Method Statement For Installation of Pre-Finished Engineering Flooring and Skirting
Method Statement For Installation of Pre-Finished Engineering Flooring and Skirting
Weather tightness
Before commencement of the flooring works, the building fabric should have
been completed including window and glazing, external wall finishing
including cleaning, T & C of air-conditioning units, etc. It is also important
that the water test for all openable and fixed windows (after glazing
installation) should be completed and passed, rectification of failure have also
been finished as well.
Dryness of slab
The concrete structure, masonry works and in particular concrete slab and
cement sand screeding should be thoroughly dry before flooring material is
delivered to individual flats.
Completion of preceding trades
In order to attain the best result of wood flooring, it is important to schedule the
work such that the laying of wood floorings is the last finishing work.
Therefore the following trades (but not limited to) should have been completed
prior to the commencement of wood flooring works:
a)
Wet trades within the flat including tiling, plastering, stone threshold, etc.
b)
c)
d)
e)
f.)
g.)
Setting out line for final finished floor level to be provided by Main
Contractor.
Testing Slab
What to be tested
It is required to test the dryness of slab of individual flat. It is also required to
test the cement sand screeding to ensure the screed is reasonable sound, hard,
free from loose screeding/excessive sand and is bonded well to the concrete
slab below. Tolerance for screeding will be +/-3mm within 2m.
Vapour Barrier
Proposed system should ensure moisture does not reach the finished floor, with
proper vapour barrier system, consisting of:
1st Vapour Barrier
Lay one layer of 0.12mm thick polyethylene sheet covering the entire area
including turn-up at wall line behind skirting, lapping edges nominal 75mm.
2nd Vapour Barrier
Minimum 15 1b asphalt/bitumen felt to be laid between the engineering
finishes floor and plywood sub-floor and allow nominal 75mm lapping edges,
butt ends.
5.
Plywood Sub-floor
Plywood
Use nominal 15mm thick plywood. Plywood in size of 2ft x 8ft or 4 x 4ft
panels for easy vertical transportation, easy handling and allow more movement
joints between panels. The plywood panels shall be nailed by 38mm long
nominal size concrete nails at 450mm centres.
Application
Before nailing sub-flooring, roll out the 1st vapour barrier over the finishing
floor slab.
Loose lay plywood panels on polyethylene film over entire floor and at right
angles to the finished flooring besides the finished flooring is at diagonal
direction. Keep nominal 15mm space at all wall lines and between panels.
6.
End up nailing at the far wall with the same nominal 8 to 10mm space allowed
on the beginning wall.
Avoid end of finish floor meet over a subfloor joint.
7.
Protection
Right after the fixing of flooring, protect the floor by laying corrugated plastic
protection board or equivalent onto the flooring and plastic sheet to skirting to
prevent from damage.
Remove the protection only when instruction is given by the MTC, the Architect
and Client to do so.
8.
Skirting Fixing
Sequence
Skirting will be prefinished in factory and fixed right after the commencement
of Wood Flooring works.
Fixing
The top edge level of the skirting shall be the theoretical design level plus 3mm
positive tolerance. The joints of skirting shall be butt, fit and tight with mitre
joint at wall corner. The skirting shall be fixed onto the wall by 25mm long
concrete nails maximum 500mm centres, approx. 25mm away from the edges.
Nails should stagger from top and bottom rows such that each fixings centre
shall be no more than 300mm apart.
Nail heads shall be touched up by Furniture Repair Pencil of which colour
should matches with the finish of the skirting.
9.
- END -