ENGR301 Midterm Winter 2013 Solutions
ENGR301 Midterm Winter 2013 Solutions
#: __Solutions_______________________________________________________
COURSE:
SECTION:
EXAMINATION: Midterm
one of the following contract types has the lowest risk to the owner?
Unit price.
Cost plus.
Lump sum.
Construction management.
[1]
[1]
4. The first build activity cannot starts until after the first design activity is completed in:[1]
a. Traditional project delivery method.
b. Phased project delivery method.
c. Fast track project delivery method.
d. None of the above.
5. A project is:
[1]
a. A set of sequential activities performed in a process or system.
b. A revenue generating activity that needs to be accomplished while achieving
customer satisfaction.
c. An ongoing endeavor undertaken to meet customer or market requirements.
d. A temporary endeavor undertaken to create a unique product or service.
6. Which
a.
b.
c.
7. Which one of the following costs is usually disregarded in Engineering Economic Analysis?
[1]
a. Opportunity costs.
b. Variable costs.
c. Sunk costs.
d. Marginal costs.
8. In cost control earned value refers to:
[1]
a. How much money of the budget should have been spent in view of the planned cost
of work.
b. How much money of the budget should have been spent in view of the amount of
work performed.
c. How much money was actually spent for work already performed.
d. None of the above.
9. Which one of the following flow charts best illustrates an Owner-Builder project delivery
system?
[1]
a.
c.
b.
d.
FALSE
[1]
As a sole trader your personal assets cannot be seized to pay off your business debts.
TRUE
FALSE
[1]
[1]
As the level of detail in an estimate increases, the cost of making the estimate also increases.
TRUE
FALSE
14. Which
a.
b.
c.
d.
[1]
15. How much would $3000 deposited in a bank account be worth after 5 years at 2.75%
compound interest?
[1]
a.
b.
c.
d.
16. Which
a.
b.
c.
d.
$2,224,731
$3435
$3,412
$44,250
one of the following statements is TRUE about the WBS?
The WBS is deliverable-oriented.
The WBS is an unstructured list of activities in chart form.
The WBS is the same as an Organizational Breakdown Structure.
The WBS refers to the Bill of Material (BOM).
17. Which
a.
b.
c.
d.
[1]
[1]
[1]
The following questions refer to the AON diagram provided on page 5. Do a forward pass,
backward pass, and total float calculations (durations are in days); clearly showing the ES, EF, LS
and LF for each activity. Use an early start of 0 for the first activity, and a late finish of the last
activity equal to its early finish. Answer the following questions based on the outcome of the
forward and backward pass.
19. The projects duration is:
a. 22 days
b. 19 days
c. 38 days
d. 61 days
[1]
20. The LF
a.
b.
c.
d.
[1]
of activity C is:
Day 8
Day 11
Day 10
Non of the above
[1]
[1]
[1]
24. If the duration of activity I is increased by 4 days, by how many days will the projects
overall duration increase?
[1]
a. 0 days
b. 4 days
c. 6 days
d. 2 days
25. The earned value of the project at this point in time is:
a. $237,237
b. $225,625
c. $213,750
d. $230,750
[1]
26. The cost variance of the project at this point in time is:
a. -$44,763
b. $0
c. $11,875
d. -$11,612
[1]
27. The schedule variance of the project at this point in time is:
a. -$44,763
b. $0
c. $11,875
d. -$11,612
[1]
28. Assuming that variances are atypical, i.e. ETC = BAC - EV, the EAC for this project is:
[1]
a. $296,612
b. $261,613
c. $308,487
d. $285,000
29. Which one of the following statements best describes the current performance of the
project?
[1]
a. The project is currently over budget and behind schedule
b. The project is currently below budget and ahead schedule
c. The project is currently below budget and behind schedule
d. The project is currently over budget and ahead of schedule
30. Which one of the following expressions establishes economic equivalence of the cash flows at
t=2?
[1]
a.
b.
c.
d.
M(F/P,i%,2)+$B(P/A,i%,5)+x(P/G,i%,5)
M(F/P,i%,1)+$B(P/A,i%,4)+x(P/G,i%,5)
M(F/P,i%,1)+$B(P/F,i%,3)+ $B+x(P/F,i%,4)+$B+2x(P/F,i%,5)+$B+3x(P/F,i%,6)
M(F/P,i%1)+[$B+x(A/G,i%,4)](P/A,i%,4)
31. An engineer purchases a piece of equipment for $1000 and spends $90 per year on
maintenance. During the fourth year, a major overhaul cost of $300 is expected. Benefits
from use of the equipment follow an arithmetic gradient series with G = $50. At the end of
six years the engineer sells the equipment for $400. Which one of the following cash flow
diagrams represents the aforementioned transaction from the engineers viewpoint?
[1]
$1000
$700
$250
$200
$150
$50
$100
$90
$90
$90
a.
$90
$90
$390
$610
$160
0
1
$10
$60
$40
$190
b.
$1000
$790
$590
$340
$240
$190
$140
0
1
c.
$1000
$590
$340
$240
$190
$140
0
1
$790
d.
$1000
32. From the cash flow diagram, find the value of A that will establish economic equivalence with
the given deposit and withdrawals at an interest rate of 12%.
[4]