Quensh Culvert Replacement Method Statement PDF
Quensh Culvert Replacement Method Statement PDF
Contract No
K020786
Contract Title
Document Title
Site Address
Method Statement
Client
Battlers Well Foundation
Document Title
Method Statement for
Culvert Replacement after new Development
Contract Title
North Harrow Community Centre
Proposed Mixed Use Development
Order or Package Number
Title
Date
Signature
Title
Date
Signature
VERSION CONTROL
Rev
0
Date
17 Apr 10
By
DM
18 Jun 10
DM
Checked
Comment
For Preliminary Comments by Harrow Council
For Formal Approval
Version: 2.0
Page 1 of 16
Method Statement NHCC Culvert Replacement
Method Statement
METHOD STATEMENT
Contract Title
Client
Author:
Darren Male
Contract No:
K020786
Date:
17 April 2010
SITE ADDRESS
North Harrow Community Centre, Station Road, Harrow HA2 6AE
LOCATION OF WORKS
Culvert running to rear of site from north to south west
SCOPE OF WORKS
Replacement of Culvert
Note: This Method Statement has been prepared as a hypothetical worst case method
statement based upon the potential requirement to replace, repair or rehabilitate the culvert at
a undefined future date. It provides a detailed system of work based upon information
provided.
This method statement includes this document, risk assessments, staged progress plans as
well as a programme of works.
A full construction phase health and safety plan would be prepared should any actual work be
required. If required, work would be subject to CDM Notification. Environment Agency, Harrow
Council Drainage Department and Sewerage Undertaker Drainage Department Environment
Permits will be required.
The existing culvert is understood to be of good structural condition and not likely to be
subject to a future daylighting requirement imposed by either the Environment Agency, local
drainage undertaker or North Harrow Community Centre.
The method statement is based upon the worst case requirement to undertake complete
replacement works. A No Dig Cured In Place Pipelining (CIPP) technique would be advocated
for any rehabilitation at structural condition grade 4 and in some circumstances grade 5.
A CCTV or man entry inspection would be required to determine the necessary replacement
technique in line with the WRC Sewerage Rehabilitation Manual.
Version: 2.0
Page 2 of 16
Method Statement NHCC Culvert Replacement
Method Statement
Materials
2. General Foremen
3. Lead Hand
4. Civils Assistants
Competencies
Setting out, CAT scanning and for raising
appropriate records. NVQ4
Responsible for ensuring that works are
carried out by appropriate persons, using the
materials and methods shown in this
procedure or as directed by Engineer. NVQ2
Excavation
Confined Space Entry
Manual Handling
Health and Safety Awareness / CPCS
Abrasive Wheels & Disc Cutter
Excavation
Confined Spaces Entry
Manual Handling
Health and Safety Awareness / CPCS
5. Excavator Operator
8. Crane Operator
Version: 2.0
Page 3 of 16
Method Statement NHCC Culvert Replacement
Method Statement
Excavation
Confined Spaces Entry
Portable Plant
Vehicle Movements on Site
Abrasive Wheels
Hand Tools
Compressor & Pneumatic
Manual Handling
Lifting Operations
Quality Issues
RELEVANT DOCUMENTATION
Site File (including Training & Equipment certificates; Risk Assessments, Safe Systems of
Work and Method Statements; Waste Carriers License and Waste Transfer Note)
Details of the temporary Dam works and river diversion methods, drawings and approvals
form EA
HSE Notification (Form F10)
Job Sheet
Utility drawings
Pre-commencement Site Specific Risk Assessment
As built Documentation (This will include both the details of the culvert construction as well
as the re-instatement of the drainage services running adjacent to the existing culvert)
Customer Satisfaction Form for signature on completion
Version: 2.0
Page 4 of 16
Method Statement NHCC Culvert Replacement
Method Statement
Standard
Y Type
Standard
High-Visibility
Vest / Jacket
EN471 Class 2 /3
Overalls
Dry / Waterproof
Hard Hat
EN397
Bump Cap
EN812
Gloves
Safety Boots
Mechanical / Abrasion
EN388
Respiratory
Protective
Equipment
Face Shield
EN166.3.9.B, 169/175
Impact Resistant
Helmet
Goggles
Safety Harnesses &
Equipment
Y
Y
Y
Gas Monitor
Breathing
Apparatus
Intrinsically Safe
Flashlight
Fire
Extinguisher
1 CO2
2 AFFF Foam
1 Fire Blanket
Spill Kit
Safety Signs:
Welfare:
Other (Specify):
Client / CDM Coordinator consultation with neighbours and local authority (COPA
Section 61 Construction Noise Order).
Version: 2.0
Page 5 of 16
Method Statement NHCC Culvert Replacement
Method Statement
PRE-CONSTRUCTION WORKS
Description
Stage
Deliverables
Programme of Works
The Gantt Chart attached is the result of a critical path analysis
carried out on logically linked project activities contained within
Primavera P6 Project Management database.
The programme has been developed with the aim to schedule all
major activities required to take the project from award to a
successful handback. This has necessitated the need to review
each element of work with respect to interfaces, availability of
resources, buildability, as well as documentation requirements.
As such, any deviations from the construction strategy will need
to be considered separately to mitigate any adverse impact on
the programme. During the development of the programme a
number of key items were considered
1.
Programme of
Works.
Progress charts
As-built chart
Version: 2.0
Staged Progress
Plans
Page 6 of 16
Method Statement NHCC Culvert Replacement
Method Statement
PRE-CONSTRUCTION WORKS
Description
Stage
Deliverables
Contract Milestones
The activities in this WBS show the governing milestones and
hammocks that define the important and overall snapshot of the
works. Included here are the two activities that refer to approvals
by Harrow Council and the Environment Agency for design and
methodology approvals.
3.
Approvals by
Harrow Council,
EA and Statutory
Authorities
The programme infers that the total time on site will be circa 65
days (13 weeks) and the overall period between the notification
by Harrow of culvert replacement and the re-opening of the
community centre will be about 26 weeks.
Design Development
Activity M-00020 will be the appointment of the Design
Consultants and Project Manager by Batters Well Foundation
4.
Design Drawings
and Co-ordination
with Harrow
Drainage Dept
and EA
Documentation
5.
Version: 2.0
Documentation
Page 7 of 16
Method Statement NHCC Culvert Replacement
Method Statement
PRE-CONSTRUCTION WORKS
Description
Stage
Deliverables
Procurement
The first action by the PM will be to notify the Statutory
Authorities, giving a period of 10 week notification lead-in time.
The Culvert Replacement Contractor will be appointed based on
preliminary drawings and a negotiated tender process.
6.
7.
Version: 2.0
Page 8 of 16
Method Statement NHCC Culvert Replacement
Method Statement
SITE METHODOLOGY
Stage
Assessments
Applicable
Description
Site Mobilisation
1.
2.
Lone Workers
Persons or
Animals
Operatives are not permitted to work in severe adverse weather Unfit Habitation
conditions or poor lighting.
With consideration to above, determine capability to complete
job [Refusal to Work on Safety Grounds]. If further advice or
assistance is required, contract Controller.
All operatives to wear the required PPE and follow Site Rules.
A register of all operatives will be prepared and H&S rules will be
enforced at all times
Traffic Management
4.
Version: 2.0
Traffic Circulation
Pedestrian
Management
Vehicles
Operating on Site
Page 9 of 16
Method Statement NHCC Culvert Replacement
Method Statement
SITE METHODOLOGY
Stage
Assessments
Applicable
Description
Preparation for Permanent Works
Check all relevant site / apparatus drawings and use CAT &
Jenny locator. Mark location of apparatus.
Check all plant and equipment prior to use ensuring that it is in
good condition and within its service, test and / or calibration
date.
5.
The site will be prepared and all top soil will be stored along the
south east side of the site. The top soil will be restored after the
permanent works and replaced to its original condition.
Excavation:
Underground
Services
Hand Tools
6.
Crash Decks /
Trackway
Dilapidation
Survey
Vehicles
Operating on Site
Sheet Piling Risk
Assessment
Striking Buried
Services
The piles will be driven with the vibro hammer until they reach
refusal or design toe level (10m estimated subjected to sheet
piling design).
Author: Darren Male
Date: 18 June 2010
Version: 2.0
Page 10 of 16
Method Statement NHCC Culvert Replacement
Method Statement
SITE METHODOLOGY
Stage
Assessments
Applicable
Description
Where piles reach refusal they will be driven using an impact
hammer to design toe levels. Where any piles achieves refusal
prior to reaching the design toe level, after use of the impact
hammer, the level and location will be recorded and a temporary
works check carried out to ensure suitability.
The sheets will be fully clutched to provide a tight seal between
them. The sheets will be propped within the safety zone in the
neighbouring backyard in case additional stability will be
required.
Excavation and Demolition Works
Begin excavation with machine excavation.
Where using hand-held pneumatic breakers then work rotated in
team to ensure that no one person uses vibrating equipment for
more than 2 hours per day.
Undertake excavation carefully using a banksman to look watch
out for signs of services (tapes, tiles etc), using blunt hand tools
to excavate near suspected buried services. Look for signs of oil
or chemical contamination.
8.
Excavation:
Persons and
equipment falling
into excavation
Compressors and
Pneumatics:
Hand Arm
Vibration
Excavation:
Striking Buried
Services
Excavation:
Siltation and
Pollution of
Watercourses
Ladders and
Steps: Fall of
Person or Object
from Ladder
Siltation and
Pollution of
Watercourses
Access into culvert must be via ladder, with two points of access
provided if necessary.
Version: 2.0
Page 11 of 16
Method Statement NHCC Culvert Replacement
Method Statement
SITE METHODOLOGY
Stage
Assessments
Applicable
Description
Disposal of water from excavations
Prior to dewatering or storage of excavated material, identify
local drainage systems and implement controls against loss of
silt
9.
10.
Excavation:
Siltation and
Pollution of
Watercourses
Collapse of
excavation or
spoil
COSHH
guidelines
12.
Version: 2.0
Lifting Loads
Traffic
management
Delivery Logistics
Page 12 of 16
Method Statement NHCC Culvert Replacement
Method Statement
SITE METHODOLOGY
Stage
Assessments
Applicable
Description
Preparation of Culvert Bed Base
13.
Excavation:
Persons and
equipment falling
into excavation
Working in
Trenches
Collapse of
excavation or
spoil
14.
All culverts will be off-loaded from the tipper directly into the
trench base, with the use of the Demag AC40 City Crane.
The box culvert line will be laid from the downstream end with
sockets facing upstream to receive the next box culvert.
Lifting Loads
Inspect the box culvert before laying to ensure that the
jointing surfaces are clean and that no damage has occurred
Lifting Plans
in handling and transport to the site.
Lower the box culvert carefully on to the prepared base
Manual Handling
aligning the spigot with the socket of the unit already laid.
Prevent loose surface bedding material from entering the
joint space during positioning of the unit by placing a
hardboard strip beneath the base joint.
If any adjustment to level is necessary, remove the box
culvert and adjust the surface level of the bedding. Local
packing will not be used to adjust the levels
Version: 2.0
Page 13 of 16
Method Statement NHCC Culvert Replacement
Method Statement
SITE METHODOLOGY
Stage
Assessments
Applicable
Description
Applying the Jointing Material
15.
COSHH
Manual handling
Working in
Confined Spaces
16.
17.
Version: 2.0
Lifting Loads
Manual Handling
Manual Handling
Page 14 of 16
Method Statement NHCC Culvert Replacement
Method Statement
SITE METHODOLOGY
Stage
Assessments
Applicable
Description
Completion Works
18.
Version: 2.0
Manual Handling
Collision of road
vehicles with
persons or
equipment
Lone Workers
Driving at Work
Waste
Page 15 of 16
Method Statement NHCC Culvert Replacement
Method Statement
COSHH
COSHH materials will include Concrete, Diesel and Grouts and Repair
Mortars.
All materials will be controlled by a COSHH co-ordinator who will produce
data sheets as required.
First-Aid box provided on all vehicles.
Local arrangements for contacting emergency services to be identified.
Location of nearest hospital A&E: Watford Road, Harrow, Middlesex, HA1
3UJ Tel: 020 8864 3232 1.8 miles:
First Aid
In case of accident or injury requiring medical attention call 999 and inform
Control.
Always inform Health and Safety Officer of all incidents, accidents and near
misses. Ensure that the Incident Report Form is completed
Environmental
If silt enters the downstream surface water system then implement drain
blockers and inform the Contract Manager..
Other
Position / Employer
Contact Number
TBC
Contract Manager
TBC
TBC
Duty Manager
TBC
Nizar Merali
Clients Representative
TBA
AUTHORISATIONS
Authorised By
Signature
Date
Position
Approved by
Signature
Date
Position
Received By
Signature
Date
Position
Version: 2.0
(Contract Manager)
(Clients Representative)
Page 16 of 16
Method Statement NHCC Culvert Replacement
Method Statement
RAG No.
028
HARM
Employees
(The User)
Persons at Risk
Alternatives
(Elimination /
Reduction)
Training and
Awareness
Health
Requirements /
Surveillance
Severity
Likelihood with
Controls
Very Unlikely
Very Unlikely
Very Unlikely
Very Unlikely
General Public
Environment
1.
Lifting is usually the only practicable method. The safest method of lifting shall be used.
1.
As roles require: Appointed Person for Lifting Operations; Lifting Equipment / Crane Operators License (including
Manufacturers License where required); Slinger / Load Handler; Signaller; Banksman.
1.
None specific persons operating lifting equipment shall be medically fit and have good hearing and sight (corrected as
required).
Planning /
Preparation
1. Lifting equipment will be suitable for the task and used, serviced and maintained in compliance with manufacturers
recommendations and legislative requirements. Thorough Examination Certificates (6 monthly, 12 monthly or in line with a
written scheme of examination) must be in date and made available for inspections. Equipment will be properly stored to
prevent deterioration or damage. Lifting machinery and accessories shall be marked with the safe working load. Lifting
equipment designed to lift persons will be marked as such, equipment specifically NOT designed for people lifting will be
marked as such.
2. The lift will be planned and supervised by trained competent persons. Planning should consider the load to be lifted (weight,
shape, centre of gravity, lifting points), path (radius of lift, overhead clearance), environment (ground conditions, traffic
management, High Voltage Overhead Power Lines [See RAG.025]), positioning of the crane, lifting equipment required and
personnel required.
3. Where appropriate, information on weight, centre of gravity and slinging arrangements of the load shall be obtained.
Operational
Control
1. Equipment will be inspected prior to use and safety defects reported immediately. Equipment will not be used where safety
defects are present. Inspections shall be recorded.
2. Access and egress to the lifting equipment controls (e.g. crane cab or MEWP cage) must be via a safe means, and if the
equipment is for lifting persons, adequate protection from slips, trips and falls must be installed and used.
3. The area of the arc of operations will be clear of all persons. No person shall enter the crane operating area without
permission. Loads are not to be swung over site huts, buildings, public areas or other areas where persons may be present
unless persons have been excluded from those areas. If the above is not practicable, then other measures may be applied.
4. Lifting equipment should be positioned to prevent crushing or strikes at its extreme positions.
5. Sufficient trained competent Slinger / Signaller to be available to sling and control load, especially when the drivers vision of
the load is obstructed. Telephone/radio communication or a system of agreed hand or other signals must be used between
the crane operator and the Slinger / Signaller.
6. Guide ropes shall be used on large loads to guide and steady lift.
7. The table of Safe Working Loads for various radii to be clearly visible to the driver.
8. Practice lifts undertaken when required to gauge the weight, centre of gravity and suitability of slinging arrangements.
9. Where there is a significant risk of overturning / overloading, devices such as rated capacity indicators or limiters used.
Prohibitions /
Restrictions
1. The raising and lowering of people by work equipment which is not specifically designed for the purpose should only be
undertaken in exceptional circumstances, when it is not practicable to gain access by less hazardous means.
2. If wind conditions are such that small branches are moving or paper is blowing around check the wind speed using the
anemometer, and stop work if it exceeds the limit of the equipment.
3. Equipment will not be used where safety defects are present.
4. Persons under 18 years old must not use lifting equipment unless deemed competent by an authorised person.
Personal /
Environment
Protective
Equipment
Emergency
Preparedness
and Response
Type
Standard
Workwear - As appropriate
1.
2.
Adequate first aiders and first aid kits, including eye washes available.
Do not move a casualty who has fallen from height due to increased risk of internal damage or damage to the spine>
Casualties should be kept as still as possible, unless they are at imminent danger e.g. from a collapsing structure, but no
other person shall put themselves at additional risk in rescuing another person.
Version: 1-0
Page 1 of 8
F-SM-16 Lifting Plan
Risk Assessment
RISK ASSESSMENT AND SAFE SYSTEM OF WORK
Title:
RAG No.
068
HARM
Pollution of Watercourse
Habitat Loss
Sewer flooding and related property
damage, odour etc
Water quality impact
Transfer of invasive species eg nonnative fish, disease, plants
Severity
Habitat Loss
Prosecution
Public Complaint
Property Damage
Habitat Damage
Prosecution
Pumping to Watercourse
Persons at Risk
Likelihood with
Controls
Unlikely
Very Unlikely
Very Unlikely
Very Unlikely
Very Unlikely
Environment
Alternatives
(Elimination /
Reduction)
1.
Training and
Awareness
Health
Requirements /
Surveillance
1. Not applicable.
Planning /
Preparation
Operational
Control
Prohibitions /
Restrictions
Personal /
Environment
Protective
Equipment
Emergency
Preparedness
and Response
Assessed by
1.
2.
Do not pump foul into surface water or surface water into foul.
Use of vactor recycling units must be monitored to ensure they do not use sewage-contaminated water in surface water
drains.
Type
Standard
Not Applicable.
1.
Darren Male
Spillage Response Kits including oil-only pads and booms should be available.
Approved By
Assessment Date
08 February 2010
08 February 2013
Version: 1-0
Page 1 of 1
RAG.068 Discharge to Drain, Sewer and Watercourse
Risk Assessment
RISK ASSESSMENT AND SAFE SYSTEM OF WORK
Title:
COMPRESSED AIR FED TOOLS (Non-Vibrating)
HAZARDS
HARM
Noise
Damage to hearing
Cut / Laceration
Can be fatal.
Major Injury
Very Unlikely
Reportable Injury
Very Unlikely
Very Unlikely
Reportable Injury
Very Unlikely
Environmental Pollution
Very Unlikely
Environmental Pollution
Very Unlikely
Employees
(The User)
Persons at Risk
010.2
Entanglement / Entrapment
(in exposed moving parts)
Uncontrolled hoses (whiplash under pressure)
RAG No.
General Public
Environment
Alternatives
(Elimination /
Reduction)
1. None identified. Compressed air is often the most effective and safest form of energy transfer for site works, particularly in
inaccessible areas or wet environments.
2. Any associated use with cutting equipment must be read inconjuntion with 10.1 Pneumatic and Compressed Air Fed Tools.
Training
1.
Health
Surveillance
1.
Noise 2. Skin condition (diesel and oil is carcinogenic and a skin irritant).
1.
2.
3.
4.
Planning /
Preparation
Preference will be given when selecting equipment to that which offers low noise levels.
Compressors and tools subject to planned maintenance and suitable recorded weekly inspections.
Guards and covers must be fitted to moving parts of compressors, especially on V-belts and pulleys.
Air receivers fitted with pressure gauge, safety valve, drain point and access for cleaning, and identify the safe working
pressure.
5. Indicative noise levels assessed and appropriate actions taken.
6. Exposure to oil mist and fumes will be monitored and suitable controls put in place. Air supplies used for breathing purposes
must be periodically tested for purity. Consideration will be given to the type of material being cut and a COSHH assessment
undertaken for any hazards resulting from the dust generated.
7. Inform neighbours of duration of noise if there is a potential for nuisance.
Operational
Control
1. Hoses are the right size for the tool and that the length of the hose is kept as short as possible. All connections must be
properly clamped to prevent the hose whipping.
2. Hoses must be kept free from corrosive materials and protected from interference by passing traffic. Hoses and connections
must be inspected for damage prior to use. Any damaged items must be removed from use. Hoses must be kept clean
when disconnected.
3. Compressor generator must be integrally bunded or site within a bund or secondary containment.
Prohibitions /
Restrictions
Personal /
Environment
Protective
Equipment
Standard
BS EN 388
Ear muffs
BS EN 352 Part 1
FFP1/2 to BS EN EN 149
Safety Boots
BS EN 345
Workwear
Emergency
Preparedness
and Response
Assessed by
1.
2.
3.
Darren Male
All sites to have as a minimum an Emergency Response First Aider and First Aid including Eye Wash.
Drainage to be protected from silt / wash water using booms or sand.
Health and Safety Executive notified of any confirmed cases of Hand-Arm Vibration.
Approved By
Assessment Date
Review Date (3 yr. max)
22 June 2007
Version: 6-0
22 June 2010
Page 1 of 1
RAG.010 Compressors and Pneumatic Tools
Risk Assessment
RISK ASSESSMENT AND SAFE SYSTEM OF WORK
Title:
CONFINED SPACES NC2 and NC3
RAG No.
HAZARDS
HARM
Employees
(The User)
Persons at Risk
011.2
Fatality
Very Unlikely
Fatality
Very Unlikely
Reportable Injury
Very Unlikely
Fatality
Reportable Injury /
Fatality
Very Unlikely
General Public
Alternatives
(Elimination /
Reduction)
1. Conduct survey from surface using mechanical assistance including CCTV Cameras where practicable.
Training and
Awareness
1. Confined Spaces CP1 Top Man and CP2 Confined Space Entry.
Health
Requirements /
Surveillance
Very Unlikely
Environment
1. Ensure emergency / rescue procedures are in place, external rescue support available if necessary and persons entering
confined space use rescue harness and lines / winches as appropriate.
Planning /
Preparation
2. Check weather conditions and tide cycles that could affect fluid levels.
3. Entry into National Category 4 Confined Spaces to be under a site specific risk assessment.
Operational
Control
Prohibitions /
Restrictions
1. Only persons trained in Confined Space Entry and medically fit to work near or in confined spaces.
2. No person to enter confined space (e.g. to recover dropped equipment) without appropriate training, breathing apparatus
and rescue equipment.
Personal /
Environment
Protective
Equipment
Emergency
Preparedness
and Response
Assessed by
Type
Standard
BS EN 388
BS EN 352 Part 3
Hard hat
EN397
Safety Boots
BS EN 345
Workwear / Wetwear
Gas Monitor
1.
Darren Male
Ensure emergency / rescue procedures are in place, external rescue support available if necessary and persons entering
confined space use rescue harness and lines / winches as appropriate.
Approved By
Assessment Date
04 January 2007
04 January 2010
Version: 6-0
Page 1 of 1
RAG.011.2 Confined Spaces NC2 and NC3
Risk Assessment
RISK ASSESSMENT AND SAFE SYSTEM OF WORK
DRAIN, INTERCEPTOR AND CESSPIT TANKERING AND CLEANING
RAG No.
015
To be read in Conjunction with Confined Spaces and Sewage and Contaminated Waters
RISK FACTOR (in relation to harm)
HAZARDS
HARM
Likelihood with
Severity
Controls
Slippage on Liquid Waste / Trip on Pipes
Slip and Fall
Major Injury
Unlikely
Title:
Persons at Risk
Fatality
Disease /
Reportable Incident
General Public
Very Unlikely
Unlikely
Environment
Alternatives
(Elimination /
Reduction)
Training and
Awareness
1. High Pressure Water Jetting; Confined Spaces (CP1); Use of Tankers, Submersible Pumps and Associated Equipment
Health
Requirements /
Surveillance
Planning /
Preparation
1. Plant specific risk assessment in place for the operation and maintenance of vehicles, plant and associated equipment.
2. If removing waste from site, then ensure that carrier has a valid Waste Carriers License.
1. Care to be taken during hose release operation to control any spillage.
2. Operatives to ensure they have sound footing and firm hold of the equipment.
3. Workplace and adjacent areas kept free from debris and spillages.
4. Hoses placed correctly to avoid trip hazards.
Operational
Control
Prohibitions /
Restrictions
Personal /
Environment
Protective
Equipment
Emergency
Preparedness
and Response
Type
Standard
Gloves - PVC
BS EN 374
Ear muffs
Safety Boots
BS EN 345
Workwear
1.
Carry eye-wash as part of first aid kit. Wash of any areas effected by contaminated water with hot soapy water. If any liquid
is ingested or inhaled then seek medical attention.
2.
Wash back any spilt sewage into manhole. Do not use disinfectant unless with a COSHH Assessment.
Assessed by
Darren Male
Approved By
Assessment Date
04 January 2007
04 January 2010
Version: 6-0
Page 1 of 1
RAG.015 Drainage Cleaning and Tankering
Risk Assessment
RISK ASSESSMENT AND SAFE SYSTEM OF WORK
Title:
EXCAVATION STRIKE OF BURIED SERVICES
HAZARDS
RAG No.
HARM
Electrocution and burns
Fire or Explosion
Persons at
Risk
Alternatives
(Elimination /
Reduction)
18.1
Very Unlikely
Drowning
Consequential injuries caused by
casualties reaction to shock
Poisoning or toxic atmosphere
Major Injury
Unlikely
Fatality
Very Unlikely
Fatality
Very Unlikely
General Public
Employees
(The User)
Environment
Training and
Awareness
Health
Requirements /
Surveillance
Planning /
Preparation
1. Contact service owners; establish position of known services via drawings and / or site visit.
To be read in conjunction with RAG.18.2 Excavation - Falling into; RAG.18.3 Excavation - Collapse; 18.4 Excavation Excavated Soil and Disposal of Groundwater
1. Use electrolocation device to detect presence of high voltage cables, mark position of located and of other known services.
2. Undertake pre-start toolbox talk on location of services, and warn of possibility of unknown services.
Operational
Control
3. Undertake excavation carefully using a banksman to look watch out for signs of services (tapes, tiles etc).
4. Use blunt hand tools to excavate near suspected buried services.
5. Always assume services are live and ensure all services are properly identified.
6. Ensure all affected persons are aware of services that are uncovered during excavation.
Prohibitions /
Restrictions
Personal /
Environment
Protective
Equipment
Emergency
Preparedness
and Response
Assessed by
Darren Male
1. No excavation shall be commenced until a cable trace has been completed. Hand dug trial holes shall be used where
appropriate.
Type
Standard
BS EN 388
Safety Goggles
BS EN 166 1B / BS
Ear Muffs
BS EN 352 Part 1 or 3
Safety Boots
BS EN 345
Workwear
1.
Report any faults or damage to services immediately to the service owner. (i.e. gas smell water leakage).
Approved By
Assessment Date
04 January 2007
04 January 2010
Version: 6-0
Page 1 of 1
RAG.018.1 Excavation Strike of Buried Services
Risk Assessment
RISK ASSESSMENT AND SAFE SYSTEM OF WORK
Title:
EXCAVATION FALL INTO
RAG No.
18.2
HAZARDS
HARM
Training and
Awareness
Health
Requirements /
Surveillance
None required.
Planning /
Preparation
General Public
Very Unlikely
Environment
To be read in conjunction with RAG.18.1 Excavation Strike of Buried Services; RAG.18.3 Excavation Entry; 18.4 Excavation
- Excavated Soil and Disposal of Groundwater and RAG.018.5 Excavation Work Near Trees.
1. Excavations must be signed and suitable barriered or plated over to prevent persons falling into hole. Any excavations
greater than 2 meters deep must have barriers that can physically prevent a person falling. Particular care must be taken
where vulnerable persons such as children may be present. The selection of fencing / barriers must take into account the
possibility of children trespassing onto site.
Operational
Control
2. Traffic routes and walkways over excavations must be strong enough to support the anticipated load. Any routes for
pedestrians must consider the needs of disabled persons.
3. Signs and barriers must be erected and periodically (minimum 7 days) inspected by a competent person. The results of any
inspection must be recorded in the excavation inspection book.
4. Stoplogs must be positioned to prevent vehicles approaching too close to side of excavations. Materials and equipment must
be stored in a position that precludes them inadvertently falling into the excavation.
5. Suitable and safe access and egress routes must be provided for persons and equipment.
Prohibitions /
Restrictions
1. No excavation shall be commenced until a cable trace has been completed. Hand dug trial holes shall be used where
appropriate.
2. No person to enter excavation unless authorised to do so in compliance with RAG.18.3 Excavation Entry.
Personal /
Environment
Protective
Equipment
Emergency
Preparedness
and Response
Assessed by
Darren Male
Type
Standard
BS EN 388
Safety Goggles
BS EN 166 1B
Hard Hat
BS EN 397
Ear Muffs
BS EN 352 Part 1 or 3
Safety Boots
BS EN 345
Workwear
1.
2.
Assessment Date
04 January 2007
04 January 2010
Version: 6-0
Page 1 of 1
RAG.018.2 Excavation Fall Into
Risk Assessment
RISK ASSESSMENT AND SAFE SYSTEM OF WORK
Title:
EXCAVATION ENTRY
HAZARDS
Training and
Awareness
Health
Requirements /
Surveillance
Planning /
Preparation
Entrapment
Fatality
Unlikely
Fatality
Unlikely
Fatality
Unlikely
Fatality
Fatality / Dangerous
Occurrence
Unlikely
Drowning.
Strike by Falling Object
Collapse of Excavation
18.3
HARM
Persons at
Risk
Alternatives
(Elimination /
Reduction)
RAG No.
Employees
(The User)
General Public
Unlikely
Environment
Hand Arm Vibration and Noise if using manually operated equipment. 2. Working at Heights / Use of Ladders. 3. Use of
Winches and Tripods.
Operational
Control
1. Ensure any excavations requiring shoring / trench support are inspected by a competent person upon establishment and a
minimum of seven days thereafter or after any event that might reduce the effectiveness of the structure. Inspection to be
recorded on the Excavation Inspection Record.
2. Ensure that any loading from vehicles, equipment or materials are considered at the time of selection of the shoring / support
equipment. Vibration should also be considered.
3. The possibility of collapse of structures adjacent to the excavation must be considered when selecting shoring / support
equipment.
4. Dewatering activities must be conducted as per RAG.018.4 Excavation Dewatering and Control of Spoil. The destabilising
effect of water must be considered during excavation.
5. Spoil must be placed at an angle of repose such that it cannot collapse back into the excavation. Sufficient room must be
allowed at the planning stage for storage of spoil.
6. Work undertaken in the excavation must not affect the effectiveness of any controls.
7. Where possible, at least two methods of access shall be provided. All ladders should be tied or stabilised and protrude
sufficiently above the landing place. Ladder access should be sited away from areas where excavators are working or
materials are being lifted or lowered by crane.
8. Persons in control of excavation must be able to identify when the excavation becomes a confined space due to its
configuration and the likelihood of the presence of toxic gas or explosive gas or high / low oxygen. When identified as a
confined space then a risk assessment for an entry into a confined space will be undertaken and the controls implemented
as per RAG.011.1&.2. Persons entering a confined space will be trained and equipped to do so.
9. The lifting of loads shall be undertaken as per RAG.028 Lifting Operations and Lifting Equipment and Work Near Overhead
Power Lines as per RAG.025.
Prohibitions /
Restrictions
Personal /
Environment
Protective
Equipment
Emergency
Preparedness
and Response
Assessed by
Darren Male
Standard
BS EN 388
Safety Goggles
BS EN 166 1B
Hard Hat
BS EN 397
Ear Muffs
BS EN 352 Part 1 or 3
Safety Boots
BS EN 345
Workwear
1.
2.
Assessment Date
04 January 2007
04 January 2010
Version: 6-0
Page 1 of 1
RAG.018.3 Excavation Entry
Risk Assessment
RISK ASSESSMENT AND SAFE SYSTEM OF WORK
Title:
LIFTING OPERATIONS AND LIFTING EQUIPMENT
HARM
Alternatives
(Elimination /
Reduction)
Training and
Awareness
Health
Requirements /
Surveillance
028
HAZARDS
Very Unlikely
Very Unlikely
Very Unlikely
Very Unlikely
Employees
(The User)
Persons at Risk
RAG No.
General Public
Environment
1.
Lifting is usually the only practicable method. The safest method of lifting shall be used.
1.
As roles require: Appointed Person for Lifting Operations; Lifting Equipment / Crane Operators License (including
Manufacturers License where required); Slinger / Signaller.
1.
None specific persons operating lifting equipment shall be medically fit and have good hearing and sight (corrected as
required).
Planning /
Preparation
1. Lifting equipment will be suitable for the task and used, serviced and maintained in compliance with manufacturers
recommendations and legislative requirements. Thorough Examination Certificates (6 monthly, 12 monthly or in line with a
written scheme of examination) must be in date and made available for inspections. Equipment will be properly stored to
prevent deterioration or damage. Lifting machinery and accessories shall be marked with the safe working load. Lifting
equipment designed to lift persons will be marked as such, equipment specifically NOT designed for people lifting will be
marked as such.
2. The lift will be planned and supervised by trained competent persons. Planning should consider the load to be lifted (weight,
shape, centre of gravity, lifting points), path (radius of lift, overhead clearance), environment (ground conditions, traffic
management, High Voltage Overhead Power Lines [See RAG.025]), positioning of the crane, lifting equipment required and
personnel required.
3. Where appropriate, information on weight, centre of gravity and slinging arrangements of the load shall be obtained.
Operational
Control
1. Equipment will be inspected prior to use and safety defects reported immediately. Equipment will not be used where safety
defects are present. Inspections shall be recorded.
2. Access and egress to the lifting equipment controls (e.g. crane cab or MEWP cage) must be via a safe means, and if the
equipment is for lifting persons, adequate protection from slips, trips and falls must be installed and used.
3. The area of the arc of operations will be clear of all persons. No person shall enter the crane operating area without
permission. Loads are not to be swung over site huts, buildings, public areas or other areas where persons may be present
unless persons have been excluded from those areas. If the above is not practicable, then other measures may be applied.
4. Lifting equipment should be positioned to prevent crushing or strikes at its extreme positions.
5. Sufficient trained competent Slinger / Signaller to be available to sling and control load, especially when the drivers vision of
the load is obstructed. Telephone/radio communication or a system of agreed hand or other signals must be used between
the crane operator and the Slinger / Signaller.
6. Guide ropes shall be used on large loads to guide and steady lift.
7. The table of Safe Working Loads for various radii to be clearly visible to the driver.
8. Practice lifts undertaken when required to gauge the weight, centre of gravity and suitability of slinging arrangements.
9. Where there is a significant risk of overturning / overloading, devices such as rated capacity indicators or limiters used.
Prohibitions /
Restrictions
1. The raising and lowering of people by work equipment which is not specifically designed for the purpose should only be
undertaken in exceptional circumstances, when it is not practicable to gain access by less hazardous means.
2. If wind conditions are such that small branches are moving or paper is blowing around check the wind speed using the
anemometer, and stop work if it exceeds the limit of the equipment.
3. Equipment will not be used where safety defects are present.
4. Persons under 18 years old must not use lifting equipment unless deemed competent by an authorised person.
Personal /
Environment
Protective
Equipment
Type
Standard
BS EN 388
Safety Goggles
BS EN 166 1B
Hard Hats
BS EN 397
Safety Boots
BS EN 345
Workwear
As appropriate
1.
2.
Assessed by
Darren Male
Adequate first aiders and first aid kits, including eye washes available.
Do not move a casualty who has fallen from height due to increased risk of internal damage or damage to the spine>
Casualties should be kept as still as possible, unless they are at imminent danger e.g. from a collapsing structure, but no
other person shall put themselves at additional risk in rescuing another person.
Approved By
Assessment Date
Review Date (3 yr. max)
04 January 2007
Version: 6-0
04 January 2010
Page 1 of 1
RAG.028 Lifting Operations and Lifting Equipment
Risk Assessment
RISK ASSESSMENT AND SAFE SYSTEM OF WORK
PORTABLE PLANT
036
Control of Heavy Plant and Machinery including Fork Lift Trucks, Mini Diggers, Excavators, RAG No.
Dump Trucks, Track Trollies
RISK FACTOR (in relation to harm)
HAZARDS
HARM
Likelihood with
Severity
Controls
Muscular
Strain;
Entrapment
of
Major Injury /
Use of Plant / Equipment
Unlikely
Extremities; Fracture
Reportable Injury
Collision with Other Vehicle (Road or Rail) due to
Fatality (potentially multiple)
Fatality
Very Unlikely
Failure of Driver or Slewing
Collision with Other Vehicle (Road or Rail) due to
Fatality (potentially multiple)
Fatality
Very Unlikely
Slewing
Muscular
Strain;
Entrapment
of
Major Injury /
Manual Handling
Unlikely
Extremities; Fracture
Reportable Injury
Asphyxiation; Inhalation of dust, oil mist
Fatality / Reportable
Exposure to Fume
Unlikely
and fumes; Fire / Explosion; Air Pollution
Injury
Exposure
to
Harmful
Substance;
Handling Oils and Fuels
Reportable Injury
Unlikely
Pollution of Land or Water
Employees
Persons at Risk
Other Site Staff
General Public
Environment
(The User)
Alternatives
(Elimination /
1. None specified.
Reduction)
Title:
Training and
Awareness
1.
Plant Operators License (as applicable); Spillage Response; Banksman (where required).
Health
Requirements /
Surveillance
1.
Planning /
Preparation
Operational
Control
Prohibitions /
Restrictions
Personal /
Environment
Protective
Equipment
Emergency
Preparedness
and Response
Assessed by
1. All new machinery chosen on capability, emissions, noise and vibration; shall be CE marked; be inspected by a competent
person before use to determine it is safe (do not rely on the CE mark or manufacturers guarantee). have a EC Declaration
of Conformity; provided with instructions in English. Machinery shall not be used if it is thought to be unsafe.
2. Work equipment and guards, safety devices, controls etc shall be inspected, examined, maintained and serviced by a
competent person as per statutory requirements and manufacturers instructions.
3. The correct equipment must be used for the job in hand. The equipment must be designed for that job and not modified or
extended beyond the capability of the plant.
4. Where there is risk of entanglement, shearing, crushing, trapping or cutting then adequate guards must be fitted. Guards
must be used when the machine is in use. Guards shall be inspected to ensure they are convenient to use and not easy to
defeat, otherwise they may need modifying.
5. Equipment shall have adequate controls, particularly to turn off equipment in an emergency.
6. For mobile plant: where there is a risk of falling out of the equipment then cab guard rails, barriers (side, front and / or rear)
and / or seat restraints shall be installed and used. Where there is a risk of mobile plant rolling over, then roll-over protective
structures (ROPS) and seat belts must be fitted and used correctly. Where there is a risk of falling objects, a Falling Object
Protective Structure (FOPS) shall be installed.
1. MHG:013 Manual Handling of Portable Plant shall be followed for the manual movement of plant and RAG.048 Vehicles
Operating on Sites for motorised movement. Competent Banksmen shall be used where required.
2. Where there is the potential for the mobile plant to impact upon the operations of a highway or railway, then a banksman
shall be in place during the movement of the plant in case of the plant driver being incapacitated through heart attack or
other disabling injury. The banksman shall be able to stop the plant to prevent injury.
3. Where the excavator arm or crane jib can enter the running road or rail through slewing, then slew restrictors shall be
installed. These may be electronic, mechanical or a physical barrier.
4. Extra care to be taken when working on or near slopes, especially when crossing the gradient.
5. Where hazards cannot be eliminated or isolated then the correct PPE shall be provided. No loose clothing or jewellery shall
be used near parts of the machine where there is a risk of entrapment.
6. For plant generating noise, then RAG:033 Noise and Public Nuisance shall be followed.
7. Plant shall not be used in an enclosed place due to the collection of fumes. Good ventilation shall be provided. Exposure to
oil mist and fumes will be monitored and suitable controls put in place which will include, in order: fume capture, extended
exhaust pipes, maintenance and service, respiratory protection.
8. Plant shall not be refuelled on or near gullies or drains, and where practicable not on exposed soil or gravelled areas. Filling
shall be via a suitable spout or funnel. Fuels to be stored in a labelled proprietary plastic or metal fuel can. Where plant is
left unattended, they shall be locked, and any fuel access points secured.
1. Plant shall be used as per the training and instruction. Plant shall not be driven too fast; overloaded; used for tasks it is not
designed or authorised to do; modified by unauthorised persons; left unattended with engines running; carry passengers
unless an additional seat is provided.
2. People shall not be carried on work equipment unless it is designed for that purpose, except under exceptional
circumstances with the concession (permission) of Health and Safety Officer. Under these circumstances the mobile work
equipment must have features to prevent people falling from it e.g. trailers with sides and / or secure handholds.
3. Do not operate near ignition sources or smoke near petrol driven generators or fuel containers.
Type
Standard
As applicable to Work Task and Work Environment.
1.
Darren Male
Assessment Date
04 January 2007
04 January 2010
Version: 6-2
Page 1 of 1
RAG.036 Portable Plant
Risk Assessment
RISK ASSESSMENT AND SAFE SYSTEM OF WORK
Title:
VEHICLES OPERATING ON SITES - Including Self Propelled Plant
HAZARDS
HARM
Strike injury
RAG No.
Fatality
Very Unlikely
Major Injury
Very Unlikely
Fatality
Very Unlikely
Fatality
Very Unlikely
Operational
Control
Prohibitions /
Restrictions
Personal /
Environment
Protective
Equipment
048
Unlikely
Environment
2.
3.
All drivers will hold a current relevant driving licence and / or training certificates. Visiting drivers will be briefed on site rules
and hazards.
Banksman or Slinger / Signaller Certificate.
Spill and Fire Response (if handling hazardous substances)
1.
1. Vehicles intended for use on the public highway will comply with the current licensing requirements. All vehicles will be
properly maintained, serviced and inspected.
2. The site will be surveyed and vehicle routes planned to avoid danger to pedestrians, contact with buildings, structures,
overhead power lines and to be clear of all excavations.
3. Designated pedestrian pathways shall be provided. Where an enclosed pedestrian route, or a doorway or staircase, joins a
vehicle route there should be an open space of at least one metre from which pedestrians can see along the vehicle route in
both directions. Where such a space cannot be provided barriers or rails should be provided to prevent pedestrians walking
directly onto the vehicular route.
4. Vehicle operating areas and traffic routes will be clearly signed and fenced off where practicable.
5. Speed restrictions will, where necessary, be agreed, displayed and enforced.
6. Where there is insufficient illumination around the work area then adequate artificial lighting shall be provided.
1. A Banksman must be provided where drivers do not have clear visibility and when vehicles manoeuvre adjacent to scaffold
and access towers.
2. Where audible / visual warnings are not fitted to vehicles, banksmen will be used to give warning to others when vehicles
are reversing.
3. Any access /scaffold towers shall not have any personnel working on them when vehicle movements are taking place.
4. Persons operating in the vicinity of moving vehicles shall wear high visibility clothing.
5. Any movement of vehicles in the vicinity of High Voltage Overhead Power Lines shall be as per RAG.025.
6. Loads will be assessed and the unloading or loading of vehicles planned to ensure that the movement of loads is properly
controlled. Loading and unloading will only take place in designated areas and under proper control. Drivers will ensure
loads are placed evenly in vehicles and that the vehicle is not overloaded.
7. Tipping vehicles will not move with the body raised.
8. Hazardous Substances shall be delivered, moved, stored and used as per RAG.020 and the applicable COSHH
Assessment.
1. Persons under 18 years should not work where there is the risk of vehicular collision.
2. No working in severe weather conditions including rain, fog and snow.
Type
Standard
As a minimum:
High Visibility jackets or vests
1.
Adequate first aiders and first aid equipment shall be provided. Persons injured by vehicle collision or crushing injury should
not be moved due to the increased risk of internal or spinal injury. Persons who are struck by moving vehicles should not be
moved unless at risk of further harm, but do not place any other person at risk if attempting a rescue.
2.
Adequate fire and spillage response kits and trained personnel shall be available.
Emergency
Preparedness
and Response
Assessed by
Darren Male
Approved By
Assessment Date
04 January 2007
04 January 2010
Version: 6-0
Page 1 of 1
RAG.048 Vehicles Operating on Sites
Risk Assessment
RISK ASSESSMENT AND SAFE SYSTEM OF WORK
Title:
HAZARDS
HARM
RAG
063
No.
RISK FACTOR (in relation to harm)
Likelihood with
Severity
Controls
Major Injury
Very Unlikely
Fatality
Very Unlikely
Fatality
Very Unlikely
Major Injury
Very Unlikely
18 February 2009
Version: 1-0
18 February 2012
Page 1 of 1
RAG.063 Excavators Used as Cranes
Risk Assessment
RISK ASSESSMENT AND SAFE SYSTEM OF WORK
Title:
RAG No.
068
HARM
Pollution of Watercourse
Habitat Loss
Sewer flooding and related property
damage, odour etc
Water quality impact
Transfer of invasive species eg nonnative fish, disease, plants
Severity
Pumping to Watercourse
Persons at Risk
Habitat Loss
Prosecution
Public Complaint
Property Damage
Habitat Damage
Prosecution
Blocked drains; Habitat
Loss; Prosecution
Habitat Loss
Prosecution
General Public
Likelihood with
Controls
Unlikely
Very Unlikely
Very Unlikely
Very Unlikely
Very Unlikely
Environment
Alternatives
(Elimination /
Reduction)
1.
Training and
Awareness
Health
Requirements /
Surveillance
1. Not applicable.
Planning /
Preparation
Operational
Control
Prohibitions /
Restrictions
Personal /
Environment
Protective
Equipment
Emergency
Preparedness
and Response
Assessed by
1.
2.
Do not pump foul into surface water or surface water into foul.
Use of vactor recycling units must be monitored to ensure they do not use sewage-contaminated water in surface water
drains.
Type
Standard
Not Applicable.
1.
Darren Male
Spillage Response Kits including oil-only pads and booms should be available.
Approved By
Assessment Date
08 February 2010
08 February 2013
Version: 1-0
Page 1 of 1
RAG.068 Discharge to Drain, Sewer and Watercourse
Employer:
Contract:
Programme:
Title:
Activity ID
Activity Name
Week
13 14
Dur
-3
-2
-1
10
11
12
15
16
Start Date:
Finish Date:
Data Date:
Baseline:
17
18
19
20
21
22
10.May.10
08.Nov.10
10.May.10
23
24
25
26
27
129d
Contract Milestones
129d
Harrow Council: Culvert Replac...
M-00010
0d
M-00020
0d
M-00030
0d
M-00040
20d
M-00050
15d
M-00060
0d
M-00070
0d
M-00080
Site Possession
0d
M-00090
M-00100
Substantial Completion
0d
Substantial Completion
M-00110
De-mobilisation
5d
De-mobilisation
M-00120
5d
M-00130
As-Built Drawings
5d
As-Built Drawings
M-00140
Site Close-Out
0d
M-00150
M-00160
M-00170
Site Possession
Snagging (Hammock) / Testing &...
10d
Site Close-Out
Site Works Hammock
65d
Project Works
129d Hammock
0d
Pre-Construction Works
75d
Design Development
50d
D-00010
15d
D-00020
15d
D-00030
15d
D-00040
15d
D-00050
15d
D-00060
15d
Documentation
15d
D-01010
15d
D-01020
15d
Critical Work
End Milestone
Consultant
M&E Subcon
Rem Work
Harrow Council
Contractor
Piling Subcon
Start Milestone
Battlers Well
STATS / EA
Level of Effort
Proj Manager
ID:K020 Cul-01
Filter: TASK filter: All Activities
Primavera Systems
28 29
Employer:
Contract:
Programme:
Title:
Start Date:
Finish Date:
Data Date:
Baseline:
D-01030
15d
Week
9 10 11 12 13 14 15 16 17
Prepare and Issue Method State...
D-01040
15d
D-01050
15d
D-01060
15d
D-01070
15d
D-01080
15d
Activity ID
Activity Name
Dur
-3
Procurement
-2
-1
18
19
20
21
22
10.May.10
08.Nov.10
10.May.10
23
24
25
26
27
70d
P-00010
0d
P-00020
50d
P-00030
10d
P-00040
P-00050
0d
25d
Negotiate and Award M&E Subont...
P-00060
10d
P-00070
10d
P-00080
0d
P-00090
25d
P-00100
10d
P-00110
10d
P-00120
P-00130
0d
10d
P-00140
0d
P-00150
10d
Construction Works
65d
10d
CM-00010
3d
CM-00020
3d
CM-00040
3d
CM-00050
5d
CM-00060
Plant Mobilisation
5d
Plant Mobilisation
CM-00070
2d
Critical Work
End Milestone
Consultant
M&E Subcon
Rem Work
Harrow Council
Contractor
Piling Subcon
Start Milestone
Battlers Well
STATS / EA
Level of Effort
Proj Manager
ID:K020 Cul-01
Filter: TASK filter: All Activities
Primavera Systems
28 29
Employer:
Contract:
Programme:
Title:
Activity ID
Activity Name
Dur
-3
CM-00100
-2
-1
0d
Enabling Works
10
11
12
Week
13 14
Start Date:
Finish Date:
Data Date:
Baseline:
15 16 17 18 19 20 21
Site Establishment Complete
22
10.May.10
08.Nov.10
10.May.10
23
24
25
26
27
28 29
21d
CS-00010
10d
CS-00020
10d
CS-00030
5d
CS-00040
5d
CS-00050
5d
CS-00060
3d
CS-00070
5d
CS-00080
5d
Culvert Replacement
39d
CR-00010
5d
CR-00020
5d
CR-00030
CR-00040
10d
CR-00050
12d
CR-00060
12d
CR-00070
10d
CR-00080
12d
CR-00090
10d
Completion Works
8d
25d
CW-00010
10d
CW-00020
10d
CW-00030
10d
CW-00040
10d
CW-00050
10d
CW-00060
5d
CW-00070
5d
Critical Work
End Milestone
Consultant
M&E Subcon
Rem Work
Harrow Council
Contractor
Piling Subcon
Start Milestone
Battlers Well
STATS / EA
Level of Effort
Proj Manager
ID:K020 Cul-01
Filter: TASK filter: All Activities
Primavera Systems
40
Demag AC40
Tonne
Dimensions
Dimensions (mm)
Hookblock
Capacity (t)
40
4.3
Raised
3195
3085
340
1490
Weight (t)
0.48
0.13
Lowered
3115
3005
260
1410
The charts that have been included have been reproduced from manufacturer specifications, and while every effort has been
made to ensure their accuracy, we do not accept any responsibility for errors or omissions. We also need to draw your
attention to the guidance notes on page 47 to assist you with your crane selection.
CL13
40
Demag AC40
Tonne
City & Low
Headroom Cranes
Over rear
7.8
40
7.8
34.3
32.4
30.5
28.3
10.7
25
25
25
25
24
20.3
17
20
14
8.8
4.5
Free on wheels
over Rear
25.3
14
13.2
12.2
11.2
10.3
7.6
5.9
5
4.3
3.5
3
2.5
28.4
11.1
10.8
10.1
9.4
7.6
6
4.9
4
3.4
2.8
2.3
1.8
31.2
7.8
14.5
12.9
11.5
10.4
10.7
14
12.4
11.1
10
9
7.5
6.1
13.6
15.1
13.4
12.1
11
10
8.4
7.2
5.9
4.8
4.1
9
8.8
8.3
7.3
5.9
4.7
3.8
3.1
2.6
2.1
1.7
1.4
1.1
CL14
20
10.7
25
25
25
23
18.4
13
9.8
13.6
21
21
21
20.7
18
14.4
11.1
8.9
7.3
6.2
5.2
19.5
16
16
16
14.2
11.4
9.2
7.6
6.4
4.8
3.7
3
2.5
25.3
13.6
10.9
8.7
7.7
6.5
4.9
3.8
3
2.5
2.1
1.7
1.5
28.4
10.8
8.8
7.4
6.3
4.7
3.6
2.8
2.3
1.8
1.5
1.2
31.2
8.8
7.2
6.1
4.5
3.4
2.7
2.1
1.7
1.3
1
0.8
0.6
0.8
The charts that have been included have been reproduced from manufacturer specifications, and while every effort has been
made to ensure their accuracy, we do not accept any responsibility for errors or omissions. We also need to draw your
attention to the guidance notes on page 47 to assist you with your crane selection.
Demag AC40
Lifting Capacities - Outriggers in min. position
Radius
(m)
4
4.5
5
6
7
8
9
10
12
14
HB
10.7
11.2
9.2
7.7
5.7
4.3
13.6
12.6
10.5
8.9
6.7
5.3
4.3
3.6
3
8.0
2.8
2.1
40
Tonne
19.5
12.9
10.8
9.2
7
5.5
4.5
3.8
3.2
2.3
1.7
10.7
13.6
5.9
5.4
4.7
3.6
2.8
6.6
5.8
4.7
3.8
3.1
2.6
2.2
4.8
1.9
1.3
Radius
(m)
10
12
14
16
18
20
22
24
26
28
30
32
34
36
0
6.5
6.2
5.9
5.4
4.9
4.5
4
3.3
2.8
2.3
1.9
1.6
0
5
4.8
4.6
4.4
4
3.3
2.7
2.2
1.8
1.5
1.2
0.9
0.7
The charts that have been included have been reproduced from manufacturer specifications, and while every effort has been
made to ensure their accuracy, we do not accept any responsibility for errors or omissions. We also need to draw your
attention to the guidance notes on page 47 to assist you with your crane selection.
CL15
40
Demag AC40
Tonne
City & Low
Headroom Cranes
Runner
Radius
(m)
3
3.5
4
4.5
5
6
7
8
9
10
7.8
151)
151)
152)
152)
153)
8.31)
7.81)
12
7.51)
7.61)
7.61)
6.81)
14
6.22)
5.81)
5.81)
5.81)
16
53)
4.51)
4.81)
4.61)
18
42)
3.91)
3.71)
20
3.42)
3.22)
2.91)
22
2.93)
2.62)
2.32)
24
2.13)
1.92)
26
1.83)
28
HB
Radius
(m)
3
3.5
4
4.5
5
6
7
8
9
10
1.52)
1.23)
152+3)
112+3)
7.8
151)
151)
152)
152)
153)
10.7
15.
151)
151)
151)
151)
13.31)
102)
7.93)
7.52+3)
3.82+3)
2.22+3)
1.42+3)
0.82+3)
31.2
7.21)
61)
12
4.71)
4.81)
4.61)
4.31)
14
3.62)
3.71)
3.51)
3.31)
16
2.93)
2.91)
2.71)
2.51)
18
2.42)
2.11)
1.91)
20
1.92)
1.72)
1.51)
22
1.63)
1.32)
1.12)
24
1.13)
0.82)
26
0.83)
HB
1)
2)
28
CL16
31.2
152+3)
6.82+3)
4.82+3)
2.32+3)
1.22+3)
3)
The charts that have been included have been reproduced from manufacturer specifications, and while every effort has been
made to ensure their accuracy, we do not accept any responsibility for errors or omissions. We also need to draw your
attention to the guidance notes on page 47 to assist you with your crane selection.