Annual Maintenance of CSD Pet Line
Annual Maintenance of CSD Pet Line
9/20/14
Project Management
Contents
Project Proposal: ........................................................................................................................................... 2
Project Scope: ............................................................................................................................................... 2
Project Objectives: ........................................................................................................................................ 2
Work Breakdown Structure: ......................................................................................................................... 2
Responsibility Matrix: ................................................................................................................................... 2
Project Scope ................................................................................................................................................ 3
Project Objectives ..................................................................................................................................... 3
Project Deliverables .................................................................................................................................. 3
Milestones................................................................................................................................................. 3
Technical Requirements............................................................................................................................ 3
Risk Assessment of Annual Maintenance Project ..................................................................................... 4
Time related risks ...................................................................................................................................... 4
A.
B.
C.
Table 1. Defined Conditions for impact scales of a risk on Major Project Objectives ............................... 6
Table 2. Probability v/s Impact of above mentioned time, cost, scope and quality related risks of
projects ......................................................................................................................................................... 7
Table 3. Activity Description of Project ........................................................................................................ 9
Figure 1. Gantt Chart Of various Activities Of Project ......................................................................... 10
Figure 2. CPM Diagram ........................................................................................................................ 11
Table 4. Responsibility Matrix Of Project .................................................................................................. 12
Table 5. Work Breakdown Structure & Costs .......................................................................................... 14
Project Proposal:
A project proposal is a detailed description of a series of activities aimed at solving a certain
problem. In order to be successful, the document should provide a logical presentation of a
research idea.
Project Scope:
Project scope is the definition of end result or mission of your project a product/service for your
client/customer. The primary purpose is to define as clearly as possible the deliverable(s) for the
end user and to focus project plans. As fundamental and essential this scope definition occurs, it
is frequently overlooked by project managers of well-managed, large corporations. To ensure
that the scope definition is complete, following checklist can be followed
Project Objectives
Deliverables
Milestones
Technical Requirements
Limits & exclusions
Reviews with Customer
Project Objectives:
Project objectives are those points which have to be accomplished from the project. The
objectives stated in the project must be precise and should be made keeping the stakeholders
interest in mind. The objectives must clearly show whats in it for the stakeholders.
Responsibility Matrix:
In this matrix responsibility is assigned to each person responsible for a particular activity in the
project. With the help of this matrix project manager could follow up all activities by
maintaining the communication to person responsible for their respective activities.
Project Scope
Project Objectives
Project Deliverables
Milestones
Technical Requirements
To increase the overall Owen efficiency to increase the power factor to .96
To increase the blowing efficiency of Blow Molder from 82% to 88%
To increase the pre-form yield from 98.7% to 99.3%
Reducing the rejection due to filling level from Filler machine from 2% to 1.6%.
To increase the Capper Yield from 98% to 99%.
To improve the seven critical factors of packaging from 87% to 91%.
Project Objective
Cost
Time
Scope
Quality
1
Very Low
Insignificant Cost
Increase
Insignificant time
increase
Scope decreases
barely noticeable
Quality degradation
barely noticeable
2
Low
<5% cost increase
2 days increased
Minor areas of
scope affected
Only very
demanding
applications are
affected
3
Moderate
5-10% cost
increase
2-5 days
increased
4
High
10-15% cost
increase
5-10 days
increased
5
Very High
>20% cost
increase
>10 days
increased
Major areas of
scope affected
Very High
Probability
High
Probability
Moderate
Probability
Low
Probability
Very Low
Probability
Probability
Impact
T-C
T-A
T-B/C-A
S-A
Q-A
Very Low
Impact
Low
Impact
Moderate
High
Very
High
Activity
Rotory
Brake Unit
Base Cam
Transmission Body
Bell Nozzle Cylinder
Base Mold Support
Stretching Cylinder
Transfer Arm Assembly
Oven Section Hydraulic
Console Assembly
Compensation Valves
Preblow Valves
Mold Locking
Star
Lift Cylinder
Lever
Rinser
Valve Maintenance
Capper
Support of Tulip
Electrical
Mechanical Operations
Level Probe
Vacuum Drum
Hose Pipe
Infeed Worm
Glue Roller
Main Block
Vacuum Drum 1
Centering Turret
Cutter Assembly
Vacuum Distribution
Glue Roller 1
Heater
Applicator
Brake Unit 1
Guide
Air Conveyor
Blower
FRL Unit
Head Assembly
Article Conveyor
Activity
time
Predecessor 1
3
2
2
2
2
2
1
2
2
1
2
2
2
2
2
1
2
2
2
2
2
3
2
5
8
9
6
2
6
3
6
2
5
5
2
3
4
6
4
2
5
6
Rotory
Brake unit
Base Cam
Transmission Body
Bell Nozzle Cylinder
Base Mold Support
Stretching Cylinder
Transfer Arm Assembly
Oven Section Hydraulic
Console Assembly
Compensation Valves
Preblow Valves
Lift Cylinder
Lever
Rinser
Valve Maintenance
Capper
Support of Tulip
Electrical
Mechanical Operations
Level Probe
Vacuum Drum
Hose Pipe
Infeed Worm
Glue Roller
Main Block
Vacuum Drum
Main Block
Cutter Assembly
Vacuum Distribution
Glue Roller
Heater
Applicator
Brake Unit
Guide
Air Conveyor
Blower
FRL Unit
Head Assembly
Predecessor 2
Predecessor 3
Brake Unit
Brake Unit
Base Cam
Base Cam
Brake Unit
Console Assembly
Brake Unit
Star
Lift Cylinder
Rinser
Capper
Support of Tulip
Electrical
Level Probe
Vacuum Drum
Hose Pipe
Hose Pipe
Vacuum Drum
Cutter Assembly
Mold Locking
Lever
Lift Cylinder
Rinser
Level Probe
Electrical
Warmer Conveyor
Conveyor Bend
Warmer Comb
SU System
Dry Run
Quality Results
3
4
3
4
1
2
Article Conveyor
Warmer Conveyor
Conveyor Bend
Warmer Comb
Warmer Comb
Dry Run
Glue Roller 1
Brake Unit 1
Project Team
MACHINES
Blow Molder
1.1 Rotory
1.2 Brake Unit
1.3 Base Cams
1.4 Transmission Body
1.5 Bell Nozzle Cylinder
1.6 Base Mould Support
1.7 Stretching Cylinder
1.8Transfer Arm Assembly
1.9Oven Section Hydraulic
1.10Console Assembly
1.11 Compensation Valves
1.12Preblow Valve Air Leakage
1.13Mold Locking assembly
R
S
R
R
S
R
R
S
R
S
S
S
R
S
S
R
S
R
R
S
S
R
S
R
S
R
S
R
S
R
S
S
S
S
S
R
S
S
S
S
S
S
S
R
S
S
R
S
R
S
R
S
2. FILLER
2.1Star
2.2Lift Cylinder
2.3Lever
2.4Rinser
2.5Valve Maintenance
2.6Capper
2.7Support Of Tulip
2.8Electrical
2.9Mechanical Operation
2.10Level Probe
R
S
R
R
S
S
R
R
S
R
S
R
S
R
R
R
R
S
R
S
3. LABLER
3.1Vacuum Drum
3.2Hose Pipe
3.3Infeed Worm Assembly
3.4Glue Roller assembly
3.5Main Block
3.6Vacuum Drum Assembly
3.7Centering Turret Guide Assembly
3.8Cutter assembly
3.9Vacuum Distribution
3.10Glue Roller Assembly
3.11Heaters
3.12Applicator
R
R
S
R
S
S
R
R
S
S
S
S
R
S
S
S
R
R
R
S
S
R
S
R
S
S
R
S
R
R
S
S
R
S
R
R
4. UNSCRAMBLER
4.1Brake Unit
4.2Guide (2lt)
4.3Air Conveyor
4.4Blower
4.5Frl Unit Air Leakage
R
S
R
R
R
S
R
S
S
S
5. CASER
5.1 Head Assembly
5.2Article Conveyor
R
S
S
R
R
S
S
R
R
S
7.DRY RUN
7.1Blow Molder Trial Run
7.2Filler Trial Run
7.3Labler Trial Run
7.4Unscrambler Trial Run
7.5Caser Trail Run
R
R
S
R
S
S
S
R
S
R
R
8.QUALITY RESULT
MACHINES
1. DISASSEMBLING
2. MAINTENANCE OF MACHINES
2.1 BLOW MODLER
2.1.1 Rotory
2.1.2 Brake Unit
2.1.3 Base Cams
2.1.4 Transmission Body
2.1.5 Bell Nozzle Cylinder
2.1.6 Base Mould Support
2.1.7 Stretching Cylinder
2.1.8Transfer Arm Assembly
2.1.9Oven Section Hydraulic
2.1.10Console Assembly
2.1.11 Compensation Valves
2.1.12Preblow Valve Air Leakage
2.1.13Mold Locking assembly
2.2 FILLER
2.2.1Star
2.2.2Lift Cylinder
2.2.3Lever
2.2.4Rinser
2.2.5Valve Maintenance
2.2.6Capper
2.2.7Support Of Tulip
2.2.8Electrical
2.2.9Mechanical Operation
2.2.10Level Probe
DAYS COST
8
400000 TOTAL COST
6350000
47
5500000
1500000
200000
150000
150000
200000
300000
200000
100000
100000
40000
15000
20000
12000
13000
1000000
200000
150000
100000
40000
30000
30000
350000
30000
20000
50000
2.3.1Vacuum Drum
2.3.2Hose Pipe
2.3.3Infeed Worm Assembly
2.3.4Glue Roller assembly
2.3.5Main Block
2.3.6Vacuum Drum Assembly
2.3.7Centering Turret Guide Assembly
2.3.8Cutter assembly
2.3.9Vacuum Distribution
2.3.10Glue Roller Assembly
2.3.11Heaters
2.3.12Applicator
700000
15000
1700
40000
30000
50000
100000
120000
18000
200000
20000
19000
86300
2.4. UNSCRAMBLER
400000
2.3 LABLER
2.4.1Brake Unit
2.4.2Guide (2lt)
2.4.3Air Conveyor
2.4.4Blower
2.4.5Frl Unit Air Leakage
120000
40000
50000
150000
40000
2.5. CASER
600000
400000
200000
1300000
800000
500000
2.6.1Warmer Conveyor
2.6.2Su System
3. ASSEMBLING
400000
4.DRY RUN
50000
12000
7000
5500
22000
3500
Summary
The above data is an Annual Maintenance Project of CSD Pet Line, one of the beverage line in PepsiCos
manufacturing plant in India. The production ends in the month of November and the entire beverage
line goes for the maintenance work which lasts for 2 months. The annual maintenance is considered to
be one of the most important task because the quality of maintenance done will help the plant to perform
as per the AOP Targets for the upcoming year, as well as this time is the only time when the demand of
the product is low due to chilling winters and the company can afford a shutdown of 2 months.
The maintenance of the line is done in an old traditional way which generally depends on the experience
and knowledge of few of the operators and production engineers. In this project we have applied few of
the theoretical knowledge of Project Management in order to change the style and reduce the projects
risk. The entire work is divided into small packages and these work packages are then allocated to
Operators and Production Engineers in terms of Primary Responsibility and Secondary Responsibility. The
various risks associated with the project are analyzed and they are segregated in terms of Impact and
likely hood of occurrence.
The network diagram shows that the entire project will take 67 days and there are 20 critical activities
which needs special attention as they fall on the Critical Path, these activities must be given special
importance in order to prevent the maintenance to extend beyond the deadline.