Attachment Report Submitted
Attachment Report Submitted
INDUSTRIAL REPORT
FACULTY OF INDUSTRIAL TECHNOLOGY
CIVIL AND WATER ENGINEERING DEPARTMENT
STUDENT NAME
NHANGA SHEPHERD
REGISTRATION NUMBER
N0110767B
ACADEMIC SUPERVISOR
ENG A. CHINYAMA
INDUSTRIAL SUPERVISOR
ENG P. NDLOVU
COMPANY
SOUTHLAND
DATE OF SUBMISSION
30 APRIL 2015
NO110767B
ii
iii
DEDICATION
I dedicate this report to my loving mother for her unwavering support, to my family for
believing in my potential and ability to reach greater heights. To my late father for
bestowing the gift of life upon me.
iv
ACKNOWLEDGEMENTS
To mom for her hard work and immense effort and immeasurable love.
To Marian, Mazvita and Tariro who always challenge me to be the best of me.
Above all to God Almighty for his guidance, provision, and protection who made
all things possible.
ANNOTATIONS
Most of the notations used in this report are based on the British Standard Codes of
Practice and some internationally acceptable symbols. In the design of reinforced
concrete, I adopted the BS8110 code of practice. Here is a list of the principle symbols
used;
AS
As
Asv
Width of section.
bw
Breadth of web.
fcu
fy
fyv
Gk
Qk
hf
Thickness of flange.
lx
ly
Mu
vi
ABSTRACT
This report gives a brief account of the practical experience and concepts acquired during
the industrial attachment period.
The student was mostly involved in structural engineering projects on his tenure at
Southland .Here is a brief account of the projects he undertook.
Gweru Megawatt House: The project involves the design of a six storey office block and
a shopping mall. Structural design was to be performed to the building starting from
preliminary design up to detailed design. The project also had some bulk excavations on
the site due to the bad silt clay soils from the geotechnical investigations.
Proposed Spar distribution centre: This project was mainly structural with a few civil
works for the localised sewer and water reticulation .For the sewer system long sections
had to be produced which involved the calculation of manhole depths, pipe gradient, and
invert levels.
Warehouse Chimbwa: This project involved the design of a double storey warehouse
with the first floor being used as office space. Structural layouts had to be produced and
also in company were the reinforcement fixing details.
Shawa mine Run off Mine Bin: This project involved the analysis of the effect of
mechanical use of the dumber or loader to remove the mine run off. The loads involved
had to be calculated and structure analysis done.
House Cornelius: The project entails the design, producing structural layouts,
reinforcement fixing details for the foundation, ground floor, first floor and the staircase.
A bending schedule had to be produced in conjunction with the layouts.
Proposed Fourth Street Development: On this project waffle slabs had to be designed
and structural layouts from foundation to the fourth floor .The first four floor were to be
used as parking area their the loads were very high and also for big spans proposed by the
Architect a waffle slab was inevitable .
Conclusion
The student amassed a lot of experience which included structural design of members,
producing structural and reinforcement layouts, bending schedules
vii
Key words:
Run off mine Are the boulders that are left after raw mineral material has been screened.
viii
Table of Contents
DEDICATION .................................................................................................................................... iv
ACKNOWLEDGEMENTS .................................................................................................................... v
ANNOTATIONS................................................................................................................................. vi
ABSTRACT ................................................................................................................................... vii
1. INRODUCTION ......................................................................................................................... 1
1.1 Company Profile .................................................................................................................... 1
1.1.1 Background ..................................................................................................................... 1
1.2 Vision ..................................................................................................................................... 2
1.3 Mission and Mission Statement ............................................................................................ 2
1.3.1 Mission ........................................................................................................................... 2
1.3.2 Mission Statement.......................................................................................................... 2
1.4 Core Values ............................................................................................................................ 2
1.5 Southland Organisational Structure ...................................................................................... 3
1.6 The firms Schedule of Services are: ...................................................................................... 4
2.0 Southlands Project Approach ................................................................................................... 6
2.1 Office documentation: .......................................................................................................... 7
3. ACCOUNT OF WORK PERFORMED ..................................................................................... 8
3.1 PROPOSED ZEIPF GWERU MEGAWATT HOUSE ......................................................... 8
3.1.1Background ...................................................................................................................... 8
3.1.2Tasks Performed .............................................................................................................. 8
3.1.3 Design Methodology ...................................................................................................... 9
3.2.1 Design Calculations....................................................................................................... 11
3.2.2 Column axial loads and foundations section ................................................................ 25
3.2.3 Bulk Earthworks Calculations and Civils Bill of Quantities Pricing................................ 28
3.2.4 Administrative work carried out on ZEIPF Gweru Megawatt Project. ......................... 31
3.2.5 Conclusion .................................................................................................................... 32
3.2.6 Experience gained ........................................................................................................ 33
3.3 ZEIPF Proposed Spar Distribution Centre ............................................................................ 34
3.3.1 Background: .................................................................................................................. 34
ix
1. INRODUCTION
The five year Honors Undergraduate Degree in Civil and Water Engineering at the
National University of Science and Technology pre-requisites a student to go for
industrial attachment where he gets a platform to apply the theory he has attained in his
first three academic years and also develop and nature practical skills he will acquire
through the whole fourth year he is attached. The faculty designed its programs to
incorporate practical experience through a full academic where he is under supervision
from his assigned industrial supervisor. The student will execute actual and real
engineering work during the attachment period with the help of the industrial supervisor
which his performance will be evaluated and commented in his log book every four
weeks.
The student dedicates this chapter to introducing to you Southland (Pvt) Limited, where
he got the opportunity to get an appreciation of the civil engineering field.
They also believe in managing client expectations, preferring to deliver beyond what they
project themselves to be. Southland is a member of the Zimbabwe Association of
Consulting Engineers (ZACE), Association for Project Managers in Zimbabwe. Its
principals are Professional Engineers in South Africa and Zimbabwe and professional
Construction Project Managers in South Africa and Zimbabwe.
1.2 Vision
To mix tried and tested methods with new ideas, to champion new concepts in
construction delivery.
We seek to communicate effectively with our clients to deliver property facilities that fit
owners functionality and investment needs .We emphasise initiating and planning
projects properly to avoid downstream problems.
1.3 Mission and Mission Statement
1.3.1 Mission
Our mission is to deliver projects where design reflects due diligence and application of
competent engineering principles.
1.3.2 Mission Statement
We strive to produce projects whose design fits their purpose, projects that are cost
effective and functional.
1.4 Core Values
We aim to overwhelm our clients with:
Goodness
Proactivity
Capacity
The trainee was dynamically involved in all departments of the firm which tangled both
technical and administrative roles on his tenure at Southland.
Reinforcement detailing.
Design Calculations.
Reinforcement Inspections.
Requesting Quotations.
Filing documents both in soft copy on the Network Server and in hard copy and
maintaining Drawing issues register.
Preliminary drawings: These are drawings that are based primarily from outputs of
preliminary design stage. They are issued for approval before any work commences and
to be used for cost estimation by the Quantity Surveyor.
Tender drawings: These are produced for tendering stage to declare the intentions of the
engineer in the project concerned. They help to show the approach the engineer will
adopt in fulfilling the task at hand. They are used by the contesting Contractors for
costing the Scope of Work to be Performed and Bidding.
Construction Drawings: These are produced after all permission has been granted to
proceed with the works. They are used for setting out the Works from the drawing to the
actual work on the ground. This drawings are based on detailed design and contains
necessary details for the awarded Contractor.
1.8.1.3 Prokon
This is a computer program that is used to calculate aspects of structural elements like
adequacy of a section to resist moments, shear force, torsion amount and size of
reinforcement either by evaluating current sections or designing for lightest sections.
3.1.1Background
ZEIPF is a defined contribution scheme offering pension saving facilities for current staff
and pension benefits for live former employees of ZESA Holdings and its subsidiaries.
The proposed Megawatt House Gweru being funded by ZEIPF will have the ZETDC
Gweru Office as the anchor tenant located at the back of the site with a planned mixed
use facility fronting the road as a future development. The size of the stand is more than
adequate to accommodate the proposed head office as well as the various intended
commercial mixed use. Southland were consulted to provide structural and civil
engineering services for the proposed development.
3.1.2Tasks Performed
The student was tasked to do the preliminary design of the six storey office block from
the Architects drawings. The layout and size of members are very often controlled by
architectural details, and clearances for machinery, equipment, head room available,
ceilings, HVAC, and bulkhead. The student had to check that the sizes are adequate to
carry the loading, or alternatively decide on structural member sizes that are adequate and
if the Architect had provided member sizes that were too big for the loading and student
had to suggest adequate structural members which are smaller in order to optimise the
8
design that is put it within the provided Clients budget and also making the design more
efficient, safe and economic
The Architect in her architectural design had provided for an allowance of:
230mm wide load bearing external walls which will not change.
For the outside columns the Architect had insisted that she would want them to be kept to
the proposed sizes of 600x600mm for aesthetic reasons only the interior columns can be
altered.
The preliminary analysis had to provide the maximum moments and shears in order to
ascertain reasonable dimensions.
3.1.3 Design Methodology
The student followed the steps outlined by the flow chart illustrated in Fig 3.1 in coming
up with the adequate structural member sizes for the office block building .The British
Standard(BS) is the adopted Code of Practice for structural designs performed by the
student.
Fig 3.1 Preliminary member sizing Flow Chart followed using Code of Practise
BS 8810
CL 2.4
CL 3.2.1
IMPOSED LOADS
CONCRETE GRADE
ESTIMATED SELF
WEIGHT
CONCRETE COVER
DEAD LOADS
MINIMUN SECTION
PRELIMINARY ANALYSIS
ESTIMATE d FROM
CL 3.4.4
M/bd Fcu0.156 SINGLY REINFORCED
0.156< M/bd Fcu<10/Fcu DOUBLY REINFORCED
V/bd < MAX ALLOWABLE
CL 3.4.5
CL 3.4.6
CHECK SPAN/DEPTH
RATIO
10
The Principal Engineer suggested to have two approaches to the structure which are;
The flat slab is a reinforced concrete slab supported directly by concrete columns without
the use of intermediary beams with a slab of constant thickness throughout or in the area
of a column it may be thickened as a drop panel or the column of constant section that
may be flare to form a column head. The slab beam arrangement as the name suggest
follows the path of slab beam-column path.
The flat slab design has the following advantages;
Windows can extend to the underside of the slab and no beams to obstruct natural
lighting and circulation of air therefore less energy needed for air conditioning
and lighting.
Method of Design
Flat Slab Method
11
REF
CALCULATIONS
RESULT
BS
8110-1
Table
3.9
BS8111
Table
4.9
d=212m
m
h
=250mm
12
REF
BS6399
-1
Table 1
CALCULATIONS
DEAD LOADING
self-weight(24KN/mx0.25m)
ceiling
screed & finishes
services
water tank (5000L) spread over 1 panel
area=5.5x5.5 =30.25m
therefore load =50KN/30.25=1.61KN/m2
KN/m
6
0.6
0.44
0.1
1.65
8.79
TOTAL GK=
BS
6399-3
CL.4.2
C
RESULT
IMPOSED LOADING
TOTAL QK=
Gk=8.79
KN/m
KN/m
1.5
1
2.5
QK=2.5K
N/m
design loading
N=1.4gk +1.6qk
=1.4x8.8+1.6x2.5=16.32KN/m
BS
8100
RC
Design
by
W.H
Mosley
&J H
Bungey
N=16.32
KN/m
13
chapter
8
F=630 for
internal
column
BS
8100
RC
Design
by
W.H
Mosley
&J H
Bungey
L=effective span
,half column strip =5.5/4=1.375m
Lx=Ly=1.375x2=2.75m
chapter
8
Lx=Ly=2.
75m
14
REF
CALCULATIONS
RESULT
1) Bending Moments
F=494
KNm
Ms=298.6
8 KNm
2) Shear Force
@ first interior Support
Vd=0.6F
=0.6x493.68KN=296.21KN
Punching Shear Check
V=0.67
ok
15
REF
CALCULATIONS
RESULT
500KN
Dead loading
Self-weight(24KN/mx0.25m)
Ceiling
Services
Screed & finishes
Wall Partitions
TOTAL Gk=
imposed loading
KN/m
6
0.4
0.25
1.2
2.5
10.35
gk=10.35
kN/m
KN/m
16
2.5
2.5
qk=2.5K
N/m
N=1.4x10.35+1.6x2.5=18.49KN/m
Force load on each interior column every flight
level =N x area of panel
=18.50x5.5x5.5 =559.63KN560KN
b=206m
m
17
(300x300)mm
B1=300m
m
Vp=N/(perimeter of Shear x d)
Vp=N/(2a+2b+12d)d
BS
8110-1
Table
3.8
V=1.36
ok
18
REF
CALCULATIONS
RESULT
ISTRUCT/ICE
MANUAL
FLAT
SLAB
CL
3.7.6
2)
Shear Check at the critical section
i.e. 1.5 d from column perimeter
boundary;
Vd=V/ud< Vc u=critical perimeter
1.15x300x10/3744x212=0.45< 0.584=Vc
V= 0.45
ok
B1350x350
mm
B2460x460
mm
19
3340.5KN =11.8 b
b=532.1mm adopt 600x600mm column size
Conclusion the Architect's Column Sizes Are
adequate
PAD FOUNDATION SIZING
20
21
Method of Design
Roof Design
Design of Steel Roof structure to be done in accordance
with:
BS6399(Part 3 - Imposed Roof Loads)
BS5950(Structural use of Steel)
Code of practice 3 Chapter 5 (CP3)
Use of Structure
Office Block
Assumptions
All steel to be used is to be of Grade43
The roof is to be designed as an inaccessible roof
Roof Loading
REF
CALCULATIONS
BS6399
Live load
Minimum UDL for roof width no access
qk = 0.6 kN/m2
RESULT
0.044
0.05
0.1
0.018
0.03
0.242
gk = 0.242
kNm-2
qk = 0.6
kN/m2
cl 4.3.16
Wind Load
22
CP3
-1
Vs =
19.2ms-1
Dynamic Pressure
q=kVs2
where k = 0.613
q = 0.613 x 19.22 = 226
Force acting on Roof Surface
F = (Cpe -Cpi)qA
at zero degrees
Cpe = 0.7
Cpi = -0.3
Area of roof truss=length of truss X truss spacing
Area of roof surface = 22.23x5.750=128m2 (Area Of
Truss).
F = (0.7 - (-0.3) )x 226 x 128= 28.93kN (Per Truss)
Force acting per node = Force/ the number of nodes per
truss
= 28.93 / 20= 1.45 kn
wk = 1.45
23
REF
CALCULATIONS
Dead loads Per Node
RESULT
DL=1.55
kN/node
IL=3.83
kN/node
Load Cases
load Case 1
1.2gk + 1.2qk +1.2wk
= 1.2( 1.55+1.45+3.85))
= 8.076kN/m2
Load Case 2
1.4gk + 1.6qk
= 1.4x1.55 + 1.6x3.83
= 8.3 kN/m2
N=8.3kn
24
loading of purlins
W=9.96kn/
m
This loading values where then used by other Engineers in the analysis of the roof
trusses.
3.2.2 Column axial loads and foundations section
The trainee was also instructed to calculate the total critical loads into columns in order to
get the loads for the foundations. Columns are structural members in buildings carrying
roof and floor loads to the foundations. Columns primarily carry axial loads, but most
columns are subjected to moment as well as axial load. The student had to calculate the
axial loads of the column stack which comprised of the roof, floor slabs and beams in the
case of the shopping mall. Each internal column would support four quarter slab panels
thus making it a full panel supported by each column. The loads that act on a structure
normally take the path:
1. The roof loads flow through the purlins to the truss supported by columns .The
truss produce reaction forces at the supports (columns) in which the loads flows
through into the foundations that transfer the load into the ground. For large truss
spans the loading may follow the route - purlin, truss, girder, column, and finally
to the ground.
25
2. Loads acting on the slab are transferred into the beams and then from beams into
the columns to the foundation and dying into the ground. For flat slabs where
there are no intermediary beams the loading from the slab is transferred directly
into the columns.
The column loading calculated were the Office Block columns, Supermarket columns,
and the Shopping mall columns. Each building section the student calculated the critical
edge column and the critical interior column
The total load through the column is equal to the summation of dead loads or self-weight
and the imposed loads. Dead load is due to the weight of walls, permanent partitions,
floor slab self-weight, roof self-weight, finishes and all other permanent construction
including services of a permanent nature. The imposed load is assumed to be produced by
the intended occupancy or use, including the weight of movable partitions, distributed,
concentrated, impact and inertia loads.
The student calculated the dead loads from the unit weights given in BS 648 then
multiply the unit weight by the member dimension or from the actual known weights of
the materials used. The imposed loads were calculated from the BS6399 Part 1 by
multiplying the uniform distributed loads with the applied area.
Then Total service load =Total dead load + Total imposed load
Total Ultimate Load=1.4 x total dead load+ 1.6 x total imposed load
26
Supermarket
Office Block
Shopping Mall
Columns
Columns
Columns
Edge Columns
650kN
Internal Columns
984kN
1489kN
2278kN
756kN
1210kN
The Student was also instructed to come up with a ground slab, pile cap, and pile section
for the building. Soil Mechanics Laboratories (Pvt) Ltd had performed the geotechnical
investigation on the building site and the results suggested that piling and a suspended
ground floor as the best option. In view of the bearing capacities in their soil report, the
soils are silt clay and have relatively low bearing capacities and are expansive soils.
From their experience of these type of soils, they envisage encountering hard surface (or
rock) 7m to 9m from the present ground level, however this has to be determined solely
by the piling contractor. The trial pits tests had been conducted up to a depth of three
metres.
Ground beams of 230x600mm from the top of the slab through the pile cap
2 Piles of 450mm diameter into each pile cap the piles intruded by 60mm into the
cap to avoid lateral movement or piles sliding off the pile cap
Two 200x600mm deep void formers between each pile cap couple and under the
ground slab. The void former light expanded polystyrene membranes or just card
27
board which are put under suspended ground floors of high reactive of expansive
soils. The void formers creates voids and when the soils expands, it expands into
the voids thus avoiding the reactive soil put stress on the ground slab.
The Supervisor instructed the Student to calculate the earthworks volumes that will be
moved on the site using the site topographical map with spots heights and the road and
storm water layout which had the levels for the finished pavement. The building level had
been setup at 1421.55 on top of the slab level.
Estimation of areas and volumes is basic to most engineering schemes such as route
alignment, pavement design for both roads and parking and creating platform for the
building. The excavation and hauling of material on such schemes is the most significant
28
and costly aspect of the work, therefore the cut and fill had to be balanced and far as
possible to reduce costs. The Quantities were produced for tender Bill of Quantities
pricing. The student used the Spot Heights Method to calculate the excavations and fill.
This method uses grid levels from which the depth of construction is from the natural
ground level to the pavement level or building platform .The volume is computed from
the mean depth of construction in each section forming a truncated prism, the bottom area
used was a square of sides 10x10m.
The volume of Excavation =Area of Square Grid X (mean natural ground spot heights of
the square-pavement level or building level.)
=A X [(S1+S2+S3+S4)/4 PL
Where the Area of the grid was 10X10m=100m
29
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
-542
6053
30
The student was also tasked by the Supervisor to price civil works tender Bill of
Quantities .The trainee had to get some rates through quotations and engaging suppliers.
The Bill of Quantities shows item, bill description which describes work to be performed
or item to be supplied and fixed, the unit of measurement ,the quantities of the item ,rate
of the item per unit and then the amount .The BOQ structure is such that it has a cover
page, summary, the preliminaries and generals ,and measurement section.
For all the internal design review meetings the student had to take minutes and distribute
them. The student had to be very attentive to detail and scribe very quickly to avoid
missing important proposals or queries and statements made in the meetings. When
preparing minutes the trainee had to follow the following setup:
Cover page (meeting name, number and purpose, date and location, those present
and absent,
The Student at most times after meetings was tasked to produce action plans and query
sheets if any queries have been raised in the meeting.
Action Plans consisted of actions that where discussed in meetings, it would consists of
an action point, the person to take the action and timeline of that action. On all occasions
31
action plans had to be distributed before the meeting minutes where prepared so that the
people sited for the actions can get notified.
Query sheet or Request for information list is a document prepared to formally request
for essential information to necessitate the progression of works or a task that is being
done on a project.it has the name of the person making the query, the information
requested, the respondent, the status and the response to the request, then the date of
response .The student would get tasked to write all queries that had to be sent to the
Architect on the Megawatt Project an example of requests made would be a request for
section details of the roof service room and clarification on the number of elevators in the
building .
For every engineering drawing that was submitted to the Quantity Surveyor ,Project
Manager ,and Architect it had to be accounted for by the use of issue sheets which the
engineering consultant and the recipient had to sign to acknowledge that drawings where
received. The trainee was always tasked to prepare the issue sheets on those occasions.
3.2.5 Conclusion
The study of alternative solutions and continuous liaison with other members of the
design team is important to come to a mutually agreeable outline scheme. The
preliminary designs where used to draw the structural layouts for the information
drawings sent to the Quantity Surveyor for cost estimating, which entails the valuation
(apportioning costs to the different measured parts of the work) of the probable inputs
(resources) that will be required to complete the work. The estimated cost is the total
estimated quantities (labour, material, plant usage and other indirect costs) multiplied by
estimated or known unit cost. It is usually used as one of the considerations in the
determination of a price at which the contractor is prepared to do the work. The
32
Information drawings were also sent to the Project Manager to evaluate the scope of
works, the Architect, and Client for approval.
3.2.6 Experience gained
33
3.3.1 Background:
The proposed development was a Zimbabwe Electricity Industry Pension Fund Project,
being the client of the project and the tenant being Spar where the building was to be
used as the tenants headquarters and distribution centre for all its commodities.The Spar
Distribution Centre sewer layout out has been drawn before the student was attached at
the company .When he got attached drawing the sewer long sections was one of the first
assigned meant he was handed.
The student was instructed by the Supervisor to draw long sections of the sewer line from
the sewer layout AutoCAD drawing, in producing the long sections layout the student
had to calculate the manhole depths, pipe gradient
3.3.3 Calculating Gradient of Pipes and Depths of Manholes
The student had to establish a chainage route for each sewer line branch, a long section
was produced for each sewer line branch. The ground levels for the manholes were
extrapolated from the contour layout that is superimposed onto the sewer line layout.
34
Where ILN = Invert level of the Nth manhole, ILN-1= Invert level of the (N1)th manhole.
D = Distance between manholes and S = Pipe Gradient
GL = Ground Level and IL = Invert Level
35
36
37
The student was tasked to produce a layout for a fuel tank which was supported by two
reinforced concrete plinths of 1300mm long which had to have its own foundations for
support .For reinforcement fixing details the plinth had S245 mesh wire, the trainee sized
the plinth to produce a beam of dimensions 200X500mm deep and the strip foundations
was 500x230mm deep.
The student is now able to represent the sewer long sections on an AutoCAD
drawing.
38
3.4.1 Background:
The project entails the design and drawing structural layouts of a building which was to
be used as a warehouse. The warehouse was a double storey with the ground floor to be
used for distribution and storage of stock. The first floor was to be used as office space
.The warehouse ground floor had eight bays of dimensions 5x14.23 metres .The first
floor only covered one and half bays with the half bay being a cantilevered balcony .The
first floor hand columns and structural walls for support. The Architect had proposed a
concrete stub column up to the first floor with a steel H-Section protruding from first
floor to the roof.
3.4.2Task Performed.
The student produced the structural layouts from the calculations done the Supervisor of
the first floor, stair case and columns. From calculations the slab had to be 150 mm deep
with four reinforced concrete columns supporting a bay and the balcony cantilevered.
The Structural Floor level (SFL) of the first floor was set at 2.750m from the Ground
SFL .The slab was also supported by 230mm load bearing walls. The staircase slab had
also to be 150mm deep or 150mm waist with a rise of 153mm and tread of 300mm.
For Staircases 700>2R+G>550mm where R=rise and G =Going or trend.
2(153) +300=606mm>550 mm and <700mm therefore OK
The student had to produce the reinforcement fixing details for the structural members.
39
Check directions of span of slab, outer bottom steel B1 should be parallel to short
span, and check layering of slab reinforcement
Check location of laps remembering the maximum length of bar available and
locally its available up to 6m.
The should be top steel on every support to transfer moments into the support and
resisting the hogging moments at the supports
In slabs there is moment steel and distribution steel, B1 and T1 is represent the
moment steel which actually resists loading and carry the moments and B2& T2
distributes the loading into the moment steel and also maintains rigidity of the
reinforcement cage.
For overlapping of two bars 50d (d= rebar diameter) the overlapping distance.
40
Fig 3.4.1 Reinforcement fixing details for column and base pad
41
Fig 3.4.2 Fixing Details of Reinforcement for the First Floor slab &Stair case
42
The fixing details for reinforcement should be done with precision to avoid mistakes
which might be costly to the client and to the engineer it might compromise the
robustness of the member section. The drawing must be through checked if any
reinforcement bar might have been missed of misplaced. The reinforcement fixing
drawing is then used to produce a bending schedule.
The experience gained:
The student can also produce structural layouts from Architectural drawings
easily.
43
3.5.1 Background
R.O.M Bin, is the first port for raw ore. The ore will pass through bar screens for the first
screening. Boulders of considerable size are screened and collected manually. Due to
Safety Regulations requirement, boulders are now collected mechanically using a loader
and therefore imposing additional dead and live load to the structure.
The task performed by the student involved calculating the total loading that will act on a
full filled and loaded bin .The student had also to input calculated load into the Prokon
software for member section analysis to evaluate if the imposed weight of the loader to
compromise the strength of the structure
Loading calculation:
PROJECT : SHAWA MINE
Structural Design and Loading file
44
Method of Design
Runoff Mine Design
Design of Steel structure to be done in accordance with:
BS5950(Structural use of Steel)
Use of Structure
Assumptions
All steel to be used is to be of Grade43
Assume the specific gravity of Rock material (Gs)=2.7
Volume of the trapezoidal shell is half the cubical envelope of the
shape
REF
CALCULATIONS
RESULT
Dead Loads.
Volume of ore material contained
=4.6x4.6x3+0.5(4.6x4.6x2.4)=88.9 m3
soil
mechanics
J.N Smith
gk =
2500KN
Imposed Loading
taking 25% of the dead weight of truck
0.25x 70KN=17.5KN
qk=17.5KN
45
REF
CALCULATIONS
RESULT
Total load
N=1.6Qk+1.4Gk
=1.6x17.5 +1.4x2500
=3528KN
UDL LOAD=3528/(4.6X4)=191.7kn/m
UDL=191.7
kn/m
46
47
48
Elements
Description
Columns
203x133x30
Engineering Recommendation
I UB
Horizontal Bracings
203x133x30 GOOD
Cross bracings
90X90X6
POOR
A1
Slender, requires
additional bracing
49
3.6.1 Background
This project was a double storey house to be built in the one of the hefty suburbs of Harare
in Mount Pleasant.
Architectural drawings and site geotechnical investigation results were issued to the
Supervisor from the Architect and recommended a strip foundation of a depth
1200mm.From the Architectural drawings the student came up with the following
structural layout drawings which are:
3.6.2 Tasked Performed
Foundation and ground floor layout:
The student produced a foundation layout with a strip footing as recommended by the
geotechnical report and deep up to calculated depth of 1400mm by the Engineer. Strip
footings are used under relatively uniform point loads or line loads. The main structural
function of the strip is to disperse the concentration of load sideways into an increased
width of sub-strata in order to reduce the bearing stress and settlement to an acceptable
limit and also strip foundation distribute loads longitudinally.
The strip foundation of reinforced concrete ground beam. The ground slab had to be
100mm thick with S193 fabric mesh on top with cover of 25mm.For 230mm load bearing
walls
Reinforcement fixing details For Strip Foundation:
The detailing of the strip footing was done by the trainee .The strip beam for 230mm load
bearing wall had dimensions of 700mm breath by 230mm depth with six Y12 straight rebar
and Y8 links with a spacing of 250mm.The student prepared the bending schedule for the
strip footing of the whole foundation.
50
52
53
The spread of the links where indicated by the student above the elevation of the beam with
and indicator line terminated by arrow heads, and the links are represented by a
perpendicular thick line.
Bent up shear bars (U bars)
Two U-bars were put on each side of the beam, the horizontal leg of the bent up shear bars
were made to extend at least a tension anchorage length in this case the trainee used a
horizontal leg lengths of 600mm.
Stir case detailing
The detailing of the slab of a stair case is the same as that of a slab, the student showed the
reinforcement on plan flights and landings where they differ for each storey height. The
trainee also showed reinforcement layout on stair case section.
3.6.3 Conclusion
The reinforcement fixing detail drawings are used by the contractor or specialist steel fixer
to tie the reinforcement.
The bending schedules are used by
Reinforcement fabricators
3.7.1Background
The proposed development will involve the construction of a multi-storey mixed use
development to perform the following functions;
Bus Interchange
Office Tower
The Architectural Concept plan has a support Grid of generally about 10m by 12m
throughout the entire footprint of the development.
This grid may be maintained for footprints confined within the boundaries of the Office
Towers and Budget Hotel Tower but is mainly functional for the following areas/levels
because the columns need to have larger spacing to allow for:
Car Parking,
Bus Interchange,
55
All of which are to be constrained to the fourth level of the structure and with most of their
plinth outside the confines of the 3 tower structures, the support grid can be widened. In
which case Frame elements will be primarily ribbed or Coffer/Waffle slabs supported
directly on columns for the four levels.
The depth of ribs excluding topping should not exceed four times their average
width;
56
The thickness of structural topping or flange should not be less than 50 mm or one
tenth of the clear distance between ribs (Table 3.18 in BS8110 -1985).
The waffle slab had 150mm wide ribs which are 675 mm deep and running in both
orthogonal directions and a slab topping of 150mm and within the 675mm ribs .The ribs
were set at 500mm apart centre to centre and the slab was made a solid from the edge of
the supporting beam to the adjacent rib to increase the shear strength at the supporting
beams. Floor slabs are supported on four sides two-way spanning action occurs therefore
the ribs spanned in both directions. The typical one panel layout of a coffer slab is shown
by the drawing shown in Fig 3.7.1
The student is now informed on the coffer slab layout and specification details.
The student is also now familiar with the design of the waffle slab.
57
58
3.8 Inspections
The student along with the Supervisor conducted construction inspections on
various projects that were under construction. When putting up a structure it is
imperative for the design engineer to conduct inspections and checks on each stage
of construction to ensure that specifications and, instructions issued by the engineer
are adhered to, and thus avoid compromising the robustness of the desired structure.
Inspection of rail track level by a theodolite to check if the rails are on the same
level and parallel and supporting plinth level of granite cutting machine on
Southern Granites Expansion project .The granite would be transported on the
rails.
Comments were made about the inspection done, the next instructions were issued in the
site book and signed.
59
Developed good file organisation skills got familiar with the process of issuing
drawings and schedules with an issue sheet, for future reference.
Got skilled in the reinforcement detailing and fixing details of slabs, beam,
staircases ,columns and foundation bases, and strip footings and also the
preparation on the reinforced detailed member bending schedules
5.2 Recommendations
61
References:
Rex Lancaster, Chaplin E.C, Doran DC and Higgins J B, (1989), Standard Method of
Detailing Structural Concrete, Upper Belgrave Street, London.
Reynolds, C. E., and Steedman .J .C. (1999), Reinforced Concrete Designers Handbook,
E& F.N. Spon , Taylor &Fransic Group, London, UK.
Trevor Draycott (1990), Structural Elements Design, Oxford Auckland, Johannesburg,
Delhi.
W.H Mosley and J.H Bungey., (1976), Reinforced Concrete Design, Macmillan,
University of Liverpool, United Kingdom.
MacGinley .T .J, and Choo. B.S, (1990), Reinforced Concrete Design Theory and
Examples, E& F.N. Spon, New York & London.
62
63
64