Detecting Distribution Transformer Faults
Detecting Distribution Transformer Faults
Transformer Faults
Increasing Distribution System Productivity
June 2005
Table of Contents
Abstract ...................................................................................................................................................... 1
Introduction ................................................................................................................................................ 1
Transformer Facts ...................................................................................................................................... 1
Fusing Operations ...................................................................................................................................... 2
Transformer Failures .................................................................................................................................. 2
Eventful Transformer Failures .................................................................................................................... 2
Field Experience ........................................................................................................................................ 3
Built-In Internal Fault Detectors .................................................................................................................. 4
TM
The IFD .............................................................................................................................................. 4
Technology Value to Utilities ...................................................................................................................... 5
Restoration Cost Savings through Productivity Improvements .............................................................. 5
Return on Investment Considerations ................................................................................................... 7
Aging Physical Infrastructure ................................................................................................................. 7
Customer Service .................................................................................................................................. 7
Risk Assessment ................................................................................................................................... 8
IFD Reliability Standards ............................................................................................................................ 8
Testing for Reliability ............................................................................................................................. 8
IFD Reliability in Service........................................................................................................................ 9
Other Transformer Fault Detection Methods .............................................................................................. 9
Fuses..................................................................................................................................................... 9
Current Limiting Fuses .........................................................................................................................10
Stronger Transformer Tanks ................................................................................................................10
Completely Self Protected Transformers (CSPs) .................................................................................10
Conclusion ................................................................................................................................................12
About the Author .......................................................................................................................................12
Contributors ..........................................................................................................................................12
References ................................................................................................................................................13
Appendix A: Fault Protection and Identification Options and Benefits.......................................................14
Appendix B: Cost Analysis Possible Costs Associated with Transformer Faults....................................15
Abstract
Utilities are constantly looking for ways to
increase productivity in the distribution system.
This means reducing the total lifecycle cost of the
system; improving labor costs, improving
customer service and protecting assets. This
includes the value of improved worker safety.
One area showing considerable promise of
increasing the productivity is rapid detection of
internal faults in pole top transformers.
Introduction
Utility line crews re-energize single phase, poletop transformers frequently1. Over time, vendors
improved the quality of transformers, fuses and
related tools and equipment, making it more
challenging for the line worker to detect
equipment failures. Additionally, the need for
faster problem resolution with fewer resources is
a constant management challenge. This paper
outlines these challenges and describes a
simple, direct, cost effective solution for utilities.
Pole top transformers are usually connected to
the primary supply network via a fuse cutout. The
fuse cutout is a protective device with two
purposes. Firstly, by separating a downstream
problem from the upstream supply, it limits the
number of customers affected by the fault or
overload. Second, by interrupting the flow of
power to the fault, the risk of damage to
equipment and injury to people is limited. The
protective characteristics of the link are intended
to serve both these purposes with a high degree
of reliability, while also minimizing the frequency
of unnecessary (nuisance) operations.
The reason for excessive current includes
internal faults caused by failure of the transformer
insulation system. However, unless the internal
fault produces signs on the transformers exterior,
it may be difficult to reliably detect and confirm its
presence without cumbersome and time
consuming measures. For example, it takes at
least 15 minutes to disconnect the secondary
leads to enable the line crew to measure the
impedance of the transformer and/or check the
integrity of the insulation by applying a test
voltage from a suitable source. Therefore, the
challenge to utilities is how they can efficiently
and reliably determine if an internal fault has
occurred.
Transformer Facts
Service personnel often need to locate, diagnose
and correct the causes of outages rapidly. The
June 2005
Page 1
Fusing Operations
The fuse cutout is designed to protect the
transformer and related equipment and services.
About 20% of the time when the cutout operates
the transformer has failed. The rest of the time
the cutout has operated for a non-transformer
problem. However, unless the reason for the
failure is obvious, the line worker has a time
consuming problem determination process to
follow. A tool that can readily identify when a
component has failed saves time in all
circumstances.
If a transformer has obviously failed, the
Investigation can be stopped and the unit
replaced and resources can be more quickly
released to fix the next problem.
When the line worker knows the transformer is
not faulted which is in approximately 80% of the
refusing operations, the line worker can look to
different causes for the fuse operating before
starting the process of safely re-energizing. This
allows the line worker to focus on the more likely
outage sources and leads to a faster, safer
resolution to the problem. So in all circumstances
where the fuse has operated, the line worker
saves time if there is a transformer failure
identification tool.
Transformer Failures
The rate of transformer failures is often debated.
Few utilities have good tracking systems however
there are a few utilities such as Progress Energy
June 2005
10
Page 2
Field Experience
If the tank failed just before the fuse operated,
the consequences to the transformer might be
limited. However, faults often do not cause
eventful failure before the first fuse operation.
Eventful situations often occur when the line
worker is re-closing on already faulted units. This
can place line crews in a hazardous situation.
Internal transformer faults develop to the point
that the cutout will operate, but there may be no
visible external indication of a transformer fault
other than the fuse operation. It is often unclear
whether the transformer has failed or the fuse
has blown for some other reason in spite of a
thorough external examination.
In this situation, a line crew will normally re-fuse
and close back in the line. While many utilities
require crews to test the transformer, this is often
not done if everything appears okay. This is
June 2005
Page 3
like this, the line crew needs all the help it can
get.
The IFDTM
One detection method measures the pressure
differential across a flexible membrane to activate
a fault signaling mechanism. One device that
incorporates this principle is the Internal Fault
Detector (IFD), developed by IFD Corporation.
The IFD was in development for over a decade,
and represents the result of a collaborative R&D
effort involving financial and technical support by
a group of utilities. The objectives of the IFD
were to improve lineman productivity, enhance
June 2005
16
J.P. Chisholm, N. Cuk and S.H. Hicks, IFD
Corporation: Development of an Internal Fault Detector
for Pole-Top Distribution Transformers: Report No
T994700-5003 December 1998 prepared for and
Page 4
Figure 1
Prior to operation, the pressure detecting membrane
and its trigger shaft (red and blue vertical rod) are in the
lowered position, locking the indicator (yellow) in place.
The large spring on the right side stores the energy to
push the indicator out; the small coaxial assembly on
the left is the pressure relief device (PRD).
Figure 2
When the membrane reacts to pressure pulse caused
by an internal fault, it moves up, carrying the trigger
shaft with it (red and green). This releases the
indicator, which is pushed out by the spring. Once this
happens, pressure is relieved through the IFD. The
blue arrows indicate the flow of gas through the
indicator assembly.
June 2005
Page 5
Situation Analysis
Two Man Crew
In this example, a two-man crew, using a bucket
equipped vehicle or material handling aerial
device, investigate the outage. The crew may be
dispatched from a local office or central operating
center. The hourly rates for this combination are
quite high, including two skilled trades people,
expensive work equipment and often, overtime
pay rates.
While this arrangement has impressive work
capacity, most of the outages handled involve
inspection, re-fusing and re-closing. If the utility
adheres to a test before re-close practice, the
crew will spend a great deal of their time
isolating, testing and reconnecting transformers
with no internal faults.
Now consider the same operation, where
transformers are equipped with IFDs. If the
transformer has actually failed, the crew will in all
probability, know immediately by looking at the
IFD. If it has not operated, the crew proceeds
with its normal practice, just to be sure. If the IFD
has operated, they can order a new transformer
without even getting out of the truck.
In this case, (because the crew did not set the
outriggers or raise the boom) it can quickly
proceed to the next trouble call. The workers can
either go back to the original location when the
new transformer has arrived, or leave it for the
crew that brings out the replacement unit. If they
are lucky, the line workers may have the correct
spare on the truck.
Most utilities reviewing this scenario believed the
IFD would save at least hour, on average. One
standards engineer provided the following
savings range estimate.
Descripton
Truck and two crew (per hour)
Estimated fuse costs
Financial analysis when an IFD is installed
on the faulted transformer
Truck and two crew (1/2 hour savings)
Fuse savings (increase this by number of
attempts)
Savings per transformer
Less IFD cost
Net Savings per transformer
COSTS
$100-750
$5-25
SAVINGS
$50-375
$5-25
$75-370
$35-$45
$30-335
Situation Analysis
Two Man Crews During a Storm
Cost savings increase if we use the same
example above, but expand it to address a typical
June 2005
Units
100
20
10
SAVINGS
$2,00014,000
$100-500
$2,100 - $14,500
$21-145
Situation Analysis
Critical Event
In this example, a two-man crew, using a bucket
equipped truck investigates an outage. The
transformer has an undetected internal fault, and
there are no external signs of a failure. When the
line worker closes the line back in, the
transformer has a catastrophic failure. The line
worker(s) is injured and can be expected to be off
the job for an extended period of time. Other
assets are damaged and repair is extensive.
Costs include: Time lost from work, time
dedicated to accident investigation and reporting,
uninsured medical costs covered by company,
employee's loss in earning power, economic loss
to the injured person's family, legal costs,
occupational health and safety worker wages,
supervisor time, management time, medical and
compensation insurance, cost of training
temporary or new employees, oil clean up, pole
replacement, landscaping, potential penalties,
potential fines and negative public relations.
It is difficult to consider this potentiality, and the
topic is often avoided due to its infrequency and
the nature of the subject. Nonetheless, the costs
for this type of incident are always extensive and
Page 6
Return on Investment
Considerations
17
June 2005
Customer Service
In the era of electric utility deregulation and
competition, reliability of service to the customer
has become an important issue. Today, more
and more jurisdictions regulate utilities based
directly on customer service levels. Outages and
customer interruptions can be very costly.
Typical reliability measurements being adopted
are SAIFI (System Average Interruption
Frequency Index), SAIDI (System Average
Interruption Duration Index), and MAIFI
19
Page 7
(Momentary
Index).
Average
Interruption
Frequency
Risk Assessment
As mentioned in an earlier section, eventful
transformer failures do occur. These events can
be costly to a utility depending on the impact of
the event. Each utility has its own experience,
will likely know its own cost of accidents and
injuries, and can assign a value on worker
protection and accident prevention. Most large
utilities have enough actual experience to make
this calculation. Even the cost of reporting an
incident with the potential for injury, or where a
spill has required environmental cleanup, can
quickly reach thousands of dollars.
Accidents that result in injuries cost much more
and the costs of the investigation, treatment, and
increased insurance premiums can significantly
impact the bottom line. From this angle, any
improvement in worker safety yields a direct
bottom line benefit.
Risk Assessment Considerations
Lost wages
Lost time
Regulatory involvement
June 2005
Page 8
June 2005
Fuses
For over a century, the primary method of
detecting internal transformer faults is with fuses.
These devices have simple and direct operating
principles; high current melts a wire, which is
either sufficient in itself to interrupt the flow of
current or it initiates a mechanical (or chemicalmechanical) sequence in a cutout.
The advantage of these devices is that they both
detect and interrupt the fault current and, in the
case of overhead cutouts, visibly indicate
Page 9
5.
2.
3.
June 2005
21
Page 10
6.
7.
8.
9.
2.
3.
4.
5.
June 2005
Page 11
Conclusion
Contributors
Don Duckett, P. Eng. has been active in the
electric distribution utility industry since 1967.
Daniel Desrosiers, P. Eng. 25+ years with
Hydro Quebec.
Stuart Hicks, P. Eng. has over 40 years of
experience
in
Canadian
utilities
and
manufacturers.
Stephen Hudson, P. Eng. 10 years in the
manufacturing industry.
Robert Panting, retired from utility operations
after a 40+ year career.
Robert Thompson, transformer manufacturer
with over 25 years industry experience.
Mal Swanson, P. Eng. Over 30 years electrical
industry experience.
June 2005
Page 12
References
N. Cuk, S.H. Hicks. Development of an Internal
Fault Detector For Pole-Top Distribution Transformers,
(02/23/04);
http://www.enr.com/features/bizlabor/archives/04
0223.asp
June 2005
Page 13
Visible Isolation
of Transformer?
Visible
Transformer
Fault Indication?
Standard
transformer &
cutout (base case)
No
Yes**
No
Completely Self
Protected
Transformer
Internal Fault
Detector
Description
Material Cost
No
Safety
Improvements &
Environmental
Protection?
No
Labor Cost
NA
Usually
No
Yes
$60-100*
Yes
No
No
Yes
$200-300**
Yes
Yes**
Yes
Yes
$35-50
* Does not include changes to pole height or installation cost. The offset cost of no longer installing a standard PRD in the transformer tank is not included.
** From cutout operation
Page 14
Description
Operational Cost Savings
2 line crew & truck (hourly)
Lineman & scout truck
Materials Cost Savings
Lightning arrestors
Bushings
Fuses
Poles
1ph structure material
3ph structure material
9.5m pole cca
12.5m pole cca
Anchor
Epoxy arm 1ph
Epoxy arm 2ph
8' wood cross arm
Arrestor 9kv
Arrestor 27kv
Arrestor bracket
Cutout 15kv
Cutout 27kv
Effort
(hours)
Estimated Costs
.25 - .75
.25 - .75
$100-750
$60-400
.25 - 1
.25 - 1
.25 - 1
.25 - 1
.25 - 1
.25 - 1
.25 - 1
.25 - 1
.25 - 1
.25 - 1
.25 - 1
.25 - 1
.25 - 1
.25 - 1
.25 - 1
.25 - 1
.25 - 1
$40-80
$50-100
$3-50
$250-500
$31-192
$134-475
$130-200
$250-400
$30-100
$65-150
$100-200
$40-100
$30-70
$50-80
$5-30
$60-100
$80-140
$100-1500
$100-10,000
$100-10,000
$100-5,000
$100-10,000
$75-150
Page 15
Description
More Serious Events Potential Cost Reduction
Damaged tank removal (additional time)
Transport time
PCB lab test & shipment
Contaminated soil disposal fee/ barrel
PCB clor-n-oil test kit
Clean Up crew
Supervisor time
Paperwork to announce spill
Environmental officer time
Fill repair/sod/landscaping resources
Permit to dispose of soil
Digger truck
Pole replacement - labor only
Load pole
1 ph pole assemble & install
3ph pole assemble & install
Transfer 1ph xfmr c/w c.o.
Transfer 3ph xfmr bank c/w c.o.
Connections at xfmr
Connections at ser. Ent
Span of triplex run
Span of prim 1 ph run
Arrestor installation
When Injuries are Involved
Legal fees
Occupational health and safety worker
Supervisor time
Management time
OSHA
Medical expenses
Compensation insurance
Cost of training temporary or new employees
Time lost from work by injured employees
Effort
(hours)
.5 - 4
.5 - 2
.5 - 10
2.0 - 16.0
2.0 - 16.0
2.0 - 16.0
20 - 100
2.0 - 16.0
Estimated Costs
$100-1,500
$100-1,500
$100-10,000
$0-50,000
$100-500
$200-10,000
$200-10,000
$200-10,000
2.0 - 4.0
1.5 - 3.0
.25 - .75
.5 - 2
1.0 - 3.0
1.0 - 3.0
2.0 - 5.0
.25 - .75
.25 - .75
.25 - .75
1.0 - 3.0
.25 - .75
$200-10,000
$0-200
$400-3000
$175-1,000
$100-500
$75-200
$100-500
$100-500
$200-1,000
$50-200
$50-200
$50-200
$100-500
$50-200
10 - 100
10 - 100
10 - 100
10 - 100
$3,000-500,000
$1,000-100,000
$1,000-100,000
$1,000-250,000
Lost time by workers other than those injured buy who were
directly or indirectly involved in injuries
Uninsured medical costs covered by company
Employee's loss in earning power
Economic loss to the injured person's family
Potential penalties
Potential fines
Customer Service Costs
Failure to fulfill customer commitments
Unrealized Revenue
- Business
- Consumer
June 2005
Page 16