Guidelines For Relay Setting
Guidelines For Relay Setting
The
Electrical
Power
Engineers
1.0
PHILOSOPHY
Overcurrent protection schemes are generally designed with a primary means of clearing a
fault, as well as one or more backup methods. Where possible, it is preferred that
instantaneous methods of detecting overcurrent be used as the primary protection method
on all of the major equipment associated with the power system. Instantaneous clearing of
a fault is desirable:
to avoid long clearing times that could result in the entire system becoming
unstable, resulting in a complete loss of power to the system.
Instantaneous methods of relaying generally include differential, pilot wire, and impedance
relays. Backup protection is generally accomplished with time overcurrent relays and
impedance relays with a time delay.
Good objectives for clearing times are:
that the primary protection clear a fault in less than 0.25 seconds for the
maximum available fault current and
that the backup protection clear a fault in less than 1.00 seconds for the
maximum available fault current.
Faster clearing times are desirable whenever it is possible for the three reasons given
above.
2.0
Overcurrent protective devices at 480V are set to open at or below the downline
cable or busway ampacity per NEC Section 240.3; except when the ampacity
does not correspond to a standard rating, the next higher standard rating may
be used as long as this rating does not exceed 800 amps. (See Section 5.3 for
more details.)
Overcurrent Coordination
Page 1
3.0
2.
3.
Long time settings of overcurrent devices are above the maximum expected full
load current for that device.
Relay - Relay coordination requires (1) that there be a minimum of 0.25 to 0.40
seconds time margin between the relay curves at the maximum fault current to
account for the interrupting time of the circuit breaker, relay over-travel time, relay
tolerances, and a safety factor or (2) that the downline relay curve be less than
90% of the upline relay curve.
For induction disk relays, the minimum desired time margin for a 5 cycle
breaker is generally 0.30 seconds:
5 cycle breaker
0.08 seconds
relay over-travel
0.10 seconds
CT ratio & safety factor
0.12 seconds
0.30 seconds
For digital relays, the minimum desired time margin for a 5 cycle breaker
is generally 0.25 seconds:
5 cycle breaker
0.08 seconds
relay accuracy +.02 sec. 0.04 seconds
CT ratio & safety factor
0.13 seconds
0.25 seconds
Margin between pickup levels of > 10% for two devices in series.
2.
3.
4.
Static Relay - Fuse coordination requires a minimum 0.12 second time margin
between the curves.
5.
6.
Fuse - Fuse coordination requires that the total clearing time of the downline
fuse curve be less than 75% of the minimum melt time of the upline fuse curve
to account for pre-loading.
7.
Fuse - Low Voltage Breaker coordination requires that the down-line breaker
maximum time curve be less than 75% of the minimum melt time of the up-line
fuse curve to account for pre-loading.
Overcurrent Coordination
Page 2
4.0
8.
9.
Low Voltage Breaker - Fuse coordination requires a minimum 0.1 second time
margin between the curves to allow for temperature variations in the fuse.
10.
Low Voltage Breaker - Low Voltage Breaker coordination requires only that
the plotted curves do not intersect since all tolerances and operating times are
included in the published characteristics.
11.
2.
B.
The instantaneous pickup is > 1.6 x Isc for maximum fault downstream of
transformer to avoid the tripping of the primary breaker for an
asymmetrical secondary fault. A multiplier of 1.8 is used for larger
transformers.
C.
The instantaneous pickup is > 1.3 x Isc for maximum fault downstream of
transformer to avoid the tripping of the primary breaker for an
asymmetrical secondary fault, if the relay is equipped with a DC filter that
will filter out the offset portion of an asymmetrical fault current.
B.
The instantaneous pickup is > 1.6 x 1.1 x locked rotor current to avoid
tripping the breaker for the maximum asymmetrical current for starting the
motor or for a nearby fault. The total factor of 1.8 is due to asymmetry and
motor saturation during starting.
C.
The instantaneous pickup is > 1.3 x locked rotor current to avoid tripping
the breaker for the maximum asymmetrical current for starting the motor
or for a nearby fault, if the relay is equipped with a DC filter that will
completely filter out the offset portion of an asymmetrical current.
D.
For relays that do not completely filter out the offset portion of an
asymmetrical current, such as Multilin 469 relays, use the following
guidelines:
i.
Enable the Overreach (DC) Filter and set the Short Circuit Trip
(instantaneous) pickup setting > 1.5 x locked rotor current.
Overcurrent Coordination
Page 3
ii.
3.
Enable the Overreach (DC) Filter, set the Short Circuit Trip delay
setting > 10 ms, and set the Short Circuit Trip (instantaneous) pickup
setting > 1.3 x locked rotor current.
B.
C.
D.
4.
When ground relays (50/51G) are used to detect ground currents on the
main breakers, faster clearing times are possible since the criteria of item
3C above for residual relays does not apply. A delay of 0.4 seconds is
chosen to allow coordination with the downline motor relays that are
typically set with a 0.05 second delay.
Overcurrent Coordination
Page 4
5.0
This discussion focuses specifically on the guidelines for and the setting of low voltage
breakers on 480V systems. Many of these comments can be extrapolated to other low
voltage systems as well.
5.1
The incident energy associated with three phase arcing faults on the 480V main bus
generally determines the PPE label that is needed for each of the feeder fused switches or
breakers that are fed from the main 480V bus. For transformers in the range of 1500 to
3000 kVA, the following observations are generally true:
1.
If a 480V main class L fuse is used with a rating on the order of 125% of the
transformer rating, the incident energy for faults on the main bus will be
> 100 cal/cm2.
2.
If a main 480V breaker is used with a long time pick up (LTPU) on the order of
125% of the transformer rating, a short time pickup (STPU) in the range of 2 to 3
times the LTPU, and a short time delay of 0.3 to 0.4 seconds, the incident energy
will generally be < 40 cal/cm2 (i.e. PPE Level = 4).
3.
4.
Based on item #1, replacing a main fuse with a main breaker could significantly
lower the incident energy from > 100 cal/cm2 to < 40 cal/cm2. With the
Maintenance Mode option on the trip unit, the incident energy could even be
reduced to < 8 cal/cm2 for certain down-line tasks, as discussed in item #3 above.
5.
When there is a main breaker (or possibly a main fused switch) other
considerations that can reduce the incident energy include:
A. Bus differential relaying
B. Zone selective interlocking
C. Remote tripping
D. Not paralleling of transformers
E. The use of non-louvered doors and panels, which can reduce the
exposure to the qualified worker.
Overcurrent Coordination
Page 5
5.2
The basic system for these guidelines is illustrated in Figure 1 and is described as follows:
480V double ended substation
Generator on one transformer
Tie breaker normally open
Two transformers are not operated in parallel
The generator can operate in parallel with one transformer or independently
Figure 1
Objectives in coordination:
Main and tie breakers coordinate with all feeders
Main and generator breakers coordinate in fault current region
Generator breaker coordinates with feeders as much as possible
Achieve PPE = 4 at main bus with margin
Achieve PPE = 2 at remote MCCs and PDPs with margin
Coordination of the tie breaker with the main and generator breakers is not critical
The setting band must be considered when selecting the pickup and instantaneous
settings. In many cases the tolerance on the LVCB settings are in the range of
+/- 10 to 20%. The defined margins need to include these tolerances.
The guidelines for setting low voltage breakers are summarized as follows. Where
coordination and protection are not compromised, lower pickup settings for short time and
instantaneous functions can and should be used. (See Qual-Tech Document QT-629 for
other options in accounting for the variation in the arcing current.)
1.
Main Breakers:
LTPU:
LT Delay:
STPU:
Set low enough to trip for 85% of the 85% arcing current.
This setting is generally in the range of 2 to 3 times the LTPU.
Overcurrent Coordination
Page 6
2.
3.
ST Delay:
Instantaneous:
None
Ground PU:
Ground Delay:
0.5 seconds
Tie Breakers:
LTPU:
LT Delay:
STPU:
ST Delay:
Instantaneous:
None
Ground PU:
Ground Delay:
Generator Breakers:
LTPU:
LT Delay:
STPU:
Low enough to trip for 85% of the 85% arcing current without
main transformer. Due to the decaying generator current for
a fault, this can be difficult if not impossible. Usually the
lowest setting of 1.5 times the LTPU is used.
ST Delay:
Instantaneous:
Ground PU:
Ground Delay:
Overcurrent Coordination
Page 7
4.
Feeder Breakers:
LTPU:
LT Delay:
STPU:
5.3
ST Delay:
Instantaneous:
Ground PU:
Ground Delay:
From NEC 240.4 (B) and (C), for protective devices rated 800 A or less, the next higher
standard overcurrent device rating, above the ampacity of the conductors being protected,
is allowed if the following conditions are met:
1.
The conductors are not part of a branch circuit supplying more than one receptacle
for cord-and-plug-connected portable loads.
2.
The ampacity of the conductors is not the same as a standard ampere rating of a
protective device.
3.
The next higher standard rating is not higher than 800 A.
For protective devices rated over 800 A, the conductor ampacity shall be greater than or
equal to the overcurrent device.
Section 240.91 (B) allows for higher overcurrent device ratings if the facility is a supervised
industrial installation. For overcurrent devices rated over 800 A, the ampacity of the
conductors it protects shall be equal to or greater than 95% of the rating of the device, with
the following conditions met:
1.
The conductors are protected within recognized time vs. current limits for
short-circuit currents.
2.
All equipment in which the conductors terminate is listed and marked for the
application.
From NEC 240.6, the standard protective device ampere ratings are: 15, 20, 25, 30, 35,
40, 45, 50, 60, 70, 80, 90, 100, 110, 125, 150, 175, 200, 225, 250, 300, 350, 400, 450,
500, 600, 700, 800, 1000, 1200, 1600, 2000, 2500, 3000, 4000, 5000, 6000.
Overcurrent Coordination
Page 8
6.0
COORDINATION PRIORITIES
With the above criteria considered, there are cases where complete selectivity is not
achievable. For these cases, the following priorities (level 1 being the highest) are used to
determine the overcurrent device settings:
Priority Level 1:
a.
b.
c.
d.
In a switchgear lineup, the main overcurrent device coordinates with all feeder
overcurrent devices.
e.
For a normally closed tie breaker with two normally closed main breakers, the
tie breaker coordinates with the main breaker. With a normally open tie
breaker, the tie breaker is set the same as the mains.
f.
g.
The first of three devices in series in a fault current path coordinates with the
third device in the path.
Priority Level 2:
a.
b.
c.
d.
The first of two devices in series in a fault current path coordinates with the
second device in the path.
e.
For a fused breaker, the breaker settings should be such that the breaker
clears low and intermediate magnitude fault currents while the fuse operates
to clear the high magnitude fault currents.
Overcurrent Coordination
Page 9