8 Thickness and Tonnage Control
8 Thickness and Tonnage Control
Paving Report
CHAPTER EIGHT:
THICKNESS AND TONNAGE CONTROL
The thickness and width of the paving operation are shown on the typical
sections in the contract plans or the proposal. The actual compacted
thickness of the mat is required to conform to the planned design. The
design thickness is determined so the pavement is strong enough to carry
the anticipated traffic. If the mat is too thin, the pavement will likely fail
prematurely. If the mat is too thick, the pay quantities will overrun and
increase the cost of the contract unnecessarily.
The thickness of the mat is checked by verifying the uncompacted
thickness behind the paver and by verifying the actual rate of spread.
The plans specify the rate in pounds per square yard that the HMA is to be
placed. This is known as the "Planned Quantity". The planned quantity is
used in checking the thickness and the rate of speed.
Example 2:
Planned quantity = 165 lb/yd
165 = 1.5 inches = 1 inches
110
The mat thickness for 165 lb/yd would be approximately 1 1/2 inches.
DEPTH CHECKS
Ensuring that the actual amount of mix placed by the Contractor complies
with the plans is the responsibility of the HMA Technician. The
Technician is required to collect weigh tickets as the mix is delivered to
the paving site and keep a record of the actual amount of mix placed. This
record allows the Technician to determine the "Placed Quantity" and
compare this quantity to the "Planned Quantity".
The Technician is required to compute the actual rate of spread and
compare this rate to the planned rate. The planned rate is typically shown
on the plans in pounds per square yard. The actual rate of spread may be
computed in pounds per linear foot, tons per linear foot, or pounds per
square yard. Both the planned and actual rates are required to be in the
same units for valid comparisons. The PE/PS is consulted for the
preferred method.
8-2
A weigh ticket which shows the net weight of the material is required to
be furnished for every load of mix delivered to the paving site. The weigh
ticket is issued to the truck driver at the weighing site and is required to be
signed by the INDOT Weighman supervising the Contractors weighing
operations. However, when the Contractor is using computerized scales
there is not a requirement for a weighman and the tickets are delivered to
the contract unsigned.
The HMA Technician is required to collect a weigh ticket for each load
from the truck driver at the same time the material is unloaded at the
paving site. Upon taking the ticket, the Technician is required to:
1)
2)
Write on the ticket the starting station of the load and the
lane (right, left, or center) where the material is placed. A
preferred method of designating lanes is EBPL (eastbound
passing lane), EBDL (eastbound driving lane), etc.
8-3
3)
4)
At any time during the day and at any point along the roadway, the
number of tons of mix that has been dumped into the paver is required to
be known.
COMPUTING RATES OF SPREAD
As stated above, there are several methods of computing the actual rate of
spread. The calculations differ primarily in the units in which the rates are
expressed. The three methods are:
1)
2)
3)
For a width of 12 ft as shown in the above diagram, the square yards per
linear foot would be:
1 x 12 = 1.33 yd2/lft
9
8-4
Examples of the three methods of checking the actual rates with planned
rates are as follows. The diagram below indicating the amount paved and
quantities used applies to all three examples.
2)
3)
8-5
4)
5)
The planned quantity equals 330 lb/yd. The placed quantity of 312.9
lb/yd is less than the planned quantity indicating an underrun and a mat
that is too thin. The Contractor is required to make the necessary
adjustments.
After load 10, the paver is at Station 20+00 and 500,000 pounds have been
placed.
Total length = (20+00) (10+00) = 1000 lft
Area = (1000 x 12) / 9 = 1333 yd
Placed Quantity = 500,000 / 1333 = 375 lb /yd
The placed quantity of 375 lb/yd is greater than the planned
quantity indicating an overrun.
After Load 20, the paver is at Station 32+70 and a total of 1,000,000 lb
have been placed.
Total length = (32+70) (10+00) = 2270 lft
Area = (2270 x 12) / 9 = 3027 yd
Placed quantity = 1,000,000 / 3027 = 330.4 lb/yd
The placed quantity equals the planned quantity indicating the
spread rate is correct.
Method 2 Pounds per Linear Foot
The planned quantity is 330 lb/yd
1) Convert the planned quantity from lb/yd to lb/lft
length of one foot x width paved = 1 x 12 = 1.33 yd/lft
9 ft/yd
9
planned quantity x yd/lft = 330 x 1.33 = 440 lb/lft
8-6
2) Total the weights of the loads placed in pounds to the point where
the check is made.
The total of the first five loads equals 240,000 pounds
3) Determine the total length paved in linear feet
Loads 1 through 5 began at Station 10+00 and end at Station
15+75
(15+75) - (10+00) = 575 lft
8-7