Unit 5 SAP
Unit 5 SAP
0113U103
Integrated Planning Process in Management Accounting
Unit Overview
This unit discusses the importance and role of planning in Management Accounting.
Creating plan data enables you to make a plan/actual comparisons and
target/actual comparisons, which make Management Accounting more efficient and
effective.
Unit Objectives
After completing this unit, you will be able to:
Unit Contents
Lesson: Integrated Planning
Cycle146
Exercise 7: Integrated Planning
Cycle.165
Lesson: Integration of Activity-Based
Costing.175
Exercise 8: Planning with Activity-Based
Costing181
Standard cost estimate must be free of errors (status KA, costed without
errors).
The marking release must be allowed. The authorization should be set up
once per period by the employee responsible. If you mark a standard cost
estimate, the results are updated in the material master records as the future
standard price.
When you release the standard cost estimate, these future prices are updated as
the current standard price.
1. You can release a standard cost estimate only once per period, unless you
delete the previously released standard cost estimate (using a special
program) from the database. You should also always check the standard cost
estimate to ensure that it is correct before you release it for a product.
Specialized reports in the Information System allow you to do this.
Exercise 7: Integrated Planning Cycle
Exercise Objectives
After completing this exercise, you will be able to:
Business Example
Because the company plans to manufacture products and to provide services based
on market demand, a decision was made to start the planning cycle in Profitability
Analysis. The resulting sales plan (business plan) was transferred to Sales and
Operations Planning (SOP), and the required material quantities and production
resources were calculated.
Task 1:
Check fixed and variable prices for activites.
1. Before a standard cost estimate is created, you must check the calculated
price for one of the production activities in pump assembly routing R-F1##.
Review the planned activity price for activity price for activity type 1421 and
cost center 4230. Make a note of the fixed and variable plan prices for the
activity.
Task 2:
Following cost center planning, you have to recalculate the cost of goods
manufactured for R-F1##. To accomplish this, create a standard cost estimate
taking into account the planned activity prices.
1. Create a standard cost estimate for material R-F1## with costing variant
PPCI and a lot size of 500 pieces. Change the default for the Costing From
Date to today. Leave the other defaults data for Costing Date To, Quantity
Structure and Valuation as is.
Lesson: Integrated Planning Cycle
Lesson Overview
This lesson describes integrated planning from the point of view of
Management Accounting.
Much of the plan data does not necessarily have to be entered by controllers,
rather it can be transferred from other components, such as Profitability
Anlaysis, Profit Canter Accounting, and Product Costing, via integration.
Lesson Objectives
After completing this lesson, you will be able to:
Business Example
2. On the Create Material Cost Estimate with Quantity Structure screen, check
the cost calculation results.
Expand the panel on the left side of the screen. Select the pump and expand
the subtree to display all the material components in a hierarcy.
3. Display all the details (resources) used for each of these materials, including
production activities, components, processes and overhead rates.
To do this, select the pump and choose Display Only Materials/All Items.
Locate activity type 1421 and cost center 4230 and verify that the price listed
matches the price that you reviewed in the the first task, Check fixed and
variable prices for activities.
Reduce the size of the panel on the left again.
4. Now analyze the itemization displayed in the lower section of the screen. You
can expand the upper edge of the screen by dragging it upward with the
mouse.
Change the costing allocation base to 1 piece by choosing. Settings Cost
Display.
What is the cost of pump R-F1##?________________________
Select other layouts to obtain a cost display with a different layout (for
example, layout 1SAP09 for a list sorted by cost elements).
5. Save the costing with itemization and log.
Task 3:
Release the cost estimate.
1. To use the results of this costing as the future standard price, you must mark
the cost estimate by choosing Price Update from the menu.
Inputs for integrated internal orders, the scheduled activity is posted to the sender
cost center/sender process. In addition, planned settlements and periodic repostings
of integrated orders to cost centers/processes are allowed.
You can use a costing sheet to calculate your own overhead costs. If you use the
traditional method, you apply the overhead costs to the reference object as a
percentage or quantity rate. In the costing sheet, you determine how the overhead
costs are calculated for the costs of goods manufacture and the cost of goods sold.
Figure 71: Master Data in Product Cost Accounting
Cost are normally planned for orders that have a long life cycle. Orders with a short
life cycle, such as for unexpected small repairs, are normally not planned.
Three different cost planning levels are available for planning internal orders:
Overall planning is the simplest level for planning order costs. You can plan
overall values and annual values irrespective of the cost elements.
Primary/secondary costs and revenue planning can be used if you have
detailed information about an internal order. For manual planning purposes,
primary/secondaryncosts and revenue planning comprises the planning of
primary costs, activity inputs, and revenues. If the order is plan integrated,
you can, for example, credit plan values with settlement to a cost center.
Unit consting can be used to carry out more detailed planning than is possible
on cost elements.
In product costing with quantity structures, costs are calculated for a material via
automatic derivation of the quantity structur fro bills of material and routings or the
master recipe, or from network resources.
In product costing without quantity structures, cost are calculated for a material
without a quantity structure being derived automatically.
With reference and simulation costings, costs are calculated for an abstract object
know as a base planning object.
Figure 77: Product Cost Planning: Overview
When you create a cost estimate with quantity structure, you must enter the
costing variant, the material, the plant, and the lot size. The dates proposed from
the costing variant specify the following:
products or cumulatively at the product group level. You can select any market
segment (for example, all products from one division) and time frame (reporting
period) to transfer.
For plan integration, you use the following master data:
Material masters
Bills of material
Work centers
Routings
Master data enables cost objects to be created quickly and efficiently in the SAP
system. The data shown in the figure material master, BOM, work center, routing
is copied to the quantity structure of a production order.
After you have marked the costing, display the Costing 2 view of the material
master record for R-F1## and review the future price that is entered in the material
aster record.
2. Release the cost estimate for material R-F1## so that it becomes the current
standard price. Check this in the Costings 2 view in the material master
record.
After output quantities are planned, the costs are planned. The cost center manager
does not plan all the costs manually. Many costc can be taken from the plans in
other components. Planning data from the following components can be used:
After all this data has been transferred, the cost center manager plans the
remaining costs manually. Plan prices are calculated last.
Figure 74: Transferring Planned Values to Cost Centers
In integrated planning, data can be transferred form upstream systems of Cost
Center Accounting to cost center planning. If you have planned this data in
upstream systems and now want to transfer it unchanged to cost center planning, it
is not necessary to replan the data in Cost Center Accounting.
To be able to use integrated planning, several requirements must be met in Cost
Center Accounting and in the upstream systems. For example, if you want to
transfer planned values for statistical key figures, you must first create master
records for these key figures and then link them to the Logistics Information System.