Construction MGT
Construction MGT
By
ONWUJI, R.C
(PG/MSC/02/36668)
Lecturer: ARC.UZUEGBUNAM
July 2004
Table Of Contents
Introduction---------------------------------------------------------------------------------4
1.0
Project
Analysis--------------------------------------------------------------6
2.0
Site
---------------------------------------------------------------------------6
3.0
Site
-----------------------------------------------------------------------7
Feasibility
Selection
Investigation
3.1
Surveys------------------------------------------------------------------------------7
Site
3.2
Geotechnical
Investigation------------------------------------------------------------8
3.3
Drainage
And
Survey---------------------------------------------------------8
Utilities
Property
Archaeological
3.7
Environmental
Issues-------------------------------------------------------------------9
3.8 Legal Aspect----------------------------------------------------------------------------9
4.0 Design Criteria-----------------------------------------------------------------------11
5.0 Master Schedule----------------------------------------------------------------------11
6.0 Cost Plan And Cost Control--------------------------------------------------------12
6.1
Creation
Of
Project
System------------------------12
Cost
Control
And
Estimating
Quantities
Poor
Cost
Federal
INTRODUCTION
Construction management can be defined as the planning, control
and co-ordination of a project from inception to completion. This is
aimed at meeting the clients requirements in order that the project will
be completed on time within authorized cost and to the required
quality standards.
Construction management starts by gaining an understanding of the
clients objective and by providing the expertise to allow the client to
define more precisely what is needed and how it can be achieved. In
this way, construction management can influence the decision on the
type of facility required, its use, user needs, architectural concepts,
construction time scale and cost criteria.
The client can also be guided around such obstacles as unavailability
of relevant project resource and be advised on how to buy best, to
contracts,
land,
financial
taxation.
5
arrangement,
insurance
and
and
recommendations.
Reaching a decision about project viability based on the report
and recommendations.
Ground level/contours
Physical features
Existing boundaries
Adjacent properties
Site access
Structural survey
Previous use of site
3.2 GOTECHNICAL INVESTIGATION
Trial pits
Bore holes and bore hole logs
Geology of site including underground workings
Laboratory soil test
Site test
Ground water observation and pumping test
Geophysical survey
3.3 DRAINAGE AND UTILITIES SURVEY
Existing site drainage(open ditch, culvert or piped system)
Extent of any other utilities that may cross the site (oil pipelines,
water, electricity)
3.4 TRAFFIC SURVEY
Examination of traffic records from local authority
Traffic counts
Traffic patterns
Delay analysis
Noise levels
3.5 ADJACENT PROPERTY SURVEY
Right of light
Party wall agreement
Schedule of conditions
Foundations
Drainage
Access
Public utilities serving the property
3.6 ARCHAELOGICAL SURVEY
Examination of records
Archaeological remains
3.7 ENVIRONMENTAL ISSUES
Effects
of
proposed
development
on
local
environment;
10
11
HAS CLIENT
INSTRUCTED
INVESTIGATION
ADVISE CLIENT OF
THE NEED
REVIEW WITH
CLIENT
DOES SCOPE OF
WORK ADEQUATELY
REFLECT SITE
CHARACTERISTICS
DEFINE SCOPE OF
INVESTIGATION
AND AGREE WITH
CLIENT
IS ADDITIONAL
INVESTIGATION
REQUIRED
SELECT SUITABLE
ORGANISATION TO
CARRY OUT
INVESTIGATION
INSTRUCT
ADDITIONAL
INVESTIGATION
AGREE REVISED
DATE FOR
COMPLETION
MONITOR
PERFORMANCE AND
PREPARATION OF
FINAL REPORT
12
This involves style development in buildings relating to our up-todate technical opportunities, and designers face a barrage of possible
structural solutions, and a great number of alternative building
materials.
Quality design styles should be adapted such that the buildings will
remain very adaptable over a long period of time. In other to achieve
this, building design criteria should therefore aim at:
Modifying the climate
Supporting patterns of activity
Adding to our resources
Providing delight
5.0 MASTER SCHEDULE
A schedule of work form inception stage to completion stage. It
involves schedule of material, labour, cost and work schedule. Other
schedules can be drawn from here depending on alterations made.
Since the project is expected to be realized within a time frame and
budget, the master schedule should be drawn to guides the project
manager and give him responsibilities to monitor the progress of the
project from inception to completion.
The master schedule should be developed and agreed with the client
and members of the professional team concerned and detailed
programme for each stage of the project prepared as soon as the
necessary parameters are established.
13
14
parties,
may
the
procedure
be
carried
out
and
also
comparative
cost
of
alternative
forms
of
16
17
18
19
20
CONCLUSION
With all these listed, we can now agree that construction
management at the predesigned stage entails a lot. This process is
21
reached
satisfactorily
and
in
record
time
putting
into
22
REFERENCE
Chartered institute of building (1992) Code of practice for project
management for construction and development.
Harper, R.H. (1990) Building, the process and the product, Berkshire:
The chartered institute of building.
Bassey, N. (1994) the management of construction, Nigeria: Kraft
book limited
Nigerian urban and regional planning decree 1992.
23