Available Short Circuit Current
Available Short Circuit Current
Circuit impedance and short circuit ratings are required per NEC 110.10
Short circuit calculations are needed for plan review for most non-residential projects with new or re-designed
services. These calculations are usually done by the electrical designer on sealed plans.
AVAILABLE FAULT CURRENT INFORMATION NEEDED FOR
SHORT CIRCUIT CALCULATION
1.
The transformer electrical information is found on the transformer or by contacting the power
company. This information includes the voltage, phase configuration and KVA.
2.
The contractor provides the wire size and material (al,cu), length of conductors and raceway
material (metal or pvc).
These values are inserted into the calculator of choice. There are several web sites with free
calculators.
THE FOLLOWING ATTACHMENTS ARE PROVIDED TO ASSIST YOU WITH
CALCULATING THE AVAILABLE SHORT CIRCUIT CURRENT.
Page 1 of3
DTE Energy
IPowered ~Y Goo~le
Electric Service
Transformer Impedances
New Service
The tables below list the current transformer impedances tor Detroit Edison's power distribution
yonstruction fees
Overhead service
Dual Voltage 7.6kV X 4.8kV Primary Single Phase - 120/240
Underaround service
Size in kVA
o/o Impedance
15
1.6-3.0
uodemround
25
1.6-3.0
Transtonuer
impedances
50
1.6-3.0
100
1.6-3.0
167
1.8-3.0
Build Green
Safety I Damage Prevention
eBuilder News
Related links
Avoid winter
Community Lighting
Gas Service
. [_e~!ili]
Converting to
Map Requests
Size in kVA
%Impedance
50
1.6-3.0
100
1.6-3.0
167
1.8-3.0
%Impedance
15
1.6-3.0
25
1.6-3.0
50
1.6-3.0
100
1.6-3.0
167
1.8-3.0
%Impedance
100
1.6-3.0
250
3.0. 3.5
%Impedance
75
1.6-3.0
250
1.63.5
333
1.6"3.7
500
1.6-3.7
....
%Impedance
25
1.5-2.75
50
1.5-2.5
Page 2 of3
100
1.5-2.5
167
1.8-3.0
250
3.0-3.4
'lo Impedance
50
1.5-2.5
100
1.5-2.5
167
1.8-3.0
'lo Impedance
150
1.6-2.5
300
1.6-2.5
500
1.8-3.5
750
5.75
13,200 GRD Y/7620 - 4801277 VOLTS
Size in kVA
'lo Impedance
150
1.6-2.5
300
1.6-2.5
500
1.8-3.5
750
5.75
4800 X 13,200 GRD Y/7620- 2081120 VOLTS*
Size In kVA
'lo Impedance
75
1.6-2.5
150
1.6-2.5
300
1.6-2.5
500
1.8-3.5
4800 X 13,200 GRD Y/7620- 2401120 VOLTS*
Size in kVA
'lo Impedance
300
1.6-2.5
500
1.8-3.5
4800 X 13,200 GRD Y17620 - 4801277 VOLTS*
%Impedance
Size in kVA
75
150
1.6-2.5
..
1.6-2.5
300
1.6-2.5
500
1.8-3.5
%Impedance
750
5.75
1000
5.75
1.6-3.0
50
4800 X 13,200 - 4801277 VOLTS
Size in kVA
%Impedance
750
5.75
1000
5.75
1500
5.75
Customer Support
Page 3 of3
Subsidiaries
Special Topics
192
Normally, short circuit studies involve calculating a bolted 3-phase fault condition. This
can be characterized as all 3-phases bolted together to create a zero impedance
connection. This establishes a worst case (highest current) condition that results in
maximum three phase thermal and mechanical stress in the system. From this
calculation, other types of fault conditions can be approximated. This worst case condition should be used for interrupting rating, component protection and selective coordination. However, in doing an arc-flash hazard analysis it is recommended to do the arcflash hazard analysis at the highest bolted 3 phase short circuit condition and at the
minimum bolted three-phase short circuit condition. There are several variables in a
distribution system that affect calculated bolted 3-phase short-circuit currents. It is
important to select the variable values applicable for the specific application analysis. In
the Point-to-Point method presented in this section there are several adjustment factors
given in Notes and footnotes that can be applied that will affect the outcomes. The
variables are utility source short circuit capabilities, motor contribution, transformer percent impedance tolerance, and voltage variance.
In most situations, the utility source(s) or on-site energy sources, such as on-site
generation, are the major short-circuit current contributors. In the Point-to-Point method
presented in the next few pages, the steps and example assume an infinite available
short-circuit current from the utility source. Generally this is a good assumption for
highest worst case conditions and since the property owner has no control over the
utility system and future utility changes. And in many cases a large increase in the utility
available does not increase the short-circuit currents a great deal for a building system
on the secondary of the service transformer. However, there are cases where the actual
utility medium voltage available provides a more accurate short circuit assessment
(minimum bolted short-circuit current conditions) that may be desired to assess the arcflash hazard.
When there are motors in the system, motor short circuit contribution is also a very
important factor that must be included in any short-circuit current analysis. When a short
circuit occurs, motor contribution adds to the magnitude of the short-circuit current;
running motors contribute 4 to 6 times their normal full load current. In addition, series
rated combinations can not be used in specific situations due to motor short circuit
contributions (see the section on Series Ratings in this book).
For capacitor discharge currents, which are of short time duration, certain IEEE (Institute
of Electrical and Electronic Engineers) publications detail how to calculate these
currents if they are substantial.
Step 2.
At some distance from the terminals, depending upon wire size, the L-N fault
current is lower than the L-L fault current. The 1.5 multiplier is an approximation
and will theoretically vary from 1.33 to 1.67. These figures are based on change in
turns ratio between primary and secondary, infinite source available, zero feet from
terminals of transformer, and 1.2 x %X and 1.5 x %R for L-N vs. L-L resistance and
reactance values. Begin L-N calculations at transformer secondary terminals, then
proceed point-to-point.
Step 5.
Step 6.
1
1 +f
Calculate the available short circuit symmetrical RMS
current at the point of fault. Add motor contribution, if
applicable.
M=
Note 3. Utility voltages may vary 10% for power and 5.8% for 120 Volt lighting services. Therefore, for highest short circuit conditions, multiply values as calculated in step
3 by 1.1 or 1.058 respectively. To find the lower end worst case, multiply results in step
3 by .9 or .942 respectively.
Note 4. Motor short circuit contribution, if significant, may be added at all fault locations
throughout the system. A practical estimate of motor short circuit contribution is to multiply the total motor current in amps by 4. Values of 4 to 6 are commonly accepted.
Step 4. Calculate the "f" factor.
IS.C. primary
IS.C. primary
3 Faults
1.732 x L x I 3
f=
C x n x E L-L
2 x L x I L-L
f=
C x n x EL-L
Note 5. The L-N fault current is higher than the L-L fault current at the secondary terminals of a single-phase center-tapped transformer. The short-circuit current available (I)
for this case in Step 4 should be adjusted at the transformer terminals as follows: At L-N
center tapped transformer terminals, IL-N = 1.5 x IL-L at Transformer Terminals.
IS.C. secondary
2 x L x I L-N
f=
C x n x EL-N
Where:
L = length (feet) of conductor to the fault.
C = constant from Table 4 of C values for conductors and
Table 5 of C values for busway.
n = Number of conductors per phase (adjusts C value for
parallel runs)
I = Available short-circuit current in amperes at beginning
of circuit.
E = Voltage of circuit.
Step B.
f=
1 Transformer
(I S.C. primary and
I S.C. secondary are
1 fault values:
I S.C. secondary is L-L)
f=
M=
Step C.
transformer
transformer
IS.C. secondary
H.V. UTILITY
CONNECTION
Vprimary
Vsecondary
x M x I S.C. primary
193
Fault X1
One-Line Diagram
Available Utility
Infinite Assumption
1500 KVA Transformer,
480V, 3, 3.5%Z,
3.45%X, .56%R
1500 x 1000 =
1804A
480 x 1.732
Step 4.
If.l. =
Step 2.
Step 3.
Step 5.
M=
Step 6.
f=
2000A Switch
KRP-C-2000SP Fuse
x x
= 1.732 25 51,540 = 0.0349
22,185 x 6 x 480
Step 4.
Step 5.
M=
Step 6.
Fault X1
1
400A Switch
LPS-RK-400SP Fuse
Step 1.
If.l. =1804A
25' - 500kcmil
6 Per Phase
Service Entrance
Conductors in Steel Conduit
Fault X2
1.732 x 50 x 49,803 =
.4050
22,185 x 480
1
= .7117
1 + .4050
1
= .9663
1 + .0349
Fault X2
2
Motor Contribution
System B
*Assumes 100% motor load. If 50% of this load was from motors, IS.C. motor contrib. = 4 x 1,804 x .5 = 3608A
Fault X1
One-Line Diagram
Available Utility
Infinite Assumption
Step 1.
Step 2.
Multiplier =
Step 3.
Step 4.
f=
Step 5.
M=
30 - 500 kcmil
4 Per Phase
Copper in PVC Conduit
Fault X2
100 =
28.57
3.5
Step 4.
Step 5.
M=
Step 6.
1
= .905
1 + .1049
1.732 x 30 x 34,370 =
.0348
26,706 x 4 x 480
Fault X3
1600A Switch
KRP-C-1500SP Fuse
1
Fault X1
400A Switch
LPS-RK-350SP Fuse
Step 6.
33,215A
1
= .9664
1 + .0348
I S.C.sym
RMS
Step A.
f=
Step B.
M=
Step C.
= 34,370 x .9664 =
1
= .4286
1 + 1.333
480 x .4286 x 30,059 =
29,731A
208
20 - 2/0
2 Per Phase
Copper in PVC Conduit
Fault X2
194
A
B
C
1. It is necessary that the proper impedance be used to represent the primary system.
For 3 fault calculations, a single primary conductor impedance is only considered
from the source to the transformer connection. This is compensated for in the 3
short circuit formula by multiplying the single conductor or single-phase impedance
by 1.73.
Primary
Secondary
Short
Circuit
2. The impedance of the center-tapped transformer must be adjusted for the halfwinding (generally line-to-neutral) fault condition.
The diagram at the right illustrates that during line-to-neutral faults, the full primary
winding is involved but, only the half-winding on the secondary is involved.
Therefore, the actual transformer reactance and resistance of the half-winding
condition is different than the actual transformer reactance and resistance of the full
winding condition. Thus, adjustment to the %X and %R must be made when
considering line-to-neutral faults. The adjustment multipliers generally used for this
condition are as follows:
Primary
Secondary
Short Circuit
L2
L1
The calculations on the following pages illustrate 1 fault calculations on a singlephase transformer system. Both line-to-line and line-to-neutral faults are considered.
L1
Short Circuit
50 Feet
L2
195
196
Full
%
Short
Circuit
Load
Impedance
Amps
(Nameplate)
Amps
kVA
25
104
1.5
12175
37.5
156
1.5
18018
120/240
50
208
1.5
23706
1 ph.*
75
313
1.5
34639
100
417
1.6
42472
167
696
1.6
66644
45
125
1.0
13879
75
208
1.0
23132
112.5
312
1.11
31259
150
416
1.07
43237
120/208
225
625
1.12
61960
3 ph.**
300
833
1.11
83357
500
1388
1.24
124364
750
2082
3.50
66091
1000
2776
3.50
88121
1500
4164
3.50
132181
2000
5552
4.00
154211
2500
6940
4.00
192764
75
90
1.00
10035
112.5
135
1.00
15053
150
181
1.20
16726
225
271
1.20
25088
300
361
1.20
33451
277/480
500
602
1.30
51463
3 ph.**
750
903
3.50
28672
1000
1204
3.50
38230
1500
1806
3.50
57345
2000
2408
4.00
66902
2500
3011
4.00
83628
* Single-phase values are L-N values at transformer terminals. These figures
are based on change in turns ratio between primary and secondary, 100,000
KVA primary, zero feet from terminals of transformer, 1.2 (%X) and 1.5 (%R)
multipliers for L-N vs. L-L reactance and resistance values and transformer
X/R ratio = 3.
** Three-phase short-circuit currents based on infinite primary.
UL listed transformers 25 KVA or greater have a 10% impedance toler ance. Short-circuit amps shown in Table 1 reflect 10% condition. Transformers constructed to ANSI standards have a 7.5% impedance tolerance
(two-winding construction).
For example, a 10% increase in system voltage will result in a 10% greater
available short-circuit currents than as shown in Table 1.
3
%Z
1.2
1.3
75
1.11
150
1.07
225
1.12
300
1.11
333
1.9
500
1.24
500
2.1
These represent actual transformer
installations.
Suggested
X/R Ratio for Calculation
1.1
1.1
1.5
1.5
1.5
1.5
4.7
1.5
5.5
nameplate ratings taken from field
197
Nonmagnetic
600V
5kV
389
617
982
1559
1555
2430
2418
3826
3789
4811
4745
6044
5926
7493
7307
9317
9034
11424
10878
13923
13048
16673
15351
18594
17121
20868
18975
22737
20526
24297
21786
26706
23277
28033
25204
29735
26453
31491
28083
2407
3753
4679
5809
7109
8590
10319
12360
14347
15866
17409
18672
19731
21330
22097
23408
24887
Three-Conductor Cable
Conduit
Steel
600V
5kV
389
617
982
1559
1557
2431
2425
3830
3812
4820
4785
5989
5930
7454
7365
9210
9086
11245
11045
13656
13333
16392
15890
18311
17851
20617
20052
22646
21914
24253
23372
26980
25449
28752
27975
31051
30024
33864
32689
237
376
599
952
1482
2350
2961
3730
4678
5838
7301
9110
11174
12862
14923
16813
18506
21391
23451
25976
28779
1476
2333
2929
3673
4580
5646
6986
8627
10387
11847
13492
14955
16234
18315
19635
21437
23482
237
376
599
952
1482
2351
2963
3734
4686
5852
7327
9077
11185
12797
14917
16795
18462
21395
23633
26432
29865
951
1479
2342
2945
3702
4632
5766
7153
8851
10749
12343
14183
15858
17321
19503
21718
23702
26109
15kV
951
1480
2347
2955
3719
4664
5820
7271
8981
11022
12636
14698
16490
18064
20607
23196
25790
29049
2415
3779
4726
5828
7189
8708
10500
12613
14813
16466
18319
19821
21042
23126
24897
26933
29320
Nonmagnetic
600V
5kV
389
617
982
1560
1558
2433
2428
3838
3823
4833
4803
6087
6023
7579
7507
9473
9373
11703
11529
14410
14119
17483
17020
19779
19352
22525
21938
24904
24126
26916
26044
30096
28712
32154
31258
34605
33315
37197
35749
2421
3798
4762
5958
7364
9053
11053
13462
16013
18001
20163
21982
23518
25916
27766
29735
31959
1478
2339
2941
3693
4618
5717
7109
8751
10642
12115
13973
15541
16921
19314
21349
23750
26608
237
376
599
952
1482
2353
2966
3740
4699
5876
7373
9243
11409
13236
15495
17635
19588
23018
25708
29036
32938
1479
2344
2949
3709
4646
5771
7202
8977
10969
12661
14659
16501
18154
20978
23295
25976
29135
15kV
952
1481
2350
2959
3725
4682
5852
7329
9164
11277
13106
15300
17352
19244
22381
25244
28262
31920
15kV
Note: These values are equal to one over the impedance per foot and based upon resistance and reactance values found in IEEE Std 241-1990 (Gray Book), IEEE Recommended Practice for Electric Power
Systems in Commerical Buildings & IEEE Std 242-1986 (Buff Book), IEEE Recommended Practice for Protection and Coordination of Industrial and Commercial Power Systems. Where resistance and reac tance values differ or are not available, the Buff Book values have been used. The values for reactance in determining the C Value at 5 KV & 15 KV are from the Gray Book only (Values for 14-10 AWG at 5 kV
and 14-8 AWG at 15 kV are not available and values for 3 AWG have been approximated).
Busway
Plug-In
Feeder
Copper
Aluminum
Copper
225
28700
23000
18700
400
38900
34700
23900
600
41000
38300
36500
800
46100
57500
49300
1000
69400
89300
62900
1200
94300
97100
76900
1350
119000
104200
90100
1600
129900
120500
101000
2000
142900
135100
134200
2500
143800
156300
180500
3000
144900
175400
204100
4000
277800
Note: These values are equal to one over the
impedance in a survey of industry.
198
High Impedance
Aluminum
Copper
12000
21300
31300
44100
56200
15600
69900
16100
84000
17500
90900
19200
125000
20400
166700
21700
188700
23800
256400
300 500KVA
750 2500KVA
15 1000KVA
0.16
0.21
0.15
0.20
0.17
0.25
Based on the infinite source method at the primary of the transformer. A quick
calculation for the Maximum Fault Current at the transformer secondary terminals is
FC = FLA / %PU Z
FC = 1202 / 0.0575 = 20,904A
This quick calculation can help you determine the fault current on the secondary of a
transformer for the purpose of selecting the correct overcurrent protective devices that
can interrupt the available fault current. The main breaker that is to be installed in the
circuit on the secondary of the transformer has to have a KA Interrupting Rating greater
then 21,000A. Be aware that feeder breakers should include the estimated motor
contribution too. If the actual connected motors are not known, then assume the
contribution to be 4 x FLA of the transformer. Therefore, in this case the feeders would
be sized at 20.904 + (4 x 1202 = 25,712 Amps
GENERATOR FAULT CURRENT
Generator fault current differs from a Transformer. Below, we will walk through a
1000KVA example.
800KW
KVA = KW / PF
KVA = 800 / .8
KVA = 1000
FLA = KVA / 1.732 x L-L Volts
FLA = 1000 / 1.732 x 0.48
FLA = 1,202
(As listed in the table for generator subtransient X values is 0.16)
FC = FLA / X
FC = 1202 / 0.16
FC = 7,513A
So, the fault current of a 1000KVA Generator is a lot less then a 1000KVA transformer.
The reason is the impedance value at the transformer and Generator reactance values are
very different. Transformer 5.75% vs. a Generator 16%
Z = 5.75%
MVA Value
1000KVA / 1000 = 1 MVA
MVA Value = 1MVA / Zpu = 1MVA / .0575 = 17.39 MVA
Use the admittance method to calculate Fault Current
1 / Utility MVA + 1 / Trans MVA = 1 / MVAsc
1 / 500 + 1 / 17.39 = 1 / MVAsc
0.002 + 0.06 = 1/ MVAsc
MVAsc = 1 / (0.002 + 0.06)
MVAsc = 16.129
FC at 480V = MVAsc / (1.73 x 0.48)
FC = 16.129 / 0.8304
FC = 19.423KA
FC = 19, 423 A
The 480V Fault Current Value at the secondary of the 1000KVA transformer based on an
Infinite Utility Source at the Primary of the transformer as calculated in the Transformer
Fault Current section in this article is 20,904A
The 480V Fault Current Value at the secondary of the 1000KVA transformer based on a
500MVA Utility Source at the Primary of the transformer as calculated in the System
Fault Current section in this article is 19,432A
The 480V Fault Current Value at the secondary of the 1000KVA transformer based on a
250MVA Utility Source at the Primary of the transformer the calculated value is 18,790A
When the cable and its length is added to the circuit the fault current in a 480V system
will decrease to a smaller value. To add cable into your calculation use the formula.
Cable MVA Value MVAsc = KV2 / Z cable. Use the cable X & R values to calculate
the Z value then add to the Admittance calculation as shown in this article.
The conclusion is that you need to know the fault current value in a system to select and
install the correct Overcurrent Protective Devices (OCPD). The available FC will be
reduced as shown in the calculations when the fault current value at the primary of the
transformer is reduced. If the infinite method is applied when calculating fault current
and 4 x FLA is added for motor contributions, then the fault current value that is obtained
will be very conservative. This means the calculated value in reality will never be
reached, so you reduce any potential overcurrent protection device failures due to fault
current.