Module - 6 Quality Management For Construction Projects
Module - 6 Quality Management For Construction Projects
Submodule 1: Introduction
A.
B.
Make certain that the necessary changes are made in the contractor's
QC system, if excessive construction deficiencies occur.
C.
D.
Produce the quality specified in the plans and specifications, and for
design-build contracts in the Request for Proposal, as well as the
contractor's accepted proposal,
6-2
EXERCISE
Submodule 6.1
1.
2.
3.
4.
6-3
5.
6-4
NOTES
CONSTRUCTION QUALITY MANAGEMENT
FOR CONTRACTORS
6-5
NOTES
CONSTRUCTION QUALITY MANAGEMENT
FOR CONTRACTORS
6-6
A.
Purpose:
The primary purpose of the Three-Phase Control System is to require the
contractor to plan and schedule the work to ensure that he is prepared to
start each new definable feature of work. The three phases of control
(preparatory, initial, and follow-up) are the core of the Construction
Quality Management System. When they are performed as outlined in
the specifications, success in completing the work to comply with
requirements of the contract is enhanced. In Module 3, Submodule 1,
the three-phase control system was mentioned as a required part of the
contractor's quality control plan.
B.
6-7
C.
6-8
2.
3.
D.
6-9
3 Phases of Control
Using a simplified Schedule
OCT
NOV
DE C
JA N
Figure 1
6-10
FE B
MAR
APR
MAY
JUN
CMU Walls
Initial Phase:
Follow-up Phase:
Figure 2
CMU Walls
Initial Phase:
Follow-up Phase:
QC Manager
QC Specialists
Superintendent
Subcontractor Foreman
QA Representative
QC Manager
QC Specialist
Superintendent
Subcontractor Foreman
QA Representative
Figure 3
6-11
EXERCISE
Submodule 6.2
1.
2.
6-12
PRACTICAL EXERCISE
Submodule 6.2
PREPARATORY PHASE MEETING EXERCISE
You are:
Pipe is on site
Submittals are approved
Excavation permit is issued
Safety plan covers the work and is satisfactory
Layout work is complete
TEAM 1
6-13
PRACTICAL EXERCISE
Submodule 6.2
PREPARATORY PHASE MEETING EXERCISE
You are:
Pipe is on site
Submittals are approved
Excavation permit is issued
Safety plan covers the work and is satisfactory
Layout work is complete
Project Superintendent
Quality Control Manager
Site Work Subcontractor's Superintendent
Storm Drainage System Second Tier Subcontractor's Foreman
Safety Engineer
TEAM 2
6-14
SAMPLE
Preparatory Phase Checklist
Contract No.: _____________________
Date: _____________
I. Personnel Present:
Name
Position
Company/Government
1.
2.
_________________________________________________________________________
_________________________________________________________________________
3.
4.
5.
6.
7.
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
(List additional personnel on reverse side)
II. Submittals
1.
Review submittals and/or submittal log 4288. Have all submittals been approved?
Yes __________ No _____________
If No, what items have not been submitted?
a. _______________________________________________________________________
b. _______________________________________________________________________
c. _______________________________________________________________________
6-15
6-16
NOTES
CONSTRUCTION QUALITY MANAGEMENT
FOR CONTRACTORS
6-17
NOTES
CONSTRUCTION QUALITY MANAGEMENT
FOR CONTRACTORS
6-18
A.
B.
C.
D.
6-21
EXERCISE
Submodule 6.3
1.
What are the major components of the sample Quality Control Report in
submodule 3.2?
2.
How often are Quality Control and Quality Assurance Reports required?
3.
b.
(2)
(3)
Is anything missing?
6-23
d.
e.
(2)
(2)
6-24
(3)
6-25
NOTES
CONSTRUCTION QUALITY MANAGEMENT
FOR CONTRACTORS
6-26
NOTES
CONSTRUCTION QUALITY MANAGEMENT
FOR CONTRACTORS
6-27
A.
Importance of Testing:
Testing is an extremely important part of CQM. If tests are not performed
properly, there are many construction procedures and materials that cannot be
confirmed as adequate. Visual observation alone is insufficient.
B.
C.
Types of Tests:
1.
2.
Procedures:
1.
2.
The contractor must provide a list of required control tests and specify
whether the tests are to be performed by an independent, approved testing
6-28
laboratory, or through the use of his own personnel and facilities. For
CORPS contracts approved testing laboratory means laboratories that
have been validated by the Materials Testing Center (MTC) at Waterways
Experiment Station in Vicksburg, MS.
3.
4.
b.
c.
5.
6.
7.
a.
b.
c.
d.
e.
f.
6-29
D.
a.
b.
c.
Test Tracking System: In accordance with Section 01451A and Section 01450N,
the contractor must establish and maintain a system to track verification, control
and acceptance tests. Each planned test type and frequency must be entered into
the tracking system prior to beginning work. Results and dates of individual tests
are to be added to the system as they are performed. Any failing test results will
have retests performed, entered into the system and cross referenced. The
tracking system must be reviewed frequently to assure that any activity underway
is having all planned tests performed as scheduled.
6-30
EXERCISE
Submodule 6.4
1.
Define QC testing.
2.
Define QA testing.
3.
6-31
4.
5.
6-32
NOTES
CONSTRUCTION QUALITY MANAGEMENT
FOR CONTRACTORS
6-33
NOTES
CONSTRUCTION QUALITY MANAGEMENT
FOR CONTRACTORS
6-34
6-35
Materials Turnover: The QC Manager will verify that all required keys,
spare parts and materials have been sorted, identified, and demonstrated to
be usable prior to final inspection.
6-36
EXERCISE
Submodule 6.5
6-37
NOTES
CONSTRUCTION QUALITY MANAGEMENT
FOR CONTRACTORS
6-38
NOTES
CONSTRUCTION QUALITY MANAGEMENT
FOR CONTRACTORS
6-39