Lecture 4 A - Cost Estimating Techinques
Lecture 4 A - Cost Estimating Techinques
Objectives
Define engineering cost estimating
Explain different types of engineering cost
estimates
Use several common mathematical cost
estimating models in cost estimating
Costs Estimating
Three general types of estimates:
Rough (or order of magnitude) estimate
Budget estimate
Detailed estimate
Cost Estimating
Rough (order of magnitude) estimate
Used in projects initial planning and
evaluation phases
Has little detail and little accuracy
Used only for quantification (order of
magnitude)
Made quickly and easily
Accuracy from 30% to +60%
source: Newnan et al: Engineering
Economic Analysis
Cost Estimating
Budget estimates
Used for budgeting only at conceptual or
preliminary stage of project
More detailed than rough, so require more
time and resources
Accuracy from 15% to +20%
Cost Estimating
Detailed estimate
Used during projects detailed design and
contract bidding phases
Made from detailed quantitative models,
blueprints, product specification sheets,
vendor quotes
Require most time and resources
Accuracy from 3% to +5%
source: Newnan et al: Engineering
Economic Analysis
Difficulties in Estimating
One of a kind estimates: especially difficult
since (almost) all parameters must be
estimated (could use estimation by
analogy)
Time and effort available: both are
required for a detailed estimate (these
resourced must be planned/scheduled)
Estimator expertise: more experienced
and knowledgeable estimator usually
makes better estimates
source: Newnan et al: Engineering
Economic Analysis
Estimating Models
Estimating Models
Per-unit model
Uses per-unit factor, e.g. utility cost per
m2, gasoline cost per km, safety cost per
employee to develop estimate
Simple and useful
Only for rough estimate
10
Estimating Models
Segmenting model
Divide estimate into its individual
components (on basis of a Work
Breakdown Structure WBS)
Prepare estimates for each of these
components
Total estimate is sum of all component
estimates
source: Newnan et al: Engineering
Economic Analysis
11
Estimating Models
Cost indexes
Dimensionless numbers reflecting the
change in price over time (commodity
price indexes, e.g. labour costs, composite
indexes, e.g. Manufacturers Price Index)
Cost at time A
Cost at time B
12
Example
Miriam is interested in estimating the annual labour and
material costs for a new production facility. She obtained the
following data:
Labour costs:
Labour cost index value was 124 ten years ago and is 188
today
Annual labour costs for a similar facility were $575,500 ten
years ago
Material costs:
Material cost index value was at 544 three years ago and is
715 today
Annual material costs for a similar facility were $2,455,000
three years ago
source: Newnan et al: Engineering
Economic Analysis
13
Example: solution
Labour costs:
Annual cost today
Annual cost 10 yrs ago
Material costs:
Annual cost today
Annual cost 3 yrs ago
14
Estimating Models
Power-sizing model
Used to estimate costs of industrial plants and
equipment.
Uses exponent x, the power-sizing exponent, to
represent economies of scale in size or capacities
=
Cost of equipment B Size(capacity ) of equipment B
15
=
Cost of equipment B Size(capacity ) of equipment B
16
(http://web.em.doe.gov/aceteam/workpdfs.html)
18
19
20
21
22
23
300,000
4 1.14
(1 + 0.08)
(100m 5m )
+ 7 m (1 0.01) = 209.15m
0.92
200,000
source:
http://www.ce.cmu.edu/pmbook
24