Project Report
Project Report
1) INTRODUCTION
1.1Project Description
1.2 Salient features
1.3 Geotechnical risk report
2) NATM
2.1 Introduction
2.2 Seven important features of NATM
2.3 Broad Principles of NATM
2.4 Description of NATM
2.5 Suitability of NATM over TBM
2.6 Components and sequence of execution in NATM
4) Tunnel monitoring
4.1 Introduction
4.2 Pressure cell data and graphs
4.3 Strain meter data and graphs
4.4 Deformation Monitoring point
4.5 Multipoint Extensometer
5) Conclusion
6) Photo Gallery
CHAPTER 01
INTRODUCTION
PROJECT DESCRIPTION:
2
Length(km)
Important/major
bridges
Minor bridges
(Section1)
(Section2)
(Section3)
Udhampur-Katra
KatraQuazigund
QuazigundBaramula
25
148
92
29
27
Tunnel length(km)
10.9
No. of stations
109.54
12
Total
119
292
64
165
640
-------15
696
120.44
30
Item
Udhampur-Katra
Katra-Quazigund
Max.Curvature(degr
ee)
2.75
2.75
2.75
Maximum height of
bridge(m)
85m
359m
13
45m
3.15
11.21
-------
Max. depth of
bank(m)
21
55
9.7
Max. depth of
cutting(m)
20
40
12
Alignment on
curvature
14%
37.83%
14.66%
Longest span(m)
Longest tunnel(km)
154m steel
girder over the
river Jhajjar
QuazigundBaramulla
The project is one of the most difficult projects under taken on Indian
subcontinent. The terrain passes through young Himalayas, which are full of
geological surprise and numerous problems. For execution purpose, project
has been divided into three sub-sections. Construction progress is on its way.
Katra Quazigund leg is most difficult stretch of this project. The alignment
of this stretch which is 148Km long passes through Patni and PirPanjal
ranges.
This alignment requires construction of 92 important/measures bridges and
27 minor bridges, the alignment also requires, interlaid construction of 65
number of tunnels, totaling to a length of 110Kms bringing the percentage of
the total length of the alignment on tunnel to approx. 76%.
CHAPTER
02
NATM
Introduction
NATM was first described as the modern tunneling method by Rabcewick.
This method was developed in Austria from where it got its name. This
method makes use of primary flexible lining of shotcrete, wire mesh, lattice
girders, rock bolts. In case of weaker rock mass the use of pipe fore pole/pipe
roofing is also used for crown support which leads to less outbreak and
ensures safety during the execution of the actual work. The main aspect of
NATM is the dynamic design based on the rock mass classification as well as
8
The New Austrian Tunneling Method includes a number of techniques for safe
tunneling in rock conditions in which the stand-up time is limited before
failure occurs. These techniques include the insect: smaller headings and
benching or the use of multiple drifts to form a reinforced ring made which
the bulk of the tunnel can be excavated. These techniques are applicable in
soft rocks such as shales, phyllite and mudstones in which the squeezing
and swelling problems are likely to occur. The techniques are also applicable
when tunneling in excessively broken rock, but great care should be taken in
attempting to apply these techniques to excavations in hard rocks in which
different failure mechanisms occur.
3.
4.
5.
6.
7.
Measurement
Lining
Closing of invert
Rock mass classification
Dynamic design.
Mobilization of the strength of the rock mass: the method relies on the
inherent strength of rock mass being conserved as the main component of
tunnel support. Primary support is directed to enable the rock to support
itself.
Shotcrete protection: loosening and excessive rock mass deformation
should be by filling a layer of 25-50mm of sealing shotcrete immediately
after opening of the face.
Measurements: Every deformation of the excavation must be measured.
NATM requires installation of sophisticated instruments. These are embedded
in lining, ground such as load cells, extensometers and reflectors.
Primary lining: The Primary lining is thin. It is active support and the tunnel
is strengthened not by thicker lining, but by flexible combination of rock
bolts, wire mesh and lattice girders.
11
2.
3.
Heavily faulted areas and/or wide fault ones are also expected, TBM
may be trapped by ground movement behind the face.
4.
5.
6.
7.
8.
Because of all these reasons NATM was selected for tunneling in PirPanjal
instead of TBM.
Face drilling
Loading/charging and blasting
Defuming
Mucking
Profiling(by total station0
Shotcreting
Erecting lattice girders.
Rock bolting
Face drilling includes the drilling of holes for the gelatin explosive
horizontally in the face of tunnel at every section to be blasted. The holes are
usually drilled in the of 25mm,32mm or 40mm diameter , dependingon the
diameter of explosive pallet/rod to be used. Only a few of the holes drilled in
the tunnel face are actually charged with explosive, rest of them are left as
dummy holes which is very important to maintain the profile of tunnel
section and avoid irregular cutting, over break and undercutting as much as
possible.
Charging is the second step of tunneling after drilling holes. It involves
loading the particular holes with gelatin explosive. After covering the face
with some fiber to prevent scattering out of the stone pallets which may
14
the tunnel wall with the help of boomer. These are cheaper than
other types of rock bolts.
2. Swellex Rock Bolts:
These rock bolts are used at places where too much water comes
out of tunnel wall. This type of bolts is swelled once it is inserted
into the wall with the help of a water jet at high pressure. Diameter
varies from 25-32mm, and length varies from 4-6m.
3. SDA/SDR Bolt:
Self-Drilled Anchor comes with a tungsten carbide alloy bit at its tip
which helps to drill in this bolt into the tunnel wall. SDA is used at
places where Sn bolts cant be driven due to crushed rock mass and
collapse of drilled holes. Diameter of SDA 25mm to 76mm and
length ranges from 4-6m.
16
CHAPTER 03
GEOTECHNICAL AND
GEOLOGICAL
INVESTIGATION OF T74R
17
3.1
Introduction
This chapter includes results of shallow and deep boreholes,
geological logs, and laboratory test results of representative rock
core/samples, standard penetration test (SPT) besides geological
studies around the tunnel T-74 alignment area.
Objective and scope of work:
The objective of the investigation for tunnel T-74R is to generate
a report incorporating subsurface geological data collected from
different boreholes together with limited surface geological
studies carried out along the tunnel alignment.
Another important objective was to prepare geological logs of the
completed boreholes and to prepare geological sections along
the tunnel alignment for future reference and records.
3.2
BOREHOLE:
In total 9 numbers of boreholes, 4 deep and 5 shallow have been
drilled along the tunnel alignment area. Most of these boreholes
have been drilled upslope of the alignment and projected on the
actual tunnel alignment for interpretation and preparation of
geological section. Layout plan of drill holes is attached as fig 3.1
in this report. The summary of boreholes with depth and location
is given in table 3.1.
BOREHOLE DRILLING:
Wire-line rigs which are hydraulic operated are used. Drilling is
carried as per IS 1892 -1979.
Equipment:
Following equipment were used for the execution of the work:
1. Drill rig with accessories and mud circulation pump.
2. Casing of required size.
3. NX size core barrel.
18
Borehole
No.
Elevation
1867.525
Coordinates
Chainage(K
m)
Formation
level (invert)
(m)
Depth(m)
N3695043.383
125.790
1564.097
315.00
128.382
1593.968
415.00
128.759
1598.582
62.00
129.153
1603.317
520.00
132.460
1642.450
60.20
132.496
1642.075
45.10
133.018
1648.856
36.00
133.031
1649.703
85.20
133.089
1649.703
85.20
(m)
E512930.391
2
1989.339
N3694573.992
E515062.361
1915.916
N3694397.190
E515402.385
2112.570
N3694179.892
E515732.904
5A
1692.707
N3694957.932
E517665.796
5B
1677.039
N3694992.593
E517711.077
1712.743
N3695576.809
E517796.357
6A
1712.473
N3695578.950
E517796.388
1723.913
N3695576.950
E517796.388
Field Execution:
Wire-line rig is used for drilling. The diameter of the borehole in soil was
100/150mm. Casing was used to protect the bore hole from the side
collapse. Initially guide casing is provided and further boring was carried out
of 100/150mm dia. size in soil. SPT, DS I conducted as per specification or as
per direction of engineer in charge. Whenever rock is encountered, NX/NQ
core barrel is used to collect the rock samples. The SPT, DS and rock sample
are preserved into core boxes with labels. Rotary drilling machines uses a
rotary action combined with downward force to grind away the material in
which a hole is being drilled.
Rotary drilling machine requires a combination of a number of elements
1. A drilling machine or a rotary drill at the ground surface which delivers
torque and thrust.
20
2. A flush pump, which pumps the fluid down the hole in order to cool the
mechanical parts and lift the cutting of the rock to the ground surface
as drilling proceeds.
3. A string of hollow drill rods, which transmit torque from the rig and
flush the fluid from the flush pump to the bottom of the hole
4. And a drilling tool for example core barrel which grinds away the rock
and in addition may be designed to take a sample.
Wire line drilling is a technique which has been used widely for deep drilling
for many years, principally because it reduces the trip time (i.e. time
required to extract the core tube from the bottom of the hole, empty the core
and replace the core tube). This technique has proved to be very effective in
coring of the relatively difficult deposits such as over consolidated clays,
chalks and interlayer sands, gravel, limestone and clays.
vertical position. The outer barrel s turned by the rig, as flush is pumped
down it. The latching mechanism holds the inner barrel down but does not fix
it so that it must rotate with the outer barrel. When the outer and inner
barrels have been drilled for the length of the run, the wire line is winched
upwards. The inner barrel and the core are hoisted to ground surface, where
the core is extracted band a new length of outer barrel is added to the string.
22
Lithography
Soil, clay, sand, pebbles etc.
Age
-------------
Pliocene and
Pleistocene
Siwalik
Miocene and
Pleistocene
----------
-----------------
Murree
------------Vihi
Zewan
Panjal volcanic
Agglomerate slate
Murree thrust
Limestone and shale
Limestone, slate and flagstone
Basic lava flow
Miocene to Oligocene
--------------Triassic to Jurassic
Miocene to Oligocene
Permian
Upper carbonaceous
Fenestella shale
Middle carbonaceous
Syringotheris
Limestone
Machal
Lower carbonaceous
CambroSilurian
24
Ramban
Phyllite, carbonaceous,
phyllite/slate, quartzite and
limestone
Phyllite, slate, quartzite, gypsum
Carbo-silurian
Proterozoic
-----------------------------------------------Panjal
Thrust--------------------------------------------------------Salkhala
Proterozoic
Lithological unit
Abstract
Trikuta
Reasi thrust
Fault zones
Dolomite
Completely fractured
Quartzite
Intermediate layers of shale
Fault zones
26
fractured in nature. Weathering grade of the rock is between W/I to W/IV. The
tunnel alignment area is covered by hill wash and debris material. The area
all along the alignment is slide prone. The general trend of rock mass varies
from N700W-S700E to N300W-S300E with dip 400 to 700 north easterly. Wide
variation in dip and strike indicates that the rock have undergone intense
deformation due to folding and faulting. Generalized geological map of the
area has been prepared (after AMBERG) and using borehole data with limited
traverse studies.
Fault:
The proposed tunnel may intercept faulted contact between Ramsu
formation and Machal formation around chainage 132.650km at tunnel
formation level. Heavy ingress of water together with the abnormal over
break is expected in this section.
Fold:
The anticline fold is suspected roughly along the Mohmangat Nala. This is
indicated by variabledip of rocks along both the banks of Nala, however this
fold is located from the tunnel alignment.
3.5 Subsurface Exploration by Drill Holes:
BH-01: Drilled at chainage of 125.790km reveks 69m thick overburden. From
0.00m to 20m, over burden consists of hill slope debris material consisting of
highly weathered fragments/rock cutting of quartz, phyllite intermixed with
greyish brown silt clay matrix and from 20m to 69m overburden consists of
light greyish to whitish color rock fragments of phyllite with iron oxide
leaching and wash material. The overburden appears to be an old slide zone.
From 69m-124m depth the bedrock consist of fine grained, light grey to grey
colored, highly fractured phyllite with 600 to 650 foilation. Quartz veins and
limonitic staining is seen at places. From depth 124m-145m depth, phyllite
and quartzite are recorded. Phyllite is light grey to grey in color, the rock is
highly fractured from 145m-227m, greyish to dark greyish in color, inclined
jointed, highly fractured and foliated quartzite phyllite is recorded. Light grey
to grey colored,
31
Here blast induced fractures are not included in the estimation of the Jv
Q System:
Large part of the tunnel alignment constitutes entirely Ramsu formation
comprising phyllite, quartzite phyllite, with subordinate carbonaceous
phyllite, quartzite and limestone bands and Machal formation constituting
entirely by phyllite and slates with rare limestone and agglomerate
interbands. Therefore, Q value and RMR classification has been calculated
in respect of phyllite, quartzite phyllite and slate which are crossing major
part of the tunnel alignment.
On the basis of an evaluation of a large number of case histories of
underground excavations, Barton et al (1974) of the Norwegian Geotechnical
Institute proposed a tunneling Quality Index (Q) for the determination of rock
mass characteristics and tunnel support requirements. The numerical value
of the index Q varies on a logarithmic scale from 0.001 to a maximum of
1,000 and is defined by:
Q= (RQD/Jn) x (Jr/Ja) x (Jw/SRF)
Where RQD is the rock Quality Designation
Jn is the joint set number
Jr is the joint roughness number
Ja is the joint alteration number
Jw is the joint water reduction factor
SRF is the stress reduction factor
should be several times this size and the smallest fragments less than half
the size.
Geo-mechanics
classification
Classification/RMR
The first five of these parameters are grouped into five ranges of values
which are assigned specific rating to reflect their influence on total rock mass
quality. The rating of sixth parameter is considered depending on orientation
of tunnel with respect to the strike and dip of the formation to arrive at the
final rock mass classification. By adding the relevant rating of the above
parameters , RMR has been calculated for the dominant type of rock mass
crossing the tunnel alignment.
37
38
Table 3.6: Support system corresponding to rock quality given in RMR system
Rock mass
class
Exacavation
shotcrete
Steel sets
I-Verygood
rock
Locally, bolts in
crown 3m long
spaced 1.5-2m
with occasional
wire mesh.
50mm in
crown where
required.
None
Systematic bolts
4m long, spaced
1.5-2m in crown
and walls with
wire mesh in
crown.
50-100mm in
crown and
30mm in
sides.
None
Systematic bolts
4-5m long,
spaced 1-1.5m in
crown and walls
with wire mesh.
100-150mm
in crown and
100mm in
sides.
Light to
medium
ribs spaced
1.5m where
required.
RMR: 81-100
II- Good rock
RMR: 61-80
RMR: 21-40
39
RMR: <20
Install support
concurrently with
excavation. Shotcrete as
soon as possible after
blasting
Systematic bolts
5-6m long,
spaced 1-1.5m in
crown and walls
with wire mesh.
Bolt invert
150-200mm
in crown,
150mm in
sides and
50mm on
face.
Medium to
heavy ribs
spaced
0.75m with
steel
lagging and
forepoling if
required.
Close
invert.
Parameters
Value
Rating
50-100mpa
Spacing of discontinuities
>60mm
RQD
<25%
Condition of discontinuities
Persistence
1-3mm
Aperture
1-5mm
Roughness
Smooth
Filling
Soft
weathering
Moderately
Damp
5
10
-2
Total rating
34
Poor
Rock class
IV
40
Parameters
Value
Rating
100-250mpa
12
Spacing of discontinuities
>60mm
RQD
<25%
Condition of discontinuities
Persistence
1-3mm
Aperture
>5mm
Roughness
Smooth
Filling
Soft
weathering
Slightly
weathered
Wet
Favorable
-2
Total rating
37
Poor
Rock class
IV
41
Parameters
Value
Rating
100-250mpa
12
Spacing of discontinuities
>60mm
RQD
<25%
Condition of discontinuities
Persistence
1-3mm
Aperture
>5mm
Roughness
Smooth
Filling
Soft
weathering
Highly
weathered
Wet
Favorable
-2
Total rating
33
Poor
Rock class
IV
Safe Bearing Pressure: Safe Bearing Pressure (SBP) of the rock mass has
been calculated by using RMR system. SBP has been calculated for phyllite
and quartziticphyllite of Ramsu formation and phylliye/slate of Machal
formation. All the above rock types fall in poor category with total rating of
34, 37 and 33, respectively. It is recommended that during construction. The
net SBP calculated on the basis of RMR system is given in table 3.10 below:
42
II
III
IV
Description of
rock
Very good
Good
Fair
Poor
Very good
RMR
100-81
80-61
60-41
40-21
20-0
Qs (MP)
6.0-4.5
4.5-2.9
2.9-1.5
1.5-0.6
0.6-0.4
Stand up time based on RMR classification has been calculated for both the
rock formation. The standup time for tunnel excavation may be taken as 10
hours for 2.5 span.
43
Permeability Tests:
Double packers tests have been conducted in the northern end of the tunnel
alignment towards Banihal, in BH-5A, BH-5B, BH-7.the tests have been
carried out to determine permeability of the rock mass at different depths, as
per IS-5529 specification .the formation grade lies between 40m to74m
below ground surface in this section.
S.N
O.
Borehole
No.
Depth
Core
No.
Rock Type
Remark
01
5A
29.8031.00
109
Fresh
slatyphyllite
Fine grained
schistose texture
02
5A
35.0035.70
123
Fresh
slatyphyllite
Fine grained
schistose texture
03
5A
46.0047.00
169
Fresh
slatyphyllite
Fine grained
schistose texture
04
5A
49.0050.00
185
Fresh
slatyphyllite
Fine grained
schistose texture
44
Rock Bursting/Squeezing:
In Himalayas the phenomena occurs in deep tunneling in the areas of active
in-situ stresses. As per calculation based on thickness of rock mass over the
tunnel and Q value, the alignment lies in the safer zone. However this
phenomenon can also occur at shallow depths where the rock are highly
fragile and fractured andfolded. Suitable remedial measures may be kept in
readiness for such situation.
45
Over-break:
Considering the poor quality of the rock, excessive over break/chimney
formations are likely to occur. Remedial measures are grouting and heavy
support may be kept in readiness.
CHAPTER 04
46
TUNNEL
MONITORING
4.1 Introduction
Monitoring section consists of 3D monitoring ponits (DMP), Strain meters,
Pressure cells and Multipoint (3 Point and 2 Point) extensometers. In tunnel
monitoring these instruments are installed at proper sections after primary
Shotcreting to measure the deformation, squeezing and lateral and
longitudinal shifting of tunnel till the tunnel gets stabilized. The read out unit
gives readings of pressure cells, Strain meters and MPBXs directly in
engineering units and final linning is given to the tunnel section. The details
of the instrument are given below.
STRAIN METERS
Strain has no units and we calculate it in micro strains (s)
Readings in s= [(F.R in digits I.R in digits) x G.F]
digit/mm
where G.F is in
47
LR initial reading is taken after the installation of the strain meter on the wire
mesh/lattice girder (before Shotcreting). This is also called the zero reading.
This reading is subtracted from the subsequent reading which is taken after
shotcreting.
F.R is final reading taken after shotcreting.
G.F gauge factor is provided with every instrument by the manufacturer. It is
different for each instrument.
Range of strain meter is 1500 micro strain. ve sign indicates compressive
strain and +ve sign indicates tensile strain.
Five- three pairs of strain meters have been installed. One pair on crown, 2 nd
on left and 3rd on the right hand side. For crown the strain meters are names
as SS1I and SSM 1O where 1 indicates crown position and I and O for the
outer strain meters, similarly SSM 2I for the left side and SSM 3I-3O for the
right side.
48
1. PRESSURE CELLS
Pressure cells are fixed on the lattice girders. These measures the pressure of
rock mass coming on the lattice girder and pressure is indicated on the
portable Readout unit in MPa.
For pressure cell RPC-1 for crown (Radial pressure cell), RPC-2 for the left
side and RPC-3 for the right side.
49
2. M.P EXTENSOMETER
In tunnel T-74R, 2-3 point extensometers are being installed. The sensors are
attached to the connecting fiber glass rods at the mouth of MPBX housing.
The convergence/divergence of surrounding rock is measured on the
portable Readout unit in mm.
MRE 1-6
MRE 1-3
MRE 2-9
MRE 2-6
MRE 2-3
MRE 3-9
MRE 3-6
MRE 3-3
51
52
53
54
55
56
57
58
59
60
61
62
63
64
SM-3
S2
Location
Chainage:7247.25
Position : 19:30Hrs
Read out
Unit
Observation
S.No.
1
2
3
4
5
6
7
8
9
10
11
Date
18-032013
19-032013
20-032013
23-032013
26-032013
01-042013
03-042013
17-042013
22-042013
29-042013
02-052013
SM2-I
SM2-O
Time
Remarks
Ch. No.
273(e)
0.00
Ch. No.
274(e)
0.00
6.20
-35
13.00
-34
-104
13.21
Reading before
shotcrete
Reading before
shotcrete
Excavation in progress
-50
-120
9:21
Excavation in progress
-90
-134
12.12
-123
-145
10.30
-135
-150
11.40
-140
-160
12.34
-136
-172
12.21
-180
-223
12.10
-176
-226
11.44
65
04-052013
-168
12-06-2013
14-06-171
2013
19-06-165
2013
21-06-163
2013
24-06-161
2013
10-06-159
2013
28-10-257
2013
29-10-257
2013
29-10-256
2013
26-11-256
2013
29-11-255
2013
04-11-214
2013
13-11-172
2013
04-12-178
2013
13-12-212
2013
16-12-214
2013
27-12-258
2013
11-01-259
2014
18-01-258
2014
25-01-260
2014
01-02-258
2014
10-02-261
2014
13-02-278
-334
11.22
-168
-347
-352
10:32
-320
11:26
-340
11:09
-342
11:15
-339
11:35
-335
11:41
-328
11:50
-438
12:00
-451
12:30
-441
12:24
-442
11:00
-440
11:16
-406
11:20
-392
11:34
-392
11:30
-444
11:11
-452
11:40
-454
12:14
-458
12:20
-454
12:44
-456
13:28
-459
12:44
11:34
66
DATE
Change in
Easting from
initial(x)(mm)
Change in easting
from initial
elevation(z)
Change in
northing from
initial (y)
14-06-2013
0.0
0
0.00
0.00 0.00
0.00
0.00
0.00
0.00
0.00
15-06-2013
4.0
0
6.00
5.00 -2.00
-1.00
-1.00
2.00
-1.00 3.00
17-06-2013
6.0
0
7.00
4.00 -3.00
-2.00
-2.00
3.00
-2.00 3.00
19-06-2013
7.0
0
8.00
4.00 -4.00
-3.00
-3.00
1.00
-3.00 4.00
21-06-2013
6.0
7.00
4.00 -4.00
-3.00
-3.00
0.00
-2.00 3.00
67
0
24-06-2013
6.0
0
7.00
4.00 -5.00
-3.00
-3.00
1.00
-1.00 3.00
25-06-2013
7.0
0
7.00
3.00 -4.00
-3.00
-3.00
0.00
-2.00 3.00
27-06-2013
8.0
0
8.00
3.00 -4.00
-3.00
-3.00
1.00
-3.00 4.00
28-06-2013
7.0
0
7.00
4.00 -4.00
-3.00
-3.00
1.00
-1.00 4.00
29-06-2013
6.0
0
7.00
4.00 -4.00
-3.00
-3.00
1.00
-2.00 3.00
01-07-2013
7.0
0
8.00
3.00 -4.00
-3.00
-3.00
0.00
-2.00 4.00
01-07-2013
6.0
0
8.00
4.00 -4.00
-3.00
-3.00
0.00
-3.00 4.00
01-07-2013
7.0
0
8.00
3.00 -4.00
-3.00
-3.00
1.00
-2.00 3.00
01-07-2013
600
7.00
3.00 -4.00
-3.00
-3.00
1.00
-2.00 4.00
01-07-2013
7.0
0
8.00
4.00 -4.00
-3.00
-3.00
0.00
-2.00 3.00
Section
S3
Location
Read out
Unit
Observation
S.No.
1
2
3
4
5
6
7
8
9
10
11
12
13
Date
02-032013
02-032013
02-032013
02-032013
02-032013
02-032013
02-032013
02-032013
02-032013
02-032013
02-032013
02-032013
02-032013
Time
Remarks
MRE 19
Ch.
260(m
m)
0.00
MRE 16
Ch.
261(m
m)
0.00
MRE
1-3
Ch.
262(m
m)
0.00
12.00
0.02
0.01
0.02
10.23
0.03
0.02
0.02
11.00
0.01
0.01
0.01
11.34
0.01
-0.02
0.00
11.40
0.00
0.00
0.00
11.50
0.00
0.00
0.01
12.12
0.00
0.00
0.00
12.23
0.00
0.00
0.00
13.12
-1.00
-1.00
-1.00
13.10
-1.00
0.00
0.00
11.56
-1.00
-1.00
-1.00
11.40
-1.00
0.00
-1.00
11.23
69
04-032013
06-032013
07-032013
09-032013
10-032013
11-032013
12-032013
13-032013
14-032013
15-032013
16-032013
18-032013
21-032013
22-032013
24-032013
28-032013
29-032013
30-032013
03-062013
05-062013
10-082013
13-082013
15-082013
-1.00
-1.00
0.00
11.30
0.00
0.00
0.00
11.55
-1.00
-1.00
-1.00
12.12
-0.02
0.01
-0.02
13.11
-0.01
-0.01
-0.01
13.00
-0.01
-0.02
-0.02
12.18
-0.02
-0.03
-0.03
12.44
-0.01
-0.02
-0.02
11.55
-0.01
-0.01
-0.02
11.44
-0.03
-0.03
-0.04
11.12
-0.08
-0.08
-0.07
10.53
-0.09
-0.09
-0.09
10.40
-0.09
-0.07
-0.09
14.10
-0.09
-0.07
-0.10
10.23
-0.09
-0.10
-0.10
10.40
-0.10
-0.09
-0.10
11.40
-0.10
-0.09
-0.10
12.40
-0.10
-0.09
-0.10
14.21
-0.09
-0.09
-0.10
14.12
-0.09
-0.09
-0.09
11.40
-0.09
-0.09
-0.08
12.45
-0.09
-0.09
-0.10
11.50
-0.09
-0.09
-0.09
10.20
70
17-012014
19-012014
10-022014
-0.09
-0.09
-0.09
10.50
-0.09
-0.09
-0.10
11.43
-0.09
-0.09
-0.09
10.22
05
CONCLUSION
71
Conclusion
a) T-74R consists of main tunnel and and escape tunnel connected to each
other by CPBs.
b) The rock mass in PirPanjal range is highly inhomogeneous hence NATM
was adopted
c) Extensive geological and geotechnical investigation was carried to decide
the design criteria.
d) The overall rack mass is fair, hence light lattice girder and rock bolting
was done.
e) Subsurface exploration by boreholes along T-74R alignment was carried
out to understand quality of rock mass at the formation grade.
f) The bulk composition of rock mass of Ramsu and Machal formation is
commonly
phyllite with minor quartzite, phyllite/slatyphyllite and agglomerate slate.
g) The rocks are thinly foliated, highly fragile and fractured in nature and
intensely deformed due to faulting and folding.
h) Core recovery varies from 0 to 99% and RQD from O to 95%. The Q value
of phyllite, quartziticphyllite of the formation varies between 0.33 to 0.83.
i) Recommended maximum unsupported span of phyllite varies from 1 to 2
m for poor rock class.
j) RMR for phyllite, quartziticphyllite varies from 33 to 37 for poor rock class.
k) On the basis of RMR stand up time may be 10 hrs. For 2.5m span.
m) The soil is inhomogeneous in Present 0356 hence NATM is Preferred over
TBM.
n) The deformation, squeezing and lateral movements of tunnel were
observed and it was found that deformations were within permissible limits
in almost all cases.
72
06
PHOTO GALLERY
73
74
75
76