Manual Aspen Analyzer Version 7
Manual Aspen Analyzer Version 7
Economic Analyzer
V7.0
User Guide
Contents
1 Introduction .......................................................................................................11
Main Features...............................................................................................11
Links to Process Simulator Software Programs.........................................11
Mapping of Simulator Models to Process Equipment Types.........................11
Sizing of Equipment.............................................................................12
Capital Investment and Schedules: Engineer-Procure-Construct.................12
Development of Operating Costs ...........................................................12
Investment Analysis and Aspen Process Economic Analyzers Link to Your
Spreadsheets......................................................................................12
Alternative Capacities and Locations ......................................................12
Detailed, Interactive Process Economics .................................................13
Links to Project Evaluation Programs......................................................13
Understanding Aspen Process Economic Analyzers Project Workflow ....................13
The Guide ....................................................................................................14
Organization.......................................................................................14
Related Documentation ..................................................................................15
Installation Guide ................................................................................15
Known Issues and Workarounds ............................................................16
New Features in Aspen Engineering V7.0 ................................................16
Icarus Reference .................................................................................16
Piping and Instrumentation Drawings .....................................................16
Technical Support .........................................................................................16
Online Technical Support Center............................................................16
2 Getting Started...................................................................................................17
Starting Aspen Process Economic Analyzer........................................................17
Starting a Project Scenario .............................................................................18
Creating a New Project Scenario............................................................18
Importing an Aspen Process Economic Analyzer 5.0/5.1 Project Scenario ....22
Opening an Existing Project Scenario ...............................................................24
Understanding the Icarus Interface..................................................................26
Project Explorer ..................................................................................26
Main Window ......................................................................................28
List View ............................................................................................30
Palette...............................................................................................32
Properties Window...............................................................................34
Customizing the Icarus Interface ...........................................................35
Aspen Process Economic Analyzer's Toolbar ............................................36
Aspen Process Economic Analyzer Menu Bar............................................38
Working with Project Scenarios .......................................................................42
Saving Project Scenarios ......................................................................42
Deleting Project Scenarios ....................................................................43
1 Introduction
1 Introduction
1 Introduction
1 Introduction
1 Introduction
1 Introduction
1 Introduction
1 Introduction
10
1 Introduction
Main Features
Links to Process Simulator Software
Programs
Aspen Process Economic Analyzer, formerly known as Aspen Icarus Process
Evaluator, uses expert system links to effect the automatic transfer of your
process simulator output results. Links are available to process simulator
programs from AspenTech, Chemstations, Hyprotech, SimSci and others.
Aspen Process Economic Analyzer can link to virtually any commercial and
proprietary process simulator program.
1 Introduction
11
Sizing of Equipment
Size of equipment is a prerequisite to costing and the results of size
calculations performed during process simulation are loaded automatically by
Aspen Process Economic Analyzer. With Aspen Process Economic Analyzer,
you can revise sizes, enter your values for unsized equipment or develop
sizes using Aspen Process Economic Analyzers built-in expert sizing
programs.
1 Introduction
12
automatically re-size all project components and stream flows. You can
change the plant location (choosing from twenty-two different countries), and
Analyzers plant relocation technology will automatically revise the design and
cost basis parameters, including parity exchange rate, workforce rates,
productivities, and construction practices.
1 Introduction
13
Notes:
During the project workflow, you can go back to previous steps to refine
the project.
The Guide
Organization
This guide contains the following:
1 Introduction
14
Related Documentation
In addition to this document, a number of other documents are provided to
help users learn and use Aspen Process Economic Analyzer. The
documentation set consists of the following:
Installation Guide
Aspen Engineering V7.0 Installation Guide
1 Introduction
15
Icarus Reference
Aspen Icarus Reference Guide, for Icarus Evaluation Engine (IEE)
Technical Support
Online Technical Support Center
AspenTech customers with a valid license and software maintenance
agreement can register to access the Online Technical Support Center at:
http://support.aspentech.com
H0TU
UTH
Send suggestions.
1 Introduction
Technical advisories
Product updates
16
2 Getting Started
Click the Windows Start button, point to Programs, and then point to
AspenTech.
Aspen Process Economic Analyzer starts. The Main window, empty because
no project is open, appears on the left. The Palette appears in the upper-right
and the Properties window appears in the lower-right.
2 Getting Started
17
-or
Click
on the toolbar.
2 Getting Started
18
Note: You can create scenarios in project directories other than the default
one provided by Aspen Process Economic Analyzer. See Preferences
Locations on page 50 for instructions on adding project directories.
X35H
This is the name of the scenario within the project. As with the Project Name,
long filenames are accepted, including spaces, while punctuation marks, such
as question marks (?), exclamation points (!), tildes (~), and asterisks (*) are
not allowed.
If you do not enter a Scenario Name, Aspen Process Economic Analyzer uses
BaseCase as the default.
4
Click OK.
2 Getting Started
19
In the Units of Measure section, you can keep the default basis of
Inch-Pound (IP) or select Metric. The Units of Measure selection cannot be
changed after creating the project scenario.
If desired, enter more details about the project scenario in the Remarks
field. Remarks can be up to 6,000 characters in length and can be
comprised of letters, numbers, and punctuation. Remarks can be edited
later by accessing Project Properties from the Project Basis view (see page
56).
X37H
Click OK.
For example, if you want to use CM/H (centimeters per hour) instead of M/H
(meters per hour) to specify conveyor belt speed in your metric-basis project,
do the following:
9
10 On the Velocity and Flow Rate Units form, enter CM/H as the new unit
name for M/H. Then enter the conversion factor between the two units in
the Conversion field. In this example, the conversion factor between the
two units is 100 because:
100 CM/H = 1 M/H.
2 Getting Started
20
11 Click OK to accept the modifications and return to the previous dialog box.
When finished modifying input units of measure, click Close.
Aspen Process Economic Analyzer displays the General Project Data form,
where you can select a country base and currency.
The default country base is US and the default currency is Dollars (USD).
Changing the country base automatically changes the currency to that of the
country base. You can, however, enter a currency different than that of the
country base. Just be sure to also enter a currency conversion rate (the
number of currency units per one country base currency unit).
Country base affects various system default values. Chapter 36 of Icarus
Reference provides a table listing the default values used for each country
base.
2 Getting Started
21
This is the only time you can enter country base and currency. Other
specifications on this form can be entered later by selecting General Project
Data in the Project Basis view (see page 57).
X38H
-or
Click
on the toolbar.
2 Getting Started
22
Note: You can create scenarios in project directories other than the default
one provided by Aspen In-Plant Cost Estimator. See Preferences Locations
on page 50 for instructions.
X340H
This is the name of the scenario within the project. The selected Aspen
Process Economic Analyzer 5.0 or Analyzer 2.0B project files project and
component specifications will be imported into this scenario.
Again, long filenames are accepted, including spaces, while punctuation
marks, such as question marks (?), exclamation points (!), tildes (~), and
asterisks (*) are not allowed.
After making an entry in the Scenario Name field, the Import button
becomes active.
4
Click Import.
Select either Aspen Process Economic Analyzer 5.0 and 5.1 or Analyzer
2.0B and click OK.
2 Getting Started
23
The project scenarios settings will be imported into the new project scenario.
-or
Click
on the toolbar.
Note: In the pictured dialog box, the project named Expansion has been
expanded on the tree structure to show the scenario named BaseCase.
2 Getting Started
24
The tree structure on the left side of the dialog box displays the projects in
the default project folder:
...\AspenTech\Economic Evaluation V7.0\Data\Archives_Aspen Process
Economic Analyzer
Clicking + next to a project expands the view to display the scenarios under
that project. Selecting a scenario displays the following scenario information
in the pane on the right:
The project scenario opens. The Main Window now displays Project Explorer
and the List view. See Understanding the Icarus Interface on page 26 for
instructions on working with these and other features now available on the
interface.
X341H
Palette Shortcut
You can also open a project from the Palette, which appears to the right of
the Main Window in the default interface arrangement (it can also be floated
in the Main Window or dragged onto the Main Window and re-sized, as shown
below).
In the Projects view tab, right-click a scenario; then, on the menu that
appears, click Open.
2 Getting Started
25
Main Window - Provides workspace for all Aspen Process Economic Analyzer
documents, List view, specification forms, and other views. See page 28.
X34H
Project Explorer - Organizes project items in tree format. See page 26.
X34H
Palette - Allows access to libraries, projects, and components. See page 32.
X345H
Project Explorer
Project Explorer is a graphical representation of the project. It has three
views:
Process view
Project view
2 Getting Started
26
To switch views:
Click the appropriate tab at the bottom of Project Explorer. (Stretching the
width of the Project Explorer will display the full names on the tabs.)
Click the
PLUS SIGN
Click the
MINUS SIGN
Icon
Description
Specifications folder
Specification
Icon
Description
Icon
Description
Area
Project component
2 Getting Started
27
Main Window
The Main Window is located to the right of Project Explorer by default. The
Main Window is a workspace for all Aspen Process Economic Analyzer
documents, the List view, and other views. The relative size of each window
can be adjusted by clicking on the division bar and dragging it to the desired
location.
Here, the Main Window in Workbook Mode displays several tabs because a
component specifications form and a project specifications form have been
opened.
Workbook Mode
By default, the Main Window is in Workbook Mode. In this mode, tabs are
placed at the bottom of the window. These tabs represent all windows open in
the Main Window. Clicking on a tab brings the associated window to the
foreground.
Clicking Tile or Cascade on the Window menu displays all windows open in
the Main Window. Regardless of the window arrangement, the tabs are still
at the bottom of the Main Window when in Workbook Mode. Clicking the
maximize button ( ) on a window returns all windows to full tab view.
Clicking the condense button ( ) on the menu bar displays all windows open
in the Main Window as they were when last condensed.
2 Getting Started
28
This is how the Main Window appears when in Workbook Mode with
Cascade selected as the condensed window arrangement.
Aspen Process Economic Analyzer lets float Project Explorer, the Palette, and
the Properties Window in the Main window. When in this state, these windows
behave identically to other windows that are part of the Main Window. See
Customizing the Icarus Interface on page 35 for details.
X348H
You can turn off Workbook Mode by unmarking Workbook Mode on the
View menu.
When Workbook Mode is off, no tabs are displayed. In this Mode, to bring a
window to the front, you must click on the desired window or select the
desired window from the Window menu.
2 Getting Started
29
List View
The List view in the Main Window displays details on items selected in
Project Explorer. For example, when you click on an area in Project Explorers
Project view, the List view displays a list of all components in the area. This
is referred to as the area-level list (shown below), in which the components
are displayed in rows with component details in columns. When you click on a
component in Project Explorers Project view, the List provides information
only on the selected component, with component details listed in rows. This is
referred to as the component-level.
Note: In the interface arrangement pictured here, the Palette and the
Properties Window have been hidden to make room for the Main Window.
to
press
ALT+1
ALT+2
ALT+0
Filtering Mechanism
You can limit area-level lists to a single category of component. To do so,
click the drop-down arrow on the toolbar and click on a category.
2 Getting Started
30
For example, if you click ? Incomplete Items, the list will only include
components that still have specifications that need to be entered in order for
the component to be included in an evaluation.
Column Settings
You can select which columns appear on the area-level list and in which
order.
A pop-up menu lists all of the columns. Columns currently displayed are
checked.
To move a column to the right on the List View, click Move Down.
2 Getting Started
31
To return the columns to the default setting (shown above), click Reset.
When you restart Aspen Process Economic Analyzer, all columns will be
displayed in the default order unless Save Window States is selected in
Preferences (by default, Save Window States is selected). See Saving
Window States on page 36 for more information.
X349H650
Palette
The Palette contains elements that you can apply to the project scenario. If
you think of Project Explorer as a picture of the project scenario, you might
think of the Palettes contents as the pigments and dyes used to first sketch
out and then color in that picture.
For example, if you wish to import areas or components from another
scenario into your current scenario, you can double-click on the scenario in
the Palette to get a listing of its areas and components and then drag the
area/component to the Project Explorers Project View. (See Importing Areas
and Components on 198.)
351H
2 Getting Started
32
Finally, when you add a component to the project scenario, you can choose
from the components listed in the Palettes Components view. Then, after you
add the component, it appears in Project Explorers Project view. (See
Adding a Project Component on page 182).
X35H
In the default interface arrangement, the Palette appears on the right side of
the screen. Like Project Explorer, it can be displayed in a variety of ways. See
Customizing the Icarus Interface (page 35) for display options. To
hide/display the Palette, press ALT+1 or used the checked command on the
View menu.
X354H
As indicated previously, the Palette has three views: Projects, Libraries, and
Components. The Components view, shown below, has a scrollable split
window that displays details on equipment items. The division bar can be
adjusted to hide or expand the details section.
Note: The Palette pictured in this section has been dragged onto the Main
Window and re-sized.
2 Getting Started
33
default project folder and any other active project folders. (See Preferences,
particularly the Locations subsection on page 50, for instructions.)
X35H
Properties Window
When you select a field on a specifications form, the Properties Window
provides a description of the field. The description often includes minimum,
maximum, and default values.
Here, the Properties Window (docked on the right side of the screen) displays
information on the Heat Transfer Area field, which is selected on the
specifications form.
Clicking on the Properties Window freezes and unfreezes the content. When
the content is frozen, you can move to another field while retaining the
description of the original field in the Properties Window.
2 Getting Started
34
Like the Palette and Project Explorer, the Properties Window can be displayed
in a variety of ways. See Customizing the Icarus Interface on page 35 for
display options.
X356H
Note: When the Float In Main window is selected on the pop-up menu, the
Allow Docking option is inactive.
Click the border that contains the Close button ( ) and hold down the
mouse button. A bounding outline will appear as you drag the window.
Drag the outline to the desired edge and release the mouse button.
2 Getting Started
35
When multiple windows are docked to the same edge, you can use the
division bar to adjust the relative sizes. You can also use the Contract/Expand
( / ) buttons to either switch from one window to the other or split the
side.
2 Getting Started
36
to
Create a new project scenario. See Creating a New Project Scenario on
page 18.
X358H
Save the current project. See Saving a Project Scenario on page 42.
X360H
Print.
Load simulator data. See Loading Simulator Data on page 143.
X361H
Load Capital Costs and other reports. See page 405 for instructions.
X364H
X368H
X370H
Zoom in. Active in PFD and Block Flow Diagram (BFD) view.
Zoom out. Active in PFD and BFD view.
Hide/Display ports in PFD view.
Go back. Navigate back through previously viewed links.
Go forward. Navigate forward through previously viewed links.
Other buttons that appear on the toolbar are always inactive in Aspen Process
Economic Analyzer. They are for use in other Icarus programs.
2 Getting Started
37
Click
this
to
New
Open
Close
Save
Save As
Save the current project scenario as a different file. Details on page 42.
X371H
X372H
X37H
X374H
Import
Export
to
Icarus
2000
Save the current project scenario as an Icarus 2000 (*.ic2) project file.
Print
Preview
Print
Setup
View and modify printer name and properties, paper size and source, and
orientation.
Page
Setup
Exit
2 Getting Started
38
Run Menu
Click this
to
Load Data
Map Items
X376H
X37H
Evaluate
Project
Develop
Schedule
Scan for
Errors
Regenerate
Block
Diagram
Regenerate the Block Flow Diagram. If you have indicated that some
of the simulator streams are utility streams, the placement of blocks
will reflect this.
Regenerate
Process Flow
Diagram
Reroute All
Streams
Re-number
X378H
X379H
X380H
X381H
X382H
2 Getting Started
39
View Menu
Click this
to
Toolbar
View or hide the toolbar. See page 36 for description of the toolbar.
Status Bar
View or hide the status bar. See page 26 for description of the status
bar.
Project
Explorer
Palette
View or hide the Palette. See page 32 for description of the Palette.
Properties
Window
Workbook
Mode
Capital Costs
View
X38H
X384H
X385H
X386H
X387H
X38H
X389H
X390H
Investment
Analysis View
Block Flow
Diagram
Display Block Flow Diagram of the loaded simulator data. See page
146 for details.
Process Flow
Diagram
Display Process Flow Diagram. This command is not active until you
have mapped the simulator items. See page 171 for details.
Streams List
X391H
X392H
X39H
2 Getting Started
40
Tools Menu
Click this
to
Icarus Editor
External
Simulation
Import Tool
Access the simulator link for importing simulation data. See page 139
for instructions on using this tool with HYSYS.
Options
X395H
Click this
to
Automatic
Item
Evaluation
View
Spreadsheets
in Excel
Reporting
Assistant
Access the Reporting Assistant Options dialog box, where you can
create your own customized report spreadsheets, combining
information from all other Icarus generated spreadsheets. See pages
455 through 455 for details.
X396H
X397H
Custom Tasks
Preferences
2 Getting Started
X398H
41
Window Menu
Click this
to
Cascade
View the Main Window contents in Cascade mode. See page 28.
Tile
View the Main Window contents in Tile mode. See page 28.
Arrange Icons
# XXX
X39H
X40H
Help Menu
Click this
to
Contents
Documentation
Training
Product
Support on the
Web
About
2 Getting Started
Click
42
You can select in Preferences not to have this prompt appear (see page 47).
X401H
2 Getting Started
In the project directory, right-click the scenario within and, on the menu
that appears, click Delete.
43
Note: You can select in Preferences not to have this prompt appear (see
page 47).
X403H
A window appears asking if you wish to save the cached information found in
storage.
2 Getting Started
44
Click Yes.
You cannot overwrite the scenario being salvaged. Y you must specify a
project and scenario name different from that of the original scenario.
4
Click OK.
Aspen Process Economic Analyzer creates the new scenario. Except in name,
this project scenario is identical to the scenario that was open when Aspen
Process Economic Analyzer was abnormally exited. After creating the new
scenario, Aspen Process Economic Analyzer asks if you want to open it.
2 Getting Started
45
Right-click on the project scenario in the Palette and click Unlock on the
pop-up menu.
You can now open the project scenario as you normally would.
Preferences
The settings in Preferences allow you to specify how Aspen Process
Economic Analyzer will act each time it is used.
To access Preferences:
U
2 Getting Started
46
Click
To do this
OK
Apply
Cancel
General
In the General tab view, you can select the following:
Prompts
Select which prompts appear.
Close Project prompt to save any changes when closing project.
Overwrite Project prompt to confirm overwriting project that has the same
name as the one being created.
Delete Project prompt to confirm deletion of project.
Delete Area prompt to confirm deletion of area.
Delete Component prompt to confirm deletion of component.
Cancel Component Edit prompt to save changes when you click Cancel after
editing a Component Specifications form.
Delete Library prompt to confirm deletion of library.
2 Getting Started
47
Capital Cost Report mark to display the Capital Cost Report in Icarus Editor.
Reporter Report mark to display the Single Component Summary, exported
from Aspen Icarus Reporter, in the Main Window.
Display
Save Window States mark to have Aspen Process Economic Analyzer save
the position of Project Explorer, the Main Window, the Palette, and the
Properties Window, as well as selected columns on the List view. Unmark to
have Aspen Process Economic Analyzer open with the default interface
arrangement (shown on page 26).
X407H
Display Aspen Capital Cost Estimator & Analyzer Choice Dialog on Aspen
Process Economic Analyzer mark to have Aspen Capital Cost Estimator ask
you at startup whether to use Aspen Process Economic Analyzer and/or
Analyzer in the Aspen Process Economic Analyzer environment. This option is
included here because Preference selections (except for file locations) made in
one product affects all other Aspen Icarus products in the AES suite.
Show Report Group in Aspen Capital Cost Estimator mark to have Aspen
Capital Cost Estimator display Report Groups.
Forms
The Forms tab view provides options related to Component Specification and
Installation Bulk forms.
Display P&I Installation Bulks in Grid mark to have Aspen Process
Economic Analyzer display all items on the Installation Bulk specification
forms for Pipe and Instrumentation. If you unmark the checkbox, Aspen
Process Economic Analyzer allows you to select, when opening the form, the
items to include.
Use OK Button in Installation Bulks Form to Go to Main Component
Form mark to have Aspen Process Economic Analyzer return you to the
main Component Specifications form when you click OK at an Installation
Bulks form. Otherwise, clicking OK simply closes the Component
specifications.
2 Getting Started
48
Backup
The Backup tab view lets you select when backups are to be performed. You
can select both options.
Automatic Task Backup mark to have Aspen Process Economic Analyzer
perform a backup before executing major tasks, such as a project evaluation.
Timed Backup (Interval, in minutes) mark to have Aspen Process
Economic Analyzer perform a backup at a specified interval. Specify the
interval in the box provided.
You can also select to either have Aspen Process Economic Analyzer overwrite
the project backups or create unique backups.
Overwrite Project Backups mark to have Aspen Process Economic
Analyzer overwrite the previous backup every time the program performs a
backup.
Unique Project Backups mark to have Aspen Process Economic Analyzer
retain previous backups by creating a unique backup each time. Depending
on the frequency of backups (see task and timed backup options above),
selecting Unique Project Backups could result in large amounts of disk space
being consumed by backups.
Process
The Process tab view provides options for importing from an external project.
Import Connected Streams mark to include connected streams when
importing an external project.
Import Installation Bulks mark to include installation bulks when
importing an external project.
The Process tab view also provides options for unsupported simulator models
and custom model tool activation.
Map Unsupported Models To Quoted Cost Item mark to have Aspen
Process Economic Analyzer map, by default, unsupported simulator models to
quoted cost items.
Unsupported Models refer to models not listed in the Project Component
Map Specifications dialog box shown on page 80. Aspen Process Economic
Analyzer does not recognize them and, therefore, cannot map them to Icarus
project components. If this option is left unmarked, Aspen Process Economic
Analyzer will not map unsupported models. As a result, a unit operation could
appear disconnected in the Process Flow Diagram (PFD).
X408H
Quoted cost items are not project components, but act as place markers to
ensure that unit operations remain connected in the PFD.
2 Getting Started
49
Note that marking this option will not affect the mapping of supported
simulator models. If a simulator model is listed in the Project Component Map
Specification dialog box, then the specified mapping will be used. Further, if a
simulator model is listed and has no default mapping (that is, Current Map
List section is blank), then it is assumed that the user does not want to map
such simulator models to any Icarus project components.
For example, if this option is marked, a USER unit operation in Aspen Plus can
be mapped to a quoted cost item if this option is marked. This ensures that
the unit operation remains connected in the PFD.
Activate Custom Model mark to activate the Custom Model tool explained
on pages 206 through 212.
X409H
X410H
UTH
Locations
In the Locations tab view, you can select:
Project Directories
Add/remove alternate project directories and set the default project
directory. See Adding Project Directories on page 51 for instructions.
X41H
Note: In some cases the description warns against changing the location.
Note: Make sure to create the IP and MET subfolder structure when
changing the source locations for library files that are units dependent (for
example, Basis for Capital Cost, EML, UML, Custom Piping Specs, and so
on).
2 Getting Started
50
2 Getting Started
51
Select the folder you wish to add as an alternate directory and click OK.
To set an alternate project directory as the default, select it and click Set
Default.
Aspen Process Economic Analyzer displays a prompt asking you to confirm the
change.
4
2 Getting Started
52
If the old default location is not on the list of alternate project directories,
Aspen Process Economic Analyzer displays another prompt asking if you wish
to add it to the list.
Note: Adding the old default directory to the alternate project directory list
lets you easily revert to it.
6
Before the added project directory appears on the Create New Project dialog
box and elsewhere, you will need to either restart Aspen Process Economic
Analyzer or else right-click on the current project in the Palette and click
refresh on the pop-up menu.
Logging
The Logging tab view is reserved for future releases, in which it will be used
to help clients with Technical Support issues. It is not currently activated.
2 Getting Started
53
2 Getting Started
54
The Project Basis defines specifications that pertain to the overall project
scenario. These specifications influence the design and cost estimate by
defining system defaults and environmental variables.
Project Basis Specifications are accessed from the Project Basis view in
Project Explorer.
A red arrow on an icon indicates that you can right-click on the item to access
a pop-up menu.
55
Project Properties
Project Properties are initially specified when creating a new project.
Project Name
Scenario Name
Units of Measure
Remarks: Any remarks entered will appear immediately after the Title
Page of evaluation reports in Icarus Editor. Remarks can be up to 6,000
characters in length and can be comprised of letters, numbers, and
56
Units of Measure
Country Base
Currency Symbol
57
Estimate Date: Appears immediately under the project title at the top of
the Title Page in Icarus Editor. Reports generated by Aspen Icarus
Reporter also include an Estimate Date; however, the Estimate Date
shown in Aspen Icarus Reporter is the date on which the project
evaluation was run.
Click IMPORT.
The dialog that appears defaults to looking for the .D01 files for your Aspen Process
Browse to the Aspen Process Economic Analyzer project you want to import.
Your Aspen Process Economic Analyzer template (standard basis file) is now
in the new Aspen Icarus Project Evaluator system.
Workforce wage rates (for both the overall project and by craft),
productivities, and workweek definition.
58
With no project open, expand the Basis for Capital Costs folder in the
Palettes Libraries view. Expand the appropriate units of measure basis
folder Inch-Pound or Metric. Right-click on one of the specification files
and click Modify.
Note: If you are modifying a file you will need to later select the file in the
project. To do so, right-click on Basis for Capital Costs in the Project
Explorers Project Basis view, click Select, and select the file.
Aspen Process Economic Analyzer displays the Basis for Capital Costs
library in Project Explorer.
59
If, for example, you want to use CM/H (centimeters per hour) instead of
M/H (meters per hour) to specify conveyor belt speed in your metric-basis
project, click Velocity and Flow Rate and then click Modify.
On the Velocity and Flow Rate Units form, enter CM/H as the new unit
name for M/H. Then enter the conversion factor between the two units in
the Conversion field. In this example, the conversion factor between the
two units is 100 because:
Click OK to accept the modifications and return to the previous dialog box.
60
You can change the basis for all output units of measure by selecting a
different basis in the Unit of Measure Basis section; however, note that this
voids all previous customizations.
2
To customize only individual units, such as velocity and flow rate units,
select the unit type and click Modify. Then, for each unit you wish to
change, enter the new unit name and the conversion factor (between the
old and new units).
61
In this example, centimeters per hour (CM/H) replaces meters per hour
(M/H). A conversion factor of 100 has been entered because 100 CM/H = 1
M/H.
3
For example, if you want to use CM/H (centimeters per hour) instead of
M/H (meters per hour) to specify conveyor belt speed in your metric-basis
project, enter CM/H as the new unit name for M/H. Then, enter the
conversion factor between the two units in the Conversion field. In this
example, the conversion factor between the two units is 100 because 100
CM/H = 1 M/H.
Click OK to accept the modifications and return to the previous dialog box.
General Specs
General Specs greatly affect the total capital and operating cost of the
project.
Right-click General Specs in the Project Basis views Basis for Capital
Costs folder.
The section of the Standard Basis file containing General Specs appears in a
specification form.
62
Since the process is new and unproven, contingency value is made high
compared to the base condition. Also, since the process complexity is high,
the contingency is raised again. The Grass roots/Clear field project type
lowers the contingency because of reduced site constraints.
Note: You must clear the Contingency Percent field for the system to
calculate the contingency based on your changes.
Field
Description
Process
Description
Process
Complexity
63
Field
Description
instrumentation and controllers (for
example, batch), whereas simplicity
implies offsites.
Process Control
Project Information
Project Location
Project Type
Contingency
Percent
Estimated Start
Year/Month/Day
of Basic
Engineering
Soil Conditions
Around Site
64
Field
Description
Equipment Specification
Pressure Vessel
Design Code
Vessel Diameter
Specification
P and I Design
Level
North America = 4
South America = 5
Central America = 5
Europe = 1
Asia = 1
Africa = 4
Australia =
Specifies cost of ocean freight as a percentage of material costs. The value for
this field depends on the project location selected in the standard basis.
Ocean freight for the different locations is adjusted based on the percentage
of plant material that can be purchased locally. The percent adjustments for
the different locations are:
North America = 0
South America = 8
Central America = 5
65
Europe = 0
Asia = 0
Africa = 8
Australia = 12
Taxes/Duty (% of material)
Specifies taxes as a percentage of total material costs. The value used in the
capital cost evaluation depends on the project location chosen in the file. They
are:
Europe = 0.00
Asia = 6.00
Africa = 4.00
Australia = 7.00
Contingency (%)
Process Description
Process Complexity
Project Type
You must clear the Contingency Percent field for the system to calculate the
contingency based on your changes.
The following data defines the general design conditions to be applied to the
entire project being estimated; this information is used to reflect the desired
project design methodology.
New process = 10
Redesigned process = 7
Licensed process = 5
Proven process = 3
66
compressors, drivers and generators. The following value is chosen for the
above field based on the project location:
North America = 7
South America = 10
Central America = 10
Europe = 7
Asia = 10
Africa = 15
Australia = 7
Specifies the soil type used to develop data for civil work throughout the
project. Based on the soil type chosen, soil loading and soil density are
selected. Icarus Reference, Chapter 19, provides a complete definition for all
the soil types. Once the soil type is selected, the system automatically selects
the type of piles used in the project. The following pile types will be selected:
Soil Type
Pile Type
Soft clay
Firm clay
Wet sand
Sand+clay
Dry sand
Sand
Gravel
Soft rock
Hardpan
Med-rock
Hard rock
Power Distribution
MAIN Substation
UNIT
67
Grass roots/Clear
field
Transformers,
Switchgears
MCC, SW
Transformer
Switchgear
MCC
Switchgear
MCC
None Added
None Added
Plant Modifications
/ Revamps
Switchgear
MCC
Process Control
Components Included
Project Type
Operator Center
Control Center
The system
Grass roots/Clear field YES
YES
develops a
Plant
addition
NO
NO
project schedule
suppressed
based upon the
infrastructure
estimate scope
All others
NO
YES
of work
including dates and durations for design engineering, procurement, delivery
of materials and equipment, site development and construction. The
construction schedule is integrated with the cost estimate to provide the basis
for estimation of schedule-dependent costs such as equipment rental
requirements, field supervision and construction management.
The schedule commences at the start of basic engineering, as indicated by
the date for basic engineering in the standard basis file.
In addition, the General Specs provide defaults for various general design
conditions that control project design methodology. This in turn affects costs
for equipment, material and manpower, and the overall project schedules.
These defaults are not editable in Aspen Process Economic Analyzer. The
following defaults (based on their major categories) are used by Aspen
Process Economic Analyzer to convey specifications for the project design
data:
68
Item
Defaults
Equipment
Piping
Steel
Project Schedule
Specifies an adjustment, as a
percentage, to the schedule durations
developed by the system for delivery of
equipment items, bulk materials, control
system. This adjustment applies to
receipt of vendor data and
fabricate/ship lead times.
Construction Schedule Adjust (%):100
Specifies an adjustment, as a
percentage, to the schedule durations
developed by the system for all
construction manpower.
Bar Symbol: *
69
% man-hour: 100
Engineering
Adjustment for
Detailed
engineering Phase
% man-hour: 100
Contracts
(scope/definition)
Contract number: 1
Construction Workforce
Construction Workforce specifications are divided into General Rates and Craft
Rates.
General Rates
The General Wage Rates information globally sets wage rates and
productivities for all crafts.
To access:
1
Right-click on General Wage Rates in the Project Basis views Basis for
Construction Workforce folder.
70
Description
Number of
shifts
Productivity
adjustment
Indirects
71
Field
Description
Wage Rate
percent of
base
Productivity
percent of
base
Overtime rate
percent
standard
Helper wage
percent craft
rate
72
Field
Description
Craft Rates
Craft Rates set the wage rate and productivity individually for each craft.
To access:
1
Right-click on Craft Rates in the Project Basis views Basis for Capital
Costs\Construction Workforce folder.
Aspen Process Economic Analyzer displays the Wage Rate Info specifications
form in the Main Window.
To add multiple definitions to Craft Wage Rates, click the Add button on
the button bar:
Use these fields to set the wage rate and productivity individually for each
craft.
Field
Description
Craft
wages/prod.
73
Field
Description
crafts not referenced are assigned wage
rates and productivities specified in
General Wage Rate or the system
default values.
Craft code
Wage rate/mh
Productivity
Indexing
The Material and Man-hour specification forms in the Indexing folder allow
you to manipulate the material and/or man-hour costs for process equipment
and installation bulks. You can also adjust these indexes by location by using
the Location specification form.
For example, you could specify to increase the material costs associated with
a type of process equipment.
Indexing is used to tailor Aspen Process Economic Analyzer to mimic your
work methods and costs. If your equipment costs for a category are
consistently offset from Aspen Process Economic Analyzers values, use
Indexing to correct that.
74
To adjust the index for all equipment or for all of one of the installation
bulks, enter the index value in the box provided. For example, entering
200 in the Equipment box will double the material costs for all items
under the equipment account group.
To adjust the index for a sub-category, click the arrow-button in the box. This
accesses a similar form listing sub-categories corresponding to the Code of
Accounts (see Icarus Reference, Chapter 34, for a complete list). Adjustments
to a sub-category override adjustments to the account-group.
3
To adjust by location
1
Type the Code of Account (COA) to indicate the start of the COA range, or
click the red arrow and then click Select by the subcategory on the COA
Subcategory Selection window.
75
76
Enter the amount to escalate material costs and/or the amount to escalate
man-hour costs.
Process Design
The Process Design specifications are used in Aspen Process Economic
Analyzer projects that contain a simulator input. These specs allow Aspen
Process Economic Analyzer to map simulator models into Icarus project
components. For example, a distillation column model in a simulator may be
mapped to a combination of equipment such as a double diameter tower, an
air-cooler (for a condenser), a horizontal tank (for a reflux drum), a general
service pump (for a reflux pump) and a thermosiphon reboiler.
The Process Design Specifications indicate the default settings that the
system uses for mapping all models of the same class. These specs can be
customized in files and used in many projects.
To access:
1
77
Note: Each simulator cross-reference UOM file contains a basis (which may
be METRIC or I-P). The basis indicates the Aspen Process Economic Analyzer
base units set to which simulator units will be converted.
The left side of the screen displays the simulation output units. The right side
of the screen displays the corresponding Aspen Process Economic Analyzer
units. The conversion factors between the two units are entered in the lowercenter section of the screen.
Aspen Process Economic Analyzer provides a set of common simulator units
and their conversions to Aspen Process Economic Analyzer units. You can
modify and/or add units to these files.
Specifying the Mapping for a Simulator Unit
Select the simulation unit from the Units Used list in the Simulation
Output section. In the example below, the simulation unit is CM/HR
(Centimeters/Hour).
Select the appropriate units category from Units Category list in the Aspen
Process Economic Analyzer section. In the example below, the units
category is Velocity.
Select the appropriate Aspen Process Economic Analyzer unit from Units
list in the Aspen Process Economic Analyzer section. In the example
below, the Aspen Process Economic Analyzer unit is M/H (Meters/Hour).
78
Enter the conversion factor between the two units (the simulation unit and
the Aspen Process Economic Analyzer unit) in the Conversion Factor box.
In the example below, the conversion factor between 100 CM/HR = 1 M/H
When a unit has been mapped and saved, a green box appears next to the
simulation unit. A yellow box indicates the unit is not mapped.
Deleting a Mapping
To delete a mapping
Removing a Unit
To remove a particular unit from the simulation units list
79
Adding a Unit
To add a new unit to the list, enter the new unit symbol in the New Units to
Add box in the Simulation Output section and click Add. Changes will not
affect existing project components.
Unsize the item or unmap the items and then re-map and re-size.
Once all of the units have been specified, click OK to store and save the
specifications.
It is critical that all simulator units of measure be mapped into Aspen Process
Economic Analyzer units. When the simulator output is loaded, Aspen Process
Economic Analyzer identifies all units of measure in the file. Any units not
mapped in the projects current simulator cross-reference UOM specification
are automatically added to the list and you are alerted to the need to define
the mapping and re-load the file.
You must correct this in order to continue without problems. Complete the
steps above to specify the mapping for a simulator unit. Scroll through the
Units Used list for any yellow-tagged units. Map all these, save the file, and
re-load the simulator data.
To access:
1
80
Models that are mapped in the current file are marked with an asterisk (*). If
no asterisk is present, then that model will not generate any project
components when loaded, mapped, and sized.
3
You can select a simulator item and review the mapping(s) for that item.
81
Model Description
CCD
Countercurrent
decanter
CFUGE
Centrifuge filter
Centrifuge SOLID-BOWL
COMPR
Compressor/turbine
CRUSHER
Solids crusher
Jaw crusher
CYCLONE
Solid-gas cyclone
DECANTER
Liquid-liquid decanter
DISTL
Shortcut distillation
rating
DSTWU
Shortcut distillation
design
ESP
Electrostatic
precipitator
FABFL
Baghouse filter
FILTER
Continuous rotary
vacuum
FLASH2
Two-outlet flash
FLASH3
Three-outlet flash
FSPLIT
Stream splitter
HEATER
Heater/cooler
HEATX
Two-stream heat
exchanger
HYCYC
Solid-liquid
hydrocyclone
PUMP
Pump/hydraulic
turbine
RADFRAC
Rigorous
fractionation
PETROFAC
Consists of 42
configurations. It has
been confirmed that
the following can be
mapped to Aspen
82
Process Economic
Analyzer:
PREFLIF- preflash
block with furnace,
zero pumparounds
and zero
sidestrippers.
Furnace block
CDUIOF crude
block with furnace,
three pumparounds
and three
sidestrippers.
CDU 3 vacuum
block with two
pumparounds and
two sidestrippers.
RBATCH
Batch reactor
RCSTR
Continuous stirred
tank
REQUIL
Equilibrium reactor
RGIBBS
Equilibrium reactorgibbs
RPLUG
Plug-flow reactor
RSTOIC
Stoichiometer reactor
RYIELD
Yield reactor
SCFRAC
Short-cut distillation
SCREEN
Vibrating system
SWASH
Single-stage solids
washer
VSCRUB
Venturi scrubber
Model Description
BAGH
Baghouse filter
COMP
CFUG
CRYS
Crystallizer or melting by
cooling/heating
CSED
CYCL
DRYE
Dryer
EREA
Equilibrium reactor
ESPT
Electrostatic precipitator
83
FIRE
Fired heater
FLAS
Multipurpose flash
FLTR
GIBS
Gibbs reactor
HCYC
Hydrocyclone
HTXR
Heat exchanger
KREA
LLVF
Vapor/liquid/liquid flash
MIXE
PUMP
Centrifugal pump
REAC
Stoichiometric reactor
SCDS
SCRE
Screen
TOWR
WASH
Washer
Model Description
BAG FILTER
Baghouse filter
COLUMN
Distillation column
(condenser)
COMPRESSOR
Compressor
CSTR
Continuous stirred-tank
84
jacketed
CYCLONE
Gas-solid separator
EXPANDER
Expander
Gas turbine
FILTER
HEATER
Heater/cooler
HEATEX
HYDROCYCLONE
Solid-liquid hydrocyclone
PIPING
Pipeline
PLUG
Plug-flow reactor
PUMP
Pump
RATEHEATEX
REQUI
Equilibrium reactor
RGIBBS
Gibbs-energy reactor
RSTOIC
Stoichiometric reactor
SOLIDSEP
Solids separator
Model Description
AIR COOLER
Air cooler
BAG FILTER
Baghouse filter
COLUMN
Distillation column
COMPRESSOR
Compressor
CSTR
Continuous stirredtank
CYCLONE
Gas-solid separator
EXPANDER
Expander
Turbo expander
FILTER
HEATER
Heater/Cooler
HEATX
HYDROCYCLONE
Solid-liquid
hydrocyclone
PLUG
Plug-flow reactor
PUMP
Pump
REQUI
Equilibrium reactor
RGIBBS
Gibbs-energy reactor
RSTOIC
Stoichiometric reactor
85
SEP
Separator
TANK
Tank
Model Description
CENTRIFUGE
Centrifuge
COLUMN UNITS
Distillation column
(condenser)
Compressor
CRYSTAL
Crystalizer
CSTR
DECANTER
Countercurrent decanter
DEPRESSURE
Non-steady-state depressure
DRYER
Solids dryer
EXPANDER
Expander
Gas turbine
FLASH
FLASH
HEATEX
PLUG
Plug-flow reactor
PUMP
Pump
REACTOR
Reactor
RIGHTEX
ROTDRUM
SHORTCUT
Distillation column
Design Criteria
After the simulator model is loaded into Aspen Process Economic Analyzer,
mapping and sizing of the items can be performed. If an item is already sized
inside the simulator, the sizing parameters are automatically brought into
Aspen Process Economic Analyzer and used.
Items not sized by the simulator can be sized following the instructions in
Chapter 6. In addition to process information obtained from the simulator,
certain design specifications may be required before sizing can be
accomplished.
86
Aspen Process Economic Analyzers Sizing Expert uses design values based on
the user-defined field values on specification forms in the Design Criteria
sub-folder. The values on these forms provide the basis for developing design
specifications from operating conditions for all equipment to be sized.
You can enter design conditions (design pressure and temperature) for all
equipment (using the Common form) and also enter design conditions for
types of equipment. (Conditions entered on the equipment type forms
override those on the Common form).
Common
Design pressure and temperature entered on the Common specifications form
applies to all equipment except equipment for which you have separately
specified these design conditions.
Design Pressure
Click on the Design Pressure field to open the Design Pressure
Specifications form. The specifications form lets you specify rules for
calculating the design pressure based on the range in which the operating
pressure falls. The design pressure is calculated from the operating
pressure using the formula shown on the form. You can modify the
pressure limit (upper and lower limit) as well as parameters A and B.
87
Design Temperature
Click on the Design Temperature field to open the Design Temperature
Specifications form. The specifications form lets you specify rules for
calculating the design temperature based on the range in which the
operating temperature falls. The design pressure is calculated from the
operating temperature using the formula shown on the form. You can
modify the temperature ranges (upper and lower limit) as well as
parameters A and B.
Pumps
In addition to entering design pressure and temperature (see instructions
under Common, page 87), you can enter the following design criteria for
pumps:
X415H
For example:
88
Compressors
In addition to entering design pressure and temperature (see instructions
under Common, page 87), you can enter the following design criteria for
compressors:
X416H
Driver Type
Specifies the driver type used for compressors. The default value is
None. The selections are NONE, GAS ENGINE, MOTOR, TURBINE.
Heat Exchangers
In addition to entering design pressure and temperature (see instructions
under Common, page 87), you can enter the following design criteria for heat
exchangers:
X417H
Launch MUSE
MUSE performs detailed simulation of multi-stream plate-fin heat
exchangers made from brazed aluminum, stainless steel or titanium.
A valid MUSE version 3.3 license is required to use this feature.
Select Yes to launch MUSE during interactive sizing of plate fin heat
exchangers. Select No to run MUSE in the silent mode.
89
Note: The final surface area in general is greater than the calculated
value because of mechanical considerations.
Towers
In addition to entering design pressure and temperature (see instructions
under Common, page 87), you can enter the following design criteria on the
Towers form (applies to all towers):
X418H
The value in this field is added to the calculated height of the tower.
The value in this field is added to the calculated height of the tower.
90
Packed Towers
In addition to entering design pressure and temperature (see instructions
under Common, page 87), you can enter the following design criteria for
packed towers:
X419H
Packing Type
Two types of packings, random and structured, are used in packed towers.
The type of packing affects the flood point pressure drop estimation and
the packing efficiency (HETP) value.
The value in this field is used by the Sizing Expert in the calculation of the
tower diameter and height.
If you do not enter a value, Aspen Process Economic Analyzer uses 1.0 as the
derating factor.
HETP
The concept of HETP (height equivalent of a theoretical plate) enables
comparison of efficiency between packed and plate columns. Because
there are only a few variables that significantly affect HETP and due to the
unreliability of even the best mass transfer models, rules of thumb for
HETP successfully compete with the mass transfer models.
For the packing types available in Aspen Process Economic Analyzer
(given in the Icarus Reference), Aspen Process Economic Analyzer
estimates the HETP value based on the packing shape, dimensions and
type of material. If a user-provided value is available, then the Sizing
91
Expert uses the value in the above field for calculating the height of the
packed tower.
Trayed Towers
In addition to entering design pressure and temperature (see instructions
under Common, page 87), you can enter the following design criteria for
trayed towers:
X420H
Foaming Tendency
Vapor disengagement is easy in non-foaming, low-pressure systems.
However, vapor disengagement from downcomer liquid in foaming
systems is difficult as the liquid hangs on to the entrained vapor.
Sufficient residence time must be provided in the downcomer to allow
adequate disengagement of vapor from the descending liquid. Industrial
practice has created a guideline for the mum downcomer velocity of clear
liquids based on their foaming tendency.
The following values for the downcomer liquid velocity are used based on
the choice for the above field.
Downcomer Liquid Velocity, (FPS)
Tray Spacing, INCHES
Foaming
Tendency
18
24
30
Low
0.4 0.5
0.5 0.6
0.6 0.7
Moderate
0.3 0.4
0.4 0.5
0.5 - 0.6
92
High
0.2 0.25
0.2 0.25
0.2 - 0.3
Tray Efficiency
Overall column efficiency is defined by:
E_oc = N_t/ N_a
where:
N_t =
Number of theoretical stages required for the separation minus
the sum of theoretical stages provided by the reboiler, condenser, and
intermediate heat exchangers.
N_a =
93
If the user specification is not available for the field, then the value is
estimated using empirical correlations from the literature.
Configurations Towers
Use this form to specify design criteria for tower configurations.
Vessels
In addition to entering design pressure and temperature (see instructions
under Common, page 87), you can enter the following design criteria on the
Vessels form (applies to all process vessels):
X421H
Residence Time
For example:
Vessel operation pressure: <250 PSIA
Diameter: 6 FEET
Calculated vessel height: 6 X 3 = 18 FEET
Residence time overrides Process Vessel Height to Diameter Ratio.
94
Agitated Vessels
In addition to entering design pressure and temperature (see instructions
under Common, page 87), you can enter the following design criteria for
agitated vessels:
X42H
Agitator Type
The various types of agitators that can be chosen for design are described
in the Icarus Reference. The type of agitator selected determines the
default driver power and impeller speed. This is used to estimate the
agitation requirements in tanks.
Storage Vessels
In addition to entering design pressure and temperature (see instructions
under Common, page 87), you can enter the following design criteria for
storage vessels:
X423H
95
Once the volume of the storage vessel is determined based on the process
fluid flow rate and design conditions, the actual dimensions (height and
diameter) of the equipment must be estimated. You can specify the
dimensional requirements of the equipment using this field.
A default is used if the field is empty or has value 0.0. The default depends on
the operating conditions for the vessel.
96
When horizontal vessels are used for three phase separations, the heavy
second liquid phase is removed in the drip leg situated at the bottom of
the vessel.
Vertical Vessels
In addition to entering design pressure and temperature (see instructions
under Common, page 87), you can enter the following design criteria for
vertical vessels:
X425H
Miscellaneous
Limestone/Crushed Stones
97
Coal
Cinders
Coke
Wood
Configurations Flash
Use this form to specify design criteria for flash configurations.
Utility Specifications
Most chemical processes require heating or cooling process utility fluids to
operate. In many cases, the choice of which utilities are used plays an
important role in determining the total project cost by defining heat transfer
equipment sizing. In addition, utility costs form an important part of the
operating costs of the plant.
In the design of heat exchangers and reboilers, Aspen Process Economic
Analyzer permits you to select appropriate process utility fluids for the
application. You can select utility fluids from the list already present in Aspen
Process Economic Analyzer or can create your own based on utility fluid
classes allowed by Aspen Process Economic Analyzer. Once the utility
resource for the equipment is selected either by you or by the Sizing Expert,
then an actual utility process stream is created for the equipment. The utility
stream contains the amount of utility used by the equipment. During the
operating cost evaluation, Aspen Process Economic Analyzer processes all the
utility streams connected to the equipment to determine the utility cost for
every utility resource used in the project.
You can override these selections by a combination of disabling/enabling
appropriate utilities and re-mapping and re-sizing the equipment items.
Alternately, you can specify the desired utility in the interactive Sizing Expert.
This method is available even if the utility has been disabled.
To modify or create a utility stream:
1
98
**
In the Create New Utility Stream section, type the name and select one
of the following fluid classes:
99
**
Click Create.
100
Investment Analysis
Investment Parameters
To specify parameters required for investment analysis:
1
101
102
Tax Rate
The tax rate for investment analysis, in terms of percent per period, is used
to calculate the percentage of earnings before taxes that must be paid to the
government.
Depreciation Method
There are four depreciation methods allowed in Aspen Process Economic
Analyzer. The description of each follows:
Straight Line The straight line method is used most commonly. In this
method, the Salvage Value is subtracted from the Total Project Cost. This
result is then divided by the Economic Life of Project, so that the project is
depreciated evenly over its economic life.
Sum of the Digits When this method is used, the Depreciation Expense
decreases during each period of the Economic Life of Project. Therefore, the
highest value for the depreciation occurs in the first period and decreases
every period thereafter. The sum of the digits multiplier is n/((N(N+1))/2),
where N is the Economic amount is the Total Project Cost less its Salvage
Value. For the duration of the projects economic life, this factor is multiplied
by the depreciable amount.
Double Declining (Balance) When this method is used, the project is
depreciated in geometric increments. The multiplier for the first period is 2/N,
where N is the Economic Life of Project. For the second period the
depreciation rate, D2, is (1-D1)D1 where D1 is 2/N. For the third period, the
depreciation rate, D3, is (1-D1)D2. For the fourth period, the depreciation
rate is (1-D1)D3. These factors are multiplied by the Total Project Cost. This
103
process (multiplying the factor by the capital cost) continues until the Straight
Line Method produces a higher value for the depreciation. When the Straight
Line Method produces a higher value, this higher value is used for the
remaining depreciation calculations.
Accelerated Cost Recovery System (ACRS) The ACRS approach assumes
that operations begin during the second half of the first period and stop
during the first half of the last period. Therefore, as a result of the two halfperiods (one at the beginning and one at the end of the operating cycle), it
takes 6 periods to depreciate a project which has an Economic Life of 5
periods. The ACRS adapts the Double Declining Balance Method to the halflife system. The depreciation rate for the first period, D1, is 2/N, where N is
the Economic Life of Project. However, the half-life convention reduces this
factor to 1/N. For the second period the depreciation rate, D2, is D1(1-1/ N).
For the third period the depreciation rate, D3, is D1(1-1/N-D2). This process
(multiplying the factor by the Total Project Cost continues until the Straight
Line Method produces a higher value for the depreciation. When the Straight
Line Method produces a higher value, this higher value is used for the
remaining depreciation calculations.
Escalation Parameters
Project Capital Escalation
This number indicates the rate at which project capital expenses may increase
expressed in percent per period. If the addition of Engineer-Procure-Construct
(EPC) period and start-up period is greater than one whole period, Project
Capital Escalation is used to escalate the capital expenses for periods beyond
the first period.
Products Escalation
This is the rate at which the sales revenue from products of the facility is to
be escalated (increased) in terms of percent per period.
Utilities Escalation
User-entered percentages reflecting the anticipated utility price increase each
period.
104
Laboratory Charges
This is a cost per period indicating the cost of having product analyzed each
period.
Operating Charges
This includes operating supplies and laboratory charges. It is specified as a
percentage of the operating labor costs. (If you specify a value for either
Operating Supplies or Laboratory Charges, the system will add the two
entered values and calculate the percentage of Operating Labor Costs. (This is
done for compatibility with earlier releases of the system.)
Plant Overhead
This field consists of charges during production for services, facilities, payroll
overhead, etc. This number is specified as a percent of operating labor and
maintenance costs. This number should not be used for the construction of
the facility, only for operation after start-up.
G and A Expenses
This represents general and administrative costs incurred during production
such as administrative salaries/expenses, R&D, product distribution and sales
costs. Specify this number as a percentage of subtotal operating costs.
105
Operating Mode
This refers to the operating mode of the facility. The available options are:
Continuous Processing - 24 Hours/Day
Continuous Processing - Less than 24 Hours/Day
Batch Processing - 24 Hours/Day
Batch Processing - 1 Batch per Shift
Batch Processing - More than 1 Batch per Shift
Intermittent Processing - 24 Hours/Day
Intermittent Processing - Less than 24 Hours/Day
The operating mode of the facility affects the number of operators/shift and
maintenance costs of facility equipment.
Process Fluids
Process Fluids indicate the types of fluids involved in the process. The
selection affects operating and maintenance costs. The selections are:
Liquids
Liquids and Gases
Liquids and Solids
Liquids, Gases, and Solids
Gases
106
Aspen Process Economic Analyzer displays the Operating Unit Costs in the
Main Window.
The Operating Unit Cost form specifies Labor Unit Costs and non-heat transfer
Utility Unit Costs.
Labor Unit Costs are given for Operators and Supervisors. The total cost of
operating labor is calculated by:
Determining the total number of operators and supervisors necessary to run
the facility for a certain number of hours.
Adjusting that number for the number of hours the facility operates per
period.
Multiplying that number by the respective Labor Unit Costs and adding them
together.
107
Supervisor
The loaded wage rate paid for supervision in terms of the cost per supervisor
per hour. Supervision includes all labor associated with overseeing personnel
who operate the facility.
Electricity
The unit cost per KWH of electricity used for the facility.
Potable Water
The potable water unit cost per MMGAL or MB used for the plant.
Fuel
The fuel unit cost per MMBTH or MEGAWH used for the plant.
Instrument Air
The instrument air unit cost per KCF or MB.
108
In the Create New Stream section, type a name for the stream.
Click Create.
109
Process Stream
This field provides a list of fluid streams present in the current project. You
can select any stream to represent the raw material. Also, there is a provision
in Aspen Process Economic Analyzer for you to provide actual value for the
raw material rate if none of the process streams represent the raw materials
for the project. In this case, you must specify the field value as none.
Rate
This field gives the total rate of raw materials consumed for the process in the
desired rate units.
When a new raw material fluid is specified, Aspen Process Economic Analyzer
checks whether enough information has been specified to estimate the raw
material cost.
Rate Units
This field describes the flow rate units for the current raw material. The
choices available for the field vary with the selection made for Specification
Basis and your choice of Base UOM:
Specification Basis
I-P
METRIC
Mass, Gas
LB/H
KG/H
KLB/H
MEGAG/H
MLB/H
TON/H
TPH
110
Mass, Liquid
LB/H
KG/H
KLB/H
MEGAG/H
MLB/H
TON/H
TPH
Mass, Solid
LB/H
KG/H
KLB/H
MEGAG/H
MLB/H
TON/H
TPH
Volume, Gas
GPH
M3/H
MMGAL/H
L/S
CFH
KCFH
Volume, Liquid
GPH
M3/H
MMGAL/H
L/S
CFH
KCFH
Volume, Solid
GPH
M3/H
MMGAL/H
L/S
CFH
KCFH
Energy
BTU/H
MMBTU/H
KW
MEGAW
CAL/H
Unit Cost
This field provides the cost value per unit mass, volume or energy used to
estimate the raw material cost for the project.
7
When you are done entering raw material specifications, click OK.
The new stream appears in the Existing Stream list on the Develop Raw
Materials Specifications dialog box. You can enter a maximum of 150 raw
material streams using this dialog box. When done, click Close.
Product Specifications
An investment analysis conducted on any process needs to include an
accurate figure for the projects total revenue. In order to do so, it is very
important to accurately account for all the products obtained from the
process.
Aspen Process Economic Analyzer allows you to identify simulation streams as
product materials for the process. Once the simulation stream is defined,
Aspen Process Economic Analyzer determines the necessary amount of
product materials generated based on the information provided in the product
material specification file.
The product material costs are directly placed in the PROJSUM.ICS
spreadsheet, where they are used for further cashflow analyses.
111
Click Create.
112
Process Stream
This field provides a list of streams present in the current project. You can
select any of the streams to represent the product material. Also, there is a
provision in Aspen Process Economic Analyzer for providing an actual value
for the product material rate if none of the process streams represent the
product materials for the project. In this case, you must specify the field
value as none.
Rate
This field defines the total rate of product materials obtained for the process
in the desired rate units. Do not enter a value if you have specified a process
stream.
When a new product material is specified, Aspen Process Economic Analyzer
checks whether the minimum information necessary to estimate the product
material cost has been specified.
The following minimum information must be present before Aspen Process
Economic Analyzer can proceed with the estimate.
Rate Units
This field describes the flow rate units for the current product material. The
choices available for the field vary with the selection made for Specification
Basis and your choice of Base UOM:
Specification Basis
I-P
METRIC
Mass, Gas
LB/H
KG/H
KLB/H
MEGAG/H
MLB/H
TON/H
TPH
113
Specification Basis
I-P
METRIC
Mass, Liquid
LB/H
KG/H
KLB/H
MEGAG/H
MLB/H
TON/H
TPH
Mass, Solid
LB/H
KG/H
KLB/H
MEGAG/H
MLB/H
TON/H
TPH
Volume, Gas
GPH
M3/H
MMGAL/H
L/S
CFH
KCFH
Volume, Liquid
GPH
M3/H
MMGAL/H
L/S
CFH
KCFH
Volume, Solid
GPH
M3/H
MMGAL/H
L/S
CFH
KCFH
Energy
BTU/H
MMBTU/H
KW
MEGAW
CAL/H
Unit Cost
The field provides the cost value used to estimate the product material cost
for the project.
6
The new stream appears in the Existing Stream list on the Develop Product
Specifications dialog box. You can enter a maximum of 150 product material
streams using this dialog box. When done, click Close.
Developing Streams
After opening a project, new streams can be developed. You have the option
to develop completely new streams or use an existing stream as a base.
When an existing stream is used as a base, the new stream can be either
copied from the existing stream (Absolute Basis mode) or copied from and
linked dynamically to the existing stream (Relative Basis mode).
To develop streams:
1
Right-click Streams in the Project Basis views main folder (at the
bottom).
114
115
The functions of the six buttons on the Develop Stream specifications form
are explained below:
Click
To do this:
OK
Apply
Same as clicking OK, but does not exit the Develop Stream specifications
form. This allows you to review the estimates and revise the data.
Update
Same as clicking Apply, except that if the Primary Fluid Component, the
Temperature, and/or the Pressure were changed, then all the physical
properties of the stream will be estimated using these new values.
Cancel
Exit the Develop Stream specifications form without making checks and
does not save or change any information in the database.
Reset
Mixture
116
fluid selected here is used as the basis for any properties that are unavailable
and need to be estimated to complete the specifications for the stream. The
available general fluid classifications are:
y Alcohol
y Aromatic Liquid
y Halogenated Gas
y Inorganic Gas
y Solid
y Glycerol
y Phosphoric Acid
y Ammonia
y Hydrogen
y Propane
y Argon
y Isopropyl Alcohol
y Propanol
y Carbon Monoxide
y Methane
y Propylene
y Carbon Dioxide
y Methanol
y Steam
y Ethane
y N-Butanol
y Sulfuric Acid
y Ethanol
y Nitric Acid
y Toluene
y Ethyl Benzene
y Nitrogen
y Water
y Ethylene
y Oxygen
If the Primary Fluid Component is specified, the other needed information will
be filled in with default values. This feature is only apparent when no
temperature or pressure is entered into the Develop Stream specifications
form and the Primary Fluid Component is changed. After changing the
Primary Fluid Component, either press Enter or click on another field and the
default values will be loaded. If either the pressure or temperature value is
changed from the default value, clicking OK, Apply, or Update will estimate
the properties at the new condition(s).
Base Stream
The Base Stream field contains the name of the stream on which the
displayed stream was based. This cannot be changed.
If the name begins with the character $, the stream was created using
Absolute Basis and the stream name following this character is that of the
parent stream. A stream created using Absolute Basis uses the data from the
parent stream; however, if the parent steams data changes afterward, the
Absolute Basis stream is not updated.
If the value begins with the character @, the stream was created using the
Relative Basis and the stream name following this character is that of the
parent stream. A stream created using Relative Basis is updated when its
parent streams data changes.
117
Description
Select information from the menu to describe the particular stream. For
example, you can indicate the source component of the stream (for example,
From Pump P-103) or tag it with one of the available utility stream names.
Mass Flow
The Mass Flow fields are used to determine the phase of the stream. For
instance, if the stream has only Liquid Mass Flow specified, the stream is
totally liquid; therefore, it will have no vapor properties estimated for it. The
reverse is true for a case with only a Vapor Mass Flow specified. For cases
with both types of flow, all properties will be estimated and the Primary Fluid
Component will belong to the phase of the largest mass flow.
Note: Aspen Process Economic Analyzer automatically calculates Total Mass
Flow from the individual mass flow values.
Density
The Density fields are required information. Thus, if a particular phase has a
mass flow rate specified, then the corresponding density must also be
specified. Clicking Update will estimate any required density fields based on
the flow rate, except in the case of Solid Mass Density. It is recommended
that you enter a Liquid Mass Density if one is available.
After you click Apply, Aspen Process Economic Analyzer normalizes the
Fraction values to total a sum of one.
The values shown above would change into the values shown on the next
page.
118
The check also combines duplicate entries into one entry by combining the
two fraction specifications.
After the check is done, the components are sorted in order of decreasing
fractional amount, as shown above. When you click OK, Aspen Process
Economic Analyzer loads into the specifications form the name of the fluid
with the highest fraction and the properties of the mixture generated from the
contributions of the individual components.
119
simulator or pre-map streams, then the new description you provided is used
for this calculation.
Also, stream connectivity information is used to identify the nature of the
stream. If the stream is being generated then it is considered to be revenue
for the project, and if it is being consumed it is considered an expense. (Note:
Streams that are connected at both ends to process equipments are ignored
in estimating the utility usage costs. Also, utility streams that have a zero unit
cost do not show up in the final report.)
User-defined streams that are not connected to any equipment (do not show
up in the PFD) are considered as input streams, i.e., consumption.
System-generated utility streams are included in the utility usage calculation
as long as they are connected to equipment. A case where they would be
disconnected would be if you manually disconnect these streams or if the
equipment to which these streams are connected is deleted.
Notes to Analyzer Utility Model (AUM) Users:
Cooling Water utility resources that need to be accounted in the Analyzer
Utility Model (AUM) should be named as either Cooling Water or Cooling
Water xx where xx can be two digits ranging from 01 to 99, for example,
Cooling Water 01.
User-created utility resources that do not adhere to this format (for example,
CW, Sea Water, Cooling Water o3) will not be identified as cooling water
streams and will be excluded from AUM's cooling water analysis.
Cooling water streams that are not associated with any equipment, will be
assigned to the Area with the maximum cooling water flow rate. For areas
assigned to two or more circuits, the collected unassigned cooling water flow
rate will be assigned to the first area in the circuit handling the largest circuit
flow rate.
Cooling water can either be bought or be made. If it is to be made, the dew
point of ambient air added to the lower model limit for the approach gradient
will determine the lowest possible deliverable temperature. To ensure that
your specified cooling water utility resource streams can be made, review the
limits for the two cooling water models (CTWCOOLING and
CTWPACKAGED).
Stream Connectivity
Process streams are connected to project components in a real way. You
can see this in the Process Flow Diagram (PFD) that you can display after
loading and mapping simulator blocks. Each stream has a Source end and a
Sink end. The Source end connects to an Outlet port on a component and the
Sink end to an Inlet as depicted below:
120
In the PFD view, when you Edit Connectivity (see page 175) for the Sink
end of a stream and move the mouse over a component, only Inlet port(s)
turn green, thereby indicating their availability for making a connection to a
Sink end.
X426H
The same concept also carries into the Interactive Sizing form (see page
219). Only streams whose Sink ends are not connected are listed in the
pulldown for any Inlet. This explains why the Inlet and Outlet pulldowns will
include different streams.
X427H
Since the connectivity in the PFD and the Interactive Sizing form are two
ways of looking at the same information, Aspen Process Economic Analyzer
tracks your changes and synchronizes them in both views. Thus, if you
change the connectivity in one view, Aspen Process Economic Analyzer
automatically changes it in the other view.
When you first map and size components, the streams in the simulator will be
connected to the project components and the underlying process conditions of
those streams are available for further use. For example, you may create new
streams based on the properties of any stream, connected or not, then use
these new streams as Sources/Sinks for connecting new components (you
might do this to set up spares). You may also add a New Mapping to an item
already mapped and the newly mapped and sized item utilizes the underlying
stream properties.
Go to the Create tab view on the Develop Streams dialog box. Without
selecting a stream from the Base Streams list, click Create. (The Basis
selection will not matter.)
121
Enter a name for the new stream in the Create Stream dialog box. This
name must not be the same as any existing streams in the project.
Click OK.
Note: See page 116 and 116 for descriptions of the buttons and fields on this
form.
X428H
X429H
Enter values for the new stream. See page 116 for descriptions of the
different fields.
X430H
On the Create tab view on the Develop Streams dialog box, click the
stream to be used as the base.
122
Select the Basis mode. If the Basis mode is Relative, the data from the two
streams will be linked so that when the base stream is changed the new
stream will inherit these changes. If the Basis mode is Absolute, the data
from the base stream is copied to the new stream at the time the new stream
is created. Changes in a base stream will not affect a new stream created via
Absolute basis.
2
Click Create.
Enter a name for the new stream in the Create Stream window. This name
must not be the same as any existing streams in the project. Click OK.
Aspen Process Economic Analyzer displays the specifications form for the
newly created stream. The data is that of the Base Stream. Data appears
gray (dimmed) to indicate that it is relative to a referenced Base Stream.
123
Note: See pages 116 and 116 for descriptions of the buttons and fields on
this form.
X431H
X432H
Even in a Relative Stream, you may override any value with a manual entry.
If you do so, the text turns black, indicating that that value is absolute and
therefore no longer references a Base Stream.
4
Deleting a Stream
Note: Only user-added streams and streams added by the Sizing Expert as
utilities can be deleted.
To delete a stream:
1
At the Delete tab view, select the stream to be deleted. You may need to
use the scrollbars to locate a stream if a large number of streams exist in
the currently opened project.
124
Click Delete.
A dialog box will appear asking for confirmation of the delete action.
3
Specification Libraries
The default specifications are derived from files that you can access, when
outside of a project, from the Palettes Libraries view.
125
Design Criteria
Investment Parameters
Product Specifications
Utility Specifications
When you create a project scenario, Aspen Process Economic Analyzer selects
the specification file to use based upon the selected units of measure basis.
However, you can right-click on any of the above Project Basis specification
categories in Project Explorer, click Select on the pop-up menu, and select a
different file from which to derive the default specifications.
Creating a File
To create a specification file:
1
With no project open, go to the Libraries tab view in the Palette and
expand the desired specification category.
126
Click OK.
Aspen Process Economic Analyzer creates the file and displays the
specifications in a separate window.
6
When you are done, close the specifications window. If a library file is
open, you cannot access another library file or open a project.
See page 129 for instructions on selecting the newly created specification file
to use in a project.
X43H
Modifying a File
To modify an existing specification file:
1
Importing a File
You can import specification files from elsewhere on your computer or
network.
To import a file:
1
In the Palette (Libraries view), expand the library to which you wish to
import a file.
In the Select a File for Import dialog box, locate the file and then click
Open.
127
Duplicating a File
To duplicate a file:
1
In the Palette (Libraries view), right-click on the file you wish to duplicate,
and then click Duplicate on the pop-up menu.
Enter a file name and description (optional) for the new file.
Click OK.
Aspen Process Economic Analyzer creates the file and displays the
specifications in a separate window.
4
When you are done, close the specifications window. If a library file is
open, you cannot access another library file or open a project.
Deleting a File
To delete a specification file:
128
Note: You cannot delete files named Default, only modify them.
Aspen Process Economic Analyzer displays a dialog box listing the files
available for the selected category.
Select a new file from which to derive default specifications and click OK.
129
130
Overview
If the process you wish to evaluate in Aspen Process Economic Analyzer is
based on a simulator file report from a process simulator software program,
the first step, after creating a project scenario and defining the Design Basis,
is to load and map simulation data.
Aspen Process Economic Analyzer supports reports from the following
simulators:
131
Navigate to:
On the Data menu, click Properties. This will open the data browser to
the property specifications.
In the data browser tree structure, open the folder Prop-Sets located in
the Properties folder.
Type a name for the property set or use the default name.
Click OK.
Scroll down the list of available properties, clicking those you wish to
select. To start the scroll window, click in a physical properties cell:
o
MASSVFRA
MASSSFRA
MASSFLMX
VOLFLMX
MASSFLOW
TEMP
PRES
MWMX
132
The specifications for this property set are complete as indicated by the check
mark displayed on the tree view of the data browser.
8
Click the Prop-Sets folder. You will see the property set you just created
in the object manager and the status should be Input Complete.
10 Type a name for the property set or use the default name.
11 Click OK.
12 Click the Qualifiers tab.
13 In the Phase cell, click Total.
14 Click the Properties tab.
15 In the Substream field, click ALL.
16 Now click the Units cell corresponding to the CPMX property and pick
either of the following units:
o
KJ/KG-K
-oro
BTU/LB-R
VOLFLMX
MASSFLMX
KMX
MUMX
CPMX
MWMX
25 Now click the Units cell corresponding to the CPMX property and pick
either of the following units:
o
KJ/KG-K
-oro
BTU/LB-R
133
Move the three property sets you just created to the Selected property
sets box.
Click the > button to move them to the Selected property sets box.
Click Close.
The specifications required for loading an AspenPlus report file are now
complete. You can close the data browser window.
After running the simulation, you must create an output report.
In the Save As dialog box, use the drop-down menu to select Report
Files (*.rep) or XML files (*.xml).
Click Save. This will create the ASCII report file needed to load into Aspen
Process Economic Analyzer with the name given above.
Note: The order on any of the tower models must be set to TOP-DOWN in
order for the tray information to get loaded into Aspen Process Economic
Analyzer correctly. This is the default setting.
134
When the prompt appears, the Aspen Process Economic Analyzer project
name will be designated to be the name of the simulation file from AspenPlus.
AspenPlus will designate the scenario name. If the scenario name is changed,
any future attempts to run the link for the same project will result in a new
Aspen Process Economic Analyzer project being created. It is recommended
that the scenario name designated by AspenPlus be left as it is for maximum
usability.
3
Click OK.
Click OK.
Click OK.
If the simulation has specified units that are undefined, a prompt will appear
to do so. Define all AspenPlus units with those available in Aspen Process
Economic Analyzer.
Click OK.
Because all other project basis settings have been specified, mapping and
sizing can be performed at this time.
135
Note: In ChemCAD for Windows, just click the Output menu from the menu
bar.
2
Select Streams
Stream Properties
Property
Select
De-Select
OVERALL PROPERTIES
Mass flow rate
X
X
Pressure
Enthalpy
Molecular wt.
Total act.dens
VAPOR PROPERTIES
Mass flow rate
Molecular wt.
Vap. Viscosity
Vap. Cp
LIQUID PROPERTIES
Mole flow rate
Molecular wt.
Liq. Viscosity
Liq. Cp
136
Property
Select
De-Select
SOLID PROPERTIES*
Mass flow rate
Molecular wt.
Density
PSD
DISTILLATION OPTIONS
Tray profile
Tray properties
Tray sizing
TRAY COMPOSITIONS
Mass flow rate
If you want Aspen Process Economic Analyzer to use tray sizing information
from the simulator, then you must include the appropriate sizing information.
6
After the completion of all these specifications, generate the output report
by selecting Calculate and Give Results. This should generate an output
report. You can rename it if you wish. This is the file to be used as input
for Aspen Process Economic Analyzer.
MIXER.SPC
TEE.SPC
HTXRATE.SPC
BALANCE.SPC
CALC.SPC
MASSBAL.SPC
MOLEBAL.SPC
For all other operations, use the default .spc files provided by Hyprotech.
137
For HYSIM version 386|C2.12 or earlier, copy the stream format file
STRSUM.FMT located in the /Aspen Process Economic
Analyzer/Docs directory of your HYSIM working directory. If you have
HYSIM version STD:C2.63 and above, copy the stream format file
STRSUM2.FMT located in the /Aspen Process Economic
Analyzer/Docs directory to your HYSIM working directory and rename it
STRSUM.FMT. You must either delete or rename the existing
STRSUM.FMT file to perform this.
The output report generated from HYSIM should contain operation output
(defined as spec_sheet in HYSIM) and the complete stream summary. Both
of these outputs must be saved under the same file name. The information is
appended to the file and does not get overwritten.
operation output
stream summary
The list of streams present in the current project is displayed. Click the <> option for all the streams to be written in file_name.
The procedure creates the required report (file_name), which can be loaded
into Aspen Process Economic Analyzer and used for project evaluation.
If sizing operations are performed inside the simulator and you want the
information to be carried over to Aspen Process Economic Analyzer, the
following steps must be performed in addition to the above procedure:
1
Inside the size option, choose the unit operation desired; then press
Enter.
Select the particular equipment (for example, col-101) ; then press Enter.
Important:
The operation names and stream names can not contain the following
characters:
138
+, -, *, or spaces
The ASCII report has to be created in the default units specified by HYSIM
for the ENGLISH and the SI modes of operation. You can run a simulation
in any simulator-provided units. However, prior to creating the report file,
you must convert the units to the default specifications provided by
HYSIM.
Incorrect
(start stage) 1
user_section_1 :
(end stage) 10
user_section_2:
(start stage) 11
(end stage) 10
user_section_2 :
(end stage) 15
(start stage) 1
(start stage) 3
(end stage) 15
The report format should be such that the width of the report should be
less than or equal to 4 streams wide. This can be accomplished from the
format option provided in HYSIM.
Stream summary should follow the operation output in the report, that
is, the order should be maintained.
139
Select the process simulator project you created; then click Open.
Click the Browse button for the Export File field. The Export File will
contain the exported simulation results data from the selected HYSYS
project. Do not include any file extensions for this file. The import tool will
automatically assign a d01 extension to this file.
Select the location and enter the file name you want to be used to contain
the exported data. You can also select an existing file.
Click Save.
On the Tools menu, click Connect. HYSYS will automatically start with
the selected project.
The following figure shows the file Cheplant.hsc in the HYSYS interface.
140
Click Export on the Simulator Link dialog box to start the process of
exporting the simulation data from the selected HYSYS project into the
Export File.
Once finished, you will see five files with the name you gave to the Export
File. These files contain the exported data.
Note: These files should always go together, in case you want to copy them
to another location.
D:\test\cheplantn.d01 Icarus database file
D:\test\cheplantn.d02
D:\test\cheplantn.d03
D:\test\cheplantn.d04
9
On the Simulator Link dialog box, click Disconnect. The tool will close
HYSYS. If you want to keep HYSYS running and make changes to your
simulation, you can use the Export Again button to export the data again
into the Export File.
You can change the input keyword file (*.inp) to include the required
print options using keywords for those using PRO/II directly
-or
You can change the print options from within the PROVISION user
interface.
For either method, the operation names and stream names should not contain
the following characters:
141
On the Input menu, select Problem Description. Make sure that the
Problem Identifier field is not blank; something must be entered.
Molecular Weights
Actual Densities
Transport Properties
Flowing Enthalpies
E Click OK.
F Repeat for each remaining COLUMN unit operation in list.
Note: See the note in the KEYWORD section regarding COLUMN sidestrippers
UIDs.
9
Using Keywords
For General Print Options, use the following keywords:
Print
INPUT = ALL
STREAM
= ALL
RATE = M
WIDTH = 80
For COLUMN operations, use the following keyword:
Print PROPTABLES = PART or ALL
142
Aspen Process Economic Analyzer displays a message saying what the new
simulator type is.
Click OK.
143
The Open dialog box appears, showing all simulator files in the Report
folder. You can browse other drives and folders as well.
Note: The List view now displays the pathname of the selected simulator file
when you select Simulator File Name in Project Explorer.
6
-or
Click Yes.
144
145
146
Note: You can move a block by clicking on the center of the block and
dragging it to the desired location. This will also move the streams connected
to the block. If the simulator data is reloaded, the block and stream locations
will be regenerated by Aspen Process Economic Analyzer.
In addition to the blocks displayed in the Process view, the BFD displays
streams, direction of stream flows, inlets, and outlets.
The commands on the View menu change when the BFD is active.
147
Block commands
The Map command and Delete Mappings command are explained in the
next section, Mapping Simulator Items to Icarus Project Components, starting
on page 147. Alteration of mapping will alter the blocks' color based on its
status.
Stream commands
You can double-click a stream to access the Develop Stream specifications
form. This form is explained on page 116.
X435H
Zooming
You can use the Zoom In and Zoom Out buttons to increase or decrease the
magnification by degrees:
You can also select an exact magnification by using the Zoom dialog box.
148
The Zoom dialog box also has two options that affect printing:
Fit into one page
Mark this box to have Aspen Process Economic Analyzer re-size the BFD to fit
onto one page when printed. This automatically selects the next option,
What-You-See-Is-What-You-Get, since the screen image will reflect the size
required to fit on one printed page.
What-You-See-Is-What-You-Get (WYSIWYG)
When WYSIWYG is cleared, zooming in or out will only affect the
magnification factor on the screen, while the printer always prints at 100%.
However, if WYSIWYG is selected, the magnification factor on the printer will
be changed so that the printed image will have the same size as the image
appearing on the screen.
149
The View menu contains some options that are only displayed when the Block Flow
Diagram is active
Use this
to
Toolbar
Status Bar
Project Explorer
X436H
X437H
X438H
Palette
Properties Window
X439H
X40H
Workbook Mode
150
X43H
Streams List
Grid Visible
Snap to Grid
Ports Visible
Zoom
If you want to map all items, access the Map dialog box by doing one of
the following:
Click
on the toolbar.
-or
151
If you want to map a single block or all blocks in an area, do one of the
following:
-or
In the Block Flow Diagram, right-click a block then click Map on the
menu that appears.
Note: If you clicked the Map button on the toolbar or clicked Map Items on
the Run menu, only the Map All Items check box is available in the Source
section.
If you clicked Map on a pop-up menu, both Map Selected Item(s) the
default choice and Map All Items are available.
Select the desired mapping options.
Option
Description
Source
152
Option
Description
Basis
Last Mapping
Default
Use the Component Map Specs file for the basis, but
override the mapping using specific data in the simulator.
For example, if you select this option and a reboiler type is
specified in the simulator report, an equivalent reboiler
type will be used in the mapping.
Further, if the Preferences | Process | Use Automatic
Mapping Selection when Available was selected, then
additional engineering rules of thumb will be used for a
selected category of equipments (for example, pumps,
compressors, and heat exchangers) to come up the
mapping recommendations. (Note: Currently this mode is
active only when blocks are mapped one at a time.)
Users are encouraged to review these recommendations
and either accept them or select a different equipment type
based on their knowledge of their processes and practices.
Options
Size Icarus Project
Component(s)
Click OK.
153
Note: All simulator items are displayed because Map all Items was selected
at the previous dialog box. Those components being mapped have asterisks
next to them.
If you selected Map Selected Item(s) on the Map dialog box, the
Simulator Items list displays just the selected simulator block(s). If you
selected Map all Items, the Simulator Items list displays all simulator
blocks.
The Current Map List displays any components that are already mapped to
the simulator block highlighted on the Simulation List.
The Configuration option box is active only for blocks representing column
models. (In the sample project, Block B7 represents a column model.)
You must use the arrow scroll buttons to see all ten possible configurations.
Selecting a configuration type automatically fills in the Current Map List with
the components required for that configuration type. See Tower
Configurations for more information.
4
If the simulator block represents a column model that does not yet have all
its required mappings, the Select a Suffix dialog box appears, listing the
types of components (indicated by suffixes that appear at the end of Item
Descriptions on the List view) that still need to be mapped to the block.
154
Suffix
To indicate
bottoms split
bottoms splitter
bot exchanger
bottoms exchanger
bottoms pump
bottoms pump
Cond
cond acc
condenser accumulator
ovhd exchanger
Overhead exchanger
Overhead split
Overhead splitter
ovhd pump
Overhead pump
precooler
Reb
reflux pump
reflux pump
Tower
main tower
Trim
Other
user-selectable.
spray cond
Spray condenser
sc cooler
155
Select a component.
The Project Component Map Preview dialog box now displays the
component category's item symbol (for example, AG) and the component
type (for example, DIRECT) in the Current Map List. More component
details are displayed in the Icarus Project Component Description
section.
156
By default, the Component Name field contains the block name. You may
want to modify it to be more descriptive and to distinguish the component
from others to which the block has also been mapped. This can be as simple
as adding a descriptor at the end.
Each component mapped from the block must have a unique name; if another
component already has the default component name, Aspen Process
Economic Analyzer prompts you to enter a unique name after you select
another component.
7
With the block now mapped, the List view displays the components mapped
from the simulator block.
Component Status
You may notice a "?" in the Status column of a project component mapped
from the simulator block. This indicates that there are still specifications that
need to be entered for the component.
157
Entering specifications in the required fields will change the status to OK.
Required fields are indicated by color-coding explained on page 186, under
Entering Component Specifications.
X47H
If you do not enter the specifications and the "?" remains in the Status
column, the item will not be included in the project evaluation and will have
"0" cost associated with it. It will not cause SCAN messages.
Deleting Mappings
To delete mappings:
Tower Configurations
Because a column can be mapped to multiple pieces of equipment, Aspen
Process Economic Analyzer requires that you select a tower configuration on
the Project Component Map Preview dialog box.
Standard Single
Standard Total
Standard Split
158
Full Single
Full Split
This term
means
Single
Split
Total
the reflux pump handles the total outlet liquid flow from
the accumulator. In such configurations, the splitting into
a reflux and overhead liquid product occurs after the
reflux pump.
Circ.
overhead pump
159
160
161
162
163
164
165
166
Note: Flow rate of the Spray Cond Total Recycle (SCTR) stream is calculated
using Ratio of Recycle to (Ovhdliqprod + Reflux) Flowrates = mSCTR / (mOVH
LIQ PROD+ mREFLUX). Ratio of Recycle to (Ovhdliqprod + Reflux) Flowrates
is an input specified in the Design Criteria.
mSCTR = mass flow rate of the SCTR stream.
mOVH LIQ PROD = mass flow rate of the Overhead Liquid Product stream.
mREFLUX = mass flow rate of the Reflux stream.
167
The duty for the SC COOLER and SC TRIM exchangers are calculated using
Ratio of SC Trim Duty to Overall Duty = QSCTRIM / QCONDENSER
B
where:
Ratio of SC Trim Duty to Overall Duty is an input specified in the Design
Criteria
QSCTRIM
B
QSCCOOLER
B
QCONDENSER
B
Then the temperatures of the streams exiting the Spray Condenser Cooler
and Spray Condenser Trim exchangers are calculated using:
a Q = mCpDeltaT calculation.
Flow rate of the streams exiting the SC Tot Recycle Trim Splitter are
determined using:
SC Trim Splitter Flow Split Ratio = mSCRTSEx1 / mSCCEx
B
168
SC Trim Splitter Flow Split Ratio is an input specified in the Design Criteria
mSCCE
B
mSCRTSEx1
B
(this is the one that subsequently goes through the SC TRIM exchanger)
mSCRTSEx2
B
Sizing Selection
This section outlines the workflow of the sizing selection feature available in
Aspen Icarus Process Evaluator. Sizing selection is a mechanism that lets you
pre-define and/or define sizing rules for project components. Specifically, you
can set rules on equipment models or specific project components to be sized
with one or more custom models.
If an item is not selected, the mapping preview screen does not appear for
editing during these steps, but the sizing selection specifications is applied
to the selected project component(s).
169
If selected, you will see the Sizing Selection preview after the mapping
preview screen for a chance to edit how the project components are sized
(see Figure 14).
You can specify the sizing routines (System Sizing and custom models) for
each project component (created by mapping from a simulator or manual
creation) that will be applied during the size-all step.
If a custom model is specified in the current sizing list for a project
component, the project component will be sized in the order shown in the
Current Sizing List (see Figure 14). Any custom models listed will be sized
using the custom model tool automatically without any user-interaction
170
Specifying Additional
Components
Icarus project components can be added to areas mapped from a simulator
report. However, these project components must initially be added in a useradded area. You can later rearrange the components in Project Explorers
Project view, drag components from a user-added area to an area mapped
from the simulator report.
Follow the instructions for adding a project component on page 182.
X450H
171
Use the Drag-and-Find feature to locate any equipment item on the PFD.
Drag an equipment item from Project Explorer (Project view) and drop it
on the PFD.
The icon in the PFD that corresponds to the selected equipment will be
positioned in the upper left-hand corner (regardless of magnification).
Note: If you eventually select Reroute All Streams on the Run menu,
Aspen Process Economic Analyzer chooses the most logical routes for all
streams.
172
Use this
to
Toolbar
Status Bar
Project Explorer
Palette
Properties Window
Workbook Mode
173
X460H
Streams List
Grid Settings
Snap to Grid
Ports Visible
Zoom
Add Stream
Edit Connectivity
174
details.
Set the Across and Down grid increments in the Increments section.
Specify in the Units section whether the specified increments are in
inches or centimeters.
Select the Snap to Grid check box to turn on Snap to Grid mode. When
you drag a block in this mode, the blocks bounding outline moves in
increments corresponding to the grid.
Finally, in the Visibility section, click whether to show or hide the grid.
Editing Connectivity
The Edit Connectivity feature lets you make changes to the layout of items in
the PFD. Because this involves connecting and disconnecting streams to
ports, the Ports Visible option should be on, as it is by default.
If the ports are not visible, click the Ports Visible button
175
-or
2
Place the cursor over the end of the stream you want to connect to a
different inlet port.
-or
2
Place the cursor over the added project component that you wish to insert
into an existing stream.
176
Move the cursor over a stream. Click when you have placed the cursor
over the desired stream.
Aspen Process Economic Analyzer disconnects the Sink end of the stream
from the inlet port on the current component, then automatically re-connects
it to the inlet port on the inserted component.
Aspen Process Economic Analyzer also creates a new stream, which appears
white and has properties relative to the initial stream. Aspen Process
Economic Analyzer connects the Source end of this new stream to the outlet
port of the inserted item and the Sink and to the inlet port of the original.
The added item can now be sized manually or using the Size Item option,
which either automatically sizes the item or, if interactive sizing is available,
accesses the Sizing Expert. The Sizing Expert, explained in Chapter 6, will
utilize the newly connected streams.
Adding a Stream
From PFD view, you can create a new stream and specify its connectivity. The
process of developing streams is explained in detail under Developing
Streams, page 114.
X46H
177
To add a stream:
1
-or
Absolute If the Basis Mode is Absolute, the data from the base
stream is copied to the new stream at the time the new stream is
created. If the data of the base stream is altered at any time after
this point, the data of the new stream remains unchanged.
Click Create.
178
Click when you have placed the cursor over the desired outlet port.
Click when you have placed the cursor over the desired inlet port.
179
-or
Use this
to
Modify
Disconnect
Erase the stream from the screen and store it, so that you
can select it when using the Draw Disconnected Stream
feature (see page 179).
Reconnect Source
Reconnect Sink
Delete
X467H
180
5 Defining Project
Components
When developing an Aspen Process Economic Analyzer project, you can add
project components in Project view to user-defined areas (areas not mapped
from the simulation report). Once added, you can drag them to different
areas. Components are categorized as follows:
Note: See ICARUS Reference Guide for information on individual components.
Category
To define
Process Equipment
Plant Bulks
Site Development
Buildings
Quoted Equipment
Equipment Model
Library
181
Adding an Area
To add an area:
1
The Area Type determines how equipment will be installed in the area. See
Chapter 36 of Icarus Reference for information.
4
Click OK.
182
Drag-and-drop
Drag a component from the Palette to an area on Project Explorers Project
view and enter an item description. This adds the component to the area
without displaying the Component Specifications form; the specifications are
left to be entered at your convenience.
Pop-up menu
Right-click on an area and click Add Project Component from the pop-up
menu, then select a component from the Project Component Selection dialog
box and enter an item description. This adds the component and also displays
the Component Specifications form, where you can complete the component
definition right away.
With the Palette (Components view) and Project Explorer (Project view)
displayed, drag a component from the components list to an area on the
Project Explorer.
Note: The Recent Items folder in the Components view stores the last 10
project component selections.
2
To drag, click the component and hold down the mouse button.
Move the cursor until over the area where you want to place the
component.
183
Enter an item description (required) and User Tag Number (optional), then
click OK.
The component is added. Project Explorer displays a block for the component
under the selected area. The List view displays general information. You may
notice a question mark (?) in the Status column on the List view. This
indicates that there are still specifications that need to be entered for the
component. To enter the specifications, follow the instructions under Entering
Component Specifications on page 186.
X468H
184
185
Entering Component
Specifications
After adding a component, you still need to enter at least some component
specifications to complete the components definition. Many component
specifications have default values used when no value is entered, but most
component specifications require further input. If a component added still has
any specifications requiring input, a question mark (?) appears in the status
column of the List view for that component.
You do not have to enter specifications immediately upon adding a
component; you may wish to wait until more information about a project
becomes available.
As more information about a project becomes available, you may also wish to
modify previously entered component specifications. The following
instructions apply as well to modifying previously entered specifications.
Color coding
Red Border: An entry must be made in the field. All specifications forms
have at least one required entry field.
Green Borders and Thick Gray Borders: An entry must be made in either
the field with the thick gray border or in the two fields with the green
borders. The field with the thick gray borders and the fields with the green
186
borders are mutually exclusive. In the form pictured to the right, either
the pump size must be selected or the fluid head and liquid flow rate must
be entered. The Properties Window notes this in the Description.
Enter the specifications.
Note: While on either the component or installation bulks specifications form,
you can quickly determine the net effect of all your changes by clicking the
Evaluate
button and reviewing the resulting report. See page 462 for
more information
X469H701
Fields with red borders are required. If theres a combination of two fields
with green borders and one with a thick gray border, an entry must be made
either in the two fields with the green borders or in the field with the thick
gray border.
To define installation bulks for the component:
1
Click the Options drop-down and select the type of bulks to define.
After defining the component and installation bulks, save the specifications
form by clicking OK.
187
Aspen Process Economic Analyzer displays the specifications form for the
selected installation bulk items. See the subsections that follow for
descriptions of the different types of installation bulks.
4
When you are done defining the installation bulk, save your changes in
either of two ways, depending on what you intend to do next:
o
188
Note: You can select in Preferences to have Aspen Process Economic Analyzer
return you to the main Component Specifications form after you click OK (see
page 48).
X473H
Matl/Man-hours Adjustments
Using Matl/Man-hours Adjustments, you can specify percent adjustments of
system-calculated values as follows:
Category
Equipment
Setting
Piping
Civil
Steel
Instrumentation
Electrical
Insulation
Paint
189
Note: Clicking the demolition (DEML) option causes the following changes
to the component:
Man-hours and labor costs are charged to demolition COAs (for example,
109, 309, 409, and so on)
For example, if you know unsetting the component is 15% easier than initially
setting it, then enter 85% in the Setting labor adjustment field.
4
Save your changes in either of two ways, depending on what you intend
to do next:
o
190
Matl/Man-hours Additions
Using Matl/Man-hours Additions, you can add lump sum material costs and/or
man-hours to a specified COA. All additions are reported as is. Additions are
neither indexed nor adjusted by Matl/Man-hours Adjustments. Up to 20
additions can be defined per component.
Pressure
Temperature
Stress relief
Insulation type
Paint treatment
The component starts with piping depicted in the Piping and Instrumentation
Drawings manual. You can also display the components piping and
instrumentation drawing by clicking the P&ID button on the Component
Specifications form.
It displays the piping you are adjusting on the Pipe Details Installation
Bulk form.
191
You can revise the pipe volumetric model for a component line-by-line.
Specifications on the Pipe Item Details Installation Bulk form override the
project-, area- and component-level specifications that otherwise determine
the design of all lines of pipe. For example, area dimensions determine all
lengths of lines generated by volumetric models except those lines for which
you enter a specific length.
192
Click Add.
Duct
Duct installation bulk items specify individual runs of process ductwork and
associated fittings and insulation. Up to 5 duct lines may be specified for each
component. Use the same methods described for multiple lines of pipe.
193
Civil
Civil installation bulk items specify bulk excavation and up to three different
foundation types/sizes. The available foundation types are listed in the Icarus
Reference.
From the specified foundation types and volumes, Aspen Process Economic
Analyzer calculates:
Rebar
Grout
Anchor bolts/embedments
Steel
The Steel installation bulk specifies the following:
Ladders
Stairs
Platforms
Instrumentation
Instrument installation bulk items specify individual instrumentation loops or
parts of loops with associated sensors, transmitters and signal cabling. Up to
50 loops may be defined for each component.
Note: To reduce the time required to retrieve data when multiple instrument
items have been added, select in Preferences to not display all items. If
Display P&I Installation Items is unmarked on the Preferences General tab
view, selecting Instrumentation will display a dialog box from which you can
select the item you wish to edit or select to add a new item. See page 47 for
instructions on accessing and entering Preferences.
X476H
194
This option should rarely be used, It is a rapid way to discard the complete
instrument model for this item. The system now generates instrumentation
for those loops that you subsequently define. To define new loops, you
continue to use this blank option for each successive loop. Once you have
used this option, the other options below cannot be used because the model
is already discarded.
This option is used to add a new loop to a component. The number of the new
loop must be higher than any other automatically created or user-defined
loop. It is not necessary to add loop numbers in numeric order; however,
they will be generated and reported in numeric order. For example, if a
component generates loops 1 to 6, then an added loop may have the number
7 to 50.
This option deletes a single loop, including sensor, transmitter, cable, control
center connections and final control element.
195
option to redefine the loop, then use the + option. Whether you are
appending a sensor or control element, you should make entries for both the
sensor and control valve locations.
To define more than one adjustment, use the same methods described earlier
for Pipe Item Details (page 193).
X47H
196
Notes:
(A)
Junction boxes can be found under PLANT BULKS, INSTRUMENTATION,
JUNC-BOX.
(B)
Multi-core runs can be found under PLANT BULKS,
INSTRUMENTATION, ELECTRONIC SIGNAL WIRE. You can specify it with or
without the junction box.
(C)
Control centers can be found under PLANT BULKS,
INSTRUMENTATION, MULTIFUNCTION CONTROLLERS (electronic) or PLANT
BULKS, INSTRUMENTATION, INSTRUMENT PANEL ANALOG (pneumatic).
Electrical
The Electrical installation bulk specifies local equipment lighting, control
wiring and power/cable and motor starters for up to three different types of
electrical loads.
Insulation
The Insulation installation bulk specifies insulation and fireproofing for
component and installation bulk steel. For components, the insulation type,
jacket type, thickness and area may be specified. For component and steel
fireproofing, type, rating and area may be specified.
197
Paint
The Paint installation bulk specifies surface preparation and painting of
component and installation bulk steel. Paint for pipe is specified under piping.
Entry field specifications include:
Right-click on the area in Project Explorers Project view and then click
Modify on the pop-up menu.
Aspen Capital Cost Estimator displays the Area Specifications dialog box.
198
Select
To do this
Area Specs
Area Modules
199
On the menu that appears, select the specification category you want to
define/modify.
Select
To do this
Area Specs
Area Modules
Click OK.
200
Have Project Explorers Project view open, since you will drag the
component or area there.
Note: You can only display the areas and components of a scenario that has
the same units of measure as the current scenario. If units of measure are
different, a message will appear in the Status bar notifying you of this when
you double-click on the scenario.
To import a component:
Drag the component to the desired area in Project Explorer, Project view.
Aspen Process Economic Analyzer adds the area and its components.
Drag the area from the Palette to the desired area in Project Explorer.
Aspen Process Economic Analyzer adds the components to the area without
creating a new area.
201
bulks and/or connected streams (see page 49). By default, installation bulks
are included and connected streams are not.
X479H
Have Project Explorers Project view open, since you will drag the scenario
there.
Drag the scenario from the Palette to Project Explorers Project view.
Click Yes.
Copying Components
The Copy command copies a selected component and all of its associated
installation bulks. This is useful if you want to add a component which is
similar to an existing item. The item can be copied and modified with less
effort than creating a new item.
Remember to change the Item Description when copying components to
distinguish the copy from the original.
Right-click on the component in either Project Explorer or the List view (at
area level, so that components are listed), and then click Copy on the
pop-up menu.
202
You can also copy multiple components at once: select the desired
components on the List view, right-click on one of the components, and
click Copy on the pop-up menu.
Right-click on the area to which you want to add the component(s) and
click Paste on the pop-up menu.
Modifying Components
You can modify the following components using Spreadsheet View:
Vessels
Towers
Heat Exchangers
Pumps
On the main menu bar, click View | Spreadsheet View | <the type of
component to modify>.
On the menu that appears, click the option you want to modify.
Click OK.
203
Copying Areas
Use Area Copy and Paste to create or modify an area specification that is
identical to an existing area.
Right-click on the project node where you want to copy the area.
In the dialog box that appears, type a name for the new area (for
example, area1).
The new area is added identical (except in name) to the area you copied.
Deleting Components
The Delete command removes a component and all associated installation
bulks from the project.
To delete a component:
1
Right-click the component in either Project Explorer or the List view; then
click Delete on the pop-up menu.
Note: You can select in Preferences not to have this prompt appear (see page
47).
X480H
You can also delete multiple components at one time: select the
components on the List view, right-click one of the components; then
click Delete on the pop-up menu.
Re-numbering Components
After deleting components, you may wish to re-number the remaining
components so that the numbering contains no gaps and reflects the order in
which components were added.
For example, if you add components A, B, C, D, and E in that order, the
automatically generated Order Numbers would be 1, 2, 3, 4, 5, respectively
204
(the Order Number appears on the List view). If you then delete components
B and C and re-number, components A, D, and E would have Order Numbers
1, 2, 3, respectively. The order in which they were created would still
determine the Order Numbers.
To re-number components:
On the Run menu, click Re-number and then click Project Components on
the sub-menu.
Deleting Areas
The Delete Area command removes the selected area and all of its
components.
To delete an area:
1
Note: You can select in Preferences not to have this prompt appear (see
page 47).
X481H
Re-Numbering Areas
Areas have reference numbers that are internally stored and then used by the
Evaluation Engine. They are not visible in the current version of Aspen
Process Economic Analyzer. Just as with components, re-numbering is
intended to close gaps in the numbering after deletion.
To re-number areas:
1
205
206
The User Custom Model dialog box appears. It displays the name of the
project, scenario, and project component selected for the operation. It also
displays available Microsoft Excel (.xls) template files.
Click the Excel template file that you have created for the selected project
component.
Click Run.
207
Input
Custom Rules
Output
The Input worksheet displays the original Icarus system values from Aspen
Process Economic Analyzer.
The Custom Rules worksheet is provided for storing any data that you may
wish to use in the output formulas.
208
Input specs have been placed on the Custom Rules along with sample
alterations for the following:
The values are in the same column-row position as on the Input worksheet,
so that you can easily reference the Input data when entering formulas.
You send the entries on the Output worksheet to Aspen Process Economic
Analyzer by clicking Apply or OK on the Custom Model tool.
209
Go to the Custom Model tool; then click OK to send the output to Aspen
Process Economic Analyzer and close the tool.
When you display the specifications form of the component, you will see the
values from the Output worksheet.
Creating a Template
To create a template for a component:
1
Starting on Row 6, Column B for item information, enter the slot names
for the specifications that you want to have sent from Aspen Process
Economic Analyzer when the file is run for a component.
Slot names for every equipment and plant bulk item are provided in Icarus
Technology Object Definitions (API.pdf). For example, to have the tool send
210
Shell Design Temperature to Excel when the file is run for Fixed Tube
Heat Exchangers, you would need to enter CPDesignTemperatureShell.
3
For connection stream information, enter slot names starting on Row 43,
Column B.
For material and man-hour adjustments, enter slot names starting on row
70, column B.
For the pipe-item details, enter slot names starting on row 101, column B.
After using the Custom Model tool for any number of components, you can
continue to experiment with different specifications and easily revert back to
the custom specifications by running the tool at the project level. Simply
right-click Main Project or Project Area in Project Explorers Project view;
then click Custom Model.
If more than one project component has been selected for the custom model
(for example, multi-selection, area selection, project selection), a message
box will appear asking you to specify the mode of operation.
If you click Yes, you will be able to specify a custom model template and all
of the selected project components will be processed with the one chosen
template.
If you click No, only project components with a link to a custom model
template will be processed with their associated template.
211
Note: the output will be based on the values in the Output workbook in
Excel. If the Output workbook contains formulas based on input, changes in
input since originally running the Custom Model will affect the output when
the Custom Model is re-run.
This re-runs all custom models stored in the Custom Model tool.
212
Overview
Note: To see the list of the Equipment and Slots of those Equipment which
will be affected by mapping when you do Map Based On Last Session, see
Appendix A. The slots listed on the table in Appendix A WILL CHANGE.
Right-click the component in Project Explorer and click Size Item on the
pop-up menu.
213
DHE FIXED-T-S
DHE FLOAT-HEAD
DHE U-TUBE
DRB KETTLE
DRB THERMOSIPH
DRB U-TUBE
Compressors
DCP CENTRIF
DCP GEN-SERV
DGC CENTRIF
DGC CENTRIF-IG
DGC RECIP-MOTR
EGC RECIP-GAS
DCP ANSI
DCP ANSI-PLAST
DCP API 610
DCP API 610-IL
DCP CANNED
DCP TURBINE
DCP PULP STOCK
DCP NAG DRIVE
Pumps
DCP ANSI
DCP ANSI-PLAST
DCP API 610
DCP API 610-IL
DCP CANNED
DCP TURBINE
DCP PULP STOCK
DCP NAG DRIVE
Vessels
DHT HORIZ-DRUM
DVT CYLINDER
DVT SPHERE
DVT SPHEROID
DVT STORAGE
214
486H
The Re-Size command will clear all the previous sizing results and then size
the equipment based on the current process conditions (those that you have
entered and those available from the currently loaded simulator file).
Therefore, if the component being re-sized is one of those for which
interactive sizing is available, the Interactive Sizing form that appears is
blank.
If you would like to keep some of your component specifications (i.e., not
have them replaced by those calculated by the Sizing Expert), do not use the
Re-size command. Instead, use the Size command or the Size button to
access the Interactive Sizing form with current specifications retained, rather
than cleared. Then, clear all fields except those you want to retain and click
OK to execute sizing. Aspen Process Economic Analyzer will re-calculate only
the blank fields.
215
216
In the Streams tree structure, click User. Leave the Basis as Absolute,
since you are creating a completely new process stream.
Click Create.
Click OK.
temperature
pressure
Example:
Click Apply.
Aspen Process Economic Analyzer fills in the rest of the fields in the Liquid
Information section.
217
Click OK to return to the Develop Streams dialog box, where you now
need to create an outlet stream.
10 In the tree structure, click User. Notice that the inlet stream that you just
created is now displayed under User.
11 Click that stream and, in the Basis group, click Relative. The new outlet
stream will be based upon the inlet stream.
12 On the Create Stream dialog box, enter a stream name, such as
Process-OUT.
218
13 Click OK.
The Develop Stream specifications form appears. Specifications that appear
gray are the same as those of the base stream. Any modifications made will
appear black.
219
Add an equipment item for which interactive sizing is available and display
the Component Specifications form. If you are following the example, add
a floating head shell and tube exchanger. (See page 182 for instructions
on adding components.)
X487H
220
Any other data you provide (for example,, Duty, Overall heat transfer
coefficient, LMTD, and so on) helps the Expert do its job better, but is not
necessary.
221
-orIf you are cooling a fluid, select the stream carrying the fluid to be
cooled.
Utility Resources
If you specify a utility resource as a stream, the Sizing Expert will estimate
the actual utility rate required for the heat transfer and use this rate to create
utility streams as though they were user-specified. The utility stream names
are prefixed by ICU and are present under the Utility category in the
Develop Streams dialog box. These utility streams differ from utility resources
in that they have an actual flow rate whereas a resource is a reservoir that
can provide utility streams at any required flow rate.
Default Utility Resources Available for I-P Projects
Inlet
temperature
Exit
temperature
Operating
Pressure
(DEG F)
(DEG F)
(PSIA)
Steam @100PSI
327
327
100
Heat
source
Steam @165PSI
363
363
165
Heat
source
Steam @400PSI
444
444
400
Heat
source
600
550
25
Heat
source
675
25
Heat
source
-21
15.5
Heat sink
-150
15.5
Heat sink
Refrigerant Ethane
-130
-130
15.5
Heat sink
Refrigerant
Propylene
-50
-50
15.5
Heat sink
Refrigerant Propane
-40
-40
15.5
Heat sink
Cooling Water
95
75
50
Heat sink
Utility
type
Exit
temperature
Operating
Pressure
(DEG C)
(DEG C)
(KPA)
Steam @2760KPA
229.2
229.2
2760
Heat
source
Steam @1135KPA
184
184
1135
Heat
source
Utility
type
222
Exit
temperature
Operating
Pressure
(DEG C)
(DEG C)
(KPA)
Steam @690KPA
164
164
690
Heat
source
315
287
2523
Heat
source
357
2523
Heat
source
-29.8
105
Heat sink
-101
105
Heat sink
Refrigerant Ethane
-90
-90
105
Heat sink
Refrigerant
Propylene
-45
-45
105
Heat sink
Refrigerant Propane
-40
-40
105
Heat sink
Cooling Water
35
24
105
Heat sink
Utility
type
223
If you are heating a fluid, select again the utility to use as the heating
source.
-orIf you are cooling a fluid, select the stream carrying the cooled fluid from
the exchanger.
to access the
Click on the Cold Inlet Stream field and then click
drop-down list of utility resources and user-created streams.
If you are heating a fluid, select the stream carrying the fluid to be
heated.
A If you are following the example, select the Process-IN stream that you
created in the previous set of instructions (see Creating Streams, pages
216 through 219).
X48H
X489H
B If you are cooling a fluid, select a heat sink utility to use as a cooling
medium.
to access the
Click on the Cold Outlet Stream field and then click
drop-down list of utility resources and user-created streams.
If you are heating a fluid, select the stream carrying the heated fluid from the
exchanger.
If you are following the example, select the Process-OUT stream that
you created in the previous set of instructions (see Creating Streams, pages
216 through 219).
X490H
X491H
If you are cooling a fluid, select again the heat sink utility to use as the
cooling medium.
Click Apply. Aspen Process Economic Analyzer fills in the other fields on the
Interactive Sizing form.
224
Note: results are not transferred to the Component Specifications form until
you click OK and the sizing is successfully completed (i.e., without generating
error messages).
10 Click OK.
Aspen Process Economic Analyzer provides a message informing you of the
overdesign factor.
225
12 Click OK to save.
You can now run an item evaluation and see the values generated by the
Sizing Expert in the item report.
226
To view or edit the sizing selection, click on the equipment model. All
equipment models default to System Sizing (see figure 2).
227
To add or remove a custom model to the sizing selection list, click New
Sizing; then click your choice on the list of available custom models (see
Figure 3).
The current sizing list for the equipment model is order dependent (see figure
4).
Figure 4: Current Sizing List with System sizing and two custom models
Once this library has been specified, it must be selected in the project (see
figure 5).
228
Sizing Areas
The Area sizing feature in Aspen Process Economic Analyzer develops length
and width of an area from the equipment in the area. When actual area
dimensions are not available, you can get a better estimate of area length
and width from the system when these parameters are not specified in the
area specs form.
The system calculated area length and width is used in the design of all area
bulks. You can use the system calculated area parameters as the area specs.
Modify an area spec by right-clicking the area; then, on the menu that
appears, clicking Modify.
Click Specification | Area Specs; then, on the menu that appears, click
Modify.
In the report, the system-calculated length and width for each area appear in:
Modify an area spec by right-clicking the area; then, on the menu that
appears, clicking Modify.
Click Specification | Area Specs; then, on the menu that appears, click
Modify.
Click Area Piping; then enter data for the piping envelope.
In the report, the system-calculated length and width for each area appear in:
229
Modify an area spec by right-clicking the area; then, on the menu that
appears, clicking Modify.
Click Specification | Area Piping; then, on the menu that appears, click
Modify.
Clear the data in the Utility length parameter (0) and Utility stations
(-) fields.
Click OK.
Click Area Steel; then, on the menu that appears, click Modify.
Clear the data in the Pipe rack length (0) field; then click OK.
Some areas generate utility headers, utility stations. and pipe rack bulks. This
information appears in:
Sizing Requirements,
Calculations, and Defaults
Certain types of components have minimum input requirements for sizing.
Those requirements are provided in the following sections, along with
explanations of how the sizing is calculated for different component types.
Air Coolers
Minimum Input Requirements
Inlet Stream
Exit Stream
Sizing Procedure
The air cooler thermal and detailed mechanical design equations are given
below:
U*A*MTD
MTD
f*LMTD
pi*D_tube*N_tubeRows*N_tubesPerRow* Tube_length
230
where:
Q
Heat Duty
MTD
LMTD
N_bays
Number of bays
N_tube_rows
N_tubesPerRow
Tube_length
Length of tubes
231
(tube length/bay width). For any aspect ratio of up to 1.5, only one fan is
selected.
Defaults
Tube pitch
2.5 INCHES
Tube thickness
0.125 INCHES
Bay width
4 ft to 20 ft
Tube rows
3 to 6
Maximum Tube
length
3*Bay width
Agitated Tanks
Minimum Input Requirements
Inlet stream
Exit stream
Sizing Procedure
The capacity of the agitated tank is determined by the following equation:
C
Q * (T_r / 60.0)
where:
C
Capacity , CF
T_r
The diameter of the agitated tank is determined using L/D and geometry:
C
(/4) * D^2 * L
where:
D
L + h_d
where:
232
h_d
1 FEET
=
=
=
ANCHOR
STD
T6FB
Operating pressure is obtained from the simulator report. If the report does
not have a value, then the pressure of the inlet stream having the maximum
value is chosen as the operating pressure.
The operating pressure is used to obtain the L/D ratio (if user specification is
absent).
where:
P
Pressure, PSI
The project component must have at least one process stream connected to
the inlet and exit. Also, since the sizing procedure is based on the liquid
holding period, at least one of the streams should have liquid phase.
The design pressure and temperature are based on the operating pressure
and temperature as modified by your entries on the Design Criteria
specifications form.
Compressors
Minimum Input Requirements
233
Sizing Procedure
The capacity requirement for the compressor is calculated from the inlet
stream information. The inlet stream flow rate and density are used to
estimate the total volumetric flow rate through the compressor.
The compression ratio (exit to inlet pressure) is obtained from the operating
pressures of the inlet and exit stream.
The compressibility factor (inlet and exit) is based on user-specified
information, if available, or estimated by the sizing expert based on the
Primary Fluid Component.
The Icarus Evaluation Engine estimates the driver power if it is neither userspecified nor provided in the simulator report. The engine currently uses a
mechanical efficiency of 100% to arrive at the brake horsepower. The brake
horsepower, thus calculated, is compared against a table of available
standard motor sizes. If the calculated brake horsepower is not found in the
table, then the motor with the next higher horsepower is selected.
If the driver horsepower is either user-specified or provided in the simulator
report, the engine uses this value. However for pricing the compressor, the
table of available standard motor sizes is referred. If the specified horsepower
is not found in the table, then the price of the motor with the next higher
horsepower is used.
In the case of simulator inputs, different simulators provide information that
may be slightly different. For instance, in the case of AspenPlus, the
compressor calculations take into account any mechanical efficiency specified
during the simulation run. So the brake horsepower reported in the case of
AspenPlus already takes into account the mechanical efficiency. However,
other simulators, such as SimSci (Actual Work); HYSIM and HYSYS (Energy
Required), and ChemCAD ( Actual Power); do not account for mechanical
efficiency. Keep this in mind and be aware of what has been accounted for in
the simulation side when using simulator information as inputs.
Defaults
Minimum inlet pressure for air compressors is 14.696 PSIA
Crushers
Minimum Input Requirement
Sizing Procedure
The sizing expert estimates the solid flow rate from the inlet stream
information. The crushing ratio (feed to product size) is set at 4.
Work index is the total energy in KWH/TONS, needed to reduce the feed to a
size so that 80% of the product will pass through a 100 micron screen. The
234
where:
P
Driver power, HP
T_m
W_i
d_p
d_r
Defaults
Crystallizers
Minimum Information Required
Inlet and Exit Stream information
Additional Information
Final Product size
Sizing Procedure
The sizing program calculates the crystallizer capacity based on the inlet and
exit stream information.
Default value of 0.83 MM is used as final product size if the user-specified
value is not available from the simulator report.
In addition, the following defaults values are used for the design parameters:
Growth
rate
0.36 MM/H
= d_p / (3 * R_g
where:
235
d_p
Product size, MM
R_g
Based on the minimum and maximum values for the required fields in the
component specification form, the number of additional crystallizers are
estimated.
Dryers
Minimum Input Requirement
Inlet and Exit stream information
Sizing Procedure
The sizing program calculates the dryer capacity based on the total
evaporation rate for the drying process. For tray and drum dryers, an average
depth of 2.25 FEET is used to determine the total dryer requirements. For
vacuum and jacketed rotary vacuum dryers, the dryer capacity is determined
by obtaining value of the drying time and the average percentage utilization
of the dryer capacity.
The system defaults are as follows:
Drying
time
0.75 HOUR
Average
percentage
utilization
25
The number of additional items required for the given drying operation is
determined from the knowledge-based engine in Aspen Process Economic
Analyzer, which analyzes minimum and maximum values for the required
fields in the specification form.
Dust Collectors
Minimum Input Requirement
Inlet and Exit stream information
Sizing Procedure
The sizing program estimates the vapor volume flowing through the dust
collector using the exit stream information available from the simulator
report.
In case of cyclones, the sizing program assumes a default linear velocity of
150 FPS. The height to width ratio is fixed at 2.5.
236
Using the above defaults, the volumetric rate through the separator is
obtained using Zenz correlation represented by the following equation:
Q
2.5 (D ^ 2) V / 16
where:
Q
In case of baghouse dust collectors, the sizing program uses Nylon as the
default filter cloth material to determine the air to media ratio which then
determines the diameter of the separator.
Air to media ratio is the flow rate of air (at 70 DEG F) in CFM. The default
ratio results in a pressure drop of 0.5 INCHES of water when passed through
1 SF of clean fabric.
The sizing program uses a default air to media ratio of 10 CFM.
The minimum and maximum values of the required field(s) shown in the
component specification form are used to determine the number of identical
equipment items.
Filters
Minimum Input Requirement
Inlet stream
Exit stream
Sizing Procedure
The sizing program calculates the total amount of filtration product rate based
on the exit stream information. Based on the type of filter selected, the
average dimension of the filter equipment is selected and the filter size is
then optimized for the given operation such that the dimensions selected for
the equipment are within the minimum and maximum values as specified by
the knowledge-based engine.
In case of batch filtration, a default batch time of 0.25 HOUR is used. In case
of plate and frame filters, default value of cake thickness of 0.3 FEET is used.
In the case of continuous operation, the cycle time default is 0.08 HOUR.
Based on the actual capacity requirement and the maximum and minimum
sizes provided by the knowledge-based engine, the number of identical items
is determined.
237
Heat Exchangers
The heat exchanger sizing program estimates the heat transfer area required
for the given operating conditions. The model also performs detail estimation
of the number of tubes, tube length, and other internal components of the
heat exchanger based on either user-defined specifications (from the process
simulator report or the Design Criteria specifications form) or system defaults.
Sizing Procedure
The process stream(s) are classified into various categories. The Primary Fluid
Component class that you specify for the process fluid(s) flowing through the
heat exchanger is used to estimate the following design parameters:
Fouling resistance
Duty requirement for the heat exchanger is either directly obtained from the
simulator report or estimated based on the inlet and exit process stream
information for the process model. In case the fluid undergoes phase change,
a boiling point temperature, Tb, is estimated that would lie between the inlet
and exit stream temperature. The estimated Tb is then used in the calculation
of the sensible and latent heats based on the Primary Fluid Component. The
sensible heat of any solids present in the stream is also accounted for in the
duty calculation.
In estimating the design pressure on shell and tube heat exchangers, the
2/3rd Rule is applied if it has been selected on the Design Criteria
specifications form (see page 86).
P
X492H
If only the process fluid conditions are specified by the simulator model, the
heat exchanger sizing program determines the appropriate utility from the list
of utilities that you specify using the Utility Specifications accessed from
Project Basis view (see page 98). If multiple utilities are available for heat
transfer, then the sizing expert uses the utility fluid with a temperature
approach closest to the process fluid. This minimizes the heat transfer losses.
However, a minimum of 1 degree Fahrenheit difference in the final
temperature of the process fluid and the utility fluid must exist for the utility
fluid to be selected for the process. If an appropriate utility fluid is not
available for the heat transfer process, the heat exchanger sizing program will
terminate without estimating the heat exchanger size requirements.
X493H
238
General Information
The utility requirement is estimated only when the system determines the
utility fluid. If both shell and tube side fluid stream information is specified in
the simulator report, then the system assumes that both of the fluid streams
are process streams and that no utility fluid is expended.
239
Presently, the model defaults are used for determining the material of
construction.
For shell and tube heat exchangers, if the heat transfer surface area
calculated by the sizing program is greater than the largest heat exchanger
designed by the design and cost engine, then the heat exchanger is divided
into multiple shells with identical configurations. The capital cost estimation is
then calculated based on the complete heat exchanger.
Note: When mapping a rigorous heat exchanger model (HXRIG) from
SimSci, the number of shells in parallel is used to determine the number of
shells in Aspen Process Economic Analyzer. For Aspen Process Economic
Analyzer, the maximum number of shells in series is 1.
Pumps
Minimum Input Requirements
Inlet and Exit stream information
Sizing Procedure
The sizing program calculates the total capacity requirements for the selected
pump based on the total flow rate of the inlet fluid stream(s) obtained from
the simulator.
240
Flow Rate/Capacity
Pump flow rate is obtained from the simulator information. If the information
does not exist, then pump flow rate is calculated based on the stream flow
rates. The stream is assumed to be completely liquid phase and no check is
made for presence of vapor phase.
The pump flow rate obtained from the simulator information is multiplied by
the pump overdesign factor, also referred as the capacity over-design factor,
present in the Design Criteria specifications file.
Pump % Efficiency
Pump efficiency is directly obtained from the simulator. If the value is not
present in the simulator report, then the default value of 70% is used.
Pump Overdesign
You can modify the pump overdesign factor either on the Design Criteria
specifications form or the Interactive Sizing form. Modifying the overdesign
factor using the Design Criteria specifications form (page 86) will applies the
new factor to all the pumps in the project. Modifying the overdesign factor for
a pump using the Interactive Sizing form (page 219) applies the factor only to
that particular pump. This allows you to either specify the factor for all pumps
or specify the factor individually for each pump.
X49H
X495H
Driver Power
If you specify a driver power in the component specification form then this
value is used. If the user does not provide the value then it is calculated by
the cost engine. The Icarus Evaluation Engine calculates the hydraulic
horsepower based on the capacity, viscosity and head, and then uses the
pump efficiency to estimate the brake horsepower. The brake horsepower is
compared against a set of standard available motor sizes to estimate the
pump driver power.
If multiple inlet streams are present, the minimum value of pressure is used
for determining the operating pressure of the equipment.
h_d h_s
241
FEET
where:
H
h_d
=
=
h_s
Assumptions:
Velocity heads are not included in estimating the suction and discharge
heads.
The specific gravity of the fluid is based on inlet streams conditions. The
discharge pressure for the pump is based on the maximum value for the exit
stream(s). The suction pressure is based on the minimum value for the inlet
streams(s).
Screens
Minimum Input Requirement
Sizing Procedure
The sizing program determines the capacity of the screen based on the inlet
flow rate estimated from the stream information.
The screen opening size is used to determine the final product size.
The feed material for the vibrating screen is obtained from the Design Criteria
specifications. The following choices are available:
Limestone/Crushed Stones
Coal
Cinders
Coke
Wood
The material type affects the screen unit capacity which is defined as the
amount of solid (in tons per hour) flowing through one square foot of screen
242
Towers
Minimum Input Requirements
Number of stages
Inlet stream
Exit stream
Sizing Procedure
The distillation column sizing module can be used to size the following Icarus
process equipment:
DDT TRAYED
DDT PACKED
TW TRAYED
TW PACKED
DC HE TW
Models used
AspenPlus
HYSIM/HYSYS
COLUMN
Pro/II
243
Sidestrippers
Sidestrippers attached to tower models are separated from the main tower
model during the loading process. Sidestrippers load information from the
same tables in the report from which the main tower information is discerned.
For example, the typical information loaded for sidestrippers in Pro/II are:
SIDESTRIPPER ABC
COLUMN SUMMARY
TRAY
TEMP PRESSURE
DEG C KPA
1/ 10 200.3 600.50
2/ 11 202.2 601.53
22.
7.8
20.0L
5.0V
8.5V
20.1L
SIDESTRIPPER ABC
TYPE
STREAM
PHASE
FROM
TRAY
FEED ABCDRW
LIQUID
FEED ABCSTM
VAPOR
PROD ABCSRVP VAPOR
10
PROD ABCPRD
LIQUID
11
TO
TRAY
10
11
LIQUID
FRAC
1.0000
.0000
FLOW RATES
KG-MOL/HR
23.00
5.55
8.46
20.09
HEAT RATES
M*KJ/HR
1.3216
.2785
.5325
1.0678
Information is obtained for the sidestrippers in the same manner as for the
main tower unit (Refer to information for obtaining process data for main
tower unit).
Pumparounds
The inlet and outlet fluid conditions for pumparounds are obtained from the
stage information to which the unit is connected. Additionally, the duty
associated with each pumparound is loaded into the unit. This unit is then
separated during the loading process and is treated as an independent
simulator model which can be mapped and sized on its own.
For example, the information required by pumparound units in PRO/II are
obtained from the following part of the column report:
COLUMN SUMMARY
NET FLOW
TRAY TEMP
DEG F
.
.
.
40R
355.9
RATES
PRESSURE
LIQUID
PSIG
33.00
5618.9
HEATER
VAPOR
FEED PRODUCT
LB-MOL/HR
4301.4L
DUTIES
MM BTU/HR
94.6551
PUMPAROUNDS
TRAY
TEMP,
FROM TO FROM
40
40 355.9
416.1
1.0000
.4108 7273.09 995.238 3569.48
244
Main tower
Overhead condenser
Condenser accumulator
Overhead split
Reflux pump
Overhead pump
Reboiler
Bottoms split
Both overhead and bottoms split are process stream splitters and therefore
do not represent any project component. In Aspen Process Economic
Analyzer, during mapping and sizing process, they are typically mapped as a
quoted cost item with zero cost.
In addition, the equipment design could involve splitting the units into more
than one actual piece for reasons of economy. For example, in many
applications, condensers are split into a precooler (which is typically an air
cooler but also can be any other type of heat exchanger) and a trim cooler
(typically a shell and tube heat exchanger).
Tower models (such as RADFRAC model in AspenPlus, COLUMN UNIT in
PRO/II and COLUMN in HYSIM/HYSYS) can be mapped into any of the
following ten Aspen Process Economic Analyzer configurations:
Tower
Condenser
Condenser accumulator
Overhead split
Reflux pump
Bottoms split
Reboiler.
Full - Single
o
Tower
Condenser
Condenser accumulator
Overhead split
Reflux pump
Overhead pump
245
Bottoms split
Reboiler
Tower
Precooler
Trimcooler
Condenser accumulator
Overhead split
Reflux pump
Bottoms split
Reboiler
Full - Split
o
Tower
Precooler
Trimcoooler
Condenser accumulator
Overhead split
Reflux pump
Overhead pump
Bottoms split
Reboiler
Tower
Condenser
Condenser accumulator
Overhead split
Reflux pump
Bottoms split
Reboiler
Circulation pump
Tower
Condenser
Condenser accumulator
Overhead split
Reflux pump
246
Overhead pump
Bottoms split
Reboiler
Circulation pump
Tower
Precooler
Trimcooler
Condenser accumulator
Overhead split
Reflux pump
Bottoms split
Reboiler
Circulation pump
Tower
Precooler
Trimcoooler
Condenser accumulator
Overhead split
Reflux pump
Overhead pump
Bottoms split
Reboiler
Circulation pump
247
1
2
3
4
5
6
7
8
9
10
TEMP.
F
PRESSURE
PSI
149.27
223.45
227.79
230.39
232.06
233.25
234.18
234.98
235.72
236.74
20.000
22.000
22.100
22.200
22.300
22.400
22.500
22.600
22.700
22.800
BTU/LBMOL
LIQUID
VAPOR
-0.12156E+06
-0.11895E+06
-0.11909E+06
-0.11918E+06
-0.11925E+06
-0.11931E+06
-0.11935E+06
-0.11939E+06
-0.11942E+06
-0.11941E+06
HEAT DUTY
BTU/HR
-42602.
-.23509+08
-87138.
-92519.
-95701.
-97662.
-98970.
-99924.
-0.10068E+06
-0.10135E+06
-0.10196E+06 45802+08
Table 2:
Stage molar liquid flowrates and Stage molar vapor flowrates
are loaded. (Column 1 and 2)
STAGE
FLOW RATE
FEED RATE
PRODUCT RATE
LBMOL/HR
LBMOL/HR
LBMOL/HR
LIQUID
VAPOR LIQUID VAPOR MIXED
LIQUID VAPOR
1
2
3
4
5
6
7
8
9
10
1239.
0.2571E+05
0.2586E+05
0.2595E+05
0.2602E+05
0.2606E+05
0.2610E+05
0.2614E+05
0.2617E+05
0.2357E+05
430.0
.57657-01
1669. .24001+05
2140.
2286.
2380.
2444.
2493.
2532.
2568.
2604.
430.0000
.23571+05
Inlet and exit streams (and their stage numbers) are loaded in the mapping
step.
For example, in the case of a RADFRAC model for AspenPlus, the following
portion of the report is loaded in Aspen Process Economic Analyzer:
INLETS7
OUTLETS - 8
9
STAGE
2
STAGE
1
STAGE
10
When sizing information is present in the report, the mapping program loads
all the relevant information present in the sizing sections.
248
For example, in the case of a RADFRAC model for AspenPlus, the following
portion of the sizing report is loaded in Aspen Process Economic Analyzer for
every section:
Case : Tray tower sizing section
STARTING STAGE NUMBER
ENDING STAGE NUMBER
TRAY SPECIFICATIONS
TRAY TYPE
TRAY SPACING
2
29
METER
SIEVE
0.60960
METER
4.00228
2
9
SPECIFICATIONS
TYPE
HEIGHT
FT
FT
BERL-SADDLE
2.00000
16.0000
Operating Temperature
The maximum temperature value for all the stages (given by column 1) is
used as the operating temperature for the tower.
Operating Pressure
The maximum pressure value for all the stages (given by column 2) is
used as the operating pressure for the tower.
Design Pressure
The maximum value from the stage pressure profile is used for calculating
the design pressure of the tower (that is, after applying the user-defineddesign value from the design criteria file). When stage pressures are not
available, the maximum value of pressure from all the inlet streams is
used.
Design Temperature
The maximum value from the stage temperature profile is used for
calculating the design temperature of the tower (that is, after applying the
user-defined design value from the design criteria file). When stage
temperatures are not available, the maximum value of temperature from
all the inlet streams is used.
Number of Stages
249
For example, in the case of RADFRAC model for AspenPlus, consider the
following table:
STAGE
1
2
3
4
5
6
7
8
9
10
TEMP.
F
PRESSURE
PSI
BTU/LBMOL
LIQUID
VAPOR
HEAT DUTY
BTU/HR
149.27
20.000
-0.12156E+06
-42602.
-.23509+08
223.45
22.000
-0.11895E+06
-87138.
227.79
22.100
-0.11909E+06
-92519.
230.39
22.200
-0.11918E+06
-95701.
232.06
22.300
-0.11925E+06
-97662.
233.25
22.400
-0.11931E+06
-98970.
234.18
22.500
-0.11935E+06
-99924.
234.98
22.600
-0.11939E+06
-0.10068E+06
235.72
22.700
-0.11942E+06
-0.10135E+06
236.74
22.800
-0.11941E+06
-0.10196E+06 .45802+08
Liquid Density
Density of liquid flowing inside the column is estimated from the density of
the inlet streams and the exit streams. If liquid density cannot be obtained
from the streams, the density of water is used as default.
Vapor Density
Density of vapor flowing inside the column is estimated from the density
of the inlet streams and the exit streams. If vapor density cannot be
obtained from the streams, the vapor density is estimated based on gas
law. The vapor density is estimated at the minimum operating pressure
and operating temperature.
Sizing Procedure
The sizing procedure varies depending on the type of internals desired and
the simulator model used for the operation. The procedure described below
gives a description of the actual steps used by the sizing module to estimate
the sizes for the different types of trayed and packed towers.
250
The type (class) of the fluid in the column is used to estimate some of the
properties in designing the tray internals, such as surface tension,
foaming tendency, deration factor if they are not specified in the
simulation output report or on the Design Criteria specifications form.
You can specify the overall column tray efficiency in the Tray Efficiency box
on the Design Criteria specifications form. If the value is not provided,
then it is estimated using Locketts modification of the OConnell
Correlation. This correlation is based on tests on actual plant columns and
has been the standard of the industry.
The tray efficiency is used to calculate the actual number of stages required
for the separation.
EOC
0.492 ( L )
-0.245
where:
EOC
A default value of 1.5 is used for the relative volatility of key components that
you can modify on the Design Criteria specifications form. The liquid viscosity
is either directly obtained from the report or estimated from the fluid
classification.
Once the internal height of the column is estimated (based on the actual
number of trays), additional height for vapor disengagement and liquid
return is based on your Design Criteria specifications.
251
Section 1:
Diameter
5 FEET
Tray Spacing
24 INCHES
Stages
2 to 4
Diameter
6 FEET
Tray Spacing
30 INCHES
Stages
5 to 7
8 FEET
Section 2:
Section 3:
Diameter
Tray Spacing
18 INCHES
Stages
8 to 10
The sizing program will design a double diameter tower with the following
dimensions:
Top Section
Diameter
6 FEET
30 INCHES
=
=
2 to 7
Bottom Section
Tray Spacing
18 INCHES
Bottom Section
Stages
8 to 10
Bottom Section
Diameter
8 FEET
The program estimates the cross sectional area for each stage. Then, the
maximum value is used to design the single diameter tower. In case of double
diameter tower, the program estimates the diameter for the bottom section
and the top section based on the cross sectional area estimated for each
stage.
252
Bibliography
Distillation Design, by Henry Z. Kister.
Applied Process Design For Chemical And Petrochemical Plant, Volumes 1
and 3, by Ernest E. Ludvig.
Standard Handbook of Engineering Calculations, by Tyler G. Hicks
Chemical Engineers HandBook, by Perry and Chilton, 6th Edition.
D = 0.0956 Wv / K L v
12
253
where:
D
Diameter, FEET
Wv
L
v
18
3.4
24
4.2
30
4.7
30+
5.0
.155 (Fp0.7)
where:
FL
Fp
Note: You can provide the value for the packing factor on the Design Criteria
specifications form. The system defaults are used for each of the different
types of packings if you do not enter a value.
Once this pressure drop is known, the flood velocity is calculated using the
latest version of GPDC (Generalized Pressure Drop Correlation) charts for
both random and structured packings.
HETP Prediction
You can provide the HETP value on the Design Criteria specifications form. If
the value is not specified, rules of thumb prediction reported in literature are
used to predict the packed tower efficiency.
For random packing columns, the following rules are used for estimating HETP
(FEET):
HETP
dp
1.5 dp
For estimating the structured packing efficiency, the following rule of thumb is
used:
HETP,
INCHES
1200 /ap + 4
254
ap
System Defaults
The following system default values may be modified on the Design Criteria
specifications form and Component Specifications form:
Sieve
Tray Spacing
24 inches
Flooding Factor
80 %
Foaming Tendency
Moderate
Random
Packing Material
1.0PPR
0.75 SF/CF
Top vapor
disengagement
height
4 FEET
6 FEET
General Defaults
Vessels
Horizontal Vessels
The following graphic shows a typical horizontal vessel.
255
Residence Time
Separation Factor
Design Requirements
The maximum number of exit streams is three; two of the streams can be
liquid.
Calculating Diameter
Vessel diameter is based on the maximum allowable vapor velocity inside the
separator, to reduce the liquid entrainment in the vapor.
The following two methods are available in Aspen Process Economic Analyzer
(chosen from the Design Criteria specifications) to obtain vapor velocity.
256
ln (SF)
k_v
k_v * k_vm
v_m
where:
l_mfr
v_mfr
l_rho
v_rho
Vapor Density
System Factor
SF
Separation Factor
k_v
Polynomial Function of SF
k_vm
-1.877478097
-0.8145804597
-0.1870744085
-0.0145228667
-0.0010148518
The above relation for Separation Factor is valid for a W(SF) between 0.006
and 5.0. If W falls outside the range, the sizing program gives a warning
message and the limiting value of W is used to estimate Separation Factor.
For example, if calculated value of W is 0.001, then the value used in the
correlation is 0.006. If the calculated value of W is 10.0, then the value used
in the correlation is 6.0.
257
For estimating vapor velocity, the liquid bubbles are assumed to remain in
spherical shape.
The terminal settling velocity can be obtained for different flow conditions.
For laminar flow (K < 3):
v
disengagement velocity
where:
gravitational constan
rho_l
liquid density
rho_v
vapor density
dp
mu_v
v*f
v_m
disengagement velocity
disengagement
where:
v_vol/v_m
t_csa
v_csa/r_vc
v_csa
Vapor area
v_vol
r_vc
t_csa
where:
258
D_v
sqrt ((t_csa * 4) /)
where:
D_v
Calculating Length
Vessel liquid holdup volume is obtained based on the light liquid flowrate and
the residence time. The vessel length is then calculated as given below:
l_vol
l_vfr * r_t
where:
l_vol
L
Length
l_vfr
=
=
=
r_t
r_vc
Residence time
r_vc
<
If
P <=
250
PSIA,
P <=
500
500
then L/D=
P>
then L/D=
PSIA,
3
4
5
After estimating the length (L) and diameter (D) of the vessel, the ratio of
L/D is compared with the Process Vessel Height to Diameter Ratio specified on
the Design Criteria specifications form.
hl_vfr * r_t
bt_vol / hl_vel
259
=
=
where:
hl_vfr
hl_vel
boot length
boot diameter
Vertical Vessels
The following graphic shows a typical vertical vessel.
Residence Time
260
Separation Factor
l_vfr * r_t
l_ht
(l_vol * 4) / ( * D^2)
where:
l_vol
l_vfr
=
=
r_t
residence time
l_ht
LLLTap_ht
=
=
ddHLLTap_ht
d_ht
=
=
=
disengagement height
me_ht
mea_ht
If the calculated l_ht is less than the minimum height between the taps,
specified in the design criteria, then the minimum height is used.
261
262
Interconnecting Volumetric
P&ID Lines
Connect pipelines between components in a Aspen Capital Cost Estimator
project, estimate the project, and create piping line list report for connected
lines with the same line tag.
263
The GUI displays five lists. All equipment and its associated pipelines in the
project are displayed in two groups:
Connect From
Connect To
The first two lists display equipment and piping lines in the Connect From
group.
The third list displays all connected lines.
The fourth and fifth lists display piping lines and equipment in the Connect
To group.
264
On the list in the Connect From and Connect To groups, click the
desired equipment item.
The line lists will then display only the lines corresponding to the selected
equipments. When the mouse hovers over an equipment or a line, the tooltip
in the list provides additional information related to this item. The related
additional information is also displayed in the bottom text area when clicking
on an equipment or a line.
Select the Auto Generate Line Tag check box, or, in the Line Tag field,
type a unique line tag.
Click Connect.
265
Repeat Steps 1-4 above to connect all the desired lines between the
equipment items.
All connected lines will be removed from middle list and will be displayed in
the respective line list.
266
267
All connections on the GUI are saved, but the project is not updated.
as shown below:
268
On the main menu, click Run | Map Stream to Lines to launch the GUI.
269
The GUI displays four lists. All the streams are displayed in the STREAM list
box. All equipments and their associated pipelines in the project are displayed
in the last two list boxes. The middle list displays all mapped streams and
lines.
The line list will then display only the lines corresponding to the selected
equipment. When the mouse hovers over an equipment or a line or a stream,
the tooltip in the list provides additional information related to this item. The
related additional information is also displayed in the bottom text area when
clicking on an equipment item, a line, or a stream.
270
On the Aspen Capital Cost Estimator | Line list, click a piping line.
Click Map.
Repeat steps 1-3 above to map all the desired streams and lines.
Note: Use Filter to display all unmapped equipment and all unmapped lines
if needed.
271
Click Un-Map.
The selected items are removed from the middle list and go back to their
respective lists.
272
On the Map Stream to Lines dialog box, click Auto Map to automatically
map streams to lines.
273
274
275
276
For one-of-a-kind cost items not worth storing in a library, the unit cost
library may be used to create a dummy item for recall and modification in a
project. The dummy item is stored in the library with as little data as possible.
This can be retrieved and modified in as much detail as required whenever
you need a one-time cost added into a project.
To create an EML:
1
277
Enter a file name (required) for the EML and a brief description (optional),
then click OK.
278
Right-click on the library to which you want to add an item, and then click
Modify on the pop-up menu.
Enter a Reference ID for the item in the Add Item dialog box.
The one- to six-character alphanumeric Reference ID uniquely identifies
the library item being added. The ID is used to sort and search for library
items. The first character must be a letter.
Click OK.
Enter the descriptive data for a the item in the Develop Equipment Model
Library form. If following the example, enter the data exactly as shown
below. Be sure to correctly enter the sizing parameters, CAPFLOW and
PWRDRVR; Aspen Process Economic Analyzer knows to use GPM (or L/S
for METRIC) and HP, respectively, for these parameters.
279
The new item appears on the Library dialog box, which you can now close.
Open the project to which you want to add the EML item. For the purposes
of this example, you can use either an existing or newly created US/I-P
based project.
On the Select an Equipment Model Library File dialog box, click the
EML to which you added the item; then Click OK.
On the Select an Equipment Model Library Item dialog box, select the
item you added; then click OK.
280
281
man-hours tend to vary greatly based on site conditions and project types.
Items of a unique and/or variable nature are ideal for storing in a UCL.
The instructions take this example through the following stages: library
creation, adding items to the library, adding a library item to a project as a
component, and forming an assembly in the project out of multiple UCL
items.
Expand Cost Libraries in the tree-structure, and then expand Unit Cost
Library.
In the New Unit Cost Library dialog box, enter a file name (required) for
the UCL and a brief description (optional).
282
If you just added a library, the Library dialog box is displayed, and you
may skip to Step 2. If not, follow these steps:
a. Go to the Palettes Libraries tab view.
b. Expand Cost Libraries, Unit Cost Libraries, and either Inch-Pound or
Metric.
c. Right-click on the library to which you want to add an item, and then
click Modify on the pop-up menu.
Enter a Reference ID for the item in the Add Item dialog box.
283
Click OK.
In the Develop Unit Cost Library form, enter information for the new item.
Note: Costs for the item will be allocated to the specified Code of Account
(COA). See ICARUS Reference, Chapter 34, for COA definitions.
Aspen Process Economic Analyzer uses the Material Cost Per Unit and Labor
Cost Per Unit to cost the item in an estimate. If Labor Hours Per Unit is
specified and Labor Cost Per Unit is left blank, Aspen Process Economic
Analyzer will calculate the labor cost using the project wage rates at the time
of the estimate.
The Unit of Measure can be designated for each or by any appropriate unit
(i.e., 1000 SF ). Be sure to sufficiently describe the item so that you know
what the unit costs include when the item is retrieved at some future date.
The quantity is entered when the library item is retrieved into a project.
The Date and Source are for your reference and are not transferred into an
estimate.
6
To add a set of items as in the ASBABT example, repeat the process (Steps
2-4) to add the following items in addition to the one shown in the previous
graphic.
Reference No. Item Description
Code of
Account
Date of
quotation
284
AAB200
Polyethylene
Sheeting
800
.021
AAB201
AAB202
AAB300
Decontami-
.004
SF
04APR01
3.50
ROLL
04APR01
800
6.00
CAN
04APR01
800
300.00
EACH
04APR01
300.00
EACH
04APR01
.01
EACH
04APR01
nation Shower
AAB301
800
AAB400
Lighting Fixture
Removal
800
After the above are added, the Library dialog box will appear as shown
below.
When done adding items to the UCL, click Close on the Library dialog box.
Open the project to which you want to add the UCL item. To add an item
from the ASBABT library developed as an example in the previous
instructions, you can open either an existing or newly created US/I-P
based project.
285
On the Select a Unit Cost Library File dialog box, select the UCL to
which you added the item and click OK.
On the Select a Unit Cost Library Item dialog box, select the item you
added and click OK.
286
Aspen Process Economic Analyzer retrieves the unit cost data you set up in
Libraries.
287
At the Select a Unit Cost Library File dialog box, select the UCL
containing the first item to add to the assembly and click OK.
At the Select a Unit Cost Library Item dialog box, select the first item
to add to the assembly and click OK.
288
Click Add.
On the Select a Unit Cost Library File dialog box, select the UCL
containing the next item to add to the assembly and click OK.
On the Select a Unit Cost Library Item dialog box, select the next item
to add to the assembly and click OK.
289
10 Repeat the process of adding items until the form contains columns for all
the items in the assembly.
290
Highlight a library item in the Library dialog box and click Copy.
Click OK. Aspen Process Economic Analyzer adds the new item with all the
same data as the original only the Reference ID has changed.
Highlight a library item in the Library dialog box and click Delete.
291
In this field
type
Material Escalation:
Labor Escalation:
292
In the Select a File for Import window, locate the file and then click
Open.
The file is now included in the Palette and its items can be added as Aspen
Process Economic Analyzer project components.
Enter a file name and description (optional) for the new library.
293
Aspen Process Economic Analyzer displays the Library dialog box for the new
Library, which contains the same items as the original. You can add, modify,
or delete the items without affecting the original.
294
295
need for applying a factor to the baseline plant cost to scale it up or down.
Given a new capacity, ASM recreates the entire plant.
The ASM process is automatic and rapid. ASM revises sizes of components to
meet a revised capacity and the project evaluation engines do the difficult,
time-consuming evaluation work. Users find ASM performs its re-sizing
operation results to be similar to engineering design methods with the added
benefit of much reduced time and resources. Further, equal confidence can be
applied to evaluation results before and after using ASM as rules are
discipline-based and the before and after evaluation processes are identical.
Open your baseline project and save it under a new scenario name that
reflects the new capacity. This will ensure that your baseline project
remains intact, separate and apart from your about-to-be scaled project.
On the Run menu, click Decision Analyzer or click the A button on the
toolbar.
296
beyond 600% to 700%, scale your project twice. For this, the Evaluate
Project check box should be cleared. Then you can split the desired
700% into two parts: first use 350%, and on completion, scale it again at
200%.
5
heuristics for plant items that are based on footprint and plot plan
The current rule set in some instances modifies the number of items rather
than change sizes, as in the simple example of trees along a fence line, where
the number of trees would be revised rather than the size of each tree. In the
current rule set, there is no automatic provision for changing the number of
project components.
297
Limiting Conditions
It is possible that on extreme capacity scale-ups, sizes of certain equipment
or bulk items may surpass a system limiting value. In this case, an error
condition would be issued. The user would then examine the scaled model for
the particular item(s) and revise the size and number of out-of-range items
accordingly, as an item in an error condition would be excluded from the
estimate.
Scale-up Candidates
ASM rules apply to the following types of project information:
1
Note: Several sanitary process equipment items associated with batch food
processing are not scaled.
3
Installation specs: quoted costs, hours and numeric dimension specs for
piping, duct, civil, steel, electrical, insulation, paint. Text-based sizes such
as pipe schedule, wire size, etc. are symbolic and are not scaled.
Project Component Quoted Cost and Hours: While ASM has rules for
quoted cost and hours, the ASM rule may not be the best for your type of
item. Here, its better to apply a % Adjustment to the systems estimated
cost in an amount that will bring the estimated cost up to your quoted
value. Then, on scaling, the new reported cost will be calculated by
applying your % Adjustment to the estimated cost. Based on the scaled
sizes.
o
298
can relocate a project from one base location to any one of 89 worldwide
locations. You can choose to retain the location of your engineering workforce
or choose any one of 89 worldwide locations.
When you need to evaluate a project that you might engineer and/or
construct in a different city or country location, ARM will quickly and
automatically revise your project parameters with those contained in its
location knowledge base. The ARM knowledge base includes key locationdependent data and rules to convert your project from its starting base
location to your selected location using location dependent values for design
parameters, engineering and construction work forces, cost of materials, and
engineering, material and construction indirects. You can use ARM in
combination with the Analyzer Scale-up Module (ASM) and Analyzer
Economics Module (AEM) all in the same run or separately from the other
modules.
Relocation Terminology
Plant location: city and country name used to characterize the plant site.
Workflow
The figure below shows the general work process. ARM specs, contained in
the ARM rule set are applied to the users model. A description of the
elements in the table is provided in the section following the Workflow.
299
Relocation Reports
For New
Engineering and
Plant Location
Baseline Reports
For Base
Engineering and
Plant Location
Baseline
Project
Analyzer
Project
Relocation
Module
(ARM)
Relocated
Project
ARM Specs
Project
Specs
Construction
Hours
Construction
Rates
Material
Quantities
Engineering
Hours
Engineering
Rates
Construction
Indirects
Materials
Indirects
Engineering
Indirects
Construction
Contingency
Materials
Contingency
Engineering
Contingency
Construction
Fee
Construction
Cost
Engineering
Cost
Material
Cost
Project
Contingency
300
On the Run menu, click Decision Analyzer or click the A button on the
button bar:
Note: The last line on the Decision Analyzer dialog box displays three pieces
of information:
plant location
currency name
301
Having completed the choices, click OK to run the project. If you click
Cancel, all choices will be ignored and control will return to the explorer
view.
302
Proprietary sources
Surveys
Location specs
Project specs
Engineering specs
Construction specs
Location Specs
ARM is formulated for 89 locations in 33 currencies. Locations listed below
include the four Icarus country base locations. The locations are similar to
those in the Aspen Richardson International Cost Factor Manual list.
Locations are organized and sorted by continental region, country and city.
For Canadian and US locations, names include state, province or territory.
Conventional short forms of country and city names are used for simplicity.
Asia
15
Australia
Canada
Central America
303
Europe
12
Middle East
South America
United States
37
All Locations
89
Non-US Locations
52
City, Country
Near
Africa
El Hassania, Morocco
Casablanca
Ibadan, Nigeria
Johannesburg, South Africa
Asia
Beijing, China
Guangzhou, China
Shanghai, China
Bhopal, India
New Delhi
Kuala Lumpur
Manila, Philippines
Singapore, Singapore
Seoul, South Korea
Taipei, Taiwan
Australia
Samutprakam, Thailand
Bangkok
Hanoi
Melbourne, Australia
Perth, Australia
Sydney, Australia
Central America
Canada
Calgary, Canada
Montreal, Canada
Toronto, Canada
Vancouver, Canada
Windsor, Canada
Winnipeg, Canada
Europe
Brussels, Belgium
Paris, France
Frankfurt, Germany
Dublin, Ireland
Milan, Italy
304
Amsterdam, Netherlands
Rotterdam, Netherlands
Warsaw, Poland
Moscow, Russia
Barcelona, Spain
London, United Kingdom
Manchester, United Kingdom
Middle East
Cairo, Egypt
Kuwait City, Kuwait
Dammam, Saudi Arabia
Al Jubail
Istanbul
305
Oakland, CA
Philadelphia, PA
Phoenix, AZ
Portland, ME
Portland, OR
Sacramento, CA
San Francisco, CA
Seattle, WA
Sherman, TX
Spartanburg, SC
St Louis, MO
Syracuse, NY
Wilkes-Barre, PA
Project Data
The ARM knowledge base contains a comprehensive set of values for project
level data. These should be considered as a starting point in the evaluation of
a project. Concerned users should replace the ARM knowledge base values in
their relocated project with more representative values obtained from
company surveys of the intended site.
Currency: Exchange rate (FEX), as of the first day of the basis year, with
exchange rate and currency units scaled to meet Icarus currency formats.
Scaled currency units are provided at three levels: 3-character symbol, 8character name and 24-character description. Values are listed in Table 4.
o
Country
Currency
Description
Currency
Name
Currency
Symbol
Exchange
Rate, per
USD (1
Jan 2006)
Argentina
Argentine Peso
Peso-A
3.0459
Australia
Australian Dollar
Dollar-A
A$
1.3644
Brazil
Brazilian Real
Real
2.3517
306
Canada
Canadian Dollar
Dollar-C
C$
1.1641
China
Chinese Yuan
Renminbi
Renminbi
8.0755
Colombia
K Colombian Peso
K Peso
K-P
2.28393
Egypt
Egyptian Pound
Pound-E
PDE
5.786
European Union
Euro
Euro
EUR
0.8446
Guatemala
Guatemalan Quetzal
Quetzal
7.615
India
Indian Rupee
Rupee
45.195
Indonesia
K Indonesian Rupiah
K Rupiah
K-R
9.85222
Japan
K Japanese Yen
K Yen
K-Y
0.117681
Kuwait
Kuwaiti Dinar
Dinar
DK
0.2921
Malaysia
Malaysian Ringgit
Ringgit
3.7837
Mexico
Mexican Peso
Peso-MX
10.66485
Morocco
Moroccan Dirham
Dirham-M
9.3661
Nigeria
K Nigerian Naira
K Naira
K-N
0.1305
Peru
NuevoSol
NS
3.422
Philippines
Philippine Peso
Peso-P
53.14
Poland
Polish Zloty
Zloty
3.255
Russia
Russian Rouble
Rouble
RBL
28.75
Saudi Arabia
Saudi Riyal
Riyal
3.7503
Singapore
Singapore Dollar
Dollar-S
S$
1.6642
South Africa
Rand
ZAR
6.3359
South Korea
K South-Korean
Won
K Won
K-W
1.0287
Taiwan
Taiwan Dollar
Dollar-T
T$
33.147
Thailand
Thai Baht
Baht
41.0767
Turkey
New Lira
NL
1.34979
United Arab
Emirate
Dirham-U
3.6732
United Kingdom
British Pound
Pound-UK
PDS
0.5802
United States
US Dollar
DollarUS
USD
Venezuela
K Venezuelan
Bolivar
K Boliv
K-B
2.15
Vietnam
K Vietnamese Dong
K Dong
K-D
15.904
Belgium
France
Germany
Ireland
Italy
Netherlands
Spain
307
Equipment: design code (ASME, BS5500, DIN, JIS depending upon the
plant location)
Civil and Steel: seismic acceleration, soil, footing depth, low/high ambient
temperatures, wind velocity, hand excavation
Use of gin poles vs. heavy cranes: each location is assigned a value for
the heavy lift option
The following are provided by ARM for each engineering work force location:
Engineering Indirect Costs values are provided for each location for each
of the eight phases of engineering:
o
Expense rates
Payroll burdens
Office indirects
Basic Engineering
Detail Engineering
308
Procurement
Engineering Management
Construction Management
Start-up, Commissioning
= 20.6%
P
Construction
The ARM knowledge base contains a comprehensive set of construction
workforce values, which should be considered as a starting point in the
evaluation of a project. Concerned users should replace the ARM knowledge
base values in their relocated project with more representative values
obtained from company surveys of the intended site.
The following are provided by ARM for each construction work force location:
Field Craft rates hourly rates (nearly all-in) for each of 28 field crafts
in the construction work force slate and a foreman differential for each
location. By nearly all-in, we mean that each craft rate is a unique
composite of the following rate contributions:
o
Fringe Benefits
Temporary Construction
Multi-level construction
Field Supervision
309
= 20.6%
P
Material Costs
Location Indexing
The ARM knowledge base contains a set of location indexes which will
adjust country base material costs to the plant location. Two sets are
provided:
o
= 20.6%
P
310
Introduction
Analyzer Utility Modules (AUM) Design
and Scope Generators for Utility Systems
One of the difficulties with process economic analyses, both capital cost and
payback determination, is the lack of scope definition for non-process or
outside boundary limit (OSBL) portions of the project. With AUM modules
creating utility systems in harmony with the process sections of a project,
more accurate, realistic and confident business assessments can be made for
cost and economics.
Each AUM module works in the same way. It extracts information on the
specific utility needs of each project component and area in your project. You
can then interactively revise default values for design preferences and
configuration, evaluate messages, review reports of design results. On
completion, a press of a Load button will automatically transfer to your
project, a list of selected, sized, designed project components assembled
within a unique date- and time-stamped utility area. Should a prior utility
area of the same type be present in your project, you can chose to delete the
old one and replace it with new scope.
All of this takes place in times measured in minutes rather than traditional
days and weeks. Of course, evaluation time depends on the size of the
project. For front end engineering design work, AUM modules can be revisited
in each cycle of scope change to ensure the project needs are properly
satisfied by each utility system.
A Control Panel, a task bar button and numerous hypertext links provide for
easy navigation and rapid access to a status report, specs for preferences and
configurations, reports, an a guide. Messages are provided to assure data
integrity; an error condition will disallow loading of results into your project.
311
Instrument air: From a count of air operated control valves and controllers
and instrument air flow required for each based on control valve size
Plant air: From an air usage model based on a common air tool usage set,
with area utility stations derived from area size and equipment count
within an area
Up to four air plant units (APU) can be configured for a project, each with its
own set of sized components:
ductwork
compressors
interstage coolers
air receivers
pre-filters
air dryers
after-filters
You can interactively define design premises such as ambient air conditions,
equipment types, equipment redundancy, etc. and assign individual areas to
be served by each air plant unit. Redundancy capabilities include stand-alone
compressors, start-up compressors, receivers, dryers. Redundancy choices
include one at 100% capacity, two at 50% capacity, stand-by spares.
Distribution piping includes two sets, each sized for the required flow of
instrument air and plant air. Piping isos for line segments include expansion
312
loops for long runs, valves and fittings, Line segments are defined for main
feeders, main manifolds, main lines branch lines, area feeders, area headers
and for 3Dtype areas, risers and laterals. Each line type has its own iso for
valve and fitting type. Line sizes are pressure drop based.
Preparation Workflow
Overview
Overview
Introduction
o
Worksheets
Button actions
Worksheet Details
o
Status Worksheet
Preferences Worksheet
313
Circuits Worksheet
Initial Configuration
Naming conventions
1. Overview
Analyzer Utility Module (AUM) Water
One of the difficulties with economic analysis, both capital cost and payback
determination, is the lack of scope definition for non-process utility or outside
boundary limit portions of the project. The Analyzer Utility Module, AUM, was
created as the home for a series of automated utility design models to
address this difficulty. The Cooling Water Selection, Design and Sizing Model
is the first utility design model in AUM and its functionality and method of use
is described in detail in this chapter.
314
Starting with an open project that contains utility streams as part of its
definition, click Run, then click Utility Model. Or, simply click the U
button to access utility models.
At this point built-in design and processing procedures do all the hard work
under your control and guidance and a few minutes later, your project will be
augmented with a new cooling water utility area that contains designed
cooling water circuitry and associated project components. You can use the
model results using its set of adjustable design parameters or revise any and
default values within prescribed limits to suit your needs.
In the discussions to follow, the term early design metrics is used to
indicate values prepared by the cooling water model during an interactive
design session. These are presented for guidance in advance of final design
values that would be prepared on completing a project evaluation run.
Note: Worksheet names are shown in italic bold face to distinguish the
names from text.
With the process technology selected and additional scope, total project
costs are sought. Outside Battery Limits (OSBL) components are
required, particularly cooling water utility service.
315
metrics reports are provided extensively to guide you quickly and knowingly
through a study of design alternatives.
When you have settled on a design you can load the results into your project.
The loading operation begins with a click of a Load button and processing is
automatic. After a minute or so, the loading process will be complete and the
Project Basis view will be displayed on your screen. Scope items added to
your project include a uniquely named cooling water area followed by a list of
cooling water utility project components: cooling towers, circulation pumps,
chemical injection pumps, working and stand-by spares, and distribution
piping, valves and fittings. Each component is selected, designed and sized in
harmony with your design basis and the needs of heat exchange equipment in
your various project areas.
Using these two actions, you can participate interactively in the design
process, making design selections, reviewing early metrics, revising
selections, and clearing any error messages.
316
Figure 2.1. The Workflow Cycle, extracted from the Welcome worksheet
To initiate a cooling water design model session, three steps are required
1
317
The reason for this step is to ensure that the project scope and cooling water
requirements developed during evaluation are current and up to date. It will
also eliminate an error message (Figure 2.2d) that would be displayed when
accessing the cooling water model no evaluation data were available.
.
Figure 2.2d. Error message if the project was not evaluated
318
This will bring up the Utility Model dialog box, Figure 2.3b. A blank value
under Status indicates the project does not contain a prior cooling water
model area. If a project contained a prior area, the Status field would indicate
Loaded.
3b Select Cooling Water: Click OK. This will either initiate an interactive
Cooling Water Design session in MS Excel and display a Load option or
display a project-not-evaluated error message (see Step 2 above).
319
Control Center toolbar button opens the Control Center worksheet, which
has hyperlinks to other sheets and their major categories. Worksheet tabs
are color coded to match hyperlinks at the top of each worksheet.
The following sections provide a detailed description of the work process as
well as detailed descriptions of each worksheet, category and item.
The model first identifies if a prior cooling water model area is present in
the project. If present, the user can choose to Delete the prior area and
continue with the model or return to the project. If Delete is chosen, the
utility model will proceed with the design and delay deletion until it is time
to load the new results.
Welcome
Control Center
Status
Preferences
Capture
Guide
The model then displays the Control Center worksheet, which links to all
other worksheets and provides an indication of success (green signal) or
failure (red signal) to create an initial design based on default design
parameters.
320
321
Figure 2.6. A section of a Results Capture sheet showing values in the project
units of measure set.
ControlCenter: navigation
Guide: help
322
You can step from one sheet to another, revise the design basis, review
status and results, decide on an alternate design basis, make revisions,
review the results and when ready, click the Load button (see Load-CancelMinimize) to inject the results in the project. Or, you can refuse the design
using Cancel. Clicking Load conveys the design results to the project, the
cooling water design models Excel sheets and return to normal Analyzer
functions. Cancel bypasses the cooling water model and returns to Analyzer.
Two design basis sheets this is where you input your selections
o
Status sheet all messages are summarized here for your review and
repair
o
All sheets: are conveniently color coded, with red flags appearing on
error condition. All error conditions must be cleared before results can
be loaded
323
Worksheet Details
Status Worksheet
The Status sheet reports messages and has hypertext links to source
locations in the event of a reported error. Major report categories are:
Overall status
Cooling water loads: total flow rate, total heat duty, excess capacity,
total flow rate at excess capacity
Preferences Worksheet
Units of measure used in the Preferences worksheet correspond to those
defined in the project. Error messages are displayed alongside each entry;
errors are flagged in red. This sheet uses click boxes and data entry fields for
324
Figure 3.2 Extract, sample of a Preferences sheet showing click box method
of selection
325
(e) Multiple Cooling Towers: choose either one tower for all
circuits or one for each circuit
(f) Working Twin: choose a single tower at 100% capacity or
two (twins), each at 50% capacity
Layout (these are dimension limit checks that are applied to entries on
the Circuits worksheet
o
Distance
Pumps
o
Working Pumps
Piping: Limiting values for line size, by line type, where line sizes are
in the units of measure of the project, either IN DIAM or MM DIAM
326
Circuits Worksheet
Units of measure used in the Circuits worksheet correspond to those defined
in the project
This worksheet is designed to handle up to one hundred cooling water areas.
Areas are listed vertically. The worksheet is divided into five major categories
in columns of data:
1
Initial Configuration
Figure 3.3 Extract from Circuits sheet Initial Configuration (left), Step 1
(right)
The following (see Figure 3.3, left side) are reported for each area being
served by a recognized cooling water utility resource stream:
Initial Sort Sequence: sequenced by area, from the area with highest
cooling water requirements to the area with the lowest
Area Type: user-assigned area type, carried into the cooling water
design model from project area specs
Area CW Rate: area cooling water (CW) flow rate, the sum of all
recognized cooling water flow rates for equipment in an area as
adjusted by the Excess Capacity value in the Preferences worksheet
327
Status
o
Figure 3.4 Extract of Circuits sheet defining area spacing using the B/R
switch
Each line item in this section represents an area and its properties. Areas are
sorted and sequenced in descending total circuit flow rate and then by area
flow rate. Circuits are labeled A, B, C, D with circuit A being the one with the
highest flow rate; B is next etc. An area that was tagged as circuit 2 in step 1
may be in a circuit with the lowest flow and would be organized accordingly
and given a Circuit ID letter depending on the other circuit flows.
This section displays the properties and attributes of each area in the
sequenced list.
328
Initial Sort Sequence: displays the initial sort sequence number for the
area
ID of Area In Report Group (ArRg): the ArRg ID for the area
4H
5H
6H
Area Heat Duty: heat duty requirements for all equipment within the
area identified as requiring a valid cooling water resource
Base Value for Spacing Along Circuit Main Line: This is the run length
of the main segment between the prior and current area as developed
by the footprint model.
8H
Enter Revised Spacing Along The Circuit Main Line: This value will
replace the base value if it meets range limit conditions set forth in the
Preferences worksheet. By spacing is meant the distance between
successive areas. As the line items in this section represent areas that
are sorted and sequenced, the spacing for a particular line item is the
spacing between the start of the prior area and the start of the current
area. This spacing is a measure of the areas main line segment. See
the section on the Cooling Water Footprint Model. Piping runs lengths are
typically longer than spacing as they include pipe to configure fittings,
expansion loops, etc.
9H
329
Value used for spacing along circuit main line: The value used
in the design
330
quantities to control the water quality. The cooling water model provides each
cooling tower with a diaphragm type of pump and a stand-by for each of the
treatment chemicals. The model uses the following labels to identify the
types:
Corrosion inhibitor
331
areas and a maximum of four circuits for four or more areas requiring cooling
water.
Figure 4.3, case (a) is a diagram showing a single treed circuit. Figure 4.4,
case (b), illustrates multiple treed circuits. The difference between the two
cases is (a) one cooling tower for each circuit or (b) one for all circuits. Case
(a) would apply to projects with a single area or for multiple circuits, with
each circuit being served by its own cooling tower.
332
Figure 4.3 (case a). Illustration of one cooling tower used to serve a set of
areas in a single circuit. The model will permit up to four single circuits, each
having its own cooling tower and circulation pumps.
Figure 4.4 (case b). Illustration of one cooling tower used to serve multiple
circuits. For this case, the model will provide one cooling tower for all
circuits and a set of circulation pumps for each circuit.
333
Naming conventions
Naming Conventions
Project Cooling Water Utility Area: The cooling water design model will create
a cooling water model utility area to contain project components for each
circuit. On loading, the area will be named with a date and time stamp to
ensure it is unique and can be detected and properly deleted when a new
design is to take its place.
The naming convention is: AUMCoolWater ddmmmyy_tttt, where
yy is the last two digits of the session year (05 for 2005, etc)
MS
MainSeg
334
Branch segment: a short run of pipe, from the main line to a specific
project area
o
Branch
Area header: a line of pipe, valves and fittings that distributes cooling
water along the long dimension of the base of a project area
o
AH
Area Header
Risers
Laterals
VD
VentDrain
Lines with check valves are of minimal length to satisfy the plant bulk PIPE
mode and are separate line items as only one check valve is assigned to a
supply-return line pair.
Figures 4.5 and 4.6 illustrate these line types for 2D (PAD, GRADE) and 3D
area types (OPEN, EXOPEN, FLOOR, MODULE)
335
Figure 4.5 Schematic of cooling water piping for a 2D area type (PAD, GRADE)
Figure 4.6 Schematic of cooling water piping for a 3D area type (OPEN,
EXOPEN, FLOOR, MODULE)
336
Figure 4.7
337
rate and limiting line velocity (suction lines being different from distribution
lines). Line length is determined by (a) minimum length of pipe required to
each type of fitting and (b) the long area dimension, which is developed from
a cooling-water footprint model for each project area and area type.
Fittings are assigned to each line type from a list that includes elbows (EL),
tees (TE), reducers (RE), flanges (FL), blind flanges (BL), gate valves (GA),
check valves (CH).
1H
Each line type is based on five configuration components. The total line
length is determined by as the sum of the linear run distance plus pipe
lengths of pipe to satisfy the make-up of the configuration components. The
make-up of each configuration component is based on line type and consists
of quantities of the following:
Expansion loops and vent and drain stations are placed along the run based
on line length
The configuration of each line type serving each area is defined as a project
component located in the cooling water area created by the cooling water
model. Once loaded in the project, any line configuration can be reviewed
and modified in the usual manner by opening that project component in its
form.
Flow rate combined with limiting velocity results in required flow area
338
Built-in iso for each line type defines valve and fitting count
Line length is derived from spacing between areas from circuitry input,
minimum spacing between areas and minimum lengths from line
A single average value for the pressure drop across cooling water
usage components in any area is defined in the Preference worksheet
It is possible that the limiting line size for branch and area headers may be
too small for some circuits with large flows. This would result in a cluster of
two or more parallel lines. To alleviate this condition, consider increasing the
limiting line size.
Figure overview_4.8 shows a cooling tower with air and cooling water
streams and their temperatures.
Terms used in the cooling tower industry, illustrated in Figure 4.8, are:
339
CTWCOOLING
CTWPACKAGED
340
AUM_Air
Utility Design and Scope Generator
for Instrument and Plant Air
Overview
The Air Utility Module automatically and interactively:
selects, designs, and sizes air plant project components that conform to
your:
o
Augments the scope of your project with a list of designed air utility
project components in a unique air utility area on the click of the Load
button
With the Air Utility Module, you can review, revise, add other project
components and/or Run the augmented project to obtain a new project
evaluation.
The Air utility model can be
A project area
The AUM Air utility module works with each project area and its
air requirements
341
Benefits:
With LOAD, a new Air utility area will be inserted into your project with its
designed list of air system project components
Sized
Reported
In a small fraction of the time and effort it takes to do this work in the
traditional manner
Move the supplied Control Center toolbar to the top and click it.
Check Status.
498H
342
10 Click the Load button to close AUM_Air and load the design results into
your project.
11 Review Area and components.
12 Run the project, review results.
Using AUM_Air
Accessing AUM_Air
To access AUM_Air:
1
Starting with an open project that has been evaluated, click Run, then
click Utility Model. Or, click the U button to access utility models.
Click OK.
343
3
4
Welcome
Control Center
Guide
Status
Preferences
Config 1
Config 2
EquipStats
PipeStats
344
Should the design basis produce a clash with project requirements, error
messages and flags are displayed in a top-down succession of worksheets.
The first indication is given under Status Report on the Control Center
worksheet. The Status worksheet is the central reporting agency, where
checks are made and links are provided to source locations in the EquipStats
and PipeStats worksheets.
345
Click Load.
The Aspen Icarus Loader appears, showing the progress of loading the XML
data into Icarus.
When the Air Instrument, Plant data has been loaded into Aspen Icarus,
the following confirmation message appears:
Click OK.
On the main menu, click Run, then click Utility Model. Or, click the U
button to access utility models.
The Utility Model dialog box appears. Note that the Status column says
Loaded.
346
Click OK.
Note: Clicking Yes does not actually delete the Air Instrument, Plant
data in your project. You can click Yes, modify the Air Instrument, Plant
data, then choose not to replace the previous Air Instrument, Plant data
with the modified data by clicking Cancel on the Load | Cancel | Minimize
dialog box.
4
Click Yes.
If you want to replace the loaded data with your modified data, follow the
steps below.
1
347
Click Load.
The Aspen Icarus Loader appears, showing the progress of loading the XML
data into Icarus.
When the Air Instrument, Plant data has been loaded into Aspen Icarus,
the following confirmation message appears:
Click OK.
348
Click Cancel.
349
350
351
Areas assigned to an APU are collected in the sequence of the project and
are assembled in a column-row array
Row and column dimensions are figured from total area, number of areas
and an initial aspect ratio of 3:2
Air Distribution
Piping for each service is developed in the same way, except for
volumetric flow and line size
Distribution Piping
The APU feeds air to the array through a Main Feeder (MF)
Two Main Manifolds (MM) are used on extra-wide arrays, els one or none
for an array one column wide
Area headers, for 2-D area types such as Grade, Pad, etc supply air to the
I-P transducers, control valves
o
Area headers, for 3-D area types such as open steel structures, etc supply
air to Risers, then Laterals which then connect to I-P transducers and
control valves.
o
352
Schematic
The following schematic was prepared to illustrate a large project of 78 areas:
Project Components
353
Schematic of an APU
Multiple APUs
Compressor Redundancy
Project Components
The Instrument and Plant Air Utility Model creates a set of project
components in accordance with the needs of your:
Typical components
Air Compressors
Air Filters
Air Receivers
Air Dryers
Area Title contains a unique time and date to differentiate one run from
another
Area can be modified or deleted in the usual way using Aspen Process
Economic Analyzer, Aspen Process Economic Analyzer/Analyzer
Air compressors
o
Air receivers
354
Distribution piping
o
Utility stations
General Layout
355
instrument air
plant air
356
Design Considerations
Units of Measure
Designed Components
Air Receivers
Air Filters
Air Dryers
Units of Measure
Values are reported in the Unit of Measure set of the users project, in the:
Compressors
Interstage coolers
Air Dryers
357
358
359
360
Air Filters
361
Air Receivers
Air Dryers
Interactive Specs
Design Basis
o
Equipment Redundancy
Equipment Configurations
Selection Specs
Design Preferences
Air Distribution
Layout
362
User Preferences
Organized by category
Color coded
Equipment Redundancy
Stand-by spare
Optional
Optional
Equipment Configurations
Equipment configuration choices:
363
Atmospheric pressure
Air Requirements - Capacity for Instrument and Plant air (one set for all
APUs)
o
Excess capacity, %
Instrument air
Plant air
Cost
Hour to install
364
Weight
Main compressor
Install?
Start-up compressor
Install?
Running time
Interstage Coolers
Type:
Notes:
If low capacity type is selected, may generate multiple low capacity
compressors
High capacity compressors may require project mid- and/or high voltage
power distribution levels.
o
Air Receivers
o
Maximum diameter
365
o
8
Air Filters
o
Number of pre-filters
Number of post-filters
Plant air
Number of pre-filters
Number of post-filters
Distribution piping
o
Area feeder and header, risers, laterals are based on area specs
Example:
A branch line is run across each row with area feeder take-offs
to each area in a row
Main Manifolds are fed by a Main Feeder from the Air Plant Unit
366
APU Configuration:
o
Choose default (one APU for all) or assign each Report Group to
one of four APUs
367
Design Methods
368
Each line type is assigned an Iso with valve and fitting counts,
expansion loops for long runs
Sizing
369
all worksheets visible to the user have the version number printed at the
bottom of the sheet
except for currency and exchange rate, sheets are in the user's units of
measure defined in the user's project specs
o
Welcome
ControlCenter
370
Guide
Status
Preferences
Config_1
Config_2
EquipStats
PipeStats
Welcome Worksheet
371
Guide Worksheet
372
373
374
375
376
Status Worksheet
377
378
Preferences Worksheet
379
380
381
Note: For clarity in this documentation, the following screen shot is shown
below the one above it. On the actual Config 2 Worksheet, they are side by
side.
382
383
384
Click
on the toolbar.
or
On the Run menu, click Evaluate Project.
The Evaluate Project dialog box appears.
The dialog box shows the default Capital Costs report file name, Cap_Rep.ccp.
This is the report reviewed in Icarus Editor. If you want it to have a different
name, type the file name in the Report File field.
2
Click OK.
If you are using the default Preferences, Aspen Process Economic Analyzer
scans the project specifications for errors and/or inconsistencies and any
385
Note: You can select in Preferences to skip the scan for errors (see page
48).
X49H
Description/Importance Level
INFOrmational
WARNing
ERROR
FATAL
You have the option to continue or stop the evaluation process (except in the
case of FATAL errors, which stop the evaluation process). You should carefully
review these and fix any problems before proceeding.
When the project evaluation is done, Aspen Process Economic Analyzer lists
all errors found in the capital cost evaluation for your reference.
If you are using the default Preferences, Aspen Process Economic Analyzer
automatically displays the Investment Analysis spreadsheets in the Main
Window when the evaluation is complete. See Reviewing Investment
Analysis on page 439 for a description of these spreadsheets.
X50H
Note: You can select in Preferences not to have Aspen Process Economic
Analyzer automatically display the Investment Analysis (see page 48).
X501H
386
On the Decision Analyzer dialog box, mark the Develop Detailed Process
Economics Reports check box.
Enter the desired reporting currency symbol to use for the reporting of all
costs.
If the plant location currency is different from the currency used on the
reports, enter the exchange rate as the ratio of Report Currency/Plant
Location Currency.
Click OK.
387
Overview of Workbooks
In addition to showing you the economic analysis of the current project basis,
the workbooks allow you to instantly see the impact that revisions to the
basis will have on economic measurements. For example, you can revise the
required working capital percentage on the Project Input worksheet in SPECS
and, as a result, the Cash Flow bar chart on the Figures worksheet in
RESULTS will change to reflect this revision. This is explained in detail in the
Revising Premises section, page 397.
X502H
SPECS Workbook
The SPECS workbook consists of the following worksheets, which you can
navigate by clicking the sheet tabs at the bottom of the workbook window:
Guide
The Guide provides you with an online reminder of helpful information, which
you may refer to during an interactive scenario session:
Strategy - how to use this module effectively for evaluating business and
economic options.
Control Panel
The Control Panel allows you to revise high-level stream premises. It features
spinner controls and reset buttons, enabling you to change unit prices and
instantaneously see the resulting economic metrics and graphed results.
388
Key economic metrics displayed include: graphs of net present value (NPV)
and annual production revenue, payout date, Internal Rate of Return (IRR),
NPV over project lifetime, gross, operating and net revenue margins.
Decision Center
The Decision Center is AEM's navigator. It enables you to move quickly across
all of AEM's user-interactive worksheets, all of which are included in horizontal
format. To view all the worksheets in a vertical format, use the DC_V
worksheet.
Both the horizontal and vertical formats enable you to quickly locate high
level and lower level categories and the ultimate worksheet locations.
Important error messages are displayed on the Decision Center header.
An NPV graph displays the current state of the scenario including high-level
error messages with pointers to error locations.
DC_V
This worksheet contains the same content as the Decision Center worksheet
in a vertical format.
Input Worksheets
The two input worksheets are for user-interactive revisions to premises. They
define your economic scenario. Revisions are immediately reflected in the
Status, Statements, EPC, and Figures worksheets. See page 397 for
information on revising economic premises.
X503H
389
Project Input
In the Project Input worksheet, you can revise the schedule, time periods,
capital investment, cost of capital investment, phase durations, capital cost
parameters, manufacturing cost parameters, operating labor and
maintenance cost parameters, general investment parameters, and
escalation.
The following is an excerpt:
Stream Input
In the Stream Input worksheet, you can revise the stream factor to determine the
impact of turndown, turnarounds or a proposed expansion; split production into a
domestic and export stream with their associated unit prices; revise prices of byproducts, raw materials, and utilities. An important aspect of the Stream Input
worksheet is the use of periodically changing values of stream factor, unit costs
and percent to export. This feature will enable you to study the impact of market
cycles and identify economic threats and opportunities related to production over
the life of the project.
Status Worksheet
View the Status worksheet for a quick summary of which values on the input
worksheets have been revised, need correction, or are incomplete.
390
391
Capture Worksheet
The Capture worksheet and its initiating buttons
enables you to review and capture highlights of up
to 50 economic scenarios. A set of buttons is
provided to initiate the capture of current scenario
highlights in advance of working on the next
scenario.
RESULTS Workbook
The RESULTS workbook consists of six worksheets, which you can navigate by
clicking the sheet tabs at the bottom of the workbook window.
The following is an overview of the worksheets.
EPC Worksheet
The EPC worksheet provides before and after information regarding the
engineering, procurement and construction aspects of your project. The term
before refers to the state of your project based on your initial premises,
prior to interactively changing from one scenario to another in Analyzers
Economic Module. The EPC workbook provides costs in both the currency of
the plant location and a user-defined reporting currency. For example, if your
project were modeled using the European Union country base (EU, currency
in Euro) and you wished to see costs reported in Euro for a project relocated
to Mexico (reporting currency in k-Peso), you could define the reporting
currency to be Euro and enter the desired exchange rate between the Euro
and k-Peso. You would define the reporting currency and exchange rate along
with the relocation country, at Run time. The EPC worksheet would report
plant location costs in both Euro and k-Peso. This worksheet currently
provides the only connection between costs in the country base currency and
plant location currency.
The EPC worksheet provides the following information:
392
393
Project Basis
The Project Basis worksheet provides project name, project description,
simulator type, capital cost evaluation and parameters, time periods,
construction schedule, manufacturing cost parameters, operating labor and
maintenance cost parameters, general investment parameters, escalation,
cost summary, and EPC details based on your initial economic premises.
The following is an excerpt:
Design Basis
The Design Basis worksheet provides summary-level presentations of income,
product revenue, manufacturing costs, margins, raw material costs, utility
costs, and earnings based on your initial economic premises.
394
Statements Worksheet
The Statements worksheet, like the EPC, Status and Figures worksheets,
shows results of changes made in the Input worksheets.
395
Figures Worksheet
The Figures worksheet, like the EPC, Status and Statements worksheets,
shows results of changes made in the Input worksheets.
Flows, by Calendar Period: Net and Cumulative Cash Flow, Margins, Gross
and Operating and Net Income as a % of Revenue, Product Revenues:
Domestic and Export.
396
Revising Premises
The premises on which an economic scenario is based can be modified on the
Project Input and Stream Input worksheets. The results of modifications are
immediately reflected on the Status, Statements, and Figures worksheets.
Note: Revisions made in the workbook have no impact on the actual project
basis.
To revise premises:
1
Go to the Select field of the item you wish to change. Pressing TAB moves
the cursor to the next field, while pressing CLEAR+TAB moves the cursor
to the previous field. You can also use the mouse and arrow keys.
The Select field can contain one of the following symbols (not case-sensitive):
Enter To denote
B
397
In the event a symbol is not entered, the base value will be used.
3
Go to the input field and enter the new value. For percentage values,
simply enter the percentage value. If 0.2% is to be entered, enter 0.2. If
50% is required, enter 50. If a negative value is required, for example to
indicate construction is to begin 0.5 periods early, enter a negatively
signed value, 0.5.
As you make revisions, notes and other messages are provided to assure data
integrity. Each line item of data entry has at least one status flag.
Informational and other messages are provided to guide you in preparing a
consistent set of premises.
As soon as you move from the revised field, the revision is reflected in the
Status, EPC, Statements, and Figures worksheets.
Note: Viewing the workbooks in a split screen arrangement lets you instantly
see the results of modifications. To do so, click Arrange on the Window menu,
select Horizontal, and click OK. You will likely need to adjust the zoom to
about 50%. Keep ECOSYS.xls minimized.
For example, if you revise the required working capital percentage on the
Project Input worksheet (shown in window at the top of the split screen
pictured below), the Cash Flow bar chart on the Figures worksheet (shown in
the lower window) will change.
398
Color Coding
Project Input
As described previously, base values are listed to the right of the item
category. The Select field and Enter Revised Base Value field enable alternate
studies. First, enter either an R (not case-sensitive) in the Select field to
revise the base value. Then enter a revised value in the Enter Revised Base
Value field. You can then enter a B (not case-sensitive) in the Select field to
399
switch between revised and base value. The Value Used field shows the
current status of your selection.
The following provides additional information about the individual parameters.
Scenario Reporting
Title and date data: will be displayed in the headers of the various
worksheets and in the footer of the Status worksheet.
Schedule
A timeline is established with a calendar start date to enable the study of
economic cycles and report the timing of events. A base calendar start date is
automatically generated to accommodate the base start date of engineering.
However, as new premises are added, the lead-time between start of
calendar and start of engineering may be too short to accommodate other
efforts such as studies and changes to the fixed capital investment. Or, you
may wish to base your reporting calendar on a calendar year basis or your
companys fiscal year. Once you select the start date of the reporting
calendar, you might wish to review your initial premise for the start date of
engineering.
The engineering start date may be modified as well as the calendar start date.
Messages are provided in this section for lead-time, pre-planning time and
float to help you to establish timing of other events (see next section on
Capital Investment).
Start Date of the Reporting Calendar: defines (a) the project timeline, (b)
enables the escalation to the start date of the calendar of costs entering
the workbook from Analyzer that are founded on the System Cost Base
Date, and (c) enables the dating of tasks and events, including:
400
Plant Start-up
Start of Production
Payout
Status of the calendar: lead time, planning time, float time and other
helpful status messages.
Time Period
Hours per period: determines stream factor, stream flows per period. Your
initial premise may be revised in the Stream Input worksheet.
Capital Investment
401
Phase Durations
Catalyst and Chemicals: for the initial charge, as a percentage of FCI and
salvage value at the end of production.
Patents and Royalties, as an initial fee and/or fee, escalated for each
period of production and figured on the production for each period.
402
Operator: number of operators and hourly rate may be revised from the
base value; Total Operating Labor Cost is displayed.
Tax Rate.
Interest Rate: used in calculating net present values and payout time.
Economic Life of Project: defines the time for depreciation and should be
the same as production life.
Depreciation Method: select from Straight Lines, sum of the Digits, Double
Declining (Balance).
Escalation
Base values of the following items come from your system input and may be
revised.
Engineering
Materials
Construction
Product Escalation: individually for domestic and export product; periodto-period price/cost values take priority over escalation.
Stream Input
This worksheet allows you to revise base values (assigned or default) for
product, by-product, raw material and utility streams. Either a single value,
applicable to every period (subject to escalation if a cost), or a period-toperiod value (not subject to escalation) may be assigned. Indicate use of base
(B), revised (R) for a single value for all periods, or individual period-toperiod values (P). Symbols are not case-sensitive.
403
Phase.
Phase duration.
Start date.
Production Operations
Stream Factor, to study the impact of turndown and expansion.
Production
Price of domestic and export product and percentage of production devoted to
export product. The production capacity is reported for reference.
By-Products
Price of each by-product. By-product rates are reported for the designated
production capacity. The current version is limited to reporting 25 byproducts.
Raw Materials
Price of each raw material. Consumption of each raw material is reported for
designated production capacity. The current version is limited to reporting 25
raw materials.
Utilities
Price of each utility; for ISBL/OSBL studies, consider revising an ISBL utility
stream cost in lieu of its production by an OSBL unit and revision of the FCI
(Project Input>Capital Investment>Increment/Decrement to FCI) to account
for the OSBL units FCI Consumption of each utility is reported for
designated production capacity.
404
Click
on the toolbar.
or
On the View menu, click Capital Costs View.
The Select Report Type To View dialog box appears.
The Reporter imports and loads the reports from Aspen Process Economic
Analyzer.
405
After the reports are loaded, the Aspen Icarus Reporter window appears.
406
Run Report Run selected report. See pages 408 (Standard reports), 421 (Excel reports),
and 416 (HTML reports) for instructions.
X50H
X507H
X506H
Open Workbook Open the last Excel workbook created. See page 424 for instructions.
X508H
Create User Database Export SQL database. See page 429 for instructions.
X509H
Trend Menu
Add Trend Data to Database Add the trend data from the project reports currently loaded
in Aspen Icarus Reporter to the trending database. See page 425 for instructions.
X510H
Create New Trend in Excel Export trending database to Excel. See page 426 for
instructions.
X51H
View Existing Trend Data Open the trending data workbook in Excel. See Data Trending,
pages 425 through 428, for instructions
X512H
X513H
Clear All Saved Trends Clear the trending database. See page 425 for instructions.
X514H
Standard Reports
With Standard reports selected in the Report Mode section, the Reports
section displays a tree-structure grouping of standard reports.
Report Descriptions
Open the necessary category and sub-category folders and click on a report
to display a brief description of that report in the Description section.
407
Opening a Report
Not all of the reports contain each of the features described in this guide. For
example, the Contents view only appears on reports with multiple sections.
In order to see all the features described, select the Contractor COA
Summary report located in the following folder:
Capital Cost Reports\Direct Costs\COA Summaries
408
Navigating
If there are multiple sections, a tree-structure Contents view appears on the
left side of the window, allowing you to jump to a section simply by clicking
the section in the Contents.
The arrow buttons on the toolbar let you page through the report:
Next Page
Previous Page
Last Page
First Page
Because the last page of a report usually contains the totals, clicking the Last
Page button is a convenient way to access them.
Magnification
To change the magnification level:
1
409
Note: You can also click directly in the Magnification box (without clicking
) and then zoom in and out using the up and down arrow keys on your
keyboard.
2
When viewing the report at large magnification, you may wish to hide the
Contents view by clicking the Toggle Group Tree button
more room for the report.
. This makes
410
Searching
To search the report:
1
Click
on the toolbar.
Printing
To print the report:
1
Click
on the toolbar.
Make any desired changes to the default settings; then click OK.
411
412
413
414
HTML Reports
With HTML reports selected in the Report Mode section, the Reports section
displays a tree-structure grouping of HTML reports.
Report Descriptions
Open the necessary category and sub-category folders and click on a report
to display a brief description of that report in the Description section.
415
A status window tells you when the export is complete and asks if you would
like to view the report now.
Click Yes.
416
Note: Generating the report as an .htm file allows the report to be sent in an
e-mail.
Management Reports
With Management Reports selected in the Report Mode section, the Reports
section displays a tree-structure grouping of Management reports. These
reports are intended to serve as snapshots of the project scenario.
- or
- or
The Management Reports Viewer displays the report. Pictured below is the
Detailed Weight Information report, one of the Piping reports in the
Discipline folder.
417
Other reports, like the Equipment Cost (Total Cost) report shown below,
show simply a bottom-line total.
Reporter searches for the last Excel workbook to which you exported a report.
418
Select
To do this
Overwrite existing
workbook
Append to existing
workbook
Clicking Create new workbook expands the dialog box to let you select a
folder and enter a file name.
Note: Do not enter a file extension or period when entering a new workbook
name.
2
419
Click OK.
The Export Status dialog box informs you when the export is done and asks
if you would like to open the workbook now.
Excel Reports
With Excel reports selected in the Report Mode section, the Reports section
displays a tree-structure grouping of Excel reports.
420
Report Descriptions
Open the necessary category and sub-category folders and click on a report
to display a brief description of that report in the Description section.
You can select multiple report check boxes to open multiple reports.
Marking a folders checkbox will open all of the reports in the folder.
2
Click the Run Report button or click Run Report on the File menu.
Reporter searches for the last Excel workbook to which you exported a report.
421
Select
To do this
Overwrite existing
workbook
Append to existing
workbook
Selecting Create new workbook expands the dialog box to let you enter a
workbook path and name.
422
Note: Do not enter a file extension or period when entering a new workbook
name.
After you make your selection and click OK, Excel opens a workbook
displaying the report.
423
AutoFilter
Several of the larger Excel reports generated by Aspen Process Economic
Analyzer take advantage of the AutoFilter feature in Excel.
424
Data Trending
Data Trending facilitates comparison of scenarios by allowing you to review
capital cost summaries of different scenarios in a single Excel workbook. If,
for example, you created three different scenarios for a project, you could use
the Data Trending feature to display the direct costs of each on one
spreadsheet, with a separate row for each scenario.
The Trending Data Update dialog box tells when this is done.
Click OK.
425
The Trending Data Update dialog box tells you when Reporter has finished
adding the trend data.
Click OK.
You will need to add the trend data from the project reports of the other
scenarios you are comparing. For each of the other scenarios, open the
reports in Reporter and complete the Adding Trend Data to Database
instructions above.
Using Reporters import function, you can open the other scenarios reports
in Reporter without opening the scenarios in Aspen Process Economic
Analyzer. See page 428 for instructions.
X516H
The Export to Excel Trending Workbook dialog box gives you the choice of
either appending the trend data to the existing file or creating a new file.
426
The Export Trend Data into Excel dialog box appears. By default, all six
capital cost categories are marked.
Clear any categories you want to exclude from the workbook; then click
OK.
The Export Status window tells you when the export is complete and asks if
you would like to open the trending workbook now.
Click Yes.
Excel displays the trending workbook containing a spreadsheet for each of the
capital cost categories. Each set of trend data entered into the trending
database is displayed on a separate row. (The workbooks for any categories
excluded at the Export Trend Data into Excel dialog box are blank).
427
After having created the trending workbook, you can access it from
Reporter by clicking View Existing Trend Data on the View menu.
428
Use the browse tree to locate the project scenario folder, which should be
at:
Archives_Aspen Process Economic Analyzer\[Project]\[Project Scenario]
After clicking the project scenario folder, PROJID should appear in the File
set to import section.
3
Reporter imports the data. When complete, the selected scenarios reports
can be run from Reporter.
If the file is not found or if this is your first database creation, the Create
User Database dialog box appears with only one Export Option: Create
New Workbook. The lower part of the dialog box provides fields for
selecting a path and filename.
However, if the last created file is found, the Export Options also include
Overwrite Existing Workbook. This option is marked by default, so the
lower part of the dialog box is not visible until you select the Create New
Workbook check box.
429
To review and work with the database, start Microsoft Access and open
the .mdb file.
Click
on the toolbar.
or
2
T
430
The right-hand pane contains the report and the left-hand pane contains a
tree-structure Contents view that lets you jump to sections of the report.
Note: Click
on the toolbar to turn the Contents view on and off (or click
Contents on the View menu).
431
Report Sections
Title Page
Two title pages are produced. This way, if the report is being printed on fanfold paper, one of the title pages will be produced on a page facing up.
432
Features
Estimate Base: financial quarter from which cost basis is derived and date
Icarus Evaluation Engine (IEE) was produced. Run Date: Date and time
that project evaluation was run.
Contract Structure
The Contract Structure section provides names of contractors and reporting
arrangement.
Table of Contents
The Table of Contents lists section names and the page number on which
each starts. The number of sections may vary depending on the number of
Report Groups. If the project contains only one, then there will be only a
single summary. If more than one, there will be a separate summary for
each, plus a summary for the total project.
433
Project Summary
The Project Summary provides an overview of project costs.
434
435
Adjusting productivities, shifts per day, length of the workweek using the
General Rates specifications form and the Craft Rates specifications form.
These forms are accessed in Project Basis view under Project Basis\Basis
for Capital Costs\Construction Workforce.
The number of MEN PER DAY for each vertical bar is generated by summing the
labor assigned to all the work items that fall within the period represented by
that bar in the barchart.
436
This barchart schedule assumes that the DESIGN ENGG AND PROCUREMENT
monies are already spent at the start of construction - the curve is not truly
tied to the CPM schedule. During construction, capital is then spent for
material, direct field labor, equipment rental and subcontract work, Home and
Field Office, Start-up, etc., as the cost is incurred. By the end of construction,
the TOTAL,AMOUNT given in the Project Summary is indicated here.
Operating costs, such as start-up utilities, raw materials, initial catalyst
charges, etc., are not included.
437
Contract Summary
The Contract Summary breaks costs down by contractor.
438
If you are using the default Preferences, Aspen Process Economic Analyzer
automatically displays the four Investment Analysis spreadsheets in the Main
Window after you run an evaluation. You can set Preferences so that Aspen
Process Economic Analyzer does not automatically display the spreadsheets,
in which case you would have to select to view them as described below.
439
Click
on the toolbar.
or
Use the tabs at the bottom of the window to move among the four
spreadsheets.
Click
on the toolbar.
or
Note: In the Excel mode, additional spreadsheets are generated that report
details with regards to utilities, raw material and products. For instructions to
generate customized investment analysis reports, see Using the Reporting
Assistant in Excel mode, page 458.
X517H
Equipment Summary
The Equipment Summary (EQUIP.ICS) contains a list of project components
used in the analysis.
440
Project Summary
Project Summary (PROJSUM.ICS) contains a project summary for the capital
costs (equipment plus bulks) and schedule. This worksheet also includes
operating unit costs (labor wage rates and utility unit costs), utility flow/use
rates (steam/water flow rates, etc.) and operating and maintenance costs.
Project
Description
Analysis Date
and Time
Simulator Type
Simulator
441
Version
Simulator Report
File
Simulator Report
Date
Economic
Analysis Type
Aspen Process
Economic
Analyzer Version
Project Directory
Scenario Name
Scenario
Description
Country
Units of Measure
Currency (Cost)
Symbol
Currency
Conversion Rate
Project Type
Design code
Prepared By
Plant Location
Time Difference
Between System
Cost Base Date
and Start Date for
Engineering
User Currency
Name
User Currency
Description
User Currency
Symbol
442
the reports.
Descriptions for the following parameters are provided in more detail under Investment Parameter
specifications (page 101).
X518H
Time Period
Period Description
Duration of time
Operating Hours
per Period
Number of Weeks
per Period
Number of Periods
for Analysis
Schedule
Start Date for
Engineering
Duration of EPC
Phase
Length of Start-up
Period
Duration of
Construction Phase
Laboratory Charges
User Entered
Operating Charges
(as percentage)
Operating Charges
(Percent of
Operating Labor
Costs)
Plant Overhead
(Percent of
Operating Labor
and Maintenance
Costs)
443
G and A Expenses
(Percent of Subtotal
Operating Costs)
Desired Rate of
Return
Economic Life of
Project
Salvage Value
(Fraction of Initial
Capital Cost)
Depreciation
Method
Escalation
Project Capital
Escalation
Products Escalation
Raw Material
Escalation
Operating and
Maintenance Labor
Utilities Escalation
444
Total Products
Sales
Total Operating
and Maintenance
Labor Cost
Total Operating
Cost
Operating Labor
Cost
Maintenance Cost
Operating Charges
Plant Overhead
Subtotal Operating
Cost
G and A Cost
The costs listed under Project Results Summary are broken down into
individual elements under Project Capital Summary:
Project Capital Summary
Purchased
Equipment
Equipment Setting
Piping
Instrumentation
Electrical
Civil
Steel
445
Insulation
Reference).
Paint
Other
Subcontracts
G and A Overheads
Contract Fee
Escalation
Contingencies
Adjusted Total
Capital Cost
where:
C_at =
C_t =
w =
446
Main Product
By-product Sales
Unit Cost
Total Operating
Labor Cost
Maintenance
Cost/8000 Hours
Total Maintenance
Cost
Supervision
Supervisors per
Shift
447
Unit Cost
Total Supervision
Cost
Utilities Costs
The utility cost breakdown is given below for electricity, potable
water, fuel and instrument air as well as user defined process utilities
such as steam.
Note: The Process utilities details are available only when the results
are viewed in Excel. These are made available through separate
spreadsheets.
The description of each utility includes:
Rate
Unit Cost
Total Cost
Cashflow
Cashflow (CASHFLOW.ICS) calculates the net present value (NPV), internal
rate of return (IRR), profitability index (PI), payback period, etc.
The spreadsheet displays the cashflow information shown by period. The beginning part of the
spreadsheet contains data/results carried over from the Project Summary (PROJSUM.ICS)
spreadsheet.
Item
Description
448
TW
DTEPC
DT
WORKP
OPCHG
Operating Charges
PLANTOVH
Plant Overhead
CAPT
RAWT
PRODT
OPMT
UTILT
ROR
AF
TAXR
Tax Rate
IF
ECONLIFE
SALVAL
DEPMETH
Depreciation Method
DEPMETHN
Depreciation Method Id
ESCAP
ESPROD
Products Escalation
ESRAW
ESLAB
ESUT
Utilities Escalation
START
PODE
POD
DESRET
END
GA
G and A Expenses
DTEP
OP
MT
Construction
Sales
A number will appear in this category only after the time allotted for all prior
phases (engineering, procurement, construction and startup phases) has
expired.
SP (Products
Sales)
449
S (Total Sales)
Expenses
Includes both capital and operating expenditures per period listed
below.
CAP (Capital
Costs)
(R)Revenue
Indicates, by period, the amount of money available after capital and
operating expenses have been paid. This number is obtained by subtracting
Capital Costs and Operating Costs from Sales.
DEP
Depreciation Expense: the amount by which the value of the capital
cost decreases each period. The Total Project Capital Cost is depreciated, via
the chosen depreciation method, over the useful Economic Life of the facility.
The Straight Line Method assumes that the item will depreciate by a constant
amount over its Economic life. When the Sum of the Years Method is used,
the depreciation expense decreases during each year of the projects useful
life. When the Double Declining Balance Method is used, the project is
depreciated in geometric increments. The Accelerated Cost Recovery System
450
assumes that the project begins operating in the second half of the first year,
rather than in the beginning of the first year.
E
Earnings Before Taxes: funds available after all expenses have been
paid. This number is obtained by subtracting the Depreciation and the
Interest Expenses from the Revenue.
TAX
Indicates amount owed to the government. This number is obtained by
multiplying the tax rate by Earnings Before Taxes.
NE
Net Earnings: funds available after taxes have been paid. This number
is obtained by subtracting the Taxes from the Earnings Before Taxes.
TED
Total Earnings: total cash available from project. This number is
computed by adding the Depreciation Expense to the Net Earnings. Since the
depreciation expense is a non-cash expense (no cash actually leaves the
facility in order to pay the depreciation expense) adding the depreciation to
the net earnings gives the total cash flow obtained from the project. Inclusion
of the Depreciation Expenses reduces the amount of taxable income.
TEX
Total Expenses (Excludes Taxes and Depreciation): the total expenses
of the project including capital, operating, and any interest expense.
FVI
Future Value of Cumulative Cash Inflows: sums the Sales received
through period n and indicates what the Sales would be if they had been
received in the current period. For example, the value in period 4 is what the
sales in periods 1-4 would have been if all of these funds had been received in
period 4.
PVI
Present Value of Cumulative Cash Inflows: the current worth of all the
cash received through period n. For example, the number in period 4
represents the value that the sales generated in periods 1 through 4 would be
if those sales were received in the first period. This number is obtained by
summing all of sales from prior time periods adding this amount to sales in
the current time period. Using the specified interest rate, this total is then
discounted back to the first time period.
PVOS Present Value of Cumulative Cash Outflows, Sales.
PVOP Present Value of Cumulative Cash Outflows, Products: the current
worth of all of the cash paid through period n. For example, the number in
period 4 represents the value that the expenses paid in periods 1 through 4
would be if those expenses were paid in the first period. This number is
obtained by summing all of the outflows (Capital Costs, Operating Costs,
Interest Expense) from prior time periods and adding this amount to the
outflows in the current period. Using the specified interest rate, this total is
then discounted back to the first time period .
PVO
Present Value of Cumulative Cashflows: represents PVOS or PVOP
depending on whether or not you entered a desired payout period. If you
entered a desired payout period, the basis for the cash outflow calculation is
the Forecasted Sales. Otherwise, the basis is Product Sales.
PV
Present Value of Cashflows: the present worth of the Total Earnings
received in the current period. For example, the number in period 4
represents the value that the Total Earnings generated in period 4 discounted
back to the first time period.
Final results are shown below:
451
NPV
Net Present Value: the current worth of all the Net Earnings received
through period n. For example, the number in period 4 represents the value
that the Net Earnings generated in periods 1 through 4 if those earnings were
received in the first period. This number is obtained by summing all of the Net
Earnings from prior time periods and adding this amount to the Net Earnings
in the current time period. Using the specified interest rate, this total is then
discounted back to the first time period. The sign of this value determines the
analysis result. If, in a certain period, the sign of the net present value is
negative, then the proposed investment appears not to be profitable, thus far.
For example, if the sign of the net preset value is negative in period 3, then
the project does not appear to be profitable during periods 1, 2, and 3.
However, if the sign is positive, then the project appears to be profitable,
from period 3 onward. If the net present value equals zero, then the project
does not incur any losses or gains (break-even point).
IRR
Internal Rate of Return: the rate at which the present value of all cash
flows is zero. It is also known as the Discounted Cash-Flow Rate of Return.
This value is calculated at the End Period for Economic Life of Project (i.e.,
Economic Life of Project and considering the length of EPC and Startup
Period). At the End Period for Economic Life of Project, it is assumed the
salvage value of the plant and the working capital are recouped. IRR is the
after-tax interest rate at which the organization can borrow funds and break
even at the end of the project life.
MIRR Modified Internal Rate of Return: the profitability of the project. The
internal rate of return is the interest rate which equates the present value of
a projects expected cash inflows to the present value of the projects
expected costs (or outflows). The internal rate of return for each period is
calculated by dividing the Present Value of Cumulative Inflows by the Present
Value of Cumulative Outflows and raising this to a power and multiplied by
100. Two criteria are critical in evaluating the internal rate of return. First, if
the sign of the rate of return is negative, the project appears not to be
profitable. If the sign is positive, then the project appears to be profitable. If
the rate of return equals zero then the project incurs no losses or gains
(break-even point). In addition, if the rate of return is greater than the rate
which could be obtained from other opportunities (i.e., investing in a bank),
then the project probably should be undertaken.
NRR Net Rate of Return: the profitability of the project. The net rate of
return for each period is calculated by dividing the Net Present Value by the
Present Value of Cumulative Outflows and then multiplying the result by 100.
PO
Payout Period: the expected number of years required to recover the
original investment in the project. This row will indicate the length of time
that the facility needs to operate in order to recover the initial capital
investment (total capital cost plus working capital). If a number is entered for
the Desired Payout Period, the spreadsheet will determine the amount of
Sales necessary to meet this desired payout.
ARR
Accounting Rate of Return: measures a projects contribution to the
firms net income. This number is the ratio of the projects Average Annual
Expected Net Income to its Average Investment. For example, the Average
Annual Expected Net Income for the fourth period is determined by summing
net earnings from periods 1 through 4 and divided by 4. The Average
Investment is determined by finding the Salvage Value, and adding this
452
number to the Total Project Cost and dividing this total by 2. If the accounting
rate of return is greater than one, then this is an indication that the project
might be a profitable undertaking. If the sign is negative, then the project
does not appear to be profitable. If this number equals zero then the project
incurs no losses or gains (break-even point).
PI
Profitability Index: shows the relative profitability of any project; it
shows the present value of the benefits relative to the present value of the
costs. For each period, this number is computed by dividing the Present Value
of the Cumulative Cash Inflows by the Present Value of the Cumulative Cash
Outflows. If the profitability index is greater than one, then the project
appears to be profitable. If this index is less than one, then the project
appears not to be profitable. If this number equals zero then the project
incurs no losses or gains (break-even point).
Analysis
Analysis results are shown by period. ( - ) indicates the project in the current
period appears unprofitable, while 0 indicates break-even status.
Depreciation Calculations
This section presents details on the calculation of depreciation.
Executive Summary
Executive Summary (EXECSUM.ICS) contains a project summary intended to
be reviewed by executives and other business decision makers.
453
CAPACITY
PLANT LOCATION
Location of plant
BRIEF DESCRIPTION
SCHEDULE
Start Date for
Engineering
Duration of EPC
Phase
Length of Start-up
Period
INVESTMENT
Currency Conversion
Desired Rate of
Return
PROJECT INFORMATION
Simulator Type
Version
Report File
Report Date
454
Economic Analysis
Type
Version
Project Directory
Analysis Date
Country basis
Project Type
Design code
Prepared By
455
In the Save As dialog box, type a name for the report file that will contain
your customized spreadsheet. For example, type Custom as shown
below.
Click Save.
456
In the Save As dialog box, type a name for the template file (for
example, summary) and click Save.
In the Template Entries section, click New Entry. In the Column Label
field, enter a label (for example, Project Name) for the first column on
your custom report spreadsheet. The Display Column box should
automatically display 1.
The Entry Definition section defines the data to be entered in the above
column. Select a file name in the Source box, then enter the column and
row of the source data.
457
10 Follow the same procedure (steps 7 - 8) to add more entries. You can use
a variety of sources. For example, adding the following entries will result
in a report template that uses all three of the previously discussed .ics
files as sources.
Column Label
Display
Column
Source
Source
Column
Source
Row
Project Name
projsum.ics
projsum.ics
61
Tax Rate
projsum.ics
112
Purchased
Equipment Cost
projsum.ics
172
Total Project
Cost
cashflow.ics
14
Total
Maintenance
Cost
cashflow.ics
40
Completion
Date for
Construction
execsum.ics
17
11 When all the template entries are added, return to the Report File tab
view. To the right of the Template File field, click Browse.
12 Select the newly created template file (for example, Summary.tra) and
click Open.
13 Click OK to exit the Reporting Assistant Options dialog box.
458
Aspen Process
Economic
AnalyzerWB_TRA.xls
The global copy of these files resides in the \Data\ICS folder. The files are
copied into the individual project folder when the investment analysis results
are invoked
Note: If copies of these files already exist within the projects, then they may
not be replaced and so may have to be replaced manually by the user. In the
case of ICARUS projects that are migrated from previous versions, any older
versions of these files will be saved as a backup and the newer versions will
be used.
The Run Summary worksheet in the Aspen Process Economic
AnalyzerWB.xls workbook is the sheet that can be customized by the user.
The Aspen Process Economic AnalyzerWB_TRA.xls file stores the
customizations that are in turn used by the Aspen Process Economic
AnalyzerWB.xls. The Aspen Process Economic AnalyzerWB_TRA.xls files
stores:
Any additional user defined functions (UDF) that the user wishes to
incorporate.
Edit the Template worksheet and add any user-defined functions that you
intend to use (see sections below).
459
Run the investment analysis and ensure that your changes are reflected in
the Run Summary worksheet.
The Template worksheet has three columns that you can modify.
This column
denotes
Dest
Column Heading
Source/Formula
Here is an example:
Dest
Column Heading
Source/Formula
Time
Now()
Project Name
'Project Summary'!C8
If you intend to define and use other functions, see the sections below.
for example,
460
Aspen Process Economic Analyzer generates the report based upon the
template created in the Reporting Assistant. The data that was entered under
List of Entries on the Reporting Assistant Options dialog box appears as
columns in the spreadsheet.
Every time Add Entry for Reporting Assistant is selected, the latest data is
entered on the bottom row of the report. This way, you can compare results.
461
Item Evaluation
Aspen Process Economic Analyzer allows you to run an evaluation on a single
component and view an Item Report. The type of Item Report displayed can
be selected in Preferences (see page 48).
X519H
Right-click on the component and click Item Report on the pop-up menu.
You can also click the Evaluate button on the Component Specifications
form to run the item evaluation and display the Item Report.
462
You can include multiple components in the Item Report: on the List view
(area level), select the desired components, right-click on one of the
components, and click Item Report on the pop-up window. The resulting
Item Report lists individually the summary data (cost or sizing) for each
selected component.
463
464
The following table lists the Equipment and Slots of those Equipment which
will be affected by mapping:
Important: When you do Map Based On Last Session, the slots listed on
this table WILL CHANGE.
Object Name
DAT MIXER
CpTangentTangentHeight
CpVesselDiameter
CpDesignTemperature
CpDesignGaugePressure CpLiquidVolume
DESIGN PRESS. -GAUGE
DESIGN TEMPERATURE
CAPACITY
DIAMETER
VESSEL T-T HEIGHT
CpTangentTangentHeight
CpVesselDiameter
CpDesignTemperature
CpLiquidVolume
DESIGN TEMPERATURE
CAPACITY
DIAMETER
VESSEL T-T HEIGHT
DAT REACTOR
CpTangentTangentHeight
CpVesselDiameter
CpDesignTemperature
CpDesignGaugePressure
CpLiquidVolume
DCP ANSI
CpPumpEfficiencyPercent
465
CpFluidSpecificGravity
CpFluidHead
CpDriverPower
CpDesignTemperature
CpDesignGaugePressure
CpLiquidFlowrate
Capacity
Head
Liquid specif. grav.
Driver power
Design temperature
Design press. -gauge
Pump fractional efficiency
Pump % efficiency
No. of identical items
DCP ANSI PLAST
CpPumpEfficiencyPercent
CpFluidSpecificGravity
CpFluidHead
CpDriverPower
CpDesignTemperature
CpDesignGaugePressure
CpLiquidFlowrate
Capacity
Head
Liquid specif. grav.
Driver power
Design temperature
Design press. -gauge
Pump fractional efficiency
Pump % efficiency
466
CpPumpEfficiencyPercent
CpFluidSpecificGravity
CpFluidHead
CpDriverPower
CpDesignTemperature
CpDesignGaugePressure
CpLiquidFlowrate
Capacity
Head
Liquid specif. grav.
Driver power
Design temperature
Design press. -gauge
Pump fractional efficiency
Pump % efficiency
No. of identical items
DCP CENTRIF
CpPumpEfficiencyPercent
CpFluidSpecificGravity
CpFluidHead
CpDriverPower
CpDesignTemperature
CpDesignGaugePressure
CpLiquidFlowrate
Capacity
Head
Liquid specif. grav.
Driver power
Design temperature
Design press. -gauge
Pump fractional efficiency
Pump % efficiency
No. of identical items
467
CpFluidHead
CpFluidSpecificGravity
CpPumpEfficiencyPercent
DCP GEN-SERV
CpPumpEfficiencyPercent
CpFluidSpecificGravity
CpFluidHead
CpDriverPower
CpDesignTemperature
CpDesignGaugePressure
CpLiquidFlowrate
Capacity
Head
Liquid specif. grav.
Driver power
Design temperature
Design press. -gauge
Pump fractional efficiency
Pump % efficiency
No. of identical items
DCP IN LINE
CpPumpEfficiencyPercent
CpFluidSpecificGravity
CpFluidHead
CpDriverPower
CpDesignTemperature
CpDesignGaugePressure
CpLiquidFlowrate
Capacity
Head
Liquid specif. grav.
Driver power
Design temperature
Design press. -gauge
Pump fractional efficiency
Pump % efficiency
No. of identical items
DDDTPACKED
CpTrayType
CpTangentTangentHeightTopSection
CpDiameterTopSection
CpDesignTemperatureTopSection
CpDesignPressureTopSection
CpTangentTangentHeightBottomSection
CpDiameterBottomSection
CpDesignTemperatureBottomSection
CpDesignPressureBottomSection
TRAY TYPE
BOTTOM DESIGN PRESS.
468
CpTrayType
CpTangentTangentHeightTopSection
CpDiameterTopSection
CpDesignTemperatureTopSection
CpDesignPressureTopSection
CpTangentTangentHeightBottomSection
CpDiameterBottomSection
CpDesignTemperatureBottomSection
CpDesignPressureBottomSection
TRAY TYPE
BOTTOM DESIGN PRESS.
BOTTOM DESIGN TEMP.
TOP DESIGN PRESSURE
TOP DESIGN TEMP.
TOP T-T HEIGHT
TOP SECT'N DIAMETER
BOTTOM T-T HEIGHT
BOTTOM SECTION DIAM.
DF ROTY DISK
CpSurfaceArea
SURFACE AREA
No. of identical items
DF ROTY DRUM
CpSurfaceArea
SURFACE AREA
No. of identical items
DGC CENTRIF
CpDesignTemperatureInlet
CpDesignGaugePressureInlet
CpDesignGaugePressureOutlet
CpActualGasFlowrateInlet
ACTUAL CAPACITY
INLET PRESSURE-GAUGE
EXIT PRESSURE -GAUGE
INLET TEMPERATURE
No. of identical items
DGC CENTRIF IG
469
CpActualGasFlowrateInlet
CpDesignGaugePressureOutlet
CpDesignTemperatureOutlet
CpDesignGaugePressureInlet
CpDesignTemperatureInlet
DGC RECIP MOTR
DUTY
[2]CpTubeWallThicknessSecondService
[3] CpTubeWallThicknessThirdService
CpTubeWallThicknessFirstService
CpTubeLength
CpNumberBays
CpNumberTubeRows
[3] CpDesignTemperatureInletThirdService
[2] CpDesignTemperatureInletSecondServ
CpDesignTemperatureInletFirstService
CpHeight
[3] CpDesignGaugePressureThirdService
[2] CpDesignGaugePressureSecondService
CpDesignGaugePressureFirstService
CpBayWidth
[2] CpBareTubeAreaSecondService
[3] CpBareTubeAreaThirdService
CpBareTubeAreaFirstService
No. of tube rows
Height
Number of bays
Bay width
Tube length
Tube thickness/BWG
Inlet temperature
Design press. -gauge
Bare tuo. of identical items
DHE FIXED T S
470
Shell pressure-gauge
Shell temperature
No. of tubes/shell
Extended tube length
Tube thickness
Tube pitch
No. of tube passes
Tube outside diam.
Shell diameter
CpTubeLengthExtended
CpNumberTubePasses
CpNumberTubesPerShell
CpNumberShells
CpShellDiameter
CpDesignGaugePressureShell
CpDesignTemperatureShell
CpHeatTransferArea
CpTubeOutsideDiameter
CpTubePitch
CpTubeDesignGaugePressure
CpDesignTemperatureTube
CpTubeWallThickness
Required surface area (with overdesign)
RAW SURFACE AREA
DUTY
DHE FLOAT HEAD
471
CpHeatTransferArea
CpTubeOutsideDiameter
CpTubePitch
CpTubeDesignGaugePressure
CpDesignTemperatureTube
CpTubeWallThickness
Required surface area (with overdesign)
RAW SURFACE AREA
DUTY
DHE PRE ENGR
DUTY
RAW SURFACE AREA
Required surface area (with overdesign)
CpTubeWallThickness
CpDesignTemperatureTube
CpTubeDesignGaugePressure
CpTubePitch
CpTubeOutsideDiameter
CpHeatTransferArea
CpDesignTemperatureShell
CpDesignGaugePressureShell
CpShellDiameter
CpNumberShells
CpNumberTubesPerShell
CpNumberTubePasses
CpTubeLengthExtended
Shell diameter
Tube outside diam.
No. of tube passes
472
Tube pitch
Tube thickness
Extended tube length
No. of tubes/shell
Shell temperature
Shell pressure-gauge
Tube temperature
Tube pressure -gauge
Number of shells
Surface area
No. of identical items
DHE U TUBE
473
CpLiquidVolume
CpDesignGaugePressure
CpDesignTemperature
CpVesselDiameter
CpTangentTangentLength
DHT JACKETED
CpTangentTangentLength
CpVesselDiameter
CpDesignTemperature
CpDesignGaugePressure
CpLiquidVolume
DESIGN PRESS. -GAUGE
DESIGN TEMPERATURE
CAPACITY
DIAMETER
VESSEL T-T LENGTH
CpTangentTangentLength
CpVesselDiameter
CpDesignTemperature
CpDesignGaugePressure
CpLiquidVolume
DESIGN PRESS. -GAUGE
DESIGN TEMPERATURE
CAPACITY
DIAMETER
VESSEL T-T LENGTH
DRB KETTLE
DRB THERMOSIPH
474
CpDesignGaugePressureShell
CpDuty
SHELL PRESSURE-GAUGE
TUBE PRESSURE -GAUGE
SHELL TEMPERATURE
TUBE TEMPERATURE
DUTY
NO. OF IDENTICAL ITEMS
surface area
DRB U TUBE
surface area
NO. OF IDENTICAL ITEMS
DUTY
TUBE TEMPERATURE
SHELL TEMPERATURE
TUBE PRESSURE -GAUGE
SHELL PRESSURE-GAUGE
CpDuty
CpDesignGaugePressureShell
CpDesignTemperatureShell
CpHeatTransferArea
CpTubeDesignGaugePressure
CpDesignTemperatureTube
Required surface area (with overdesign)
RAW SURFACE AREA
DTW DC HE TW
CpDesignGaugePressure
CpDesignTemperature
CpVesselDiameter
CpTangentTangentHeight
DESIGN PRESS. -GAUGE
DESIGN TEMPERATURE
Diameter
Vessel t-t height
DTW PACKED
CpTangentTangentHeight
CpTrayType
CpTotalPackingHeight
CpVesselDiameter
CpDesignTemperature
CpDesignGaugePressure
DESIGN PRESS. -GAUGE
DESIGN TEMPERATURE
TRAY TYPE
Diameter
Vessel t-t height
Total packing height
DTW TRAYED
CpTangentTangentHeight
CpTrayType
475
CpTraySpacing
CpNumberTrays
CpVesselDiameter
CpDesignTemperature
CpDesignGaugePressure
DESIGN PRESS. -GAUGE
DESIGN TEMPERATURE
NUMBER OF TRAYS
TRAY TYPE
Diameter
Vessel t-t height
tray spacing
DVT CONE BTM
CpVesselHeight
CpVesselDiameter
CpDesignTemperature
CpDesignGaugePressure
CpLiquidVolume
DESIGN PRESS. -GAUGE
DESIGN TEMPERATURE
CAPACITY
DIAMETER
HEIGHT
DVT CYLINDER
CpVesselDiameter
CpTangentTangentHeight
CpDesignTemperature
CpDesignGaugePressure
CpLiquidVolume
CpVesselDiameter
CpDesignTemperature
CpDesignGaugePressure
CpGasVolume
DESIGN PRESS. -GAUGE
DESIGN TEMPERATURE
CAPACITY
DIAMETER
DVT JACKETED
CpTangentTangentHeight
CpVesselDiameter
CpDesignTemperature
CpDesignGaugePressure
CpLiquidVolume
DESIGN PRESS. -GAUGE
DESIGN TEMPERATURE
CAPACITY
DIAMETER
VESSEL T-T HEIGHT
CpVesselHeight
476
CpVesselDiameter
CpDesignTemperature
CpSolidVolume
DESIGN TEMPERATURE
CAPACITY
DIAMETER
HEIGHT
DVT MULTI WALL
CpTangentTangentHeight
CpVesselDiameter
CpDesignTemperature
CpDesignGaugePressure
CpLiquidVolume
DESIGN PRESS. -GAUGE
DESIGN TEMPERATURE
CAPACITY
DIAMETER
VESSEL T-T HEIGHT
DVT SPHERE
CpVesselDiameter
CpDesignTemperature
CpDesignGaugePressure
CpLiquidVolume
DESIGN PRESS. -GAUGE
DESIGN TEMPERATURE
CAPACITY
DIAMETER
DVT SPHEROID
CpVesselDiameter
CpDesignTemperature
CpDesignGaugePressure
CpLiquidVolume
DESIGN PRESS. -GAUGE
DESIGN TEMPERATURE
CAPACITY
DIAMETER
DVT STORAGE
CpVesselHeight
CpVesselDiameter
CpDesignTemperature
CpDesignGaugePressure
CpLiquidVolumeGallonsBarrels
DESIGN PRESS. -GAUGE
DESIGN TEMPERATURE
CAPACITY
DIAMETER
HEIGHT
EAC CENTRIF M
477
INLET PRESSURE-GAUGE
ACTUAL CAPACITY
CpActualGasFlowrate
CpDesignGaugePressureOutlet
CpDesignGaugePressureInlet
CpDesignTemperatureInlet
EAC CENTRIF T
EAC SINGLE 1 S
EAC SINGLE 2 S
478
CpGasFlowrate
CAPACITY
VOLUME
CpCellVolume
CpTemperature
CpFluidSpecificGravity
CpFluidHead
CpDriverPower
Head
Liquid specif. grav.
Driver power
Temperature
No. of identical items
ECP TURBINE
CpTemperature
CpFluidSpecificGravity
CpFluidHead
CpDriverPower
Head
Liquid specif. grav.
Driver power
Temperature
No. of identical items
ECR BRADFORD
CpCrusherFlowrate
CpDriverPower
DRIVER POWER
PRODUCT SIZE
MANTLE DIAMETER
RATE
ECR CONE
CpCrusherFlowrate
CpProductSize
CpMantleDiameter
CpDriverPower
DRIVER POWER
PRODUCT SIZE
MANTLE DIAMETER
479
RATE
ECR ECCENTRIC
CpCrusherFlowrate
CpProductSize
CpMantleDiameter
CpDriverPower
DRIVER POWER
PRODUCT SIZE
MANTLE DIAMETER
RATE
ECR GYRATOR
CpCrusherFlowrate
CpProductSize
CpMantleDiameter
CpDriverPower
DRIVER POWER
PRODUCT SIZE
MANTLE DIAMETER
RATE
RATE
MANTLE DIAMETER
PRODUCT SIZE
DRIVER POWER
CpDriverPower
CpMantleDiameter
CpProductSize
CpCrusherFlowrate
ECR JAW
CpCrusherFlowrate
CpProductSize
CpMantleDiameter
CpDriverPower
DRIVER POWER
PRODUCT SIZE
MANTLE DIAMETER
RATE
ECR PULVERIZER
CpFlowrate
CpProductMeshSize
CpProductFeedSize
CpMantleDiameter
CpDriverPower
DRIVER POWER
PRODUCT SIZE
MANTLE DIAMETER
RATE
RATE
MANTLE DIAMETER
PRODUCT SIZE
DRIVER POWER
480
CpMantleDiameter
CpDriverPower
CpProductSize
CpCrusherFlowrate
ECR ROLL RING
CpCrusherFlowrate
CpProductSize
CpMantleDiameter
CpDriverPower
DRIVER POWER
PRODUCT SIZE
MANTLE DIAMETER
RATE
ECR ROTARY
CpProductSize
CpMantleDiameter
CpDriverPower
CpCrusherFlowrate
DRIVER POWER
PRODUCT SIZE
MANTLE DIAMETER
RATE
ECR S IMPACT
RATE
MANTLE DIAMETER
PRODUCT SIZE
DRIVER POWER
CpDriverPower
CpMantleDiameter
CpProductSize
CpCrusherFlowrate
RATE
MANTLE DIAMETER
PRODUCT SIZE
DRIVER POWER
CpCrusherFlowrate
CpDriverPower
CpMantleDiameter
CpProductSize
ECR S ROLL LT
RATE
MANTLE DIAMETER
PRODUCT SIZE
DRIVER POWER
CpDriverPower
CpMantleDiameter
CpProductSize
CpCrusherFlowrate
RATE
MANTLE DIAMETER
481
PRODUCT SIZE
DRIVER POWER
CpDriverPower
CpMantleDiameter
CpProductSize
CpCrusherFlowrate
ECR SAWTOOTH
CpCrusherFlowrate
CpProductSize
CpMantleDiameter
CpDriverPower
DRIVER POWER
PRODUCT SIZE
MANTLE DIAMETER
RATE
RATE
MANTLE DIAMETER
PRODUCT SIZE
DRIVER POWER
CpDriverPower
CpMantleDiameter
CpProductSize
CpCrusherFlowrate
ECRYBATCH VAC
CpLiquidVolume
CAPACITY
No. of identical items
ECRYMECHANICAL
CpLength
LENGTH
No. of identical items
ECRYOSLO
CpCrystallizerRate
RATE
No. of identical items
CpDriverPower
DRIVER POWER
No. of identical items
482
ECT DISK
CpCentrifugeDiameter
DIAMETER
No. of identical items
ECT INVERTING
CpCentrifugeDiameter
DIAMETER
No. of identical items
CpBowlLength
CpBowlDiameter
DIAMETER
INSIDE DIAMETER
No. of identical items
CpCentrifugeDiameter
CpCentrifugeCapacity
CAPACITY
DIAMETER
No. of identical items
ECT TUBULAR
CpBowlDiameter
DIAMETER
No. of identical items
ECT VIBRATORY
CpProductFeedSize
CpScreenDiameter
DIAMETER
SCREEN DIAMETER
No. of identical items
ED ATMOS TRAY
ED PAN
CpSurfaceArea
AREA
No. of identical items
483
ED SPRAY
CpEvaporationRate
EVAPORATION RATE
No. of identical items
ED VAC TRAY
CpSurfaceArea
SURFACE AREA
No. of identical items
EDC CYCLONE
CpCycloneDiameter
DIAMETER
No. of identical items
CpGasFlowrate
FLOW RATE
No. of identical items
EDC WASHERS
SURFACE AREA
No. of identical items
CpTrayArea
SURFACE AREA
No. of identical items
CpTrayArea
SURFACE AREA
No. of identical items
CpTrayArea
SURFACE AREA
No. of identical items
EE FALL FILM
EE FORCED CIR
CpHeatTransferArea
Heating area
No. of identical items
EE LONG TUBE
CpTubeMaterial
484
Mat'l of construction
CpHeatTransferArea
Tube material
Heating area
No. of identical items
EE LONG VERT
EE STAND HOR
EE STAND VERT
EF CARTRIDGE
CpLiquidFlowrate
FLOW RATE
No. of identical items
EF LEAF DRY
EF LEAF WET
EF PLATE FRAM
EF SCROLL
CpProductFeedSizeSelection
FEED SIZE
No. of identical items
EF SEWAGE
CpSurfaceArea
SURFACE AREA
No. of identical items
EF SPARKLER
CpSurfaceArea
SURFACE AREA
No. of identical items
EF TUBULAR
CpLiquidFlowrate
FLOW RATE
No. of identical items
EF WHITEWATER
CpLiquidFlowrate
FLOW RATE
No. of identical items
EFU BOX
CpStandardGasFlowrate
CpProcessType
CpDuty
CpDesignTemperature
485
CpDesignGaugePressure
No. of identical items
Duty
Standard gas flow
Process type
Design temperature
Design press. -gauge
EFU HEATER
CpStandardGasFlowrate
CpProcessType
CpDuty
CpDesignTemperature
CpDesignGaugePressure
No. of identical items
Duty
Standard gas flow
Process type
Design temperature
Design press. -gauge
EFU PYROLYSIS
CpDesignGaugePressure
CpDesignTemperature
CpDuty
CpProcessType
CpStandardGasFlowrate
No. of identical items
Duty
Standard gas flow
Process type
Design temperature
Design press. -gauge
EFU REFORMER
CpStandardGasFlowrate
CpProcessType
CpDuty
CpDesignTemperature
CpDesignGaugePressure
No. of identical items
Duty
Standard gas flow
Process type
Design temperature
Design press. -gauge
EFU VERTICAL
CpDesignGaugePressure
CpDesignTemperature
CpDuty
CpProcessType
CpStandardGasFlowrate
No. of identical items
486
Duty
Standard gas flow
Process type
Design temperature
Design press. -gauge
EGC RECIP GAS
CpLiquidFlowrate
CpDriverPower
Flow rate
Driver power
No. of identical items
EGP GEAR
CpLiquidFlowrate
CpDriverPower
Flow rate
Driver power
No. of identical items
487
Tube length
Heat transfer area
No. of identical items
EHE HEATER ELC
EHE HEATER-ELC
CpHeaterPower
Power output
No. of identical items
EHE HEATER-STM
EHE JACKETED
DESIGN TEMPERATURE
DESIGN PRESS. -GAUGE
Surface area
No. of identical items
CpDesignGaugePressure
CpDesignTemperature
CpSurfaceArea
CpHeatTransferArea
Required surface area (with overdesign)
488
EHE SHELL+TUBE
EHE SUC-HEATER
489
EM ATTRITION
CpCrusherFlowrate
CpProductSize
CpMantleDiameter
CpDriverPower
DRIVER POWER
PRODUCT SIZE
MANTLE DIAMETER
RATE
EM AUTOGENOUS
CpSolidFlowrate
CpProductSize
CpDiameterInside
CpDriverPower
DRIVER POWER
PRODUCT SIZE
MANTLE DIAMETER
RATE
EM BALL MILL
CpSolidFlowrate
CpMantleDiameter
CpProductSize
CpDiameterInside
CpDriverPower
DRIVER POWER
PRODUCT SIZE
MANTLE DIAMETER
RATE
EM MIKRO PULV
RATE
MANTLE DIAMETER
PRODUCT SIZE
DRIVER POWER
CpDriverPower
CpMantleDiameter
CpProductSize
CpCrusherFlowrate
EM MIKRO-PULV
CpCrusherFlowrate
CpProductSize
CpMantleDiameter
CpDriverPower
DRIVER POWER
490
PRODUCT SIZE
MANTLE DIAMETER
RATE
EM ROD CHARGER
RATE
MANTLE DIAMETER
PRODUCT SIZE
DRIVER POWER
CpDriverPower
CpMantleDiameter
CpRodDiameter
CpProductSize
CpSolidFlowrate
EM ROD MILL
CpSolidFlowrate
CpProductSize
CpDiameterInside
CpMantleDiameter
CpDriverPower
DRIVER POWER
PRODUCT SIZE
MANTLE DIAMETER
RATE
EM ROD-CHARGER
CpSolidFlowrate
CpProductSize
CpRodDiameter
CpMantleDiameter
CpDriverPower
DRIVER POWER
PRODUCT SIZE
MANTLE DIAMETER
RATE
EM ROLLER
EP DIAPHRAGM
CpTemperature
CpFluidSpecificGravity
CpFluidHead
CpLiquidFlowrate
CpDriverPower
Liquid specif. grav.
Head
Temperature
Flow rate
Driver power
No. of identical items
EP DUPLEX
CpTemperature
CpFluidSpecificGravity
CpFluidHead
CpLiquidFlowrate
491
CpDriverPower
Liquid specif. grav.
Head
Temperature
Flow rate
Driver power
No. of identical items
EP RECIP MOTR
EP ROTARY
CpTemperature
CpFluidSpecificGravity
CpFluidHead
CpLiquidFlowrate
CpDriverPower
Liquid specif. grav.
Head
Temperature
Flow rate
Driver power
No. of identical items
EP SIMPLEX
CpTemperature
CpFluidSpecificGravity
CpFluidHead
CpLiquidFlowrate
CpDriverPower
Liquid specif. grav.
Head
Temperature
Flow rate
Driver power
No. of identical items
EP SLURRY
CpTemperature
CpFluidSpecificGravity
CpFluidHead
CpLiquidFlowrate
CpDriverPower
Liquid specif. grav.
492
Head
Temperature
Flow rate
Driver power
No. of identical items
EP TRIPLEX
CpTemperature
CpFluidSpecificGravity
CpFluidHead
CpLiquidFlowrate
CpDriverPower
Liquid specif. grav.
Head
Temperature
Flow rate
Driver power
No. of identical items
ERD DIRECT
CpSurfaceArea
SURFACE AREA
No. of identical items
ERD INDIRECT
CpSurfaceArea
SURFACE AREA
No. of identical items
ERD JAC-VACUUM
CpDryerCapacity
CAPACITY
No. of identical items
ERD VACUUM
CpDryerCapacity
CAPACITY
No. of identical items
ETDSATM SYSTEM
ETDSATM-SYSTEM
CpTraySurfaceArea
TRAY SURFACE
No. of identical items
ETDSTURBO
CpTraySurfaceArea
TRAY SURFACE
No. of identical items
ETDSVAC SYSTEM
ETDSVAC-SYSTEM
CpTraySurfaceArea
TRAY SURFACE
No. of identical items
493
ETDSVACUUM
CpTraySurfaceArea
TRAY SURFACE
No. of identical items
ETURCONDENSING
CpPowerOutput
Power output
No. of identical items
ETURGAS
CpPowerOutput
Power output
No. of identical items
ETURNON COND
ETURNON-COND
CpPowerOutput
Power output
No. of identical items
EVP MECH-BOOST
CpActualGasFlowrate
Actual capacity
No. of identical items
EVP MECH-BOOST
CpActualGasFlowrate
Actual capacity
No. of identical items
EVP MECHANICAL
CpDriverPower
CpActualGasFlowrate
Driver power
Actual capacity
No. of identical items
EVP WATER-SEAL
CpActualGasFlowrate
Actual capacity
No. of identical items
EVS HUMMER
CpNumberDecks
CpSurfaceArea
NUMBER OF DECKS
AREA
No. of identical items
CpWidth
CpLength
WIDTH
LENGTH
No. of identical items
494
EVS SIFTER 1
EVS SIFTER 2
EVS SIFTER 3
EVS SIFTER-1
CpScreenDiameter
DIAMETER
No. of identical items
EVS SIFTER-2
CpScreenDiameter
DIAMETER
No. of identical items
EVS SIFTER-3
CpScreenDiameter
DIAMETER
No. of identical items
CpWidth
CpLength
WIDTH
LENGTH
No. of identical items
CpLength
CpWidth
WIDTH
LENGTH
No. of identical items
CpLiquidVolume
CpTemperature
CpVesselHeight
CpDesignGaugePressure
CpVesselDiameter
GAUGE PRESSURE
TEMPERATURE
HEIGHT
VOLUME
DIAMETER
CpLiquidVolume
CpTemperature
CpVesselHeight
CpDesignGaugePressure
CpVesselDiameter
GAUGE PRESSURE
TEMPERATURE
HEIGHT
495
VOLUME
DIAMETER
EWFETHIN FILM
EWFEWFE SYSTEM
Overall U
Fin Thickness
Duty
CpTubePitch
CpTubeOutsideDiameterFirstService
CpTubeLength
CpTubeFinHeight
CpPowerPerFan
CpNumberTubeRows
CpNumberBays
CpFinPitch
CpBayWidth
CpBareTubeAreaFirstService
Overall Heat transfer Coefficient
CpSpecificHeatRatio
CpDriverPower
CpCompressibilityFactorOutlet
CpCompressibilityFactorInlet
CpActualGasFlowrateInlet
CpSpecificHeatRatio
CpPowerOutput
CpCompressibilityFactorInlet
CpActualGasFlowrateInlet
496
CpExchangerDepth
CpExchangerLength
CpExchangerVolume
CpExchangerWidth
CpRemarks2 :
CpMaterialCostPerUnit
CpLaborHoursPerUnit
CpLiquidFlowrate
CpFluidViscosity
CpFluidSpecificGravity
CpFluidHead
CpViscosityCS
CpLiquidFlowrate
CpFluidSpecificGravity
CpFluidHead
CpActualGasFlowrate
CpLiquidFlowrate
CpFluidViscosity
CpFluidSpecificGravity
CpFluidHead
497
498
Index
.
.D01 file extension, Icarus Object
files 128
.EML file extension, importing cost
libraries 292
.UCL file extension, importing cost
libraries 292
2
2/3 rule 89, 238
A
About command
Help menu 42
Absolute Basis
streams 114, 117, 122124, 178
Accelerated Cost Recovery System
(ACRS)
Investment Parameters,
Depreciation Method 104
Accounting Rate of Return (ARR)
Cashflow spreadsheet 453
ACRS See Accelerated Cost
Recovery System (ACRS)
Activate Custom Model option
Preferences 49
Add Area command 182
Add button
Pipe Details form 193
Wage Rate Info form 73
Add Entry for Reporting Assistant
Run menu 39, 462
Add Project Component command
183
Add Stream button
toolbar 37, 178
Index
499
Index
B
Backup options
Preferences 49
Base Design Value
Analyzer Economics Module
(AEM) 398, 399
Base Stream
Develop Stream specifications
form 117
Develop Streams dialog box
122124, 178
BaseCase, default scenario name
19
Basis
Map dialog box 153
streams 114, 117, 124, 122
124, 178
Basis for Capital Costs
construction workforce 7073
indexing 74
input units of measure 59
introduction 58
libraries 125, 126
output (reports) units of
measure customization 61
selecting defaults 126
BFD See Block Flow Diagram (BFD)
BinCacheDir
location, Preferences 50
Block Flow Diagram (BFD)
displaying 146
Drag & Find feature 147
introduction 146
right-click commands 148
View menu 150
Zoom commands 148149
Bottom sump height
500
C
Cached project information 44
Cancel button
Develop Stream specifications
form 116
Preferences dialog box 47
Capacity
changing 295
Capacity over-design factor See
Pump overdesign factor
Capital cost parameters
Project Input worksheet 403
Capital Costs
Cashflow spreadsheet 451
depreciation 103104, 451
errors 387
escalation 104, 447, 450
Executive Summary spreadsheet
455
Investment Parameters 105
Project Summary spreadsheet
444, 446447
reports 48, 435, 437
toolbar button 37, 406, 431
View command 40, 150, 173,
406, 431
Capital investment
Project Input worksheet 402
Capture worksheet
Analyzer Economics Module
(AEM) 393
Cascade command
Window menu 28, 42
Cash Flow Summary
reports, Icarus Editor 437
Cash flows
Project Input worksheet 401
Cashflow spreadsheet 449454
CASHFLOW.ICS
Cashflow spreadsheet 449454
ChemCAD
map specs 83
Index
501
Index
D
Data trending
Aspen Icarus Reporter 426
DC_V worksheet
Analyzer Economics Module
(AEM) 390
Decision Analyzer command
Run menu 388
Decision Analyzer dialog box 388
Decision Center worksheet
Analyzer Economics Module
(AEM) 390
Delete button
Pipe Details form 193
Delete Mappings command 158
Deleting
502
areas 205
components 204
mappings 158
projects and project scenarios 43
Density
Develop Stream specifications
form 118
Depreciation expense
Cashflow spreadsheet 451
Depreciation method
Project Input worksheet 404
Depreciation Method
Cashflow spreadsheet
(CASHFLOW.ICS) 450, 451
Investment Parameters 103
Project Summary spreadsheet
(PROJSUM.ICS) 445
Design code
Executive Summary spreadsheet
456
Project Summary spreadsheet
443
Design Code
General Specs 65
Design Criteria
libraries 125
selecting defaults 126
Design Criteria specifications 86
Design pressure
applying 2/3 rule for 90, 238
design criteria specifications 87
sizing agitators 233
sizing heat exchangers 239
sizing towers 249
utility specifications 101
Design temperature
design criteria specifications 88
sizing agitators 233
sizing heat exchangers 239
sizing towers 249
utility specifications 100
Desired Rate of Return
Cashflow spreadsheet
(CASHFLOW.ICS) 450
Executive Summary spreadsheet
(EXECSUM.ICS) 455
Investment Parameters
specifications 103
Project Summary
(PROJSUM.ICS) spreadsheet
445
Index
E
Earnings
Cashflow spreadsheet 452
Economic Life of Project
503
Index
504
F
Facility Type
Investment Parameters 105
FATAL message 387
Figures worksheet
Analyzer Economics Module
(AEM) 397
File menu
Aspen Icarus Reporter menu bar
408
IPE menu bar 38
Fit into one page
Zoom dialog box 149
Float in Main Window command 35
Flow rate units
product specifications 113
Fluid classes
utility streams 99
Foaming tendency
trayed towers, design criteria 92
Foreman wage rate
general wage rates 73
Form work
civil installation bulk 194
Fraction basis 119
Freeze Content button
Properties Window 34
Freight
General Specs 64
Fuel
operating unit costs
specifications 108
Furnace fractional efficiency
heat exchanger design criteria 89
FVI (Future Value of Inflows)
Cashflow spreadsheet 452
Index
G
G and A Expenses
Cashflow spreadsheet
(CASHFLOW.ICS) 450
Investment Parameters 105
Project Summary spreadsheet
(PROJSUM.ICS) 446
Galvanizing (for steel)
paint installation bulk 198
General and administrative costs
Investment Parameters 105
Project Summary spreadsheet
(PROJSUM.ICS) 446
General investment parameters
Project Input worksheet 404
General Project Data
creating a new project scenario
21
project specifications 57
General rates
construction workforce 7073
General Specs 6265
Gray borders
Component Specifications form
187
Green borders
Component Specifications form
187
Grid Settings command
View menu, PFD 174, 175
Grids
viewing in Block Flow Diagram
(BFD) 151
viewing in Process Flow Diagram
(PFD) 175
Grids Visible command
View menu, BFD 151
Grout
civil installation bulk 194
H
Heat exchangers
design criteria specifications 90
sizing 238240
utility specifications 98
Help menu 42
Helper wage rate
general wage rates 72
HETP (height equivalent of a
theoretical plate)
packed towers, design criteria 91
505
I
Icarus Editor
printing report 433
printing report section 432
reviewing results 431440
toolbar 432
Tools menu 41
Icarus Evaluation Engine (IEE)
241, 430
Icarus interface 2636
Icarus Object files 128
Icarus Project Component
Selection dialog box 156, 280,
285, 288
IEE See Icarus Evaluation Engine
(IEE)
Import command
File menu 38
Libraries view, Palette 127, 292
Import Connected Streams option
Preferences 49
Import Data command
File menu, Aspen Icarus Reporter
408
File menu, Aspen Icarus
Reporter 429
Import Installation Bulks option
Preferences 49
Import Selection dialog box
Aspen Icarus Reporter 429
Importing
areas 200
Index
components 200
project from previous version
2224
scenarios 201
specification files 127
Inch-Pound (IP), units of measure
20, 126, 127
Incomplete items 31
Indexing
Project Basis specifications 74
Indicating signal
instrumentation loop 196
Indirect costs
general wage rates 71
Project Summary spreadsheet
447
reports 447
Unit Cost Library (UCL) 276
Indirects
general wage rages 71
INFOmational message 387
Input Units of Measure
Specifications dialog box 20,
59
Installation bulks
accessing 188
civil 194
duct 193
electrical 197
instrumentation 194
insulation 197
introduction 188
material man-hour additions 191
paint 198
pipe details 191
pipe spec 191
Preferences 48
steel 194
Instrument air
operating unit costs
specifications 108
utility costs, Project Summary
spreadsheet 449
Instrument volumetric model 194
196
Instrumentation
installation bulk 194
loop adjustments 196197
material costs and man-hours
189
Insulation
installation bulk 197
material costs 189
506
J
JIS
pressure vessel design code
selection 65
Job Number field 58
Junction boxes
instrumentation loop 196
L
Labor cost per unit
Unit Cost Library (UCL) 284
Labor hours per unit
Unit Cost Library (UCL) 284
Labor Unit Costs
Index
M
Magnification
Aspen Icarus Reporter 410
Block Flow Diagram (BFD) 148
149
507
Main product
Project Summary spreadsheet
448
Main Window
display options 35
interface, default position 26
printing 38
understanding 2829
Management reports 418421
Man-hour indexing 74
Manpower Productivity Expert
(MPE)
Tools menu 41
Manufacturing cost parameters
Project Input worksheet 403
Map All Items option
Map dialog box 153
Map command
pop-up menu 152
Map dialog box 152
Map Items button
toolbar 151
Map Items command
Run menu 39, 151
Map Selected Item(s) option
Map dialog box 153
Map Unsupported Models To
Quoted Cost Item
Preferences, Process tab 49
Mapping simulator models
instructions 151158
specifications 81
units of measure mapping specs
7780
unsupported models 49, 82
Mass flow
Develop Stream specifications
form 118
Material adjustments
indexing, area level 199, 200
Material and man-hour additions
installation bulks 191
Material and man-hour
adjustments
installation bulks 189, 208
Material and man-hour indexing 74
Material cost per unit
Unit Cost Library (UCL) 284
Material costs
indexing 74
Material Index Info form 75
Material streams
product specifications 111
Index
N
Net Earnings
Cashflow spreadsheet 452
Net Present Value (NPV)
Cashflow spreadsheet 453
Statements worksheet 396
Status worksheet 393
Net Return Rate (NRR)
Cashflow spreadsheet 453
New command
File menu 18, 22, 38
New Component Information dialog
box 184
New Project button
toolbar 18, 37
NPV (Net Present Value)
Cashflow spreadsheet 453
NRR (Net Return Rate)
Cashflow spreadsheet 453
Number of Periods for Analysis
Investment Parameters 103
Number of shifts 71
Project Input worksheet 403
508
O
OK button
Develop Stream specifications
form 116
Installation Bulks form 48, 189
Mat'l Man-hour Adjustments
form 190
Open button
toolbar 24, 37
Open command
File menu 24, 38
Palette Projects view 25
Open Existing Project dialog box 24
Open Workbook command
File menu, Aspen Icarus Reporter
408, 425
Opening an existing project 24
Operating and Maintenance Labor
Escalation
Investment Parameters 104
Project Summary spreadsheet
(PROJSUM.ICS) 445
Operating charges
Cashflow spreadsheet 450
Investment Parameters 105
Project Input worksheet 403
Project Summary spreadsheet
444, 446
Operating costs
Cashflow spreadsheet 451
Figures worksheet 397
introduction to IPE 12
Investment Parameters 105
product specifications needed to
evaluate 113
Project Summary spreadsheet
444
raw material specifications
needed to evaluate 109
Operating Hours per Period
Investment Parameters 106
Project Summary spreadsheet
444
Operating labor and maintenance
Project Input worksheet 403
Operating labor and maintenance
costs
Cashflow spreadsheet 450
Investment Parameters 105, 107
Index
P
P&ID button 191, 194
Packed towers
design criteria specifications 91
sizing 254, 255
Paint
material costs 189
specs, areas 199, 200
Palette
Components view 33, 183
cost libraries 277294
deleting a project from 44
description 3234
Docking and undocking 35
dragging components from 183
floating in Main Window 35
509
hide/display 33
interface, default position 26
Libraries view 32, 125129,
277294
opening projects 25
Projects view 25, 32, 33, 44, 46,
51
Recent Items folder 183
specification libraries 125
unlocking projects from 46
View menu 40, 173
Paste button
toolbar, Icarus Editor 433
Paste command
project components 202, 204
Patents and royalties
Project Input worksheet 403
Payout period
Cashflow spreadsheet 453
Period Description
Investment Parameters 102
Phase durations
Project Input worksheet 403
Phases
Stream Input worksheet 405
PI (Profitability Index)
Cashflow spreadsheet 454
Pile types 67
Pipe Details installation bulk 191
Pipe Spec installation bulk 191
Pipe volumetric model 192193
Piping
installation bulks 191193
material costs and man-hours
189
volumetric model 192
Piping and Instrumentation
Drawings (P&ID) manual 191,
194
Piping specifications
areas 199, 200
Plant bulks
component categories 181
difference from installation bulks
188
Plant capacity
changing 295
Plant location
changing 295
Plant Overhead
Cashflow spreadsheet 450
Investment Parameters 105
Index
510
Pro/II
models used in sizing towers 243
R/R minimum 90
simulator report preparation
141142
Problem description
SimSci report preparation 142
Process Complexity
contingency affected by 66
General Specs 63
Process connection
intrumentation loop 196
Process Control
General Specs 64
Process Description
contingency affected by 66
equipment design allowance
affected by 66
General Specs 63
Process Design specifications 77
101
Process equipment 181
Process Flow Diagrams (PFD) 171
180
Process Fluids
Investment Parameters 106
Process options
Preferences 49
Process Stream field
product specifications 113
raw material specifications 110
Process vessel height to diameter
ratio
design criteria specifications 94
vessel sizing procedure 259, 261
Product escalation
Project Input worksheet 404
Product sales
per hour, Project Summary
spreadsheet 448
per period, Project Summary
spreadsheet 448
total, Project Summary
spreadsheet 446
Product specifications
investment analysis
specifications 111114
libraries 126
selecting defaults 126
Product Support on the Web
command
Help menu 42
Production
Index
511
Index
unlocking 45
Project Schedule Data Sheet
reports, Icarus Editor 438
Project Summary
reports, Icarus Editor 435
Project Summary spreadsheet
(PROJSUM.ICS) 442449
Project Title
General Project Data 58
Project Summary spreadsheet
443
Project Type
contingency affected by 66
Executive Summary spreadsheet
456
General Specs 63, 64
Project Summary spreadsheet
443
Project view 27
Projects
copying 46
creating 1822
deleting 43
opening existing 24
view 32, 33
PROJSUM.ICS
investment analysis 442449
Prompts
Preferences 47
Properties Window
description 34
Docking and undocking 35
floating in Main Window 35
Freeze Content button 34
interface, default position 26
relationship to specifications
form 34, 186
View menu 40, 173
PROVISION See SimSci's Pro/II
with PROVISION
Pump overdesign factor
design criteria specifications 88,
241
sizing procedures 241
Pumps
design criteria specifications 88
sizing 214
PV (Present Value)
Cashflow spreadsheet 452
PVI (Present Value of Inflows)
Cashflow spreadsheet 452
PVO (Present Value of Outflows)
Cashflow spreadsheet 452
512
Q
Question mark in Status column
component specifications 157,
186
Quoted cost item
mapping overhead/bottoms split
to 245
mapping unsupported models to
49
Quoted cost items
mapping unsupported models to
81
Quoted equipment 181, 188
R
Rate field
product specifications 113
raw material specifications 110
Rate Units field
product specifications 113
raw material specifications 110
Raw material
costs, Cashflow spreadsheet 450
costs, Executive Summary
spreadsheet 455
costs, project specifications 111
costs, Project Summary
spreadsheet 446, 447
escalation 104, 445, 450
project specifications 108111
Raw Material Escalation
Cashflow spreadsheet 450
Investment Parameters 104
Project Summary spreadsheet
445
Raw Material Specifications
investment analysis, project
basis 108111
libraries 126
selecting defaults 126
Raw materials
escalation 404
Stream Input worksheet 405
Rebar
Index
513
S
Sales
Cashflow spreadsheet 450
Salvage Project As dialog box 45
Salvage Value
Project Input worksheet 404
Salvage Value (Percent of Initial
Capital Cost)
Cashflow spreadsheet 450
impact on depreciation 103
Investment Parameters 103
Project Summary spreadsheet
445
recouped 453
Salvaging project scenarios 44
Save As command
File menu 38, 43
Save button
toolbar 37, 42
Save command
File menu 38, 42
Save Project As dialog box 43
Save Window States checkbox
Preferences 48
Saving
cached information 44
project scenarios 42
window states 48
Scan for Errors before evaluation
Preferences 48
Scan Messages 387
Scenario Description
General Project Data 58
Index
514
Index
515
Index
T
Tax Rate
Cashflow spreadsheet 450
Investment Parameters 103
Project Summary spreadsheet
445
Taxes
amount owed, Cashflow
spreadsheet 452
General Specs 64, 66
indirects, Project Summary
spreadsheet 447
Template files
Reporting Assistant 458
TEX (Total expenses)
Cashflow spreadsheet 452
Tile command
Window menu 28, 42
Time period
Project Input worksheet 402
Timed backup 49
Toolbar
buttons 36
description 36
docking 36
interface, default position 26
View menu 40, 173
Tools menu 41
Total direct cost
Capital Cost report, Icarus Editor
440
Equipment Summary
spreadsheet (EQUIP.ICS) 442
Total earnings
Cashflow spreadsheet 452
Total Expenses
Cashflow spreadsheet 452
Total Manpower Schedule
reports, Icarus Editor 436
Total Operating Cost, Executive
Summary spreadsheet 455
Total project cost
516
U
UCL See Unit Cost Library (UCL)
Unique Project Backup options 49
Unit Cost field
product specifications 114
raw material specifications 111
Unit Cost Library (UCL)
adding an item to 283
adding UCL item to a project 285
creating 282
definition 276
Units of measure
input customization 20, 59
output (reports) customization
61
project properties 20
scenario information 25
Unit Cost Library (UCL) 284
Units of Measure Specification
dialog box 78
Unlock command 45
Unsupported simulator models
Preferences 49
Update button
Develop Stream specifications
form 116
User Custom Model 206210
Index
User name
scenario information 25
Utilities
escalation 404
list of availiable utility resources
222
Stream Input worksheet 405
usage estimation 119
Utilities Escalation
Cashflow spreadsheet 450
Investment Parameters 104
Project Input worksheet 404
Project Summary spreadsheet
(PROJSUM.ICS) 445
Utility costs
Cashflow spreadsheet 450
Executive Summary spreadsheet
455
heat-transfer utilities 101
non-heat transfer utilities 108
Project Summary spreadsheet
449
Utility Specifications
libraries 125, 126
project specifications 98101
selecting defaults 126
Utility stream
creating 98
modifying 98
Utility Unit Costs
operating unit costs
specifications (non-heat
transfer utilities) 108
utility specifications (heattransfer utilities) 101
V
Valve tray sizing 253
Vapor disengagement height
towers, design criteria 90
Version
scenario information 25
Vessel
design criteria specifications 95
97
diameter, General Specs 65
height to diameter ratio 94, 259,
261
sizing 214, 255
View Existing Trend Data command
Trend menu, Aspen Icarus
Reporter 408, 429
517
W
Wage rates
construction workforce
specifications 7073
WARNing message 387
What-You-See-Is-What-You-Get
Zoom dialog box 149
Window menu 42
Window states, saving 48
Workbook mode
understanding 2829
View menu 40, 173
Workforce reference base
General Wage Rates 71
Working capital
Project Input worksheet 403
Working capital percentage
Project Input worksheet 399
Working Capital Percentage
Investment Parameters 105
WYSIWYG
Zoom dialog box 149
Z
Zoom
Aspen Icarus Reporter 410
Block Flow Diagram (BFD) 148
149
toolbar 37
Index
518
Index
519
Index
520