PSSR
PSSR
FACILITY:
MOC NUMBER:
MOC TITLE:
Item
Question
Group
PIPING
Construction
Inspect valves, flanges and spec breaks to confirm proper pressure rating and compatibility.
Construction
Piping and equipment has been inspected for damage, debris, integrity, and anodes
Operations
All critical piping systems have hydro, pneumatic or non-destructive testing completed and QA documentation has been
reviewed.
Relief systems, PSV's, PCV's, vent piping, flare stacks, and vent booms are installed per construction dwgs.
Construction
Operations
All permanent blinds are in place; all temporary blinds have been removed. The blind list has been reviewed and
approved.
Flange installations have been inspected for proper bolting, gaskets, isolation kits, and restriction orifices.
Operations
All drains and sewers have been inspected for plugs and covers.
Operations
10
Proper installation, operation and orientation of valves (process, instrumentation, utility...) have been ensured.
Construction
11
All filters, screens, and strainers (temporary or permanent) are properly located and installed.
Construction
12
Piping systems have been reviewed allowing for equipment/facility blowdown and isolation
Construction
13
Engineering
14
The integrity of all thermowells and bull plugs have been inspected.
Construction
15
Exhaust lines / vents are properly located away from air intakes, air conditioners, fans, sources of ignition, etc.
Construction
16
All block valves on the relief systems have been locked or car sealed open and are in a functional state
Construction
17
Lock open and lock closed valves have been inspected and are properly secured in their intended position.
Construction
18
All block valves have been reviewed for normal position (norm. open or closed) and handle has full travel.
Construction
19
All fail safe valves have been reviewed for proper action (fail open, fail close, fail unchanged); and location.
Construction
20
Engineering
21
Engineering
22
Engineering
23
Construction
24
Mechanical equipment has been checked for proper alignment, lubrication, and rotation; functional checkouts have been
performed on equipment and controls.
All equipment has been filled with proper fluids to the appropriate level and charged as necessary.
25
Operations
26
Electrical Motors (check for proper rotation and heaters are connected).
Construction
27
Operations
28
Electrical relays, circuit breakers, transformers, lighting and emergency power systems inspected and tested.
Construction
29
Controllers and disconnects are labeled if the device being controlled is not obvious.
Construction
30
Construction
31
Construction
33
All electrical seals have been packed and poured; all explosion-proof boxes, conduit covers are properly secured and all
electrical connections tightened and checked.
Any equipment and associated breaker panels not to be used or not available for use are out of service. All lockouts are
flagged, tagged and listed.
Rotating equipment trip points, especially over speed, have been checked and tested.
34
Construction
5
6
Construction
Construction
CIVIL
MECHANICAL
Construction
ELECTRICAL
32
Construction
Construction
/ NA
Initials
35
INSTRUMENTATION
All instrumentation installed to engineering design specifications (API RP 14C)
Engineering
36
Operations
37
Interlocks (Electrical and Mechanical) have been reviewed and tested for proper operation.
Operations
38
All tubing and tubing fittings have been inspected for proper fit-up and leakage.
Operations
39
Operations
40
Emergency equip. alarms, communication equip, and shutdown devices calibrated, tested, documented and activated.
Operations
41
The fire and gas detection systems have been inspected and tested and are in auto mode.
Operations
42
All bypasses and jumpers on control or safety circuits have been removed.
Operations
43
Engineering
44
Operations
46
47
Fire detection system has been reviewed for proper detector location and correct response / action.
Operations
48
All safeguards including signs (DANGER, HIGH VOLTAGE, KEEP OUT, HEARING PROTECTION REQUIRED), chains,
safety equipment boxes, PPE boxes, etc. are installed and adequately stocked.
Area has been cleared of construction equipment, surplus equipment, combustible materials, extraneous tools, unused
parts, scaffolding and empty drums.
Operations
45
49
Operations
Operations
Construction
50
DOCUMENTATION
All applicable permits and approvals have been received from regulatory agencies (MMS / USCG)
Engineering
51
Operations
52
Engineering
53
Engineering
54
Operations
55
Operations
56
Engineering
57
Training of affected personnel has been completed (operations, maintenance, emergency response, etc.).
Operations
58
All construction punch list items have been reviewed and completed
Construction
59
Engineering
60
Engineering
61
Engineering
62
Engineering
63
Engineering
64
Engineering
65
Engineering
66
Engineering
67
Operations
68
Engineering
69
Engineering
70
Engineering
71
All applicable vendor data updated. (i.e., mechanical, electrical, instrument, etc.)
Engineering
72
Pressure Equipment Pre Commissioning Form completed and sent to Operating Centre IM Specialist Form
Construction
APPROVALS
Title/Position
Name
Date
Title/Position
Name
Date
Title/Position
Name
Date
Authorization to Startup