

Clearing Up of Site

52 02-Aug-13

05-Oct-13

05-May-14

05-Jul-14

221

Clearing Up of Site

BQ1010

Final Demobilisation

26 05-Sep-13

05-Oct-13

06-Jun-14

05-Jul-14

221

Final Demobilisation

BQ1020

Completion of Work

05-Jul-14

221

Completion of Work

Section 2 - West Bound

05-Oct-13

52 05-May-14

05-Jul-14

05-May-14

05-Jul-14

05-Jul-14, Section 2 - West Bound

BQ2000

Clearing Up of Site

52 05-May-14

05-Jul-14

05-May-14

05-Jul-14

Clearing Up of Site

BQ2010

Final Demobilisation

26 06-Jun-14

05-Jul-14

06-Jun-14

05-Jul-14

Final Demobilisation

BQ2020

Completion of Work

05-Jul-14

Completion of Work

Remaining Work

Summary

05-Jul-14

13 of 13

Critical Remaining Work


Milestone

WORK PROGRAMME

Date
30-Jul-12
11-Sep-12

Revision
Rev.0
Rev.1

Checked