Project Management Report
Project Management Report
Project Management
A REPORT
ON
PROJECT
MANAGEMENT
PLANNING
TECHNIQUES
BY
SUSHIL GOSWAMI
0903143
3RD YEAR BEng MECHANICAL & OFFSHORE
ENGINEERING
CONTENTS
1. TERMS OF REFERENCE………………………………………………..page 3
2. SUMMARY………………………………………………………………….page4
3. INTRODUCTION………………………………………………………….page6
4. PROJECT PLANNING TECHNIQUES/METHODS…………….page7
5. COMPARISON OF GANTT, PERT & CPM………………………page15
6. OTHER METHODS OF PROJECT PLANNING…………………page21
7. CONCLUSION…………………………………………………………….page25
8. REFERENCES……………………………………………………………..page26
1.TERMS OF REFERENCE.
2.SUMMARY
Project management has been practiced since early civilisation. In the mid of
19th century, project management saw tremendous progress due to the
progress made in various fields. In its present state, project management is a
highly structured process. Planning is one of the key processes involved in
project management. Over the last few decades, many planning techniques
have been developed. The three basic methods of project planning are
GANTT, PERT and CPM charts.
GANTT charts were originally developed by Henry Grant during the years of
1910-1915. GANTT charts continue to be popular and are now considered to
be a common charting technique. GANTT charts are similar to bar-charts.
GANTT charts are normally used to represent the timing of tasks required to
complete a process.
PERT chart was developed by US navy during 1950s. PERT charts are also
known as event labelled charts as the start and finish dates are shown in the
diagram. At its core, PERT is a management of probabilities, which it does
quite elegantly using simple statistics. It uses two types of techniques of
representation- activity on arc (AOA) and activity on node (AON). PERT chart
shows a network of activities and their interdependencies. Before an activity
could start, all its predecessor activities must have been completed. PERT
charts are normally used as a tool for planning and control of time.
CPM charts quite similar to PERT charts but the main focus of them is to
identify critical activities or critical path involved in a project. These are the
tasks or activities that a delay within will delay the whole project. At its core,
CPM is a deterministic tool which allows an explicit estimate of costs in
addition to time.
DSM is a simple tool to perform both the analysis and the management of
complex systems. As a management tool, it provides a project representation
that allows for feedback and cyclic task dependencies.
3. INTRODUCTION
Projects are one-off pieces of work in the form of related tasks, or activities
which when completed within a fixed timescale satisfy one or more
objectives. Since early civilisation, project management has been practiced.
By 1950s, project management saw a tremendous development as a
discipline due to the progress made in the fields of construction, engineering,
telecommunications, and defence. Examples of projects which influenced the
development of modern project management as we know it today include a)
Polaris missile project, 1956; b) Apollo project, 1960; and c) E.I. du Pont de
Nemours chemical plant project, 1958. (1)
1. Initiation
2. Planning
3. Execution
4. Monitoring
5. Controlling
6. Completing a plan/project as specified.
There are three basic systems used to prepare the plan. There are few others
but are normally mixtures of elements from two or more of the basic
systems.
GANTT chart: The chart is commonly known after Henry Gantt who designed
this chart around the years 1910-1915. (4). In general, a GANTT chart is a
kind of bar chart which illustrates a project schedule. It represents the timing
of tasks required to complete a project.
Now, let’s have a look at the GANTT chart on the next page made using
Microsoft Project.
The above GANTT chart shows the different tasks involved in the project.
Each task takes up one row. Time runs along the top in increment of minutes.
The expected time for each task is marked by a horizontal bar whose left end
marks the expected beginning of the task and whose right end marks the
expected completion time. For example, the task ‘WAKE FAMILY’ is expected
to start at the end of the 5th minute and finish at the end of the 10th minute.
It spans over duration of 5 minutes. (4, 5)
GANTT charts are simple to design and easy to construct. GANTT charts give a
clear illustration of project status, but one problem with them is that they
don’t indicate task dependencies. We can’t tell how one task falling behind
schedule affects other tasks. (4, 5)
Now, let’s have a look at PERT chart for the same project.
PERT is known as event labelled because the start and finish are noted in the
diagram.
prepare finish
breakfast breakfast
A PERT is constructed from a series of start and end elements like the ones
shown above.
ALARM GOES OFF ID: 1 WAKE FAMILY ID: 2 MUM SHOWER ID: 3
DUR: 5 MINS RES: DAD DUR: 5 MINS RES: DAD DUR: 40 MINS RES: MUM
DUR: 5 MINS
CPM chart: The critical path method (CPM) is a step-by-step technique for
process planning that defines critical and non-critical tasks with the goal of
preventing time-frame problems and process bottlenecks. The CPM is ideally
suited to projects consisting of numerous activities that interact in a complex
manner. The CPM was developed in the 1950s by DuPont, and was first used
in missile-defence construction projects. Since that time, the CPM has been
adapted to other fields including hardware and software product research
and development. (8)
A CPM chart generally needs a list of activities for a project where each
activity has a list of predecessor activities. Critical Path Method (CPM) charts
are similar to PERT charts and are sometimes known as PERT/CPM. In a CPM
chart, the critical path is indicated. A critical path consists of set of
dependent tasks (each dependent on the preceding one) which together take
the longest time to complete. Although it is not normally done, a CPM chart
can define multiple, equally critical paths. Tasks which fall on the critical path
should be noted in some way, so that they may be given special attention.
The critical path for any given method may shift as the project progresses;
this can happen when tasks are completed either behind or ahead of
schedule, causing other tasks which may still be on schedule to fall on the
new critical path. (8, 9)
We would be using the AOA (activity on arc) form of the CPM chart for the
afore-mentioned project.
In the example above, notice the dummy tasks leading from tasks 4 and 6 to
task 8. They indicate that task 8- ‘eating breakfast’ cannot commence until
tasks 4- ‘son shower’ and 6- ‘father shower’ are completed. Also, task 8
cannot start until it predecessor, task 7- ‘prepare breakfast’ is complete.
Hence, a dependency must be shown for tasks 4 and 6 leading to task 8. But
if we draw normal task arrows from task 4 and 6, it means that something
needs to be done on those arrows, but there is no task, just the dependency.
So, we use dummy (dotted) lines which show that a dependency exists even
though there is no task between the two tasks. (5, 8)
Now, we can clearly see that critical path here in this example is Alarm, Wake
All, Mum Shower, Prepare Breakfast, Eat breakfast, Load car and Drive. If any
of these tasks get delayed, the whole plan will get delayed. (5, 8)
The minimum time the family would take before they could reach the
football game after the alarm goes off is the total of the critical task
durations= 5+5+40+15+15+5+25=110 minutes. (5)
In the above PERT chart, the critical path has been shown by darker arrows.
DISADVANTAGES:
1. Estimates must be complete before the chart could be
drawn.
2. A GANTT chart does not effectively address the
dependencies between jobs (although constraints can
be added as vertical lines).
3. Dependencies are hard to verify.
4. It is difficult to show two sets of dates when using
techniques such as earliest start date and latest start
date.
ADVANTAGES:
DISADVANTAGES:
CPM shares most of the advantages and disadvantages of PERT charts. Both
of them being network diagrams have many common key advantages and
benefits and suffer from many similar limitations.
ADVANTAGES:
DISADVATAGES:
By now, we have seen the various aspects of GANTT, PERT and CPM charts.
While GANTT charts provide an easy graphical representation of when
activities (might) take place, they don’t clearly indicate details regarding the
progress of activities. Beside, they fail to show dependencies between
different activities. Some of these shortcomings of GANTT charts are solved
to a large extent by network diagrams like CPM and PERT charts. These
charts show interdependence of various activities by means of connecting
arrows called network techniques. GANTT charts fail at providing enough
information about critical activities which govern the success or failure of a
whole project. CPM/PERT charts identify these critical activities. Further,
these techniques can also tell us how close the remaining activities are to
becoming critical (this available delay is also called slack or float). (4, 17, 14)
PERT and CPM are very similar in their approach; however, two distinctions
are usually made. The first relates to a way in which activity duration are
estimated. In PERT, three time estimates are used to form a weighted
average of the expected completion time, based on a probability distribution
of completion times. Therefore, PERT is a probabilistic tool. This makes PERT
a better tool for non-repetitive jobs like research and development work,
where time and cost tend to be quite uncertain. In CPM, there is only one
estimate of duration; that is, CPM is a deterministic tool. This makes CPM a
better tool for jobs of repetitive in nature where activity time estimates can
be predicted with considerable certainty due to the existence of past
experience. The second difference is that allows CPM allows for an explicit
estimate of costs in addition to time. Thus, while PERT is basically a tool for
planning and control of time, CPM can be used to control both the time and
the cost of the project. (14)
Over the time, CPM and PERT charts have merged together into one single
technique. Extensions of both CPM and PERT allow the user to manage other
resources in addition to money and time, to trade-off resources, to analyse
different types of schedules, and to balance the use of resources. (4, 14, 17)
are randomly numbered in the chart, and they influence each other
through the pattern of arrows. It’s quite difficult to understand and
visualise the structure of the example through the diagram in the
left part. On the right side of the figure is the corresponding DSM
that maps the interactions between the process tasks, listed in rows
and columns in same order. The matrix is filled with oriented
interactions from the elements in columns to the elements in rows.
Thus, looking at the off-diagonal marks in a column, task 7 in the
example figure below will describe which other tasks on the output
of the task corresponding to the column. Similarly, the off-diagonal
marks within a row, 5 in the example, represent all of the tasks
whose output is required to perform the task corresponding to that
row, i.e. 1, 3 and 8 in the example. The diagonal cells are usually
meaningless since they would represent a dependency of a task on
itself. (10)
7.CONCLUSION
Project management is a highly-structured process in its present state and
there are many methods/techniques which can be employed to prepare a
plan. The three basic systems which are commonly used are GANTT, PERT
and CPM. Each of them has its own place in a project plan. A GANTT chart is
quite useful for easy graphical visualisation of a project but it suffers from
many drawbacks. For example, it fails to provide enough information about
the interdependencies of different activities involved in a project. On the
other hand, PERT/CPM charts enable a user to identify critical activities in a
project. While PERT can be used for planning and control of time, CPM charts
can be used to control both time and cost of a project. CPM charts are quite
similar to the PERT charts but include an explicit indication of the ‘critical
path’. Otherwise, CPM shares same strengths and weaknesses as the PERT,
and the two are often lumped together as one technique. (4, 14)
8.REFERENCES
1. Sandro Azzopardi, The Evolution of Project Management Part2,
accessed on 5th November 2009. Available from:
https://ilrb.cf.ac.uk/citingreferences/vancouver/page08e.html
2. Project Management Institute, PMBOK guide- 3rd edition, PMI, 2009.
3. Lecture notes by Dr. C. MacLeod.
4. D. Grover, Graphical Project Planning Techniques: An overview of
GANTT, PERT and CPM charts, 01/06/2002. Accessed on 11th November
2009.
5. Mark Kelly, McKinnon Secondary College, Buffalo PERT- a PERT
example inspired by Buffalo University, Australia, july21, 2005.
Accessed on 12th November 2009. Available from:
http://www.mckinnonsc.vic.edu.au/vceit/ganttpert/buffalo/buffalo-
pert.htm
6. TechTarget, PERT chart, accessed on 14th November 2009. Available
from:
http://searchsoftwarequality.techtarget.com/sDefinition/0,,sid92_gci3
31391,00.html
7. Mark Kelly, McKinnon Secondary College, Project Management Terms,
Australia, july21, 2005. Accessed on 12th November 2009. Available
from:
http://www.mckinnonsc.vic.edu.au/vceit/ganttpert/projmanterms.ht
m
8. TechTarget, Critical Path method, accessed on 14th November 2009.
Available from:
http://whatis.techtarget.com/definition/0,,sid9_gci1180430,00.html
9. Martin E. Modell, A Professional’s Guide to System Analysis, 2nd
edition, McGraw Hill, 1996. Available at:
http://www.mckinnonsc.vic.edu.au/vceit/ganttpert/dev-pert.html
10. Antoine D. Guivarch, MIT, USA, Concurrent Process Mapping,
Organisation, Project and Knowledge Management in Large-Scale
Product Development Projects Using the Design Structure Matrix
Method, July 2003. Accessed on 21st November 2009.
11. Craig Borysowich, ToolforIT, Pros and Cons of Gantt charts, 2/2/2008,
Accessed on 20th November, Available from:
Sushil Goswami BEng. Mechanical & Offshore Engineering Page 26
Robert Gordon University
Project Management
http://it.toolbox.com/blogs/enterprise-solutions/pros-cons-of-gantt-
charts-22233
12. Envision software, PERT estimation, accessed on 22nd November,
Available from:
http://www.envisionsoftware.com/Management/Pert_Estimation.ht
ml
13. Heizer & Render, Operations Management, Prentice Hall, 2009, USA,
Accessed on 22nd November 2009. Available from:
http://online.uis.edu/spring2000/bus322/lectures/chap16/sld049.htm
14. Zetamuhendislik, Project Management, accessed on 21st November
2009, available from http://zetamuhendislik.com/pages/Project.htm
15. Craig Borysowich, ToolboxforIT, Pros and Cons of PERT/CPM charts,
2/2/2008, Accessed on 20th November, Available from: :
http://it.toolbox.com/blogs/enterprise-solutions/pros-cons-of-the-
pertcpm-method-22221
16. NetMBA, CPM- Critical Path Method, accessed on 23rd November
2009, Available from:
http://www.netmba.com/operations/project/cpm/
17. Antonio Prensa, Project Management Institute, The Critical Path
Method, Puerto Rico, Accessed on 22nd November 2009, Available
from:
http://pdf2me.com/view?pdf=http://www.pmipr.org/html/Presentaci
ones/The%20Critical%20Path%20Method.pdf
18. Craig Borysowich, ToolboxforIT, IDEF3- Process Description,
31/08/2007, accessed on 24th November 2009, available from:
http://it.toolbox.com/blogs/enterprise-solutions/idef3-models-
process-description-18705
19. OGC, PRINCE2, Accessed on 24th November 2009, Available from:
http://www.ogc.gov.uk/methods_prince_2__benefits.asp
20. PRINCE2, What is PRINCE2?- PRINCE2 definition, accessed on 24th
November 2009, Available from: http://www.prince2.com/what-is-
prince2.asp