European Spallation Source: ESS Partner and Industry Day Delft, 12 March2014
European Spallation Source: ESS Partner and Industry Day Delft, 12 March2014
Jim Yeck
CEO & Director General
Dimensions of ESS
A Next Generation Materials Research Infrastructure
SCIENCE
PROJECT/FACILITY
A partnership of 17
European nations
committed to the goal of
collectively building and
operating the worlds
leading facility for research
using neutrons by the
second quarter of the 21st
century.
Life science
Soft condensed matter
Chemistry of materials
Energy research
Magnetism and superconductivity
Engineering materials and
geosciences
Archaeology and
heritage conservation
Fundamental and particle physics
SOCIETY
Research directly related to societal values
Opportunity to benefit from the innovation
capacity of industry.
Driver for job creation
LIGHTNING
NEW
MATERIALS
FUNCTIONAL
FOOD
SOLAR
ENERGY
MEDICINE
PACEMAKERS
TAILOR
MADE
MATERIAL
COSMETICS
MOBILE
PHONES
BIO FUEL
TRANSPORTS
IMPLANTS
GEO SCIENCE
Why neutrons?
Charge neutral
S=1/2 spin
Nuclear scattering
Deeply penetrating
Directly probe
magnetism
Sensitive to light
elements and isotopes
Better drugs
2020+
2000s
1990
1980
1970
2013-10-11
1960
Reactors
J-PARC (1MW)
SNS
MTR
1015
NRU
HFIR
NRX
HFBR
X-10
1010
ISIS
ILL
LANSCE
ZINP-P/
J-PARC
IPNS
WNR
KENS
FRM-II
SINQ
PIK
OPAL
ZINP-P
CP-2
Spallation
CP-1
Berkeley 37-inch cyclotron
105
Pulsed Sources
1
1930
Chadwick
1940
1950
1960
1970
1980
1990
2000
2010
2020
Sweden,
Denmark and Norway:
50% of construction
15-20% of operations
European partners:
50% of construction
2014
Construction work
starts on the site
2023
ESS starts
user program
2009
Decision: ESS will
be built in Lund
2019
2012
ESS Design Update
phase complete
2003
First European design
effort of ESS completed
First neutrons on
instruments
ESS organization
Administration & Finance
Committee
M. Scharff, Chair
Science
Advisory Committee
A. Matic, Chair
Technical
Advisory Committee
R. Garoby, Chair
Conventional Facilities
Advisory Committee
TBD, Chair
J. Yeck
DIRECTOR GENERAL AND CHIEF EXECUTIVE OFFICER (CEO)
SENIOR EXECUTIVE ASSISTANT
ADMIN ASSISTANT
ASSOCIATE DIRECTOR FOR OPERATIONS, ES&H and QA
QUALITY ASSURANCE MANAGER
QUALITY ASSURANCE CONSULTANT
SENIOR ADVISOR
INFRASTRUCTURE DIRECTORATE
. Larsson (I)
DIRECTOR
PERSONAL ASSISTANT
CONVENTIONAL
FACILITIES DIVISION
K. Hedin
HEAD OF DIVISION
L. Lavesson (C)
A. Thonng
U. Hammarlund (C)
TEAM ASSISTANT
DESIGN GROUP
DEPUTY DIRECTOR
PERSONAL ASSISTANT
P. Jacobsson
HEAD OF DIVISION
ACCELERATOR
DIVISION
U. Agnvik (C)
T. Hansson
F. Jrud
G. Myhr (C)
D. Sklde (C)
M. Lindroos
HEAD OF DIVISION
H. Danared
DEPUTY HEAD OF
DIVISION
ENERGY DIVISION
J. Weisend II
DEPUTY HEAD OF
ACCELERATOR
PROJECTS
J. Molander (C)
GROUP LEADER
D. McGinnis
CHIEF ENGINEER
F. Bergstedt (C)
B. Hedn
J. Lundgren
R. Sjholm
K. Svedin
E. Lindstrm
F. Indebetou (C)
M. Eneroth
J. Lehander
E. Lagrelius (L), M. Lindberg (A)
ENVIRONMENT,
SAFETY & HEALTH
(ESH)
DIVISION
T. Parker
HEAD OF DIVISION
CONSTRUCTION
GROUP
SCIENCE DIRECTORATE
D. Argyriou
DIRECTOR
MACHINE DIRECTORATE
F. MEZEI (I)
DIRECTOR
I. Persson
TARGET DIVISION
G. Trahern
HEAD OF DIVISION
E. Pitcher
DEPUTY HEAD OF
DIVISION
M. Rescic (C)
SYSTEM ENGINEER
C. Blixt
ADMINISTRATIVE
ASSISTANT
DEPUTY DIRECTOR
SENIOR ADVISOR
PERSONAL ASSISTANT
INTEGRATED
CONTROL SYSTEM
DIVISION
J. Haines
HEAD OF DIVISION
F. Plewinski
T. McManamy (C)
CS SW & SVCs
GROUP
S. Gysin (I)
GROUP LEADER
E. Laface
K. Rathsman
TARGET
CONTROLS
GROUP
K. Hlne
M. Herbst
P. Carlsson
L. Berdn
G. Svensson (C)
C. Vettier (C)
CS HW & IS
GROUP
D. Piso Fernandez (I)
GROUP LEADER
O. Kirstein
S. Petersson rskld
E. Lagrelius (L), M. Lindberg (A)
NEUTRON
TECHNOLOGIES
DIVISION
O. Kirstein
HEAD OF DIVISION
R. Hall-Wilton
DEPUTY HEAD OF DIVISION
M. Dell Anno Boulton
TEAM ASSISTANT
DETECTOR
GROUP
L. Coney
GROUP LEADER
A. Sadeghzadeh
PROTECTION
SYSTEMS GROUP
A. Nordt
GROUP LEADER
G. Jacobsson
TEAM ASSISTANT
TARGET PHYSICS
NEUTRON
INSTRUMENTS
DIVISION
COMMUNICATIONS AND
EXTERNAL RELATIONS
DIVISION
K. Andersen
HEAD OF DIVISION
M. Strobl
DEPUTY HEAD OF
DIVISION
A. Weeks
HEAD OF DIVISION
P. P. Deen
P. Henry
A. Jackson
R. Lechner (C)
E. Oksanen
W. Schweika
M. Sharp
N. Tsapatsaris
H. Wacklin
R. Hall-Wilton
GROUP LEADER
C. Hglund
K. Kanaki
A. Khaplanov
T. Kittelmann
S. Kolya
D. Pfeiffer
CHOPPERS
GROUP
I. Sutton
GROUP LEADER
SCIENTIFIC
ACTIVITIES
DIVISION
A. Hiess
HEAD OF DIVISION
B. Linnenberg
TEAM ASSISTANT
H. Bordallo (C)
M. Everett
S. Hall (C)
P. Schurtenberger (C)
C. Theroine
M-L. Ainalem
M. Ekdahl
M. Nilsson
A. Simoes (C)
PARTNERS &
INDUSTRY GROUP
U. Gunsenheimer
(A)(C)
GROUP LEADER
R. Larrea Basterra (C)
O. Rey Orozco (C)
A. Schmidli
PROJECT SUPPORT
DIVISION
J. Brisfors
HEAD OF DIVISION
I. Persson
PERSONAL ASSISTANT
J. Andersson
M. Jakobsson
K. Jonsdottir
J. Nilsson (C)
S. Ossowski
M. Palade
A. Stenberg (C)
H. Szentes (C)
M. Klein-Velderman (C)
J. Wollberg
LEGAL DIVISION
O. Graber-Soudry
HEAD OF DIVISION
MEDIA
COORDINATION
GROUP
S. Backman (C)
A. Iriondo Plaza (C)
J. Lngberg
C. Ramberg (C)
Vacant
GROUP LEADER
T. Lindqvist (C)
K. McFaul
K. Myram (C)
R. Eriksson (C)
SUPPLY,
PROCUREMENT &
LOGISTICS DIVISION
A. Weeks (A)
HEAD OF DIVISION
Science
Advisory Committee
A. Matic, Chair
Technical
Advisory Committee
R. Garoby, Chair
Conventional Facilities
Advisory Committee
TBD, Chair
J. Yeck
DIRECTOR GENERAL AND CHIEF EXECUTIVE OFFICER (CEO)
SENIOR EXECUTIVE ASSISTANT
ADMIN ASSISTANT
ASSOCIATE DIRECTOR FOR OPERATIONS, ES&H and QA
QUALITY ASSURANCE MANAGER
QUALITY ASSURANCE CONSULTANT
SENIOR ADVISOR
TURE DIRECTORATE
Larsson (I)
DIRECTOR
MACHINE DIRECTORATE
F. MEZEI (I)
DIRECTOR
K. Hlne
M. Herbst
P. Carlsson
L. Berdn
G. Svensson (C)
C. Vettier (C)
SCIENCE DIRECTORATE
D. Argyriou
DIRECTOR
DEPUTY DIRECTOR
PERSONAL ASSISTANT
J. Lehander
E. Lagrelius (L), M. Lindberg (A)
SENIOR ADVISOR
PERSONAL ASSISTANT
S. Petersson rskld
E. Lagrelius (L), M. Lindberg (A)
NEUTRON
COMMUNICATIONS AND
PROJEC
5 MW accelerator capability
Construction cost of 1,843 B
Operations cost target of 140 M
22 public instruments
Critical Path
Licencing
Licensing
Accelerator Buildings
ConvF
AccSys
Spoke & Medium Beta CM
(Prod&Inst&Comm)
NSS
High Beta CM
(Prod&Inst&Comm)
Instrument Construction
Ground break
First installations
on-site (ACCSYS)
First Beam
on Target (570 MeV)
Machine installed
for 2.0 GeV
Last of Instr
17 Const
Instr HO to Op
Target station
154M
Accelerator
510M
NSS/Instruments
350M
In-kind
Cash
In-kind potential
In-kind planned
Cash
300
250
200
150
100
50
0
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
400
350
300
Construction (1843 M)
250
200
150
100
50
0
Construction (1843 M)
Initial Operations + ramp-up
Steady State Operations
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028
65
62
48
39
11
60
90
2064 2065
1
140 140 140 140 140 140 140
Next 6 months
1st Annual Review action plans
Review Charge
Committee Charge
06 Sep 2013
1. Is the technical design sound and likely to meet the performance expectations identified in the ESS
Technical Design Report?
2. Are the technical specifications sufficiently advanced and under adequate configuration control to
support the project baseline?
3. Are the cost, schedule, and risk estimates complete, reasonable, and adequately understood to serve
as the performance baseline for the construction project? Does the project baseline provide flexibility
to address typical project risks, e.g., schedule float, budgetary contingency, technical performance
margin, etc.?
4. Are the Safety, Health and Environment and Quality Assurance aspects being properly addressed given
the projects current stage of development?
5. Are the plans for managing the regulatory permitting adequate for this stage of the project?
6. Are all the prerequisite activities and documents necessary to support a project performance baseline
complete?
7. Are the plans for host laboratory support functions (HR, IT, Legal, Finance, etc.) adequate to support
the construction project?
8. Are the plans for managing procurements, including staffing the procurement function, appropriate?
9. Are the plans for managing In-Kind contributions appropriate?
10. Is the management team organized and adequately staffed to successfully execute the project?
!
11. Will ESS be ready to establish the project performance baseline in early 2014 and start conventional
construction in mid-2014?
Review Committee
for the Annual Review of the
European Spallation Source (ESS)
November 12-14, 2013
Committee Chair, M arzio Nessi, CERN
Committee Coordinator, M ark Reichanadter, SLAC
Subcommittee 1
Accelerator
* * * Philippe, Lebrun, CERN
Mikael Eriksson, Max-Lab
Carlo Bocchetta, SOLARIS
Maurizio Vretenar, CERN
Francis Perez, ALBA
*
**
**
**
Subcommittee 4
Neutron Scattering Systems
Shane Kennedy, ANSTO
Ken Herwig, ORNL-SNS
Sean Langridge, ISIS
Mark Johnson, ILL (DMSC)
Geoffrey L Greene, UT-SNS
Winfried Petry, FRM-II
Subcommittee 7
M anagement, Sourcing,
I ntegration, SHE and QA
* Torsten kesson, Lund University
Ken Blackler, ITER
Helmut Krech, formerly of ESRF (in-Kind)
Serge Prat, XFEL (In-Kind)
Anders Unnervik, CERN (Procurement)
Andreas Hoppe, DESY (SHE)
Frank Kornegay, retired SNS-ORNL (SHE)
Paul Berkvens, ESRF (SHE)
Subcommittee 2
Target
* ** Phil Ferguson, ORNL-SNS
Yujiro Ikeda, J-PARC
Friedrich Groeschel, IFMIF
Georg Bollen, MSU-FRIB
Subcommittee 3
I ntegrated Control System
* Bob Dalesio, BNL
Anders Wallander, ITER
Mark Heron, Diamond Light Source
Subcommittee 5
I nfrastructure
* ** Tim Watson ITER
Wilhelm Bialowons, DESY
** Peter Lundhus, formerly of resundskonsortiet and Femer Belt
Ingvar Carlsson, formerly of TVL (Energy)
Subcommittee 6
Cost and Schedule
* Steve Gilligan, ITER
Cathy LaValle, BNL-NSLS-II
Barbara Thibadeau, ORNL
Observers
David Edvardsson, Swedish Ministry of Education and Research
Morten Scharff, Danish Ministry of Science, Innovation and Higher Education
Philippe Lavocat, French Ministry of Higher Education and Research
Pascale Delbourgo, French Ministry of Higher Education and Research
Sven Landelius, Chair ESS AB
Tom Barrett, EIB
* = Subcommittee Chairperson
* * = M ember of ESS Advisory Committee (SAC, TAC, CFAC)
Count: 34 (excluding observers and coordinator)
24
First impressions
- The first ESS annual review took place at LUND the 12th-14th November 2013
- Present : ESS project team, 33 members of the review team organized in 7
subcommittees and 7 observers (see next slide for details)
First impressions:
- The review committee congratulates the ESS team and its management for the
quality of the material and presentations submitted to the reviewers
- The ESS is now a real project from all points of view, well shaped and well
organized. ESS is now managing to the established baseline.
- A big effort was made in the last 10 months to build up an organization
structure with names and clear responsibilities attached to it
- The management of the project is strong, well determined, motivated and
success oriented. The ESS overall schedule foresees first protons on target in
December 2019. The cost cap has been fixed to 1.843 Beuro (year 2013).
- ESS will start real construction work in June 2014 (ground break)
25