Using Down Hole Chokes
Using Down Hole Chokes
ABSTRACT
This article describes a case study detailing planning,
completion, testing, and production of the first Maximum
Reservoir Contact (MRC), Multilateral (ML) and Smart
Completion (SC) deployment in Ghawar field.
The well was drilled and completed as a proof of concept.
It was completed as a trilateral and was equipped with a SC
that encompasses a surface remotely controlled hydraulic
tubing, retrievable advanced system coupled with a pressure
and temperature monitoring system.
The SC provides isolation and downhole control of
commingled production from the laterals. Using the variable
position flow control valve, the well managed to improve and
sustain oil production by eliminating water production.
Monitoring the rate and the flowing pressure in real time
allowed optimal well production.
The appraisal and acceptance loop of the completion has
been closed by having this well completed, put on production
and tested. Approval of the concept was achieved when the
anticipated benefits were realized by monitoring the actual
performance of the well.
Leveraged knowledge from this pilot has provided an
insight into SC capabilities and implementation. Moreover, it
has set the stage for other developments within Saudi Aramco.
BACKGROUND
Haradh forms the southwest part of the Ghawar oil field
located about 80 km onshore from the Arabian Gulf in the
Eastern Province of Saudi Arabia, Fig. 1. The Haradh field
consists of three increments where the initial production
started in May 1996 from Increment 1, followed by Increment
2 and 3 in April 2003, and January 2006, respectively.
Increment 1 was initially developed using mainly vertical
wells, while Increment 2 was developed with horizontal wells.
The subsequent Maximum Reservoir Contact (MRC),
Multilateral (ML) wells and Smart Completion (SC)
installations in Increment 2 were part of a proof of concept
project to test and evaluate the impact of these technologies on
reservoir, well performance and overall reservoir management
strategies. As a result of the proof of concept project,
Increment 3 was developed with MRC, ML wells with SCs.
SPRING 2009
63
GENERAL GEOLOGY
The producing horizon at the well location belongs to the lower
member of the Arab-D formation, which is characterized by a
complex sequence of anhydrite and limestone events with
varying degrees of dolomitization. This particular well is
located in the west flank of Haradh Increment 2, in an area
characterized by heterogeneity in reservoir rock properties,
salinity and fluid movement. Fluid mechanism in this specific
area is highly influenced by the presence of fracture corridors
and strataform super permeability. The motherbore of this well
(L0) extends to the vicinity of the projected flood front while
the other laterals extend away from the flood front, Fig. 2.
The location dictated drilling a well that can capture real
time data, maximize control, optimize production, and
increase well value.
COMPLETION STRATEGY
After analyzing the reservoir data, SC solutions were sought
to meet reservoir and production main objectives, including
but not limited to:
Sustain well productivity.
Improve sweep.
COMPLETION DESIGN
The HRDH-A12 well was drilled in 2004, and was completed
with a 7 liner set horizontally into the Arab-D producing
interval. A 618 horizontal open hole was then drilled out from
the bottom of the 7 liner. Due to heavy losses while drilling
L0, a 4 liner was set covering part of this open hole section.
Two 618 horizontal sidetracks (L1 and L2) were then drilled
from the 7 liner completing the trilateral well. The well was
initially completed and put on production from barefoot
laterals. A year later, the well was worked over to install a SC.
64
Fig. 4. Downhole choke valve flow area and recommended flow rate.
COMPLETION PERFORMANCE
A multidisciplinary team consisting of reservoir, drilling,
completion and production engineers, as well as the vendors
experts, was formed to assure smooth and successful
operation. The team applied a project management approach
to the design, planning and installation process.
The SC was subsequently installed in early April 2005.
During the equipment testing, installation and subsequent
flow testing of the well, each of the valves were actuated
through more than 10 complete cycles (110 position changes),
which is equivalent to several years of typical operation. As a
precautionary measure and to ensure the functionality of the
Downhole Control Valves, the valves were tested downhole
prior to setting the packers.
During testing of the well once the completion was installed,
a multiphase flow meter provided three-phase flow rate
measurements. This data along with the downhole pressure
and temperature measurements were transmitted in real time
for instantaneous analysis and subsequent decision making.
WELL PERFORMANCE
Lateral
L0
L1
L2
Total
Table 1. Lateral lengths
Length
7.125 ft
4,042 ft
7,200 ft
18,367 ft
SPRING 2009
65
Lateral
L2
L1
L0
Test
1
2
3
4
5
6
7
L1
L2
5
5
0
0
0
10
0
3
0
0
0
3
10
3
2
0
5
2
0
10
2
Rate
WC%
7.7
1.0
3.5
3.5
3.9
Dead
6.0
22
97
65
0
0
66
CONCLUSIONS
Leveraged knowledge from this experiment provided insight
into SC capabilities and implementation; moreover, it set the
stage for other increment developments (i.e., Haradh
Increment 3). Several lessons learned of high impact can be
identified, most notably:
1. Quality control of the system is a priority for successful
implementation. This can be illustrated by function testing
the completion in hole prior to setting the packers.
2. HRDH-A12 could have been dead without SC.
3. Real time surveillance and control capabilities permit
proactive measures.
4. Downhole flow control can alleviate the natural fractures
impact on dominating production.
5. Smart Completions have demonstrated the potential to
reduce well interventions7.
ACKNOWLEDGEMENTS
The authors would like to thank Saudi Aramco management
for permission to publish this article.
REFERENCES
1. Afaleg, N., Pham, T., Otaibi, U., Amos, S. and Sarda, S.:
Design and Deployment of Maximum Reservoir Contact
Wells with Smart Completions in the Development of a
BIOGRAPHIES
Saeed M. Al-Mubarak is a Supervisor
in the Southern Area Reservoir
Management Department, and a
specialist in Real-Time Reservoir
Management (RTRM) and Intelligent
Fields. He has been very involved in
the development, the design and the
implementation of Intelligent Fields and various advanced
well completion systems. Saeed has more than 15 years of
petroleum industry experience. His contributions to the
international technical community are numerous, including
his acceptance to be a Society of Petroleum Engineers (SPE)
Distinguished Lecturer in RTRM during 2009-2010. Saeed
received his B.S. degree in Chemical Engineering in 1992
from King Fahd University of Petroleum and Minerals
(KFUPM), Dhahran, Saudi Arabia and is currently
pursuing a M.S. degree in Petroleum Engineering from the
same university.
Tony R. Pham is a Senior Petroleum
Engineering consultant with more than
20 years of experience in the petroleum
industry. In 1976 he graduated with a
B.S. degree in Petroleum Engineering
from the Texas A&M University,
College Station, TX.
Sultan S. Al-Shamrani is a Reservoir
Engineer working in the Southern
Area Reservoir Management
Department. He has 5 years of
industry experience, mainly in new
field development and intelligent field
implementation. Sultan graduated
from the University of Tulsa, Tulsa, OK in 2004 with a
B.S. degree in Petroleum Engineering.
Muhammad Shafiq is a Senior Advance
Completions Architect with Schlumberger
in Saudi Arabia. He is currently
responsible for real-time reservoir
monitoring and control. Muhammad has
12 years of oil field experience. He
received his B.S. degree in Petroleum
Engineering from the University of Engineering and Technology,
Lahore, Pakistan in 1995.
SPRING 2009
67