FDOT FacilitiesDesignManual 2010
FDOT FacilitiesDesignManual 2010
SEPTEMBER 2010
FLORIDA DEPARTMENT OF
TRANSPORTATION
FACILITIES
DESIGN
MANUAL
Topic No. 625-020-016
Topic 625-020-016
Facilities Design Manual
September 2010
TABLE OF CONTENTS
Chapter 1 Introduction ............................................................... 1-1 1-10
Chapter 2 Project Organization .................................................. 2-1 2-21
Chapter 3 General Design Guidelines ........................................ 3-1 3-21
Chapter 4 Facility Specific Guidelines ........................................ 4-1 4-63
Appendix
Table of Contents
Topic 625-020-016-b
Facilities Design Manual
March 2010
Topic 625-020-016
Facilities Design Manual
September, 2010
Chapter 1
INTRODUCTION
1.1
PURPOSE
1.2
AUTHORITY
1.3
SCOPE
The Facilities Design Manual serves as a technical reference for the architectural
Design Team. This manual is intended to assist the Design Team recognize those key
issues that are interdependent and critical to the success of the project; and produce
designs compatible with the Departments preferred details, construction methods,
Introduction
1-1
Topic 625-020-016
Facilities Design Manual
September, 2010
CADD standards, and building scope and nature. The intent of standardizing
construction elements is to provide a mechanism to build economical building projects.
This manual addresses project management, coordination, design, and execution of
work.
Primarily, this manual is tailored to the standardization of building components and
materials that have been proven to provide a cost-effective building. Compliance with
these requirements is mandatory for Department building projects and for other projects
as directed by the project manager. Deviations from the requirements of this manual
must be requested in writing to, and approved in writing by, the project manager.
Codes, regulations, standards, Technical Design Memos issued by the Department,
and project requirements are subject to change from time to time due to changes in
state and local government authorities having jurisdiction over the work. Additionally,
each project has unique requirements that may result in design changes to
accommodate site conditions.
1.4
Introduction
1-2
Topic 625-020-016
Facilities Design Manual
September, 2010
1.5
This document is organized into five parts, plus appendices of supporting material:
Chapter 1 - Introduction
Chapter 2 Project Organization
Chapter 3 Design Guidelines
Chapter 4 Facility Specific Guidelines
Appendices
The Project Organization chapter describes how projects are organized and the
phases of building project delivery from planning through post-occupancy. The Project
Organization, the Design Guidelines and the Appendices are intended to apply to all
building projects. The Facility-Specific Guidelines apply only to specific types of
facilities (i.e., rest areas, offices, weigh stations, etc.)
Users of this Manual are encouraged to become familiar with those portions applicable
to their individual project(s). Compliance with these guidelines is mandatory unless
otherwise directed in writing by the project manager.
1.6
Notify the project manager, in writing, of conflicts associated with the use of this manual
that are contrary to normal design practice.
Introduction
1-3
Topic 625-020-016
Facilities Design Manual
1.7
September, 2010
UPDATES
The State Production Support Architects will issue periodic revisions and updates to this
manual. Revisions will be coordinated with various user groups and reviewed for
consistency by the Forms and Procedures Office (in accordance with Procedure No.
025-020-002, Standard Operating System) prior to release. Use the version of the
manual in effect at the time of Architectural/Engineering (A/E) contract execution.
1.8
The following abbreviations, definitions and industry standards apply throughout this
document.
Topic 625-020-016
Facilities Design Manual
MBE
NSF
OIS
PM
PVC
SF
SFM
September, 2010
Professional
Minority Business Enterprise (state)
Net Square Feet
Office of Information Systems
Project Manager
Poly-Vinyl Chloride
Square Foot/Feet
State Fire Marshal's Office
1.8.2 Definitions
Definitions under this section are not necessarily complete; rather, they may be more
explicitly defined within each Division, Section or Article of the Technical Special
Provisions.
Approved: The term "Approved" when used in conjunction with the consultants action
on the contractor's submittals applications and requests shall be interpreted as "Positive
Action, No Exception Taken" and shall be limited to the authority delegated to the
consultant(s) acting within the scope of the duties assigned to him by the contract
documents. Such positive action and/or approval by the consultant shall not relieve the
contractor from responsibility to fulfill all the requirements as set forth and delineated in
the contract documents, unless modified otherwise by supplemental agreements.
Beneficial Occupancy: Does not allow full occupancy as the Certificate of Occupancy
has not been issued by the Building Department; however, the stage of completeness
allows the Department to install equipment, systems and furnishings in preparation for
conducting intended operations.
Building: A "building" is defined as that portion of the project within the footprint of a
structure designed for human occupancy or use. Where project facilities, systems, or
components cross this delineation, logical break points will be used:
For a sidewalk leading to the 'building' -- the delineation would be where the
sidewalk contacts the structure.
For fencing or exterior walls -- the delineation would be where the fence or wall
abuts the structure.
For water piping -- the delineation would be the main valve; etc.
Introduction
1-5
Topic 625-020-016
Facilities Design Manual
September, 2010
Site plans, parking lots, site utilities, stormwater, walkways and other site
features.
Conformity of Work with Standards: Industry quality and performance standards shall
apply to the construction performed, except where the contract documents specify more
stringent requirements. Industry standards, as referenced in the contract documents,
shall impart equal force and effect as if bound or copied directly into the contract
documents. Referenced standards shall take precedence over other recognized
industry standards.
Conflicting Requirements: Where two or more codes or standards establish
conflicting requirements affecting the minimum standards for quality, quantity, and
performance levels, the most stringent requirement shall govern.
Contract Documents Consist of the: Special Provisions, Technical Special Provisions
(specifications), Drawings, FDOT Design Standards, Supplemental Specifications, and
FDOT Standard Specifications, in that order.
DOR (Designer of Record): Either the Architect or the Engineer in charge of and
responsible for each design discipline who has affixed their signature and professional
seal to the appropriate construction document(s).
Experienced: In conjunction with "installer", refers to previous work history in
successful performance of the work by the individual, company or corporate entity
Introduction
1-6
Topic 625-020-016
Facilities Design Manual
September, 2010
contracting for the work. The minimum previous experience requirement shall not be
less than three (3) years of satisfactory performance of this specialized work and
successfully completing five (5) previous projects of similar size, scope and design,
incorporating similar materials and systems.
Design Team The interoffice team of Department and consultant staff who participate
in the Design phase of the project.
Furnish: To supply all materials to be incorporated in the work under this contract
including delivery to the project site, prearranged to accommodate off- loading,
unpacking, assembly, cleaning, installation and other on-site operations.
Indicated: Refers to graphic and/or narrative representations on the drawings,
specifications sections, articles, paragraphs, schedules and all similar requirements of
the contract documents.
Install: Describes operations at the project site which include but are not limited to,
unloading, unpacking, assembly, erection, placing, anchoring, applying, working to
dimension, finishing, curing, protecting, cleaning, adjusting and all other operations to
complete and finish construction.
Installer: A sub-trade entity employed by the contractor to execute a specific portion of
the work in a specialized field of expertise.
Minimum: Values expressed in quantities, quality, dimensions, volumes, gauges,
thicknesses or tolerances, shall constitute the minimum acceptable standards
determining conformance to the prescribed target values or midpoint of the target
range. The intent of the contract documents is that the materials and the workmanship
will be in conformance with a standard of execution to realistically achieve the
prescribed target values established for the project. Executed work not in accordance
with the requirements of the contract documents that result in sub-standard,
unsatisfactory products or systems, or unacceptable in-place work shall, under direction
of the Project Manager, in coordination with the Architect, be removed, replaced, or
corrected in accordance with an approved repair procedure, and all associated costs
shall be paid by the contractor.
Project Manager The Department staff member assigned to manage the project.
This person may change as the project progresses through its development phases
(planning, design, construction, occupancy and maintenance, etc.)
Provide: To furnish and install, complete and ready for use. Manufacturer's products,
components, accessories comprising an assembly or system not specifically mentioned
or shown in the contract documents, but conspicuously essential to produce a complete
functioning installation or system, is considered part of the work and shall be provided
and included in the work, at no additional cost to the Department.
Introduction
1-7
Topic 625-020-016
Facilities Design Manual
September, 2010
Shown, Noted, Scheduled, Specified: These terms are used to assist in locating the
reference. No limitation on location is intended except as specifically noted.
Testing Laboratories: An independent entity (state or privately operated) engaged to
perform specific inspections or tests, at the project site, the plant or point of origin and
to forward the results of such inspections and tests to the CEI Project Engineer.
Trade Association Standards: Trade associations are nationally recognized by the
construction industry, as the standards generating organization given authority to
develop and maintain industry adopted standards. Trade association names and titles
of general standards are frequently abbreviated. Wherever abbreviations are used in
the contract documents they infer the recognized name of the trade association.
Work In the context of this document, means the project assignments appropriate to
the project phase. This is intended as an inclusive term to incorporate all activities
needed to fulfill project requirements.
Aluminum Association
Associated Air Balance Council
American Architectural Manufacturer's Association
American Association of Nurserymen
American Association of State Highway and Transportation Officials
American Association of Textile Chemists and Colorists
American Concrete Institute
American Council of Independent Laboratories
American Concrete Pipe Association
Air Diffusion Council
American Forest Product Association
Associated General Contractors of America
American Hardware Association
American Institute of Architects
American Institute of Steel Construction
American Iron and Steel Institute
American Institute of Timber Construction
Air Movement and Control Association
American National Standards Institute
American Plywood Association
1-8
Topic 625-020-016
Facilities Design Manual
ARI
ARMA
ASA
ASC
ASCE
ASHRAE
ASME
ASPE
ASSE
ASTM
AWI
AWPA
AWPB
AWS
AWWA
BHMA
BIA
CISPI
CTI
DHI
EIA
FCCHR
FGMA
FM
IEC
IES
IEEE
IPCEA
HI
MBMA
MISS
NAAMM
NAPHCC
NCMA
NDS
NEC
NECA
NEMA
NFPA
NPA
NWWDA
PCI
Introduction
September, 2010
Topic 625-020-016
Facilities Design Manual
PDI
SDI
S.D.I.
SIGMA
SJL
SMACNA
SPIB
SSPC
TCA
TPI
UL
USGBC
September, 2010
1.9
Corps of Engineers
Department of Transportation
Federal Highway Administration
Federal Specification
Military Standardization Documents
Department of Justice
FORMS
Introduction
1-10
Topic 625-020-016
Facilities Design Manual
September 2010
Chapter 2
PROJECT ORGANIZATION
TABLE OF CONTENTS
Project Organization ....................................................................................... 2-1 2-21
2.1 Codes, Rules and Regulations..................................................................... 2-2
2.2 Permits and Inspections ............................................................................... 2-4
2.3 Standard Document Requirements .............................................................. 2-5
2.4 Pre-design Services - Phase I ...................................................................... 2-5
2.5 Schematic Design - Phase II ........................................................................ 2-6
2.6 Design Development - Phase III .................................................................. 2-8
2.7 Construction Documents - Phase IV .......................................................... 2-10
2.8 Bid Phase - Phase V .................................................................................. 2-11
2.9 Construction Administration - Phase VI ..................................................... 2-12
2.10 Post Construction Services - Phase VII ..................................................... 2-15
Exhibits ................................................................................................................ 2-17
Project Organization
2-1
Topic 625-020-016
Facilities Design Manual
September 2010
PROJECT ORGANIZATION
2.1
2.1.1
General
Certification: The Consultant shall provide with each design review submittal a listing
of codes, rules, regulations, and standards that are applicable to the project.
2.1.2
The following agencies have statutory authority over the design and construction of
publicly owned and leased buildings in Florida. Each has specific requirements with
which the Consultant shall comply.
Building Codes: The Local Building Official has jurisdiction over building code
issues. The Local Building Official will issue the Building Permit and conduct
building inspections during the course of building construction.
Fire Codes: The State Fire Marshal (SFM) has jurisdiction over fire and life
safety issues. "Plans Review and Permitting Requirements", Appendix A-4,
describes the requirements of the SFM.
Project Organization
2-2
Topic 625-020-016
Facilities Design Manual
September 2010
required. The Consultant shall coordinate these issues to ensure the project
meets local requirements.
Well and Storm Water Management: Water Management Districts and local
health departments have jurisdiction over certain environmental issues. The
Design Consultant is responsible for obtaining current rules and regulations, as
well as proper permit applications that may pertain to and affect the project.
Use and Development Permits: Certain use and development permits are
required by local, state, and/or federal agencies prior to commencement of
construction. These permits, covering items such as sewage, water, air quality,
and other environmental issues, etc., shall be obtained prior to release of
documents for bidding. It is the Consultants responsibility to identify, apply for,
and secure such permits on behalf of the Department. (The Contractor obtains
the Building Permit from the Local Building Official.)
2.1.3
Approvals
It is the responsibility of the Consultant to assure that the development of the project is
fully coordinated with the above agencies and that all approvals may be readily
obtained. It is the responsibility of the Consultant to obtain approvals and permits from
the agencies having jurisdiction at the appropriate phase of the project.
Project Organization
2-3
Topic 625-020-016
Facilities Design Manual
2.2
September 2010
The Consultant is responsible for submitting plans to the State Fire Marshal, paying
applicable review fees and obtaining approved drawings. The Consultant is also
responsible for submitting, acquiring permits and paying fees for environmental, well
and stormwater, and use and development permits. The Consultant shall include these
fees in their price proposal.
The successful building Contractor is responsible for applying to the Local Building
Official for all Building Permits for the project and for paying for building permit and
inspection fees. The Contractor shall include these fees in their bid price.
2.2.1
The Local Building Official is the building permitting and inspection agency for State
building construction projects. The Local Building Official reviews the construction plans
and specifications and inspects all phases of construction for conformance to local,
state and national code compliance. Inspection by and approval of the Local Building
Official is intended to ensure that construction complies with applicable building codes,
but does not relieve the Consultant, Contractor or THE DEPARTMENT from complying
with the building codes, standards and regulations.
The Local Building Official provides inspections during the Department construction
phase to enforce building code compliance. The Local Building Official, in consultation
with the State Fire Marshals Office, will issue a Certificate of Occupancy upon final
inspection and approval of the construction. Local Building Official submittal
requirements may vary. The A/E Consultant is responsible for complying with the
submittal requirements of the appropriate code enforcement authority.
2.2.2
The Department of Insurance, Division of State Fire Marshal (SFM) is the review and
inspection agency for State building construction projects for conformance to the Life
Safety Code and other Fire Safety Standards prior to construction or change of
occupancy. SFM may inspect state owned and state leased spaces as necessary prior
to occupancy or during construction, renovation, or alteration to ascertain compliance
with the uniform fire safety standards. The Local Building Official will not issue a
Certificate of Occupancy (CO) until the SFM inspects and approves the construction
work.
See Appendix A.4 for SFM submittal requirements, fee schedule and submittal
Project Organization
2-4
Topic 625-020-016
Facilities Design Manual
September 2010
checklist.
2.2.3
The Department Project Manager functions as the responsible party for Department
project design and construction. The project manager ensures Consultant compliance
with the Consultant Contract in the execution of the Work.
The Department is the final approving authority for its building construction projects
statewide.
2.3
2.3.1
See Architectural Standards Chapter 23 of the CADD Production Criteria Handbook for
CADD software and plans preparation standards.
2.3.2
All technical special provisions, specifications, and special provisions shall be printed in
an 8 1/2" x 11" vertical (portrait) format. Any oversize sheets shall be folded to fit within
the specified format.
2.4
2.4.1 General
Pre-design services may, at the Departments option, be required. In this phase, the
Consultant shall consult with the Department to determine those services necessary to
establish: 1) the facility program and 2) the budget and time constraints for the project.
Project Organization
2-5
Topic 625-020-016
Facilities Design Manual
September 2010
2.5
2.5.1 General
In the Schematic Design Phase, the Consultant shall prepare Site Analysis and
Schematic Design Documents consisting of drawings and other documents illustrating
the general scope, scale and relationship of project components for approval by the
Department. Designs shall be conceptual in character based on: 1) program
requirements provided by the Department and reviewed and agreed upon by the
Consultant or 2) program requirements developed by the Consultant and the
Department.
A plan showing how the project fits into the master plan for facility development.
Site plan showing existing and proposed roads, pedestrian and vehicular
circulation, utility systems, landscape architecture and special site features. All
existing and proposed R/W required for the project shall be shown.
Project Organization
2-6
Topic 625-020-016
Facilities Design Manual
September 2010
Studies relative to the site: its topography, ecology, botanical and other relevant
features contributing to the solution or requiring alterations of the existing site.
Results of fire flow test (as appropriate) run to determine if water service
improvements are necessary to handle fire protection requirements.
Description of the features and provisions provided in the facility for use by
persons with disabilities in compliance with the ADA and the Florida Accessibility
Code for Building Construction.
Provide a review of codes that impact the project, report specific problems, and
recommended solutions.
The Project Manager shall approve the above elements of Schematic Design before
Project Organization
2-7
Topic 625-020-016
Facilities Design Manual
September 2010
2.6
2.6.1 General
Upon approval of the Schematic Design and Site Analysis Phases, and authorization by
the Department, the Consultant shall proceed with the Design Development
documents.
The Consultant shall, with the Departments concurrence, schedule and conduct
necessary conferences and meetings with the Department and other affected parties, to
ensure that the project is developed in a coordinated manner. At these occasions the
Consultant shall present and explain the project in adequate detail, responding to all
questions and comments. The Consultant shall compile and provide minutes of all
project meetings to all participants.
The Consultants Design Development submission shall be of sufficient detail to fully
explain scope of the project in all of its particulars so as to be readily understandable.
The information consisting of drawings, cost estimates, specifications, design criteria,
and other data presented shall be coordinated and complementary.
If the Design Development documents are acceptable, the Department project manager
may authorize the Consultant to proceed with the next phase.
Building(s): Plans shall include a plan of each floor, exterior and interior
elevations, building sections, wall sections and details, schedules for finishes
and equipment, type and class of construction, large scale drawings of special
Project Organization
2-8
Topic 625-020-016
Facilities Design Manual
September 2010
Plumbing: Provide design and information for drinking water distribution and
waste water collection systems; provide preliminary layout of systems including
elevations and line sizes; plans showing horizontal and vertical services with
sizes; fixtures and equipment; water pressure and volume requirements;
additional details and information necessary to fully describe the complete
systems.
Project Organization
2-9
Topic 625-020-016
Facilities Design Manual
September 2010
Fire Protection: Provide plans and information showing horizontal and vertical
layouts service hydrants, stand pipes and test valves; risers and hose cabinets;
sprinkler system and type (wet or dry), including water pressure and volume,
special systems (foam, carbon dioxide, etc.); hazard rating and insurance rating;
other necessary data. Show results of fire flow tests.
Provide data to explain the design concept and Design Development documents.
2.7
2.7.1 General
Subsequent to the approval of the Design Development documents and upon
authorization by the Department, the Consultant shall prepare complete Contract
Documents sufficient for construction purposes. The Consultant shall review in general
with the Department all codes, permits, and other requirements, prior to preparation of
construction documents.
The Consultant shall submit progress documents, at 30%, 60%, and 90% phase per the
consultant contract and the project schedule. Upon completion of Contract Documents,
the Consultant shall submit sets of documents to the Department in a quantity as
required by the consultant contract or as directed by the Project Manager to allow
simultaneous review by all reviewing parties (agencies).
Upon satisfactory written response to all review comments and appropriate revision of
the contract documents, the Department will determine the acceptability of the contract
documents and advise the Consultant.
Project Organization
2-10
Topic 625-020-016
Facilities Design Manual
September 2010
2.8
Release for Printing: Upon completion of reviews, revisions and receipt of approvals
from the Department, the Local Building Official (or DMS), and SFM, and authorization
from the Department, the Consultant shall print and properly sign and seal the
Construction Documents per the requirements above.
The Consultant shall assist the Department in preparing, or prepare the Construction
Documents for bidding per Consultant Contract requirements.
The Consultant shall respond to Contractor inquiries concerning the technical
requirements of the Construction Documents. The Consultant shall also prepare letters
of clarification and/or addenda, with the Departments approval and authorization. The
Department will issue these documents.
Project Organization
2-11
Topic 625-020-016
Facilities Design Manual
September 2010
2.9
2.9.3 Partnering
On many projects, the Department may determine that project Partnering will benefit
all parties. The intent of Partnering is to mold groups of unorganized, sometimes
Project Organization
2-12
Topic 625-020-016
Facilities Design Manual
September 2010
Project Organization
2-13
Topic 625-020-016
Facilities Design Manual
September 2010
The Departments standard construction meeting agenda form will be used. The
Project Manager will determine and identify the specific requirements for the
conferences.
2-14
Topic 625-020-016
Facilities Design Manual
September 2010
2-15
Topic 625-020-016
Facilities Design Manual
September 2010
made during construction from the Contract Documents and actual locations of all
concealed work installed during construction. Review accuracy of the information
submitted by the Contractor; prepare record drawings reflecting all significant changes
in the work made during construction; transmittal of record drawings and all other
relevant project data to the Department.
Warranties and Guarantees: Inspection(s) prior to expiration of the warranty and
guarantee period to determine adequacy of material, systems, and equipment
performance; document defects and recommend to the Department actions concerning
inadequate performance of building components, systems, and/or equipment.
Operation and Maintenance: Arrange for and coordinate instructions on operation and
maintenance of equipment with supplier/manufacturer; review all operation and
maintenance manuals.
Start-up Assistance: On-site observations, troubleshooting, and assistance in the
operation of building systems during initial occupancy; assist in coordinating remedial
work by the Contractor(s) after final completion.
Project Organization
2-16
Topic 625-020-016
Facilities Design Manual
September 2010
Exhibit A
Cover Sheet Layout
Project Organization
2-17
Topic 625-020-016
Facilities Design Manual
September 2010
Exhibit B
Cover Sheet Details
Project Organization
2-18
Topic 625-020-016
Facilities Design Manual
September 2010
Exhibit C
Certificate of Contract Completion
Project Organization
2-19
Topic 625-020-016
Facilities Design Manual
September 2010
Exhibit D
Schedule of Contract Values
Project Organization
2-20
Topic 625-020-016
Facilities Design Manual
September 2010
Exhibit D (cont.)
Schedule of Contract Values
Project Organization
2-21
Topic 625-020-016
Facilities Design Manual
September 2010
Chapter 3
GENERAL DESIGN GUIDELINES
TABLE OF CONTENTS
3.1
3.2
3.3
3.4
3.6
3.7
3.8
3.9
3.10
3.11
3.12
3.13
3.14
3.15
3.16
3.17
3.18
3.19
3.20
3.21
3.22
3.23
3.34
General
Code and Standards
Design Information
Site Design Considerations
Building Envelope
Division 1 General Structural Design Data
Division 3 Concrete
Division 4 Masonry
Division 5 Metals
Division 6 Wood, Plastic and Composits
Division 7 Thermal and Moisture Protection
Division 8 Openings
Division 9 Finishes
Division 10 Specialties
Division 11 Equipment
Division 12 Furnishings
Division 13 Special Construction
Division 14 Conyeying Systems
Division 21 Fire Supression
Division 22 Plumbing
Division 23 Heating, Ventalation and Air Conditioning
Division 26 Electrical
Division 32 Exterior Improvements
3-3
3-6
3-6
3-6
3-19
3-21
3-21
3-22
3-22
3-23
3-23
3-28
3-31
3-32
3-33
3-33
3-33
3-33
3-34
3-35
3-36
3-42
3-54
_____________________________________________________________________
General Design Guidelines
3-1
Topic 625-020-016
Facilities Design Manual
September 2010
CHAPTER 3
GENERAL DESIGN GUIDELINES
3.1
GENERAL
This chapter describes design guidelines for the project manager and the consultant to
use while developing the building project design. The building systems, components
and items described are minimum requirements. These Guidelines have been
developed over a period of years of satisfactory performance on state building projects.
They are intended to aid the consultant by establishing design criteria, quality levels,
and limiting the selection of systems and materials to those that have a proven record.
These Guidelines are not intended to inhibit the use of innovative materials and
techniques where those can be proven to provide equal or better performance than the
described items.
The Design Guidelines are separated into 48 Divisions recognized by the Design and
Construction Industry. This manual will review in general terms, those divisions and
their respective subsections that are applicable to the design and construction of FDOT
buildings. Divisions are not used for areas outside the building. For areas outside the
buiding use the FDOT Standard Specifications for Road and Bridge Construction
and FDOT Design Standards. These Guidelines will not address all 48 divisions and
subsections individually. They will focus on key issues and the interdependency and
relationship of the divisions used to develop Department projects.
3.2
Appendix 4.2 contains a list of codes, standards and other regulations adopted for use
in Florida. Consult with authorities having jurisdiction for applicable codes and inform
the Project Manager about any changes from the list, for his/her information only.
Review with the Project Manager what submittals are required by the Contract for
interim reviews, letting documents, and final close out of the project, i.e., CADD "asbuilts," CD ROMs, bound maintenance manuals, etc. Refer to the Plans Preparation
Manual, Topic No. 675-000-007 and 675-000-008 and this manual for general
Department design criteria and process information.
Utilize the room numbering system provided by Project Manager. Provide fire
extinguishers as required by code. Locate on plans.
_____________________________________________________________________
General Design Guidelines
3-2
Topic 625-020-016
Facilities Design Manual
3.3
September 2010
DESIGN INFORMATION
Space Planning / Facility Programming: Consult with the Project Manager and the
Facility-Specific Guidelines, Chapter 4, to determine the space and organizational
requirements of the project. Develop the facility program to the level appropriate to the
scope of services.
3.4
Building occupants: 1 space per 300 gross sq. ft. min. or meet requirements of
local zoning ordinances, whichever provides the most number of spaces.
Parking for disabled: In accordance with the current Florida Accessibility Code
for Building Construction (Chapter 11 of the Florida Building Code)
Parking Layout and Relationship to Building (Subject to topography and local site
conditions):
Screen a majority of off-street parking from view from the street with regional
landscape materials. The parking layout should be near the building it serves.
_____________________________________________________________________
General Design Guidelines
3-3
Topic 625-020-016
Facilities Design Manual
September 2010
Landscaped islands with curbs shall be located at the ends of all parking rows
and throughout the parking lot at an interval that averages no fewer than one
island for every 12 consecutive spaces, or where governed by local codes (which
ever is greater).
Driveways and parking spaces shall be hard surface paving materials. Porous
paving may be substituted as an alternative design to aid storm water
management.
Locate accessible parking spaces near public entrances and major staff
entrances.
_____________________________________________________________________
General Design Guidelines
3-4
Topic 625-020-016
Facilities Design Manual
September 2010
For elevated sidewalks, provide a curb ramp within the sidewalk limits or slope
the sidewalk down to the level of the access aisles. A curb ramp shall NOT
extend into the access aisle or accessible space.
Slopes in accessible parking spaces and access aisles shall not exceed 2% in
any direction.
Locate visitor parking spaces near the main entrance of the building and closer
to the building than staff parking.
Paint for parking area pavement markings shall be durable traffic paint listed in
the Departments Qualified Products List in colors described in the Design
Standards.
Sidewalks shall be a minimum of 5' wide. Surfaces shall be slip resistant under
wet and dry conditions. Slope to drain away from building.
Sidewalks shall meet the requirements of the ADA Accessibility Guidelines and
the Florida Accessibility Code:
_____________________________________________________________________
General Design Guidelines
3-5
Topic 625-020-016
Facilities Design Manual
September 2010
o If slope is greater than 1:20 (5%), ramp must have 5-0 minimum level
landings each 30 rise.
5-0 landing at top of ramp and interim landings
6-0 landing at bottom of ramp
o Maximum slope of ramp is 1:12; 1:14 maximum is preferred.
o Handrails are required on both sides of ramp
3.4.3
34-36 high
Site Lighting
Drainage
Storm drain inlets should be located 25' minimum from major building entrances.
Provide ground surface grades to prevent ponding during heavy rain and runoff from
entering the building. Coordinate with storm-water requirements.
Parking Areas:
Concrete valley gutters shall be used to control runoff in parking areas if uniform
sheet flow is determined not to be feasible. If valley gutters are used, they shall
be placed along the island curbs at the side of an access drive, and not down the
center of the drive.
The minimum slope in off-street parking lots without valley gutters is 1%. The
maximum slope is 5%. If the topography is so steep that the parking area cannot
be graded without exceeding a 5% slope, the parking area shall be terraced
using continuous landscaped islands with a minimum width of 8'. A grade
transition will occur in the islands sufficient to allow for a 5% maximum slope in
the parking area.
_____________________________________________________________________
General Design Guidelines
3-6
Topic 625-020-016
Facilities Design Manual
September 2010
Walks and paths should be arranged to traverse steep areas at an angle to site
contours, with turns back and forth at landings so runoff does not become
concentrated in any one direction for long distances.
Plazas should have a maximum slope of 2% in any direction and a uniform
surface that prevents ponding.
Sod areas, except for retention ponds, should have a minimum slope of 1%, and
a maximum slope of 1:3.
3.4.5
Site Improvements
Review security surveillance features during the design of plazas, terraces and parking
areas with the FDOT Project Manager. Special attention should be given to provide
adequate visual control including elimination of potential concealed spaces near public
pedestrian areas.
Show point-of-entry for water service to handle potable and fire service requirements.
Show location of site fire-service facilities (hydrants, standpipes, etc.)
Parking Area Lighting:
An illumination diagram shall be provided for the parking areas and all major
public walkways adjacent to the building showing illumination levels in footcandles for each area.
_____________________________________________________________________
General Design Guidelines
3-7
Topic 625-020-016
Facilities Design Manual
3.4.6
September 2010
Exterior Signs
Designs for site signs shall be reviewed by the Project Manager. Assure sign
configuration and location does not interfere with driver sightlines for traffic along
adjacent roadway(s) or entering the site.
Steel or aluminum finished with 2-part catalyzed urethane paint is the preferred material
for outdoor signage. The catalyzed paint finish is preferred over anodizing for
aluminum. Note: Catalyzed paint contains lead products and must not be used at
playgrounds, Rest Area facilities, or where the presence of children is likely.
Outdoor dimensional letters shall be cast aluminum, bronze, or stainless steel.
Aluminum should be painted rather than anodized.
The sign shall be clearly legible from a distance of at least 100'. Minimum height of the
letters shall be 6".
Building Identification Signs should be located at or next to the main entrance walk of
the building.
3.4.7
Traffic Signs
Traffic signs shall meet the roadway signing requirements of Florida DOT and the
Manual on Uniform Traffic Control Devices (MUTCD).
3.4.8
Solid Waste
The dumpsters shall be sized to hold 3 pounds of solid waste per employee per day.
Coordinate the location of solid waste dumpsters with the Project Manager.
LEED requires recycling of paper, plastic, metals, corrugated cardboard and glass.
Coordinate space for recycling dumpsters with the FDOT Project Manager.
Locate dumpsters on reinforced concrete slabs.
Waste receptacles should be placed along walkways near building entrances.
Waste receptacles shall include covers, domes, etc., to shed rainwater.
Waste receptacles made with recycled materials are encouraged.
_____________________________________________________________________
General Design Guidelines
3-8
Topic 625-020-016
Facilities Design Manual
3.4.9
September 2010
Benches, (Exterior)
Topic 625-020-016
Facilities Design Manual
September 2010
If the planter is to contain a shade tree, the minimum planting area shall be no less than
64 sq. ft., with a minimum soil depth of 4'.
Planters shall not be installed over any building areas that could possibly sustain water
damage whether occupied or not.
Special care shall be given to control efflorescence and moisture deterioration of the
planter.
3.4.13 Bicycle Racks
Bicycle racks are desired. Coordinate with Project Manager and local ordinances for
location and number of bike racks.
3.4.14 Bus Shelters
Coordinate shelter locations and design with the Project Manager and local transit
authority.
Shelters shall be accessible to persons with disabilities and compatible with the overall
building design concept.
The shelter shall be anchored to a concrete pad that is built adjacent to and accessible
from the sidewalk.
3.5
3.5.1.
BUILDING CORE
Toilet Rooms
Toilet rooms shall meet all requirements of the Americans with Disabilities Act (ADA)
and the Florida Accessibility Code for Building Construction (FACBC).
In assembly occupancies and assembly-use buildings, provide toilet rooms and fixtures
meeting the requirements of potty parity (three womens toilets for each two mens
toilets and urinals.)
In general, lavatories shall have cold water only. Hot water is typically used only in
areas requiring level of hygiene provided by hot water (food service areas, kitchens,
etc.) Faucets shall be mechanical automatic turn off type or infrared auto turn on and
off type.
_____________________________________________________________________
General Design Guidelines
3-10
Topic 625-020-016
Facilities Design Manual
September 2010
Floors shall be unglazed ceramic or non-slip porcelain floor tile in 8" x 8" or larger
sizes with a maximum of 2 tile colors.
Separate color schemes may be developed for the Men's and Women's toilet
rooms or on a floor-by-floor basis.
_____________________________________________________________________
General Design Guidelines
3-11
Topic 625-020-016
Facilities Design Manual
September 2010
Walls in stalls shall be 8" x 8" gloss finish ceramic or porcelain tile to 7'-4" AFF
minimim with a maximum of 3 tile colors. Walls above tile work shall be a multicolored epoxy paint system.
Coordinate all grout joints in the wall, base and floor tiles so they are aligned.
Ceilings shall be water resistant gypsum board painted with semi-gloss latex paint.
Ceiling height to be 9' AFF minimum.
Doors shall be painted or stained solid core wood, painted hollow metal, or stainless
steel, 3'-0" x 7'-0" minimum. Frames shall be painted hollow metal or stainless steel.
All toilet accessories shall be stainless steel. Recessed type units shall be used where
practical. Toilet stall accessories shall be through-partition type. Provide a 4" wide
stainless steel shelf over wall-hung lavatories and water closets.
3.5.2
Water fountains
Water fountains and electric water coolers shall be recessed in order to avoid
obstructing corridors meet ADA requirements for Clear Floor Space.
Exterior drinking fountains may be surface-mounted meet ADA requirements for Clear
Floor Space and Protruding Objects.
3.5.3
Janitor Closets
Topic 625-020-016
Facilities Design Manual
September 2010
Ceilings shall be water resistant gypsum board painted with semi-gloss enamel.
Provide a stainless steel mop rack and shelf.
Doors shall be painted or stained solid core wood or painted or stained hollow metal,
3'-0" x 7'-0" minimum. Frames shall be painted hollow metal.
Size the janitor closet to provide storage space for cleaning supplies. Consult with
theFDOT Project Manager.
3.5.4
Electrical and Communications rooms shall not be located next to elevator shafts,
stairwells, pipe chases or other spaces that would prevent conduits from entering from
all sides.
_____________________________________________________________________
General Design Guidelines
3-13
Topic 625-020-016
Facilities Design Manual
3.5.5
September 2010
Communications Rooms
Consult with the Project Manager and the Departments Office of Information Systems
(OIS), and refer to the DMS "General Facility Requirements for
Telecommunications Systems" for design criteria for the communications room and
the overall system.
These rooms shall not provide access to any other space or room.
Communications rooms shall be equipped with receptacles, surge suppression and
grounding as required by the communications program. Provide all circuits in
communication rooms with isolated grounds.
Communications rooms shall have walls covered with 4" x 8" x 3/4" fire retardant
plywood painted with semi-gloss enamel.
Communications rooms shall not be used to house building controls, security
equipment or other such uses unless expressly approved by the Project Manager.
Communications rooms may be required to have 24-hour stand-alone HVAC on
emergency power. Coordinate with Project Manager.
3.5.6
Mechanical Rooms
Topic 625-020-016
Facilities Design Manual
September 2010
doors shall be painted hollow metal, and sized for equipment width and height. Frames
shall be painted hollow metal.
Intake louvers in exterior doors or walls shall have insect screens, which are removable
for access or cleaning.
Overhead coiling doors or removable wall sections may be provided for removal and
replacement of large equipment items such as boilers, air handlers, chillers and water
tanks. Knockout walls are acceptable if they can be removed and replaced with minimal
disruption or damage to other areas of the building and maintain required fire resistance
ratings.
Servicing requirements require an adequate clearance with a minimum clearance of 3
from any wall around mechanical equipment. Increase space as required by
manufacturer.
Provide clear space at one end of all boilers and chillers to allow rod cleaning and
replacement of the internal tubing (show on Plans).
At air handlers, provide clearance for removal and replacement of filters, fan shafts and
coils (show on Plans).
3.5.7
Stairs
Walls shall be CMU or shaft wall, with high traffic, washable latex, two-color paint
system.
Treads, risers, and landings shall be steel with concrete filled pans or reinforced
concrete. The floors, stairs (tread and risers) and all landings of interior stairs may be
vinyl tile, ceramic tile or sealed concrete.
Doors shall be fire-rated, solid core wood, painted or stained; or hollow metal painted,
3'-0" x 7'-0" minimum. Frames shall be painted hollow metal, and fire rated as required
by code.
Light fixtures shall be located 7'-0 minimum above landing in explosion-proof
housings.
Light fixtures shall be accessible with a 6-foot ladder.
In order to encourage use of stairs in lieu of elevator, provide at least one stair in multistory buildings conveniently located near main pedestrian traffic flows, i.e. adjacent to
_____________________________________________________________________
General Design Guidelines
3-15
Topic 625-020-016
Facilities Design Manual
September 2010
elevator lobby. Provide sufficient width, 5'-0 minimum so two adults can pass each
other comfortably while traveling in opposite directions.
Guard railings shall be designed with vertical pickets or in-fill panels.
Provide vision panels in all stair doors.
3.5.8
Corridors
Walls shall be painted, fire-rated gypsum board painted with eggshell high
traffic/washable latex type wall paint. Vinyl wall covering is permitted at the discretion of
the Project Manager.
Floors shall have glue-down carpet with a minimum 10-year warranty, ceramic tile or
VCT. Carpet shall be a tufted textured graphics loop with a minimum pile face weight of
26 ounces per square yard. Base shall be coved vinyl/rubber, 4" high, mininim 1/8"
thick.
Ceiling shall be 2' x 2' suspended acoustical ceiling tile with square edge.
Indirect lighting may be used provided access is not unduly restricted.
3.5.9
Main Lobby
Floors:
Floor finish and base shall be slip resistant hard tile (ceramic, quarry, or stone),
thin-set.
A metal edge strip shall be installed where tile abuts carpet or other floor
materials.
Walls shall be gypsum board with appropriate fire rating. Finishes shall be durable and
washable such as paint, plaster, or vinyl wall covering.
_____________________________________________________________________
General Design Guidelines
3-16
Topic 625-020-016
Facilities Design Manual
September 2010
Ceiling finish shall be acoustic ceiling panel, painted gypsum board, or metal.
At building entry doors for the general public and staff, use vestibules or revolving doors
to control wind flushing. Coordinate the use of automatic or power-operated openers
with the Project Manager.
Limit public access into building to the lobby and the loading area. Building emergency
exits shall be used as exits only and shall not to be used for normal access.
Coordinate location of building directories with Project Manager.
No mail chute shall be provided in any Department building.
Provide "Reception" or "Security" station, unless indicated otherwise in the program.
Coordinate with Project Manager.
3.5.10 Card Readers or Keypads
Card readers or keypads shall be provided at all applicable entries (to be determined
during project Design phases).
3.5.11 Office Spaces
Walls shall be painted gypsum board and terminate 6" above the ceiling except that
walls of offices for Select Exempt and Senior Management personnel shall extend to
the deck above. Conference rooms, training rooms, and those spaces requiring
confidentiality should also extend to the deck above. Walls are not to be acoustically
insulated except as required by the Facility Program. Provide return air transfer boots
in walls extended to deck.
Ceilings shall be flat lay-in 2' x 2' acoustic panels with square edge, generally 9'-0"
above finished floor (A.F.F.).
Doors shall be solid core wood, painted or stained, 3'-0" x 7'-0" minimum.
Frames shall be painted hollow metal. Knock down frames are permitted.
3.5.12 Conference Rooms
Accessories such as tack boards, marker boards, and projection screens shall be
provided and located as required by Facility Program.
_____________________________________________________________________
General Design Guidelines
3-17
Topic 625-020-016
Facilities Design Manual
September 2010
3.6
BUILDING ENVELOPE
The building shall be designed to ensure weather tightness, minimize maintenance and
energy use and maximize building longevity and architecturally compatible with the
_____________________________________________________________________
General Design Guidelines
3-18
Topic 625-020-016
Facilities Design Manual
September 2010
environment. Life-cycle cost analysis shall be used. Note minimum U-values listed in
FLACOM or EnergyGauge (Summit).
3.6.1
Roof System.
Metal hipped, standing seam roof systems are preferred and shall have the following
characteristics:
Aluminum Material:
o 0.032" minimum for roof panels, trim and flashing unless otherwise
determined by the Architect.
o 0.032" minimum for soffit panels, pre-manufactured soffit venting.
o 0.080" minimum for gutter and downspout covers.
o 4Finish: Polyvinyldenefluoride, Kynar 500, Hylar 5000 resin based coating.
o Seam Height: 2" minimum
o Pan width: 16" maximum
Warranty:
o Roofing panel manufacturer shall warranty for minimum period of 20 years
against perforation or structural failure of metal roofing panels and
accessories.
o Roofing panel manufacturer shall warranty for minimum period of 5 years that
the finish color will not change more than 5 NBS units in accordance with
ASTM D 2244-78 and will not crack, peel or lose adhesion with the substrate
for a period of 20 years.
o Roofing panel manufacturer shall warranty for minimum period of 20 years
specifying the metal panel system will be watertight. Warranty will state if
repairs are necessary, guarantor will provide materials and labor to make
repairs at no cost to Owner.
_____________________________________________________________________
General Design Guidelines
3-19
Topic 625-020-016
Facilities Design Manual
3.6.2
September 2010
CMU
Brick Veneer
ICF
3.6.3
All exterior glazing shall be insulated double-pane. One-story, full-height glazed opening
shall be a center glazed storefront system. Two-story high lobby areas shall have a
curtain-wall type system. Glazing protections shall meet the impact-resistance
requirements of the building code.
The following are the major glazing system components:
3.7
Topic 625-020-016
Facilities Design Manual
3.8
September 2010
DIVISION 3 - CONCRETE
3.9
DIVISION 4 - MASONRY
Topic 625-020-016
Facilities Design Manual
September 2010
There should be no obstructions within the cavity that may allow water to backup and
drain into the back-up wall.
Detail flashing against parapets, under copings, gravel stops, over shelf angles,
windows, doors, horizontal relief joints and at changes from horizontal to vertical plane.
Show three-dimensional flashing intersections in isometric detail.
Specify brick masonry with low moisture absorbency.
Brick masonry accessories:
Specify the type of tie design that will allow for vertical and horizontal differential
movement between face brick and backup wall or structure without allowing
water to bridge gaps.
For multi-story masonry construction, design steel shelf support angles, which will allow
for building movement and wall deflection.
3.10
DIVISION 5 - METALS
AISC Specification for Structural Steel Buildings - Allowable Stress Design and
Plastic Design.
_____________________________________________________________________
General Design Guidelines
3-22
Topic 625-020-016
Facilities Design Manual
September 2010
3.11
The quality and design of wood members and fastenings used for load supporting
purposes shall conform to the following applicable standards:
American Forest & Paper Association AFPA/ASCE 16 Standard for LRFD for
Engineered Wood Construction
All wood in direct contact with soil, water, masonry and concrete shall be naturally
durable wood or preservative-treated. Treatments and condition of use shall comply
with the applicable standards of the AWPA.
Particleboard shall not be used in roof deck, wall sheathing or any exterior or main wind
force resisting system.
_____________________________________________________________________
General Design Guidelines
3-23
Topic 625-020-016
Facilities Design Manual
3.12
September 2010
Provide walk pads around maintenance items along the route from roof access
points to the maintenance items.
HVAC units or equipment are not permitted on the roof, except exhaust fans,
vents, and outside air intakes.
Drainage considerations:
Emergency overflow drains are preferred over through-wall scuppers on lowslope roofs. Provide minimum 4" high leaf guards on drains.
Expansion joints shall be elevated upon a solid tapered base; drainage shall be
positive and away from the joint at every side.
Drainage pieces: These should be kept a sufficient distance from parapets and
up-stands to allow the installer to work from all sides.
Detailing:
Limit the use of pitch pockets. Uncapped pitch pockets are not permitted.
Detail every flashing condition required for type of building designed. Show
three-dimensional flashing intersections in isometric detail.
_____________________________________________________________________
General Design Guidelines
3-24
Topic 625-020-016
Facilities Design Manual
September 2010
Show all roof ventilators, and any other types of FDOT approved equipment to
scale on Roof Plan.
Provide metal coping on parapet tops. Terminate roof membrane under coping.
Quality Assurance:
Concrete R-19
Coordinate with Life-Cycle Cost Analysis and the Florida Energy Efficiency Code for
Building Construction.
3.12.3 Air Barriers
Air barriers shall be made of durable, non-porous materials and shall be sealed to
adjoining wall, ceiling or floor surfaces with a suitable long-life mastic and tape. Taped
and sealed drywall may constitute an air barrier but lay-in acoustical tile ceilings (T-bar
_____________________________________________________________________
General Design Guidelines
3-25
Topic 625-020-016
Facilities Design Manual
September 2010
ceilings) may not. Batt insulation facings and asphalt-impregnated fiberboard and felt
paper are not considered air barriers.
Where vented-to-the-outside, dropped ceiling cavities occur over conditioned spaces,
the ceiling shall be considered to be both the upper thermal envelope and pressure
envelope of the building and shall contain a continuous air barrier between the
conditioned space and the vented unconditioned space that is also sealed to the air
barrier of the walls.
Where unvented dropped ceiling cavities occur over conditioned spaces that do not
have an air barrier between the conditioned and unconditioned space (such as T-bar
ceilings), they shall be completely sealed from the exterior environment (at the roof
plane) and adjacent spaces by a continuous air barrier that is sealed to the air barrier of
the walls. In that case, the roof assembly shall constitute both the upper thermal
envelope and pressure envelope (air barrier) of the building.
Exterior Joints in the Envelope: All exterior joints cracks and holes in the building
envelope shall be caulked, gasketed, weather-stripped or otherwise sealed. Such joints
shall include, but not be limited to the following:
Through wall panels and top and bottom plates in exterior walls.
Between wall and floor where the floor penetrates the wall.
Around penetrations of flue vents, or attic hatches, and walls with building
cavities between floor/ceilings and ceilings/roof decks.
Topic 625-020-016
Facilities Design Manual
September 2010
Roofing membrane system selected shall meet Factory Mutual (FM) Requirements I-90
for wind uplift or Underwriters Laboratories (UL) Class 90.
Membrane Roof Warranties:
Warranty shall be non-prorated, non-penal sum type and shall include the total
roofing system consisting membrane, flashing, connections, insulation and deck.
Specify that a single subcontractor is responsible for the entire roof system.
3.12.5 Sheet Metal Flashing and Trim
Use the latest edition of the "Architectural Sheet Metal Manual" published by the
Sheet Metal and Air Conditioning Contractors National Association (SMACNA) as a
design guide.
Preferred flashing materials includes: Copper, Aluminum.
Verify substrate materials and joint compounds are compatible with flashing and will not
cause:
Against parapets
Expansion joints
_____________________________________________________________________
General Design Guidelines
3-27
Topic 625-020-016
Facilities Design Manual
September 2010
Corner conditions
o Wall Flashing:
Thru-wall flashing
Expansion joints
Corner conditions
Design metal flashing and coping caps to eliminate or minimize the use of sealants. Do
not rely on sealants as the primary barrier to water penetration.
Where sealant joints are required, utilize sealants that are designed to accommodate
the movement characteristics of, and are compatible with, the flashing material and the
substrate.
Protect dissimilar metals against galvanic action.
Base flashing should have an 8" minimum upstand from roof, and be a minimum of 4"
above a 4" cant. Metal counterflashing should lap base flashing at least 4".
Counter-flashing shall be removable and replaceable or renewable. Wall system shall
have a permanent sill or seating.
3.12.6 Joint Sealants
Specify sealant type to compensate for amount of anticipated joint movement and
environmental conditions to be encountered.
Specify bond breakers to prevent three-sided adhesion.
Specify sealants that are compatible with substrates. Verify that all sealants:
_____________________________________________________________________
General Design Guidelines
3-28
Topic 625-020-016
Facilities Design Manual
September 2010
Specify sealant primer if required for adhesion to substrate. Consult with sealant
manufacturer to verify performance applicability expected.
Do not use custom color sealants.
If coatings or waterproofing compounds are specified on exterior building skin, verify
that they are compatible with sealants and will allow for desired sealant adhesion.
Specify that the contractor shall have sealant manufacturers perform adhesion and
compatibility tests for each type of sealant, using actual samples of sealant specified
and substrate materials and coatings to be adhered to by sealant.
Use caulking only for interior joints that do not require waterproofing or movement
capabilities.
Use acrylic latex caulk conforming to ASTM C 834.
Limit caulking joints to in width or less.
3.13
DIVISION 8 OPENINGS
Topic 625-020-016
Facilities Design Manual
September 2010
Optional: Provide power door operators with hard-wired switches at main employee
and visitor entrances. Coordinate with Project Manager.
3.12.4 Aluminum Windows
Detail windows to prevent air infiltration. Testing to AAMA/NWWDA 101/I.s.2-97 or
ASTM E283-91 shall determine compliance with the criteria of air leakage, as
appropriate. Air Leakage shall not exceed 0.3 cfm / lin. ft.
Provide windows with thermal break construction. Provide units that have been tested
for thermal performance in accordance with AAMA 15003.1.
Design window sections to accommodate expected wind pressure and turbulence. The
contractor is to submit signed and sealed calculations.
Design window sections to accommodate Code-required wind-borne debris, missile
impact loads. The Contractor shall submit signed and sealed calculations and test
reports to verify code compliance.
Components:
Window frames should be designed with baffled weep holes. Do not allow weep
holes to be blocked by sealant.
Compatibility testing should be specified for all setting materials that come in
contact with each other, such as sealants or setting blocks, gaskets, and edge
shim material.
Specify that setting block locations will be verified in the field to not seal off weep
holes.
Topic 625-020-016
Facilities Design Manual
September 2010
Cylinders shall be keyed to the FDOT key system, and are subject to the Great
Grand Master (GGMK), Grand Master (GMK), Master (MK) and Change (CK)
key system. Locksets must accommodate the FDOT standard cylinder.
_____________________________________________________________________
General Design Guidelines
3-31
Topic 625-020-016
Facilities Design Manual
o
o
o
o
September 2010
3 each GMK
6 each MK
3 per lock CK
One lockable key cabinet to suit job requirements with 100% expansion
space.
3.12.6 Glazing
Glazing systems shall be designed to accommodate expected building movement.
Verify that glass selected can accommodate expected thermal expansion and
contractions.
Glass shall meet State of Florida Energy Efficiency Code requirements and FlaCom
and Energy Gauge (Summit) as a part of the exterior building envelope.
Provide non-operable windows with a shade coefficient of 0.32 - 0.45. The ratio of
visible light transmittance to the shading coefficient should be equal to or greater than
1.
Verify that glass meets U-value and shading coefficients required by mechanical
equipment design and FlaCom and Energy Gauge (Summit).
Window sections shall conform to American Architectural Manufacturers Association
(AAMA) standards for commercial or heavy commercial windows.
Insulated glass shall conform to Sealed Insulating Glass Manufacturers Association
(SIGMA) guidelines for vertical and sloped glazing.
Provide Project Manager a "washability" design statement applicable for all glass
surfaces, external and internal that describes how glass is accessed for routine
cleaning.
Coordinate maintenance design criteria with Project Manager prior to inclusion in the
specifications:
Topic 625-020-016
Facilities Design Manual
September 2010
Consider providing attic stock glass for future replacement as part of base bid.
Confirm requirement with Project Manager.
Specify that the General Contractor will provide certification that units installed meet the
specified requirements.
Coordinate glass colors for project with the Project Manager prior to submitting the
Schematic Design documents.
Reflective glass, if approved by Project Manager, shall not exceed 35% reflectivity.
Require warranty on insulated units covering seal and against build-up of condensation.
3.14
DIVISION 9 - FINISHES
Topic 625-020-016
Facilities Design Manual
September 2010
Topic 625-020-016
Facilities Design Manual
September 2010
3.15
DIVISION 10 - SPECIALTIES
C-fold or Z-fold paper towel dispensers with integral disposals; surface or semirecessed mounting.
Soap dispensers.
Toilet accessory finishes shall be brushed stainless steel. Finishes shall be coordinated
with each other, door hardware, and plumbing hardware.
Mirrors shall be full width of counter at floating counters or individual over wall mounted
lavatories. Provide warranty against silver spoilage.
_____________________________________________________________________
General Design Guidelines
3-35
Topic 625-020-016
Facilities Design Manual
3.16
September 2010
DIVISION 11 - EQUIPMENT
3.17
DIVISION 12 FURNISHINGS
3.18
3.19
Drop ceiling height shall be 9'-0 minimum. One elevator must have 10'-0"
minimum if separate Service elevator is not provided.
Doors and frames shall be 36" wide center opening with No. 4 satin stainless
steel finish.
Side and rear wall finish shall be plastic laminate with stainless steel handrails.
_____________________________________________________________________
General Design Guidelines
3-36
Topic 625-020-016
Facilities Design Manual
September 2010
Cab height shall be 10'-0" with a 2" x 2" silver anodized aluminum suspended
ceiling grid with satin stainless steel T-bars at 9'-6".
Doors and frames shall be 48" wide center opening with No. 4 satin stainless
steel finish.
Wall and floor finishes must match passenger elevators if in visible proximity of
passenger elevators.
The service elevator shall serve all floors including mechanical or penthouse
floors.
Elevator equipment room walls shall be acoustically insulated and fire-separated from
surrounding spaces.
Refer to Division 23 for HVAC requirements in equipment rooms.
3.19.2 Vibration and Seismic Controls for HVAC Piping and Equipment
Pumps, fans and other equipment subject to vibration shall be checked and tested at
the full set of speed ranges available from the controls. Maximum acceptable vibration
levels shall be specified.
Specify spring-isolated inertia bases for pumps located in off-grade mechanical rooms
and direct mount pump bases on housekeeping pads when located at grade level.
3.20
Topic 625-020-016
Facilities Design Manual
September 2010
3.21
DIVISION 22 - PLUMBING
Topic 625-020-016
Facilities Design Manual
September 2010
Topic 625-020-016
Facilities Design Manual
September 2010
3.22
Evaluate equipment selection block loads and life-cycle cost analyses during the
schematic development stage of the project. Perform Life-cycle analyses in
accordance with the Florida Energy Efficiency Code procedures.
Proposed architectural features shall be the basis of design. Provide an updated HVAC
load and life-cycle cost analyses for any architectural changes that affect the thermal
performance of the building (i.e., changes to wall insulation, site orientation, area of
fenestration, etc.
Design the HVAC system to maintain relative humidity at less than 60%.
Cooling and heating loads shall be based upon the actual intended occupancy and
_____________________________________________________________________
General Design Guidelines
3-40
Topic 625-020-016
Facilities Design Manual
September 2010
internal loads as defined during the schematic design phase. Miscellaneous loads shall
be based upon actual number of computers and other heat-producing appliances such
as refrigerators, copiers, computers, servers, etc. For office space, the occupant density
shall be 250 sq. ft. per person, unless otherwise directed. Consult with the Project
Manager and document the design load parameters on the plans.
Provide HVAC design parameters schedule in the plans at the design development
phase. Specify outdoor design temperatures, indoor temperatures, design humidity
level, occupant density, and any other pertinent data or assumptions that affect design.
Provide a ventilation schedule on the plans to demonstrate compliance with ASHRAE
Standard 62.2004 - Ventilation for Acceptable Indoor Air Quality. A schedule is
required for each building/floor and shall include room number, function, number of
occupants, ventilation rate, ventilation methodology, subtotals, and/or totals, and any
related notes or assumptions. The ventilation design shall utilize the intermittent or
variable occupancy rate, or indoor air quality procedures where allowed in accordance
with the standard. The design shall minimize or eliminate outside air during unoccupied
periods. Utilize CO2 controls or demand-controlled ventilation approaches where cost
effective.
Provide air balance schedule on the plans to demonstrate proper building
pressurization. The HVAC systems shall be designed and controlled to maintain the
building and/or each floor at a slight positive pressure of 3 to 5 percent. The schedule
shall include the room number or name, function, supply, exhaust, transfer and return
air flow rates; and subtotals for each air handler unit and/or floor.
Large conference rooms shall be designed to compensate for the shift in loads in
outside air needs during occupied and unoccupied periods. Use a building energy
management system, switching, or other means to determine occupancy. Do not use
constant-volume systems.
Equipment rooms with transformers totaling 30 KVA or more, or over 4,000 BTU/hr heat
dissipation shall be indirectly air conditioned by one of the following methods, listed
according to preference:
Ducted, parallel-fan variable air volume (VAV) terminal unit to circulate air into
the equipment room from the return air plenum (this method uses the building as
a heat sink)
_____________________________________________________________________
General Design Guidelines
3-41
Topic 625-020-016
Facilities Design Manual
September 2010
Topic 625-020-016
Facilities Design Manual
September 2010
Topic 625-020-016
Facilities Design Manual
September 2010
Controls for central energy plant systems, pumpsand chilled water shall be the same on
multiple buildings.
Require pipe welder certification to be current, within 3 months, and that it covers the
type and position of welds required for the project.
Require hydrostatic tests for hydronic piping systems. Prohibit the use of air or any
other compressible gas as a testing medium.
Include specifications for cleaning and treating hydronic piping systems including chilled
water and hot water systems.
3.22.3 Hydronic Pumps
Provide separate and distinct set of controls, starters, etc for pumps and other items of
equipment intended as backup , or provide an AFD/Starter with A/B switch, as
appropriate; to assure full backup.
Review pumps with speed control to assure that proper cooling and lubrication takes
place at all speeds. Specify the lowest speed on the drawings and/or in the project
manual.
Test pumps and other equipment subject to vibration at the full set of speed ranges
available from the controls. Maximum acceptable vibration levels shall be specified on
the plans.
3.22.4 Metal Ductwork
Design ducts to handle the water column pressure available from the fan motor(s) with
the speed controls, dampers and other pressure controlling devices operating in peakload condition.
Ducts shall be constructed of G-90 galvanized steel sheet.
Specify sealing transverse and longitudinal seams regardless of pressure class.
Specify duct pressure test procedures and duct-pressure testing prior to installing
insulation.
_____________________________________________________________________
General Design Guidelines
3-44
Topic 625-020-016
Facilities Design Manual
September 2010
hours of operation
wet-bulb temperature
Topic 625-020-016
Facilities Design Manual
September 2010
operate the system in accordance with the design intent. The sequence of operations
should address occupied, unoccupied, winter, summer, and Test & Balance (T & B)
operating modes.
The EMCS shall minimize or shut off outside air and eliminate reheat during
unoccupied periods and control humidity during both occupied and unoccupied periods.
Where air flow metering does not exist or other design requirements dictate, provide
CO2 sensing in return-air plenums or ducts on large office buildings and trend this point
to monitor (indirectly) air quality and to activate additional ventilation as required.
Unless specified otherwise, the EMCS shall be fully integrated and include a personal
computer (PC) interface for HVAC systems with 150 tons or more cooling capacity.
Systems with less than 150 tons, or where a budget deficit exists, shall utilize time
clocks and/or programmable unitary controllers. In all installations, the EMCS shall
incorporate stand-alone module system architecture and not be dependent on the
Central Processing Unit (CPU) for routine operations.
The EMCS shall maintain the controlled variables at their set points within the following
tolerances:
Space temperature:
2.00 F
Duct temperature:
2.00 F
Relative humidity:
5%
Pressure differential:
5%
5%
5%
The CPU, PC and related peripheral equipment shall meet industry standards at the
time the controls system contract is executed and be adequate to operate the system in
accordance with the design intent.
Assure the equipment/component I.D. numbers, the building management system I.D.
numbers, and the control systems are the same.
Assure controls for central energy plant systems such as chilled water match and/or
_____________________________________________________________________
General Design Guidelines
3-46
Topic 625-020-016
Facilities Design Manual
September 2010
standardized throughout the facility. Pumps and chilled water controls shall be the same
for multiple buildings, etc.
3.22.8 Axial HVAC Fans
Size and specify fans to provide low noise and vibration levels.
Specify the maximum-acceptable noise and vibration levels on the plans for fans over
five motor horsepower.
3.22.9 Centrifugel HVAC Fans
Fans shall be sized and specified to provide low noise and vibration levels.
Specify the maximum-acceptable noise and vibration levels on the plans for fans over
five motor horsepower.
3.22.10 Air Terminal Units
Specify parallel fan powered VAV boxes with heating type of electric resistance or
hydronic type per LCCA for exterior zones and straight VAV units for interior zones in
office facilities.
3.23
DIVISION 26 - ELECTRICAL
Topic 625-020-016
Facilities Design Manual
September 2010
tester.
Provide an electrical system testing specification. Describe tests to be performed and
acceptance criteria. Provide timely notice to the owner to witness tests and furnish test
results to owner.
Provide maintenance schedules incorporating manufacturer's recommendations.
Maintenance schedules shall address status information on switchgear, replacement of
indicator light bulbs, resetting of targets and testing of relays and controls.
Provide a list of over-current relay settings, ground fault relay settings and settings for
adjustable circuit breakers. Relays shall be tested and the settings verified. Provide
detailed operational parameters and protection with manufacturer's acceptance.
At completion of building construction, verify that the differentiation between normal
power, emergency power, and optional standby power has been maintained at all
levels. Emergency power shall be limited to those devices essential to the operation of
the building under emergency.
Coordinate testing of circuit breakers in the emergency power system and optional
standby system to assure a fault on the optional standby system will trip the correct
circuit breaker and leave emergency power functioning.
Provide comprehensive on-site and factory training on electrical equipment operation
and safety concerns for personnel who will operate the buildings (3 or 4 individuals).
3.23.3 Raceway and Boxes for Electrical Systems
Minimum conduit sizes shall be 3/4" diameter for runs with up to five No. 12 AWG
conductors and diameter for flexible conduit to connect light fixtures.
Metal conduit connections shall be tight to ensure electrical continuity. PVC conduit
connections shall be solvent welded.
Underground high voltage circuits, over 600 volts shall be installed in concrete encased
PVC conduit, type DB, 4" diameter or greater. The top of the concrete envelope shall be
more than 24" below grade.
Rigid galvanized steel conduit or IMC may be direct buried, exposed to damage,
exposed to weather, or cast in concrete.
Conduits concealed in walls or ceilings shall be EMT.
Plastic conduit may be used in lieu of rigid steel conduit in unexposed locations. Rigid
galvanized steel ells and RGS turn-ups above the slab shall be used.
_____________________________________________________________________
General Design Guidelines
3-48
Topic 625-020-016
Facilities Design Manual
September 2010
Flexible conduit and liquid-tight in wet locations may be used for connections to light
fixtures, dry-type transformers, and equipment with noise, vibration, or motion
problems.
Wireways shall be galvanized steel with hinged cover.
Cable trays or J hooks shall be provided for telecommunications systems with 2 or
more entries into communications rooms spaced to prevent crowding. Details on the
plans shall clearly depict the method of installation and a coordinated path for the tray
to follow.
3.23.4 Low-Voltage Electrical Power Conductors and Cables
Conductors shall be stranded copper wire sizes No. 12 AWG and larger.
600-volt insulation for wires and cables shall be type THHN / TWHN.
Insulation for primary voltages over 600 volts shall be type XLP.
Neutrals or equipment grounding conductors #4 AWG and larger may be black
insulated wire identified by white or green tape in lieu of white or green insulation, per
NEC. Phase conductors #8 AWG may be color coded with tape. Apply 3 bands of
colored tape, 3/4" wide and 1" apart with four wraps of tape in each band, at each end
of each wire.
Use the following wire insulation colors, by Voltage:
480/277 volts
brown, orange, yellow
208/120 volts
black, red, blue
Neutral
natural gray
white
Ground
green
green
Phase Conductors
Topic 625-020-016
Facilities Design Manual
September 2010
Boxes for exposed or exterior work shall be aluminum with threaded hubs.
EMT fittings shall be compression type steel fittings.
3.23.7 Wiring Devices
Receptacles shall be commercial grade, NEMA 5-20R, side wired, grounding type.
All branch circuits shall be electrically continuous when any receptacle is removed.
Switches shall be specification grade 125/277 volt 20 ampere, poles as required.
Cover plates shall be standard size plastic with smooth finish.
Color for switches, receptacles, and cover plates shall be selected by the owner.
Special purpose receptacles shall be provided to suit equipment requirements.
3.23.8 Electrical Cabinets and Enclosures
Enclosures and cabinets for electrical equipment shall be welded construction.
3.23.9 Electric Motors
Specify high-efficiency type electric motors.
Motors for VFD service shall be inverter-duty type.
3.23.10 Enclosed Controllers
Specify starters with an H-O-A switch, horsepower rated, with melting alloy thermal
overloads for each pole and auxiliary contacts.
All motor starters in one project shall be products of one manufacturer. When adding to
existing facilities, new motor starters shall match the existing, if possible.
3.23.11 Variable Frequency Motor Controllers
Adjustable Speed Controllers for AC motors may be used in lieu of throttling for control
of airflow or fluid flow. Motors for VFD service shall be inverter-duty type.
_____________________________________________________________________
General Design Guidelines
3-50
Topic 625-020-016
Facilities Design Manual
September 2010
Surge suppressors for control loops for adjustable speed drives shall be provided to
prevent damage from lightning and transferred potentials if the loop extends to another
building or is over 100' long.
3.23.12 Hangers and Supports for Electrical Systems
Use UL approved pillows of fire stop material which can be removed and re-stacked to
allow reuse of the fire stop materials when cables are added to or removed from
penetrations of fire walls.
Conduits, cable trays, boxes and fittings shall be hung from the building structure with
metal supports. No electrical item shall be hung from pipes or ductwork.
3.23.13 Identification for Electrical Systems
Electric panel identifiers shall include the number of the room in which they are located.
Electrical Panels shall have an engraved laminated plastic label attached with glue and
screws with the panel identifier in 1" letters and voltage rating in 2" letters.
Embossed plastic tape labels are not be used.
Panels shall have typewritten directories.
3.23.14 Emergency Power
Emergency generators, when provided, shall be driven by a diesel or natural gas
engine. The generator shall be a brushless design with solid-state exciter.
If an emergency power system is provided, overcurrent coordination shall prevent a
short circuit on any branch circuit from disabling any other emergency branch circuit.
3.23.15 Medium Voltage Electrical Distribution
Medium-voltage equipment (over 600 volts and less than 40,000 volts), if installed
indoors, shall be in a separate, dedicated, locked medium-voltage equipment room.
Outdoor, medium-voltage equipment shall be installed in a pad-mounted, weatherproof,
_____________________________________________________________________
General Design Guidelines
3-51
Topic 625-020-016
Facilities Design Manual
September 2010
locked metal cabinet complying with the National Electrical Safety Code that
completely encloses all terminals and equipment.
Provide landscaping to shield outdoor, medium-voltage installations from view.
3.23.16 Low-Voltage Transformers
Coordinate location of transformers with HVAC equipment.
Dry Type Transformers shall be UL labeled, manufactured with 220O C insulation and
designed for a maximum of 150O C rise above a 40O C ambient temperature.
Provide sound isolation including a neoprene pad under transformer sized for the
weight of the transformer installed and flexible metal conduit for electrical connections.
Aluminum transformer windings may be used.
Autotransformers may be used where appropriate.
Transformers 30 KVA and larger shall be floor mounted.
Ground-bonding jumper, required by NEC 250-28, shall be connected directly to the
"X0" terminal at the transformer.
K-13 Rating transformer shall be used for computers.
3.23.17 Power Factor Correction Equipment
Power factor correcting capacitors shall not cause more than 10% overvoltage during
light load periods.
Automatic switching may be provided to prevent overvoltage.
3.23.18 Grounding and Bonding for Electrical Systems
Each building shall have a copper No. 2 AWG minimum ground ring per NEC 250-81.
The ground ring may be installed in footings or grade beams as a concrete encased
electrode encircling the building. Splices and connection to the ground ring shall be
cadwelded.
_____________________________________________________________________
General Design Guidelines
3-52
Topic 625-020-016
Facilities Design Manual
September 2010
Structural foundation drawings shall include ground rings and details if conductors
penetrate concrete.
Provide a detailed grounding plan showing all ground electrodes, grounding electrode
conductors, bonding to other grounded systems, grounding for separately derived
systems and ground connections for communications equipment.
An equipment-grounding conductor shall be installed in every feeder and branch circuit
conduit and raceway.
Equipment grounding conductors installed in metal conduits or raceways shall be
bonded to that conduit or raceway at both ends of the run, to minimize ground
impedance.
A separate grounding bus, a "ground source," shall be installed on the wall of a
communications room but not in an electrical room. (An electrical room has the
equipment grounding bus inside the panelboards to comply with NEC.)
Medium-voltage, outdoor, pad-mounted equipment shall be grounded to a ground ring
3' from the pad and 3' below grade with 20' x 5/8" copperweld ground rods at each
corner of the ground ring with 2 ground electrode conductors going to opposite sides of
the ring. The ground ring shall be the same size as the grounding electrode conductor
and No. 2 min. PVC conduits may be cast into the pad for the ground electrode
conductor.
Main ground shall be bonded to main cold water pipe and building reinforcing steel.
3.23.19 Low-Voltage Electrical Distribution
Short circuit currents for the service entrance, including motor contributions, shall be
listed on the electrical 1-line diagram showing the service entrance.
A load calculation complying with NEC Article 220 shall be included on the single-line
diagram showing the service entrance and shall be used to size the service entrance
equipment. Service entrance equipment shall not exceed NEC by more than 50%.
The "six switch" rule for service disconnects may be used to avoid 480-volt breakers
with GFI protection.
Buses shall be copper.
_____________________________________________________________________
General Design Guidelines
3-53
Topic 625-020-016
Facilities Design Manual
September 2010
Spare fuses mounted in a wall cabinet shall be provided for fusible devices.
Analog voltmeters and ammeters shall not be installed in service equipment.
Instrumentation for building automation systems may be installed on service entrances.
Service entrances for 600 volts or less shall have surge suppressors with shunt type
protection and high-energy metal oxide varistors as the primary suppression element.
The metering systems used for the electrical distribution equipment may include phase
voltage, phase amperes, KW demand peak retained and current value, KWH totalizing.
NOTE: The meter accuracy is for billing purposes on KWH and 0.5% on all
others for the full range of the CT and PT ratings. The metering shall be
electronic with the capability to be hot linked via FCN/WWW. These meters may
be connected to the building management system, depending on the size of the
building.
3.23.20 Low-Voltage Circuit Protective Devices
Safety switches shall be heavy duty, quick-make, quick-break, horsepower-rated in an
appropriate NEMA enclosure.
3.23.21 Panelboards
Panelboards shall be dead-front with bolt-on thermal magnetic circuit breakers with
copper buses.
A panelboard shall have a main breaker if it is fed from a panel in another room or if a
main breaker is required by code.
All panel boards on one project shall be the product of one manufacturer. When adding
to an existing facility, new panels shall match the existing.
Provide 25% spares in 120/208-volt and in 277/480-volt panelboards.
Switchboard is to be service entrance labeled, dead-front, metal enclosed, front
connected, free standing with ground fault protection for all devices rated 480 volts and
1,000 amperes or greater.
_____________________________________________________________________
General Design Guidelines
3-54
Topic 625-020-016
Facilities Design Manual
September 2010
Main device shall be circuit breaker or fusible bolted pressure contact switch.
Distribution devices shall be group mounted fusible switches or molded case circuit
breakers.
Fusible devices shall have spare fuses mounted in a wall cabinet.
Panelboards servicing computers shall have the neutral service conductor oversized by
200%.
All branch circuits serving computers shall have a separate neutral.
3.23.22 Interior Lighting
Lighting loads shall not exceed 1.5 watts per square foot in any room. The owner may
approve exceptions for rooms with ceiling heights above 12' and other special
applications.
A life cycle cost analysis shall be submitted if occupancy sensors, photocells, or other
energy conservation devices are specified.
Interior lighting levels shall be the lesser of the average maintained levels listed in the
IES Handbook or the levels listed below:
50 foot-candles
Conference rooms
30 foot-candles
Corridors
10 foot-candles
Toilet rooms
20 foot-candles
Storage rooms
20 foot-candles
General office space shall be lighted via standard 2' x 4' 2 or 3-lamp fluorescent
parabolic lighting fixtures. Indirect lighting shall be provided for PC screens, training
rooms, conference rooms and offices for visual comfort.
Use single-lamp 1 x 4 fluorescent fixtures in corridors with long axis of fixture aligned
with the long dimension of the corridor.
_____________________________________________________________________
General Design Guidelines
3-55
Topic 625-020-016
Facilities Design Manual
September 2010
Toilet rooms may be lighted with a combination of any or all of the following:
Recessed 2' x 4', two-lamp fluorescent troffer with 0.125" acrylic prismatic lens.
Ballasts shall be electronic, operating at 20-megahertz min., with less than 10% total
harmonic distortion, with 5-year warranty.
Semi-specular louvers and reflectors shall have fingerprint and dust-resistant finish.
The Project Manager shall approve use of 2' x 4' fluorescent fixtures.
Exit lights shall have white poly carbonate, easy snap housing with 6" stroke red letters
and LED lamps with a 25-year warranty.
Energy efficient lamps shall be installed where economically feasible.
Incandescent lamps, including tungsten halogen lamps, shall only be used for seldomvisited areas like elevator pits and attics, and in explosion proof fixtures. The use of
compact fluorescent lamps in lieu of incandescent lamps is encouraged.
Fluorescent lamps shall be energy efficient types and all fluorescent lamps of one size
shall be the same color. The preferred lamp is T8 32 watt 800 series CRI of 80 to 85
and color temperature 4100 Kelvin.
3.23.23 Roadway and Parking Lighting
Coordinate selection of light poles style, color, and luminaries with the Project Manager.
Provide a foot-candle illumination plan for the parking areas and all major public
walkways adjacent to the building.
The maximum variation of exterior lighting from maximum to minimum is ten to one
(10:1). The minimum allowable exterior light levels are:
Building entrances
4.0 foot-candles
_____________________________________________________________________
General Design Guidelines
3-56
Topic 625-020-016
Facilities Design Manual
September 2010
Arterial roads
1.2 foot-candles
Local roads
1.0 foot-candle
Parking areas
1.0 foot-candle
Sidewalks
1.0 foot-candle
Site lighting and signage shall be controlled by a photocell and timer located within the
buildings, or by the Building Management System.
The site lighting design for roadways, parking and sidewalks shall have light poles of
the type, height and the number of fixtures that yield the lowest life cycle cost.
Entry doors shall be illuminated by a light fixture in the soffit above the door.
Coordinate the use of bollards with lights or other low level lighting fixtures with the
Project Manager.
3.23.24 Emergency Lighting
Battery pack lighting and emergency standby are not acceptable unless pre-approved.
Emergency generators/distribution systems are the preferred method.
3.23.25 Classified Location Lighting
Explosion proof fluorescent light fixtures using 48" T8 or T12 lamps are not acceptable.
Use halogen, high-intensity discharge (HID), or compact fluorescent (CFL) lamps as
indicated by life cycle cost analysis.
Vandal-resistance light fixtures shall be supplied as required by the program.
3.23.26 Transient Voltage Suppression for Low-Voltage Electrical Power Circuits
Transient voltage surge suppression (TVSS) system shall be provided at all branch
circuit panelboards. The surge suppression system shall start at the main distribution
panelboards and improve in quality and class at each point. The state will provide the
suppression devices at the point of use.
_____________________________________________________________________
General Design Guidelines
3-57
Topic 625-020-016
Facilities Design Manual
September 2010
TVSS mounting and wiring shall conform to the manufacturers instructions. Provide a
suitable circuit breaker. Wiring shall take the most direct route from TVSS to ground
bus.
Class "C" surge protection on the primary panel and class "B" surge protection on
breaker panel may be provided for both convenience power as well as lighting power
circuits. Also, Class A surge protection may be used on actual loads.
Secondary service entrance shall be provided with a surge suppressor with shunt type
protection circuitry, and high energy metal oxide varistors as the primary suppression
element.
The TVSS system shall be designed, manufactured, tested and installed in accordance
with current adopted editions of the following:
ANSI / IEEE
NEMA Standards
Topic 625-020-016
Facilities Design Manual
September 2010
Flag poles shall be aluminum and shall be grounded with a No. 2 bare copper cable
electrically continuous from the pole grounding lug to a 20 x 5/8 copperweld ground
rod driven until the top of the rod is 24" below grade.
Underground circuits installed in PVC conduit or direct buried, may be protected from
lightning by installing a bare copper counterpoise, solid No. 4 wire or larger, laid 6"
above the PVC conduits or 6" above direct buried cable or on top of the concrete
envelope, if used, with one counterpoise per duct bank. Bond the counterpoise to a
building ground electrode or a driven ground rod at each end.
Provide surge protection for any wiring that connects to building.
3.23.28 Communications
Provide a premise distribution system to serve as a vehicle for transport of data and
voice telephone signals throughout the building from designated demarcation points to
outlets located at various desks, workstations and other locations.
Each office location shall contain the following systems outlets minimum:
Coordinate outlet locations for best use in each area. Portable or open space
furnishings shall use outlet drop systems designed for use therewith.
3.23.29 Communications Horizontal Cabling
Use the following standards for Telecommunications:
_____________________________________________________________________
General Design Guidelines
3-59
Topic 625-020-016
Facilities Design Manual
September 2010
UL Underwriter's Laboratories.
o CT faceplates
o CT4-FP-(XX) - Single gang plastic faceplate for one coupler
o CT8-FP-(XX) - Double gang plastic faceplate for four couplers
o CT-MFP-(XX) - Modular furniture adapter
3.23.30 Digital, Addressable Fire-Alarm System
Provide a complete combination manual automatic, zoned, supervised fire alarms
system capable of interfacing with the existing Capitol Security Office Fire Command
Center and connected to the local fire department.
_____________________________________________________________________
General Design Guidelines
3-60
Topic 625-020-016
Facilities Design Manual
September 2010
3.24
If water from a local utility is used for the irrigation system, separate irrigation
water meters shall be installed to avoid sewer charges for water used.
Provide backflow preventers that comply with local regulations. Backflow valves
shall be screened from public view. Verify that the use of backflow preventers in
conjunction with pop-up style sprinkler heads conforms with local ordinances.
_____________________________________________________________________
General Design Guidelines
3-61
Topic 625-020-016
Facilities Design Manual
September 2010
All irrigation piping shall be PVC. Main lines and lateral lines shall be schedule
40 PVC piping with solvent welds.
Use pop-up style heads in lawns and riser mounted heads in shrubbery.
Provide additional shrub and groundcover planting in the area between the
parking lot curb and the sidewalk, rather than a single row of shrubs to meet the
landscape screen requirement.
Have barriers erected around protected trees before construction activity begins.
Sod will be flush with the finish elevation of the sidewalks and concrete curbs, to
avoid water ponding on walks.
All plant material used in landscaping shall be healthy, disease free and pestfree. Use Florida #1 or better plant material, as described in "Grades and
Standards for Nursery Plants" published by the Florida Department of
Agriculture.
Establish a guarantee period of 365 days after the warranty maintenance period
ends in which the Contractor will guarantee free replacement (labor and
materials) of any plant material that does not survive. Interim 90-day inspections
by the Construction Engineer shall take note of all vegetation, materials and
methods.
_____________________________________________________________________
General Design Guidelines
3-62
Topic 625-020-016
Facilities Design Manual
September 2010
3.24.3 Plants
Have barriers erected around protected trees before construction activity begins.
Mulch, applied at the time of planting, should have a minimum depth of 3".
Specify plant material used in landscaping to be healthy, disease free and pestfree. Use Florida #1 or better plant material, as described in "Grades and
Standards for Nursery Plants" published by the Florida Department of
Agriculture.
Wildflower mixes should be of low growing varieties, generally less than 16"
height.
Establish a guarantee period of 365 days after the warranty maintenance period
ends in which the Contractor will guarantee free replacement (labor and
materials) of any plant material that does not survive. Interim 90-day inspections
by the Construction Engineer shall take note of all vegetation, materials and
methods.
_____________________________________________________________________
General Design Guidelines
3-63
Topic 625-020-016
Facilities Design Manual
September 2010
_____________________________________________________________________
General Design Guidelines
3-64
Topic 625-020-016
Facilities Design Manual
September 2010
CHAPTER 4
FACILITY-SPECIFIC GUIDELINES
TABLE OF CONTENTS
4-1
4-2
4-3
4-4
4-5
4-6
4-7
4-8
4-9
4-10
4-11
4-12
4-13
4-14
4-15
4-16
4-17
4-18
4-19
4-1
Topic 625-020-016
Facilities Design Manual
4-1
September 2010
AUTO SHOPS
Auto Shops are facilities where Department vehicles are serviced and repaired. They
generally have service bays with vehicle lifts and/or service pits. Mechanical systems
included in most Shops are: high-pressure pneumatic systems for operating airpowered tools, high-pressure hydraulic systems for operating the lifts, low-pressure
hydraulic systems for dispensing vehicle lubricants, vehicle exhaust evacuation
systems, etc. Each of these will have its own power distribution system, compressor,
generator, piping system, etc. Generally not mechanically cooled, auto shops will
usually have passive and power ventilation, and radiant heating systems.
The Auto Shops are business and industrial occupancies and may be comprised of a
large vehicle service area (separate facilities with capability to service/repair small
vehicles (cars, pickups, vans, etc.) and large vehicles (dump trucks, tractors, bulldozers, etc.) with adjacent offices and storage facilities.
Some Auto Shops may have refueling facilities as a part of the building function.
Others may be a part of a Shop and Warehouse building. The building structure is
generally either concrete masonry unit or pre-engineered rigid-frame metal
construction.
While some Auto Shops may have underground hydraulic lifts, it is recommended that
new facilities be designed with aboveground vehicle lifts.
4-2
Topic 625-020-016
Facilities Design Manual
4-2
September 2010
CREW BUILDINGS
Roof
Common structural systems (recyclable materials)
Light-gauge metal trusses
Pre-engineered metal building
Designed for 20 year life with warranty
Metal roofing system over substrate
Few penetrations
Well ventilated
Avoid roof slopes of less than 3" to12"
4-2.4 Finishes
Floors in restrooms, crew rooms and offices shall be vinyl tile. All others floors
shall be designed for durability and low (i.e., epoxy coatings or hardened
concrete).
Walls separating interior crew storage areas shall be chain link fencing or CMU
Exterior walls shall be designed for durability, vandal-resistance and low
maintenance (i.e., CMU, stucco, metal panels).
Interior walls of crew rooms, and offices shall be 5/8" gypsum wallboard with
satin finish latex paint
Interior walls of restrooms and dressing rooms to be ceramic tile over 1/2"
cement board or epoxy coated CMU
Facility Specific Guidelines
4-3
Topic 625-020-016
Facilities Design Manual
September 2010
4-2.5 Ceilings
Ceiling in storage areas shall be chain link fencing, insulation to be installed
along roof structure and encapsulated. Ceilings in restrooms, crew rooms and
offices shall be 2'x2' acoustical tile with a ceiling height of 8'.
4-2.6 Office space
Offices shall be approximately 140 s.f. with provisions for mechanical, electrical,
and data rooms.
4-2.7 Crew rooms
Provide a crew room for each crew. Room shall include one locker for each
anticipated crew member. Room should be twice as large as corresponding crew
storage area.
4-2.8 Crew storage
Each crew storage area is to open to the exterior of building and be located on
ground floor. Provide long overhang at exterior doors to facilitate
loading/unloading of vehicles in inclement weather.
4-2.9 Rest rooms/dressing rooms
Provide male and female dressing rooms including a locker for each anticipated
crew member. Include two or three showers in each rest room/dressing room.
4-4
Topic 625-020-016
Facilities Design Manual
September 2010
4-5
Topic 625-020-016
Facilities Design Manual
September 2010
4-6
Topic 625-020-016
Facilities Design Manual
4-3
September 2010
12
2"x4" Al um
i numFram
i ng
w/ Kynar 500 Fi ni sh
Sam
pl e Text t o Vary by Loc
t yp.
D
oubl e-Si ded D
i rect ory
Top Il l um
i nat ed Suspended
Bet ween 4x12 Al um
. Post s
D
i rect ory = 45" x 74" (36" x 70
Al um
i numFram
e w/ Kynar 500 Fi n
Cl ear O
peni ng Si ze = 36"h x 70
G
l azi ng t o be Lexan, or equ
4"x12" Al um
i numPost s
w/ Kynar 500 Fi ni sh
30x36
Fl ori da m
ap
Front
30x36
Fl ori da m
ap
Back
Brochure Rack
2"x4" Al um
i numFram
i ng
w/ Kynar 500 Fi ni sh
open
4"x12" Al um
i numPost s
w/ Kynar 500 Fi ni sh
D
oubl ed U
nder D
i rect ory
5" Concret e Sl ab
w/ 6x6 #10/ 10 wwm
End Elevation
SCALE:
Side 1 Elevation
SCALE:
4-7
Topic 625-020-016
Facilities Design Manual
4-4
September 2010
MAINTENANCE/CONSTRUCTION YARDS
These Operations Centers are comprised of facilities to house the field operations
functions of the Department. There are main yard and sub-yards. They may include
such facilities as: offices, storage facilities, laboratories, shops (carpenter, metal, and
vehicle), warehouses, crew buildings, etc.
Office buildings
o
Maintenance offices
o
Construction offices
Vehicle and equipment storage
Materials storage
o
open bins
o
covered sheds
Testing labs
Mini-service buildings
o
vehicle repair
o
fuel station
Open canopies
o
fuel dispensing
Fuel storage facilities (tanks)
o
above-ground
o
in-ground
Hazardous materials storage buildings
o
site-built
o
pre-engineered
Vehicle wash facilities
o
vehicle pad
o
water supply
o
drainage/filtration
Ease of expansion
Design utilities infrastructure to allow for future expansion:
o
Water supply lines stub-ups, capped off
o
Sanitary sewer piping stub-ups, capped off
o
Electrical panels sized to allow additional circuits / fixtures
4-8
Topic 625-020-016
Facilities Design Manual
September 2010
4-4.2 Structure
4-4.3 Roof
4-4.4 Finishes
Floors in restrooms, crew rooms and offices shall be vinyl tile. All others floors
shall be designed for durability and low (i.e., epoxy coatings or hardened
concrete).
Walls separating interior crew storage areas shall be chain link fencing or CMU
Exterior walls shall be designed for durability, vandal-resistance and low
maintenance (i.e., CMU, stucco, metal panels).
Interior walls of crew rooms and offices shall be 5/8" gypsum wallboard with satin
finish latex paint.
Interior walls of restrooms and dressing rooms to be ceramic tile over 1/2"
cement board or epoxy coated CMU.
4-4.5 Ceilings
Ceilings in storage areas to be chain link fencing, insulation to be installed along
roof structure and encapsulated. Ceilings in restrooms, crew rooms and offices
to be 2'x2' acoustical tile with a ceiling height of 8'.
4-9
September 2010
NORTH ELEVATION
WEST ELEVATION
EAST ELEVATION
SOUTH ELEVATION
Topic 625-020-016
Facilities Design Manual
4-10
UP
ASSIST
MAINT
ENG
ENG
MMS
FILE
ROOM
FISCAL
CLERK
CORRIDOR
ASSIST
MAINT
ENG
CONTRACT
INSPECTORS
CONT
ENG
OFFICE
MANAGER
COPY
/FAX
FIELD PERMIT
ENG
ENG
SENIOR
CLERK
ELECTRICAL
PERMIT
INSPECTORS
DATA
ENTRY
RECEPTION
DATA INPUT/MMS
CORRIDOR FEC
CONFERENCE
WORK/STORAGE
ROOM
AREA
STORAGE
ROOM
ASSIST
MAINT
ENG
CORRIDOR
MAINT
ENG
CORRIDOR
COMMUNICATION
UP
CLOSET
OFFICE
CORRIDOR
DATA
ROOM
COMM
ROOM
OFFICE
ENTRY
LOBBY
SEC
SPEC
E-III
E-IV
E-I
(6) TECH'S
CORRIDOR
WOMEN
CUST.
SEC/
RECEPTION
ELEV
COPY/FAXPE-III
EQ
ROOM
MEN
CORRIDOR
E-I
E-I
CCEI
PE-I
MECHANICAL
E-IV
E-II
PE-II
CRS
(6) TECH'S
CORRIDOR
MEETING/
TRAINING
CONFERENCE
ROOM
CORRIDOR
ELECT
STORAGE
STORAGE
UP
Topic 625-020-016
Facilities Design Manual
September 2010
4-11
Topic 625-020-016
Facilities Design Manual
4-5
September 2010
MATERIALS LABS
Materials laboratories consist of Major labs (i.e., the State Materials Office in
Gainesville, which researches and tests a wide variety of materials used on Department
projects) and Minor labs (i.e., District Materials Labs, which may conduct testing on
materials used on specific projects).
Laboratories include complex and comprehensive facilities and systems to test
physical, chemical and environmental qualities of a wide range of materials.
For Example: the State Materials Laboratory in Gainesville includes:
soils lab
bituminous lab
corrosion lab
nuclear equipment
accelerated pavement testing facility
administrative offices
4-12
Topic 625-020-016
Facilities Design Manual
September 2010
UP
LOG/INSTANDING
MECH/ELEC
WOMEN.
JAN
MEN
CURING
CON
CURING
METALSPREP.
METALSPREP.
AUTOCLAVE
SMPLPREP.
METALS TESTING
4-13
Topic 625-020-016
Facilities Design Manual
4-6
September 2010
OFFICE BUILDINGS
Office buildings house the administrative functions of the Department at multiple levels.
Some are stand-alone facilities and others may be part of a campus of buildings serving
multiple functions.
Large
o Central office
o District headquarters
o Urban offices
Small
o Regional planning offices
o Maintenance/Construction Offices
o Maintenance offices
o Construction offices
o Portable offices
For large office buildings, staff areas shall be developed with offices along the exterior
wall and around the interior core. This leaves an open area for modular
workstations/systems furniture. The following are the components of the user area
interior space plan. Coordinate structural bay sizes and layouts with office sizes and
layouts.
Systems furniture:
Standard Office:
Supervisor Office:
Conference Room:
4-14
Topic 625-020-016
Facilities Design Manual
September 2010
4-15
Topic 625-020-016
Facilities Design Manual
4-7
September 2010
Picnic shelters are to be placed at interstate rest areas and welcome centers. Typically,
at least 2 large shelters and 6 small shelters are placed at each facility. This may be
increased or decreased based on needs at the particular project site. At least one
shelter of each size will be planned to accommodate persons with disabilities.
Shelters may be placed at other public-access facilities and at Department offices and
yards. They come in two sizes:
4-16
Topic 625-020-016
Facilities Design Manual
September 2010
E
S
E
L
Facility Specific Guidelines
4-17
Topic 625-020-016
Facilities Design Manual
4-8
September 2010
4-8.1 References
AISC - Specification for Structural Steel for Buildings -Allowable Stress Design
and Plastic Design.
AISC - Quality Certification Program, Category MB.
ASTM A36/A36M - Structural Steel.
ASTM 123 - Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products.
ASTM 153 - Zinc Coating (Hot-Dip) on Iron and Steel Hardware.
ASTM A307 - Carbon Steel Bolts and Studs, 60,000 psi Tensile strength.
ASTM A325/A325M - High Strength Bolts for Structural Steel Joints.
ASTM A446/A446M - Steel Sheet, Zinc-Coated (Galvanized) by the Hot-Dip
Process, Structural (Physical) Quality.
ASTM A490/A490M - Heat Treated Steel Structural Bolts, Classes 150 ksi
Tensile Strength.
ASTM A500 - Cold Formed Welded and Seamless Carbon Steel Structural
Tubing in Rounds and Shapes.
ASTM A501 - Hot-Formed Welded and Seamless Carbon Steel Tubing.
ASTM A525/A525M - Steel Sheet, Zinc-Coated (Galvanized) by the Hot-Dip
Process.
ASTM A529/A529M - Structural Steel with 42 ksi Minimum Yield Point (1/2
maximum thickness).
ASTM A572/A572M - High-Strength Low-Alloy Columbium-Vanadium Steels of
Structural Quality.
ASTM C665 - Mineral Fiber Blanket Thermal Insulation for Light Frame
Construction and Manufactured Housing.
ASTM A792/A792M - Steel Sheet, Aluminum-Zinc Alloy Coated by the Hot-Dip
Process.
ASTM C991 - Flexible Glass Fiber Insulation for Pre-Engineered Metal Buildings.
ASTM C1107 - Packaged, Dry, Hydraulic-Cement Grout (Non-shrink).
AWS A2.0 Standard Welding Symbols.
AWS D1.1 - Structural Welding Code - Steel.
MBMA (Metal Building Manufacturers Association) - Metal Building Systems
Manual.
SSPC (The Society for Protective Coatings) - Steel Structures Painting Manual.
SSPC - Paint 20 Zinc Rich Coating.
Building Materials Directory - Roof Deck Construction.
4-18
Topic 625-020-016
Facilities Design Manual
September 2010
Design members to withstand dead load, and design loads due to pressure,
suction and uplift of wind calculated in accordance with Building Code. At a
minimum, design load shall be I-90 (110 mph wind speed).
Design exterior wall and roof system to withstand imposed loads with no more
than 1/180 deflection of span.
Size and fabricate wall and roof systems free of distortion or defects detrimental
to appearance or performance.
Design structural components, develop shop drawings, and perform shop and
site work under direct supervision of a Professional Engineer experienced in
structural design of this work and licensed in the State of Florida.
4-8.4 Warranty
4-19
Topic 625-020-016
Facilities Design Manual
September 2010
Fabricate members in accordance with AISC Specification for plate, bar, tube,
or rolled steel shapes.
Anchor Bolts: Formed with bent shank, assembled with template for casting into
concrete.
Siding: Minimum 0.015 metal thickness, flat profile, 2 deep, lapped V edges,
fitted with continuous gaskets.
Liner: Minimum 0.015 metal thickness, flat, perforated profile, lapped V edges
(fitted with continuous gaskets).
Girts/Purlins: Rolled formed structural shape to receive siding, roofing and liner
sheet.
Internal and External Corners: Same material, thickness and finish as adjacent
material, profile brake formed to required angles.
Flashing, Closure Pieces, Fascia, Infills, Caps: Same material and finish as
adjacent material, profile to suit system.
4-20
Topic 625-020-016
Facilities Design Manual
September 2010
Form gutters, downspouts and scuppers to collect and remove water. Fabricate
with connection pieces.
Form sections in maximum possible lengths. Hem exposed edges. Allow for
expansion at joints. Fabricate support straps of same material and finish as
roofing metal, color as selected.
4-8.10 Finishes
4-21
Topic 625-020-016
Facilities Design Manual
4-9
September 2010
REFUELING STATION
The Department's Maintenance Yards usually have facilities to refuel state vehicles.
These refueling stations are mini-gas stations that may also offer limited vehicle service
to state vehicles. Below is a sample layout for a facility that offers self-service fuel only.
Slave pumps may be used to allow personnel to fill saddle tanks without moving vehicle
and re-entering TRAX system information.
GRASS
OWNER
TRAX System
WOMEN'
Slave pump
GAS
STORAG
Main/Master pump
MEN'S
GRASS
OWNER
FLOOR PLAN
ELEVATION
PREFINISHED STANDING SEAM
METAL ROOF (TYP)
8x8x16 CMU (PAINTED),
(SHADING INDICATES DIFFERENT
COLORED PAINT)
EXPOSED RIGID STL FRAME
6'-0"
0'-0"
0'-0"
REF FIN FLR
ELEVATION
4-22
Topic 625-020-016
Facilities Design Manual
September 2010
Site Prototypes: Two concepts are described. Amenities for both include: auto,
RV and truck parking; site lighting; on-site or off-site (preferred) water and waste
water utilities; open layout for security; expansion capability; ease of patrol; easy
access; residential scale; pet walks; dumpster storage; lawn equipment storage,
etc.
Concept 1: - Automobile parking in front
- Truck / RV parking in rear
- Building between parking
Concept 2: - All parking in rear
- Building closest to roadway
o Site Concept 1: This is similar to the way existing rest area facilities have
been planned in Florida, except the auto and truck parking have been
switched. The reasoning for switching the parking is to provide a more inviting
4-23
Topic 625-020-016
Facilities Design Manual
September 2010
residential scale to the site. Many travelers may be turned off by the up-front
presence of a large number of commercial vehicles. Large trucks also screen
the building, reducing visibility from the roadway. The truck parking area
tends to be dirtier and smellier (nature of diesel fuel and exposed chassis
elements). Placing truck parking in the rear minimizes the impact of these
vehicles, improving the image of the rest area.
o Site Concept 2: This concept further minimizes the impact of the parking on
the building image as seen from the roadway. All parking is in the rear. The
building is closest to the roadway, so it is the first part of the rest area to be
seen upon approach.
There are advantages to using Site Concept 2 when compared to Site Concept 1:
some operational, some related to design and construction.
Operational:
o Easier for security staff to patrol.
o Unidirectional view to/from buildings.
4-24
Topic 625-020-016
Facilities Design Manual
September 2010
Design/construction:
o 20-30% less pavement.
o 20-40% less ROW depth.
o 50% less pedestrian facilities.
o Simpler drainage system.
Small:
(basic)
Large:
(common)
Men - 32 fixtures
Women - 48 fixtures
Family - 4 restrooms
Building Costs: It is estimated that the building component of a rest area would
cost approximately $175-225 per square foot (this could be higher: typically, the
more rural the location, the greater the cost). Costs are based on indoor heated
and cooled gross floor area, plus covered outdoor areas such as courtyards, roof
overhangs and picnic pavilions.
Building Capacity: The building sizes were determined in consultation with the
Department Statistics Office. We reviewed the 20-year traffic projections Average Daily Traffic, (ADTs) for I-4, I-10, I-75 and I-95. We estimated the 40year ADTs based on projections of past and present growth. Using the
Departments Rest Area Facilities Computation Form, we calculated the
number of toilet fixtures needed for the mens and the womens restrooms. This
process takes into account the States potty parity requirements for Assembly
Occupancies (due to occupant load, rest areas are classified as Assembly Use
Business Occupancies.)
It has been projected that, within 20-40 years, interstate traffic will dictate a large
facility for all rest area sites. The large prototype is sized to accommodate up to
70,000 vehicles ADT. By comparison, the small facility will accommodate up to
4-25
Topic 625-020-016
Facilities Design Manual
September 2010
35,000 vehicles ADT. It has been further determined that, if the traffic is greater
than this, the region around the rest area would be so urbanized, (i.e., local
traffic that would not normally use a rest area), as to probably not require the
presence of a rest area (potential for future closures?). Private facilities in the
area could accommodate the needs of the traveling public, eliminating the need
for a public rest facility.
Picnic Pavilions: The rest area buildings described below are shown with the
option of attaching picnic pavilions to the ends of the buildings, or placing them
around the building (the latter is present practice). Attaching them would provide
space for 8-12 picnic tables in close proximity to amenities and security.
Attaching them to the building would more easily facilitate expansion of a small
building into a large building (roof, floor and utilities would be in the original
construction of the small). The size of the attached pavilion is equivalent to one
module of expansion.
The following describes the basic requirements of each of the facility types: small
and large. The module of expansion is equivalent to the heated and cooled area
of the small facility, less the vending and security office - approx. 6,800 s.f. If a
facility is planned and constructed using the modular growth precepts (i.e.,
infrastructure for expansion already in place), the cost to expand a small facility
into a large facility could be greatly reduced. It should cost 1/3 to 1/2 less to
construct an addition to an in-place infrastructure than to construct a full addition:
a potential savings of $0.6 - $1.0 million per building, per addition.
o Small Building: With a total of 16 mens and 24 womens fixtures, plus 4
family restrooms, the small building would be suitable for low to medium
capacity highways such as I-10 or I-275, and portions of I-75 and I-95.
Floor Area:
Roof Area:
Expected costs:
o Large Building: With a total of 32 mens and 48 womens fixtures, the large
building would be used for the high capacity highways such as I-4, 1-75 or I95, or as an ultimate expansion capability in the future.
4-26
Topic 625-020-016
Facilities Design Manual
September 2010
Floor Area:
Roof Area:
Expected costs:
The building construction costs would be approximately the same whether the picnic
pavilions are attached to the buildings or are detached and scattered around the site.
Either way, we would likely construct picnic facilities of essentially the same area at
about the same cost. The real savings would come when the small building is
expanded into this area to make the large building.
4-10.5 Rest Area Facility Standards
Building Facilities:
o Equal accessibility for men and women
similar proximity to restroom facilities from all approaches
o Facilities to be model of accessibility for person with disabilities
family restrooms
primary accessible stalls
alternate accessible stalls
adaptable standard stalls
access to buildings and picnic pavilions
access within buildings
communications
signage
phones
emergency stations
o Provisions for potty parity
business occupancy - assembly use
3 womens toilets for 2 mens toilets/urinals
o Modular facilities design
small facility is module of expansion
utilities infrastructure in place for expansion
water supply lines stub-ups, capped off
sanitary sewer piping stub-ups, capped off
electrical panels sized to allow additional circuits / fixtures
o Picnic pavilions sized to expand into
foundation and slab as expansion module
roof structure allows expansion
walls design to provide knock-outs for doors, etc.
4-27
Topic 625-020-016
Facilities Design Manual
September 2010
Structure:
o Structural systems shall be designed for worst-case structural conditions,
wind loads, soil conditions, etc.
o In coastal areas/corrosive environments, consider using non-corrosive
materials (i.e., concrete, CMU), where feasible.
o Foundation and Floors shall be slab on grade w/monolithic or strip footings.
o Walls and columns shall be concrete masonry unit (CMU) or reinforced
concrete with brick veneer. Coordinate with the Project Manager.
Roof:
o Common structural systems (recyclable materials).
light-gauge metal trusses
wood trusses
fire ratings
o Decorative metal or wood structure at courts and picnic pavilions
similar to Polk Co., I-4 - steel
similar to Collier Co., I-75 (Alligator Alley) - wood
Finishes:
o Floors designed for durability and ease of maintenance
floor tile, brick pavers, epoxy coatings, etc.
non-slip surfaces
o Walls designed for durability and vandal-resistance requiring minimal
maintenance.
exterior walls of brick, CMU, stucco, etc. w/graffiti-resistant coatings
interior walls of tile, brick, CMU, plaster, etc.
epoxy coatings on exposed CMU, plaster, etc.
o graffiti resistance
o ease of cleaning
fire ratings
o Ceilings designed for durability and minimal maintenance
plaster, epoxy coatings, etc.
fire ratings
o Roof designed for 20 year life and warranty
metal roofing system over substrate
few penetrations
well ventilated
4-28
Topic 625-020-016
Facilities Design Manual
September 2010
Restrooms General:
Out-swinging entry doors or no entry doors.
Water closet number determined by 20 year projected ADTs.
Toilet fixtures to be commercial elongated ceramic w/1.6 gal/flush-valves.
Urinals to be commercial elongated ceramic w/1.0 gal/flush-valves.
Lavatories to be accessible commercial ceramic (not extended hospital type).
Automatic sensors/hands-free operation for urinals, lavatories and hand
driers.
o Direct access to staff areas for maintenance/cleaning.
o Standard toilet stalls and urinals w/screens.
Standard stalls sized to be adaptable to alternate accessible stall
Solid phenolic or textured stainless steel partitions
Open tops and bottoms for safety and ease of cleaning
Solid core doors w/ textured stainless steel finish
Stainless steel commercial lever door hardware, w/occupied indicators
Hollow metal door frames w/ epoxy finish
o
o
o
o
o
o
o Accessible stalls
Primary stalls for wheelchair users
o Raised toilet seat
o Grab bars at side and rear of toilet
o Lavatory in stall
o Flush-valve levers on open side nearest lavatory
o Paper towel dispenser and waste receptacle
o Hand drier in stall
Alternate stalls for users of other mobility aids
o Raised toilet seat
o Grab bars each side of toilet
o Urinal screens
4" CMU or reinforced concrete partitions w/ tile finish
open tops and bottoms for safety & ease of cleaning
Mens Restroom:
o Toilets in stalls described above
o Urinals to make-up 2 of required fixtures
o Primary accessible stalls located closest to the entry
4-29
Topic 625-020-016
Facilities Design Manual
o
o
o
o
o
Family Restroom:
o
o
o
o
o
o
o
o
Womens Restroom:
o
o
o
o
o
o
o
o
o
September 2010
4-30
Topic 625-020-016
Facilities Design Manual
o
o
o
o
September 2010
4-31
sto
women
men
women
men
Cars
f
f
ofc
vending
sto
picnic
RV's / Trucks
Dog Walk
Future Cars
Retention Area
Dog Walk
Future
Trucks
Lawn Equipment
Future Cars
Dog Walk
Retention Area
Future
RV's
Trucks / RV's
Dumpster
Topic 625-020-016
Facilities Design Manual
September 2010
4-32
sto
men
women
f
f
f
f
ofc
vending
Cars
men
women
sto
picnic
RV's / Trucks
Retention Area
Dog Walk
Future Cars
Dog Walk
Future
Trucks
Lawn Equipment
Retention Area
Dog Walk
Future Cars
Future
RV's
Trucks / RV's
Dumpster
Topic 625-020-016
Facilities Design Manual
September 2010
4-33
September 2010
8'6
8'
Topic 625-020-016
Facilities Design Manual
8'
8'
12
'6
COURT
PHONES
PHONES
'
12
STORAGE
VENDING
LIVINGAREA
716 sq ft
6'
UTILITY
110'4
HC
43'11
55'8
BATH
HC
COURT
COURT
BATH
HC
Same
HC
MEN
STORAGE
YARD
STORAGE
UTILITY
LIVINGAREA
11906 sq ft
Large
Building
LIVINGAREA
GRASS AREA
SIDE
WALK
SIDE
WALK
SIDE
WALK
GRASS AREA
SIDE
WALK
GRASS AREA
TRASH CAN
OPEN COURT
OPEN COURT
TRASH CAN
SIDE WALK
SIDE WALK
PHONES
PHONES
GRASS AREA
SIDE
WALK
GRASS AREA
POST
BENCH SEAT
GRASS AREA
GRASS AREA
STORAGE
FLAG POLE
PAD AROUND
FLAG POLE WITH
WALKWAY
VENDING
SIDE
WALK
FLAG POLE
BENCH SEAT
PAD AROUND
FLAG POLE WITH
WALKWAY
VENDING
SECURITY
ROOF LINE ABOVE
SIDE WALK
SIDE WALK
TRASH CAN
BENCH SEAT
MECH/ELEC
MECH/ELEC
ENTRY
CHASE
WOMEN
MAP CASE
FAMILY PRIM SEC
BENCH
SEAT
RESTROOM AREA
COVERED
PICNIC AREA
Same
WATER
COOLER
COVERED PICNIC
AREA
CHASE
FAMILY PRIM
SEC
INFO CASE
MEN
COVERED COURT
ENTRY
MECH/ELEC
BENCH SEAT
ROOF LINE
ABOVE
OFFICE
YARD
EQUIP.
CHASE
MECH/ELEC
TRASH CAN
POST
GRASS AREA
GRASS AREA
LIVINGAREA
247 sq ft
OPEN COURT
BENCH SEAT
SMALL
BUILDING
4-34
Topic 625-020-016
Facilities Design Manual
September 2010
These sample drawings illustrate the desired layout and character of new rest areas.
4-35
Topic 625-020-016
Facilities Design Manual
4-11
September 2010
WAREHOUSEAUTOSHOP
JANITOR
MECH.PHONE
FE
SMALL
ENGINE
REPAIR
SMALL
ENGINE
STORAGE
MEN'S
WOMEN'S
LIBRARY
GENERAL SERVICING
BAYS
UP
EWC
HALL
WAREHOUSE
METAL
FABRICATION
SHOP
HALL
SUPERVISOR'S
OFFICE
CARPENTER
SHOP
EQUIPMENT
OFFICE
OFFICE
DOWNSPOUT
BOLLARDS
METAL DOOR
12' x 12' OVERHEAD DOOR
CANOPY
METAL DOOR
METAL DOOR
12' x 16' OVERHEAD DOOR ALUMINUM WINDOW
AUTOSHOP
WAREHOUSE
DOWNSPOUT
FRONT ELEVATION
ROOF MOUNTED
EXHAUST FAN
BOLLARDS
CANOPY
METAL PANELS
DOWNSPOUT
DOWNSPOUT
DOWNSPOUT
DOWNSPOUT
LOADING
TRUCK WELL
METAL DOOR
AUTOSHOPWAREHOUSE
ROOF MOUNTED
EXHAUST FAN
12' x 16'
OVERHEAD DOO
FRONT ELEVATION
DOWNSPOUT
LOADING
TRUCK WELL
DOWNSPOUT
DOWNSPOUT
DOWNSPOUT
TRENCH DRAIN
RIGHT ELEVATION
LEFT ELEVATION
4-36
Topic 625-020-016
Facilities Design Manual
4-12
September 2010
STORAGE FACILITIES
Open storage bins constructed of reinforced CMU walls are used to store materials that
are not susceptible to weather damage: typically sand and gravel. Covered storage
facilities are used to protect vehicles and equipment which may be damaged by the
weather.
When required, provide facilities for storage of hazardous materials per Life-Safety
Code requirements.
(TYPICAL)
SLOPE DOWN
1/8 " / FT.
BOLLARD, TYPICAL
46'-0"
VEHICLE BAY
VEHICLE BAY
VEHICLE BAY
METAL PANELS
ON BACK WALL
AND SIDE WALLS
15'-0"
75'-0"
METAL PANELS
OVERHANG
8" ~ METAL BOLLARDS
8" ~ METAL BOLLARDS
4-37
Topic 625-020-016
Facilities Design Manual
September 2010
4-13 TOWERS
Tower facilities in this section may include the following:
4-38
Topic 625-020-016
Facilities Design Manual
September 2010
Ease of expansion.
Utilities infrastructure in place for expansion.
Water supply lines / stub-ups, capped off.
Sanitary sewer/Waste-water piping / stub-ups, capped off.
Provide wastewater treatment per local requirements.
Electrical panels sized to allow additional circuits / fixtures.
Excessive use of corrosion resistant materials on structure.
4-14.2 Slab
Design concrete slab to support heavy truck loads. Slope slab to catch basin in slab to
carry water, via grease trap, to sewer treatment system or to wastewater treatment
system.
4-14.3 Structure
4-14.4 Roof
4-39
Topic 625-020-016
Facilities Design Manual
September 2010
EQUIPMENT PROVIDED
BY CONTRACTOR
SLOPE
PE
SLO
E
SLOP
PE
O
SL
ALUMINUM CANOPY
FLOOR PLAN
1'
EQUIPMENT PROVIDED
BY CONTRACTOR
WEST ELEVATION
OPEN
EQUIPMENT PROVIDED
BY CONTRACTOR
21'-6"
JOIST BEARING
OPEN
20'-6"
JOIST BEARING
1/4 "
SOUTH ELEVATION
4-40
Topic 625-020-016
Facilities Design Manual
September 2010
Stock room/office area: Contains shelves for the snacks, drinks and supplies
and a work area for the blind services vendor. This area requires power, lighting,
telephone, plumbing, and drainage. The vendor also sorts the money from the
machines here.
Up to 8 vending machines
Overhead rolling/coiling door for secure servicing of machines
Up to 240 s.f. product storage/office, heated and cooled
Utilities: power, water, sewer, phone
Ease of access from parking and building vestibule/courtyard
Separate meter for utilities
4-41
Topic 625-020-016
Facilities Design Manual
September 2010
Stucco on CMU
Public Entry
O. H. Rolling Door
Vending Area
FD
178 sq.ft.
Water
Cond.
28"x40" Vending
Machine (8 ea.)
Desk
J
Drop Box
Drop
Safe
CMU
5 Shelves
3 Shelves
FD
Service
Entry
Stucco on CMU
Stucco on CMU
5 Shelves
AH
AC
5 Shelves
SNACKS
OPEN
4-42
Topic 625-020-016
Facilities Design Manual
September 2010
4-16 WAREHOUSES
4-16.1 Modular Facilities Design
Ease of expansion
Utilities infrastructure in place for expansion
Water supply lines stub-ups, capped off
Sanitary sewer piping stub-ups, capped off
Electrical panels sized to allow additional circuits and fixtures
4-16.2 Structure
4-16.3 Roof
4-16.4 Finishes
Floors in restrooms, parts counter area, and offices to be vinyl tile all others to be
designed for durability and ease of maintenance: epoxy coatings or hardened
concrete.
Exterior walls to be designed for durability, vandal-resistance and lowmaintenance.
Exterior walls of CMU, stucco or metal panels.
4-43
Topic 625-020-016
Facilities Design Manual
September 2010
Interior walls of rest rooms, offices, and parts counter shall be 5/8" sheet rock with
latex paint interior. Walls of restrooms shall be ceramic tile wainscoting over 1/2"
cement board or epoxy coated CMU.
4-16.5 Ceilings
4-16.6 Restrooms
4-16.8 Doors
Provide a minimum of one 12' x 16' overhead door at truck well and one 12' x 12'
overhead door to allow forklift access to and from warehouse.
Provide a minimum one 3-0 x 6-8 metal door allowing entry/exit to warehouse and
to parts counter.
Provide shelves with a capacity of 100 lbs/s.f. for bulk storage, seed bins/small
parts, tire storage racks, also provide area for palletized items and sign storage.
Provide emergency eye wash station.
Provide vents for the removal of hot air, and to provide air circulation in building.
4-44
Topic 625-020-016
Facilities Design Manual
September 2010
See water treatment section for minimum separation requirements between water
lines and sewer lines.
Piping under paved area shall be cast iron pipe, or PVC pipe encased in cast iron
sleeve.
Unless directed otherwise, FDOT plants will be extended aeration package type.
Submit calculations showing plant component size requirements.
4-45
Topic 625-020-016
Facilities Design Manual
September 2010
Locate lift-stations to minimize adverse effects such as odors, noise and lighting.
Provide fenced enclosures. Ensure that truck-mounted hoist can pull pumps
without removal of fencing. Lift-stations shall be fully operational and accessible
during a 25-year flood and the mechanical and electrical equipment shall be
protected from physical damage by a 100-year flood.
Design lift-stations to withstand flotation forces when empty. Specify and detail
easily accessible aluminum filter baskets at the inlet.
Specify encapsulated, mercury float switches to provide lead pump on, lag pump
on, pumps off and alarm. Specify high-quality submersible pumps in full detail to
prevent substitution of cheaper pumps. Pumps shall alternate in operation.
Submit pump calculations and curves during the review process.
Specify stainless guide rails, lifting chain and discharge connection bolted to the
sump floor. Force mains shall be at least 4 in diameter.
Provide protection from lightning and transient voltage surges. Provide a standard
receptacle for connecting portable power generating equipment. Provide a riser
with appropriate coupling device and valving to the discharge pipe to connect
portable pumps and appurtenances.
4-46
Topic 625-020-016
Facilities Design Manual
September 2010
X'
X'-X"
X'-X"
BLOWER CONNECTION
4" THREADED
X'
AIR DIFFUSER
ASSEMBLY (TYP)
WALKWAY GRATING
2'-3 1 /4"
X'
4" INFL.
P.E. CONN.
12'
DIGESTER
XXX GALS.
ACCESS LADDER
INFLUENT
STILLING
WELLS
AERATION
xx,000 GALS.
4" EFFLUENT
P.E. CONN.
CHLORINE CONTACT
XXX GALS.
MIXING BAFFLES
WASTE
SLUDGE 3"
RETURN
SLUDGE 3"
SLUDGE EDUCTOR
PIPE 3"
PLAN VIEW
HANDRAILS
1-1/2" SQ. TUBING
SETTLING
XXX GALS.
EFFLUENT WEIR
SCUM BAFFLE
ADJ. AIR VALVES
11'-9" WEIR
32"W.L.
18" W.L
18" W.L.
6"
TYP.
29"
X'-X"
11'-0" 10'-6"
X'-X"
X'-X"
GRADE
SECTION 'A-A'
BASE SLAB
SLUDGE
EDUCTOR
42"
48"
12"
11'-0"
42"
12'-0"
SECTION
4-47
Topic 625-020-016
Facilities Design Manual
September 2010
4-48
Topic 625-020-016
Facilities Design Manual
September 2010
Inspection Barn: This is an open-air (roof and partial walls) building that covers
an inspection pit allowing inspectors to conduct commercial vehicle inspection
operations up to 24 hours per day in relatively protected environment. The
inspection pit is about 90 long. Trucks straddle the pit to allow inspectors access
under the vehicle to conduct safety inspections of the trucks undercarriage
systems and suspension. The pit contains mechanical systems to aide in the
evacuation of oils or grease that may drop from trucks; and noxious fumes or
other heavier-than-air gases, which may collect in the pit.
Weight Inspectors Office: This space space houses the administrative activities
for inspectors (desk, communications, file storage, etc.) It is located immediately
adjacent and accessible to the Inspection Barn.
4-49
Topic 625-020-016
Facilities Design Manual
September 2010
4-50
Topic 625-020-016
Facilities Design Manual
September 2010
Comfort Station
Inspection Barn
Inspectors Office
T3
AC
X-BRACING TO BE
LOCATED IN THIS BAY
RIDGE VENT
GUTTER
CANOPY
BOLLARD (TYP.)
BRICK
RIGHT ELEVATION
RIDGE VENT
GUTTER
X-BRACING TO BE
LOCATED IN THIS BAY
LEFT ELEVATION
4-51
Topic 625-020-016
Facilities Design Manual
September 2010
For new systems, these considerations are usually determined by the roadway
design. Close coordination and planning between the various design disciplines
during early planning or project phases would result in more optimized and better
engineered facilities.
A daily flow must be determined in order to size equipment. Over the years,
FDOT has derived a daily flow based on the 20 year ADT (Average Daily Traffic).
Adjust toilet and urinal gal/use to reflect specified equipment. BOD value is
required for wastewater treatment plant design. Adjust values if actual data is
available.
The number for Total Processed Water is the projected flow in 20 years. If
windshield-washing facilities are planned, this flow must also be accounted for in
the water supply system.
4-52
Topic 625-020-016
Facilities Design Manual
September 2010
4-19.3 WELLS
Size the well and pump to accommodate future expansion. Calculate the demand flow
based on an engineering analysis; supply fixture unit calculations may not be adequate
to estimate the peak demand.
The Engineer must visit and evaluate the site before locating the well. Do not site well in
areas subject to flooding or ponding. Provide the required setback distances from
potential sanitary hazards. Provide at least two wells. Protect the wells and pumps from
tampering and vandalism. Ensure that vertical clearances permit driving and pulling the
well casing and the pump.
Provide auxiliary power with automatic switch over for the well pumps and the water
treatment plant.
Provide a concrete apron minimum 6 x 6x 4 thick, with the well at its center and the
surface sloping away from the wellhead. Provide a sanitary seal and a vent at wellhead.
A raw water sampling tap, a check valve and a gate valve shall also be provided at the
discharge.
Obtain Consumptive Use Permit from local Water Management District.
4-19.4 DRINKING WATER PLANTS
Develop from 20 year ADT. If future facilities are planned, the drinking water plant
should be sized to accommodate the future expansion. Allowances must also be made
for windshield washing facilities.
Locate the plant as close to the well as practical. If the rest area design has provisions
for future expansion, the plant should be sited to facilitate the planned expansion.
Specify hypo-chlorinators to achieve the required level of disinfection. Do not use gas
chlorinators. Specify all pressure vessels as ASME code vessels.
Design the chlorination system to maintain a minimum free chlorine residual of 0.2
mg/liter throughout the distribution system at all times.
4-53
Topic 625-020-016
Facilities Design Manual
September 2010
4-54
July 2010
Facilities Design Manual
APPENDIX
TABLE OF CONTENTS
Appendix A.1
Appendix A.2
Appendix A.3
Appendix A.4
Appendices
A-1
July 2010
Facilities Design Manual
APPENDIX A.1
Standard Method of Area Calculation
and Space Measurement
The purpose of this section is to standardize the communication and computation of
building areas and space measurement; to allow comparison of values on the basis of
generally agreed upon standard units of measurement. (The Florida Department of
Management Services developed this standard.)
This standard shall be used to measure floor space in existing and new buildings, lease
space and state owned buildings. It is applicable to any type of construction, being
based on the premise that the net area is that which the agency may occupy and use
for its employees and furnishings.
The following space types shall be used for calculating building area and estimating
costs:
1.
Net Usable Areas shall be the sum of all occupiable space in a building. The
area shall be measured from the inside finish of permanent outer building walls to the
office side of permanent corridors and other permanent partitions, and to the center of
partitions that separate the premises from adjoining usable areas. This usable area
shall include ALL spaces located within the perimeter of the subject area. No
deductions shall be made for columns and other projections into the building. For glass
walls, measure from the inside face of the glass.
2.
Public Convenience Area shall be the sum of all areas devoted to the welfare
of the general public, such as lobbies, corridors, toilet rooms, telephone booths, etc.
3.
Utility Area shall be the sum of all areas devoted to the mechanical operation of
the building such as mechanical rooms, electrical rooms, telephone equipment rooms,
elevator shafts, equipment and machinery rooms, pipe and duct shafts and chases,
penthouses, etc..
4.
Building Service and Storage Area shall be the sum of all areas devoted to
janitor closets, maintenance areas, receiving areas, loading docks, etc.
5.
General Circulation areas shall be the sum of all areas devoted to horizontal
and vertical circulation of occupants between the several areas of the building. (i.e.,
corridors and stairs)
Appendices
A-2
July 2010
Facilities Design Manual
6.
Exterior Sheltered Area shall be the sum of all covered walkways, patios, and
similar spaces. These areas shall be calculated using a factor of 0.50.
7.
Structural Area shall be the sum of all areas devoted to the building structure
such as columns, bearing walls, etc.
8.
Gross Building Area shall be the sum of all areas described above.
9.
Exterior Developed Area shall be the sum of all specific purpose areas such as
plazas, fountains, walkways, landscaping, etc.. These areas shall be calculated using a
factor of 0.25.
10.
Gross Project Area shall be the sum of the gross building area and the exterior
developed area.
11.
Net Maintainable Area shall be the gross project area less the structural area.
Appendices
A-3
July 2010
40,000
K=
0.135
D=
0.6
= 20 Year ADT
(Allow for local commuter traffic)
= Ratio of Design Hourly Volume to ADT
(Generally 0.135)
= Directional distribution of Design Hourly Volume
(Generally 0.6)
T=
0.25
= Percent of
overall traffic represented by Trucks
& Recreational Vehicles (RV=s)
(Generally 0.25)
Insert Factor
Total
B=
B=AxKxD=
B = __3240__
C=
__75__ % x B =
__25__ % x B =
C1 + C2 = C =
C1 = __2430__
C2 = ___810__
C = __3240__
__10%_ x C1 =
D1 = ___243__
__15%_ x C2 =
D1 + D2 = D0 =
D2 = ___122__
D0 = ___365__
__0.33_ x D1 =
E1 = ____81__
0.5 x D2 =
E2 = ____61__
2.25 x D0 =
F = ___821__
0.04 x F =
0.5 x G =
0.75 x G =
G = ____32_*
Men = ____16__
Women = ____24__
D0 =
E=
F=
G=
Appendices
A-4
July 2010
= 20 Year ADT
(Allow for local commuter traffic)
= Ratio of Design Hourly Volume to ADT
(Generally 0.135)
= Directional distribution of Design Hourly Volume
(Generally 0.6)
K=
D=
T=
= Percent of
overall traffic represented by Trucks
& Recreational Vehicles (RV=s)
(Generally 0.25)
Insert Factor
Total
B=
B=AxKxD=
B = ________
C=
______ % x B =
______ % x B =
C1 + C2 = C =
C1 = ________
C2 = ________
C = ________
______ x C1 =
D1 = ________
______ x C1 =
D1 + D2 = D0 =
D2 = ________
D0 = ________
______ x D1 =
E1 = ________
0.5 x D1 =
E2 = ________
2.25 x D0 =
F = ________
0.04 x F =
0.5 x G =
0.75 x G =
G = _______*
Men = ________
Women = ________
D0 =
E=
F=
G=
Appendices
A-5
September 2010
APPENDIX A.2
Applicable Codes, Standards, and Regulations
The following list of codes, standards, rules, and regulations are required for the design
and construction of state buildings by Florida Statutes (F.S.) as implemented by various
departmental rules in accordance with Florida Administrative Code as described below.
In cases of conflict between these documents, the more stringent requirements shall
apply.
Building Codes:
Florida Building Code
Accessibility for Persons with Disabilities:
Florida Accessibility Code for Building Construction (FACBC)
Chapter 11 of the Florida Building Code
Section 255.21 and Chapter 553, Part V, F.S.
ANSI A117.1 - 1986
Titles II and III, Americans With Disabilities Act (ADA), Public Law 101-336; and
the ADA Accessibility Guidelines (ADAAG)
Fire Codes and Rules:
NFPA 70-1990
NFPA 101-1997
NFPA 10-1998
NFPA 11-1999
NFPA 11A-1998
NFPA 12-1998
NFPA 13-1996
NFPA 30-1996
NFPA 54-1996
NFPA 58-1998
Consult with the Florida State Fire Marshals office for other frequently used codes.
Energy Conservation:
Rule 13D-10, F.A.C., Rules for construction and leases of State Owned Buildings
to ensure energy conservation
Section 255.251, F.S., Florida Energy Conservation Act of 1974".
Section 255.255, F.S., Life-cycle costs.
Glass:
Chapter 553, F.S., Part III, Glass
Appendices
A-6
September 2010
Elevators:
Chapter 7C-5, Florida Elevator Code
Chapter 399, F.S., Elevators
Flood Plain Management Criteria:
Section 255.25, F.S., Approval required prior to construction or lease of
buildings.
Rules of the Federal Emergency Management Agency (FEMA)
Extinguishing Systems
NFPA 10
NFPA 13
NFPA 14
NFPA 17
NFPA 20
NFPA 24
NFPA 2001
Fire Extinguishers
Sprinkler
Standpipe & Hose System
Dry Chemical
Centrifugal Fire Pump
Private Fire Service Mains
Standard on Clean Agent Fire Extinguishing Systems
Miscellaneous Systems
NFPA 45
NFPA 80
NFPA 88A
NFPA 105
NFPA 110
NFPA 220
NFPA 241
SFM Rule 4A-47
SFM 4A-51
Appendices
A-7
Other:
Chapter 10D-6 F.A.C.
Chapter 17-6.070 F.A.C.
Chapter 17-761 F.A.C.
September 2010
These documents are revised periodically by the responsible agencies and adopted by
authorities having jurisdiction on building projects. The design consultant and the
project manager are advised to obtain applicable versions of these documents from the
responsible agency prior to use.
Appendices
A-8
September 2010
APPENDIX A.3
State Fire Marshal Plans Review Submittal
Requirements, Fee Schedule and Submittal Checklist
The plans for all construction of any new, renovation, or alteration of any existing state
owned or state leased building are subject to review and approval of the Division of
State Fire Marshal for compliance with the Uniform Fire Safety Standards prior to
commencement of construction or change of occupancy. The Division of State Fire
Marshal may inspect state owned and state leased spaces as necessary prior to
occupancy or during construction, renovation, or alteration to ascertain compliance with
the uniform fire safety standards, Section 633.085, F.S. and Chapter 4A-52, F.A.C.
PLANS REVIEW FEES State Owned Buildings:
For Plans Review: The Consultant shall send two (2) complete sets of signed and
sealed contract documents to:
Division of State Fire Marshal
Plans Review Section
The fee for plans review of all construction documents for new construction or
alterations to existing facilities shall be paid in advance by the Design Professional prior
to the review of the documents. This fee is included in the consultant contract.
The check should be made payable to and sent to:
DEPARTMENT OF INSURANCE
Receipt Processing Section
The fee for plans review is determined by multiplying the estimated construction cost of
the building project, less the real estate, by the constant .0025.
Example: $2,000,000 x .0025 ~ $5,000 fee (There is a minimum fee of $100.)
In situations where the user state agency, through it's own facilities prepares the
construction documents, then the user agency is responsible for paying the fee in
advance by FLAIR Journal Transfer. A copy of the journal transfer (voucher) is to
accompany the plans.
Complete the attached Review Request Form, in its entirety, and include it with the plan
submittal to the State Fire Marshal's Office.
Appendices
A-9
September 2010
The total building is valued at $400,000 and the state is leasing 25% of
the NET building square footage. The fee would be calculated by
multiplying $400,000 by 25% = $100,000.00 (cost of leased space)
multiplied by .0025 ~ $250.00.
When plans are approved and the approval letter issued, that approval is good for one
(1) year from date of issue. After that, the plans must be re-submitted and another
review fee paid.
Plans Disposition:
The Division of State Fire Marshal will require submitter to furnish two (2) sets of signed
and sealed contract documents or approval to the Plans Review Section for review.
When the documents are approved for construction, one (1) set will be stamped with
the Fire Marshal's stamp of approval and returned to the submitter.
The stamped set of plans must be kept on the job site for the fire safety inspector's use
at the time of inspection. It shall be the responsibility of the submitter to see that the
"approved" set of plans is on the construction site before work begins and remains
there until final inspection and approval has been issued.
Appendices
A-10
September 2010
Do the plans show the number of floors in this building and the location of the
project under consideration in comparison to the entire floor and building?
Is the building sprinklered and, if so, do the plans show the location of the
sprinkler heads in the area(s) under consideration?
Do the plans show the exit marking(s), locations), and direction of travel?
Is there emergency lighting and, if so, what is the type and location?
What is the type and location(s) of the fire extinguisher(s)?
Are there any special fire extinguishing systems (such as Halon 1301 or dry
chemical hood system)?
If applicable, do the plans show the type and location(s) of smoke and/or heat
detector(s) (including duct detectors)?
Are there any manual fire alarm pull stations and, if so, where are they located
and what is their elevation above floor?
Are there any smoke dampers and, if so, what are their type and location(s)?
Access panels?
Do the documents show the door fire rating on the schedule?
Do the plans show a nationally tested wall assembly detail for rated walls?
Do the plans show the exits and their exit discharge i.e., top of structure to the
level of exit discharge?
If applicable, do the plans show the stair and handrail detail?
What are the interior finishes i.e., paneling, drywall, wallpaper and its flame
spread rating?
While answering these few questions will expedite the process, they are not the
complete set of questions that could be asked. If there are any special circumstances,
or hazards that require further clarification, the reviewer will attempt to contact you;
therefore, include the name and telephone number of a contact person with your plan
submission. Please, remember that if you are called and asked for additional
information or clarification, the reviewer needs this information in writing before he can
approve the project. If the statutory time (10 days on a lease or 30 days on state
owned) expires he must disapprove the project and a resubmittal process may add
further delay to the project.
The following items are areas where your assistance is required. Please ensure that all
submittals address these necessary items where applicable and help prevent lost time
due to disapprovals based on lack of information.
Appendices
A-11
September 2010
1.
Renovations or Alteration - Any alteration, or any installation of new equipment
shall be installed under requirement of new construction. The areas shall be identified
clearly and shall show the area of concern in relation to the total building. This will
ensure that the proposed renovation or alteration will not diminish the life safety
components of the building.
2.
Equivalency Concepts - Any requirement of the code that a designer wishes to
modify by alternative arrangements shall in no case afford less safety to life than the
code presently requires. Any request to use equivalency concepts will only be
considered when technical documentation is submitted.
3.
Classification of Occupancy - Plans shall indicate type of occupancy based on
N.F.P.A. 101, Chapter 4.
4.
Change of Occupancy - Designer shall identify the existing type occupancy and
clearly identify the new occupancy use and areas.
5.
Floor Area - The gross square feet of the building shall be indicated on the
plans. All assembly rooms shall have net floor area given.
6.
High Hazard Area - Any areas of a building, structure, or parts thereof,
containing highly combustible, flammable, explosive products or materials likely to burn
rapidly shall be identified on submittal. The designers all identify amounts and types of
hazardous materials used throughout the facility.
7.
Means of Egress - All three components of the means of egress (exit access,
exit and exit discharge) shall be clearly identified on submittal. Travel distance to exits
shall be detailed.
8.
Occupancy load- The occupant load for each floor and calculations showing
how load was obtained "shall be shown". All assembly rooms, spaces, or areas will be
identified and calculated with calculations shown on plans.
9.
Construction Type - The type of construction shall be identified as it may qualify
per N.F.P.A. 220.
10.
Atrium - Any building in which the designer has incorporated an atrium shall
have the atrium area clearly defined on the contract document.
11.
Penetration of Smoke or Fire Barriers - Passage of pipes, conduits, bus ducts,
cables, wires, air ducts, pneumatic ducts and similar service equipment shall be
detailed as close to installation as the submitter can reasonably do so.
12.
Fire Detection, Alarm and Communications Systems - All existing or new
systems shall be clearly identified on plans. The type system and the appropriate
Appendices
A-12
September 2010
N.F.P.A. standard that was used for design and installation shall be indicated on the
plans signed and sealed by the Designer of Record.
13.
Automatic Sprinkler System, Standpipes and Fire Pumps - All existing or
new systems shall be clearly identified on plans. The type system and appropriate
N.F.P.A. standard that was used for design and installation shall be indicated on plans
signed and sealed by the Designer of Record. Hydraulic calculations, also signed and
sealed by the Designer of Record, shall accompany the plans.
14.
All sheets shall have the correct name of the facility, i.e.- Building Name, Building
Number, Office Complex Name, Street Address, City, County, and Zip code and
assigned lease number noted on the document.
If there are any questions concerning this notice, please contact the State Fire
Marshal's Plans Review Section.
Appendices
A-13
September 2010
APPENDIX A.4
FDOT Publications
The following publications are adopted as a part of this Manual by reference.
1.
2.
3.
4.
5.
6.
7.
8.
9.
Appendices
A-14