Security Notes 2sec066
Security Notes 2sec066
Introduction
A power system is said to be secured if credible loss of generating plant or
transmission circuit does not cause:
1. A sustained rise or fall in frequency above or below predetermined limit.
2. A sustained rise or fall in voltage that cant be brought within the acceptable
limit by voltage correction devices.
3. A sustained overloading of the circuit which cant be relieved by using spare
capacity or any pre-arranged reduction of demand.
4. The supply interruption to the consumer.
Credible loss is related to probability of an incident occurring such as loss of
generating unit or transmission line .From experience these probabilities can be
assessed and accordingly security arrangement can be made.
Security measures keep the system operating when components fail. For example
loss of generation equipment is taken care by maintaining a proper amount of
spinning or spare reserves so that remaining units can make up deficit without
violating the frequency limit or shedding any load. Similarly loss of transmission
network is taken care by maintain proper transmission flows and casing remaining
network to share the load. Since the time of component failure is unpredictable the
system must be operated at all time such that the system will not be left at the
dangerous position if any credible loss occurs. Generally power system equipment
operates without limits. Most pieces of equipment is protected by automatic devices
when their limit is violated. If any event occur in the system that leaves it operating
with limits violated, a series of further actions switch other equipments out of
service. Consequently a large part or entire of system may collapse which is known
as system black out.
iii.
The drop in the frequency due to the loss of the largest unit is halted
before the frequency limit is violated.
The redistribution of the power flows in the system resulting from the
replacement of a particular generating unit by running spare capacity will
not cause the overloading of any circuit.
The underestimation of the demand which comes too late to run
additional plant can be recovered.
Beyond spinning reserve the unit commitment problem may involve various
classes of scheduled reserves or off line reserves such as quick start , diesel or
gas turbine, hydro and pumped hydro that cam be brought up to full capacity
quickly.
b. Incipient fault
c. Starting losses
d. Minimum up time
f. Crew Constraints
g. Coordination constraints
h. Fuel constraints:
The system diversity may go sometimes unexpectedly to lower side than the usual
value .This might effect the system security since the operator should shed power
of some area .The daily loadcurve of each plant gives the operator an idea of how
the load varies across different time in a day and he could plan accordingly.He,
thereby , takes decision on units to be loaded next and spinning reserves for the
different periods in a day.
3) Import /Export:
Since , import /Export is done through the tie-line , its effect is same as that of
interconnection .
UNIT COMMITMENT
Maintainan
ce
Unit
Economic
Economic
Scheduling
commitm
ent
Load
Load
Dispatch
Dispatch
Unit commitment is the process of finding what unit or combination of unit should
be used to supply the given load most economically .A great amount of money can
be saved by turning units off , i.e . de-commiting them , when they are not needed .
Unit commitment fits between maintenance scheduling and generation scheduling
in the management of generation resources. Since it is to be decided what units or
combination of units are to be used to supply a given load before the economic
Load Dispatch , the Unit Commitment problem is also called Pre-dispatch problem.
See class notes for remaining portion of unit commitment.