RPCL Nit Technical Specification
RPCL Nit Technical Specification
PREPARED BY:
MARCH 2011
PART A
R3
10-03-2011
Final Issue
S.K.A
J.K.K
K.B
R2
10-02-2011
Revised Issue
S.K.A
J.K.K.
K.B.
R1
08-12-2010
Revised Issue
S.K.A
J.K.K.
K.B.
R0
03-08-2010
Draft Issue
S.K.A
J.K.K.
K.B.
Rev
Date
Description
Prepared By
Checked
Approved By
REV. NO.: R3
PAGE 2 OF 506
TABLE OF CONTENTS
SECTIONS
1.0
PAGE
MECHANICAL ................................................................................. 7
1.1.1 General........................................................................................ 7
1.1.2 Coal Unloading System ................................................................ 8
1.1.3 Coal Crushing System .................................................................. 8
1.1.4 Coal Bunkering System .............................................................. 10
1.1.5 Coal Stacking and reclaiming System ......................................... 10
1.1.6 Coal blending system ................................................................ 12
1.1.7 Manual unloading system .......................................................... 12
1.1.8 Coal area Drainage system......................................................... 13
2.0
1.2
ELECTRICAL.................................................................................. 13
1.3
MECHANICAL ............................................................................... 16
2.2
ELECTRICAL.................................................................................. 23
2.3
2.4
CIVIL ............................................................................................ 32
3.0
4.0
4.2
MECHANICAL ............................................................................... 41
4.1.1 Rated and design capacity ......................................................... 41
4.1.2 Standards/Codes ....................................................................... 42
4.1.3 Specification of Equipment ........................................................ 43
ELECTRICAL.................................................................................. 86
REV. NO.: R3
PAGE 3 OF 506
4.3
4.4
5.0
6.0
SPARES LIST...............................................................................316
7.0
8.0
6.1
6.2
ELECTRICAL................................................................................ 321
6.3
7.2
8.2
8.3
8.4
8.5
9.0
REV. NO.: R3
PAGE 4 OF 506
REV. NO.: R3
PAGE 5 OF 506
REV. NO.: R3
PAGE 6 OF 506
SYSTEM DESCRIPTION
1.1
MECHANICAL
1.1.1
General
1.1.1.1
The propose 2 X 800 MW TPS is receiving coal from mines which has
calorific value ranging from 4000 5100 Kcal/Kg. It is also proposed
to use imported Indonesian coal with calorific value of 6000 Kcal/Kg
and high volatile and moisture content. The Indian coal and the
imported coal shall be blended with maximum 70:30 % ratio. Thus the
coal handling plant is required to operate with different type and
combination of coal depending upon the availability of both Indian
and imported coal. The boiler has been designed with worst Indian
coal with calorific value of 4100 Kcal/Kg.
1.1.1.2
1.1.1.3
Coal in size of (-) 300mm for the proposed 2 X 800 MW power plant is
envisaged to brought to Site by Railway in all types of Box-N type
wagons as per latest RDSO G-33 norms. All transporting facilities
including wagons and locomotives to transport the coal from the mine
to the plant will be provided by Railways.
1.1.1.4
In order to handle the large quantity of coal required for the plant at
90% PLF five to six rakes are required to be handled daily. In order to
handle unloading of six (6) nos. rake per day and avoid demurrage for
holding the wagons it is proposed to install Five (5) nos. wagon
tipplers with three available for actual operation and other one under
maintenance and the other as the standby. The availability of three
wagon tippler at any time would facilitate unloading of three rakes
simultaneously with in the allotted time of unloading of wagons. The
arrangement of wagon tippler is designed in cluster of three and two
wagon tipplers so that the normally one stream of conveyor from two
wagon tippler would be operated at full capacity.
1.1.1.5
REV. NO.: R3
PAGE 7 OF 506
except stack yard conveyors. Out of two stream conveyors one stream
will be working and other stream will be standby. However coal
handling plant shall be designed for simultaneous and continuous
1.1.2
1.1.2.1
the bottom will be provided with rack and pinion gate for isolation of
hoppers. Below the each wagon tippler hoppers apron feeder and
dribble feeder shall be provided. Apron feeder and dribble feeder will
feed coal to conveyor BCN-1A from Wagon tippler-1, BCN-1B from
Wagon tippler-3, BCN-1C from Wagon tippler-5, BCN-1D from Wagon
tippler-2, BCN-1E from Wagon tippler-4.
In wagon tippler hoppers, grizzlies shall be provided at ground level.
Wagon tippler shed floor level will be equal to rail top level.
1.1.3
1.1.3.1
The
raw/washed coal from wagon tippler WT-1, WT-3 and WT-5 will be
fed to conveyor BCN-1A, BCN-1B and 1C respectively and further shall
be transferred either to conveyor BCN-2A or BCN-2B at junction tower
JT-15. Coal from Conveyor BCN-2A/B shall be transferred to either
REV. NO.: R3
PAGE 8 OF 506
that coal from two crushers of stream-A can be fed to bunkers and
coal from Stream-B can be stacked.
1.1.3.2
The washed/imported coal from wagon tippler WT-1, WT-3 and WT-5
Path-3- Coal of (-)300 mm is received (Raw coal): The raw coal from
wagon tippler WT-2 and WT-4 will be fed to conveyor BCN-1D and 1E
respectively and further shall be transferred either to conveyor BCN2C or 2D at junction tower JT-19, which in turn feed to conveyors
BCN-4C/D at primary crusher house, PCH. In primary crusher house
there are four Nos. of primary crushers of rotary breaker type which
shall reduce the size of coal from (-) 300 mm to (-) 150 mm. Output
of primary crushers shall be feed to conveyor BCN-4C/D for further
transportation of coal to secondary crusher house SCH-1.The capacity
of each rotary breaker are of Designed capacity - 1250TPH, Rated
capacity - 1000 TPH, out of four primary crushers, two crushers will
of ring granulator type which shall reduce the size of coal from (-) 150
mm to (-) 20 mm. Vibrating screens shall be provided above crushers
to screen out the coal of size (-) 20 mm. Coal above 20 mm size from
be
feed
to
conveyor
BCN-5A/B
or
10A/B
for
further
REV. NO.: R3
PAGE 9 OF 506
1.1.4
1.1.4.1
fed to Junction towers JT-14, JT-6, JT-5, JT-4, JT-3, JT-2 and JT-1
through conveyors BCN
1.1.4.3
5A/B, 16A/B,
17A/B, 18A/B, 19A/B, 20A/B, 21A/B and 22A/B respectively for direct
bunkering.
1.1.5
1.1.5.1
For stacking and reclaiming of coal Three (03) nos. stacker cum
reclaimer will be provided each of stacking capacity 2200 TPH
(Designed)/2000 TPH (Rated) and reclaiming capacity 2200 TPH
store 30 days coal requirement of the plant. The height of each stock
pile shall be 8.75 meters. Boom length of each stacker cum reclaimer
shall be 36 meters. Minimum capacity of coal stackyard shall be 6.0
lakh MT
1.1.5.2
Path-1: The coal from Secondary crusher house SCH-2 shall be feed to
either conveyor BCN- 10A/B. coal from conveyor BCN-10A/B shall be
transferred to Junction towers JT-11, JT-12 and JT-13 through
conveyors BCN-6, BCN-7 and BCN-8 for stacking of coal in six nos of
REV. NO.: R3
PAGE 10 OF 506
stack piles for stacking Indian/imported coal pile through stacker cum
reclaimer SCR-1, SCR-2 and SCR-3 respectively.
1.1.5.3
The reclaimed coal through yard conveyors BCN-6, BCN-7 and BCN-8
will feed coal to conveyor BCN 11A/B at junction towers JT-8, JT-9 and
JT-10. The reclaimed and blended coal received on to conveyor BCN-
The reclaimed coal through yard conveyors BCN-6, BCN-7 and BCN-8
will feed coal to conveyor BCN 11A/B at junction towers JT-8, JT-9 and
JT-10. The reclaimed and blended coal received on to conveyor BCN11A/B will be fed to conveyor BCN-15A/B at junction tower JT-7 and
onward transfer to junction towers JT-6, JT-5, JT-4, JT-3, JT-2 and
JT-1 through conveyors BCN
1.1.5.6
Path-3 - The coal from Secondary crusher house SCH-1 shall feed to
either conveyor BCN-5A/B. coal from conveyor BCN-9A/B shall be
transferred to Junction towers JT-16, JT-17and JT-18, through
conveyors BCN-6, BCN-7 and BCN-8 for stacking of coal in six nos. of
stack piles for stacking Indian/imported coal pile through stacker cum
reclaimer SCR-1, SCR-2 and SCR-3 respectively.
1.1.5.7
The reclaimed coal through yard conveyors BCN-6, BCN-7 and BCN-8
will feed coal to conveyor BCN 11A/B at junction towers JT-8, JT-9 and
JT-10. The reclaimed and blended coal received on to conveyor BCN11A/B will be fed to conveyor BCN-15A/B at junction tower JT-7 and
onward transfer to junction towers JT-6, JT-5, JT-4, JT-3, JT-2 and
REV. NO.: R3
PAGE 11 OF 506
1.1.6
1.1.6.1
The stacker cum reclaimer shall be used for blending of coal for
feeding to the boiler bunker during normal operation when rakes are
not available. Any of the stacker cum reclaimer (SCR) shall be able to
reclaim the indigenous coal from the dedicated indigenous coal stock
pile for the purpose of blended coal, the indigenous coal and the
imported coal can be blended in any ratio from 90:10 up to 70:30.
1.1.6.2
The indigenous coal shall be reclaimed through one SCR and other
SCR would reclaim the imported coal. On the common conveyor
mixture of the two coals shall be blended through three transfer tower
(JT-8, JT-9and JT-10) to provide reasonably good mixture for feeding
to raw coal bunker.
1.1.6.3
In case any of the SCR is out of service the blending can be achieved
through one SCR reclaiming indigenous coal while the imported coal
shall be reclaimed through manual reclaiming hoppers.
1.1.6.4
Blending can also be done on crusher by unloading one rake each for
both Indian and imported coal simultaneously. Feed rate of coal will be
adjusted by adjusting the feed rate of the feeder below wagon tippler
hopper during direct bunkering of coal. During bunkering of coal from
stock pile feed rate for blending of coal will be controlled from
REV. NO.: R3
PAGE 12 OF 506
1.1.8
Around the coal stock yard, ground drains shall be constructed to take all the
effluents/leach water from coal stockyard. This water along with water from
other coal handling areas shall be led to decantation tanks (02 nos.) where all
the coarse particles will settle down. The decanted water with finer particles will
be collected in coal pile run off pond (2 nos.). Clear water from runoff pond will
be collected in a RCC collection tank where it will be pumped to CMB/ETP.
Two (02) Nos. pumps (1W+1S) shall be provided. Capacity of each decantation
pond shall be 25000 M3. Capacity of collection tank shall be 35000 M3 and
capacity of each pump shall be 300 M3/hr.
Suitable drains shall be provided in entire coal handling plant area. These drains
shall be connected to decantation tank.
1.2
ELECTRICAL
REV. NO.: R3
PAGE 13 OF 506
For the motors up to 160 kW, the power is fed through 415 V switchgear, >160
kW and less than 1500 kW motors, the power is fed through 3.3 kV switchgear.
All local push button stations for HT drives are provided with only Emergency
stop PB, all LT drives are provided with Start / Stop PB to enable Starting /
Stopping of all equipment locally for maintenance purposes.
A separate DC system is envisaged for the CHP area for breakers, DC lighting,
etc., Separate lighting transformers are provided for illumination purposes. A
decorative type 3 x 36 W CFL fitting is envisaged for the CHP control rooms and
switchgears. The illumination level and type of fittings are described in the
specification.
AC drive (VFD) and DC drive (like for Apron feeders) is provided as per the
system requirement.
The peripheral earthing for the CHP is made to reduce the earth resistance less
than 0.5 ohm. The required treated pit and test pit is as per IS 3043. For
electronic equipment earthing is to be done as per IEEE 1100 and separate earth
pit is to be provided.
1.3
I&C system will consist of all local instruments Viz. Pressure Gauge, Temperature
Gauge, limit switch, Pull cord switch, Belt Sway switch, Electronic Zero speed /
Under speed switch, Bunker level switch/ indicator, other field sensors, Local
panel & push button station, CHP control room equipment, as required erection
hardware & interconnecting cables required for the control & monitoring of the
entire Coal handling Plant along with control of Wagon Tippler & StackerReclaimer as turnkey basis. A PLC based control system shall be provided for
operation, control, interlocking, tripping of the entire coal handling plant and all
associated equipment whenever required under specified abnormal conditions.
All 3.3 KV drives shall be provided with fluid coupling temperature/ bearing
Temperatures measurement & shall be measured with Duplex RTD. Redundant
Temperature Measurement sensor shall be provided for all bearing temperature
measurement. Stator winding temperature measurement element shall be
duplex type and all temperature measuring points shall be connected to PLC.
Winding temperature high alarm will be generated in the PLC system. 3.3 KV
REV. NO.: R3
PAGE 14 OF 506
drives shall also be provided with vibration monitoring devices and shall be
connected with PLC.
REV. NO.: R3
PAGE 15 OF 506
SCOPE OF WORK
The scope of supply and work for Coal Handling System under the specification
to
site),
fabrication
(as
needed),
construction,
erection,
2.1
MECHANICAL
The scope of coal handling plant shall be deemed to include all such items
which although are not specifically mentioned in this section but are needed to
make the system complete in all respect for safe reliable, efficient and trouble
free operation but not limited to followings:
2.1.1
Five (05) Nos. wagon tipplers along with integral weighing system.
Wagon tippler shall be consisting of rails, tippling platform, cradle
arms, cradle arm bearing, Side stop with pads, top stop with pads,
driving motors, Girth gear and pinion drive, balance weight,
limit
Five (05) Nos. Side arm chargers with power supply system, support,
Rack and Pinion, Hydraulic arrangement, electricals, buffer stop etc;
one no. for each wagon tippler.
REV. NO.: R3
PAGE 16 OF 506
2.1.3
2.1.4
One (01) No. rack and pinion gate for each wagon tippler hopper.
2.1.5
Five nos. (05) Wagon tippler gratings of mesh size 300mm X 300mm
for wagon tippler hoppers; One no. for each hopper.
2.1.6
One (01) No. Apron feeder for each wagon tippler hopper with drive
and accessories.
2.1.7
One (01) No. Dribble feeder for each wagon tippler hopper with drive
and accessories.
2.1.8
2.1.9
Belt conveyors:
Each conveyor will be complete with drive equipment including motor,
Gear Box, Fast speed coupling, Slow speed coupling, Carrying idlers,
self aligning carrying idlers, Return idlers, self aligning return idlers
impact idlers, head pulley, snub pulley, tail pulley, pull cord, belt sway
and zero speed switches, chute jam switches, deck plate for complete
length of conveyors, gravity take-up system, internal and external
scrappers stringers with short support, all over ground conveyors will
be provided with conveyor galleries.
2.1.10
2.1.11
2.1.12
2.1.13
Four (04) Nos. Rotary breaker (Primary crushers) with drive equipment
including motor.
REV. NO.: R3
PAGE 17 OF 506
2.1.14
2.1.15
2.1.16
Four (04) Nos. Vibrating screens with drives and supporting structure;
one no. for each secondary crusher in Secondary crusher House -1.
2.1.17
Four (04) Nos. Vibrating screens with drives and supporting structure;
2.1.18
2.1.19
2.1.20
2.1.21
2.1.22
One (01) No. Rack and pinion gates for each Emergency reclaim
one no. for each secondary crusher in Secondary crusher House -2.
hoppers
2.1.23
One (01) No. Vibrating feeder below each emergency reclaim hoppers
2.1.24
2.1.25
Eight (08) Nos. Mobile trippers complete with all electrical, rails and
rail fixing arrangement to operate in conjunction with bunker feeding
conveyors.
2.1.26
REV. NO.: R3
PAGE 18 OF 506
2.1.27
Eight (08) Nos. fixed tripper on Conveyor 9A/B and 10A/B; Two (02)
Nos. for each conveyor
2.1.28
Eight(08) Nos. Metal detectors, one at each conveyor BCN-2A, 2B, 2C,
2D, 4C, 4D,16A and 16Bcomplete with all accessories.
2.1.29
2.1.30
2.1.31
2.1.32
Six (06) Nos. Coal sampling units, one at each conveyor BCN-2A, 2B,
4C, 4D, 16A and 16B
2.1.33
One (01) No. Manual unloading hopper for unloading sick wagons
2.1.34
One (01) No. rack and pinion gates below manual unloading hopper
2.1.35
2.1.36
points except Bunker bay and Crusher House. DS system shall consists
of water pumps (1W + 1S), compressor (1W + 1S), enclosed hood, etc.
(2). There shall be two service water pumps (1W + 1S) which supply
water to (a) local water storage tank of DS system of stock yard,
transfer house, etc., (b) service water tap point for plant sealing, toilet,
etc., each system DS shall be provided with (1W + 1S) pumps.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
PAGE 19 OF 506
(3). Service water piping shall be provided all along the tunnels and
galleries with tap off points at 30 m interval to enable cleaning of
walkways / deck plates using flexible hose.
(4). Service water piping with tap off points (with isolating valve and
quick connecting coupling) shall be provided for each floor of junction
towers, transfer house and crusher house. Two (2) points per floor in
junction tower and transfer house and four (4) points per floor in
crusher house. Flexible hose of 20 m long each shall be provided with
storage box.
(5). Each tap off point shall contain isolating valve with quick
connecting coupling to enable fixing of hoses.
REV. NO.: R3
PAGE 20 OF 506
(4). The air to cloth ratio of the bag filter shall not exceed 2
m3/min/sqm. The bag filter cleaning system shall be reverse pulse jet
air system. Necessary instrument air supply shall be provided.
(5). Thickness of suction hood, dust collecting hopper and ducts shall
be minimum 5 mm. Thickness of casing of centrifugal fan shall be
minimum 5 mm.
(6). Dust extraction system shall be provided for at all coal transfer
points and also in the crusher house. The DE system shall have
cyclone separator and / or bag filter. The outlet dust emission shall be
max 50 mg/Nm3.
(7). Bunker ventilation system will be provided for the bunkers to
minimize the dust nuisance on the tripper floor and also to prevent
fire hazards inside the bunkers due to volatile gases liberated by coal.
The DE system shall have cyclone separator and bag filter. The outlet
dust emission shall be max 50 mg/Nm3. The bunker ventilation shall
be designed for handling minimum of 60,000 m3/hof volume of dusty
air.
(8). These shall be operated from the local control panels with
monitoring in CHS and interlocked with operation of conveyor
equipment.
(9). DE system shall be designed for two stream operation.
The tunnel ventilation system shall be designed based on a minimum
of 12 air changes per hour. Adequate capacity of supply air fan and
exhaust fan shall be provided.
2.1.38
REV. NO.: R3
PAGE 21 OF 506
2.1.39
2.1.40
2.1.41
2.1.42
2.1.43
Two Nos. (1 W+1 S) Sump pumps with piping and valves at each pent
house, Emergency Reclaim hopper, Manual unloading hopper and
wagon tippler hopper areas and connected tunnels. The sump pump
shall be suitable to handle coal slurry and impeller shall be of non
clogging type.
2.1.44
2.1.45
Five (05) Nos Bulldozer along with Dozer shed with repair bay for
reclaiming coal from stock piles.
2.1.46
Four (04) Nos. locomotives along with all accessories and loco shed
with repair bay.
2.1.47
2.1.48
Air conditioning of main CHP control room wagon tippler control and
operator cabin of SCR complete with all accessories
2.1.49
REV. NO.: R3
PAGE 22 OF 506
2.1.51
2.1.52
2.2 ELECTRICAL
The scope of Contractor shall include Engineering design, manufacture,
inspection, supply including transportation to site, transit insurance, storage at
site, transportation from place of storage to erection site, erection, testing and
commissioning and handing over in fully operable condition satisfactory to
Owner of all electrical equipment required for the coal Handling System for
2X800 MW Yeramaras Thermal Power Project, besides obtaining all statutory
authorities shall be in the scope of the Bidder. The entire cost including all
necessary fees, incurred for obtaining such approval / clearances, shall be borne
by the contractor.
The bidder shall design the Electrical system suitable to operate both streams of
CHP simultaneously & continuously. Electrical system should also be designed in
such a way that the transformers, switch gears, bus duct, etc., are adequately
rated considering simultaneous operation of all wagon tipplers, primary &
secondary crushers, coal conveyers etc. continuously.
REV. NO.: R3
PAGE 23 OF 506
Power & Service Transformers 2 nos. 11/3.6 kV Power Transformer for all HT
loads of CHP and required No. of 11/0.433 kV transformers for feeding all the
auxiliary loads of Wagon tipplers and crusher area LT loads and 2 nos. 11/0.433
kV transformers for feeding all the auxiliary loads of Bunker area and required
number of transformers as per system requirement for SR area. The
transformers shall be complete with all fittings and accessories. The quantity
shall depend on the geographical location of loads and shall be chosen such that
the transformers are 100% redundantand shall be rated to take care of the entire
load on the respective switchgear considering the outage of the other
transformer. The fire wall is to be provided as per CBIP / Indian Electricity rules.
Neutral earthing equipment The adequate value of neutral grounding resistor
is to be selected to restrict the phase to earth fault current for 3.3 kV system to
300 A. The resistor is to with stand the fault current for a period of 10 seconds.
HT Switchgear (11 & 3.3 kV): Fully draw out type 11 kV& 3.3 kV Switchgears
with two incomers (2x100%) & a bus coupler scheme complete with Vacuum
Circuit breakers, busbars, Instrument
transformers,
relays,
meters,
transducers, line PT, Bus PT, terminal blocks & accessories for feeding all the
loads of the Coal Handling System package shall be included in the scope of
work. All HT feeders shall have vacuum circuit breaker.
The bidder has to submit the electrical system arrangement in entire CHP area
including SR to the Owner / Consultant for his approval. Any change made by the
Owner / Consultant is final.
LT Switchgear (415 V): Fully draw out type 415 V switchgear with 2x100%
incomers & bus coupler scheme complete with Air Circuit breaker, bus bar,
mentioned elsewhere in the specs. For apron feeder of WT and long travel of
stacker reclaimer, the bidder can offer VFD/Variable Speed drives. In case of
apron feeder the drive panels may be located in Wagon tippler control room,
which can be discussed & finalized during detailed Engineering.
REV. NO.: R3
PAGE 24 OF 506
part
of
One lot of MV/LV Power, control, Instrumentation, trailing cable and any
other special cables required for proper operation, monitoring and
control
of
the
Cable raceway system consisting of cable racks, cable trays, Cable rack
/ tray supporting structures, support members / channels for cable
trays, cable tray covers, cable trenches, Duct Banks, conduits, pipe
sleeves, hume pipes, associated foundation and civil works, cable tray
accessories, etc., as required.
c)
d)
Necessary fire protection systems like fire barriers, fire breaks, fire
stops, and fire proof sealing for wall/floor openings(after laying of all
cables) and fire protective coating systems etc., as necessary.
All the above items and any other item required for completing the Cable carrier
system shall be provided for the entire Coal Handling System.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
PAGE 25 OF 506
supplying all the DC loads and DC lighting system of the Coal Handling
System package.
As a minimum requirement, 1x100% 220 V batteries of suitable capacity with
2x100% float cum boost chargers and DC distribution board shall be provided
for catering to the requirements of Coal Handling System. The sizing of the
battery and charger is to be designed as per the specification.
Primary and Secondary Earthing and Lightning protection system: For the entire
Coal Handling System area, buildings, etc., complete with buried peripheral
earthing and earth electrodes or earth pits for the entire area shall be provided
in
this
package. This
shall
include
earthing
conductors
buried
in soil,
REV. NO.: R3
PAGE 26 OF 506
MLDB, two (2) nos. adequate capacity of uncabled feeders are to be given to
GCW bidder for his further usage.
The major areas to be illuminated under the scope of this package are
o
HT /LT switchgear
Crusher area
Transformer area
Coal yard
Stacker reclaimer
Wagon tippler
Marshalling yard
Loco shed
Dozer shed
The areas listed are however indicative only for the purpose of guidance to the
bidder and is subjected to change during detail engineering after finalization of
plant layouts.
The minimum lux level shall be as per highest value mentioned in the IS 3646 /
as mentioned in the specs whichever higher is to be maintained.
The necessary software shall be used to determine the number of fittings
required in a particular area and desired lux level.
Equipment painting and its thickness is to as per relevant standard.
Special
tools
and
tackles
as
required
for
installation,
operation
and
Essential and Start-up spares for all equipment shall be included in the
scope. Bidder shall furnish a comprehensive list of the same.
REV. NO.: R3
PAGE 27 OF 506
detail design
stage.
Control of all 11 kV, 3.3 kV and 415V breakers i.e. incomer, Bus coupler,
outgoing breakers of all switchboards shall be possible from PLC / DCS and the
same shall be linked with plant DCS located in the main control room. Remote
position, service position, breaker healthy i.e. trip circuit healthy, spring
charged, reset position of trip relay, other permissives interlocks, etc., shall be
considered as input to PLC / DCS system.
The current and voltage measurements for each bus and line shall be available
on PLC / DCS. The operation, indications and fault alarms for the motors of the
auxiliaries shall be displayed.
Any other electrical equipment which are not specifically listed above but
are required to make the CHP complete in all respects as per specification shall
be included in the scope of work.
The scope shall also include preparation and submission of all required
drawings for Owners approval not limited to:
i)
Main One Line Diagram for CHP clearly highlighting the scope of work
considered by the vendor.
ii)
Detailed Single Line Diagram for 11 kV, 3.3 kV and 415 V, DC and UPS
iii)
iv)
system.
layouts
for
Earthing &
all
layout
CHP
areas / buildings /
drawings,
lighting
layout
REV. NO.: R3
PAGE 28 OF 506
earthing
details
etc.,
as
required
vi)
vii)
Panels.
viii)
ix)
x)
The scope shall include submission of all required design calculations for
the following:
o
o
The contractor shall include all the required schedules including the following in
the scope:
REV. NO.: R3
PAGE 29 OF 506
Data Sheets for all equipments included in the scope shall be submitted for
review & approval by Owner.
MQP & Field Quality Plan (FQP) are to be submitted for Owners approval.
b)
(B/W), one no. A3 colour medium speed laser and one no. high
speed (180 columns) dot matrix printer shall be provided in
Solid
d)
Emergency Trip push button for HT drives & for all Electrical
e)
state
annunciation
system/PLC
based
system
with
f)
including
cable,
both
side
required
REV. NO.: R3
PAGE 30 OF 506
g)
h)
2.3.2
One no. 24 TFT operator work station and one no. 24 TFT operator
work station cum engineering work station and one no. A4 size (B/W
printer shall be provided for each stacker cum reclaimer control room.
Bidirectional communication shall be provided between stacker cum
reclaimer PLC and CHP control System. For more details regarding
number of HMI, Printers, LCD display units and others bidder shall
refer CHP PLC configuration diagram E072-03-CHP-1-03-08-R1.
2.3.3
One no. 24 TFT operator work station and one no. 24 TFT operator
work station cum engineering work station and one no. A3 colour
medium speed laser and one no. high speed (180 columns) dot matrix
printer shall be provided for each wagon tippler control room.
Bidirectional communication shall be provided between wagon tippler
PLC and CHP control System. For more details regarding number of
HMI, Printers, LCD display units and others bidder shall refer CHP PLC
configuration diagram E072-03-CHP-1-03-08-R1.
2.3.4
2.3.6
REV. NO.: R3
PAGE 31 OF 506
include
the
Vibration
Probes
(Proximity/
Thrust/
Velocity/
Accelerometer), Special Cables, Sensors/ Signal Conditioners, PreAmplifiers (if required), minimum IP-55 Junction Boxes, Signal
Conditioners, Pre-Amplifiers, Vibration Monitors, etc.
2.3.7
2.3.8
PLC I/O cards and relays for control and monitoring of all instruments,
drive and equipment are to be housed in air-conditioner environment
(room/enclosure).
2.3.9
2.3.10
2.3.11
Any other item not covered herein but essential for successful
installation and commissioning of the coal handling plant and integrity
of the system shall be included by the Bidder.
2.3.12
2.4
CIVIL
all
necessary
survey,
tests,
studies,
investigations
including
REV. NO.: R3
PAGE 32 OF 506
Site clearance, leveling and grading to achieve FGL as per requirement: for
Bulldozer Shed.
Works related to transformers and other electrical facilities for CHP area (As
per Electrical specification & scope)
Foundations and Support columns (as and where required ) for Belt
Conveyors/Gallaries etc.
All main roads in CHP area and approach roads connecting all facilities in the
Coal Handling package to the nearest main roads of BTG area, including
Civil works required for illumination of the facilities in the Coal Handling
package and connecting approach roads.
REV. NO.: R3
PAGE 33 OF 506
Garland Drains, Decantation tanks, Coal pile run off pond, Coal sampling
room and Office Complex for O & M staff for CHP
About 15 nos. of toilet blocks along with adequate size of soak pit / septic
tanks and water tanks and connections are to be provided in the coal
handling area. The location and size of the toilets blocks to be decided
during detail engineering.
The work to be performed under this specification shall include all incidental
items not mentioned or specified but reasonably implied or necessary for the
completion and proper functioning of the plant, all in strict accordance with the
involved under this specification are given hereinafter. The items, though not
specifically mentioned, but are needed to make the system complete shall be
treated as though included and the same shall also be furnished and erected /
constructed unless otherwise specifically mentioned as excluded.
The bidder should also note the following details, pertaining to the scope of
civil works under this specification:
i)
REV. NO.: R3
PAGE 34 OF 506
The work shall be carried out both below and above ground level and
shall include basements, equipment foundations including vibration
isolation systems, grounding, slabs, beams, columns, footings, rafts,
walls, steel frames, brick walls, stairs, trenches, pits, access roads,
the complete
Underground/partially
underground
transfer
points
(RCC
construction)
Office complex for O&M staff and storage rooms near main
control room.
iv)
Scope shall also include supply and laying earthing mat all around the
periphery of buildings, structures, and outdoor equipment, as per the
approved drawings.
v)
The analysis, design and detailed drawing for the structures like wagon
tipplers tunnels etc. coming below the railway track shall be got
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
PAGE 35 OF 506
construction.
vi)
vii)
of
temporary
access
roads
for
approach
to
the
The scope shall also include setting up by the Contractor of a complete testing
laboratory in the field to carry out all relevant tests required for the Civil and
structural works as detailed elsewhere in the specification.
REV. NO.: R3
PAGE 36 OF 506
REV. NO.: R3
PAGE 37 OF 506
Terminal Points
3.1.1 Mechanical
Potable and service water at one point 5 meter away from Secondary crusher
house -1.
3.1.2 Electrical
3.1.4 Civil
Roads:
All approach roads interconnecting all facilities under CHP package and their
connections to the Main plant roads at suitable locations. (As per enclosed
drawing).
REV. NO.: R3
PAGE 38 OF 506
Sewerage line:
Upto existing connection chamber/ manhole nearest to the toilets. However, if
no chamber / manhole exists, the bidder shall provide the same with proper
connections.
Drains:
All garland drains/ local drains for effective drainage of rain water at all facilities
and roads under CHP package and their connections to the Main storm water
drainage network at suitable locations.
3.2
Exclusions
3.2.1 Mechanical
3.2.3 Civil
Roads:
Main plant roads except approach roads interconnecting all facilities under CHP
package and their connections to the Main plant roads at suitable locations.
Sewerage line:
Beyond connection chamber/ manhole near the toilet.
Drains:
Storm water drains beyond CHP battery limit.
REV. NO.: R3
PAGE 39 OF 506
REV. NO.: R3
PAGE 40 OF 506
TECHNICAL REQUIREMENTS
4.1
MECHANICAL
of each
conveyor
1000 TPH
1250 TPH
(-) 300 mm
(-) 150mm
Vibrating Screens
Rated capacity of each screen
1000 TPH
1250 TPH
(-) 20mm
capacity
{considering
(-) 150 mm
2000/2200 TPH
capacity
of
conveyor
Design Capacity (considering specified %
bucket fill)
REV. NO.: R3
PAGE 41 OF 506
(i) Stacking
2200
TPH(Designed)/2000
2200
TPH(Designed)/2000
TPH(Rated)
TPH(Rated)
8.75 Meters
36 meters
(-) 20 mm
All other equipment under the scope of work of the contract shall be suitable to
the system capacities parameters as specified above.
4.1.2 Standards/Codes
The design, manufacture, inspection and testing of all equipment/system shall
comply with all the currently applicable statutes, regulations and safety codes in
the locality where the equipment is to be installed. All equipment/system shall
conform to the latest edition of the following standards and codes. Other
internationally acceptable standards/codes, which ensure equal or higher
performance than those specified, shall also be accepted. Nothing in this
specification shall be construed to relieve the contractor of the required
statutory responsibility.
IS: 8598:
IS: 8531:
IS: 2062:
IS: 4682:
IS: 11592:
REV. NO.: R3
PAGE 42 OF 506
Wagon Tippler
Wagon tippler shall be as per RDSO latest G-33 (Revision-1) norms. The wagon
tippler provided shall be hydraulically operated type.
in
data
Electronic weighing.
The tippler shall consist of tippling platform, cradle arms, cradle arm
bearing, Side stop with pads, top stop with pads, driving motors, gear and
pinion drive, balance weight,
limit
shafts,
steel,
walkways,
bearings, supporting
platforms
and
all
other
During each cycle of operation, the tippler shall be capable of holding, complete
unloading
and
replacing
the
standard
railway
wagon
to
its
original
position. The wagon tippler shall be designed for outdoor installation and
shall be of heavy
and
suitable
duty
construction
rigidly
reinforced
throughout
The operation of the wagon tippler shall be through hydraulic motor without
gear
box
&
coupling
&
directly
coupled
to
driven
shaft
and
completely automatic such that one operator can control all the operations
from a single control panel. However, one more labourer shall be required to
uncouple loaded wagon from the rake during operation of wagon tippler.
The location of the control room shall be such that the operator can have a
clear view of the tippler operation as well as the railway facilities. The
tippler design shall be co-ordinated with that of the unloading hopper
and it shall be arranged to provide convenient access to any part of the
tippler
and
REV. NO.: R3
PAGE 43 OF 506
The design of civil and structural work for the wagon tippler complex shall be as
per relevant IS codes. The design of equipment as well as civil and structural
work of
the
impact
factor
and
allowable
stresses
etc.
It
shall
major repair, assuming proper maintenance and usage. The tippler table shall
be designed to allow passage of the standard main Indian Railways diesel
locomotive
of
over
dirt
and
other
wearing surface.
proper
tippling
angle
The
foreign
tippler
at
the
do
not
come
shall
be
designed
in
contact
to
have
matter
maximum
to
hold
the
partially
uploaded
without any damage or distortion. Limit switches shall be provided to cut off
power supply at the end of travel. Back up limit switches shall also be provided.
Provisions shall be made for alignment of tippler
platform
by
inching
REV. NO.: R3
machine
cut from
solid
in
fabricated
blank.
All
shall
be
totally
enclosed
and
positive
braking
action,
actuated
by
remote
operation.
The
mechanism. The
brake
shall
be
heavy
duty
type,
electrically
Bidder. The brake shall be fail safe type and it shall perform satisfactorily even
in the event of power failure.
Rack & Pinion arrangement shall have ample strength to drive cradle with full
wagon. The material of construction shall be of a high grade steel to
suite the specific operating condition. Factor of safety to be considered as
per code to withstand the operation. Colour signal shall be provided at the
inhaul side of tippler table for the guidance of loco operator.
All shafting shall be proportioned for stiffness as well as strength. Shafts
76 mm (3) in diameter and more shall be fabricated from steel forgings
or hot rolled steel rounds with a minimum carbon content of 0.3%. Shafts
smaller than 76mm may be made from cold finished steel, or hot rolled
steel. Shafts turned to provide changes of section shall have a minimum 6
mm fillet radius wherever such changes occur.
All shaft couplings shall be gear type flexible and an approved product
of a reputed
develop
manufacturer
of
equipment
of
this
nature
and
shall
provided for
all couplings.
REV. NO.: R3
PAGE 45 OF 506
Bidder shall furnish necessary electricals, control desk, safety interlocks for
controlling the operation of the wagon tippler from control desk.
at the maximum tipping position for the specified length of time and lower the
empty wagon
tilting
to
the
original
position.
Separate
push
buttons
for
Suitable interlocks shall include but not being limited to the following:
Signal light:
Besides above, any other limit switches required for the safe operation of
wagon tippler shall be provided.
The complete design of the wagon tippler and accessories shall meet the
approval of RDSO and obtaining the necessary approval from RDSO / Zonal
railways statutory authority for wagon tippler and its layout is included in
the scope of Bidder, under this specification.
REV. NO.: R3
PAGE 46 OF 506
when required, for obtaining above approval. All the statutory fees/charges
for obtaining such approval shall be borne by bidder.
4.1.3.2
The side arm charger shall be used for wagon positioning at the wagon
tippler for unloading of materials, It shall be used for pushing / pulling a rake of
60 wagons of 110MT gross weight each and locating wagons one by one on
tippler platform. The tractive effort shall not be less than 30 Tons.
The train shall be brought by locomotive either heading or pushing and
stopped with the leading wagon within range of the side arm charger. The
charger shall be driven to the leading wagon, its arm shall be lowered and it
shall be coupled to the first wagon of the train. The train shall be hauled forward
by the charger until the front of the second wagon is about 2 meters
away from the tippler. The charger shall stop and the first wagon shall be
uncoupled from the train. The charger shall then propel the leading wagon to
the tippler, automatically uncouple and shall run clear of the tippler. Its
arm shall be raised and it shall travel back to the train and the tippler shall
rotate. On reaching near the standing train, the charger arm shall be lowered
and shall be coupled to the train ready for repeating the cycles. In the next cycle
the train shall be drawn up by the wagon length and the previously tippled
wagon on the tippler table shall be pushed on the outhaul side. The charger
shall be used under manual control to eject the last wagon from the tippler, if
the next wagon is not already in position.
The supply includes side arm charger with power supply system, support, Rack
and Pinion, electricals, buffer stop etc
The side arm charger shall be mounted alongside the main rail track and shall
run on its rail track parallel to the main track. It shall have a suitable stroke from
point just over one wagon length ahead of tippler to a point just beyond the
tippler on the outgoing side. The rail envisaged for SAC shall be standard rail
section.
It shall be fitted with an arm pivoted at right angles to the track capable of being
raised and lowered and carrying at its outer end an automatic coupler to couple
the train.
REV. NO.: R3
PAGE 47 OF 506
The charger frame shall consist of a single fabrication from rolled sections and
plate on which every other item shall be directly mounted to form a robust
compact unit.
The charger shall run on four steel wheels mounted on spherical roller
bearings.
To resist the moment reaction of the pushing force, two pairs of steel side guide
rollers shall be fitted. They shall be fitted on spherical roller bearings and shall
have a simple lockable adjustment for true running and to take up wear. The
side guide rollers shall run on the sides of the heads of the charger
running track.
The arm shall be of welded construction. Raising and lowering of the arm shall
be by means of a hydraulic power cylinders mounted on the charger frame. A
spring-loaded coupler shall enable automatic coupling of the arm to the wagon
coupler and an actuator release mechanism with a hydraulic cylinder shall be
provided for decoupling.
The charger shall have adequate power for pulling a train load of 60 loaded all
type of Box-N wagons on a straight and level track. It shall be hydraulically
driven by means of a pinion and land mounted rack.
The drive pinion shall be mounted on the output shaft of the hydraulic drive
motor without any gear box & coupling.
The side arm charger shall have a hydraulic power pack mounted on board,
which shall provide power to independent hydraulic motors without any gear
box & coupling directly coupled to driven shaft for charger transverse and arm
hoist.
proportional control valves with electronic cards, filters, piping, tank and
accessories.
The charger shall be electrically interlocked with tippler for proper sequential
operation with respect to operational and safety requirements.
REV. NO.: R3
PAGE 48 OF 506
provided with toe guard. Chequered plates on floor shall be provided to prevent
slipping.
Centralized system of lubrication shall be provided for the equipment. However,
all parts of the equipment needing manual lubrication shall be easily
accessible. All oil pipes and grease nipples shall be well covered to prevent
materials from falling on them.
The side arm charger shall be suitable to move 60 loaded Box N wagons on a
straight and level track and shall be suitable to position all types of
4.1.3.3
Apron Feeder
The apron feeder shall be suitable for continuous duty and shall be robust in
construction. It shall be capable of absorbing the shock load due to impact of
falling large coal lumps of up to 300 mm size and other heavy metallic
components / pieces without damaging the feeder.
The driving and driven ends with sprocket shafts shall be supported in heavyduty anti-friction bearing with minimum triple labyrinth sealing for dust
protection and shall have provision for external lubrication. The Sprocket shaft
shall be constructed of alloy Steel.
The steel chain shall be constructed out of wear resistant deep hardening alloy
steel, in heavy sections. The steel sections shall be held together by alloy steel
bar pins with wheels on either side which will move on rails. All sections shall be
so designed that it can operate under the worst conditions of operation with wet
coal, muddy coal etc. without jamming. All parts shall move smoothly.
REV. NO.: R3
PAGE 49 OF 506
The entire assembly of the feeder parts, the bearings, driving and driven
sprockets etc shall be housed on heavy duty structural frame with arrangement
for mounting the same on RCC foundation.
The feeder shall be provided with reliable tensioning arrangement to take care
of elongation in the feeder.
The Apron feeder shall be driven through variable speed electric drive without
any gear box & coupling & directly coupled to driven shaft. The feed shall be
regulated by variable speed electric drive.
plate of adequate height and style suitable for installation below wagon tippler.
Also stationary skirt plate shall be provided to guide coal below wagon tippler
hopper without clogging or jamming. Pans/ aprons should be reinforced to take
impact of maximum 300 mm lump of coal falling for a height to suit the system
& thickness of pan shall be 20 mm (min.). Pan material should be LA-55/ boron
steel material.Hardness of material shall be 45 to 50 RC.
The feed of coal over the downstream conveyor from both the apron feeders
should not cause overloading of the downstream conveyor over the entire range
of speed of operation of the apron feeder. To achieve this, belt weigher signal
may be suitably used to trip the apron feeder in the event of any overloading of
the conveyor belt.
Zero speed switches shall be provided on apron feeder.
4.1.3.4
All Belt Conveyors shall be supplied and erected along with necessary
supporting structures, platforms, on ground or overhead galleries, trestle
structure with foundation footings, carrying and return idlers, automatic takeDoc. No.: E072-03-CHP-O-02
REV. NO.: R3
PAGE 50 OF 506
ups, pulleys, drive motors with suitable reduction units and couplings, belting,
transfer chutes, flap gates, hydraulic couplings and other necessary accessories
as per scope specified elsewhere.
Design Requirement
Belt conveyor system shall be designed as per latest edition of 'Belt Conveyors
for
Bulk
Materials",
published
by
CEMA
or
equivalent
latest
the pulleys shall be as per IS: 8531. For selection of pulley shaft diameter a
margin of minimum 20% shall be considered on maximum tension. In
determination of pulley diameter no account shall be taken of pulley lagging.
Pulleys of same diameter shall be completely interchangeable in totality and
component wise. To have interchangeability of same diameter pulleys procured
under separate contracts for a station, the bearing center distance of pulleys
shall be adjusted.
Idlers
Carrying idlers shall be provided with three equal rolls with troughing angle of
35 deg. and 2 deg. forward tilt
The rolls used in idlers shall be supported from fabricated steel brackets. Fixing
arrangement of rollers with brackets shall be drop-in type. For adjusting the
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
PAGE 51 OF 506
alignment of the idlers, slotted holes shall be provided in idler supporting base
plates. Direction of belt travel shall be clearly marked on the brackets of carrying
idlers.
Idler rollers shall be waterproof, dust proof and weather proof against a high
velocity water jet. All idlers shall be provided with at least double labyrinth dust
seal.
Impact idlers used at the loading and transfer point shall be so designed as to
avoid direct loading impact, belt damage and excessive punishment to the
carrier.
The self-aligning idlers shall be direct acting type, complete with actuating
rollers fitted with the ball bearings and mounted inclined towards the belt. The
idler frame shall be suitably cradled about a vertical pivot, supported in bearing
over a fixed plate. Adequate sealing arrangement shall be provided to prevent
contamination of the lubricant by dirt and moisture.
Transition type toughing idlers shall be used adjacent to all pulleys to permit
proper support of the loaded belt near the pulleys without excessive stretch of
the belt edges. The transition idlers shall be provided with preferably adjustable
concentrator (end) rolls and long center rolls to suit the toughed belt contour
between the last regular toughing idler and the adjacent pulleys.
All the conveyors shall be provided with one self-cleaning type rubber disc
return idler located near the head pulley for cleaning the return belt.
Proper arrangement shall be provided in the brackets of all types of idlers for
preventing the rollers from coming out of the brackets during normal /
abnormal conditions. The base frame for all carrying shall be of C-channel and
side bracket shall be of pressed C- type. The pulleys below the magnetic
separator shall be non magnetic material (Aluminum / SS)
External Belt Cleaner
Counter Weight scraper type cleaner with modular segmented and replaceable
polyurethane scrapers blades complete with main cleaner, pre-cleaner along
with accessories and necessary fines chutes shall be furnished for all belt
conveyors, tripper head pulley and belt feeders at discharge pulleys. The
modular units shall be easily replaceable. The scraper assembly shall be easily
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
PAGE 52 OF 506
maintainable from outside without any interference with the chute arrangement
and assembly.
Internal Belt Cleaner
V-plough type belt cleaner made of mild steel flats and hard rubber strips with
automatic wear adjustment and necessary accessories shall be furnished for
cleaning internal surface of the conveyor belt.
Belt Take-up Arrangement
The automatic take-ups should be located at a place where these will work best
in relation to the drive to keep the belt tension at a minimum.
Height of take-up guide structure shall be sufficient to allow the take-up weight
movement up and down for all operating conditions of conveyor.
Two meter safety fencing along with suitable gate and locking arrangement shall
be provided around gravity take-up at the base level / ground level.
Suitable guides shall be provided both for take up pulley and take up weight.
Suitable buffer arrangement shall be provided to arrest the fall of take-up pulley
For double stream conveyors, a partition of 3mm steel plate shall be provided
between the two take-up pulleys along entire travel zone of take-up pulleys.
REV. NO.: R3
PAGE 53 OF 506
The Plummer blocks for pulleys shall be of horizontally split type construction
with minimum (4) nos. bolts holding the two split halves and with min (4) nos.
foundation bolts. Conical head shape nipples conforming to IS: 4009, suitable
drain plug and eyebolt shall be provided. Side covers of Plummer blocks shall be
heavy-duty metallic sheets. No plastic components shall be used.
The snub pulleys on each conveyor shall be located to provide a belt wrap on the
drive pulleys.
The rubber lagging of pulleys and method of lagging and testing the same shall
conform to IS: 4682.
Pull chord Switch & Belt Sway Switches
Pull chord type (manually reset type) emergency stop switches shall be located
on both sides of belt conveyors along the walkways for the entire length of
conveyors for emergency stopping of conveyor with a spacing of 30m. Local pull
chord actuation shall be provided by means of mechanical flap. Local indication
for pull as well as remote chord actuation shall be provided. Their enclosure
shall be of cast aluminum having degree of protection of IP-65.Remote Pull Cord
Trip Indicators/Locators shall be provided in the CHP Control room to inform the
operator about the exact location of the actuated switch.
REV. NO.: R3
PAGE 54 OF 506
Each switch shall have two NO and two NC contacts one for alarm and one for
trip, which shall be wired up to terminal block. The terminal block shall have
facilities for cable looping.
Zero Speed Switch
Each conveyor drive shall be provided with zero speed switches to stop the
system in case of belt speed falling below the tolerable limit. Adequate
the belt shall be made to increase uniformly in the direction of belt travel. The
skirt plates shall be fitted with modular segmented and replaceable rubber
skirting pads having facility of adjusting the pressure on the belt conveyor and
shall have provision of on-line removal for the purpose of easy maintenance.
Conveyor Galleries
All over ground and overhead conveyors shall be located in suitably enclosed
Galleries made of Structural steel. Galleries of adequate width and depth (2700
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
PAGE 55 OF 506
mm clear head room) shall be provided complete with conveyor bottom deck
plates, seal plates, walkways of chequered plates hand rails on both sides of
each conveyor belt (except where equipment like trippers etc. traverse over
conveyor), conveyor supports etc.
exceeds 10 degrees. It should be totally sealed so that no water falls down while
washing.
The conveyors shall be provided with continuous steel decking plate of
minimum 3 mm thickness.
Provision shall be kept with platforms and ladders for crossing over conveyors at
approximately every 100m intervals of route length and minimum one per
conveyor.
Steel trestle to support the conveyor bridge shall rest upon concrete foundation
with suitable approach/access platforms. Hand railing shall be provided to
approach the conveyor gallery through monkey ladder. Suitable wire mesh doors
on steel frame construction lockable from outside only shall be provided at
these locations. All monkey ladders shall have cage for safety of personnel using
them. The monkey ladder shall be placed on every trestle where height of
conveyor gallery is 10 m or more. There shall be hand railings, suitable seating
& holding arrangement for manual pickers and disposal chutes to ground level
etc.
The bottom portion of galleries of conveyors which crosses the buildings, roads,
railway tracks, main plant area shall be provided with chequered plate of
minimum 3 mm thickness. The bottom portion of gallery at road and rail
crossing shall be minimum 8.0 meter from the top of the rail/road. For natural
REV. NO.: R3
PAGE 56 OF 506
4.1.3.5
Transfer Chutes
Transfer chutes shall be adequately sized (The size of transfer chute shall be
20% more than the design size to avoid the chokage of wet coal) and sloped to
ensure smooth flow of coal without any accumulation anywhere. The actual
valley angle and chute design shall be finalised after carrying out coal flow
ability studies at worst conditions. In any case the minimum valley angle of
chutes shall not be less than 60 degrees from horizontal.
Direct impact of material on conveyor belt shall be avoided by providing an
inclined surface at 60 degrees valley angle at the feeding point to guide the
material in the direction of belt travel. Further, chute construction below flap
gate shaft shall be such that there will not be any accumulation of coal dust
between chute and flap gate in that zone.
Chutes shall be made of structural steel plate conforming to IS 2062 unless
otherwise stated in the Data Sheet and shall be welded construction. Mating
flanges shall be bolted. Felt gaskets shall be provided at all flanged connections.
The minimum thickness of steel plate shall be as indicated in the Data Sheet.
Liners shall be applied as called for in Data Sheet. For chutes liners shall be
applied over all sides unless otherwise stated. Material and thickness of liner
plates shall be as indicated in Data Sheet. Liners shall be fastened with chutes by
countersunk hexagonal head nut. The maximum size of liner shall be 500mm X
500mm.
A long chute guiding flow from considerable height shall be provided with
impact plates wherever change in direction of flow takes place. Hinged
inspection doors (generously sized) of leak proof construction shall be provided
for access/ maintenance purpose, at approachable heights, of the chutes. All
chutes should have one inspection door at every floor and for the ones in
between the floors, suitable access ladder and platform etc. shall be provided.
Maximum distance between two inspection doors in a chute shall be 2 meters. In
addition to mounting bolts, swiveling eccentric handle(s) to tighten the door
further against rubber shall also be provided.
Bolted flange joints shall be of dust tight construction and necessary sealing
material shall be provided in all the flange connections for adequate sealing
REV. NO.: R3
PAGE 57 OF 506
4.1.3.6
Flap gates
Suitable travel and thrust dependent limit switches shall be furnished. These
shall be placed internal to the drive unit and shall be completely dust-proof. The
limit switches shall be capable of adjustments to vary the total length of travel of
the gates. The travel dependent switch shall control the travel and prevent any
over travel of gates on either direction. The thrust dependent limit switch shall
trip off the actuator motor in case of excessive thrust due to jamming of the
gates during its travel in either direction.
Both faces of flap gate main plate, liner plate of suitable material and thickness
shall be provided as per enclosed data sheet.
For standardization purposes, only one standard type of actuator for flap gates
shall be provided as per enclosed Data Sheet.
Approach/maintenance platforms complete with the chequered plate floor, hand
rails, ladders etc. shall be provided for all flap gates.
REV. NO.: R3
PAGE 58 OF 506
4.1.3.7
Rack and pinion gates shall be complete with all accessories as specified herein
after and shall conform to the requirement specified unless modified in data
sheet A.
plat and run on suitable rollers mounted on both side of frames. Wheel shall be
mounted and keyed to shaft for safe operation. Hold back device shall be
provided with the pinion shaft to ensure non-reversal of the gate movement
during opening and closing.
Gate shall be provided with seals on all four sides. Pressure lubricated tight ball
bearings shall be provided for shaft and rollers. The gate plate shall be provided
with suitable liner fixed on gate plate.
Pinion shaft shall be of EN 8 material. Wheels, Pinions and racks shall be made
of CI, IS: 210 grade 260.Chain shall conform to IS: 2429.
4.1.3.8
Primary Crusher
Rotary breaker shall be used as primary crushers to reduce the coal size from (-)
300 mm to (-) 150 mm. Crusher shall be supplied complete with accessories
and sub systems.
Crushers shall be provided with vibration isolation system.
REV. NO.: R3
PAGE 59 OF 506
The drive chain equipment for each crusher shall consist of drive motor, fluid
coupling. The crushers with its drive chain equipment shall be mounted on a
base plate with necessary accessories, e.g., anchor bolts, coupling guards etc.
The entire inside surface of crusher coming in contact with coal shall be
provided with abrasion resistant steel liners.
The Plummer block shall be fixed with minimum four numbers of high tensile
steel bolt studs of adequate size complete with adequate locking device and
locating arrangement. Also, the jacking screw shall be provided for easy lifting
of top part of the plumber block.
Additional support shall be provided to plummet block across the longitudinal
axis of crusher rotor to take care of misalignment against certain jerk, regular
vibration etc., with simple readjustment facilities. Further, Plummer blocks shall
be provided with provisions for installing vibration monitoring equipment.
Necessary locking arrangements shall be provided for suspension bars at both
the ends of rotor assembly to arrest any relative movement of the same.
Two
REV. NO.: R3
PAGE 60 OF 506
4.1.3.9
Secondary Crushers
Crusher shall be provided for sizing the input coal to (-) 150 mm size and (-) 20
mm size output coal. Crusher shall be supplied complete with accessories and
sub systems.
Crushers shall be provided with vibration isolation system.
Design and general arrangement of crusher shall permit easy maintenance,
maximum accessibility for inspection and effective dust sealing.
REV. NO.: R3
PAGE 61 OF 506
Two
does not occur during operation, particularly during rainy season when the coal
gets sticky. The segregated material shall be directly fed onto the corresponding
belt conveyors/feeders through separate hoppers/chutes provided under each
vibrating screen. The width of vibrating screen shall match to feed the material
uniformly over the entire length of crusher rotor without any deflector in the
feeding chute.
Construction Requirement
The deck of vibrating screen shall have robust construction.
The vibrating screens shall be mounted on the floor with the help of helical
springs made of alloy steel. No rubber/synthetic material for the support shall
be acceptable.
Suitable sealing arrangement shall be provided between the vibrating structure
and chute work to avoid dust nuisance in the surrounding area. Proper
REV. NO.: R3
PAGE 62 OF 506
feeder shall be of unbalanced motor type. The vibrating feeders and their
mounting arrangement shall be properly designed to suit the existing lay out. It
shall be ensured that no vibration is transmitted to the supporting/surrounding
structures from springs / Rubber cushions. The trough of the feeders shall be of
tray type construction and shall be made out of minimum 8 mm thick MS plate
(IS 2062-1992). Liner (Sail Hard) shall be provided inside the trough bottom
along its length and sidewall for entire cross section. The trough liner shall be
provided with adequate side guard to avoid spillage. Liners shall be fitted with
counter sunk head bolt. The trough shall be covered with dust tight hoods with
provision of cut out and flange for dust extraction. The equipment will be
provided with enclosed dust proof vibrators (un-balanced masses). The
unbalanced mass unit (minimum Four (4) for each motor) shall have provision
for change near location as required at field. The feeders shall be of base
mounted type.
Each vibrating feeder shall be supplied complete with supporting structures,
feed chutes, manually operated feed control gates, hood cover, electric plates
and fixing nuts and bolts, suspension rods, turnbuckles etc. Anchor bolts for
base mounting connection for base mounted feeders, if any, to the floor are also
included under the scope of supply of the bidder.
The successful bidder shall insure that minimum amount of assembly will be
required for erection and commissioning of equipment at site. Site welding etc.
shall be avoided as far as possible.
The feeders shall be of robust construction and of balanced design.
Existing Switchgear and Control System shall control vibro-feeders for flow
control.
Duty Condition
The feeder is to be installed under surge hopper in crusher house and shall be
required to operate all the three shifts per working day and 330 days per year.
REV. NO.: R3
PAGE 63 OF 506
The surrounding may be quite dusty and wet. The feeder shall be able to give
satisfactory performance under the worst working condition.
Constructional Features
General
The feeder shall be of adequate strength to withstand heavy-duty operation. It
shall be sturdy and robust in construction and at the same time can give
uninterrupted operation. It shall have inherent design characteristic viz. rugged
construction low power consumption, low maintenance and variable rate control.
Trough
The trough and trough frame shall be rugged enough for duty condition and
shall be designed for easy assembly and dish-assembly. The trough shall be
provided with replacement abrasion resistant liner plate. The size of the feeder
shall be selected to suit the duty condition. Trough shall be constructed from
Mild steel fabricated from plates and sections. Wear resistant liners shall have to
be used for heavy-duty application purpose.
Stroke Length
The equipment shall have long stroke and low frequency to give the required
Rated output of 1000 TPH. The frequency controller suitable for manual, remote,
automatic adjustment shall have to be used from 0 100% of the capacity
utilization.
Drive Unit
The feeder shall have low HP to weight ratio so as to permit the use of small
motor to drive the eccentric weights at the optimum frequency for a specific
application. The feeder should have each starting, smooth stopping features and
shall operate at extremely low noise level.
Lubrication
Grease nipples are to be provided at all bearing points for manual greasing. The
arrangement for centralize greasing system should also be provided.
Compliance to standards
The design and construction of the feeder shall conform form to the relevant ISS
or equivalent international standard. The material of the different component of
the feeder shall have to be selected to suit heavy-duty application purpose.
REV. NO.: R3
PAGE 64 OF 506
Electro-hydraulic thruster operated rail clamp shall be provided for holding the
REV. NO.: R3
PAGE 65 OF 506
The rail mounting for under-carriage shall be four legged system with
hydraulic/mechanical equalising arrangement to make it three point suspension
system for the best stability during operation. The traverse carriage and the
under-carriage shall be interconnected in a manner, which will permit uniform
distribution of overloads even if the rails are not level.
The bucket wheel boom shall be provided in Centre of machine and suspended
on supporting mast.
The drive mechanism of the boom conveyor shall consist of protective devices
against overloads. The slew speed shall be variable. Boom conveyor shall be
The hydraulic system of luffing of bucket wheel boom shall be such that in case
of failure of hydraulic system due to leakage or any other reason the boom
could be held in position.
Bucket wheel drive system with hydraulic coupling shall be provided. The
buckets shall be readily removable. Bucket wheel drive would be revisable type
to facilitate withdrawal of wheel in event of under cutting. Material shall be
reclaimed by buckets and discharge into boom conveyor.
One tripper and one intermediate conveyor shall be furnished for stacker-cumreclaimer unit for working in conjunction with the yard conveyor. The tripper &
intermediate conveyor shall be complete with supporting structure, walkways,
platforms, railing, belt scrapper, head pulleys, bend pulleys, hold-down pulley,
chute and support of welded constructions with wheel bogies.
Group-wise lubrication system shall be provided combining different zones of
lubrication points under different groups depending upon location and number
of lubrication points.
REV. NO.: R3
PAGE 66 OF 506
shall run in a cable tray in-between the track rails. Cushion shall be provided in
the cable reeling drums for about 15 m extra cabling length.
Further, limit switches shall be provided to prevent traverse movement, slew and
hoisting etc. beyond the respective safe extremities. Interlocking shall also be
provided for S/R rail clamps and travel motors.
Hydraulic control shall be provided for:
Hoisting/luffing
Construction Requirement
Suitable RCC platform to be provided at one end of travel of the stacker-cumreclaimer to rest the head end of the boom during maintenance or out of
operation. Walkways with hand railings shall be provided on both sides of boom
conveyor.
The air conditioned operators cabin shall be suitable for operation in monsoon
and tropical conditions. The cabin shall be provided with toughened glasses with
wipers and the arrangement shall be such that glasses can be cleaned from
outside without any scaffolding. The cabin shall be kept in horizontal position
through hydraulic cylinders irrespective of the angle of inclination of the boom
conveyor. Lights and fan for operators cabin shall be provided.
REV. NO.: R3
PAGE 67 OF 506
Primary samplers (separate for each conveyor) shall be rugged, able to withstand
severe shock loads and operate trouble free.
Belt feeders shall be provided for entire sampling path up to sample collector.
The feeders shall meter the flow accurately, produce a non-plugging condition
and resist sticky and wet coal. For rejects path also, belt feeders shall be
preferred.
Lot size shall be equivalent coal quantity handled in 8 hours operation
assuming average conveyor loading at 75% of rated conveyor capacity. However,
sampling system shall also be suitable for taking one gross sample for each lot
of coal in one full rake load.
Minimum 4 nos. sample collecting bins of stainless steel shall be provided. The
bins shall be provided with air tight connection and automatic indexing
arrangement.
Construction Requirement
The traversing mechanism and all parts including electrical shall have dust tight
protection. Belt feeders shall be positively self cleaning. No chain/belt drives
shall be accepted. The primary / secondary samplers shall be self-contained
type.
The crushers base should be built of reinforced concrete and be sufficiently
large in mass.
No control gates to regulate the flow of material shall be incorporated in the
chute work.
Bias connections shall be provided at suitable locations. The materials rejected
from samplers shall be returned to main conveyor stream
REV. NO.: R3
PAGE 68 OF 506
complete
with
rails,
including
necessary
supporting
structures,
approach/ maintenance platforms with ladders and hand railings, trailing cables,
all electrical including machine mounted local control panel & control panel on
one end of Bunker.
Design Requirement
It shall also consist of belt scrapper with adjustable rubber strip, rubber lagged
head and bend pulleys complete with shaft bearings, chutes, stops & limit
switches, brakes etc. The tripper shall have provision for dropping coal both
sides of conveyor into the bunker and also back to the conveyor for the purpose
of skipping intermediate bunkers.
The rating of tripper travel motor shall be adequate to move the tripper
smoothly either in same or opposite direction to belt direction under fully
loaded conditions. Coefficient of adhesion shall be considered as maximum
0.15.
Minimum two drive axles shall be provided for tripper travel. Arrangement shall
be provided at the starting point of the tripper to avoid folding of belt.
In case of tripper running at a speed more than its rated speed due to chute
jamming or other reason, conveyor shall trip and annunciation shall appear.
The supporting structures for the rails with necessary end stops shall also be
supplied under this specification. Suitable belt hold down guide pulley shall be
provided over the concave curve of belt over tripper.
The Bidder shall include in his proposal necessary electrical for traveling trippers
such as motorised cable reeling drum with trailing cables, cable trays for resting
the trailing cables and end limit switches for protection against over travel of the
tripper. The cable reeling drum and trailing cable of each tripper shall be
suitable for the entire length of the bunker bay. Mechanical track stops shall
also be provided. The cables shall have copper conductors, proper insulating
material and braided armouring in accordance with IS: 691.
REV. NO.: R3
PAGE 69 OF 506
The traveling trippers shall be provided on either side with fail-safe A.C.
thrustor operated brake of totally enclosed type, which shall engage as soon as
tripper travel motor stops. A.C. thrustor operated rail clamps with hand
operation facility from either side of the tripper shall also be provided.
The bunker sealing arrangement shall keep the bunkers sealed and prevent dust
emission into tripper room. Separate openings shall be provided on the bunker
floor of each bunker to measure level of coal in the bunker. Hinged door/flaps
shall be provided on these openings.
Suitable grating to be provided in between bunkers in the tripper travel zone.
Opening size will be decided during the detail engineering stage.
Construction Requirement
Suitable dust cover shall be provided over tripper head pulley. Serrated rubber
seal shall be provided at open side to prevent dust nuisance. Suitable dust tight
access doors shall be provided. Counter-weighted type belt cleaner shall be
provided below the tripper head pulley for cleaning the carrying side of the belt.
The tripper shall run on rails (90 lbs/yard) with double-flanged wheels. Rails for
tripper travel shall be mounted on supporting structure of respective conveyors.
Suitable system for monitoring position of tripper shall be provided. In addition,
travel end limit switches and end stops shall also be provided.
Suitable access platform of chequered plate with ladders, hand railing and
walkways on both sides shall be provided for access/maintenance of equipment
on tripper.
operator can cross the belt through the same. Needed guide rollers, bearings,
brackets, safety guards etc. shall be provided by the Bidder.
Suitable rail cleaners shall be provided on leading and trailing edge of tripper for
either track. 3mm deck plate continuous shall be provided below carrying idlers
on the tripper conveyors.
Provision shall be kept for automatic tripping of bunker bay conveyor in event of
traveling tripper getting dragged (i.e. travel speed in excess of rated speed).
REV. NO.: R3
PAGE 70 OF 506
Rail clamp shall be designed for holding the machine stationary. Electro
Hydraulic thrustor shall be fitted directly above spring without any intermediate
linkage mechanism. Rail clamp shall operate satisfactorily under this condition
without the need for any adjustments.
conveyors as specified. The sets shall be complete in all respects with drives,
magnets, inline belts, hoppers, chutes, tramp-iron boxes and all electrical
ancillaries like control panels etc. The magnetic separator shall be able to
separate M 20 bolts and nuts and 50KG MS Plates/ MS round bar of L/D ratio of
less than 5.
Design Requirement
The minimum strength of the magnet shall be 1000 gauss (force index of
magnet shall be 100000) at the specified mounting height. Designer shall select
magnet width to suit above.
Characteristic curve of magnet with the value of flux density varying between 50
mm from magnet surface to face of conveyor belt shall be provided. The
magnetic separator shall be located such that it picks-up tramp iron from coal
trajectory after it has been discharged from head pulley.
Suitable zero speed switch shall be provided.
REV. NO.: R3
PAGE 71 OF 506
The belt shall be designed to withstand high temperature at the bottom of the
magnet and any serious damage due to the impact of the sharp edges of the
tramp iron. The belt shall be provided with rubber cleats spaced suitably.
Construction Requirement
Suitable structural member from the top shall support the magnetic separator
units by taking support from the operating floor beams with turnbuckle
arrangement to facilitate the necessary adjustments during operation.
ON/OFF control push buttons with indicating lamps shall be provided at the
local station.
Suitable arrangements shall be provided in the magnet for keeping the coil of
the magnet dry from atmospheric condensation when the magnetic separator is
not in use.
IS: 11547
REV. NO.: R3
PAGE 72 OF 506
The electronic systems shall include all signal conditioning, power amplifiers
and printed circuits etc. The printed circuits shall be encapsulated against dust
and moisture.
It shall be suitable for outdoor installation in a dusty area. The electronic circuit
enclosure, sensors housing shall be dust and water tight and explosion proof.
The electronic printed circuits shall be encapsulated with epoxy or other suitable
material for protection against dust and moisture.
The contractor shall furnish one (1) necessary test load chain sets required for
calibration and periodic testing of the equipment.
sensor shall be protected from rain and direct sunlight by means of a nonmetallic covering other than wood. Control unit shall have adjustable controls
for sensitivity, ON/OFF push buttons, reset table operation counter, audio-visual
alarms local remote selector switch and all other necessary controls for trouble
free operation of metal detector. It shall be suitable for mounting on wall,
column, structure etc. with IP-65 Degree of protection. It shall be constructed
from FRP with thickness not less than 2mm.
REV. NO.: R3
PAGE 73 OF 506
pieces of tramps, if any, between tramp marker and coil before restoring
conveyor. TOTAL COUNT, which is not reset table, shall also be provided on the
same LED display on demand.
IS: 3681
IS: 7403
The gearboxes shall be designed for 24 hours continuous duty. Gearboxes with
cooling coils are not acceptable.
The gears used shall be helical or worm reduction units or spiral bevel speed
reduction units conforming to suitable Standards. Above 40 kW drive rating, all
gearboxes shall be helical or bevel helical type only.
Gear Boxes shall be of sealed type and mounted on machined or ground
surfaces.
Service factor will be taken 1.25 for conveyor drive gearboxes and for gear
boxes in other application service factor will be taken 1.2
Flexible Couplings
The design of the coupling shall be such that it can take shock and
misalignment without sacrificing its efficiency.
provided on low speed side of gearbox for all conveyors. Flexible couplings shall
be geared type.
Fluid Couplings
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
PAGE 74 OF 506
Fluid couplings shall be provided in all the drive chains for belt conveyor
systems and coal crushers if the actual power requirement at motor output shaft
is more than 30 KW. The fluid coupling for LT motors shall be of traction type
(except for yard conveyor). Cooling water coils for traction type fluid coupling
shall not be accepted.
actuators shall be provided for scoop tube operation from local as well as
remote.
allJTS and crusher house. Dust Extraction System shall be with dry type off
cyclone separator and/or bag filters.
manually by provision of suitable globe valve and gate valve combination. The
throw and spread of the swiveling nozzles will be so selected that two or three
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
PAGE 75 OF 506
4.1.3.23 LOCOMOTIVE
Locomotive shall have two 2-axle bogies with all 4 axles independently
motored. The locomotive shall have two diesel engines of 350 h.p. Gross driving
two nos. traction generators. The generators output is fed to the traction. Power
from the Traction Generators will be transmitted to bogie wheels by means of
four traction motors through a single reduction spur gear unit having a gear
ratio of 17 / 94.
The design incorporates the features and equipment well proven in traction
service and conforms to the extent possible to Indian Railways Standards.
The Loco shall be designed for fairly heavy rainfall and dusty atmosphere.
The leading dimensions and data of the CAR shall be as under:
Wheel Arrangement
BO-BO
Rail Gauge
37180001108
22.5t 3%
68 Liters.
1000 mm
2200 mm
6000 mm
11500 mm
3040 mm
Maximum Height
4030 mm
1065 mm
REV. NO.: R3
PAGE 76 OF 506
17/94
90 + 0% Tonnes
- 3% Tonnes
Negotiability on Curve
45 Meters
Two
Diesel Engine
nos.
Cummins
India
Make
NTA855L
Two nos. MIS BHEL make, Type
Traction Generator
TG4302AZ
Traction Motors
LME/1242
Maximum speed
30Kph
The loco shall be able to operate satisfactorily under the following conditions:
Ambient Temperature
0- 55 deg. C
Altitude
Humidity
40 % to 100 % RH
Mechanical Parts
Main Frame
The main frame shall be all-welded steel construction using rolled sections and
plates. It shall be designed to withstand a squeeze load of 400 tonnes. The
frame ends shall be suitable for fitting standard transition type center buffer
couplers, draft gear and side buffers.
The design of the main frame shall permit lifting the complete locomotive from
suitably located jacking pads and lifting pins.
The design of the main frame shall include a heavy deck plate extending over
the entire length of the frame. All equipment shall be mounted on the deck plate
through brackets and pads suitably positioned for both the Power Pack.
Provisions shall be made in the design of the main frame for placement of
ballast weights as required to increase I adjust locomotive axle load.
REV. NO.: R3
PAGE 77 OF 506
Cast steel bogie centre pivot rings shall be welded onto the bogie frames. These
shall be provided with mild steel liners at the bottom on which the pivots of the
main frame shall rest. Metallic sideliners shall also be provided. Oil lubrication
shall be provided between the pivot of mainframe and pivot seat of bogie.
Multi wear mono block rolled steel wheel shall be fitted on fully machined forged
axles having outboard bearing journals.
Sealed grease lubricated A P taper roller bearings, with adapters shall be used
on the axle bearing journals. The adapters shall be of cast steel with welded
manganese steel wear liners.
Sand boxes and pneumatic sand traps shall be provided as a part of our
standard design at each end of the two bogies to deliver sand to the respective
wheels.
The wheel hub shall be provided with the arrangement for easy extraction of
wheel from axle by oil injection devices.
Brakes
The locomotive shall be provided with air brakes for the locomotive. All wheels
shall be provided with clasp brakes, with 2 opposed brake blocks acting on each
wheel tread. The brake blocks shall be of the composite type having cast steel
brake shoe holders carrying renewable cast iron brake shoe inserts.
Effective brake force on each wheel shall be in the range of 70-80% of the wheel
load. Adjustment of the brake power to suit wheel load shall be achieved by
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
PAGE 78 OF 506
corresponding adjustment of the brake cylinder air pressure. The brake rigging
linkage shall be common for all axles.
A hand brake shall be provided, which shall act on two wheels of anyone axle,
through the same set of brake blocks and rigging as for main brakes. The hand
brake shall also be actuated from the driver's cab.
Buffing and Drawgear
Each end of the locomotive shall be fitted with a standard transition type centre
buffer coupler, draw gear and side buffers (using rubber pads).
Superstructure
The superstructure shall essentially comprise of driver's cabin and separate
hood for radiator, diesel engine & generator for ease of handling during
maintenance.
The entire superstructure shall be fabricated from rolled sections and clad with
rolled sheet. The arrangement for attaching the superstructure to the main
frame shall permit easy removal when required.
A hood shall be provided over the each power pack. The superstructure of the
hood shall be of fabricated steel construction, thoroughly braced and secured to
the main frame.
The layout of the full width cab shall be such as to enable free movement by the
driver from one side to the other.
Cab roof and sidewalls shall be provided with internal paneling of steel sheet
with glass wool insulation.
Entry to the cab shall be through two diagonally opposite doors leading from the
walkways.
Provision shall be made for large sliding glass windows on the cab side panels
and fixed glass windows on end panels. All glass panels shall be of safety glass
mounted in rubber bidding.
Two upholstered seats shall be provided in the cab.
REV. NO.: R3
PAGE 79 OF 506
Two numbers dry powder type; 2.5 kg capacity fire extinguisher shall be
provided.
Fuel Tank
A fuel tank fabricated from heavy gauge steel plate shall be located below the
main frame and between the bogies. The tank has capacity of approximately
3000 litters. The tank shall be provided with a standard filling connection; a
glass level indicator; a vent and cleaning out lets.
Equipment
The Power pack shall consists of CIL, Pune make diesel engine NT A855l as
prime mover for Traction Generator TG 4302AZ. The output of traction
generator is fed to axle hung nose suspended traction motors TM 4605AZ
(BHEL) through single reduction gear ratio of 17/94.
Diesel Engine
The locomotive shall be powered by Kirloskar Cummins Diesel Engine. Details of
diesel engine are as given below:
Make
Type
NTA855l
Cylinder arrangement
In Line
140 X 152
BS 5514
Engine governing
winding for cranking of the engine. The frame is circular rolled steel fabrication
with laminated poles and field coils. The armature is built on solid shaft with a
steel fan. The commutator has arch bound construction. Anti-friction bearing
mounted in the frame supports one end of the generator armature, and the rear
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
PAGE 80 OF 506
main bearing of the engine supports the other end. The magnet frame is bolted
to the engine flywheel housing.
The machine receives its cooling air through the car body filters.
This alternator confirms to the following parameter:
Application rating
Weight complete
900KGs
Ventilation
Self cooled
Feature
Traction Motors
Connections
Application rating
Maximum Current
1000 Amps.
1935 Kgs.
Ventilation
Forced Cooled
REV. NO.: R3
PAGE 81 OF 506
For ease of maintenance, valves, filters and other fittings in the air circuit shall,
as far as possible be grouped together.
Blower
One blower per power pack shall be provided. Each of these blowers is rated for
4000 cfm. Each blower provides cooling to the two traction motors of one bogie
through duct.
Lighting
The locomotive shall be provided with headlight at each end.
Aspect lights shall be provided with headlight at each end.
The cab shall be provided with lights on the ceiling for general illumination. The
load ammeter & air pressure gauges shall be illuminated.
Conveniently positioned lights shall be provided in the hoods.
Fan
One ceiling fan shall be provided in the driver's cab.
Horn
Two dual- tone pneuphonic horns shall be provided with air-operated wipers.
Controls and Instruments
Driver's Controls
The necessary controls and gauges for the operation of the locomotive by the
driver shall be provided at two control stations on both sides of the cab. These
controls and gauges are completely duplicated and consist of the following:
-
Throttle Handle
Reverse Handle
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
PAGE 82 OF 506
Horn Switch
Load Ammeter
Wiper Switch
Battery switch
Ground fault
Wheel slip
load Ammeter
Battery ammeter
IS: 807:1976
REV. NO.: R3
PAGE 83 OF 506
IS: 3815
IS: 325
IS: 3938
IS: 3043
REV. NO.: R3
PAGE 84 OF 506
with class-F insulation limited to temperature rise of Class-B and suitable for
heavy duty reversible crane service with duty rating as per data sheet A. The
starting torque of motor shall not be less than 2.75 times the rated torque and
pull out torque shall not be less than 250% of the rated full load torque.
Hoist motion shall be provided with two brakes.
electro hydraulic thyristors and other electromagnetic type. The design shall be
such that braking action in the off position and release with current are
provided.
Trolley travel shall be provided with electro-magnetic brake.
The brake shall be effective in both directions. All brakes shall apply
automatically when power supply fails or when the main contactor is in off
position or emergency push button is operated.
Each hoist will be operated Pendent push button station. The pendent push
button station shall be robust and heavy-duty type. It shall be suspended by
wire rope to prevent pull on cables.
For trolley travel, flexible trailing cable system mounted on retracting
supporting system shall be preferred. The conductors shall consist of insulated
conductor cables with permanent Termination on hoist machinery.
Suitable limit switches shall also be provided to limit the travel of bottom block
at either end of its travel when lowering and hoisting. Similarly limit switches
shall be provided to limit the travel of trolley at either end of its travel.
Hoists will move on Monorail beam supported on structures.
Training
Further to
REV. NO.: R3
PAGE 85 OF 506
4.2
ELECTRICAL
4.2.1
Power Transformer
4.2.1.1
Design criteria
The power transformer of 11 kV/3.6 kV, three phase, two winding, 50 Hz,
ONAN/ONAF cooled transformer with OCTC 5% in steps of 2.5% on HV side.
The minimum quantity will be as per the Electrical single line diagram.
The 11/3.6 kV power transformers shall be oil immersed type rated for 100%
load and shall be three phase, two winding, ONAN /ONAF cooled with off circuit
taps of 5% in steps of 2.5% on HV side.
The impedance of 11/3.6 kV transformers shall be so chosen such that the fault
level does not exceed short circuit capability of 40 kA for 3 sec on 3.3 kV
Switchgear including the motor contributions. The voltage drop should not be
more than 10% at the bus during starting of the highest motor when transformer
is fully loaded.
Voltage variation
10%
b.
Frequency variation
5%
c.
10%
frequency variation
absolute sum)
REV. NO.: R3
PAGE 86 OF 506
Transformers shall operate below the knee point of the saturation curve at 110%
voltage to preclude Ferro-resonance and non linear oscillations.
Starting from Hot condition, transformers shall be capable of remaining in
operation for following conditions without injurious heating after failure of
forced cooling:
a. At full load for not less than 10 minutes after outage of all cooling
Sizing
points and all other loads and based on the ambient temperature. The basis
given below is the minimum requirement. In case during the operation of plant it
is found that the rating selected is not adequate due to incorrect load
assumptions or due to any other reason, it will be Contractors responsibility to
replace the transformer and associated switchgear and breakers.
MVA rating of the transformer shall be based on the actual load figures and
redundancy.
Each transformer shall be rated to cater to the entire load on the respective
switchgear taking into consideration the outage of the other transformer.
The rating that shall be established shall take into account load variations
during the design engineering stage. Due consideration for reduction in
capacity due to transformer regulation shall be given. Spare Capacity of at
REV. NO.: R3
PAGE 87 OF 506
least 10% shall be available in each transformer at the time of handing over
the plant.
4.2.1.3
Specific Requirements
Tanks
The tank shall be fabricated from good commercial grade low carbon steel of
adequate thickness and shall be of welded construction.
The tank wall shall be reinforced by stiffener to ensure rigidity so that it can
withstand
without
any
deformation
(a)
mechanical
shock
during
transportation, (b) oil filling by vacuum, c) Short circuit forces and (d)
continuous internal pressure of 35 kN/m2 over normal hydrostatic pressure
of oil, e) Continuous vacuum of Mercury as specified in CBIP.
All removable covers shall be provided with weatherproof, hot oil resistant,
resilient gaskets. The design shall be such as to prevent any ingress of water
into or oil from the tank.
The tank shall be provided with one set of bi-directional flanged wheels for
rolling the transformer parallel to either center line over 1676 mm rail gauge.
In case more than two rails are required to be provided the rail gauge of
1676 mm shall be maintained between two adjacent rails
Jacking pads, lifting lugs and pulling eyes shall be provided to facilitate
movement of the transformer. All heavy removal parts shall be provided with
eye bolt for ease of handling.
One drain valve, which can be operated safely even when transformer is on
fire, located away from main transformer, shall be provided.
Suitable guide shall be provided in the tank for positioning the core and coil
assembly.
Adequate space shall be provided at the bottom of the tank for collection of
sediments.
The core shall be built up with high grade, non-aging, low loss, high
permeability, grain oriented, cold-rolled silicon steel laminations especially
suitable for core material.
The laminations shall be free of burrs and sharp projections. Each sheet shall
have an insulating coating resistant to the action of oil,
Insulation structure for the Core to bolt and core to core clamp plates shall
be adequate such as to withstand a voltage of 2 kV for one minute.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
PAGE 88 OF 506
Winding shall not contain sharp bends which might damage the insulation or
produce high dielectric stresses. No strip conductor wound on edge shall
have width exceeding six times the thickness.
All leads from the windings to the terminal board and bushings shall be
rigidly supported to prevent injury from vibration or short circuit stresses.
Guide tube shall be used where practicable.
The core and coil assembly shall be securely fixed in position so that no
shifting or deformation occurs during movement of transformer or under
short circuit stresses.
Off circuit taps as specified shall be provided on the high voltage winding.
The transformer shall be capable of operation at its rated kVA on any tap
provided the voltage does not vary by more than 10% of the rated voltage
corresponding to the tap.
The off circuit tap changing will be by a three phase gang operated switch.
Arrangement shall be such that contacts are correctly engaged.
A warning plate indicating that switch shall be operated only when the
transformer is de-energized shall be provided. Arrangement shall be such
that switch can be operated at standing height from ground level. The
operating handle can be padlocked at any tap position. The design shall be
such that lock cannot be inserted unless the contacts are correctly engaged.
REV. NO.: R3
PAGE 89 OF 506
The mechanism shall be provided with a tap position indicator. All contacts
shall be silver plated and held in position under strong contact pressure to
ensure low contact drop and avoid pitting.
Insulating Oil
The transformer shall be filled with mineral insulating oil suitably inhibited to
prevent sludging.
and
the
specific
requirements
specified
in
the
schedule
of
Test
Characteristics
Appearance
Methods
IEC: 296
Specification
Clear,
free
from
Density @
3
29.50C
Kg/cm3
Kinematic Viscosity,
ISO: 3675
---
---
0.820 - 0.895
mm2/s
@400C
11.0 Max
@270C
@
ISO: 3014
-300C
16.0 Max
1800Max
ISO: 2719
140 Min.
Pour Point 0C
ISO: 3016
- 30 Max
ISO: 6295
0.04
IEC: 296
0.03 Max
Corrosive Sulphur
ISO: 5662
Non corrosive
0C
(After filteration)
Resistivity
@270C
IEC: 247
@900C
11
(Before filteration)
2500 x 1012
150 x 1012
IEC: 247
270C
REV. NO.: R3
0.002 Max
0.0005
PAGE 90 OF 506
S.No.
Test
Characteristics
Methods
12
Antioxidant additives
IEC: 666
Not Detectable
13
IEC: 733
40 Max.
14
Oxidation stability
@
1000C
(164 hours)
0.15 Max
IEC: 74
900C
0.03 Max
0.1 Max
15
---
4 Max
16
Aromatic Content
FTIR
4-8
IEC: 247
25 x 1012 Min
IEC: 247
2 x 1012 Min
IEC: 247
0.1 Max
17
18
Specification
IEC: 296
0.05 Max
---
0.05 Max
FTIR
---
First filling of oil along with 10% excess shall be furnished for each
transformer. Oil shall be supplied in non-returnable containers suitable for
outdoor storage.
Oil preservation shall be by means of flexible oil resistant air bag sealed
conservator tank with silica gel breather to avoid direct connection between
atmosphere and transformer oil. It shall be complete with level gauges,
pipes, drain valve, air release valve & plugs, Air cell breather valve, pressure
gauge (on top of conservator) etc. The level gauges shall be so placed that
same can be readable standing from ground. Necessary device shall be kept
to provide annunciation in the event of rupturing of Air cell. Magnetic oil
level gauge shall be provided with low level contacts for signaling shall be
provided.
Bushings
REV. NO.: R3
PAGE 91 OF 506
Bushings shall conform to IS 2099 (for Electrical) and IS 3347 Part-IV (for
metal parts).
Terminal Arrangement
The physical position of the terminals and the markings shall be as per
relevant IS/IEC unless otherwise required to suit the layout.
The 11kV side shall be connected through self supported detachable type
cable end box. Gland plate shall be provided at the bottom to facilitate cable
entry.
Cooling System
Transformer cooling shall be ONAN/ONAF. In addition cooling equipment shall
conform to the requirement stipulated below:
a) The transformer shall be provided with 2 x 60% capacity cooler banks
mounted on transformer. Each cooling unit shall be complete with its radiator
banks, fans and other accessories.
b) Each cooler bank shall have its own cooling fans, shut off valves at the top
and bottom (80mm size), lifting lugs, air release plug at the top, a drain and
sampling valve at bottom.
c) Cooler fans of both cooler banks shall operate continuously. Each cooler
bank shall be provided with standby fan. Selector switch shall be provided for
selection of fans to be in service or in standby. Cooling calculation for
d) Suitable manual control facility for cooler fans shall be provided. Control
shall be suitable for manual and automatic operation of fans.
REV. NO.: R3
PAGE 92 OF 506
e) Cooling fan shall be suitable for operation on 415 + 10% V, three phase, 50
Hz +/-5% power supply. & shall conform to IS:325. Each cooling fan shall be
provided with starter with thermal overload & short circuit protection. The
motor winding insulation shall be conventional class F type. Motor shall have
enclosure with degree of protection equivalent to IP 55 as per IS: 4691. The
temperature rise of the motor shall be limited to 70 deg. C above ambient of
50 deg by winding resistance method.
Cooling fans shall not be overhung from radiator fins. They shall be mounted
on suitable structural members using vibration mounts. They shall be
provided with a galvanized mesh guards. Terminal covers and greasing cups
of fan motors shall be accessible without removing the guard. The fans shall
be removable without dismantling supporting framework.
f) Duplicate feeders shall be provided for cooler control cabinet. The contractor
shall supply all necessary equipment for automatic changeover from 415 V, 3
phase, 3 wire from notmal to standby incoming supply in the event of failure
of normal supply and vice versa. Changeover scheme shall included on delay
timer to prvent immediate changeover.
Marshalling Box
A sheet steel, weatherproof, IPW55, marshalling box shall be provided for the
transformer. The box shall contain all auxiliary devices except those which
must be located directly on the transformer.
All terminal blocks for cable connection shall be located in this box.
The marshalling box shall be provided with cubicle lamp with door switch,
space heater with thermostat and removable cable gland plate.
(two sets each) in the Marshalling box to facilitate wiring to remote panel /
DCS / PLC.
b)
c)
d)
e)
REV. NO.: R3
PAGE 93 OF 506
f)
PRV operated
Analog outputs
LV winding temperature
HV winding temperature
Oil temperature
Wiring
All control, alarm and indication devices provided with the transformer shall
be wired up to the terminal blocks.
Wiring shall be done with flexible, 1100 V grade PVC wires in conduit or PVC
armoured cable. Minimum wire size shall be 2.5 mm2 copper. Not more
than two wires shall be connected to a terminal. 10% spare terminals shall be
provided.
shall be provided for terminating the panel wiring. Terminals shall be stud
type, suitable for terminating 2 nos. 2.5 mm2 stranded copper conductor
and provided with acrylic insulating cover. Terminals for C.T. secondary leads
shall have provision for shorting and grounding.
Wire termination shall be made with crimping type connectors with insulating
sleeves. Wires shall not be spliced between terminals.
Grounding
The grounding pads, located on the opposite sides of the tank, shall be
provided for connection to ground mat.
Grounding pad shall have clean buffed surface with two tapped holes, M10
G.I. bolts and spring washers for connection to 75x10 mm G.I. flat.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
PAGE 94 OF 506
Two nos neutral earthing via neutral grounding resistor of required rating to
For continuity of earth connection, all gasketed joints shall be provided with
braided copper wire jumpers
4.2.1.4
Auxiliary Equipments
Current transformer
Two core, turret mounted, Neutral current transformer and Two core. Turret
mounted phase bushing current transformer with multi ratio taps (On one
phase of HV & LV winding) shall be provided.
The arrangement shall be such that the C.T. can be removed from the
transformer without removing the tank cover.
A double float type Buchholz relay of proven design complete with all
accessories such as test cock, gas collecting device and valves required for
sampling shall be provided. The device shall be provided with two electrically
independent contacts, one for alarm on gas accumulation and other for
tripping on sudden rise in gas pressure.
Pressure relief device
Tank shall be provided with two numbers of pressure relief device which shall
operate at a pressure below the test pressure for the tank and radiators. The
device shall be rain proof after blowing and shall be provided with a device
visible from ground to indicate operation. This device shall be equipped with
remote monitoring / alarm contacts.
Valves
Valves shall be of full way type with flanged ends and shall be opened by
turning counter clockwise when facing the hand wheel. There shall be no oil
leakage when the valves are in closed position. The flanges shall have
machined faces.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
PAGE 95 OF 506
Every valve shall be provided with an indicator to show the open and close
positions and shall be provided with pad locking facility. All flanged valves
shall be provided with oil tight blanking for protection.
Painting
The internal surfaces in contact with insulating oil shall be painted with heat
resistant insulating varnish which shall not react with and be soluble in the
insulating liquid used.
The external surfaces, after cleaning, shall be given a coat of high quality red
oxide or yellow chromate primer followed by filler coats.
The transformer shall be finished with two coats of synthetic enamel paint
conforming to shade 632 of IS 5.
Transportation
is left above the oil to take care of the expansion of the oil. The space is
filled with inert gas under atmospheric pressure.
Impact Recorder
Impact
recorder/indicator
shall
be
provided
to
monitor
the
impact
Oil conservator with filler cap, drain valve, plain oil level gauge, air release
valve & plugs, air cell breather valve, pressure gauge (on top of conservator)
and MOG.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
PAGE 96 OF 506
150 mm dial magnetic oil level gauge with low level alarm contacts
150 mm dial oil temperature indicator with maximum reading pointer and
electrically separate contacts for trip and alarm and embedded temperature
detectors (PT-100). Separate RTDs with CCU units with two numbers of
analog outputs shall be provided for remote indications.
Seven Numbers Thermometer pockets (two nos each for OTI, HV WTI, LV WTI
and one no spare).
Jacking pads at least four in number at suitable height for lifting the
complete transformer filled with oil, pulling eyes on each face of transformer
and lifting lugs.
Two-grounding pads.
Neutral earthing bar of copper of specified section installed from the neutral
bushing to ground level suitably supported along its run on porcelain
insulators together with clamping arrangements at neutral bushing.
Ladder with safety device for access to the top of transformer tank.
REV. NO.: R3
PAGE 97 OF 506
Weather proof marshalling box for housing control equipment and terminal
connections.
Rating and terminal marking plates, oil filling instruction plate, valve
schedule and caution plate.
4.2.1.5
Standards
All equipments provided under the specification shall in general, conform to the
latest issue of the following standards:
International &
Indian
Standards
Title
No.
IS: 2026
IS: 2099
IS: 325
Current transformers
IS: 375
IS: 3637
IS: 4691
IS: 2147
IS : 5
IS: 6272
IS: 320
IS: 3347
IS: 6600
IEC: 185
IEC: 34
IS: 10028
IS: 1866
standards
IEC: 76
IS: 2705
recognized
Power transformers
IS: 3639
IS: 335
internationally
maintenance of transformers
rotating electrical machinery
IEC: 144
IEC: 354
Electrical equipment
bushing
REV. NO.: R3
IEC: 60
IEC: 71
NEMA-TR-1
PAGE 98 OF 506
International &
Indian
Standards
internationally
Title
No.
recognized
standards
transformers
IS: 10597
IS: 9434
IEC: 567
equipment
IS: 12676
IEEE: 32
bushings
The electrical installation shall meet the requirements of Indian Electricity Rules
1956 & IS: 10028 Code of practice for selection, installation & maintenance of
transformers as named up to date.
4.2.1.6
Tests
Dielectric test.
REV. NO.: R3
PAGE 99 OF 506
Valid type test certificates for impulse test shall be submitted. The type test
report shall not be more than 5 years old. If valid type test certificate is not
available then type test shall be carried out on each type of transformers without
any extra cost. For short circuit the valid test certificate of similar transformer is
to be produced.
All auxiliary equipments shall be tested as per relevant standards. Test
certificates shall be furnished for brought out items. High voltage withstand test
(2000 V to earth) shall be performed on auxiliary equipments and wiring after
complete assembly.
4.2.2
4.2.2.1
General criteria
The number and rating of service transformers shall be decided based on the
Electrical single line diagram for auxiliary power distribution drawing without
sacrificing the unit and common load concept. The transformers shall generally
comply with specific requirements as follows:
The service transformers shall be rated for 100% load and shall be three-phase,
two winding, ONAN cooled with off-circuit taps of +/- 5% in steps of 2.5% on HV
side. The transformers shall be suitable for outdoor applications having Dyn11
Vector group. The star point shall be solidly earthed.
The impedance of the transformers shall be chosen such that the fault level does
not exceed the short circuit capability (50 kA /1 sec) on 415 V switchgear
including the motor contributions and also voltage dip while starting any
auxiliary does not exceed the limit acceptable for the equipment concerned but
not exceeding 10%.
In case of single core cable termination, gland plate shall be of aluminium.
Transformer shall operate without injurious heating, at rated MVA at any voltage
within 110% of rated voltage of that particular tap.
Transformers shall be capable of delivering the rated current, at a voltage equals
to 115% of rated voltage without exceeding rated temperature rise.
REV. NO.: R3
Transformer shall operate below the knee of the saturation curve at 110%
voltage to preclude ferro resonance and non-linear oscillations.
Transformers and accessories shall be designed for fault levels indicated in 415
V switchgear specifications. Dynamic ability and thermal ability to withstand the
short circuit force shall be demonstrated by tests / calculations.
Noise level shall be as per NEMA TR-1.
The transformers shall be designed with particular attention to suppress
harmonic voltage, especially third and fifth, so as to eliminate wave form
distortion.
Each transformer shall be rated to take care of the entire load on the respective
switchgear considering the outage of the other transformer. An appropriate
diversity factor with a minimum of 0.9 for continuously running loads and 0.4
for intermittent loads like cranes, plug points, sump pumps, elevator etc., shall
be considered.
The rating established shall takeinto account, load variations during the design
engineering stage. Due consideration for reduction in capacity due to
transformer regulation shall be given. Spare capacity of at least 10% shall be
available in each transformer at the time of handing over the plant.
4.2.2.2
Specific Requirements
The transformer shall generally comply with all following specific requirements
a)
b)
The tank cover shall be conventional one with bolted joint at the top
c)
d)
Off-circuit tap changers with lockable operating handle and mechanical tap
position indicator shall be provided.
e)
g)
The transformer shall be suitable for cable connection for HV /bus duct
f)
h)
For bus ducts suitable flanged bushing connection shall be provided. The
winding terminations shall be brought out on outdoor type of bushings.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
i)
If cables are used the neutral of the LV side of the transformer shall be
brought out in a separate cable box or if the same cable box is used for
neutral also, then metallic partition between phases and neutral shall be
provided.
j)
Transformer mounted protective devices (OTI, WTI, MOG, CCU, Neutral CTs,
etc) shall be provided and wiring from all devices mounted on
transformer such as OTI, WTI, MOG, Neutral CTs etc. shall be brought to
one terminal box with cables for connection to plant protection, indication
and controls. Remote winding and oil temp indicators is under the scope of
k)
the bidder The cables should not touch transformer body to avoid heating.
l)
Necessary lifting lugs, jacking pads, and pulling eyes shall be provided
lifting and skidding of transformers without removing oil.
m)
Each radiator bank shall be provided independently mounted with inlet and
out let valves to enable replacement of radiator when transformer is in
service.
n)
o)
The rating and nameplate shall contain all details as per IS 2026. In
addition, following details shall also be included.
i)
iii)
iv)
Transportation weight.
vi)
vii)
ii)
v)
viii)
Temperature rise
Untanking weight.
each winding.
ix)
p)
impedance is related.
REV. NO.: R3
drain valve, bolted cover at one end for cleaning, valves for shutting off oil
to transformer, breather and Buchholz relay.
4.2.2.3
Core
Core shall be constructed with high-grade cold rolled non-ageing grain oriented
silicon steel. Each lamination shall have insulated coating. The insulated
structure for core to bolts and core to clamp plates shall withstand 2.0 kV for
one minute. The core clamping structure shall be designed to minimize eddy
current losses. The core shall be provided with lugs for lifting of core with coils.
The core and coil assembly shall be rigidly fixed to avoid their shifting during
transport or short circuit. Frame work and clamping arrangement shall be
securely earthed.
Winding
Winding shall be made up of tinned or enameled electrolytic copper more than
99.9% purity unless and otherwise specified. Conductor shall be transposed at
sufficient intervals in order to minimize the eddy current. Permanent current
carrying connection in the winding shall be brazed or welded. Clamping bolts for
current carrying parts in the oil shall be made up of oil resistant material. The
coils shall be properly supported and shall be subjected to seasoning process so
that further shrinkage should not occur during service.
The complete core and coil assembly shall be dried in vacuum at not more than
760 mm of HG and Internal gas pressure of 0.35 kg/cm2 with oil at working
level. Top cover shall be bolted type to remove the core and winding at site. Man
holes with bolted covers shall be provided in the top / side of transformer for
REV. NO.: R3
gasket shall be of cork neoprene or better type and all gasketted joints shall be
so arranged that gaskets shall not be exposed to whether. Valves of forged
carbon steel up to 50mm and of gunmetal or of cast iron bodies with gun metal
fittings above 50mm shall be provided. Valves for drain, filtration, oil sampling,
vacuum pulling and radiator isolation shall be provided with adequate size.
Bushings
All the bushing shall be of porcelain type. Bushing rated for 400 A and above
shall have non-ferrous flange and hardware. Busing shall confirm to IS 3347 and
insulation level as per IS 2099.
4.2.2.4
Tests
Valid type test certificate shall be submitted. If valid type test certificate is not
available then type test shall be carried out on each type of transformer without
any price implication to Owner.
Routine tests as per IS 2026 on all transformers. In addition to all routine test as
per IS 2026, the following tests shall be conducted on one transformer of each
type and size.
a. Heat Run Test with dissolved gas analysis before and after.
b. Vacuum Withstand and deflection measurement on tank.
c. Pressure test on tank with deflection measurement
d. Measurement of losses and efficiency
REV. NO.: R3
4.2.3
HT Switchgear
4.2.3.1
Design criteria
and other loads in the plants. Duty involves direct on line starting of large
induction motors. The motor starting current shall be 6 times the full-load
current with IS tolerance, with a maximum of 3 starts per hour.
The switchgear shall be located in a clean but hot, humid and tropical
atmosphere. For continuous operation at specified ratings, temperature rise of
the various switchgear components shall be limited to the permissible values
stipulated in the relevant standards and/or this specification.
The Switchgear and components shall be capable of withstanding the
mechanical forces and thermal stresses of the short circuit current without any
damage or deterioration of material. Circuit breaker shall not produce any
harmful over-voltage during switching off of induction motors, unloaded lines
and unloaded transformers. If required, surge protective device shall be
provided in the scope of supply to limit the over-voltage
4.2.3.2
a) The fault level for the switchgear, circuit breakers, isolators, earth switch
shall be arrived at, on the following basis
e) Calculations for arriving at the time constant at this plant shall be furnished
to justify breaker selection in accordance with IEC for breakers.
REV. NO.: R3
4.2.3.3
a) The continuous current rating of the 3.3 kV switchgear buses and their
incomer breaker shall be rated as LV winding current of respective
transformer with 20% margin rounded off to the next higher standard rating.
b) The continuous current rating of the feeders shall be based on the name
plate current rating of the connected equipment with 20% margin.
c) The continuous current rating of 3.3 kV buses with bus coupler arrangement
shall be the maximum load on the bus due to running auxiliaries plus 20%
margin, rounded off to the next higher standard rating.
4.2.3.4
Detailed Requirements
4.2.3.5
The switchgear shall be indoor, metal clad, floor mounted, draw out type and
suitable for located in a clean but hot, humid and tropical atmosphere. Degree
of protection shall be IP42. Additional stiffeners shall be provided to increase
rigidity wherever cutouts are made.
Enclosure shall be constructed with rolled steel sections and cold rolled steel
sheets of at least 2.0 mm thickness, Gland plates shall be 2.5 mm thick made
out of hot rolled or cold rolled steel sheets and for non-magnetic material it
shall be 3.0 mm.
Each circuit shall have a separate vertical panel with distinct compartments for
circuit breaker/contactor truck, cable termination, main bus bars and auxiliary
control devices. The adjacent panels shall be completely separated by steel
sheets except in busbar compartments where insulated barriers shall be
provided to segregate adjacent panels. However, manufacturer's standard
switchgear designs without inter panel barriers in busbar compartment may also
be considered.
The circuit breakers / contactors and bus VTs shall be mounted on withdraw
able trucks which shall roll out horizontally from service position to isolated
position. For complete withdrawal from the panel, the truck shall rollout on the
floor or shall roll out on telescopic rails. In case the later arrangement is offered,
suitable trolley shall be provided by the Bidder for withdrawal and insertion of
the truck from and into the panel. The number of trolleys to be provided shall be
two nos. per switchboard.
REV. NO.: R3
The trucks shall have distinct SERVICE, TEST and ISOLATED positions. It shall be
possible to open the breaker/contactor compartment door in isolated position
only, so that the switchgear retains its specified degree of protection.
The switchgear assembly shall be dust, moisture, rodent and vermin proof, with
the truck in any position SERVICE, TEST, ISOLATED, and all doors and covers
closed. All doors, removable covers and glass windows shall have gaskets all
round with synthetic rubber or neoprene gaskets.
The VT/ relay compartments shall have degree of protection not less than IP: 52
shall (whether isolated or removed from panel) even when the breaker /
contactor compartment door is opened. Tight fitting gourmet/gaskets are to be
provided at all openings in relay compartment.
The switchgear construction shall be such that breaker operation and internal
explosions do not endanger the operating personnel, and the front of the panels
shall be specially designed to withstand these. Pressure relief device shall be
provided in each high voltage compartment of a panel, so that in case of a fault
in a compartment, the gases produced are safely vented out, thereby minimizing
the possibility of its spreading to other compartments and panels. The pressure
relief device shall not however reduce the degree of protection of panels under
normal working conditions.
The switchgear shall be cooled by natural airflow and forced cooling shall not be
accepted.
Total height of the switchgear panels shall not exceed 2600 mm. The height of
switches, pushbuttons and other hand-operated devices shall not exceed 1800
mm and shall not be less than 700 mm.
REV. NO.: R3
Safety shutters complying with IEC - 298 shall be provided to cover up the fixed
high voltage contacts on bus bar and cable sides when the truck is moved to
ISOLATED position. The shutters shall move automatically, through a linkage
with the movement of the truck. Preferably it shall however, be possible to open
the shutters of busbar side and cable side individually against spring pressure
for testing purpose after defeating the interlock with truck movement
deliberately. It shall also be possible to padlock shutters individually. In case,
insulating shutters are provided, these shall meet the requirements of Clause
3.102.1 Note -2 of IEC - 298 and necessary tests as per IEC -298 Clauses
5.103.1 shall be carried out. A clearly visible warning label "Isolate elsewhere
be provided, which will ensure that breaker is OFF before opening the back
doors.
In the Service position, the truck shall be so secured that short circuit forces do
not displace it. Bus bars, jumpers and other components of the switchgear shall
also be properly supported to withstand all possible short circuit forces
corresponding to the short circuit rating specified.
Suitable base frames made out of steel channels shall be supplied along with
necessary anchor bolts and other hardware, for mounting of the switchgear
panels. These shall be dispatched in advance so that they may be installed and
leveled when the flooring is being cast.Welding of base frame to the insert plates
as per approved installation drawings shall be in Bidder's scope.
Dummy panel shall be provided in the switchgear line up, if required, for easy
termination access of power and control cables. Dummy panel / bus trunking
panel shall be of full cubicle with closed roof and rear door similar to enclosures
for active cubicles.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
4.2.3.6
All bus bar and jumper connections shall be of high conductivity Copper with
specified
current
ratings
with
below
mentioned
maximum
temperature
90oC
105oC
It shall be possible to extend the bus bars at either end of the switchboard for
addition of panels in future. Both ends of bus bars must be suitably drilled for
this purpose.
Bus bar cross-section shall be uniform throughout the length of switchgear.
Continuous current rating of bus connections / dropper shall be same as that of
continuous current rating of associated breaker. Bus bars and other high voltage
connection shall be sufficiently corona free at maximum working voltage.
Contact surfaces at all joints shall be silver plated and no oxide grease applied
to ensure an efficient and trouble free connection. All bolted joints shall have
necessary plain and spring washers. All connection hardware shall have high
corrosion
resistance.
connections.
Suitable
bimetallic
connectors
shall
be
used
for
Bus bar insulators shall be of arc and track resistant high strength, nonhygroscopic, non-combustible type and shall be suitable to withstand stresses
due to over-voltages, and short circuit current. Bus bar shall be supported on
the insulators such that the conductor expansion and contraction are allowed
without straining the insulators. In case of organic insulator partial discharge
shall be limited to 100 pico coulomb at rated voltage x 1.1 / v3. Use of
insulators and barriers of in-flammable material such as Hylam shall not be
accepted.
Successful Bidder shall furnish calculation establishing adequacy of busbar sizes
for the specified continuous and short time current ratings.
REV. NO.: R3
Bus bars shall be color coded for easy identification and so located that the
sequence R-Y-B shall be from left to right, top to bottom or front to rear, when
viewed from front of the switch-gear assembly.
The temperature rise at the switchgear terminals intended for external cable
termination shall not exceed 40 deg. C. Further the switchgear parts handled by
the operator shall not exceed a rise of 5 deg. C.
4.2.3.7
The VCBs offered shall be of gang-operated type. The whole equipment shall
conform to the relevant IS/IEC specifications of the latest publications whether
specifically mentioned or not with regard to construction, safety protection,
clearance etc.
The VCBs along with accessories shall be mounted in a withdraw able truck. The
VCBs are meant for direct on-line charging of transformers and starting of
motors and for incomers/tie feeders.
The contact arms for connecting the Vacuum Circuit Breakers conducting part
to the main bus bars and to the cable side shall be of copper with silver plating.
High quality metal oxide surge arresters shall be provided with VCBs for
transformer & motor feeders.
The wiring for the VCBs shall be of plug and socket arrangement. The length of
the plug cord shall be such that the plug can be inserted into the socket only
when the breaker is in service and Test positions but it shall be necessary to
withdraw the plug from the socket before the breaker truck can be withdrawn
from the cubicle.
The VCBs shall be physically and electrically interchangeable.
REV. NO.: R3
The operating mechanism shall be stored energy type. The status of the closing
spring shall be such that the spring shall be automatically re-charged after the
closing operation of the breaker. The closing spring shall be charged through
220 V DC spring charging motors. Provision shall also be available for manual
charging. Each VCB shall be provided with necessary handle for the same.
Spring charging motor of suitable rating shall be provided with necessary limit
switches and protection. The spring charging motors supplied for all the
breakers shall be of the same make and rating. The charging time for the motors
shall not be greater than 15 secs at rated voltage. Motor shall be rated for 220 V
DC and shall operate satisfactorily at all voltage between 85-110% of the rated
voltage. Power supply to the spring charging motor shall be cut off when the
closing spring is charged manually.
The VCB shall be provided with suitable mechanical close and trip
devices.
material. Bearing pin bolts nuts and other parts shall be adequately pinned and
locked to prevent loosening or changing with repeated operation of the breaker.
The VCBs shall be provided with close release and shunt trip coils. The control
supply for the VCBs shall be through 220 V DC. The close release coil shall
operate satisfactorily at all values of voltage between 85-110% while the shunt
trip coils shall operate between 70-110% of rated voltage.
Provision shall be made available in the VCB for checking the wear of the main
contacts.
Each VCB shall be provided with auxiliary contacts / limit switches as indicated
below.
Sufficient number of auxiliary contacts operated by the breaker mechanism for
interlocking / indication / feedback purpose shall be provided.
Auxiliary
REV. NO.: R3
All auxiliary contacts of the VCB including the spare contacts are to be wired and
brought up to the multi pin control plug.
Positive earthing of the circuit breaker frame shall be maintained with the earth
bus in the breaker compartment in test and service positions. The circuit breaker
frame shall be earthed before the main breaker contacts / control circuit
contacts are plugged in the associated stationary contacts.
The following interlocks are to be provided.
a)
The truck cannot be moved from test to service or vice versa when the
breaker is ON
b)
c)
The control wiring plug cannot be disconnected from the socket when the
d)
Provision shall be made to trip the breaker if tried to draw out when the
breaker is in closed condition.
Supporting insulators for the poles shall be of epoxy cast resin type and shall be
able to withstand stresses due to maximum short circuit current.
The bus bars fixed in the breaker shall be of electrolytic copper of suitable cross
section to withstand a short circuit current of 40 kA/3 sec.
Inter pole insulation shall be provided between adjacent poles. The entire joints
/ connections end shall be silver plated.
ensured.
Control wiring for the breaker shall be with single core, flexible, 1100 V grade
insulated wire with multi strand copper conductor of 1.5 mm2 cross section.
4.2.3.8
The circuit breaker will normally be controlled from remote control panels
through interposing relays. The control switch located on the switchgear would
normally be used only for testing of circuit breaker in isolated position, and for
tripping it in an emergency.
REV. NO.: R3
Facilities shall be provided for mechanical tripping of the breaker/ contactor and
for manual charging of the stored energy mechanism for a complete duty cycle,
in an emergency. These facilities shall be accessible only after opening the
compartment door.
Each panel shall have sufficient no. of limit switches, for the Service position and
TESTposition. Each of these limit switches shall have at least four (4) contacts
that shall close in the respective positions.
Auxiliary Contacts of breaker may be mounted in the fixed portion or in the
withdraw able truck as per the standard practice of the manufacturer, and shall
be directly operated by the breaker / contactor operating mechanism.
Auxiliary contacts mounted in the fixed portion shall not be operable by the
operating mechanism, once the truck is withdrawn from the service position, but
remain in the position corresponding to breaker open position. Auxiliary
contacts mounted on the truck portion, and dedicated for Owner's use shall be
wired out in series with a contact denoting breaker service position. With truck
withdrawn, the auxiliary contacts shall be operable by hand for testing.
For Owner's use six (6) normally open (NO) and six (6) normally closed (NC)
auxiliary contacts shall be provided for all feeders.
Contact multiplication, if necessary to meet the above contact requirement, shall
be done through suitable latch relay of reputed make.
Closing of the breaker shall be possible only when truck is either in TEST or in
SERVICE position and shall not be possible when truck is in between. Further,
closing shall be possible only when the auxiliary circuits to breaker truck have
been connected up, and closing spring is fully charged.
Mechanical (Castell key) or a full proof electrical interlock shall be provided
between the isolator and associated circuit breaker such that the former cannot
be operated unless the latter is opened.
REV. NO.: R3
It shall be possible to easily insert breaker of one typical rating into any one of
the panel meant for same rating but at the same time shall be prevented from
inserting it into panels meant for a different type or rating.
Indicating lamps shall be provided in the panel front as brought out in the
specification elsewhere. It shall be possible to easily make out whether the truck
Current Transformers
All current transformers (CT) shall be cast resin type. All secondary connections
shall be brought out to terminal blocks where wye or delta connection shall be
made.
Core balance CTs (CBCT) shall be provided on all feeders. These CBCTs shall be
mounted inside the switchgear panel. The window size of CBCT's shall be based
on the overall diameter of the cables, to be finalized during detailed
engineering.
Accuracy class of the Current Transformers and its metering shall be as per CEA
regulation on installation and metering 2006 and its amendment in 2010 or the
following whichever gives higher accuracy is to be selected for metering and
protection:-
Class PS for differential relaying (or as required depending on the type of relay
selected).
Class 5P20 for other relaying.
Class 0.5 and ISF <=10 for metering.
Class 0.2 or better and ISF <=2 for performance / precision metering.
Current transformer secondary shall be rated for 1 A.
Feeders requiring remote metering and/or current monitoring shall be provided
with current transducers with calibration for full-scale reading.
REV. NO.: R3
The burden and the parameters of the CTs shall be commensurate with the
connected loads including lead burdens, changes during engg stage and 20%
spare.
In case of smaller rated CTs (say 200 A and less), at the expected fault level, the
CT saturation may result in the non operation of the instantaneous short circuit
protection. In such cases, separate protection CT with higher ratio, selected to
avoid saturation at high fault currents shall be provided if required or else
calculations to prove non-requirement shall be furnished for Owners approval.
Calculations for sizing and selection of various CT parameters shall be
submitted for owners approval.
4.2.3.10 Voltage Transformers
All Voltage Transformer (VT) shall be cast-resin, draw out type. Accuracy class
of the Voltage Transformers and its metering shall be as per CEA regulation on
installation and metering 2006 and its amendment in 2010 or the following
whichever gives higher accuracy is to be selected for metering and protection:-
3.3 kV Bus and line VTs shall be 3 nos. single phase VTs with an accuracy class
of 0.5 / 3P with 75 VA burden for secondary winding -1 and class 3P with 25 VA
burden for secondary winding-2. For tie feeders it shall be 1 no. 1 phase VT of
Class 0.2 / 3P with 10 VA burden. Bus PTshall be mounted in a separate vertical
panel.
The voltage transformers shall have suitable HRC current limiting fuses on
REV. NO.: R3
have the dynamic and short time ratings at least equal to those specified for the
associated switchgear and shall safely withstand the thermal and mechanical
stress produced by maximum fault currents specified when mounted inside the
switchgear for circuit breaker modules. However, current transformer mounted
in fuse backed contactor module shall have the dynamic and short time rating
compatible with the let through current of the fuses.
The parameters of CT & VT specified in this specification are tentative and shall
be finalized by the Owner in due course duly considering the actual burden of
various relays and other devices finally selected and 20% spare. In case the
Bidder finds that the specified ratings are not adequate for the relays and other
devices offered by him, he shall offer CT & VT of adequate ratings and shall
bring out this fact clearly in his bid.
All CT & VT shall have clear indelible polarity markings. All secondary terminals
shall be wired to separate terminals on an accessible terminal block.
4.2.3.11 Relays
Relays shall be of draw out design with built-in testing facilities and flush
mounted at the front of panel. Small auxiliary relays may be in non-draw out
execution and mounted within the cubicle.
Relays shall be rated for operation on 110 V secondary voltage and 1 or 5 A
secondary current. Number and rating of relay contacts shall suit the job
requirements.
Unless mentioned otherwise in the specification, protective relays shall be
multifunction type numerical relays.
protection.
All
functions
including
protection,
automation,
REV. NO.: R3
modified, if required, using the front panel user interface. Communication port
for local and remote (with suitable protocol) communication shall be located in
the front and rear part of the relay. A laptop loaded with support software
(complete
version)
shall
be
supplied
for
local
off
line
programming,
measurements, extracting and viewing of events, disturbance etc. The relay shall
be housed in dust tight enclosure, suitable for IP 52 degree of protection.
Separate numerical relay shall be provided for differential protection of motors
above 1000 kW and E/F protection of motor shall be achieved through CBCT.
The Contractor shall furnish, install & co-ordinate all relays to suit the
requirements of protection, interlock schemes and bus transfer schemes.
Detailed relay setting calculations for all the switchgears shall be furnished for
owners review and approval.
All relays shall withstand a minimum test voltage of 2 kV AC rms for one minute.
4.2.3.12 Instruments and Meters
Indicating instruments and integrating meters shall be flush mounted on panel
front and shall be digital multifunction type except for motor feeders. For motor
feeders the instruments shall be of at least 96 mm x 96 mm size with 90 deg.
scales, and shall have an accuracy class of 0.5Sor better unless otherwise
specified. The covers and cases of instruments and meters shall provide a dust
and vermin proof construction.
Analog meters shall have white dials with black numerals and lettering. Black
knife edged pointer with parallax free details will be preferred.
Ammeters on motor feeders shall have a compressed scale at the upper current
region to cover the motor starting current without gradation from one to six
times the rated CT secondary current. These shall be suitable to withstand the
above current of motors which can last up to 30 seconds (under stalled
condition) without any damage or loss of accuracy.
REV. NO.: R3
meters etc.) shall be provided and mounted by the bidder as shown in different
modules.
4.2.3.13 Transducer
All transducers shall be tested as per IEC - 298 (for impulse test etc) and SWC as
per ANSI C 3790a. 1989
Transducers shall be provided for conversion of AC electrical quantities such as
voltage, current and power. Transducers shall be of low burden type having 4
20 mA DC linear galvanically isolated output compatible with secondary
indicating instrument. Transducer shall be dual channel type. Accuracy Class
shall be 0.5.
4.2.3.14 Control and Selector Switches
Control and selector switches shall be of heavy duty, rotary type with
escutcheon plates clearly marked to show the positions. The switches shall
be of sturdy construction suitable for mounting on panel front. Switches with
shrouding of live parts and sealing of contacts against dust ingress shall be
preferred.
On-Off control switches shall have three positions and shall be spring return
to 'Neutral' from close and trip positions. They shall have two contacts
closing in close position and two contacts closing in trip positions, and shall
have Pistol Grip handles. Last motion feature shall be provided wherever
required.
Selector switch shall have two stay put positions as per the module
requirements. They shall have two contacts for each of the positions and
shall have black Spade handle
Ammeter and Voltmeter selector switches shall have four stay put positions
with adequate number of contacts for three phase system. These shall have
OVAL handles. Ammeter selector switches shall have make before break type
contacts to prevent open circuiting of CT secondary.
REV. NO.: R3
Fuses shall be HRC, link type, with minimum interrupting capacity equal to
the listed short circuit current. Fuses shall be furnished complete with fuse
bases and fittings. Visible indication shall be provided on blowing of the
fuse.
MCBs, if used, shall be three/four pole, trip free, with manual close / open
mechanism. Automatic tripping provision for over load and short circuit shall
also be provided. MCBs shall be rated for full fault level of the system. MCB
shall be provided with required number of auxiliary contacts as per circuit
requirement.
Indicating lamps shall be of the panel mounting reputed make, clustered LED
type only. The lamps shall have escutcheon plates marked with its function,
wherever necessary.
Breaker Closed
GREEN
AMBER
Breaker/Contactor in REMOTE
DC ON
iii) LED lamps and lamp covers shall be easily replaceable from the front of the
REV. NO.: R3
iv) All indicating lamps shall be suitable for continuous operation at 90 to 100%
b) Fuse, links and MCB shall be provided to permit individual circuit isolation
from bus wires without disturbing other circuits. All spare contacts of relays,
switches and other devices shall be wired up to terminal blocks.
c) Wiring shall be done with flexible, 1100 V grade, PVC insulated wires with
stranded copper conductors of 1.5 mm2 for control and 2.5 mm2 for current
and voltage circuits.
d) Each wire shall be identified, at both ends, with interlocking type permanent
markers bearing wire numbers as per Contractor's Wiring Diagrams. AC / DC
wiring shall have separate color-coding.
e) Wire termination shall be made with crimping type connectors with insulating
sleeves. Wires shall not be spliced between terminals.
ESI standard 12.1 or equivalent. WAGO terminal of cage clamp with lugs shall
also be acceptable.
b) Terminal blocks for CT and VT secondary leads shall be provided with links
to facilitate testing, isolation star/delta formation and earthing. Terminal
blocks for CT secondary shall have the short circuiting facility. It shall be
similar to ELMEX CATD type.
REV. NO.: R3
g) Terminal blocks used for interface with DCS/PLC via termination cabinet shall
be suitably sized to facilitate proper termination of interconnecting cables
plates etc. and the electrical clearances available shall be submitted for
Owner's approval during detail engineering.
power lugs and associated hardware (to suit the cable size) and removable
undrilled gland plates. For all single core cables gland plates shall be of
nonmagnetic material.
REV. NO.: R3
c) Each stationary unit shall be connected directly to the ground bus. The frame
of each circuit breaker and draw out VT unit shall be grounded through
heavy multiple contacts at all times except when the primary disconnecting
devices are separated by a safe distance.
bolting to earthing conductors. All joint splices to the earth bus shall be
made through atleast two bolts and taps by proper lug and bolt connection.
e) The truck and breaker / contactor frame shall get earthed while the truck is
being inserted in the panel and positive earthing of the truck and breaker /
contactor frame shall be maintained in all positions i.e. SERVICE, TEST and
ISOLATED as well as throughout the intermediate travel. The truck shall also
get and remain earthed when the control plug is connected irrespective of its
position.
f) All metallic cases of relays, instruments and other panel mounted equipment
shall be connected to earth by independent stranded copper wires of size not
less than 2.5 sq. mm. Insulation colour code of earthing wires shall be green.
g) Earthing wires shall be connected to terminals with suitable clamp
connectors and soldering shall not be acceptable. Looping of earth
connections that would result in loss of earth connection to other devices,
when a device is removed is not acceptable. However, looping of earth
connections between equipment to provide alternative paths of earth bus is
acceptable.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
h) VT and CT secondary neutral point earthing shall be at one place only on the
terminal block. Such earthing shall be made through links so that earthing of
one secondary circuit may be removed without disturbing the earthing of
other circuits.
i)
The Contractor for maintenance work shall provide separate earthing trucks
for each switchboard. These trucks shall be suitable for earthing the
Closing of the earth switch on a live connection. Three (3) nos. voltage
capacitive dividers shall be provided on each phase of the section intended
for earthing and three (3) nos. "RED" neon lamps connected to these on the
panel front for visual indication.
The earthing device (truck/ switch) shall have the short circuit withstand
well as backside by large engraved name plates giving the distinct feeder
description along with panel numbers. Back side name plates shall be fixed
in panel frame and not on the rear removable cover.
REV. NO.: R3
x 150 mm for panels. Caution notice on suitable metal plate shall be affixed
at the back of each vertical panel
heater(s),
suitably
located
in
breaker
contactor
and
cable
b) For motor space heater supply, one breaker / contactor normally closed (NC)
auxiliary contact of each motor feeder shall be wired out in series of switch
fuse upto terminals block in the respective panels of switch boards. The
motor space heater supply shall be taken from Panel space heater supply
given to switch board.
heater, motor heater, plug/socket circuits shall have individual switch fuse
units
4.2.3.25 Control Supply and Space Heater Supply
a) The following power supplies shall be provided to each switchgear:
1. AC supply
2. DC supply
b) Isolating switch fuse units shall be provided at each switchgear for the
incoming supplies, 4-pole, single throw for A.C. and 2-pole, double throw
REV. NO.: R3
for D.C. Moulded case circuit breaker (MCCB) shall also be accepted as an
alternative for AC circuit only.
c) Bus-wires of adequate capacity shall be provided to distribute the incoming
supplies to different cubicles. Isolating switch fuse units / MCCB shall be
provided at each cubicle for A.C/D.C. supplies.
4.2.3.26 Tropical Protection
a) All equipment, accessories and wiring shall have fungus protection, involving
special treatment of insulation and metal against fungus, insects & corrosion.
4.2.3.27 Painting
a) All sheet steel work shall be pretreated, in tanks, in accordance with IS:
6005.
b) Alkaline cleaning shall do degreasing. Rust and scales shall be removed by
pickling with acid. After pickling, the parts shall be washed in running water.
Then these shall be rinsed in slightly alkaline hot water and dried.
d) Finishing paint shade for complete panels excluding end covers shall be light
grey shade of 631 of IS 5 for extreme end covers of all boards, unless
required otherwise by the Owner. The paint thickness shall not be less than
100 microns.
protect the finished surfaces from scratches, grease, dirt and oil spots during
REV. NO.: R3
For this purpose, synchronising facility complete with synchro check relay and
other required accessories are to be provided as per the requirement.
During planned outage, the breaker to be brought in shall be closed after
checking synchronism of the incomer and running bus and the breaker to be
taken out shall be tripped automatically through a trip selector switch. In the
event of selected breaker failing to trip, the incoming breaker shall be tripped
after a time delay.
During normal running conditions, should any of the incomer trip due to
tripping of corresponding station switchgear breaker, the bus coupler breaker
j)
k) Auxiliary contacts.
l)
Terminal blocks
m) Interposing relays
n) Hand reset lockout relay
PT module type G1/G2
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
Item Description
Module G1
Module G2
1 phase VT*
27 (VAGM-22) (microprocessor /
----
Voltmeter **
-----
As required
As required
Numerical relays)
relays)
necessary during detailed engg stage shall also be provided. Out of these some
will be selected for the sequential event recording. For each feeder grouped
alarm for any abnormal condition of that feeder shall be provided on the control
panels. The control / interlock schemes for various types of feeders shall be
commensurate with their application.
a) Common for each breaker panel
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
i.
Status indication
Breaker ON
Breaker OFF
Breaker in service
Breaker in test
4.2.3.32 Protections
Minimum protections to be provided for different type of circuits are listed
below
Incomer
1. IDMTL over current (51) for phase fault
2. IDMTL over current (51N) for earth fault
3. IDMTL over current (51SN) for stand by earth fault (for incomer from
transformer only).
4. Restricted E/F (64) (for incomer from transformer only)
5. Under voltage with time delay (27)
6. VT fuse failure
7. Circuit breaker failure
8. Local Breaker Back Up
Tie feeder
a) IDMTL over current (51) for phase fault
b) IDMTL over current (51N) for earth fault
f) Synchronizing check relay, if applicable, complete with guard relay and hard
wires.
Motor feeder
REV. NO.: R3
h) Under Voltage with time delay ( Marshalled from Bus PT U/V timer )
i)
Winding temperature
j)
Bearing temperature
b) Inst / Definite time O/C (50G) for earth fault (through CBCT)
c) Differential protection (for transformers rated 5 MVA and above)
d) Gas pressure alarm and trip.
e) Winding temperature alarm and trip.
f) Oil temperature alarm and trip.
g) Pressure relief device operated alarm.
h) Conservator oil level low alarm.
i)
j)
REV. NO.: R3
All protective relays shall be provided with self reset type of contacts.
Apart from protection relays, each breaker shall be provided with separate
discrete auxiliary relays for anti-pumping (94), trip annunciation (30), trip
supervision (74), electrically reset type breaker contact multiplication (52X) relay
and lockout (86) functions. Lockout relay shall be hand reset type. For
Code
Description
a)
IS: 722
AC electricity meters.
b)
IS: 996
c)
IS: 1248
d)
IS: 13947
Degree
of
protection
provided
by
enclosures
for
IS: 2544
f)
IS: 2705
Current transformers
g)
IS: 3156
Voltage Transformers
h)
IS: 3231
REV. NO.: R3
S.N
Code
Description
i)
IS: 3427
j)
IS: 5082
k)
IS: 6005
l)
IS: 8686
m)
IS: 9046
n)
IS: 9224
o)
IS: 9385
HV fuses
p)
IS: 9431
q)
IS: 9921
r)
IS: 11353
IS: 13118
IEC99 part- Metal oxide surge arrestor without gap for AC system
4
u)
IEC-56
v)
IEC-99-1
Part-1
w)
IEC-298
x)
CIGRE
13.02
voltage test
CHAPTER-3
PART-A&B
Installation shall conform to Indian Electricity Act and Indian Electricity Rules as
amended upto date. The Indian Electricity Act and Indian Electricity Rules can be
obtained from:
Kitab Mahal
State Emporium Building
Baba Kharag Singh Marg
New Delhi - 110 001
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
INDIA.
Equipment conforming to any other internationally accepted standards would
also be considered if they ensure performance and constructional features
equivalent or superior to the standards listed above. In such case, the Bidder
shall clearly indicate the standard(s) adopted. The Bidder shall furnish copy in
English of the latest revision of the standards along with the copies of all official
amendments and revisions in force as on date of opening of bid and shall clearly
bring out the salient features for comparison.
4.2.3.34 Tests
Type Tests
All equipment to be supplied shall be of type tested quality. The contractor shall
submit for Owner's approval the reports of all the type tests as listed in this
specification and carried out within last five years from the date of bid opening.
These reports should be for the test conducted on the equipment similar to
those proposed to be supplied under this contract and the test(s) should have
been conducted at an accredited laboratory.
In case the contractor is not able to submit report of the type test(s) conducted
within last five years from the date of bid opening, or in the case of type test
report(s) are not found to be meeting the specification requirements, the
contractor shall conduct all such tests under this contract free of cost to the
Owner and submit the reports for approval.
Type test reports for the following type tests shall be submitted:
1.
Short circuit duty test on circuit breaker, mounted inside the panel offered
2.
Short time withstand test on circuit breaker, mounted inside panel offered
4.
5.
Temperature rise test on breaker and panel together. For this test, the test
set up shall include three panels with breakers, the test breaker and panel
being placed in the Center.
6.
The adjacent panels shall also be loaded to their rated current capacity.
Alternatively the test panel may be suitably insulated at the
sides,
REV. NO.: R3
which
7.
Test to verify pressure relief devices operation of the panel. This shall be
done on one panel of each voltage class.
8.
9.
13. Any other testindicated in IEC 694, IEC 298 and IEC 62271.
The following type test reports (as applicable) shall be submitted on surge
a) IP - 4x: It shall not be possible to insert a one (1) mm. dia steel wire into the
enclosure from any direction, without using force.
b) IP- 5x: It shall not be possible to insert a thin sheet of paper under gaskets
and through enclosure joints.
Routine & Acceptance Tests
a) Dielectric test on the main circuit.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
j)
Any other test indicated in IEC 298, IEC 694 nad IEC 62271.
For various bought out items like CT, VT, Relays, and meters. Surge suppressor,
etc for which identification can be physically verified and test certificate from
manufacturer can be correlated. Contractor should indicate following in the QAP.
1. Review of manufacturer's TC as per relevant standard & Compliance to
requirements of this specification
2. Physical check and functional / operational check to ensure that item is fit
for assembly on the switchboard cubicle.
For
all
other
items
where
identification
has
not
been
envisaged
by
2. Physical check & functional / operation check to ensure the item is fit for
assembly on the switchboard cubicle.
REV. NO.: R3
4.2.4
LT Switchgear
4.2.4.1
415 V system shall be 3 phase, 4-wire system with solid neutral earthing. Single
phase feeders shall be provided with control transformers in each bus section.
The switchgear shall derive power from the designated service transformers or
from 415 V switchgear based on geographical location and common loads.
4.2.4.2
Feeder details
Each of the switchgear / MCC shall be provided with two bus sections, two
incomers and a bus coupler each rated for 100% of the loads connected to the
switchgear.
The switch gear / MCC shall be provided with suitable number and type of
outgoing feeders for the respective auxiliary loads of the system/area, power
supply feeders to various panels, lighting, space heating panels, control
cabinets, welding and all other loads encountered in the plant.
In addition, following feeders shall be provided in each bus section of all
switchgear.
(a)
Spare feeders: Minimum of one number feeder of each rating and type in
each switchgear / MCC. 2 nos. 50 kVA (one in each section) lighting
transformer feeder for owners use in switchgear shall be provided.
(The above quantity is the minimum requirement, at the time of handing
over. Any additional quantity required for any increase/change during
detailed engineering stage also shall be duly considered.)
(b)
Bus VT module
(d)
(e)
Alarm module for common alarm for out going feeder fault.
(c)
(f)
4.2.4.3
Power receptacles
3-phase, 4 wire, 63A power receptacle / welding receptacles with switch shall be
provided two nos each in pump house & switchgear rooms.
The receptacle shall be industrial heavy-duty type and shall have suitable
interlock facility for safety. The receptacle shall conform to IS 1293 and the
switch to IS 4064.
REV. NO.: R3
The fault level on the 415V buses shall be calculated based on transformer
contribution and motor contribution and shall be limited to 40 kA. However,
switchgear and all components shall be designed for 50 kA.
A margin of 10% over the S.C current thus calculated shall be applied and
rounded off to next higher standard ratings and this value shall be adopted for
the switchgear. The momentary current rating shall be 2.1 times this value.
The short time current withstands duration for switchgear and all components
shall be considered as one second.
4.2.4.5
Continuous Currents
The continuous current rating of the bus bars, the incomers, bus couplers of the
switchgear, which are fed by the transformers, shall be rated at the LV side full
load current of the corresponding transformers with 20% margin rounded off to
the next higher standard rating.
4.2.4.6
Construction features
All the 415V equipments / devices like bus support insulators, CBs, CTs, PTs etc
mounted inside the switchgear shall be suitable for continuous operation and
satisfactory performance under the following supply conditions.
(a) Variation in supply voltage - +/-10%
REV. NO.: R3
panel and base frame, removable cover and doors. The switchboard shall be
fully compartmentalized conforming to requirements of IS 8623.
The minimum clearance in air between phases and between phases and earth for
the entire run of horizontal and vertical bus bars shall be 25 mm. Wherever it is
not possible to maintain these clearances, insulation shall be provided by
barriers. However, for horizontal and vertical bus bars, the clearances mentioned
above should be maintained even when these are sleeved or insulated. All
connections from bus bars up to fuses shall be fully shrouded to minimize the
risk of phase to phase and phase to earth shorts.
Cable alley shall be minimum 300 mm wide for motor control modules rated up
to 90 kW and 500 mm wide for modules rated above 110 kW and also for circuit
breaker controlled modules. No component shall be mounted in the cable alley.
Operating devices shall be incorporated only in front of the switchgear.
Switchgear shall be divided into distinct vertical section of:(a)
(b)
(c)
(d)
All modules of identical size & type shall be fully interchangeable without any
modifications. (The ratings of CB / MCCB / LBS for incomer / bus coupler of 415
V switchgear / MCC / ACDB shall be identical)
CRCA Sheet steel of not less than 2 mm thickness shall be used and for base
frame 3 mm is to be provided.
The cable entry shall be from bottom only with separate gland plate for power
and control cable. In case of single core cables, gland plate shall be of non
magnetic material.
4.2.4.7
Bus bars
Three phase, neutral (with atleast 50% rating of main bus bar) and continuous
earth Bus. Bus bar and tapping shall be provided with PVC Sleeve. Bus bars shall
be provided with colour-coded sleeves. Rating of horizontal buses shall be in
line with incomer rating and vertical bus bar for the compartment shall
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
commensurate with all outgoing feeders. Temperature rise of bus bars shall not
be more than 40 deg. C above ambient of 50 deg. C. Bus bar and connection
shall be of high conductivity Aluminium / Aluminium alloy of suitable hardness
and purity complying with as per IS 5082. All bus connectors shall be Silver
plated.
4.2.4.8
Circuit Breakers shall be three pole, single throw, air break type with stored
energy, trip free mechanism and shunt trip coil.
Circuit breakers shall be draw out type, having SERVICE, TEST & ISOLATED
positions with positive indication for each position.
Circuit breakers of identical rating shall be physically and electrically
interchangeable.
All incomer breakers, bus-section breakers, and motor feeder breakers shall
have motor wound spring charging mechanism. All other outgoing feeders shall
generally have hand-operated spring charging mechanism.
All breakers with motor wound spring charging mechanism shall have facility of
manual spring charging also.
For motor wound mechanism, spring charging shall take place automatically
after each breaker closing operation. One open- close-open operation of the
circuit breaker shall be possible after failure of power supply to the motor.
Mechanical safety interlock shall be provided to prevent the circuit breaker from
being racked in or out of the service position when the breaker is closed.
Automatic safety shutters shall be provided to fully cover the female primary
disconnects when the breaker is withdrawn.
Each breaker shall be provided with an emergency manual trip, mechanical ON-
REV. NO.: R3
In addition to the auxiliary contacts required for normal breaker operation and
indication, each breaker shall be provided with the following for interlocking
purpose :
a) Position/cell switch with minimum 4NO + 4NC contacts.
b) Auxiliary switch, with minimum 6NO +6NC contacts, mounted on the
stationary portion of the breaker panel and operated mechanically by a sliding
level from the breaker in SERVICE position.
Alternatively, electrically reset-latching relay may be used for the purpose. The
exact requirement of contacts of the position/cells switch, limit switch, auxiliary
switch and latching relay shall be decided by the Bidder taking into account the
scheme requirements. Limit/auxiliary switches shall be convertible type, that is,
suitable for changing N.O. contact to N.C. and vice-versa.
Spring charge limit switch shall be provided for breakers with motor wound
spring charging mechanism. These limit switches shall be provided with
minimum 2NO + 2NC contact.
4.2.4.9
The MCCBs shall be of current limiting type. When MCCBs are used as short
circuit
protection
devices
for
motor
modules
they
shall
provide
REV. NO.: R3
Terminal arrangements shall be such that all terminals at switchgear ends, which
are to be connected to remote alarms and indication at DCS / PLC, shall be
separated out and shall be kept isolated from other Terminals. 240 V AC, 110 V
AC, 220 V DC & other voltages shall be segregated to avoid mix up of voltages.
motor feeders shall be with suppressed scale. For MCC verticals, CT pertaining
to a particular module should be mounted in the respective withdraw able
module itself. CT should not be mounted in cable alley.
Switchgear shall be suitable for easy extension on both the sides. It shall be
possible at a later stage to add cubicles on both sides of the switchgear by
extending the bus bars.
Secondary of CTs & VTs shall be made through disconnecting type terminals
with necessary shorting and earthing facilities. All the control wiring shall be
through stud type terminal.
The breaker ratings indicated in the data sheets referred to the nominal rating of
the breaker. However, breakers shall be capable of carrying continuously at least
120% of circuit breaker current at an ambient temperature of 50 deg. and with
breaker mounted inside the panel. If a higher rated breaker is necessary to meet
this, the same shall be used.
All the bolted joints in the body of the switchgear shall be earthed through
flexible jumpers.
REV. NO.: R3
the instrument compartment door. All the hand reset relays shall be mounted on
the panel at a convenient height for operation.
All the internal wiring shall be carried out using 1100 V grade, stranded copper
conductor with PVC insulation and shall be flame, vermin and rodent proof. The
minimum size of the copper conductor used for panel wiring shall be as follows:
(a) All circuit except CT: 2.5 sq mm per lead.
(b) CTs : 4 sq mm or 2 x 2.5 sq mm
The minimum number of strands per conductor shall be 07. Extra flexible wires
shall be used for internal wiring of the Devices mounted on moving parts.
Following colour coding shall be used for internal wiring:(a) Red, Yellow & Blue: For respective phase /PT wires.
(b) Black : For neutral wires.
(c) Green : For Earth wires
(d) Red ferruled wires for trip circuit.
(e) All other with grey coloured wires.
The inter panel wiring shall be brought out to a separate set of terminal blocks
located near the slots meant for inter panel connecting wires.
Control supply of each module shall be taken through dedicated control
transformer of ratio 415 V / 110 V.
At least 20% spare terminal shall be provided on each panel and this spare
terminal shall be uniformly distributed on all rows of terminal blocks. A
All hardware required for meeting the functional requirements stated above,
whether specifically listed out in the specification or not, shall be included in the
scope of supply.
Current transducers, power transducers and Voltage transducers shall be
provided for remote metering.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
Separate CTs / cores shall be provided for protection and metering circuits.
The cable terminations inside the cable alley shall be completely shrouded so
that it shall be possible to work on any one of the terminations by switching OFF
the corresponding feeder switch only.
All bezels, handles, screws, bolts, washers, hinges, etc. shall be of the best
quality electro galvanized or passivated to withstand attack from corrosive
atmosphere.
Horizontal busbar chambers shall be at the top of the board for bottom cable
entry. Bus bars shall be completely shrouded to prevent metal pieces falling on
the busbar during maintenance.
In case of copper to aluminium connections, proper treatment shall be given to
minimise the bimetallic effect. That is, all joint surfaces at aluminium to copper
joints shall be silver / tin plated, alternatively Cu-Al washers (bimetallic washers)
can be used.
Motors rated above 90 kW shall be connected to ACB and below shall be with
MCCB.
4.2.4.11 Changeover scheme
All the switchgear with sectionalized buses and circuit breaker controlled will be
normally operated with the bus coupler breakers open. Auto changeover facility
shall be provided for all switchgear such that if there is a prolonged under
voltage on any one of the bus sections, the respective incoming breaker shall
trip and the bus coupler breaker shall close, provided voltage is available on the
other bus section and protection is not operated on other bus. Total change over
time shall not exceed 1.5 seconds. The bus coupler panel shall be provided with
auto-manual-off selector switch and in manual position, an alarm shall be
generated at DCS / PLC.
This auto changeover shall be blocked if the other incoming breaker had tripped
either on a bus fault or manually. Changeover back to the normal source of
REV. NO.: R3
For this purpose, a selection shall be provided for selecting the incomer to be
tripped. Thus, depending on the selection made, incomer to bus section A or
to bus section B will be tripped once bus section breaker is closed manually,
thus maintaining continuity of supply.
Timers with a time delay on pick up of 0.5. - 5 sec. for annunciation of the
running breaker failing to trip within a pre-set time, (i.e. if the two sources
remain paralleled for more than a pre-set time) shall be provided along with
tripping of last closed breaker if selected breaker does not trip.
When the normal supply is to be brought back into operation, the incomer
breaker shall be closed whereupon the bus coupler shall trip automatically.
4.2.4.12 Incomers, Bus Couplers & breaker control motor and tie feeders
The incomer modules and bus coupler modules of all the switchgear shall be
fully draw out air circuit breakers controlled from local / DCS / PLC located at
control room. The miscellaneous distribution boards rated less than 400 A shall
be provided with MCCBs.
The breaker ratings indicated in the data sheets refersto the nominal rating of
the breaker. However, breakers shall be capable of carrying continuously at least
120% of circuit breaker current at an ambient temperature of 50 deg. and with
breaker mounted inside the panel. If a higher rated breaker is necessary to meet
this, the same shall be used.
The incomer modules shall be interlocked with their upstream breaker such that
they can be closed only when upstream breaker is closed and trip automatically
when upstream breaker is tripped.
All the Tie feeders shall be provided with breakers at both ends with necessary
metering and protection at both ends.
Each circuit breaker cubicle shall be complete with following minimum
accessories:-
REV. NO.: R3
(i) Protective relays along with trip circuit supervision relay and master trip relay.
(j) Meters as indicated elsewhere.
(k) Required CTs/PTs/CBCTs.
(l) Space heaters.
REV. NO.: R3
It shall not be possible to close the Breaker if OFF Push Button is locked in off
position.
It shall not be possible to close the Breaker if crank hole is open.
The circuit breaker shall be provided with automatic safety shutters, so that
before the breaker reaches isolated position the main isolating contacts are
protective
relays
and
instruments
shall
be
mounted
in
separate
PTs shall be fully draw out type with required no of cores and ratios as
specified elsewhere.
(b)
(c)
Under voltage and No voltage relays with timers and fuse fail relays.
(d)
(e)
(f)
(g)
REV. NO.: R3
based on size of motors. Test & services position switches and associated
contactors for interlocking.
(b)
(d)
(e)
Relays as required.
(f)
(c)
All the motors rated 30 kW and above shall be provided with a CT, ammeter and
a current transducer with remote metering in DCS / PLC.
4.2.4.16 Protections
The minimum protections to be provided for circuit breaker controlled feeders
are listed below :
a)
Incoming Feeders : 3-Inverse time O/C relays (51) for phase faults and 1Inverse time O/C relay (51N) for Earth faults
b)
REV. NO.: R3
The relay shall have facility for user interface capability, character display,
keypad, LED indicator and communication port along with licensed
version software.
90 kW and below: - The thermal overload relay in all three phases with
built in protection against single phasing and short circuit protection by
MCCBs.
c)
d)
Outgoing Feeders: 2-Inverse time O/C relay (51) for phase fault, 1Inverse time O/C relay (51N) for Earth fault
All inverse time O/C relay shall be 1.3 secs. version / 3 secs. version and the
same will be decided during detailed Engineering.
Apart from protection relays, each electrically operated breaker shall be
provided with anti pumping (94), trip annunciation (30), lockout (86) and trip
circuit supervision (74) relays. Lockout relay shall be hand reset type.
Fuse failure relay shall be provided for the voltage transformer.
4.2.4.17 Control / Alarms / Indication / Ser Points
The control room DCS / PLC shall provide indication & alarms for the 415 V
auxiliary supply as given below. Any additional indications/alarms considered
necessary during detailed engineering also shall be provided. Some of these
shall be selected for sequential event recording. For each breaker and bus,
grouped alarm for any abnormal conditions shall be provided in the control desk
DCS / PLC. For all breaker fed switchgear, status indications shall be available on
Control desk / DCS / PLC in the form of SLD.
(a) Alarms in CRT
REV. NO.: R3
Motor ON
Motor OFF
Feeder fault
Breaker service
The current, voltage and power measurements for each bus shall be available
both on DCS / PLC as indicated in this section and specified elsewhere in the
specification. The necessary transducers shall be included by the vendor. Also
for
specific
motors
where
the
current
transducers
are
indicated,
the
The tests shall include but not necessarily limited to the followings:
a) Operation under simulated service condition to ensure accuracy of wiring,
correctness of control scheme & proper functioning of the equipment.
b) All wiring and current carrying parts shall be subjected to appropriate High
Voltage Test.
c) Primary current & voltage shall be applied to all instrument transformers.
d) Routine test shall be carried out on all equipment such as circuit breakers,
instrument transformers, relays, meters, contactors etc as per relevant
standard.
Type Tests
REV. NO.: R3
to prove the design. Type tests performed before five (5) years are not
acceptable.
4.2.4.19 Module selection
Motor feeder
Type
Motor Rating
AU/AR
0 - 5.5 KW
BU/BR
MCCB
Module
Contactor
Cable size
32A
16A
400mm
5.6 - 11KW
63A
32A
3/c - 16 Sq.mm Al
600mm
CU/CR
11.1 - 22 KW
63A
63A
3/c - 35 Sq.mm Al
600mm
DU
22.1 - 50 KW
100A
100A
3/c - 95 Sq.mm Al
900mm
EU
50.1 - 75 KW
200A
160A
900mm
FU
75.1 -90 KW
400A
300A
1200mm
Rating
size
MCCB Rating
Cable Size
Module size.
AF
32 A
4/c 16 Sq.mm - Cu
300mm
BF
63 A
4/c 35 Sq.mm - Al
300mm
CF
100 A
3.1/2 95 Sq.mm - Al
600mm
DF
200 A
600mm
EF
400 A
900mm
FF
630 A
900mm
4.2.5
4.2.5.1
HT Power Cables
HT cables shall be 11 kV (UE), 3.3 kV (UE) grade suitable for use in medium
resistance earthed system, with stranded & compacted aluminium conductors,
extruded semi-conducting compound screen, extruded XLPE insulated, dry
LT Power Cables
REV. NO.: R3
Control Cables
Control cables shall be 1100V grade, multicore, minimum 2.5 sq.mm cross
section, stranded copper conductor having 7 strands, extruded PVC insulated,
extruded inner PVC sheathed of type ST-1, galvanised steel wire armoured and
extruded outer sheath made of FRLS PVC compound of type ST-1 confirming to
relevant standards. In situations where accuracy of measurement or voltage drop
in control circuit, warrant, higher cross sections as required shall be used. For all
the CT & PT cables, minimum 4 sq.mm cables shall be used.
4.2.5.4
Lighting wires
1100 V grade, single core stranded copper conductor PVC insulated wires
conforming to IS 694-1990 / IEC 60227 part 1 to 5 (1979) / IEEE -719 (1981).
Minimum cross section of copper wire shall be minimum 2.5 mm2 for lighting
circuits and 4 mm2 for receptacle circuits.
4.2.5.5
11/3.3 kV (UE) and 1100 V (E) grade power and control flexible trailing annealed
tinned copper conductor, EPR insulated, EPR inner sheathed and CSP outer
sheathed and shall have conductor screen of rubber cable shall conform to IS
requirements and any other applicable standards.
Cable Properties
All single core power cables shall have wire armouring of aluminium, whereas
multicore power cable shall have galvanised steel round wire armouring.
The outer sheath of all cables shall be of extruded layer of suitable synthetic
material compatible with specified ambient and operating temperature of the
cables. The sheath shall be resistant to water, UV radiation, fungus, termite and
rodent attack.
REV. NO.: R3
The inner and outer sheath of FRLS PVC compound shall meet the following
performance requirements:
(a)
The critical oxygen index value shall be minimum 29 when tested at 27+
20C as per ASTM-D-2863-77 and the temperature index shall be
minimum 2500C at oxygen index value of 21 when tested as per NES715.
(b)
(c)
(d)
The smoke generation under fire shall have maximum smoke density
The cables will pass the hydraulic stability and ultraviolet tests as per DIN
53387.
The finished cable shall pass the flammability test as per IEC-332-1 and IEEE383. In addition, it shall also pass flammability test as per Class F3 of Swedish
Standard SS-424-1475.
4.2.5.6
Power cables
Power cable sizes shall be selected on the following basis:
Power cables shall carry the full load current of the circuit continuously under
site conditions considering the various derating factors like ambient air/ground
temperature, grouping, method of laying, short circuit withstand capacity for
applicable fault, maximum voltage drop limits, etc.
Power cables shall withstand the fault current of the circuit for the duration not
less than the maximum time taken by the primary protective system to isolate
the fault. Fault clearing times for 3300 V motor feeders and transformer feeders
having high-set instantaneous protection shall be 0.16 secs, whereas tie
between two 415 V switchgear and any two 3300 V switchgear shall be 0.5 secs,
and for incomers and tie feeders 1.0 sec.
For 3300 V motors controlled by vacuum contactors with back-up HRC fuses,
the minimum cross-section of cables shall be based on the cut-off current of
the fuses and its fusing time.
REV. NO.: R3
For the cables to 415V motors and feeders protected by fuses, the cross section
shall be chosen according to the cut-off current of the fuse and its fusing time
or full load current, whichever is higher.
Voltage dip at motor terminals during starting of motors will be limited to the
following values:
(i)
Voltage drop in feeder cables shall be limited to 3% during full load running
condition.
For power supply to valve actuator motors, actuators of various isolating and
regulating dampers and exhaust fans, 3 core 2.5 sq. mm stranded copper
conductor cable may be used in view of ease of termination. These cables shall
be in other respects similar to cables described above.
Control Cables
Current transformers leads shall be checked for the lead burden vis--vis the
current transformer VA capacity and 4 sq.mm cables shall be used for
connection of CT to loads. In case 4 mm2 conductor imposes unacceptable high
burden on CTs, higher cross section of conductor shall be used.
Voltage transformer leads shall be checked for voltage drop with 4 sq.mm,
which shall be limited to within 1% for all cases. In case the voltage drop with 4
sq. mm conductors exceed this value, higher conductor sizes shall be used.
In multi core control cables the following minimum reserve cores shall be
provided.
Cable Terminations
All 11 kV termination kits shall be of heat shrinkable type and suitable for XLPE
insulation and the same shall have been tested for short circuit as per relevant
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
standards. Double compression type cable glands and copper lugs shall be used
for termination.
All 1100 V termination for XLPE / PVC power cables and control cables shall be
by crimping type tinned copper lugs and double compression type cable glands.
Cable Joints
Cable joints shall be avoided to the extent possible. If joints are unavoidable due
to circuit length, in excess of permissible maximum drum length, they shall be
heat shrinkable type having a short circuit with stand capacity of 40 kA for 0.5
sec. for 11 kV cables and 50 kA for 0.5 sec. for 1100 V grade cables.
4.2.5.7
Access to maintenance.
(i)
Direct burial of cables shall be avoided as far as possible. The Contractor shall
prepare detailed cable routing diagram, cable tray layouts, cable schedules,
interconnection schedules for all cables being supplied under this Contract. It is
anticipated that a few cables supplied outside this Contract would be required to
be routed in the cable carrier system being provided by this Contractor. The
details of these cables would be made available to the Contractor to prepare
integrated cable layout/routing drawing considering the cable being installed by
others.
Cable Trench
Cable trenches shall be of different sizes depending on the number of cables
laid in that route.
REV. NO.: R3
Preferred working space between the cable support arms and the wall are as
follows. Contractor shall design the trenches accordingly.
Trench depth
Width of Trays
Working Space
1500 mm (5 tiers)
600 mm
750 mm
1200 mm (4 tiers)
600 mm
750 mm
1000 mm (3 tiers)
600 mm
750 mm
700 mm (2 tiers)
300 mm
350 mm
Buried Cables:
Cables in trenches shall be laid on 8 cm of riddled sand and covered with 8cm of
riddled sand. RCC slabs shall be provided for covering these trenches. On top of
RCC slabs / bricks, the earth shall be back filled, rammed and levelled. Suitable
separation shall be provided when more than one cable is laid in the same
trench. The maximum trench depth shall normally be 1.5 m and thickness of top
cover of 75 mm. If the trench is to cross railways tracks/roads or any load
bearing area the cables shall be taken through suitable GI conduits / pipes /
ducts.
Cable Trays
Cable trays of prefabricated ladder and perforated types and the associated
accessories such as coupler plates, tees, elbows, etc., shall be fabricated from
12 gauge (2.5 mm thick) mild steel sheets. Cable tray covers shall be fabricated
from 16 gauge (1.70 mm thick) MS sheets.
Cable trays, accessories and covers shall be hot dip galvanised. Galvanising
thickness shall be minimum 85 microns and mass of Zinc coating not less than
610 gm/m2.
The spacing of rungs for ladder type of trays shall be not more than 250 mm.
Vertical raceways shall be formed by either structural members or slotted angles
or by running the prefabricated trays vertically.
Conduits & Pipes
The galvanised steel conduits shall be used for sizes up to 63.5 mm. The
conduits shall be manufactured by electric resistance welding process and shall
be hot dip galvanised. The conduits and fittings shall comply with IS: 1653,
3837 & 2667.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
Galvanised steel pipes shall be used for sizes from 80 mm on wards. They shall
be medium duty class-B type as per IS. The pipes shall be manufactured by
electric resistance welding and hot dip galvanised. The pipes and fittings shall
comply with IS.
Flexible steel conduits shall be manufactured with electro galvanising process.
The flexible conduits and their fittings shall comply with IS: 3480, 4649.
The hume pipes/RCC pipes shall comply with IS:458.
Cable/Cable tray supports
Cable tray supports shall be fabricated from standard steel structures of
different sizes. The sizes selected shall be adequate for the weight of
cables/trays encountered.
The steel members shall be cleaned thoroughly for rust and painted as follows:
For indoor - One shop coat of red oxide zinc chromate primer and two site
coats of aluminium alkali paint.
For outdoor & corrosive areas like battery room - Hot dip galvanised.
of upper tray).In vertical raceways with multi tiers the tiers shall be located at
least with 400 mm intervals.
In trenches & tunnels the width of the cable tray shall be limited to 600 mm.
Separate cable trays/tiers shall be provided for 11 kV, 3.3 kV power, 415 V /
240V power, control cables and instrumentation cables.
Cable trays shall be supported at every 1000 mm interval.
Cable trays shall be welded to the mounting/carrier structures.
All outdoor cable trays shall be erected in vertical plane. Vertical trays (raceways)
and all outdoor cable trays shall be provided with removable 16 gauge
galvanised MS sheet covers.
REV. NO.: R3
Each continuous laid out length of cable tray shall be earthed at minimum two
places by GI flats of minimum size 25 mm x 3 mm, the distance between
earthing points shall not exceed 10 meters.
When cables are taken in vertical raceways /trays and they pass from one floor &
other floor pipe sleeves in concrete shall be provided.
In heat zone areas as far as possible the cables shall be taken away from that
area to avoid heat. If Cabling in heat zones cannot be avoided, the cables shall
be terminated in a junction box of IP 67 protection class away from the heat
zones and small length of cables may be laid from junction box to the respective
equipment to facilitate easier replacement in case of fire. Bunching of cables in
the heat zones and boiler areas shall be avoided and laid in separate groups.
4.2.5.8
Cable Installation
Cables to each circuit shall be laid in one continuous length. Cable jointing and
splicing shall be avoided. Jointing will be allowed only for the cases where the
route length is more than the maximum possible drum length.
Outdoor cable installation
(a) Where cables cross roads and water, oil, gas or sewage pipes, the cables
shall be laid in hume or steel pipes. For road crossings, the pipe for the
cable shall be buried at not less than 600 mm. Hume pipes shall be
preferred to steel pipes from the point of view of corrosion.
(b) The cables shall be tied to tray rungs by means of 3 mm dia. nylon cord at
an interval of 5000 mm and also at bends.
(c) For good sealing arrangement at entry points, suitable pipe sleeves,
for
passage
of
cables
into
building
from
cable
(a) Different voltage grade cables shall be laid in separate trays. When trays are
arranged in tiers, HV cables shall be laid in top trays and cables of
subsequent voltage grades in lower tiers of trays.
REV. NO.: R3
(c) 1100 V grade power cables of 120 mm size and above shall normally be
laid in single layer in trays/on racks.
(d) Smaller 1100 V grade power cables below 120 mm may be run in double
layers, where required, due to space restrictions.
Single core power cables for 3 phase AC circuits laid in trays/racks/ trenches
in trefoil groups shall be held in trefoil clamps placed at an interval of 3 m.
The trefoil groups of cables shall be additionally tied by means of 3 mm dia.
nylon cord as follows:
(b) Identification tags made from aluminium sheet shall be attached to each end
of each cable by means of GI binding wire. Tags shall be additionally put at
an interval of 30 metres on long runs of cables and in pull boxes.
(c) All cable terminations shall be done with solderless tinned copper crimping
type lug. Cable terminations shall be done with double compression type
brass cable glands. For transformer feeders, HT motors, LT motors of 110
kW and above only RPCL approved make lugs shall be used at both motor
and switchgear ends.
(d) Control cable termination: RPCL approved make of connectors shall be used.
REV. NO.: R3
shall not be broken at each joint. The unearthed end of armour and screen
shall be insulated.
4.2.5.11 Testing and commissioning of cables
(a) Cables shall be checked for insulation resistance before and after jointing.
(b) High voltage testing
All cables of 1.1 kV grade 400 mm and above and all HV cables shall be
shall be submitted. In case Type test certificate for similar type & size is not
available, the same shall be conducted in presence of Purchaser or his
representative if Purchaser so desires, at no extra cost to the purchaser.
4.2.5.12 Earthing
(a) Metallic sheaths, screens and armour of all multi core cables shall be
earthed at both equipment and switchgear end.
(b) Sheath and armour of single core power cables shall be earthed at
switchgear end only. For long lengths of cables multiple earthing may have
to be adopted to safeguard against the presence of standing voltages under
normal as well as fault conditions.
4.2.5.13 Fire proof sealing system (FPS)
Fire proof sealing system shall consist of
(i)
both
horizontal
and
vertical,
through
brick
or
RCC
walls/floors, to prevent the spread of fire from one area, which is separated
from others by fire-resistant barriers.
(ii) `Fire-breaks' provided on long runs of cable racks/trays to prevent the
propagation of fire along the cable rack, within a single fire-area or firezone.
The FPS system shall also include all the necessary accessories and equipment
required for supporting, holding in position, fixing and installation of the firestop/fire-break.
REV. NO.: R3
The FPS system shall comply in all respects with the requirements of the codes
and standards listed below :
IEEE-634
ASTM-E-814 / ASTM-E-119
ANSI-IEEE-383
IEC-331
IEEE 383
Fire Stop/Seal
The FPS system adopted for cables or cable trays penetrating through walls and
floor openings, or cables passing through embedded conduits/pipes/ pipesleeves, constitutes a `fire stop/seal', which is meant to prevent spreading of
fire between areas separated by fire-resistant barriers.
Fire Break
The fire proofing system, other than fire-stops, adopted to retard flame
propagation along long runs of horizontal or vertical cable trays in the same fire
zone or area, in an event of a fire, shall constitute a `fire-break' and shall be
provided by applying a suitable fire-resistant coating on cables and cable trays
for the required length, with or without a fire resistant panel, at the point of the
fire break to obtain the fire-rating specified.
Performance Requirements
(i)
The fire stops shall be suitable for retrofitting of cables through the
penetration seal without disturbing the sealing of the cables already
existing.
REV. NO.: R3
Fire stops
Fire stops shall be provided for cable penetration openings listed below:
MCCs, various control and relay panels and other bottom entry panels,
shall be effectively sealed by fire stops.
(ii)
On linear runs of cable trays between fire stops or fire breaks, fire
breaks shall be provided at intervals of 15 metres on horizontal cable
runs and 5 m on vertical cable runs.
Contractor shall furnish the test certificates for the fire stops and fire breaks
after award of Contract for Purchaser / Purchasers Representative review. If the
certificates are not satisfactory all the tests shall be conducted free of cost. The
offered system i.e. fire stops and fire breaks shall be identical (or better) with
the system which is successfully type tested for the specified rating i.e. the
composition density of the material, thickness of coating in case of fire breaks
and any other properties of the material / system offered shall be identical or
better than the tested system and shall be subject to Purchaser / Purchasers
Representative approval.
Performance Tests: Tests on Fire Stops
(a)
(ii)
(b)
(c)
REV. NO.: R3
Before conducting the fire rating and hose stream tests, each test specimen
shall be preconditioned for thermal ageing, water immersion and vibration.
(d)
During the fire rating test, the transmission of heat through the cable
penetration fire stop shall not raise the temperature on its unexposed
surface above the self ignition temperature of the outer cable covering, the
cable penetration fire stop material, or material in contact with the cable
penetration fire stop, with a maximum temperature limit on the unexposed
surface of 200oC.
(e)
Additional Tests
Oxygen index test (for both C1 & C2) the Oxygen index shall not be less than
29.
Flame Retardance test on single cable and on bunched cables (for both
C1&C2)
REV. NO.: R3
2.5 meter above the bottom edge of the burner, measured at the front
and rear of the cable assembly.
The level of HCL evolved shall not exceed 20 per cent by weight
Smoke density test (for category C2)
The cables shall meet the requirements of light transmission of minimum
40% after the test.)
4.2.6
Instrumentation cables
4.2.6.1
General Requirement
1.
2.
3.
bidder scope.
Bidder shall supply all cable erection and laying hardware like cable trays,
supports, flexible conduits, cable glands, lugs, pull boxes etc. on as
4.
required basis for all the systems covered under this specification.
In addition to above, bidder shall supply all the cable including co-axial
cables, OFC cable and required converters for interconnecting main plant
and other subsystems in bidder scope.
Overall and pair shielded armored cables for Analog Signals & overall Shielded
armored cables for Digital Signals.
Overall and triad shielded armored triad cables for RTD signals.
REV. NO.: R3
Signal cables shall be minimum 0.5 Sq.mm. All these cables should be FRLS
type.
4.2.6.2
Detailed requirements
cable similar to instrumentation cables can be used for RTDs. The cables shall
confirm to relevant latest standards.
Cable Properties
All cable shall have galvanised steel round wire armouring.The outer sheath of
all cables shall be of extruded layer of suitable synthetic material compatible
with specified ambient and operating temperature of the cables. The sheath
shall be resistant to water, UV radiation, fungus, termite and rodent attack.
The outer sheath of FRLS PVC compound shall meet the following performance
requirements:
(a)
The critical oxygen index value shall be minimum 29 when tested at 27+
20C as per ASTM-D-2863-77 and the temperature index shall be
minimum 2500C at oxygen index value of 21 when tested as per NES715.
(b)
(c)
The smoke generation under fire shall have maximum smoke density
rating of 60% when tested as per ASTM-D-2843-7.
(d)
The cables will pass the hydraulic stability and ultraviolet tests as per DIN
53387.
The finished cable shall pass the flammability test as per IEC-332-1 and IEEE-
383. In addition, it shall also pass flammability test as per Class F3 of Swedish
Standard SS-424-1475.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
All the instrumentation cables shall be provided with overall shielding. However
multipair cables carrying analog signals shall be provided with individual pair
shielding in the addition to overall shielding. Shielding shall be of AluminumMylar tape with 100% coverage and with at least 20% overlapping. Separate drain
wires for the individual pair shield (wherever applicable) as well as overall shield
shall be provided.
All prefabricated cables shall have 10% spare cores which will not be connected
to pin connectors.
Voltage grade of the instrumentation cables shall be 1.1 kV grade
Thickness of outer sheath shall not be less than 1.8 mm in any case. The
variation in diameter and the ovality at any cross section shall not be more than
1.0 mm.
All instrumentation cables shall be suitable for continuous operation at 70 deg.
C, except for high temperature resistant Teflon insulated cables, which shall be
suitable for continuous operation at 205 deg. C. The cables shall be suitable for
laying in trays, conduits, ducts.
REV. NO.: R3
All floor slots of desk/panels/cabinets used for cable entrance shall be provided
with removable gasketed gland plates and sealing material. Split type grommets
shall be used for prefabricated cables.
All the special tools as may be required for solder less connections shall be
provided by C&I Vendor.
Wire sizes to be utilized for internal wiring:
0.5 Sq.mm.
Ammeter/voltmeter circuit,
1.5 Sq.mm.
2.5 Sq.mm.
Terminal Blocks
All terminal blocks shall be rail mounted/post mounted, cage clamp type/other
standard type with high quality non-flammable insulating material of polyamide
/ melamine suitable for working temperature of 100 deg. C.
The terminal
blocks in field mounted junction boxes, racks, etc., shall be suitable for cage
clamp type / other standard type connections as approved by Owner.
All the terminal blocks shall be provided complete with all required accessories
including assembly rail, locking pin and section, end brackets, partitions, small
partitions, test plug bolts and test plug, transparent covers, support brackets,
distance sleeves, warning label, marking, etc.
4.2.7
DC System
4.2.7.1
Design criteria
REV. NO.: R3
Battery
The battery shall be lead acid type with plante positive plates as per IS 16521991.
The plates shall be designed for maximum durability during all service
conditions including high rate of discharge and rapid fluctuations of load.
For arriving at the battery capacity, the following shall be considered.
The minimum and maximum ambient temperature is to be considered as 5 deg
C & 50 deg C respectively for battery design.
The temperature correction factor as given in IS. For this purpose the lowest
electrolyte temperature shall be considered as 5 deg.C above the minimum
ambient temperature. A min design margin of 15% is to be considered.
4.2.7.3
Specific Requirements
i) Construction
a) Each cell shall be assembled in heat resistant, shock absorbing, robust
transparent SAN container.
b) Electrolyte level shall be marked on the clear glass SAN container or level
indicators as applicable. The markings shall be for upper and lower limits.
c) Sufficient sediment space shall be provided so that the cells will not have to
be cleaned out during normal life.
d) Open type cells shall not be accepted. Anti splash type vent plug shall be
provided for sealed-in type cell.
e) Separator between plates shall permit free flow of electrolyte. Separator shall
be of acid resisting materials. Proper arrangement to keep end plates in
position shall be furnished.
f) The cells shall be supported on porcelain insulator fixed on to the rack with
adequate clearance between adjacent cells.
g) The cell terminals posts shall be provided with connector bolts and nuts,
effectively coated with lead to prevent corrosion.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
h) Lead or lead coated copper connectors shall be used to connect the cells of
battery set.
i)
Positive and negative terminal posts shall be clearly and indelibly marked for
j)
Lead coated bent copper plate, tubular copper lugs, bolts, nuts, washers, etc.
easy identification.
Racks shall be free standing type, mounted on porcelain insulators, suitable for
double row single tier arrangement.
Numbering tags / plates for each cell shall be attached on to the racks.
Each battery shall be complete with accessories and devices, including but not
limited to the following :
a) Acid resistant battery racks
g) One Filler hole thermometer fitted with plug and cap and having specific
gravity correction scale
h) Three Pocket thermometers, Acid resisting funnels
i)
j)
REV. NO.: R3
Battery chargers
The float cum boost charger shall be rated to cater the following:
a) Trickle charging current of the battery
b) Continuous load on the DC system
General
REV. NO.: R3
Construction
The charger shall comprise a continuous line up of free standing, floor mounted
sheet steel panels, with all access from the front.
The panel shall conform to the degree of protection IP-42. Minimum thickness
of sheet metal used shall be 2 mm CRCA.
Access doors shall be with concealed hinges and neoprene gaskets. Ventilating
louvers shall be covered with fine wire mesh. Door above 600 mm width shall
be double leaf design.
All equipment within the panels shall be arranged in modular units and laid out
with sufficient space for easy maintenance.
MCCB & switches, meters, relays, etc. shall be flush mounted on the front of the
panels. Name plates of approved size and type shall be provided for all circuits
and devices.
REV. NO.: R3
4.2.7.7
Charger equipment
All power diodes and control rectifiers shall be silicon type. Rectifier transformer
shall be dry type, double wound, with copper conductor and class B insulation.
Blocking diodes shall be fully rated and redundant so that failure of a single
diode shall not incapacitate the system in any way.
MCCB shall be air break type, 3 pole / 4 poles as required by scheme,
conforming to IS-13947. Performance category shall be P2.
MCCB shall be equipped with three distinct positions for ON, OFF & TRIP. It
shall be possible to lock the handle in OFF position.
MCCB shall have built in short circuit and overload release.
MCCBs shall be rated for continuous and short circuit current in conformity with
the Battery and Charger equipment rating.
Fuse shall be HRC type and arranged for easy replacement. Semi-conducting
device fuses shall be fast acting.
Indicating lights shall be cluster type LED. Both lamp and lens shall be
replaceable from front.
Meters shall be 96 x 96 mm switchboard type, with 250 deg., antiglare glass,
1% accuracy with zero adjuster on the front.
4.2.7.8
One (1) twenty points alarm facia shall be provided on each charger panel,
complete with proper actuating devices, circuitry and legends.
The arrangement shall be such that on occurrence of a fault the corresponding
window will light up and stays lighted until the fault is cleared and reset button
is pressed.
Each time a window lights up, a master relay will get energized to provide group
alarm signals in PLC located in plant control room.
The alarm points shall be as follows:
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
i)
AC supply failure
ii)
DC voltage low
iii)
DC voltage high
iv)
DC system ground
v)
Charger overload
vi)
viii)
ix)
x)
vii)
xi)
xii)
xiii)
xiv)
xv)
Mains AC available
ii)
DC output available
iv)
v)
iii)
The charger shall essentially comprise the following items but not limited to:
a)
b)
One (1) moving coil DC voltmeter and ammeter for float cum boost
chargers.
provided.
c)
One (1) moving coil centre zero ammeter, with shunt to read discharge /
charge current of the battery, with suitable range.
d)
e)
REV. NO.: R3
4.2.7.9
Controls
The following manual controls shall be provided on the front of the panel:
a)
b)
Voltage setters for setting the output of float / equalizing / boost charge.
Setting shall be independent of each other so that setting of one voltage
shall not require resetting the other.
c)
d)
b)
Lamp, heater and receptacle circuits shall have individual switch fuse
units.
The panels shall be completely wired up. All wiring shall be routed
through wiring troughs. Wires shall be ferruled at both ends for
identification.
b)
Panels shall have removable gland plates at the bottom for cable entry. All
incoming / outgoing cables shall be terminated in suitable terminal
blocks.
c)
Control terminal blocks shall be cage clamp type. 20% spare terminals
shall be provided.
4.2.7.11 Grounding
a)
The charger panels shall have fully rated ground bus with two ground
terminals, one at each end.
b)
Each terminal shall comprise two bolt drilling with M10 GI bolts and nuts
to receive ground connection of 50 x 6 mm GI flat.
4.2.7.12 Painting
a)
The panels shall be chemically cleaned, phosphated and sprayed with two
coats of high quality primer and stoved after each coat.
REV. NO.: R3
b)
The panels shall be finished in light gray shade no.631 as per IS-5 with
two coats of synthetic enamel paint.
4.2.7.13 DC switchboards
For feeding the 220V DC loads, 220V DC switchboard shall be provided.
The switch boards shall be provided with suitable quantity and type of outgoing
feeders for the auxiliaries, control supplies to various panels / systems. For each
load and auxiliary, one separate feeder shall be provided. In addition, the
following feeders shall be provided in switchboard.
a)
Spare feeders 20% of each type and rating with a minimum of two nos.
feeders. This is the minimum quantity at the time of handing over the
system.
The short circuit current rating of the switchboard shall be arrived considering
the contribution from charger and battery with 5% margin, with a minimum of
20 kA for 1 sec.
The continuous current rating of the bus bars, incomers for 220V DC
switchboards shall be the maximum DC load on the bus plus 20% margin
rounded off to the next higher standard rating.
4.2.7.14 Specific requirements
Positive and negative sleeved bus bars in the DC switchgear shall be completely
segregated from each other by sheet steel partitions.
Module details
i) Incomer
The incomer modules shall be suitable for DC application ACB controlled. Each
incomer shall be provided with
REV. NO.: R3
Earth fault relay with potential free contact for remote annunciation
Indicating lamps for ON, OFF, earth fault, under voltage conditions
Necessary hardware and circuitry for fault alarm and for lamp test and reset
These feeders shall have DC switch fuse units of draw out type, ON, OFF &
FAULT indicating lamps, supply supervision relays & lamp test.
The feeders rated 200 Amps and above (as applicable) shall be provided with
a shunt and ammeter.
The offered batteries and chargers shall comply with the technical requirement
enclosed vide DATA SHEET-A.
4.2.7.15 Standards
All equipments provided under the specification shall in general, conform to the
latest issue.
4.2.7.16 Tests and tests reports for Battery, Battery Charger and DC
Distribution Board
a) Acceptance test
The following acceptance tests shall be carriedout at manufacturers works in
presence of Owner or his representatives
Verification of markings
Verification of dimensions
b) Type test
Type test certificates as mentioned below for similar equipment supplied by the
bidder shall be submitted. In case type test certificates for similar equipment is
not available or type test certificate is more than 5 years old, the same shall be
conducted in presence of Owners or his representative if Owner so desires.
REV. NO.: R3
Endurance test
c) Functional checks
d) Voltage regulation for rated input supply for loads from 0-100%.
e) Load test to show the charger can deliver the rated duty without the current
limiter device operating.
High voltage test, excluding electronic controller, at 2kV AC for one minute.
j)
Heat run test shall be conducted at full load for 24 hours at the vendor works
on charger.
c) Routine test shall be carried out on all equipment such as circuit breakers,
relays, meters, contactors, switch-fuses, etc.
Type test reports on identical board issued by an authorised test house shall be
furnished
4.2.8
HT Motor
4.2.8.1
HT Motor Specification
REV. NO.: R3
shall match the requirements of the driven equipment so that adequate starting,
accelerating, pull up, break down and full load torques are available for the
intended service.
4.2.8.2
ConstructionalFeatures
Motors shall be squirrel cage type. The motor winding shall be of copper.
Motor rating for belt conveyors (as applicable) shall have a minimum margin
of 20% and for other motors 10 % over the required kW.
Motor shall run continuously at rated output over the entire range of voltage
and frequency variations.
Motors >160 and up to 1500 kW shall be suitable for 3.3 kV, 3 phase, 50 Hz
power supply.
Motors shall be capable of developing the rated full load torque even if the
supply voltage drops to 70% of rated voltage. If such operation is envisaged
for a period of one-second pull out torque of the motor shall be at least
205% of full load torque.
Starting current, starting time, starting voltage etc shall be compatible with
the supply voltage and its parameters, protection system. All motors (except
DC motors) shall be started Direct On Line (DOL).
the nominal voltage and shall not stall at 70% of nominal voltage for one (1)
minute. With voltage and frequency within permissible variation band, the
motors shall be capable of 3 equally spaced starts in 1 hour with motor
initially at temperature not exceeding rated operating temperature. 2 start in
REV. NO.: R3
The motors shall also be capable of restarting under full load after a
The motor shall be self ventilated type, totally enclosed fan cooled (TEFC). All
insulated winding shall be of copper and. impregnated. All motors shall have
class F insulation, but limited to class B temperature rise as per IS: 325
For 3.3 kV motors, 6 nos. duplex RTDs for winding shall be provided with
Cable boxes of all 3.3 kV motors shall be provided with quick disconnecting
type terminal connectors.
The motor shall start smoothly and rapidly and maintain steady operation.
The motor characteristics such as speed, starting torque, acceleration time
etc. shall be properly coordinated with requirement of driven equipment.
a)
The locked rotor withstand time under hot condition at 110% rated
voltage shall be more than motor starting time at minimum permissible
voltage by at least 2.5 seconds for motors up to 20 seconds starting time
and by 5 seconds for motor with more than 20 seconds starting time.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
b)
rotation .
Cable box and terminal box for 3.3 kV motors shall be phase segregated
type.
d)
e)
All 3.3 kV motors shall have winding temperature detectors and bearing
temperature detectors and indicators.
f)
Motor shall be provided with sealed and optimum lubricated anti friction
bearings, Provision of replacing lubricant without opening the bearing by
use of greasing gun/ drain plug shall be provided.
g)
The Noise level shall not exceed 85 db (A) at a distance of 1.0 M from
motor at no load condition. The maximum double amplitude vibrations
for motors up to 1500 rpm shall be 25 microns and 15 microns up to
3000rpm.
h)
i)
The frame of each motor shall be provided with two separate and distinct
grounding pads complete with tapped hole, GI bolts and washer.
j)
k)
l)
Motor shall be provided with space heaters. The space heater shall be
REV. NO.: R3
The motor shall be designed to permit easy access for drilling holes
through motor feet or mounting flange for installation of dowel pins after
assembling the motor and the driven equipment.
n)
Drawings, Documents, Data and Manuals shall be submitted with the bid
and in quantities and procedures as specified in Conditions of Contract
and/or elsewhere in this specification for approval and subsequent
distribution after the Effective Date of Contract.
o)
The type tests must have been conducted not earlier than five years from
the date of bid opening. Type Test certificates shall be furnished for
motors of similar design. Alternatively, type tests shall be conducted
afresh with no cost to owner. The bidder shall furnish two sets of the
following as per IS/IEC along with the offer:
Surge withstand test on the sample coil after placing it in stator core
at (4U + 5kV) and with at least five impulse of 1.2/50 micro sec. wave,
for HV motors only, where U is the line to line voltage in kV. The
tested sample coil shall not be used for the motors supplied.
p)
Finally certified reports of all the tests carried out at the works shall be
furnished in requisite no. of copies for approval of the Owner. The
equipment shall be dispatched from works only after receipt of Owner's
written approval of the test reports.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
4.2.8.3
1
IS: 12075
BS - CP 1014
Proofing
4
IS 4691
IS 5572
IS 4728
electrical machinery
7.
IS6362
IS 4029
induction motors
9.
IS 2968
10
IS 2253
motors
IS 8239
IS 2148
apparatus
4.2.9
LT Motor
4.2.9.1
LT Motor Specification
REV. NO.: R3
accelerating, pull up, break down and full load torques are available for the
intended service.
4.2.9.2
Constructional Features:
a) Motors shall be squirrel cage type except for cranes. The motor winding shall
be of copper. Motor shall be suitable for voltage variation of 10%, frequency
variation of 5% and combined voltage and frequency variation of 10%.
b) Motor rating shall have a minimum margin of 10% over the required kW
requirement of driven equipment.
c) Motor shall run continuously at rated output over the entire range of voltage
and frequency variations.
f) Motors <160 kW shall be 415V rating. Motors of rating >90 kW shall be ACB
operated.
g) Motors shall be capable of developing the rated full load torque even if the
supply voltage drops to 70% of rated voltage. If such operation is envisaged
for a period of one-second pull out torque of the motor shall be it at least
205% of full load torque.
h) The motor shall be capable of operating satisfactorily at full load for 5
minutes commencing from hot condition without injurious heating with 85%
rated voltage at motor terminals.
i)
j)
Starting current, starting time, starting voltage etc shall be compatible with
the supply voltage and its parameters, protection system.
REV. NO.: R3
m) The motor shall be self ventilated type, totally enclosed fan cooled (TEFC). All
insulated winding shall be of copper and. impregnated. 2 RTD duplex type in
each phase of the winding slots with terminals brought out in a junction box
shall be provided. All motors shall have class F insulation, but limited to class
B temperature rise as per IS: 325
n) All motors shall be DOL started.
Motor shall be provided with sealed and optimum lubricated anti friction
bearings, Provision of replacing lubricant without opening the bearing by use of
greasing gun/ drain plug shall be provided.
REV. NO.: R3
The Noise level shall not exceed 85 db (A) at 1.5 M from motor at no load
condition. The maximum double amplitude vibrations for motors up to 1500
rpm shall be 40 microns and 15 microns up to 3000rpm.
Motor terminal box shall be located in accordance with Indian Standards clearing
the motor base plate/foundation. It shall be split type with removable cover with
access to connections and shall have the same degree of protection as motor. It
shall have sufficient space inside for termination connection of XLPE insulated
armored aluminum cables. It shall be capable of withstanding maximum system
fault current for duration of 0.25 sec.
The frame of each motor shall be provided with two separate and distinct
grounding pads complete with tapped hole, GI bolts and washer.
In addition to the minimum information required by IS, the information about
Temperature rise in Deg.C under rated condition and method of measurement,
Degree of protection, Bearing identification no. and recommended lubricant
should be shown on motor rating plate.
Motor of rating above 30 kW shall be provided with space heaters. The space
heater shall be rated 240 V, 1 phase 50 Hz and sized.
All accessory equipment such as space heater, temperature detector shall be
wired to and terminated in terminal boxes, separate from and independent of
motor (power) terminal box. Motors shall have perfectly located drain plug.
Motors weighing 25 kg or more shall be provided with eyebolt or other adequate
lifting provisions.
Drawings, Documents, Data and Manuals shall be submitted with the bid and in
quantities and procedures as specified in Conditions of Contract and/or
elsewhere in this specification for approval and subsequent distribution after the
Effective Date of Contract.
The type tests must have been conducted not earlier than five years from the
date of bid opening. Type Test certificates shall be furnished for motors of
similar design. Alternatively, type tests shall be conducted afresh with no cost to
owner. The bidder shall furnish two sets of the following tests as per IS/IEC
along with the offer.
REV. NO.: R3
Terminal box fault level withstand test for each type of terminal box of LT
motors only.
Operation of LT motor at full load at 85% VR for 10 min. upto 110 KW and
80 % VR for motors above 110 KW.
Finally certified reports of all the tests carried out at the works shall be
furnished in requisite no. of copies for approval of the Owner. The equipment
shall be dispatched from works only after receipt of Owner's written approval of
the test reports.
Motor Operated Valve Actuators
The actuator motors shall be designed for short time duty (S2) in accordance
with IEC 34-1. Degree of protection for actuator motor enclosure shall be IP65 and IP-67 for indoor and outdoor respectively.
The actuator motor shall be time rated for at least 15 minutes or twice the
Motor shall have minimum class 'F' insulation with temperature rise restricted
to class 'B'.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
Motor shall be suitable for direct on-line (DOL) starting and starter shall be
integral to the motor.
The actuator shall be complete with all accessories viz. torque limit switch,
endof- travel switch, adjustable position limit switch, hand-wheel etc.
4.2.9.3
1.
IS12615 EEF 1 or
equivalent standard
2.
IS: 12075
BS - CP 1014
4.
IS 4691
Proofing
IS 5572
IS 4728
7.
IS6362
machinery
IS 4029
motors
9.
IS 2968
motors
10.
IS 2253
IS 8239
REV. NO.: R3
IS 2148
apparatus
4.2.10
Enclosure shall be rectangular and shall be made of aluminum alloy sheets. The
Bus ducts shall be non phase segregated and natural air-cooled type in
construction.
The design and construction of the bus ducts shall be such as to limit the
temperature rise within the following values when operating continuously at the
current corresponding to the rated MVA of transformer and 90% rated voltage.
The hot spot temperature of the bus conductor is 90 deg C including joints. The
hot spot temperature of bus enclosure is 70 deg C.
The bus ducts will be installed partially indoor and partially outdoor in a hot,
humid and tropical atmosphere.
REV. NO.: R3
Bus duct, associated equipment and wiring shall be provided with tropical finish
to prevent fungus growth. All ventilation openings shall be screened and drains
shall be filtered to prevent entrance of dust and insects.
mechanical forces and thermal stresses of the short-circuit currents without any
damage or deterioration of material. Bus conductor support insulator span shall
be chosen considering minimum factor of safety of 2.5 for cantilever strength
under short circuit condition.
In the bus duct routing the phase changeover is to be avoided. The bus duct
entry to switchgear is from top only.
The portion of bus duct at the transformer end will be subject to vibration
normally prevalent for this type of installation in a power generating station.
Suitable means shall be provided to isolate the transformer vibration from rest
of the bus structure/bus duct.
Equipment mounted outdoors
The circumferential neoprene rubber gaskets shall be provided for dust tight
joints with adjacent enclosure sections. The bus enclosure shall have extended
bellows or equivalent means to allow for temperature changes and vibrations.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
Flexible joints shall be provided in enclosures at all points where the bus duct
terminates at equipment to withstand vibration, expansion/ contraction and at
suitable intervals in any straight run of the bus duct where expansion and
contraction would otherwise result in stresses in the supporting structures.
Epoxy resin cast seal-off bushings complete with wall-frame and support plates
shall be provided where the bus duct penetrates the building wall. The seal is to
prevent free exchange of air between indoor and outdoor portions of the bus
duct.Wall frame assembly and seal off bushings shall be fabricated out of
aluminum angles and sheets.
Silica-gel breather shall be provided on both indoor and outdoor portions of the
bus duct. Filtered drains for drainage of condensate shall be provided at the
lowest points and at such locations where accumulation of condensate can be
expected.
Shipping length of the bus duct shall be not more than three (3) metres in
length. Each shipping section shall have at least two (2) supports both for
conductor in each phase and enclosure. Suitable blanked flanges with cover shall
be provided on the enclosure of the busduct (indoor and outdoor) to allow
connection of hot air duct of hot air blowerto improve insulation level after long
shut down etc.
REV. NO.: R3
insulators may be offered. Bus support insulators shall be of 7.2 kV/1.1 kV class
and shall be mounted on resilient pad.
Insulator shall be mounted in such a way so as to permit easy removal or
replacement without disassembly of the bus. The insulator mounting plate shall
be designed for cantilever loading to withstand the short circuit force. Support
span shall be taken into consideration.
The conductor shall be fastened on the insulator through fixed and slip joints so
as to allow conductor expansion or contraction without straining the insulator.
REV. NO.: R3
Between the bus duct portions supported from building steel to prevent
transmission of vibration.
The equipment terminal connections shall be easily accessible and shall provide
sufficient air gap for safe isolation of equipment during testing.
Suitable bi-metallic connectors shall be provided wherever the material of bus
conductor and equipment terminals are different.
4.2.10.6 Grounding
A continuous 70x10mm galvanized mild steel earth bar shall be provided along
the entire run of each bus duct. Each section of the bus duct enclosure shall be
bonded to this earth bar at least at both ends of the enclosure. The earth bar
shall be connected to the main earthing system at its two ends by the
contractor.
4.2.10.7 Supporting Structures
All supporting structures required for hanging and/or supporting the complete
bus duct shall be furnished. These include all members, indoor/outdoor posts,
bolts, shims, base plates, beams, hangers, brackets, bracings and hardware.
REV. NO.: R3
temperature above the dew point to prevent moisture condensation within the
bus duct. Space heaters shall be rated for 240V, single phase, 50Hz AC supply.
The space heaters and thermostats shall be wired up to terminals in suitably
located terminal boxes to be provided by the contractor. The space heater wiring
inside the bus duct enclosure shall be done with high temperature resistant
cables as the ambient temperature existing inside the bus duct enclosure may
vary from 800C to 900C
Controlling the space heaters of each bus duct shall be done from the feeders
earmarked in LT Switch gear panels.Single phase 240 V power supply at the
Switch gear panel for complete run of every bus duct is required. All cabling
between space heaters/thermostats and switch gear panels in the run of bus
duct shall be supplied and erected by the contractor. Cable entry points to the
bus duct shall be sealed properly by providing suitable glands.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
IS code
Description
a)
IS:226
b)
IS:737
c)
IS:800
d)
IS:1367
PART-13
e)
IS:2099
f)
IS:13947
PART-1
g)
IS:2544
h)
IS:2633
REV. NO.: R3
S.N
IS code
Description
articles
i)
IS:4759
j)
IS:5082
k)
IS:8084
Updated
upto:1992
l)
ANSI C37:20
opening. These reports should be for the test conducted on the equipment
similar to those proposed to be supplied under the contract and the test(s)
should have been either conducted at an independent laboratory or should
have been witnessed by a client.
test(s)
conducted within last five years from the date of bid opening, or in the case
c) All acceptance and routine tests as per the specification and relevant
standards shall be carried out. Charges for these shall be deemed to be
included in the equipment price.
d) Type test reports for the following type tests shall be submitted:
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
Visual inspection
IR test
Typical calculation for arriving the size of the conductor and the insulator
spacing
Type test report (short circuit, impulse withstand, temperature rise test) for
similar bus duct manufactured by the proposed manufacturer.
4.2.11
Neutral Grounding
REV. NO.: R3
240V AC systems for lighting and the space heating shall be solidly earthed
system. The neutral of the transformers shall be connected to the earth bus
through a link in the respective board, which is inturn connected to the power
plant earth grid.
240V AC control supply shall be solidly earthed system. The earth side of the
transformer shall be connected solidly through a link to the earth bus in the
respective modules of switchgear/control panels.
110 V AC control supplies shall be a solidly earthed system. The earth side of
the transformers shall be connected solidly through a link to the earth bus in
the respective modules of switchgear / control panels.
220 V DC system shall be unearthed.
Sizing of Neutral Earthing Equipment:
The neutral earthing resistor ohmic value for Power transformer neutral earthing
shall be such that earth fault current is limited to 300 Amps.
4.2.11.2 Specific Requirements
a) Each neutral earthing resistor unit shall be air cooled and self-supporting
type. The enclosure shall have a degree of protection of minimum IP-54 for
indoor and IP-55 for outdoor.
b) The resistor elements shall be made of non-aging stainless steel or
equivalent corrosion resistant material and all element connections shall be
bolted type. All the resistor elements shall be internally connected and end
The resistors shall be provided with taps at 25%, 50% & 75%.
REV. NO.: R3
f)
4.2.11.3 Tests
1
Measurement of resistance.
Check for temp. rise of enclosure and current flow in the resistances.
applicable).
4.2.12
Illumination system
areas covered under the scope work of the bidder. The lighting system shall be
designed based on actual loads, plus 20% margin, for future requirement, on
total load.
The Contractor shall carefully consider these illumination levels before
proceeding with the design work.
Lighting distribution boards shall be provided with Lighting Transformer,
lighting Panel shall be provided with incoming MCCB and a number of outgoing
circuits operated by MCB.
REV. NO.: R3
Fluorescent Lamp (CFL) fittings. Ventilation Room (if any) shall be done with
fluorescent fittings. Battery Room shall be done with flameproof / anti corrosion
fittings.
Normal AC lighting - This will be provided by A.C. lighting fixtures distributed
throughout the different areas. These lights will be ON as long as the normal
A.C. supply is healthy. The main lighting distribution boards will be fed through
respective 1:1 ratio lighting transformer, which forms a part of the MLDB.
Normal A.C. supply thus made available by the MLDB is 415V-3ph-4 W-50 Hz
effectively grounded. The distribution of lighting circuits should be such that no
two consecutive fixtures are fed from the same circuit.
Exit sign with built-in lamp preferably Light Emitting Diode (LED) shall be
provided at all strategic location. The exit lamps shall remain ON all the time.
In an area, the lighting fixtures shall be arranged in different phases/ LPs such
that even in case one lighting panel is faulty complete lighting is not affected. In
case of any location the lighting shall be arranged at least from two phases.
The circuit loading on each circuit shall be restricted to 80% of the MCB rating.
The voltage drop from LDB and any fixture shall not exceed 3%.
Requirements
REV. NO.: R3
All equipment and accessories shall be designed for continuous operation under
site conditions without exceeding permissible temperature rise as stipulated in
relevant standards.
MCCB, miniature circuit breakers (MCB), bus bars shall be fully rated for short
circuit level at the point of application. MCB should be used in place of HRC
fuses
All equipment and accessories shall have proper enclosure to suit the site
conditions. Enclosure degree of protection is subject to Owners approval.
All wiring from lighting panels to fixtures and receptacles shall be carried out by
FRLS PVC wires in G.I. conduits.
Heavy-duty power cables will be used only for connections between:
Method of calculation
Standard Lumen method shall be adopted for interior & exterior lighting in order
to determine the number of lighting fixtures for obtaining the desired average
level of illumination.
The coefficient of utilization shall be considered to take care of Lumen loss due
to
Mounting height
Moreover a maintenance factor shall also be considered to account for the fall of
illumination due to aging, pollution like dust deposit etc. Maintenance factors to
be considered for various areas shall be as follows:
Area
Control Room
Doc. No.: E072-03-CHP-O-02
Maintenance factor
0.65 0.75
REV. NO.: R3
Switchgear/MCC Room
0.60-0.65
0.55 0.60
0.50-0.55
Circuit loading of each lighting Panel shall be done in such a way that almost
balanced loading in all the phases i.e R, Y & B is achieved. At least two sub
circuits shall be used for illumination of a particular area. Sub circuit loading of
each lighting panel shall be restricted to 2 kW.
The vendor will submit their total design proposal for area lighting including
lighting of buildings, streets, bays, etc., with detail drawing for the approval of
the owner
4.2.12.2 Detailed Requirements
4.2.12.3 Equipment & Material
Equipment and material shall comply with description, rating, type and size as
required
Equipment and materials furnished shall be complete and operative in all details.
All accessories, control devices, internal wiring, fittings, supports, hangers,
anchor bolts etc. which form part of the equipment or which are necessary for
safe and satisfactory installation and operation of the equipment shall be
furnished.
All parts shall be made accurately to standard gauges so as to facilitate
replacement and repair. All corresponding parts of similar equipment shall be
interchangeable.
Lighting fixtures shall be designed for minimum glare. The surface finish
shall be smooth and scratch resistant.
Fixture shall be suitable for 19 mm conduit entry and 16 SWG G.I. earth wire
connection.
REV. NO.: R3
4.2.12.5 Lamps
Energy efficient lamps (higher lumens per watt) should be provided e.g
instead of incandescent lamp CFL should be used wherever appropriate
Sodium vapour lamp shall be colour corrected type with screwed cap
All fluorescent lamps shall be bi-pin rotary type and either cool daylight or
Lamps shall be suitable for use in position and capable of withstanding small
vibrations. Restrictions and special features, if any, shall be clearly indicated
in the bid.
4.2.12.6 Ballast
Electronic ballasts shall be provided for fluorescent & CFL lamps.
Ballast windings shall have maximum operating temperature of 120oC without
Ballast for Metal halide / Sodium vapor lamp shall be provided with suitable
tapings to set the voltage within range specified.
REV. NO.: R3
Indoor boards / panels shall be dust and vermin-proof, IP-54 or better; outdoor
boards / panels shall be weather proof with canopy & double door IP-55 or
better.
Two ground pads with M10 bolts and nuts shall be provided on each board /
panels for connection to 50 x 6/25 x 3 mm G.I. flat.
Each board/panel shall be completed with designation and caution notice plates
fixed on front cover and a circuit directory plate fixed on inside of the front
cover.
The plates shall be of anodized aluminium with inscriptions indelibly etched on
it. Bus bar shall be electrolytic grade, hard drawn aluminium; color coded for
easy identification and designed for a maximum temperature of 85 deg. C.
REV. NO.: R3
Panel busbar shall be electrolytic grade hard drawn aluminium, colour coded for
easy identification of required size.
4.2.12.9 Receptacles
Receptacles shall be heavy duty, complete with individual plug, top socket and
switch.
The conduit box of the receptacle shall be provided with earthing screws with
washer and nuts welded on the surface for grounding with 16 SWG G.I. wire.
Arrangement shall be provided inside the conduit box for grounding of third pin.
Shrouded type plug shall be provided with corresponding matching arrangement
at sockets to prevent accidental contact with finger during plug insertion.
The distribution of receptacles shall be such that the loading on each phase of the
LDB is approximately equal.
4.2.12.10 Fans & Regulators
The fans shall have three well balanced blades, and shall be reasonably free from
noise. Pedestal fans shall also be provided as per Owners requirement.
Fan motor shall be totally enclosed type with copper winding and class E
insulation. Regulator shall have minimum five steps.
REV. NO.: R3
R phase
BLACK
Neutral
YELLOW
Y phase
RED
+ ve DC
BLUE
B phase
BLACK
- ve DC
1C, 6 sq mm
REV. NO.: R3
REV. NO.: R3
4.2.12.20 Painting
All sheet steel enclosures shall be chemically cleaned, rinsed, phosphated, rinsed
and dried. After the treatment, steel surfaces shall be given undercoats of primer
and finished with two coats of sprayed on enamel of lacquer of approved shade.
4.2.12.21 Samples
Owner reserves the right to call for samples, if considered necessary, and the
same shall be submitted by the Contractor free and without any obligation.
4.2.12.22 Consumables and Hardware
The Contractor shall furnish all erection materials, hardware and consumables
required for the complete installation.
The materials shall include but shall not be limited to the following:
Consumables - Welding rods & gas, oil and grease, cleaning fluids, paints,
electrical tape, soldering materials etc.
Hardware - Bolts, nuts, washers, screws, brackets, supports, clamps, hangers,
saddles, cleats, sills, shims etc.
Supply - cement, sand, stone etc. required for the execution of the contract shall
be the responsibility of the Contractor.
Testing equipment - The Contractor will provide such checking and testing
equipment as test lamp, buzzer, 500-volt meggar, earth meggar, Lux meter,
multi meters etc. and also other testing equipment as required.
4.2.12.23 Specific Requirement - Installation
General
REV. NO.: R3
accessories including civil foundation work, installing lighting fixture, wiring and
cabling work are included within scope of contractor.
Flood Lighting Tower - Erection of Flood Lighting Towers including civil
foundation work shall be done by Contractor. Contractor shall also mount
assembled fixtures, outdoor & lockable type isolating switch cubicle, install
necessary cabling and wiring and make connections.
Conduit System
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
In case of un-armoured cable, all G.I. conduits shall originate from the respective
lighting panel and terminate in lighting fixtures, receptacles, etc. Standard
installation procedure shall be followed for cleaning conduits after installation.
Exposed G.I. conduits shall be run in straight lines parallel to building columns,
beams and walls as far as practicable. Unnecessary bends and crossings shall be
avoided to present a neat appearance.
Wooden plug inserted in the masonry or concrete for conduit support is not
acceptable.
Embedded conduits shall be securely fixed in position to preclude any movement.
In fixing embedded conduit, if welding or brazing is used, extreme care should be
taken to avoid any injury to the inner surface of the conduit.
Where conduits are run on cable trays, they shall be clamped to supporting steel
at an interval of 600 mm.
For directly embedding in soil, the conduits shall be coated with an asphalt base
compound. Concrete pier or anchor shall be provided where necessary to support
the conduit rigid and to hold it in place.
Conduits shall be installed in such a way as to ensure against trouble from
trapped condensation.
Running threads shall be avoided as far as practicable. Where it is unavoidable,
check nuts shall be used.
REV. NO.: R3
Conduits shall be kept, wherever possible, at least 300 mm away from hot pipes,
heating device etc. when it is evident that such proximity may impair the service
life of cables.
Slip joints shall be provided when conduits cross structural expansion joints or
where long run of exposed conduits is installed so that temperature change will
cause no distortion due to expansion or contraction of conduit run.
Lighting fixture shall not be suspended directly from junction box in the main
conduit run.
Conduits and fittings shall be properly protected during construction period
against mechanical injury. Conduits ends shall be plugged or capped to prevent
entry of foreign material.
REV. NO.: R3
Wiring
Wiring shall be generally carried out by HR PVC FRLS wires in conduits. All wires
in a conduit shall be drawn simultaneously. No subsequent drawing is
permissible.
Wire shall not be pulled through more than two equivalent 90 bends in a single
conduit run.
Wiring shall be spliced only at junction boxes with approved type connections or
terminal strips. Maximum two (2) wires can be connected to each way of the
terminal block.
For lighting fixtures, connection shall be teed of through suitable round conduit
or junction box so that the connection can be attended without taking down the
fixture.
For vertical run of wires in conduit, wires shall be suitably supported by means of
wooden/hard rubber plugs at each pull/junction box.
A.C. and D.C. circuits shall not be run in the same conduit.
Receptacle sub-circuits shall be kept separate and distinct from lighting and fan
sub-circuits.
Separate neutral wire shall be provided for each circuit. Wiring throughout the
installation shall be such that there is no break in the neutral wire
Cabling
In outdoor areas, main runs shall be by means of armoured cable laid in trenches
or directly buried in ground.
Buried cables shall be laid and covered with sand/riddled earth and protected
from damage by bricks at sides and pre cast concrete slab at top.
When buried cables cross road / railway track, additional protection to be
provided in form of hume / G.I. pipe / RCC box culvert.
4.2.12.24 Grounding
REV. NO.: R3
Steel for fabrication shall be straightened and cleaned of rust and grease. All
fabrication shall be free of sharp edge.
All excavation shall be backfilled to the original level with good consolidation.
4.2.12.27 Foundation & Civil Works, Structural Work
REV. NO.: R3
All steel fabrication shall be given two coats of redoxide primer followed by epoxy
finish coating to shade 631 of IS 5.
Efficiency (BEE)
Electronic ballast should be used for the fluorescent and CFL
4.2.12.30 Standards
All equipments provided under the specification shall in general, conform to the
latest issue but not limited to the following:
S.N
a)
IS code
IS:1913
Description
Electric Lighting Fittings General and Safety
REV. NO.: R3
S.N
IS code
Description
Requirements
b)
IS:6665-1972
IS:3646 (Part-
IS:1777
III)
c)
Reflectors
d)
IS:5077
e)
IS:4012
f)
IS:4013
g)
IS:8224
h)
IS:4013
Part I and II
i)
IS:2148
j)
IS:11322
Flood Lights
Pt-V SECT-5
k)
IS:11322
Pt-V SECT-3
l)
IS:3528
m)
IS:3553
n)
IS:1258
o)
IS:11276
p)
IS:3323
q)
IS:2215
r)
IS:3324
s)
IS:1534 (Part
1)
t)
IS:7027
u)
IS:6616
v)
IS:1569
w)
IS:8017
x)
IS:2418 (Part
1)
y)
IS:9900
z)
IS:418
REV. NO.: R3
S.N
IS code
Description
aa)
IS:7569
ab)
IS:11322 Pt-III
ac)
IS:9974
ad)
IS:9583
ae)
IS:11105
af)
IS:11322
Luminaires (Part 1 to V)
ag)
IS 5578
IS 11353
ah)
IS 4237
ai)
IS 11118
aj)
IS 8623
ak)
IS 13947
al)
IS 13947
Part-3
am)
IS 8828
an)
IS 2705
Current Transformers
ao)
IS 3156
Voltage Transformers
ap)
IS 1248
aq)
IS 722
AC Electricity Meters
ar)
IS 3231
as)
IS 2148
at)
IS 5571
au)
IS 3854
Hazardous Areas
av)
IS 1293
aw)
IS 374
ax)
IS 9537
ay)
IS 3837
REV. NO.: R3
S.N
IS code
Description
az)
IS 3480
ba)
IS 9537
Part-2
bb)
IS 3419
Part-2
bc)
IS 694
bd)
IS 2713
be)
IS 5082
bf)
IS 6005
bg)
IS 2667
bh)
IS 13158
bi)
IS 2905
REV. NO.: R3
To prove the fire resistant characteristics, and rodent and termite repulsion
property, each type of cable shall also be subject to the following additional type
tests at works;
Oxygen index test as per ASTM D 2863. Minimum vale of oxygen index shall be
30.
Flammability test on finished cables as per the requirement of IEEE-383, IEC332-1 and Swedish standard SS 4241475 clause F3.
Smoke generation by outer sheath under fire as per ASTM D 2843. The cables
shall meet the requirements of light transmission of minimum 40% after the test.
The test shall be carried out by extrapolation method beyond temperature at
which the material of sheath may start deformation as per BICC handbook
chapter-6 on cable in fire. The minimum value of temp. index shall be 250 Deg.
C.
Acid gas generation by outer sheath under fire as per IEC-754-1 and the
minimum acid gas generation shall be less than 20% by weight.
Test for rodent & termite repulsion property
The Test shall be carried out to note the presence of rodent and termite
repelling chemical in PVC compound. Normal procedure is that a few chipping of
the PVC compound are slowly ignited in a porcelain dish on crucible in a muffle
furnace at about 600 Deg. C. The resulting ignited ash is boiled with a little
Type test (as indicated in Cable specs) certificates for type tests & as stipulated
in Indian Standard carried out on similar equipment shall be furnished by the
Bidder along with his offer.
All equipment shall be demonstrated to operate in accordance with the
requirements of this specification.
REV. NO.: R3
4.2.13
Installation / Erection
REV. NO.: R3
Any material or accessory which may not have been specifically mentioned but
which is necessary or usual for satisfactory and trouble-free operation and
maintenance of the equipment shall be furnished without any extra charge.
The Contractor shall supply all brand new equipment, material and accessories
REV. NO.: R3
After the treatment of steel surfaces damaged during transit sufficient quantity
of anti-corrosive paint shall be applied and subsequently finished with two coats
of final paint of approved shade.
Cable Trays
Ladder type cable trays shall be pre-fabricated sheet steel, minimum 2.5 mm
thick, with hot dip galvanized (zinc coating not less than 610g/sq. m).
The sizes of the trays shall be as follows:
i.
ii.
iii.
The contractor shall supply cable termination & jointing kits for HT/L.T. power
and control cables along with all accessories of RPCL approved make only.
For the cable termination and straight through joints both HT/L.T. power and
control cables, supply of items of jointing kit such, as, necessary boxes, if any,
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
glands shall match with the sizes of different HT/L.T. power, control &
Instrumentation cables.
Cable lugs
Cable lugs shall be heavy duty tinned copper suitable for termination of different
cross-section of HT/L.T. power, control & Instrumentation cables of AL & CU
conductor. Lugs for power, control & Instrumentation cables shall be crimping
type.
All materials for grounding work like earth mat, risers, structure and equipment
connections, shield wire etc. shall be supplied by the Contractor.
Specific Requirements - Services
Responsibility of erection
The Contractor shall be fully and finally responsible for proper erection, safe and
satisfactory operation of plant and equipment under his scope of work to the
entire satisfaction of the Owner.
The work shall be executed in accordance with the directions, instructions,
approved drawings and specifications.
REV. NO.: R3
Equipment and material which are wrongly installed shall be removed and reinstalled to comply with the design requirement at the Contractors expense, to
the satisfaction of the Owner without any cost implication to Owner.
Extra Work
The Contractor shall, when requested by the Owner, perform extra work and
furnish extra materials not covered under his scope of work, but necessary to
complete the installation without any price implication.
Methods and Workmanship
Contractor shall also takeout insurance policies which would cover the risk of
losses / damages of his tools & tackle and material/equipment which is in his
custody as also loss/ damages to any personnel.
Safety Measure
All safety rules and codes as applicable to work shall be followed without
exception. All safety appliance and protective devices including belts, hand
REV. NO.: R3
purposes. If for any reason the work is held up, the Contractor shall bring it to
the attention of the Owner in writing without any delay.
During the progress of work the Contractor shall submit monthly progress
report and such other reports on erection work and organisation as the Owner
may direct.
If in the opinion of the Owner the progress of erection work by the Contractor at
any stage needs expediting so as to ensure completion of work within stipulated
time, the Owner shall have the right to instruct the Contractor to increase
Contractors manpower in appropriate categories and/or the working hours per
day and/or erection tools and tackles and the Contractor shall comply with such
instruction forthwith.
Consumables and Hardware
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
The Contractor shall furnish all erection materials, hardware and consumables
required for the complete installation.
The Materials shall include but not limited to the following:
a)
Consumables :Welding rods & gas, oil and grease, cleaning fluids, paints,
electrical tape, soldering materials, cleaning cloths, cotton waste etc.
b)
b)
Hand operated Megger of 500 V & 1 kV grade for Insulation testing and
5000 V motor operated Megger for power circuits, bus bars connections
above 11 kV
c)
d)
e)
High potential test set suitable for 3.3 kV and 415 V (A.C.)
f)
g)
h)
REV. NO.: R3
systems.
i)
j)
spirit
level,
continuity
tester,
db-meter,
phase
sequence
tester,
The Contractor shall make his own arrangement to store all the materials
supplied by him. Materials delivered shall be stored or brought to the erection
site or erected as necessary.
The Contractor shall submit a detailed account of materials after completion of
work and transport back the excess materials to Owners stores.
Opening of Case
All packing cases and packages shall be opened in presence of Owner or his
authorized representatives. Packing cases shall be opened carefully to avoid
damage to timber. Nails and strips shall be collected separately in boxes and not
to be thrown away at random.
All packing materials, timbers, nails and strips shall become property of the
REV. NO.: R3
same are available. All necessary jobs required for statutory clearances will
under Bidders scope.
Equipment shall be installed in a neat workmanlike manner so that it is level,
plumb, square and properly aligned and oriented. The contractor shall assemble
all equipment furnished in disassembled condition at site, mount and wire-up
loose equipment, fittings and accessories and complete all connections.
The Contractor shall ensure that instruments and gauges to be used for testing
and inspection have valid calibration and the accuracy can be traced to National
Standards.
The Contractor shall design, fabricate and supply the supporting structures,
base frame, holding down bolts etc, as required, of all equipments. All erection
work shall be carried out in strict compliance with manufacturers instructions
and shall include all necessary adjustments, checks and measurements.
It shall be the Contractors responsibility to obtain valid license and approval
from local statutory authorities including Electrical Inspector/CEA, wherever
applicable, for carrying out any work or for installation carried out which comes
under the purview of such authorities. The entire cost, including all necessary
fees, incurred to obtain such license and approvals, shall be borne by the
contractor.
It is the responsibility of the Contractor to provide watch & ward and security for
the equipment / component parts covered in this contract.
The Contractor shall ensure workmanship of good quality and shall assign
qualified supervisors/Engineers and competent labour who is skilled having
valid licence/authorisation/work permit, careful and experienced in carrying out
similar works. The Purchaser/Engineer shall reserve the right to reject noncompetent person employed by the Contractor, if the workmanship is not found
All internal wiring of the equipment which has been left incomplete because of
shipping split or which requires minor modifications shall be carried out by the
Contractor. The Contractor shall record results of all erection tests and
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
measurements. The Contractor shall submit copies of those test results to the
Owner for his reference and record.
It shall be the responsibility of the Contractor to obtain necessary Licence/
Authorization/permit for work for his personnel from the Licensing Board of the
locality/state where the work is to be carried out. The persons deputed by the
Contractors firm should also hold valid permits issued or recognised by the
Licensing Board of the locality/state where the work is to be carried out.
4.2.13.5 Installation Work Scope
Temporary Lighting arrangement for the work Area
The Contractor shall on his own arrange for the temporary lighting arrangement
for the work area to carry out the installation work in the plant premises.
Construction Power
Construction power for construction activities only will be made available at one
point & suitable number of outlets to cater to all the requirements shall be
derived by the Contractor.
The construction power supply will be 11 kV, 3 Phase, and 50 Hz.The
Construction Power system by its design and nature shall be a temporary system
and not part of the permanent power supply. The Contractor acknowledges that
electricity sourced may be unreliable in quality and availability and its
interruption or non-availability or variations in supply voltage of frequency for
any reason shall not constitute a condition for claim of extra time or costs on
part of the Contractor. Further, Contractor shall be responsible for making
necessary arrangements to ensure that uninterrupted Construction Power supply
(DG sets) is available.
b) Power for temporary equipment put in place until such time as permanent
Plant Power supply systems are installed. Such temporary equipment shall
REV. NO.: R3
transformers
and
their
accessories
and
mountings
like
radiators,
Protruding fittings
Bushings
Tightness of Bolts
REV. NO.: R3
Oil leakage
Assembly of transformer
Alignment
Mechanical Work
Testing of cables
The connections shall ensure good electrical contact. The connector and joints
shall be rigid to withstand all mechanical and electrical stresses. Suitable
bimetallic clamps shall be used for all the connections between the conductors
of different materials.
All live parts shall have sufficient practical clearances from earthed parts and
ground. The clearances of strung busbar shall be decided considering the effect
of sag.
REV. NO.: R3
The contractor shall be responsible for supplying and installing the various
conductors required for connection of the various equipment. The tenderers
scope shall include all bolts, nuts and washers required for installation. All
connections etc., shall be so made that stress between connecting terminals will
be reduced to the minimum.
The physical layout of the system shall be such that the system extension or
conversion can he carried out with minimum changes and easy methods.
Further, it shall be ensured that all civil works for the foundations are completed
by the agency before taking up erection of structure.
Installation of Switchgear Panels
The base frame of all panels shall be welded to the structures or to the civil
consultation with the purchaser. Damage to the paint during welding shall be
rectified by the contractor.
After mechanical installation of the board is completed, instruments shall be
installed wherever required and wires shall be connected to the instruments. The
wiring
of
intermediate
terminal
strips
between
REV. NO.: R3
two
panels,
wherever
The contractors scope of installation will also include all the civil works
associated with complete earthing network.
All earth connections shall ensure a permanent low resistance contact. Earth
connections required to be removed for the purpose of testing of
It has to be ensured that main earth bus in the installation as well as earth
buses in individual sections/areas shall form complete ring and they shall be
interconnected.
Duplicate earthing (two separate and distinct connections with earth) shall be
employed for all equipments.
Wherever any earth conductor crosses the road, it shall be taken through GI
pipes.
Wherever not detailed, the route of the conductor and location of the earth
pit shall be arranged so as to avoid obstruction, crossing etc, according to
convenience at site and shall be got approved by the owners representative
in-charge of the works.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
The distance between two pits shall be at a minimum distance of twice the
length of electrodes.
All accessories required for the earth pits such as electrodes, charcoals, salt,
clamps, clips, bolts/ nuts washer, GI pipes, funnel cast iron cover and also
The electrodes shall be well packed with earth, charcoal and salt mix up to
the level of connections.
All joints of bare galvanised earth strips shall be welded so as to form rigid
earth ring. All such welded joints shall be given necessary coating of cold
galvanized paint as per relevant standards and a coat of suitable bitumen
compound to prevent corrosion.
In case the joints are made by using suitable connectors the entire joint shall
be fully sealed by suitable compound so that no metallic part is exposed.
The contractor shall make his own arrangements for necessary crimping
tools, soldering equipments drilling machines and other tools and tackles
which are necessary for completing the installation.
portion of the busduct may be supported from the floor or ceiling beams and
outdoor portion of the busduct shall be supported from ground below on
suitable foundation. Wall frame assembly shall also be installed as per
Contractor's drawings, wherever called for.
Motors
REV. NO.: R3
Installation - Cabling
General
Cable installation work shall mean supply and erection of cable trays/racks,
supports, hangers, junction boxes, conduits, laying of cables either in ground or
on trays inside trenches, tunnels, overhead trays, in conduits etc. dressing and
clamping, jointing inclusive of supply of necessary jointing kits, lugs, glands,
ferrules, tapes etc. and other accessories, grounding of cable armour. In case of
direct laying in ground, all excavation work, necessary back-filling, supply of
bricks and protective concrete slabs, removal of excess earth shall be part of the
installation work.
Pre-fabricated cable trays and accessories shall be assembled & erected at site
as per instructions of Manufacturer.
Cable trays either inside concrete trenches or inside buildings and racks inside
cable shafts shall be aligned and leveled properly. All tray runs shall be installed
parallel to the trench/building walls and floors except otherwise noted in the
drawings.
REV. NO.: R3
The Contractor shall also maintain and submit when requested, a record of cable
insulation value when drawn from store, after laying, before and after
termination/ jointing. Conduit/pipes shall be used only in short lengths in
certain areas where required and/or as directed by the Owner. The Contractor
shall furnish all conduits complete with accessories as required.
Conduits shall be flexible or rigid depending upon nature of application. Except
for inside an enclosure wherever the cable enters or leaves the conduit, the
REV. NO.: R3
Cable drums shall be stored on hard and well-drained surface so that they may
not sink. In no case shall the drum be stored on the flat, i.e. with flange
horizontal.
Rolling of drums shall be avoided as far as practicable for short distance; the
drums may be rolled provided they are rolled slowly and in proper direction as
marked on the drum. In absence of any indication, the drums may be rolled in
the same direction as it was rolled during taking up the cable.
For unreeling the cable, the drum shall be mounted on jacks or on cable wheel.
The spindle shall be strong enough to carry the weight without bending. The
drum shall be rolled on the spindle slowly so that the cable should come out
over the drum and not below the drum.
While laying cable, cable roller shall be used at an interval of 2000 mm. The
cables shall be pushed over the roller by a gang of people positioned in between
rollers over a suitable distance. Cable shall not be pulled from the end without
having intermediate pushing arrangement. Bending radius of the cable during
installation shall not be less that what is specified by the manufacturer.
Cable laying
Cable shall be installed in ladder type trays except for some short run in rigid /
flexible conduit for protection or crossings. Cables laid on trays and risers shall
be neatly dressed and clamped at an interval of 1500 mm.
Clamps for multicore cables shall be fabricated out of 25x3 mm aluminium flats.
All power cables shall be clamped individually and control cables shall be
clamped in groups of three or four cables. All single core power cables shall be
REV. NO.: R3
cable jointing, crimping, shorting and grounding as required for the complete
job. All equipment required for all such operations shall be furnished by the
Contractor.
Furnishing of all consumable materials, such as, soldering material, electrical
tape, sealing material as well as cable jointing kits shall be included in the offer.
Cable joint kits for all cables shall be supplied by Contractor under this
REV. NO.: R3
requires major modification, the same shall be carried out by the Contractor at
the discretion of Owner.
Control cable cores entering switchgear/distribution board etc. shall be neatly
bunched and served with PVC perforated type tape to keep it in position at the
terminal block. The Contractor shall put ferrules on all control cable cores in all
junction boxes and at all terminations. The ferrules shall carry terminal numbers
as per drawings. All ferrules shall be coloured, plastic and interlocked type.
Spare cores shall be similarly ferruled, crimped with lug and taped on the ends.
Spare cores shall be ferruled with individual cable number. Termination and
connection shall be carried out in such a manner as to avoid strain on the
terminals.
All cable entry points shall be properly sealed and made vermin and dust-proof.
Unusual opening, if any, shall be effectively closed. Sealing work shall be carried
out with approved sealing compound having fire withstand capability for at least
three hours.
Cable Joints
Cables shall be installed without joints. However, in exceptional cases, joints
may be allowed by Owner for which prior approval has to be taken.
REV. NO.: R3
All ground conductors shall be painted black for easy identification. Equipment
ground connections, after being checked and tested by the Owner, shall be
coated with anti-corrosive paint.
Whether specifically shown or not, all conduits, trays, cable armour and cable
end box, electrical equipment, switchboards, panels, cabinets, junction boxes,
switches, fittings, fixtures, structures etc. shall be effectively grounded.
Transformer ground connections and neutral earthing shall be in the scope of
Contractor.
2 nos, earth electrodes to be provided for each transformer body earthing &
neutral earthing. For Neutral earthing of transformer, plate type earthing to be
done. For Electronic parts separate redundant earth pit shall be provided
(Copper Electrode).
Painting
The contractor shall paint steel fabrications at site with two (2) coats of red
oxide primer and two (2) coats of gray (shade no. 631 of IS:5) synthetic enamel
paint.
All damaged parts shall be cleaned and coated with two (2) coats red oxide
primer paint followed by a finishing coat of approved colour. Only touch up
painting shall be done.
All damaged galvanized surfaces shall be coated with cold galvanising paint. All
equipment after erection shall be touch up painted only. All primer and paint
including touch up paints shall be supplied by the Contractor.
Structure Grounding
All steel structures are required to be grounded from ground mat. Laying,
supporting along with foundation connecting at ground mat are within the scope
of this specification.
Installation - Earthing & Lightning Protection System
The installation work shall include unloading at site, storing, laying, fixing,
jointing / termination, testing and commissioning of equipment associated with
the safety earthing system of the plant and lightning protection system for
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
buildings and allied structures. All welding / brazing equipment, necessary tools
and testing equipment shall be furnished by the Contractor.
The Contractor shall be responsible if any installation materials are lost or
damaged during installation. All damage and thefts shall be made good by the
Contractor till the installation is handed over to the Purchaser.
The earthing of cable supporting structure, cable carriers, cable trays shall be in
the scope of the Contractor.
The Contractor shall carry out the lightning protection and earthing of all
equipment / panels / structures as indicated in the Project drawings. Whether
specifically
shown
in
drawings
or
not,
building
columns,
handrails,
shall include excavation of earth upto 600 mm deep and 450 mm wide, laying of
conductor at 600 mm depth brazing / welding / cad welding if required, of main
grid conductor, joints as well as risers of length 500 mm above ground at
required locations and then backfilling. Backfilling material to be placed over
buried conductor shall be free from stones and other harmful mixtures. Backfill
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
shall be placed in layers of 150 mm, uniformly spread along the ditch, and
tampered utilising pneumatic tampers or other approved means, If the
excavated soil is found unsuitable for backfilling, the Contractor shall arrange
for suitable soil from outside.
main buried earth grid, as per project drawings / relevant standards. The scope
of work shall include excavation, construction of the earth pits including all
materials required for construction of earth pits, placing the rod and fixing test
links on those pipe/rod/plate electrodes in test pits and connecting to main
earth grid conductors.
The scope of installation of lightning conductors on the roofs of buildings shall
include construction of upstands, laying, anchoring, fastening and cleating of
horizontal conductors, grouting of vertical rods wherever necessary, laying,
fastening / cleating / welding of the downcomers on the walls / columns of the
building and connection to the test links to be provided above ground level.
The scope of installation of the test links shall include mounting of the same at
Earth leads between earthing riser and equipment earthing terminals shall follow
as direct and as short a path as possible.
REV. NO.: R3
REV. NO.: R3
Earth pits shall be treated with salt and charcoal if average resistivity of soil is
more than 20 ohm metre.
The lightning protection air termination rods and/or horizontal air termination
conductors shall be fixed in such a way that they remain in their installed
position even during severe weather conditions.
shall follow a direct path to earth. There shall not be any sharp bends, turns and
kinks in the down conductors.
All joints in the down conductors shall be of welded/brazed type. All metallic
structures within 2 meters from down conductors shall be bonded to lightning
protection system.
The lightning protection system shall not be in direct contact with underground
metallic service ducts, cables, cable conduits and metal enclosures of electrical
equipment. However all metal projections, railings, vents, tanks etc. above the
roof shall be bonded together to form a part of roof grid.
Excavation and Back Filling
The Contractor shall perform all excavation and backfilling as required for
buried cable and ground connections.
The Contractor shall make use of his own arrangements for pumping out any
water that may be accumulated in the excavation. All excavation shall be
backfilled to the original level with good consolidation.
Cleaning up of Work Site
The Contractor shall, from time to time remove all rubbish resulting from
execution of his work. No materials shall be stored or placed on passage or
drive- ways.
REV. NO.: R3
Upon completion of work, the Contractor shall remove all rubbish, tools,
scaffoldings, temporary structures and surplus materials etc. to leave the
premises clean and fit for use.
Inspection & Testing
On completion of erection works, the Contractor shall request the Owner for
inspection and tests with minimum fourteen (14) days advance notice.
The Engineer shall arrange for joint inspection of the installation for
completeness and correctness of the work. Any defect pointed out during such
inspection shall be promptly rectified by the Contractor.
The installation shall be then tested and commissioned in presence of the Owner
and put on trial run for stipulated Contract period. The Contractor shall arrange
for inspection of his installation work by electrical inspector and shall obtain
necessary approval/certificate for his installation work.
All rectification, repair of adjustment work found necessary during inspection,
testing, commissioning and trial run shall be carried out by the Contractor
without any extra cost.
Commissioning and Trial Run
Following
successful
inspection
and
testing,
the
equipment
shall
be
commissioned and put on trial run along with the main plant in a manner
mutually agreed upon based on the commissioning schedule of main plant.
The Contractor shall assist the purchaser in commissioning and trial run with
men and material as required and/or as directed by the Owner.
Taking over of Installation
On successful testing, commissioning and trial run, the Contractor shall request
Owner in writing for taking over the installation.
The Owner, on receipt of the request, shall arrange to take over the installation
either wholly or in part as the case may be after a final inspection.
Till such taking over, the responsibility of the whole installation against theft or
damage of any kind shall remain with the Contractor.
REV. NO.: R3
Till the equipments taken over by the owner, the equipment will be operated and
maintained by the contractor, however elimination of defects and complete
readiness of equipments for taking over by the owner should be done not
Code No
(a)
IS:10028
(b)
IS:10118
(c)
(d)
IS:900
IS:5216
work
(e)
IS:2629
(f)
(g)
IS:732
IS:1646
Guarantee
In the installation if any trouble arises due to the use of defective or faulty
material and/or bad workmanship within a period of 12 months from the date of
taking over, the Contractor shall guarantee to replace or repair the defects to
satisfaction of the Owner free of charge.
4.2.14
Earthing
steel, lightning protection system shall be connected to main plant ground grid
to have earth continuity for safety.
4.2.14.2 Design Criteria
Fault Current & Duration
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
Galvanised steel
(b)
(c)
Electrodes
GS Pipe / Rod
(d)
The Contractor shall undertake the soil resistivity measurements at site and
select suitable type of conductors.
Size of Conductors
(i) Main Earthing Conductors
1
I
= K
------ IS 3043 Cl.12.2.2.1
S
t
I =
S =
t =
K =
Qc
( B 20)
( B f )
ln e
20
( B i )
20 =
Qc =
Doc. No.: E072-03-CHP-O-02
Volumetric
heat
REV. NO.: R3
capacity
of
conductor
PAGE 243 OF 506
material
(J/deg.C.cu.m).
B
i =
f =
Reduction in thickness/diameter, mm
>0
<10
8.0
>10
<25
7.0
>25
<50
5.5
>50
<75
4.5
>75
<100
3.0
>100
1.5
Galvanised steel rod electrodes of suitable diameter and length shall be used as
per the recommendation of IS-3043. For test pits, electrodes shall be heavyduty type (Class C) GI pipe of suitable diameter with perforations. Electrodes
installed in the test pits shall have disconnecting facilities. For treated earth pits,
GI pipe shall be provided as per IS 3043 including charcoal, salt etc. Necessary
number of treated earth pits shall be provided for power transformer and for all
LT transformer Neutral & body earthing.
(iii) Earthing of Electrical equipment on cranes and travelling machines (as
applicable):
Every electrical equipment shall have double earthing.
A ring earthing system shall be provided within the crane / machine to which
electrical equipment shall be connected at least at two places. The earth ring on
REV. NO.: R3
Each end of each gantry rail shall be bonded to the plant earthing system. In
addition, intermediate earthing bond shall also be provided on the rails at every
60 m in case of longer tracks. Flexible copper bonds shall be provided across
any gap in the running gantry rails.
For mobile equipment with flexible cables, one separate copper conductor of
adequate size shall be provided for earthing.
(iv) Equipment Earthing Leads
The size of the earthing leads shall be decided based on the type of equipment
and structure to be earthed and shall be provided generally as per IS-3043 and
also with a view to minimize the number of sizes.
(v) Conductors for lightning protection system
The size of conductors for lightning protection system shall be decided based
on mechanical strength.
IS-3043
(b)
IEEE-80
(c)
to electrical
Inspector/CEA for his approval. All necessary fees for obtaining such approvals
shall be borne by the contractor. Necessary modification wherever required shall
be carried out by the Contractor and got approved by the Inspector at no extra
cost to the Purchaser. After installation the resistance of the ground grid shall be
tested in presence of Purchaser/Consultant as per the IE rules. After the test,
report shall be submitted to Electrical Inspector/CEA for approval. The
submission of Earthing layout, drawings and obtaining Electrical Inspectorates
final clearances & approval shall be within the responsibility of the Contractor. If
the resistance is observed to be not less than 0.5 ohm, the Contractor shall drive
additional earth pits such that resistance is less than 0.5 ohm.
REV. NO.: R3
4.2.14.4 General
Metallic frames of all current carrying equipment, supporting structures
adjacent to current carrying conductors, structures, lightning protection system
conductors and neutral points of various systems shall be connected to a single
earthing system. Two earthing leads shall be used if rated voltage of equipment
is above 250V. If the rated voltage is 250V or below, one earth lead shall be
provided. Metallic structures adjacent to electrical equipment shall be earthed
by one earthing lead.
Earthing conductors in outdoor areas shall be installed at a minimum depth of
600 mm.
All cable trays in the plant buildings as well as inside the trenches shall be
connected to earth grid at an interval of about 10 m.
Each RCC / Steel column of the building shall be interconnected to the floor
earthing grid in the ground floor.
Cable trays, steel pipes / conduits, steel columns, etc. shall not be used as earth
continuity conductors.
Instrumentation system and computer system shall be provided with a dedicated
earthing system suitable for the equipment.
Earthing grids of all the buildings, outdoor yards shall be interconnected to
form a single grid for the plant.
REV. NO.: R3
Earthing grid design shall be done in such a manner that the grid resistance is
less than 0.5 ohm.
4.2.14.6 Earthing System Installation
The spacing between two electrodes shall be at least equivalent to twice the
length of the electrode.
Earthing conductor running exposed on column, walls, etc., shall be supported
by suitable cleating, at intervals of 750 mm.
The earthing conductor crossing the road / track shall be laid in hume pipe or
laid at a greater depth to avoid damage.
When earth conductor passes through floors, walls, etc., suitable pipe sleeves
shall be provided and the same shall sealed after installation.
The connection between earthing pads / terminal to the earth grid shall be
made short and direct and shall be free from kinks & splices.
Metallic conduits, and pipes shall not be used as earth continuity conductor.
Flood light poles & towers, their junction boxes shall be connected to the
earthing conductor to be run along with supply cable.
For rust protection, the welds shall be treated with zinc chromate
REV. NO.: R3
given in IS-2309 and any building whose risk index is more than 40 shall be
provided with lightning protection.
4.2.14.9 Lightning Protection System Layout
The lightning systems design and installation shall generally comply with IS:
2309 code of practice for the protection of building and allied structure against
lightning.
Each down conductor shall be connected to a rod electrode, which in turn shall
be connected to the station earthing system through test links.
4.2.14.10 Lightning Protection System Installation
Conductors of lightning protection system shall not be connected with
conductors of safety earthing system above ground level.
The down conductors shall be welded to steel structures at 1000 mm interval or
cleated to wall at 750 mm interval. Wherever welded, the weld locations shall
be treated to provide rust protection.Each down conductor is connected to main
earth grid through a test pit.
Each down conductor shall be provided with a test link at a height of about
1000mm above ground level.
All the metallic structures within a vicinity of 2000 mm shall be connected to
the lightning protection conductors.
The minimum sizes of equipment earthing leads given below are typical and
shall be as per IS 3043
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
Sl.no.
Type of Equipment
Size (MM)
Material
No. of
Leads
RISERS
70 X 10
GALVANISED MS FLAT
N.A.
RUNWAY
70 X 10
GALVANISED MS FLAT
N.A.
70 X10
GALVANISED MS FLAT
TWO
CONDUCTOR/ MAIN
EARTH LEAD ALONG
COLUMNS
3
SYSTEM NEUTRALS
70 X 10
GALVANISED MS FLAT
TWO
415 V DISTRIBUTION
70 X 10
GALVANISED MS FLAT
ONE FOR
BOARDS
EACH
SECTION
6
FUSE DISTRIBUTION
50 X 8
GALVANISED MS FLAT
TWO
BOARDS
7
HT MOTORS
70 X 10
GALVANISED MS FLAT
TWO
415 V MOTORS :
65 X 10
GALVANISED MS FLAT
TWO
25 X 6
GALVANISED MS FLAT
TWO
ABOVE 55kW
9
415 V MOTORS : 22
TO 55kW
10
415 V MOTORS : 1
25 X 3
GALVANISED MS FLAT
TWO
11
FRACTIONAL HP
8 SWG
G S WIRE
TWO
25 X 6
GALVANISED MS FLAT
TWO
8 SWG
G S WIRE
TWO
70 X 10
GALVANISED MS FLAT
TWO
TO 22kW
MOTORS
12
CONTROL PANEL,
CONTROL DESK,
WELDING
RECEPTACLES
13
PUSH BUTTON
STATION &
JUNCTION BOX
14
CABLE TRAYS,
COLUMNS &
STRUCTURES
15
BUS DUCT
ENCLOSURES
REV. NO.: R3
No. of
Sl.no.
Type of Equipment
Size (MM)
Material
(i)
70 X 10
GALVANISED MS FLAT
TWO
70 X 10
GALVANISED MS FLAT
TWO
25 x 6
GALVANISED MS FLAT
TWO
70 X 10
GALVANISED MS FLAT
TWO
70 X 10
GALVANISED MS FLAT
TWO
Leads
DUCT
(ii)
SEGREGATED PHASE/
NON SEGREGATED
PHASE BUS DUCT
16
17
TRANSFORMER
TANKS/ RADIATORS
TRANSFORMER
NEUTRAL
18
LIGHTING
EQUIPMENT
(i)
50 X 8
GALVANISED MS FLAT
TWO
(ii)
WELDING SOCKETS
50 X 6
GALVANISED MS FLAT
TWO
(iii)
LIGHTING POLES
25 X 3
GALVANISED MS FLAT
TWO
(iv)
12 SWG
G S WIRE
TWO
Materials
Above ground
Below ground
: MS.
4.2.15
Equipment
Indoor control panels provided for control of miscellaneous systems in the plant
viz., air conditioning, evaporative air cooling, etc. shall comply with the
requirements outlined under technical requirements below.
All the meters provided on the panel shall be min. 96 sq.mm with an accuracy
class of 0.5. All meters shall be digital type.
For motor circuits, ammeters shall have a suppressed extended scale to indicate
the motor starting current.
The facia annunciation windows if provided on the panel, shall conform to
requirements outlined under instrumentation and control section.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
The required 240V, 1 phase AC supply required for panel illumination and
receptacle and space heaing shall be derived in the control panel itself.
Technical Requirements
S.N.
1
Description
Requirements
Location
Indoor/Outdoor
depending
on
location
2
Type of mounting
Wall/Floor
Cable entry
Top/bottom
depending
on
layout
4
Dark
no.632
admiralty
(epoxy)
Grey
as
shade
per
IS-
5/Glossy white.
5
Supply voltage
Space
heater,
voltage
7
provided for bi-directional motors (LT motors)& only stop push button for all HT
motors as per scheme requirement.
The degree of protection of LPBs shall be IP65 with canopy for outdoor and IP54
for indoor applications.
REV. NO.: R3
All PBs shall be push to actuate type and the stop PB shall be lockable in off
position as per the scheme requirement.
All push buttons shall be provided with 2 nos. NO and 2 nos. NC contacts for
various interlocking purposes. One contact of stop PB shall be directly wired to
the switchgear module for direct tripping and another contact to control system.
Terminals to be suitable for 2 cores of 2.5 sq mm conductors with 20% spare
terminals.
All LPBs shall be of Poly Carbonate material.
Junction Boxes (JBs)
The JBs used in outdoor areas shall have DOP of IP 65 with canopy and
weatherproof type. Sheet steel thickness of JBs shall be minimum 2.0 mmand
hot dip galvanized.
Junction boxes/marshalling boxes (JBs/MB) shall be provided to enable running
a large core cables from (JB/MB) to control panels, terminal cabinets, etc.
All JBs, shall be of polycarbonate material.
Danger boards shall be provided in line with the statutory requirements.
Rubber mats shall be provided to meet the safety and other statutory
requirements.
Welding Sockets
Industrial type 63A and 100A (welding purpose) sockets shall be provided in
sufficient number to facilitate extension of power supply to various machine
tools, welding sets etc.,
Welding switch socket outlets shall be provided at every 60m distance. Generally
the socket outlets shall be provided in such a manner so that using 30m flexible
cable with welding set, total plant area can be covered. For conveyor area (as
applicable), the welding socket outlets are to be located on either side of the
conveyor.
Testing
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
b.
4.3
I&C system will consist of all local instruments Viz. Pressure Gauge, Temperature
Gauge, limit switch, Pull cord switch, Belt Sway switch, Electronic Zero speed /
Under speed switch, Bunker level switch/ indicator, other field sensors, Local
panel & push button station, CHP control room equipment, as required erection
hardware & interconnecting cables required for the control & monitoring of the
entire Coal handling Plant along with control of Wagon Tippler & StackerReclaimer as turnkey basis. A PLC based control system shall be provided for
operation, control, interlocking, tripping of the entire coal handling plant and all
associated equipment whenever required under specified abnormal conditions.
All 3.3 KV drives shall be provided with fluid coupling temperature/ bearing
Temperatures measurement & shall be measured with Duplex RTD. Redundant
Temperature Measurement sensor shall be provided for all bearing temperature
PLC system shall be redundant with respect to Power Supply, Processor and
Communication bus. Redundant Input card shall be used for measurement of
Critical points related to protection of the equipment. All output commands to
MCC/ SWGR shall be provided through interposing relay and output redundancy
commands for critical drives. The control panel shall be minimum IP 55
protection class.
All alarms shall be generated in the solid state/PLC system and system shall be
connected with 24 TFT for alarm & other display. The control system shall have
hooter with required hardware and driven from PLC output. Test, Accept and
Reset Push Button shall be connected to the PLC system and programmed for
alarm annunciator.
REV. NO.: R3
A modular control desk of approved quality. HMI with 24 TFT monitor editable
programming software with latest configuration hardware and quantities as per
PLC configuration.
Interfacing with Plant DCS
Bidder shall provide interface requirements with plant DCS as per architecture
drawing. CHP PLC shall be linked with plant DCS, wagon tippler, stacker cum
reclamier,
etc.
through
bidirectional
redundant
TCP/IP
fast
Ethernet
in bidders scope. Bidder shall co-ordinate with the DCS vendor in achieving the
interface successfully & complete. A typical PLC based control system
configuration block diagram for Coal Handling Plant is provided for reference,
DRG No: E072-03-CHP-I-03-08-1.
prolonged period of time and shall perform accurately and safely under the
environmental & operating conditions described in the specification.
ii. All equipment, and accessories furnished under the specification shall be
from the latest proven control and instrumentation product range of
iv. Each item included in this specification shall be inspected and tested by the
Bidder in his works for full compliance with specification requirements,
completeness, proper assembly, satisfactory operation, cleanliness and state
of physical condition as applicable.
v. Full details regarding all equipment and systems including complete Bill of
Materials, drawings, data, information, technical literature and other details
required to fully establish the capability and performance of the equipment
and systems offered shall be provided as a part of the contract.
REV. NO.: R3
vi. To ensure smooth and optimal maintenance, easy interchange ability and
efficient spare parts management of various C&I items, it shall be ensured
that each C&I item is of same make, series and from same family of hardware
( as far as practicable).
vii. All plants and equipment which needs regular operation and monitoring shall
be provided with remote operation/ monitoring facilities, at respective
control rooms/centers. Automatic control facilities to be incorporated
wherever applicable.
REV. NO.: R3
e) General requirements and tests for printed wiring boards - IS-7405 (PartI)/1973.
Instrument Switches and Contacts
a) Contact Rating
b) Contact Rating
Enclosures
a) Types of enclosures - NEMA Standard ICS-6-110.15 through 110.22 (Type 4
to 13).
1972).
Apparatus, Enclosures and Installation Practices in Hazardous Area
a) Classification of hazardous area - NEMA Article 500, Volume-6, 1978.
b) Electrical Instruments in hazardous dust locations - ISA-RP 12.11.
c) Intrinsically safe apparatus - NFPA Article 493 Volume-4 1978.
d) Purged and pressurized enclosure for electrical equipment in hazardous
location - NFPA Article 496 Volume-4, 1978.
Annunciator
a) Specifications and guides for the use of general purpose annunciator - ISA PR
18.1.
b) Surge withstand capability tests - ANSI C37.90 a - 1971 and IEEE Standard
472-1974.
Interlocks, Protections
a) Relays and relay system associated with electric power apparatus - IEEE
Standards 3.13.
b) Surge withstands capability tests - ANSI C37.90 a - 1971 and IEEE Standard
472-1974.
c) General requirements and tests for switching devices for control and
auxiliary circuits including contactor relays - IS-6875 (Part-I)/1973.
Instrument Tubing
a) Seamless Carbon Steel Pipe - ASTM-A-106.
b) Material for socket welds fittings - ASTM-A-105.
c) Dimensions of fittings - ANSI-B16.11.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
e) Standard specification for tinned soft or annealed copper wire for electrical
purpose - ASTM B33.
Cable Trays, Conduits
a) Guide for the design and installation of cable system in power generating
station (cable trays, support systems and conduits) IEEE Standard 422, NEMA
VE-1, NEC-1981.
b) Guide for the design and installation of cable system in power generating
station (cable trays, support systems and conduits) IEEE Standard 422, NEMA
VE-1, and NEC-1981. Test Standards NEMA VE-1-1979.
c) Galvanizing of carbon steel cable trays - ASTM A-386.
instrumentation
system/
Bidder in his scope of supply. Bidder shall prepare and implement all required
control loops, interlock & protection logics to make the entire system complete
for the satisfactory operation & control of the entire system. Bidder shall furnish
all control loops along with write-up, Interlock and protection logic diagrams
along with write-up, operation & control philosophy, Analog / digital monitoring
points, lists etc. for the entire Coal handling Plant.
The operation and control of entire coal handling plant including Wagon
unloading, conveyer, tippler, stacker-reclaimer etc. shall be performed from its
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
own dedicated PLC located in CHP & respective control room in a completely
integrated manner. This shall include following as minimum:
i)
24 TFT monitor, printers and time synchronisation facility with plant GPS
master clock ( time format shall be as per GPS master clock requirement).
j)
Three nos. 24 TFT operator work station, one no. 24 TFT operator work
station cum engineering work station, Two nos. industrial grade 52 thin
bezel LCD display unit, one no. A4 size (B/W), one no. A3 colour medium
speed laser and one no. high speed (180 columns) dot matrix printer
shall be provided in CHP control room. For more details regarding
number of HMI, Printers, LCD display units and others bidder shall refer
CHP PLC configuration diagram E072-03-CHP-1-03-08-R1.
k)
l)
Emergency Trip push button for HT drives & for all Electrical power
breakers mounted on auxiliary console/ panel.
m)
Bidder shall provide necessary modular control desk and standard make
furniture for installation of operator station / engineering station in the
control room, shall be subject to approval by Owner.
n)
Bidder shall also co-ordinate with Main Plant DCS supplier for achieving
o)
suitable interface between Coal Handling Plant PLC and Main Plant DCS.
Few hardwired signals exchange between CHP PLC and Main Plant DCS
provision has to be made.
p)
Local control panels for coal sampler, Belt weigher, ILMS, Dust
suppression, Dust extraction, ventilation system, etc. shall be provided.
One no. 24 TFT operator work station and one no. 24 TFT operator work
station cum engineering work station and one no. A4 size (B/W printer shall be
provided
for
each
stacker
cum
reclaimer
control
room.
Bidirectional
communication shall be provided between stacker cum reclaimer PLC and CHP
control System. For more details regarding number of HMI, Printers, LCD display
units and others bidder shall refer CHP PLC configuration diagram E072-03CHP-1-03-08-R1.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
One no. 24 TFT operator work station and one no. 24 TFT operator work
station cum engineering work station and one no. A3 colour medium speed laser
and one no. high speed (180 columns) dot matrix printer shall be provided for
number of HMI, Printers, LCD display units and others bidder shall refer CHP PLC
configuration diagram E072-03-CHP-1-03-08-R1.
All junction boxes, local push button stations, all Interconnected cabling
between sensors to JB/ Panel, Panel to I/O card, card to PLC system operator
racks, impulse/ air supply pipes/ tubes, erection hardware, instrument isolation
valves, instrument fittings (double compression type) and other accessories
within battery limits.
All field instruments/ sensors/ switches/ belt protection switches, final control
elements with actuators as per finalised P&IDs, schemes, operation and control
philosophy and logics approved during detailed engineering stage within the
coal handling plant package.
Vibration monitoring system for HT drives as recommended by package vendor
and same shall be located in the CHP control room and interfaces with CHP PLC.
The vibration monitoring system shall include the Vibration Probes (Proximity/
REV. NO.: R3
Any other item not covered herein but essential for successful installation and
commissioning of the coal handling plant and integrity of the system shall be
included by the Bidder.
All necessary Vendor/Drawing/documents shall be subject to approval from
Owner.
Logic
controller shall be provided with adequate and reliable protection safeguard for
various equipment and to assist the operator for easy safe and efficient starting
and stopping of various drives in the process. The system shall be designed by
selecting high-grade components of proven quality and proper design of system
electronics. The system shall be able to operate satisfactorily with reference to
the specified environmental conditions as indicated in the specification. The
REV. NO.: R3
The system shall have extensive self-diagnostic hardware and software features
for easy and fast maintenance of the PLC. Safety barriers shall be provided for
intrinsically safe input / output circuits.
The PLC shall have very high noise immunity in order to ensure safe and reliable
a) PLC shall be provided with 10% hard wired spares (up to terminal block), 10%
I/O free channels and expandable 20% free slots for future.
b) The system shall be capable of handling the long-term storage of data for 90
days and retrieval.
c) The system shall be provided with programming and diagnostic facility, while
in operation also.
d) Each processor shall not be loaded not more than 60% including spare I/Os.
4.3.4.2
REV. NO.: R3
DC. Each module shall have LED for each I/O channel to indicate the status of
each input / output. Redundancy in I/O level shall be maintained for critical
services.
PLC inputs shall be provided with potential free dry contacts. All the inputs shall
be double ended i.e., two wires per input and not common return for all inputs.
The contact interrogation voltage for input contacts shall be 24V DC minimum.
Each input channel shall be protected by separate fuse.
Output contacts from the PLC shall be potential free dry contacts. Each output
shall be short-circuit proof and protected by fuse.
Visual indication of fuse blown must be provided for each input and output
channel and should be alarmed.
4.3.4.3
Processor subsystem
The processor sub system shall include CPU, memory, power supply,
communication interface etc.
Dedicated PLC processor shall be envisaged for each Auxiliary plant. The
processor shall have capability to implement all the control functions required.
The processor shall have sufficient memory for storage of the program
instructions as applicable to the logic requirements. CPU shall be of 32/64 bit or
REV. NO.: R3
than 50 m/s or better) and shall not result any process or system upset.
In case of failure of complete processor system i.e., both processors, outputs
shall take fail safe state automatically.
defined as the cycle time taken by the system to read input, process input
executing logic and update control output for all the logics configured within the
system.
peripherals, or any other activity which consume processor time shall also be
accounted while computing scan time.
4.3.4.4
Communication subsystem
The redundant communication subsystem shall provide reliable and high speed
data transfer between the processor subsystem, I/O subsystem, PLC cubicles,
PLC and operator work station and other devices connected to the system.
Redundancy in communication subsystem shall be provided, such that on the
failure of the active device, communication link or bus, the redundant device
Information about the failed device shall be displayed locally as well as on the
PLC console. It shall be possible to manually switch-over the communication
from main bus device to redundant bus device without interrupting the PLC
functions.
Design Requirements
a)
REV. NO.: R3
The PLC based automation system shall be capable of acquiring the status
of equipment, acquiring the analog and digital signals, displaying of
status in the form of mimic diagram, video trend, bar graph, bar chart,
over view, group over view, loop overview, alarm overview display,
Process control and monitoring for each PLC based system listed earlier
shall be envisaged through operators station, keyboard and mouse.
However, direct local switching of individual drives and actuators shall be
possible for maintenance purpose with the necessary basic protection
d)
incorporated.
e)
checks
before
Command
initiation.
Also
programme
The PLC system shall be designed for fully automatic operation of the
entire system in both auto and manual operation.
Complete
control
of
system
operations
with
protection,
controls.
3.
4.
REV. NO.: R3
4.3.4.5
PLC Console
PLC Console shall be provided as operator Interface station for control and
monitoring of the plant. This shall be done through dynamic mimic displays and
control displays.
The PLC console shall also be used for program storage, display, fault diagnostic
and alarm monitoring.
Each console unit shall have latest configured CPU with 24 TFT monitor, bulk
memory, DVD read/write disk drive, keyboard and mouse.
PLC Console shall consist of color TFT monitor of 24 size, mouse, the
programming keyboard, operating keyboard and laser printer. The TFT Monitor
and Laser printer shall meet the specification requirement indicated in the
specification.
Isolation shall be provided between programming terminal and related
REV. NO.: R3
display and print alarms. System shall have all alarm related functional keys like
acknowledge, reset etc. Other design features like set point / dead band
adjustment,
alarm
priority,
manual
and
automatic
inhibition
based
on
predefined logic etc. shall be provided, which shall be as finalised during detail
engineering.
The alarm display shall be built bottom up with the most recent alarm at the top
of the list. When a point returns to normal, the associated alarm line shall
change colour suitably and on acknowledgement, the line shall be blanked out.
The alarms below the blank lines shall move upward to fill the empty lines. If
the capacity of the monitor display page is exceeded, alarm history shall be
stored in memory to accept the over- flow. This alarm history shall be displayed
upon operator demand. The format and details of alarm displays shall be
finalised during detail engineering.
When a point goes into an alarm state and appears on the alarm screen, the time
of alarm shall flash until acknowledged by the operator. Acknowledgement by
the operator shall cause the time to stop flashing. All alarm initiations and
return to normal, shall be logged on a printer.
4.3.4.6
System Software
The system software shall include all programs for the PLC and PLC console
which are required to perform all the PLC functions including communication
and self-diagnostics.
Diagnostic software shall have the capability to provide information about the
REV. NO.: R3
hardware/machine in system at site. All licenses shall be valid for the continuous
service life of the plant.
All the software listings including source code for application software. All
specific to-project data files etc. shall be submitted by the bidder.
The bidder shall furnish a comprehensive list of all system /application software
documentation after finalisation for owner review and approval.
4.3.4.7
Peripherals
controller,
operation
interfacing
unit
with
keyboard,
mouse.
Operators stations shall be provided with graphic and mimic capabilities with
minimum 64 distinct colours. The graphic resolution shall be 1280 x 1024 dots
minimum with 0.25 mm dot pixel and refresh rate shall be 85 Hz or better.
Suitable optical filter for minimum secondary glare shall be provided.
The colour laser printer shall be automatic duplex printing type suitable for
printing both A4 and A3 size paper. Printing speed shall be minimum 6ppm for
colour and 24 ppm for black and white. The printer shall be heavy-duty type
with minimum 50,000 pages/month printing capability, 600 dpi resolution, 128
MB memory and 3000 sheet input capability.
Dot matrix type character printer 132/136 column with minimum speed 400 cps
shall be provided for printing operator requested functions and graphics. Paper
width and line spacing shall be selectable. Noise level shall not exceed 60 db at
a distance of one (1) metre from printer. Sound proof enclosure shall be
provided. Facility to lock or release the printers on demand shall be provided.
Automatic back up facility of printer functions shall be provided. The operator
shall be able to direct logs, reports etc. to any printer from any of the HMI
stations. Furniture for keeping the printer shall be provided. The printer shall
REV. NO.: R3
have self contained test and diagnosis to aid in trouble shooting. The interface
shall be either RS232C or RS422A or any other latest protocol.
4.3.4.8
manufacturer and as felt necessary for safe and smooth running of the process
and equipment offered.
The System Control Panels shall house the controls for the plant including
tripping and status indications. Interlock and protection logics for equipment
and process shall also be provided at the panel. The panel shall accommodate
indicators, annunciators, push buttons, selector switches, indicating lamps,
control switches, auxiliary relays, contactors, PLC etc as required. The location
and design of panel shall be subject to Owners approval.
Bidder shall refer the typical configuration of the PLC systems of Coal Handling
Plant
4.3.4.9
Some important ON/OFF status and trip signals from different equipment of
Coal Handling Plant shall be connected to plant DCS. Bidder will supply, lay and
terminate all the required cables up to DCS marshalling panel. The termination
of signal at one end of DCS marshalling panel will be under bidders scope.
long life shall be provided. Voltage regulation shall be within 1%. All the
necessary chargers, inverters, isolation transformers, surge protection devices
shall be provided. For CPU / I/O cards power supply shall be derived from UPS
by providing redundant 240V UPS AC/DC 24 V DC convertor for each cubicle.
REV. NO.: R3
4.3.5.1
Pressure Transmitter
provided.
(b) The Drive protection trip due to pressure shall be derived from LVM of
transmitter signal and not through switches.
Specification:
Micro-processor based indicating type (LCD display), rack mounted with
accuracy of 0.1% of span, external zero and span adjustment. Repeatability:
0.05% of FSR or better. Linearity: 0.1% of FSR or better. Hysteresis: 0.1% of
FSR or better. Self diagnostics, temperature sensor for compensation. Powers
and
chemical
diaphragm with 15 m PVC covered SS armored capillary for corrosive and oil
services, 3 way manifold & name plate, etc. Material for accessories will be SS.
Remote communication with field communicator/ control system. HART protocol
output shall be available in each transmitter.
4.3.5.2
Wherever indicating type transmitters are provided, local indicators shall not
be provided.
Specification
Microprocessor based indicating type (LCD display), rack mounted with accuracy
epoxy coating, haste alloy sensing element. Accessories like snubbers for pump
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
4.3.5.3
Flow Transmitters
4.3.5.4
Level Transmitter
continuous
remote monitoring and/or control of level are envisaged. The transmitter shall
provide suitable 4-20mA dc output signal for control and indication/recording.
The instrument will be displacer type for tanks normally under vacuum. For all
other tanks the instrument will be differential pressure type.
4.3.5.5
Temperature Indicators
(b)
(c)
(d)
(e)
Thermometersshall be Indicating type, field mounted, filled system with ten (10)
metres SS capillary with SS armour and six (6) inch dial (white dial with black
REV. NO.: R3
calibration, linear calibration over the range and SS bulb with 316
4.3.5.6
Thermowells
plugging with chain, etc. shall be provided. Material of accessories will be SS.
Thermowell shall be hex head of bar stock assembly. In case flanged wells are
required for any specific application, the same shall be supplied as required. The
thermowell construction shall meet the ANSI 19.3-1994 (latest) requirements.
4.3.5.7
Temperature Elements
All temperature elements shall be supplied with associated junction box with IP
65 protection class.
4.3.5.8
Duplex PT-100 type with accuracy of 0.5% of span, response time 1-2
seconds; Spring loaded mineral insulated three (3) wire RTD assembly housed in
aluminium
enclosure.
REV. NO.: R3
4.3.5.9
Pressure switches
applications
corrosive
and oil
discharge
services, name
plate & mounting brackets. Material of accessories will be SS. Auto reset micro
switch with internal adjustment for set values with 2 SPDT contacts rated for 0.2
A at 220 V DC. IP 65 or equivalent degree of protection for enclosure. Over
range protection 50% above maximum pressure.
provided.
accessories
REV. NO.: R3
&mounting brackets, etc. Material of accessories will be SS. Auto reset micro
switch with tamper proof external adjustable set values with 2 SPDT contacts
rated for 0.2 A at 220 V DC. IP 65 or equivalent degree of protection. Over range
The instrument shall be external float type with SW connection with isolation
facility for surface mounted tanks and top mounted with still pipe for all sumps.
Still pipes will be provided with adequate supports.
Specification
Float or Displacer type with dual process connections. an accuracy of 1% of
span with
external adjustable set values with 2 SPDT contacts rated for 0.2 A at 220 V DC.
IP 65 or equivalent degree of protection. Repeatability shall be 0.5% FSR.
(b)
(c)
(d)
(e)
engineering.
Specification
Direct reading, pipe mounted Pressure gauges of aluminium casing (epoxy
coated) with 4 1/2 inch / 6 inch phenolic dial (white dial with black numerals),
316 SS Bourdon tube, AISI 304 movements and micrometer type adjustable
aluminium pointer, an accuracy of 0.5% of span including accessories like
siphons for
chemical diaphragm for corrosive and oil services and name plate, etc. Material
REV. NO.: R3
Suitable
platforms
shall
be
provided
for
purpose
of
taking
Specification
Tubular type level gauges for low-pressure up to 7 kg/cm2 & reflex type for
high-pressure water & steam services & vacuum services with automatic ball
check
valves, illuminator (240 AC) Pyrex/ borosilicate glass, mica shield, brass
guard rods & brass holders. Material of accessories (name plate, etc.) will be SS.
Tubular glass OD will be 5/8. Vent & drain valves shall be provided. Connection
shall be screwed or flanged (ANSI class 150 RF).
REV. NO.: R3
Type of
Description
No.
I/O
No of I/O
a.
Start Command
DO
b.
Stop Command
DO
c.
ON Feedback
DI
d.
OFF Feedback
DI
e.
DI
DI
DI
g.
Switchgear
Available
(breaker
in
service
RTD
i.
RTD
j.
RTD
k.
AI
2.
a.
Start Command
DO
b.
Stop Command
DO
c.
ON Feedback
DI
d.
OFF Feedback
DI
e.
Swgr/MCC
relay
DI
DI
Disturbance
(Overload
f.
remote)
3.
a.
Open Command
DO
b.
Close Command
DO
c.
DI
REV. NO.: R3
Sl.
Type of
Description
No.
I/O
No of I/O
d.
DI
e.
DI
f.
DI
g.
DI
h.
AI
a.
Open Command
DO
b.
Close Command
DO
c.
Swgr/MCC
DI
DI
PLC.)
Disturbance
(Overload
relay
e.
DI
f.
DI
g.
DI
h.
DI
i.
AI
REV. NO.: R3
Door shall be screwed at all four corners. Door handle shall be self-locking
with common key. Door gasket shall be of synthetic rubber.
Suitable for mounting on walls, columns, structures etc. The brackets, bolts,
nuts, screws, glands and lugs required for erection shall be of brass, included
in C&I Vendors scope of supply.
Terminals shall be rail mounted cage-clamp type suitable for conductor size
up to 2.5 mm2. An M6 earthing stud shall be provided.
Enclosure shall be minimum IP: 55 or better for all applications except CHP.
For CHP application the protection class shall be IP 65 minimum.
4.3.10
Installation / Erection
The Vendor shall get prior approval as per approved quality assurance plan of
the Owner / Consultant before any installation work starts.
Impulse / sample piping, air supply and pneumatic tubing, cable trays and
equipment shall be supported rigid enough to prevent vibration and anchored
sufficiently to prevent strains on equipment installed.
Supporting clamps
shall be provided at least at every one metre distance for better rigidity.
Argon arc
REV. NO.: R3
All the panels, desk, cabinets supplied by the Vendor shall be bolted to the
floor channel.
Testing requirements
The calibration
equipment shall cover complete range and shall have the desired accuracy of
not less than 0.1%.
from National Physical Laboratory (NPL) or IDEMI for the duration of Contract
Period.
The Vendor shall follow the standard procedures for calibration of various
instruments and as set by the manufacturer of instruments and as instructed
by the Owner including any requirements of field calibration.
First, the
calibrations shall be carried out independently by the Vendor and later in the
presence of Owner who shall certify the same. Proper documentation in this
regard shall be maintained and handed over to the Owner.
All the instruments shall be calibrated for the entire range of the instrument
for which it is designed. Calibration shall include test for repeatability.
All switches shall be tested for the actuation of both normally open and
normally closed contacts at the desired set points and also for the fixed /
differential settings.
All the float operated level switches shall be tested for the movement of the
float and linkages to make to break the switch contacts by filling up with
water before installation. For such tests, necessary testing set up required
shall be arranged by the Vendor.
Air leak tests shall be performed on all impulse lines, air supply and
pneumatic
lines.
Necessary
equipment
such as
portable
compressor,
connecting pipes, materials, cables and test gauges shall be provided by the
vendor.
For all electrical actuators of the valves, functioning, setting and performance
of limit switches / torque switches of various positions shall be checked
before and after installation of the actuators. The position transmitters for
inching applications shall also be calibrated.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
Commissioning requirements
Prior to taking the instruments in service, all impulse lines, sampling lines and
air supply lines shall be blown as required with the establishment of adequate
line pressure and temperature conditions to keep the lines thoroughly clean.
On-line i.e., without removing control valves from the pipe calibration of the
positioners and stroking of control valves / control dampers shall be carried
out as required during control system tuning.
After delivery of the equipment, the Vendor shall locate all the equipment
including electronic cards in final position, check all the power wiring,
grounding and interconnection cables, all in accordance with manufacturers
recommendations. The Vendor shall perform initialisation of system power, field
loading of system configuration / software and data base, demonstration of
system functionality to verify conformance with manufacturers instructions and
specifications, tuning of control loops, implementation of any configuration
changes including hardware, software and additional tappings / instruments,
cabinets as required and providing general trouble shooting and final solutions
to application and / or instrument problems.
Training
Further
to
relevant
clauses
regarding
training
specified
elseware,
The
Operator training
4.4
CIVIL
4.4.1 General
The works to be performed under this specification include execution of
complete civil, architectural and structural works for foundations for equipment,
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
drawings & design reports and getting the same approved by owner/ consultant
including
all
necessary
survey,
tests,
studies,
investigations
including
Site
screens.
Bulldozer Shed.
All main roads in CHP area and approach roads connecting all
facilities in the Coal Handling package to the nearest main roads,
including drains and culverts wherever required.
REV. NO.: R3
Garland Drains, Decantation tanks, Coal pile run off pond, Coal
sampling room andOffice Complex for O & M staff for CHP
For detailed civil work specifications, Part C of this document shall be referred.
This specification covers the methodology to be followed for design and
construction of all civil, structural and architectural works for the complete Coal
handling system. Description of various items of work and nature of work
involved under this specification are given hereinafter. The items, though not
specifically mentioned, but are needed to make the system complete shall be
treated as though included and the same shall also be furnished and erected /
constructed unless otherwise specifically mentioned as excluded.
The work shall be carried out according to the design/ drawings to be developed
by the Contractor and approved by the Owner/Engineer. For all buildings,
facilities, systems, structures, etc., necessary layout and details are to be
of
Government
department
as
per
the
directions
of
the
REV. NO.: R3
The Contractor shall be solely responsible for the correctness of the layout and
levels and shall provide necessary instruments, materials, access to works, etc.,
to the Owner/Engineer for general checking of the correctness of the civil works.
All the quality standards, tolerances, welding standards and other technical
requirements shall be strictly adhered to.
The Contractor shall inspect the site, examine and obtain all information and
data required and fully appraise himself of the prevailing conditions at the
proposed site, access to site, communications, transport, right of way,
availability of local labour, materials and their rates, local working conditions
climatic conditions including monsoon pattern, soil conditions, local conditions
and site specific parameters and shall include for all such conditions and
contingent measures in the bid, including those which may not have been
specifically brought out in the specifications.
In case of any conflict between stipulations in various portions of the
specification, most stringent stipulation would be applicable for implementation
by the Contractor without any extra cost to the Owner/Engineer.
4.4.1.1
Construction Water
The Construction water will be arranged by the owner free of cost at ground
level reservoir
within the plant area. Arrangements for drawing the water from
ground level reservoir and distribution of pipe line network for various locations
Statutory Requirement
Contractor shall comply with all the applicable statutory rules pertaining to
Factory act, Fire safety rule of Loss prevention association, Water act for
Pollution control, Explosives act etc.
according to Factories act shall also be complied with. Statutory clearances shall
be obtained and norms of State Pollution Control Board shall be followed.
Statutory body /Act requirements shall be fulfilled by the CONTRACTOR and in
case any modifications /additions to the building /Structures are to be made as
per the above, shall be carried out by the Contractor at no extra cost to the
owner.
REV. NO.: R3
4.4.1.3
Submissions
documents shall be made using MS office. Contractor shall submit two sets of
soft copies of all documents and drawings on CDs along with requisite sets of
hard copies of the same.
The documents and drawings as listed below are to be submitted for the
approval of the Owner/Engineer unless specified otherwise. The list given below
is not exhaustive but indicative only.
i.
ii.
iii.
iv.
Project design intent document giving the basis of design, which shall
cover all the aspects, parameters, assumptions, references, structural
idealization/ mathematical model, loading cases, load combinations,
analysis and design for all buildings, facilities, systems and structures etc.
v.
REV. NO.: R3
vi.
Analysis,
design
calculations
and
drawings
for
pipe
supports,
trestles, pipe trenches, ducts, etc required to complete the scope of this
specification.
vii.
etc.,
architectural
facia
and
projections,
miscellaneous
decking, wall cladding, surface drains, rain water down comers, sanitary,
plumbing, etc.
viii.
ix.
Shop drawings/ fabrication drawings of all structural steel works (only for
reference) and design calculations for important joints/ connections.
x.
xi.
Marking
scheme
identifying
the
equipment
lay-down
areas,
with
xiii.
xiv.
xv.
Specifications, design & drawings for profiled roof metal deckings and
metal claddings.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
xvi.
xvii.
xviii. As built drawings with quantities of various items of work system wise,
building wise, structure wise, etc. duly certified by Site after execution of
work for information/ record.
xix.
The contractor has the option to use mild steel as per IS:2062 conforming
to IS:8500 for structural steel works in various buildings/ structures. He
shall submit detailed fabrication and welding procedure along with his
design/scheme drawings.
xx.
xxi.
Plinth level of the buildings in the coal handling plant, in general and crusher
house, junction towers/houses and MCC / control room in particular shall not be
kept less than 0.5 meter above the finished ground level, except specifically
mentioned otherwise.
4.4.2.2
Crusher houses
REV. NO.: R3
RCC,
supported
overstructuralsteelbeams.
level.
metalcladding
Above
shall
3m
be
level,
provided
permanentlycolourcoatednon-insulated
document.Adequately
asspecified
elsewhere
sized
in
this
windows
openingsand
RCCkerbwallof
kerbplatesshall
minimum
beprovidedaroundall
300mmshallbe
smallopenings.
providedalroundthefloor
with
handrails.
Flooring for crusher house shall be of RCC with non-metallic floor hardner
topping.
The crusher shall be on RCC deck supported on steel helical spring units and
viscous damper (vibration isolation system), which in turn shall be supported on
the independent RCC sub-structure isolated from building floors. Dynamic
analysis shall be done for the top deck together with the springs and dampers to
determine the natural frequencies and amplitudes of vibration. A mathematical
model of the top deck shall be formulated with three-dimensional beam / plate
finite element for the purpose of analysis with the springs idealized with vertical
and horizontal stiffness. The mass of the machine together with that of the top
plate shall be considered for the analysis. Single degree of freedom systems may
be used for evaluating the rigid body modes. Natural frequencies upto at least
20% above the operating frequencies shall be checked. Forced response dynamic
analysis shall be carried out for the unbalanced forces during operating
condition using sinusoidal forcing function. The vibration isolation system shall
be designed for at least 90% isolation efficiency. A ratio of at least 10 (ten) shall
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
be ensured between the stiffness of the supporting structure and the stiffness of
the spring system in each direction to achieve decoupling between the two (the
stiffness of the spring system being lower). This ensures that the supporting
structure is relatively Rigid with respect to the springs and the vibration
sized
for
serving
all
the
floors
shall
be
provided.
elevator
shaft
shallbeof
non-
be
of
brick
masonry.
RCCkerbwallof
minimum
300mmshallbe
arrangementsshallbeprovidedto
therainwaterthroughgalvanisedgutterofmatching/
andHDPEdowncomer pipes asperIS:4985.
4.4.2.3
let
approvedcolour
Junction houses
The junction towers which are supporting the coal conveying galleries to coal
bunkers shall accommodate mill reject silos within the junction towers&structure
REV. NO.: R3
shall be designed accordingly. Further, the sizing of the junction tower shall be
as per the space indicated in the Mechanical G.A.
4.4.2.4
1
Both
sidesof
thecentral
andsidewalkwaysshallbe
shall
be
of
skidarrangement
chequered
along
plate
construction
with
with
kerb
antiplates.
Floorsoftheconveyorgalleryshallbeprovidedwith
sealplatesifspecifiedinMechanical section.
3
cladding
shall
be
of
permanently
colour
coated
non-
insulatingmetalcladding.
Roofframingshallbegivenaslopeof1vertical:3horizontal. A continuous slot
opening in the side cladding of 300mm justbelowtheroofsheeting and
Fourleggedtrestlesshallbeprovidedata
spacingnot
exceeding
100m
All over ground and on ground conveyor gallery shall be of enclosed type
steel structure with two lattice girders having rigid jointed portal frame at
both ends. The lattice shall be braced together in plan at top and bottom
and roof truss shall be provided at regular interval. The gallery shall be
covered on sides and top with permanently colour coated metal sheeting
REV. NO.: R3
shall
be
treatedashingedandthe
otherendonrollers
for
the
purposeof analysis.
7
Transfer
tower
supporting
the
end
of
conveyor
gallery
shallbesomodeledthat,onlyverticalreactionistransferred
Thetopofpedestalforthefoundationsshallproject
functional
requirements
and
shall
provide
space
for
iii)
Steps shall be provided (rise not exceeding 130 mm) along the
REV. NO.: R3
v)
vi)
x)
Stackercumreclaimerrailshallbesupportedon
continuous
RCC
beam/
The entire coal storage area shall be provided with adequately sloped PCC
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
sized for carrying drainage from coal yard and surrounding areas to
theRCC decantation /settling tank with baffle walls and lead to the coal pile
runoff pond (earthen pond). Decantationtankshallbesized to store about
30 minutes peak runoff. Coal pile runoff pond capacity shall be sufficient
to store about 30 days discharge.
3
design
requirements.
Beyondthestockpileareauptojunctiontowers
oneitherside,foundationsfortrestlesandshortsupportsshall
also
be
(Consists of tippler platform, hopper, wagon tippler tunnel, wagon tippler shed,
WT control room, MCC room, side arm charger, power pack room etc.)
1
Steel gratings of mesh size 300 mm x 300 mm over wagon tippler hopper
shall be provided. The hopper and gratings shall be designed for
movement of front end loader/bulldozer over them. Bull-dozer weight
shall be considered. Wet coal column height of 1.5m shall also be
considered for grizzly design under separate load case over entire area of
grizzly.
The lowest level of grizzly shall be at finished floor level for easy removal
REV. NO.: R3
of boulders coming along with the coal. Openings in the wagon tippler
shed shall be provided in such a way that the front end loader can access
the entire area of the grizzly. The minimum height of opening shall be
6m above plinth level. Plinth level of the pit shall be kept at least 500 mm
above graded level with RCC sloped paving on the dozer entry side of
adequate width to enable bulldozer/front end loader movement.
6
RCC access shaft with staircase leading to the bottom of the pit shall be
provided. Minimum width of the staircase shall be 1200mm. To facilitate
equipment/ machinery handling, Monorail with hoist shall be provided in
the access shaft projecting through double-leaf steel sliding door.
The wagon tippler shed shall be covered with permanently colour coated
metal sheets supported on columns. These columns shall be designed as
free standing structure.
Wagon tippler shed floor level shall be kept equal to rail top level.
4.4.2.7
1
Tunnels (Cut and Cover type), Pent houses and Transfer Houses
with
non-
metallic
floor
hardner
shallbeprovided
sloping
angles
shallbeprovidedtolead
thedrainage/
seepage
keep the system dry & hassle-free. Sumps of suitable capacity shall be
provided in the transfer house also facilitating the effective drainage.
2
Wherever
tunnel
slope
exceeds
tunnelfloorshallbeprovidedwithPCCstepsto
operating
maintenance
caseofdoubleconveyor,suchstepsshall
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
12
degrees,
the
facilitate
movement
of
personnel.
In
the
beprovidedin
thecentre
PAGE 292 OF 506
also.
Tunnelshallbeprovidedwithwalkwayoneithersideofthe
conveyor.Handrailshallbe p ro v i de d o n b o th s id e s o f the w a l k w a ys
a s d e ta i l e d f o r c on v ey o r g a l l e r i es . Ho wev e r, the s in gle pi pe
han d ra il can be fixedtothetunnelwallto serveashandrail.
4
RCC
Penthouseshall
beprovided
at
the
l o ca t io n ,
tunnelentersthe
houseshallbeprovidedwithaliftingbeamtofacilitate
w h e re
th e
groundlevel.Pent
movement
of
similar
in
function
toajunctiontower,
meet
exceptthat
belowgroundlevel.
floors,
roof,
RCC
access
shaftwith
staircaseandmonorail
shaft
shall
be
provided
with
ramp
towards
the
door.
above
the
toidentifytheextentoftheundergroundstructure.
8
gradedground
4.4.2.8
Size and number of these buildings/ rooms shall be decided based on the
geographical location/arrangement of various components/facilities and their
electrical
load
requirementasmentionedintheElectricalportionofthisdocument.
REV. NO.: R3
These shall generally be of RCC framed structure with cable vault as per
electrical system requirements. Side cladding shall be of brick walls with
provision of minimum two doors of adequate size and windows of adequate
number and size for proper ventilation and lighting. The fire barrier wall, if
required in front of transformer shall be provided as per TAC / LPA regulations.
The control room building shall be complete with toilet, drainage, plumbing,
shall
be
provided
in
place
of
RCC
abovesunshade,faciashallbeavoidedtopreventaccumulationof
parapet.
Similarly,
dust.
Central
control desk area shall be provided with false ceiling suitable for air
conditioning.Coal yard office & electrical maintenance room shall be provided on
first floor with attached toilets & drinking water facilities. Provision for water tank
of suitable capacity shall also be made. Coal yard office shall be air conditioned.
All electrical buildings/control room shall have a clear head room of 3.50 m
(minimum) at all floors.
4.4.2.9
basedon system design and may consistof RCC reservoirs/tanks, pump houses
with pump foundations, fan rooms with fan foundations etc., spread over the
complete Coal handling area. Location and details of these structures will depend
on requirement based on system design.
4.4.2.10 Bulldozer shed with/ Auto repair shop
This shall be of steel framed structure with permanently colour coated metal
cladding sheeting, with a column free area for bulldozer movement in shed area.
The minimum area for this facility shall be 400sqm. The auto repair shop shall
have sides with colour coated metal cladding sheeting except for bottom three
meters of brick work.
steel glazed side hung windows. Doors shall be of flush welded steel for
REV. NO.: R3
Adequate provision for garland drains, roof drainage, dewatering sump, Plinth
protection etc shall also be made.
4.4.2.11 Emergency reclaim hopper/ Manual unloading hopper with shed
Hoppers shall be RCC construction. The pit shall accommodate the hoppers
along with feeders and conveyors below. The hopper pit shall be of RCC
construction and designed as water retaining structure. During construction,
proper provision shall be made to make the pit completely waterproof. Suitable
sump shall be provided in the pit to affect surface water drainage. RCC access
shaft shall be provided with staircase to the bottom of the pit. Monorail for
taking machinery into and out of the pit shall be provided in the access shaft
projecting through double leaf steel sliding door. Plinth level of the pit shall be
kept at least 500mm above graded level with RCC sloped paving all round to
enable bulldozer movement. Shed of minimum 6m height above hopper pit shall
be of structural steel construction. Two numbers of columns shall be raised at
the centre of the span on opposite sides of the pit and shall be designed as free
standing structure, to support double cantilever only by roof framing, to facilitate
dozer movement. These columns shall be encased with concrete as specified
elsewhere in this document to avoid direct impact to the columns by dozer
Side cladding
REV. NO.: R3
Necessary no. of pits of adequate size for servicing / repair of locomotives shall
be provided in the floor with suitable steps etc as may be required. Adequate
provision for dewatering sump, garland drains, roof drains, Plinth protection etc
shall also be made.
4.4.2.13 Coal sampling room & Coal office building
A coal sampling room shall be provided at a suitable location for preparation and
analysis of crushed coal samples. This shall be a two storied RCC framed building
with RCC roof and brick/solid concrete block masonry walls. Minimum size of the
building shall not be less than 20 x 20m, each in ground & first floor of the
building for keeping coal samples, coal crushing, weighing and other required
equipmentand also to accommodate O & M staff. One smaller enclosure shall be
provided in the building with masonry partition wall where ovens or other
required equipment shall be kept.
The rooms shall have working platforms of adequate width for keeping crushers
and other required equipment and performing routine activities. Adequately
sized shelves shall also be provided in the building. The floor shall be of heavy
duty concrete floor with granolithic finish and non-metallic hardner topping.
Adequate ventilation and natural lighting shall be provided with steel glazed side
hung windows. Doors shall be of flush welded steel for personnel movement. The
building shall be complete with drainage, plumbing, sanitary, plinth protection
shall
be
provided
in
place
of
RCC
parapet.
Similarly,
abovesunshade,faciashallbeavoidedtopreventaccumulationof dust.
4.4.2.14 Important Buildings and Systems
i.
ii.
iii.
iv.
v.
About 15 nos. of toilet blocks along with adequate size of soak pit /
septic tanks and water tanks and connections are to be provided in the
coal handling area. The location and size of the toilets blocks to be
decided during detail engineering.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
vi.
Any other civil / structural work not mentioned here, but required for
completing the scope of mechanical or electrical works in the coal
handling system.
cases latest revisions with amendments, if any shall be followed. Apart from the
specific codes mentioned herein, all other relevant and related codes concerning
the specific jobs under consideration and/or referred to in these codes and
technical specification shall be followed wherever applicable. (All codes shall be
latest as on the date of issuing the Tender/Bid document).
EXCAVATION AND FILLING
IS: 9758
IS: 10379
of
practice
PROPERTIES,
BUILDING
IS: 383
for field
control
of
moisture
and
AND
HANDLING
OF
COMMON
MATERIALS
IS: 455
IS: 808
IS: 1077
IS: 1161
IS: 1363
IS: 1364
IS: 1542
REV. NO.: R3
IS: 1786
IS: 2062
IS: 2116
IS : 2185 Part I
IS : 2185 Part II
IS: 2386
(Parts-I to VIII)
IS: 3812
IS: 4031
(All Parts)
IS: 4032
IS: 4082
IS: 8112
IS: 8500
IS: 12269
IS: 456
IS: 516
IS: 650
IS: 1199
IS: 1791
IS: 2502
IS: 2505
IS: 2645
IS: 2750
IS: 2751
IS: 3370
(Part I to IV)
liquids
IS: 3414
REV. NO.: R3
buildings
IS: 3558
IS: 4014
(Parts I & II)
IS: 4326
IS: 4990
IS: 5525
for
detailing
of
reinforcement
IS: 5624
IS: 6461
IS: 6509
IS: 7861
IS: 9012
IS: 9103
IS: 10262
IS: 11384
IS: 12118
IS: 12200
in
IS: 13311
Part-1
Part-2
Rebound hammer
SP:23
SP: 24
SP: 34
SP:
7(Part
Sec.7)
IS: 10297
IS: 10505
REV. NO.: R3
IS: 2212
IS: 2250
SP: 20
IS:277
IS: 730
IS: 2527
IS: 7178
IS: 8183
IS: 8869
IS: 12093
IS: 12866
IS: 14246
translucent
sheets
made
from
thermosetting
IS: 2016
IS: 814
IS: 1852
IS: 3502
IS: 6911
IS: 3757
IS: 6623
IS: 6649
IS: 800
IS: 816
IS: 4000
REV. NO.: R3
IS: 7215
IS: 12843
SP: 6
(Part 1 to 7)
IS: 1608
IS: 1599
IS : 2595
IS : 3664
IS : 3658
IS : 5334
IS : 1661
IS : 2333
Plaster-of-Paris
IS : 2402
IS : 2547
IS : 458
IS : 554
IS : 651
IS : 774
IS : 775
Cast iron brackets and supports for wash basins and sinks
IS : 778
IS : 781
Copper alloy gate, globe and check valves for water works
purposes
Cast copper alloy screw down bib taps and stop valves for
water services
REV. NO.: R3
IS : 782
Caulking lead
IS : 783
IS : 1172
IS : 1230
IS : 1536
IS : 1537
IS : 1538
IS : 1703
IS : 1726
IS : 1729
Basic
requirements
for
water
supply,
IS : 1795
IS : 1879
IS : 2065
IS : 2326
IS : 2470
(Part-I & II)
IS : 2548
IS : 2556
(Part 1 to 15)
IS : 3114
IS : 3438
IS : 3486
IS : 3589
IS : 3989
and
sanitation
IS : 1742
IS : 2064
drainage
IS : 4127
IS : 5329
REV. NO.: R3
buildings
IS : 5382
Rubber sealing rings for gas mains, water mains and sewers
IS : 5961
IS : 7740
IS : 8931
Cast copper alloy fancy bib taps and stop valves for water
services
IS : 9762
IS : 10446
IS : 10592
IS : 12592
IS : 12701
SP: 35
Tower Bolts
Part-I
Ferrous metals
Part-II
Nonferrous metals
IS : 208
Door Handles
IS : 281
IS : 362
Parliamentary Hinges
IS : 420
IS : 1003
(Part-I)
door shutters
IS : 1038
IS : 1081
IS : 1341
IS : 1361
IS : 1823
IS : 1868
IS : 2202
(Part-II)
type); particle board face panels and hard board face panels
IS:2209
IS:2553
Safety glass
REV. NO.: R3
IS:2835
IS:3548
IS:3564
IS : 3614
IS:4351
IS:5187
Flush bolts
IS:5437
IS:6248
IS:6315
IS:7196
Hold fasts
IS:7452
IS:10019
IS:10451
IS:1322
IS:1346
IS:1580
IS:3067
IS:3384
IS:2114
IS:2571
IS:4971
IS:8042
IS:13801
IS:1477
Part-I
Pre-treatment
REV. NO.: R3
Part-II
Painting
IS:1650
IS:2074
Part-I
Part-II
Schedules
Code of practice for painting concrete, masonry and plaster
IS:2395
surfaces
Part-I
Part-II
Schedule
Specification of synthetic enamel paint, exterior, under-
IS:2932
IS:2933
IS:4759
IS:5410
IS:5411 (Part-I)
IS:6278
IS:10403
IS:1080
spread foundations
IS:1904
IS:2950 (Part-I)
IS:2974
to V)
IS:6403
IS:8009
Part-I
Shallow foundations
Part-II
Deep foundations
IS:12070
REV. NO.: R3
IS:875 (Pt. I to Code of practice for design loads other than earthquake) for
V)
IS:1893
IS:3764
IS:7205
IS:7293
IS:7969
REV. NO.: R3
Anti-termite treatments
3.1.1
i)
ii)
Reference to only some of the codes in this document and various clauses
of design criteria shall not limit or restrict the scope or applicability of
other relevant codes. It shall be ensured that all other codes relevant to a
specific job, in addition to those already mentioned, are followed
wherever applicable.
iii)
Where British / American / DIN or other codes and standards are referred
to in this document, equivalent Indian Standards may be substituted if
available.
iv)
v)
The Codes and Standards listed below are applicable for the design and
construction of structures and buildings in general. Codes and Standards
applicable for specific design and construction are listed elsewhere in
reference sections.
vi)
Specifications for materials supplied from India follow the Indian Standard
Specifications.
vii)
viii)
ix)
REV. NO.: R3
x)
4.4.4 Deliverables
1.
2.
3.
4.
drawings, Detailed RCC Drawings, civil work details, Architectural details &
QA & QC Plan
6.
7.
8.
9.
10. Standard notes and drawings for steel and concrete structures along with
typical details of handrails, staircase, sunshades, grade slabs etc.
REV. NO.: R3
REV. NO.: R3
Handling Plant Control Room through Three nos. (3) Operator Stations, one (1)
number Operator Station cum Engineering Work Station and color graphic
displays of 2 x 52 thin bezel LCD monitors. The three (3) Nos. 24 LCD/TFT
monitors shall be configured to display alarm and also serve normal operation,
however, hard annunciation facia shall be provided for alarm and annunciation.
The PLC system of CHP shall have redundant MODBUS TCP/IP connectivity with
the Stacker & Reclaimer PLC system through cable reeling drum, further
alternative connection shall be discussed and finalised during detail engineering.
The PLC system of CHP shall have redundant MODBUS TCP/IP connectivity with
the wagon tippler PLC located at the Wagon tippler control cabin.
One (1) no. A3 colour size laser jet printer shall be provided which shall be
connected to the data highway and One (1) no. dot matrix printer shall be
provided which shall be connected directly to the engineering work station. The
required furniture such as operator desk, chairs, etc shall be provided by the
bidder. The CHP PLC shall be linked to DCS through high speed redundant
TCP/IP fast Ethernet connectivity as well as hardwired signals for monitoring
purposes. The following signals as minimum shall be hardwired directly from
CHP PLC to DCS:
Operation of the coal handling plant shall be based on the coal flow path
selection. The operator shall be able to select from PLC the desired Coal flow
path of the coal delivery, delivering coal from Track hopper/ Wagon Tippler to
the coal bunkers or coal stockyard, or from coal stockyard to the bunkers.
The coal handling plant operator shall select any one of the above paths from
monitor located on the main control desk. The flow stream path is then selected
by positioning different flap gates at the desired position from monitor to select
the conveyors. Once the system is in operation, the gates cant be moved from
their positions and path. After the selected path is in operation the movement of
the path selector will not have any effect on the system. The system shall be in
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
operation with a time delay and with a hooter sound. If selection is wrong, PLC
shall generate an audio-visual warning.
The control system will be designed for Auto & Manual operation of the
conveyors in the selected path. Auto / Manual selection shall be done from the
keyboard.
Auto Mode: In the Auto mode, the conveyors and related equipment will start
sequentially when the System Start is activated. During stopping, when the
System Stop is activated, all conveyors will stop sequentially (in the reverse
sequence) allowing time delays for clearing the materials on conveyor.
Manual Mode: In Manual Mode, the operator will start the conveyor system in
the same sequence as in Auto mode by pressing individual Start push buttons.
The operator will also stop the conveyor system, by pressing System stop or
individual Stop push buttons in the reverse sequence.
All the conveyors shall be protected from reverse running due to power failure
by providing mechanical or electrical locking system.
The starting sequence of the conveyors shall follow a direction opposite to that
of flow of material i,e :
1.
2.
In case of stacking of coal in stockyard, start from yard conveyor and end
conveyor end up with reclaim conveyor below track hopper/ wagon tippler.
up with reclaim conveyor. However for yard conveyor to start, the stacker reclaimer shall be in operation.
3.
4.
Any individual equipment (belt conveyor etc.) should not be allowed to start
unless the equipment immediately following the same in the direction of flow of
material is already in operation. Stop / tripping of any equipment from running
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
condition shall trip all preceding equipment in the system, but shall not effect
succeeding ones which shall continue to operate except crushers. Interlocking of
various conveyors shall be achieved with Flap gate, Rack & Pinion gate, limit
switches and zero speed switches.
Motors shall start only when the brake / rail clamp if provided, is in not
applied condition.
Crushers shall be provided with fluid coupling oil temperature, speed and
vibration monitoring instruments. Crushers shall trip in case fluid coupling oil
temperature/ speed / vibration are going beyond set limits of design.
Once a conveyor trips, flap gate directing coal from this conveyor shall change
over its position with a time delay and shall come back to the original position
control cabin. Monitoring of the Wagon tippler and side arm shall also be done
from the CHP control room.
Dust Suppression and dust extraction control: The fixed nozzles spraying water
on to coal at the discharge of various conveyors, shall be energised only
when the respective conveyors are operating.
REV. NO.: R3
The DS system of W.T. Hoppers shall have provision for interlocking with the
wagon unloading mechanism. The system shall be controlled from W.T. Hopper
Control Rooms. D.S System for waiting wagon in W.T area shall however be
separately controlled through solenoid valve from W.T Hopper Control Rooms.
Dust suppression system at crushed coal pile area shall be operated through
solenoid valves. The system shall be controlled from central control desk cum
mimic of the coal handling plant.
All dust extraction system shall be started or stopped manually from the central
control desk of CHP in addition to local start/stop push button. The stop P.B.
shall be lockable type with Indication in mimic panel. The Start/Stop system for
dust suppression and ventilation equipment shall also be similar.
Remote electrically operated butterfly type dampers will be provided at each
dust extraction point with multiple extraction point for balancing the air flow.
Ventilation systems shall be started and stopped manually from CHP control
room. Local Start/Stop Push Button shall also be provided. The stop P.B. shall be
of lockable type.
Interlocking: Generally the following conveyors / equipment will come under
interlock scheme:
1)
Conveyors
2)
Flap gates
3)
4)
Metal detectors
5)
6)
Crushers
7)
Vibrating feeders
8)
Paddle feeders
9)
Belt Scale
2)
Ventilation systems
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
3)
Maintenance equipment
All conveyors and equipment shall have local push buttons. Belt scale shall be
started when relevant conveyors are started. The dust suppression systems will
be energized as soon as the conveyors at the transfer points are energized.
Interlock for H.T. Motor: H.T. motors shall continue to run on no load by
disengaging the fluid coupling in the event of failure of any process interlock.
The H.T. motors will however be tripped in the event of any motor fault like O/L,
high motor winding temperature etc.
Safety interlocks to be taken care for conveyors and other equipment as a
minimum.
Conveyors:
1)
2)
3)
Under speed switch closed at 90% speed of the conveyor within designed
accelerating time
4)
5)
6)
7)
8)
9)
2)
3)
4)
Travelling Tripper
1)
2)
3)
REV. NO.: R3
1)
2)
3)
Vibrating Feeder
1)
2)
2)
3)
Crusher
1)
2)
3)
4)
REV. NO.: R3
REV. NO.: R3
SPARES
6.1
MECHANICAL
S.No.
1.0
Description
Quantity
Conveyors
(a) Idlers
Pulley bearings
Plummer Blocks
100m
2.0
Wagon Tippler
2.1
Rack segments
12 Nos.
2.2
Bushes
03 complete sets
2.3
03 complete sets
2.4
06 Nos.
06 sets
03 Nos.
(d)
coupling
(e) Hydraulic motor & solenoid 03 complete set
valves
(f) Electric motor for main power 02 Nos
pack pump
2.5
03 complete sets
2.7
02 Nos
hinge 24 Nos.
pieces
3.0
Apron Feeder
3.1
Carrying rollers
30 Nos.
3.2
30 sets
3.3
Apron pans
30 sets
REV. NO.: R3
S.No.
Description
3.4
3.5
Quantity
06 Nos.
4.0
10 Nos.
15 Nos
5.0
5.1
Lifting shelves
06 Nos.
5.2
Deflector
03 Nos
5.3
Screen plate
15 Nos.
5.4
06 Nos.
5.5
Adapter assembly
06 Nos.
5.6
100 Nos
5.7
Guide rollers
03 sets complete
5.8
Gear Box
Bearings (complete for Gear box)
Oil seals
5.9
Chain (complete)
03 sets
6.0
6.1
6.2
6.3
Liners
6.4
Kick-off plate
6.5
Cage bar
6.6
6.7
Suspension bars
6.8
Screen plate
7.0
7.1
Drive Bogie
Bogie wheel complete with
06 Nos.
bearings
Spur wheel
Doc. No.: E072-03-CHP-O-02
06 Nos.
REV. NO.: R3
S.No.
Description
Quantity
Labyrinth seal
12 Nos.
06 Nos.
Non-drive bogie
Bogie wheel complete with
06 Nos.
bearings
Labyrinth seal
7.3
7.4
7.5
7.6
12 Nos.
Reduction gear
Pinion and wheel (1st pair)
06 sets
06 sets
Oil seals
08 sets
09 sets
02 sets
02 sets
Oil seals
06 sets
01 No
03 Nos.
conveyor (complete)
7.7
Luffing Mechanism
Hydraulic piston & cylinder with
04 sets
bellows
Hydraulic pump complete
03 Nos.
2 Nos
02 sets
02 sets
06 sets
7.9
03 sets
01 No
Bucket wheel
complete buckets with teeth
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
04 Nos.
PAGE 319 OF 506
S.No.
Description
Quantity
7.10
8.0
8.1
8.2
Travel drive
8.3
9.0
15 Nos.
Six (06) Nos.
9.1
Bearings
9.2
V-belt
06 sets
9.3
Eccentric disc
06 sets
9.4
12 sets
9.5
08 sets
10.1
Bearing
10.2
V-Belt
06 Sets
10.3
Eccentric disc
06 Sets
11.0
Telescopic Chute
11.1
Gear box
03 Nos.
11.2
Sheeves
11.3
Bearings
12.0
12.1
Head pulley
12.2
Tail pulley
12.3
12.4
Set of sprockets
12.5
12.6
Rectifier assembly
13.0
13.1
13.2
14.0
14.1
Preamplifier
14.2
14.3
Transformer module
Doc. No.: E072-03-CHP-O-02
of each type of
S.No.
Description
Quantity
14.4
14.5
Convertor modules
15.0
16.0
16.1
etc.
for WT hopper
For conveyors
16.2
Sprinkler (complete)
17.0
17.1
motor
17.2
Seals
18.0
18.1
Filter bags
18.2
V-belt
18.3
18.4
Bearings
6.2
Sl.No
I
and duct
ELECTRICAL
Description
Quantity
operating mechanism
and rating
andtruck mounted
2
Two Nos.
Set of gaskets
Five Sets
6
7
rate
Amount
11 / 3.3 kV Switchgear
Breaker with complete
Unit
Five Nos
each
REV. NO.: R3
Sl.No
8
9
Description
switches
11
Current Transformers:
12
Voltage Transformers:
15
II
1
2
type
Transducers of each type
Two Nos
& range
Digital Multi-function
Meter
type
415 V Switchgear
Power Contactors and
One No of each
Auxiliary contactors
BI-Metallic Thermal
Overload Relay
HRC fuses
Control fuses
Protective relays
Trip Relays
MCB
MCCB
10
type& range
One No of each
Protective relays
Indicating lamps (LED)
14
rate
Amount
Local/remote selector
10
13
Unit
Quantity
Range
Five Nos of each
Rating
Five Nos of each
Rating
Two Nos of each
type
Two
Nos of
each
type
Two Nos of each
rating offered
Two Nos of each
rating offered
One No of each
rating
REV. NO.: R3
Sl.No
11
Description
Quantity
Five Nos
13
Five Nos
14
Five Nos
15
Local/Remote switch
Five Nos
16
Five Nos
18
19
20
indicating lamps
Interposing Current
Transformers
Transducers
Digital Multi-function
colour
One of each range
Two of each type &
rating
Five nos. of each
Meter
III
3.3 kV HT MOTORS
3.3 kV Motor
rate
Amount
Two Nos
complete
12
17
Unit
type
Bearings Temperature
Indicators
set comprising
Terminal connector
assembly
Cooling fan
RTD
IV
415 V LT MOTORS
415 V Motors
1 No of each type
1 No of each type
1 Set for each rating
of motor
Sl.No
Description
Quantity
Power Transformer
Gaskets(One
rate
Amount
Number
of
1 set
1 set.
CT of each type
1 No.
1 No.
1 No.
1 No.
Buchholz relay
1 set
Unit
Complete
for
HV
&
1 No each.
LV
winding
9
10
1 set
11
1 No.
1 set each
12
13
14
1 set
1 No.
1 Set
size
relay,
timers,
Switches
comprising
MCB,
one
Service Transformer
Gaskets(One
Number
of
1 set
1 set.
CT of each type
1 No.
Explosion
4
diaphragm/Pressure
vent
1 No.
relief
device as applicable
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
Sl.No
Description
Quantity
1 No.
Buchholz relay
1 set
Complete
for
HV
&
Unit
rate
Amount
1 No each.
LV
winding
8
9
10
11
Complete
Remote
Oil
Temperature
remote
1 set
1 set
CCU
Unit
with
VII
Battery Chargers
1 set
indicator Complete
12
1
1 No.
1 No.
Fuses including
FiveNos of each
semiconductor fuse
rating
components)
Thyristors
Diodes
Meters
LED Lamps
Switches
VIII
HT bus duct
1
2
2 nos
1 set each
equipments
terminal
Connector
1 set each
1 set each
REV. NO.: R3
Sl.No
Description
Quantity
Expansion bellow
1 set each
IX
LT bus duct
2 nos
1 set each
Unit
rate
Amount
Flexible
terminal
equipments
1 set each
Connector
1 set each
Expansion bellow
1 set each
Illumination
Illumination spares
10% of supplied
quantity
XI
Miscellaneous
10% for each type or
Interposing Relay
Fuses
eachType and
Rating
6.3
Description
Quantity
Power supply
2)
3)
4)
cable)
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
5)
Memory Unit
6)
cabinet
Audible device
9)
10)
Battery
11)
Key Board
12)
Annunciation Facia
13)
14)
Interconnecting cables
15)
50%
size
Measuring Instruments
1
Electronic Transmitters
(i)
model
no.
measurement
of
(for
or
nos.
of
each
type
whichever is more.
Temperature elements
(i)
(ii)
Indicators
(a)
REV. NO.: R3
digital
system)
(b)
indicators
of
electrical
Vertical Indicators
Vertical indicators of each model
(c)
meters
semaphore
indicator,
frequency
meter
(analog),
synchroscope
REV. NO.: R3
REV. NO.: R3
Flow Diagrams.
ELECTRICAL
1. Deviation from the tender specification
2. Completely filled in Data Sheet-B.
3. QAP format
4. List of sub-vendors with their credential.
CONTROL & INSTRUMENTATION
Control
philosophy
operation
philosophy
Design
philosophy
Redundancy philosophy.
Power supply scheme for PLC system including Peripheral & Remote I/O.
QAP format
REV. NO.: R3
7.2
drawings to the Purchaser, who in turn will review and furnish comments on only
important drawings / documents.
drawings / documents which will be submitted to the Purchaser with due dates
of submission immediately after award of Contract.
Design Data
Drawings
(b)
(c)
Conveyor gallery
(d)
Conveyor tunnel
(e)
(f)
(g)
(h)
REV. NO.: R3
(i)
Conveyors
Idlers
(b)
Pulleys
(c)
(d)
Vibrating screens
(e)
Vibrating feeders
(g)
(i)
Chutes
(h)
(j)
(l)
Metal Detector
(m)
Belt weigher
(n)
(K)
ILMS
(o)
Apron feeder
(p)
Dribble feeder
(q)
(s)
Travelling tripper
(t)
Belt switches
(u)
Take-up arrangement
(v)
Pumps
(r)
Flap Gates
Stacker/Reclaimer
(b)
Motors
(c)
Fluid couplings
REV. NO.: R3
ELECTRICAL
1. POWER TRANSFORMER
S. No
Description
Control schematics
Wiring diagrams
10
11
12
13
Instruction manuals on transformer and its various fittings. The manual shall
clearly indicate method of installation, check-ups and tests to be carried out
before commissioning of the equipment.
14
15
Cooling calculation
16
Foundation details
17
Roller assembly
18
19
Vender List
20
22
23
REV. NO.: R3
2. HT SWITCHGEAR
S. No
Description
Bill of material
Control schematic
Wiring diagrams
Instruction manuals on circuit breakers and its accessories (The manual shall
fittings
8
9
10
11
3. LT Switchgear
S. No
Description
Bill of material
per IS or IEC of identical Equipment of the offered items are not submitted,
the Bidder shall have to conduct the type test on the offered Equipment
before delivery free of charge to the Owner or Bidders testing charges are to
be mentioned.
4
Description
REV. NO.: R3
S. No
Description
enclosure connections rigid & flexible, seal-off bushings, connections with
switchgear and transformer terminals etc.
Bill of Materials
Calculation for temperature rise for bus and enclosure as per IEEE No. 298
Foundation plan
10
Structure layout
5. HT MOTORS
S. No
Description
Complete list of all tests to be carried out, with code/standard followed and
brief description of test procedure, for
a)
Tests at works
b)
d)
c)
Acceptance tests
List of spares
Consumable spares (for day to day maintenance, inspection & overhaul of plant
Strategic spares (generally high cost and/or long lead-time spares required
Manufacturing drawings for those spare parts going out of production beyond
10
drawings
and data will be submitted for review within four (4) weeks from the date of
issue of notice of proceed
11
12
All different characteristic curves of motor for 100%, 90% and 80% of the
Motor
supply voltage
REV. NO.: R3
6. LT Motors
S. No
Description
Test reports
Description
Confirmed cable data
Test reports
8. DC System
S. No
Description
Duty cycle diagram and battery sizing calculation in the format of IEEE-485
transformer etc
10
11
12
13
REV. NO.: R3
S. No
14
Description
Charger schematics and wiring diagrams
15
Test reports
16
9. Erection Package
S. No
Description
Data Sheet and technical leaflets on cable trays, conduit, junction boxes,
Dimensional drawings and data sheets for different equipment supplied under
PLC BOQ
Input/output List
Control
philosophy
operation
philosophy
Design
philosophy
Redundancy philosophy.
REV. NO.: R3
Process mimics
Earthing schemes
Wiring diagrams for panel, local panel, junction boxes, actuators, starters
etc.
REV. NO.: R3
REV. NO.: R3
The coal handling system and equipment shall perform satisfactorily to meet the
guarantee requirements specified in the following chapter and also those
specified in this specification.
After the coal handling system is ready, the same shall be tested at rated
capacity within six (6) months from the date of initial operation preferably
during the monsoon season to prove the performance of the system and
equipment. The capacity figures specified for the equipment shall have to be
achieved with tolerance on the positive side. The guarantee requirements shall
be made without undue vibrations in the conveyor supports, junction towers,
crusher houses, transfer houses, etc.
The wagon unloading system shall be capable of unloading the designed
number of wagons on continuous basis to achieve the specified capacity.
The coal handling system from stockpile to bunkers shall operate continuously
at an average capacity as specified over a period of 24 hours. The 24 hours
boiler requirement of coal shall be handled in a maximum 14 hours.
Each crusher shall be capable of crushing rated capacity with specified
maximum lump size of coal even while handling damp and sticky coal having
20% moisture (including surface moisture) during monsoon season. The largest
size of output particles shall not exceed those specified in the specification.
Screens shall screen out 95% of material having dimension of (-) 20 mm even
during rainy seasons.
Stacker reclaimer shall be stable under specified design condition and shall meet
all the requirements specified. The bucket wheel shall reclaim coal at the rated
capacity specified while handling well compacted, damp and sticky coal during
rainy seasons. The capacity shall be arrived at on working for 4 hours over
complete cross section of the coal pile. Also, the stacker shall stack coal at the
rate capacity specified. The stacker reclaimer shall have the facility for bypass
operation while conveying coal directly to bunkers via yard conveyor.
The capacities of all equipment / conveyors / feeders shall be equal to or more
than the specified.
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
All drive motors shall be suitable for direct-on-line starting and capable of
starting fully loaded conveyors / feeders.
Noise level produced by any rotating equipment (other than crusher) individually
and collectively should not exceed 85 dBA at a distance of 1.5 meter from it in
any direction under any load condition.
Vibration level of equipment at bearings shall not exceed the following limits for
different equipment.
Vibration levels shall conform to the limits specified below and shall be
measured as per VDI 2056 / BS 4675.
Equipment
a) At the bearing of drive pulley, motor and gear box for the following
equipment:
i)
115 microns
75 microns
Reclaimer
ii)
200 microns
Magnetic separator shall separate the magnetic material of the sizes and shapes
mentioned in this specification effectively.
REV. NO.: R3
8.2
ILLUMINATION LEVELS
8.3
EARTHING RESISTANCE
An earthing resistance of less than 0.5 ohm shall be achieved when measured
after isolating CHP earthing system.
8.4
At the outlet of dust extraction system, the dust concentration should not
exceed 100 mg/Ncu.m.
8.5
ENDURANCE TEST
Each stream and each path shall be tested at rated capacity for 24 hours to
prove that the system functions satisfactorily without any trip due to overload or
system fault.
All necessary instruments including walkie-talkies etc. for carrying out
performance testing of coal handling system shall be provided by the
Contractor.
The specified performance figures of the equipment shall be proved by the
Contractor during the performance tests. Should the results of the tests show
any vibration from the specified values, the Contractor shall modify the
equipment as required to enable it to meet the requirements.
REV. NO.: R3
REV. NO.: R3
Centre lines of WT hopper, junction towers, transfer houses, crusher house and
elevation of bunker floor shall be finalized by the Contractor. The sizes of the
junction towers, transfer houses and crusher house and the floor elevations shall
be finalized by the Contractor considering a minimum clear walkway space of
1200 mm around the equipment in each floor. The clear distance between the
floors shall be minimum 3000 mm and head room shall be suitable for handling
/ removing the equipment at the head end and tail end. The floor of junction
towers, transfer houses and crusher house shall be designed for keeping the
heaviest part of the equipment anywhere on the floor for maintenance of
equipment shall be provided. The length and elevation of the conveyors shall be
finalized by Contractor based on the limitations for the inclination furnished in
the specification.
A clear width of 4 M shall be provided at the end of the bunker bays on each
side of boiler for maintenance purpose.
Adequate space around the crusher in the crusher house shall be provided for
opening the cage of the crusher and for removal of the shaft.
Partitions with slide doors shall be provided in the crusher house between the
crushers to enable maintenance of standby crusher when the other crusher is
operating. Adequate maintenance space and handling facilities shall be provided
on both sides of the partition wall separately.
All conveyor galleries shall be provided with dust sweeping hopper covered with
removable chequered plates. There shall be one dust hopper for each walkway
of gallery and the same shall be provided at each trestle location. Similarly 2
nos. dust hoppers shall be provided for each floor or junction towers / crusher
houses. These dust hoppers shall be connected to a dust chute to enable the
dust swept to be led to the ground level.
REV. NO.: R3
10.0
REV. NO.: R3
VENDOR LIST
VENDOR LIST
The successful bidder shall furnish sub vendor list for Mechanical, Electrical and
C&I, items / equipments / systems for RPCL review and approval along with
credentials of the firm and performance certificates of the items / equipments /
systems.
REV. NO.: R3
11.0
REV. NO.: R3
DATA SHEETS
Description
Units
Values
1.
Belt Conveyors
1.1
flow diagram.
each conveyor
1.2
1.3
1.3.1
The capacities of
conveyors from Wagon
tippler to bunker
including yard
conveyors are, Designed
2200 TPH and Rated
2000 TPH. Except
manually unloaded coal
conveyor BCN-23, which
has a capacity of
Designed-600 1200 TPH
and Rated- 500 1000
TPH.
1.4
Belt speed
1.5
Belt
1.5.1
Belt width
1600
mm
conveyors
for
from
all
wagon
unloading
Belt specification
REV. NO.: R3
Sl. No
Description
Units
Values
resistance as per spec
type and suitable for 35
degree troughing angle .
The cover shall be Fire
resistant grade type (BS
490 Part-I ). Fire
resistant property shall
conform to Canadian
1.5.4
Top 5 mm
Bottom 3 mm
5 No. for WT to crusher
1.5.5
90 %(maximum)
allowable tension
1.5.6
As per design/ IS
1.6
Pulleys
1.6.1
Shell thickness
16 mm
1.6.2
24 mm
1.6.3
1.6.4
rubber. 12 mm thick
plain
1.6.5
Rubber of lagging
a)
Hardness :55 to 65
durometer (shore A)
b)
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
Elongation : Over
PAGE 349 OF 506
Sl. No
Description
Units
Values
300%
c)
Strength :160-200
kg/cm2
d)
e)
f)
Adhesion strength
:10 kg/cm
1.7
1.7.1
Type
1.7.2
Casing
Horizontal Split
1.7.3
Sealing
1.7.4
Lubrication
Greasing arrangement
with conical head shape
nipples
1.7.5
Bearing life
1.7.6
Type of Bearing
1.8
Pulley width
1.9
Pulley Material
1.10
Shaft Material
1.11
Maximum allowable
deflection
5 minutes
Idlers
1.12.1
Carrying idlers
be minimum 152.4 mm
&5.4mm, Spacing -1000
mm
1.12.2
Return idlers
REV. NO.: R3
Sl. No
Description
Units
Values
2 roll V type. Roller dia
and thickness shall be
minimum 152.4 mm
&5.4mm Spacing 3000
mm
1.12.3
Impact idlers
Shall be provided on
idlers
Bearings
1.13
Technological structures
1.13.1
Stringers/Short supports
As required
1.13.2
Deck plate
1.13.3
length of conveyors
mm
1200
side of conveyor
1.14
1.15
Skirt Boards
1.15.1
Length
REV. NO.: R3
Sl. No
Description
Units
Values
1.15.2
Height
As required
1.15.3
Width
1.15.4
Side plate
Min. 10 thk
1.15.5
Top cover
6 mm thk M.S.
2.
Stacker Reclaimer
2.1
Type
Rail
mounted,
bucket
Number required
Nos.
2.3
Location
2.4
2.5
Capacity
Three (03)
Outdoor
while
TPH
2000
stacking TPH
2200
(Designed)
2.6
Duty
Machine
shall
be
Capacity
while
reclaiming TPH
2000(Rated)/2200(Desig
(Rated/Designed)
ned)
2.8
Material handled
Crushed Coal
2.9
Belt
width
of
boom
and mm
As required
intermediate conveyor
2.10
2.11
2.12
Maximum
wheel
load tones
Track gauge
To
be
furnished
by
bidder
m
7.0 (minimum)(length of
travel to be furnished by
bidder)
2.14
2.15
8.75
8.75
graded level
above
rail
level
(minimum)
2.16
reclaimer
2.17
2.18
36 m
Traveling speed
m/se
REV. NO.: R3
Sl. No
Description
Units
c
2.19
Stability factor
Values
m/min.
In accordance with ISO
5049/1
2.20
For
operating
conditions
of
1.5
(Live
Load
only
considered
For
operating
conditions
of
1.5
maximum
wind
IS 875(latest edition)
load
2.22
machine
with
maximum
position)
Material
of
construction
of
Bucket Wheel
M.S., IS:2062
2.23.2
Bucket
2.23.3
Lips
Manganese Steel
2.24
Type of drive
2.24.1
Bucket wheel
drive-
speed
suitable
variable
hydraulic
for
operation
drive
inching
(no.
of
buckets-8)
2.24.2
Slewing
Hydraulic
2.24.3
LT drive
VVVFD
2.25
to
manual
control
3.
Primary Crushers
3.1
Type of crusher
Rotary Breaker
3.2
No. required
3.3
Material to be crushed
3.4
45
REV. NO.: R3
Sl. No
3.5
Description
Units
Values
Maximum 20
coal
3.6
Material Temperature
Max. 50
3.7
Ambient Temperature
3.8
Hour
24
s/day
3.9
Bulk density
T/m3
0.8
3.10
Rated capacity
TPH
1000
Designed capacity
TPH
1250
3.11
Output size
(-)150 mm 98%
3.12
Type of Drive
3.13
Maintenance/inspection door to
Yes
coupling
be provided?
3.14
Material of construction
3.14.1
Shaft (Rotor)
Forged Carbon/Alloy
Steel
3.14.2
Frame
3.14.3
Breaker Plate
3.14.4
Liner plate
3.15
Bearing
3.15.1
Bearing Type
3.15.2
Life
3.15.3
Lubrication
Oil
3.15.4
Cooling Arrangement
Oil bath
3.16
Enclosure
Dust tight
4.
Secondary Crushers
4.1
Type of crusher
Ring granulator
4.2
No. required
Anti-friction roller
Hrs
50,000 (Min.)
Material to be crushed
Doc. No.: E072-03-CHP-O-02
Sl. No
Description
Units
4.4
4.5
Values
45
Maximum 20
coal
4.6
Material Temperature
Max. 50
4.7
Ambient Temperature
4.8
Hour
24
s/day
4.9
Bulk density
T/m3
0.8
4.10
Rated capacity
TPH
1000
Designed capacity
TPH
1250
4.11
Output size
(-)20 mm 98%
4.12
Type of Drive
4.13
Maintenance/inspection door to
Yes
be provided?
4.14
Material of construction
4.14.1
Shaft (Rotor)
4.14.2
Suspension Bar/Ring/Roller
Mn-Steel
IS : 276
4.14.3
Frame
4.14.4
Breaker Plate
4.14.5
Cage Assembly
Mn-Steel Gr III
4.14.6
Liner plate
IS : 276
Resistance
4.15
Bearing
4.15.1
Bearing Type
4.15.2
Life
4.15.3
Lubrication
Oil
4.15.4
Cooling Arrangement
Oil bath
4.16
Enclosure
Dust tight
5.
Flap Gates
5.1
Service requirement
5.2
Type
Anti-friction roller
Hrs
REV. NO.: R3
50,000 (Min.)
Sl. No
Description
Units
Values
5.3
Required numbers
5.4
Location
5.5
Material handled
5.6
coal
mm
Material size
5.7
0C
50
5.8
0C
14
5.9
Actuator
5.9.1
Type
Motorized
5.9.2
Travel range
As required
5.10
Materials of construction
5.10.1
Gate
IS-2062
5.10.2
Main plate
12 mm
5.10.3
Liner
10 mm thick SS 409
5.11
Bearing
5.11.1
Type
5.11.2
Life
5.12
Method of lubrication
ball or roller
h
50,000 (min)
Single shot, pressure
lubrication
6.
6.1
Type
6.2
Location
6.3
Emergency reclaim
hopper and 1nos. for
manual reclaim hopper
6.4
mm
Material handled-coal lump size
REV. NO.: R3
Sl. No
Description
Units
Values
hopper , crushed (-) 20
mm for Emergency
Reclaim hoppers
6.5
6.6
OC
50
OC
14
T/M3
0.8
6.7
Bulk density
6.8
Moisture content
6.9
Size of opening
As required
6.10
Yes
6.11
Type
of
chain
for
manual
Maximum 20
Endless
operation
6.12
Yes
6.13
Materials of construction
6.13.1
Slide gate
IS-2062
6.13.2
Rack
IS 210 Gr 260
6.13.3
Pinion
IS 210 Gr 260
6.13.4
Drive shaft
6.13.5
M.S.
6.14
Bearing
6.14.1
Type
6.14.2
Life
6.15
Method of lubrication
50,000 (min)
Single shot, pressure
lubricated
6.16
Type of Seal
6.17
Double Labyrinth
kg
25 (max) at choked
condition
7.
Chutes
7.1
Material handled
Coal
7.2
Bulk density
T/M3
7.3
Lump size
mm
7.4
Belt width
mm
As required
7.5
20
7.6
TPH
As required
7.7
Belt speed
m/s
As required
7.8
Pulley width
Doc. No.: E072-03-CHP-O-02
0.8
Sl. No
Description
Units
Values
7.9
60
7.10
Material of chutes
IS-2062
7.11
7.11.1
Liner material
7.11.2
Liner thickness
mm
12
SS 409
mm
10
*Note : Size of the chute shall be 20% more than the designed size
8.
Vibrating Screens
8.1
8.2
TPH
1000 / 1250
8.3
No required
Nos.
8.4
Material to be handled
Coal
8.5
8.6
Output size
(-)20 mm
8.7
20%
8.8
As per manufacture
standard
8.9
Inclinatioin
8.11
wear resistant
8.12
Type of Bearing
Heavy duty
9.
9.1
Type
9.2
Capacity
9.3
As required
9.4
Duty Class
II as per IS:3938
9.5
Type of trolley.
Electrically operated
REV. NO.: R3
Sl. No
Description
9.6
Type of Rope
9.6.1
Construction
Units
Values
6x37 with Fibre core of
best plough steel having
tensile strength of 160180 kg/cm2
9.6.2
Type of core
Fibre
9.6.3
Factor of safety
9.7
Operating speed
9.7.1
Hoisting
3.0 m/min
9.7.2
Trolley
manufacturer standard
9.8
Total lift
As required
9.9
Cross Travel
As required
9.10
As required
Motor
9.11.1
Type
9.11.2
Duty/Rating
9.11.3
No. of starts/hr.
150
9.11.4
Degree of protection
IP 54
9.11.5
Class of insulation
F limited to temperature
rise of class-B.
10.
10.1
Location
10.2
Belt Width
10.3
Material
10.4
Bulk weight
T/m3
0.8
10.5
mm
As required
Coal
and (-) 20 mm
10.6
Flow rate
10.7
50 kg MS round Bar of
TPH
REV. NO.: R3
As required
Sl. No
Description
Units
Values
bolts & nuts /50 Kg MS
Plates.
10.8
Type
Suspended
10.9
10.9
Type of Magnet
mm
Bidder to Indicate
Electromagnetic
Oil
500
belt
10.11
10.12
10.13
Accessories
Bidder to decide
Gaus
s
1000
Suspension
lifting
Hooks
Cleated Belt
10.14
Control Panel
10.15
Quantity
11.
Belt Weighers
11.1
Material
11.2
Temperature
OC
Ambient
11.3
Moisture Content
Maximum 20
11.4
Bulk weight
T/m3
0.8
11.5
mm
11.6
Flow rate
TPH
As required
11.7
Location
11.8
Quantity
11.9
Coal
11.11
Load cell
11.12
Control station
11.13
Control cabinet
REV. NO.: R3
Sl. No
Description
Units
Values
digit
Totalizer, Remote
Weighing range
20 110%
11.15
Accuracy
range)
Suitable
device
calibration
&
accuracy
shall
for
testing
be
provided
11.16
Electrical
Wall
mounted
panel
based
controller
digital
flow
with
rates
&
totalized
1 no 4-20 mA analog
signal corresponding to
TPH rate for the Clients
PLC
1 no pulse signal output
corresponding
totalized
pulses
to
for
Clients PLC
Power Supply to control
panel AC/3Ph/50 Hz
5% /415V 5%
12.
Metal Detector
12.1
Material handled
Coal
12.2
Capacity (flow)
As required
12.3
Size of material
12.4
Bulk Density
0.8
12.5
Type
Electronic
12.6
Size
To suit
Belt Width of
conveyor
12.7
Location
REV. NO.: R3
Sl. No
Description
Units
Values
12.8
Material of Construction
12.9
12.10
Sensitivity
12.11
Hooter / Siren
12.12
Quantity
12.13
Control Unit/Panel
13.
Vibrating Feeders
13.1
55
for
Rated
2000/Designed
unloading hopper
13.2
Feeding capacity
TPH
2200
for
reclaim
manual
Emergency
hopper
and
Manual
unloading
hopper
13.3
Material handled
13.4
Lump size
Coal
mm
(-)
20
for
Emergency
mm
for
Manual
unloading hopper
13.5
T/M3
0.8
13.6
OC
50
13.7
% of inherent moisture
Maximum 20
13.8
Hours of operation
Hour
24
s
13.9
Installation
Indoor
13.10
Electro
Mechanical
Belt width
mm
REV. NO.: R3
As required
Sl. No
Description
Units
Values
13.12
Belt material
Synthetic
13.13
Tray liner
Tiscral/Sailhard
13.14
Yes
13.15
Yes
13.16
Deck slope
By Bidder
13.17
Deck size
By Bidder
13.18
By Bidder
14.
14.1
provided
WagonTippler
Type of Wagon Tippler
clamping
operation: hydraulic
Tippler
operation:
weighing
as
per
latest
Quantity Required
Five (05)
14.3
Required No. of
25tips/hr-
Tippling/hr
(Guaranteed)
Design
22tips/hr- Rated
14.4
Track Gauge
1676mm
14.5
Wagon
as
per
Hours of operation
24
14.7
design
14.8
wagons
manufactured by
Indian Railways
REV. NO.: R3
Sl. No
14.9
Description
Units
Values
Drive details:
a. Reduction of speed
Through
b.
Motor
hydraulic
Shoe
brake
Apron Feeder
15.1
LOCATION
Beneath
Wagon
Tippler
Hopper
15.2
Capacity (Rated/Design)
TPH
2000 / 2200
15.3
Duty
Continuous
15.4
Capacity Range
20% to 110 %
15.5
Number required
Five (05)
15.6
Material to be handled
ROM Coal
15.7
mm
(-)300
15.8
Bulk density
T/M3
15.9
15.10
Drive
Variable
drive
speed
without
electric
gear
box
Dribble Feeder
LOCATION
Type
Belt Type
16.2
Capacity (Rated/Design)
TPH
16.3
Duty
Continuous
16.4
Number required
Five (05)
16.5
Material to be handled
ROM Coal
16.6
16.7
Type of Belt
16.8
mm
Top 5, Bottom 3
16.9
Width
mm
mm
2000 / 2200
(-)300
Nylon-Nylon/EP
of apron feeder
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
Sl. No
16.10
17.
17.1
Description
Units
Take-up
Values
Screw type
17.2
Location
Below
Wagon
Tippler
platform
17.3
Number
17.4
Weighment Position
Static
17.5
Microprocessor
based
Wagon
Tippler
Control
Room
17.7
17.8
Type of Wagon
18.
18.1
Type
Wagon
Location
1) Conveyor transfer
points, Junction
towers/Transfer
house
2) Stockpile
3) Wagon Tippler
18.3
Type of nozzles
REV. NO.: R3
Sl. No
Description
Units
Values
other area
18.4
18.5
each
feed
and
discharge
points of conveyor
18.6
transferred
at stockpile
18.7
system
VENTILATION SYSTEMS
19.1
19.1.1
Type
19.1.2
19.1.3
Capacity
mg/N
m3
50
Based on 12 air changes
per hour
19.2.0
19.2.1
No of Air Changes/hr
12 (Minimum)
19.2.2
Type of fan
Centrifugal
19.2.3
Location
Tunnels
19.2.4
19.2.5
Material of duct
M/s
10 (maximum)
RCC for tunnel portion 18
gauge GI Sheet for others
19.2.6
Grills
GI construction with
louvers
19.3
REV. NO.: R3
Sl. No
Description
Units
Values
MCC room
19.3.1
Room size
Contractor to decide
19.3.2
20
HOPPERS
20.1
Designation
WT hopper, Emergency
Reclaim Hopper and
Manual unloading
hoppers
20.2
Number Required
20.3
hopper
20.4
20.5
RCC
20.6
20.7
Liner
10 mm TISCRAL /SAILMA
21.0
21.1
Purpose
REV. NO.: R3
Sl. No
Description
Units
Values
particles
will
settle
Construction
22.0
22.1
Type
Automatic
22.2
Location of sampler
22.3
22.4
Type of Primarycutter
Swinging type
22.5
Material of construction
22.5.1
Primary cutter
SS-304/316
22.5.2
22.5.3
SS-304/316 or MS with
SS liner
23.0
23.1
Type
Rack
Traction
Drive
&
&
Pinion
Hydraulic
without
gearbox
and coupling.
23.2
Qty
Five (05)
23.3
BOX N type
23.4
Hauling capacity
60 Nos.
Wagons, each
23.5
Duty
Continuous ; 24hrs/day
23.6
Operating
Speed (Forward
&
Reverse)
with
&
Load
without Load
23.7
23.8
Mode of Control
Automatic
23.9
Centralized
23.10
4 Nos
23.11
4 Nos. (wheels)
22tips/hr (Rated)
REV. NO.: R3
Sl. No
23.12
Description
Units
Track Gauge
Values
1676 mm
24.0
EOT crane
24.1
No. of Cranes
24.2
Safe
24.3
Type of girder
24.4
Duty class
M5 Mechanical
24.5
Rated
Crane
M5 Electrical
capacity
(SWL)
20
Tonnes
24.6
Hook type
24.7
Operation from
24.8
Hoisting Rope
24.8.1
Hoisting rope
Pendant
Flexible plough steel with
lubricated fibre core as
per IS 2266.
24.8.2
Hoist drum
is
position.
at
highest
24.9
Type of brakes
24.9.1
For hoist
24.9.2
No. Required
Two
24.9.3
AC Electro hydraulic
thrustor
24.9.4
Cross travel
1 No. AC Electro
hydraulic thrustor
24.10
Speeds
24.10.
Main hoist
3 m/min
24.10.
Cross travel
7.0 m/min
24.10.
Long travel
10.0 m/min
REV. NO.: R3
Sl. No
24.11
Description
Units
Values
Through VVVFD
24.12.
Main hoist
10 % of main speed
24.12.
Auxiliary hoist
10 % of main speed
24.12.
Cross travel
10 % of main speed
24.12.
Long travel
10 % of main speed
24.13
Limit switches
24.13.
Cross
24.13.
Long travel
24.13.
Hoisting
24.14
Gearboxes
Totally
immersed
Types of motors
24.15.
cross travel
Squirrel cage
24.15.
long travel
Squirrel cage
24.15.
hoisting
Squirrel cage
24.16
As required
24.17
Span
As required
24.18
Long travel
As required
REV. NO.: R3
Electrical
Power Transformer
S.No
Description
Particulars
1.
As per SLD
2.
Cooling
ONAN/ONAF
3.
Type
2 Winding
4.
Voltage Ratio
11 kV/3.6 kV
5.
Frequency
50 Hz
6.
Phases
3 (Three phase)
7.
i) ONAN rating
Rated MVA
8.
Service
Outdoor
9.
Duty
Continuous
10.
11.
of 50 deg C
50C
ii)
55C
winding
method
12.
measured
by
resistance
13.
Winding
i)
Rated
power
frequency
withstand
voltage kVrms
voltage kVp
14.
Bushing
i)
Rated
power
withstand
As per IS 2099
As per IS 2099
voltage kVrms
frequency
voltage kVp
15.
16.
Vector group
17.
Tap Changer
HV:130
LV: 50
DyN11
i) Tap range
18.
OCTC
Conventional type
REV. NO.: R3
S.No
Description
19.
Particulars
Noise level
20.
NEMA TR-1
1.9 tesla
21.
Creepage distance mm
31 mm / kV
22.
Reference standard
IS 2026/IEC60076
23.
System earthing
HV (11 kV)
LV (3.3 kV)
24.
Auxiliary supply
415V, 3 ph. 50 Hz
25.
Required
26.
Type
CFVV
27.
28.
resistance)
resistance)
of
(CFVV/VFVV/CbVV)
voltage
variation
1 minute
non-uniformly insulated
HV
Uniform
LV
Uniform
Service Transformer
S. No
1.
Description
Particulars
Quantity
As per SLD
Reference standard
IS 2026/IEC60076
3.
Cooling
ONAN
4.
Type
2 Winding
5.
Voltage Ratio
As per SLD
6.
Frequency
50 Hz
7.
Phases
3 (Three phase)
8.
ONAN rating
9.
Service
Indoor
10.
Duty
Continuous
11.
Overload capacity
12
50 C
55C
REV. NO.: R3
S. No
Description
Particulars
Insulation Level
a) Impulse
(1.2/50
s)/
frequency
power
withstand
As per IS
ii) L.V
As per IS
b) Insulation Type(HV/LV)
14
Uniform/Uniform
Bushing Particulars
(i)
As per IS
As per IS
31mm/KV
IS 2099
15
HV-130
16
Vector group
17.
Tap Changer
LV-25
DyN11
i) Type
Off-Circuit
+/-5%
2.5%
Full
18
Noise level
NEMA TR-1
19
1.9 tesla
21
System earthing
HV
Non effectively
LV
Effectively
22
Fault level
50
24
CFVV
25
110%
26
Only
kA
(to
match
the
continuous,125%
One
corresponding LT switchgear)
(CFVV/VFVV/CbVV)
Notes:
REV. NO.: R3
parallel
i)
The Transformer shall be capable of withstanding without damage 1.4 times the
ii)
The specified kVA rating shall be available at the lowest HV winding tap (-5%)
The transformer should withstand the 3 phase fault current for 3 sec for a fault at the
bushing of the transformer
HT Switchgear
S.No
Description
For 11 / 3.3 kV
Switchgear Assembly
1.
11 / 3.3 kV
2.
12 / 3.6kV
3.
Rated Frequency
50 Hz
4.
Type
5.
Service
Indoor
6.
Enclosure
IP-42
7.
Number of phases/poles
Three
8.
9.
By vendor
10.
By vendor
11.
40kA(rms)
12.
withstand voltage
14.
15.
16.
100kA(peak)
i) Control voltage
220 V DC (198V-240V)
220 V DC unearthed
220 V DC/240 V AC
50C
B)
BUSBARS
1.
REV. NO.: R3
S.No
Description
C)
1.
Cable entry
For 11 / 3.3 kV
CONSTRUCTIONAL REQUIREMENTS
Power Cables-Bottom
Control Cables- Bottom
2.
Top
3.
D)
CIRCUIT BREAKERS
1.
2.
an ambient of 50C
As per requirement
i) A.C. component
40 kA
3.
100 kA(peak)
4.
5.
6.
Operating Mechanism
7.
Auxiliary Voltage
8.
9.
i) Closing
220 V DC (85%-110%)
ii) Tripping
220 V DC (70%-110%)
220 V DC (85%-110%)
Duty Cycle
0-3-CO-3-CO
Operation Time
i) Opening time (ms)
E)
RELAYS
1.
F)
METERS
1.
Accuracy class
0.5S
2.0kV (rms)
2.0kV (rms)
2.
G)
CURRENT
1.
Class of insulation
Class E or better
2.
3.
Accuracy class
TRANSFORMER (CT)
i) Protection core
0.5
REV. NO.: R3
S.No
Description
For 11 / 3.3 kV
4.
H)
1.
2.
Class of insulation
Class E or better
3.
Other parameters
As specified elsewhere
I)
TRANSDUCERS
3 Amperes
1.
CURRENT TRANSDUCERS
2.
Input
3.
Rated Frequency
50Hz
4.
Output
5.
6.
Accuracy
J)
VOLTAGE TRANSDUCERS
Input
Output
Accuracy
0.5%
K)
VAR TRANSDUCERS
Input
Rated Frequency
50Hz
Output
Accuracy
L)
WATT TRANSDUCERS
Input
Rated Frequency
50Hz
Output
Accuracy
0.5%
M)
FREQUENCY TRANSDUCERS
Input
Rated Frequency
50 Hz
Range
45-55 Hz
Output
Accuracy
0.5%
REV. NO.: R3
LT Switchgear
S.No
A)
1
Description
Particulars
POWER SUPPLY
AC SYSTEM
Voltage
Frequency
50Hz 5%
Combined variation
frequency)
earthed
Fault Level
2.
3.
B)
50 kA(rms)
220 V DC
Fault Level
20 kA (indicative only)
220 V DC
220 V DC
CUBICLE DATA
CB is used as incomer
Dynamic Rating
CB is used as incomer
C)
105kA(peak)
CIRCUIT BREAKER
Type
Operating duty
Symmetrical interrupting
50 kA(rms)
105kA(peak)
type
D)
AC Component
50kA(rms)
DC Component
No of aux. contacts
METERS
Accuracy class
2.0 kV (rms)
E)
REV. NO.: R3
S.No
Description
Particulars
Type
1100V, 50 Hz
Class of insulation
E or better
For metering
breaker
protected feeders
Dynamic withstand
For CTS Associated with circuit
105 kA(peak)
breaker
protected feeders
F)
Limited by fuse
BUSDUCT
Type
Non-Segregated
2.5 kV
50 kA(rms)
105 kA(peak)
withstand voltage
withstandCurrent
current
G)
Cast Resin
Voltage Ratio
440/110V
Method of construction
Y/Y
Class of insulation
Class E or better
2.5kV
withstand voltage
I)
CONTACTORS
Type
Utilizing Category
J)
RELAYS
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
S.No
Description
Particulars
CONTROL TRANSFORMERS
Type
Dry/Cast Resin
Voltage Ratio
Class of insulation
Class B or better
2.5 kV
Rating
withstand voltage
L)
TRANSDUCERS
CURRENT TRANSDUCERS
Input
Rated Frequency
50 Hz
Output
Over current
Accuracy
M)
0.5%
VOLTAGE TRANSDUCERS
Input
Output
Accuracy
0.5%
VAR TRANSDUCERS
Input
Rated Frequency
50Hz
Output
Accuracy
0.5%
WATT TRANSDUCERS
N)
Input
Rated Frequency
50Hz
Output
Accuracy
0.5%
FREQUENCY TRANSDUCERS
Input
Rated Frequency
50Hz
Range
45-55 Hz
Output
Accuracy
0.5%
REV. NO.: R3
MCCB
S.No
A)
Description
Particulars
General
Type
Metal-clad, draw-out
Service
Indoor
Enclosure
In
switchgear
room
and
control
the
panels
shall
have
AC
DC
i) Voltage
415V 10%
ii) Phase
3-phase
iii) Frequency
50Hz 5%
10%
neutral
variation
v) System grounding
sum)
and
(absolute
Solidly
grounded
220V 10%
Ungrounded
16 to 630A
AC
DC
i) Interrupting
50kA
20 kA (Values are
50kA
20 kA (Values are
2.5kV
1.5kV
tentative only)
tentative only)
B)
220V DC 10%
CIRCUIT BREAKER
Duty Cycle
0-3-CO-3-CO
Breaking Current
i) A.C. Symmetrical
50 kA for 1 sec
Making Current
105kA(peak)
Auxiliary Voltage
REV. NO.: R3
S.No
C)
Description
Particulars
i) Closing
220V DC (85%-110%)
ii) Tripping
220V DC (70%-110%)
220V DC (85%-110%)
CONTACTOR DUTY
i) AC
Class
III-Category
AC3
for
ii) DC
D)
SWITCH DUTY
AC
DC
i) Motor feeders
AC23
DC22
AC22
DC22
HT Cables
S. No
1.
Description
Conductor
Particulars
Stranded and compacted aluminium conductor of
2.
Conductor Screen
3.
Insulation
4.
Insulation Screen
Core Identification
6.
Inner Sheath
Armour
Overall Sheath
9.
frequency variation
Voltage
+/-10%
Frequency
+/-5%
REV. NO.: R3
S. No
Description
Particulars
10% (absolute)
Permissible conductor
90 deg C
temperature
corresponding to
maximum current
Maximum permissible
conductor temperature
130 deg C
foe emergency
overloading
Conductor temperature
250 deg C
duty
10.
40 kA.
11.
Drum/ Length/Tolerance
Wooden/500/1000meter/ 5%
Current
LT power cables
S.No
Description
Particulars
1.
Conductor
2.
Insulation
3.
Inner Sheath
4.
Armor
Overall Sheath
6.
50 kA for 1 second.
7.
Drum/ Length/Tolerance
Wooden/1000/500metre/ 5%
8.
Current
frequency variation
Voltage
+/-10%
Frequency
+/-5%
10% (absolute)
Permissible conductor
90 deg C
temperature
REV. NO.: R3
S.No
Description
Particulars
corresponding to
maximum current
Maximum permissible
130 deg C
conductor temperature
foe emergency
overloading
Conductor temperature
250 deg C
duty
LT Control cables
S.No
Description
Particulars
1.
Conductor
2.
Insulation
3.
Inner Sheath
4.
Armor
5.
Overall Sheath
6.
General requirement
Instrumentation cables
Table A: Cable Parameter
Conductor Size
0.5 Sq.mm.
Parameter/ Type
Individual and
Compensating
shielded
(with/without
of Cable
overall
Shielded
F)
Mutual
capacitance at 0.8
120 nF/Km.
Teflon Coated
(Type I)
100 nF/Km.
kHz (max.)
overall
REV. NO.: R3
120 nF/Km;
100 nF/Km.
Cables
Teflon
coating)
(Type A, B, C)
200 nF/Km
Conductor
Resistance (max.)
73.4 ohm/km
73.4
Type F
(loop)
(loop) For
73.4 ohm/km
ohm/km
(loop)
Insulation
100 M ohm/
100 M ohm/
100 M ohm/
100 M ohm/ Km
Cross-Talk figure
60 dB
60 dB
60 dB
60 dB
Characteristic
320 ohm
340 ohm
Attenuation at 1
1.2
1.2 dB/Km
1.2 dB/Km
Type F
G/0.8 dB for
resistance
Km
impedance (max.)
kHz (max.)
dB/Km for
Km
Km
ohm
for Type
Type E
Conductor Size
Description
0.5 mm2
0.5 mm2
0.5 mm2
0.5 mm2
(2/4/8/12/16/20/24
pair) for
0.5 mm2
0.5 mm2
&
outer-sheath
for
high
temperature
application.
S
As per specific
Requirement for
monitoring
Standard /
each application
cable,
System
Bus
REV. NO.: R3
cable,
Bus
DC System
S.N
Description
A)
BATTERY
Application
Ambient temperature
Particulars
Coal Handling Plant
i) Maximum
50C
ii) Minimum
5oC
Type
Battery voltage
220 V
Terminal Connection
B)
BATTERY CHARGER
Charger
Float-cum-boost
Type
Enclosure
Ambient Temperature
50C
A.C. Input
i) Supply
10%
5%
v) Short-circuit level
Solidly earthed
variation
D.C. Output
i) Trickle charging mode
Performance Parameters
i) Output Voltage Regulation (load
1%
Charger Panel
i) Type
REV. NO.: R3
S.N
Description
Particulars
ii) Enclosure
9
Rectifier Transformer
i) Type
10
C)
Class-F
Naturally air-cooled
i) Rectifier Transformer
Restricted to class-B
ii) SCR
Silicon
Yes
Yes
Diode
Peak Inverse Voltage
1200 V
Filter Choke
Insulation Class
Class-F
Contactor
i) Type
Meter
i) Size
96 x 96 mm2
ii) Accuracy
1%
Changeover switch
i) Type
minimum 2 NO + 2 NC auxiliary
contacts
Yes
Terminal Connection
i) A.C. Input
b) To Load
C)
DCDB
General
Type
Service
Indoor
REV. NO.: R3
S.N
2
Description
Particulars
System
Voltage
220 V
Phase
2 wire
System
Ungrounded
MCCBs
3
16 A to 630 A
20 kA (indicative only)
Insulation level
LT Motor
1.
Description
a.
A.C. Motor
2.
a.
Type of Motor
: Squirrel Cage
b.
: Continuous
c.
Normal/Energy efficient
d.
: 415V 10%
: 50Hz 5%
: 415V
e.
3.
a.
Full Load %
4.
Performance
:>90%
a.
Method of Starting
: DOL
b.
: <7.2 p.u.
c.
d.
e.
: Minimum 5 minutes
5.
Construction
a.
Type of Ventilation
: Self ventilated
: IP-55
b.
c.
Method Of Cooling
d.
Insulation Class
e.
Tropicalized
: Yes
6.
(TEFC)
restricted to class B
REV. NO.: R3
a.
7.
Accessories
c.
: 0.25 sec
: 240V, 1Phase, 50 Hz
HT Motor
S.No
Description
A.C. Motor
2.
3.
: 3.3 kV
Type of Motor
: Squirrel Cage
: Continuous
Normal/Energy efficient
: Energy Efficient
: 50Hz 5%
: 10% absolute
4.
:>90%
Performance
Method of Starting
: DOL
: 6.0 p.u.
5.
7.
torque
: Minimum 5 minutes
Construction
Type of Ventilation
6.
Value
: Self ventilated
: IP-55
Method Of Cooling
Insulation Class
Tropicalized
: Yes
(TEFC)/CACA
restricted to class B
: Detachable
Time
: 0.25sec
Accessory TerminalBox
Cable glands furnished
: Required
HT Bus Duct
S. No
Description
Particulars
REV. NO.: R3
S. No
Description
Particulars
3.3 kV
Reference standard
IS 8084
1.
3.3kV
2.
3.6kV
Current rating
As required
3.
Frequency
4.
Service
5.
Number of phase
6.
One
7.
minute
50Hz
Indoor/ Outdoor
power
Three
frequency
withstand
voltage (Dry/Wet)
10 kV
40 kV
s wave shape
8.
9.
10.
Type of Cooling
Natural
11.
12.
Aluminum/Al alloy
13.
Aluminum/Al alloy
14.
2mm
15.
3mm
16.
Phase segregated
i) Voltage class
3.6 kV
a) Dry
10 kV
b) Wet
10 kV
40 kV
v) Material of Insulator
Porcelain
17.
18.
19.
20.
40C
40C
20C
Degree of protection
Appendix F of IS 8084.
REV. NO.: R3
LT Bus duct
S. No
Description
Particulars
IS 8084
1.
415 V
2.
460 V
Current rating
As required
3.
Frequency
50 Hz
4.
Service
5.
Number of phases
6.
8.
9.
105 kA
10.
Type of Cooling
Natural
11.
12.
Al/Al alloy
13.
Al/Al alloy
14.
2 mm
15.
3 mm
16.
Indoor/Outdoor
3 phase 4 wire
3 kV
(Dry/Wet)
50 kA for 1 sec
Non segregated
i) Rated Voltage
415 V
3 kV
b) Wet
3 kV
Porcelain
17.
18.
19.
40 deg C
40 deg C
20 deg C
Illumination
Lux level requirement - Area wise
REV. NO.: R3
Sl.
No
1
Area / Structure
Cable vault
Average
illumination
level in Lux
100
Type of
Type of fixture
Luminaire
1 x 70 W
HPSV lamp
gear.
2
All switchgear
room
250
300
Energy
efficient
lamps
Battery rooms
150
Energy
efficient
lamps 2 x 28
W FL
Outside working
Conveyors
areas
enclosed
200
Energy
cover.
lamps
70
100
efficient
250 W HPSV
lamp
1 x 70 W
HPSV lamp
gear box.
8
Underground
conveyor tunnel
Crusher house,
junction towers
40
70 W HPSV
box
100
1 x 70 W
HPSV lamp
control gear.
10
Coal yard
25
Flood light
1 x 400 W
11
Coal unloading,
50
Flood light
1 x 400 W
REV. NO.: R3
HPSV
Sl.
No
Area / Structure
Average
illumination
Type of
Type of fixture
level in Lux
Luminaire
track hopper
HPSV
stacker reclaimer
Road and Yard
lighting
12
Roads and
compounds
10
1 x 70 W
HPSV / LED
control gear
13
Parking area
14
15
50
cabins (air
350
350
conditioned areas)
with false ceiling
but non air -
1 x 250 W
HPSV
Energy
efficient 2 x
28 W FL
Energy
efficient 2 x
28 W FL
conditioned
16
350
conditioned
Energy
efficient 2 x
28 W FL
without false
ceiling
17
Corridors,
walkways, stair
case, etc.,
18
Building periphery
lighting
100
1 x 28 W FL
1 x 70 W
HPSV lamp
Control room
20
Other areas
1 x 100 W
1 x 100 W
REV. NO.: R3
incandescent
lamp
incandescent
Sl.
Area / Structure
No
21
Average
illumination
level in Lux
Stair case /
landing
Type of
Type of fixture
Luminaire
reflector
lamp
1 x 100 W
reflector
lamp or CFL.
incandescent
Other than above areas, bidder should get approval for Lux level from Owner /
Consultant.
DC lighting percentage
S.No
Area Description
DC lighting (% of total)
100
10
Cable vault
100
10
Transformer yard
100
Control room
100
10
Stair case
100
10
devices / meters as per relevant standard to prove the specified values. The
working plant shall include the floor level and also depending on the area.
Lighting transformer details
Sl. No
Description
Particulars
Type
Voltage Rating
433/415V
Cooling
AN
Impedance
Voltage Control
Class of Insulation
REV. NO.: R3
70C
Neutral
Solidly Grounded
Mounting
of 50 Deg C
Essential/Minimum
Description
Requirements
CPU
1.0
Type
32/64 BIT
2.0
Processor speed
100 MHz
3.0
CPU Memory
1 MB
4.0
Flash Memory
Built in 256 KB
5.0
Drive
DVD read/write
6.0
0.4
7.0
Yes
8.0
Embedded Communication
Serial
9.0
Bidder to decide
10.0
Discrete I / O processing
6000
11.0
Analog I / O processing
8 KB
12.0
Protocols Supported
micro
function
sec
Boolean
Input Module
24 V DC Positive / Negative
2.0
Module Function
Input
3.0
24 V DC Positive / Negative
4.0
32/16
5.0
Input Group
Channel Indication
7.0
Fault Indication
8.0
0 30V DC
9.0
ON State Voltage
13.5 30 V DC
10.0
05V
REV. NO.: R3
S.No.
11.0
Essential/Minimum
Description
Requirements
12.0
500V rms
13.0
14.0
Surge Immunity
1kV peak
15.0
Impedance
20 K Ohms ( Typical )
16.0
Yes
Module Type
2.0
Module Function
Output
3.0
32/16
4.0
Output Group
5.0
Channel Indication
6.0
Fault Indication
7.0
20 60 V DC
8.0
Response time ON
1 ms Max.
9.0
1 ms Max.
10.0
11.0
500V rms
12.0
module
back plane
Surge Immunity
1kV peak
Module Type
Discrete
2.0
Module Function
Output
3.0
Relay
4.0
24V DC
5.0
32 Non-Latching Type
6.0
Channel Indication
7.0
Fault Indication
REV. NO.: R3
S.No.
Essential/Minimum
Description
Requirements
Module
8.0
Response time ON
10
ms
with
ms
typical
bounce time
9.0
Maximum Power
60W Typical
10.0
11.0
12.0
Contact Type
13.0
Contact Resistance
50 mw ( by voltage drop 6V DC
1A ) typical
14.0
Required.
Module Type
Analog
2.0
Current
3.0
16/8
4.0
4-20 mA
5.0
Channel Indication
6.0
Fault Indication
7.0
Response Time
5 ms Typical
8.0
Resolution
9.0
Accuracy
10.0
11.0
12.0
Isolation
between
channel
500V rms
to 1000V DC/AC
channel
13.0
1000V DC/AC
14.0
Surge Immunity
1kV peak
Module Type
Analog
2.0
Module Function
Output
3.0
Output Type
Current
4.0
16/8
5.0
Analog Output
4-20 Ma / 0-20 Ma
REV. NO.: R3
S.No.
Essential/Minimum
Description
Requirements
6.0
Channel Indication
7.0
Fault Indication
8.0
9.0
10.0
Isolation
between
channel
500V rms
to 1000V DC/AC
channel
11.0
1000V DC/AC
12.0
Surge Immunity
1kV peak
13.0
Impedance
14.0
Resolution ( Voltage )
12 Bits
I / O Interface Module
1.0
Module Type
Bus Interface
2.0
Electrical Isolation
Non-isolated
differential
communication
3.0
Communication Module
1.0
Module Type
2.0
500 KB / sec
3.0
Electrical Isolation
Non-isolated
differential
communication
4.0
5.0
Power Supply
1.0
Module Function
2.0
Power Source
3.0
Output Power
Power Supply
240 V AC, 50Hz
As per System requirement
Features
Essential/Minimum Requirements
1.
Make
Bidder to state
2.
Model No.
Bidder to state
3.
Type of Transmitter
4.
Accuracy
Doc. No.: E072-03-CHP-O-02
Sl.No.
5.
Features
Essential/Minimum Requirements
4-20 mA DC (Analog)
along with
(based
on HART protocol)
6.
7.
Stability
for
Ranges
up
to
and
including70 Kg/cm.
0.25% of calibrated span for six
months for Ranges more than 70
Kg/cm (g).
8.
9.
10.
Load impedance
Housing
durable
corrosion
resistant
coating.
11.
Over Pressure
12.
Connection (Electrical)
13.
Process connection
14.
Adjustment/calibration/main
tenance
well
as
manual
adjustability
from
PC
based
system.
In
addition total two (2) no. of handheld type universal calibrators per
unit, compatible with HART protocol,
shall be provided.
15.
Accessories
-Diaphragm
seal,
pulsation
for
DP/level/flow
transmitters.
REV. NO.: R3
Sl.No.
Features
Essential/Minimum Requirements
-For
hazardous
area,
explosions
Diagnostics
17.
Power supply
24V DC 10%.
18.
Repeatability
19.
Sensitivity
20.
Yes
Notes.
1. LVDT type is not acceptable.
Where the process fluids are corrosive, viscous, solid bearing or slurry type,
diaphragm seals shall be provided. Parts below the diaphragm shall be
removable for cleaning. The entire volume above the diaphragm shall be
completely filled with an inert liquid suitable for the application. For HFO,
LFO Applications, SS capillary with thin wafer element with ANSI RF flanged
ends are to be provided.
Features
Essential/Minimum Requirement
1.
Make
Bidder to state
2.
Model No.
Bidder to state
3.
material
4.
Body material
Die-cast aluminum
5.
Dial size
150 mm
6.
End connection
7.
Accuracy
1% of span
8.
Scale
9.
Range selection
10.
11.
Housing
12.
Zero/span adjustment
Provided
13.
Identification
REV. NO.: R3
Accessories
SS Thermo well
15.
Material of Bourdon/
316 SS / 304 SS
movement
16.
Repeatability
17.
Response Time
40 seconds
18.
19.
Applicable Standard
BS 1401
20.
Others
Features
Essential/Minimum Requirement
1.
Make
Bidder to state
2.
Model No.
Bidder to state
3.
material
4.
Body material
Die-cast aluminum
5.
Dial size
150mm
6.
End connection
7.
Accuracy
1% of span
8.
Scale
9.
Range selection
10.
11.
Housing
12.
Zero/span adjustment
Provided
13.
Identification
14.
Accessories
15.
16.
Material of Bourdon/
movement
Enclosure
REV. NO.: R3
17.
Applicable standard
18.
Accessories
Notes:
Where the process fluids are corrosive, viscous, solid bearing or slurry type,
diaphragm seals shall be provided. Parts below the diaphragm shall be
removable for cleaning. The entire volume above the diaphragm shall be
comp-lately filled with an inert liquid suitable for the application.
For HFO, LFO Applications, SS capillary with thin wafer element with ANSI RF
flanged ends are to be provided.
Level Gauges
Sl.No
Features
Essential/Minimum Requirement
1.
Make
Bidder to state
2.
Model No.
Bidder to state
3.
material
4.
Body material
5.
Dial size
6.
End connection
7.
Accuracy
2%
8.
Scale
Linear vertical
9.
Range selection
10.
11.
Housing
12.
Identification
drain/vent 15 NB
Accessories
14.
Visible Length
REV. NO.: R3
Notes:
Length of gauge glass shall not be more than 1400 mm. If the vessel is
higher, multiple gauge glasses with 50 mm overlapping shall be provided.
Temperature Switches
Sl. No
Features
Essential/Minimum Requirement
1.
Make
Bidder to state
2.
Model No.
Bidder to state
3.
Sensing Element
4.
Material
5.
End connection
6.
7.
Repeat-ability
8.
No. of contacts
9.
Rating of contacts
contact
DDCMIS or PLC)*
10.
Elect. Connection
Plug in socket
11.
adjustment
12.
Enclosure
13.
Accessories
14.
Mounting
glands
mounting
15.
Feature
1.
Make
Bidder to state
2.
Model No.
Bidder to state
3.
Sensing Element
REV. NO.: R3
Sl. No
Feature
4.
Material
AISI 316 SS
5.
End connection
6.
7.
Repeat-ability
8.
No. of contacts
9.
Rating of contacts
10.
Elect. Connection
11.
Set
point/
dead
Plug in socket
band Provided over full range
adjustment
12.
Enclosure
Weather
and
13.
Accessories
Syphon,
snubber,
minimum IP-55
dust
proof
as
chemical
per
seal,
Mounting
15.
Switch Type
16.
Accuracy
+1%
vibration proof.
Level Switches
Sl. No
Feature
1.
Make
Bidder to state
2.
Model No.
Bidder to state
3.
Sensing Element
4.
Material
5.
End connection
Manufacturer standard
6.
7.
Repeat-ability
8.
No. of contacts
REV. NO.: R3
Sl. No
9.
Feature
Rating of contacts
10.
Elect. Connection
Plug in socket
11.
12.
Enclosure
13.
Accessories
14.
Switch type
sealed,
shock
&
vibration proof.
RF Type Level Switch
Sl.
Essential / Minimum
Feature
No
Requirement
A.
Application
B.
Electronic Controller
240 V AC, 50 Hz
Input Supply
Body material
Relay Output
Nos.
Relay
Changeover
Class of Protection
IP-66
Ambient Temperature
55 Deg. C (Max)
Local Indication
Green
Normal Level
Red
Alarm Level
Yellow
Probe Healthy
Cable Connectio
C.
Repeatability
Sensing Probe
Type of Probe
Rigid
Material
Cast Aluminium
REV. NO.: R3
100%
Sl.
Essential / Minimum
Feature
No
Requirement
PTFE
IP-66
Mounting
Side Mounted
Cable Connection
5/8 ET(1No.)
Process Connection
40 NB BSP THREADED
Signal Cable
Coaxial
cable
Between
for
Sensing
Connection
probe
and
Type
Application
Environment Class
Orientation
Vertical
Probe Type
Probe Material
SS 316L
Connection material
SS 316L
Accuracy
+/- 5 mm
Type(Transmitter)
SMART, 2 Wire
Operating Principle
Output
4-20 mA, DC
Electrical Connection
NPT
Enclosure Class
IP 66
Electrical Power
11-42 V DC
Housing material
Local Display
LCD Display
Units of Measurement
Length mm
REV. NO.: R3
Measuring Ranges
Up to 30 meters (typical)
Signal Processing
Operating Freq
Display
Diagnosis
On-line
Status
Construction
Plug-on board
Power supply
240 V AC 50 Hz / 24V DC
Signal Output
Hysteresis
Output contacts
Resolution
0.1% of span
Operating temp
MOC Sensor
Humidity
Enclosure
8A 230V AC.
Polycarbonate housing.
Cable Connection
3/4" ET
Mounting
Accessories
Cable
gland,
prefab
cable,
mounting
accessories.
ZERO SPEED SWITCH
Probe
Type
Size
As per requirement
Protection class
Enclosure type
Supply voltage
Speed range
Electronic unit
REV. NO.: R3
Repeatability
Within 1%.
Differential
2 NO + 2 NC
Contact rating
Ambient Temperature
0-50 Deg. C.
Preferable features
Protection class
Enclosure type
Flame proof
Output contacts
2 NO + 2 NC
Contact Rating
Protection class
Enclosure type
Flame proof
Output contacts
2 NO + 2 NC
Contact Rating
Operating handle
ends
REV. NO.: R3
Description
1.0
Belt Conveyors
1.1
Units
Values
Meter
1.3
1.4
Capacity of conveyor
1.4.1
Designed
1.4.2
Rated
1.5
Material
1.5.1
1.5.2
T/cum
1.6
M/sec.
1.7
Belt Details
1.7.1
Belt width
1.7.2
Belt specification
1.7.3
1.7.3.1
Top
mm
1.7.3.2
Bottom
mm
1.8
TPH
strength
1.9
Belt Tension
1.9.1
Actual
1.9.2
Allowable
1.10
1.11
1.12
1.13
jointing allowance
1.14
1.14.1
Dia of Pulley
1.14.2
Shell thickness
1.14.3
1.14.4
conveyor
REV. NO.: R3
Sl. No
Description
1.14.5
1.14.6
Rubber of lagging
1.15
1.15.1
Type
1.15.2
Casing
1.15.3
Sealing
1.15.4
Lubrication
1.15.5
Bearing life
1.16
Pulley width
1.17
Pulley Material
1.18
Shaft Material
1.19
Maximum allowable
Units
Values
deflection of
Technological structures
1.20.1
1.20.2
1.21
mm
Conveyor
1.22
1.23
Tensioning arrangement
1.23.1
type
1.24
Idlers
1.24.1
Roller Material
1.24.2
1.24.3
1.24.5
Spacing
1.24.5.1
Carry ing
1.24.5.2
Return
1.24.5.3
Impact
1.24.5.4
1.24.5.5
1.24.6
Bearing
1.24.6.1
Life
1.24.6.2
Type
1.24.6.3
Make
1.24.6.4
Type of Seals
1.24.6.5
Lubrication arrangment
REV. NO.: R3
mm
Sl. No
Description
1.25
1.25.1
Manufacturer
1.25.2
Type
1.25.3
Reduction Ratio
1.25.4
1.25.5
Mechanical efficiency
1.25.6
Material of construction
1.25.6.1
Casing
1.25.6.2
Gear
1.25.6.3
Pinion
1.25.7
Duty Condition
1.25.8
1.25.9
1.25.9.1
Provided
1.25.9.2
1.25.10
1.25.11
Location
Units
Values
Yes/No
Indoor /
Outdoor
1.26
Belt Cleaners
1.26.1
1.26.2
1.27
Skirt Board
1.27.1
1.27.2
1.27.3
1.27.4
1.27.5
Skirt height
1.27.6
Skirt weight
1.27.7
1.27.8
1.27.9
1.27.10
1.27.11
REV. NO.: R3
Sl. No
Description
Units
Values
Fluid coupling
1.28.1
Make
1.28.2
Type
1.28.3
Rated KW transmitted
1.28.4
1.28.5
Rated sleep
1.28.6
1.28.7
Type of cooling
1.28.8
Hours of Operation/Day
1.28.9
1.28.10
Direction of rotation
1.28.11
Balancing
1.29
Flexible Coupling
1.29.1
Make
1.29.2
Type
1.29.3
1.29.4
Service Factor
2.
Coal Crusher
2.1
Material to be crushed
2.2
2.3
2.4
Material Temperature
2.5
Ambient Temperature
2.6
Hours/day
2.7
Bulk density
T/m3
2.8
Capacity
TPH
2.9
Output size
2.10
Material of construction
2.10.1
Rotor
2.10.2
Suspension Bars
2.10.3
2.10.4
2.10.5
2.10.6
Frame liners
2.11
Bearing
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
Sl. No
Description
Units
2.11.1
Bearing Type
2.11.2
Life
2.11.3
Lubrication
2.12
Cooling Arrangement
2.13
Enclosure
2.14
Power Consumption
2.15
Motor Rating
3.
Chutes
3.1
Material handled
3.2
Bulk density
T/M3
3.3
Lump size
mm
3.4
Belt width
mm
3.5
3.6
Flow rate
TPH
3.7
Belt speed
m/s
3.8
Pulley width
3.9
Fabrication
3.10
Material of Construction
3.10.1
3.10.2
Thickness
3.10.3
c) Liner material
3.10.4
d) Liner thickness
3.11
4.
Electric Hoist
4.1
4.2
4.3
Capacity
4.4
Travel speed
M/Sec
4.5
Hoisting speed
M/Sec
4.6
Total lift
4.7
MM
Values
Hrs
Site/shop
mm
mm
arrangement
4.8
Applicable standards
4.9
curvature
5.
Manual Hoist
5.1
REV. NO.: R3
Sl. No
Description
Units
5.2
5.3
Capacity
5.4
Type of travel
M/Sec
5.5
Kg
5.6
Total lift
5.7
Applicable standards
5.8
Values
curvature
6.
Flap Gates
6.1
Service Requirement
6.2
Type
6.3
Required numbers
6.4
Material handled
6.5
Material size
mm
6.6
Bulk Density
T/M3
6.7
Moisture content
6.8
Hours of operation/day
6.9
6.9.1
No of switching/hr
6.9.2
Travel range
6.9.3
Actuator type
6.9.4
6.9.5
6.9.6
Degree of protection
6.10
6.10.1
Gate
6.10.2
Liner
6.11
Bearing
6.11.1
Type
6.11.2
Life
6.11.3
Method of lubrication
7.
7.1
Type
7.2
Location
7.3
Required Nos.
7.4
REV. NO.: R3
mm
PAGE 413 OF 506
Sl. No
Description
Units
7.5
Bulk density
T/M3
7.6
Moisture content
7.7
Size of opening
7.8
7.9
Type of chain
7.10
7.11
7.12
Materials of Construction
7.12.1
Slide gate
7.12.2
Rack
7.12.3
Pinion
7.12.4
Drive shaft
7.12.5
7.13
Bearing
7.13.1
Type
7.13.2
Life
7.13.3
Method of lubrication
7.13.4
Type of Seal
7.14
7.15
Motor rating
Vibrating Screens
8.1
Location
8.2
Rated capacity
8.3
No required
8.4
Material to be handled
8.5
8.6
Output size
8.7
8.8
9.1
Type
9.2
9.3
9.4
9.5
Weighing type
9.6
9.7
Values
Kg
TPH
REV. NO.: R3
Sl. No
Description
Units
Values
and remote
9.8
Guaranteed accuracy
9.9
9.10
Control station
9.11
Control cabinet
9.12
Weighing range
9.13
Electrical
10
10.1
Type
10.2
10.3
MM, Kg
10.4
MM
10.5
Gauss
M/min
10.7
Yes/No
10.8
10.9
Force Index
11
Metal Detectors
11.1
Type
11.2
11.3
Detecting capacity
11.4
Annunciation/Hooter provided
11.5
11.6
Material handled
11.7
Capacity (flow)
TPH
11.8
Size of material
mm
11.9
Bulk Density
T/cum.
11.10
Material of Construction
11.11
11.12
Sensitivity
12
REV. NO.: R3
Sl. No
Description
Units
12.1
Bag filter
12.2
12.3
12.4
M3/hr
12.5
M2
12.6
Air-to-cloth ratio
12.7
Values
Mg/nm3
atmosphere
12.8
Efficiency
12.9
Materials of construction
12.9.1
a) Bags
12.9.2
b) Cage of bags
12.10
Dry Cyclone
12.11
Manufacturer
12.12
12.13
Model No.
12.14
Type
12.15
Capacity
12.16
Pressure drop
12.17
13
13.1
13.2
M3/hr
%
Yes/No
description furnished?
13.3
Spray nozzles
13.4
13.5
13.6
Nozzle Spacing
13.7
Tanks
13.7.1
Number
13.7.2
Material of construction
13.7.3
Capacity
14
Stacker/Reclamer
14.1
14.2
Number required
14.3
14.4
MM
MM
M3
REV. NO.: R3
TPH
Sl. No
14.5
Description
Average Capacity (over a period of 4
Units
Values
TPH
hours) (Rated)
14.6
Peak (Rated)
TPH
14.7
Material handled
14.8
Belt width
mm
14.9
Wind pressure
Kg/m2
14.9.1
Operating
14.9.2
Non-operating
14.10
tones
14.11
14.11.1
Track gauge
14.11.2
Rail size
14.11.3
Length of runway
14.11.4
14.11.5
14.11.6
14.12
Bucket wheel
14.12.1
14.12.2
Number of bucket
14.12.3
Width of bucket
14.12.4
14.13
Material of construction
14.13.1
Bucket wheel
14.13.2
Bucket
14.13.3
14.14
Boom Conveyor
14.14.1
Length
14.14.2
Width
14.14.3
Troughing angle
14.14.4
Belt Speed
14.14.5
Range of Luffing
14.14.6
14.14.7
14.14.8
14.14.9
with impact
graded level
REV. NO.: R3
Sl. No
Description
14.14.10
14.14.11
14.15.
14.15.1
Bucket wheel
14.15.2
Slewing
14.15.3
LT drive
14.16
Type of brakes
14.16.1
14.17
Stability Factor
14.17.1
Units
Values
14.18
14.19.
CRD
14.19.1
Type
14.19.2
No. furnished
14.19.3
Size
14.19.4
Capacity
14.20
Operator Cabin
14.20.1
Type
14.20.2
Location
15
Sump Pump
15.1
Designation
15.2
15.3
Design Flow
(m3/hr)
15.4
Head
MWC
15.5
Speed
RPM
15.6
Operation
15.7
Depth of sump
bottom of sump
15.8
Base Frame
15.9
Constructional Features
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
Sl. No
Description
15.9.1
Type of pump
15.9.2
15.9.3
Prime Mover
15.10
Material of Construction
15.10.1
Casing
15.10.2
Impeller
15.10.3
Shaft
15.10.4
Column Pipe
15.10.5
Seal
15.10.6
Coupling type
15.10.7
Coupling
15.10.8
Coupling guard
15.10.9
Base plate
15.10.10
Gaskets
Units
16.
Apron Feeder
16.1
LOCATION
16.2
Capacity (Rated/Design)
16.3
Duty
16.4
Capacity Range
16.5
Number required
16.6
Material to be handled
16.7
mm
16.8
Bulk density
T/M3
16.9
16.10
Drive
17.
Dribble Feeder
TPH
17.1
LOCATION
17.2
Type
17.3
Capacity (Rated/Design)
17.4
Duty
17.5
Number required
17.6
Material to be handled
17.7
17.8
Type of Belt
17.9
mm
17.10
Width
mm
17.11
Take-up
Values
TPH
mm
REV. NO.: R3
Sl. No
18.
Description
Units
Values
18.1
Type
18.2
Location
18.3
Number
18.4
Weighment Position
18.5
18.6
18.7
18.8
Type of Wagon
19.
19.1
Type
19.2
Location
19.3
Type of nozzles
19.4
19.5
19.6
19.7
20.0.
VENTILATION SYSTEMS
20.1
20.1.1
Type
20.1.2
20.1.3
Capacity
20.2
20.2.1
No of Air Changes/hr
20.2.2
Type of fan
20.2.3
Location
20.2.4
20.2.5
Material of duct
20.2.6
Grills
Mg/Nm3
REV. NO.: R3
Mps
Sl. No
20.3
Description
Units
Values
20.3.1
Room size
20.3.2
21
HOPPERS
21.1
Designation
21.2
Number Required
21.3
21.4
21.5
21.6
21.7
Liner
22.0
22.1
Purpose
22.2
Capacity
22.3
Construction
23.0
23.1
Type
23.2
Location of sampler
23.3
23.4
Type of Primarycutter
23.5
Material of construction
23.5.1
Primary cutter
23.5.2
23.5.3
24.0
24.1
Type
24.2
Qty
24.3
24.4
Hauling capacity
24.5
Duty
24.6
Operating
hopper
Cu.m
TPH
24.8
Mode of Control
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
Sl. No
Description
Units
24.9
24.10
24.11
24.12
Track Gauge
25.0
EOT Crane
25.1
GENERAL
25.1.1
Manufacturer
25.1.2
Quantity
25.1.3
Values
25.1.5
Span
25.1.6
Distance
M
from
operating
floor
to
SPEEDS
25.2.1
M/min
25.2.2
M/min
25.2.3
Hoisting speed
M/min
25.3
25.4.
CLEARANCES
AND
HOOK
CONSTRUCTIONAL FEATURES
25.5.1
25.5.2
25.5.3
25.5.4
25.6
HOISTING SYSTEM
25.6.1
Rope
25.6.2
Rope diameter mm
25.6.3
Rope construction
25.6.4
25.6.5
25.6.6
25.6.7
Factor of safety
25.6.8
Rope drum
REV. NO.: R3
Sl. No
Description
25.6.9
25.6.10
Drum material -
25.6.11
25.7
Hook
25.7.1
Hook material
25.7.2
25.8
Hoist Brake
25.8.1
Number of brakes
25.8.2
Type
25.8.3
Make
25.8.4
Size
25.9
Limit Switch
25.9.1
Numbers
25.9.2
Type
25.9.3
Make
25.10
CROSS TRAVEL
25.10.1
CT brake
25.10.2
Number of brakes
25.10.3
Type
25.10.4
Make
25.10.5
Size
25.10.6
Wheels
25.10.7
Materials
25.10.8
Hardness
25.10.9
Limit switches
25.10.10
Number
25.10.11
Type
25.10.12
Make
25.10.13
Type of Stoppers
25.10.14
25.10.15
25.11
25.11.1
Make
25.11.2
Type
25.11.3
Rating
25.11.4
Permissible Starts/Hr.
Units
Values
mm
mm
Mm
REV. NO.: R3
Sl. No
25.12
Description
Units
Values
CRANE CONTROL
Electrical
Power Transformers
S. No
Description
1.
Reference standard
2.
Make& Quantity
3.
Rating
4.
Cooling
5.
Type
6.
Voltage Ratio
7.
Frequency (Hz)
8.
Number of windings
9.
Phases (Nos.)
10.
Particulars
Service
12.
13.
Duty
14.
Overload capacity
15
a) Full load
b) 80 % load
16.
17.
18.
50C ambient
a) ONAN
REV. NO.: R3
S. No
Description
Particulars
b) ONAF
19.
Winding material
20.
Windings
HV
LV
22.
i) H.V.
ii) L.V.
23.
Bushing HV/LV/LVn
i) Make
ii) Type
iii) Voltage class (kV)
iv) Rated power frequency withstand voltage
(kVrms)
24.
Minimum clearance
a) Between phases
i) In air (mm)
ii) In oil (mm)
b) Between phase and earth
i) In air (mm)
ii) In oil (mm)
25.
Vector group
26.
Tap Changer
i) Type
ii) Tap range
iii) Tap control
iv) Winding tapped (HV/LV)
27.
i) No load losses
ii) Load losses
iii) Cooler losses
28.
REV. NO.: R3
S. No
Description
Particulars
29.
30.
31.
voltage (%)
32
b) For 1 Minute
c) For 5 Seconds
33.
34.
35.
Cooling system
i) Number of Cooler Bank
ii) Capacity of Each Cooler Bank
iii) No of Radiators per Cooler Bank
iv) No of Fans per Cooler Bank
v) Whether Standby Fan for each cooler Bank
Provided
Insulating oil
i) Approximate volume (litre)
ii) 10% excess oil furnished (Yes/No)
iii) Type of oil preservation system provided
37
Marshalling box
i) Weather proof, suitable for outdoor duty
(Yes/No)
REV. NO.: R3
S. No
Description
Particulars
40.
41
Weights
Total
c) Oil
e) Total weight
f)
42
Un-Tanking weight
Shipping Section
Service Transformer
S.No
Description
Particulars
11/0.433 kV
1.
Reference standard
2.
Make
3.
Quantity
4.
Cooling
5.
Type
6.
Voltage Ratio
7.
Frequency (Hz)
8.
9.
Phases (Nos.)
10.
a)Principal tap
b) Maximum tap
c) Minimum tap
11.
Service
12.
13.
Duty
14.
Overload capacity
15.
REV. NO.: R3
S.No
Description
Particulars
17.
Winding material
19.
Windings
HV
20.
21.
Winding
(kVp/kV)
insulation
level
Impulse/power
frequency
i) H.V.
ii) L.V.
iii) L.V. neutral
22.
Bushing
HV/LV/LV(N)
i) Make
ii) Type
iii) Voltage class (kV)
iv) Rated power frequency withstand voltage (kVrms)
v) Rated lightning impulse withstand voltage (kVp)
vi) Creepage distance, mm
vii)Short circuit current rating
viii)Rated current
ix) Weight of bushing, kg
x) Applicable standard
24.
Clearances
a) Between phases
i) In air (mm)
ii) In oil (mm)
b) Between phase and earth
i) In air (mm)
ii) In oil (mm)
25.
Vector group
REV. NO.: R3
LV
S.No
26.
Description
Particulars
Tap Changer
i) Type
ii) Tap range
iii) Tap control
iv) Winding tapped (HV/LV)
ii) Provided with caution plate (Yes / No)
iii)
i) No load losses
ii) Load losses
iii) Tolerance on above mentioned losses (%)
28.
Efficiency at 75C
i) At full load
ii) At 75% load
iii) At 50% load
iv) Maximum efficiency
v) Load and power factor at which the max. efficiency
occurs
29.
30.
31.
32.
33.
REV. NO.: R3
S.No
Description
Particulars
(Sec.)
34.
Terminal connections
i) H.V.
ii) L.V.
iii) L.V. neutral
35.
Marshalling box
i) Weather proof (Yes/No)
ii) Degree of protection
36.
37.
38.
39.
40.
41.
HV to tank
LV to tank
HV to LV
42.
43.
Terminal blocks
i) Make
ii) 10% spare terminals furnished? (Yes/No)
44.
Wiring
i) Cable type
ii) Voltage grade, Volt
iii) Conductor size
iv) Current circuits, mm2
v) Other circuits, mm2
45.
Radiator
a)
Overall dimensions l x b x h
b)
c)
46.
Type of mounting
47.
48.
Accessories
Each
transformer
accessories (Yes/No)
furnished
with
REV. NO.: R3
fittings
and
S.No
Description
Particulars
50.
51.
52.
accessories
Approximate weights, kg
a) Core and coil
b) Oil
c) Un tanking weight
d) Total weight
53.
Shipping data
q) Weight of the heaviest package, kg
r) Dimension of the largest package (LxBxH), mm
s) Parts detached for transit
54.
Rollers
a) Quantity
b) Whether bi-directional (Yes/No)
c) Gauge
d) Whether lockable in both the positions (Yes/No)
55.
56.
Make
b)
Type (Yes/No)
c)
Quantity
d)
Voltage
e)
Current ratio
f)
g)
h)
Knee-point voltage
i)
Short-time
j)
k)
l)
Applicable standard
withstand
duration in secs.
current
WTI
in
amps.
NCT
and
Termination Arrangement
a) Details
of
HV
cable
furnished? (Yes/No)
termination
arrangement
REV. NO.: R3
S.No
Description
Particulars
58.
Paint shade
HT Switchgear
S. No
Description
A)
1.
Make
2.
Type
3.
Reference Standard
4.
5.
6.
7.
Number of phases/poles
8.
9.
9.1
9.2
10.
11.
For 11 / 3.3 kV
12.
13.
14.
16.
Metal-clad construction?
17.
Degree of Protection
18.
19.
20.
Service
21.
Enclosure
22.
factory
i) Control voltage
ii) Service voltage
B)
Construction
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
S. No
1.
Description
For 11 / 3.3 kV
1.1
1.2
1.3
2.
2.1
2.2
Breaker Cubicle
Cubicle door can be closed with breaker in TEST position
(Yes/No)
3.
4.
4.1
4.2
Rear (mm)
5.
5.1
C)
BUSBARS
1.
Make
2.
3.
Reference Standard
4.
5.
Size (mm)
6.
Skin-effect ratio
7.
Reactance
8.
9.
10.
11.
12.
13.1
KA (rms)
13.2
14.
Bus Connections
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
S. No
Description
14.1
Silver plated
14.2
15.
16.
16.1
Make
16.2
Type
16.3
Reference Standard
16.4
16.5
16.6
16.7
17.
D)
1.
Colour finish
2.
Cable entry
For 11 / 3.3 kV
a) Power Cables-Bottom
b) Control Cables- Bottom
3.
4.
E)
CIRCUIT BREAKERS
1.
Make
2.
Type
3.
Reference standard
4.
5.
6.
7.
8.
9.
9.1
Symmetrical (kArms)
9.2
Asymmetrical (kArms)
10.
10.1
Rate of rise
10.2
Peak voltage
11.
11.1
Unloaded transformer
11.2
Loaded transformer
11.3
Unloaded lines
11.4
Induction Motor
12.
Insulation Level
REV. NO.: R3
S. No
Description
12.1
12.2
13.
13.1
A.C. component
13.2
D.C. component
14.
15.
15.1
15.2
15.3
16.
17.
18.
19.
20.
21.
22.
22.1
At tripping
22.2
At closing
23.
Type of contacts
23.1
Main
23.2
Arcing
24.
24.1
24.2
25.
For 11 / 3.3 kV
Material of contacts
25.1
Main
25.2
Arcing
25.3
25.4
26.
27.
27.1
Between poles
27.2
28.
29.
29.1
Rating (kW)
29.2
29.3
REV. NO.: R3
S. No
30.
Description
Closing Coil
30.1
Voltage (V)
30.2
30.3
31.
Tripping Coil
31.1
Voltage (V)
31.2
31.3
32.
For 11 / 3.3 kV
33.
Operating Duty
34.
Operating Mechanism
34.1
Type
34.2
34.3
34.4
35.
Breaker/Cubicle Accessories
36.
37.
37.1
37.2
37.3
37.4
37.5
Operation counter
37.6
Charge/Discharge indication
37.7
37.8
37.9
37.10
37.11
38.
Cell/Auxiliary Switch
38.1
38.2
Contacting rating at
a) Rated & Making current
b) Interrupting current (Inductive)
c) P.F. for A.C. & L/R for D.C. interruption
39.
40.
REV. NO.: R3
S. No
Description
For 11 / 3.3 kV
41.
rating)
42.
43.
Auxiliary Voltage
i) Closing
ii) Tripping
iii) Spring Charging
44.
F)
1.
Push Buttons
1.1
Make
1.2
1.3
1.4
2.
2.1
2.2
2.3
Watts/voltage
2.4
2.5
3.
Selector Switch
3.1
Make
3.2
3.3
3.4
3.5
G)
1.
Make
2.
Type
3.
Reference Standard
4.
CT ratios
5.
6.
6.1
6.2
(kA rms)
REV. NO.: R3
S. No
6.3
Description
Class of insulation
6.4
6.5
6.6
7.
7.1
Class
7.2
7.3
7.4
8.
Metering C.T.
8.1
8.2
8.3
8.4
9.
9.1
Relaying C.T.
Incomer/Tie feeder V.A Burden class
9.2
9.3
9.4
H)
1.
Make
2.
Type
3.
Reference Standard
4.
Voltage ratio
5.
6.
Accuracy class
7.
VA burden (VA)
8.
8.1
Continuous
8.2
30 seconds
9.
For 11 / 3.3 kV
Class of insulation
10.
11.
12.
Winding Connection
12.1
Primary
12.2
Secondary
I)
FUSES
1.
Voltage class
2.
Rupturing capacity
3.
Rated current
REV. NO.: R3
S. No
Description
For 11 / 3.3 kV
4.
5.
J)
RELAYS
1.
2.
3.
Type of mounting
4.
Reference standard
5.
6.
All
specification (Yes/No)
relevant
(Yes/No)
relay
leaflets
and
catalogue
furnished
RELAY DETAILS
1.
Incomer/Tie
1.1
Make/Type
1.2
1.3
a)
b)
c)
2.
Transformer feeder
2.1
Make/Type
2.2
2.3
a)
b)
c)
3.
Motor feeder
3.1
Make/Type
3.2
3.3
a)
b)
c)
4.
4.1
Make/Type
4.2
a)
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
S. No
Description
For 11 / 3.3 kV
b)
c)
K)
METERS
1.
Make
2.
Type
3.
Reference Standard
4.
Size
5.
Scale
6.
Accuracy class
7.
8.
Meter switch
8.1
Make
8.2
Type
8.3
Catalogue No.
L)
SECONDARY WIRING
1.
2.
Voltage grade
3.
Conductor material
4.
4.1
Potential circuit
4.2
5.
M)
TERMINAL BLOCK
1.
Make
2.
Type
3.
Catalogue No.
4.
N)
CABLE TERMINATION
1.
O)
1.
Make
2.
Type
3.
4.
specified (Yes/No)
Cable Lugs
4.1
Type
4.2
Material
5.
Cable Gland
5.1
Type
5.2
Material
REV. NO.: R3
S. No
5.3
Description
With tappered washer
5.4
5.5
a)
b)
c)
P)
GROUND BUS
1.
2.
Material
3.
Size
Q)
NAME PLATE
1.
Material
2.
Thickness
3.
3.1
Panel
3.2
Equipment/ devices
R)
1.
Cubicle Heater
1.1
Thermostat controlled?
1.2
Wattage
1.3
2.
Voltage
Plug Socket
2.1
Type
2.2
Rating
3.
Motor Heater
3.1
3.2
3.3
4.
S)
A.C./D.C. SUPPLY
1.
1.1
1.2
2.
For 11 / 3.3 kV
2.1
2.2
T)
TROPICAL PROTECTION
1.
2.
REV. NO.: R3
S. No
U)
1.
Description
For 11 / 3.3 kV
PAINTING
Finish of switchgear
1.1
Inside
1.2
Outside
V)
1.
Earthing equipment
2.
3.
Test cabinet
W)
1.
2.
3.
4.
5.
6.
Installation
X)
CONTACTORS
1.
2.
3.
Rated Frequency
4.
5.
6.
Utilization category
7.
8.
9.
10.
11.
Asymmetrical current
12.
13.
a)
AC component
b)
DC component
Operating time
a)
Closing time
b)
Opening time
Y)
TRANSDUCERS
1.
CURRENT TRANSDUCERS
1.1
Input
1.2
Rated Frequency
1.3
Output
1.4
REV. NO.: R3
S. No
Description
1.5
For 11 / 3.3 kV
Accuracy
2.
VOLTAGE TRANSDUCERS
2.1
Input
2.2
Output
2.3
Accuracy
3.
VAR TRANSDUCERS
3.1
Input
3.2
Rated Frequency
3.3
Output
3.4
Accuracy
4.
WATT TRANSDUCERS
4.1
Input
Rated Frequency
Output
Accuracy
5.
FREQUENCY TRANSDUCERS
5.1
Input
5.2
Rated Frequency
5.3
Range
5.4
Output
5.5
Accuracy
Z)
TESTS
1.
1.1
1.2
1.3
1.4
LT Switchgear
S. No
Description
A)
1.
Make
2.
Type
3.
Reference Standard
Particulars
4.
5.
6.
7.
Number of phases/poles
8.
9.
REV. NO.: R3
S. No
Description
Particulars
voltage (kVrms)
9.1
9.2
10.
11.
12.
Short time rating for bus bars, circuitbreakers, current transformers and
switch gear assembly (kArms)
13.
14.
15.
16.
Metal-clad construction
17.
Degree of Protection
18.
19.
B)
Construction
1.
1.1
1.2
1.3
2.
Breaker Cubicle
2.1
2.2
3.
4.
4.1
4.2
Rear (mm)
5.
5.1
REV. NO.: R3
S. No
Description
Particulars
b) Bus coupler
C) Transformer
d) Motor
C)
BUSBARS
1.
Make
2.
3.
Reference Standard
4.
5.
Size (mm)
6.
Skin-effect ratio
7.
Reactance
8.
9.
ambient
10.
11.
12.
13.1
kA (rms)
14.
Bus Connections
14.1
Silver plated
14.2
15.
16.
16.1
Make
16.2
Type
16.3
Reference Standard
16.4
16.5
16.6
16.7
D)
1.
Colour finish
CONSTRUCTIONAL REQUIREMENTS
REV. NO.: R3
S. No
2.
Description
Particulars
Cable entry
a) Power Cables-Bottom
b) Control Cables- Bottom
3.
4.
E)
CIRCUIT BREAKERS
1.
Make
2.
Type
3.
Reference standard
4.
5.
6.
7.
8.
9.
ambient
an ambient of 50C
and operating duty
9.1
Symmetrical (kArms)
9.2
Asymmetrical (kArms)
10.
10.1
Rate of rise
10.2
Peak voltage
11.
11.1
Unloaded transformer
11.2
Loaded transformer
11.3
Unloaded lines
11.4
Induction Motor
12.
Insulation Level
12.1
12.2
13.
s wave (kVp)
13.1
A.C. component
13.2
D.C. component
14.
15.
15.1
15.2
15.3
REV. NO.: R3
S. No
Description
Particulars
16.
17.
18.
19.
20.
21.
22.
22.1
At tripping
22.2
At closing
23.
Type of contacts
23.1
Main
23.2
Arcing
24.
24.2
25.
Material of contacts
25.1
Main
25.2
Arcing
25.3
25.4
26.
27.
27.1
27.2
Between poles
Between live parts and ground
28.
29.
29.1
Rating (kW)
29.2
29.3
30.
Closing Coil
30.1
Voltage (V)
30.2
30.3
31.
Tripping Coil
31.1
Voltage (V)
31.2
31.3
REV. NO.: R3
S. No
Description
Particulars
32.
33.
Operating Duty
34.
Operating Mechanism
34.1
Type
34.2
34.3
34.4
35.
Breaker/Cubicle Accessories
36.
37.
the following
37.1
37.2
37.3
37.4
37.5
Operation counter
37.6
Charge/Discharge indication
37.7
37.8
37.9
37.10
37.11
37.12
Cell/Auxiliary Switch
Are switch contacts convertible types?
(Yes/No)
Contact rating at
a) Make or Continuous
b) Break (Inductive)
REV. NO.: R3
S. No
Description
Particulars
39.
40.
41.
43.
F)
1.
Push Buttons
1.1
Make
1.2
1.3
Contact rating at
a) Make and Continuous (Amp.)
b) Break [Inductive] (Amp.)
1.4
2.
2.1
Make
2.2
2.3
Watts/voltage
2.4
3.
3.1
Selector Switch
Make
3.2
3.3
Contact rating at
a) Make and Continuous (Amp.)
b) Break [Inductive] (Amp.)
3.4
G)
1.
Make
2.
Type
3.
Reference Standard
4.
CT ratios
5.
6.
6.1
6.2
6.3
Class of insulation
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
S. No
6.4
Description
Particulars
6.5
6.6
7.
(Yes/No)
7.1
Class
7.2
7.3
7.4
8.
Metering C.T.
8.1
8.2
8.3
9.
Relaying C.T.
9.1
9.2
9.3
H)
1.
Make
2.
Type
3.
Reference Standard
4.
Voltage ratio
5.
6.
Accuracy class
7.
VA burden (VA)
8.
8.1
Continuous
8.2
30 seconds
9.
Class of insulation
10.
11.
12.
Winding Connection
12.1
Primary
12.2
Secondary
I)
HRC FUSES
1.
Voltage class
2.
Rupturing capacity
3.
Rated current
4.
5.
REV. NO.: R3
S. No
Description
Particulars
J)
RELAYS
1.
2.
facilities
(Yes/No)
3.
Type of mounting
4.
Reference standard
5.
6.
specification (Yes/No)
RELAY DETAILS
1.
Incomer / Tie
1.1
Make/Type
1.2
1.3
(Multifunctional)
a)
b)
c)
2.
Transformer feeder
2.1
Make/Type
2.2
2.3
(Multifunctional)
a)
b)
c)
3.
Motor feeder
3.1
Make/Type
3.2
3.3
(Multifunctional)
a)
b)
c)
4.
4.1
REV. NO.: R3
S. No
4.2
Description
Particulars
a)
b)
c)
K)
METERS
1.
Make
2.
Type
3.
Reference Standard
4.
Size
5.
Scale
6.
Accuracy class
7.
8.
Meter switch
(Yes/No)
8.1
Make
8.2
Type
8.3
Catalogue No.
L)
INTERNAL WIRING
1.
2.
Voltage grade
3.
Conductor material
4.
4.1
Potential circuit
4.2
5.
M)
TERMINAL BLOCK
1.
Make
2.
Type
markers
3.
Catalogue No.
4.
N)
CABLE TERMINATION
1.
O)
1.
Make
2.
Type
3.
REV. NO.: R3
S. No
4.
Description
Cable Lugs
4.1
Type
4.2
Material
5.
Particulars
Cable Gland
5.1
Type
5.2
Material
5.3
5.4
5.5
a)
b)
c)
P)
GROUND BUS
1.
2.
Material
3.
Size
Q)
NAME PLATE
1.
Material
2.
Thickness
3.
3.1
Panel
3.2
Equipment/ devices
R)
1.
Cubicle Heater
1.1
Thermostat controlled?
1.2
Wattage
1.3
Voltage
2.
Plug Socket
2.1
Type
2.2
Rating
3.
Motor Heater
3.1
3.2
3.3
4.
S)
A.C./D.C. SUPPLY
1.
supply: -
1.1
1.2
REV. NO.: R3
S. No
2.
Description
Particulars
2.1
2.2
T)
TROPICAL PROTECTION
1.
2.
protection?
materials?
U)
PAINTING
1.
Finish of switchgear
1.1
Inside
1.2
Outside
V)
1.
Earthing equipment
2.
3.
Test cabinet
W)
1.
FEEDERS)
2.
3.
4.
5.
voltage (peak)
current
6.
Installation
X)
CONTACTORS
1.
2.
3.
Rated Frequency
4.
ambient
5.
6.
Utilization category
Y)
TRANSDUCERS
1.
CURRENT TRANSDUCERS
1.1
Input
1.2
Rated Frequency
1.3
Output
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
S. No
Description
Particulars
1.4
1.5
Accuracy
2.
VOLTAGE TRANSDUCERS
2.1
Input
2.2
Output
2.3
Accuracy
3.
VAR TRANSDUCERS
3.1
Input
3.2
Rated Frequency
3.3
Output
3.4
Accuracy
4.
4.1
WATT TRANSDUCERS
Input
Rated Frequency
Output
Accuracy
5.
FREQUENCY TRANSDUCERS
5.1
Input
5.2
Rated Frequency
5.3
Range
5.4
Output
5.5
Accuracy
Z)
TESTS
1.
1.1
1.2
1.3
1.4
2.
2.1
2.2
2.3
MCCB
S.No
Description
A)
General
1.
Make
2.
Type
Particulars
REV. NO.: R3
S.No
Description
3.
Service
4.
No. of poles
5.
Enclosure
6.
System
Particulars
AC
DC
AC
DC
i) Voltage
ii) Phase
iii) Frequency
iv) Combined voltage and frequency
variation
v) System grounding
7.
Rated current
i) Continuous (at 50C ambient &
within cubicle Amp.)
9.
10.
Operating Mechanism
i) Type
ii) Antipumping feature provided
iii) Trip free or fixed trip
11.
12.
Spare
auxiliary
switch
with
6NO+6NC
xi) Micro switch for release
13.
REV. NO.: R3
S.No
Description
Particulars
i) Interrupting
ii) Short time for 1 second
14.
15.
B)
CIRCUIT BREAKER
1.
Duty Cycle
2.
Breaking Current
i) A.C. Symmetrical
3.
Making Current
4.
Auxiliary Voltage
i) Closing
ii) Tripping
iii) Spring Charging
C)
CONTACTOR DUTY
i) AC
ii) DC
D)
SWITCH DUTY
AC
DC
i) Motor feeders
ii) Other feeders
Illumination
S.No
Description
Particulars
Technical Particular
1.
Lighting Fixture
2.
LUMINARIES
2.1
Flood Lighting
Housing
Front clamps
Mounting bracket
Reflector type
Gasket
Type of lamp
Lamp wattage
Ballast power consumption
Igniter details (if applicable)
2.2
Indoor Decorative
Housing
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
S.No
Description
Particulars
Gear Tray
End Plate
Mirror Assembly
Dimensions
Type of lamp
Wattage of lamp
Type of ballast
Ballast power consumption
Reflector type
Type of fitting
2.3
Indoor
Type of lamp
Wattage of lamp
Type of reflector
Type of Ballast
Ballast power consumption
Type of fitting
Any other information
2.4
2.5
Indoor Decorative
Rail
Cover
Diffusers
2.6
2.7
REV. NO.: R3
S.No
Description
Particulars
Mounting bracket
Reflector
Gasket
2.8
3.
Lighting Panel
Indoor
Outdoor
4.
5.
6.
Switch Board
i)
ii)
7.
Lighting Tower
i)
8.
Lighting Transformer
8.1
Type
8.2
KVA Rating
8.3
Voltage Rating
8.4
Cooling
8.5
Voltage Control
8.6
Class of Insulation
8.7
8.8
Neutral
8.9
Mounting
8.10
Impedance
9.
Indoor Lighting
9.1
9.2
Make of main DB
9.3
Make of sub-lighting DB
9.4
9.5
9.6
Control operations
9.7
Escape lighting
9.8
9.9
Make of cables
for same
REV. NO.: R3
S.No
Description
Particulars
9.10
9.11
DC
9.12
9.13
9.14
9.15
emergency
lighting
control
necessary contactor
board
with
areas
enclosure
9.17
9.18
Make of ballast
9.19
Make of switches
9.20
Erection
9.21
accessories
clamps, saddles
such
as
junction
9.22
9.23
Make
9.24
9.25
10.
Outdoor Lighting
10.1
10.2
Make of fittings
10.3
10.4
10.5
of
numbers
flame-proof
fittings
and
boxes,
catalogue
10.6
Control of lighting
10.7
Automatic
10.8
10.9
11
Timer details
12
REV. NO.: R3
HT Cables
S.No
Description
A)
GENERAL
1.
Make
2.
Type
3.
Applicable Standard
4.
5.
Location of factory
6.
Voltage grade
7.
B)
CONDUCTOR
1.
Applicable Standard
2.
Particulars
i) Continuous
ii) Short time
3.
Material copper/aluminium/grade
4.
Size
5.
6.
7.
No. of strands
8.
9.
10.
11.
12.
C)
SHIELDING ON CONDUCTOR
1.
Material
2.
Type/Applicable Standard
3.
Minimum thickness
4.
Whether extruded
5.
Tolerance of thickness
D)
INSULATION
1.
Material
2.
Type/Applicable Standard
3.
Thickness
4.
5.
6.
7.
8.
REV. NO.: R3
S.No
9.
Description
Particulars
E)
SHIELDING ON INSULATION
1.
Material
2.
Type/Applicable Standard
3.
Thickness
4.
5.
6.
7.
8.
F)
INNER SHEATH
1.
Material
2.
Type/Applicable Standard
3.
Thickness
4.
Whether extruded
5.
6.
7.
G)
ARMOURING
1.
Material
2.
Type/Applicable Standard
3.
4.
Size
5.
6.
H)
OVERALL SHEATH
1.
Material
2.
Type/Applicable Standard
3.
Thickness
4.
Colour
5.
Tolerance of thickness
6.
Whether extruded
7.
8.
9.
outer sheath
in outer sheath
REV. NO.: R3
S.No
I)
Description
Particulars
J)
L)
M)
N)
O)
Description
A)
GENERAL
1.
Make
2.
Type
3.
Applicable Standard
4.
5.
Location of factory
6.
Voltage grade
7.
B)
CONDUCTOR
1.
Applicable Standard
2.
Particulars
i) Continuous
ii) Short time
3.
Material copper/aluminium/grade
4.
Size
5.
6.
7.
No. of strands
8.
9.
10.
11.
12.
C)
INSULATION
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
S.No
1.
Description
Particulars
Material
2.
Type/Applicable Standard
3.
Thickness
4.
5.
6.
7.
8.
9.
D)
INNER SHEATH
1.
Material
2.
Type/Applicable Standard
3.
Thickness
4.
Whether extruded
5.
6.
E)
ARMOURING
1.
Material
2.
Type/Applicable Standard
3.
4.
Size
5.
6.
F)
OVERALL SHEATH
1.
Material
2.
Type/Applicable Standard
3.
Thickness
4.
Colour
5.
Tolerance of thickness
6.
Whether extruded
7.
8.
9.
G)
H)
H)
outer sheath
in outer sheath
REV. NO.: R3
S.No
Description
I)
J)
Particulars
K)
Instrumentation Cables
S.No
Description
A)
GENERAL
1.
Make
2.
Type
3.
Applicable Standard
4.
5.
Location of factory
6.
Voltage grade
7.
B)
CONDUCTOR
1.
Applicable Standard
2.
Particulars
i) Continuous
ii) Short time
3.
Material copper/aluminium/grade
4.
Size
5.
6.
7.
No. of strands
8.
9.
10.
11.
12.
C)
INSULATION
1.
Material
2.
Type/Applicable Standard
3.
Thickness
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
S.No
Description
4.
5.
6.
Particulars
8.
9.
D)
INNER SHEATH
1.
Material
2.
Type/Applicable Standard
3.
Thickness
4.
Whether extruded
5.
6.
E)
ARMOURING
1.
Material
2.
Type/Applicable Standard
3.
4.
Size
5.
6.
F)
OVERALL SHEATH
1.
Material
2.
Type/Applicable Standard
3.
Thickness
4.
Colour
5.
Tolerance of thickness
6.
Whether extruded
7.
8.
9.
G)
H)
outer sheath
in outer sheath
H)
I)
J)
REV. NO.: R3
S.No
Description
Particulars
i) In ground
ii) In duct
iii) In air
K)
Description
No
A)
DRUM
1.
Drum length
2.
3.
4.
B)
ELECTRICAL PROPERTIES
1.
DC resistance at 20C
2.
AC resistance at 20C
3.
4.
5.
6.
Value
8.
9.
10.
11.
C)
OTHER DETAILS
1.
2.
3.
i) At 30C
ii) At 35C
iii) At 45C
iv) At 50C
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
Sl.
Description
No
4.
Value
CABLE TRAYS
1.
Make
2.
Type/Material/Size
3.
4.
Location of factory
5.
Applicable Standard
6.
Thickness
i) Trays
ii) Supports
iii) Brackets
7.
Earthing System
8.
9.
10.
11.
12.
E)
CABLE CLAMPS
1.
Material
2.
Type
3.
Thickness
U)
1.
Make
2.
Type/Size
3.
Applicable Standard
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
Sl.
Description
No
4.
5.
6.
7.
8.
9.
Value
(kV)
10.
11.
Type test report for above tests plus for humidity and
12.
Kit particulars
CONDUITS
1.
Make
2.
Type/Material
3.
Applicable Standard
4.
Gauge
i) Upto 25mm dia.
ii) Above 25mm dia.
5.
Catalogue furnished?
G)
JUNCTION BOX
1.
Make
2.
Type/Material
3.
Applicable Standard
4.
Degree of protection
5.
Catalogue furnished?
Outdoor/Indoor
6.
H)
TERMINAL BLOCK
1.
Make
2.
Type
3.
Applicable Standard
4.
Current rating
5.
Catalogue furnished?
6.
REV. NO.: R3
Sl.
Description
No
Value
H)
FERRULES
1.
Make
2.
Type/Material
3.
Applicable Standard
4.
Color
5.
Interlocked type?
I)
TREFOIL CLAMPS
1.
Make
2.
Type/Material
3.
4.
5.
Make
6.
Type
J)
1.
Approval of CPRI
2.
3.
4.
5.
6.
K)
1.
Make
2.
Type
3.
Approval of CPRI
5.
Instrumentation cable
Conductor Size
S.No.
(a)
0.5 sq.mm
Parameter/Type
Type E,F
Type-G,I
Type A,B&C
Mutual capacitance at
0.8kHz(max.)
(b)
(c)
Insulation Resistance
(min.)
(d)
Cross-talk figure at
0.8kHz(min.)
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
(e)
Characteristic
(f)
Attenuation at 1kHz(max.)
Type
Conductorsize in sq.mm
impedance(max.) at 1 kHz
0.5
0.5
0.5
0.5
0.5
0.5
0.5
Remark
DC System
S. No
Description
A)
BATTERY
1.
General
1.1
Make
1.2
Type
1.3
Catalogue No.
1.4
Application
1.5
Reference Standard
2.
Rating
2.1
2.2
2.3
Particulars
3.
Performance
3.1
3.2
3.3
3.4
3.5
4.
Battery Characteristics
furnished? (Yes/No)
REV. NO.: R3
S. No
4.1
Description
Particulars
4.2
4.3
4.5
5.
Cells
5.1
5.2
5.3
5.4
5.5
5.6
furnished?
6.
6.1
6.2
6.3
7.
Plates
7.1
7.2
7.3
8.
Separator
8.1
Type
8.2
Material
8.3
Thickness
9.
Electrolyte
9.1
REV. NO.: R3
S. No
Description
Particulars
9.3
Electrolyte conform to
10.
Racks
10.1
10.2
10.3
10.4
Material of rack
10.5
10.6
10.7
furnished?
10.8
11.
11.1
11.2
11.3
12.
Ventilation requirements
12.1
12.2
12.3
13.
13.1
13.2
13.3
13.4
13.5
13.6
13.7
13.8
13.9
13.10
13.11
13.12
14.
Mounting
REV. NO.: R3
S. No
15.
16.
Description
Particulars
Intermediate tapping
Ambient temperature
i) Maximum
ii) Minimum
B)
BATTERY CHARGER
1.
General
1.1
Make
1.2
Type
1.3
Catalogue No.
1.4
Reference Standard
1.5
Charger
2.
A.C. Input
2.1
Supply
2.2
2.3
Phase (No.)
2.4
2.5
2.6
Short-circuit level
2.7
System earthing
3.
D.C. Output
3.1
Voltage
3.2
Current (Amp.)
3.3
3.4
4.
Type of Cooling
5.
6.
Performance
6.1
6.2
6.4
7.
Miscellaneous
7.1
REV. NO.: R3
S. No
Description
Particulars
8.
A.C. Switch
8.1
Make
8.2
8.3
Reference Standard
8.4
9.
A.C. Fuse
9.1
Make
9.2
9.3
Reference Standard
9.4
10.
A.C. Contactor
10.1
Make
10.2
10.3
Reference Standard
10.4
10.5
Utilization category
10.6
preventor provided?
11.
Rectifier Transformer
11.1
Make
11.2
11.3
Reference Standard
11.4
Ratings
i) KVA
ii) Voltage
iii) % Reactance
11.5
Class of insulation
11.6
Method of cooling
12.
12.1
Make
12.2
12.3
Reference Standard
12.4
REV. NO.: R3
S. No
12.5
Description
Particulars
Surge Current
i) One-cycle (Amp.)
ii) Repetitive cycle (Amp.)
12.6
12.7
12.8
Filter Choke
i) Insulation class
13.
D.C. Contactor
13.1
Make
13.2
13.3
Reference Standard
13.4
13.5
Utilization category
14.
Blocking Diodes
14.1
Make
14.2
14.3
Reference Standard
14.4
Current Rating
i) One-minute (Amp.)
ii) One-hour (Amp.)
14.5
15.
Indication Lights
15.1
Make
15.2
15.3
Reference Standard
15.4
Wattage (Watt)
15.5
16.
Meters
16.1
Make
16.2
16.3
Reference Standard
16.4
Size
16.5
Accuracy
17.
Alarm-Facia
17.1
Make
17.2
17.3
Reference Standard
17.4
REV. NO.: R3
S. No
Description
18.
Change-over Switch
18.1
Make
18.2
18.3
Reference Standard
18.4
Rating (Amp.)
18.5
No. of poles
18.6
19.
D.C. Switch
19.1
Make
19.2
19.3
Reference Standard
19.4
Rating (Amp.)
19.5
No. of poles
19.6
20.
Charger Panel
20.1
Make
20.2
Type
20.3
Reference Standard
20.4
Enclosure
Particulars
i) Degree of protection
ii) Sheet steel thickness (mm)
20.5
21.
Internal Wiring
21.1
Insulation
21.2
Voltage grade
21.3
22.
Power Terminals
22.1
Make
22.2
23.
Control Terminals
23.1
Make
23.2
23.3
24.
MCCB
24.1
Make
24.2
Type
24.3
No. of poles
REV. NO.: R3
S. No
24.4
Description
Particulars
Rated Current
i) Continuous (at 50C ambient & within cubicle
Amp.)
24.6
24.7
Operating Mechanism
i) Type
ii) Antipumping feature provided
iii) Trip free or fixed trip
24.8
24.9
26.
27.
27.
29.
30.
C)
1.
Make
2.
Type
3.
Reference Standard
4.
Voltage
5.
Construction
5.1
REV. NO.: R3
S. No
Description
5.2
6.
Enclosure
6.1
Degree of protection
6.2
Particulars
i) Door
ii) Side Sheet
iii) Base Frame
7.
Panel size (H x D x W)
8.
Bus Bar
8.1
Make
8.2
8.3
8.4
D)
1.
Make
2.
3.
4.
5.
6.
7.
E)
Terminal Connection
1.
A.C. Input
2.
D.C. Output
crossing
i) To Battery
ii) To Load
F)
LT Motor
S.No.
Description
1.
Manufacturer
2.
3.
Nos. required
REV. NO.: R3
Particulars
S.No.
Description
4.
Application
5.
6.
Capacity for
Particulars
At 400C ambient
7.
8.
9.
Degree of protection
10.
Type of duty
11.
12.
Permissible variations in
(a) Voltage
(b) Frequency
13.
(c) Combined
(a)
(b)
14.
(c)
15.
Maximum
permissible
time
at
minimum
16.
17.
18.
Load
Efficiency
(% of full load)
Power Factor
100
50
25
0
At Start
Duty Point
19.
Stator Winding
i)
Connection
REV. NO.: R3
S.No.
Description
Particulars
With IS tolerance
ii)
Without IS tolerance
21.
22.
23.
24.
25.
mechanism
coupled
or
Mechanism
transferred
26.
i)
ii)
iii)
mechanism
coupling.
27.
28.
coupled
through
i)
ii)
iii)
Flexible
At rated voltage
ii)
iii)
At rated voltage
ii)
iii)
29.
30.
31.
stall time
motor)
i)
At rated voltage
ii)
iii)
REV. NO.: R3
S.No.
Description
i)
32.
Particulars
At rated voltage
ii)
iii)
Insulation
i)
Class of insulation
ii)
33.
34.
i)
ii)
By resistance method
By Thermometer method
35.
Method of starting
36.
37.
38.
39.
i)
ii)
iii)
iv)
0% of rated voltage
Bearings
i)
Number
ii)
Type
iii)
Lubrication system
iv)
v)
vi)
Recommended lubricant
vii)
viii)
ix)
x)
xi)
xii)
bearings.
REV. NO.: R3
S.No.
Description
xiii)
Particulars
xiv)
Yes/ No
40.
41.
Terminal
42.
43.
44.
with
accessories
i)
Main
ii)
Space heaters
iii)
iv)
v)
Moisture detectors
vi)
Neutral terminals
separate
i)
ii)
iii)
Location
iv)
v)
Space Heater
i)
Number
ii)
Location
iii)
Capacity of each
iv)
v)
Voltage
Nos. provided
ii)
Location
45.
Type of mounting
46.
Shaft orientation
47.
Shaft extension
48.
49.
REV. NO.: R3
S.No.
Description
50.
Motor
51.
Lifting device
52.
Weight
i)
ii)
iii)
iv)
Weight of cooler
v)
53.
54.
i)
ii)
iii)
55.
Particulars
GD2
Yes / No
Yes / No
Yes / No
iv)
Yes / No
v)
Yes / No
vi)
Yes / No
vii)
Yes / No
Drawings furnished
i)
Yes / No
ii)
Yes / No
Yes / No
Yes / No
HT Motor
S. No.
Description
1.
Manufacturer
2.
3.
Nos. required
4.
Application
5.
6.
Capacity for
i)
Particulars
7.
8.
REV. NO.: R3
S. No.
9.
Description
Particulars
Degree of protection
10.
Type of duty
11.
12.
Permissible variations in
(a) Voltage
(b) Frequency
13.
(c) Combined
15.
16.
17.
18.
Load
Efficiency
(% of full load)
Power Factor
100
50
25
0
At Start
Duty Point
19.
Stator Winding
i) Connection
With IS tolerance
ii)
Without IS tolerance
21.
22.
23.
REV. NO.: R3
S. No.
Description
24.
25.
Particulars
ii)
At rated voltage
At rated voltage
ii)
iii)
29.
30.
31.
stall time
motor)
i)
At rated voltage
ii)
iii)
32.
33.
At rated voltage
ii)
iii)
Insulation
i)
Class of insulation
ii)
REV. NO.: R3
S. No.
Description
i)
ii)
Particulars
By resistance method
By Thermometer method
34.
Method of starting
35.
36.
37.
38.
i)
ii)
iii)
iv)
0% of rated voltage
Bearings
i)
ii)
iii)
Number
Type
Lubrication system
iv)
v)
vi)
bearings.
Recommended lubricant
xi)
Yes/ No
REV. NO.: R3
Yes/ No
S. No.
Description
i)
ii)
Particulars
filling.
lubricant should be replaced
v)
39.
40.
i)
ii)
iii)
iv)
v)
41.
vi)
ii)
iii)
iv)
v)
Space Heater
i)
ii)
iii)
iv)
43.
Space heaters
i)
42.
Main
v)
Number
Location
Capacity of each
Total power requirement
Voltage
44.
i)
Nos. provided
ii)
Location
REV. NO.: R3
Yes / No
S. No.
Description
i)
Particulars
ii)
45.
Type of mounting
46.
Shaft orientation
47.
Shaft extension
48.
49.
50.
Motor GD2
51.
Lifting device
52.
Weight
i)
ii)
iii)
iv)
v)
53.
54.
Thermometer provided
i)
ii)
55.
iii)
i)
ii)
iii)
Yes / No
iv)
Yes / No
Yes / No
Yes / No
v)
vi)
Yes / No
Yes / No
Yes / No
Drawings furnished
i)
REV. NO.: R3
Yes / No
Yes / No
S. No.
Description
Particulars
Yes / No
Yes / No
Description
1.
Make
2.
Type
3.
Reference Standard
4.
5.
6.
Phase (Nos.)
7.
Frequency (Hz)
8.
9.
10.
11.
Particulars
/ kVrms)
Degree of protection
Type of Cooling
12.
13.
temperature (Amp.)
16.
Material
i) Conductor
ii) Enclosure
REV. NO.: R3
S. No
19.
Description
Particulars
Conductivity
i) Conductor
ii) Enclosure
20.
Conductor Size
21.
Conductor Shape
22.
23.
24.
(mm)
details)
busduct
i) Material
ii) Thickness
25.
26.
Skin-effect Ratio
27.
28.
29.
30.
i) Phase to phase
ii) Phase to earth
31.
Bus Insulator
i) Make
ii) Type
iii) Reference Standard
iv) Number per support
v) Voltage Class (kV)
vi) Rated Voltage (kV)
vii) Creepage distance (mm)
viii) Compression strength (kgf)
ix) Cantilever strength (kgf)
x) Tensile strength
xi) Basic impulse level kV
xii) Material of Insulator
32.
33.
34
Seal of bushing
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
S. No
Description
a.
Make
b.
Type
c.
Reference standard
d.
e.
f.
Creepage distance
Particulars
(Dry / Wet)
35
36
37
Material of enclosure
b)
Thickness of enclosure
c)
d)
Note: (i) Bidder to submit the data sheet for each type and rating of bus duct
separately.
(ii) Strike out whichever is not applicable for LT bus duct
Earthing
Sl.No
Description
Value
Riser Connections
Material
Size
REV. NO.: R3
Lightning protection
Sl. No
Description
Value
Features
Bidder Data
1.
Make
2.
Model No.
3.
Type of Transmitter
4.
Accuracy
5.
6.
7.
Stability
8.
9.
Load impedance
10.
Housing
11.
Over Pressure
12.
Connection (Electrical)
13.
Process connection
14.
Adjustment/calibration/maintenance
15.
Accessories
16.
Diagnostics
17.
Power supply
18.
Repeatability
19.
Sensitivity
20.
Temperature Gauge
Sl.No
Features
1.
Make
2.
Model No.
Bidder Data
REV. NO.: R3
Sl.No
Features
Bidder Data
3.
4.
Body material
5.
Dial size
6.
End connection
7.
Accuracy
8.
Scale
9.
Range selection
10.
11.
Housing
12.
Zero/span adjustment
13.
Identification
14.
Accessories
15.
16.
Repeatability
17.
Response Time
18.
19.
Applicable Standard
20.
Others
Features
Bidder Data
1.
Make
2.
Model No.
3.
4.
Body material
5.
Dial size
6.
End connection
7.
Accuracy
8.
Scale
9..
Range selection
10.
11.
Housing
12.
Zero/span adjustment
13.
Identification
14.
Accessories
15.
16.
Enclosure
Doc. No.: E072-03-CHP-O-02
REV. NO.: R3
Sl. No
Features
17.
Applicable standard
18.
Accessories
Bidder Data
Features
Bidder Data
1.
Make
2.
Model No.
3.
4.
Body material
5.
Dial size
6.
End connection
7.
Accuracy
8.
Scale
9.
Range selection
10.
11.
Housing
12.
Identification
13.
Accessories
14.
Visible Length
Temperature Switches
Sl No.
Features
Bidder Data
1.
Make
2.
Model No.
3.
Sensing Element
4.
Material
5.
End connection
6.
7.
Repeat-ability
8.
No. of contacts
9.
Rating of contacts
10.
Elect. Connection
11.
12.
Enclosure
13.
Accessories
14.
Mounting
15.
REV. NO.: R3
Feature
Bidder Data
1.
Make
2.
Model No.
3.
Sensing Element
4.
Material
5.
End connection
6.
7.
Repeat-ability
8.
No. of contacts
9.
Rating of contacts
10.
Elect. Connection
11.
12.
Enclosure
13.
Accessories
14.
Mounting
15.
Switch Type
16.
Accuracy
Level Switches
Sl. No
Feature
Bidder Data
1.
Make
2.
Model No.
3.
Sensing Element
4.
Material
5.
End connection
6.
7.
Repeat-ability
8.
No. of contacts
9.
Rating of contacts
10.
Elect. Connection
11.
12.
Enclosure
13.
Accessories
14.
Switch type
REV. NO.: R3
Feature
A.
Application
B.
Electronic Controller
Input Supply
Body material
Relay Output
Contact Rating
Class of Protection
Ambient Temperature
Local Indication
Green
Red
Yellow
Cable Connectio
Repeatability
Sensing Probe
Type of Probe
Material
C.
Insulation
Bidder Data
(B/W
Active& :
Mounting
Cable Connection
Process Connection
Signal Cable
Bidder Data
Type
Application
Environment Class
Orientation
Probe Type
Probe Material
REV. NO.: R3
Feature
Bidder Data
Connection material
Accuracy
Type(Transmitter)
Operating Principle
Output
Electrical Connection
Enclosure Class
Electrical Power
Housing material
Local Display
Units of Measurement
Bidder Data
Principle of
Measuring Ranges
Signal Processing
Operating Freq
Display
Diagnosis
Status
Construction
Power supply
Signal Output
Hysteresis
Output contacts
Resolution
Operating temp
MOC Sensor
Humidity
Enclosure
Cable Connection
Mounting
Accessories
REV. NO.: R3
Size
Protection class
Enclosure type
Electronic unit
Supply voltage
Speed range
Repeatability
Differential
Contact rating
Ambient Temperature
Preferable features
Protection class
Enclosure type
Output contacts
Contact Rating
Protection class
Enclosure type
Output contacts
Contact Rating
REV. NO.: R3
Operating handle
PC
Sl. No
Feature
1.
Make
2.
Model No.
3.
CPU
4.
Main memory
5.
Drives
6.
Hard disk
7.
Monitor
8.
Graphic accelerator
9.
Communication port
Bidder Data
REV. NO.: R3
12.0
REV. NO.: R3
Drawing No.
Description
1.
E072-03-CHP-M-03-01-R2
2.
E072-03-CHP-M-03-02-R3
CHP layout
3.
E072-03-CHP-E-03-06-R3
4.
E072-03-CHP-I-03-08-R1
PLC Configuration
Note: All the above drawings are only for tender purpose.
REV. NO.: R3
13.0
REV. NO.: R3
ANNEXURES
I)
i)
6-8
Volatile Matter %
22-30
Fixed Carbon %
37-45
Ash %
18-32
4000 - 5100
Ultimate Analysis
Carbon %
72.3-82.5
Hydrogen %
2.8-5.1
Nitrogen %
1.4-2.0
Oxygen %
11.2-18.3
Sulphur %
0.03-1.3
Total Sulphur
0.73-1.68
HGI
II)
Value
4555
Ash Parameters
Initial Deformation C
1,060
Softening C
1,100
Hemispherical C
1,140
Fluid C
1,200
SiO2
28.29
Al2O3
18.71
Fe2O3
12.42
CaO
10.9
MgO
4.11
TiO2
0.65
Na2O
4.46
K2O
0.87
Mn3O4
0.17
P2O5
0.53
SO3
18.89
Total
100
REV. NO.: R3
B)
Particulars
No.
unit
data
< 15
1.0
Proximate Analysis
1.1
Moisture
1.2
Ash
< 10
1.3
Volatile matter
22-45
1.4
Sulphur
<O.6
1.5
Gross FCV
1.6
HGI
Kcal/kg
6000
45-55
REV. NO.: R3
Description
NO.
Quantity
WAGON TIPPLER
5 NOS.
5 NOS.
5 NOS.
1 LOT
1 LOT
PRIMARY CRUSHER
4 NOS.
SECONDARY CRUSHER
8 NOS.
VIBRATING SCREEN
8 NOS.
3 NOS.
10
11
12
METAL DETECTORS
13
TRAVELLING TRIPPER
8 NOS.
14
FIXED TRIPPER
12 NOS.
15
FLAP GATES
16
SUMP PUMP
17
BELT VULCANISER
1 NO.
18
1 LOT
19
20
ELECTRIC HOISTS
1 LOT
21
1 Lot
22
VENTILATION SYSTEMS
1 Lot
23
24
1 Lot
25
GATES
26
DOZER
5 NOS.
27
LOCOMOTIVES
4 NOS.
28
Elevator
2 No.
29
1 Lot
REV. NO.: R3