Seafco Research Development
Seafco Research Development
2014
PREFACE
Seafco Public Company Limited is a deep foundation contractor established in 1974. The company
has been involved in numerous foundation and deep excavation projects in Thailand, including
large-scale foundation works, infrastructure projects, and more recently the underground structures
of Bangkoks second subway project (MRT Blue Line Extension Project). SEAFCO expanded its
operation overseas and successfully took part in the construction of diaphragm walls for Marina
Bay Sands in Singapore in 2007. SEAFCO has also established Seafco (Myanmar) Company
Limited in late 2013 and completed two projects to date.
Consolidating state-of-the-art technology, sophisticated equipment and engineering professionals,
SEAFCO initiated the innovative techniques and solutions in geotechnical and foundation
engineering in Thailand and Myanmar. To improve the currently used methods, material, system,
design concepts and construction techniques, SEAFCO has spent considerable time and effort
on Research and Development activities.
SEAFCOs R&D team continuously conducts research on bored piles, barrettes, diaphragm
walls, associated testing methods, deep excavation and other geotechnical engineering works.
New findings and research results have been presented in a number of conferences and
seminars organized by various institutions both domestically and internationally. In forty years,
R & D Division of SEAFCO has produced over 100 technical papers (both in English and Thai)
which were presented and published in international conferences held in various countries. The
purpose of this publication is to mark the auspicious occasion of SEAFCO 40th Anniversary. It is a
compilation of selected published papers in the international conferences. The case studies and
research works presented in these papers are mainly from the projects carried out by SEAFCO
in Bangkok and other parts of Thailand. Published papers authored by SEAFCOs employees in
other major projects and research studies overseas are also included.
I would like express my appreciation to the clients, consultants, designers, universities, institutions,
the Engineering Institute of Thailand under H.M. the Kings Patronage (EIT) and partners who have
been continuously supporting SEAFCO for 40 years. I also would like to acknowledge the effort of
SEAFCOs R&D team for their commitment and hard work in the research works.
I hope that researched works and findings contained in these publications will be useful and serve
as a source of reference to all in the field of geotechnical and foundation engineering, particularly
those who are involved in the construction industry of Thailand.
Narong Thasnanipan
President & CEO
Seafco Public Company Limited
FOREWORD
First of all, I would like to extend my congratulations to SEAFCO for 40 years of successful
establishment, not only as a business entity but also as a great contributor for construction industry
of Thailand.
SEAFCO is well known for research minded initiatives in foundation engineering. SEAFCO shares
outcomes of its R&D works to the engineering society by publishing technical papers, organizing
conferences, and delivering lectures in various institutions in both Thailand and overseas. I
proudly acknowledge the contributions SEAFCO has been making to strengthen the foundation of
civil engineering society in Thailand and beyond.
Since the time I was working on my doctoral research, I have found SEAFCOs publications
in various international conferences very useful to understand practical aspects of deep
foundations. SEAFCO puts the innovative theory into practice by equipping itself with knowledge,
experience and professionalism. SEAFCO R&D team has put in commendable effort to compile
all of their published papers and produced the book Current Practices in Deep Foundations
and Diaphragm Wall Construction in Thailand. Geotechnical specialists, foundation engineers,
structural engineers and practitioners in construction industry will find this book beneficial.
I, as the President of the Engineering Institute of Thailand under H.M. The Kings Patronage (EIT),
would like to sincerely thank Seafco Public Company Limited for endless support they have been
providing to the various activities of EIT under the leadership of CEO Khun Narong Thasnanipan. In
particular, SEAFCOs great support in a leading role to Thailand Underground & Tunneling Group
(TUTG) in winning the bid for Thailand to host the World Tunnel Congress 2012 and successfully
organizing the event at Queen Sirikit National Convention Center in Bangkok from 18 to 23 May
2012.
I believe SEAFCO will continue to grow in business with trust and confidence of its stakeholders.
I am also confident that SEAFCO will maintain its position as the leading innovators of foundation
and geotechnical engineering.
I wish SEAFCO all the success.
Table of Contents
Record Load Test on a Large Barrette and its Performance in the layered
soils of Bangkok
Thasnanipan N., Maung A. W. & Z. Z. Aye ................................................................. 107
Performance of Wet-Process Bored Piles Constructed with
Polymer-Based Slurry in Bangkok Subsoil
Thasnanipan N., Z. Z. Aye, Submaneewong C. & Teparaksa W. ............................... 117
Barrette of Over 50,000 kN Ultimate Capacity Constructed in
the Multi-Layered Soil of Bangkok
Thasnanipan N., Z. Z. Aye & Teparaksa W. ................................................................ 135
Performance of Toe-grouted Large Bored Piles in Sand-Gravel
Formation of Chiang Mai City, Northern Thailand
Thasnanipan N., Z. Z. Aye & Teparaksa W. ................................................................ 145
Application of Polymer-based Slurry for Wet-process Bored Piles
Construction in Mylti-layered Soil of Bangkok
Z. Z. Aye, Singtogaw K. & Submaneewong C. ........................................................... 155
Development in Construction of Bored pile and Barrette for
Infrastructure Projects in Thailand, A Country Report
Thasnanipan N., Singtogaw K., Z. Z. Aye & Pravesvararat S. .................................... 163
Behaviour of Polymer-based Slurry for Deep-seated Bored Piles
in Multi-layered Soil of Bangkok
Thasnanipan N., Z. Z. Aye & Boonyarak T. ................................................................. 175
Effectiveness of Toe-Grouting for Deep-Seated Bored Piles
in Bangkok Subsoil
Thasnanipan N., Z. Z. Aye & Submaneewong C. ....................................................... 185
C urrent Practice and Future Trends of Cast-in-place Deep Foundation
in Thailand
Thasnanipan N., Singtogaw K., Z. Z. Aye & Pravesvararat S. ................................... 199
Development and Achievement of Deep-seated Bored Piles and
Barrettes Construction in Thailand in the Past Forty Years,
A Country Report
Thasnanipan N., Z. Z. Aye, Submaneewong C. & Boonyarak T. ................................. 211
Barrette for High-rise Buildings and Heavy Structures in Bangkok
Sub-soil Thasnanipan N., Z. Z. Aye, Boonyarak T., Kitpayuck P.
& Thasnanipan N. ...................................................................................................... 223
Barrettes
Strip Piles
MEMBER OF
A - 13
A - 14
A - 15
A - 16
A - 17
Conditions
Increment %
In Failure Load
In Skin Friction
In End Bearing
12-24
9-27
11-21
GROUTING ASSEMBLY
Current base grouting practice
uses two U-circuits consisting of
12mm diameter PE tubes attached at the bottom with 12mm
GI pipes with perforations
wrapped with rubber sleeves
(manchettes). They are attached
with the reinforcement cage to
place the manchettes at the base
of the pile.
GROUTING CRITERIA
Grout Pressures:
Maximum
pressure developed is a single
most important parameter.
It
should be gradually achieved by
low injection rates to avoid hydraulic fracturing.
Grout Volumes:
Usually
total grout take is not a limiting
criteria and is used to decide
about the staged grouting. Generally, the higher the required
maximum pressure to be
achieved, the higher will be the
grout volume under similar condi-
Injection Rates:
It is not a
direct controlling parameter but
instead used to achieve maximum pressure in a gradual
manner. Injection rates of 510litres/min are proved to be
satisfactory.
Residual Pressures: Normall y
residual pressures of the order
of 20-30% of target maximum
pressure are desirable.
PERFORMANCE OF
GROUTED PILES
BASE
L o ad (to n )
0
500
1000
1500
2000
2500
3000
3500
4000
-10
0
-20
10
Settlement (mm)
N
G
B
G
B
G
Soft Clay
Stiff Clay
Silty Clay
-30
20
Dense Sand
30
-40
40
Hard Clay
-50
50
Dense Sand
60
N o n -G ro u te d P ile - D ia . 1 .5 x6 0 .0 0 m
B a s e -G ro u te d P ile A - D ia .1 .5 x5 5 .1 6 m (3 S ta g e s - to ta l 2 0 0 0 ltr)
B a s e -G ro u te d P ile B - D ia .1 .5 x6 0 .0 0 m (3 S ta g e s - to ta l 2 0 0 0 ltr)
-60
SEAFCO
A - 18
Clayey Sand
Silty Clay
-30
Sand
Silty Clay
Silty Clay
-50
1000
1500
2000
2500
Sand
3000
Age: 61 days
30
-30
Bas e-Gro u ted Pile - Dia. 1.5x59.72m (2 Stag es - to tal 1500 ltr)
500
Silty Clay
3000
3500
20
30
Non-Grouted Pile - Dia. 1.5x60.2m
Base-Grouted Pile - Dia. 1.5x60.3m (2 Stages - total 1500 ltr)
Load (ton)
0
1500
-20
1000
1500
2000
-30
2500
3000
3500
10
Dense Sand
10
500
Stiff Clay
20
30
20
-40
Desne Sand
30
-50
40
-60
40
Age: 60 days
50
Silty Clay
SEAFCO
2500
Age: 82 days
Sandy Clay
Dense Sand
-60
2000
Age: 62 days
-10
1000
Settlement (mm)
-50
1500
10
Soft Clay
Load (ton)
0
Hard Clay
Hard Clay
Sand
-20
-40
1000
-60
-30
Load (ton)
500
-50
70
Stiff Clay
Age: 57 days
60
B
G
Stiff Clay
-40
50
Soft Clay
N
G
40
Silty Clay
-10
40
Sandy Clay
-10
30
Dense Sand
-20
20
80
-60
20
Settlement (mm)
-50
Settlement (mm)
Hard Clay
2000
10
-40
1500
-20
1000
10
Settlement (mm)
Stiff Clay
500
500
Soft Clay
Lo ad (ton)
-10
-30
-60
Soft Clay
Stiff Clay
-20
-40
Base-Grouted Piles - CP
Load (ton)
Soft Clay
-10
Settlement (mm)
60
Dense Sand
References:
Teparaksa, W., Thasnanipan, N. and Anwar M. A. (1999), Base Grouting of Wet Process Bored Piles in Bangkok
Subsoils, Eleventh Asian Regional Conference, International Society for Soil Mechanics and Geotechnical Engineering, Seoul, Korea, August 16-20, 1999. Pp. 269-272.
Lui, J. and Gao W. S. (1999), The Behavior of Post-grouting Pile Groups under Vertical Load, Eleventh Asian Regional Conference, International Society for Soil Mechanics and Geotechnical Engineering, Seoul, Korea, August 1620, 1999. Pp. 209-212.
Thasnanipan, N. (1997), Current Development of Bored Piling Techniques in Bangkok (in Thai), Technical Seminar
on Foundation 1997 organized by the Engineering Institute of Thailand, Bangkok, Thailand, February 4, 1997. Pp. 126.
Teparaksa, W. (1992), Behavior of Base-Grouted Bored Piles in Bangkok Subsoils, Piling: European Practice and
Worldwide Trends. Conference organized by the Institution of Civil Engineers, London, April 7-9, 1992, Thomas Telford. Pp. 296-301.
A - 19
Object
Contiguous bored pile wall and bored piles for construction of basement and foundation of the Rama
Thibodi Hospital.
Project Description
Bored pile wall with temporary braced excavation
method for construction of 3 level basements for car
parking.
Type of Work
Foundation Piling, Contiguous bored pile wall.
Owner
Layout of contiguous and foundation bored piles.
Rama VI Hospital.
Designer
Arun Chaiseri Consulting Engineers Co., Ltd.
Main Contractor
Ch. Karnchang Public Company Limited.
Project Schedule
2005-2006
Construction Method
Excavation with contiguous pile wall using bottom up construction method to 11.5m.
Construction Details
Foundation bored pile:
7 (0.8mx55m)
121 (1.0mx55m)
163 (1.2mx55m)
32 (1.5mx55m)
364 (1.0mx20.0m)
Excavation with braced pile wall for construction of footings and basements.
Subsoil Conditions
Soft clay:
Medium clay:
Stiff clay:
Dense sand:
Hard clay:
Very dense sand:
0.0-11.0m
11.0-14.0m
14.0-28.0m
28.0-30.0m
30.0-47.0m
47.0-55.0m
A - 20
MahaNakhon
Type of Work
Owner
Project Schedule
2011-2012
Construction Details
Foundation bored pile:
Diaphragm Walls:
0.80mx57-65m = 59 +11
1.00mx57-65m = 13+14
1.20mx65.0m = 4
0.80mx3.0mx65.0m = 1
1.20mx3.0mx65.0m = 114
9,264sqm (0.6m to 0.8m
thick x 16.0m to 22.0m)
Subsoil Conditions
Soft clay:
Medium clay:
Stiff clay:
Dense sand:
Hard clay:
Very dense sand:
Hard Clay:
Very Dense Sand
2.0-8.0m
8.0-13.0m
13.0-24.0m
24.0-38.8m
38.8-43.0m
43.0-49.1m
49.1-55.0m
55.0-67.0m
No. 144, Prayasuren Road, Bangchan, Khlong Sam Wah, Bagkok 10510, Thailand. Tel. (662) 919-0090 to 97, Fax. (662) 919-0098, 518-3088. Email: [email protected],
Homepage: www.seafco.co.th.
A - 21
Object
Construction of basement structures of a 42 storey
office tower on 9 storey retail podium.
Project Description
Construction of bored pile foundations, diaphragm
walls and deep excavation works for 2-3 level basements construction.
Type of Work
Foundation piling, diaphragm walling and substructure works.
Layout of the project.
Owner
Land and House Property Company Limited.
Designer
Palmer &Turner (Thailand) Limited.
Project Schedule
2008-2009
Construction Method
Construction Details
Foundation bored pile:
Diaphragm Walls;
Voume of Excavation:
Temporary Bracing:
Temporary Platform:
Concrete Volume:
Steel Reinforcement:
Basement Floor:
0.80mx57m = 22
1.20mx57m = 65
1.50mx57m = 183
1.80mx57m = 25
8,172 sq.m. (0.80m thick
x 18m deep)
95,000 cu.m.
1,987 tons
3,807 sq.m.
24,295 cu.m. (substructure)
4,350 tons (substructure)
30,909 sq.m.
Subsoil Conditions
Soft clay:
Medium clay:
Stiff to very stiff clay:
Hard clay:
Dense Sand:
2.5-9.0m
9.0-15.3m
15.3-40.0m
40.0-42.8m
42.8-60.0m
Completed substructure.
No. 144, Prayasuren Road, Bangchan, Khlong Sam Wah, Bagkok 10510, Thailand. Tel. (662) 919-0090 to 97, Fax. (662) 919-0098, 518-3088. Email: [email protected],
Homepage: www.seafco.co.th.
A - 22
Substructure Works
Object
Construction of foundation mats, footings, deep basements for car parking and wastewater treatment
tanks.
Project Description
Type of Work
Owner
Designer
Project Schedule
Construction Method
Construction Details
Temporary bracing:
Earth excavation:
Basement floor area:
1,478 tons
54,000cu.m
13,000sq.m.
Subsoil Conditions
Soft clay:
Medium clay:
Stiff clay:
Hard clay:
Very dense sand:
0.0-14.0m
14.0-15.0m
15.0-24.0m
24.0-40.0m
40.0m+
A - 23
Type of Work
Owner
Project Schedule
2011
Construction Details
Foundation bored pile:
Bored Pile Wall
Bored Pile Wall
Foundation bored pile:
Diaphragm Walls:
0.60mx18.5m = 126
0.60mx22-23.0m = 433
0.80mx18.5m = 393
0.80mx60.0m = 158
1.00mx60.0m = 30
1.20mx60.0m = 27
1.50mx60.0m = 308
1.80mx60.0m = 140
0.80mx3.00mx60.0m = 4
1.00mx3.00mx60.0m = 22
7,057.5 sqm (0.8-1.0m thick
x18.0-22.0m)
Subsoil Conditions
Soft clay:
Medium clay:
Stiff clay:
Dense sand:
Hard clay:
Dense Sand:
1.5-13.5m
13.5-16.3m
16.3-32.5m
32.5-34.0m
34.0-53.9m
53.9-58.0m
No. 144, Prayasuren Road, Bangchan, Khlong Sam Wah, Bagkok 10510, Thailand. Tel. (662) 919-0090 to 97, Fax. (662) 919-0098, 518-3088. Email: [email protected],
Homepage: www.seafco.co.th.
A - 24
Object
Construction of a 2 level underground car park under
a football field.
Project Description
Construction of bored pile foundations, diaphragm
walls and deep excavation works for 2 level basements and football field on top.
Owner
Srinakrin Wiroj University
Project Schedule
2008-2010
Construction Method
Construction Details
Foundation bored pile:
Diaphragm walls;
Excavation volume:
Basement floor:
Concrete volume:
Reinforcement:
0.60mx18.5m = 508
7,664 sq.m. (0.60m thick
x 16m deep)
102,000 cu.m
36,000 sqm
39,624 cu.m
4,218 tons
Excavation with diaphragm wall using top-down construction method for basement construction.
Subsoil Conditions
Soft clay:
Medium clay:
Stiff clay:
Hard clay:
Sand:
Hard clay:
Dense sand:
2.0-14.5m
14.5-17.0m
17.0-22.0m
22.0-41.5m
41.5-46.0m
46.0-49.0m
49.0-60.0m
No. 144, Prayasuren Road, Bangchan, Khlong Sam Wah, Bagkok 10510, Thailand. Tel. (662) 919-0090 to 97, Fax. (662) 919-0098, 518-3088. Email: [email protected],
Homepage: www.seafco.co.th.
A - 25
Object
Deep foundation work for wastewater treatment plant.
Project Description
Bored piles and diaphragm walls for construction of
deep basements for a wastewater treatment plant in
Bangsu, Jatujak area.
Type of Work
Foundation piling, diaphragm walling and soil improvement.
Owner
The Bangkok Metropolitan Administration.
Project Schedule
2008-2009
Construction Details
Foundation bored pile:
0.80mx57.0m= 971
1.00mx57.0m = 7
1.00mx57.0m = 380
1.50mx57.0m = 46
Diaphragm Walls:
Soil mixing:
1,734 cu.m
Subsoil Conditions
Soft clay:
Medium clay:
Stiff to very stiff clay:
Dense sand:
2.0-10.0m
10.0-13.5m
13.5-24.0m
24.0-60.0m
A - 26
Object
Underground car park with disable access, natural
light and ventilation for the Central Hospital of Bangkok Metropolitan Authority. Large open space and
garden on the roof top.
Project Description
Diaphragm wall with top down excavation method for
construction of 4 level basements for car parking and
roof top garden.
Type of Work
Foundation Piling, Diaphragm Walling, Deep Excavation, Civil Construction.
Diaphragm wall and bored pile construction.
Project Schedule
2005-2007
Construction Method
Construction Details
Foundation bored pile:
Diaphragm Wall:
Basement floor area:
Landscaping:
69 (1.8mx22m)
4,900sq.m. (0.8m thick,
20.0m deep)
11,200sq.m.
2,800sq.m.
Subsoil Conditions
Soft clay:
Medium clay:
Stiff clay:
Dense sand:
Hard clay:
Very dense sand:
0.0-11.0m
11.0-14.0m
14.0-30.0m
30.0-37.0m
37.0-42.0m
42.0-50.0m
A - 27
Object
Deep foundation works for a 47 storey luxury condominium.
Project Description
Bored piles, contiguous pile wall, diaphragm walls
and soil improvement for construction of deep basement.
Owner
Sathorn Park Co., Ltd. & Grace Ivory Co., Ltd.
Designer
Project Schedule
2007-2008
Construction Details
Subsoil Conditions
Soft clay:
Medium clay:
Stiff clay:
Dense sand:
2.5-10.0m
10.0-16.0m
16.0-26.0m
26.0-60.0m
No. 144, Prayasuren Road, Bangchan, Khlong Sam Wah, Bagkok 10510, Thailand. Tel. (662) 919-0090 to 97, Fax. (662) 919-0098, 518-3088. Email: [email protected],
Homepage: www.seafco.co.th.
A - 28
SRINAKRIN UNDERPASS
Civil Works
Project Description
Type of Work
Owner
Project Schedule
2009-2011
Construction Details
Foundation bored pile:
1.00mx29.0m =
73
0.80mx3.0x25.0m = 3
Diaphragm Walls:
13,672sqm
(0.8m thick x 25.0m)
Structural Concrete:
Reinforcement Steel:
42,230cu.m
5,266tons
Subsoil Conditions
Soft clay:
Medium clay:
Stiff clay:
Hard clay:
3.0-15.0m
15.0-18.0m
18.0-19.5m
19.5-25.0m
A - 29
RI
VE
R
BANG SU STATION
AY
A
LEGEND :
MRTA ISP (Underground Structures-North)
MRTA ISP (Underground Structures-South)
MRTA Interchange Station
MRTA Station
SRT System (Hopewell)
BMA System (BTS)
CH
AO
PH
R
GENERAL
WORK UNDERTAKEN
BORED PILES:
Dia. 0.6mx19.5-23.5m
Dia. 1.0mx36.0m
Dia. 1.2mx36.0m
Dia. 1.5mx36.0m
1.2mX3.0mX44.5-55.0m
859 tons
24,338.9 sq.m. (1.0m Thick)
1,612.8 sq.m. (1.2m Thick)
BARRETTES:
STEEL STANCHION:
DIAPHRAGM WALL:
20.25
6.03
6.03
12 nos.
95 nos.
9 nos.
5 nos.
63 nos.
20.25
Foot Path
+101.000
TOP SLAB
+98.900
CONCOURSE SLAB
Soft Clay
ORANGE LINE PLATFORM
ORANGE LINE SLAB
Stiff Clay
DIAPHRAGM WALL
BASE SLAB
+80.450
+78.450
Silty Sand
BARRETTE
C
L TRACK
C
L TRACK
D04/99
TYPE OF WORK:
OWNER:
MAIN CONTRACTOR:
DESIGNER:
PERIOD:
A - 30
SEAFCO
2-SC
2-SC
2-SC
ENTRANCE
12.1
OPEN
AREA
4-CF
4-CF
ENTRANCE
12.2
CL
CL
CL
LINE
TO RAMA IX
ROAD
2-SC
THAI
INSURANCE
R.S.TOWER
2-SC
VEN
T.
SHAFT
1
TBM
DRIVE
SHAFT
RATCHADAPHISEK RD.
ENTRANCE
12.4
CL
27.000
TO LATPHRAO
ROAD
CL
ORANGE
CL
ENTRANCE
12.3
VEN
T.
SHAFT
2
359.500
S u (t/m 2 )
10
15
SPT
N (B lo w s /ft)
40
60
B H -3
-1 0
-2 0
-2 0
-3 0
-3 0
Depth (m)
-1 0
Depth (m)
SO FT C LAY
-4 0
80
B H -2
B H -3
S T IF F C L A Y
M E D IU M
DENSE SAND
20
F IL L
B H -3 7
-4 0
HARD CLAY
-5 0
-5 0
-6 0
-6 0
-7 0
-7 0
A large volume of bentonite slurry supply, storage and treatment facilities for
an excavation up to 300 cu.m.
A - 31
Concreting a barrette with pre-placed steel stanchion, using double tremie sets .
Steel stanchions on
ready to be installed.
site,
A - 32
All rights reserved. No part of this publication may be reproduced in any form or by
any means, without the prior written permission of SEAFCO PUBLIC CO., LTD.
SEAFCO
References
Teparaksa, W., Thasnanipan, N., Maung, A. W. and Wei, S. H. (1998), Prediction and Performances of Short Embedded Cast In-situ Diaphragm Wall for Deep Excavation in Bangkok Subsoil, Fourth International Conference on
Case Histories in Geotechnical Engineering, St. Louis, Missouri, March 9-12, 1998. Pp. 686-692.
Thasnanipan, N., Anwar, M., A., Maung, A. W. and Tanseng, P. (1999), Performance Comparison of Bored and
Excavated Piles in the Layered Soils of Bangkok, Symposium on Innovative Solutions in Structural and Geotechnical
Engineering in Honor of Professor Seng-Lip Lee, AIT, Bangkok, May 14-15, 1999. Pp. 345-353.
A - 33
GENERAL
Rangsan Silom Precious (present name is Royal Charoen Krung)
building is located at the corner of Silom and Charoen Krung Roads,
Bang Rak, Bangkok. It is a 63-storey tower with six basement levels
constructed by using top-down method. Foundation bored piles of
1.5m in diameter founded in sand layer at depths up to 60m, support
the building. The piles were base-grouted. A 1.02m thick cast in-situ
diaphragm wall (toe depth 36.0m below ground level) was used for
basement excavation and construction. The maximum excavation
depth was about 20.0m. 95 built-up steel stanchions pre-founded in
bored piles were used for supporting the basement slabs and parts of
superstructure during simultaneous construction of basements and
the super structure. Three basement slabs, B1, B3 and B5 with
openings were used as lateral supports to the diaphragm wall to allow
excavation reach to the required depths.
WORK UNDERTAKEN
BORED PILES:
Section of building.
Dia. 1.0mx36.0m
5 nos.
Dia. 1.5mx60.0m
529 nos.
534 piles
Built-up Sections
95 nos.
13,748 sq.m. (1.02m Thick)
5 Inclinometer Tubes in the wall and 1
Tube in the soil behind the wall.
BASE GROUTING:
STEEL STANCHIONS:
DIAPHRAGM WALLS:
INSTRUMENTATION:
I-1
I-2
I-6
I-3
LEGEND
BORED PILE
BORED PILE WITH STANCHION
I-5
15
25
50m
I-4
TYPE OF WORK:
OWNER:
SUPERSTRUCTURE
CONTRACTOR:
DESIGNER:
PERIOD:
SEAFCO
A - 34
SPT
Top Fill
10
Su (t/m2)
20
30
N (Blows/ft)
0
40
-10
-10
-20
-20
20
40
60
80
100
Depth (m)
Dense Sand
Depth (m)
-30
-30
-40
-40
-50
BH-1
BH-1
BH-2
BH-2
-60
-60
Subsoil conditions.
All rights reserved. No part of this publication may
be reproduced in any form or by any means, without
the prior written permission of SEAFCO PUBLIC
CO., LTD.
L o ad (to n )
0
500
1000
1500
2000
2500
3000
3500
4000
B1 -2.70
Settlement (mm)
10
B3 -7.90
20
MAT FOUNDATION
30
D-WALL
-36.0m.
40
B5 -13.10
B6 -15.70
D-WALL
-36.0m.
50
60
N o n -Gro u te d P ile - D ia . 1 .5 x6 0 .0 0 m
B a s e -Gro u te d P ile A - D ia .1 .5 x5 5 .1 6 m (3 S ta g e s - to ta l 2 0 0 0 ltr)
B a s e -Gro u te d P ile B - D ia .1 .5 x6 0 .0 0 m (3 S ta g e s - to ta l 2 0 0 0 ltr)
References:
Teparaksa, W., Thasnanipan, N. and Tanseng, P. (1999), Analysis of Lateral Wall Movement for Deep Braced Excavation in Bangkok Subsoils, Civil and Environmental Engineering Conference New Frontiers & Challenges, AIT,
Bangkok, November 8-12, 1999.
Lee, S. L. and Yong, K. Y. (1992), Base Grouting of Bored Piles, 2nd International Conference on Deep Foundation
Practice incorporating PILETALK 1992, Singapore, 4-6 November 1992. Pp. 147-153.
SEAFCO
144 Prayasuren Road, Bangchan, Khlong Sam Wah, Bangkok 10510.
A - 35
GENERAL
DON MUANG
N
FROM
IC
THE V
TORY
M EN T
M ONU
AT
ED
EX THE
PR
ES FIRS
SW T S
AY TA
GE
TO
5 15
35
AS
OK
EDIN
DA
EN
G
EL
EV
WORK UNDERTAKEN
DIAPHRAGM WALL:
INSTRUMENTATION:
Thickness 1.0m
Toe Depth 21.0m
10,545sq.m.
8 Inclinometer Tubes in the wall
2 Inclinometer Tubes in the ground
behind the wall, 8 Sets of VWSG. and
2 Vibrating Wire Piezometers
0.00m
Back Fill
Soft Clay
-6.50m
Drain Pipe
-21.00m
Stiff Clay
Diaphragm Wall
D02/99
TYPE OF WORK:
OWNER:
MAIN CONTRACTOR:
DESIGNER:
PERIOD:
Diaphragm Wall
Bangkok Metropolitan Administration.
Unique Engineering and Construction Co., Ltd.
Epsilon Co., Ltd.
1996
A - 36
SEAFCO
U n d ra in e d S h e a r S tre n g th
SPT
N (B lo w s /ft)
S u (t/m )
0
10
15
20
25
30
F IL L
10
20
30
40
-5
B H -2
B H -3
-5
B H -4
Depth (m)
Depth (m)
M E D IU M
DENSE SAND
B H -4
-1 0
-1 5
-2 0
-2 0
-2 5
-2 5
-3 0
-3 0
S T IF F C L A Y
B H -3
B H -5
-1 0
-1 5
60
B H -1
B H -5
SOFT CLAY
50
0
B H -1
B H -2
All rights reserved. No part of this publication may be reproduced in any form or by
any means, without the prior written permission of SEAFCO PUBLIC CO., LTD.
SEAFCO
Portal section.
Tunnel section.
References:
Thasnanipan, N., Maung, A. W. and Singtogaw, K. (1996). Experience in Construction of an Underpass Tunnel using
Diaphragm Wall Bangkok (in Thai), Technical Seminar on Construction of Basements 1996 organized by Engineering
Institute of Thailand, Bangkok, 18 September 1996. Pp. 55-70.
Teparaksa, W., Thasnanipan, N. and Tanseng, P. (1999), Analysis of Lateral Wall Movement for Deep Braced Excavation in Bangkok Subsoils, Civil and Environmental Engineering Conference New Frontiers & Challenges, AIT, Bangkok, November 8-12, 1999.
A - 37
D02/99
GENERAL
+14.80
10
+11.30
20M
+7.80
+0.70
0
-3.20
-5.80
-8.40
Soft to
Medium
CLAY
SPT-N (Blows/ft)
20 40 60 80 0
50
100
Phase 1
Phase 2
5
10
15
Bored Pile
Stiff to Very
Stiff CLAY
20
25
Medium to
Very Dense
SAND
30
35
WORK UNDERTAKEN
BORED PILES:
DIAPHRAGM WALL:
EARTH WORK:
TEMPORARY BRACING:
INSTRUMENTATION:
TYPE OF WORK:
OWNER:
MAIN CONTRACTOR:
DESIGNER:
PERIOD:
Vane Shear
Strength (kPa)
+4.30
+0.80
Dia. 0.8mx48.0m
17 nos.
Dia. 1.0mx48.0m
33 nos.
Dia. 1.2mx48.0m
5 nos.
Dia. 1.5mx48.0m
23 nos.
7,742sq.m. (0.8m Thick)
59,592cu.m.
586.50 tons
6 Inclinometer Tubes, 10 Tiltmeters,
5 Vertical Beam Sensors, VWSGs in
one Panel, 4 Earth Pressure Gauges,
20 Surface and Deep Settlement
Plates.
A - 38
SEAFCO
D10
D9
S4
I-1
S10
S9 I-2
S3
D3
5 Sto
rey B
EL1
S8
D8
S2
D2
T2
T10
EL5
I-3
T9
uildin
g
D7
EP-1
T3
S5
I-5
S6
T4
5 Storey Building
Legend
D5
I-4 D6
T8
EL4
S7
T7
T5
EL2
T6
EL3
5 Storey Building
0
Inclinometer in D-Wall
Tilt plate
Vertical beam sensor
Surface settlement plate (1.0m)
5 Storey
Building
D1
I-6
S1
T1
6 10
20m
200
400
600
800
0.0
Settlement (mm)
5.0
10.0
15.0
20.0
SEAFCO
References:
Thasnanipan, N., Maung A. W. and Tanseng, P. (1999), Behavior and Performance of Diaphragm Walls under Unbalanced Lateral Loading along the Chao Phraya River, 5th International Symposium on Field Measurements in Geomechanics FMGM99, 1-3 December, 1999, Singapore. Pp 267-272.
Teparaksa, W., Thasnanipan, N. and Tanseng, P. (1999), Analysis of Lateral Wall Movement for Deep Braced Excavation in Bangkok Subsoils, Civil and Environmental Engineering Conference New Frontiers & Challenges, AIT,
Bangkok, November 8-12, 1999.
Thasnanipan, N., Maung A. W., Tanseng, P. and Wei, S. H. (1998), Performance of a Braced Excavation in Bangkok
Clay, Diaphragm Wall Subject to Unbalanced Loading Conditions, 13th Southeast Asian Geotechnical Conference,
16-20 November, 1998, Taipei, Taiwan, ROC. Pp 655-660.
A - 39
GENERAL
I-3
Excavation -15.5m
Bored Pile
Barrette
Inclinometer Tube
I-2
89.35
Excavation -14.0m
WORK UNDERTAKEN
BORED PILES:
BARRETTES:
DIAPHRAGM WALL:
INSTRUMENTATION:
-14.00
-6.90
10
-9.60
-12.30
-13.30
-18.00
-15.50
-18.00
525
700
CONSTRUCTION STAGE
1050
1225
1400
1575
1750
-10
-15
-20
-25
-30
-40
TEMPORARY BRACING
LAOD (Tons.)
TYPE OF WORK:
OWNER:
MAIN CONTRACTOR:
DESIGNER:
PERIOD:
875
-35
LEGEND
2
350
-5
12
SETTLEMENT (mm.)
175
- 4.20
11
-11.80
14
-9.00
-1.50
13
-5.10
Dia. 1.2mx60.0m
443 nos.
0.8mX2.7mX60.0m
50 nos.
7,002sq.m. (0.8m Thick)
4 Inclinometer Tubes in the wall
+1.70
15
1
I-1
120.25
16
-2.40
I-4
A - 40
SEAFCO
1925
Su (t/m2)
0
10
15
SPT N
20
25
0.0
Top Fill
-3.0
BH-1
Medium to Very
Stiff Clay
Depth (m)
Depth (m)
40
-9.0
-15.0
-18.0
-18.0
-21.0
-21.0
-24.0
-24.0
-27.0
30
-12.0
-15.0
Dense Sand
20
-6.0
-9.0
-12.0
(Blows/ft)
-3.0
BH-2
-6.0
Soft Clay
10
0.0
-27.0
Work in progress.
SEAFCO
References:
Thasnanipan, N. and Singtogaw, K. (1996), Construction of Diaphragm Wall and Bored Piling for Sathorn Complex
Project (in Thai), Technical Seminar and Site Visit on Construction of Deep Basements using Short Embedded Diaphragm Wall in Bangkok, organized by Engineering Institute of Thailand. Bangkok, 19 December 1996. Pp. 129-143.
Teparaksa, W., Thasnanipan, N., Maung, A. W. and Wei, S. H. (1998), Prediction and Performances of Short Embedded Cast In-situ Diaphragm Wall for Deep Excavation in Bangkok Subsoil, Fourth International Conference on Case
Histories in Geotechnical Engineering, St. Louis, Missouri, March 9-12, 1998. Pp. 686-692.
Teparaksa, W., Thasnanipan, N. and Tanseng, P. (1999), Analysis of Lateral Wall Movement for Deep Braced Excavation in Bangkok Subsoils, Civil and Environmental Engineering Conference New Frontiers & Challenges, AIT,
Bangkok, November 8-12, 1999.
A - 41
GENERAL
I-6
I-7
I-5
I-4
INDEX
BORED PILE 0.80m.
BORED PILE 1.20m.
I-3
I-1
10
20m
I-2
WORK UNDERTAKEN
BORED PILES:
STEEL STANCHIONS:
DIAPHRAGM WALL:
INSTRUMENTATION:
Dia. 1.0mx58.0m
5 nos.
Dia. 1.2mx58.0m
114 nos.
Dia. 1.5mx58.0m
56 nos.
414x405-498x432mm 80 nos.
6,058 sq.m. (1.0m Thick)
7 Inclinometer Tubes in the wall.
0.0m
B1
B3
-6.7m
D-WALL
-11.8m
-14.5m
BORED
PILE
-21.0m
TYPE OF WORK:
OWNER:
SUPERSTRUCTURE
CONTRACTOR:
DESIGNER:
PERIOD:
Basement section.
SEAFCO
Tel. (662) 919 0090-7, Fax. (662) 919 0098
A - 42
SPT
Top Fill
10
Su (t/m2)
20
30
N (Blows/ft)
0
40
-10
-10
-20
-20
20
40
60
80
100
Depth (m)
Dense Sand
Depth (m)
-30
-30
-40
-40
-50
BH-1
BH-1
BH-2
BH-2
-60
-60
Subsoil conditions.
All rights reserved. No part of this publication may be
reproduced in any form or by any means, without the
prior written permission of SEAFCO PUBLIC CO.,
LTD.
500
1000
1500
2000
OPENING
OPENING
B3 SLAB
10
20m
10
20
30
40
50
SEAFCO
References:
Thasnanipan, N. and Singtogaw, K. (1996), Bored Piling and Diaphragm Wall Work for Excavation of Five-level Basement of Rajavej Hospital (in Thai), Technical Seminar and Site Visit on Experience in Construction of Deep Basements in Bangkok Soft Clay, organized by Engineering Institute of Thailand. Bangkok, 26 March 1996. Pp. 104-140.
Teparaksa, W., Thasnanipan, N. and Tanseng, P. (1999), Analysis of Lateral Wall Movement for Deep Braced Excavation in Bangkok Subsoils, Civil and Environmental Engineering Conference New Frontiers & Challenges, AIT,
Bangkok, November 8-12, 1999.
A - 43
A - 44
Sponsored by;
Chinese Institute of Civil and Hydraulic Engineering
Southeast Asian Geotechnical Society
Thirteenth Southeast Asian Geotechnical Conference, 16-20 November, 1998, Taipei, Taiwan, ROC
A. W. MAUNG
P. TANSENG
SYNOPSIS
Barrettes become not an uncommon foundation element used to support multi-storey buildings, elevated
expressways and underground station boxes in Bangkok, Thailand. The demand for barrettes is necessitated mainly by
constraints of site conditions, construction method, equipment and extensive bearing capacity requirement, etc. This paper
presents construction practice and the performance of barrette constructed in Bangkok metropolis. Trial trenching near a canal
for assessment of trench stability and soil deformation are presented. Choice of barrette and common defects found in barrette
are also discussed.
INTRODUCTION
CONSTRUCTION METHOD
Normally a cable hung grab mounted on crawler crane is
used for trenching under supporting fluid which is
commonly bentonite slurry. Concrete pouring is carried out
under bentonite slurry using tremie pipes. Properties of
573
24.00
B15
B20
B3
B10
B19
Best Fit
20.00
Time (Hours)
16.00
12.00
8.00
4.00
0.00
0.00
10.00
20.00
30.00
Depth (m)
40.00
50.00
60.00
30.00
B15
B20
B3
B10
B19
Best Fit
25.00
20.00
15.00
Creep (mm)
10.00
0.0
100
Slurry
Level
Guide Wall
Creep (mm)
-100
0.0
Canal
TOP SOIL
5.00
0.00
0.00
10.00
20.00
30.00
Depth (m)
40.00
50.00
60.00
2.0
2.0
Steel
Sheet Pile
Soft clay
0.1
Stiff clay
0.2
0.3
Med. sand
0.4
0.5
V. stiff clay
0.6
0.7
Dense sand
0.8
0.9
4.0
4.0
6.0
6.0
8.0
8.0
10.0
12.0
10.0
12.0
MEDIUM
CLAY
TRENCH STABILITY
Depth (m)
SOFT
CLAY
Depth (m)
After 24 Hours
After 48 Hours
14.0
14.0
574
No. of
Remarks
Project
Minimise Construction
Equipment
Limited Head Room
for Excavation
Combination
with
Diaphragm Wall
Foundation as well as
portion of column
10
PERFORMANCE OF BARRETTES
11
10
Available load test results, 4 nos of static load test and one
dynamic load test, are summarized below in Table 3.
9
Perimeter (m)
8
7
6
5
4
3
Project
2
1
0
0
D
QUALITY CONTROL
Note:
Barrette
Dimension
(m)
0.82x2.70x
61.80*
Test
Load
(kN)
14000
28000
35000
12000
24000
12900
25800
30140
11000
27500
20555
0.82x2.70x
44.00
0.80x2.70x
55.00
Total
Settlement
(mm)
4.83
12.56
17.63
5.65
34.15
4.46
11.01
12.35
3.07
7.97
14.00
0.80x2.70x
50.00
1.00x2.70x
48.94**
* with base grouting
** load test by dynamic load
Permanent
Settlement
(mm)
0
0
3.47
0.15
24.72
0.24
2.10
2.17
0.21
0.15
3.0
SPT-N (BLOWS/30cm)
0
Defect found
Possible Causes
Concrete cover
Bentonite slurry
inclusion or poor
quality concrete
Reinforcement
cage deviation
Uplift of
reinforcement cage
50
100
-4
-1 0
-1 6
SOFT
CLAY
STIFF
CLAY
-2 2
-2 8
DENSE
SAND
-3 4
-4 0
-4 6
SILTY
CLAY
DENSE
SAND
-5 2
-5 8
-6 4
-7 0
576
SILTY
CLAY
DENSE
SAND
Load (MN)
0
10
20
30
40
Settlement (mm)
5
10
15
20
25
30
35
Cycle - 1
Cycle - 2
Cycle - 3
40
DEPTH
(m)
SPT-N (BLOWS/30cm)
0
50
100
FILL
-3
-6
-9
SOFT
CLAY
-1 2
-1 5
-1 8
-2 1
-2 4
-2 7
-3 0
-3 3
-3 6
SILTY
CLAY
-3 9
-4 2
-4 5
-4 8
-5 1
-5 4
-5 7
SILTY SAND
-6 0
-6 3
-6 6
Teparaksa W.
University of Missouri-Rolla
Rolla, Missouri
DESIGN, CONSTRUCTION AND BEHAVIOUR OF BORED CAST IN-SITU CONCRETE PILES IN BANGKOK SUB SOIL
Narong Thasnanipan
Seafco Co., Ltd.
Bangkok 10320
Thailand
Wanchai Teparaksa
Civil Engineering Dept.
Chulalongkorn University
Bangkok 10330
Thailand
Ganeshan Baskaran
Seafco Co., Ltd.
Bangkok 10320
Thailand
Paper No.1.20
ABSTRACT
This paper briefs design considerations, construction methods and materials, static load test results and pile integrity test results of the
cast in-situ bored piles constructed as foundation elements for a wastewater treatment plant. The treatment plant is located in
Bangkok, capital of the Kingdom of Thailand and is to serve about 195,000 inhabitants of the city. A total of 402 piles, 296 nos. of
1500 mm diameter and 96 nos. of 1000 mm diameter, were designed to carry the whole structural load of the treatment plant.
Maximum working load on individual piles was designed to be 1000 tons and 500 tons for 1500 mm and 1000 mm diameter pile
respectively with a safety factor of 2.5. Initially the pile toe depth was designed to be 60m below the ground level, and embedded into
hard clay for 1500 mm diameter piles while the smaller diameter pile embedded into second sand layer at a depth of 53m and base
was not decided to be grouted. Pile load test results on fully instrumental pilot piles showed the failure well before reaching the
designed test load. Piles were re-designed and pile toe depth was set to be 55m, embedded into dense sand layer for both sizes and
base grouting was decided to be done for all piles. Proof load test results performed on four working piles(contract piles), two for
each size, produced well acceptable results conforming to the design and structural specifications and requirements. However,
settlements observed were higher than that observed for other projects in the vicinity. Base Grouting was done using tube - a
manchette method. A maximum volume of 500 liter of cement grout (w/c ratio ~ 0.5) or maximum grouting pressure of 40 bars was
used as limiting criteria. However, maximum pressure of 40 bars was hardly achieved. From the proof load test results ultimate load
capacity was estimated and compared using different methods suggested by previous researchers. Integrity test was decided to be
performed on each pile and results available currently are summarized.
KEYWORDS
Bored Piles, Base Grouting, Static Pile Load Test, Integrity Test, Pile Capacity
281
11
INTRODUCTION
282
12
Slurry properties
The limiting values for the bentonite slurry according to the
contract specification were 1.04 - 1.20 for density; 30-40s for
viscosity (Marshs cone); not less than 7 for pH and not more
than 3% for sand content.
Based on the results from a project just near by the site and
past experiences in the vicinity it was proposed that the above
mentioned required capacity could be achieved by base
grouting the piles with tip founded at about 55 m from the
ground.
283
13
the grout volume was the limiting factor. Usually the grouting
pressure was within the range of 20 - 30 bars.
Injection rate of grout was 10 - 15 liters/ min. Experiments on
grout samples collected from three of the bored piles
(1500mm dia.) in this site was performed by Anwar (1997).
Comparison of base grouted and soft base (non base grouted)
piles were studied and summarized in Table 1. It was
recommended that low injection rate about 1-2 liters/min
would improve the effectiveness of base grouting. However,
practicality and sustainability of grout pump, especially for
large volume of grout, can hardly justify this requirement.
Though the direct comparison of effect of base grouting is not
possible as the compared piles are founded in different soil
strata other parameters in Table 1 are worth enough to be
noted.
GROUTING
Diameter(mm)
Base Depth (m)
Design Load Qd (ton)
Failure Load (ton)
Load at 20mm total settlement (QL)
% increase in QL
Portion of QL carried by shaft (QS)
% increase in QS
Portion of QL carried by base (Qb)
% increase in Qb
Total settlement at (Qd) (mm)
Total settlement at 1.5 Qd (mm)
* - Estimated
Base
Soft
Grouted
Base
1500
1500
55
60
1000
1000
2725 *
1750
2290
1520
50.66
1720
1450
18.6
570
70
714
5
8.13
7.5
15.08
284
14
Pile
No.
Dia.
(m)
Base
depth
(m)
TP - 1
TP - 2
TP - 3
TP - 4
1000
1000
1500
1500
55
55
55.3
55.5
Pile
No.
Dia.
(m)
Base
depth
(m)
TP - 2
TP - 4
1000
1500
55
55.5
Fig. 4(a) Load test on pilot pile with non base grouted pile
(Diam. 1500mm, Toe embeddment at depth 60m
below ground)
Pile
No.
Dia.
(mm)
Base
depth
(m)
TP - 1
TP - 2
TP - 3
P-4
1000
1000
1500
1500
55
55
55.3
55.5
Fig 4 (b) Load test on pilot pile with non base grouted pile
(Diam. 1000mm, Toe embeddment at depth 53m
below ground)
285
15
Diam.
1500 mm
nos.
%
300
100
25
8.3
04
1.3
Diam.
1000mm
nos.
%
59
100
10
16.9
02
3.4
04
10
1.3
3.3
04
6.8
10
03
3.3
1.0
08
-
13.6
-
Notes:
1. These variations were attributed to the sub soil conditions
2. All the cracks have been found on piles adjacent to the
excavation supported by steel sheet piles
CONCLUSION
Fig. 6 (a) (proof) Load test on contract pile (TP - 3)
Dia. 1500mm, Toe depth 55.3 m below Ground Level
16
ACKNOWLEDGEMENT
The authors are much thankful for all the staff and employees
of SEAFCO CO., LTD. especially for Mr. Kamol
Yooyuenpattana and Mr. Chetsadar Plongkrathok.
REFERENCES
Anwar M. A [1997], Base grouting to improve the
performance of wet process bored piles in Bangkok sub soils,
AIT Master Thesis, Bangkok, Thailand.
Fleming, W. G. K., F. Reiding and P. Middendorp. [1985]
Faults in cast in place piles and their detection, Proc.
Second Intern. Conf. On Structural Faults and Repair., ICE,
Westminister, London, pp. 301 - 310.
Joshi, R. C., and H. D. Sharma [1987] Prediction of ultimate
pile capacity from load tests on bored and belled, expanded
base compacted and driven piles Proc. Intern.. Symp. On
Prediction and Performance in Geotechnical Engineering,
Galgary, pp. 135 - 144.
Ng Kim Cheng [1983], The construction problems and
performance of large bored piles in second sand layer, AIT
Master Thesis, Bangkok, Thailand
Teparaksa, W. [1994], Newly developed toe-grouted bored
pile in soft Bangkok clay; Performance and Behaviour,
Intern. Conf. On Design and Construction of Deep
Foundations, FHWA, Florida, pp. 1337 - 1351..
Woo Siu Mun and C. H. Juang [1994], Analysis of pile load
test results, Conf. On Deep Foundations and Ground
Improvement Schemes, Bangkok, Thailand.
287
17
19
Deep Foundations on Bored and Auger Piles, Vam Impe & Haegeman (eds) 1998 Balkema, Rotterdam, ISBN 90 5809 022 1
ABSTRACT: Static pile load test results of ten large diameter bored piles founded in the multi-layered soils
of Bangkok are discussed in this paper. All piles were instrumented with vibrating wire strain gauges
(VWSG) and telltale extensometer rods. Range of shaft friction and end bearing values mobilized in different
soil horizons are reported. Progressive type of failure mechanism which is peculiar with the long piles in
multi-layered soils, and found to be initiated from the soil layers present at the middle reach of pile shaft and
then extending towards the top and bottom layers, is also presented. Brittle type of failure observed in some
sand and very stiff to hard clay layers is also discussed. Settlements at design loads calculated from global
factor of safety concept and limit load concept are also compared. Additionally, back calculated
and values are also compared with the previously recommended values for similar soils.
1 INTRODUCTION
Bored cast in situ piles are extensively used as a
foundation element in Bangkok due to the
requirements of huge loads to be transferred and
limitations of using driven piles like limited
capacities, associated soil movements and some
unwanted environmental effects. Diameters of these
piles normally fall in the range of 0.80 to 1.50 m and
toe depths down to 60m from ground level are quite
common. Soil profiles of plain of Bangkok are
always evident of the presence of marine Bangkok
Soft Clay (BSC) at the top changing to medium at
about 15 to 18m. First sand layer is usually 5 to 10m
thick and found at 25m to 30m depth, below is a
series of stiff to hard clay and medium to very dense
silty sand layers (Ref. to the Figs. 5 to 14 for typical
soil profiles). Actual pore pressure conditions in the
upper BSC are hydrostatic from circa 1m below
ground level. Then the hydrostatic conditions
changes to piezometric draw down near the bottom
level of BSC. Piezometric draw down resulted in
increased effective overburden pressure of about 20
ton/m2 in the first sand layer and below as shown in
Figure 1. The under drainage in the Bangkok soils is
attributed to the deep well pumping in the area.
According to the latest reports, piezometric draw
down conditions have started recovering since last
few years due to the control over deep well pumping
and shifting of industrial areas away from Bangkok
metropolitan.
511
21
14
2.0xQd1
13
15
16
17
QL
Limit load
at a
settlement of
1% of Dia.
(ton)
Gross
Qd3
settlement Difference of
at Qd3
Qd3 as
Design
(mm)
compared to
load
'=QL/1.5
original Qd1
(%)
(ton)
6=(4/5)
18
19
20
21
1582
1230
1.29
1435 1715
1575
975
650
6.8
0.0
1929
930
2.07
2815 2017
2416
9.3
15.0
1140
760
5.5
16.9
1118
800
1.40
8.2
12.3
920
610
5.5
22.0
970
930
1.04
650
430
5.5
-4.4
1106
690
1.60
675
450
4.5
0.0
641
620
1.03
759 997
878
5.0
7.2
830
550
5.0
52.8
TP-7 1.2x43.6
450
1499
850
1.76
891 1390
1141
4.2
5.4
1150
770
4.5
71.1
TP-8 1.2x43.5
450
519
640
0.81
1057
5.9
48.5
850
570
4.7
26.7
TP-9 1.0x43.5
400
701
530
1.32
867 946
5.2
36.5
750
500
4.9
25.0
799
1100
0.73
3.5
6.4
16.3
1000
670
5.0
34.0
512
22
12
Qd1
11
Qd2/Qd1
10
Qd2=
Qu ave/2.5
Average Failure
Load
Qu ave
Chin-Konder's
Mazurkiewicz's
Mobil/Estim
Skin
Friction
Brinch-Hansen's
Friction
(ton)
De'Beer
Davisson
Pile
No.
SETTLEMENT(mm) AT
1.5xQd1
Total Estimated
Skin
Qd1 Mobilized
4 TEST PILES
Test piles discussed in this paper were all
constructed following the procedure discussed in
section 2. All piles were instrumented with VWSG
at five to seven different levels to estimate the shaft
friction transferred to different soil horizons. One set
of telltale extensometer rods was also used near the
tip of each test pile to measure the elastic shortening
of the pile shaft and finally pile base movement at
different stages of load testing. Static maintained
load testing method was used for all piles. Test loads
were applied using a system of hydraulic jacks
against the reaction frame of steel girders fixed
against anchored reaction piles. Normally three
cycles of loading are applied with first cycle up to
the design load Qd and maintained for 12 hours
followed by second cycle of loading up to 2 times of
Qd and maintained for 24 hours. Third cycle of
loading is applied up to 2.5 times Qd or maximum
pre-decided test load. Some times a fourth quick
loading cycle up to the maximum test load is also
applied and maintained for two hours. All test piles
except TP10 were tested to well above the expected
failure loads with the concept of sufficiently
mobilizing the end bearing.
SPT-N
Ave.
Skin Friction
Cu
Mobilized (ton/m2)
(Ave.)
Average
Maximum
2-12
4.7
6.0
13.9
1.3
20-35
14.0
7.5
18.8
0.54
Hard Clay
40-46
21.5
7.3
24.6
0.34
18-68
11.2
19.9
20->100
15.6
25.1
Clay
513
23
Dense Sand
Hard Clay
V.Stiff Clay
Hard Clay
12
Soft Clay
V. Stiff Clay
Dense Sand
9
Skin Friction Mobilized (ton/m
)
10
14
Dense Sand
10
Dense Sand
Hard Clay
Hard Clay
Hard Clay
Hard Clay
Hard Clay
6
4
2
V.Stiff Clay
200
400
600
800
1000
3
2
1
0
0
200
400
600
800
1000
1200
Butt Load
(ton)
Pile
No.
TP-1
TP-2
TP-3
TP-4
TP-5
TP-6
TP-7
TP-8
TP-9
TP-10
418
71
382
230
194
199
101
481
199
201
25.7
16.2
18.3
16.3
13.0
9.1
15.8
9.1
14.1
8.0
94.1
34.7
81.6
90.7
60.5
13.8
58.4
90.9
69.0
16.3
68.4
18.4
63.3
74.4
47.5
4.7
42.7
81.9
55.0
8.3
5.7
1.5
6.3
7.4
4.7
0.5
3.6
6.8
5.5
0.7
370
63
487
293
247
254
89
426
253
178
500
500
500
206
430
500
183
500
500
228
100
100
70
45
35
50
40
60
60
50
514
24
500
TP3
SPT-N (Blows/ft)
0 20 40 60 80 100 0
400
TP1
Load (Tons)
1000 1500 2000
2500
Soft to Medium
CLAY (CH)
10
300
20
TP5
250
200
TP9
30
350
500
Fill Material
TP8
Depth (m)
450
Dense SAND
Very Stiff CLAY
Dense SAND
Very Stiff CLAY
150
40
TP2
100
50
TP-2
R = 0.889
50
0
0
3
4
% (Base Sett./Dia. of
Pile)
500
2000
Fill Material
10
1500
2000
20
Pile Head Movement (mm)
Load (Tons)
1000
1500
1000
500
Soft to Medium
CLAY (CH)
40
60
80
100
TP-2
30
40
Depth (m)
20
120
Medium to Dense
SAND (SM or SC)
Stiff CLAY
(CH)
50
SPT-N (Blows/ft)
Very Dense SAND
(SC)
TP-1
60
Load (Tons)
20 40 60 80 100 0
400
800
1200
1600
Top Soil
Soft Clay
10
1000
1500
2000
Depth (m)
20
20
30
40
60
40
Dense to Very Dense
Sand
80
TP-3
50
100
120
TP-1
500
1000
1500
20
40
60
80
100
120
TP-3
25
2000
SPT-N (Blows/ft)
0
20
40
60
400
800
Load (Tons)
SPT-N (Blows/ft)
Load (Tons)
80 0
1200
1600
20
40
60
80 0
200
400
600
800
1000
Fill Material
Depth (m)
Depth (m)
30
20
Soft to Medium
CLAY (CH)
10
Loose Sand
20
10
30
40
40
Hard Clay
50
TP-6
50
TP- 4
60
500
1000
1500
20
40
60
80
100
40
60
80 0
500
Load (Tons)
SPT-N (Blows/ft)
1000
1500
Fill Material
Soft to Medium
CLAY
20
40
60
80 0
400
800
1200
Fill Material
Soft to Medium
CLAY (CH)
10
30
40
(1.
0m
x
43.
0m
) .
20
Stiff CLAY
Depth (m)
De 20
pth
(m)
TP
5
30
10
TP- 6
Load (Tons)
SPT-N (Blows/ft)
20
20
40
TP-4
120
40
Hard CLAY (CL)
TP-5
50
50
TP-7
500
1000
1500
2000
20
40
60
80
100
120
20
40
60
80
100
120
TP- 5
TP- 7
26
Load (Tons)
SPT-N (Blows/ft)
0 20 40 60 80 100
400
1200
0 20 40 60 80 100 0
500
1000
Fill Material
10
30
Hard CLAY (CH, CL)
40
30
20
Medium Dense
SAND (SM)
Depth (m)
20
40
Dense to Very Dense
SAND (SM)
TP-8
50
50
500
1000
1500
60
Applie d Loa d (Tons)
20
60
80
100
TP- 8
0 20 40 60 80 100 0
20
40
Load (Tons)
SPT-N (Blows/ft)
500
1000
TP- 10
Fill Material
layers is 8 with 4.5, 6.0 and 12.8 for the three piles
seated in clay layers. From Table 3 it can be
confirmed that the end bearing values in clay layer
also depend upon the base settlement and values of
Nc more than 9 can also be mobilized at high base
settlement ratios. An other possible reason for the
value of Nc more than 9 may be the underestimation
of undrained shear strength of clay from correlation
with SPT-N discussed in section 3.1.
10
Medium Dense
SAND (SM)
30
Hard CLAY (CH, CL)
40
Dense to Very Dense
SAND (SM)
TP-9
6 CONCLUSIONS
500
1000
1500
2000
20
Pile Head Movement (mm)
50
1000
40
20
500
120
TP-10
2000
Depth (m)
10
Load (Tons)
SPT-N (Blows/ft)
800
Fill Material
40
60
80
100
120
TP- 9
27
517
28
29
Deep Foundation on Bored and Auger Piles, Avan Impe & Haegeman (eds) 1998 Balkema, Rotterdam, ISBN 90 5809 022 1
ABSTRACT: Effect of construction time and slurry viscosity on the shaft friction capacity of cast in situ
bored piles have been studied by various investigators in the past but the extent to which these parameters
effect the shaft capacity is still not clear. Major obstacle in this regard is that it is hard to normalize the shaft
capacity degradation against other numerous parameters which are influencing simultaneously. Results from
eleven pile load tests, constructed with different slurry viscosities and construction times, in the layered
alluvial strata of Bangkok are presented in this paper.
It has been concluded that slurry viscosity, do not have significant effect on the shaft load transfer of these
piles but considerably reduced with increase in construction time. Trend of reduction in capacity seems to
follow an exponential decrease with increase in construction time with major part of degradation within first
24 hours of construction time.
60 m from ground level are quite usual. Soil profile
of plain of Bangkok generally consists of Quaternary
alluvial deposits of alternating sand and clay layers
as shown in Figure 1, down to the rock face which is
reported to be at least 550 m deep in the area
(Balasubramanium, 1991).
1 INTRODUCTION
Average Engineering
Parameters
P o re P re s sure (t/m )
0
20
30
40
Su = 10 - 20 KPa
t = 14-16 KN/m3
-1 0
-3 0
c
tati
ros
SPT-N = 20 - 50
t = 20.0 KN/m3
Su = 250 KPa -4 0
Lin
wn
Do
t = 21.2 KN/m3
w
Dra
etric
40
Lin
om
iez
al P
Actu
Depth (m)
10
20
Weathered Crust
Hy
50
60
-5 0
Dense to Very Dense
Sand (SM)
SPT-N = 50 - 100
t = 20.0 KN/m3
-6 0
171
31
60
32
30 - 60
1.04 - 1.15
pH
7 - 11
Sand Content
<4%
1.20
Tomlinson,1957
1.00
Density (g/cc)
Adhesion Factor ,
0.80
Suchada,1989
for bored piles in Bangkok soils
0.60
0.40
0.20
0.00
0.00
5.00
10.00
15.00
20.00
25.00
30.00
33
Pile No.
Pile
Dimensions
(m)
Bentonite
Slurry
Viscosity
(sec.)
Construction
Time
(hrs)
Pile Age at
the Time of
Load Testing
(days)
TP-1
1.2x57.1
38
43.0
32
TP-2
1.2x46.3
38
13.1
29
TP-3
1.0x46.5
37
9.8
25
TP-4
1.0x49.5
37
38.7
TP-5
1.0x43.0
38
26.0
TP-6
1.0x41.0
45
TP-7
1.2x43.6
55
TP-8
1.2x43.5
TP-9
1.0x43.5
Actual Shaft
Capacity
(ton)
Actual/Estimated
Shaft Capacity
H=(G/F)
1230
1200
0.98
930
1300
1.40
800
1250
1.56
15
930
750
0.81
19
690
700
1.01
11.8
32
620
800
1.29
16.8
32
850
1100
1.29
38
12.3
24
640
750
1.17
37
11.3
18
530
700
1.32
Estimated
Shaft
Capacity
(ton)
TP-10
1.2x62.0
41
32.4
27
1534
2000
1.30
TP-11
1.2x54.2
38
30.0
39
1050
1300
1.24
6 TEST PILES
Test piles discussed in this paper were all constructed
following the procedure discussed in section 4. All
piles were instrumented with Vibrating Wire Strain
Gauges (VWSG) at five to seven different levels to
estimate the shaft friction transferred to different soil
horizons. One set of telltale extensometer rods was
also used near the tip of each test pile to measure the
elastic shortening of the pile shaft and finally pile
base movement at different stages of load testing.
Static maintained load testing method was used for
all piles. Test loads were applied using a system of
hydraulic jacks against the reaction frame of steel
girders fixed against anchored reaction piles.
Normally three cycles of loading are applied with
first cycle up to the design load Qd and maintained
34
500
1000
1500
2000
2500
0
20
TP-1
Movement (mm
TP-2
TP-3
40
TP-4
TP-5
TP-6
60
TP-7
TP-8
TP-9
80
TP-10
TP-11
100
120
25
TP-1
1.40
27
TP-2
TP-3
32
32
39
1.20
TP-4
24
TP-5
TP-6
19
32
1.00
TP-7
TP-8
TP-9
15
0.80
TP-10
TP-11
0.60
35
40
45
50
Bentonite Viscosity (sec)
55
175
35
60
1.60
25
TP-1(Tip in SAND)
TP-2(Tip in SAND)
1.40
18
1.20
32
TP-3(Tip in SAND)
27
32
TP-4(Tip in CLAY)
39
TP-5(Tip in SAND)
24
TP-6(Tip in SAND)
TP-7(Tip in CLAY)
19
1.00
32
TP-8(Tip in SAND)
TP-9(Tip in SAND)
15
0.80
TP-10(Tip in
SAND,Base Grouted)
TP-11(Tip in
SAND,Base Grouted)
0.60
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
45.0
50.0
10 DISCUSSION
11 CONCLUSIONS
1.
176
36
2.
3.
4.
AKNOWLEDGEMENTS
Writers wish to acknowledge the co-operation of
Mr. Aung Win Maung and Mr. Pornpot Tanseng, in
the preparation of this paper.
REFERENCES
Baker, Jr. C. N. et al. (1970), Load Carrying Capacity
Characteristics of Drilled Shafts Constructed with the Aids
of Drilling Fluids, Research Report 89-6, Center for
Highway Research, The University of Texas at Austin, TX.
Balasubramanium, A. S. (1991), Inaugural Lecture on
Contributions in Geotechnical Engineering Soil Mechanics
and Foundation Engineering, AIT, Bangkok, March 14,
1991.
Bowles, J.E.(1988), Foundation Analysis and Design,
McGraw-Hill.
Cernak, B. (1976), The Time Effect of Suspension on the
Behaviour of Piers, 6th European Conf. On Soil Mechanics
and Foundation Engineering, Vienna.
Corbett, B. O. et al. (1975), A Load Bearing Diaphragm Wall
at Keinsington and Chelsa Town Hall, London, Conf. on
Diaphragm Walls and Anchorages, ICE, London.
Fleming, W. K. (1977), The Use and Influence of Bentonite in
Bored Pile Construction, CIRIA Report PG3.
Littlechild, B. and Plumbridge, G. (1998), Effects of
Construction Technique on the Behaviour of Plain Bored
Cast In Situ Piles Constructed Under Drilling Slurry, 7th
Intl. Conf. and Exhibition on Piling and Deep Foundations,
Vienna.
Majano, R. E. and ONeil (1993), Effect of Slurry Dosage and
Exposure Time on Perimeter Load Transfer of Drilled
Shafts, ADSC Publication.
Nutalaya, P. (1981), Subsidence Studies of the Bangkok Plain,
AIT Research Reports.
Pitupakorn, W. (1985), Predictions of Prestressed concrete pile
capacity in Bangkok stiff clay and clayey sand, 8th
Southeast Asian Geotechnical conf., Kuala Lumpur.
Stas, C. V. and Kulhawy, F. H. (1984), Critical Evaluation of
Design Methods for Foundations Under Axial Uplift and
Compression Loading, Report EL-3771, EPRI, Palo Alto,
Calif.
177
37
39
41
346
132.10
96.20
Test-Barrette
Test
Pile
132.68
94.00
Figure 1. Foundation footprint of BECM tower project, showing the location of test pile and barrette.
3. CONSTRUCTION PROCEDURE
3.1 Bored Pile
Wet process method with rotary drilling bucket was employed. Bentonite slurry conforming to the
widely accepted specifications were used as supporting fluid. Top 15 m soft clay was temporarily
cased to assure the stability of the borehole. Firstly, auger was used to drill within the temporary
casing, followed by rotary bucket with bentonite slurry down to final depth of excavation. Airlift
technique was applied to clean the borehole base of any congregated sediments. Before lowering the
reinforcement cage special cleaning bucket was used to scrap of the borehole walls and the base.
Reinforcement cages were lowered inside the borehole by simultaneously attaching the
instrumentation at specified locations. Soon after lowering the rebar cage tremie concreting was
started. Properties of the bentonite slurry used are given in Table 1. Polystyrene grains plug was
used before the first charge of concrete to avoid the mixing of bentonite with concrete. Time
consumed in different construction activities is plotted in Figure 3.
3.2 Barrette
Mechanical rope-grab in conjunction with bentonite slurry was used to excavate the trench. A guide
wall cast with inside clear dimensions slightly more than the nominal size of the barrette was used to
guide the grab during initial bites. Since time consumed in the preparation of instrumentation was
quite long, refer Figure 3, desanding was continuously done to keep the bentonite slurry agitated,
which also helps to minimize the growth of filter cake by actually reducing the exposure time.
42
347
0
DEPTH (m)
Su (UC) t/m2
5.0
10.0
1000
2000 3000
1000
2000
3000
4000
5000
0.0
10.0
-20
First Stiff
Clay
-30
First
Sand
-40
30.0
Bored Pile
Soft
Clay
-10
20.0
Weathered
Crust
Barrette
Hard
Clay
-50
Second
Sand
-60
Tip Level
-57.5 m
Tip Level
-57.5 m
60
1.50 m
0
50
3.00 m
100
60
SPT-N (blows/30cm)
VWSG
Bored Pile
1.50 m
Barrette
Mechanical Extensometer
Figure 2. Comparison of bored pile and barrette, with soil profile at the site.
As another measure, trench was once again occupied by grab to scour the trench walls and to
remove, if any, filter cake formed on the walls (Refer: Drilled Shaft Inspectors Manual, 1989). It is
authors opinion that, if due to some unforeseen reasons, reinforcement cage lowering have to be
delayed for considerable period of time or for overnight. It is a good practice to use the grab again to
scrap the trench walls which eliminates any foreseeable bad effects due to such unexpected delays.
After lowering the rebar cage, tremie concreting was done.
Table 1. Comparison of bentonite slurry properties.
Pile
Barrette
Viscosity (sec)
33
36
36
49
Density (g/cc)
1.08
1.10
1.10
1.17
pH value
0.1
0.8
1.0
1.1
43
348
B arrette
D rilling
D eSanding
C age Low ering
Trem ie Pipe Preparation
C oncreting
B ored P ile
10
20
30
40
50
60
70
80
T im e Co n su m e d (h o u rs)
44
349
Figure 4a. View of the test frame having maximum capacity of 6000 tons.
5.00 m
5.00 m
B20
5.00 m
Main Beam
5 x I 400 x 2000 x 9000 mm.
B13
B14
B15
5.00 m
Hydraulic Jacks
Reference Beam
B
B9
45
350
46
351
L/B = 1
L/B = 3
L/B = 5
Figure 7. Orientation of principal stresses and stress contours around the excavated trenches with
different aspect ratios.
47
352
earth pressure on flat surface of trenches with large aspect ratios. Although the exact determination
of earth pressure developed on the surface of trench depends on the soil properties and the over
burden pressure at the level of consideration, it can be concluded that no significant difference in
earth pressure is observed between the bore hole (L/B=1) and the barrette (L/B =2).
7. RESULTS OF LOAD TEST
Values of unit skin friction developed at the interface of different soil horizons along the pile
and barrette shafts are given in Table 2 and are also plotted in Figure 2. Comparison of unit skin
friction values prove that there is no significant difference in shaft load transfer between pile and
barrette, even though the construction methodology adopted is different. These findings are in line
with the conclusions made by Thasnanipan et al (1998-a). Load settlement curves of the pile and
barrette are shown in Figure 8.
Table 2. Comparison of unit skin friction and end bearing mobilized for the test pile and barrette.
Mobilized Skin Friction (ton/m2)
Depth
Soil Type
Pile
(m)
Barrette
0 - 13.5
13.5 - 25.0
25.0 - 35.0
35.0 - 50.0
50.0 - 55.0
0.20
5.90
11.46
3.09
3.43
2.63
7.01
22.76
11.11
14.84
At Design Load
Max. Mobilized
0.26
3.58
13.25
3.55
3.19
2.24
8.86
25.28
9.61
7.49
270
101
A p p l i e d L o a d (T o n s)
0
500
1000
1500
2000
2500
3000
3500
4000
P ile H e a d M o ve m e n t (m m
20
B ar r ette
Pile
40
60
80
48
4500
5000
5500
353
8. CONCLUSIONS
1) No significant difference in shaft load transfer has been observed between the wet process bored
pile and barrette, in spite of the presence of considerable difference in construction techniques
followed and other relevant parameters like bentonite slurry viscosity and construction time.
2) All foreseeable negative effects attributed to construction parameters can be eliminated by
observing good engineering practices.
3) Reaction frame can be designed and erected to apply very high compression loads of the order of
6000 tons for pile load testing.
ACKNOWLEDGEMENTS
The authors wish to thank Dr. Wanchai Teparaksa and their colleague Mr. Kamol Singtogaw for
their invaluable suggestions. They also wish to thank Mr. Natamon of STS Engineering Consultants
Co., Ltd. for providing the necessary data.
REFERENCES
Drilled Shaft Inspectors Manual (1989), Prepared by The Joint caisson Drilled Shaft Committee of
the ADSC: The International Association of Foundation Drilling and DFI: Deep Foundation
Institute, NJ. USA.
Hosoi, T, Yagi N & Enoki, M. (1994), Consideration to the Skin Friction of Diaphragm Wall
Foundation, 3rd Intl. Conf. on Deep Foundation Practice incorporating PILETALK, Singapore.
Static Load Testing Report of Barrette Pile for BECM Tower Project, Rama IX Road, Prepared by
EDE-STS Engineering Joint Venture, Bangkok, Thailand.
Static Load Testing Report of Bored Pile for BECM Tower Project, Rama IX Road, Prepared by
EDE-STS Engineering Joint Venture, Bangkok, Thailand.
Thasnanipan, N, Baskaran G. & Anwar, M.A. (1998-a), Effect of Construction Time and Slurry
Viscosity on Shaft Capacity of Bored Piles, Proc. of the 3rd Intl. Geotechnical Seminar on Deep
Foundations on Bored and Auger Piles, Ghent, Belgium, Balkema.
Thasnanipan, N., Maung, A.W. & Tanseng, P (1998-b), Barrettes Founded in Bangkok Subsoils,
Construction and Performance, Proc. of the 13th Southeast Asian Geotechnical Conf. Taipie,
Taiwan, R.O.C.
49
51
Eleventh Asian Regional Conference on Soil Mechanics and Geotechnical Engineering, Hong et al. (eds)
1999 Balkema, Rotterdam, ISBN 90 5809 053 1
ABSTRACT: Base grouting techniques are widely used to rectify the soft toe problem of bored piles in Bangkok. Two different
techniques, commonly known as flat jack and tube-a-manchette are used. This research study is mainly focused on the tube-amanchette technique. Six piles were constructed with the provision of PVC-casing inside the shaft to allow the drilling through the
pile bases in order to collect the soil samples below the pile tip. Piles were base grouted by varying the controlling parameters such as
grout volumes, pressures and injection rates. Soil samples were collected from beneath and at some distance away from the pile tip,
and analyzed. It is observed that grout does not penetrate into the surrounding sand of the pile toe even at high pressures. It partially
replace and/or precompress the sediments present under the pile tip and most of the grout just rises up the soil/pile interface by
replacing the bentonite cake. Recommendations are made to eliminate the soft toe problem more effectively.
0
Ist Sand
2nd Clay
2nd Sand
Increase
in
failure
load
(%)
26-66
27
12-24
Increase
Increase
in skin
friction
(%)
in end
bearing
(%)
24-66
51
9-27
28-61
1
11-21
Displacement at fully
mobilized skin friction
-10
FIRST STIFF
CLAY
-20
DEPTH
(m)
FIRST
SAND
-30
-50
-60
-65
PVCCASING
SECOND STIFF
CLAY
-40
SECOND SAND
FILL
SOFT
CLAY
1 INTRODUCTION
30 cm
Pile
tip
Concrete
coring
Manchettes
0.5-1.0m
SPT
2-3m
Position of PVC-casing
with test pile no.
Washboring & soil
sampling location
(% of Pile Dia.)
NGB
0.49 0.51
0.37
1.04
GB
1.34-1.35
0.74
1.59-1.86
3 GROUTING PROCEDURE
Two grouting circuits in the form of U-loops with manchettes
placed at a level of 5 to 10 cm above the pile tip arranged in a
53
269
Portland cement Type I grout with w/c ratio equal to 0.55 was
used. Volume of grout was measured from the number of pump
strokes and also crosschecked against the volume consumed
from the agitator tank. Nominal grout volume used for each pile
was 540 liters but a slight difference shown in Table 2 in actual
volume of grout measured might be due to the difference in IR
used during grouting and at the time of calibration.
All the three piles were grouted with different IR varying
from 3 to 36 liters/min. In each case, after injecting target grout
volume, grout circuit valve was closed to lock the maximum
pressure achieved. Residual pressures two minutes after closing
the pump were also measured and are given in Table 2.
After 15 to 20 days of base grouting, diamond bit rotary
drilling with double tube sampler was used to core through
concrete present below the base of the PVC-casing. Right after
reaching the pile tip, Standard Penetration Test (SPT) was
started. Steel liners were used inside the split spoon sampler to
collect soil samples. All the concrete and soil samples retrieved,
carefully examined on site to determine the grout content
present. Additionally, in order to determine the lateral spreading
of grout into the surrounding soil of pile tip, additional boreholes
were drilled 30 cm away from the pile periphery. Washboring
was used down to approximately 1 m above the pile tip level and
then SPT was employed to collect the samples.
4 TESTING METHODOLOGY
Grout
Volume
(Liters)
Injection
Rate
(Liters/min)
Maximum
Pressure
Achieved
(bar)
Residual
Pressure 2 min
after closing the
pump
(bar)
TP-1
TP-2
TP-3
500
545
520
32 3*
36
8
26 16*
36
24
14
3
8
54
270
SAND
SILT
Type III
CLAY
100
90
MC-300
MC-500
80
70
Portland Type I
60
50
40
D15 - Range of
Sand Samples
30
20
Injection Rate
TP-1
TP-2
TP-3
10
100
200
300
400
500
20
10
600
0.1
0.01
0.001
GR = D15/D95
(1.1)
9 INSTALLATION EFFECTS
SPT-N values obtained right below the pile tips and 30 cm away
from the pile are compared with the values from nearest
borehole (10 20 m) performed at the time of soil investigation
in Figure 6. It is quite clear that the density of the sand
surrounding the tip have been increased appreciably, especially,
below the tip of the piles.
SPT-N (Blows/30cm)
25
50
52
75
100 25
50
TP-1
75
100 25
TP-2
50
75
100
TP-3
53
56
Pile Tip
55
Pile Tip
Depth (m)
54
Pile Tip
Pressure
20
30
Pressure (bar)
30
10
40
Residual pressure after 2 min.
40
57
58
Under the pile tip
Nearest borehole
Figure 6. Comparison of SPT-N values around the grouted pile tip and
the nearest borehole from soil investigation.
55
271
Figure 8. Model pile showing the grouted zone below the tip.
3.
4.
REFERENCES
From the analysis of the model piles, it was revealed that: a) full
pile base area coverage by grout can be achieved if manchette
level is less than 20 cm above the pile tip; b) a partial base area
coverage was found up to 30 cm and if; c) manchette level is
more than 40 cm above the tip, grout directly percolates towards
the pile shaft by bursting the side concrete cover. Presence of
grout on the vertical pile/soil interface at the shaft was also
confirmed in all cases. Although a direct comparison of grout
flow in model piles and prototype piles can not be made due to
the difference in overburden pressures but the upward flow of
grout along the pile shaft can be the most likely phenomenon in
base grouting. Which, subsequently act as a rock socket and
significantly increases the pile stiffness (Francescon, 1992).
11 CONCLUSIONS
From the study carried out following conclusions can be drawn.
1.
2.
56
272
Conference Proceedings
Volume 2 (Part II)
Editors:
D. G. Lin
D. T. Bergado
N. Phien-wej
P. Nutalaya
A. S. Balasubramaniam
57
59
Corbett et al. (1970) presented the results of load testing of test panel excavated under
bentonite slurry, excavation took 2 days and on completion the panel was left open overnight,
but bentonite was renewed prior to concrete. The authors inferred that the presence of
bentonite suspension even for such a long time was not adversely affected the development of
skin friction.
Farmer, Buckley & Sliwinski (1970) conducted the laboratory tests on model concrete
pile. The results indicated that presence of a bentonite filter cake at the concrete/sand
interface has little effect on load transfer. Full scale tests on three deep bored piles
constructed under bentonite, indicated that the load transfer was extremely higher than the
expected. They concluded that high load transfer level may be obtained from piles
constructed under bentonite, this may be due to uneven side-wall configuration.
Reese & Tauma (1972) found that the values of load transfer developed in clayey soils
on the sides of the shaft constructed by the slurry displacement method are comparable to
those in the shafts constructed in the dry.
Wates & Knight (1975) concluded from their investigation that a bentonite filtercake of
a significant thickness would develop in 24 hours. In order to prevent a build up of filtercake,
the slurry should be left in place much less than 24 hours.
Cernak (1976) performed full scale load test on three barrettes in sandy gravels. Two of
the barrettes were constructed using slurry with different exposure times (8 and 97 hours) and
their load test results indicated a decrease of skin friction capacity of 43% and 56%
respectively, as compared to the other barrette excavated dry and concreted immediately. It
must be noted that the major part of the reduction i.e. 43% took place in the first 8 hours of
construction time while only 13% (56-43) reduction took place in the rest of 89 hours (97-8)
for the second barrette. These findings support the conclusion of Wates & Knight (1975).
Sliwinski (1977) reported that displacement of suspension of slurry from the sides of the
bored hole does not constitute a major problem. The rising column of concrete will displace
the fluid suspension because of the considerable difference in unit weight and shear strength
of the materials. The author stated that the field and laboratory tests seem to indicate that the
influence of some bentonite in the parent soil has an insignificant influence on load support
providing that the properties of the slurry are within reasonable limit and the concreting is
done within a reasonable short time after the excavation is completed.
Fleming & Sliwinski (1977) reported on 49 filed tests from several countries. The test
results suggest that the use of bentonite suspension has no detrimental effect on shaft friction
while in granular soil, there is an indication that skin friction at high displacement may be
slightly be reduced, though there may be reasons unrelated to the bentonite process. They
suggested that concreting should be completed within 24 hours of the completion of boring.
Reese & Tucker (1985) concluded that the capacity of bored piles constructed under
slurry could be substantial with proper construction technique. The slurry will be ejected from
the excavation and substantial bond will develop at the interface of the concrete and the
supporting soil. However, the authors also suggested that the slurry must not be left more
than few hours in the excavation without operation of drilling tool; otherwise, a thick filter
cake will develop on the side of the excavation.
Reese & O Neil (1988) suggested that a solution to the problem of reduced skin
friction due to excessive filter cake is to maintain the properties of the slurry within tolerable
limits and to place the concrete the same day that the excavation is completed. If for some
reason, it is impossible to place the concrete without undue delay, the drilling machine must
be re-occupied the excavation to rework the borehole. If the slurry remains for a period of
time without agitation, the filter cake can become thick.
V ~ 60
60
Fleming et al. (1992) concluded that the process of forming a pile under bentonite
suspension does not materially reduce the shaft friction in both granular soil and cohesive
soil. The rising column of concrete with a slump in excess of 175 mm from tremie process
will largely remove the filter cake layer on the wall surface of shaft. However, if the hole is
left filled with slurry for long period (no agitation action), this will give rise to a significant
reduction in shaft friction on completed piles.
ONeil & Reese (1992) reported the effect of slurry properties on two drilled shafts
constructed in similar ground conditions (alternating layer of very stiff clay and dense sand).
Shafts 1 and 2 were constructed with Marsh cone viscosity of 37 and 49 sec respectively.
Time between opening the borehole and completion of concreting for both piles was 5 to 7
hours. Minor difference in load transfer of both shafts was found and the authors concluded
that the difference in slurry properties used for the construction for both shafts had a little
effect on shaft load transfer.
Wardle et al. (1992) concluded from four piles tested in London that the axial capacity
of driven and jacked piles after one or two months were 14 to 28% greater than those
measured during or immediately following installation. CRP tests performed after about 3
years recorded further increase of between 14 to 20% (total became 28 to 48%). Although, it
was not possible to record the capacity of the bored pile immediately after installation, the
capacity of this pile increases by 47% between 2 months and three years.
Majano & ONeil (1993) attempted to model the formation of filter cake in the
laboratory with different slurry dosages, differential pressures and exposure times. They
stated that perimeter load transfer is a complex function of the physical and chemical
characteristics of the slurry and the geomaterials, the roughness of the borehole, the fluid
pressures exerted by concrete, the shearing properties of the soil, and possibly the chemistry
of the fluid concrete. They attempted to correlate the potential degradation of the soil-pile
interface to the thickness and shear strength of the cake formed against the walls, and argued
that the shear strength and thickness can not be measured with only one or two parameters
like slurry dosage and differential pressure. With a bentonite concentration of 72 kg./m3 and
differential pressure of 0.5 psi, they achieved a filter cake thickness of 3.14 and 4.5 mm after
a contact time of 4 and 24 hours. Authors also compared the laboratory tests with the actual
field conditions and proved that due to the presence of enormously high differential pressures
in the field in some cases, thickness of filter cakes which would be considered detrimental for
shaft load transfer, require few hours to develop (Authors proved that a filter cake of 6 mm.
thickness would require only 2.3 hours to develop in the field under a differential pressure of
10 psi).
Hosoi et al. (1994) reported that when the diaphragm wall foundation is cast in slurry,
mud cake could not be fully scoured by concrete. So the evaluation of the shaft friction
mobilized on the wall foundation cannot overlook the effect of mud cake. They concluded
from laboratory tests that the friction resistance between concrete and the sample soil
(decomposed granite) through bentonite slurry cake is smaller than the shear strength of the
sample soil.
Ho & Lim (1998) reported that the barrette sized 2.8 m x 0.60 m x 47.4 m excavated
under bentonite slurry support at Singapore Post Center project with a total construction time
of about 110 hours has been tested. The test result showed that substantial shaft friction could
be mobilized to carry load satisfactory with a reasonable factor of safety and within a
tolerable displacement of 12 mm at working load.
Littlechild & Plumbridge (1998) presented that the values of actual shaft resistances
mobilized for in the five pile load test carried out at BERTS project and compared to the
calculated shaft resistances, where calculated shaft resistance is based on the design approach
adopted on the project. For cohesive soil fs = Cu, taken as 0.5 for stiff and hard clay
61
V ~ 61
layers and for sand layers shaft resistance of 120 KPa has been determined for all sand layers.
Construction time and slurry viscosity on this project was controlled to be less tan 24 hours
and 35 sec respectively. They concluded that shaft friction capacity of bored piles constructed
under bentonite slurry tends to decrease as the construction time and slurry viscosity increases.
Thasnanipan, Baskaran & Anwar (1998) presented the shaft friction values mobilized
from eleven instrumented bored piles constructed under slurry with different construction
times and bentonite viscosity from various sites in Bangkok area. They concluded that the
slurry viscosity up to 55 sec./Qt do not have significant effect on the shaft load and
degradation of shaft capacity with increase in construction time beyond 24 hours is not
excessive.
DESIGN CONSIDERATIONS AND PARAMETERS
Selection of design parameters, which suits the local construction practices and
procedures, is very important. Design parameters are normally selected based on the previous
researches of local institutions/organizations along with some special considerations specific
to the sites. Following are the recommendations and suggestions that need to be observed for
the estimation of shaft load capacities in Bangkok subsoils.
Sliwinski and Fleeming (1974) suggested that in clay soil, the bentonite has no effect on
friction and no reduction of the normal factors for deriving adhesion is justified. There may
indeed be a slight increase of adhesion. In granular soils, the bentonite has some effect. The
reduction of friction calculated from effective lateral pressure and coefficient of friction
should be considered in the region 10-30%.
Oonchittikul (1990) back analyzed a parameter = (Ks.tan ) from instrumented bored
pile load tests conducted with bentonite slurry in Bangkok subsoils by using the effective
stresses with both the hydrostatic pore pressure and the declined pore pressure. The resulted
value in the first and second sand layers from effective overburden pressure based on
hydrostatic pore pressure falls in the range of 0.4 to 0.65 and 0.2 to 0.4 respectively while
value in the first and second sand layers from effective overburden pressure based on declined
pore pressure falls in the range of 0.1 to 0.48 and 0.1 to 0.2 respectively. In both cases
value in second sand layer is less than the value in the first sand layer. The author inferred
that the overburden pressure might not fully develop at great depth in sand layer as it has been
assumed in the calculations.
Hooley & Brooks (1992) have suggested that if the traditional pile design approach is
used, the proper interpretation must be given to the accuracy of the data employed by soil
investigation as the potential error in the calculation of ultimate base resistance increases
steadily with depth and shaft resistance error increases gradually with depth. The authors
reported that it is noticeable that the amount of scatter in the test result from soil investigation
samples increases with depth and thus the average line is more difficult to define at greater
depths. If the scatter is analyzed statistically, upper and lower bound of average line can be
identified on the basis of chance of error 0.01% probability.
Eide & Bellis (1992) extracted data from 13 numbers of loading tests taken to failure
from the test results of over 109 tests in Bangkok which are presented by Oonchittikul (1990).
The authors found average shaft friction in stiff clay and dense sand in the range 78 to 130
KPa and adopted 100 KPa as design value, which is commonly used for design in Bangkok
Subsoil.
Teparaksa (1992) reported the problem from bentonite sedimentation causes a soft base.
Unexpectedly, low skin friction can be mobilized at failure (design at yield point) in soft base
condition. The author also reported that the static load test results on 1.50 m dia. pile at Pok
62
V ~ 62
Klao bridge project in Bangkok indicates an excessive settlement at 4000 KN load which is
caused by deposition of bentonite at the base of the pile. Analysis of load transfer indicates
that the skin friction of first stiff clay, first sand, and second stiff clay are equal and about 40
KPa at 4000 KN load. After the base grouting with cement-mortar, the analysis shows the
skin friction of this soil is between 40 to 90 KPa at about 5 mm. movement. They are in the
expected range for each soil layer, which is not affected by grouting.
Meiner et al. (1993) studied the influence on bearing behavior of bored piles when the
pile base is approaching a layer of soft soil layer and concluded that a significant punching
mechanism is obtained for value of t/d =2, where t is the distant from pile base and the clay
layer and, d is the pile diameter. This punching mechanism would decrease significantly both
shaft and base resistance.
Tomlinson (1996) suggested that if pile is excavated by grab under water, there is
considerable loosening of the soil. This causes a marked reduction in both end bearing and
skin friction. Then the design calculation will be calculated on the basis of a low relative
density of the granular soil.
Littlechild et al. (1998) reported that the shaft resistance of both the plain and shaft
grouted bored piles in sand appears to be mostly independent of the vertical effective stress
over the stress range encountered. From the test result of plain bored piles constructed in
accordance with a given specification of BERTS project in Bangkok i.e. bentonite viscosity
<35 sec and construction time of less than 24 hours, the shaft resistances fall in the range 65
to 170 KPa. In addition, they have determined a design line for shaft resistance of plain bored
piles in Bangkok sand of 120 KPa for all ranges of vertical effective stresses.
Thasnanipan et al. (1998) revealed that the end bearing capacity of bored pile where toe
is embedded in to the clay layer would be reduced and this end bearing capacity reduction
might influence the shaft resistance capacity too. This conclusion was reinforced by the pilot
pile load test result in the project located on Rama III road in Bangkok having diameter 1500
mm, toe founded at 60m in clay layer, failed at only about 17500 KN with total settlement of
over 90 mm. While the designed maximum test load was 25000 KN compared to the pile load
test from contract pile of same diameter toe depth founded in sand layer at depth 55 m and
base grouted. Result of test up to 2500 tons with total settlement of only 29.26 mm and elastic
recovery was 17.52 mm recorded.
CODES AND SPECIFICATIONS
Specifications are prepared for the good of the project. Specs drafted by ignoring the
practical site constraints and specific project needs can cause a job to become problem for all
parties. For example, some specs have been found to stressing on maximum allowable
construction time of 24 hours, which sometimes become impossible to adhere to because of
the prevailing traffic congestion in the city centers and local authority regulations in Bangkok,
and ultimately instigate the contractor to breach the law in order to comply with such
unpractical specs. A summary of the slurry specifications used worldwide is given in Table 1.
In the following are given some suggestions related to the excavation under bentonite slurry.
Fleming et al. (1975) suggested that the specifications should set out a cause of action to
perform the work, which is reasonable from the contractors point of view and gives a
reasonable expectation of achieving the desired end product. A specification loses
creditability on site if its requirements are outside the range of practical achievement and such
a specification can only be detrimental to the whole job. They further suggested that obscure
requirements will naturally be the first to be forgotten. Thus, for example, it is better to say
after mixing concrete shall be placed before it lose the specific workability than to say
concrete shall be placed within X minute (s) from mixing.
V 63
~ 63
Lttlechild & Plumbridge (1998) reported that the majority of the piling contractors state
that a maximum construction time for bored pile constructed to depth 50m under bentonite
slurry for BERTS project in Bangkok of less than 24 hours per pile would not be realistic. A
maximum construction time of 24 hours and slurry viscosity of less than 35 seconds (use of
Bentosund bentonite only) were therefore adopted for the project.
Chodorowski & Duffy (1998) presented the typical control and progress charts for 24
hours limit on construction time of bored piles at BERTS project, Bangkok. Charts prepared
by the authors show that during the 24 month period of bored pile construction, there was
noticeable percentage of pile constructed longer than 24 hours of approximately 15% which
in some months as much as 30%. They reported that longer construction time of more than
24 hours per pile was due to difficulties in securing continuous concrete supply as a result of
traffic congestion in the area of different piling sites.
Table 1: Summary of recommended values of slurry properties used for bored piles.
Authors
Parameter
Slurry Type
Density
(gm/
cc)
pH
Sand Content
Marsh Funnel
Viscosity
(sec/
Qt)
Plastic (cP
Viscosity
)
Yield(Pa
Point
)
10 min. Gel Strength
(Pa
)
Differential Head
(m
)
Fluid Loss
(30 minute test)
* Maximum Contact
Time
(hr.)
FP
S
1975,
1977
FDOT
Hutchin Hodgso
Holden
gso
,
n
1987,
n
1984
1977
et al.,
1988
1975
Bentonite Calcium
Bentonite
<1.10
1.024 to
1.218
9.5 to 12
<11.7
<6%
(by weight)
Bentonite
1.024 to
1.135
10.8 to 11.7
<14%
<35%
by volume
(by weight) (5% max.
by weight)
Bentonite
Sodium
or
Bentonite
Attapulgite
1.03 to
1.20
8 to 11
10% max.
(by volume)
Rees
e&
O'Neil
1988
Bentonite
or
Polymer
Bentonite
or
Bentonite
Attapulgite
<1.10
<1.36
Friction
Shaft
1.03 to 1.10
1.03 to 1.20
1.02 to 1.07
1.02 to 1.13
<1.10
<1.15
8 to 11
9.5 to 12
8 to 12
8 to 11
8 to 11
8 to 10
8 to 10
9.5 to 10.8
9.5 to 11.7
(by volume)
<25%
(by volume
Friction
Shaft)
<4%
<4%
(by volume)
1.03 to 1.20
1.03 to 1.20
8 to 12
<4%
28 to 40
28 to 45
<20
<20
3 to 20
<20
<20
<20
4.2 to 41.8
2 to 10
1.9 to 10
4 to 40
1 to 1.5
>1
Bentonite
1989
30 to 40
10 to 40
Bentonite
1988
3.6 to 20
Bentonite
or
Attapulgite
AASHTO
4 to 40
ICE
FPS
ARUP
1996
ACI
30 to 90
1992
Majano
&
O'
Neil
1993
ICE
30 to 90
26 to 50
28 to 45
28 to 45
<4 %
<10%
<2%
<2%
32 to 60
32 to 60
30 to 70
< 90
6 to 8.5
6 to 10.0
2 to 6.0
2 to 6.5
4 to 40
4 to 40
1.5
< 40
<60
ADSC and DFI drilled shaft inspectors manual clause 4.5.1, advised that where
bentonite slurry remains in the shaft unagitated for 3 or 4 hours, or more than 24 hours even
though agitated, a mud cake may develop on the shaft walls which can reduce friction.
Unless, the designer has accounted for caking and appropriately reduced design friction
value or the specification gives other limitation, portion of the shaft or socket designed for
side friction should either be excavated and concreted within a 24 hours period (and no more
than 3 hours when the slurry is not agitated) or re-reamed or re-scraped to remove the mud
64
V ~ 64
cake prior to concreting, or some method which is acceptable to the geotechnical engineer and
the inspector used to demonstrate that detrimental mud caking has not occurred.
ADSC Specification Clause 2.3.5.2 (g) specified that the drilled pier constructed under
bentonite slurry should be concreted and completed the same day that of excavation. If this is
not possible, the excavation shall be re-drilled, cleaned and slurry tested before concreting.
Shaft friction could be mobilized to carry load satisfactorily with a reasonable factor of safety
and within a tolerable displacement of 12 mm at working load.
FHWA guide for drilled shaft specification, stipulates that, that drilling slurry is an
effective method of stabilizing drilled shaft excavation until either a casing has been installed
or concrete has been placed. Primary concerns connected to slurry use are: the shape of the
borehole would be maintained during the excavation and concrete placement; the slurry does
not weaken the bond between the concrete and both the natural soil and rebar; all of the slurry
is displaced from the borehole by the rising column of fresh concrete; and any sediment
carried by the slurry is not deposited in the borehole. The engineers concerns regarding the
behavior and effectiveness of slurry project, can be satisfied by appropriate specification
requirements. These requirements include: specifying a suitable range of slurry properties
both prior to and during excavation and prior to concreting; performing slurry inspection test;
and construction of pre-production trial shaft by the slurry method.
FULL SCALE TEST TO ASSESS THE EFFECT OF CONSTRUCTION PARAMETERS
Since the degree of effect of different parameters greatly depends upon the soil
properties encountered, conclusions made for one type of soil are not directly applicable to
other locations with different geology. Static, instrumented load test program on bored and
barrette pile conducted at BECM tower project Rama IX road, Bangkok, provided the unique
chance to determine the effects of construction parameters on the shaft capacity (Thasnanipan
et al., 1999). Bored pile 1.5m diameter and a barrette 1.5x3.0m in cross-section had same
lengths of 57.5m founded in the second sand layer and located 30m apart having similar soil
embedment conditions. Properties of the bentonite slurry used are given in Table 2.
Table 2. Comparison of bentonite slurry properties for test pile and barrette.
Pile
Properties
Viscosity (sec)
Density (g/cc)
pH value
Sand Content (%)
Before feeding
to the borehole
33
1.08
8
0.1
Barrette
36
1.10
8
0.8
Before feeding
to the trench
36
1.10
8
1.0
49
1.17
9
1.1
Total construction time for the bored pile and barrette was 27 and 75 hours,
respectively. However, the total elapsed time between the final excavation (re-drilling &
cleaning) and concreting for the pile and barrette was 16.25 and 20 hours, respectively. In
spite of considerable difference in the total construction time and slurry viscosity, values of
unit shaft friction mobilized in different soil layers did not show any difference in the shaft
load transfer characteristics. This proves that the total construction time is not a crucial
parameter, which effects the shaft load capacity if good engineering practices like re-drilling
the borehole is applied.
V ~ 65 65
CONCLUSIONS
Conclusions of various researchers can be summarized as follows:
Bentonite viscosity up to the normally recommended range i.e. 60 sec., given in Table 1
does not have any significant effect on the skin friction capacity of bored piles. In
authors point of view, filter loss is the more relevant property of the slurry, which
directly effects the formation of the filter cake and finally results in the shaft capacity
reduction rather than the viscosity.
Selection of pile design parameters with due consideration of site constraints is equally
important. Adequate strength reduction factors based on the local experiences suggested
by local research institutions need to be considered.
Concreting should be completed within 24 hours after the finishing excavation of
borehole. If due to some unavoidable reasons borehole is left filled with slurry beyond 24
hours with out agitation, re-drilling must be carried out to scarp off any filter-cake present
on the walls of the borehole.
Performance of bored piles, to a large extent, depends upon the installation procedures
and, the skill of the operating crew, if proper construction procedures have been followed
REFERENCES
ADSC and DFI (1989), Drilled Shaft Inspectors Manual prepared by The Joint CaissonDrilled Shaft Committee of the ADSC: The International Association of Foundation
Drilling and DFI: Deep Foundations Institute.
ADSC Standards and Specifications, Foundation Drilling Industry. (1995). Incorporations.
ACI 336.1 94.
American Concrete Institute (1989), Standard Specifications for the Construction of Drilled
Piers, ACI Structural Journal 89, 1, pp. 94-103.
Cernak, B. (1976), The Time Effect of Suspension on the Behavior of Piers, 6th European
Conf. on Soil Mechanics and Foundation Engineer, Vienna.
Chaidesson, R. (1961), Influence of the Boring Method on the Behavior of Cast-In-Place
Bored Piles (in French with English Summary). Proc. 5th Int. Conf. Soil Mech. Paris.
Chodorowsi A.R. & Duffy, M.R. (1998), Quality Assurance and Testing on a contract for
16,000 Large Diameter Bored Cast In-Situ Piles. 7th Int. Conf. and Exhibition on Piling
and Deep Foundations, Vienna, Austria.
Corbett, B.O., Davies, R.V. & Langford, A.D. (1970), A Load Bearing Diaphragm Wall at
Kensington and Chelsea Town Hall, London. Proc. of the Conf. on Diaphragm Wall &
Anchorage organized by ICE, London.
Eide, O. & Bellis, J.A. (1992), Foundation of Bridges in Bangkok. Int. Conf. on Deep
Foundation. London.
V ~ 66
66
Farmer, I.W., Buckley, P.J.C. & Sliwinski, Z. (1970), The Effect of Bentonite on the Skin
Friction of Cast-in-Place Piles. Proc. of the Conference on Behavior of Piles. organized
by ICE London.
Federation of Pilling Specialists (1975), Specifications for Cast-In-Place Piles Formed under
Bentonite Suspension, Ground Engineering, 8, No. 2, 50 pp.
Fleming, W.G.K. & Sliwinski, Z.J. (1977), The Use and Influence of Bentonite in Bored Pile
Construction, CIRIA REPORT PG3.
Fleming, W.G.K., Fuchsberger, M., Kipps, O. & Sliwinski, Z. (1975), Diaphragm Wall
Specification, Proc. of the Conference on Diaphragm Wall & Anchorage organized by
ICE, London.
Fleming, W.G.K., Weltman, A.J., Randolph, M.F. & Elson, W.K. (1992), Piling Engineering
(2nd edition). John Willy & Sons.
Florida Department of Transportation (1988), FDOT Standard Specification for Road and
Bridge Construction, Section 455: Foundations of Structures, Tallahassee, FL.
Guide Drilled Shaft Specification, U.S. Department of Transportation, Federal. Highway
Administration. Geo-Technical Engineering Note Book. Geotechnical Guideline no. 14.
Distributed by ADSC, Texas, USA.
Ho, C.E. & Lim, C.H. (1998), Barrettes Designed as Friction Foundations, Proc. of Fourth Int.
Conf. on Case Histories in Geotechnical Engineering. St. Louise, Missouri.
Hodgson, F.T. (1977), Design and Control of Bentonite/Clay Suspensions and Concrete in
Diaphragm Wall Construction, Seminar on A Review of Diaphragm Walls, ICE,
London.
Holden, J.C. (1984), Construction of Bored Piles in Weathered Rocks, Part 4: Bentonite
Construction Procedures, Technical Report No. 69, Road Construction Authority of
Victoria, Australia.
Hooley, P. & Brooks, S.R. (1992), Site Investigation of Bored Piling in London Clay. Piling
European Practice and Worldwide trends. Proc. of a Conf. organized by the ICE,
London.
Hosoi, T., Yaki, N., & Enoki, M. (1994), Consideration to the Skin Friction of Diaphragm
Wall Foundation. 3rd Int. Conf. on Deep Foundation Practice incorporating Piletalk
1994, Singapore.
Hutchinson, M.T., Daw, G.P., Shotton, P.G., & James, A.N. (1974), The Properties of
Bentonite Slurries Used in Diaphragm Walling and Their Control, Proc. of Conf. on
Diaphragm Walls and Anchorages, ICE, London.
Littlechild, B. & Plumbridge G. (1998), Effects of Construction Technique on the Behavior of
Plain Bored Cast in Situ Piles Constructed under Drilling Slurry, 7th International Conf.
and Exhibition on Piling and Deep Foundations Vienna, Austria.
Littlechild, B.D., Plumbridge , G.D. & Free, M.W. (1998), Shaft Grouted pile in sand and
clay in Bangkok .7th Int. Conf. and Exhibition on Piling and Deep Foundations, Vienna,
Austria.
Majano, R.E. & ONeil, M.W. (1993), Effect of Mineral and Polymer Slurry on Parameter
Load Transfer in Drilled Shaft. A Report to ADSC; by University of Houston, USA.
V ~ 67
67
Meibner, H., Shen, Y.L., Van Impe, W.F & Vogt, C. (1993), Punching Effect for Bored Piles.
Proc. of the 2nd Int. Geotechnical Seminar on Deep Foundation on Bored and Auger
Piles; Ghent, Belgium.
ONeil, M.W. & Reese, L.C. (1992), Behavior of Axially Loaded Drilled Shafts in Beaumont
Clay. Report No. 89-8, The University of Texas at Austin. U.S.A.
Oonchittikul, S. (1990), Performance of Bored Piles in Bangkok Subsoils. M. Engg Thesis,
V ~ Bangkok,
67
Asian Institute of Technology (AIT),
Thailand.
Reese, L.C. & Tauma, F.T. (1972), Load Test of Instrumented Drilled Shafts Constructed by
the Slurry Displacement Method. Center for Highway Research. The University of
Texas at Austin. U.S.A.
Reese, L.C. & Tucker, K.L. (1985), Bentonite Slurry in Construction Drill Piers. Proc. of a
Session sponsored by the Geotechnical Engineering Division of the American Society
of Civil Engineers in Conjunction with the ASCE Convention, Denver, Colorado.
Reese, L.C. & ONeil, M.W. (1988), Drilled Shafts: Construction Procedure and Design
Methods prepared for U.S. Department of Transportation, Federal Highway
Administration office of Implementation, Mc.Lean, Virginia. in cooperation with
ADSC: The International of Foundation Drilling. Dallas, Texas.
Sliwinski, Z. & Fleming, W.G.K. (1974), Practical Consideration Affecting the Performance
of Diaphragm Walls, Proc. of the Conf. on Diaphragm Wall and Anchorages, ICE,
London.
Sliwinski, Z.J. (1977), The Effect of the Bentonite Displacement Method of Construction on
the bearing Capacity of piles and Diaphragm Wall Elements. Notes for the meeting of
the concrete Society. Croydon, October 12, 1977, (Unpublished.).
Teparaksa, W. (1992), Behavior of Base Grouted bored piles in Bangkok Subsoils. Piling
European Practice and Worldwide Trends. Proc. of the conf. organized by the ICE,
London.
Thasnanipan, N., Baskaran G. & Anwar, M.A. (1998), Effect of Construction Time and
Bentonite Viscosity on Shaft Capacity of Bored Piles, Proc. of the 3rd Int. Geotechnical
Seminar on Deep Foundations on Bored and Auger Piles, Ghent, Belgium.
Thasnanipan, N., Maung, A.W. & Tanseng, P. (1998), Barrettes Foundation in Bangkok
Subsoils, Construction and Performance. Thirteenth Southeast Asian Geotechnical
Conference, Taipei, Taiwan.
Thasnanipan, N., Teparaksa, W., Maung, A.W. & Baskaran, G. (1998), Design, Construction
and Behavior of Bored Cast In-Situ Concrete Piles in Bangkok Sub Soil. Proc. of
Fourth Int. Conf. on Case Histories in Geotechnic Engineering, St. Louise , Missouri.
Tomlinson, M.J. (1996). Pile Design and Construction Practices. (4th Edition).
Wardle, I.F., Price, G., & Freeman J., (1992), Effect of Time and Maintained Load on the
Ultimate Capacity of Pile in Stiff Clay. Piling European Practice and Worldwide trends.
Proc. of the Conf. Organized by the ICE, London.
Wates, J.A. & Knight, K. (1975), The Effect of Bentonite in the Skin Friction in Cast in-Place
Piles and Diaphragm Walls. Proc. of Sixth Regional Conf. for Africa on Soil Mechanics
and Foundation Engineering, Dorhan, South Africa.
V ~ 68
68
69
71
P-1
P-2
Depth (m)
P-3
Figure 1: Typical soil profile along a 4.5 km long stretch of an expressway in the plain of
Bangkok, with different pile embedment conditions.
embedment conditions like P-1 and P-3, 2nd stiff clay often exhibit a brittle type of failure and
peak skin friction values are mobilized well before the sand layers.
A family of t-z curves obtained from the instrumented pile load tests showing this type
of failure is presented in Figure 2. The peak friction values in these layers are mobilized at
very low pile head movements (10 15 mm depending upon the depth of stiff clay layer) and
well before the ultimate friction values of other soil layers present along the pile shaft. When
rest of the soil layers reach their peak friction values stiff clay layers have reached the residual
friction values.
10
8
9
7
6
5
4
3
2
1
0
0
200
400
600
800
1000
1200
Figure 2: Family of curves obtained from instrumented pile load tests showing typical brittle
failure in stiff clay layers.
72
V ~ 70
A typical load test showing this type of behavior is shown in Figure 3. It can be seen
that the stiff clay layers reach their ultimate friction values well before the sand layers and at
the maximum test load stiff clay layers reach their residual friction values. Design parameters
like and suggested by different researchers like Suchada (1995) for the estimation of
ultimate skin friction in Bangkok subsoils give a reasonable estimate for the embedment
conditions like at P-2 in Figure 1 or where the thickness of 2nd stiff clay layer is relatively
low. Exceptions have been observed in case of embedment conditions especially like P-1,
where a thick 2nd stiff clay layer is present. Owing to the difference in shaft friction
development with pile head movement in the stiff clay layers as shown in Figure 3, direct
summation of (simple superposition) ultimate shaft friction capacities in different soil
horizons leads to over estimation of shaft capacity of these piles. Due to the brittle nature of
failure mechanism in very stiff to hard clay layers peak friction resistance is mobilized at
comparatively very little movement at the pile/soil interface. Residual values of friction
resistance in these layers drop to 50 percent or even smaller of the peak friction values
mobilized.
Butt Load
0.00
14
Soft Clay
Su = 1.5 t/m 2
10.00
40.00
1st Sand
2nd Stiff
Clay
Su = 13.5 t/m 2
SPT-N = 35
Su = 25.5 t/m 2
50.00
Medium Clay
1st stiff Clay
Depth (m)
30.00
1st Stiff
Clay
Su = 4.5 t/m 2
Bored Pile
Medium
Clay
20.00
Soft Clay
12
10
1st Sand
2nd Stiff Clay
2nd Sand
2nd Sand
SPT-N = 50
400
800
1200
1600
2000
Figure 3: Skin friction development with the increase in butt load which clearly shows a
typical early yielding of stiff clay layers.
On the extreme, from some instrumented pile load test results it has been observed that
stiff clay layers reach their peak friction values near the design service loads. Rest of the soil
layers need further pile/soil interface movement for the full mobilization of skin friction, and
at this stage, stiff clay layers have already arrived at their residual friction values. Now
depending upon the relative thickness of stiff clay layers, overall shaft friction capacity
mobilization is affected differently. If the thickness of very stiff to hard clay layers is such
that their contribution in the total shaft friction capacity is proportionally high, when stiff clay
layer yields, load settlement curve shows a localized plunging behavior. The movement of
such plunging consists of few millimeters and when the other soil layers shares the deficit in
73
V ~ 71
Table 1: Comparison of maximum skin friction values mobilized and the values at maximum
test load.
Soft Clay
1.5
1.7
1.13
1.6
1.07
Medium Clay
4.5
2.2
0.49
1.9
0.42
13.5
5.8
0.42
5.1
0.38
25.5
8.8
0.34
4.2
0.16
Undrained
Shear
Strength
Su (ton/m2)
Clay Layer
peak and residual friction capacity of these layers, once again pile starts taking load followed
by this local plunging, as shown in figure 4, till the final plunge exhibiting the failure of all
soil layers along the pile shaft reaches. It must be noted that this localized plunging was
earlier conjectured to be because of the soft toe of the piles. On the other hand if the
contribution of skin friction derived from very stiff to hard clay layers is proportionally low,
localized plunging due to earlier failure of very stiff to hard clay layer is not visible. Normal
practice to estimate the contribution of skin friction from clay layers is by using method,
with a value of equal to around 0.3 for very stiff to hard clay layers. Instrumented pile load
test results have shown that skin friction values calculated using value equal to 0.3
corresponds to the peak skin friction in these layers. Owing to the brittle type of failure
mechanism in these layers, values at full mobilization of total shaft friction capacities drop
to as low as 0.15 in some cases and the ultimate shaft capacity calculated gives over estimates
as compared to the actually mobilized capacities. Skin friction values mobilized in the pile
load test shown in Figure 3 are given in Table 1.
0
500
1500
2000
0
20
TP-1
TP-2
40
60
80
100
120
Figure 4: Typical load-settlement curves showing localized plunging before the overall failure
of the pile.
74
V ~ 72
Peak and residual values mobilized in the stiff clay layers from Table 1 are plotted in
figure 5 along with the suggested curves by different researchers. It can be noted that the
peak value mobilized in 2nd stiff clay layer corresponds well to the value suggested by Stas
& Kulhawy (1984). But the residual value at the maximum test load drops below the curve
suggested by Suchada (1989). So the values proposed in figure 5 for the stiff to hard clay
layers gives overestimate of the ultimate shaft friction under theses conditions.
1.20
Bored Cast Insitu Piles
1.00
Adhesion Factor ,
Tomlinson,1957
0.80
Suchada,1989
for bored piles in Bangkok soils
0.60
0.40
Peak
Stas and Kulhawy, 1984
0.20
Residual
0.00
0.00
5.00
10.00
15.00
20.00
25.00
30.00
Figure 5: Comparison of adhesion factor , suggested by different researchers with the actual
mobilized in the stiff clay layers.
EFFECT OF LOWER END BEARING VALUES ON SKIN FRICTION
Meibner & Van Impe (1993) firstly reported the influence of lower end bearing values
on the shaft friction capacity of piles. Laboratory model tests as well as finite element
analysis performed by the authors showed that the presence of soft soil within a depth of two
to four times pile diameter below the pile tip, not only decrease the end bearing but also the
skin friction capacity. Thasnanipan et al. (1998) also revealed that the end bearing capacity of
bored pile where toe is embedded in to the clay layer would be reduced and this end bearing
capacity reduction might influence the shaft resistance capacity too. This conclusion was
reinforced by the pilot pile load test result in the project located on Rama III road in Bangkok
where bore pile having diameter 1500 mm, toe founded at 60m in clay layer, failed at only
about 1750 tons with total settlement of over 90 mm. While the designed maximum test load
was 2500 tons. An other contract pile of same diameter and founded in sand layer at depth 55
V ~75
73
m and base grouted was successfully tested up to 2500 tons with total settlement of only
29.26 mm and elastic recovery was 17.52 mm recorded. Even though the second pile was
shorter in length than the first, more skin friction was mobilized due to the improved end
bearing conditions. A similar decrease in the shaft friction capacity in the sand layers has
been observed from the instrumented pile load tests at another project in Bangkok.
CONCLUSIONS
For the piles embedded in the multi layered soils of Bangkok, estimation of ultimate shaft
friction capacity needs to consider the brittle type of failure mechanism of stiff to hard clay
layers and the values selected need to be adjusted accordingly. Where the pile tips are
embedded in the clay layer, effect of lower values of end bearing on shaft capacity should also
be considered.
ACKNOWLEDGEMENTS
The authors are grateful to their colleagues, especially Mr. Pornpot Tanseng for their
assistance in the preparation of this paper.
REFERENCES
Meibner, H., Shen, Y.L., Van Impe, W.F. & Vogt, C. (1993), Punching Effect for Bored
Piles. Proc. of the 2nd Int. Geotechnical Seminar on Deep Foundation on Bored and
Auger Piles; Ghent, Belgium.
Stas, C.V. & Kulhawy, F.H. (1984), Critical Evaluation of Design Methods for Foundations
Under Axial Uplift and Compression Loading, Report EL-3771, EPRI, Palo Alto, Calif.
Suchada (1989), Bored Piles in Bangkok Subsoils, M. Engg. Thesis, AIT, Bangkok.
Thasnanipan, N., Baskaran G. & Anwar, M.A. (1998), Large diameter bored piles in
multilayered soils of Bangkok, Proc. of the 3rd Intl. Geotechnical Seminar on Deep
Foundations on Bored and Auger Piles, Ghent, Belgium, Balkema.
Thasnanipan, N., Teparaksa, W., Maung, A.W. & Baskaran, G. (1998), Design, Construction
and Behavior of Bored Cast In-Situ Concrete Piles in Bangkok Sub Soil. Proc. of Fourth
Intl. Conf. on Case Histories in Geotechnic Engineering, St. Louise, Missouri.
Tomlinson, M. J. (1957), The adhesion of Clay Piles Driven in Clay Soils, Proc. 4th Intl.
Conf. on Soil Mechanics and Foundation Engineering, London.
76
V ~ 74
GeoEng2000
An International Conference on
Geotechnical & Geological Engineering
19-24 November 2000
Melbourne Exhibition and Convention Centre
Melbourne, Australia
77
GeoEng2000 An International Conference on Geotechnical and Geological Engineering 19-24 November 2000, Melbourne, Australia
ABSTRACT
An efficient design of foundations for transmission line towers has always been a challenge for the
engineers due to the variety and cyclic nature of the loads. Foundations, especially for the four-legged
towers, are subjected to all types of loads (compression, tension, torsion and shear) in different combinations.
The cyclic nature of the loads further complicates the situation. Available design parameters proposed by
different researchers are also mostly based on the monotonic loading conditions and are not directly
applicable for tower foundations. This paper presents the analysis, design and construction practice of the
barrettes used for the transmission line towers in Thailand. Adaptability of the barrettes under different site
constraints like sensitive underground pipelines is also described.
INTRODUCTION
The 230kV-transmission line project presented in this paper involved construction of 40 transmission
towers, 400m apart. The project site was located about 200km, east of Bangkok, Thailand. The transmission
line was planned to convey electricity from the power plant to a sub-station. The alignment of 15.6km-long
transmission line partially runs along the boundary of an Industrial Estate and thus the foundations of these
towers are in close vicinity of existing underground gas pipelines and utilities above ground (Fig.1).
Foundation layouts, construction method and the work area were thus restricted by presence of these utilities.
GULF OF THA
ILAND
LEGEND :
LATTICE TYPE TOWER
MONOPOLE TYPE TOWER
TRANMISSION LINE
POWER
GENERATION
PLANT
GAS PIPELINE
CHEMICAL
PLANT
CHEMICAL
PLANT
CHEMICAL
PLANT
1.5km
GAS
SEPARATION
PLANT
CHEMICAL
PLANT
CHEMICAL
PLANT
0km
CHEMICAL
PLANT
2.5km
5km
SUB STATION
79
Construction of barrettes in a site with limited headroom and constraints and performance of barettes in
Bangkok soil has been reported by Thasnanipan et. al. (1998) and (1999). The past experience indicated the
feasibility of this project.
SOIL CONDITIONS
40
39
38
37
36
35
34
33
32
31
30
29
28
27
26
25
24
23
22
21
20
19
18
17
16
15
14
13
13/A
12
11
10
BH
No.
Initially, only a few boreholes were made to investigate subsoil conditions. However as the great distance
between towers meant that substantial variations in soil conditions could occur. An extensive soil
investigation was later carried out at all tower locations by drilling to verify subsoil condition to optimize
barrette design and for excavation feasibility. The general subsoil profile revealed fine to coarse sand at the
top, overlaying silty clay (lateritic soil) with varying thickness. The lateritic soil was not present at some
locations. Below the sand and lateritic soil was completely decomposed granite at varying depths. Figure 2
shows cross sections of subsoil at tower locations along the transmission line. The groundwater level found
also varied from about 0.6m to 9.2m below ground surface.
0.00
5.00
DEPTH (M)
10.00
15.00
20.00
25.00
30.00
LEGEND
CLAYEY SAND
SANDY CLAY (LATERITIC SOIL)
SANDY CLAY (COMPLETELY DECOMPOSED GRANITE)
SILTY SAND (COMPLETELY DECOMPOSED GRANITE)
BH-3
BH-11
SPT-N
SPT-N
50
100
50
BH-20
BH-32
SPT-N
100
50
BH-39
SPT-N
SPT-N
100
50
100
50
100
0.00
5.00
DEPTH (M)
10.00
15.00
20.00
25.00
30.00
80
BARRETTE DESIGN
The design of barrettes mainly involved (1) layout arrangement and (2) structural and geotechnical
capacity of barrettes in connection with load, site and soil conditions and construction practicality.
Regarding the layout, a four-barrette group (Fig. 5) was selected to support 38 lattice towers (up to 61.4m
high) individually where a large area was available. Otherwise, a cruciform barrette (Fig. 6) was used for
monopole towers (51.4m high). Compression, uplift and lateral forces were considered the significant loads
to barrettes and they depended on the position of the tower in the line, the natural forces (wind) exerted on
towers and cables and the weight of tower and cables. The towers were generally classified according to
their positions on the line; end towers, edge towers and towers on a straight line between two other towers.
The end towers were longitudinally loaded from one side by the cables and the overturning moment on such
towers was large. The edge towers were loaded both vertically and transversally while the towers on straight
line mainly carried a vertical load. A summary of estimated loads on the individual barrettes of the towers is
presented in Table 1. To achieve load carrying and uplift capacity based on the imposed load and soil
conditions, barrette sizes of 1.0x2.7m and 0.8x2.7m with depths from 11.0m to 22.0m were selected.
0.8x2.7
0.8x2.7
0.8x2.7
0.8x2.7
0.8x2.7
0.8x2.7
0.8x2.7
0.8x2.7
0.8x2.7
32
33
34
35
36
37
38
39
40
0.8x2.7
31
0.8x2.7
29
30
0.8x2.7
0.8x2.7
28
0.8x2.7
18
0.8x2.7
17
27
0.8x2.7
16
0.8x2.7
0.8x2.7
15
Horizontal (kN)
1087
898-1087
309-505
26
23
0.8x2.7
14
22
0.8x2.7
13/A
25
21
0.8x2.7
13
0.8x2.7
0.8x2.7
12
11
10
0.8x2.7
24
0.8x2.7
0.8x2.7
20
0.8x2.7
Uplift (kN)
3078
2804-3078
1032-1565
19
1.0x2.7 Monopole
1.0x2.7 Monopole
1.0x2.7 Monopole
Size
No.
Tower Barrette
Remark
0.00
5.00
DEPTH (M)
10.00
15.00
20.00
25.00
30.00
BARRETTE
0.80X2.70m
2.47
15.90
GAS PIPE
LINE
34"
2.67
15.90
3.48
4.47
GAS PIPE LINE
34"
A
-
0.
80
70
2.
15.90
SECTION A-A
81
Generally, a safety factor higher than 2.3 and 1.2 was adopted for compression and uplift load capacity
respectively. For uplift capacity, reduced friction capacity (up to 50%) in the cohesionless soil above fixity
level was used in calculation since barrettes were subjected to horizontal cyclic loading. Alexander J.
Verstraeten. (1987) has described decrease of friction by dynamic loading patterns in details. Finite element
method (FEM) was used for calculating bending stesses in the barrettes and prediction of lateral movements.
A total of 6 pile types was classified according to imposed loads, pile dimensions and soil conditions, and
then analysed by FEM. Reinforcement of barrettes was designed using strength design method. A concrete
cover 75mm was used for all barrette types.
The lattice towers were anchored in the barrettes by stubs and cleats which were cast into the extended
barrette section after trimming the barrette top. For monopole towers, anchor bolts and steel flanges were
used.
Three monopole towers were used where the lattice type tower could not be allocated. Due to the
presence of underground gas pile lines and the narrow area available, it was difficult to allocate barrette
groups with adequate alignment to resist the maximum bending moment and horizontal force up to
25,840kN-m and 635kN respectively. Cruciform barrettes were then designed to resist such high bending
moments and forces acting on the base of the monopole.
MONOPOLE
TOWER
2.00
PILE CAP
CRUCIFORM
BARRETTE
1.0X2.70m
1.00
2.70
3.40
SECTION A-A
GUIDE WALL
TREMIE PIPE
REINFORCEMENT
CAGE
BENTONITE
SLURRY
EXCAVATION
INSTALLATION OF
REINFORCEMENT
82
CONCRETING
Sediment or loose materials at the bottom of the trench were removed and any built-up filter cakes were
scraped off by the grab before reinforcement cage installation. Entire barrette length was fully reinforced
and up to 24m-long reinforcement cages were fabricated in one complete section, for installation into the
trench. The reinforcement cage of the cruciform barrette was as the same shape as the barrette. For the
purpose of lifting and handling the cage, temporary stiffeners, lacing and tie bars were necessary. These
temporary bars were removed section by section while the cage was lowered into the trench.
After excavation, the trench profile was checked with Koden drilling monitoring equipment. Tremie
concreting method was used for casting the barrettes. Since the cutoff level of barrettes was generally at
ground level, ready-mixed concrete was poured until all slurry and slime in the trench was completely
displaced and fresh concrete could be seen.
Up to 172kg/m3 and 381kg/m3 of SD40 steel bars with maximum steel percentage at barrette top section
(about 12.0m) were used to reinforce the group and cruciform barrettes respectively. Ready-mixed concrete
with cube strength of 38MPa at 28days was used for casting barrettes.
CONSTRUCTION PROBLEM AND CORRECTION
A trench collapse was reported during desanding operation after trenching was completed for a barrette
of lattice tower. A sudden fall of bentonite slurry level by a few meters in the trench was observed and then
the trench was found filled with soil up to 10m depth. Mode of failure of the trench was found to be in the
form of a localized cavity failure in the loose sand present at 2.0m to 6.0m depth. Failure surface did not
extend up to the ground surface and the guide wall was still intact without any distortion or damage. The
most probable cause of the trench collapse was due to heavy rainfall during construction. Surface water was
seen in the vicinity of the construction area. The rain had raised the groundwater level to near the ground
surface and caused a groundwater flow reversal towards the trench, triggering cavity formation in the loose
sand stratum. The cavity progressively increased in size, leading to the collapse of the trench during the
desanding operation. The collapse trench was backfilled with cement-bentonite mix, and wooden piles were
driven into the collapse area outside of the barrette outline. The guide wall was then raised up to 1.5m above
ground level. The trench was re-excavated under the slurry head 1.5m above the expected groundwater level
and the barrette was completed.
QUALITY CONTROLS
All trenches were checked for verticality and dimensions prior to reinforcement cage installation to avoid
any obstruction associated with trench inclination. In particular, all sides of the cruciform trench were
checked. If necessary, verticality of trench was improved by careful chiselling with the grab. Profiles of the
trench for a cruciform barrette is shown in Figure 10.
As the subsoil conditions varied from one location to another, they were observed during trenching
process and verified with the soil conditions assumed in design, especially in the lower section of the
barrette. Slurry quality was regularly tested and maintained within the specified ranges. Since barrettes
83
were highly reinforced, in order to achieve a good flow of concrete, the concrete mix was checked for
appropriateness of slump and cohesiveness prior to casting.
Sonic integrity/seismic test was carried out on all barrettes about 5 days after casting for checking barrette
integrity. The test indicated that integrity of all barrettes were sound. Figure 11 shows a signal acquired by
sonic integrity test on the cruciform barrette.
DISCUSSION AND CONCLUSION
For barrette piling in loose cohesionless soil, chances of rapid groundwater level rise due to the rain, tide,
etc., need to be considered during trenching. If necessary, guide wall with appropriate height above the
possible highest groundwater level must be used.
Barrettes are versatile and can be used efficiently in the areas where conventional bored piling cannot be
done. Moreover, barrette construction uses less quantity of equipment than bored piling and thus it is
suitable for the piling work requiring shifting from one location to another.
Verticality of trench is critical for barrettes with complex cross-sectional shape, such as cruciform, T and
H for reinforcement cage installation. A thick concrete cover up to 100mm is thus recommended, in
particular for cruciform barrettes for ease of reinforcement cage installation and to maintain the adequate
concrete cover, considering trench verticality against high stiffness of rebar cage.
REFERENCES
Thasananipan N., Singtowkaew K. and Tanseng P. (1999), "Experiences in Construction of Barrette (in
Thai)", National Convention on Civil Engineering, Pattaya, Thailand, May 24-26, 1999. pp. GTE-144149.
Thasnanipan, N. Maung, A. W. and Tanseng, P. (1998), "Barrettes Founded in Bangkok Subsoils,
Construction and Performance", Thirteenth Southeast Asian Geotechnical Conference, Taipei, Taiwan,
ROC, November 16-20, 1998. pp. 573-578.
Alexander J. Verstraeten. (1987), "Steel Pile Foundations for Transmission Line Towers, as Used in Western
Europe", Proceeding of the 2nd International Conference of Deep Foundation Institute, Luxembourg, May
4-7, 1987. pp. 297-325.
84
Proceedings of the
85
GEOTECH-YEAR 2000
Developments in Geotechnical Engineering
27-30 November 2000, Bangkok, Thailand
87
areas it lies under weathered crust layers of 2m thick. Depending on the location, this layer is
extended up to 12-18m. About 2m thick Medium Clay layer can be observed between Soft
Clay and underlying Stiff Clay. Generally Stiff Clay layer occurs directly underneath
Medium Clay and its depth goes up to 22m. Below Stiff Clay layer, First Sand layer 5-8m in
thickness can be found. This First Sand layer, however, is absent in some areas. Stiff to Hard
Clay layer underlies First Sand and it is found to be about 5m thick. Second Sand layer
generally occurs at depths between 45 to 65m.
Stanchions are mainly installed in the large diameter deep-seated bored piles and
barrettes founded in first or second sand layer. Bored piles of diameter 1.50m to 1.8m and
rectangular-shape barrettes of 0.80x2.8m to 1.5x3.0m (thickness x width) founding at depth
between 50m and 60m are commonly used to accommodate the stanchions. Wet process
method is always used for construction of these large bored piles and barrettes in Bangkok.
For bored piles, temporary casing of 14-15m in length is used as a support in soft clay layer.
Soil inside the casing is normally excavated by auger applying rotary drilling method and
drilling is continued with the bucket under the slurry from the top of sand layer to the final
depth. A cable-hung-grab mounted on crawler crane is used for excavation of trench with
slurry support in barrette construction. Guide walls having a minimum depth of 1.2m are
commonly used for initial guiding of grab excavation at the top of the trench. Tremie
concreting is necessary for casting both bored piles and barrettes.
APPLICATION OF TOP-DOWN CONSTRUCTION METHOD
Top-down construction method as the name implies, is a construction method, which
builds the permanent structure members of the basement along with the excavation from the
top to the bottom. Top-down method is mainly used for two types of urban structures, tall
buildings with deep basements and underground structures such as car parks, underpasses and
subway stations. For tall buildings with deep basements, a full application of top-down
method enables superstructure to build concurrently with excavation and construction of the
basement giving a significant advantage in reducing the overall construction time. Top-down
method is the most appropriate solution in minimizing the duration and disruption to surface
traffic and other urban activities, for the construction of the underground car parks,
underpasses and subway stations where the structure is located directly underneath the
existing roads.
Application of top-down method offers three main advantages as outlined below.
It does not require temporary bracing system so that time requirement and cost for
temporary works (both material and labor costs) are eliminated, in turn significantly
saving cost.
88
338
Excavation for basement must be carried out with the support of permanent
retaining wall so that basement floor slabs can be utilized as lateral bracing.
Diaphragm wall of 0.8m to 1.2m in thickness with sufficient embedment in firm soil
layers is commonly used as a retaining wall whereas prefabricated steel columns known as
stanchions embedded in either large diameter deep-seated bored piles or barrettes are utilized
as structural columns. Figure 1 illustrates the top-down construction method with utilization
of stanchions and diaphragm wall.
F3
Top
F2
F1
GF
B1
Stanchion
B2
Down
B3
B4
Bored Pile
D-wall
General Information
Application
For semi top-down
construction
For temporary decking
Mediumsized
stanchion
Steel H-beams
350x350x390 kg/m
Heavy
stanchion
Steel
H-beams
508x457x738kg/m
Composite steel columns
built up by 2 or more small
to medium size H-beams
Large section pre-cast RC
column (seldom use)
89
Limitation
Limited capacity of light
stanchion does not allow for
construction
of
super
structure until completion of
basement construction
Limited number of super
structure floors construction
Depending on the loading
condition, numbers of
superstructure floors can be
constructed before
completing basement
excavation
339
Tremie pipe
Stanchion
Stanchion
Slurry
Slurry
Slurry
Backfill
Temporary
casing
Temporary
casing
Temporary
casing
Pile cut-off
level
Pile cut-off
level
Pile cut-off
level
Concrete
Concreting by tremie
method
Installing stanchion by
plunging into concreted pile
Concrete
90
340
Concrete
Guide frame
Stanchion
Stanchion
Stanchion
Slurry
Slurry
Tremie pipe
Temporary
casing
Temporary
casing
Temporary
casing
Pile cut-off
level
Pile cut-off
level
Pile cut-off
level
Pile cut-off
level
concrete
concrete
Stanchion installation
Concreting
(1 tremie for bored pile and
2 tremie for barrette)
Backfill
(a)
(b)
Figure 4. (a,b) Installation of 24m long stanchion into borehole prior to concreting
Guide Frame for stanchion positioning
Guide frame is used for positioning of stanchion in both installation methods.
Effectiveness of guide frame plays one of the important roles in achieving positional accuracy
of stanchion. Figure 5 (a,b) shows the guide frame used for pre-concreting installation method
in one major project constructed by Seafco Co., Ltd.
91
341
(a)
(b)
Figure 5 (a,b) Guide frame used by Seafco for pre-concreting installation in one major project
REVIEW OF THE STANCHION INSTALLATION METHODS USED IN OTHER PARTS
OF THE WORLD
The stanchion installation methods used in other parts of the world have been presented
in some published papers. Among these, Findlay (1989) reviewed a number of stanchion
installation methods used in construction of large diameter bored piles for top-down
construction particularly in UK. The author reported that steel columns can be placed with
better accuracy by dry process bored piling method than wet process method (with support
fluid).
Hollingsworth (1991) demonstrated the installation of stanchions by plunging into
concrete with the aid of an adjustable guiding frame called Cemloc (European Patent No.
0302717) for seven levels basement of 25m deep constructed by top-down technique in
London.
Ressi di Cervia and Tamaro (1991) briefly explained the stanchion installation method
used for construction of an underground garage with top-down technique in Boston, USA.
Steel columns were installed prior to concreting in load bearing elements (LBE) or barrette
excavated by cable-hung mechanical clamshell buckets. The authors cited that using the same
equipment for construction of diaphragm wall and load bearing elements minimized the
congestion on site and streamlined the schedule.
Crawley and Stones (1996) presented the installation of 30m long composite steel
columns for top-down construction applied for Westminster Station in Central London.
Columns were placed with the aid of guide frame followed by concrete pouring. Accuracy of
25mm at the top of column with verticality of 1:200 was achieved as stated by the authors.
Arz (1989) presented an installation of heavy composite columns fabricated from six
steel H-beams encased by concrete (cast during fabrication) for construction of six storey
building with five basement using top-down method in Germany. Due to the high accuracy
requirement of 25mm, adjustable guide frame equipped with three hydraulically control arms
were used. Stanchions were installed prior to concreting as reported by the author.
From the available literatures it is noted that pre-concreting method is more common in
use than post-concreting method.
PROBLEMS ENCOUNTERED IN POST-CONCRETING INSTALLATION METHOD
The major problem commonly encountered in this installation method is inability to
install the stanchion at the design position due to one or combination of the following causes.
92
342
Stanchion can not be inserted up to the required depth as concrete becomes hard due
to the premature setting
During lowering, stanchion is stuck by reinforcement cage and due to the hardening
of the concrete, extraction of stanchion becomes impossible for reinstallation
As the installation of the stanchion is often associated with many unforeseen problems,
it is likely in many cases that concrete becomes stiff or prematurely set during the installation.
In Bangkok, premature setting of concrete is usually found to be attributed by;
inappropriate mix
severe weather
Factors effecting
accuracy
Verticality of piles
Concrete stiffening
or hardening
during installation
Inappropriate
backfill material
Improper back
filling
Improper
temporary casing
extraction
Discussion
Due to the use of fixed guide arm for guiding
stanchion against borehole wall, its verticality
is solely influenced by the verticality of
borehole.
93
Maintain
343
Factors effecting
accuracy
Verticality of piles
Concrete flows
pushing at
stanchion during
tremie concreting
Improper back
filling
Improper temporary
casing extraction
Skill and experience of the contractor plays a major role in achieving positional
accuracy of the stanchion provided that the installation is practical with the design elements
such as size of foundation piles in relation to size of stanchion.
94
344
Table 4 shows the summarized technical information of some major projects with
different stanchion type, size and installation depth.
Table 4. Summarized technical information of stanchion application in some major projects in
Thailand
Project
No.
Installation
Method
Bored pile
1.5x 60m
Pre-concreting
Bored pile
1.8x65m
Barrette pile
1.2x3.0x47m
Bored pile
1.8x65m
Bored pile
1.5x35m
1.8x35m
Postconcreting
Pre-concreting
-29.5m
Pre-concreting
-14.5m
Pre-concreting
-11.5m
2
3
4
5
Basement
Excavation
Depth (m)
-20.0m
-24m
Location
Silom Road
Bangkok
Rama IV Road
Bangkok
Ratchadapisek
Road Bangkok
Payathai Road
Bangkok
Haadyai
Note: * Top levels of stanchion in Project 2 and 3 are 3m and 1.8m below ground level respectively.
A view of heavy stanchions (built-up sections) exposed after excavating to the first
basement level is presented in Figure 7. Pre-concreting installation was used to install the
stanchions in this project.
Figure 7. View of built-up stanchions exposed after excavation to the first level of basement
COMPARISON OF AS-BUILT POSITIONAL TOLERANCE ACHIEVED BY TWO
INSTALLATION METHODS
Although the as-built position of stanchions installed by two different methods have yet
to be statistically analyzed, field survey data of Projects 2 and 3 indicated in above Table 4
suggested that stanchions could be more accurately installed by pre-concreting method.
Stanchions with as-built horizontal deviation greater than 100mm installed by two methods
(expressed by percentage) are presented in the table below.
95
345
Installation Method
Depth of
Measurement
Post-concreting Method
15.5m B.G.L
20 %
Pre-concreting Method
13.5m B.G.L
4%
CONCLUSION
Two common stanchion installation methods have been presented with particular
emphasis on the common problems encountered by each method and recommended measures
to alleviate them. According to the authors experience, pre-concreting installation method
provided fewer problems in practical installation and achieved better positional accuracy. A
comparison of as-built position of stanchion between two projects also suggested that
stanchions could be more accurately installed by pre-concreting installation method.
The designers such as structural engineers and architects should be aware of the
accuracy achievable by practical installation method and take it into consideration at the
design stage.
Stanchion installation contractor should select the appropriate method, equipment as
well as experienced personnel plus a well-formed plan with the consideration of all potential
problems to achieve the successful construction of foundation structure, which is of primary
importance for top-down technique.
REFERENCES
Arz P. 1989. Foundations of the Ko-Galerie in Dusseldorf Using Top-down Building
Technologies, Proceedings of the International Conference on Piling and Deep
Foundations, London, 15-18 May 1989 : 185-192. Rotterdam: Balkema.
Crawley J.D. & Stones C. S. 1996. Westminister Station Deep Foundation and Top-Down
Construction in Central London, Geotechnical Aspects of Underground Construction in
Soft Ground, London : 93-97. Rotterdam : Balkema.
Findlay J. D., Wren G.E. 1989. Review of the Methods Used to Construct Large Diameter
Bored Piles for Top Down Construction. Proceedings of the International Conference
on Piling and Deep Foundations, London, 15-18 May 1989 : 199-210. Rotterdam:
Balkema.
Finsted J. A. 1991. Royal Christiana Hotel : Basement with Permanent Sheet Pile Wall, Upand-down Method, 4th International DFI Conference : 387-392. Rotterdam: Balkema.
Hollingsworth J.R. 1991.
Diaphragm Walls, Load Bearing Piles and Piled Soil
Reinforcement for a Deep Top-down Basement Construction, 4th International DFI
Conference : 79-84. Rotterdam : Balkema.
Manoharn S. & Aye Z. Z. (1994) , Bored Pile with King-post and Secant Pile Wall
Construction for Top-Down Method Central Sukhothai Hotel Haddyai, Latest
Technology in Construction Technology Conference, Bangkok, Thailand
Yong K.S., Tsen C.N. & Tang S.K. 1998. Performance of a Deep Excavation with Top-down
Construction, 13th Southeast Asian Geotechnical Conference, 16-20 November 1998.
Taipei, Taiwan ROC : 587-593
96
346
Proceedings of the
97
GEOTECH-YEAR 2000
Developments and Geotechnical Engineering
27-30 November 2000, Bangkok, Thailand
347
99
used to case the top weak soil subjected to heavy construction loads. Drilling and
reinforcement cage installation and concrete placing are successively executed under drilling
slurry. The concret is poured with tremie pipes, displacing the slurry well above the cutoff
level. The temporary casing is then extracted immediately after concreting.
CHARACTERISTICS OF CONCRETE AND CONCRETE MIX
Concrete mix for bored piles is designed according to concrete pouring process and
mechanical properties required. Concrete for wet process piles needs to be specially mixed
having cohesiveness with high workability (high slump/excellent fluidity) which is not prone
to segregation and retain it workability as far as possible throughout the tremie placing
operation for the complete pour. Addition to those characteristics, compaction under selfweight, resistance to harsh environment, resistance to leaching, and appropriate strength are
essential.
Workability
Excellent fluidity is essential that the concrete has the ability to flow readily through the
tremie pipe, to flow laterally through a reinforcement cage and a high lateral stress against the
sides of borehole. High workability is best achieved with rounded natural aggregates and
natural sand in the mix.
Self Compaction
Compaction under self-weight is essential as vibration of concrete is impractical, except
near the surface. The degree of compaction achieved is determined by the density ratio (the
ratio of density actually achieved to the density of the same concrete fully compacted). The
recommended compacting factor for the required workability of tremie concrete is 0.95 to
0.96 (Xanthakos 1994). Fresh concrete is usually placed through tremie pipes and displaces
the slurry by gravity action only. In some cases, lack of self-compaction in the concrete will
lead to defects, such as reversed hanging up, and whirls in the completed pile. If the
initial shear of the concrete is very high, the flow is likely to restrain, resulting in bentonite
trapped in areas not reached by the concrete (Xanthakos 1994).
Resistance to Segregation
The concrete mix should be cohesive and resistant to segregation, as improperly
designed mixes will segregate during placement, resulting in inferior concrete containing
honeycombs and high permeable zones within the pile shaft. Concrete that bleeds or
disintegrates under the pressures of its own weight can also block the tremie pipe or accept
bentonite.
Controlled Setting
The concrete must retain it fluidity thorough the depth of borehole during complete
placement of the concrete in the borehole and attain an appropriate strength within a
reasonable time after placement. Retarders are used to prevent premature stiffening of some
cements or to delay stiffening under difficult placing conditions. The setting time must be
checked against the time necessary to complete the placement. The retarders should be used
under competent technical advice and after adequate testing.
100
348
>175 mm.
Below 0.6
Aggregate Type
Sand Type
Sand Content
Cement Content
Admixture
The use suitable admixture which will improve the workability and
extend the period during which such workability is maintained are to be
advocated.
101
349
Table 2. Range of Cement Content in kg/m3 and Water Cement Ratio in General use for
Concrete Mixes (After Bartholomew 1979)
Conditions
Normal
Moderately
Highly and Very
Pile Type
Aggressive
Highly
Aggressive
450-475
450-475
450-475
Precast
0.4 0.5
0.4
0.4
300-450
350-450
380-500
Bored Piles Dry Process
0.5 0.55
0.475 - 0.5
0.45 - 0.5
Bored Piles with Tremie Process
350-450
350-450
400-500
0.5 0.6
280-370
0.475 - 0.5
330-450
0.43 - 0.45
370-500
0.25 0.6
0.3 0.55
0.3 - 0.45
Concrete for bored piles compared to that for pre-cast drive piles is the least dense
concrete due to pouring and casting process. Bored pile concrete was cast in the aggressive
subsurface conditions such as, high salinity, ground water fluctuation or in the vicinity of sea
and river. In such environment, the concrete can easily be leached out by ground water. In
this case cement content and water cement ratio given in the Table 2 needs to be reviewed
considering the site conditions.
Fleming et al (1977) pointed out that the high cement content favored for in-situ pile
construction enable the necessary workability mixes to be used with adequate margins of
safety against the inevitable variations in strength and workability. It also compensates for
some reduction in strength, which may occur on interfaces during displacement.
Concrete is permeable to water to the extent that it has interconnecting void spaces
through which water can move. Calcium hydroxide liberated by hydrating cement is watersoluble and may leach out of harden concrete, leaving voids for the ingress of water.
Permeability of concrete is governed by amount of cementitious material, water content,
aggregate grading, consolidation and curing efficiency.
MEHTOD OF CONCRETE POURING
The quality of piles depends on a good pouring procedure as well as on good quality of
concrete. In wet process, the concrete is usually placed by a steel tremie pipe of 20-25cm in
diameter (minimum 6 times of coarse aggregate size).
Prior to charging the tremie pipe with concrete, the bottom of tremie needs to be sealed
by a plug of some descriptions may be inserted at the top of tremie before or after the tremie
is placed in the bored hole as appropriate. There are two potential problems that are associate
with the initial charging of tremie with concrete; the concrete can segregate during placement
and the air in tremie will prevent the complete filling of the tremie. These problems can be
avoided if the tremie is filled slowly. Faulty initial charging of tremie during concreting can
cause entrapment of mud within the concrete.
Excessive initial lifting of tremie can result in possible distribution of leached concrete
caused by concrete falling through the slurry. The bottom of tremie must stay well below the
top of the column of fresh concrete all the time. Moreover, the tremie must not be lifted and
102
350
lowered rapidly to avoid the cause of contamination of concrete with slurry. It is suggested
that the tremie pipe must not be lift and lowered rapidly to start or restart the flow of the
concrete (Reese & Neil 1988). However Xanthakos (1994) suggested that if the concrete is
not deposited easily the triemie pipes may be moved up and down with movement not
exceeding 30cm. Moreover, the tremie pipes should not be moved horizontally.
In the area of high ground water level, the concrete must be deposited above the
external water table before the casing is withdrawn. The hydrostatic pressure in the concrete
column should be greater at all time than the pressure in any column of fluid outside the
casing.
COMMON DEFECTS
The common defects of piles are cold joints, zone of segregated or contaminated
concrete, trapping of bentonite mud and cavities. The first two types of defect result from
interruptions in the concrete placement or premature extracting of the tremie pipe either
partially or completely above the concrete-slurry interface. Mud trappings are caused by
concrete of low workability and impediment to the flow of concrete due to closely spaced
bars. Discontinuities or partial separation in the piles at the bottom edge of temporary casing
can be caused by accidental lifting of low workability concrete or concrete without controlled
setting during casing extraction. If the concrete in the casing is too stiff and has considerable
frictional resistance against the casing, a column of concrete can be pulled up with the casing.
Permeability of concrete depends on the capillary porosity, water-cement ratio and
degree of hydration. High permeability of concrete can be contributed by presence of
capillary pores that are interconnecting voids in the concrete (Figs 1 & 2). The
interconnecting voids are caused by bleeding of concrete due to excessive water used in the
mix. Bleeding raises the water and air bubbles to top surface of fresh concrete and raises the
water-cement ratio of concrete upper part of the forms, thereby reducing the strength and
increasing porosity of concrete. Concrete mixed with a water-cement ratio higher than 0.6
can be more permeable. Function of concrete self-compaction can also reduce the
permeability and increase the density. In piles, usually the fresh concrete compacts under its
own weight, resulting in an increasing density with depth. Besides, concrete in a great depth
of pile is generally cured in stable temperature and moisture.
Usually one type of concrete mix is used for piling in a particular project in most cases.
However, the project in the vicinity of the river, some bored piles are to be installed closer to
103
351
the river than the remaining piles and thus the concrete mixes need to be designed
accordingly. For the piles installed in the deposition side of the river where sand deposits
occur, these piles are usually subjected to be effected by the ground water flow (Fig. 3). If
the cement content is not high enough in the concrete mix and bleeding or segregation occurs,
dampness or wet patches caused by capillary suction to ground water through the previous
tremie location and vertical steels can be found on the pile head (Figs 4 & 5). Figure 6 is a
photo of core sample obtained from the pile that exhibits the dampness on top, showing
segregated concrete caused by bleeding.
Crust Soil
Capillary Suction
Thru Previous
Tremie Location
Hydraulic pressure
and Capillary suction
Permeable
Soil
Water Flow into
High Permeable
Concrete
Soft to Stiff
Clay
Figure (7) show the some segregated concrete extracted from the tremie pipe, which
was blocked with such concrete. Settlement of solid particles or aggregates in the concrete
mix cause bleeding by migration of the water to the top surface of fresh concrete, reducing
water-cement ratio of the lower part of the mix. As a result, lower part of the concrete mix
stiffens rapidly with aggregates. In such case stiffening concrete can also block the tremie
104
352
pipe during concrete pouring (Fig. 8) causing disruption in casting process and thus effects
the quality of pile. Equipment for concrete pouring must also be adequate and reliable to
avoid any interruption due to a breakdown in continuous tremie concrete pouring operation.
Due to a congested bar arrangement, concrete cannot flow through the bars and as a
result concrete cover can be lost. Good arrangement of reinforcing bars is thus necessary.
The horizontal spacing of main bars should be at least 10cm and 15cm (minimum 4 times of
the maximum size of aggregate) for small and large diameter bars respectively.
RECOMMENDATIONS AND CONCLUSIONS
Foundation designers and concrete suppliers should pay more attention to workability
and many other important factors required for cast in-situ tremie concrete than strength alone.
It is essential to design the better quality mix than the concrete for other structural works in
some aspects, considering the process of work.
For the projects, such as elevated highways, viaducts and bridges, variable soil and
ground water conditions can be encountered along the project area. In such cases, concrete
mixes need to be designed to suit these conditions and used accordingly in bored pile
construction.
An adequate cement content and water cement ratio is necessary to have good
impermeability of concrete which is one of factors influencing the durability of concrete,
especially for bored piles in water bearing subsoil.
It is concluded that appropriate concrete mix and casting practice is essential in bored
piling work to achieve good quality piles.
REFERENCES
Bartholomew, R. F. (1979), The Protection of Concrete Piles in Aggressive Ground
Conditions: An International Appreciation, Proceedings of the Conference on Recent
Developments in the design and Construction of Piles, ICE London, 21-22 March 1979,
pp. 131-141
Fleming, W. K. and Sliwinski, Z. J. (1977), The Use and Influence of Bentonite in Bored
Pile Construction, CIRIA Report . PG. 3.
105
353
Reese, L. C. & O Neil, M. W. (1988), Drilled Shafts: Construction Procedures and Design
Methods, U.S. Department of Transportation, Federal Highway Adminstration, Virginia
incorporation with ADSC., Dallas, Texas, USA.
Xanthakos, P. P (1994), Slurry Walls as Structural systems, 2nd Edition, McGraw-Hill Inc.
106
354
Pornpot Tanseng
Organized by
CI-PREMIER CONFERENCE ORGANIZATION
ISBN: 981-04-2512-0
107
th
5 International Conference on Deep Foundation Practice incorporating Piletalk : 4 6 April 2001, Singapore
ABSTRACT
This paper presents the load transfer characteristics of fully instrumented barrette of 1.5x3.0m in size
seated about 57m below the ground level. The test results were compared with those from the
instrumented load test on bored pile of diameter 1.5m with the same length, located 30m away. No
significant difference in load transfer has been observed between barrette and pile despite the
considerable difference in construction method applied and time consumed.
Keywords : Barrette, static load test, load transfer characteristics
1. INTRODUCTION
Barrettes have been used as deep foundations for various structures in Bangkok for a number of
years. The large load carrying capacity achievable by flexible dimension and length of barrettes
provides a major advantage in prevailing subsoil condition of Bangkok. In addition to extensive bearing
capacity requirement, the demand for barrettes is necessitated mainly by site constraints, applicable
construction method and equipment. Barrettes with dimension ranging from 0.80mx2.7m to
1.5mx3.0m for safe working load capacity from 1100 to 2300 ton have been used in some major
projects. To assess the performance of large-capacity foundation element in layered subsoil of
Bangkok, instrumented load testing is compulsory. This paper presents the static load test results of
instrumented barrette tested up to 5290 ton for foundation of a fifty-storey building in Bangkok. The
test results, particularly load transfer characteristics, and shaft friction capacity were compared with
those of bored pile diameter 1.50m with the same length located 30m away.
2. OVERVIEW OF THE PROJECT
Foundation of the fifty-storey tower called for 560 bored piles of 1.2m and 1.5m diameter and 24
number of barrettes having cross section size of 1.5m x 3.0m. Bored piles and barrettes were seated
at approximate depth of 57m in the second sand layer. Barrettes were designed to support the large
load for towers lift shafts as bored piles were not feasible to utilize in such case. Base grouting was
applied for barrettes and bored piles at the locations of high column load mainly in the central tower
area. Instrumented static pile load test was proposed for one barrette and one bored pile of diameter
1.5m. The design safe working loads for the base grouted barrettes and bored piles are 2,300 ton and
1,175 ton respectively. Foundation plan of the project is shown in Figure 1.
363
109
132.10
96.20
Test-Barrette
Test
Pile
132.68
94.00
Figure 1 Layout of foundation showing location of test barrette and bored pile
3. SUBSOIL CONDITION
Soil investigation from five boreholes at different location reveals that subsoil layers along the site
are relatively consistent. Similar to other localities in Bangkok a typical subsoil profile at the site is
characterized by the alternating layers of clay and sand deposits as soil succession shown in Figure 7.
Soft, highly compressible dark gray marine clay lies beneath weathered crust layers of 2m thick and
extends up to 13.5m. Stiff Clay layer occurs directly underneath Soft Clay and its depth goes up to
26m. Below Stiff Clay layer, First Sand layer of 10m in thickness can be found. Hard Clay layer
underlies First Sand and it is found to be about 12m thick. Second Sand layer occurs at depths
between 50 to 72m. Undrained shear strength (Su) obtained from unconfined compression test and
Standard Penetration Test (SPT) are shown in Figure 7.
4. CONSTRUCTION METHODS
Both barrette and bored pile were constructed by wet process under bentonite slurry. Bentonite
slurry conforming to the widely accepted specification was used. Properties of the bentonite slurry
used are given in Table 1. Single stage base grouting was applied 24 hours after concreting for both
barrette and bored pile. The detailed procedures utilized in the construction of two different foundation
structures are outlined below.
Table 1. Comparison of bentonite slurry properties
Properties
Before feeding
to the borehole
Barrette
After Recycling &
Before Concreting
(near trench base)
1.17
Before feeding to
the borehole
1.08
Bored Pile
After Recycling & Before
concreting
(near borehole base)
1.10
Density (g/cc)
1.10
Viscosity (sec)
36
49
33
36
1.0
1.1
0.1
0.8
pH value
Mechanical rope-grab was used to excavate the trench. A guide wall cast with inside clear
dimensions slightly larger than the nominal size of the barrette was used to guide the grab during
364
110
initial bites. Since time consumed in the preparation of instrumentation was relatively long, desanding
was continuously done to keep the bentonite slurry agitated, which also helps to alleviate the growth of
filter cake by minimizing the actual exposure time. As another measure, trench was once again
occupied by grab to scrap the trench walls to remove, if any, filter cake formed on the walls. This
attempt is in line with the recommendation made by Reese and ONeill (1988) [1]. It is authors opinion
that, if due to some unforeseen reasons, reinforcement cage lowering have to be delayed for
considerable period of time, it is a good practice to use the grab again to scrap the trench walls. This
measure eliminates any foreseeable negative impacts caused by unexpected delays. After lowering
the rebar cage, tremie concreting was done.
Rotary drilling was employed for bored pile excavation. Different from barrette excavation,
temporary casing of 15 m length was used as a support in Soft Clay layer for bored pile drilling to
assure the stability of the borehole. Firstly, auger was used to drill within the temporary casing,
followed by rotary bucket with bentonite slurry down to final depth of excavation. The base of the
borehole was cleaned by recycling technique to minimize any congregated sediments. Before lowering
the reinforcement cage special cleaning bucket was used to scrap of the borehole walls and the base.
Reinforcement cages were then lowered inside the borehole while attaching the instrumentation
simultaneously at specified locations. Soon after lowering the rebar cage tremie concreting was
commenced. Polystyrene grains plug was used before the first charge of concrete to avoid the mixing
of bentonite with concrete. Time consumed in different construction activities is plotted in Figure 2.
B arrette
D rilling
D eSanding
C age Low ering
Trem ie Pipe Preparation
C oncreting
B ored P ile
10
20
30
40
50
60
70
80
Figure 2 Time consumed in different construction activities of barrette and bored pile
( after Thasnanipan, 1999 [2] )
5. LOAD TEST PROGRAM AND INSTRUMENTATION
5.1 Test Pile Layout
Test pile layout of barrette is presented in Figure 3. With overall height of 8m, reaction frame
utilized for static load testing on barrette in this project was claimed to be one of the biggest of its kind
in the region. Four barrettes were used as anchoring system. Five numbers of built-up steel girders
st
supported on each side by two 1 level cross beams were used as main beams to achieve the
maximum capacity of 6000 tons. First level beams were supported against the second level cross
beams. Second level cross beams were anchored against surrounding barrettes using anchor blocks
at the top. Specially fabricated rigid transfer girders were used to distribute the tension force coming
from the tie-bars to dowel bars above the anchor barrette heads. Sixteen numbers of hydraulic jacks
each having 500 ton capacity were placed between the test barrette cap and the main beams of the
reaction frame. General view of the barrette load test set up is presented in Figure 4.
Test pile layout of bored pile was similar to those of other static bored pile load tests in Thailand.
Steel test frame anchored against four bored piles was used in bored pile load test. Different from the
test frame of barrette, only 1 layer of cross beams was required for that of bored pile.
111365
5.00
5.00
2n d C ro ss
B eam
1st C ro ss
B eam
5.00
AN C H O R
B AR R E TTE
M ain B eam
H ydrau lic
Jacks
5.00
TE S T
B AR R E TTE
2n d C ro ss
B eam
1st C ro ss B eam
2n d C ro ss
B eam
Figure 3
Barrette test pile layout showing the configuration of 6000 ton capacity reaction frame
Figure 4 General view of the reaction frame for static load test on barrette
112
366
Test Pile
Barrette
2300 ton
5290 ton
-5 mm
-12 mm
-61 mm
Bored Pile
1175 ton
2700 ton
-6 mm
-19 mm
-67 mm
Table 3 shows the estimated ultimate load capacity of barrette and bored pile from the load vs pile
head movement using different method.
Table 3 Estimated ultimate capacity of barrette and bored pile
Test Pile
Barrette
Bored Pile
Parameter
Qult (ton)
5180 ton
5156 ton
5100 ton
18 mm
18 mm
17 mm
Qult (ton)
2675 ton
2734 ton
2620 ton
30 mm
38 mm
22 mm
1000
2000
3000
4000
5000
6000
20
Barrette
Pile
40
60
80
Figure 5 Pile head movement at the last load cycle (maximum loading) of barrette and bored pile
367
113
1 .2
1 .2
1 .0
0 .8
0 .6
0 .4
0 .2
0 .8
0 .6
0 .4
0 .2
0 .0
0
0 .0
0 .5
1 .0
1 .5
2 .0
2 .5
0 .0
1 .0
2 .0
s / D (% )
3 .0
4 .0
5 .0
s / D (% )
6b (Bored Pile)
6a (Barrette)
Figure 6 Ratio of mobilized skin friction to mobilized maximum skin friction against ratio of
pile head movement to equivalent pile diameter
10
0
Weathered
Crust
1000
2000
3000
1000
2000
3000
4000
5000
Soft
Clay
-10
-20
First Stiff
Clay
-30
Fi r st
Sand
-40
Hard
Clay
-50
Second
Sand
50
100
S P T - N ( b l ows / 3 0 c m)
1.50 m
B ored
P ile
3.00 m
1.50 m
T i p Level
-57.5 m
T i p Level
-57.5 m
-60
B arrette
60
VW SG
M echanical
Extensom eter
Figure 7 Load transfer curves of test barrette and bored pile with typical soil profile at the site
114 368
10
0
Weathered
Crust
-20
First Stiff
Clay
-30
F i r st
Sand
-40
20
30
0
0
Bored Pile
Barrette
Calculated
Soft
Clay
-10
10
10
10
20
20
Depth (m)
Depth (m)
DEPTH (m)
S u ( U C ) t / m2
30
10
20
30
Bored Pile
Barrette
Calculated
30
40
40
50
50
60
60
Hard
Clay
-50
Second
Sand
-60
50
100
SPT-N (blows/30cm)
Figure 8 Comparison of calculated and mobilized unit skin friction of barrette and bored pile
6. 4 Effect of Construction Time on Shaft Capacity Reduction
Excessive construction time is one of the main parameters claimed to be responsible for shaft friction
capacity reduction of drilled shaft foundation constructed with wet process under bentonite slurry as
reported by various researchers. Total construction time of barrette and pile were 75 hours and 27
hours respectively. Though total construction time consumed for test barrette was almost 3 times more
than that of bored pile, there is no significant difference in shaft load transfer between them. The
measures adopted in construction of barrette to minimize the excessive filter cake formation along the
sand layers by proper desanding (continuous agitation), and retrenching with grab are considered the
main reasons contributed to this achievement. Comparison of developed unit skin friction values of
barrette and pile proves that difference in utilized bentonite viscosity as shown in Table 1 does not
have significant effect on the shaft capacity. These findings are in line with conclusions made by
Thasnanipan et al (1999) [4].
6.5 Effect of Shape on Shaft Load Transfer
Hosoi et al (1994) [5] concluded, from the results of numerical analysis that earth pressure acting on
the flat surface of diaphragm wall panel is larger than that of circular bored pile. Thasnanipan et al
(1999) [2] attempted to assess the effect of different aspect ratios (L/B) on the earth pressure
developed around the trenches by using finite element program and reported that no significant
difference in earth pressure was observed between the borehole (L/B=1) and the barrette (L/B=2).
Further research is necessary to evaluate this finding. No significant difference is found between the
maximum mobilized skin friction against displacement of rectangular-shape barrette and circularshape bored pile according to Figure 6a and 6b respectively. Displacements at maximum mobilized
skin frictions of barrette and bored pile fall within the range (0.5 % - 2 % of shaft diameter) reported by
Reese (1978) [6].
369
115
7. CONCLUSIONS
(1) Elastic deformation of both barrette and bored pile at relevant design load was found to be
negligible. Shaft resistance of barrette and bored pile was not fully mobilized at relevant design
load. These observations suggested that the selected size and length of barrette and bored pile
for specified design loads are sufficient for acting as friction piles.
(2) Mobilized shaft frictions of barrette and bored pile at maximum test load particularly in the first
sand layer are considerably higher than calculated values. Shaft friction capacity improvement
was considered to be contributed by base grouting which is in line with the findings reported by
various researchers.
(3) Despite the considerable difference in construction method applied and construction time
consumed (75 and 27 hours for barrette and bored pile respectively), similar characteristics of
shaft load transfer were observed between barrette and bored pile. This achievement indicated
that adopted measures (proper desanding and scraping of trench wall by grab prior to
reinforcement lowering) to alleviate the excessive growth of bentonite filter cake on the barrette
wall proved to be effective.
(4) Static load test up to 5290 ton conducted on barrette set the record as the highest load ever
tested for a single cast-in-situ deep foundation in Thailand.
ACKNOWLEDGEMENTS
The authors wish to express their appreciation to Dr. Wanchai Teparaksa and Mr. Kamol Singtogaw
for providing invaluable suggestions in the initial stage of the load test program. The authors also wish
to thank Mr. Chanchai Submaneewong for his assistance in preparing this paper.
REFERENCES
[1] Reese L.C., & ONeill M. W., Drilled Shafts : Construction Procedures and Design Methods,
ADSC: The International Association of Foundation Drilling, Dallas, Texas, USA, 1988
[2] Thasnanipan N., Anwar M. A., Maung A.W., Tanseng P., Performance Comparison of Bored and
Excavated Piles in the Layered Soils of Bangkok, Symposium on Innovative Solutions in
Structural and Geotechnical Engineering in Honor of Professor Seng-Lip Lee, Asian Institute of
Technology & National University of Singapore, 1999, p.p. 345-353.
[3] Teparaksa W., Thasananipan N., and Anwar M. A., Base Grouting of Wet Process Bored Piles in
Bangkok Subsoils, The Eleventh Asian Regional Conference on Soil Mechanics and
Geotechnical Engineering, Seoul, Korea, 1999, p.p. 269-272.
[4] Thasnanipan N., Anwar M. A. & Maung A. W., Review of the Shaft Capacity Degradation of
Bored Piles Constructed with Bentonite Slurry, Civil and Environmental Engineering Conference,
Asian Institute of Technology, Bangkok, Thailand, 1999, p.p. V-59 to V-68.
[5] Hosoi T., Yagi N., & Enoki M., Consideration to the Skin Friction of Diaphragm Wall Foundation,
rd
3 Intl. Conf. on Deep Foundation Practice incorporating PILETALK, Singapore, 1994
[6] Reese L. C., Design and Construction of Drilled Shafts, 12th Terzaghi Lecture, Proc. ASCE, Vol.
104, No. GT1, 1978, p.p. 95-116
116
370
SPONSORED BY
The Geo-Institute of the American Society of Civil Engineers
February 14-16, 2002
Orlando, Florida
EDITED BY
Michael W. ONeill
Frank C. Townsend
117
144
Geotechnical
Parameters
0
Bangkok Soft
Clay
200
400
600
Weathered Crust
10
20
Medium to
Stiff Clay
30
Medium
Dense Sand
(First Sand)
40
Hard Clay
50
Dense to Very
Dense Sand
(Second Sand)
30
SPT-N= 20-40
t = 20kN/m 3
SPT-N= 50-100
t = 21KN/m 3
60
40
50
Line
tatic
ros
ine
Hyd
nL
dow
raw
cD
etri
zom
Pie
ual
Act
Depth (m)
10
60
Figure 1. Typical soil profile of Bangkok plain with piezometric drawdown conditions.
Subsoil Profile and Existing Pore Pressure Condition
Subsoil profile is relatively consistent at different localities in Bangkok. A typical
subsoil profile is characterized by the alternating layers of clay and sand deposits as
shown in Figure 1 and is briefly described below.
Weathered crust of 2 m thick is commonly found as the top layer. In urban areas
of Bangkok, this layer is covered by filled material. Soft to very soft, highly
compressible dark gray marine clay lies beneath weathered crust. Depending on the
location, this layer extends up to 12-18 m. About 2 m thick medium clay layer can be
observed between soft clay and underlying stiff clay. Generally stiff Clay layer occurs
directly underneath medium clay and its depth goes up to 22 m. Below stiff clay layer,
first sand layer 5-8 m in thickness can be found. This first sand layer, however, is
absent in some areas. Stiff to hard clay layer underlies first sand and it is found to be
about 5 m thick. Second sand layer generally occurs at depths between 45 to 65 m.
Existing pore water pressure conditions in upper part of Bangkok soft clay are
hydrostatic from nearly 1m below the ground level. Then the hydrostatic condition
changed to piezometric drawdown near bottom level of Bangkok soft clay as shown in
Figure 1. Excessive ground water abstraction from the deep aquifers in the past is
responsible for this significant drawdown of piezometric pressure (Nutalaya, 1981,
Thasnanipan et al., 1998).
Wet-Process Bored Pile Construction Method
In Bangkok, medium to large diameter (0.6 m to 1.8 m diameter) bored piles with depth
ranging from 24 m to over 60 m are constructed by wet process due to the prevailing
subsoil condition and limited application of dry process. Wet process method as its
120
145
name implies makes the pile under wet condition by using drilling slurry. Temporary
casing of 14-15 m in length is also used as a support in soft clay layer. Drilling is
commonly commenced by dry process with auger applying rotary drilling action in the
soft clay layer and stiff clay layer. Before reaching to the first sand layer slurry is fed to
the borehole and drilling is continued with the bucket to the final depth. A cleaning
bucket is commonly used to clean the bottom of the borehole prior to reinforcement
cage installation. Tremie concreting is necessary for the piles installed under wet
process.
Polymer-Based Drilling Slurry
The primary function of drilling slurry is to prevent the borehole instability as deepseated bored piles are required to install through water bearing and caving soils.
Bentonite slurry was mainly used in the past as it adequately fulfilled the requirement.
Polymer-based slurry has become increasingly popular as an alternative supporting fluid
in recent years. The main reason for switching to use polymer-based slurry is to
minimize the problems associated with environmental issues caused by the use of
bentonite slurry.
In the initial stage of using polymer-based slurry, the major concerns were the
potential negative impact on stability of the borehole and the shaft friction capacity as
this alternative slurry was not yet accustomed to the bored piling industry in Bangkok.
Trial boreholes conducted in the initial stage of introducing polymer-based slurry
revealed that borehole is well stablized if the right dosage is used. Dry anionic partially
hydrolyzed polyacrylamide (PHPA) polymer powder premixed with fresh water and a
small percentage of bentonite is mainly used for long bored piles in Bangkok. First, a
small dosage of bentonite powder is premixed with fresh water prior to polymer powder
introduction. The predetermined dosage of dry polymer is then added and mixed with
the betonite slurry. Premixed polymer-based slurry is stored in the steel tanks before
supplying to the bored pile drilling. The reason for adding bentonite for long bored piles
is to minimize the fluid loss which was observed from the trial boreholes drilled only
with pure polymer slurry. Depending on the thickness of sand layers present at site and
the length of pile, addition of bentonite may not be necessary. Close monitoring was
made by sonic caliper measurement (KODEN drilling monitoring equipment) to check
the stability of the borehole. The results of the sonic caliper measurement proved that
borehole can be well stabilized with the use of polymer-based slurry at total
construction time prior to concreting even over 24 hours. According to the cross-hole
sonic logging or sonic coring tests conducted on bored piles, there is no evidence that
degraded concrete remains along the pile shaft due to the use of polymer-base slurry.
Load tests were carried out to confirm the capacity of bored piles constructed
with the alternative drilling slurry. As most of the test piles constructed with polymerbased slurry gave smaller settlement values, particularly at maximum test load than
those obtained from piles constructed with bentonite slurry, confidence in using
polymer-based slurry was raised among the designers and the contractors.
Review of Shaft Friction Capacities Affected by Drilling Slurry
Shaft capacity degradation of wet-process bored piles may be attributed to three main
factors : reduction of effective stress at borehole interface, properties of slurry and
121
146
Total stress approach is used to calculate the shaft friction capacity of clay
fs
Cu
= .Cu
= adhesion factor
= undrained shear strength
122
147
Mixed Ratio
per m3 of water
Properties of Slurry
Prior to Concreting
Total Time Prior
to Concreting
Dia. x Depth Polymer Bentonite
Sand
(Hrs : Mins)
Density Viscosity*
(m)
(kg)
(kg)
pH Content**
(g/ml)
(sec/qt)
(%)
Pile
Dimension
TP-1
0.80 x 49
0.50
12
17 : 20
1.06
40
TP-2
0.80 x 50
0.50
12
12 : 20
1.03
45
0.5
TP-3
1.20 x 51
0.50
10
14 : 00
1.01
44
TP-4
1.80 x 62
0.50
10
23 : 00
1.04
51
TP-5
1.50 x 54
0.50
12
15 : 30
1.04
44
0.5
TP-6
1.00 x 51
0.22
7 : 00
1.02
36
TP-7
1.00 x 30
0.50
3 : 45
1.03
45
TP-8
0.80 x 41
0.50
10
6 : 55
1.01
44
0.1
TP-9
0.80 x 43
0.50
12
8 : 00
1.03
45
0.5
TP-10
0.60 x 26
0.50
2 : 30
1.02
43
TP-11
0.60 x 24
0.70
0 : 45
1.02
42
123
148
Prediction vs Performance of Test Piles. As none of the test piles except TP-5 was
tested to failure load, no attempt is made to determine the capacity of the piles from the
failure load criteria for further assessment. Instead the performance of test piles is
evaluated from load-settlement characteristics as described below.
As large quantities of tested-to-failure instrumented load test results of bored
piles constructed with bentonite slurry in Bangkok are available, load-settlement
behavior of this pile type can be accurately predicted using back-analyzed data. Loadsettlement behavior of all test piles constructed with polymer-based slurry presented in
this paper were predicted by taking the parameters obtained from back-analyzed data of
bentonite bored piles.
Predicted load-settlement curves are compared with those of actual test results as
shown in Figure 2 to 12. It is to be noted that the term gross settlement indicated in
the graphs represents the total pile head movement at applied load. The objective of
these comparisons is to assess from the actual load test results, whether or not use of
polymer-based slurry in bored pile construction affects the capacity of bored piles.
The summary of predicted and measured load-settlement data is presented in
Table 2. At the design load, measured pile head movement of most of the piles are
within 5 mm as can be seen in the table. It is also evident that movement measured from
the field load test is smaller than that of prediction for most of the test piles, and is more
clear at the applied load ranging from 1.5 to 3 times of pre-defined design load. This
finding pointed out that better capacity of bored pile constructed in Bangkok can be
achieved with use of polymer-based slurry. The pattern of the load-settlement curves
obtained from the filed tests suggested that majority of the applied load is resisted by
the shaft friction. Therefore, it is reasonable to conclude that overall shaft frictional
resistance of bored pile is improved with the use of polymer-based slurry.
SPT-N (Blows/ft)
1
10
Soft to
Medium
Clay
10
20
Stiff to Very
Stiff Clay
20
30
40
50
60
Medium to
Very Dense
Sand
Hard clay
Medium to
Very Dense
Sand
Very Dense
Sand
50
100
30
40
50
Depth (m.)
2000
4000
6000
8000
10000 12000
0
-5
-10
-15
-20
-25
Measurement
Prediction
-30
60
124
149
SPT-N (Blows/ft)
1
0
Soft Clay
20
30
40
50
100
2000
4000
6000
8000
10000
12000
0
10
Loose Sand
Stiff to Very
Stiff Clay
20
30
Dense to Very
Dense Sand
40
Hard Clay
Dense to
Very
Dense Sand
-10
Depth (m.)
10
50
-20
-30
-40
Measurement
Prediction
-50
50
-60
60
60
1
0
50
100
Soft Clay
10
10
Depth (m.)
Stiff Clay
20
30
Hard Clay
Dense Sand
20
30
Hard Clay
40
40
50
Dense to
Very Dense
Sand
4000
8000
12000
16000
20000
50
-10
-20
Measurement
Prediction
-30
-40
60
60
Figure 4. Load Settlement curves of TP-3 (Dia. 1.20 x 51 m) : Prediction vs. Measurement.
STP-N (Blows/ft)
0
50
100
Depth (m.)
20
30
Stiff Clay
Dense
Sand
40
Hard Clay
50
Very
Dense
Sand
60
70
10
0
Soft to
Med. Clay
5000
10000
15000
20000
25000
30000
35000
-5
-15
Measurement
Prediction
-25
-35
Hard Clay
125
150
STP-N (Blows/ft)
0
0
Depth(m.)
20
Very Soft to
Soft clay
Stiff to Very
Stiff Clay
30
40
50
60
100
10
20
30
V. Dense Sand
Hard Clay
Medium
Dense to
Very Dense
Sand
Hard clay
5000
10
50
40
-25
-50
-75
Measurement
Prediction
-100
-125
-150
50
60
50
100
Soft Clay
30
40
Depth (m.)
20
Stiff Clay
Dense Sand
V. Stiff Clay
Dense Sand
50
60
10
-5
-10
-15
-20
Measurement
Prediction
-25
-30
-35
Very Dense
Sand
70
50
100
Depth ( m.)
10
15
20
25
30
Soft Clay
Soft to
Med. Clay
Stiff Clay
Hard Clay
Very
Dense Sand
1000
2000
3000
4000
5000
6000
7000
-5
-10
-15
Measurement
Prediction
-20
-25
-30
-35
35
126
151
STP-N (Blows/ft)
0
50
100
Depth (m.)
20
30
40
2000
4000
6000
8000
10000
12000
10
Soft - Med.
Stiff Clay
Medium to
Dense Sand
Stiff Clay
Dense to
Very
Dense Sand
50
-20
-40
Measurement
Prediction
-60
-80
-100
60
20
Stiff to Very
Stiff Clay
30
Medium to
Dense Sand
40
50
100
Hard Clay
Dense to
V. Dense Sand
Depth (m.)
10
50
10
15
20
25
30
35
40
45
1000
2000
3000
4000
5000
6000
7000
0
-5
-10
Measurement
Prediction
-15
-20
50
Figure 10. Load-Settlement Curves of TP-9 (Dia. 0.80x43 m) : Prediction vs. Measurement
SPT-N (Blows/ft)
0
50
100
0
Very Soft
to Soft Clay
Depth (m.)
10
15
Stiff to Very
Stiff Clay
20
25
Dense to Very
Dense Sand
500
1000
1500
2000
2500
3000
0
-2
-4
-6
Measurement
Prediction
-8
-10
-12
30
35
Figure 11. Load-Settlement curves of TP-10 (Dia. 0.60x26 m) : Prediction vs. Measurement
127
152
SPT-N (Blow/ft)
0
50
100
Depth (m.)
10
15
20
Soft Clay
Medium Clay
Stiff Clay
25
30
35
Dense Sand
Hard Clay
500
1500
2000
2500
0
-5
-10
Measurement
Prediction
-15
-20
40
Figure 12. Load-Settlement curves of TP-11 (Dia. 0.60x24 m) : Prediction vs. Measurement
Design
Load,
DL
(kN)
Maximum
Test Load
(kN)
TP-1
0.80 x 49
3300
TP-2
0.80 x 50
TP-3
Pile ID
Measured
DL
2xDL
2.5xDL
DL
2xDL
2.5xDL
9900
5.50
12.70
17.50
3.90
9.80
14.95
3300
9900
6.50
16.52
24.20
5.20
14.74
21.05
1.20 x 51
7200
18000
6.62
17.50
29.80
4.61
14.19
19.76
TP-4
1.80 x 62
11000
33000
5.62
14.07
20.55
4.00
9.88
12.96
TP-5
1.50 x 54
12000
32000
9.31
26.29
127.10
8.60
12.79
23.03
TP-6
1.00 x 51
4500
11250
5.50
13.91
19.80
2.49
7.10
9.15
TP-7
1.00 x 30
2600
6500
3.50
10.65
20.80
1.67
3.96
5.38
TP-8
0.80 x 41
3300
9900
5.72
15.90
30.20
2.75
8.05
11.60
TP-9
0.80 x 43
3300
6600
6.20
15.10
4.52
11.20
TP-10
0.60 x 26
1000
2500
2.56
6.35
9.50
1.61
3.76
4.55
TP-11
0.60 x 24
800
2000
2.59
7.84
14.30
1.09
3.19
4.22
Instrumented Pile Load Test. Shaft frictional resistance of polymer-based bored piles
in sand layers were of major interest to the authors as it is considered that drilling slurry
has less influence on clay layers according to the previous studies on bentonite bored
piles.
Three instrumented pile load tests were available at the time of this paper
preparation. Vibrating wire strain gauges (VWSG) and mechanical extensometers (ME)
were installed at the major soil boundaries for all 3 piles. It is to be noted that the lowest
level of strain gauges and extensometer of test piles TP-1, TP-2 and TP-3 are located at
1.5, 1.0 and 1.0 m above the relevant pile tip level respectively.
128
153
Load distribution curves along the test pile shaft at various applied load are
shown in Figure 13 to 15. The values of unit skin friction developed by the maximum
test load at the different soil layers along the shaft of test piles in comparison with those
of ultimate unit skin friction calculated using the formula shown in the earlier section
are also illustrated in these figures.
Load (kN)
SPT-N (Blows/ft)
1
50
100
4000
8000
0.0
10
10.0
10
20
20.0
20
Medium Dense
to V.Dense
Sand
30
30.0
30
Hard Clay
40
40.0
40
50
50.0
50
60
60.0
60
50
100
150
Soft to
10
Depth (m.)
20
30
40
Medium Clay
Stiff to
Very Stiff
Clay
Medium to
V.Dense Sand
50
Very Dense Sand
60
Mobilized at 9900 kN
Qult (calculated)
Figure 13. Load distribution curves and unit skin friction of TP-1 (Dia. 0.80x49 m).
SPT-N (Blows/ft)
1
0
Depth (m.)
20
30
40
50
100
4000
8000
12000
Loose Sand
10
10
10
Stiff to Very
Stiff Clay
20
20
20
Dense to Very
Dense Sand
30
30
30
Hard Clay
40
40
40
50
50
50
60
60
Soft clay
10
Load (kN)
50
100
Dense to Very
50
60
Dense Sand
60
Mobilized at 9900 kN
Qult (calculated)
Figure 14. Load distribution curves and unit skin friction of TP-2 (Dia. 0.80x50 m).
129
150
154
0
Soft Clay
10
50
100
Load (kN)
SPT-N (Blows/ft)
6000
12000
18000
10
10
10
20
20
20
30
30
30
40
40
40
50
50
50
60
60
60
50
100
150
200
250
Depth (m.)
Stiff Clay
20
30
V. Stiff to
Hard clay
Dense Sand
Hard Clay
40
Dense to
Very Dense
Sand
50
60
Mobilized at 18000 kN
Qult (calculated)
Figure 15. Load distribution curves and unit skin friction of TP-3 (Dia. 1.20x51 m).
A summarized comparison between measured total shaft friction resistance at
maximum test load and that of theoretically calculated values of 3 test piles is presented
in Table 3.
Table 3. Calculated and measured shaft resistance
Pile
ID
Pile
Dimension
Dia. x Depth
(m)
Design
Load
(kN)
Maximum
Test Load
(kN)
TP-1
0.80 x 49
3300
TP-2
0.80 x 50
TP-3
1.20 x 51
Measured /
Calculated
Calculated
Measured at
Maximum Test Load
9900
6900
9710
1.41
3300
9900
6200
9670
1.56
7200
18000
10820
17060
1.58
130
155
shaft diameter, the shaft frictions of upper soil layers (soft clay and stiff to very stiff
clay) were fully mobilized and it is likely that medium dense sand (first sand) layer
almost reached to ultimate shaft friction resistance. However, it is most likely that very
dense sand (second sand) was not fully developed to the ultimate stage. The same
behavior is observed for test piles TP-2 and TP-3.
Shaft friction factors of the first and second sand layer of TP-1, TP-2 and TP-3
are back calculated from the load transfer values of relevant layers obtained from the
VWSG data. However, the back-calculated factors (named as pseudo- for purpose of
convenient reference in this paper) particularly for the second sand layer are the values
at applied maximum test loads and not at ultimate test loads. In other words, it is likely
that the back-calculated factors for the second sand layer are the values at partially
mobilized shaft friction of this layer. The back-calculation of value is mainly aimed to
get an idea on the magnitude of factors for polymer-based bored piles from the
currently available data in comparison with the design values commonly used for
bentonite bored piles constructed in Bangkok.
Figure 17 shows the values of pseudo- of polymer-based slurry piles obtained
from 3 instrumented pile load tests plotted on the graph of values derived from the
full-scale static pile load tests of bentonite bored piles in Bangkok subsoil from the
previous research works (Submaneewong, 1999). Submaneewong (1999) recommended
the design line of factors for bentonite bored piles in the first and second sand as
indicated in Figure 17. It is evident that pseudo- for the first sand layer of all 3 test
piles constructed under polymer-based slurry are significantly higher than those of
design values. The pseudo- values of the second sand layer are also slightly higher
than those of design line. It is most likely that values of second sand layers would be
higher than pseudo- values indicated in Figure 17 if the piles were tested to higher
loads or to failure, since shaft friction at this layer might not have been fully mobilized
at applied maximum test load as described in above paragraphs. These findings
suggested that polymer-based slurry bored piles produced better shaft friction resistance
in sand layers than that of bentonite bored piles. Further research is needed to determine
the values of the first and second sand layers at fully mobilized shaft friction
resistance.
200
Soft clay
Stiff to very stiff clay
Medium dense sand
Very dense sand
150
100
Very dense sand
(Second sand)
50
Soft clay
0
0
12
16
20
24
Figure 16. Unit skin friction versus pile head movement of different soil layers (TP-1).
131
156
1 .0
(Ks tan )
0 .8
Chiewcharnsilp (1988)
0 .6
Submaneewong
( 1999 )
0 .4
0 .2
0 .0
28 .0
30 .0
32 .0
34 .0
36 .0
38 .0
132
157
extended to EDE Co., Ltd. for providing the load test data. The authors also wish to
thank Miss. Siriphen Chaiyapak (former office engineer, SEAFCO Co., Ltd.) and Mr.
Artorn Kantawateera (trainee student, Khonkaen University) for their assistance in
preparing this paper.
References
Ata A. A. and ONeill M. (1998). Side-wall stability and side-shear resistance in
bored piles constructed with high-molecular-weight polymer slurry, Third
International Geotechnical Seminar on Deep Foundation on Bored and Auger Piles,
Ghent, Belgium, 19-21 October 1998, Balkema, Rotterdam, 111-117.
Bustamante M. and Gianeselli L. (1998). Performance of polymer slurries in large
diameter bored pile, Third International Geotechnical Seminar on Deep Foundation on
Bored and Auger Piles, Ghent, Belgium, 19-21 October 1998, Balkema, Rotterdam
119-127.
Harayama H. (1990). Load settlement analysis for bored piles using hyperbolic transfer
functions, Soil and Foundations, Vol. 30, No. 1, Japanese Society of Soil Mechanics
and Foundation Engineering, 55-64.
Littlechild B. and Plumbridge G. (1998). Effects of construction technique on the
behavior of plain bored piles constructed under drilling slurry, Seventh International
Conference and Exhibition on Piling and Deep Foundations, Deep Foundation Institute,
Vienna, Austria, 15-17 June 1998, 1.6.1-1.6.8.
Nutalaya, P. (1981). Subsidence Studies of the Bangkok Plain, AIT Research Report,
Asian Institute of Technology, Bangkok, Thailand.
Reese L. C., (1978). Design and Construction of Drilled Shafts, Twelfth Terzaghi
Lecture, Proc. ASCE, Vol. 104, No. GT1, 1978, 95-116.
Submaneewong C. (1999). Behavior of instrumented barrette and bored piles in
Bangkok subsoils, (in Thai), M.Eng. Thesis, Department of Civil Engineering, Faculty
of Engineering Chulalongkorn University, Bangkok, Thailand.
Thasnanipan N., Ganeshan B. and Anwar M.A. (1998). Effect of construction time
and bentonite viscosity on shaft capacity of bored piles, Third International
Geotechnical Seminar on Deep Foundation on Bored and Auger Piles, Ghent, Belgium,
19-21 October 1998, Balkema, Rotterdam, 171-177.
Thasnanipan N., Tanseng P. and Anwar M. A. (1998). Large diameter bored piles in
multi-layered soils of Bangkok, Third International Geotechnical Seminar on Deep
Foundation on Bored and Auger Piles, Ghent, Belgium, 19-21 October 1998, Balkema,
Rotterdam, 511-518.
133
SPONSORED BY
The Geo-Institute of the American Society of Civil Engineers
February 14-16, 2002
Orlando, Florida
EDITED BY
Michael W. ONeill
Frank C. Townsend
135
137
1074
Project Summary
The project is located in the prime area of Bangkok on Rama IX road. The design of
fifty-storey office complex called for the high-capacity piled foundation : 560 bored
piles of 1.2 m and 1.5 m diameter and 24 barrettes having cross section size of 1.5 m x
3.0 m. Bored piles and barrettes were seated at an approximate depth of 57 m in the
sand layer. Barrettes were designed to support the large load for towers elevator shafts
as bored piles were not feasible in this case. Base grouting was applied for barrettes and
bored piles at the locations of high column load mainly in the central tower area.
Instrumented static pile load tests were carried out for one barrette and one 1.5 m
diameter bored pile. The design safe working loads for the base grouted barrettes and
bored piles are 23,000 kN and 11,750 kN respectively. The barrette load test was
conducted on July 8, 1998 with maximum applied load of 52,900 kN.
Subsoil Profile and Ground Water Condition
Similar to other localities in Bangkok a typical subsoil profile at the site is characterized
by the alternating layers of clay and sand deposits as shown in Figure 1. Undrained
shear strength (Su) from unconfined compression tests and standard penetration tests
(SPT) are indicated with depth in Figure 1. It is to be noted that unconfined
compression tests were conducted only for soft clay layer whereas SPT tests were
carried out for all the layers below soft clay. Soil investigation from five boreholes at
different location reveals that subsoil layers along the site are relatively consistent. The
soil layers present at site are briefly described below.
S u ( U C ) kN/m2
DEPTH (m)
0
50
100
0
Weathered
Crust
S oft Clay
1
0
-10
Stiff Clay
-30
Medium to
Dense Sand
400
600
Ac
-20
200
Hy
d ro
s ta
tic
L in
ra w
ic D
dow
in
nL
5
0
e tr
Dense Sand
H ard C lay
4
0
zom
-50
ie
lP
Hard
Clay
tu a
-40
-60
0
50
100
S P T - N ( b l o w s / 3 0 cm)
Figure 1. Soil profile at site and the typical ground water condition of Bangkok
138
1075
Soft, highly compressible dark gray marine clay lies beneath a two meter thick
weathered crust and extends up to 13.5 m. A stiff clay layer occurs directly underneath
soft clay and its depth goes up to 26 m. Below the stiff clay layer, 10 m thick medium to
dense sand layer also known as the first sand layer can be found. Hard clay underlies
the first sand and it is found to be about 16 m thick. Dense to very dense sand (the
second sand layer) occurs at depths between 51 to 72 m. Within the second sand layer, a
thin layer of hard clay is found.
Figure 1 depicts the present typical piezometric profile of Bangkok. As can be
seen in the figure, existing pore water pressure conditions in upper part of Bangkok soft
clay are hydrostatic from nearly 1m below the ground level and then the hydrostatic
condition changed to piezometric drawdown below the bottom level of Bangkok soft
clay. Excessive ground water abstraction from the deep aquifers in the past is
responsible for this significant drawdown of piezometric pressure (Nutalaya, 1981,
Thasnanipan et al., 1998).
Installation Method and Process
Both the barrette and bored pile were constructed by wet process under bentonite slurry.
Bentonite slurry conformed to the locally accepted specification (AASHTO 1992) was
used. The actual properties of the bentonite slurry used are given in Table 1 along with
those specified by the project. Single stage base grouting was applied 24 hours after
concreting for both barrette and bored pile. The detailed procedures utilized in the
construction of two different foundation structures are outlined below.
Table 1. Comparison of bentonite slurry properties
Project
Properties Specified
Values
Density
(g/cc)
Marsh
Funnel
Viscosity
(sec/qt)
API Sand
Content
(%)
pH value
1.03-1.20
1.10
28-45
36
< 4.0
8-12
1.17
1.08
1.10
49
33
36
1.0
1.1
0.1
0.8
139
1076
the bentonite slurry to the final depth. Since time consumed in the preparation of
instrumentation was relatively long, circulation of the bentonite slurry was continuously
done to keep the slurry agitated, which also helped to alleviate the growth of filter cake
by minimizing the actual exposure time. Prior to lowering the reinforcement cage the
trench was once again occupied by grab to scrape the trench walls to remove, if any,
filter cake formed on the walls. This attempt is in line with the recommendation made
by Reese and ONeill (1988). It is authors opinion that, if due to some unforeseen
reasons, reinforcement cage lowering have to be delayed for considerable period of
time, it is a good practice to use the grab again to scrape the trench walls. This measure
eliminates any foreseeable negative impacts caused by unexpected delays. After
lowering the rebar cage, tremie concreting was done.
Hydraulic rotary drilling was employed for bored pile excavation. Different
from barrette excavation, temporary casing of 15 m length was used as a support in Soft
Clay layer for bored pile drilling to assure the stability of the borehole. Firstly, an auger
was used to drill within the temporary casing and to the bottom of the stiff clay layer.
Bentonite slurry was then supplied to the borehole and drilling was continued with a
bucket down to final depth of excavation. Before lowering the reinforcement cage a
special cleaning bucket was used to scrape the borehole walls and to clean the base.
Reinforcement cages were then lowered inside the borehole and concreting was carried
out by tremie method. Time consumed in different construction activities of test
barrette and bored pile is shown in Table 2. Equipment used in the excavation of
barrette and bored pile are shown in Figure 3.
Table 2. Time consumed in different construction activities of test barrette and bored pile
Activities
Barrette
19
36
10
2.5
7.5
75
Drilling
Recycling and Desanding
Reinforcement Cage Lowering
Delay
Concreting
Total Time Consumed
Bored Pile
7
4
7
4.5
4.5
27
140
1077
the maximum target volume (1500 and 750 liter for barrette and bored pile respectively)
or the maximum target grouting pressure (40 kN/m2) was achieved, whichever came
first. The grouting for test barrette and bored pile was stopped by the volume criteria
since the maximum grouting pressure achieved for both piles was only 20 kN/m2.
BARRETTE
BORED PILE
3.0 m.
DIA. 1.50 m.
1.5 m.
Po re P re ss ure (kN/m 2 )
Depth (m)
0
Weathered Crust
GUIDE WALL
-10
S t iff Clay
Medium to
Dense Sand
dro
t ic
st a
Li n
e
dow
i ne
n L
-57.0 m.
-57.0 m.
r aw
ic D
Dense Sand
Hard Clay
Dense to Very
Dense Sand
5
0
e tr
Hard Clay
z om
4
0
Hy
ie
lP
-60
tu a
-50
600
Ac
-40
400
1
0
BENTONITE SLURRY
-30
200
TEMPORARY
STEEL CASING
Soft Clay
-20
6
0
Mechanical cable-suspended
grab used for barrette excavation
141
1078
Equipment and
Drilling Process
Total
Construction
Method / Use of Construction
Time
Temporary
Casing
Shape
Properties
of
Bentonite
Barrette
Mechanical grab
with excavation
under gravity and
grab action
None
75 hours
Rectangular
Different
as
indicated
in Table 1
Bored
Pile
Hydraulic rotary
piling rig with
rotary drilling
action
15 m Steel
Casing
27 hours
Circular
Different
as
indicated
in Table 1
142
5.00
1079
5.00
2n d C ro ss
B eam
8.00
4.00
1st C ro ss
B eam
4.00
5.00
AN C H O R
B AR R E TTE
An ch o r P ile
P ile C ap
H yd rau lic
Jacks
8.00
TE S T
B AR R E TTE
5.00
M ain B eam
4.00
M ain B eam
Test P ile
C ro ss B eam
2n d C ro ss
B eam
1st C ro ss B eam
2n d C ro ss
B eam
Figure 4.
Figure 5. General view of the reaction frame for static load test on barrette and bored pile
Instrumentation and Monitoring System. Vibrating wire strain gauges (VWSGs) and
Mechanical Extensometers (ME) were fixed at five levels along the shafts at the known
interface boundaries of different soil layers. At each level, four sets of VWSGs and one
set of ME were installed for the pile whereas six sets of VWSGs and two sets of ME
were installed for the barrette.
Direct measurement from four dial gauges placed in diametrically opposite
positions having equidistance from the test pile axis was used as a main monitoring
system of test pile head movement. Precise leveling and piano wire were also utilized as
backup for pile head movement measurement. Additional two dial gauges were also
143
Conference Papers
NINTH INTERNATIONAL
CONFERENCE AND EXHIBITION
ON PILING AND DEEP
FOUNDATIONS
3 5 June 2002
NICE Acropolis
France
Sponsored by
Deep Foundations
Institute
145
147
Figure 1 Geological map of Chiang Mai and adjacent areas (modified from Intrasuta, 1983)
B H -2
BH-1
0
10
DEPTH (m.)
15
20
25
6
11
14
11
9
16
16
35
24
56
51
26
24
40
40
32
53
57
33
27
35
43
STR ATUM 10
4 9 C LAYEY S AN D
30
50
ST R AT U
62
M 10
C LA YE Y
33
SA N
40
45
STR ATUM 3
LO O SE SAN D
2 3 STR ATUM 5
1 8 M ED IU M TO
1 5 VER Y D EN SE SAN D
13
17
10
23
17
15
51
29
50
30
STR ATUM 2
M ED IU M TO
STIFF S ILTY C LAY
B H -3
15
10
18
13
11
12
56
40
87
90
50/5"
50/0.5"
37
33
33
41
47
37
69
31
50
93/11"
50/0"
9
9
4
3
5
STR ATUM 1
LOOSE CLAYEY
TO SILTY SAND
26
29
40
33
55
20
32
2 6 STR ATUM 10 C LAYEY SAN D
40
52
58
53
67
40
95/11"
STR ATUM 11
50
78
50/5"
50/0"
TE S T P ILE
SAND AND
G R AV EL M IXTUR E
B H -5
4
8
5
16
10
19
19
17
15
EL
46
UM 6
G R AV
STR AT
DENSE
3 7 M E D IU M T O
24
UM 8
E
STR AT M TO D EN S S AN D
M E D IU Y T O S IL T Y
E
Y
A
CL
STR ATUM 9
VER Y S TIFF TO H AR D
SILTY C LAY
B H -4
6
3
STR ATUM 4
SO FT TO M ED IU M STIFF
D AR K G R EY C LAY
16
20
58
42
21
58
3 5 STR ATUM 7
VER Y S TIFF SILTY CLAY
68
51
46
47
42
44
22
53
39
44
55
55
31
54
50/5"
18
13
12
16
15
8
7
27
23
15
24
64
56
18
31
49
25
49
42
40
28
55
50
36
57
41
50/5"
50/6"
50/3"
50/1"
85
50/5"
50/0"
50
Figure 2 Generalized soil profile along the project (the numbers denoted behind the borehole are SPT-N values)
148
Description
Clayey sand
(brownish grey)
Medium to very
stiff silty clay
Loose sand
Soft to medium
stiff silty clay
Medium to very
dense sand
Gravel
Very stiff clay
Medium to dense
clayey sand
Very stiff to hard
silty clay
Clayey sand
Very dense sandgravel formation
Very dense gravel
SPT
N
Unit
Weight
(KN/m3)
18.0
4 to 16
19.0
8 to 18
90-120
18.5
18.0
3 to 5
3 to 7
35-60
19.5
15 to 46
21.0
20.0
21.0
21 to 68
21 to 38
26 to 40
150-200
-
22.0
22 to 69
> 200
22.0
22.5
26 to 49
40 to 90
50 / 0
Su
2
(KN/m )
Y'
All the contract bored piles including the test pile were
constructed by rotary drilling under wet process or slurryreplacement method, using bentonite slurry as support
fluid in boring process. Depending on the presence of
loose material, temporary steel casings of length ranging
from 3 to 11 m were used to stabilize the borehole in top
soil layer. After installing the temporary casing by
hydraulic vibrator (Vibro-hammer) soil inside the casing
was drilled out by an auger. The borehole was filled with
bentonite slurry prior to advancing the drilling below the
casing. Drilling bucket was then used to excavate the
soil under the slurry. Upon reaching to 15-19 m depth,
verticality of the borehole was checked by Koden drilling
monitor (sonic caliper method). Koden test at this depth
also helped to assess the stability of borehole in gravel
layer (stratum 6). After the careful examination of the
borehole verticality monitoring results, drilling was
continued to the final depth. Additional Koden tests
were performed to ensure the verticality of the borehole
at regular interval before reaching to the final depth if
excessive inclination was found in the first test.
Depth (m) x
x'
x'
Y
Y
Top of
slurry
Y'
0.0
Clayey
sand
Stiff clay
5.0
Fine sand
10.0
Coarse sand
Gravel with
sand
Very stiff
clay with
trace of
sand
15.0
20.0
25.0
30.0
35.0
Dense sand
Sand-gravel
formation
40.0
Marsh Funnel
Viscosity
(sec/qt)
API Sand
Content
(%)
pH
Before drilling
1.05
31
After recycling
1.07
33
0.5
After cage
lowering
1.10
30
Stage
149
75
1500
75
Pile W all
Main Reinforcem ent
Sonic Tube (ID =54 m m )
Horizontal Pipe (ID. =40 m m )
with Manchette
Rubber Sleeve
(Manchette)
Pile Base
S EC T IO N O F G R O U T C IR C U IT
Horizontal Pipe (ID.=40 m m )
Sonic Tube (ID.=54 m m )
Perim eter of
Bored Pile
Rubber Sleeve
(Manchette)
75
1500
75
PILE TOE-GROUTING
Original Specification
150
20
SPT
2nd SP T
1s t SPT
nd
st
40
60
SPT
SPT-N
80
100
Borehole W all
Main Reinforcement
Sonic Tube (ID =54 m m )
Loose Material
(Sedim ents)
MECHANISM OF TOE-GROUTING
Teparaksa et al. (1999) investigated the penetration of
grout into the sand layer from the toe-grouting of bored
piles in Bangkok. Toe-grouting was performed 24 hours
after concreting with maximum pressure 40 bar for
grouting the base of large diameter deep-seated bored
piles in medium to fine sand layer. From the series of
SPT and soil sampling performed below the pile toe, the
authors concluded that grout did not permeate into the
sand layer at pile base. Upward flow of grout along the
pile / soil interface is the most likely phenomenon of toegrouting in Bangkok as stated by them.
Convex
Concrete
Surface
Loose Material
(Sedim ents)
Pile
Concrete
Convex
Concrete
Surface
Pile
Concrete
151
5000
10000
15000
20000
25000
S kin friction : f
1
4
12
16
End resistance : q
D ep th (m )
15000
Maxim um Mobilized
U nit Shaft Friction
(KPa)
30000 0
10
10
20
20
30
30
40
40
50
50
50
100
f=
Z
a f + bf Z
Zref, f
qu lt
fu lt
2
P ile s h a ft d is p la c e m e n t : Z
Applied Load
(KN)
f u lt
20
1
bf
af
150
1
be
ae
1
q u lt
2
q =
Ze
ae + beZe
Z ref, e
0
P ile tip d is p la c e m e n t : Z
152
zn
n+1
z2
3
k f1
Node No.
k f2
k fn
n+1
Depth
(m)
0-4
4-12
12-14
14-16
16-18
18-22
22-24
24-30
30-32
32-36
36-42
42-44
ke
Preliminary Analyses
Two preliminary analyses were carried out. The input
soil parameters required in the analyses were
established based on the recommendation of Hirayama
(1990) as shown in Table 3 with the following key
assumptions.
Same shaft resistance values (derived from SPT-N
values of original site investigation) for both cases
Preliminary Case 1 : No pile toe improvement so that
normal toe condition exists lower factor (100) is
used in ultimate end resistance derivation.
Preliminary Case 2 : Toe-grouting improves pile toe
so that stiffer toe condition than case 1 higher
factor (300) is used in ultimate end resistance
derivation.
Ultimate end
Resistance, qult (KPa)
gravel
qult
fult
qult
fult
qult
35
70
90
100
150
150
200
150
150
150
150
200
8.5
35
70
90
100
150
150
200
150
150
150
150
200
25.5
30
30
60
60
60
135
135
135
135
135
135
110
40
10000
5N ( 200 KPa)
20000
30000
Preliminary Case 1
Preliminary Case 2
Back Analysis
Measured
8
12
16
20
24
7
7
18
20
30
24
60
50
44
40
40
85
fult
SPT
N
Sand
Clay
Sand
Gravel
Sand
Clay
Sand
Clay
Sand
Clay
Clay
Sandgravel
Assumed
displacement
required to fully
mobilize shaft
resistance
Assumed
displacement
required to fully
mobilize end
resistance
Ultimate shaft
Resistance, fult (KPa)
Soil
Type
28
300N
Note : Normal toe condition in above table represents nongrouted or plain pile toe condition
153
CONCLUSIONS
10000
Measured displacement
at 25 ,000 KN
20000
30000
40000
20
40
60
80
100
120
140
160
Measured
REFERENCES
180
To examine the influence of end resistance on the loaddisplacement mechanism, a series of additional back
analyses were carried out using different values of end
resistance with the fixed shaft resistance values
(obtained from the load test results) as presented in
Figure 13. It is evident from Figure 13 that loaddisplacement behavior is not excessively sensitive to
variation for end resistance values in the range of 30 to
60 MPa.
For end resistance less than 15 MPa,
displacement
increases
significantly and
loaddisplacement curve turns to a plunging failure pattern,
which is more significant for the case of 10 MPa as can
be seen in the figure. In summary, it should be pointed
out that test pile would have experienced plunging type
of failure if it had seated on the normal pile toe condition
(non-grouted or plain pile). It is therefore considered
that pile end resistance was effectively improved by the
toe-grouting method employed.
154
155
ABSTRACT: As an alternative to the classic bentonite slurry, polymer-based slurry has been increasingly
used for wet-process bored piles in Bangkok. Polymer-based slurry having environmentally friendly
properties, is found to be a good solution in minimizing the problems associated with the disposal of
contaminated soils as well as the site pollution. This paper presents the practical application of polymer-based
slurry for construction of medium to large diameter deep-seated bored piles in Bangkok. Important factors in
using polymer-based slurry in Bangkok subsoil are also discussed.
KEYWORDS : Polymer-based slurry, bentonite slurry, filtercake, fluid loss, wet-process bored pile
1. Introduction
157
158
Properties of slurry
prior to concreting
0.80
49
T2
0.80
50
Pile ID
T3
1.20
51
1.80
62
1.50
54
0.50
0.50
0.50
0.50
0.50
12
12
10
10
12
14:00
23:00
15:30
T1
17:20 12:20
T4
T5
1.06
1.03
1.01
1.04
1.04
40
45
44
51
44
0.5
0.5
12
20
13
18
13
Properties of slurry
prior to concreting
1.00
51
1.00
30
T7
Pile ID
T8
0.80
41
0.60
26
0.60
24
0.50
0.50
0.50
0.50
0.50
10
7:00
3:45
6:55
2:30
0:45
1.02
1.03
1.01
1.02
1.02
36
45
44
43
42
0.1
12
12
15
11
T6
T9
X'
X'
Y
Y'
TOP OF
CASING
TOP OF
SLURRY
10
MEDIUM
CLAY 15
STIFF 20
CLAY
T10
25
DENSE 30
SAND
35
159
Common
Practice in
Bangkok
(PBS**)
Density
1.05
(g/cc)
Maximum
Viscosity 40 90*
33 - 45
50 - 120
40 to 90
(sec/qt)
(+/- 5)
pH
7 - 12
8 11.7 8 11.7
8 11
API Sand
1.0
0 to 1
0 to 1
Less than
Content Maximum
1%
*or as recommended by manufacturer and approved by
geotechnical engineer, ** Polymer-based slurry
Property
160
Bentonite Slurry
Add bentonite
powder in water
and mixed by
Electric mixer
(or)
Water jet mixer
(using
submersible
pumps in tank
and mix with
jetting action)
Main function
in borehole
stability
Unit weight
(density) and
filtercake effect
Sand
suspension in
slurry column
Ability to suspend
sand particles
Desanding
process
Use desanding
equipment
Pile base
cleaning
Cleaning bucket
or air lift or
recycling
Possible
degradation of
shaft friction
capacity if
continuous
agitation is not
applied
Particulate
nature
Potentially
hazardous to
aquatic life
Not be disposed
in drainage
system or
sewers
Effect on long
exposure time
Environmental
impact
Polymer-based slurry
First add bentonite
powder in water
and mixed similar
to normal bentonite
mixing
Adding polymer
powder in
premixed bentonite
slurry and mix with
electric mixer
Vigorous mixing of
polymer powder
must be avoided
Unit weight
(density) and
binding of soil
particle by polymer
strand
Possible forming of
very thin filter cake
due to addition of
bentonite
Sand particles tend to
full out of suspension
and settle on base of
borehole.
Desanding equipment
is not required. Use
sedimentation tank to
allow fine sand and
silt settle before
reuse.
Mainly cleaning
bucket. Occasionally
by airlift
Shaft friction
degradation has not
been encountered
(from available
literatures and
Bangkok experience)
Non-particulate
nature
Non-hazardous
Can be disposed on
site in drainage
system or sewers
Load (kN)
1
4000
8000 12000
0 .0
1 0.0
10
2 0.0
20
3 0.0
30
4 0.0
40
5 0.0
50
50
100
150
So ft to
20
M edium Clay
Stiff to
Very Stiff
Clay
Depth (m.)
10
30
40
M edium Dense
to V.Dense
Sand
Hard Clay
M edium to
50
Mobilized at 9 9 0 0 kN
60
Qult (calculated)
60
6 0.0
Lo ad (k N)
1
0
8000 12000
Lo o se Sand
10
10
Stiff to Very
Stiff Clay
20
20
Dense to V ery
Dense Sand
30
30
40
40
50
50
50
60
60
60
50
100
150
So ft clay
Depth (m.)
10
20
30
40
H ard Clay
Dense to V ery
Mobilized at 9 9 0 0 kN
Qult (calculated)
1
0
0
10
10
20
20
30
30
40
40
50
50
50
60
60
60
50
100
150
200
250
Soft Clay
10
Stiff Clay
Depth (m.)
4000
20
V. Stiff to
Hard clay
30
De nse Sand
Hard Clay
40
De nse to
D
Mobilized at 1 8 0 0 0 kN
Qult (calculated)
161
Calculated
Measured at
max. test load
Measured
Calculated
T1
0.80
49
3300
9900
Test Pile ID
T2
T3
0.80
1.20
50
51
3300
7200
9900
18000
6900
6200
10820
9710
9670
17060
1.41
1.56
1.58
Thasnanipan et. al. (2002, [5]) reported that loadsettlement behavior of eleven polymer-based bored
piles constructed in Bangkok subsoil are better than
that of prediction using bentonite bored piles
parameters.
7. Main Factors on Shaft Friction Capacity
Improvement of Polymer-based Bored Piles
Shaft friction capacity improvement of bored piles
constructed under polymer-based bored piles in
comparison with those of bentonite bored piles is
considered to be contributed by the following
factors.
No thick mudcake or filtercake is formed by
polymer-based slurry
Polymer strands tend to bind the soil particle in
the formation which generates the drag forces and
cohesion (Unlike plate-shaped bentonite, polymer
molecules are hair-shaped strands)
8. Conclusion
(1) The practical application of polymer-based
slurry in construction of wet-process bored piles
in Bangkok subsoil has been presented.
(2) The measurement of borehole profile by sonic
caliper and construction records proved that
there is no adverse effect of using polymerbased slurry in Bangkok subsoil as far as the
stability of borehole is concerned.
(3) Overall shaft resistances of bored piles
constructed with polymer-based slurry are
higher than that of theoretically calculated
values using bentonite bored pile parameters in
the order of 1.5.
(4) The developed average unit shaft frictions in
sand layers of 3 instrumented bored piles
constructed under polymer-based slurry are
found to be higher than those of ultimate values
calculated by empirical formula using bentonite
piles parameters. This finding suggested that
162
Organized by :
Department of Civil Engineering, Kasetsart University
Tokyo Institute of Technology
University of Philippines - Diliman
163
ABSTRACT
This paper presents the authors experiences in development of bored piles and
barrettes for infrastructure projects in Thailand with particular focused on construction issues.
Some literatures related to wet-processed bored piles and barrettes in Thailand published
through out the past 30 years are also summarized together with recent research works.
KEYWORDS : bored pile, barrette, deep foundations, bentonite, polymer-based slurry
INTRODUCTION
Cast-in-place deep foundations, particularly wet-processed deep-seated large diameter
bored piles and barrettes have been used for foundations of various infrastructure projects in
Thailand for over two decades. The versatility of the construction method and the high-load
capacity which in turn offered the constructibility and cost-saving are the main factors
contributed to the increasing use of deep-seated large diameter bored piles and barrettes. In
the initial stage there were a number of questions on design and construction aspects of these
foundation systems particularly in Bangkok subsoil. With the passage of time, the
construction equipment, installation techniques and testing of deep foundation elements have
been developed. Large numbers of instrumented full-scale static pile load tests were
conducted through out 1990s which provided better understanding on behavior of these deepseated foundations. Researches focused on the design parameters and methods were produced
based on these test results. The design parameters were so well established that wet-process
cast-in-place foundations became regarded as reliable foundations for not only in the property
sectors but also for practicing engineers involved in the infrastructure projects. This paper
presents the development of wet-processed bored piles and barrettes in Thailand. The
information contained in the paper are mainly from the infrastructure developments built in
Bangkok and adjacent areas.
CONSTRUCTION METHOD
Large diameter deep-seated wet-processed bored piles can be constructed by 2
methods, reverse-circulation and rotary drilling method. As construction procedure of historic
reverse-circulation method has been well documented in many literatures and it is less
frequently utilized nowadays in Thailand, only a rotary-drilling method is briefly presented in
this article as follows.
In rotary drilling method, a temporary casing of appropriate length (12 to 18m in
Bangkok depending on the thickness of soft clay) with required diameter (internal diameter
not less than that of design bored pile diameter) is first installed to ensure the stability of the
borehole in the top soft or loose soil layers. In some projects where the vibration is strictly
165
Year of
Construction
1971
1979
1982
Construction Method
Reverse circulation
Reverse circulation
Reverse circulation
Diameter
(m)
1.50
1.50
1.50
Depth
(m)
45
46
49
The first wet-processed bored pile of rotary-drilling method down to first sand layer
was constructed in Bangkok in late 1970 for high-rise building project, Royal Orchid Hotel.
Since then bored piles constructed by rotary-drilling method have been extensively used for
foundations of various heavy structures such as high-rise buildings, elevated expressways,
overpass-bridges, underground car park buildings, waste-water treatment plants and most
recently underground train stations of Bangkok first subway project. By mid 1980, bored pile
became the foundation of choice for heavy structures particularly in urban area of Bangkok.
The versatility of the construction method and the high-load capacity which in turn offered
the constructibility and cost-saving are the main factors contributed to the increasing use of
deep-seated large diameter bored piles and barrettes. Most of the early wet-process bored
piles (1980s) in Bangkok were constructed up to 50 m depth. Diameter of bored piles
166
commonly constructed in early days were ranging from 0.6 to 1.5 m. Table 2 below
summarizes the information of early major high-rise building projects in Bangkok.
Table 2 First high-rise building projects constructed by large diameter wet-processed bored
piles in Thailand (from 1979 to 1983)
Project Name
Royal Orchid Hotel
(1979)
Taiping Tower
(1980)
River City Hotel
(1982)
Asoke Tower
(1983)
Time Square
Building (1983)
Construction Method
Rotary-drilling with
auger and bucket
Rotary-drilling with
auger and bucket
Rotary-drilling with
auger and bucket
Rotary-drilling with
auger and bucket
Rotary-drilling with
auger and bucket
Diameter (m)
0.80 - 1.00
Depth (m)
33.0
0.80 - 1.50
32.0
0.80 1.00
27.5
0.80 - 1.50
50.0
0.80 - 1.50
50.0
Barrette
In some projects where bored piles were not feasible due to the site constraints,
applicable construction method and/or extensive bearing capacity requirements, the use of
barrette foundations would make a suitable alternative. Barrettes with dimension ranging from
0.80 m x 2.7 m to 1.5 m x 3.0 m for safe working load capacity from 11,000 to 23,000 kN
have been used in some major projects.
The first barrette in Bangkok was believed to be constructed in late 1970 for the
foundation of Bangkok Bank Head Office Building at Silom road with size of 0.6-0.8 x 2.5m
and toe depth of 33m in late 1970. Barrettes can be constructed with flexible layout plan for
both vertical and lateral loads. The layout pattern of barrettes can be arranged in a continuous
row or column, radial, alternating long and short axis of barrette and a combination of two or
more of such patterns. One type of equipment can be used for constructing both barrettes and
diaphragm walls in particular projects thus reduces the mobilization cost for additional
equipment. In addition to the large bearing capacity requirements, on site difficulties such as
limited head room where piling rigs cannot be utilized, under such situations like presence of
overhead high voltage power cables, existing overpasses or structures for elevated
expressways and planned subway stations, also demands the barrettes. A summary of
observation on barrettes of completed 26 projects completed with respect to selection criteria
is presented in Table 3.
Table 3 Summary of Barrette Selection
Criterion
High Load Capacity
Minimize Construction
Equipment
Limited Head Room for
Excavation
Combination with
Diaphragm Wall
Foundation as well as
portion of column
No. of Project
4
6
Remarks
Incorporated with bored piles
Alternative for bored piles
3
10
167
Static load test up to 5290 ton conducted on barrette set the record as the highest load
ever tested for a single cast-in-situ deep foundation in Thailand (Thasnanipan et. al. 2002a)
PROBLEMS OF WET-PROCESSED BORED PILES AND BARRETTES
IN EARLY DAYS
Basic but extensive problems were experienced in early stages of bored pile construction in
Thailand as summarized below.
Limited availability and capacity of equipment
Lack of skills in operation of equipment (particularly drilling rig)
Adverse effect due to a slow rate of drilling (e.g. excessive formation of filter-cake by
using bentonite slurry)
Limited knowledge and less advance technique in control of bentonite slurry
Limited experience in construction method and related negative impact
Quality of concrete for tremie concreting method
Lack of experienced engineers and foremen
Improper construction and quality control specification and guidelines for deep-seated
piles in local soil condition
Improper design for constructibility
DEVELOPMENT IN CONSTRUCTION
Over the past 3 decades, along with the development of wet-processed piling
technology world-wide, equipment, construction method, design as well as better
understanding and realization of construction impact on the performance have been
significantly improved in Thailand. Table 4 summarizes the areas of improvement in bored
pile and barrette construction and main factors contributed to these.
Research works presenting some of these developments were published both locally
and internationally. The design, construction and behavior of bored cast in-situ concrete piles
in Bangkok Subsoil was presented by Thasnanipan et. al., (1998a). The construction and
performance of barrettes in Bangkok Subsoil was also reported by Thasnanipan et. al.,
(1998b). Effect of construction time and bentonite viscosity on shaft friction of bored piles
was also pointed out by Thasnanipan et al., (1998c). Teparaksa et. al., (1999) published the
base grouting of wet process bored piles in Bangkok subsoil which demonstrated the method
of base grouting and reported the grout spreading mechanism for long bored piles and
performance of base grouted bored piles.
(a)
(b)
Fig. 1 (a) Guide wall for cruciform barrette (b) View of cruciform barrette after installation of
reinforcement
168
Construction of cruciform barrette (shown in Figure 1) for monopole type highvoltage power transmission line was described in the work of Thasnanipan et. al., 2000a.
Above-mentioned research works reflect the development history of bored pile and barrettes
in Thailand and offered useful information to the local construction industry and perhaps to
the international deep foundation engineering society.
Table 4 Summary of development in bored pile and barrette construction
Area of
development /
improvement
Speed of
construction
In the past
(Early 1980s)
At present
Minimum 3 days
required to complete
diameter 1.5m tip 50m
bored pile
Bored pile
Maximum diameter 2.0m
and common depth 2550m for bored pile.
Barrette
Limited in size and depth
Base grouting
Not available
Bored Pile
Maximum Diameter
2.0m and common
depth 25-60m
Barrette
Various sizes &
depth over 60m
Available
Application of
polymer-based
slurry (for bored
pile only)
Construction
impact on quality
and performance
Quality control in
construction
process
Quality control
test method and
interpretation
Not available
Extensively use
Improving
Well established
and systematic
Better equipment
available and better
knowledge in
interpretation
Main factor
contributed to
development
Better equipment,
operating skills as
well as improvedknowledge in
construction method,
management and
local soil condition
Better equipment,
operating skills as
well as improvedknowledge in
construction method,
management and
local soil condition
Equipment
availability and
advance technology
Material availability
and research works
Experience from past
projects and research
works
Experience from past
projects and research
works
Advance equipment,
experience from past
projects and research
works
Experience from past projects and extensive research works provided better
understanding on construction impact on quality and performance of these wet-processed
deep foundations. Marked difference between outcome quality of bored piles constructed in
1980s and 1990s can be observed by significant less defects found in the latter. It can also be
observed from load test results that bored piles constructed in late 1990 have higher capacity
than those of 1980s as shown in Table 5.
169
Table 5 Load test results of bored piles constructed in 1970 to 1980 and 1990s
Year of
construction
Project Name
Pile Dimension
(Dia. & Depth)
1971
1995
Pinklao bridge
Central Plaza
Pinklao
Taiping tower
High-rise building
at Ekamai Rd.
1980
1990
1.5m x 45m
1.2m x 45m
Design
Load
(ton)
410
700
Test
Load
(ton)
820
1400
Total settlement
at max. test load
(mm)
5
27
1.0m x 32m
1.0m x 32m
300
390
1125
975
118
23
Fig. 2 Progress of piling work for the Rama VIII main bridge
Bored piles have been extensively used for foundations of the majority of the elevated
expressways since 1991. Thousands of base-grouted bored piles were constructed for these
infrastructure projects including Second Stage Expressway (1991), Don Muang Tollway
Extension (1997), Bangna-Bang Pli-Bangprakong Expressaway (1998), and Wat Nakorn-In
project (2001). Over 700 bored piles of diameter ranging from 0.8m to 1.5m with depth from
35m to 54m were constructed (1999-2000) by polymer-based slurry for the foundation of
Rama VIII Bridge, one of the initiatives of his majesty the King Bhumibol Adulyadej.
Progress of piling works at the bank of Chao Phraya river for the main bridge of Rama VIII
Bridge is depicted in Figure 2.
The availability of more reliable and powerful equipment and tools for drilling makes
possible to construct the rock-socket bored piles. Figure 3 shows the drilling rig equipped
with rock-auger used for construction of highway bridge across Mool River in 2001, in the
north-eastern part of Thailand, where drilling was carried out through weathered-sandstone by
powerful rotary drilling rig with core barrel and rock-auger.
Fig. 3 Rock-socket bored pile construction for Mool River Project - Ubon Ratchathani Province
170
171
1.20
Bored Cast Insitu Piles
1.00
Adhesion Factor ,
Tomlinson,1957
0.80
Suchada,1989
for bored piles in Bangkok soils
0.60
0.40
Peak
Stas and Kulhawy, 1984
0.20
Residual
0.00
0.00
5.00
10.00
15.00
20.00
25.00
30.00
Fig. 4 Comparison of adhesion factor , suggested by different researchers with the actual
mobilized in the stiff clay layers (after Thansnanipan et. al 1999)
1 .0
Submaneewong (1999) : Bored Piles (Tip in 2nd Sand)
Submaneewong (1999) : Bored Piles (Tip in 2nd Hard Clay)
0 .8
Chiewcharnsilp (1988)
Polymer Bored Pile TP-1 (1st Sand)
(Ks tan )
Submaneewong
( 1999 )
0 .2
0 .0
28.0
30.0
32.0
34.0
36.0
38.0
Fig. 5 Back-calculated values of polymer bored piles at maximum test load plotted on
design line of bentonite bored piles constructed in Bangkok subsoil
(after Thansnanipan et. al 2002b)
.
DEVELOPMENT IN QUALITY CONTROL TESTING
Improvement of testing equipment and powerful computer facilities are the key factors
contributed to the development in quality control testing. Interpretation skills relevant to local
soil condition and construction method of these tests were significantly improved in local
industry. For instance, in early 1980, interpretation of the sonic integrity (seismic test) test
results were needed to send to the specialists abroad which made the testing cost more
expensive. Significant cost-saving were achieved in some major projects of late 1990, as more
practical and precise interpretation were made to verify and establish the acceptance criteria in
proving the quality of suspected piles with anomalies.
172
173
quality control testing and value-engineering. Starting from planning stage, site investigation,
design, construction and inspection should be integrated such that designers, contractors and
construction inspectors participating as a team with common goal. Appropriate and practical
specification should be established jointly by these parties for local soil condition and
construction method. Practical acceptance criteria should be developed to verify bored piles or
barrettes with suspected anomalies. Continuing education should be promoted for both
designers, inspection engineers and contractors. The Geotechnical Chapter of the Engineering
Institute of Thailand under the royal patronage of his majesty the King Bhumibol Adulyadej,
has started to establish the standard code of practice and guidelines for wet-processed bored
piles which will serve as a yardstick for the deep foundation industry upon completion in near
future.
REFERENCES
Bowles, J. E. (1968) Foundation analysis and design, McGRaw-Hill, New York
Broms B. B. (1966) Methods of calculating the ultimate bearing capacity of piles a summary, Soils-Soils, No.
18-19, pp. 21-32
Chiewcharnsilp, S. (1988) Static load transfer and predictions of carrying capacity of bored piles (in Thai), M.
Eng. Thesis, Chulalongkorn University, Bangkok, Thailand
Chiruppapa, P. (1968) Cast in-situ bored piles in Bangkok Clay, M. Eng. Thesis No. 213, Asian Institute of
Technology, Bangkok, Thailand
Meyerhof, G. G. (1976) Bearing capacity and settlement of pile foundations, Journal of soil mechanic and
foundation division, Proceeding ASCE Vol. 102, GT3, pp. 197-223
Ng, K. C. (1983) The construction problem and performance of large bored piles in second sand layer, M. Eng.
Thesis No. GT 82-26, Asian Institute of Technology, Bangkok, Thailand
Promboon, S . and Brenner, R.P. (1980), Large diameter bored piles in Bangkok clay, Proceedings of 10th
conference on soil mechanic and foundation engineering, Vol. 2, pp. 815-818
Suwanakul, V. (1969) Cast in-situ piles in Bangkok clay, M. Eng. Thesis No. 260, Asian Institute of Technology,
Bangkok, Thailand
Teparaksa W., Thasnanipan N., and Anwar M. A. (1999), Base grouting of wet process bored piles in Bangkok
subsoils, 11th Asian Regional Confer. on soil mechanics and geotech. Engg., Seoul, Korea, pp. 269-272.
Thasnanipan N., Teparaksa W., Maung A.W., Ganeshan B., (1998a) Design, construction and behavior of bored
cast in-Situ concrete piles in Bangkok Subsoil, Proceedings: Fourth International Conference on Case
Histories in Geotechnical Engineering, St. Louise, Missouri, U.S.A., p.p.281-287
Thasnanipan N., Maung A.W., Tanseng P., (1998b) Barrettes founded in Bangkok subsoils, construction and
performance, Thirteenth Southeast Asian Geotechnical Conference, Taipei, Taiwan, ROC, p.p.573-578.
Thasnanipan N., Ganeshan B., Anwar M.A., (1998c), Effect of Construction Time and Bentonite Viscosity on
Shaft Capacity of Bored Piles, Third International Geotechnical Seminar on Deep Foundation on
Bored and Auger Piles, Ghent, Belgium. p.p. 171-177.
Thasnanipan N., Maung A.W., Ganeshan B., (1998d), Sonic Integrity Test on Piles Founded in Bangkok
Subsoil-Signal Characteristics and Their Interpretations, Proceedings: Fourth International Conference
on Case Histories in Geotechnical Engineering, St. Louis, Missouri, U.S.A., p.p.1086-1092
Thasananipan N., M. A. Anwar Maung A. W (1999) Failure Mechanism of Long Bored Piles in Layered Soils
of Bangkok, Civil and Environmental Engineering Conference, Bangkok, Thailand, p.p. V-69 to V-73.
Thasnanipan N., Tanseng P., Maung A.W. & Anwar M. A. (2000a), Barrettes : A Versatile Foundation for
Transmission Line Towers, An International Conference on Geotechnical & Geological Engineering,
Melbourne, Australia, 19-24 November 2000
Thasnanipan N., Maung A. W. & Navaneethan T.., Z. Z. Aye (2000b), Non-Destructive Integrity Testing on
Piles Founded in Bangkok Subsoil, 6th International Conference on Application of Stress-Wave Theory
to Piles, September 2000, Sao Paulo, Brazil
Thasnanipan N., Zaw Zaw Aye and Wanchai Teparaksa (2002a) Barrette of Over 50,000 kN Ultimate Capacity
Constructed in the Multi-Layered Soil of Bangkok, Proceedings of the International Deep Foundations
Congress 2002, Geotechnical Special Publication No. 116, Volume Two, ASCE, Febuary 14-16 2002,
Orlando, Florida, USA, p.p. 1073-1087
Thasnanipan, N., Zaw Zaw Aye, Chanchai Submaneewong and Wanchai Teparaksa (2002b) Performance of
Wet-Process Bored Piles Constructed with Polymer-Based Slurry in Bangkok Subsoil, Proceedings of
the International Deep Foundations Congress 2002, Geotechnical Special Publication No. 116, Volume
One, ASCE, February 14-16 2002, Orlando, Florida, USA, p.p. 143-157
174
Zaw
Zaw
175
Aye
and
Thayanan
ABSTRACT: This paper focuses the behaviour of polymer-based slurry both in the practical construction of
deep-seated bored piles and in the laboratory. The behaviour of polymer slurry with different mixed-ratios is
studied in the laboratory by means of model tests. Test models were constructed with the sand samples obtained from 25 to 40m depth, First and Second Sand layers of Bangkok. The model tests showed that significant strength improvement can be achieved in slurry-sand interface if polymer slurry (polymer 0.05% by
weight) is mixed with a small percentage of bentonite (1% by weight). The model tests also proved that filtration of slurry in permeable layers can be reduced by adding a small percentage of bentonite in polymer slurry.
1 INTRODUCTION
Depth (m)
10
Medium
Dense Sand
(First Sand)
40
Hard Clay
50
Dense to Very
Dense Sand
(Second Sand)
30
SPT-N= 20-40
t = 20kN/m 3
SPT-N= 50-100
t = 21KN/m 3
40
50
e
Lin
30
Line
Medium to
Stiff Clay
tatic
20
60
600
wn
wdo
Dra
177
Bangkok Soft
Clay
400
ros
Hyd
Subsoil profile is relatively consistent at different localities in Bangkok. A typical subsoil profile is
characterized by the alternating layers of clay and
sand deposits as shown in Figure 1.
10
200
Weathered Crust
etric
zom
Pie
ual
Act
Geotechnical
Parameters
60
layer is formed in the soil-slurry interface of permeable layers. This thin membrane of polymer-based
slurry is capable of reducing the high filtration in
sand layers of Bangkok. However, overall volume of
fluid loss for polymer-based bored piles is found to
be higher than that of bentonite bored piles according to the field observation of deep-seated bored pile
construction in Bangkok. Figure 2 (a) and (b) demonstrates the generalized behaviour of bentonite and
polymer slurry in borehole respectively.
Thick filter
cake is
formed
Suspended
soil particle
in bentonite
slurry
Bentonite
slurry
Soft sediment
at base of
bored hole
(a)
Soil particle
is settling
Thin filter
cake is
formed
(b)
Sand
Particle
Polymer slurry
mix with very
little amount of
Bentonite
Dense sediment
at base of
bored hole
Polymer Chain
Structure
(b)
Figure 2. Generalized behaviour of slurries in borehole (a) bentonite slurry (b) polymer-based slurry
5 BEHAVIOUR OF SLURRIES IN
LABORATORY
Laboratory study was conducted to investigate the
followings properties of Bangkok sand layers in different types of slurries (Boonyarak, 2002).
Filtration through the sand layers
Shear strength of slurry-sand interface (by pocket
penetrometer)
Friction test for slurry-sand interface
5.1 Sand specimen preparation
The procedure involved in preparation of sand
specimen is outlined below.
178
Slurry
Type
Mixed ratios of
slurry (percentage to
water by weight)
Polymer Bentonite
(%)
(%)
1
2
3
4
5
6
7
8
9
10
0.05
0.05
0.05
0.08
0.08
0.08
0.10
0.10
0.10
0.15
1
1.5
2
0
1
2
0
1
2
0
Marsh
Slurry
Density Funnel
(g/cm3) Viscosity (sec)
1.007
41.8
1.012
64.3
1.019
71.3
1.000
43.3
1.008
49.8
1.020
98.3
0.999
45.5
1.008
58.6
1.020
110
0.999
50.0
11
12
13
14
15
16
0.15
0.15
0.20
0.20
0.20
0
1
2
0
1
2
5
1.009
1.019
1.000
1.008
1.020
1.050
71.8
120.4
60.3
83.2
160.3
70
SLURRY
pH
FILTER CAKE
(SLURRY-SAND INTERFACE)
SAND
9.16
9.20
9.38
7.78
8.87
9.13
7.69
9.14
9.35
7.75
9.28
9.30
7.81
9.18
9.32
9.12
FILTRATE
179
3500
3000
Polymer 0.15%
2500
2000
1500
1000
The relationship between shear strength of interface and dosage of polymer in slurry is depicted in
Figure 6. Based on the regions in which the shear
strength values fall, the test results can be categorized in 3 groups interface of pure bentonite slurry,
pure polymer slurry and polymer-bentonite slurry.
The results indicate that interface of polymerbentonite slurry is significantly stronger than that of
pure bentonite and polymer. The pictures showing
the condition of interface produced by pure polymer
slurry and polymer-bentonite slurry can be seen in
Figure 7 (a) and (b) respectively. Stronger surface
condition of polymer-bentonite interface is evident
from these pictures.
500
0
0
10
20
30
Time (min)
40
50
60
Pocket
Penetrometer
slurry-sand
interface
Sand
Figure 5. Picture and schematic of pocket penetrometer test applied on slurry-soil interface
250
200
Polymer + Bentonite Slurry
Pure Bentonite
Slurry
150
Pure Polymer
Slurry
100
50
Bentonite 0%
Bentonite 1%
Bentonite 1.5%
Bentonite 2%
Bentonite 5%
0
0
0.05
0.1
0.15
0.2
0.25
180
100
2nd sand-mortar
polymer 0.1%+bentonit 1.5%
80
bentonite 5%
60
40
20
0
0
50
100
150
200
N o rm a l
L oad
s lu rr y -s a n d
in te r fa c e
S and
F ric tio n
L oad
C e m e n t-m o rta r
(a)
(b)
Figure 9. (a) Schematic demonstration of friction test (b) photograph of friction test
The relationship between normal stress and maximum friction stress of different samples are plotted
and presented in Figure 10. Following points can be
drawn from this Figure.
Frictional resistance of slurry-soil interface of
both pure bentonite (5% bentonite) and polymerbentonite (polymer 0.1% + bentonite 1.5%) were
less than that of sand-mortar suggested that frictional resistance was reduced by application of
slurry.
181
quirements of a particular job at a particular location, where possible. Today, though use of polymer
slurry is widely acceptable in bored piling industry,
information on the desirable properties is still extremely limited. Table 2 shows the ranges of properties of polymer slurries specified by the International
Association of Foundation Drilling Standards and
Specification Committee (ADSC, 1999), those successfully used on several projects as reported by
ONeill and Reese (1999) from the work of Majano
et al. (1994) and the properties commonly applied
for bored piles in Bangkok subsoil.
Table 2. Properties of polymer slurries specified by ADSC and
Polymer-based slurry used in Bangkok
Property
Common
Practice in
Bangkok
(PBS**)
1.05
Maximum
40 to 90
(+/- 5)
8 11
Less than
1%
No specific method or formula is available to determine the required best composition of polymerbentonite ratios. Therefore, at each site, different
mixed-ratios should be made on trial in the initial
stage to determine the most appropriate ratio. Table
3 presents the mixed composition of polymer-based
slurry of bored piles constructed at 5 different locations in Bangkok. According to the load-settlement
curves obtained from static pile load tests, observed
settlements of all piles were less than those of predicted values using bentonite pile parameters Thasnanipan et al. (2002).
Table 3. Technical data of polymer-based slurry constructed at
different localities in Bangkok
Description
Density
(g/cc)
Viscosity
(sec/qt)
pH
7 - 12
8 11.7
8 11.7
API Sand 1.0
0 to 1
0 to 1
Content
Maximum
*or as recommended by manufacturer and approved by geotechnical engineer, ** Polymer-based slurry
Pile ID
T1
T2
T3
T4
T5
0.80 0.80 1.20 1.80 1.50
49
50
51
62
54
0.05
0.05 0.05 0.05 0.05
1.2
1.2
1.0
1.0
1.2
17:20
12:20
14:00 23:00
15:30
1.06
1.03
1.01
1.04
1.04
40
45
44
51
44
0.5
0.5
12
20
13
18
13
182
15
10
5
0
0
50
100
150
Soft Clay
10
Load (kN)
20
10
10
20
20
30
30
40
40
50
50
60
60
50
100
150
200
250
Stiff Clay
Depth (m.)
45
200
20
30
V. Stiff to
Hard clay
Dense Sand
Hard Clay
40
50
183
60
Dense to
Very Dense
Sand
Mobilized at 18000 kN
Qult (calculated)
Figure 12. Load distribution curves and unit skin friction of instrumented test bored pile diameter 1.20m, 51m deep constructed by polymer-based slurry in Bangkok
REFERENCES
Parameters Laboratory
test
Filtration
Polymer
(0.05%) +
bentonite
(1%) significantly
reduces filtrate volume than
pure polymer
Shear
Slurry prostrength of duced by
slurrypolymer
sand inter- mixed with
face
small percentage of
bentonite has
significant
higher
strength than
pure polymer
or bentonite
Field
observation
Polymer
(0.05%) +
bentonite
(1%) significantly reduces filtrate
volume
(slurry loss)
Discussion
notes
Laboratory
results agree
well with
field observation
Slurry produced by
polymer
mixed with
small percentage of
bentonite has
significant
higher shaft
friction capacity than
that of pure
bentonite
Frictional Slurry proSlurry proresistance duced by
duced by
of slurry- polymer
polymer
sand inter- mixed with
mixed with
face
small persmall percentage of
centage of
bentonite has bentonite has
higher
significant
strength
higher shaft
(slightly) than friction capure polymer pacity than
or bentonite
that of pure
bentonite
ADSC Standards and Specifications for the Foundation Drilling Industry. 1999, ADSC, Revised 1999, Incorporating
ACI 336.1R-98
Ata A. A. and ONeill M. 1998. Side-wall stability and sideshear resistance in bored piles constructed with highmolecular-weight polymer slurry, Third International Geotechnical Seminar on Deep Foundation on Bored and Auger Piles, Ghent, Belgium, 19-21 October 1998 : 111-117.
Balkema : Rotterdam,.
Boonyarak T. , Behaviour of Polymer Slurry for Wet-process
bored Piles Construction in Bangkok Subsoil, Master Thesis (in Thai), Chulalongkorn University, 2002
Majano R. E. and ONeill M. W. 1993. Effect of mineral and
polymer slurries on perimeter load transfer in drilled
shafts, A Report to ADSC, University of Houston, Dept. of
Civil Engineering, UHCE.
ONeill M. W. and Reese L. C. 1999. Drilled Shafts : Construction Procedures and Design Methods, U.S Department
of Transportation Federal Highway Administration, Publication No. FHWA-IF-99-025, ADSC Publication No.
ADSC-TL 4.
Thasnanipan, N., Aye, Z. Z., Submaneewong, C. and Teparaksa, W. 2002. Performance of Wet-Process Bored Piles
Constructed with Polymer-Based Slurry in Bangkok Subsoil, Proc. of the International Deep Foundations Congress
2002, Geotechnical Special Publication No. 116, Volume
One, American Society of Civil Engineers, February 14-16
2002 : 143-157. Orlando, Florida, USA : ASCE
Reduction of
frictional resistance is not
significant in
laboratory. In
lab, contact
time between
bentonite
slurry and
sand sample
was not long
enough to develop an excessively
thick filter
cake
8 CONCLUSION
Behaviour of polymer-based slurries in both laboratory and field have been presented. The laboratory
findings of this research work provided backup and
useful information for the actual construction of
bored piles in the field. The laboratory model tests
reveal that significant strength improvement can be
achieved in slurry-sand interface if polymer slurry
(polymer 0.05% by weight) is mixed with a small
percentage of bentonite (1% by weight). This mix
composition significantly reduced the filtrate volume
in the laboratory test in comparison with that of pure
polymer. Similar dosage of bentonite is commonly
added in preparing polymer-based slurry for construction of deep-seated bored piles in Bangkok
184
GEOSUPPORT 2004
SPONSORED BY
International Associations of Foundation Drilling (ADSC)
The Geo-Institute of the American Society of Civil Engineers
EDITED BY
John P. Turner
Paul W. Mayne
185
187
Geotechnical
Parameters
0
10
400
600
10
Medium to
Stiff Clay
30
Medium
Dense Sand
(First Sand)
40
Hard Clay
50
Dense to Very
Dense Sand
(Second Sand)
Su= 50-14020-KPa
t = 17-21kN/m 3
-
30
SPT-N= 20-40
t = 20kN/m 3
SPT-N= 50-100
t = 21KN/m 3
60
40
50
Line
tatic
ros
ine
Hyd
nL
dow
raw
cD
etri
zom
Pie
ual
Act
20
Depth (m)
200
Weathered Crust
Bangkok Soft
Clay
60
188
Pile Head
2 No. Horizontal
Steel Tubes with
perforation
Bored Pile
Wall
Rubber Sleeve
(Manchette)
Reinforcement
Cage
Perimeter of Bored
Pile (Bored Pile
Wall)
Pile Base
Horizontal
Steel Tube
Rubber
Sleeve
189
Grout Mixture Composition and Mixing Process. The typical cement grout consists
of cement and water with the ratio of 0.5-0.6 by weight. Bentonite or other reagent
can also be added but trial mix should be made to find out the characteristics of the
grout. Cement and water are added at right proportion in a high turbulence mixer and
mixed about 2 to 4 minutes. Cement mixture is then conveyed to the agitator. The
grout must be agitated continuously or at regular interval during the period between
the time of grout mixing and the time it enters the pump. Usually, first grout injection
should be started within 10 to 15 minutes after mixing the first batch to minimize the
stiffening of the cement grout during grouting operation. It is essential that grouting
team understands the required properties such as viscosity, density, setting time of
grout are met to effectively grout the toe of the pile. Grouting operation should be
completed within the initial setting time of the grout. Mixing rate, storage capacity
and grouting rate should be well planned to complete the grouting work within the
time limit.
Grouting procedure. The process involved in grouting by tube-a-manchettes method
is illustrated in Figure 3. First, the grout pipes are flushed with water to ensure that
the grouting loops are clear from any blockage. The pile toe is then cracked with
relatively high pressure water flow, 12 to 24 hours after concreting, to open the
manchettes and to make way for forth coming grout. The commencement of cement
grouting depending on the preset pressure criteria. If specified maximum pressure is
low (less than 20 bar / 2000 kN/m2), grouting is commenced immediately after the
pile toe cracking. Grouting is normally commenced 7 to 10 days after concreting if
higher maximum control pressure is specified to avoid damage to pile by high
pressure grouting. Grouting is stopped when the specified volume or pressure is
achieved. In current practice, pressures ranging from 20 to 60 bar (2000 to 6000
kN/m2) and grout volumes 500 to 1000 liters are normally applied.
IN
OUT
(1)
Flushing grout
tubes with water
WATER
INJECTION
GROUT UNDER
PRESSURE
(2)
Cracking with
water
(3)
Pressurized
grouting
(4)
Grouted pile base
190
Vertical Steel
Tubes
Pile
Wall
Reinforcement
Cage
Pile Base
191
flushed in a sequence to ensure that flow path exists between the tubes. To do this,
after initial cleaning, two pipes (inlet pipes) are connected to the pressure pump and
low pressure up to 10 bar (10 kN/2) is applied using clean water. The other two pipes
(outlet pipes) are filled with water and are left open. As the pressure from the pump
is gradually increased, water will start to flow from one or more of the other two
open pipes. Once the flow is observed from the first outlet pipe, it is closed off and
the water flushing continued until water flow is observed from the second pipe. The
process may be repeated in like sequence from each of the grout pipes until
satisfactory flow is observed from each pipe. Once the flushing of the preinstalled
grout pipes are completed, water-supply hoses are disconnected from 2 inlet grout
pipes and connected with the grout-supply hoses. Two outlet pipes are then opened
and cement grout is filled from two inlet pipes with low pressure until the grout
discharge from other 2 outlet pipes.
IN
OUT
GROUT
FILLING
GROUT UNDER
PRESSURE
PILE
TOE CORING
(1)
Pile toe coring
(2)
Flushing grout
pipes with water
(3)
Filling cement
grout in pipes
(4)
Pressurized
grouting
192
maximum pressure 40 bar (4000 kN/m2) for grouting the base of large diameter
bored piles constructed by wet-processed method under bentonite slurry seated in
sand layer. From the series of SPT and soil sampling performed below the pile toe
and immediate vicinity of the shaft, the authors concluded that grout did not
permeate into the sand layer at pile base. Upward migration of grout along the pile
shaft is most likely in tube--manchette method, as grout injection was applied under
relatively high pressure within 24 hours after concreting of the piles, plane of
weakness was formed at pile-soil interface which is most likely to be contributed by
the following conditions.
Stress relaxation from the drilling process was not yet fully restored along the
shaft as time gap between pile drilling and grouting was relatively short
Presence of bentonite filter-cake along the shaft
Drill-and-grout method. Grout spreading mechanism of drill-and-grout method are
discussed in relation to the steps involved in grouting operation (illustrated in Figure
5) as summarized below.
Step 1 : drilling 4 boreholes of diameter 48 mm up to 20 cm below pile toe
(using water-filled sonic tubes as access pipes to the bottom of the pile)
Step 2 : water flushing the sonic tubes to remove the sand inside the tubes and to
form flow-paths between the tubes
Step 3 : filling the sonic tubes with the grout
Step 4 : pressurized grouting until pressure reaches 6,000 kN/m2 and maintain
for 5 minutes
Step 1 creates 4 boreholes in the soil underneath the pile base. These
boreholes become larger as pocket of sand between them is washed out during Step 2
and created a cavity or relatively large opening beneath the pile base prior to the
commencement of Step 3. This cavity is filled by grout in Step 3 which eventually
formed a mass grout bulb underneath the pile base as illustrated in Figure 5.
Pressurized grout injection in Step 4 thus compacted the grouted mass which in turn
densified the grout-soil interface. Basically grout did not enter soil pores but
remained in a compacted homogeneous mass. Upward migration of grout along the
pile shaft is considered unlikely since toe-grouting was carried out minimum 14 days
after pile concreting so that time gap between concreting and grouting would have
allowed some positive improvement of pile shaft condition (influence of stress
relaxation and bentonite filter cake).
PERFORMANCE OF TOE-GROUTED BORED PILES
Typical Load Transfer Mechanism of Toe-Grouted Bored Piles in Bangkok
Table 1 shows the measured mobilized shaft resistance of bored piles with
different toe grouting method at specific load in comparison with design working
load and calculated ultimate values using empirical formula. The details of the
empirical formula commonly used in Bangkok subsoil has been presented by
193
Thasnanipan et. al. (2002). As can be seen in the table under design working load,
shaft friction carried the large portion of the load (over 90% of applied load). Only
the small percentage of the total load was transferred to the pile tip. Therefore, even
with the toe-grouting application, the end bearing component of bored piles is still
under-utilized and thus remaining unmobilized end bearing capacity serves only as a
reserve that forms the additional factor of safety.
Table 1. Summary of mobilized shaft resistance at specific load in comparison with
design working load and calculated ultimate value
Test
Pile
No.
TT-1
TT-2
TT-3
TD-1
TD-2
TD-3
3000
2500
TT1 (TAM)
2000
TT2 (TAM)
1500
TT3 (TAM)
1000
TD1 (DAG)
TD2 (DAG)
500
TD3 (DAG)
0
0
10
15
20
25
Figure 6. Mobilized unit end bearing of TAM and DAG grouted bored piles
194
Though it is not advisable to simply draw the conclusion on particular toegrouting method effects on performance of piles solely by mobilized unit end bearing
criteria from the available limited test results, the data provided in this research study
however could be taken as preliminary guidance to assess the effectiveness of the
different toe-grouting methods.
According to the recent full-scale instrumented static pile load tests carried
out in late 2002 and early 2003 on 13 drill-and-grout bored piles of diameter 1.50m
seated at depth over 50m (a complete set of data is not available while preparing this
paper), developed end bearing values of these piles were found to be scattered or
inconsistent despite the fact that grouting pressure of all piles were the same reached 60 bars (6,000 KN/m2). Therefore in authors opinion a careful justification
is to be made to design the deep-seated bored piles in Bangkok subsoil with high end
bearing values regardless of high pressure achievement in toe-grouting application.
Load vs. Pile Head Movement Comparison
Figure 7 shows the Load vs. Pile Head Movement of ungrouted, grouted
piles of tube--manchette and drill-and-grout methods. Table 2 summarized and
compared the load test results of the test piles of Figure 7.
Load (KN)
0
10000
20000
30000
40000
0
10
20
30
40
50
60
Figure 7. Load vs. pile head movement of ungrouted and toe-grouted piles
Following conclusions can be drawn from Figure 7 and Table 2.
Limit loads at 20mm pile head movement are improved (14% and 21% for Project
A and B respectively) by tube-a-manchette toe grouting method (TAM) in
comparison with ungrouted piles.
No significant difference of load-settlement behavior is found for ungrouted piles
in comparison with TAM grouted and DAG grouted piles at design load and 2
times of design load.
195
Diameter (m)
Length (m)
Qd (KN)
QL
(at 20mm total
settlement)
% increase in QL
Total pile
at Qd
head
1.5 Qd
movement 2 Qd
at
Project A
Project B
Project C
Pile No. A1 Pile No. A2 Pile No. B1 Pile No. B2 Pile No. C1
(TAM Grout) (Ungrout) (TAM Grout) (Ungrout) (DAG Grout)
1500
1500
1500
1500
1500
60.00
60.50
63.70
63.70
56.50
10,000
10,000
10,000
10,000
13,000
26,500
3.50
6.50
10.50
14.20
23,200
34,280
3.00
6.50
12.00
4.20
7.20
10.00
21.57
Project D
Pile No. D1
(DAG Grout)
1500
52.00
13,000
21,750
25,500
26,000*
3.75
6.00
9.70
N.A
6.10
11.90
21.50
N.A
5.80
11.00
17.50
196
197
CONCLUSION
Based on the field application and measured data of instrumented pile load tests,
following conclusions can be drawn.
(1) Under design working load for large diameter deep-seated bored piles with toe
grouting in Bangkok subsoil, the large portion of load (over 90% of applied
load) is carried by the shaft friction. Only the small percentage of the total load
is transferred to the pile tip. No significant difference of load-settlement
behavior is found for non-grouted piles against TAM grouted and DAG grouted
piles at design load and 2 times of design load. Therefore, for deep-seated bored
piles in Bangkok subsoil, even with the toe grouting application, the end bearing
component of bored piles could be still under-utilized. Thus the remaining
unmobilized end bearing capacity serves only as a reserve which forms the
additional factor of safety.
(2) The drill-and-grout method has higher risks than the tube--manchette method in
successfully constructing the toe grouted bored pile. Considerable additional
cost would incur in applying drill-and-grout method due to the requirement of
significant extra construction time to complete a qualified pile.
(3) Despite the considerable extra cost, various construction problems encountered
and risks involved in successful execution of grouting, drill-and-grout method
does not offer particular advantage over tube--manchette method as far as pile
capacity improvement is concerned.
(4) The potential risks involve in the practical execution and consequential impact in
minimizing the risk imposed by the method itself should be taken into account in
selecting the effective toe-grouting method.
REFERENCES
Morrison, I.M. (1987) Bored piled foundation
for Chao Phya river crossing at Wat
Sai, Bangkok, Proceedings of the 9th South East Asian Geotechnical Society
Conference, Bangkok, pp. 6-207 to 6-218.
Mullins A. G., Dapp S. D. and Lai P. (2000) Pressure-Grouting drilled shaft tips in
sand New Technological and Design Developments in Deep Foundations,
Proceedings of the Sessions of Geo-Denver 2000, Geotechnical Special Pub. No.
100, ASCE, August 5-8, 2000, Denver, Colorado, USA, p.p. 1-17
Teparaksa W., Thasnanipan N., and Anwar M. A. (1999). Base grouting of wet
process bored piles in Bangkok subsoils 11th ARC. on soil mechanics and
geotechnical Engineering., Seoul, Korea, pp. 269-272.
Thasnanipan, N., Zaw Zaw Aye, Chanchai Submaneewong and Wanchai Teparaksa
(2002) Performance of wet-process bored piles constructed with polymer-based
slurry in Bangkok subsoil, Proceedings of the International Deep Foundations
Congress 2002, Geotechnical Special Publication No. 116, Volume One, ASCE,
February 14-16 2002, Orlando, Florida, USA, p.p. 143-157
198
GeoTrans 2004
199
201
pushed down in combination with pre-boring process. Drilling is commenced by auger to drill
out the soil within the temporary casing and up to the top of the first water-bearing sand layer
or bottom of the casing in case of using short casing method. Drilling slurry or supporting
fluid is then supplied to the borehole and drilling is continued with a bucket down to the
design final depth of the pile. Before lowering the reinforcement cage, a special cleaning
bucket is used to clean the base of borehole. If bentonite slurry is used, recycling method by
air-lift or pump is applied as base cleaning process. Reinforcement cages are then lowered
into the borehole and concreting is carried out by tremie method.
A mechanical or hydraulic cable-suspended grab is commonly used for barrette
construction. Excavation of the trench is carried out by the cyclic-process of lifting and
lowering of the grab under gravity and tangential force of the clamshell operated by cables.
Different from bored pile construction, a guide wall of depth 1 to 1.5 m with inside clear
dimensions slightly larger than the nominal size of the barrette is used to guide the grab
during initial bites. Bentonite slurry is introduced to the trench as soon as initial excavation
commenced. The excavation is continued under the bentonite slurry to the final depth. After
recycling of slurry and lowering the rebar cage, concreting is done by tremie method.
OVERVIEW OF APPLICATION
Bored pile
The first wet-process large diameter bored pile was constructed for Pinklao Bridge in
Bangkok 30 years ago. Using reverse circulation method, diameter 1.50m bored pile was
installed up to 45m in the second sand layer. Three major bridges were constructed by bored
pile of reverse circulation method in Bangkok from early 1970 to 1980. The summarized
information of these bridges are tabulated below.
Table 1 First 3 major bridges constructed by large diameter wet-processed
bored piles in Bangkok
Project Name
Pinklao Bridge
Sathorn Bridge
New Memorial
Bridge
Year of
Construction
1971
1979
1982
Construction Method
Reverse circulation
Reverse circulation
Reverse circulation
Diameter
(m)
1.50
1.50
1.50
Depth
(m)
45
46
49
The first wet-processed bored pile of rotary-drilling method down to first sand layer
was constructed in Bangkok in late 1970 for high-rise building project, Royal Orchid Hotel.
Since then bored piles constructed by rotary-drilling method have been extensively used for
foundations of various heavy structures such as high-rise buildings, elevated expressways,
overpass-bridges, underground car park buildings, waste-water treatment plants and most
recently underground train stations of Bangkok first subway project. By mid 1980, bored pile
became the foundation of choice for heavy structures particularly in urban area of Bangkok.
The versatility of the construction method and the high-load capacity which in turn offered
the constructibility and cost-saving are the main factors contributed to the increasing use of
deep-seated large diameter bored piles and barrettes. Most of the early wet-process bored
piles (1980s) in Bangkok were constructed up to 50 m depth. Diameter of bored piles
commonly constructed in early days were ranging from 0.6 to 1.5 m. Table 2 below
summarizes the information of early major high-rise building projects in Bangkok.
202
Table 2 First high-rise building projects constructed by large diameter wet-processed bored
piles in Thailand (from 1979 to 1983)
Project Name
Royal Orchid Hotel
(1979)
Taiping Tower
(1980)
River City Hotel
(1982)
Asoke Tower
(1983)
Time Square
Building (1983)
Construction Method
Rotary-drilling with
auger and bucket
Rotary-drilling with
auger and bucket
Rotary-drilling with
auger and bucket
Rotary-drilling with
auger and bucket
Rotary-drilling with
auger and bucket
Diameter (m)
0.80 - 1.00
Depth (m)
33.0
0.80 - 1.50
32.0
0.80 1.00
27.5
0.80 - 1.50
50.0
0.80 - 1.50
50.0
Barrette
In some projects where bored piles were not feasible due to the site constraints,
applicable construction method and/or extensive bearing capacity requirements, the use of
barrette foundations would make a suitable alternative. Barrettes with dimension ranging from
0.80 m x 2.7 m to 1.5 m x 3.0 m for safe working load capacity from 11,000 to 23,000 kN
have been used in some major projects.
The first barrette in Bangkok was believed to be constructed in late 1970 for the
foundation of Bangkok Bank Head Office Building at Silom road with size of 0.6-0.8 x 2.5m
and toe depth of 33m in late 1970. Barrettes can be constructed with flexible layout plan for
both vertical and lateral loads. The layout pattern of barrettes can be arranged in a continuous
row or column, radial, alternating long and short axis of barrette and a combination of two or
more of such patterns. One type of equipment can be used for constructing both barrettes and
diaphragm walls in particular projects thus reduces the mobilization cost for additional
equipment. In addition to the large bearing capacity requirements, on site difficulties such as
limited head room where piling rigs cannot be utilized, under such situations like presence of
overhead high voltage power cables, existing overpasses or structures for elevated
expressways and planned subway stations, also demands the barrettes. A summary of
observation on barrettes of completed 26 projects completed with respect to selection criteria
is presented in Table 3.
Table 3 Summary of Barrette Selection
Criterion
No. of Project
Remarks
High Load Capacity
4
Incorporated with bored piles
Minimize Construction
6
Alternative for bored piles
Equipment
Limited Head Room for
3
Under existing structures such as bridges,
Excavation
elevated expressway and power lines
Combination with
10
As diaphragm wall legs
Diaphragm Wall
Foundation as well as
3
Provision for the future requirement
portion of column
Static load test up to 5290 ton conducted on barrette set the record as the highest load
ever tested for a single cast-in-situ deep foundation in Thailand (Thasnanipan et. al. 2002a)
203
(a)
(b)
Fig. 1 (a) Guide wall for cruciform barrette (b) View of cruciform barrette after installation of
reinforcement
Construction of cruciform barrette (shown in Figure 1) for monopole type highvoltage power transmission line was described in the work of Thasnanipan et. al., 2000a.
204
Above-mentioned research works reflect the development history of bored pile and barrettes
in Thailand and offered useful information to the local construction industry and perhaps to
the international deep foundation engineering society.
Table 4 Summary of development in bored pile and barrette construction
Area of
development /
improvement
Speed of
construction
Base grouting
Application of
polymer-based
slurry (for bored
pile only)
Construction
impact on quality
and performance
Quality control in
construction
process
Quality control
test method and
interpretation
In the past
(Early 1980s)
At present
Minimum 3 days
required to complete
diameter 1.5m tip 50m
bored pile
Bored pile
Bored Pile
Maximum diameter 2.0m Maximum Diameter
and common depth 252.0m and common
50m for bored pile.
depth 25-60m
Barrette
Barrette
Limited in size and depth
Various sizes &
depth over 60m
Not available
Available
Not available
Extensively use
Improving
Well established
and systematic
Better equipment
available and better
knowledge in
interpretation
Main factor
contributed to
development
Better equipment,
operating skills as
well as improvedknowledge in
construction method,
management and
local soil condition
Better equipment,
operating skills as
well as improvedknowledge in
construction method,
management and
local soil condition
Equipment
availability and
advance technology
Material availability
and research works
Experience from past
projects and research
works
Experience from past
projects and research
works
Advance equipment,
experience from past
projects and research
works
Experience from past projects and extensive research works provided better
understanding on construction impact on quality and performance of these wet-processed
deep foundations. Marked difference between outcome quality of bored piles constructed in
1980s and 1990s can be observed by significant less defects found in the latter. It can also be
observed from load test results that bored piles constructed in late 1990 have higher capacity
than those of 1980s as shown in Table 5.
Table 5 Load test results of bored piles constructed in 1970 to 1980 and 1990s
205
Year of
construction
Project Name
Pile Dimension
(Dia. & Depth)
1971
1995
Pinklao bridge
Central Plaza
Pinklao
Taiping tower
High-rise building
at Ekamai Rd.
1980
1990
1.5m x 45m
1.2m x 45m
Design
Load
(ton)
410
700
Test
Load
(ton)
820
1400
Total settlement
at max. test load
(mm)
5
27
1.0m x 32m
1.0m x 32m
300
390
1125
975
118
23
Fig. 2 Progress of piling work for the Rama VIII main bridge
Bored piles have been extensively used for foundations of the majority of the elevated
expressways since 1991. Thousands of base-grouted bored piles were constructed for these
infrastructure projects including Second Stage Expressway (1991), Don Muang Tollway
Extension (1997), Bangna-Bang Pli-Bangprakong Expressaway (1998), and Wat Nakorn-In
project (2001). Over 700 bored piles of diameter ranging from 0.8m to 1.5m with depth from
35m to 54m were constructed (1999-2000) by polymer-based slurry for the foundation of
Rama VIII Bridge, one of the initiatives of his majesty the King Bhumibol Adulyadej.
Progress of piling works at the bank of Chao Phraya river for the main bridge of Rama VIII
Bridge is depicted in Figure 2.
The availability of more reliable and powerful equipment and tools for drilling makes
possible to construct the rock-socket bored piles. Figure 3 shows the drilling rig equipped
with rock-auger used for construction of highway bridge across Mool River in 2001, in the
north-eastern part of Thailand, where drilling was carried out through weathered-sandstone by
powerful rotary drilling rig with core barrel and rock-auger.
Fig. 3 Rock-socket bored pile construction for Mool River Project - Ubon Ratchathani Province
DEVELOPMENT IN DESIGN CONCEPT AND PARAMETERS
206
In the initial stage of introducing bored piles in Thailand, the design concepts and
parameters were mainly based on the available literatures from the research works carried out
in other parts of the world such as Tomlinson (1957), Skempton (1959), Broms (1966),
Bowles (1968), Meyerhof (1976) etc. The work of Chiruppapa (1968) was believed to be the
first research data available for design parameters of bored pile in Bangkok soft clay. The
author conducted the research based on 6 dry-processed small diameter bored piles with load
cells installed at the pile toe in AIT campus in Phathumthani. Though the piles were simply
constructed by dry-processed with casing method, this early-stage research study provided
some important information such as load-settlement behavior, adhesion factor () and bearing
capacity factor (N) of bored pile in Bangkok soft clay.
With the passage of time, design method and parameters for local subsoil were
improved as a result of research works carried out in 1980s. Differences between the behavior
of driven piles and bored piles were well realized from these researches. (Ng, 1983) presented
the load distribution characteristics of wet-processed bored piles founded in both first and
second sand layers of Bangkok based on the instrumented (strain gauges) pile load test
results. (Chiewcharnsilp, 1988) reported the shaft friction factor values of sand layers in
Bangkok based on the instrumented load test results. In addition to the researches previously
available (Chiruppapa, 1968; Suwanakul, 1969; Promboon, 1981; Ng, 1983; Chiewcharnsilp,
1988) Suchada (1989) determined the shaft friction factor (adhesion factor, ) of Bangkok
clay layers based on 11 bored piles of diameter ranging from 0.50 to 0.80m with the
embedded length varying between 21.50m and 46m. It should be noted that the design
parameters obtained from the research works of 1980s were mainly based on the estimation of
shaft friction loads from plain static pile load test results with numbers of assumption since
instrumented pile load test results were limited.
With the peak of construction-boom, large numbers of instrumented full-scale static
load tests on bored piles were conducted throughout 1990s which provided better
understanding on behavior of these deep-seated foundations. Researches focused on the
design parameters and methods were produced based on these test results. The design
parameters were more accurate and well established that wet-process cast-in-place
foundations became regarded as reliable foundations in construction industry of Thailand.
With more confidence on soil parameters and behavior of these deep foundations, the
designers designed to carry significantly higher loads for bored piles and barrettes constructed
in late 1990 than those of 1980s. (Thasnanipan et. al., 1999) reported the failure mechanism
of long bored piles in layered soil of Bangkok. The authors cited that for the bored piles
embedded in the multi layered soils of Bangkok, estimation of ultimate shaft friction capacity
needs to consider the brittle type of failure mechanism of stiff to hard clay layers and the
values selected need to be adjusted accordingly. Peak and residual values mobilized in
the stiff clay layers analyzed by the authors were plotted as shown in Figure 4 along with the
suggested curves by different researchers. It can be seen from the figure that the residual
value of 2nd stiff clay layer (undrained shear strength values of 25 ton/m2) at the maximum
test load drops below the curve suggested by (Suchada, 1989). So the values proposed in
Figure 4 for the stiff to hard clay layers gives overestimate of the ultimate shaft friction under
theses conditions.
Introduction of polymer-based slurry for wet-process bored piles marked a major
breakthrough for both construction and design engineers. Thasnanipan et al.,(2002b), reported
that bored piles constructed with polymer-based slurry have higher capacity than those
constructed with bentonite slurry. Figure 5 shows the shaft friction factors of sand layers
for polymer-based bored piles in comparison with the design line of bentonite bored piles.
207
1.20
Bored Cast Insitu Piles
1.00
Adhesion Factor ,
Tomlinson,1957
0.80
Suchada,1989
for bored piles in Bangkok soils
0.60
0.40
Peak
Stas and Kulhawy, 1984
0.20
Residual
0.00
0.00
5.00
10.00
15.00
20.00
25.00
30.00
Fig. 4 Comparison of adhesion factor , suggested by different researchers with the actual
mobilized in the stiff clay layers (after Thansnanipan et. al 1999)
1 .0
Submaneewong (1999) : Bored Piles (Tip in 2nd Sand)
Submaneewong (1999) : Bored Piles (Tip in 2nd Hard Clay)
0 .8
Chiewcharnsilp (1988)
Polymer Bored Pile TP-1 (1st Sand)
(Ks tan )
Submaneewong
( 1999 )
0 .2
0 .0
28.0
30.0
32 .0
34.0
36 .0
38.0
Fig. 5 Back-calculated values of polymer bored piles at maximum test load plotted on
design line of bentonite bored piles constructed in Bangkok subsoil
(after Thansnanipan et. al 2002b)
.
DEVELOPMENT IN QUALITY CONTROL TESTING
Improvement of testing equipment and powerful computer facilities are the key factors
contributed to the development in quality control testing. Interpretation skills relevant to local
soil condition and construction method of these tests were significantly improved in local
industry. For instance, in early 1980, interpretation of the sonic integrity (seismic test) test
results were needed to send to the specialists abroad which made the testing cost more
expensive. Significant cost-saving were achieved in some major projects of late 1990, as more
practical and precise interpretation were made to verify and establish the acceptance criteria in
proving the quality of suspected piles with anomalies.
208
209
quality control testing and value-engineering. Starting from planning stage, site investigation,
design, construction and inspection should be integrated such that designers, contractors and
construction inspectors participating as a team with common goal. Appropriate and practical
specification should be established jointly by these parties for local soil condition and
construction method. Practical acceptance criteria should be developed to verify bored piles or
barrettes with suspected anomalies. Continuing education should be promoted for both
designers, inspection engineers and contractors. The Geotechnical Chapter of the Engineering
Institute of Thailand under the royal patronage of his majesty the King Bhumibol Adulyadej,
has started to establish the standard code of practice and guidelines for wet-processed bored
piles which will serve as a yardstick for the deep foundation industry upon completion in near
future.
REFERENCES
Bowles, J. E. (1968) Foundation analysis and design, McGRaw-Hill, New York
Broms B. B. (1966) Methods of calculating the ultimate bearing capacity of piles a summary, Soils-Soils, No.
18-19, pp. 21-32
Chiewcharnsilp, S. (1988) Static load transfer and predictions of carrying capacity of bored piles (in Thai), M.
Eng. Thesis, Chulalongkorn University, Bangkok, Thailand
Chiruppapa, P. (1968) Cast in-situ bored piles in Bangkok Clay, M. Eng. Thesis No. 213, Asian Institute of
Technology, Bangkok, Thailand
Meyerhof, G. G. (1976) Bearing capacity and settlement of pile foundations, Journal of soil mechanic and
foundation division, Proceeding ASCE Vol. 102, GT3, pp. 197-223
Ng, K. C. (1983) The construction problem and performance of large bored piles in second sand layer, M. Eng.
Thesis No. GT 82-26, Asian Institute of Technology, Bangkok, Thailand
Promboon, S . and Brenner, R.P. (1980), Large diameter bored piles in Bangkok clay, Proceedings of 10th
conference on soil mechanic and foundation engineering, Vol. 2, pp. 815-818
Suwanakul, V. (1969) Cast in-situ piles in Bangkok clay, M. Eng. Thesis No. 260, Asian Institute of Technology,
Bangkok, Thailand
Teparaksa W., Thasnanipan N., and Anwar M. A. (1999), Base grouting of wet process bored piles in Bangkok
subsoils, 11th Asian Regional Confer. on soil mechanics and geotech. Engg., Seoul, Korea, pp. 269-272.
Thasnanipan N., Teparaksa W., Maung A.W., Ganeshan B., (1998a) Design, construction and behavior of bored
cast in-Situ concrete piles in Bangkok Subsoil, Proceedings: Fourth International Conference on Case
Histories in Geotechnical Engineering, St. Louise, Missouri, U.S.A., p.p.281-287
Thasnanipan N., Maung A.W., Tanseng P., (1998b) Barrettes founded in Bangkok subsoils, construction and
performance, Thirteenth Southeast Asian Geotechnical Conference, Taipei, Taiwan, ROC, p.p.573-578.
Thasnanipan N., Ganeshan B., Anwar M.A., (1998c), Effect of Construction Time and Bentonite Viscosity on
Shaft Capacity of Bored Piles, Third International Geotechnical Seminar on Deep Foundation on
Bored and Auger Piles, Ghent, Belgium. p.p. 171-177.
Thasnanipan N., Maung A.W., Ganeshan B., (1998d), Sonic Integrity Test on Piles Founded in Bangkok
Subsoil-Signal Characteristics and Their Interpretations, Proceedings: Fourth International Conference
on Case Histories in Geotechnical Engineering, St. Louis, Missouri, U.S.A., p.p.1086-1092
Thasananipan N., M. A. Anwar Maung A. W (1999) Failure Mechanism of Long Bored Piles in Layered Soils
of Bangkok, Civil and Environmental Engineering Conference, Bangkok, Thailand, p.p. V-69 to V-73.
Thasnanipan N., Tanseng P., Maung A.W. & Anwar M. A. (2000a), Barrettes : A Versatile Foundation for
Transmission Line Towers, An International Conference on Geotechnical & Geological Engineering,
Melbourne, Australia, 19-24 November 2000
Thasnanipan N., Maung A. W. & Navaneethan T.., Z. Z. Aye (2000b), Non-Destructive Integrity Testing on
Piles Founded in Bangkok Subsoil, 6th International Conference on Application of Stress-Wave Theory
to Piles, September 2000, Sao Paulo, Brazil
Thasnanipan N., Zaw Zaw Aye and Wanchai Teparaksa (2002a) Barrette of Over 50,000 kN Ultimate Capacity
Constructed in the Multi-Layered Soil of Bangkok, Proceedings of the International Deep Foundations
Congress 2002, Geotechnical Special Publication No. 116, Volume Two, ASCE, Febuary 14-16 2002,
Orlando, Florida, USA, p.p. 1073-1087
Thasnanipan, N., Zaw Zaw Aye, Chanchai Submaneewong and Wanchai Teparaksa (2002b) Performance of
Wet-Process Bored Piles Constructed with Polymer-Based Slurry in Bangkok Subsoil, Proceedings of
the International Deep Foundations Congress 2002, Geotechnical Special Publication No. 116, Volume
One, ASCE, February 14-16 2002, Orlando, Florida, USA, p.p. 143-157
210
211
Chanchai
Abstract: This paper presents the development and achievements of deep-seated bored piles and barrettes construction in Thailand
based on the authors experiences, in the past four decades. Literature related to bored piles and barrettes in Thailand published
through out the past forty years is summarized together with recent research works. Problems and difficulties in construction of wetprocessed bored piles and barrettes in early days are reported. The areas of improvement, advancement and achievement in bored pile
and barrette construction and main factors contributed to these developments are also presented. An attempt is also made to briefly
discuss the future trend of bored pile and barrette foundations.
1 INTRODUCTION
Pore Pressure (kN/m 2)
Geotechnical
Parameters
0
Depth (m)
10
Bangkok Soft
Clay
200
400
600
10
30
Medium
Dense Sand
(First Sand)
40
Hard Clay
50
Dense to Very
Dense Sand
(Second Sand)
30
SPT-N= 20-40
t = 20kN/m 3
SPT-N= 50-100
t = 21KN/m 3
40
50
60
e
Lin
tic
sta
e
dro
Lin
Hy
wn
do
raw
ic D
etr
om
iez
20
Medium to
Stiff Clay
60
0
0
Weathered Crust
lP
tua
Ac
213
4. OVERVIEW OF APPLICATION
4.1 Bored piles
Using tripod rigs, small diameter dry-processed bored pile
construction was started in early 1970. The first wet-process
large diameter bored pile was constructed for Pinklao Bridge
in Bangkok 36 years ago. Using reverse circulation method, a
1.50m diameter bored pile was installed up to 45m in the
second sand layer. Three major bridges were constructed by
bored pile using the reverse circulation method in Bangkok
from early 1970 to 1980. The summarized information of
these bridges is tabulated in Table 1 below.
Table 1. First 3 major bridges constructed by large diameter
wet-processed bored piles in Bangkok.
Project
Name
Pinklao
Bridge
Sathorn
Bridge
New
Memorial
Bridge
Year
of
Construction
1971
1979
1982
Construction
Method
Reverse
circulation
Reverse
circulation
Reverse
circulation
Diameter
(m)
1.50
Depth
(m)
45
1.50
46
1.50
49
Barrette piles
The first wet-processed bored pile utilizing the rotarydrilling method down to first sand layer was constructed in
Bangkok in the late 1970s for high-rise building project, the
Royal Orchid Hotel located at the bank of Chao Phraya river.
Since then bored piles constructed by rotary-drilling method
have been extensively used for foundations of various heavy
structures such as high-rise buildings, elevated expressways,
overpass-bridges, underground car park buildings, waste-water
treatment plants and most recently underground train stations
of Bangkoks first subway project. By mid 1980s, bored piles
became the foundation of choice for heavy structures
particularly in the urban area of Bangkok. The versatility of
214
Construction
Method
Rotary-drilling
with auger and
bucket
Diameter (m)
0.80 - 1.00
Depth
(m)
33.0
Rotary-drilling
with auger and
bucket
Rotary-drilling
with auger and
bucket
Rotary-drilling
with auger and
bucket
Rotary-drilling
with auger and
bucket
0.80 - 1.50
32.0
0.80 1.00
27.5
0.80 - 1.50
50.0
0.80 - 1.50
50.0
In the past
(Early
1980s)
At present
Minimum 3
days
required to
complete
diameter
1.5m tip 50m
bored pile
Less than 1
day to
complete
diameter 2.0
m tip 60m
bored pile
Bored pile
Maximum
diameter
1.5m and
common
depth 2550m for
bored pile.
Barrette
Limited in
size and
depth
Bored Pile
Maximum
Diameter
2.0m and
common
depth 2560m
Barrette
Various sizes
& depth over
60m
Base
grouting
Not available
Available
Application
of polymerbased slurry
(for bored
pile only)
Construction
impact on
quality and
performance
Quality
control in
construction
process
Quality
control test
method and
interpretation
Not available
Extensive
use
Not well
understood
Improving
Not well
established
and
systematic
Fewer
methods
available and
limited
knowledge
in
interpretation
Well
established
and
systematic
Better
equipment
available and
better
knowledge
in
interpretation
No. of
Project
Remarks
Minimize
Construction
Equipment
Limited Head Room
for Excavation
Combination with
Diaphragm Wall
16
Foundation as well
as portion of
column
6. IMPROVEMENT IN CONSTRUCTION
Over the past three decades, along with the development of
wet-processed piling technology in other parts of the world,
equipment, construction technique and design methods as well
as better understanding of construction impact on the
performance of this type of foundation have significantly
improved in Thailand. Table 4 summarizes the areas of
improvement in bored pile and barrette construction and main
factors contributed to these developments. Some of these
improvements were published both locally and internationally.
The design, construction and behaviour of bored cast in-situ
concrete piles in Bangkok Subsoil were presented by
Thasnanipan et al., (1998a). The construction and performance
215
Main factor
contributed
to
development
Better
equipment,
operating
skills as well
as
improvedknowledge
in
construction
method,
management
and local
soil
condition
Better
equipment,
operating
skills as well
as
improvedknowledge
in
construction
method,
management
and local
soil
condition
Equipment
availability
and advance
technology
Material
availability
and research
Experience
from past
projects and
research
Experience
from past
projects and
research
Advance
equipment,
experience
from past
projects and
research
Project
Name
Pinklao
bridge
Central
Plaza
Pinklao
Taiping
Tower
High-rise
building at
Ekamai
Rd.
Pile size
(Dia. &
Depth)
1.5 m x
45 m
1.2 m x
45 m
1.0 m x
32 m
1.0 m x
32 m
Design
Load
(kN)
4100
Test
Load
(kN)
8200
max
(mm)
7000
14000
27
3000
11250
118
3900
9750
23
216
LOAD (kN)
10000
20000
30000
40000
50000
Settlement (mm)
5
10
15
20
25
30
Fig. 6a View of progress in rebar cage preparation for bidirectional load test
217
Due to the extensive bearing capacity requirements, Tshape barrettes (Thickness=1m, Width =3m) of 55m deep
were used in one of the recent major projects. View of the
guide wall and reinforcement installation of T-shape barrette
are shown in Fig. 10(a) and 10(b). Fig. 11 shows the T-shape
barrettes after exposing to the cut-off level.
The above-mentioned works reflect the development and
achievement history of bored piles and barrettes in Thailand
and offered useful information to the local construction
industry as well as to that of the international deep foundation
construction.
218
219
1.20
Adhesion Factor ,
Tomlinson,1957
0.80
Suchada,1989
for bored piles in Bangkok soils
0.60
0.40
Peak
Stas and Kulhawy, 1984
0.20
Residual
0.00
0.00
5.00
10.00
15.00
20.00
25.00
30.00
0.8
(Ks tan
0.6
0.4
0.2
0.0
28
30
32
34
36
38
0
0
10
5000
20
30
40
50
220
applicable if pile integrity is in question due to postconstruction activities, as access tubes are usually grouted
after completion of the test. The results from sonic logging test
conducted on model piles in Bangkok helped to extend the
knowledge of the signal characteristics and interpretation
(Thasnanipan et. al., 2000b). Thasnanipan et al., (2004b) also
demonstrated the application of cross-hole sonic logging test
in identifying over-cast length of bored piles prior to exposing
the pile heads.
REFERENCES
221
222
Thayanan Boonyarak
Hong Kong University of Science and Technology
223
225
Geotechnical
Parameters
Bangkok Soft
Clay
400
600
10
50
ine
SPT-N= 50-100
t = 21KN/m 3
e
Lin
Dense to Very
Dense Sand
(Second Sand)
40
tic L
50
wn
wdo
Hard Clay
ta
ros
40
30
SPT-N= 20-40
t = 20kN/m 3
D ra
Medium
Dense Sand
(First Sand)
H yd
30
c
etri
Medium to
Stiff Clay
m
iezo
al P
20
60
200
Weathered Crust
u
Act
Depth (m)
10
60
226
GUIDE WALL
TREMIE PIPE
REINFORCEMENT
CAGE
BENTONITE
SLURRY
EXCAVATION
INSTALLATION OF
REINFORCEMENT
CONCRETING
227
14
Combination with
Diaphragm Wall
Foundation as well as
portion of column
10
25
Remarks
Incorporated with bored
piles
Alternative for bored piles
Under existing structures
such as bridges, elevated
expressway and power lines
As diaphragm wall legs
Provision for the future
requirement
General configuration of barrettes as leg piles integrated with diaphragm wall and bored piles
of building with deep basement is shown in Figure 3.
Figure 3 Schematic of barrettes as leg piles integrated with diaphragm walls and bored piles
228
Adverse effect due to a slow rate of drilling (e.g. excessive formation of filter-cake by
using bentonite slurry)
Limited knowledge and less advanced techniques in control of bentonite slurry
Limited experience in construction method and related negative impact
Quality of concrete for tremie concreting method
Lack of experienced engineers and foremen
Improper construction and quality control specifications and guidelines for deepseated piles in local soil
Improper design for constructability
(a)
(b)
Figure 4. (a) Guide wall for cruciform barrette (b) View of cruciform barrette after
installation of reinforcement
Construction of cruciform barrette (shown in Figure 4) for monopole type highvoltage power transmission line was described in the work of Thasnanipan et. al., (2000a).
Construction of deep-seated T-shape and L-shape barrettes as leg-piles for diaphragm wall are
now more common in Bangkok.
229
Above-mentioned research works reflect the development history of bored pile and
barrettes in Thailand and offered useful information to the local construction industry and
perhaps to the international deep foundation engineering society.
Table 2 Summary of development in barrette construction
Area of
development /
improvement
Speed of
construction
In the past
(Early 1980s)
At present
Main factor
contributed to
development
Better equipment,
operating skills as
well as improvedknowledge in
construction method,
management and
local soil condition
Better equipment,
operating skills as
well as improvedknowledge in
construction method,
management and
local soil condition
Equipment
availability and
advance technology
Experience from past
projects and research
Minimum 3 days
required to complete
barrette 1.5mx3m of toe
depth 57m
Barrette
Limited in size and depth
Barrette
Various sizes &
depth over 60m
Base grouting
Not available
Available
Construction
impact on quality
and performance
Quality control in
construction
process
Quality control
test method and
interpretation
Improving
Well established
and systematic
Better equipment
available and better
knowledge in
interpretation
Advance equipment,
experience from past
projects and research
Experience from past projects and extensive research works provided better
understanding of construction impact of quality and performance of these wet-processed deep
foundations.
The availability of more powerful and efficient hydraulic grabs offers faster
construction of deep-seated barrettes in comparison with mechanical cable-hung grabs. Figure
5 shows the construction of barrettes using hydraulic grab.
230
231
1.20
Bored Cast Insitu Piles
1.00
Adhesion Factor ,
Tomlinson,1957
0.80
Suchada,1989
for bored piles in Bangkok soils
0.60
0.40
Peak
Stas and Kulhawy, 1984
0.20
Residual
0.00
0.00
5.00
10.00
15.00
20.00
25.00
30.00
Figure 6 Comparison of adhesion factor , suggested by different researchers with the actual
mobilized in the stiff clay layers (after Thansnanipan et. al 1999)
232
1.0
0.8
(Ks tan
0.6
0.4
0.2
0.0
28
30
32
34
36
38
233
234
1,000
2,000
3,000
4,000
5,000
6,000
20
40
60
Barrette 1.5x3.0 m, depth 57.5 m
80
(a)
Load (Ton)
Su (UC) t/m2
5
10
1000
2000
3000
4000
5000
Weathered
Crust
Soft
Clay
10
20
First Stiff
Clay
30
First
Sand
40
Hard
Clay
50
3.00 m
Barrette
Dense Sand
Hard Clay
Second
Sand
60
0
50
Tip Level
-57.5 m
100
60
SPT-N (blows/30cm)
VWSG
Mechanical
Extensometer
(b)
Figure 8 (a) Load vs. pile head movement and (b) load-transfer mechanism of base-grouted
barrette 1.50x3.00m founded at 57.5 m in Bangkok
235
1,000
2,000
3,000
4,000
5,000
6,000
7,000
10
20
30
40
Figure 9 Load vs. pile head movement of barrette 1.20x3.00m founded at 65 m in Bangkok
Applied Load (Tons)
1,000
2,000
3,000
4,000
5,000
6,000
10
20
30
40
Figure 10 Load vs. pile head movement of T-shape barrette (1.00x2.00x3.00m) founded at
55m in Bangkok (constructed in tested in 2008)
236
1.50m x 3.00m
1.2m x 3.0m
Test No. 3
T-shape barrette
(1.0m x 2.0m x
3.0m)
1.0m x 2.0m x 3.0
m (T)
-55.0
770
5.00
Bentonite
6
237
Less equipment require for barrette construction one set of barrette excavation
equipment can be used for construction of barrette and diaphragm wall for the project
with limited space
Removal of excavated soil from the site can be easier as barrette grab can dispose
directly into the dump trucks without needing to store on site provided that dumping
trucks are able to move in and out from the site during excavation time (important
issue in most of the congestive area where traffic restriction is stringent)
Bored pile
T-shape barrette
Figure 11 Mat foundation of a high-rise building supported by barrette and bored pile
Bored piles have been extensively used for foundations of the majority of the elevated
expressways since 1991. Thousands of base-grouted bored piles were constructed for these
infrastructure projects including Second Stage Expressway, constructed in 1991; Don Muang
Tollway Extension, constructed in 1997; Bangna-Bang Pli-Bangprakong Expressaway
constructed in 1998; and Wat Nakorn-In project, constructed in 2001. Over 700 bored piles of
diameter ranging from 0.8m to 1.5m with depth from 35m to 54m were constructed between
1999 and 2000 using polymer-based slurry for the foundation of Rama VIII Bridge, one of the
initiatives of his majesty the King Bhumibol Adulyadej.
However, in 2010, large numbers of barrettes were constructed for new MRT project
called Purple Line. Originally, the majority of foundations to support heavy elevated-
238
structures were designed for large bored piles of diameter 1m, 1.2m and 1.5m depending on
the loading requirement. After awarding the contracts to the main contractors, the value
engineering option using barrettes to replace bored piles proposed by the piling contractor
was accepted (as shown in Figure 12 and 13). Apart from the safety aspects, the key reasons
of changing from bored piles to barrettes are that (i) construction of barrettes requires less
equipment on the middle of the congestive road than bored piles (ii) pile cap (footing) for
barrette is much smaller than that of bored pile. Construction of over 1000 barrettes of
different sizes, 1x3m, 1.2x3m and 1.5x3m with toe depth ranging from 50m to 65m were
completed in the beginning of 2012.
Figure 12. Schematic of bored piles (original design) and proposed option of barrettes with
equivalent capacity size of footing for barrette (20m2 in plan area) is significantly less than
that of bored pile (60m2 in plan area)
239
Table 4. Comparison of equipment and construction aspects of barrette and bored pile for
construction on the public roads
Item
Description
Barrette
Bored Pile
High
Medium
High
Medium
Medium
High
4
5
Cost of equipment
Area requirement on road
High
Less
Medium
More
Excellent
Average
Less
More
The comparison of field test results and 3D finite element analysis on full-scale
instrumented static lateral load tests on T-shape barrette (Figure 14) and bored piles
constructed in Bangkok were presented by Submaneewong C (2009). Figure 15 presents the
Load-movement graphs of barrettes and bored piles under lateral loading. The findings
reported by the authors provide good reference for future design of similar elements subjected
to lateral loading, particularly result of stiffness ratio vs shear strain level of barrette and
bored pile as can be seen in Figure 16.
Soil Description
1
0
5
10
15
20
Very Soft to
Soft Clay
Medium Stiff Clay
Medium Dense Sand
15
20
-24.00
30
-40.00
40
Hard Clay
Hard Clay
55
60
-12.00
35
40
50
-7.00
10
25
35
45
-1.50
25
30
1
0
45
50
Pile Tip at
- 55.00m
55
2.00m
65
70
75
S-3
S-4
Hard Clay
S-5
1.00m
3.00m
80
S-1
S-2
S-6
Inclinometer Tube
Strain Guage
Figure 14. Lateral load test configuration for T-shape barrettes and instrumentation details
240
5000
Load (kN)
4000
3000
T-shape barrette (T4BP13)
2000
1000
0
0
10
20
30
40
50
60
70
80
90
100
Figure. 15. Movement at pile head under lateral load of barrettes and bored piles
700
600
500
G/Su
400
300
200
100
0
0.01
0.1
241
The availability of more powerful and efficient hydraulic grabs which will offer faster
construction of deep-seated barrettes
Less noise which will offer main advantages in congestive and sensitive
neighbourhood
Less equipment requirement which will offer advantages construction in limited space
More versatility (e.g. able to construct in the area with limited headroom)
Better in safety aspects as less equipment are required (especially for the construction
along the public roads, subway stations, elevated expressway etc.)
CONCLUDING REMARKS
In Thailand, according to the authors experience as a deep-foundation contractor,
development in both construction and design aspects of wet-process barrette foundations in
past decades were significant. With recognition of technical and economic advantages of
using these high capacity cast-in-place foundations by local practitioners, it is expected that
they will be more popular in the future construction industry of Thailand. However, in the
authors opinion, there is much work to be done with particular focus on constructability
issues, concrete technology for wet-processed bored piles and barrette, reliable but costeffective quality control testing and value-engineering.
Starting from the planning stage, site investigation, design, construction and
inspection should be integrated so that designers, contractors and construction inspectors can
participate as a team with a common goal. Appropriate and practical specifications should be
established jointly by these parties for local soil conditions and construction methods.
Practical acceptance criteria should be developed to verify bored piles and barrettes with
suspected anomalies. Continuing education should be promoted for designers, inspection
engineers, and contractors.
REFERENCES
Bowles, J. E. (1968) Foundation analysis and design, McGRaw-Hill, New York
Broms B. B. (1966) Methods of calculating the ultimate bearing capacity of piles a
summary, Soils-Soils, No. 18-19, pp. 21-32
242
Chiewcharnsilp, S. (1988) Static load transfer and predictions of carrying capacity of bored
piles (in Thai), M. Eng. Thesis, Chulalongkorn University, Bangkok, Thailand
Chiruppapa, P. (1968) Cast in-situ bored piles in Bangkok Clay, M. Eng. Thesis No. 213,
Asian Institute of Technology, Bangkok, Thailand
Meyerhof, G. G. (1976) Bearing capacity and settlement of pile foundations, Journal of soil
mechanic and foundation division, Proceeding ASCE Vol. 102, GT3, pp. 197-223
Ng, K. C. (1983) The construction problem and performance of large bored piles in second
sand layer, M. Eng. Thesis No. GT 82-26, Asian Institute of Technology, Bangkok,
Thailand
Pimpasugdi Suchada (1989) Performance of Bored, Driven and Auger Press Piles in Bangkok
Subsoils, M. Eng. Thesis No. GT 88-12, Asian Institute of Technology, Bangkok,
Thailand
Promboon, S . and Brenner, R.P. (1980), Large diameter bored piles in Bangkok clay,
Proceedings of 10th conference on soil mechanic and foundation engineering, Vol. 2,
pp. 815-818
Sakaret Naka (2004) Bidirectional pile test on bored piles in Bangkok subsoils (in Thai), M.
Eng. Thesis, Chulalongkorn University, Bangkok, Thailand
Submaneewong C. (2009) Behavior of T-shape barrette and bored pile subject to Vertical and
Lateral Loading, Ph.D Dissertation, Chulalongkorn University, Bangkok, Thailand
Suwanakul, V. (1969) Cast in-situ piles in Bangkok clay, M. Eng. Thesis No. 260, Asian
Institute of Technology, Bangkok, Thailand
Thasnanipan N., Teparaksa W., Maung A.W., Ganeshan B., (1998a) Design, construction and
behavior of bored cast in-Situ concrete piles in Bangkok Subsoil, Proceedings: Fourth
International Conference on Case Histories in Geotechnical Engineering, St. Louise,
Missouri, U.S.A., p.p.281-287.
Thasnanipan N., Maung A.W., Tanseng P., (1998b) Barrettes founded in Bangkok subsoils,
construction and performance, Thirteenth Southeast Asian Geotechnical Conference,
Taipei, Taiwan, ROC, p.p.573-578.
Thasnanipan N., Ganeshan B., Anwar M.A., (1998c), Effect of Construction Time and
Bentonite Viscosity on Shaft Capacity of Bored Piles, Third International
Geotechnical Seminar on Deep Foundation on Bored and Auger Piles, Ghent,
Belgium. p.p. 171-177.
Thasnanipan N., Maung A.W., Ganeshan B., (1998d), Sonic Integrity Test on Piles Founded
in Bangkok Subsoil-Signal Characteristics and Their Interpretations, Proceedings:
Fourth International Conference on Case Histories in Geotechnical Engineering, St.
Louis, Missouri, U.S.A., p.p.1086-1092
243
Thasananipan N., M. A. Anwar Maung A. W (1999) Failure Mechanism of Long Bored Piles
in Layered Soils of Bangkok, Civil and Environmental Engineering Conference,
Bangkok, Thailand, p.p. V-69 to V-73.
Thasnanipan N., Tanseng P., Maung A.W. & Anwar M. A. (2000a), Barrettes : A Versatile
Foundation for Transmission Line Towers, An International Conference on
Geotechnical & Geological Engineering, Melbourne, Australia, 19-24 November
2000
Thasnanipan N., Maung A. W. & Navaneethan T.., Z. Z. Aye (2000b), Non-Destructive
Integrity Testing on Piles Founded in Bangkok Subsoil, 6th International Conference
on Application of Stress-Wave Theory to Piles, September 2000, Sao Paulo, Brazil
Thasnanipan N., Zaw Zaw Aye and Wanchai Teparaksa (2002a) Barrette of Over 50,000 kN
Ultimate Capacity Constructed in the Multi-Layered Soil of Bangkok, Proceedings of
the International Deep Foundations Congress 2002, Geotechnical Special Publication
No. 116, Volume Two, ASCE, Febuary 14-16 2002, Orlando, Florida, USA, p.p. 10731087.
Thasnanipan, N., Zaw Zaw Aye, Chanchai Submaneewong and Wanchai Teparaksa (2002b)
Performance of Wet-Process Bored Piles Constructed with Polymer-Based Slurry in
Bangkok Subsoil, Proceedings of the International Deep Foundations Congress
2002, Geotechnical Special Publication No. 116, Volume One, ASCE, February 14-16
2002, Orlando, Florida, USA, p.p. 143-157.
Thasnanipan, N., Zaw Zaw Aye and Chanchai Submaneewong (2004a) Effectiveness of Toegrouting for Deep-seated Bored Piles in Bangkok Subsoil, Proceedings of sessions of
the Geosupport Conference: Innovation and Cooperation in the Geo-Industry,
Geotechnical Special Publication No. 124, ASCE, January 29-31, 2004, Orlando,
Florida, USA, p.p. 561-572.
Thasnanipan Narong, Zaw Zaw Aye, Thayanan Boonyarak and Natamon Kampananon
(2004b), Quantifying Pile Head Condition Before Basement Excavation by Cross-hole
Sonic Logging Tests, The Seventh International Conference on Application of StressWave Theory to Piles, Kuala Lumpur, Malaysia, August 9 11, 2004. p.p. 233-238.
Thasnanipan N., Manosuthisan C., Boonyarak T., Chanchad C., (2006) Experience in
Construction of Largest Diameter Deep-seated Bored Piles at the Bank of Chaopraya
River, Proceedings of the Eleventh National Convention on Civil Engineering, Phuket,
April 20 22, 2006
244
Sponsored by;
Chinese Institute of Civil and Hydraulic Engineering
Southeast Asian Geotechnical Society
245
Thirteenth Southeast Asian Geotechnical Conference, 16-20 November, 1998, Taipei, Taiwan, ROC
A. W. MAUNG
P. TANSENG
S.H. WEI
SYNOPSIS
0.8m thick cast-in-situ diaphragm wall having toe depth of 28m with two level temporary bracing was used
to construct the basements of a structure which is located near the river and surrounded by buildings, including a historical one
in Bangkok, Thailand. Due to the site condition, unbalanced lateral loading on the wall was expected and an excavation down
to -12.7m below the existing ground level was carried out with instrumentation, consisting of (8) inclinometer tubes installed
in the wall panels, settlement plates around excavation zone and tiltmeters and beam sensors on the existing structures. This
paper presents computer model analysis and performance of the wall including results of instrumentation. Behaviour and
performance of the wall is compared with those of other projects in Bangkok area.
INTRODUCTION
In Bangkok, the growing land price and need for space has
necessitated deeper and larger basement excavations, even in
some unfavorable subsoil and site conditions and in limited
spaces. Subsoil conditions in Bangkok is generally a very
soft clay of 12m to 18m thick layer underlain by stiff to hard
clay and series of sand layers. Excavation in such soft soil
requires efficient retaining structures and cast-in-situ
diaphragm walls have therefore come in use frequently.
This paper presents performance of a bracing excavation
with diaphragm wall adjacent to the river and surrounding
structures, including a historical building. This historical
building, having archeological and cultural values, not only
limited the height of the building but also influenced the
construction time. Since the location of planned building is
in a current limited height zone in which up to 4 storey
height is permitted, 3 level basement was included to
increase the usable floor area.
SITE CONDITION AND SUBSOIL
The building site is located nearby the Chao Phaya River
and surrounded by a historical building and other existing
structures supported by pile foundation (Fig. 1). Accurate
information on foundation of these existing buildings was
not available. The diaphragm wall along the river (D1) was
constructed about only 4.0m away from the existing old
river wall. The river bed near the river wall is about 2.2m-
247
0m
6m
10m
20m
40 60
80 100 0.0
Su (t/m2)
2.0
4.0
Weathered
Clay
RIVER
5
10
20
Soft to
Very Soft
Clay
RIVER WALL
Med. Clay
15
FOUNDATION
PILES
0.80 THK.
D-WALL
0.80 THK.
D-WALL
20
Stiff to
Very Stiff
Clay
25
Dense to
Very
Dense
Sand
30
Soft Clay
Medium Clay
Stiff Clay
Dense Sand
Layer
Top in
Depth
m
0.-3.0
12.7
14
25
?s
kN/m
35-78
30
22-34
14-25
16-19
19
19-21
20-23
cu
SPT
kPa
30
71
43-300
-
PILE FOUNDATIONS
14-52
>39
DIAPHRAGM WALL
A 800mm thick diaphragm wall was designed for excavation
down to 12.7m below the ground with two levels of
temporary bracing. The diaphragm wall toe was embedded
down to 28m to achieve the overall stability of the
excavation which is right on the river bank (Fig. 2).
Originally excavation stages were modeled by using a onedimensional finite element computer program (Nonlinear
Beam Column Analysis). Soil elements were modeled as
spring and wall elements were modeled as beam. Four types
of wall were designed to suit the temporary construction
stages and permanent conditions. The walls were reinforced
to withstand bending stresses up to 1000 kN.m/m in vertical
direction. The maximum movement of the wall was
expected to be 24.2mm.
INSTRUMENTATION
Due to the locality and particular conditions of the site,
more instrumentation than those used by other projects in
Bangkok were installed and monitored. Three types of
instrumentation - Eight inclinometer tubes were installed in
diaphragm wall panels to monitor displacement of wall, ten
settlement plates of 1.0m and 5.0m in depth around
excavation zone, and ten tiltmeters and four vertical beam
sensors on surrounding buildings were installed to monitor
tilting. Layout of instrumentation is presented in Fig. 1 .
656
248
BASEMENT EXCAVATION
The principal steps of basement excavation and construction
sequence are described below;
1. Construct capping beam and excavation to 2.5m below
ground level.
2. Install first level bracing at -1.5m and pre-load the struts
3. Excavate down to -7.0m
4. Install second level bracing at -6.5m and pre-load the
struts
5. Continue excavation down to the final depth at -12.7m
6. Construct mat foundation (Basement 3), Basement 2 and
remove second level bracing
7. Construct Basement 1 and remove the first level bracing
Since the excavation work is located adjacent to the river
and surrounded by old buildings, the diaphragm walls are
subject to three different lateral load conditions resulting
from (1) full depth of the earth, (2) steep downward slope of
riverbed, and (3) full depth of earth with possible surcharges
from the adjacent buildings. In particular, the walls
alongside the river (D1) and the opposite walls (D2), were
expected to undergo an unbalanced loading condition.
During temporary bracing design, two dimensional
computer modeling were carried out to study the effects of
unbalanced lateral loading on the wall and bracing. An
additional two dimensional model analysis was carried out
prior to designing a temporary bracing. The model analysis
indicated relatively less movement of Wall D1 towards
excavation (Fig. 3). However, the following measures were
adopted in excavation work to prevent potentially adverse
behavior of wall D1 and to keep the lateral wall movements
within tolerable limits;
1. Using a simple, but efficient temporary bracing system
2. Pre-loading of the struts (200kN/m and 400kN/m for first
and second levels respectively) on the one end of the
strut on Wall D2 only (Fig. 1).
3. Excavating the soil in front of Wall D1 side first at any
excavation stage
4. Frequent monitoring of wall movements
5. Minimizing construction time
During the initial excavation to 2.5m for installation of first
level bracing, a historic foundation was unexpectively
discovered. Excavation was suspended for about 3 months
and resumed after further excavation was permitted by the
archaeological department.
Excavation for final depth was made in the rainy season
and a berm made of sand bags for flood protection was
constructed around the perimeter of the wall. After lean
mixed blinding concrete had been cast at the final
Wale Beam
Strut
1xWF400x400 WF350x350
2xWf400x400 WF400x400
Expected
Force
(kN/m)
484.0
789.0
249
Displacement (mm)
0
20
Displacement (mm)
40
0.00
RIVER
20
-1.50
5.00
-6.50
10.00
Depth (m)
-12.70
15.00
PREDICTED
OBSERVATION
20.00
25.00
Inclinometer
No. I-7
30.00
3.0
Excavate to 7.0m
2.5
Excavate to 12.7m
2.0
0.9
1.5
1.0
1.1
1.0
1.4
0.64
2.0
0.5
0.42
3.0
0.24
0.14
Inclinometer
No. I-2
0.0
10
Displacement (mm)
0
10
20
0.00
30
40
30
20
10
Depth (m)
10000
-6.50
10.00
-12.70
15.00
PREDICTED
OBSERVATION
20.00
25.00
30.00
1000
-1.50
5.00
100
Displacement (mm)
40
Inclinometer
No. I-3
Inclinometer
No. I-5
Risk
Category 1
<1/500
Max.
Settlement
of building
(mm)
<10
Tiltmeter
1/2082*
Vertical
Beam Sensor
Risk
Category 2
1/3165*
1/500
10 - 50
Description
Negligible : superficial
damage unlikely
Slight: possible
superficial damage
which is unlikely to
have structural
significant
658
250
Depth (m)
50
100
150
200
250
15
T (mm)
0.10
T
0.05
-0.05
50
100
150
0.50
200
TILTMETER
250
EL
EL (mm)
T-1 (B3)
T-2 (B3)
T-3 (B3)
T-4 (B3)
T-5 (B3)
T-6 (B2)
T-7 (B1)
T-8 (B1)
T-9 (B1)
T-10 (B1)
0.00
0.25
VERTICAL
BEAM
SENSOR
0.00
-0.25
-0.50
50
100
150
200
70
250
I-1
I-2
I-3
I-4
I-5
I-6
I-7
I-8
60
50
40
30
INCLINOMETER
20
10
0
10
-0.10
DISCUSSION
50
100
150
200
250
Fig. 6
Tilting of adjacent buildings and horizontal
movement of diaphragm wall with construction time
PLANE STRAIN BACK ANALYSIS
A two-dimensional analysis was carried out by using finite
element program named PLAXIS (Veermeer and
Brinkgreve, 1995). A trial and error procedure in which the
values of undrained Youngs modulus (Eu) were adjusted
iteratively was adopted to obtain the best fit between
calculated and measured lateral wall movements. The
excavation stages were modeled by using plane strain
analysis. Mohr-Coulomb constitutive model was used for
clay and sand. Walls and strut were modeled as plate
element and elastic-perfectly plastic spring element
respectively. Pre-loading in struts are also included in the
analysis.
Results of analysis show that modulus value of soft clay is
about 500Su and for stiff clay modulus value is about
2,000Su. For one-dimensional analysis, the spring stiffness
used is equivalent to Eu=800Su for both soft clay and stiff
clay.
251
CONCLUSION
Braced excavation using diaphragm wall subject to
unbalanced loading due to adjacent river and surrounding
buildings, was successfully achieved with proper
instrumentation and monitoring.
Performance of the wall based on the instrumentation results
are presented and discussed.
Back analysis was carried out with two dimensional
modeling to determine the soil modulus. The soil modulus
obtained from back analysis and the modulus adopted in
wall designed were compared.
ACKNOWLEDGEMENT
The authors express their appreciation to the colleagues,
especially to Mr. Ganeshan Baskaran and Mr. Muhammad
Ashfaq Anwar for their invaluable suggestion and assistance
in the preparation of this paper. Initial analysis works
carried out by Dr. Vichai Vitayasupakorn and Mr.Young
Zou are acknowledged.
659
REFERENCES
Lake L. M., Rankin W. J. and Hawley J. (1996) Prediction
and Effects of Ground Movements Caused by Tunnelling
in Soft Ground beneath Urban Area CIRIA Report No.
30, Construction Industry Research and Information
Association, UK.
Vermeer, P. A. and Brinkgreve, R. B. .J. (1995). Finite
Element Code for Soil and Rock Analyses, Balkema,
Rotterdam.
Mana I. A. and Clough G. W. (1981) Prediction of
Movements for Braced Cuts in Clay, Journal of
Geotechnical Engineering Division, ASCE, Vol. 107,
No. GT6, pp. 36-42.
Gan C. H. (1997). Review and Analysis of Ground
Movements of Braced Excavation in Bangkok Subsoil
using Diaphragm Walls, M. Eng Thesis, Asian Institute
of Technology , Bangkok, Thailand.
Tanseng, P. (1997). Instrumented Deep Excavations in
Bangkok Subsoil , M. Eng Thesis, Asian Institute of
Technology, Bangkok, Thailand.
660
252
Teparaksa W.
University of Missouri-Rolla
Rolla, Missouri
253
686
Proceedings: Fourth International Conference on Case Histories in Geotechnical Engineering, St. Louis, Missouri,
March 9-12, 1998.
Narong Thasnanipan
SEAFCO CO. Ltd.
Bangkok 10320
Thailand
Wei Shixin
SEAFCO Co., Ltd.
Bangkok 10320
Thailand
ABSTRACT
This paper presents a case history of performances and predictions of a diaphragm wall which is subject to serve differently from its
initial purpose for which the wall was constructed. The updated requirements associated with the additional excavation created a
situation whereby the wall would become short embedded and behave like free-end supported wall. As the wall had been already
constructed during the time of modification it was only possible to modify the excavation method and bracing system. Accordingly,
the wall stability and possible toe movement were analyzed, to accommodate the updated requirements, by using finite element
methods. Continuous inclinometer monitoring has been carried out during the construction and results are being compared and
analyzed for predicted values. Performance of the wall based on comparison between the inclinometer monitoring results during
different excavation stages and predicted results, are discussed. It has been found that excavation depth for first bracing layer and
construction period are very important for diaphragm wall performance. Large initial movements in the wall strongly influence the
wall movements in the successive excavation works. Construction practice plays a major role in deep excavation work.
KEY WORDS
Diaphragm wall, Lateral movements, Inclinometer, Settlements, Free-end, Bracing, Excavation, Critical height, Cantilever
255
687
INTRODUCTION
Economic growth in Thailand during the past decade has been
forcing the construction industry to look for all feasible
methods to enhance the infrastructure of the country
especially for the Bangkok city. Huge number of high-rise
buildings with multilevel basements are being erected within a
short time possible to accommodate the booming economy.
Value of urban land is increasing in many folds beyond the
limits. Unlike in developed countries, the building rules and
regulations of this city are only in documented form and
hardly established all in practice in a short time. As a result,
developers and owners enjoy relatively more freedom to
modify the structural layout, even during and after
construction stages, to facilitate their growing demands which
are being conceptualized within a short time duration in the
fast developing city, aiming to maximize the area utilization.
The project reported in this paper is an example for such case.
(t/m3)
1.6
Undrained Shear
Strength
Su (t/m2)
1-2.9
Medium Clay CH
1.93
3.5
Stiff Clay CH
2.0
13.7-17.95
Soil Type
Soft Clay CH
SITE CONDITION
SUBSOIL CONDITION
DIAPHRAGM WALL DESIGN
256
688
used. 0.8m thick Diaphragm wall with toe depth of 18m was
found to be adequate enough for the planned basement
construction in such soil condition.
257
689
in the soil of active side about 2-3m away from the wall.
After installation of struts and pre-loading them, the lateral
movements of the wall ceased off. An increment of 2mm4mm was recorded with further excavation stages (See Fig. 5).
Struts from first to fourth levels were pre-loaded 40 t/m, 75
t/m, 75 t/m and 40 t/m respectively, 20%-25% of design load
of bracing system, prior to further excavation. The preloading of the strut was very effective to reduce lateral
movement of the wall and ensuring good intact between wall
and bracing system.
BRACING SYSTEM
The bracing system included continuous waling beams along
the diaphragm wall and longitudinal and transverse struts.
The spacing of strut was generally 6.4m to 6.8m. Table no. 2
shows the type of wide flange structural steels used for the
bracing.
Table 2 Structural steel sections used for temporary bracing
Bracing
Layer
1st
2W300x300x94kg/m
2-W300x300x94kg/m
2nd
2W350x350x137kg/m
2W350x350x137kg/m
rd
2W350x350x137kg/m
2W350x350x137kg/m
W350x350x137kg/m
2W350x350x137kg/m
4th
Strut
Wale
Fig. 6A.
Lateral Movements of the wall shown by
Inclinometer Tubes I-1 and I-2.
The pattern of movements of the wall shown by the
inclinometer readings is similar to that of cantilever condition.
Because of large movements were induced Initially, braced
mode was not developed. After reaching the final excavation
depth the observed movements of the wall at the toe level
258
690
Predicted
for 15.8m
Excavation
(mm)
77
Observed
on Site
(mm)
Top
Predicted
for 14.0m
Excavation
(mm)
35-37
Toe
11
23
1.2-16
55-98
M=Ec.Ief.[dS/dy]
where
Ec
Ief
S
y
(1)
259
691
legs provide the fixity of the wall and increase the bending
moments at a location near the bottom of the wall.
5. Moment redistribution in the wall is considered not fully
activated.
CONCLUSION
1. Movements in first excavation stage is governing the
performance of Diaphragm wall for further excavation.
2. First excavation deeper than the critical height of the soil
needs to be supported immediately.
3.
Apart from support system and
soil properties,
construction practice influenced the movement of the wall in
this particular project.
4. A successful deep excavation with short embedded
diaphragm wall has been achieved using a combination of
prediction by computer simulations and instrumented field
observations.
Fig. 9
Relationship amongst system stiffness, nondimensionalized wall movement and factor of safety against
basal heave .
260
ACKNOWLEDGEMENT
692
261
Filed Measurements
In Geomechanics
Edited by
263
Field Measurements in Geomechanics, Leung, Tan & Phoon (eds) 1999 Balkema, Rotterdam, ISBN 90 5809 066 3
ABSTRACT: In the wastewater treatment plant, an Inlet Pumping Station (IPS) is one of the most important
structures to collect and pump all wastewater to the treatment plant. The IPS presented in this paper consists
of 20m deep underground chambers. A reinforced concrete diaphragm wall system 1.0m thick and 25m. deep
was used in construction of the IPS. Four Inclinometer tubes were installed in the diaphragm wall to monitor
the lateral wall movements during excavation work for basement construction. When excavation approached
the final depth, excessive lateral wall movements were observed, but they were not taken seriously. Later,
some cracks on the capping beam and noise from the bracing system were noticed. Then the IPS collapsed
and was buried under sliding soil mass. At the time IPS collapsed five main bracing layers and only two of
the five intermediate bracing layers had been installed. This paper emphasizes the importance of instrumentation. Additionally it presents the results of investigation into the causes of the collapse, as well as the reconstruction work.
1. INTRODUCTION
nal
Ca
ng
isti
Ex
Reconstructed
Canal
Inlet Pumping
Station (IPS)
Storm Pumping
Station (SPS)
Canal Wall
Pump Sta
tion
Treatment Plant
(STP)
2. PROJECT DESCRIPTIONS
The second phase Bangkok wastewater project presented herein was started in 1995 to serve the central area of Bangkok City. The project was planned
to be completed by 1999 (ie. within 4 years). In the
sewage treatment plant (STP), the IPS is one of the
most important structures to collect and pump all
wastewater to the sewage treatment plant. Figure 1
presents the location of IPS on the sewage treatment
plant (STP) site.
247
265
Legend
-2.20
-3.95
Intermediate Strut
-5.70
I-2
-7.95
-10.20
-11.95
I-1
Diagonal
Struts
Main Strut +
Intermediate Strut
I-4
I-3
-13.70
-15.45
-17.20
-19.10
-21.0
B+
A+
I-3
SECTION A-A
-21.0
SECTION B-B
3. SOIL CONDITIONS
At the start of the project, the site consisted of very
soft clay (mud) about 2 - 3m deep. The soft clay
apparently extended westward, into the residential
area of the wooden houses. When work on the project commenced, mud was removed from the site up
to the property boundaries. Approximately a 3.0m
thick of sand backfill was placed on the site. Then
the soil conditions consisted of 3.0m thick sand
backfill, followed by soft to medium dark grey clay
approximately 16.0m deep. Then stiff to very stiff
silty clay was encountered at about 30.0m depth,
overlaying the first dense silty sand layer. The sensitivity of the soft to medium clay was in the order
of 2.5 to 6.0. A piezometric level was found at
about 21.0m below ground level, as a result of deep
well pumping. A summary of general soil properties and soil stiffness is presented in Table 1.
m
to
3.0
16.0
20.0
30.0
Soil
Description
Fill
Soft Clay
Stiff Silty Clay
Very Stiff Silty Clay
Dense Silty Sand
t
kN/m3
18.0
16.0
19.0
20.0
20.0
Su
kN/m2
12-30
100-150
175-250
-
266
50
Displacement (mm)
-100
0.00
100
5.00
5.00
10.00
10.00
Depth (m)
Depth (m)
-50
0.00
15.00
-50
50
15.00
20.00
20.00
20-Jun-97
4-Jul-97
12-Jul-97
18-Jul-97
25-Jul-97
5-Aug-97
13-Aug-97
25.00
30.00
20-Jun-97
4-Jul-97
12-Jul-97
18-Jul-97
25-Jul-97
5-Aug-97
13-Aug-97
25.00
30.00
A-Axis
B-Axis
Displacement (mm)
10
-20
0.00
0.00
5.00
5.00
10.00
10.00
Depth (m)
Depth (m)
-20
15.00
20.00
10
20.00
4-Jul-97
12-Jul-97
25.00
5-Aug-97
27-Jun-97
4-Jul-97
12-Jul-97
25-Jul-97
25-Jul-97
30.00
15.00
27-Jun-97
25.00
-10
30.00
A-Axis
5-Aug-97
B-Axis
However, the wall movements in A-axis direction were considerably large and thus the main
beams supporting the edges of the circular enclosure
seemed not effective. The two differential move249
267
Figure 5. Bracing system seen on 16, Aug. 1997 (after Thasnanipan, 1997)
Figure 6a. After collapse soil mass moved in (after Thasnanipan, 1997)
posed walls. Phien-Wej & Sriruanthong (1999) reported that at the final excavation depth in IPS reconstruction, the toe of the diaphragm wall in the
collapsed zone was found in original position and
there was no evidence of basal heave.
The importance of temporary bracing has been
emphasized in various design guides, manuals and
reports by Padfied & Mair (1984), William & Waite
(1993) and Feld & Carper (1996). In the case of
improper temporary bracing, this issue was identified as the main cause of collapse. Results of the
analysis by means of FEM (Kanok-Nukulchai, et al.
1998) concluded that the main strut supporting the
edges of the circular enclosure was grossly overstressed. The report also stated that these struts
would have progressively reached their capacity at
the initiation of the collapse and may have become
totally ineffective. It was clearly indicated by the
photographs taken just one day before the collapse
of the IPS (Fig. 8).
Figure 8 shows separations of the built-up walling beams and struts, which would reduce the capacity of the monolithic section by 30%. The three
lower intermediate struts required at the edges of the
circular enclosure were not present eventhough the
excavation works reached the final depth (Fig. 5).
This improper bracing also contributed to the cracks
observed on the capping beam. Additionally, lateral
movements of the walls, shown by inclinometer
Soft Clay
Stiff Clay
Figure 6b. Soil mass buried everything inside the pit. (after
Phien-Wej et al. 1999)
268
251
Displacement (mm)
-50
50
-100
100
0.00
0.00
5.00
5.00
10.00
10.00
Displacement (mm)
-50
50
Legend
Grouting
Zone
I-3
Depth (m)
Depth (m)
Inclinometer
Tube
15.00
I-6
I-2
15.00
I-4
20.00
20.00
I-1
25.00
FEM Analysis
Excavate 16.5 m
Excavate 16.5 m
Excavate 19.0 m
Excavate 19.0 m
30.00
30.00
A-Axis
I-5
B-Axis
I-3
I-6
269
Strain Gauge
Location
I-2
Strain Gauge
Location
I-4
I-1
I-5
Displacement (mm)
-50
-25
25
50
Feld, J. and Carper K.L (1996) Construction failure (2nd edition) John Wiley & Sons. Inc.
Kanok-Nukulchai, W. and Phien-Wej, N. (1998). Investigation
on Collapse of an Inlet Pumping Station- Looking into
modeling, Design and Construction Considerations, ACECOMS News and Views, July - September, AIT, Thailand
Katzenbach, R., Moormann, C., and Quick H (1998), A new
concept for the excavation of deep building pits in inner
urban areas combining top/down method and piled-raft
foundation, 7th Int. Conf. and Exhibition on Pile and Deep
Foundation, Vienna, Austria.
Padfied, C. J. and Mair, R. J. (1984) Design of Retaining walls
Embedded in stiff clay CIRIA Report 104.
Phien-Wej, N. (1991) Types of Design and limitations of various retaining cofferdam system, Technical seminar in
Foundation and underground construction works, organized by EIT, Feb. (in Thai) Bangkok, Thailand
Phien-Wej, N. and Sriruanthong, M. (1999) Remedial Construction of Inlet Pump Station, wastewater Project, Yannawa, Civil Engineering Magazine, EIT. Jan- March. (in
Thai.)
STS (1995) Preliminary factual report of Geotechnical Investigation for Bangkok Wastewater Treatment on Sewage
Treatment Plant, Bangkok, Thailand
Teparaksa, W., Thasnanipan, N., Muang, A. W. and Wei, S.
H. (1998) Prediction and Performances of Short embedded
cast in-situ diaphragm wall for deep excavation in Bangkok subsoil. 4th Intl. Conf. On Case Histories in Geotechnical Engineering St. Louis, Missouri, USA.
Thasnanipan, N. (1997) The Cause of failure of the cofferdam
under soil excavation and bracing installation stage at an
Inlet Pumping Station, Sewage treatment plant, SEAFCO,
Internal Report (in Thai).
Thasnanipan, N., Muang, A.W, Tanseng, P. and Wei, S.H.
(1998) Performance of A Brace Excavation in Bangkok
clay, Diaphragm wall subject to unbalanced loading
conditions. 13th Southeast Asian Geotechnical Conference.
Taipei, Taiwan, ROC.
William, B. P. and Waite, D. (1993) The Design and
Construction of Sheet Piled Cofferdams CIRIA special
publication 95, Thomas Telford.
Displacement (mm)
75 0
25
50
75
100
0.00
-2.00
5.00
Depth (m)
10.00
-11.50
15.00
20.00
-21.20
25.00
30.00
35.00
29-Mar-98
13-Apr-98
13-Apr-98
17-May-98
17-May-98
30-May-98
30-May-98
21-Jun-98
21-Jun-98
2-Aug-98
2-Aug-98
13-Sep-98
13-Sep-98
-32.00
Figure 12 shows the status of excavation and strutting before casting the new IPS structures inside the
temporary diaphragm wall. The lateral wall movements were recorded by I-2 and I-6 with maximum
wall deflections of about 50.0mm 70.0 mm respectively (Fig. 13). The reconstruction work was thus
successfully completed with proper instrumentation.
7. CONCLUSIONS & RECOMMENDATIONS
It was learnt that ignorance of instrumentation for
deep underground construction can cause a serious
disaster.
Adequate instrumentation should be provided for
deep excavation to avoid remedial work.
Monitoring and maintenance of instrumentation
should be carried out throughout the work.
Parties involved in deep underground construction should have enough knowledge in geotechical
works and instrumentation.
Proper instrumentation enabled the successful
reconstruction of IPS.
8. ACKNOWLEDGEMENT
The authors wish to express their appreciation to the
colleagues, especially to Mr. Thiruchelvam
Navaneethan for his invaluable advice and assistance in preparation of this paper.
9. REFERENCES
EIT (1999), Case study of problems related to settlement and
failures Geotechnical Engineering in the Past 2 years,
Subcommittee of Geotechnical Engineering, Engineering
Institute of Thailand (EIT)
252
270
Filed Measurements
In Geomechanics
Edited by
Teparaksa W.,
271
Field Measurements in Geomechanics, Leung, Tan & Phoon (eds) 1999 Balkema, Rotterdam, ISBN 90 5809 066 3
W. Teparaksa
ABSTRACT: This paper presents the behavior and performance of diaphragm walls constructed for basements of two buildings along the bank of the Chao Phraya River bank, Bangkok, Thailand. These buildings
were constructed at different periods under one contract. A case history on basement excavation of the first
building has been reported previously by Thasnanipan et al. (1998). For the second building, more numbers
of instrumentation including VWSGs in a diaphragm wall panel and pressure gauges in struts to monitor
stress in the wall and the performance of bracing system were used respectively. The construction sequence
adopted for excavation, performance of the walls and bracing based on instrumentation results are discussed.
1 INTRODUCTION
273
First Building
g
uildin
rey B
5 Sto
Second Building
5 Storey
Building
5 Storey
Building
5 Storey
Building
5 INSTRUMENTATION
+14.80
3 5
10
+11.30
+7.80
Vane Shear Strength (kPa)
+4.30
-3.20
-5.80
-8.40
+0.70
Bored
Pile
Pile Dia.
Building
800mm
1000mm 1200mm 1500mm
First
32*
18*
31
6
Second
17*
33
5
23
* Some piles were incorporated in diaphragm wall panels.
For both buildings, 800mm thick cast in-situ concrete diaphragm walls of 28m toe depth with two
level temporary bracings were designed for basement excavation. The maximum excavation depths
for the first and second buildings were 12.7m and
9.7m respectively. 28m deep walls were necessary
for overall stability of excavation as they were located on the riverbank.
0.80m Thick
D-Wall
4 PILE FOUNDATIONS
3 DIAPHRAGM WALLS
+0.80
Weathered Clay
Soft to
Medium
CLAY
20
40
60
80
SPT-N (Blows/ft)
0
50
100
0.00
5.00
10.00
15.00
Stiff to Very
Stiff CLAY 20.00
25.00
Medium to
Very Dense 30.00
SAND
First Bldg.
Second Bldg.
35.00
Different wall types were classified by design according to load conditions, slab supporting locations
and geometry of ground profiles. The walls were
designed generally as vertical beams to withstand
bending moments up to 1100 kN-m/m. In the slab
opening areas, additional horizontal bars were provided for secondary bending moments. A non-linear
Beam-Column Analysis using a one-dimensional fi-
Type of
Instrumentation
Inclinometer
First
Building
8
Second
Building
6
Measurements
made
Wall deflections
Settlement Plate
10
20
Tiltmeter
10
10
Vertical Beam
Sensor
Ground settlements
Tilting of Buildings
Tilting of buildings
VWSG
1 location*
Strain in rebars
Earth Pressure
2x2
Sturt forces
Gauge
* A pair of VWSG in 5 layers along the depth of wall panel
268
274
Tiltmeter
I-7
Chao Phray
a River
Inclinometer
D1
I-6
Bored Piles
Preload Position
I-8
Historical
Building
(2 Storey)
I-5
I-2
D2
B1
I-3
D3
I-1
D2
0
10
5 Storey Building
D3
D3
B3
I-4
B2
15
7 Storey Building
Scale
S4
I-1
D10
S10
D9
S9
S3
D3
I-2
T1
EL5
lding
ey Bui
5 Stor
S1
I-3
I-6
T9
S8
D8
EL1
T2
T10
D1
S2
D2
5 Storey
Building
T8
EP-1
D7
EL4
T3
S5
T4
I-5
S6
5 Storey Building
D5
D6
I-4
T5
S7
VWSG-1
EL2
T6
Legend
I = Inclinometer in D-Wall
T = Tilt plate
Pre-load position
T7
EL3
5 Storey Building
10
20
6 EXCAVATION WORK
Conventional bottom-up method with two levels of
temporary bracing was adopted for excavation to
construct foundation and basement floors of both
buildings. Prior to excavation work for the first
building, a two-dimensional computer analysis was
carried out using PLAXIS finite element computer
program to study possible behavior of the wall system under unbalanced lateral loading conditions.
Such conditions were considered to be resulting
from (1) full depth of the earth, (2) a step sloping
river bed and (3) full depth of earth with possible
surcharges from the adjacent buildings.
A major concern was that the diaphragm walls
alongside the river would be thrust from the opposite
walls. These bore a higher lateral load through axial
force of struts as excavation progressed in stages.
This wall behavior was indicated by computer modeling (Fig. 4), and previous reports by De Rezende
Lopes (1985) and Kotoda et al. (1990). To prevent
any adverse wall behavior alongside the river, the
following measures were taken;
275
269
Time (Days)
0.0
100
200
Depth (m)
2.0
300
B1
Excavation Depth
4.0
B2
6.0
B3
8.0
7 INSTRUMENTATION RESULTS
400
10.0
Max. horiz. movement
(mm)
I-4
60
I-2
40
20
0
3000
Design Line
2500
Strut Load (kN)
80
2000
First Strut
1500
1000
500
Second Strut
0
1200
50
100
200
250
10
T-1 (B3)
T-2 (B3)
T-3 (B3)
T-4 (B3)
T-5 (B3)
T-6 (B2)
T-7 (B1)
T-8 (B1)
T-9 (B1)
T-10 (B1)
Tension = positive
0.00
-0.25
-0.50
100
80
60
40
800
400
EF (4.5m)
EF (7.0m)
EF (9.5m)
EF (13.0m)
EF (17.0m)
0
-400
Settlement (mm)
Displacement
(mm)
0.25
Excavation Face
1200
-300
0.50
SF (4.5m)
SF (7.0m)
SF (9.5m)
SF (13.0m)
SF (17.0m)
-100
Soil Face
-400
Inclinometer
I-1
I-2
I-3
I-4
I-5
I-6
I-7
I-8
20
S6 (Land side)
-20
S9 (River side)
S7 (Land side)
S10 (River side)
-40
-60
20
20
0
Settlement (mm)
400
Tilt Meter
100
-200
Max. Horiz
. Movement
(mm)
800
Differential in Tilting
(Second)
Differential in Tilting
(second
)
15
200
-20
-40
-60
200
100
Tilt plates
T5
T6
0
-100
-200
10
Displacement (mm)
Depth(m)
150
Tension = positive
0
0
Time (days)
0
-5
-10
276
270
Displacement (mm)
0.00
RIVER
20
Displacement (mm)
40
40
20
-1.50
5.00
-6.50
10.00
Depth (m)
-12.70
15.00
PREDICTED
OBSERVATION
20.00
25.00
Inclinometer
No. I-7
30.00
Inclinometer
No. I-2
20
40
60
Displacement (mm)
80
80
60
40
20
-2.00
River
5.00
-7.00
Day 133
Day 155
Day 67
Day 133
-9.70
10.00
Depth (m)
Day 67
Day 221
15.00
Day 155
Day 221
Prediction
20.00
Day
25.00
30.00
67
133
155
221
Inclinometer
No. I-2
Description
Excavate to -2.5m
Excavate to -7.5m
Excavate to -9.70m
Remove strut at -7.00m
Inclinometer
No. I-4
277
271
9 CONCLUSION
<1/500
1/2082*
1/2008**
1/3165*
1/985**
1/500
Max.
Settlement
of building
mm
<10
10 - 50
Description
Negligible: superficial damage unlikely
With proper instrumentation, two basement excavations using braced diaphragm walls subjected to unbalanced lateral loading from the river and adjacent
buildings were completed.
Performance of the walls based on the instrumentation results are presented and discussed.
For underground construction work, monitoring
with instrumentation plays a major role, especially
when delay occurs during excavation. Moreover,
overall construcion cost, time and risk can be minimised with the use of instrumentation.
10 ACKNOWLEDGEMENT
The authors express their appreciation to Mr. Thiruchelvam Navaneethan for his assistance in the
preparation of this paper. We would also like to acknowledge initial analysis work carried out by Dr.
Vichai Vitayasupakorn and Mr. Young Zou.
REFERENCES
8 DISCUSSION
The planned excavation sequence and deep embedment (about 18m and 8m below the excavation and
the fixity respectively) of the walls are considered to
have contributed to minimizing the effect of unbalanced load conditions, particularly for the walls
alongside the river.
Instrumentation results, particularly from the
monitoring of wall movements have given effective
warning against inproper installation of bracing system and excavation sequences.
This allowed
improvement or modification of the bracing system
where necessary.
No damage was found in adjacent buildings, as
confirmed by instrumentation results, particularly
those from vertical beam sensors and tiltmeters.
In comparing bracing systems for the first and second building works, stiffness of the first level bracing used for the second building is estimated to be
only 50% of that for the first building while expected strut force is 25% less. Moreover single strut
arrangement in the first level bracing for the second
building is less rigid compared to dual strut arrangement which can act as a composite beam for
the first building. Instrumentation on struts confirmed that bracing system used was adequate.
In both cases, early installation of bracing, particularly for the first level is very important for
minimizing wall top movements, subsequently reducing accumulated wall movements for further excavation.
278
272
De Rezende Lopes, F. (1985). The problem of asymmetricsurcharges in strutted excavations. Ground Engineering, vol.
18, no.2, pp 31-35. GCO Publication no.1/90 (1996). Review of design methods for excavations Geotechnical Engineering Office, Civil Engineering Department, Hong
Kong.
GCO Publication no.1/90 (1996). Review of design methods
for excavations. Geotechnical Engineering Office, Civil
Engineering Department, Hong Kong.
Ikuta, Y., Maruoka M., Aoki M. and Sato E. (1994). Application of the observational method to a deep basement excavated using the top-down method. Geotechnique 44, No. 4,
pp 655-664.
Kotoda, K., Kazama, S., Ogawa, H. and Kato, K. (1990). Behavior of earth retaining structure for excavation subjected
to non-symmetrical lateral loading. Tenth Southeast Asian
Geotechnical Conference, 16-20 April 1990, Taipei, Taiwan. pp. 539-544.
Lake, L. M., Rankin, W. J. and Hawley, J. (1996). Prediction
and effects of ground movements caused by tunnelling in
soft ground beneath urban area. CIRIA Report No. 30,
Construction Industry Research and Information Association, UK.
Padfield, C. J. and Mair, R. J. (1991). Design of retaining
walls embedded in stiff clay. CIRIA Report 106. Construction Industry research and Information Association. London, UK.
Peck, R. B (1969). Advantages and limitations of the observational method in applied soil mechanics. Geotechnique 19,
No. 2, pp. 171-187.
Thasnanipan, N., Maung A. W., Tanseng P. and Wei S. H.
(1998). Performance of a braced excavation in Bangkok
clay, diaphragm wall subject to unbalanced loading conditions. Thirteenth Southeast Asian Geotechnical Conference, 16-20 November, 1998, Taipei, Taiwan. Pp. 655-660.
Williams, B. P and Waite D. (1993). The design and construction of sheet-piled cofferdams. CIRIA Special Publication
98, Thomas Telford Publications.
Conference Proceedings
Volume 2 (Part I)
Editors:
D. G. Lin
D. T. Bergado
N. Phien-wej
P. Nutalaya
A. S. Balasubramaniam
279
II ~ 67
281
ground surface settlement. The appropriate soil modelings as well as the input soil parameters
are the key issues to simulate the system. The most important soil parameter is the stiffness of
each soil layer, which is normally specified in terms of Youngs modulus (E). The E value is
very important especially for the soft clay layer that lead to induce the lateral wall movement
and ground settlement during excavation works. Normally, E is assumed to be linear and
determined from the conventional triaxial compression test and is very low as compared to the
values obtained from the empirical correlation. This is because of the high strain levels at
which the E is measured in the conventional triaxial test. The E value is recently known to be
dependent on the order of shear strain level. Mair (1993) compared the soil stiffness at various
shear strain levels for different structural systems as well as various kinds of laboratory tests as
shown in Figure 1. In case of concrete diaphragm walls, the shear strain is of the order of
0.01% to 0.10% only.
The research works on the soil behaviors at the low strain level in soft Bangkok clay
was presented by Shibuya et al (1997) based on laboratory tests as well the in-situ field vane
shear tests. Authors presented the soil stiffness in terms of Maximum Shear Modulus (Gmax).
Gmax is about 300*Su (300 times of Undrained Shear Strength) to 500*Su and if converted to
the Undrained Youngs modulus (Eu) will be equal to 900*Su to 1500*Su for Poisson ratio ()
of 0.5. Teramast (1998) also presented the soil stiffness at low strain levels based on the
Bender Element Test as Gmax = 400*Su to 570*Su or Eu = 1200*Su to 1710*Su. As shown
in Figure 1, Mair (1993) mentioned that the Bender Element Test is suitable for very low
strain levels such as applied to the dynamics or earthquake problems. Most practical value of
Eu for Bangkok subsoils is based on the empirical correlation proposed by Duncan &
Buchigani (1976) as shown in Figure 2. The Eu values were presented relative to the
undrained shear strength, which is dependent on the order of Over Consolidation Ratio (OCR).
For Bangkok soft clay where OCR is about 1.6, Eu/Su = 300-600.
Stiffness G
Retaing Walls
Foundations
Tunnels
0.0001
0.001
Bender
0.01
0.1
10
Shear Strain s: %
Resonant Coulomn
Local
Special Triaxial
Conventional
282
II ~ 68
necessary to verify the appropriate soil stiffness. The back analysis was carried out for three
case studies at the Thammasat University project, Dindang underpass project and Sathorn
Complex project. Using the 2D-FEM program namely PLAXIS (Brinkgreve & Brand,
1996) back analysis for the said projects have been carried out. The analytical plain strain
concept and the Mohr-Coulomb soil model or bi-linear modeling was used.
Thamasart University Project
The building site is located nearby the Chao Phaya River and surrounded by a
historical building seated on shallow raft foundation as shown in Figure 3. The diaphragm
wall along the river was constructed about 3-4 m away from the existing old and shallow river
wall as shown in the building section in Figure 4. The river bed near the river wall is about 3
m in depth and sloping towards the mid-stream to a depth of about 10-12 m (Thasananipan et
al, 1998). This riverbank lead to induce the unbalanced lateral earth pressure on the
diaphragm wall system between land side and riverside. A 800 mm thick diaphragm wall was
designed for excavation down to 12.7 m below the ground with two levels of temporary
bracing at 1.5 m and 6.5 m depth. The diaphragm wall toe was embedded down to 28 m to
achieve the overall stability of the excavation which is right on the river bank (Fig. 4). A site
investigation was carried out by two boreholes and four field vane shear tests, the subsoil
properties are summarized in Table 1.
Table 1. Summary of subsoil properties
Soil Type
Crust
Soft Clay
Medium Clay
Siff Clay
Dense Sand
Depth
(m)
0.0-2.5
2.5-12.7
12.7-14.0
14.0-25.0
>25.0
Wn
(%)
50
70-85
50-55
20-25
-
Unit Weight, s
(kN/m3)
19
26
17
20
20
Cu
(kPa)
30
15-30
30-45
130-250
-
SPT-N
(Blows/ft)
14-40
>39
Instrumentation
Due to the locality and particular conditions of the site, more instrumentation than those used
by other projects in Bangkok were installed and monitored. Three types of instrumentation Eight inclinometer tubes are installed in diaphragm wall panels to monitor displacement of
wall, ten settlement plates of 1.0m and 5.0m in depth around excavation zone, and ten
tiltmeters and four vertical beam sensors on surrounding buildings were installed to monitor
tilting. Layout of instrumentation is presented in Fig. 3. Since the excavation work is located
adjacent to the river and surrounded by old buildings, the diaphragm walls are subject to the
unbalanced lateral load The model analysis indicated relatively less movement of Wall D1
towards excavation in the land side and move less in the river side as well as induce forward
movement of river wall to the river (Fig. 5). This analysis led the engineer to solve the
damages of the river wall due to unbalance loading by using the following construction
methods.
283
II ~ 69
I-7
D1
I-6
I-8
Tiltmeter
B3
Inclinometer
Surface & Deep Settlement Plates
D3
Preload Position
I-5
I-2
D2
B1
Historical Building
(2 Storey)
I-3
10
15
Scale
B2
D3
I-1
5 Storey Building
D3
Bored Piles
D2
I-4
7 Storey Building
0m
6m
10m
20m
0
RIVER
5
10
RIVER
WALL
15
20
0.80 THK.
D-WALL
FOUNDATION
PILES
0.80 THK.
D-WALL
25
30
35
284
II ~ 70
Analytical Results
The analysis was trial by changing the soil stiffness and compares the results with the
field performance. Figure 6 shows the results of FEM analysis compared with inclinometer
measurements based on soil stiffness of Eu/Su = 500 and 2000 for soft Bangkok clay and stiff
clay, respectively. . Movements of Wall D1 close to the river are found to be cantilever shape
indicated by I-7 while movements of Walls D2 and D3 have inward bulging shape indicated
by I-1 to I-5. Generally the predicted and measured lateral wall movements are in a good
agreement, except for the top portion of wall in which the measured wall movements exceed
the predicted movements. The differences in wall movement were found to be caused by the
following;
Advancement of excavation in front of Wall D1 further than other walls, allowing Wall D1
to stand longer prior to strut installation than the others.
Wall D1 was in cantilever condition for about 3 months after initial excavation for first
level bracing.
0
SPT (blow/ft)
20 40
60
Su FV (kN/m 2)
80 0
10
20
30
Excavate
7.00 m
Excavate
2.00 m
40
0.00
0.00
5.00
5.00
5.00
10.00
10.00
10.00
15.00
15.00
15.00
20.00
20.00
20.00
25.00
25.00
0.00
Excavate
12.70 m
Crust
Med.
Clay
Stiff to
Very
Stiff Clay
Depth (m)
Soft to
Very
Soft Clay
Field
25.00
PLAXIS
Dense to
Very Dense
Sand
30.00
10
20
30
Displacement (mm)
40
30.00
10
20
30
30.00
40
Displacement (mm)
10
20
30
40
Displacement (mm)
285
II ~ 71
SPT (blow/ft)
0
20
40
60
20
40
60
Excavate
4.90 m
Excavate
2.7 m
Su FV (kPa)
80 0
80
0.00
0.00
5.00
5.00
10
10.00
10.00
15
15
15.00
15.00
Stiff
to Very Stiff
20
Clay
20
20.00
Crust
20.00
Field
PLAXIS
25
25
25.00
25.00
-10
10
Displacement (mm)
20
-10
10
20
Displacement (mm)
286
II ~ 72
I-3
Excavation -15.5m
Bored Pile
Barrette
Inclinometer Tube
I-4
I-2
89.35
Excavation -14.0m
I-1
120.25
16
-1.50
15
-2.40
14
-4.20
13
-5.10
-6.90
11
-9.00
-11.80
-12.30
10
-9.60
9
8
-14.00
-13.30
-18.00
12
-15.50
-18.00
LEGEND
12
CONSTRUCTION STAGE
TEMPORARY BRACING
Unit Weight
s (kN/m3)
Soft Clay, CH
Medium Clay, CH
Stiff Clay, CH
16
18
20
287
II ~ 73
Undrained Shear
Strength, Su
(kPa)
10-29
35
137-180
Analytical Results
.
The wall constructed was designed for initial excavation of -2.5m to install the first
bracing layer. However the excavation has been done to about -3.0m to -3.2m at once and a
movement of 40mm was observed. Time delay during construction of capping beam and over
excavation deeper than the critical height (Hcr = 2C/) was unsupported around three months
resulted an increase in wall movements to 55mm -70mm. Tension cracks were developed in
the soil of active side about 2-3m away from the wall. After installation of struts and preloading them, the lateral movements of the wall ceased off. Struts from first to fourth levels
were pre-loaded 40 t/m, 75 t/m, 75 t/m and 40 t/m respectively, 20%-25% of design load of
bracing system, prior to further excavation. The pre-loading of the strut was very effective to
reduce lateral movement of the wall and ensuring good intact between wall and bracing
system. Figure 10 shows the comparison of the results of FEM analysis compared with
inclinometer measurements based on soil stiffness of Eu/Su = 500 and 2000 for soft Bangkok
clay and stiff clay, respectively. The measuring data was neglect the first movement due to the
delay of the first cantilever diaphragm wall around three months. The predicted and measured
lateral wall movements are in a good agreement.
Horiz. Displacement, mm
-10
10
20
30
40
0.00
-2.40
-5.10
5.00
Depth, m
-9.00
10.00
-11.80
-14.00
-15.50
15.00
-18.00
20.00
25.00
Inclinometer Tube
Penetrate into Pile Leg
PLAXIS
I-1
I-2
Figure 10 : Comparison of wall movement from FEM analysis and inclinometer results
COMPARISONS OF ANALYSIS WITH PRESSUREMETER TEST
The trial soil stiffness based on the back analysis shows that the Young modulus of soft
Bangkok clay and stiff clay are Eu/Su = 500 and 2000, respectively. Recently, six self-boring
pressuremeter tests were performed along the route of Metropolitan Rapid Transit (MRT)
northern contract by the Cambridge In-situ of Little Eversden (1997). The self-boring
pressuremeter tests were carried out by reload/loading cycles in order to determine the soil
stiffness at various shear strain levels. Figure 11 shows the results of pressuremeter test and
288
II ~ 74
1500
1 5 00
1250
1 2 50
1000
1 0 00
G /Su
G /Su
shows the variation of shear modulus with shear strain, Figure 11.1 is for soft clay while
Figure 11.2 is for first stiff clay. For normal practice of diaphragm wall construction for deep
basements in Bangkok soft clay, the shear strain is in the order of 0.1-0.2%, where the G/Su is
about 160 or Eu/Su =480. In case of the first stiff silty clay layer where shear strain is in the
order of 0.05-0.1%, the G/Su is about 340 or Eu/Su = 1020. The soil stiffness of the soft clay
from pressuremeter test results is very close to the results of back analysis, however, the
values of stiff clay from pressuremeter test results is lower than the results of back analysis,
this is might due to the effect of bored pile stiffness inside of the excavation area. The
correlation from the self-boring pressuremeter was the non-linear soil model that will be used
to carry out the future back analysis.
750
500
500
250
250
0
0 .0 1
0 .1 0
0 .01
1 .0 0
0 .10
1 .00
750
CONCLUSIONS
The analysis and the design of the diaphragm wall are normally based on the
assumption of soil stiffness. Back analysis to verified the soil stiffness based on three
different cases as under unbalanced loading, underpass project under very close to the
foundations of the first stage expressway, and short embedded wall. The results shows that the
soil stiffness in terms of Young modulus is Eu/Su = 500 and 2000 for soft Bangkok clay and
stiff clay, respectively. These values were also corresponding to the results of self-boring
pressuremeter tests of the first blue-line subway project in Bangkok.
REFERENCES
Brinkgreve, R. and Brand, P.A.(1996): Application of PLAXIS for soil and rock plasticity,
Short Course on Numerical Analysis in Geotechnical Engineering, AIT.
Cambridge In-situ (1997): Self-boring pressuremeter MRTA initial system project, North
Contract.
Duncan, J.M. and Buchigani, A.L.(1976): An engineering manual for settlement studies,
Geotechnical Report of Civil engineering Department, university of California at
Berkeley.
289
II ~ 75
290
II ~ 76
GeoEng2000
An International Conference on
Geotechnical & Geological Engineering
19-24 November 2000
Melbourne Exhibition and Convention Centre
Melbourne, Australia
291
GeoEng2000 An International Conference on Geotechnical and Geological Engineering 19-24 November 2000, Melbourne, Australia
BANG SU STATION
CH
AO
PH
RA
YA
RIV
ER
LEGEND :
293
Construction of diaphragm walls and barrettes of the Thiam Ruam Mit station was carried out by an experienced local foundation contractor in which the authors worked while international contractors undertook
similar work for the remaining 17 stations.
SUBSOIL CONDITIONS
0m
10m
SOUTH
NORTH
STATION BOX
SOFT CLAY
TUNNEL
20m
TUNNEL
30m
SILTY SAND
40m
50m
STIFF CLAY
SILTY SAND
60m
w
%
40
64-100
16-51
16-20
Cu
kPa
30-45
15-31
107-250
61-410
s
kN/m3
17.0-19.0
14.6-16.8
18.3-21.8
20.8-21.1
21.0-21.1
SPT- N
Blow/ft
5-9
13-17
27-59
11-61
The depth of ground water table at the site generally varies from 0.9m to 2.2m. Piezometers installed in
the project area indicate the pore pressure is hydrostatic below 23m depth due to pumping of ground water.
SITE CONDITION AND PREPARATION
2-SC
R.S.TOWER
2-SC
2-SC
2-SC
OPEN AREA
Mr. P FRESH
MILK
THAI
INSURANCE
2-SC
4-CF
ENTRANCE 12.1
4-CF
ENTRANCE 12.2
C
L
C
L
C
L
C
L
VENT.
ENTRANCE
12.4
SHAFT 1
ORAN
GE LIN
E
TO RAMA IX ROAD
TBM
DRIVE
SHAFT
RATCHADAPHISEK
RD.
C
L
27.000
TO LATPHRAO ROAD
C
L
ENTRANCE 12.3
VENT.
SHAFT 2
359.000
294
width of the work area needed to be widened locally to position the grab crane for diaphragm wall panel excavation.
Utility Diversion
The site is bounded by some underground utilities, including a 1.0m diameter water pipe and telecommunication cables in the close vicinity of the work area, particularly on the east side. Above ground, 69kV electricity lines, telephone cables, drainage and sewage pipes (1.5m dia.) lay on both sides. The water pipe ran
along the planned diaphragm wall at about 3.0m depth and thus it was diverted by the other subcontractor to
the west, outside the station box prior to construction. The face-to-face clearance distance between the diverted water pipe and the outer face of the station wall was only 35cm due to space constraints. A reinforced
concrete wall to protect the pipe was constructed and it formed the bottom part of the guide wall for diaphragm wall panel excavation.
Two duct banks of the telecommunication cables were located 5-10cm away from the wall face at a depth
of 3.04m. 15mm thick steel plates were used in these locations as both guide walls and protection systems
for the duct banks.
CONSTRUCTION SPECIFICATION
Generally construction specifications were in line with the commonly practised specification for foundation works. Regarding construction tolerances, verticality of the walls and barrettes is specified within 1:200
while for pre-founded steel stanchions, the verticality allowed is within 1:400.
Table 2. Test and compliance values for bentonite
slurry
Property
Density
Viscosity
Fluid loss
Sand content
pH
Test
Specification
API RP13B1 Section
3
4
5
7
9
Freshly
Mixed
< 1.05g/ml
29-50
< 30ml
< 1%
8-12
Prior to
Placing
Rebar &
Concrete
< 1.10g/ml
29-50
< 30ml
< 2%
8-12
CONSTRUCTION PHASES
Throughout the project, the main construction schedule for the station comprised several interfacing and
parallel work activities such as for utilities and traffic diversions, temporary decking, substructure work for
station box and the TBM driving shaft which other subcontractors undertook. This meant that guide wall
construction in particular needed to follow utility diversion as the same area was to be excavated for relocation of the utilities, removal of abandoned water pipes and construction of guide walls. The temporary decking and excavation for the TBM launching shaft followed the diaphragm wall construction.
DIAPHRAGM WALL AND BARRETTE CONSTRUCTION
Equipment and Plant
Mechanical rope-suspended grabs with crawler cranes (80tons) and service cranes (50-80tons) were used
as main construction equipment. Grabs, 1.0mx2.0-3.0m and 1.2mx3.0m were used to cut the required dimensions of panel excavations. Bentonite slurry was used as supporting fluid for panel and barrette excavation. Silos having a total of 300 cu.m storage capacity and de-sanding and de-silting units (80cu.m/hr capacity) were used to supply the slurry required for up to two-panel excavation at a time.
295
29.200
15.000
OF TNL.
TBM
LAUNCHING
SHAFT
4.500
6.300
C
L
C
L
OF TNL.
3.000
4.000
6.300
4.850
Guide Walls
Generally 1.5m deep guide walls were used for panel excavation. In the location of underground water
pipes and duct banks, up to 3.0m-deep guide walls were used. Individual panels were sized with the following considerations: (1) type of reinforcement, (2) size of grabs used, (3) thickness and depth of panels, (4)
location of slab and wall openings for entrances and TBM, (5) stability of trench in connection with location
of underground utility and (6) location of public accesses and streets.
Panel Layout
The walls were divided into 184 panels with horizontal lengths varying from 2.5m to 4.85m. L-shaped
and T-shaped panels were used to form box structures of the station and TBM launching shaft (see Fig. 5).
Sequence of Construction
Construction activities took place day and night. To maintain the traffic flow, comply with local authority regulations, construction sequence and activities were planned to allow concrete pouring and spoil removal to be done before and after rush hours, in most cases at night. Generally panel excavation was carried
out at least 6.0m away from the recently cast panel or 16hrs after casting of the adjacent panels to avoid any
damage induced by excavation.
Supporting Fluid
Locally available bentonite powder was used for preparation of slurry. This product had been used for
more than a dozen completed diaphragm wall projects,. Approximately 496 tons of bentonite powder was
consumed for excavation work. The last portion of slurry displaced by concrete or contaminated with cement was usually discarded. Soil volumes of about 26,274cu.m and 10,740cu.m were excavated for diaphragm walls and barrettes respectively.
Reinforcement
Steel bars of SD50 were used for the main reinforcement bars. The reinforcement cages were 30.0m to
42.2m long and up to 4.5m wide, with 4 levels of box-out for slab connections for diaphragm wall panels.
For barrettes, cages were 48.1 to 54.6m long. 4 to 5 cage sections with lengths of 6-12m were joined to form
one continuous cage for individual panels and barrettes. The cage sections were fabricated off site and no
more than two were joined for transporting to the site. Cage sections were connected prior to and during
lowering into the trench. In order to place the box-out in position and to achieve an exact match of the cage
sections, markings were made on the main bars of each cage. U-shaped bolts were used for cage connections. Couplers were generally used for slab connection and both couplers and bent-out bars were used for
beam connections at the wall openings for entrances and slab openings. The large panel cages weighed up to
34.8 tons.
For panels with glass fibre reinforcement polymer (GFRP) for openings of TBM break-through, a temporary steel frame was necessary to hold the cage section due to different stiffness between GFRP and steel.
The frame was then cut away section by section while lowering the cage. Diaphragm wall panels were rein-
296
forced with 136-218 kg/m2 of steel bars while barrettes were reinforced with about 50kg/m3 of steel bars.
The wastage of steel was about 7% in which most quantity was consumed for cage hanging bars and frames
for soft eye openings. A total of 4,756.15 tons of reinforcement bars was used for diaphragm wall and barrettes. Steel pipes 150mm in diameter were installed inside the diaphragm wall panels at 5 locations as a
void former for inclinometer access tubes. 28 sets of vibrating wire strain gauges and total jack-out pressure
cells were also installed in the wall panels of TBM launching shaft.
Concrete Casting
Ready mixed concrete grades 40 (cube strength 40MPa at 28 days) and 35 (35MPa at 28days) to BS5328
were used for diaphragm walls and barrettes respectively. Two sets of tremie pipes were used in pouring
concrete for both diaphragm walls and barrettes. The largest single concrete pour was about 232cu.m for Lshaped panels. Total concrete volumes of 27,480cu.m and 6,611cu.m were poured for diaphragm walls and
barrettes respectively. Concrete over-consumption in diaphragm wall caused by old, sand back-fill in the
area of abandoned water pipes was estimated to be an average of 7.8% with a concrete wastage of up to
38.0% occurring in one panel. However, the average concrete wastage was 5.0%. For barrettes, the average
concrete wastage was up to 14%. The high wastage compared to building and elevated highway projects (up
to 7%) was caused by overcasting of concrete well above the cutoff level of 22m depth to ensure that sound
concrete reached above the cutoff. Aggregates were used to backfill the open trench of barrettes above the
concrete after casting.
Installation of Stanchion in Barrettes
Conventional plunging method was not adopted in view of the site conditions, low cutoff level, the stanchion design and horizontal bar arrangements in the reinforcement cage. Two specially designed installation
frames with adjustable screws were used for installation of stanchions to ensure high accuracy for verticality
and plan position. A removable 10m-long, steel column was fixed on top of the stanchion to check the verticality and alignment.
PRODUCTION RATES
The construction time required for a typical panel and barrette is detailed
in Table 3.
Table 3. Average construction time for typical diaphragm wall panels
(1.0x4.5x35.0m, cutoff 0.0m) and barrettes (1.2x3.0x44.5m, cutoff 22.5m).
Activities
Excavation
Checking verticality with Koden
Desanding
Cage installation
Stanchion installation
Tremie preparation
Concrete pouring
Diaphragm wall
Hours
18
1
4
2.5
2.5
4
Barrette
Hours
16.5
2
5
4.5
3
3.5
3.5
297
occurred at one time by a heavy downpour. Standby time (14% of construction period) took place and was
contributed by (1) obstructions by overbreak concrete during panel excavation and stop-end plate removal
and (2) standing time after panel excavation reached below the soft clay to allow subsequent construction activities such as spoil removal and concrete delivery taking place outside rush hours. Traffic diversions were
carried out in multi-phases and took at least 5% of construction period.
QUALITY, SAFETY AND ENVIROMENTAL CONTROLS
As the alignment of diaphragm wall and barrettes is critical, every excavated panel and trench was
checked with Koden monitoring equipment. Monitoring was carried out after excavation reached about
22.0m (ie. at the levels of base slab and barrette cutoff) and toe levels. Necessary corrections to trench verticality were made during excavation if required. Panel ends, especially for those panels with soft-eyes for
TBM break-through were also checked to achieve high levels of accuracy for positioning. During excavation, reference posts were used for checking the grab position and observing rope position relative to the
trench sides at all times. Prior to lowering the reinforcement cage into the trench, any mudcake built-up on
the trench faces and panel joints was scraped off by a grab to which brushes were attached. Finally, any
sediment or loose materials deposited at the bottom of the trench were also removed by using the grab.
Reference bars attached to the top of reinforcement cage were extended above ground level to check the
position of the cage with survey equipment during installation of the cage into the trench.
Delivered concrete was checked for slump and cohesiveness prior to casting. As per specifications, adequate embedding length of tremie pipes in the concrete and slurry properties were maintained to achieve
good-quality concrete casting. Plugging materials and shutters were introduced in the tremie pipes to separate first concrete pour and slurry in the trench. Samples of reinforcement bars and concrete were taken as
specified for testing in the lab. 37 barrettes were provided with 6 steel tubes each for sonic logging to test
the barrette concrete quality. No significant anomalies were detected by sonic logging test, and integrity and
quality of barrette were found adequate.
As the site was in a busy public area, site and public accesses were kept clean all the time. Flagmen were
also provided for traffic control at each construction zone. All workers were inducted in safety procedure
prior to assuming duty. Construction activities were also supervised by a full-time safety officer. The safety
officer ensured that all labor used mandatory personal protection equipment and observed the safety regulations. All heavy equipment and cranes were checked for safety and certified for operation prior to use and
for regular maintenance. Additionally, regular safety patrols and inspection were also conducted by the main
contractor and supervising engineers.
CONCLUSION
Construction work on the public road, involving various activities parallel with different
teams/subcontractors demanded comprehensive construction sequences and planning to meet the targeted
milestones. Proper coordination, planning, supervision and strict safety and environmental control by the
parties involved thus brought about the successful completion of diaphragm wall and barrette construction on
one of the busiest roads in Bangkok without any serious accident. When the paper was finalized, excavation
inside the station box had been completed and it revealed good quality of workmanship without requiring
any significant remedial work.
ACKNOWLEDGEMENT
The authors wish to express their appreciation to the MRTA and Nishimatsu Construction Co. Ltd. for
their permission to publish this paper.
REFERENCES
Thasnanipan, N. Maung, A. W. and Tanseng, P. (1998), "Barrettes Founded in Bangkok Subsoils, Construction and Performance", Thirteenth Southeast Asian Geotechnical Conference, Taipei, Taiwan, ROC, November 16-20, 1998. pp. 573-578.
298
ISBN 974-13-0107-3
299
Lecturer
Suranaree University of Technology, Nakornratchasima, Thailand
2
Project Manager, 3Geotechnical Engineer
SEAFCO Company Limited, Bangkok, Thailand
(Diaphragm wall)
ABSTRACT: Modern
buildings in Bangkok frequently require the excavation works for the basement facility
adjacent to the existing structures. Diaphragm walls have been commonly used as permanent retaining walls for
excavation works in various projects. Comprehensive monitoring system is of essential for any excavation works
particularly for those adjacent to the sensitive buildings. This paper presents the monitoring of diaphragm wall
displacement and associated movement of the ground and adjacent structures including historical building using
a number of instruments for basement construction works located at the bank of Chao Phraya River. The bracing
system and construction sequence adopted for excavation with the consideration of the presence of an
unbalanced loading condition are also briefly discussed. Building damage risk assessment using a simple
approach was carried out based on the instrumentation results and compared with the damage criteria established
by published research work. A course of action undertook in response to the observed critical movement is also
presented.
301
1.
INTRODUCTION
Excavation works in soft ground inevitably induced the ground movements which in turn may
damage the adjacent existing structures. Diaphragm walls are commonly used as permanent
retaining walls for basement excavation of many projects in Bangkok. It is necessary to use this
type of rigid retaining wall in excavation work to minimize the ground movement particularly
where the work is to be carried out in close proximity to the existing sensitive buildings. This
paper presents the monitoring of diaphragm walls displacement and associated movement of the
ground and the adjacent structures including historical building using a number of instruments
for completed construction works located at the bank of Chao Phraya River, Bangkok. Design
and construction aspects of the project have been reported by Thasnanipan et al. (1999).
2.
I1-6
D1-1
D1-6
T1-1
E1-2
T2-1
B3
T1-2
I1-8
D1-3
S2-3
D2-3
S2-1
I2-6
E2-1 S2-2
T2-2
D2-2
T2-10
E2-5
I2-3
T2-9
B6
S2-8
D2-8
Second Building
Building
T1-3
I1-5
S2-10
S2-9
D2-1
5 Storey
ing
First Build
I2-1
D2-10
D2-9
T1-4
I1-2
D1-2 T1-8
E1-4
E1-5
Historical
Building
(2 Storey)
T1-10
T1-9
E1-1
S2-5
I2-5
T1-5
T2-4
I1-3
B1
T2-8
D2-7 E2-4
T2-3
B4
T2-5 E2-2
T2-6
T2-7 E2-3
0
D1-8
D1-2
B2
D2-6 S2-7
6 10
B5
20
I1-4
Legend
T1-6
E1-3
Building
Inclinometer in D-Wall
Tilt plate
Vertical beam sensor
Surface settlement plate (1.0m)
7 Storey
302
GTE - 54
3.
SUBSOIL INVESTIGATION
Two stages of site investigation were made. Preliminary stage of site investigation was
performed during the tendering stage. Second stage of soil investigation was conducted prior to
designing temporary bracing and basement excavation work. As subsoil properties obtained from
the boreholes and test data were well reported by Thasnanipan et al. (1999), they are not
presented again in this paper.
4.
5.
6.
Monitored Parameters
Wall deflections
Ground settlements
Tilting of Buildings
Tilting of buildings
Strain in rebars
Strut forces
Excavatio
n Depth
-12.79m
Second
-9.70m
Bracing
Level
I
II
I
II
Bracing
Elevation
-2.0
-6.5
-2.0
-7.0
Strut
Sections
2 x WF350 x 350
2 x WF400 x 400
1 x WF400 x 400
2 x WF350 x 350
303
GTE - 55
7.
SETTLEMENT PREDICTION
Due to the presence of unbalanced loading condition, non-symmetric pattern of settlement
distribution around the perimeter of excavation could be expected. However, considering the fact
that pre-loading was to be used for the land side diaphragm wall but not for the riverside wall,
settlement distribution was assumed to be symmetrical. Available methods were reviewed for
predicting the ground movement with the consideration of two main factors such as, (1) simple
and practical in application (2) enable to correlate with the predicted and measured diaphragm
wall deflection.
Sio
D O = HW+ W
Surface settlement trough
volume, V To
S WO =
HE
Dy
Siy
Sub-surface settlement
trough volume, VTy
Settlement
influence zone
deflected volumn V y at depth (H w- Y)
Swy
HW
D-wall
SWO
W
Total deflected
shape volume, V O
4V O
DO
x
S io = SWO *
DO
D
DY = Y * O
HW
V
VTY = VY * TO
VO
8. INSTRUMENTATION RESULTS
8.1 Inclinometer Monitoring
The predicted and observed diaphragm wall deflections of the first building and second buildings
are presented in Figure 3a and 3b respectively. As can be seen in the figures, observed wall
movements exceeded the predicted values at the top portion of the walls for both buildings. The
delay in installing the first level bracings, leaving the walls in cantilever conditions for the long
period was the main reason of the large movement induced by the excavation at that stage.
304
GTE - 56
RIVER
20
Displacement (mm)
Displacement (mm)
Displacement (mm)
0.00
40
40
20
0.00
-1.50
20
40
60
Displacement (mm)
80
80
60
5.00
-6.50
-7.00
-9.70
10.00
-12.70
15.00
Depth (m)
Depth (m)
PREDICTED
OBSERVATION
Day 67
Day 133
Day 221
10.00
15.00
Day 155
Day 221
Prediction
20.00
Day
25.00
67
133
155
221
25.00
30.00
20
Day 67
Day 133
Day 155
20.00
40
-2.00
River
5.00
Inclinometer
No. I-7
Inclinometer
No. I-2
30.00
Inclinometer
No. I-2
st
Description
Excavate to -2.5m
Excavate to -7.5m
Excavate to -9.70m
Remove strut at -7.00m
Inclinometer
No. I-4
At Inclinometer No.I-6 of the second building, wall movement was found to reach the trigger
value at top portion when excavation reached 7.5m depth after the first level bracing installation.
Lateral wall movement reached a maximum rate of 6.5mm/day and a tension crack on the ground
was found about 8m away from the wall. A close examination of the bracing system indicated
that one strut had swayed slightly about 130mm. Immediate actions were taken by stacking
additional strut on the defective one and installing of the second level bracing carried out at that
area. The wall movements were found to cease after these actions.
The wall deflections of the first building excavation found unaffected by the unbalanced lateral
loading condition. However, for second building, monitoring results from inclinometer I-2 and I4 suggested that the wall alongside the river was pushed against the retaining soil by the opposite
wall.
8.2 Settlement and Building Movement
Figures 4a, 4b and 4c present the construction activities with time and corresponding monitoring
data. As can be seen in the figures, monitoring results reflected the construction activities in
general. It was also proved that performance and response of the diaphragm wall were largely
influenced by the construction activities. It can be observed that significant changes in the
responses were mainly occurred during the initial excavation stages in which walls were
unsupported for long period. Monitoring data particularly that of settlement and building tilt
measurement provided ample opportunity to assess the risk of the existing buildings damage. As
the measured data were far less than the critical values, the excavation works were proceeded
with confidence.
8.3 Strut Force Measurement
Daily monitoring was carried out for pressure gauges installed on struts. The comparison of
predicted and measure strut forces are presented in Table 3. In general, the measured values
indicated that the bracing system used was adequate.
Table 3 Comparisons of Predicted and Measured Strut Force
Bracing Level
First Level
Second Level
Predicted Force
(KN/m)
354.5
307.3
305
GTE - 57
Excavation Record
Time , D ays
50
100
150
200
250
50
Time, Days
100
150
200
250
300
350
Exc. De pth, m
2
4
Exc. Depth, m
6
8
10
12
14
Tilt M e te r D ata
200
Tilt, Se cond
100
T 1 - 1 (B 3 )
T 1 - 6 (B 2 )
T 1 - 8 (B 1 )
-1 0 0
-2 0 0
150
200
250
300
100
Second Strut
50
350
0.0
Exc. Depth, m
150
10
Time, Days
100
First Strut
200
2.0
4.0
6.0
Settlement, mm
250
8.0
0
-10
S6
S7
S9
S10
-20
-30
-40
10.0
Tilt, Second
100
0
-100
E2-2 (B4)
T2-4 (B4)
T2-8 (B5)
T2-10 (B6)
-200
Inclinometer Data
200
80
I-4
60
40
I-2
20
0
0
50
100
150
200
250
300
350
Figure 4 Monitoring results of instruments with construction time for First and Second Buildings
9.
306
GTE - 58
10
15
20
25
30
35
40
0
-5
-5
-10
-10
Settlement (mm)
Settlement (mm)
10
15
20
25
30
35
40
-15
-20
-15
-20
surface settlement
-25
settlement at depth 7m
settlement at depth 14m
-30
surface settlement
-25
settlement at depth 7m
-30
Figure 5 Prediction of surface and subsurface settlement induced by 1st building excavation
Distance from Wall (m)
10
15
20
25
30
35
40
-10
-10
-20
-20
Settlement (mm)
Settlement (mm)
-30
-40
10
15
20
30
35
40
-30
-40
surface settlement
surface settlement
-50
settlement at depth 7m
-50
25
settlement at depth 7m
settlement at depth 14m
-60
-60
Figure 6 Prediction of surface and subsurface settlement induced by 2nd building excavation
Depth of
Settlement
Considered*
Maximum Tilt
Measured by Tilt
Meter / EL Beam
Building Slope
Criteria for
Negligible Damage**
At surface
1/2082
At depth 5m
At surface
B2
1/4125
At depth 7m
At surface
B3
1/2578
At depth 7m
At surface
B4
1/1412
At depth 7m
At surface
B5
>1/5000
At depth
1/1771
1/4250
14m
At surface
1/926
1/926
B6
1/3437
At depth
1/2256
1/4400
14m
Note : (1) * assumed foundation level (2) ** unlikely to have superficial damage (Rankin 1988)
B1
< 1/500
< 1/500
< 1/500
< 1/500
< 1/500
< 1/500
As can be seen in Table 4, the measured maximum tilt of the buildings reasonably agree with
predicted building slopes derived from inclinometer measurement, particularly if the buildings
were assumed to be settled by subsurface settlement at assumed pile tip levels. All buildings
307
GTE - 59
were predicted to be in negligible risk category as classified by W.J. Rankin (1988). Field
inspection confirmed that no damage was caused in all buildings from the minor movements
induced by excavation works.
10. CONCLUSIONS
Instrumentation played a major role in execution and successful completion of excavation works
adjacent to the existing sensitive buildings under unbalanced loading condition. Effective bracing
system, excavation sequence and adequate embedment of the retaining walls were the main
factors contributed in minimizing negative impact of the unbalanced loading condition.
A simple approach in prediction of ground settlement and assessment of the risk of building
damage has been presented. The measured maximum tilt of the buildings reasonably agreed with
the predicted values. It is necessary to use the rigid diaphragm wall in excavation work to
minimize the ground movement particularly where the work is to be carried out in close proximity
to the existing sensitive buildings.
REFERENCES
1. Bowels J.E., Foundation Analysis and Design, 4th Edition, McGraw-Hill, Singapore, 1990.
2. Rankin W.J., Ground Movement Resulting from Urban Tunnelling : Prediction and Effects,
Engineering Geology Special Publication No.5, p. 79-92, 1988.
3. Thasnanipan, N., Maung A. W., Tanseng P. & Teparaksa W., Behavior and Performance of
Diaphragm Walls under Unbalanced Lateral Loading along the Chao Phraya River , Field
Measurements in Geomechanics, Leung, Tan & Phoon (eds), p. 267-272, Balkema, 1999.
308
GTE - 60
th
12 Asian Regional
Conference on Soil Mechanics
and Geotechnical Engineering
Performance
of
Buttress-Support
Thin
Diaphragm Wall for Underground Car Park in
Bangkok
Narong Thasnanipan,
Submaneewong
Zaw
309
Zaw
Aye
and
Chanchai
Abstract : This paper presents the geotechnical aspect of the construction of two-level underground car park building located in the culturally and historically significant area of Bangkok. Performance of buttressed-support diaphragm wall of 0.60m width is reported
based on the inclinometer monitoring results. Intensive modification of construction sequence in actual work execution with value
engineering options different from tender stage design is demonstrated along with application of observational method.
1 INTRODUCTION
CITY HALL
CITY
HALL
OPENING
OPENING
SIRIPONG ROAD
OPENING
OPENING
OPENING
SHOP-HOUSES
OPENING
MAHUNNOP ROAD
SHOP-HOUSES
DINGSOR ROAD
BRAHMIN TEMPLE
2 PROJECT OVERVIEW
OPENING
OPENING
311
I-5
I-4
first strut and final excavation level for 600mm diaphragm wall)
due to large volume of excavation work involved.
NORTH D-WALL
EAST D-WALL
WEST D-WALL
I-6
PHASE 2
Prior to the commencement of excavation works, value engineering review of the temporary works was undertaken by the contractors new team of design engineers together with the construction team. The main objectives were to minimize the
material and construction sequence involved in temporary works
so as to accelerate the excavation time thereby saving overall
costs without compromising the safety aspect. After conducting a
series of re-analyses with different conditions major modifications were made : (1) To change first strut level to 1.8m from
the original tender stage design level 1.0m (2) To use only 1
temporary strut, omitting second level raking strut with the provision of sloping soil berm against diaphragm walls. Soil berm
was to remove after completion of base slab construction in the
majority of area minimizing the elapsed time of partially unstrutted diaphragm wall between temporary strut and the final
excavation level.
124 m
SHEET PILE
I-3
I-1
PHASE 1
I-2
SOUTH D-WALL
78 m
(a)
D IA P H R A G M W A L L
RC BUTTRESS
BARRETTE
W ALE BEAM
0 .3 0
T IE B E A M
SLAB
(b)
+0.20 ROOF SLAB
0.00
CAPPING
BEAM
RC BUTTRESS
G.W.L
TIE
BEAM
-9m
-12m
-16m
WALE
BEAM
DIAPHRAGM
WALL
MEDIUM CLAY
Su = 30 kN/m2
Eu = 19250 kN/m2, = 17.5 kN/m3
STIFF CLAY
Su = 60 kN/m2
Eu = 45000 kN/m2, = 19 kN/m3
FOUNDATION
PILES
DIA.600MM.
BARRETTE
-20m.
(c)
Fig. 2 (a) Layout of diaphragm wall and piles (b) plan of diaphragm wall and buttress (c) sectional view of the structures
4 SUBSOIL CONDITION
Similar to other localities in Bangkok a typical subsoil profile at
the site is characterized by thick Bangkok soft clay layer at the
top followed by thin layer of medium clay, and stiff clay layers
as depicted in figure 2 (c). The first sand layer is found below
26m from the existing ground level.
RAKING STRUT
D-WALL
-16m
-20m
BERM
BARRETTE
SLAB
D-WALL
BORED PILE
Fig. 3 Tender stage bracing system diaphragm wall was designed to be supported by 2 struts (horizontal bracing and raker)
312
SLAB
HORIZONTAL STRUT
HORIZONTAL STRUT
SLAB
BERM
D-WALL
RAKING STRUT
BARRETTE
SHEET PILE
-16m
-14m
-16m
-20m
-20m
BORED PILE
40
60
80
100
8
10
Stage 1
Stage 2
Stage 3
Stage 4
Stage 5
with buttress
without buttress
Tender Stage
12
14
16
18
20
Depth, m.
Depth, m.
20
40
60
80
100
8
10
12
14
16
18
Stage 1
Stage 2
Stage 3
Stage 4
Stage 5
with buttress
without buttress
Tender Stage
20
Fig. 5 Phase 1 - Monitored diaphragm wall deflection at different stages with predicted maximum deflection profiles of different condition (with buttress, without buttress and tender stage)
Stage
2
3
4
5
Excavate to 4m
Excavate to 4m
Removal of berm
Removal of berm
Removal of temporary
strut after completion of
buttress
Removal of temporary
strut after completion of
buttress
With assurance of diaphragm wall performance from monitoring results of Phase 1, original plan of using horizontal struts
for North diaphragm wall was modified by using raking struts instead of horizontal struts. As can be seen in figure 8 (b), deflection of North diaphragm wall (with raking strut support) is significantly higher than that of East diaphragm wall (with
horizontal strut support). The main reason of larger movement of
north diaphragm wall is due to the fact that it was supported only
by the berm for the long period (about 52 days) before completion of raking struts so that soil-rheology effect took place during
the long elapsed un-strutted period. Time-dependent deflection
pattern due to soil-rheology effect can be observed in North diaphragm wall as illustrated in figure 9. North diaphragm wall
moved progressively toward excavation before completion of
raking struts (at 52 days) as can be seen in figure.
313
SLAB
HORIZONTAL STRUT
COMPLETED PHASE 1
STRUCTURE
RAKING STRUT
SLAB
TEMPORARY KING-POST
CAPPING BEAM
BERM
RAKER
D-WALL
BARRETTE
-16m
DIAGONAL STRUT
DIAPHRAGM WALL
D-WALL
BERM
TEMPORARY WALER
BUTTRESS
BERM
TEMPORARY
STEEL BEAM
PILE
CAP
-16m
-20m
-20m
EAST & WEST D-WALL
COM
S
TED
PLE
LAB
40
60
80
100
10
Stage 1
Stage 2
Stage 3
Stage 4
Stage 5
with buttress
without buttress
12
14
16
18
Depth, m.
Depth, m.
10
Stage 1
Stage 2
Stage 3
Stage 4
Prediction
12
14
16
18
20
20
Fig. 8 Phase 2 - Monitored diaphragm wall deflection at different stages with predicted maximum deflection profiles of different condition
Cum. Displacement , mm.
0
2
4
Depth, m.
6
8
10
12
14
16
18
20
0 days
30 days
52 day (raker installed)
56 days
74 days
Prediction
Fig. 9 Phase 2 Time dependent wall deflection of North diaphragm wall diaphragm wall was supported only by soil-berm
for 52 days before completion of raker installation.
Table 2 Summarized description of stages shown in figure 8
Stage
Excavate to 4m
4
5
Removal of temporary
strut after completion of
buttress
Removal of berm
Significant cost and time saving were achieved from the value
engineering options coupled with observational method implemented for both Phase 1 and 2. The major savings were achieved
by less operation and material utilized in the following elements
of temporary works.
Cancellation of 2nd level raking struts against diaphragm wall
for both phases
Modification of bracing system using raking struts instead of
horizontal struts for North diaphragm wall in Phase 2
13 CONCLUSION
This research study reveals that a permanent diaphragm wall
coupled with effective design and construction method supplemented by observational method could offer a logistically and financially attractive solution in construction of underground car
park without disturbing the environment in the prominent historical area of Bangkok.
314
Win
315
Maung,
Thayanan
Seafco Public Company Limited, 26/10 Rarm Intra 109 Road, Bangchan, Khlong Sam Wah, Bangkok 10510,
Thailand.
[email protected]
Abstract: This paper presents findings on trench stability resulting from the use of polymer slurry. A trial trench 0.60x4.50x18.00m
was excavated for diaphragm wall construction in Bangkok soft clay, using polymer as an alternative to bentonite slurry. Under
consideration was its superior environmental advantages for soft clay soils typical of the region, notwithstanding a limited capacity to
suspend soil particles. The trench was excavated with a cable suspended mechanical grab, filled with polymer slurry and left open for
4 days. Field measurement included recording of slurry properties, settlement surveys, inclinometer monitoring, periodical checking of
the trench profile with Koden drilling monitoring equipment and trench depth sounding. Polymer slurry properties in the trench were
found to change sharply within 12 hours, with density, pH and viscosity gradually decreasing after 12 hours. Sedimentation occurred
within a few hours after completion of trench excavation and a 7.00m thick deposit was indicated at the bottom of trench after 10.5hrs.
The deposit was cleared with the excavation grab but sedimentation recurred. The trench profiles plotted by Koden drilling monitoring
equipment showed trench surface failure starting at depths between 7.00m and 7.50m on one of the long sides of the trench face 18
hours after trench excavation, with inclinometer readings indicating maximum soil yielding of about 6mm after 10 hours. A major
collapse of the trench surface was observed approximately 36 hours after trench completion, with ground settlement of up to 9mm.
Based on field measurement results and characteristics of the polymer used, the suitability of using polymer slurry is discussed.
1. INTRODUCTION
2. SITE CONDITIONS
317
20
10
40
60
80
100
120
20
30
40
50
60
Atterberg Limit
0
20
40
%
60
80
100
120
Crust
5
Soft Clay
10
M. Stiff Clay
15
20
Stiff Clay
M. Dense Sand
25
UCS
SPT
SPT N (Blow/ft)
3. TRIAL TRENCH
The trial trench was located about 1.0m away from the
borehole. A concrete guide wall of 1.5m deep was constructed
with continuous reinforcement and cast against firm ground.
The trial trench was 0.6m wide, 4.5m long and 18.0m deep. For
field monitoring, all monitoring points, comprising 6 settlement
survey points using one inclinometer tube were located on the
opposite site of the excavation equipment to avoid disruption
caused by the excavation activities during trenching operation.
Locations of settlement survey points and inclinometer tube are
shown in Figure 2.
P2
P3
P4
P5
P6
1m
2m
2m
2m
2m
Legend
Settlement Point
P5
I1
Inclinometer
The trial trench excavation was carried out on 16th of June 1999
at 14:00hrs and completed at 23:30hrs. Sedimentation occurred
within a few hours after completion of the trench and sediment
built up to 11.0m in depth (i.e. deposit thickness was 7.0m) after
10.5hrs. The estimated rates of settlement of soil particles
ranged from 1.0m to 1.4m per hour in thickness for the first 4hrs
after trenching and then gradually decreased. Cleaning of the
trench base was carried out 14hrs after trench completion.
However, sedimentation recurred and built up to a depth of
13.0m after 12hrs.
24hrs after base cleaning (36hrs after
excavation), sedimentation built up to a depth of 6.9m due to
trench face failure.
12
24
36
48
60
72
84
96
0.00
P1
5.00
10.00
15.00
20.00
318
P1
P2
P3
P5
P4
P6
0
1
40
Settlement (mm)
30
20
Density (kN/m )
10
pH
0
0
12
24
36
48
60
72
84
96
2.00
3.00
4.00
5.00
12 Hrs
24 Hrs
36 Hrs
48 Hrs
60 Hrs
72 Hrs
96 Hrs
84 Hrs
6.00
2 Hrs
10
0.00
Time after
trench
excavation
Viscosity (sec)
0.0
0 Hr after excavation
10.0
Excavated to -9.0m
15.0
Excavated to -12.0m
6. DISCUSSION
Excavated to -15.0m
0 Hr after trenching
4 Hrs
20.0
6 Hrs
12 Hrs
79 Hrs
25.0
319
Bangchan,
North-East
Bangkok
1.37-1.80
1.6-2.0
40-105
50-85
1.6-2.0
2.0-18.7
21-71
43-84
Below
22.0m is
medium
dense sand.
Trench
Dimension in
m
Max. Ground
8mm
Settlement
Max. Soil
55
20-30
yield in mm
(after 31 days)
(after 24 hrs)
Supporting
Bentonite,
Bentonite
Fluid
Water after 32days
9mm
6
(after 10hrs)
Polymer
320
321
323
Sand layer generally occurs at depths between 45 to 65m. Typical subsoil profile of Bangkok
area is shown in Figure 1.
Geotechnical
Parameters
0
200
400
600
10
40
Hard Clay
50
Dense to Very
Dense Sand
(Second Sand)
30
SPT-N= 20-40
t = 20kN/m 3
60
50
Line
tatic
e
Lin
wn
wdo
Dra
SPT-N= 50-100
t = 21KN/m 3
40
tric
ros
H yd
Medium
Dense Sand
(First Sand)
me
30
zo
Pie
Medium to
Stiff Clay
ual
20
Act
Depth (m)
10
Bangkok Soft
Clay
0
0
Weathered Crust
60
324
It does not require temporary bracing system so that time requirement and cost for
temporary works (both material and labor costs) are eliminated, in turn significantly
saving cost.
Excavation for basement must be carried out with the support of permanent
retaining wall so that basement floor slabs can be utilized as lateral bracing.
Diaphragm wall of 0.8m to 1.2m in thickness with sufficient embedment in firm soil
layers is commonly used as a retaining wall whereas prefabricated steel columns known as
stanchions embedded in either large diameter deep-seated bored piles or barrettes are utilized
as structural columns. Figure 2 illustrates the top-down construction method with utilization
of stanchions and diaphragm wall for underground subway station.
325
Guide frame
Stanchion
Stanchion
Stanchion
Slurry
Slurry
Tremie pipe
Temporary
casing
Temporary
casing
Temporary
casing
Pile cut-off
level
Pile cut-off
level
Pile cut-off
level
Pile cut-off
level
concrete
concrete
Stanchion installation
Concreting
(1 tremie for bored pile and
2 tremie for barrette)
Backfill
326
Figure 4 Guide frame used for pre-concreting installation in Thailand Cultural Center Station
of the M.R.T Chaloem Ratchamongkhon Line
Figure 5 shows the installation of a 24m long built-up steel stanchion into the pile
borehole prior to concreting.
Figure 5 Stanchion length 24m attached to the top portion of reinforcement cage installed into
borehole prior to concreting
327
Tremie pipe
Stanchion
Stanchion
Slurry
Slurry
Slurry
Backfill
Temporary
casing
Temporary
casing
Temporary
casing
Pile cut-off
level
Pile cut-off
level
Pile cut-off
level
Concrete
Concreting by tremie
method
Installing stanchion by
plunging into concreted pile
Concrete
328
Stanchion can not be inserted up to the required depth as concrete becomes hard due
to the premature setting
During lowering, stanchion is stuck by reinforcement cage and due to the hardening
of the concrete, extraction of stanchion becomes impossible for reinstallation
As the installation of the stanchion is often associated with many unforeseen problems,
it is likely in many cases that concrete becomes stiff or prematurely set during the installation.
In Bangkok, premature setting of concrete is usually found to be attributed by;
inappropriate mix
severe weather
329
330
1600
1600
1450
1250
950
1600
1450
500
No stanchion
No stanchion
No stanchion
Total
Number
6
3
15
17
2
17
8
3
9
16
Boundary Line
D-Wall
Figure 9. Arial view of the top-down construction in progress concrete batching plant was
set up on site to minimize the concrete supply interruption in congestive area with severe
331
Major Activity
Top-down
Duration
(month)
4.5
10
12
32
36
4.5
16
13
332
Floor level
Floor level
1st Bracing
Soft Clay
B1
-3.92
Soft Clay
B1
-3.92
2nd Bracing
B2
-8.20
B3
-11.29
B4
-14.30
B5
-17.39
Stiff Clay
Hard Clay
-19.10
-24.00
Soft Clay 2
B2
-8.20
B3
-11.29
rd
3 Bracing
B4
-14.30
B5
-17.39
Stiff Clay
Hard Clay
Top-down construction
Soft Clay 2
-19.10
-24.00
Bottom-up construction
Top-Down Method
Stage
Construction Sequence
Stage
1
1
Excavate to -1.7m and install
temporary bracing at -1.5m
2
2
Excavate to -4.5m and construct B1
Slab
3
3
Remove 1st bracing at -1.5m
Excavate to -11.8m and construct B3
4
Slab
4
Excavate to -19.1m and construct
5
Mat Foundation
5
Construct B4, B2 and Ground Floor
6
6
Slab
7
Construct above floors
8
7
9
10
11
12
13
Bottom-up Method
Construction Sequence
Excavate to -1.7m and install first
level temporary bracing at -1.5m
Excavate to -7.2 m and install 2nd
level temporary bracing at -7.0m
Excavate to -13.0m and install 3rd
level temporary bracing at -12.8.0m
Excavate to -19.1 m and construct
mat foundation
Construct B4 Slab and columns
Remove 3rd level bracing
Construct B3 Slab and columns
Construct B2 Slab and columns
Remove 2nd level bracing
Construct B1 Slab and columns
Remove 1st level bracing
Construct Ground Floor Slab
Construct above floors
333
Predicted and measured diaphragm wall deflection is shown in Figure 14 As can be seen in
the figure, actual measured deflection values are less than those of prediction. The shape of
the deflection curves of prediction and actual measurement at each construction stage is fairly
identical which suggests that design parameters and assumption used in analysis are of
applicable.
Shear force (t/m)
-200 100
0
-5
-5
-5
-10
-10
-10
-100
-20
-25
-30
-50
-100
-15
-20
Top-down
Bottom-up
20
40
60
Depth (m)
-15
100
Depth (m)
Depth (m)
200
50
-15
-20
-25
Top-down
Bottom-up
-30
-25
-30
334
Top-down
Bottom-up
80
10
20
30
40
Construction Stage
1. Excavate to -1.70 m
2. Install 1st bracing and Exc. to
-4.30 m
3. Construct B1 and remove
1st bracing
4. Excavate to -11.80 m and
construct B3
5. Excavate to -19.10 m
1-P
5
3-A
1-A
3-P
2-A
2-P
10
Depth, m.
4-A
4-P
5-A
15
20
25
30
A-Actual Movement
P-Predicted movement
335
REFERENCES
Arz P. 1989. Foundations of the Ko-Galerie in Dusseldorf Using Top-down Building
Technologies, Proceedings of the International Conference on Piling and Deep
Foundations, London, 15-18 May 1989 : 185-192. Rotterdam: Balkema.
Crawley J.D. & Stones C. S. 1996. Westminister Station Deep Foundation and Top-Down
Construction in Central London, Geotechnical Aspects of Underground Construction in
Soft Ground, London : 93-97. Rotterdam : Balkema.
Findlay J. D., Wren G.E. 1989. Review of the Methods Used to Construct Large Diameter
Bored Piles for Top Down Construction. Proceedings of the International Conference
on Piling and Deep Foundations, London, 15-18 May 1989 : 199-210. Rotterdam:
Balkema.
Finsted J. A. 1991. Royal Christiana Hotel : Basement with Permanent Sheet Pile Wall, Upand-down Method, 4th International DFI Conference : 387-392. Rotterdam: Balkema.
Hollingsworth J.R. 1991.
Diaphragm Walls, Load Bearing Piles and Piled Soil
Reinforcement for a Deep Top-down Basement Construction, 4th International DFI
Conference : 79-84. Rotterdam : Balkema.
Manoharn S. & Aye Z. Z. (1994) , Bored Pile with King-post and Secant Pile Wall
Construction for Top-Down Method Central Sukhothai Hotel Haddyai, Latest
Technology in Construction Technology Conference, Bangkok, Thailand
Thasnanipan N., Maung A. W. & Z. Z. Aye, (2000) Practical Installation of Stanchions for
Top-Down Construction in Bangkok Subsoil, Year 2000 Geotechnics, Geotechnical
Engineering Conference, The Imperial Queens Park Hotel, Bangkok, Thailand, 27-30
November 2000
Yong K.S., Tsen C.N. & Tang S.K. 1998. Performance of a Deep Excavation with Top-down
Construction, 13th Southeast Asian Geotechnical Conference, 16-20 November 1998.
Taipei, Taiwan ROC : 587-593
336
337
ABSTRACT
In July 2005, an earth retaining structure with diaphragm wall was completed in the vicinity of
Bangkoks first subway system, the MRTA Chaloem Ratchamonkhon Line. Diaphragm wall design
analysis and ground movements associated with diaphragm wall construction were reviewed. The
review was carried out in accordance with technical requirements for engineering works within the
specified protection zone of MRTA structures. Preliminary diaphragm wall analyses indicated that
lateral movements of the wall should not exceed 26.54mm. A 6.0mm maximum movement allowance
is specified for MRTA structures. The construction work was undertaken in compliance with
technical requirements for engineering works within the specified protection zone of MRTA
structures. Two inclinometer tubes with 20.0m in length were installed in the ground between the
planned diaphragm wall and the south-bound tunnel. Surface settlements markers were also
established in line with the inclinometer tube location on the pavement. Ground movements were
monitored during diaphragm wall panel construction. Based on the monitoring results, the estimated
maximum ground movement at the tunnel location due to wall panel construction was less than
0.5mm, indicating no impact on the tunnels by diaphragm wall construction.
1. INTRODUCTION
Deep excavation work adjacent to existing structures have become a common construction activity in
most major cities as utilization of underground spaces, including underground car parks, basements,
mass transit subway stations and tunnels increase. With mass transit systems in place, properties
located along the commuter lines are considered the most favorable areas to be developed with
maximum utilization of areas available. In turn, deep basement construction adjacent to the existing
subway tunnels is also often necessary.
At present in Bangkok, such deep excavation work in the vicinity of the subway tunnels is
considered relatively uncommon compared to major cities in developed countries. It is anticipated that
this phenomenon will change in the near future. This paper presents an unprecedented case in
Thailand of deep excavation adjacent to a subway tunnel. The proposed hotel tower reported herein
was planned to be constructed with 2 basements using cast in-situ diaphragm wall located 7.8m to
9.6m away from the south-bound tunnel of the Mass Rapid Transit Authority, MRTA Chaloem
Ratchamonkhon Line. The main foundation for the superstructure consists of 66 bored piles (1.5m
diameter) and 7 barrettes (1.0x3.0m) embedded to depths of about 57.0m in the second sand layer of
Bangkok Suboil. For construction of basements and foundation mat of 3.5m in thickness, diaphragm
walls (0.8mx20m deep) with 2 levels of temporary bracing are planned as a retaining system for a
general excavation to -10.50m. The perimeter diaphragm wall is supported by 24 bored pile of 0.8m
in diameter. Due to the presence of the MRTA tunnels in the close vicinity of the project, a review
339
371
was carried out on the expected performance of the retaining system, with regards to technical
requirements for the engineering works within the protection zone of the MRTA.
In this paper, predicted diaphragm wall deflections and associated expected tunnel movements
are presented. Pre-established geotechnical instrumentation program and recommended contingency
measures are also described. Monitoring results of ground movement during different stages of
diaphragm wall panel construction is also reported.
2. SITE CONDITIONS
The project site is located on the eastern side of Asoke Road, Sukhumvit, Bangkok, Thailand. On the
eastern side are two one storey houses, 3 storey office building and open space car parking. The site is
flanked by a 12 storey office building on the northern boundary and a 5 storey residential building on
the southern boundary.
The MRTA twin tunnels with an outside diameter of 6.30m are located in front of the site about
15.0m below Asoke Road. Sound bound tunnel is adjacent to the site being 9.623m to 7.815m away
from the planned diaphragm wall. The layout plan of the site is presented in Figure 1.
340
372
occurred at depths of about 42.5m and 54.0m respectively in hard silty clay layers. A summary of
subsoil conditions obtained from borehole data is presented in Table 1.1.
Table 1. Summary of Subsoil Conditions
Depth below
Description of Material
Ground (m)
0-2.0
Pavement/top soil
2.0-3.0
Soft Clay 1
3.0-12.0
Soft Clay 2
12.0-15.0
Medium Stiff Clay
15.0-17.0
Stiff Clay
17.0-19.5
Stiff to Very Stiff Clay
19.5-22.0
Medium Dense Sand
22.0-35.0
Very Stiff Clay
35.0-42.5
Stiff Clay
42.5-50.0
Dense Sand
50.0-54.0
Hard Clay/ Silty Clay
54.0-66.0
Dense to Very Dense Sand
66.0-80.0*
Hard Silty Clay
Note:* at the end of borehole
Thickness
(m)
2.0
1.0
9.0
3.0
2.0
5.0
2.5
13.0
7.5
7.5
4.0
12.0
Su (UC)
(t/m2)
2.0
1.2
3.5
5.0
12.0
20.0
12.0
29.9
-
SPT N
(blow/ft)
-
18
20
30
18
>52
45
>60
>45
341
373
342
374
Based on the primary analysis with WALLAP, 0.8m thick diaphragm wall embedded to a depth of
20.0m with two levels of temporary bracing at -1.50m and 6.20m was required.
WALLAP has been used by the authors for analysis of braced excavations with diaphragm walls
and sheet piled walls in Bangkok subsoils and elsewhere. More than 12 projects have been completed
by the authors. Additionally 9 underground stations and a number of ventilation shafts of MRTA
southern part has been completed with diaphragm walls designed by using the program (Schulz C.
2001).
Prior to determination of tunnel movements using PLAXIS, the same basic model (without
foundation piles and tunnel) was used in analysis using both WALLAP and PLAXIS programs for a
comparison between analysis results to establish a correlation for further analysis using PLAXIS
program. The comparison of analyses indicated that the predicted maximum wall deflection computed
by PLAXIS is about 39.0mm which is close to the 43.0mm computed by WALLAP. Figure 4 shows
results of analysis from both WALLAP and PLAXIS programs.
-50
-100
-150
60
40
20
-20
0.00
-40
-5
-5
-5
-10
-10
-10
-15
Depth (m)
Depth (m)
Depth (m)
100
Displacement (m)
-15
-20
-20
Wallap
Plaxis
0.04
0.06
0.08
0.10
-15
-20
-25
-25
0.02
Wallap
Plaxis
-25
Wallap
Plaxis
Figure 4. Comparison of Diaphragm Wall Analysis Results from WALLAP and PLAXIS
5.1 Wall Deflection and Ground Movements
The characteristics of diaphragm wall movements in the completed projects in Bangkok have been
reviewed by Phienwej et al (1998). It was reported that in terms of the ratio of hmax /H, the typical
range of the maximum wall movement hmax fell within 0.3-0.8% of excavation depth H.
For the planned project reported herein, primarily predicted maximum wall movement of
34.00mm, about 0.31% of the excavation depth (11.0m) by WALLAP was considered in the
reasonable range and thus control of the wall deflection within the predicted range could be practically
achievable, with adequate lateral supports and proper construction sequence and time controls if there
is no existing subway tunnel nearby.
However, for calculation of lateral and vertical displacements of the ground, including those of
the existing MRTA tunnels, a two dimensional simulation is necessary and thus PLAXIS program was
selected. A number of computer simulations were carried out using the PLAXIS program to meet the
technical requirements, particularly tunnel displacement criteria.
343
375
1
B 1 11
1 st Temp. Bracing
B2
Note:
Excavate to -6.5m
Mat/Base Slab
10
Excavate to -1.8m
Excavate to -11.0m
10
Initially computer modeling, using PLAXIS to estimate the displacement of the tunnels without soil
improvement to the soft clay layer inside the excavation, indicated that tunnel displacement exceeded
the limit of 6.0mm specified for the MRTA structure or tracks.
A series of computer models with different wall configurations such as increased wall thickness
and embedment were carried out. It was found that the wall system did not significantly control the
displacement of the tunnels within the specified limit, but the expected tunnel movement is generally
governed by the wall deflection. Moreover, the computer modeling indicated that excavation for
installation of the 2nd bracing layer and subsequent removal of the bracing after completion of base
slab influenced the overall ground displacement and wall deflection, due to the presence of a thick soft
clay layer between at depths of 3.0m to 12.0m. To effectively reduce wall deflection and ground
displacement, improvement of the soft clay layer was considered necessary. We considered also that
the site conditions allowed the soft clay to be improved to the strength of stiff clay with deep cement
mixing inside the excavation zone close to the south-bound tunnel. The improve soil block could act
as a counterfort to the wall during installation of the 2nd bracing layer. Additionally the improved soil
block could also be used as a berm or contingency support for the wall during final excavation depth.
Predicted lateral and vertical displacements of the ground and tunnel movements are summarized
and presented in Table 2.
Table 2. Summary of Maximum Movements Computed by PLAXIS Program
Maximum Movement of
Maximum Movement of
ground (mm)
Tunnel (mm)
Model Type
Horizontal
Vertical @
Specified
Predicted
@ D-wall
ground level
Limit
Simple model without soil
improvement
Improved Soft Clay layer @3.013.5m, 5.0m wide inside
excavation.
40.57
38.22
6.88
<6.00
26.54
25.79
5.97
<6.00
344
376
Bangkok
Ref.
In this paper
Singapore
Hong Kong
Shanghai
Shanghai
Shanghai
London
Planned Project on
Asoke Road
Inland Revenue
Headquarter
Subsoil
Singapore
Yang et al
(1998)
Niu et al
(2003)
Chu et al
(2001)
Jianhang
(1998)
Higgins et al
(2001)
Although, general thickness of clay deposits vary with the projects, the nature of the work is
similar, it is noteworthy that deep excavation work was carried out in soft soils adjacent to existing
subway tunnels.
Table 4. Summary of Excavation Configurations
Max.
Case
Project Name
Excavation
No.
Depth (m)
A
B
C
D
Distance to
Outer Face of
Tunnel (m)
Depth to
Tunnel
Crown (m)
-18.0
16.0
11.0
-30.0
4.5
11.5
-18.5
<5.0
19.0-22.0
-23.067
12.9
6.959
-13.0
3.0
8.0
-11.0
7.8
15.0
-14
7.0
-9.0
1.0m to below
excavation
13.7
345
377
Wall Type
0.8mx20m
D-Wall
1.0mx24.5m
D-Wall
0.8+1.0mx35.0m
Secant pile wall
D-Wall
D-Wall
26m D-Wall
0.8x24.0m
D-Wall
1.0mx19.0m
Secant pile wall
Project Name
Planned Project
on Asoke Road
Inland Revenue
Headquarter
New Dhoby
Ghaut Station
Cheung Sha Wan
Gov. Office
People Park
Station
New World
Mansion
Hong Kong
Square
C
D
E
F
G
H
The George
Green
Cut&Cover
Excavation
Method
Bottom Up
2 level Strut +
improved soil berm
Top-down
Max. Wall
Deflection (mm)
Predicted
26.54
Actual
-
Predicted
5.97
Actual
-
Specified
6.0
30
25
11
15
17
15
<7@ track
18
20
Bottom Up
7 level Strut
Top-down
24
<25
<25
Bottom Up
5 level Strut
Bottom Up
35
38
<12
Bottom Up
& improved soil
berm + 3 level strut
Top-down
<40
<40
<15
-
11
<10
<10
<10
<10
12
Review of the above completed projects, with the exception of the planned project (Case A),
indicates that the specified limit of tunnel displacement ranges from 10mm to 20mm. Details of tunnel
lining and specified limits of the railway track movement of these projects were not specifically
reported. Only in Case No. C (Ref. Niu et al 2003), maximum movements of 7mm and 15mm were
recorded for both the railway track and tunnel respectively.
Based on the projects mentioned above, controlling the maximum movements of the MRTA
tunnel and railway track induced by the planned excavation for the project, within the specified limits
is possible. However the excavation work must be carried out by competent contractors with
contingency plans such as that outlined previously, with the geotechnical instrumentation and
monitoring mentioned in the following section as a minimum requirement.
5.3 Geotechnical Instrumentation and Monitoring
The following instrumentation is considered essential and monitoring must be carried out throughout
the basement construction period.
Inclinometer - 2 inclinometers in the ground between the tunnel and planned diaphragm wall and
(for diaphragm wall construction) 4 to 5 inclinometers in the diaphragm wall around the excavation.
Convergent Bolts & Tape Extensometer If necessary, adequate quantities of convergent bolts
may be installed on the tunnel segments to monitor the convergent movement with tape extensometer
at each construction stage throughout the basement excavation period.
Settlement Plates/markers A minimum of 4 settlement points on the ground across the tunnels
needs to be installed in line with each inclinometer location and surveyed at each construction stage
throughout the construction period.
Survey Movement of tracks must be surveyed at each construction stage throughout the
basement excavation period.
Contingency Plan and Actions - Since the predicted displacement of the tunnels is very close to
the specified limits, monitoring of adjacent structures and ground movements during the staged
346
378
excavation is necessary, with checking against the predicted movements at every stage of construction.
A contingency plan with trigger values of displacements being based on the predicted values must be
prepared and necessary action must be taken immediately if the measured movements of diaphragm
wall and tunnels exceed the trigger values set. It was suggested that a contingency plan including, but
not limited to, the following be prepared and carried out accordingly when required.
Preloading of struts as necessary
Localized excavation and monitoring
Provision of an additional bracing layer
Speeding up the construction.
6. SUMMARY OF ASSESSMENT
An assessment of works associated with bored piling and diaphragm wall work to meet Technical
Requirements for Engineering Works within the Protection Zone of the MRTA Chaloem
Ratchamonkhon Line is summarized in the table below.
Table 6. Summary of Assessment of Basement Excavation with Braced Diaphragm Wall
Specified
Item
Description
Provision
Assessment/Remarks
Requirement
1
2
2.1
Diaphragm Wall
Bored Piling
Bracing and Excavation
Calculations
2.1.1
Engineering Work in
Zone B
Surcharge at ground level
2.1.2
Surcharge on tunnel
2.1.3
Differential Movement
2.1.4
2.1.5
2.1.6
Piling
2.1.7
2.1.8
2.1.9
2.1.10
2.1.11
Site investigation
boreholes for location of
MRTA structure
Soil Improvement
Method Statements
Signed with
Chartered Engineer
347
379
Yes
Yes
outlined
Yes
Conformed
15kPa
(1.5t/m2)
15kPa
(1.5t/m2)
< 6mm
> 6m or (7) pile
diameter
Yes
> 10m
Yes
~ 11.0m with
braced D-Wall.
Instrumentation
program
outlined
-
Approval is obtained.
Documents
prepared
submitted for approval
&
Documents
prepared
&
submitted for approval
The site is about 8m away
from the MRTA structure.
It will be inside the perimeter
D-wall as analysed.
Moreover we also concluded that the structural design of the diaphragm wall as analyzed and designed
with the WALLAP program was adequate for the planned excavation work. However the maximum
deflection of the wall adjacent to the existing tunnels had to be reduced to 20mm, to limit the
displacement of the tunnel within the specified displacement as indicated by computer modeling with
PLAXIS program. Additionally, soft clay adjacent to the south-bound tunnel inside the excavation at
depths between 3.0m and 13.5m must be treated to improve the shear strength of the soil to that of stiff
clay layer (about 10t/m2). We intended the soil improvement to minimize the wall movement and acts
as a contingency measure in excavation. The observational approach is strongly recommended for a
deep excavation in the proximity of exiting tunnels.
7. DIAPHRAGM WALL CONSTRUCTION
A review assessment of ground movements induced by diaphragm walling was also carried out during
diaphragm wall design and analysis. Ground movements associated with diaphragm wall trenching in
Bangkok clay has been studied and reported (Thasnanipan et al, 2004). It was reported that an
inclinometer (24m long) was installed 1.0m away from the trial trench face for monitoring of soil
movement during and after trenching. Additionally 6 surface settlement points with 2.0m spacing
were also installed and monitored. The trial trench 0.6x4.5x18.0m was excavated under polymer
slurry. The monitoring results indicated that vertical ground settlement did not extend beyond 8.0m
from the trench face. The maximum vertical settlement of 9mm was found to occur at about 2.0m
away from the trench face. The inclinometer readings which were recorded 1.0m away from the
trench face indicated that the maximum lateral soil movement of 5.8mm occurred at the depth of about
3.5m below the ground. At 15.0m depth, the lateral movement of soil 1.0m away from the trench was
about 1.0mm after 12 hours of trench excavation. Based on the above information, for the diaphragm
wall construction adjacent to the existing MRTA tunnels located about 7.8m away from the outer face
of planned diaphragm wall of the project site and at depths of about 15.0m below ground level, the
following statements were made;
1. Vertical displacement of ground due to diaphragm wall trenching was expected to be within
8.0m from the trench face and thus not affect the tunnels which were located beyond 7.8m
from the trenching.
2. Lateral soil displacement within 1.0m from the trench face at a depth of 15.0m depth was
about 1.0mm. It was expected that the displacement would decreasing distance from the
trench face. At the tunnel location, no lateral soil displacement was expected as the southbound tunnel was about 8.0m from the trench face.
3. For trench stability, bentonite slurry was used instead of polymer slurry.
Diaphragm wall construction was carried out with a conventional rope-suspended mechanical
grab under bentonite slurry in July 2005. Two inclinometer tubes were installed between the southbound tunnel and the planned diaphragm wall, about 4.0m from the outer face. Since the subway
tunnels were beneath Asoke Road, settlement marks were established on the pavement in line with the
inclinometer location and crossing the tunnel alignment. Monitoring of ground movements was
carried out during construction of diaphragm wall panels nearest to the inclinometer tubes. Figure 8
shows the layout of inclinometer and settlement marks. For construction of bored piles, 15m long
temporary casing was used. The piles located within protection zone B were constructed after
completion of adjacent diaphragm wall panels to protect from the ground vibration induced by
temporary casing installation and extraction.
7.1 Soil Movement during Diaphragm Wall Construction
Soil movement during diaphragm wall panel construction were monitored (Table 7). Results of
settlement survey at the settlement marks indicated no vertical movements of the ground.
348
380
Table 7. Summary of Monitoring Results (I-6 & I-7): Soil Movements at Inclinometer Locations
Movement @ 15.0m depth
Construction Activities
(mm)
Remarks
I-6
I-7
Top 2.0m in depth was
D-Wall panel excavation to -10.0m
-0.87
-0.40
protected by concrete
D-Wall panel excavation to -20.0m
1.04
-0.81
guide walls.
After de-sanding
0.12
-0.38
After concrete pouring
-1.91
-2.18
24hrs after concrete pouring
-2.34
-1.62
36/48hrs after concrete pouring
-1.13
-2.55
Note: - movement towards tunnel (opposite to direction of excavation)
INCLINOMETER I-7 (A AXIS)
-15
-10
-5
10
15
-20
20
10
10
10
15
20
Depth, m.
20
20
25
nel
I-6
I-7
9.625m
15
Tun
MRTA Southbound
7.815m
15
25
-5
Depth, m.
-10
-15
I-4
ilding
LEGEND
Inclinometer
Settlement Point
D-Wall with Pile Leg
D-Wall with Barrette Leg
Barrette
12 Storey O
I-3
The following conclusions were made based on the above monitoring results.
1. No vertical displacement was observed at the surface settlement points; vertical displacement
of ground due to diaphragm wall trenching seemed to be within 2.0m from the trench face and
would not affect the tunnels which were located 7.8m beyond the trenching.
2. Maximum lateral soil displacement at 4.0m from the trench face at 15.0m depth was about
1.0mm towards excavation. It was expected that the displacement would decrease with
distance increasing from the trench face. At the tunnel location, lateral soil displacement was
estimated to be less than 0.5mm based on the extrapolation of displacement data.
3. After concrete casting of the panels, lateral soil movements were found to be towards the
tunnels, possibly from pressure of wet concrete. Maximum movement at depth 15.0m at the
inclinometer location was about 2.18mm after concrete pouring. After 36hrs of concrete
casting, the maximum movement observed was about 2.55mm. At the tunnel location, lateral
soil displacement was estimated to be less than 1.6mm based on the extrapolation of
displacement data.
4. After the diaphragm wall panel was completed, residual movement of the soil towards the
tunnels was observed. Due to the direction of this movement, it could be excluded from
tunnel movement measurements induced by diaphragm wall deflection during basement
excavation work.
349
381
8. CONCLUSION
At the time of drafting this paper, soil improvement with soil-cement columns was completed and
excavation work has commenced with specified instrumentation and monitoring programs. An
independent third party consultant has been appointed by the main contractor to review, inspect and
supervise the excavation work.
Diaphragm wall and foundation bored pile construction was completed, in compliance with
technical requirements for engineering work within the MRTA protection zone. Review and
assessment of the deep excavation with diaphragm wall adjacent to the existing tunnels indicated that
the project is feasible with adequate monitoring and contingency plans as outlined.
It is also concluded that diaphragm wall construction in close vicinity of existing subway tunnels
was successfully completed with adequate instrumentation and monitoring.
Further research is recommended on the actual performance of the diaphragm wall when
basement construction data and complete monitoring results are available.
REFERENCES
CIRIA Report 185 (1999), The observational method in ground engineering: Principles and
applications, CIRIA, 6 Storeys Gate, Westminster, London, UK.
Chapman T. J. P., Nicholson D. P and Luby D. (2001), Use of the observational method for the
construction of piles next to tunnels, Proceedings of the International conference on Response
of Buildings to Excavation Induced Ground Movements held at Imperial College, London, UK.,
July 17-18, 2001, pp 213-223.
Chu R. P. K., Yau P. K. F., Leung D. H. K., and Mok K. H. (2001), Integrate approach for deep
excavation along soft ground (MRTC) tunnels, Proceedings of the Third International
Conference on Soft Soil Engineering, Hong Kong, December 6-8, 2001, pp 391-396.
Higgins K G, Paterson J., Moriaty J., Potts D. M., and Jardine R. J. (2001), The effect of an
excavation in a stiff fissured clay on existing tunnels in close proximity, Proceedings of the
International Conference on Response of Buildings to Excavation Induced Ground Movements
held at Imperial College, London, UK., July 17-18, 2001, pp 313-324.
Jianhang L. (1998), Design and construction of excavation for Shanghai Metro, Big Digs Around
the World, Proceedings of Sessions of Geo-Congress 98, Geotechnical Special Publication No.
86, Boston, Massachusetts, USA, October 18-21, 1998, pp 103-123.
Mair R. J., Taylor R. N., and Bracegirdle A., (1993), Subsurface settlement profiles above tunnels in
clays, Geotechnique 43, No. 2, pp 315-320.
Niu J. X.,Wong I. H., and Makino M., (2003), Effects of deep excavation on adjacent transit tunnels
and station, Proceedings of the Twelfth Asian Regional Conference on Soil Mechanics and
Geotechnical Engineering, Singapore, August 4-8, 2003, pp 883-886.
Phienwej N., Hock G. C., and Balasubramnaiam A. B., (1998), Ground movements in deep
excavations with concrete diaphragm walls in Bangkok soils, Proceedings of the Thirteenth
Southeast Asian Geotechnical Conference, Taipei, Taiwan ROC, November 16-20, 1998, pp
637-642.
Schulz C., (2001), Geotechnical challenges in the construction of Thailands first subway,
Proceedings of the Fourteenth Southeast Asian Geotechnical Conference, Hong Kong,
December10-14, 2001, pp 413-418.
Thasnanipan, N., Maung, A. W., Boonyarak, T., and Aye, Z. Z. (2004), Stability of a trial trench
excavated under polymer slurry in Bangkok soft clay, 15th Southeast Asian Geotechnical
Conference, Bangkok, Thailand, November 22-26, 2004.
Yang K. S., Tsen C. N., and Tang S. K., (1998), Performance of a deep excavation with top-down
construction, Proceedings of the Thirteenth Southeast Asian Geotechnical Conference, Taipei,
Taiwan ROC, November 16-20, 1998, pp 587-593.
350
382
International Symposium on
Tunnelling for Urban
Development
(IS-Pattaya 2007)
351
in
Thayanan
353
Geotechnical
Risk Management
Observational Method
Identify Risk
Value Engineering
Analysed Degree
of Risk
Minimize
& Control
Construction Control
Monitoring & Review
Trigger Criteria
Exceeds
Yes
No
Implement
Planned Action
Figure 1. The elements of observational method and risk management with integration of value
engineering.
4. VALUE ENGINEERING AND APPLICATION OF OM IN BASEMENT EXCAVATION
WITH BUTTRESS-SUPPORT THIN DIAPHRAGM WALL
This project demonstrated the benefits of value engineering option powered by effective application of
observational method in historically significant area of Bangkok. The project is a two-level
underground car park located in the center of Rattanakosin Island, the heart of an old established,
historically and culturally significant area of Bangkok. The project owner, Bangkok Metropolitan
Authority (BMA) awarded the semi-turnkey basis construction contract Lam Kon Muang
Underground Car Park to SEAFCO Co., Ltd. as a contractor. The contract consists of 3 major scope
of works: (1) Construction of building foundation and retaining structure - diaphragm wall, barrette
and bored piles (2) Excavation works including temporary bracing design and installation (3)
Construction of the entire two-level underground car park building having car park area of 18,552 m2
and roof-level park of 10,936m2 plus cut-and-cover tunnel, underpass access to the City Hall.
Geotechnical aspects highlighting the application of observational method and performance of
buttress-support diaphragm wall of 0.60 m width for two-level underground car park building is
discussed in this paper.
5. PROJECT REQUIREMENT AND MAJOR CONSTRAINTS
Since there is a limited availability of car parking space in the surrounding congested neighborhood
and the project site was being used as a grade-level car parking space prior to the award of the
contract, the key requirement was to construct the underground car park in two phases to construct
Phase 1 while leaving space for car parking in Phase 2, and to utilize semi-finished underground car
park of Phase 1 during construction of Phase 2. This requirement posed the need of temporary
retaining wall between Phase 1 and 2.
354
OPENING
SIRIPONG ROAD
OPENING
OPENING
OPENING
SHOP-HOUSES
SHOP-HOUSES
DINGSOR ROAD
OPENING
SHOP-HOUSES
OPENING
MAHUNNOP ROAD
OPENING
OPENING
355
D IA P H R A G M W A L L
RC BUTTRESS
BARRETTE
W ALE BEAM
0 .3 0
T IE B E A M
P IL E C A P
SLA B
(a)
I-5
N O R T H D -W A L L
0.00
CAPPING
BEAM
RC BUTTRESS
G.W.L
S H E E T PIL E
EAST D-WALL
WEST D-WALL
PH A S E 2
I-6
2
SOFT CLAY
-9m
124 m
I-4
S ee d etails in (b )
I-3
PH A S E 1
S O U T H D -W A L L
-12m
I-1
PILE CAP
-5.60 (B2)
TIE
BEAM
2
WALE
BEAM
SOFT CLAY
DIAPHRAGM
WALL (tip=-16m)
MEDIUM CLAY
STIFF CLAY
-15m
-16m
-20m.
I-2
78 m
FOUNDATION PILES
DIA. 600mm (tip=-20m)
BARRETTE
(tip=-20m)
-20m.
(c)
(b)
Figure 3. (a) Plan of diaphragm wall and buttress (b) layout of diaphragm wall and piles (c) sectional
view of the structures
356
10
15
20
Soft clay
35
Stiff clay
Very Stiff clay
150
20
40
60
SPT N-Value (blows / ft)
200
5.00
15.00
20.00
25.00
Medium Dense
Sand
30.00
35.00
40.00
40
45
100
25
30
50
0.00
0
5
Dense sand
45.00
50.00
50
Su BH-1
Su BH-3
SPT BH-1
SPT BH-3
80
Su BH-2
Design (Su)
SPT BH-2
Design (SPT)
HORIZONTAL STRUT
RAKING STRUT
D-WALL
BERM
D-WALL
BARRETTE
-16m
SLAB
BORED PILE
-20m
Figure 5. Tender stage bracing system diaphragm wall was designed with soil-berm and 2 struts
support (horizontal bracing and raker)
357
HORIZONTAL STRUT
SLAB
HORIZONTAL STRUT
BERM
RAKING STRUT
D-WALL
SHEET PILE
BARRETTE
-16m
SLAB
-16m
-20m
-20m
-14m
BORED PILE
358
Construction Control
Reassessment
Process
No
Implement
Planned Action
Yes
20
NORMAL
40
60
ALARM
80
100
ACTION
MOST
PROBABLE
PREDICTION
Depth, m.
6
MOST
UNFAVORABLE
PREDICTION
8
10
12
14
16
18
20
Tender Stage
Prediction with buttress :
Alarm Trigger Level
Prediction without buttress
Action Trigger Level
Figure 8. Prediction of diaphragm wall performance in pre-construction stage with trigger criteria in
comparison with tender stage prediction
359
Minimum readings of 3 times a week when measured deflection values exceeded alert trigger
levels
Minimum reading 1 time a day when measured deflection values reached action trigger levels
As the most critical stage was predicted at the time horizontal temporary bracings were removed,
a full attention was paid to the inclinometer monitoring with the following special criteria and
frequencies.
First temporary strut removal was to carry out at the diaphragm wall panel where inclinometer
was located
Measured immediately before removal of temporary strut at the closest distance to the instrument.
Measured every 6-8 hours immediately after removing the first strut
Second strut to be removed must be the one located immediately adjacent to first strut which had
removed
Not to remove the second strut until inclinometer measured deflection values had stabilized
Not to remove more struts unless measured deflection values were stabilized and within alarm
trigger levels
In addition to inclinometer measurement, diaphragm wall movement was also monitored by the
survey points strategically marked on the wall panels. Ground settlement and surface cracks behind
the diaphragm wall were also visually checked by the construction team as daily basic.
360
20
40
60
80
ALARM
NORMAL
100
ACTION
2
4
MOST
UNFAVORABLE
PREDICTION
Depth, m.
6
8
Stage 1
Stage 2
10
Stage 3
12
Stage 4
Stage 5
14
Tender Stage
16
18
Figure 9.
levels
Phase 1 East Wall-Monitored diaphragm wall deflection at different stages with trigger
Cum. Displacement , mm.
0
20
40
60
80
100
0
NORMAL
ACTION
ALARM
4
6
MOST UNFAVORABLE
PREDICTION
Depth, m.
8
10
12
Stage 1
Stage 2
Stage 3
Stage 4
14
16
18
20
Stage 5
Tender Stage
Alarm Trigger Level
Action Trigger Level
Prediction without buttress
Figure 10. Phase 1 South Wall - Monitored diaphragm wall deflection at different stages with trigger
levels
361
Excavate to 4m
Removal of berm
Figure 11. Phase 1 excavation work in progress with historical Buddhist temple Wat Suthat in
background (Phase 2 area was being used as car parking space)
13. OM IN PHASE 2 - MODIFICATION OF BRACING SYSTEM
Monitoring results of the Phase 1 excavation work provided an ample opportunity to review the
design assumption, fine tune the parameters used in the analysis of the diaphragm wall for the Phase 2
and made modification of construction sequence. The major modifications are: (1) Removal of
soil-berm at East and West diaphragm wall in shorter duration than that of Phase 1, and (2) Using
raking struts instead of horizontal strut for North diaphragm wall a shown in Figure 12.
362
HORIZONTAL STRUT
SLAB
COMPLETED PHASE 1
STRUCTURE
RAKING STRUT
SLAB
D-WALL
BERM
D-WALL
BARRETTE
-16m
-16m
-20m
-20m
EAST & WEST D-WALL
Figure 12.
BERM
Value
Engineering
Option
OM in Phase 2
Design & Plan
Modification of Design
Based on Actual Performance of Phase 1
Reassessment
Process
Construction Control
Monitoring & Review
Trigger Criteria
Exceeds
Yes
No
Implement
Planned Action
363
20
NORMAL
40
60
ALARM
80
100
ACTION
MOST PROBABLE PREDICTION
2
4
Depth, m.
6
MOST UNFAVORABLE
PREDICTION
8
Stage 1
10
Stage 2
12
Stage 3
Stage 4
14
Stage 5
16
18
20
Figure 14. Phase 2 East Wall - Monitored diaphragm wall deflection at different stages with trigger
levels
With assurance of diaphragm wall performance from monitoring results of Phase 1, original
plan of using horizontal struts for North diaphragm wall was modified by using raking struts instead.
As can be seen in Figure 15, deflection of North diaphragm wall (with raking strut support) is
significantly higher than that of East diaphragm wall (with horizontal strut support). The main reason
of larger movement of north diaphragm wall is due to the fact that it was supported only by the berm
for the long period (about 52 days) before completion of raking struts so that soil-berm became soften
during the long elapsed un-strutted period.
Table 4. Description of stages shown in Figure 14 & 15
Stage East Diaphragm wall
North Diaphragm wall
1
Excavate to 2.2m and installed
Excavate to 2.2m at d-wall, and to 6.6m with
temporary strut
sloping berm
2
Excavate to 4m
Installed raking strut
3
Excavate to 6.6m with berm
Removal of berm
4
Removal of berm
Removal of raker after completion of buttress
5
Removal of temporary strut after
completion of buttress
364
20
40
60
80
NORMAL
100
ALARM
120
140
ACTION
2
4
Depth, m.
6
MOST UNFAVORABLE
PREDICTION
8
10
12
14
16
18
Stage 1
Stage 2
Stage 3
Stage 4
Alarm Trigger Level
Action Trigger Level
Prediction without buttress
20
Figure 15. Phase 2 North Wall - Monitored diaphragm wall deflection at different stages with trigger
levels
Time-dependent deflection pattern due to softening and deformation of soft clay can be
observed in North diaphragm wall as illustrated in Figure 17. North diaphragm wall moved
progressively toward excavation before completion of raking struts (at 52 days) as can be seen in
Figure 17.
Figure 16. View of buttress-support diaphragm wall prior to temporary bracing removal
365
20
40
60
80
0
2
4
Depth, m.
6
8
10
12
14
16
18
0 days
30 days
52 day
56 days
74 days
Prediction
20
Figure 17. Phase 2 Time dependent wall deflection of North diaphragm wall diaphragm wall was
supported only by soil-berm for 52 days before completion of raker installation.
TEMPORARY WALER
BUTTRESS
DIAGONAL STRUT
DIAPHRAGM WALL
TEMPORARY KING-POST
CAPPING BEAM
RAKER
BERM
TEMPORARY
STEEL BEAM
PILE
CAP
TED
PLE
COM
B
SLA
366
Figure 19. View of raker and soil-berm support soil-berm was removed locally bay by bay
Figure 20. View of buttress-support diaphragm wall after removal of temporary bracing
367
IN
SUCCESSFUL
APPLICATION
OF
Outcome of a through desk study at post-tender stage provided an effective value engineering
option which offered significant cost and time saving for overall construction program. Effective and
good communications between the design team and construction crew played a key role in successful
application of observational method to completion of the project. Systematic monitoring program with
clear defined trigger criteria was also the important element in implementing the observational method.
This case study reveals that a thin permanent diaphragm wall coupled with effective design and
construction method supplemented by the observational method and robust monitoring program could
offer a logistically and financially attractive solution in construction of underground car park without
disturbing the environment in the prominent historical area of Bangkok.
18. REFERENCES
Clayton C. R. I., 2001. Managing Geotechnical Risk. Improving Productivity in UK Building and
Construction, Institute of Civil Engineers and Thosmas Telford Ltd. UK
Clough, G.W., and ORourke, T.D., 1990. Construction Induced Movements of In-situ Walls. ASCE
Geotechnical Special Publication No. 25, pp. 439-470
Clough C.W. and T.D. ORourke, 1990. Deep Excavation and Tunneling. 7th ICSME, Mexico City
Graftio H., 1936. Some Features in Connection with the Foundation of Svir 3 Hydro-electric Power
Development, Proceedings of the first international conference in Soil Mechanics, Cambridge,
Mass., 1, pp. 284-290
OReilly M.P and New B.M., 1982. Settlements above tunnels in United Kingdom their magnitude
and prediction. Tunneling 82, pp. 173-181, London, IMM
Peck R.B., 1969. Deep Excavation and Tunneling in Soft Ground. 7th ICSME, Mexico City, State of
the Art 3, 225-290
Peck, R. B., 1969. Advantages and limitations of the observational method in applied soil mechanics,
Geotechniques 19, No.2, pp. 171-187
Powderham, A. J., 1996. An overview of the observational method : development in cut and cover
and bored tunneling projects, The Observational Method in Geotechnical Engineering, The
institute of civil engineers, Thomas Telford Publishing, London, pp. 7-24
Zaw Zaw Aye, Dhiraj Karki and Christian Schulz, 2006. Ground Movement Prediction and Building
Damage Risk-Assessment for the Deep Excavations and Tunneling Works in Bangkok Subsoil,
Proceedings of the International Symposium on Underground Excavation and Tunneling, Urban
Tunnel Construction and Protection of Environment, EIT, Bangkok, Thailand, pp. 281-297
368
Thayanan Boonyarak
Hong Kong University of Science and Technology
369
ABSTRACT
Diaphragm wall support deep excavation works of some major projects including Bangkok first subway
project are presented in this paper. Available literatures related to diaphragm wall and deep excavation works
in Bangkok are summarized together with recent research works. Problems and difficulties in construction of
diaphragm walls and deep excavation works in early days are reported. The areas of development in
diaphragm wall construction and main factors contributed to these are also presented. An attempt is also made
to briefly discuss the future trend of diaphragm wall construction and deep excavation works in Bangkok. This
paper is intended to serve as a source of reference for the practitioners in the construction industry with regard
to the application of diaphragm walls in deep excavation works in urban area of Bangkok.
INTRODUCTION
As in other major cities, growing land price and need of underground space for commercial and infrastructure
developments necessitated deeper underground excavation works in Bangkok. Diaphragm wall as embedded
earth-retaining structure is one of the most suitable solutions to facilitate the deep excavation works in urban
area of the growing metropolis. The common thickness of diaphragm wall in Bangkok ranges from 0.80m to
1.20m. Though not very common, in some cases, thick diaphragm wall of 1.50m and thin diaphragm wall of
0.50 to 0.60m were also constructed. Toe depths of diaphragm walls are in the range of 16m to over 30m
depths depending on the final elevation of the excavation. This paper aims to provide the summaries of the
technical data on diaphragm wall construction and deep excavations in Bangkok with particular focus on the
progressive development in past decades. Literatures published throughout past 20 years are summarized
along with the recent research works. The information and data presented in this paper are based on the
authors personal experience, observation from other completed projects and from published literatures.
SUBSOIL AND PIEZOMETRIC PROFILES IN BANGKOK
Subsoil profile and the present piezometric drawdown condition of Bangkok are presented in Fig. 1 below. A
typical subsoil profile is relatively consistent in different localities in Bangkok. It is characterized by
alternating layers of clay and sand deposits as shown in the Fig. 1.
371
Geotechnical
Parameters
0
Bangkok Soft
Clay
400
600
10
Dense to Very
Dense Sand
(Second Sand)
SPT-N= 50-100
t = 21KN/m 3
40
50
e
Lin
50
ine
Hard Clay
tic L
40
30
SPT-N= 20-40
t = 20kN/m 3
ta
ros
Medium
Dense Sand
(First Sand)
wn
wdo
Dra
30
Hyd
Medium to
Stiff Clay
tric
me
iezo
20
60
200
Weathered Crust
P
ual
Act
Depth (m)
10
60
(Peck et. al. 1977) defined that deep excavations are those whose depths are deeper than 6m. Sheet
piles, contiguous-pile walls, secant pile walls and sinking caisson are alternative retaining structures available
in Bangkok for deep excavations. Prevailing subsoil (existence of very soft to soft clay) and ground water
condition are the main factors for using diaphragm walls for deep basement excavation in Bangkok. For most
of the deep excavation works in urban environment, advantages offered by diaphragm walls weigh more
favourably for both technical and economical reasons while other methods have distinct limitations. Major
advantages of diaphragm wall are listed below.
Water retainable
Rigid structure so that ground movement induced by basement excavation is less than other flexible
retaining wall
Vibration and noise generated from installation of diaphragm wall is less than other methods
372
CONCRETE
PULL OUT
GL
GUIDE WALL
WL
STOP-END TUBE
BENTONITE
REINFORCEMENT
FINISHED PANEL
PANEL EXCAVATION
BENTONITE
REINFORCEMENT
EXCAVATED PANEL
FINISHED PANEL
GUIDE WALL
EXCAVATED PANEL
GUIDE WALL
STOP-END TUBE
STAGE 1
EXCAVATION
STAGE 2
REINFORCEMENT
STAGE 3
CONCRETING
STAGE 4
WITHDRAW STOP-END TUBES
373
Excavation
Depth (m)
Year of
construction
7.00
18.50
17.20
20.00
15.60
15.50
14.00
12.70
1977
1985
1991
1992
1992
1992
1992
1994
Fig. 3 illustrates the embedded length of diaphragm wall in relation to the excavation depth of the
projects listed in Table 1. It is to be noted that except shallow excavation required for Bangkok Bank Head
Office, diaphragm wall embedded deeper into hard clay layer in all projects constructed in the early days. Fig.
4 shows the embedded length of diaphragm wall in relation to the excavation depth of the projects listed in
Table 2.
From 1991, with the booming construction industry, usage of diaphragm walls for deep basements
of the high-rise buildings in Bangkok has been significantly increased. In year 1997, due to the economic
crisis, with significant decline of property sector, diaphragm wall construction was concentrated only for
infrastructure projects.
Fig. 3, Diagram showing the excavation depths in relation to embedded length of diaphragm walls in early
days (1977 to 1994)
374
Fig. 4, Diagram showing the excavation depths in relation to embedded length of diaphragm walls from 1997
to 2008
Table 2, List of some diaphragm wall projects constructed from 1997 to 2008 in Bangkok (Basement
Excavations Deeper than 10m)
Diaphragm Wall Dimension (m)
Excavation
Year of
Project Name
Depth (m)
Construction
Thickness
Depth
Charoen Pump Station
Sathorn Pump Station
MWA GMC-7A
Bank of Thailand
Hampton Condominium
Central World Plaza
Boe Bae Bumrung Meung Plaza
Esplanade
Por Teck Tung Office
Noble Remix
Life@Sathorn
Royal Maneeya
Sathorn Square
Renaissance
The Sukhothai Residences
Bangsue Wastewater Treatment
Grand Rama 9 Square
MahaNakhon Hill & Tower
MahaNakhon Retail Cube
UBC III & EM2
0.80
0.80
0.80
0.80
0.80
1.00
0.80
0.80
0.80
0.80
0.80
1.00
0.80
20.00
20.00
21.00
20.00
20.00
18.00
24.00
18.00
16.00
20.00
18.50
30.00
21.00
16.50
16.20
16.00
15.20
12.20
9.00
19.00
10.00
8.00
13.00
10.50
1.00-1.20
1.20-1.50
1.00-1.50
0.6-0.80
0.80
0.80-1.00
20.00-22.0
24.70
22-25.00
16.00-18.0
22.0
18.0-22.0
17.80
15.50
20.15
15.40
18.10
8.00-18.00
1997
1997
2002
2003
2003
2004
2004
2005
2006
2007
2008
2005
2007
2008
2008
2009
2010
2011
2011
2011
375
m
Sil
o
Lu
mp
ini
Bo
nk
ai
Pet
cha
bu
ri
Su
kh
um
vit
Sir
iki
t
Sa
my
an
Hu
aL
am
po
ng
it
/m
IX
Ra
ma
am
ph
en
Ru
am
Th
iam
Pra
cha
rat
B
Su
thi
san
Ra
tch
ada
n
La
dP
rao
Ph
aho
lyo
thi
Su
e
Ba
ng
Ka
mp
hea
ng
Ph
et
Mo
Ch
it
Extensive application of diaphragm wall for deep excavations can be observed between 1997 and
2001 for the first Bangkok subway project where 18 deep stations and associated structure plus some sections
of cut-and-cover tunnels were constructed by diaphragm wall. (Phienwej et. al., 2006) discussed the difference
between the length of diaphragm wall to depth of excavation between two contracts of the first Bangkok
subway, Chaloemratchamongkhon Line. The authors cited that it is partly due to the difference in design
criteria adopted. Fig. 5 illustrates the embedded length of diaphragm wall in relation to the excavation depth of
MRT Stations. Excavation depth over 30m carried out in Silom Station set the deepest excavation ever done in
Bangkok subsoil.
Fig. 5- Diagram showing the excavation depths in relation to embedded length of diaphragm walls of 18
subway stations of the first Bangkok Mass Rapid Transit Project
DIAPHRAGM WALL CONSTRUCITON PROBLEMS IN THE EARLY DAYS
Basic but extensive problems were experienced in early stages of diaphragm wall construction as summarized
below.
376
Slurry management
Construction impact on
quality and performance
Quality control in
construction process
In some projects where headroom is limited, special diaphragm wall grabs and equipment were
employed. Fig. 6 shows the specially-designed diaphragm wall equipment used in the project with limited low
headroom.
Fig. 6, Specially designed baby-grab with short-boom for limited low-headroom area
7
377
Diaphragm wall is an ideal solution for deep circular shafts. Though alternative method such as
sinking caisson may offer cheaper direct cost, significant time saving and maximum safety can be achieved by
using diaphragm wall in construction of deep shafts. View of diaphragm wall support deep shaft is presented
in Fig. 7.
Application of top-down construction method in diaphragm wall support deep excavation works
More understanding on excavation induced ground movement and risk of damages to adjacent
structures
Application of observational method integrated with value engineering option and comprehensive
instrumentation program
378
Fig.8. Application of top-down method for deep excavation work in Bangkok (Thasnanipan et. al., 2006)
All 18 deep underground stations of the first Bangkok MRT Subway were constructed between 1997
and 2000 by top-down method using diaphragm walls as permanent structural support. Fig. 9 shows the view
of subway station construction with application of top-down method. Skeleton slabs provided large openings
for which offered logistically significant advantage in deep excavation works.
379
to predict both vertical and horizontal surface and subsurface ground movement based on the deflection
profile of diaphragm wall. Fig. 10 shows the proposed method for prediction of subsurface ground movement.
Sio
D-wall
DDoO=2.5H
= HW+ W E
W
Total deflected
shape volume, V O
HW
HE
Dy
Sub-surface settlement
trough volume, VTy
Settlement
influence zone
deflected volumn V y at depth (H w- Y)
Swy
Siy
SWO
4VO
DO
x
Sio SWO *
DO
D
DY Y * O
HW
VTY VY *
VTO
VO
Fig.10. Demonstration of subsurface settlement prediction from diaphragm wall deflection values proposed by
(Zaw Zaw Aye et. al., 2006)
Fig.11. Typical section of diaphragm wall support deep excavation adjacent to MRT tunnel showing
protection zone, (Thasnanipan et. al., 2006)
(Thasnanipan et. al. 2006) reported an unprecedented case on use of soil-cement columns as ground
improvement to minimize ground movement induced by diaphragm wall support deep excavation adjacent to
existing Bangkok MRT tunnels. The authors presented the technical requirement of the deep excavation work
in the protection zone of MRT tunnels along with actual monitoring results of similar projects in other parts of
the world. This integration of ground improvement application to diaphragm wall deep excavation works is
expected to be more popular in the future as need of basement facilities are increasing along the existing MRT
tunnels. The performance of diaphragm wall and impact on tunnels meeting all technical criteria requireed
imposed by the Metropolitan Rapid Transit Authority of Thailand (MRTA) was subsequently reported by
(Teparaksa et. al., 2006)
10
380
Geotechnical
Risk Management
Observational Method
Identify Risk
Value Engineering
Analysed Degree
of Risk
Minimize
& Control
Construction Control
Monitoring & Review
Trigger Criteria
Exceeds
Yes
No
Implement
Planned Action
381
Fig.13. View of thin diaphragm wall supported by buttress (Thasnanipan et. al., 2004)
12
382
The authors presented a good data set of diaphragm wall movement profile showing time-dependent
progressive deflection pattern due to softening and deformation of soft clay caused by delay in installation of
raker support as shown in Fig. 14. The authors demonstrated by comparing actual monitoring results with preestablish trigger levels contributed to the understanding of the condition of the excavation as work progressed.
This approach served as the basis to judge whether contingency actions are to be implemented. To ensure the
safety of the excavation, the contingency measures exercised upon diaphragm wall deflection reaching preset
trigger levels were reported by the authors.
The actual monitoring data of different type of instrumentation presented in above literatures served
as valuable information and technical references for all parties involved in diaphragm wall and deep
excavations industry.
20
40
60
80
0
2
4
Depth, m.
6
8
10
12
14
16
18
0 days
30 days
52 day
56 days
74 days
Prediction
20
Fig.14. Time dependent wall deflection of diaphragm wall diaphragm wall was supported only by soil-berm
for 52 days before completion of raker installation (Thasnanipan et. al., 2004)
OBSERVATION OF GROUNDWATER CONDITION IN RECENT PROJECTS
Recently, deep excavations deeper than 18.0m in depth at two projects for basement constructions being
5.25km apart in Bangkok subsoil encountered presence of groundwater after reaching about 17.5m. Subsoil
information obtained by soil boring in these projects indicated a series of stiff silty and sandy clay between
15m and 24m, overlying a dense sand layer. Construction progress was significantly affected by presence of
groundwater in silty clay. Fully saturated silty clay turned liquid when disturbed by excavation activities,
causing difficulties in casting a concrete blinding layer for foundations construction. Dewatering and ground
improvement to the subgrade layer below foundation mat and footings needed to be carried out. Bearing
capacity of disturbed silty clay with high water content is very low so that cobble size concrete blocks and
crushed rocks to be compacted in to the soil for improving the subgrade. Then a lean concrete blinding layer
was cast on the subgrade part by part while dewatering.
A general piezometric profile in Bangkok shown in Figure 1 indicates a drawdown at -20m. Additional
peizometric readings from the piezometers installed at depths in the range of 28.0m to 33.0m and at 40m from
other sites in Bangkok indicate that piezometrice levels are around -15.0m and -23.0m respectively.
Piezometers installed at depths 28.0m to 33.0m shows piezometric levels increase to -12.0m within six
months. However, the groundwater encountered in the above mentioned sites was considered to be perched
water in semi permeable soils layer being vertically cut off by diaphragm walls, with an assumption that the
groundwater level was reduced gradually by pumping out.
13
383
14
384
Pongrujikorn, T., (2006) Development and Use of Underground Strucutre as Underpass in Urban Area in
Thailand, Proceedings of the International Symposium on Underground Excavation and Tunneling, Urban
Tunnel Construction for Protection of Environment, 2-4 February 2006, Bangkok, Thailand, pp. 441-448
Teparaksa, W., Thasnanipan, N., Maung, A. W. and Tanseng, P. (1999), Lessons from the collapse during
construction of an inlet pumping station: Geotechnical instrumentation aspect, 5th International Symposium
on Field Measurements in Geomechanics, Singapore, p.p. 247-252.
Teparaksa, W., Thasananipan, N., and Tanseng, P. (1999), Analysis of Lateral Wall Movement for Deep
Braced Excavation of Bangkok Subsoils, Civil and Environmental Engineering Conference, Bangkok,
Thailand, p.p. II-67 to II-76.
Teparaksa W., Boonsong C., Submaneewong C., Wisuttipat N., (2006) MRTs Tunnel Deformation due to
Deep Basement Excavation in MRTs Protection Zone, Proceedings of the 11th National Convention on Civil
Engineering, 20-22 April 2006, Phuket, Thailand (in Thai), pp. GTE-095
Thasnanipan, N., Maung, A.W., Tanseng, P., Wei, S.H., (1998), Performance of a Braced Excavation in
Bangkok Clay, Diaphragm Wall Subject to Unbalanced Loading Conditions, Thirteenth Southeast Asian
Geotechnical Conference, Taipei, Taiwan, ROC, p.p.655-660.
Thasnanipan, N., Maung, A.W. and Ganeshan, B., (2000), Diaphragm Wall and Barrette Construction for
Thiam Ruam Mit Station Box, MRT Chaloem Ratchamongkhon Line, Bangkok, An International Conference
on Geotechnical & Geological Engineering, Melbourne, Australia, 19-24 November 2000, pp. 157
Tanseng P., Aye, Z. Z. and Submaneewong, C. (2001), Monitoring of Diaphragm Wall Displacement and
Associated Ground Movement, Braced Excavation Adjacent to Historical Building at the Bank of Chao
Phraya River, Proceedings of the Seventh National Convention on Civil Engineering, Bangkok, Thailand, pp.
GTE-53-60
Thasnanipan, N. , Aye, Z. Z. and Submaneewong, C. (2004), Construction of Diaphragm Wall Support
Underground Car Park in Historical Area of Bangkok Proceedings of Fifth International Conference on Case
Histories in Geotechnical Engineering, April 13-17 2004, New York, U.S.A. pp. 5.66
Thasnanipan, N. , Aye, Z. Z., Submaneewong, C. and Boonyarak, T. (2006) Application of Top-down
Construction Method for Deep Excavations in Urban Area of Bangkok, Proceedings of the International
Symposium on Underground Excavation and Tunneling, Urban Tunnel Construction for Protection of
Environment, 2-4 February 2006, Bangkok, Thailand, pp. 383-396
Thasnanipan, N., Maung, A.W., Aye, Z. Z., Submaneewong, C. and Boonyarak, T. (2006) Construction of
diaphragm wall for basement excavation adjacent to tunnels in Bangkok subsoil, Proceedings of the
International Symposium on Underground Excavation and Tunneling, Urban Tunnel Construction for
Protection of Environment, 2-4 February 2006, Bangkok, Thailand, pp. 371-382
Zaw Zaw Aye , Dhiraj Karki and Christian Schulz [2006]. Ground Movement Prediction and Building
Damage Risk-Assessment for the Deep Excavations and Tunneling Works in Bangkok Subsoil, Proceedings of
the International Symposium on Underground Excavation and Tunneling, Urban Tunnel Construction and
Protection of Environment, EIT, Bangkok, Thailand, , pp. 281-297
15
385
Thayanan Boonyarak
Hong Kong University of Science and Technology
387
Diaphragm wall has been used as permanent retaining wall for a vehicle underpass at major
intersection in urban area of Bangkok besides deep basement structures of high-rise buildings,
subway stations, deep shafts and other forms of underground structures,. This paper presents the
key technical features of recently completed vehicle underpass along one of the busiest roads in
Bangkok. The design aspects of earth-retaining structure integrated with top-down construction
method are reported. Predicted and measured deflections of diaphragm wall at different stages of
construction are presented. Practical construction method adopted under the existing flyover is
highlighted. Difficulties encountered during the construction are briefly described. This project
marked the first application of post-tension roof slabs along with top-down construction
technique for vehicle underpass construction by cut-and-cover method in Thailand.
1.
Introduction
To combat appalling traffic congestion, Bangkok Metropolitan Authority has been implementing
various measures in both urban and sub-urban areas. Flyovers are frequently used to improve the
traffic flow along the road at many major intersections. Though underpass is not commonly
used, it is the only solution in some critical traffic jam areas. The first underpass in the form of
depressed-road for rail-road junction was believed to be constructed about 35 years ago at
Bangsue, northern outskirt of Bangkok. Several years later, vehicle underpass was constructed
using cast-in-place diaphragm wall by Bangkok Metropolitan Authority (BMA) at Din Daeng
intersection in 1994. Since then more than 20 underpasses have been constructed by BMA and
other agencies in Bangkok and other major cities in the country.
This paper presents the design and construction of recently completed vehicle underpass along
one of the busiest roads in Bangkok. The presenting project in this paper demonstrated the
effective use of underground space in congestive urban areas of Bangkok and exemplified good
solutions for environmental preservation.
2.
The project works involved construction of a vehicle-underpass and associated utility diversion
and road expansion at one of the major intersections in the eastern part of Bangkok. Figure 1
shows the alignment and location of the underpass overlaid on aerial photo of the site (modified
from GoogleEarth). Four-lane underpass was to construct in the form of 758 m long cut-andcover tunnel along six-lanes existing Srinakarin Road. As can be seen in the figure, at the
intersection, tunnel section of underpass was to construct under existing flyover of Udomsuk
Road.
389
As the main six-lanes Srinakarin Road is one of the major roads linking eastern parts and inner
Bangkok, traffic density along this road is high. Presence of two major shopping malls in the
close proximity to the intersection is also another factor contributed to congestive traffic
condition in the area.
Location of the project in the heavy traffic area and need of construction under the existing
flyover with limited headroom therefore posed major constraints, which called for the need of
careful consideration in establishing the design principles and sequence of construction. As the
construction is to be carried out along the major public road, ground movement induced by cutand-cover tunnel excavation must be minimized.
Srinakarin Rd
Udomsuk Rd
Flyover
Sub-soil Condition
Similar to other localities in Bangkok a typical subsoil profile at the site is characterized by the
alternating layers of clay and sand deposits as shown in Figure2 . Undrained shear strength (Su)
and SPT N-value obtained from 5 SI boreholes were plotted and design line was derived as
depicted in Figure 2. Typical subsoil profile at the site is characterized by thick Bangkok soft
clay layer at the top followed by thin layer of medium clay underlying by alternative of stiff clay
and dense sand layers. Undrained shear strength of soft clay is obtained by using unconfined
compressive strength test from Shelby tube sample. In stiff to hard clay layer, correlation of
undrained shear strength with SPT N-value is adopted where undrained shear strength is equals
to 6.85N (kPa) for high plasticity clay (Sambhandaraksa & Pitupakorn. 1985). Angle of internal
friction () of dense sand is estimated to be 32 by using SPT correlation (Peck et al., 1974).The
design soil parameters are tabulated in Table 1.
390
1
0
0.00
Fill
5.00
10
15
20
25
30
35
40
45
50
Soft clay
10.00
15.00
20.00
Very stiff
clay
25.00
30.00
Dense sand
35.00
Very stiff to
hardclay
40.00
45.00
50.00
20
40
60
80
Su BH-2
Su BH-4
Design Su
SPT BH-2
SPT BH-4
Design (SPT)
t
(kN/m3)
18.5
16.5
17.5
19.0
19.0
Su
(kPa)
25
17
22
40
80
(degree)
0
0
0
0
0
20-25
19.5
120
Hard clay
25-27
20.0
180
Dense sand
27-32
20.0
32
Hard clay
32-40
20.0
180
40-45
20.0
32
391
4.
Review of the practical construction method was undertaken by the contractors in-house design
team. Rigorous attention to detail of the design concept and constructability was made in the preconstruction discussions among the client, consultants, design engineers and construction team.
Original tender called for the conventional construction method to complete the excavation to
final excavation depth and construct the roof-slab in the tunnel section of the underpass by using
precast pre-stressed concrete panels. Installation of 2.5m x 18.8m heavy precast panels
underneath the existing flyover was considered difficult and high risk involved. After reviewing
different options with consideration of the constraints imposed on site and constructability, topdown construction with post-tension slabs as roof-slab of the tunnel section was selected.
4.1 Numerical analysis for diaphragm wall design
Figure 3 illustrates an example of finite element mesh of deep approach with sump pit. In other
zone, basic geometry of the mesh follows that of excavation depth, wall depth and construction
sequence of each zone. Numerical analyses are carried out by using PLAXIS V7.2 (Brinkgreve
and Vermeer, 1998) finite element program. Plane strain total stress analyses using elasto-plastic
with Mohr-Coulomb failure criterion constitutive model are adopted. Undrained shear strength
of clay (Su) and internal friction angle of sand () are selected according to subsoil properties as
previously discussed. Youngs modulus ratio (Eu/Su) of each clay ranges from 250 to 750 which
is estimated based on expected shear strain of diaphragm wall. Boundary condition consists of
roller support applied at both vertical sides and pin support applied at the bottom of the mesh.
Numerical procedure follows the construction sequence in the field conditions. The primary
objective of numerical analysis is to verify structural capacity and overall stability during
construction. It should be noted that time dependent behavior of clay is not simulated.
Depth (m)
10
25
45
Figure 3 Finite element mesh of deep approach with sump pit
392
5.
Figure 4 shows the diaphragm walls, bored piles and barrettes layout plan. Diaphragm wall was
designed as earth-retaining wall for the entire section of the underpass. Diaphragm wall having
800mm thick founded at 25m below ground level (B.G.L) was constructed in three phases. Both
Phase 1 (north section) and Phase 2 (south section) were constructed in two stages (different
working stages for east and west diaphragm walls) to meet the traffic diversion requirement.
North section of the underpass diaphragm wall was constructed in Phase 1 in the initial stage of
the project. In Phase 2, south section of diaphragm wall was constructed prior to construction of
cross-wall for a deep sump-pit - diaphragm wall with 6m deep cut-off-level perpendicular to
longitudinal alignment of the main underpass diaphragm wall.
Diaphragm wall
0.8m x 25m
Centerline of
Udomsuk Rd Flyover
Phase 1
Phase 2
Phase 3
(under flyover)
Note: only diaphragm wall in tunnel zone is shown for clarity
Figure 4 Diaphragm wall, bored pile and barrette layout plan of vehicle underpass
As the tunnel section of the underpass at the intersection was to be constructed under limited
headroom due to the presence of existing flyover, careful planning was needed for Phase 3
diaphragm wall construction. Main factors were the limited time available for traffic diversion at
the intersection and the need of special equipment to practically construct the diaphragm wall
under the flyover where headroom was only 6m. Specially-designed mechanical grab was used
to construct the diaphragm wall in this low-headroom section as shown in Figure 5. Another
major challenge involved in construction of diaphragm wall under the existing flyover was the
obstruction of existing water supply pipe at 8m below ground level along the diaphragm wall
alignment. Removing the pipe buried 8m below ground level by open-cut or sheet-pile supported
excavation option was considered time consuming, unpractical as well as risky, taking the
consequences involved into account (unpractical and risky to have 8m open-cut excavation in
soft clay, unpractical to install 16m deep sheet pile low headroom. After reviewing different
options to remove the obstructed water supply pipe, decision was made to remove the pipe by
sending a man inside the pipe - to cut the obstructed part in smaller pieces and close the pipe to
stop the flow of bentonite into the pipe during diaphragm wall construction. Risk assessment and
safety measures with contingency plan were made before actual pipe removal was done. The
obstructed section of the buried pipe was successfully removed.
393
394
6.
Figure 7 shows the plan of cut-and-cover tunnel constructed by using top-down method
integrated with post-tension slab. Total length of tunnel zone is approximately 180 m along the
longitudinal profile of underpass or about 25% of overall underpass length.
As discussed in the previous section, top-down construction requires modifications from the
original design. Instead of using temporary prop to support the diaphragm wall during
excavation of tunnel section, roof-slab was used as temporary support. Four openings were
provided at an evenly spacing of about 40 m for access of soil excavation underneath the roofslab.
Post-tension
roof slab
y40 m
y40 m
Slab opening
during construction
Figure 7 Plan view of tunnel zone showing post-tension roof slab constructed prior to
excavation and openings for excavation works
Construction sequences of tunnel zone are shown in Figure 8. Major construction activities in
each stage are given as follows.
Stage 1: Construct diaphragm wall and bored pile with embedded temporary stanchion
Stage 2: Construct upper part of median wall (spine-beam) on the top of stanchion
- Construct roof slab and apply post-tension force
- Excavate to formation level
Stage 3: Construct base slab
- Construct median wall between temporary stanchions
- Remove temporary stanchion and construct the remaining median wall
395
Stage 1
Stage 2
Stage 3
Tendon
CONSTRUCTION JOINT
CONSTRUCTION JOINT
(a)
(b)
CONSTRUCTION JOINT
Grouting hose
(c)
Typical tendon
(d)
Figure 9 (a) Precast prestress slab; original design (b) post-tension slab; actual application (c)
typical tendon profile (d) tendon and grouting hose
396
Before starting excavation underneath the roof slab, tension is applied to tendon embedded
inside the roof slab (Fig. 9c). Subsequently, grout is injected via grouting hose. Figure 9d shows
a typical tendon profile which is similar in both original and alternative design. A profile of
tendon was designed to resist loading condition of a beam with end and middle supports. In
order to apply roof slab as a permanent prop for excavation, rigorous structural capacity
checking for combined bending moment and axial force in the slab is required. Figure 10a and
10b shows a typical construction of post-tension roof slab.
(b)
(a)
Figure 10 (a) Tendon installation for roof-slab (b) grouting after post-tensioning the slab
6.2 Excavation underneath the roof slab
Figure 11a and 11b show slab opening and temporary prop in tunnel zone. Spacing between each
opening was determined by optimizing efficiency of excavation and providing space to facilitate
the construction. Excavation was carried by using a small excavator inside the tunnel (Fig. 11a)
or using a long reach boom excavator on the roof slab (Fig. 11b). Presence of roof slab provides
additional space and increase efficiency of excavation works in comparison with the original
design where temporary working platform is to be used.
(b)
(a)
Figure 11 Slab opening with temporary support (a) using a small excavator inside the tunnel; (b)
using a long reach boom excavator on the roof slab
397
Stanchion
Upper part of
median wall
Stanchion
Median wall
(b)
(a)
Figure 12 (a) Temporary stanchions supporting post-tension roof slab (b) median wall and
stanchion
7. Performance of diaphragm wall
Figure 13 shows location of instrumentation in this project. Instrumentation consists of
inclinometer, surface settlement point, strain gauge and piezometer. Instrumentation in
diaphragm is installed in three zones which are tunnel, deep approach and deep approach with
sump pit. Each zone of monitoring is selected based on its construction sequences. Table 2
summarizes construction sequence in each zone according to the location of instrumentation
which is T1, T2, D1, D2 and DS1. In this paper, only some of measured results are reported for
conciseness of paper.
D1
T1
NO-43
NO-44
NO-45
NO-46
NO-47
NO-48
NO-49
NO-50
NO-51
NO-52
NO-53
NO-54
NO-55
NO-56
NO-57
NO-58
NO-59
NO-60
NO-61
NO-63
NO-62
NO-64
G
3.000
3.000
CWN-2
4.500
4.500
CWN-3
CLE-69
SO-70
SO-71
SO-72
SO-73
SO-74
SO-75
SO-76
SO-77
SO-78
SO-79
SO-80
SO-81
SO-82
SO-83
SO-84
SO-85
SO-86
SO-87
SO-88
SO-89
SO-90
SO-91
SO-92
SO-93
SO-94
SO-95
SO-96
SO-97
SO-98
3.350
3.350
CWS-7
CWS-8
3.350
CWS-9
3.000
3.000
CWS-10
G
NI-44
S2
S1
NI-43
CLE-68
CWS-6
CWN-4
CWN-5
NO-67
NO-66
NO-65
CWN-1
NI-45
G
S1
NI-46
NI-47
NI-48
NI-49
NI-50
NI-51
NI-52
NI-53
NI-54
NI-55
NI-56
NI-57
NI-58
NI-59
S3
NI-60
NI-61
S2 NI-62
S1
P
NI-63
NI-64
NI-65
NI-66
NI-67
CLW-68
CLW-69
SI-70
SI-71
SI-72
SI-73
SI-74
SI-75
SI-76
SI-77
SI-78
SI-79
SI-80
SI-81
SI-82
SI-83
SI-84
SI-85
SI-86
SI-87
SI-88
SI-89
SI-90
SI-91
S4
S5
S5
S6
S6
DS1
SI-92
SI-93
S2 SI-94
S3
S3
S4
S4
S5
S6
D2
T2
398
I
P
SI-95
SI-96
SI-97
SI-98
399
effects may contribute to reducing of lateral wall movement compared with plane strain
condition in deep approach.
Computed result overestimates wall movement in tunnel zone while it underestimates that in
deep approach zone. The differences are expected to be due to two major causes. First, constant
soil stiffness is adopted. The reduction of soil stiffness with increasing shear strain is not
simulated. Second, time dependent soil properties are not modeled. It is apparent that time
dependent behaviour in deep approach is the major component of wall movement. Nevertheless,
computed results reasonably agree with measured result in terms of overall trend.
10
20
30
40
50
10
20
Depth (m)
10
Displacement (mm)
Displacement (mm)
Displacement (mm)
30
40
50
10
20
30
40
50
0.34
mm/day
0.14
mm/day
0.03
mm/day
15
20
25
Measured [Before
base slab]
Measured [Base slab
construction]
Measured [4 months
after base slab]
Computed [Final
stage]
Measured [Before
base slab]
Measured [Before
base slab]
Computed [Final
stage]
Computed [Final
stage]
(b)
(a)
(c)
Figure 14 Lateral wall movement in (a) tunnel zone ; top-down method (T1); (b) deep approach
bottom-up method with 1-layer bracing (D2); (c) deep approach with sump pit bottom-up
method with 2-layers bracing (DS1)
7.3 Comparison of measured wall movement with other case histories
Figure 15 shows maximum measured wall movement by using two different construction
methods and sequences reported previously in other case histories (Phienwej et al., 1995).
Previous study conducted by Phienwej et al., 1995 suggests that maximum lateral wall
movement using bottom-up construction can be up to 0.4% of excavation depth (H). On the
other hand, wall movement in top-down construction is estimated to be only 0.2%H.
In this study, movement in bottom-up construction in deep approach and top-down construction
in tunnel exceeds 0.4%H and 0.2%H line, respectively. Wall movement using top-down
construction is closer to 0.27%H line proposed by Wang et al., 2010 based on measured field
results in Shanghai soft clay. Formation level of excavation in this study is in soft clay and only
one prop is provided. Thus, passive resistance is mainly from soft clay causing larger lateral
movement compared with other case histories. Another possible reason of large lateral wall
400
60
50
40
30
20
Bottom-up [Phienwej et al., 1995]
Top-down [Phienwej et al., 1995]
10
0
Soft clay
depth
10
15
20
25
Figure 15 Measured lateral wall movement compared with other case studies in Bangkok
[Modified from Phienwej et al., 1995]
7.4 Bending moment of diaphragm wall
Figure 16 shows comparison of measured and computed bending moment of diaphragm wall.
Measured bending moment is from vibrating wire strain gauges (VWSG) installed at
reinforcement of diaphragm wall at depth of 6 and 17.5 m where bending moment is expected to
be large. Measured strain is larger than 150 thus wall flexural stiffness reduction factor of
80% is adopted. Deduced bending moment is from two times differentiation of measured lateral
wall movement (Fig. 16) using the same stiffness reduction factor as measured from strain
gauge.
In tunnel zone (Fig. 16a), measured bending moment at depth 6 m is slightly smaller than
deduced bending moment suggesting that deduced bending moment is reasonable. It should be
noticed that deduced bending moment exceeds computed bending moment from 8 to 13 m below
ground surface due to smaller stiffness in soft to medium clay in numerical analysis.
In deep approach zone (Fig. 16b), measured bending moment at 6 m from strain gauge is about
30% larger than that in tunnel zone. Deduced bending moment in deep approach also confirm
the measured result. Bending moment from depth 3 to 7 m significantly exceeds the computed
bending moment due to lacking of time dependent properties of clay in numerical analysis.
401
At depth 17.5 m, measured, deduced and computed bending appears to be in a good agreement.
In addition, deduced bending moments in both tunnel and deep approach zones are still within
allowable bending moment capacity of diaphragm wall.
500
1000
-500
500
1000
Depth (m)
10
15
20
Measured [VWSG]
Measured [VWSG]
Deduced [INC]
Deduced [INC]
Computed [FEM]
Computed [FEM]
Allowable
Allowable
25
(b)
(a)
Figure 16 Bending moment of diaphragm wall in (a) tunnel zone (T1); (b) deep approach zone
(D2)
7.5 Excess pore water pressure
Measured excess pore water pressure normalized with initial pore water pressure is shown in
Figure 17. Pore water pressure is measured from standpipe piezometer installed at a distance of 1
m away from diaphragm wall at sump pit with tip of piezometer at 10 m. Initial pore water
pressure is about 70 kPa which is considered to be reasonable if hydrostatic pore water
distribution is assumed given ground water table is at 3 m below ground surface (Teparaksa,
1999). Wall displacement at depth of 10 m is shown to compare with response of piezometer.
During the first 120 day after initial reading, although there is constant increasing of wall
movement, there is no significant change of pore water pressure. This observation may be due to
unloading of horizontal stress causes negative excess pore water pressure and shearing in soft
clay causes positive excess pore water pressure. Consequently, two components counteract each
other causing only a slight change of excess pore water pressure. From day 120 to 150, lateral
402
Wall movement
0.5
25
20
0.3
15
0.2
10
0.1
0.0
Base slab
construction
0.4
Excavate
to 10 m
u/u0
30
50
100
150
200
250
0.6
403
References
Brinkgreve, R.B.J., and Vermeer P.A. 1998. PLAXIS v7.2 Manual, A.A. Balkema, Rotterdam,
Netherlands
Peck, R.B., Hanson, W.E., and Thornburn, T.H. 1974. Foundation Engineering. New York: John
Wiley&Sons.
Phienwej, N., Akawanlop, K and Balasubramaniam, A.S. 1995. Comparative evaluation of
ground movements associated with braced - excavation in Bangkok soft clay, 10th Asian
Regional Conference on Soil Mechanics and Foundation Engineering, Beijing, 341-344
Sambhandaraksa, S., and Pitupakorn, W. 1985. Prediction of prestressed concrete pile capacity
in stiff clay and clayey sand. Proc. of 8th Southeast Asian Geotechnical Conference,
Kuala Lumpur, Malaysia, (3), 58-63
Teparaksa, W. 1999. Principle and Application of Instrumentation for the First MRTA Subway
Project in Bangkok. 5th International Symposium on Field Measurements in
Geomechanics, Singapore, 411-416
Wang, J. H., Xu, Z. H. and Wang, W. D. 2010. Wall and ground movements due to deep
excavations in Shanghai soft soils. Journal of Geotechnical and Geoenvironmental
Engineering, 136 (7), 985-994
404
University of Missouri-Rolla
Rolla, Missouri
405
1086
Proceedings: Fourth International Conference on Case Histories in Geotechnical Engineering, St. Louis, Missouri,
March 9-12, 1988.
Ganeshan Baskaran
SEAFCO Co., Ltd.
Bangkok 10320
Thailand
ABSTRACT
Sonic integrity testing is a common method used to test the integrity of piles in Bangkok. An acoustic technique equipped with
computer software, developed by TNO, PDI, IFCO, etc., is commonly used to test the piles. This paper presents the signal
characteristics and their interpretations from sonic integrity test performed on mainly bored piles varying in length, size, construction
method and founded soil strata. Toe reflection of small bored piles (diameter of 0.35m to 0.60m) constructed in Bangkok subsoil can
be observed for pile length of up to 20m to 24m . Beyond 35m below the ground , visibility of toe reflection is uncommon for large
bored piles (diameter of 0.80m and larger). Commonly predicted defects and frequency of occurrences are tabulated. Data sets have
been selected from the Data Bank of a foundations specialists organization to which the authors are associated with. Recently
completed and current projects in Bangkok have been selected so that the data set could be well represented by over 8000 piles. 285
piles (3.3%) out of 8,689 piles have been interpreted for poor concrete or inclusions, cracks and size reduction. Among these, cracks
contribute the major portion (2.2% or 194 piles). Cracks are mainly induced by either improper excavation adjacent to the piles or
trimming the pile head by ill fated ways. Small diameter piles are the most suffered by cracks. Prominent sectional variations have
been indicated by the signals at depth where temporary casing ends. Intermittent variations also are common at the interface of soft
clay and medium to stiff clay layers.
KEYWORDS
Integrity, Sonic signal, Toe reflection, Pile impedance, Discontinuity
407
1087
INTRODUCTION
CONSTRUCTION METHOD
L= c. T/2
(1)
z = E.A/c
(2)
E = .c2
(3)
(4)
Wet process too normally uses steel temporary casing of 1415m in length. A borehole is made by rotary method using
auger or auger bucket under bentonite slurry. Concrete is
poured with tremie method.
408
1088
CHARACTERISTICS OF SONIC TEST SIGNAL IN
BANGKOK SUBSOIL
Soil influence
12
Pile 49
19 Sep 95
15
18
4000 m/s
exp: 20
21
24
27
f:8
30
10
15
20
Pile G30
27 Jan 97
10.6cm/s
V2-88c
Sr
25
30
4000 m/s
exp: 20
35
40
45
f:8
50
V2-88c
Sr
Size variations
Toe reflections
Toe reflections are clear when the toe depth is 20-22m for
piles of 0.35m-0.50m in diameter and up to 24m for 0.60m
piles. In general, when pile length over diameter ratio (L/D) is
within 40, toe reflections are clear and hence the pile length is
predicted. However, for piles founded in depth deeper than 3035m the toe reflection is uncommon as damping of signals is
caused by deeper soil layers. Further, magnitude of toe
reflection is prominent for larger piles compared to small piles
with same length and constructed at same site. Figure 2 shows
the signal characteristics of different size piles constructed just
a few meters apart with same length.
5.4cm/s
0
Pile 322
10 Jan 95
10
15
20
25
30
35
4000 m/s
exp: 20
40
45
f:8
50
V2-88c
Sr
23.2m
11.0cm/s
0
12
15
Pile 6
4000m/s
12 Sep 95
exp: 20
18
21
24
27
30
f:8
V2-88c
Sr
22.0m
7.1cm/s
0
12
15
Pile 24
4000m/s
12 Sep 95
exp: 20
18
21
24
27
f:8
30
Soft Clay
V2-88c
Sr
Med.
Stiff to
Dense Stiff
Clay Hard Clay Sand Clay
Dense Sand
409
1089
Figure 6 shows bored pile sections formed at the lower end of
temporary casing. These bored piles were cast together with a
steel column for construction of deep basements with
diaphragm walls using top-down method. These piles were
exposed when excavation reached to 15m below the ground
level.
4.3cm/s
0
10
15
20
25
Pile 99
4000 m/s
25 Nov 94
exp: 20
Soft Clay
30
35
40
45
50
V2-88c
f:8
Sr
Dense Sand
Fig 4B Uniform pile size along the pile shaft is shown by both
drilling moitoring record and sonic integrity test record. (Pile
0.80m, cutoff 3.0m, toe depth -45m.)
Common causes for size variations in bored piles are;
Med.
Clay
Soft Clay
11.0cm/s
0
12
Pile 66
25 Jun 97
15
4000 m/s
exp: 20
18
21
24
27
f:8
30
V2-88c
Sr
10.0 cm/s
10.5cm/s
0
Pile 30
2 Jul 97
Med.
Clay
12
15
4000 m/s
exp: 20
18
21
24
27
f:8
30
V2-88c
Pile 168
11 Nov 95
Sr
12
16
20
4000 m/s
exp: 20
24
28
32
36
f:8
40
V2-88c
Sr
410
1090
In contrast to the size reduction, caused by smaller
auger/bucket size than the casing size, relative size increase
also have been observed. Casting records for piles indicated in
Fig. 8 noted about 30% over break of concrete volume.
Discontinuities/cracks
8.9 cm/s
0
12
15
Pile 50
4000 m/s
4 Apr 97
exp: 20
18
21
24
27
30
f:8
V2-88c
Sr
3.5 cm/s
0
12
15
Pile TEST
4000 m/s
25 Jun 97
exp: 20
18
21
24
27
30
f:8
V2-88c
Sr
12
16
24 Apr 97
20
24
4000 m/s
exp: 20
28
32
36
40
f:8
V2-88c
Sr
7.6 cm/s
0
12
16
20
Pile 1 #
4000 m/s
2 Jun 97
exp: 20
24
28
32
36
f:8
40
V2-88c
Sr
22.8 cm/s
12
Pile 28
15 Jan 97
15
18
21
24
4000 m/s
exp: 20
27
30
V2-88c
Sr
f:8
Fig. 11A The signal showing poor quality concrete at pile top
section (Pile 0.60m x 18.0m)
8.8 cm/s
0
Pile 28
18 Jan 97
Further, static pile load test results indicate the test pile (Fig.
10B) failed well before designed maximum test load. Figure
10B also shows the joint between pile cap and pile.
12
15
18
4000 m/s
exp: 20
21
24
27
f:8
30
V2-88c
Sr
Fig. 11B The signal acquired after trimming top portion. The
reflections from the lower part of the pile and toe become
visible.
411
1091
Physical pile damage due to excavation or improper chipping
to trim level
Most discontinuities or cracks in bored piles after installation
of piles can be caused by construction activities associated
with basement excavation adjacent to them and improper
trimming to design cut-off level.
12
18
24
Pile 681
8 Apr 96
30
36
Dense Sand
42
48
54
60
Sr
10
20
30
1
40
2
50
3
ms
L/c
-750
30
Ton / m
0.1
2.2
1.0
For Msd
Vel Msd
750
CONCLUSION
29-Apr-96
CAPWAP (R) Version 1 994 -1
1500
Ton
Poor concrete at
pile top (0-3m)
Cracks/
discontinuities
V2-88c
f:8
4000 m/s
exp: 20
6.2 cm/s
0
Causes
Size reduction
Type of Defect
Pile
Shaft Resistance
Distribution
(Toe 178.8 Ton)
Pile Forces at Rut
1000
Ton
ACKNOWLEDGEMENT
The authors express their appreciation to E.D.E. Co. Ltd. in
supplying test records and to Mr. Sujit Onsri and Mrs. Piyamitr
Sura-auggool for their assistance in the preparation of this
paper.
412
1092
REFERENCES
CIRIA PG72 [1977] Review of problems associated with the
construction of cast-in-place concrete piles Construction
Industry Research & Information Association.
CIRIA PG4 [1977] Integrity Testing of Piles: A Review
Construction Industry Research & Information Association.
Fleming, W. G. K., Reiding, F., and Middendorp, P. [1985]
Faults in Cast in place Piles and Their Detection,
Proceedings of the Second International Conference on
Structural Faults and Repair, The Institution of Civil
Engineers, Westminster, London, pp. 301-310.
Rausche F, Likins E. G and Hussein M. [1988] Pile Integrity
by Low and High Strain Impacts, Application of Stress-Wave
Theory to Piles, Third International Conference. Ottawa,
Canada, pp. 44-55.
Seitz, J.M. [1984] Low Strain Integrity Testing of Bored
Piles, Application of Stress-Wave Theory to Piles, Second
International Conference, Stockholm, Swedin, pp. 94-102.
Sliwinski, Z. J. and Fleming, W.G.K. [1983] The Integrity and
Performance of Bored Piles, Advances in Piling and Ground
Treatment for Foundations, The Institution of Civil Engineers,
London, UK., pp. 153-165.
413
Application of Stress-Wave
Theory to Piles
Quality Assurance on Land and Offshore Piling
Edited by
Sussumu Niyama
Jorge Beim
415
ABSTRACT: Modern buildings in Bangkok nowadays are designed with basement facility and different elevation of pile foundation which require excavation works in the immediate vicinity of the constructed bored
piles. Adverse effects on piles from adjacent excavation works in terms of excessive movement of piles and
pile damages have been observed in some projects. Assessment of bored pile damages using sonic integrity
test is focused in this paper with demonstration of test results from three case histories. Method of remedial
works for damaged piles and additional testing for pile capacity justification where available are also briefly
discussed. Stress induced in piles due to the soil movement caused by excavation works is also examined
with the aid of computerized finite element program. Location of cracks detected by sonic integrity tests is
correlated with the analyzed bending moment in pile, which exceeds the cracking moment capacity of pile.
1 INTRODUCTION
417
Causes
Poor concrete at
pile top (0-3m)
0.1
Size reduction
1.0
Cracks/discontinuit
ies
2.2
418
SOFT CLAY
MEDIUM CLAY
STIFF CLAY
(1)
where, L is a length from pile head to reflected surface, c is a velocity of stress wave and T is a travel
time of the wave for length L.
From this formula, length L, can be computed
from the travel time of reflected wave and the wave
velocity of concrete which may be estimated from
concrete strength of piles or from the reference pile
of known length.
SAND
crack induced
by large lateral
movement
crack induced
by sliding
failure
z = E A/c
E = c2
crack induced
by uplift
force
(2)
(3)
z = cA
(4)
Pile
Dia.
(m)
Defect depth
below ground
level (m)
Least
prominent
crack
Less
prominent
crack
Prominent
crack
1.0
6.0 13.8
1.2
10
6.1 7.6
1.5
9.9
420
12
18
24 30
Pile 890
10 Apr 96
5.8cm/s
12
18
24 30
42
48
54
36
12
18
24 30
Pile 894
10 Apr 96
36
42
48
8.8cm/s
12
18
24 30
36
54
42
48
54
60
42
48
54
v2-88c
sr
60
v2-88c
sr
f : 12
4000m/s
exp: 20
v2-88c
sr
f : 12
4000m/s
exp: 20
Pile 681
9 Apr 96
60
f : 12
4000m/s
exp: 20
Pile 680
8 Apr 96
5.2cm/s
36
4000m/s
exp: 20
60
f : 12
v2-88c
sr
3.5cm/s
Soft Clay
6.2cm/s
Dense Sand
Dense Sand
2.2cm/s
0
12 18 24 30 36 42 48 54 60
4000m/s
f:8
exp : 20
Pile 681
8 Apr 96
4.1cm/s
Pile 681A
29 May 96
12 18 24 30 36 42 48 54 60
4000m/s
exp : 20
f:8
12 18 24 30 36 42 48 54 60
4000m/s
exp. 20
Pile 165
13 May 97
v2-88c
Pile 193
13 May 97
sr
f: 12
12 18 24 30 36 42 48 54 60
4000m/s
exp. 20
f: 12
v2-88c
sr
v2-88c
sr
Figure 6. Sonic integrity test results of good pile and pile with
prominent crack Case II
v2-88c
sr
421
Less
prominent
crack
Prominent
crack
Defect depth
below ground
level (m)
1.0
7.5 - 9.4
1.5
14
8.4 - 21.0
20.2cm/s
Pile 103
17 Feb 93
13.3cm/s
12 15 18 21 24 27 30
4000m/s
exp : 20
Pile 48
17 Feb 93
f:8
12 15 18 21 24 27 30
4000m/s
exp : 20
f:8
18.8cm/s
0
Pile 50
17 Feb 93
12 15 18 21 24 27 30
4000m/s
exp : 20
f:8
V2-88c
sr
V2-88c
sr
V2-88c
sr
Figure 8. Case III - Seismic test results of good pile, pile with
less prominent and prominent crack (top to bottom in order)
168
422
Table 4. Summary of pile damage assessment by sonic integrity test Case III
Pile
Dia.
(m)
Prominent
crack
Defect depth
below ground
level (m)
33
5.5 13.8
0.60
Less
prominent
crack
38
No. of
pile
2
22
Case
Pile
size
(m)
Rebar
(%)
Cracking
moment
(t.m)
I
II
1.0
1.5
0.75
0.50
30
102
III
0.60
0.35
6.5
Ultimate
moment
(Whitney)
(t.m)
79
188
9.2
Moment by
FEM model
(t.m)
149.7
117.2
255.7*
13.3
Finite element analysis was carried out using twodimensional modeling. With the aid of PLAXIS
computer program staged excavation was simulated
and pile/soil movements as well as bending stress
induced in the piles were examined for above presented projects. Model profile of Case III used in
FEM analyses is presented in Figure 9.
1.52.5
17.00
0.0
5.0
Su (t/m2)
SPT (blows/ft)
20
40
60
Crust
Depth of bending
moment exceeding piles cracking
moment from
FEM (m)
11.0 & 13.0
15.0
15.5
Sheet pile
Soft CLAY
10.0
15.0
Case
II
III
Medium
CLAY
Very Stiff
CLAY
20.0
Medium
CLAY
25.0
Hard
CLAY
30.0
423
REFERENCES
Bending Moment
(T-m)
-10
10
20
Displacement
(mm)
20
Balasubramanium, A.S. 1991, Inaugural Lecture on Contributions in Geotechnical Engineering, Soil Mechanics and
Foundation Engineering, AIT, Bangkok, March 1991
Turner, M. J. 1997. Integrity Testing in Piling Practice, CIRIA
Report No. 144, Construction Industry Research and Association, London.
Thasnanipan, T., Maung, A. W. and Tanseng, P. 1998a. Damages to Piles associated with Excavation Works in Bangkok
Soft Clay, 6th International Conference on Problems of Pile
Foundations Building, Ufa, Russia. September 14-18, 1998.
pp. 91-98
Thasnanipan, T., Maung, A. W. and Baskaran, G. 1998b.
Sonic Integrity Test on Piles Founded in Bangkok Subsoil
Signal Characteristics and Their Interpretations, 4th International Conference on Case Histories in Geotechnical Engineering, St. Louis, Missouri. March 9-12, 1998. pp. 10861092.
0.00
1ST STRUT
2ND STRUT
5.00
SHEET PILE
BORED PILE
10.00
Depth
(m)
15.00
Cracking
Moment of
Pile
Interface
between Soft
and Stiff
Clay
20.00
SOFT TO MEDIUM
CLAY
STIFF CLAY
MEDIUM CLAY
STIFF CLAY
25.00
HARD CLAY
30.00
10 CONCLUSIONS
With the demonstration of three case studies, effectiveness of sonic integrity test in pile damage assessment in Bangkok is presented in this paper. This
research study also proves that external forces due to
both lateral and uplift movement of the ground induced by adjacent excavation can cause considerable
damage to constructed bored piles.
170
424
Application of Stress-Wave
Theory to Piles
Quality Assurance on Land and Offshore Piling
Edited by
Sussumu Niyama
Jorge Beim
425
Application of Stress-Wave Theory to Piles, Niyama & Beim (eds) 2000 Balkema, Rotterdam, ISBN 90 5809 150 3
ABSTRACT: Pile foundation is compulsory in Bangkok, Thailand, to support almost all types of structure
due to prevailing subsoil condition. Large bored piles of 600mm to 1800mm in diameter and barrettes
(0.8mx2.7m-1.5mx3.0m) with toe level up to 60m depth are commonly used to support heavy structures covering high-rise buildings, subway stations, elevated highways, etc. In order to test or check the quality of
such high load carrying foundation piles constructed in multi-layered soil conditions, three main types of nondestructive integrity tests such as sonic integrity, sonic logging and high strain dynamic load tests are usually
employed. Sonic integrity test is the most common method in integrity testing on both driven and bored piles.
Sonic logging test is occasionally employed as a part of pre-planned site quality control system. High strain
dynamic load test is commonly used for pile capacity evaluation. This paper presents an overview of these
three commonly used non-destructive tests on piles in Bangkok subsoil. Some findings from the authors involvement in research works are also presented.
10
Su= 40-140KPa
-20
t = 17-21kN/m3
-30
SPT-N= 20-50
t = 20kN/m3
tati
ine
cL
-40
raw
Su= 250KPa
= 21KN/m3
t
cD
Hard Clay
(CL)
-10
etri
40
Su= 10-20KPa
t = 14-16kN/m3
ros
Dense to Very
Dense Sand
(SM)
60
Hyd
30
40
om
Medium to
Stiff Clay
(CH)
20
iez
20
0
0
Weathered Crust
Bangkok Soft
Clay (BSC)
(CH)
al P
Engineering
Parameters
u
Act
Three techniques namely sonic integrity, sonic logging and high strain dynamic load tests are the
commonly used non-destructive integrity tests applied in Bangkok, Thailand. The effectiveness and
suitability in terms of both cost and method of application itself are the primary reasons of the greatest
growth in use of these tests. An overview of sonic
integrity, sonic logging and high strain dynamic load
tests conducted on piles particularly bored piles
founded in Bangkok subsoil is presented in this paper.
38m. Second Dense to Very Dense Sand layer occurs at about 46m depth. Between these sand layers,
Hard Clay layer is present.
Depth (m)
1 INTRODUCTION
wn
-50
Do
Lin
-60
427
428
172
16.0cm/
s
0
173
429
18
24
30
36
42
48
54
60
f:8
4000m/s
exp: 20
v2-88c
Sr
Temporary casing
bottom level
Outer diameter of
casing collar
11.0 cm/s
12
pile 30
14 Jan 91
Pile 66
25 Jun 97
12
15 18
4000 m/s
exp : 20
Nominal dia./dia. of
drilling tool
21
24
27
f: 8
30 v2-88c
sr
Velocity (m /s)
4300
4100
3900
3700
3500
3300
0
18
27
Days
36
45
54
63
Figure 4. A curve of sonic wave velocity vs. pile age in Bangkok sub soil (fc 35 MPa).
The results of a series of laboratory tests to determine the effects of various defects or inhomogeneities within a concrete section were reported by Stain
and Williams (1991). The test results were carried
out on small panels constructed to model various
pile construction defects and anomalies. The results
from these panels were related to tests on control
panels formed from homogeneous concrete.
Faiella and Superbo (1998) reported the analysis
of the sonic logging test results of over 6800 piles
collected from 37 sites in Italy. Based on the results
of analyses, the authors presented the defect classification criteria for piles monitored by different number of tubes as illustrated in Tables 3 (a) and 3 (b).
Table 3 (a). Defect classification criteria monitored by means
of 2 tubes (Faiella and Superbo, 1998)
Ta/Ts
<1.15
1.15-1.45
1.45-2.0
>2.0
Ta/Ts
<1.15
1.45-2.0
Pa/Pt
Pa<Pt
Pa=Pt
Pa<Pt
Pa=Pt
Pa<Pt
Pa=Pt
Type of defect
Non-homogeneous concrete
Light
Probably serious
Light
Probably serious
Probably serious
Light
1.15-1.45
Tk/D
<3
>3
<1
>1
<0.5
>0.5
>2.0
Pa<Pt
Pa=Pt
Tk/D
Type of defect
Non-homogeneous concrete
<3
>3
<3
>3
<1
1-3
>3
<1
>1
<0.5
0.5-3
>3
<0.5
>0.5
Non-homogeneous concrete
Light
Light
Serious
Non-homogeneous concrete
Light
Serious
Light
Serious
Light
Serious
Serious
Light
Serious
where:
Ta = Travel time of sonic waves in the anomalous zone
Ts = Travel time of sonic waves in the sound concrete
Tk = Thickness of the anomalous zone
Pa = Number of measurement paths affected by sonic anomalies
Pt = Total number of travel paths for each pile
D =Pile diameter
Case
6
Good concrete
pile with dirty
tubes and clean
water.
Sonic logging
profile shows
defect at pile
head due to
bleeding of concrete.
Good concrete
pile with dirty
tubes and dirty
water (contaminated with bentonite slurry)
filled.
Sonic logging
profile shows
defect at pile
head due to
bleeding of concrete, similar to
case 2.
Good concrete
with Layer of
bentonite
slurry, sand,
gravel fill
(30cm.Thickness
whole Section) at
middle of the
pile.
Sonic logging
profile shows
signal loss from
0.4m to 0.7m
due to delay of
sonic wave.
Good concrete
with Clay on
surface of one
tube (50 cm.
from top of concrete).
Profile
Discussion of
signal
Sonic logging
profile shows
non-uniform
signal, not clear
signal due to
poor concrete
and inhomogeneous concrete.
Thin smear of
2mm. bentonite
slurry on tubes
(50 cm. from
top of concrete).
Sonic logging
profile shows
signal loss from
depth
0-0.5m (more
travel time).
Thick smear of
5mm. bentonite
slurry on tubes
(50 cm. from
top of concrete).
Sonic logging
profile shows
continuous signal loss and signal delay at
depth 0-0.5m,
similar to case
7.
Weak concrete
(high w/c ratio).
Though weak
(low strength)
concrete is used,
sonic logging
profile shows
continuous signal, because of
homogeneity of
the tested media.
Sonic logging
profile shows
signal delay at
0.5m depth.
Turner (1997) pointed out the need of both theoretical knowledge and practical experience in interpretation of the test results in CIRIA Report 144. Suggestion is also made in this report that the anomaly
shown in sonic test signals can be caused not only
by changing in physical properties of the materials,
but also by factors within the measuring system itself. These factors are;
175
431
Table 5. Yearly minimum quantity of dynamic load test conducted in Thailand during 1991 to 1997
Year
No. of dynamic load test done
1991
84
1992
134
1993
242
1994
369
1995
464
1996
473
1997
695
176
432
ameter piles respectively. As can be seen in the figures, load-settlement characteristics obtained from
dynamic load test agree well with those of static load
test for both large and small diameter bored piles.
ACKNOWLEDGEMENT
The authors wish to express their appreciation to
EDE Co., Ltd. for providing the test data. Thanks
are also given to Mr. Veera Vasinvarthana and Mr.
Natomon Kampananon STS Engineering Consultants Co., Ltd. for giving permission for the use of
their previous works in this paper.
Settlem ent (m m )
-5
REFERENCES
-10
-15
Dynamic load test
Static load test
-20
0
200
400
Load (ton)
600
800
Settlem ent (m m )
-5
-10
-15
Dynamic load test
Static load test
-20
0
20
40
60
Load (ton)
80
100
9 CONCLUSIONS
Use of sonic integrity, sonic logging and high strain
dynamic tests in Bangkok has been presented.
Though sonic integrity test is a simple and cost
effective method, the reliability of the test results is
highly dependent on the experience of the person in
both field-testing and interpretation.
The results from sonic logging test conducted on
model piles in Bangkok helps to extend the knowledge of the signal characteristics and interpretation.
High strain dynamic test has become a wellaccepted method especially for load testing of piles.
Agreement between static and dynamic load test results enhances the confidence in using the dynamic
load test as shown by rapid increment in number of
tests conducted in seven years in Thailand, mainly in
Bangkok.
177
433
Problems of Pile
Foundations Building
Damages to piles associated with excavation works
in Bangkok soft clay
N. Thasnanipan, Maung A. W. and Tanseng P.
Seafco Company Limited Bangkok, Thailand
ISBN 5-88151-161-1
435
The 6th International Conference on Problems of Pile Foundations Building, Russia, September 14-18, 1998
Narong Thasnanipan
SEAFCO Co., Ltd.
Bangkok 10320
Thailand
Pornpot Tanseng
SEAFCO Co., Ltd.
Bangkok 10320
Thailand
ABSTRACT
In Bangkok, Thailand, pile foundations are commonly used to support all type of structures. The excavation for construction of
pile caps and mat foundations are carried out mostly in the soft clay layer. Sheet pile walls with temporary bracing systems are
commonly used for excavation works (depth ranging form 4.0-11.3m) in the built-up areas of central and outskirts of Bangkok
metropolis. Sometimes open cut excavation is adopted for shallow excavation (2.0-6.0m) in the areas where no buildings exist in
the close vicinity of the site. Lateral movements of soils take place in such excavations causing pile deviation and cracks to the
piles, especially located in the vicinity of boundary of excavation. Such defects have been found more frequently in smaller
diameter piles than the larger diameter piles. These tension cracks in piles are commonly observed above the level of interface of
soft and stiff clay layers where excavation induced bending moment in pile exceeds the piles cracking moment capacity. Sonic
integrity testing is usually employed to test the piles integrity. High strain dynamic load test is sometimes employed to check the
performance of piles with such defects. This paper presents four cases in which damages caused to piles by soil movement
associated with excavation works. Pile damages, especially tension cracks indicated by integrity testing, analysis on stresses in
pile due to the soil movements and behavior of retaining systems are also examined. Correlation between location of crack and
bending moment in pile which exceeds the pile cracking moment capacity also made.
KEYWORDS
Pile deviation, Lateral movement, Sonic integrity test, Dynamic load test, Pile damage, Bending moment, Cracking moment
91
437
INTRODUCTION
TYPES OF EXCAVATIONS
PILE FOUNDATIONS
Both bored and driven piles are commonly used for
foundations of structures in Bangkok subsoil. The subsoil
generally consist of a 12-18m thick very soft clay layer
overlying medium to stiff clay layer. A sand layer occurs at
depth of 20m to 35m below the stiff clay layer. A second
layer of dense sand is generally ound below 50m where the
toe of deep bored piles are founded for high rise or heavy
structures. Stiff to hard clay layers occurs intermittently
between the sand layers. Large diameter bored piles having
diameter of 800mm to 1500mm are extended down to 35m
to 60m respectively being embedded in the sand layers. For
low rise buildings driven or small diameter bored pile of
35mm to 600mm are commonly used with footing for pile
groups or for individual piles. The length of pile is
generally to 20 to 28m embedded in stiff clay or first sand
layer.
INTEGRITY OF PILES
Sonic integrity test is usually employed to test the integrity
of piles after piles have been trimmed to the design cutoff
level. Generally a minimum of 10% to a maximum of 100%
of piles are tested. A sonic integrity tester with built-in
computer having high quality signal acquisition system has
been commonly used for pile integrity testing. However,
severity of the defect/crack or any irregularity in piles is
usually determined comparatively based on magnitude of
reflection amplitude of individual piles from such a
defect/crack or irregularity, with reference to the input
pulse. Figure shows the sonic test records of a good pile
and piles with crack in different severity from Cases IV.
92
438
93
439
by Sonic
Defect
Depth
below
GL (m)
6.2-8.0
13-16.6
15.6
94
440
by Sonic
Defect
Depth
below
GL (m)
7.5-9.4
8.4-21.0
Damaged piles were cored to the depth below the crack and
grouted. Modification of reinforcement for the mat was
done for defect piles with large horizontal deviation.
Soil Retaining System - Type FSP III sheet pile (14m) with
two level of temporary bracing at about 1.0m and 3.5m
below the ground level was used. Figure 4 shows a portion
of pile layout which includes an excavation zone with
braced sheet pile wall.
95
441
From the results, only a few piles lead to low safety factor to
carry the designed load and also connected by mat.
Modification of reinforcement for the mat was done
according to redistributed load.
17.00
0
1.5 2.5
Su (t/m 2)
0.0
0.0
1.0
2.0
SPT (blows/ft)
3.0
4.0 0
20
40
60
Crust
Sheet pile
5.0
Soft CLAY
10.0
Very Stiff
CLAY
20.0
10
6.00
32.00
9.00
18.00
Center
Line
Su (t/m2)
0
Slope
1:3
Slope
1:3
5.0
Mat Zone
4.0
8.0
50
30.0
20.
0
Sheet pile
14.0
20.0
4.
0
6.
0
SPT (Blows/ft)
0
2
0
4
0
Sheet pile
Soft to Vsoft
CLAY
Medium CLAY
Stiff to Vstiff
CLAY
Su (t/m2)
SPT (Blows/ft)
2.5
5.0 0 20
40
60
Weathered
CLAY
Soft to Very
Soft CLAY
10.0
15.0
2.
0
DISCUSSION
100
MAT FOOTING
5.0
Su (t/m 2)
0.0
10
0.
0
Crust
Crust
CL
25.
0
Dense to
Very Dense
SAND
9.50
35.0
40.50
15.
0
Stiff to Very
Stiff CLAY
0.0
1
0
10.
0
25.0
30.0
5.
0
Medium
CLAY
20.0
0.
0
Soft CLAY
10.0
15.0
Hard CLAY
SPT (Blows/ft)
0
Medium CLAY
25.0
0.0
Medium CLAY
15.0
Medium
CLAY
Stiff to Hard
CLAY
25.0
96
442
-10
10
Displacement (mm)
20
40
20
0.00
5.00
Depth (m)
10.00
15.00
Cracking
Moment of Pile
Interface
between Soft
and Stiff Clay
20.00
25.00
Summary of
Type of
Retaining
(m)
Cut Slope
Sheet Pile
Sheet Pile
Sheet Pile
Level
of
Strut
1
1
2
Excav.
Depth
(m)
5.4
5.7
8.0
6.0
CONCLUSION
This paper presents four case studies on bored piles
damaged by excavation induced lateral soil movements in
Bangkok soft clay layer. Performance and response of pile
are studied by FEM modeling and confirmed with pile
integrity test results. Causes of pile damages found are also
discussed.
Max. Lateral
Movement
(mm)
117
175
56
52
97
443
ACKNOWLEDGEMENT
The authors express their appreciation to the colleagues,
especially to Mr. Ganeshan Baskaran, Mr. Muhammad
Ashfaq Anwar, Mr. Tossaporn Sree-iam and Mr. Chetsadar
Plongkrathok for their assistance in the preparation of this
paper.
REFERENCES
1. Phienwej N., Balasubramaniam A.S., and Sutabutr T.
[1996]. Performance of Retaining Structures for Deep
Excavation in Bangkok Soft Clay Short Course on
Deformation of Soils & Rocks and Displacement of
Structures, Ground Movment in Deep Excavation - Case
Histories in Bangkok Subsoil, Bangkok, Thailand. pp.14-20.
98
444
Natamon Kampananon
STS Instruments Co., Ltd.
445
1. INTRODUCTION
The first sonic logging test in Thailand was believed to be conducted in 1982 for the wet-processed bored
piles of the Memorial Bridge Project where bad concrete zones were detected at two levels, depth about
20m and 1m from the pile top as reported by Ng (1983). In the past, sonic logging test was only employed
as a pre-planed site quality control testing for large infrastructure projects in Bangkok. The primary reason
of using sonic logging test in only large scale projects was due to its relatively expensive cost since cost of
testing the entire length of deep-seated bored piles are high higher costs involved in installation of
lengthy access tubes and the test itself. With the passage of time, the application of this quality control
test is being extended. As interpretation skills relevant to local soil condition and construction method of
this test have been significantly improved in local industry, the piling engineers begins to use sonic
logging tests for further assessment of constructed bored piles.
2. WET-PROCESSED BORED PILE CONSTRUCTION METHOD
Due to the prevailing subsoil and groundwater conditions, deep-seated bored piles of toe depth over 24m
are constructed by wet-process or slurry displacement method. In the rotary drilling method, a temporary
casing of appropriate length (12 to 18m is commonly used in Bangkok depending on the thickness of soft
clay) with required diameter (internal diameter not less than that of design bored pile diameter) is first
installed to ensure the stability of the borehole in the top soft or loose soil layers.
1
President, 2Senior Vice President, 3Geotechnical Engineer SEAFCO Public Co., Ltd. ,
Bangkok, Thailand, [email protected]
4
Senior Geotechnical Engineer, STS Instruments Co., Ltd., Bangkok, Thailand
447
Drilling is commenced by auger to drill out the soil inside the temporary casing. Auger-drilling is
commonly continued up to the top of the first water-bearing sand layer or bottom of the casing. Drilling
slurry or supporting fluid is then supplied to the borehole and drilling is proceeded with a bucket down to
the design final depth of the pile. Before lowering the reinforcement cage, a special cleaning bucket is
used to clean the base of borehole. If bentonite slurry is used, recycling method by air-lift or pump is
applied as the base cleaning process. Reinforcement cages are then lowered into the borehole and
concreting is carried out by tremie method.
3. CLASSIFICATION OF THE SONIC LOGGING TEST ANOMALY
Based on the experience of testing specialist on over 3000 deep-seated bored piles in past 15 years in
Thailand coupled with the comparison between sonic logging test results and direct examination from
cored samples of zones detected with anomaly, the category and criteria for interpretation of cross-hole
sonic logging test results have been established as shown in Table 1. Figure 1 depicted the sonic signal
profile of 4 categories classified in Table 1.
Table 1. Category of sonic logging signals and criteria
Category Criteria
A
No or slight increase in transmission time not more than 10%
B
Minor increase in transmission time >10% but <25%
C
Transmission time more than Category B but transmission
time can still be defined
D
Transmission time can not be defined
Integrity
Homogeneous concrete
Minor anomaly
Major anomaly
Defect
Figure 1. Sonic profile showing different category (A, B, C and D) as classified in Table 1
4. PILE HEAD CASTING LEVEL OF WET-PROCESSED BORED PILES IN BANGKOK
In order to ensure the sound concrete at the specified pile cut-off level, wet-process bored piles are
commonly cast well above the cut-off level. Though most of the piling engineers wish to minimize the
overcast length, their primary concern is a formation of contaminated concrete at the design pile cut-off
level which would need the piling contractor to come back to the site to carry out the remedial work while
the superstructure contractor has commenced his work. There could be a claim from the superstructure
448
contractor for having delay to rectify the imperfect pile heads. Hence, most of the bored piling engineers
prefer to cast the pile significantly higher than specified pile top level as shown in Figure 2.
Figure 2. View of exposed diameter 1.20m bored piles for mat foundation - Most of the piles were
constructed with excessive overcast length (over 4m above design pile cut-off level)
The need of using the long temporary casing in Bangkok subsoil also makes it difficulty to maintain the
top of overcast at the desired level. Table 2 shows the casting tolerance above cut-off levels according to
The Institution of Civil Engineers (1996) United Kingdom.
Table 2. Casting tolerance above cut-off levels for wet-processed bored piles (ICE, UK, 1996)
Cut-off level below
Casting tolerance above cut-off level, m Condition
commencing surface, H, m
0.15 10.00
1.0 + H/12 + C/8
Piles cast under water or
Where C = length of temporary casing
support fluid
below the commencing surface
5. COMMON DEPTH OF ANOMALY FORMED BY CONTAMINATED CONCRETE IN
BORED PILES
As construction method and quality control process for wet process bored piles are being well established
in local construction industry of Thailand, defect (discontinuity or contaminated concrete) in lower part of
pile shaft rarely occurs in these days. Hence investigating the top part of pile is more important than
testing the entire length of the deep-seated piles in Bangkok subsoil. Moreover, if sonic access tubes are
installed only in the top part of bored piles, the costs associated with both the material and test process
itself would be significantly reduced and integrity testing by sonic logging method would be more
feasible. According to the authors experience from over 5,000 exposed bored piles in Bangkok subsoil, to
achieve good pile head condition within design cut-off level, bored piles constructed under polymer-based
slurry require shorter overcast lengths than those constructed under pure bentonite slurry. In authors
opinion, the tolerable overcast lengths of bored piles constructed under polymer-based slurry should be
less than those specified in Table 2. Two cases were studied to determine the common depth of significant
anomaly (Category C or D) of bored piles in Bangkok subsoil.
5.1 Case 1
According to the sonic logging test results obtained from 400 piles of diameter 1.50m with depth over
50m constructed under polymer-based slurry in Bangkok, only 2 piles (0.5% of total contract piles) were
detected with C Category in the design pile length. The level of the detected C category for these 2 piles
449
was found to be within 2m below cut-off level of the pile. The overcast length above cut-off level of 95%
of piles were within 2.5m.
5.2 Case 2
The sonic logging test conducted on 174 bored piles of diameter 1.0m with depth over 50m constructed
under polymer-based slurry reveals that no pile was detected with C category below the cut-off level. The
overcast length of 76% of piles were within 2.2m above design cut-off level.
Table 3. Summary of sonic test results from 2 cases bored piles constructed under polymer-based slurry
in Bangkok
Case
Total no. Pile diameter Number of piles detected with C
Maximum overcast
category below design cut-off level length of majority of pile
of piles
/ depth
by sonic logging test
from sonic logging test
result
(pile)
(%)
Case 1
400
1.50m / 52m
2
0.5
2.5m (95%)
Case 2
174
1.0 m / 50m
0
0
2.2m (76%)
This finding suggests that contaminated concrete rarely occur below the cut-off level if overcast length of
the pile is about 2.5m for polymer-based bored piles. Quality control of the construction process such as
slurry mixing process and composition, properties of slurry, base cleaning, maintaining adequate tremie
length, concrete quality and concreting procedure however must be according to the standard practice to
achieve this result. Practical application of polymer-based slurry for deep-seated wet-processed bored
piles in multi-layered soil of Bangkok has been reported by Thasnanipan et. al. (2003).
Contaminated
concrete only
found at top 1m
Figure 3. View of polymer-based bored pile diameter 1.8m with overcast length about 2m contaminated
concrete was found only at the pile top
6. QUANTIFYING THE PILE HEAD CONDITION BY SONIC LOGGING TEST PRIOR TO
BASEMENT EXCAVATION
Designs of the modern buildings in Bangkok frequently call for the basement facility which require design
cut-off level of the piles well below the existing ground level. In wet process bored piles construction, it is
necessary that concrete is continued to be placed until good quality of concrete is formed above the design
pile cut-off level to avoid contamination of slurry within the design pile length. Controlling the excessive
overcast length to maintain the appropriate pile top level is one of the most difficult task particularly for
the piles with low cut-off level. Checking the condition of concrete at the top part of the piles prior to
exposing the pile head for pile cap construction or basement excavation by direct inspection is impossible.
450
If the pile head condition of recently cast bored piles could be justified in the initial stage of the project, it
would be better and easier for the piling engineers to efficiently decide the optimum overcast length of the
pile which in turn would provide effective saving of unnecessary concrete consumption. Cross-hole sonic
logging test as an early indicator may be the ideal method to check the optimum overcast length of
recently constructed bored piles in controlling the excessive overcast length.
Sonic logging test could also be used as a performance-indicator for the piling contractor. In one major
project, during the excavation works for 8 to 10m deep basement construction, the main contractor
claimed that over 50% of exposed bored piles from total 174 contract piles were found to be with
excessive overcast length (over 4 to 6m from design pile cut-off level). All bored piles in this project were
constructed under polymer-based slurry and sonic logging test was conducted on every pile. The piling
contractor carefully reviewed all the sonic logging test results and found the followings;
76% of piles were within 2.2m overcast length
18% of pile were with overcast length between 2.2m and 3m
Only 10 piles (5%) exceeded overcast length of 3m.
Over 4m to 6m overcast length claimed by the main contractor was caused by the solid-like mixture of
backfill material mixed with highly contaminated concrete at the top of the piles as boreholes were
backfilled with crushed-rocks. Figure 4 shows the typical sonic logging test results of one of the piles
claimed by the main contractor as excessively overcast piles. As can be seen in the figure, homogenous
concrete was detected only up to 2m above design cut-off level whereas non-homogeneous (Category C or
D) was observed above 2m. Field observation also confirmed that majority of piles were with highly
contaminated at top 2m above design cut-off level. The main contractor finally accepted the proof of sonic
logging test result to justify the overcast length.
451
Carefully check and use the required temporary casing length considering the thickness of soft
clay layer (common thickness of Bangkok soft clay layer is 15 to 18m)
Pre-install the sonic logging access tubes covering only the top 15m for majority of the piles.
Small percentage of piles may have full length of sonic access tubes to the pile tip to randomly
check the integrity of the entire pile shaft
Check the borehole profile of each pile by drilling monitor (koden equipment) to roughly assess
the required concrete volume (to check the size and shape of borehole by drilling monitor to
estimate required concrete volume)
Strictly follow and control the slurry mixing process, slurry properties and quality check test
Use appropriate concrete mix with good quality and strictly follow and control the tremie
concreting process
Carefully withdraw the temporary casing
Construct the pile of higher design cut-off level first (if possible) and perform the sonic logging
test 10 days after concreting
If possible (for high cut-off level piles or cut-off level within 3m below existing ground)
excavate with sufficient support to visually inspect the pile head and compare with sonic logging
test. This process may not be necessary though it will be very useful to assess the sonic logging
test result to correlate with actual condition of pile top at early stage of pile construction
The piling engineer must carefully review the borehole profile, actually poured concrete volume
and sonic logging test of each completed pile to assess and justify the construction method, site
characteristic and quality assurance procedure for further improvement
8. CONCLUSION
Cross-hole sonic logging test is a useful quality control test to examine the integrity of the wet-process
bored piles in early stage of the project. Discontinuity in the form of contaminated concrete in the lower
part of pile shaft rarely occurs in these days as construction method and quality control process for wet
process bored piles have been well established in local construction industry in Thailand,. Therefore, it is
recommended that sonic logging test should be mainly used to investigate the integrity of the pile at the
top portion and a random check is performed only for few piles to examine the integrity of entire pile
shaft. An extended application of cross-hole sonic logging test in quantifying pile head condition prior to
exposing the pile has been presented. The piling engineers should pay more attention to control the
excessive overcast length to minimize the cost associated with cutting extra length of pile head and
disposal of the waste. The piling engineers should be trained to effectively apply the sonic logging method
not only as integrity-proof test but also as a tool to quantify the pile head condition at the early stage of the
piling work.
REFERENCES
Institution of Civil Engineers, 1996. Specifications for piling and embedded retaining walls, The
Institution of Civil Engineers and Crown, Thomas Telford Services Ltd. London, United Kingdom
Ng, K. C. 1983. The construction problem and performance of large bored piles in second sand layer, M.
Eng. Thesis No. GT 82-26, Asian Institute of Technology, Bangkok, Thailand
STS Instruments Company Limited, 2004. Proposal for sonic logging test (unpublished), Method
Statement for Performing and Interpretation of cross-hole sonic logging test submitted to SEAFCO Public
Company Limited, Bangkok, Thailand
Narong Thasnanipan, Zaw Zaw Aye, Thayanan Boonyarak, 2003. Behaviour of Polymer-based Slurry for
Deep-seated Bored Piles in Multi-layered Soil of Bangkok, Proceedings of the Fourth International
Geotechnical Seminar on Deep Foundation on Bored and Auger Piles, Ghent, Belgium.
452
Emerging Technologies
Natamon Kampananon
STS Instrument Co., Ltd.
453
EXISTING
10
Bangkok Soft
Clay
Medium to
Stiff Clay
30
Medium
Dense Sand
(First Sand)
40
Hard Clay
50
Dense to Very
Dense Sand
(Second Sand)
Depth (m)
200
400
600
10
20
60
0
0
Weathered Crust
30
SPT-N= 20-40
t = 20kN/m 3
SPT-N= 50-100
t = 21KN/m 3
40
50
Line
atic
rost
Line
Hyd
wn
wdo
Dra
etric
zom
AND
Pie
ual
Act
Due to the prevailing condition of subsoil deepseated large diameter bored piles of over 50 m
depth with 0.8 - 1.8m in diameter are mainly
used for heavy structures such as high rise
buildings, elevated expressways, flyovers or
overpass bridges and more recently for
underground subway stations of the first
Bangkok MRTA system. As a part of preplanned quality assurance regime and
retrospective investigation, integrity of the piles
are tested to obtain the information with regard
to the potential deficiencies of the constructed
piles which may have formed during actual pile
construction process or may have been
attributed by other activities after construction of
the piles. Three techniques namely sonic
integrity, sonic logging and high strain dynamic
load tests are the commonly used nondestructive integrity tests applied in Bangkok,
Thailand. The effectiveness and suitability in
terms of both cost and method of application
itself are the primary reasons of the greatest
growth in use of these tests.
SUBSOIL
PROFILE
Geotechnical
Parameters
60
PIEZOMETRIC
455
CONSTRUCTION METHOD
Due to the prevailing subsoil and groundwater
conditions, deep-seated bored piles of toe depth
over 24m are constructed by wet-process or
slurry displacement method using rotary drilling
machine. A temporary casing of appropriate
length (12 to 18m in Bangkok depending on the
thickness of soft clay) with required diameter (internal diameter not less than that of design
bored pile diameter) is first installed to ensure
the stability of the borehole in the top soft or
loose soil layers. In some projects where the vibration is strictly limited, a standard length of
casing with oscillator or short temporary casing
of 5 to 8 m is pushed down in combination with
the pre-boring process. Drilling is commenced by
auger to drill out the soil inside the temporary
casing. Auger-drilling is commonly continued up
to the top of the first water-bearing sand layer or
bottom of the casing when using the short casing
method. Drilling slurry or supporting fluid is then
supplied to the borehole and drilling is proceeded with a bucket down to the design final
depth of the pile. Before lowering the reinforcement cage, a special cleaning bucket is used to
clean the base of borehole. If bentonite slurry is
used, recycling method by air-lift or pump is applied as the base cleaning process. Reinforcement cages are then lowered into the borehole
and concreting is carried out by tremie method.
Type of Defect
Causes
Poor concrete
at pile top (03m)
0.1
Size reduction
Cracks/discont
inuities
456
1.0
2.2
457
Med.
Clay
Soft Clay
10.5cm/s
0
Pile 30
2 Jul 97
12
15
18
21
24
27
4000 m/s
exp: 20
30
V2-88c
Sr
f:8
SOFT CLAY
MEDIUM CLAY
STIFF CLAY
SAND
crack induced
by large lateral
movement
crack induced
by sliding
failure
crack induced
by uplift
force
14.2 cm/s
Pile 1
24 Apr 97
12
16
20
24
4000 m/s
exp: 20
28
32
36
40
f:8
V2-88c
Sr
458
7.6 cm/s
0
12
16
20
Pile 1 #
4000 m/s
2 Jun 97
exp: 20
24
28
32
36
40
V2-88c
f:8
Sr
Figure 5.
Sonic integrity test shows the
discontinuity at 11.0m has been closed by
grouting
CROSS-HOLE SONIC LOGGING TEST
Cross-hole sonic logging test can mainly be applied as a pre-planed site quality control testing.
Use of Sonic logging test for checking pile integrity has increased in Thailand in recent years. It
is used for cast-in-place foundation elements
such as bored piles, barrettes, diaphragm walls
and caissons. Both PVC and steel tubes can be
used as access tubes. Though cost of steel tube
is higher than that of PVC, steel tubes are considered more suitable than PVC tubes for two
reasons; (1) less potential for bending and damage especially for deep-seated bored piles and
barrettes with heavy steel reinforcement and (2)
better bonding with concrete. These access
tubes are sometimes also used for pile base
grouting. The access tubes are attached to the
reinforcement cage, which is installed prior to
concreting as a normal practice for cast-in-place
piling. Two access tubes are required as a minimum for cross-hole sonic logging test. For a
good coverage of the test pile, recommended
number of tubes for different sizes of bored piles
is shown in Table 4.
results and
Integrity
Homogeneous
concrete
Minor
increase
in
transmission
time
>10% but <25%
Minor anomaly
Transmission
time
more than Category B
but transmission time
can still be defined
Major anomaly
Defect
180
750<D 1000
120
1000<D 1500
90
1500< D
2500
60
2500 < D
45
459
Settlem ent (m m )
-5
-10
-15
20
40
60
Load (ton)
80
100
Settlem ent (m m )
-5
-10
-15
Dynamic load test
Static load test
-20
0
200
400
Load (ton)
600
800
Vasinvarthana
and
Kampananon
(1997)
presented the efficiency and reliability of
dynamic load test carried out in Bangkok.
Figures 7 and 8 show the load settlement curves
of dynamic and static load tests conducted in
Bangkok on large and small diameter piles
respectively. As can be seen in the figures,
load-settlement characteristics obtained from
dynamic load test agree well with those of static
load test for both large and small diameter bored
piles.
460
Dense Sand
6.2 cm/s
0
12
18
24
Pile 681
8 Apr 96
30
36
42
4000 m/s
exp: 20
48
54
60
V2-88c
f:8
Sr
1500
Ton
750
10
20
30
1
40
2
50
3
ms
L/c
-750
30
Ton / m
Pile
Shaft Resistance
Distribution
(Toe 178.8 Ton)
Pile Forces at Rut
1000
Ton
CONCLUSIONS
Integrity tests commonly applied for large
diameter bored piles in Bangkok are presented
highlighting the advantages and limitations of
each method. It is to be emphasized that
integrity test are highly dependent on the
experience of the testing firm in both field testing
and interpretation.
Interpretation should be
made with sound knowledge of pile construction
technique, subsoil condition and other factors
such as problem encountered during and post
pile construction which may influence the test
results and interpretation.
Pile construction
records are also useful in interpretation of the
piles with detected anomaly. Conclusion should
be made after careful and thorough review of
test results in conjunction with other available
461
462
463
465
466
23.2m
11.0cm/s
0
5.3cm/s
0
10
15
20
Pile G30
27 Jan 97
25
30
4000 m/s
exp: 20
35
40
45
f:8
50
12
15
18
Pile 6
4000m/s
12 Sep 95
exp: 20
21
24
27
V2-88c
30
f:8
Sr
V2-88c
Sr
22.0m
7.1cm/s
0
12
15
18
Pile 24
4000m/s
12 Sep 95
exp: 20
21
24
27
V2-88c
30
f:8
Sr
52.0m
16.0cm/
s
0
12
18
24
pile 30
14 Jan 91
30
36
42
48
54
f:8
4000m/s
exp: 20
60
10.6cm/s
0
Pile 49
19 Sep 95
12
15
18
4000 m/s
exp: 20
21
24
27
f:8
30
Sr
Soft Clay
Med.
Clay
Soft Clay
v2-88c
V2-88c
Sr
467
10.5cm/s
0
Pile 30
2 Jul 97
12
15
4000 m/s
exp: 20
18
21
24
27
f:8
30
V2-88c
Sr
Med.
clay Stiff clay
Dense sand
Temporary casing
bottom level
4.3cm/s
0
Pile 66
25 Jun 97
12
10
15
20
25
4000 m/s
25 Nov 94
exp: 20
30
35
40
45
50
V2-88c
f:8
Sr
Nominal dia./dia. of
drilling tool
Outer diameter of
casing collar
11.0 cm/s
Pile 99
15
18
4000 m/s
exp : 20
21
24
27
f: 8
30 v2-88c
sr
Soft Clay
Dense Sand
Figure 9B. Uniform pile size along the pile shaft is shown by
both drilling monitoring record and sonic integrity test record.
(Pile 0.80mx42.0m, cutoff -3.0m, toe depth 45.0m.)
Dense Sand
5.4cm/s
0
10
Pile 322
10 Jan 95
15
20
25
30
35
4000 m/s
exp: 20
40
45
f : 8
50
V2-88c
Sr
6.2 cm/s
0
Pile 681
8 Apr 96
12
18
24
30
4000 m/s
exp: 20
36
42
48
54
f:8
60
V2-88c
Sr
Soft Clay
Med.
Clay
Stiff to
Hard Clay
Dense Stiff
Sand Clay
Dense Sand
468
14.2 cm/s
Pile 1
12
16
24 Apr 97
20
24
4000 m/s
exp: 20
28
32
36
40
f:8
V2-88c
Sr
7.6 cm/s
0
12
16
20
Pile 1 #
4000 m/s
2 Jun 97
exp: 20
24
28
32
36
40
f:8
V2-88c
Sr
8.9 cm/s
0
12
15
Pile 50
4000 m/s
4 Apr 97
exp: 20
18
21
24
27
f:8
30
V2-88c
Sr
469
470
Bridge
Old building
Building near Pile
Driving
2
47
1
15
145
30
6 CONCLUSIONS
ACKNOWLEDGEMENT
The authors wish to express their appreciation to
EDE Co., Ltd. and STS Engineering Consultants
Co., Ltd. for providing the test data and project
information.
REFERENCES
Figure 14.
1987)
471
Dhiraj Karki
Christian Schulz
473
Ground Movement Prediction and Building Damage RiskAssessment for the Deep Excavations and Tunneling Works in
Bangkok Subsoil
Zaw Zaw Aye1 , Dhiraj Karki2 and Christian Schulz3
1
ABSTRACT
This paper presents the methods adopted in prediction of excavation and tunneling induced
ground movement and building damage risk-assessment carried out for the Contract No. 1 of
the M.R.T Chaloem Ratchamongkhon Line, the first underground mass transit system project
of Bangkok. The measured ground and associated movement of the buildings and structures
were within predicted values. All deep excavation works and tunneling were successfully
completed without any significant damages to the adjacent buildings and structures.
1. PROJECT OVERVIEW
The M.R.T Chaloem Ratchamongkhon Line is the first underground mass transit system
project in Bangkok developed by the Mass Rapid Transit Authority (MRTA) of Thailand.
Total length of the underground structure is 21.5km, comprises of 16 km of twin single-track
bored-tunnel, a total of 4 km long18 cut- and-cover stations, a twin 1.5km long cut-and-cover
approach tunnel to Depot and other associated structures. The project was commenced in late
1996 and opened for the public in 2004. The Contract No. 1, Underground Structure South southern portion of this initial system comprising 9 km of twin 6m outside diameter bored
tunnels, nine underground stations and cut-and-cover depot approach tunnel, was awarded to
the Joint Venture BCKT consisting of Bilfinger + Berger Bauaktiengesellschaft, Ch
Karnchang Public Company Limited, Kumagai Gumi Company Limited and Tokyu
Construction Company Limited. Figure 1 shows the full length of the Contract No. 1 in
simple schematic layout.
One of the major challenges of the Contract No. 1was the need of stacked-alignment
for a major portion of twin bored-tunnel underneath Rama IV road, one of the busiest roads of
Bangkok, which called for a stacked configuration at 3 stations, Lumpini, Si Lom and Sam
Yan. This requirement led the contractor to design and construct the deepest underground
structures of Bangkok at Si Lom Station - four-floor stacked-station of 32m deep right under
the existing flyover and adjacent to a number of sensitive structures. Deep excavation and
bored tunneling works in congested urban environment of Metropolitan Bangkok requires a
systematic process of ground movement prediction, building risk damage assessment and
protection. This paper presents the methods adopted in prediction of excavation and tunneling
induced ground movement and building damage risk-assessment carried out for the Contract
No. 1.
475
2. SUBSOIL CONDITIONS
Similar to other localities in Bangkok, a typical subsoil profile along the tunnel alignment is
characterized by the alternating layers of clay and sand deposits as shown in Figure 1.
Weathered crust of 2 m thick is commonly found as the top layer. In urban areas of Bangkok,
this layer is covered by fill material. Soft to very soft, highly compressible dark gray marine
clay lies beneath weathered crust or fill. Depending on the location, this layer extends up to
12-16 m. About 2 m thick medium clay layer can be observed between soft clay and
underlying stiff clay. Generally stiff Clay layer occurs directly underneath medium clay and
its depth goes up to 22 m. Below stiff clay layer, first sand layer of 5-8 m thickness can be
found. This first sand layer, however, is absent in some areas. Stiff to hard clay layer
underlies first sand and it is found to be about 5 m thick. Second sand layer generally occurs
at depths between 45 to 65 m.
Figure 1. Generalized soil profile along the tunnel alignment and stations
3. OVERVIEW OF GROUND MOVEMENT PREDICTION AND BUILDING
Staged Assessment for each station and tunnel sections was carried out according to the
requirement stipulated in the Outline Contract Design Specification (OCDS). Specified
references were used as basic literatures in ground movement prediction and building damage
assessment. For cut-and-cover excavation zone, the work of Peck (1969) and Clough and
ORourke (1990) were used whereas published papers of Burland et. al. (1977) and Boscardin
& Cording (1989) were applied for bored tunnels. Building damage assessment was carried
out in 3 stages; Stage 1 Assessment, Stage 2 Assessment, and Stage 3 Assessment.
476
Greenfield Site assumption was adopted in Stage 1 and 2 Assessment ignoring any
influence of the stiffness of the structure and type of supporting foundation. Stage 2
Assessment was further extended by Additional Stage 2 Assessment. In Additional Stage 2
assessment, the variation of settlement trough shape and magnitude with depth were
considered in identifying the risk of building damage. In Stage 3 assessment, a detailed
qualitative assessment of structure and vulnerability of each building or structure to damage
were taken into account, coupled with detailed structural analysis in assessing the buildings
falling in risk category 3 classified by Mair et. al. (1996).
Table 1: Building Damage Classification (after Burland et. al., 1977 and Boscarding and
Cording, 1989)
Risk
Category
Degree of
Damage
Negligible
Hairline cracks
Very Slight
Slight
Moderate
Severe
Very
Severe
Approximate
Crack Width
(mm)
0.1 to 1
1 to 5
5 to 15 or a number
of cracks greater
than 3
15 to 25 but also
depends on number
of cracks
Max.
Tensile
Strain %
Less than
0.05
0.05 to
0.075
0.075 to
0.15
0.15 to
0.3
Greater
than
0.3
Instrumentation played a major role in the construction of this first underground mass transit
system project in congestive urban area with difficult soil condition. The primary objective of
the instrumentation program was to monitor the performance of the deep excavation and
tunneling operation to ensure safe execution of the construction works and that adjacent
structures were not adversely affected. Furthermore, the instrumentation program was
established to provide feedback in application of the observational method. Extensive sets of
instrumentation were installed around the predefined influence zones of station box
excavation, tunneling and associated building, structures and utilities. In addition to other
geotechnical instruments, inclinometers, extensometers, various types of settlement points,
tile-meter, crack meter and crack gauge were installed to monitor the ground and associated
building and structures movement.
5. BUILDING CONDITION SURVEY
477
Prior to commencement of the major works, all the existing buildings and structures within
the predefined influence zone were systematically surveyed. The primary objectives of the
surveys were;
To record pre-construction status of all buildings and structures within the influence
zone. The records included were age of building, building type, storey height,
expected foundation types, visible defects supported by sketches and photographs as
appropriate
To utilize the information collected from the building / structure condition survey in
the assessment of the buildings and evaluate sensitive structures with respect to
construction aspects and monitoring
To establish a benchmark to monitor the possible effect of construction.
Expected foundation types of different buildings were classified based on the height,
number of floors and age of the buildings. Building survey information was also used to
identify the types of instrumentation required.
6. PREDICTION OF GROUND MOVEMENT INDUCED BY STATION EXCAVATION
WORKS AND BUILDING DAMAGE ASSESSMENT
ENTRANCE B
ENTRANCE A
STATION
ENTRANCE C
40
30
20
10
478
Figure 2. Settlement contour in station excavation zone prepared for stage 1 assessment
Buildings falling outside 10mm settlement contour were eliminated from further
assessment. Remaining buildings with settlement greater than 10mm were short-listed for
Stage 2 Assessment.
6.3 Stage 2 Assessment
The dimensionless settlement profile for the station box construction were fitted using a
polynomial curve to identify the point of inflexion and divide the settlement profile into
sagging and hogging zone and calculated the tensile strain induced in the buildings from
excavation works using the method proposed by Mair et. al. (1996). The results were then
used to identify the category of risk to damage according to the classification of Building
Damage Classification presented in Table 1. Buildings classified within Slight risk category
of damage were eliminated from further assessment. Buildings falling into Moderate or
higher risk category of damage were further evaluated.
6.4 Additional Stage 2 Assessment
The settlement estimated in Second Stage Assessment presented above was based on surface
movement. For the buildings located in close proximity to the excavation founded on piles, it
was considered that subsurface settlement may be more critical. Stage 2 Assessment was then
further extended by Additional Stage 2 Assessment in which the variation of settlement
trough shape and magnitude with depth were considered in identifying the risk of building
damage. Settlement of the buildings due to the excavation works were predicted assuming the
green filed condition. Neglecting restraints from foundation and structure, it was assumed
that buildings follow the ground settlement trough at foundation level (estimated pile tip
level).
Available methods were further reviewed for predicting the surface settlement with
the consideration of two main factors; (1) simple and practical in application (2) enable to
correlate with the predicted and measured diaphragm wall deflection. The method proposed
by Bowels (1988) was selected as it meets the required criteria mentioned above. Bowels
suggested the ground settlement induced by excavation as a function of ground loss due to the
deflection of the retaining wall. Bowel demonstrated the calculation of settlements at
specified distance by assuming parabolic variations of settlement within the influence
distance. Using predicted diaphragm wall deflection, surface settlement behind the
wall was computed by empirical formulas proposed by Bowels.
6.4.1 Prediction of vertical sub-surface settlement
A simplified prediction of subsurface settlement was carried out based on the calculated
surface settlement described above. First, subsurface settlement influence line was
constructed. As shown in Figure 3, settlement influence zone is assumed to decrease with
depth from Do at the surface and zero at the wall toe. With the assumption of linear
relationship between the volume of deflected wall shape and the volume of settlement trough
at any depth within settlement influence zone, subsurface settlement at different depths were
calculated.
479
W
Total deflected
shape volume, V O
S WO
Sio
HW
HE
Y
Swy
Sub-surface settlement
trough volume, VTy
Settlement
influence zone
deflected volumn V y at depth (H w- Y)
Siy
D-wall
DDoO== H2.5
W+ WHE
S WO =
4V O
DO
S io = S WO *
DO
D
DY = Y * O
HW
VTY = VY *
VTO
VO
Xi
Zi
D Oi =
Shi
S hi = S hwi *
Limit of
influence zone
D-wall
y
DO
* H Wi
HW
=
H Wi
HW Zi
Doi
Hwi
Hw
Shi
Shwi
Hg
Shwi
D Oi X i
D Oi
Deflection curve
extrapolated to zero
480
SV1
SV2
L
h = (Sh1 Sh2) / L
h
= average horizontal strain of building
Sh1
= horizontal displacement at surface at one end of the building
= horizontal displacement at surface at other end of the building
Sh2
L
= building length
Table 2 shows the summarized results of risk category obtained from two different methods
described above and assumed foundation types (without and with pile)
Table 2 Summary of risk category obtained from two different methods and foundation type
Building No. of Building
Block
stories Type
37
Masonry
Concrete
Masonry
Concrete
Masonry
Concrete
Masonry
Concrete
RC
Estimated
Pile Length
Distance
to edge
of wall
7-14m
18m
7-14m
17.5m
7-14m
32m
< 6m
2m
50m
8m
481
Risk category by
maximum tensile
strain
Without
With
pile
pile
0
0
Risk category by
chart of Boscarding
and Cording (1989)
Without
With
pile
pile
1
2
The predicted degree of damage of the buildings using simplified chart is more critical
than that of maximum tensile strain method as can be seen in above table. According to the
results obtained from of simplified chart, predicted degree of damage was higher if buildings
were assumed to be with piled foundation rather than without piled foundation.
6.5 Third Stage Assessment
Examples of the buildings and structures that required the stage 3 assessment as a result of
Stage 2 assessment are listed below.
Table 3 The buildings required Stage 3 Assessment in station excavation zones
No. of Storey /
Preliminary
Stage 2 Calculated Total
Risk Category /
Building Type
Estimated Pile Length
Tensile Strain (%)
Degree of Damage
4 / RC*
8m
0.121 %
2 / Slight
22 / RC
>22m
0.159 %
3 / Moderate
4 / RC
7-14m
0.197 %
3 / Moderate
2 / Steel Frame
15-22m
0.288 %
3 / Moderate
5 / RC, Masonry
15-22m
0.166 %
3 / Moderate
2 / RC, Masonry
<6m
0.29 %
3 / Moderate
3 / RC, Masonry
7-14m
0.242 %
3 / Moderate
1 / RC, Masonry
0.191 %
3 / Moderate
6m
* Stage 3 Assessment of this building was required due to the pre-existing damage of the building.
482
Horizontal Strain
Sh1
Sh2
(mm) (mm)
Settlement
31
Prediction
Actual
31*
Monitoring Data
L
(m)
Angular Distortion
Sv1 Sv2
S
(mm) (mm) (mm)
L
(m)
Risk
Category
Degree of
Damage
24
18.6 0.0004
48
23
25
18.60
0.0013
slight
24*
18.6
0.0004
*
53
14
39
18.60
0.0020
slight
*Predicted horizontal movement was used in computing horizontal strain for actual
miniotring data.
From the above table, following conclusions can be made.
Predicted angular distortion broadly agrees with that of actual monitoring data. Hence,
settlement prediction and assumed effective depth of piled foundation is fairly reasonable.
The settlement of actual monitroing data is slightly higher than that of prediction. This
may be due to the additional settlement caused by diaphragm wall panel construction
which influence zone might have extended to 15m from the diaphragm wall (equivalent
distance to bottom of soft clay level ).
Limiting values of the building slopes at two critical conditions specified by various
researchers as shown in the table below were also used in determining the potential building
damage of stage 3 assessment.
483
Type of Damage
1
2
Meyerhof
Polshin and
Tokar
Bjerrum
1/300 to 1/500
1/500
1/500
1/500
Structural Damage
1/150
1/250
1/200
1/150
Type of
bridge
Foundation Type
Hua Lamphong
Steel
Sam Yan
Thai-Japan Flyover
Steel
Si Lom
Thai-Japan Flyover
Steel
Lumphini
Thai-Belgium Flyover
Steel
Phetchaburi
Asok Flyover
Steel
Pre-cast pile
484
Stage 3 Assessments of above listed bridges were carried out by soil-structure interaction
analysis using finite element method. FEM Analyses were mainly carried out by in-house
design team consisted of experience geotechnical engineers of Tokyu Construction Company
Limited. Two-dimensional non-linear soil model applying Duncan-Chang parameters was
employed. The process involved in soil-structure analysis is presented in diagram as shown in
Figure 5.
Superstructure assessment
Pile Assessment
Structural analysis
Assessment
based on
differential
Settlement criteria
Assessment
based on
horizontal
movement criteria
Applied response
displacement
method
Verification of RC section of
pile
485
Extensive sets of instrumentation were installed including tilt meter, settlement points
and inclinometers. Monitoring was carried out in high frequency during critical stage of
excavation and compared with established trigger values.
486
south bound) was predicted independently and then superimposed to determine the total
settlement induced by the twin tunnels. 10mm and 25mm settlement contours were plotted in
the topographic plan with buildings and other structures including flyover and khlong bridges
in the tunnel alignment. Buildings falling outside 10mm settlement contours were eliminated
from further assessment. Remaining buildings with settlement greater than 10mm were shortlisted for stage 2 assessment.
7. 3 Stage 2 Assessment
The buildings and structures short-listed in stage 1 were assessed in this stage. Stage 2
assessment involves calculation of maximum tensile strain induced in the building and
structures due to tunnel boring and classification of risk category. Risk category of the
buildings was determined applying the method proposed by Mair et. al. (1996), similar to the
building damage assessment made for excavation induced settlement presented in earlier
sections.
7. 4 Additional Stage 2 Assessment in tunnel zones
As most of the buildings and structures in Bangkok along tunnel alignment are supported by
piled foundations, it was considered that Stage 2 Assessment using surface settlement profile
might be insufficient. Hence, Additional Stage 2 Assessment considering the variation of
settlement trough shape and magnitude with depth (subsurface settlement) was carried out for
the critical buildings.
In general, subsurface settlement trough will be narrower and steeper than those of the surface
as shown in the sketch below. A simple approach was used in predicting the subsurface
settlement profile with following assumptions.
(1) The shape of the subsurface settlement profile caused by the tunnel construction is
characterized by a Gaussian distribution similar to surface settlement profile.
(2) The ground settlement influence line for tunnel in clay is the same for subsurface as
shown in the figure below:
487
K = [0.14+0.26(1-z/z0)] / (1-z/z0)
By substituting K values for K in equation derived from Gaussian normal distribution curve
the subsurface settlement at required depth can be calculated.
7. 5 Stage 3 Assessment
7.5.1 Stage 3 Assessment for the buildings
The method used in Stage 3 Assessment of the buildings in tunnel zone was similar to that of
station excavation zone based on the superimposed predicted subsurface settlement trough
induced by twin tunnels.
7.5.2 Structures Required for Stage 3 Assessment
The most critical structure required for Stage 3 Assessment were MWA main water tunnel as
tunnel alignment crosses the water tunnels at two critical locations the first near Rama IV
and Rachadaphisek road intersection and the second at Rama IV and Siphraya road
intersection near Sam Yan station. The position of water tunnels in relation to MRT tunnels
drawn in the subsoil profile at relevant locations are presented in Figure 8 and 9.
Figure 8 Position of MWA water tunnel in relation to MRT tunnels (clear distance are 3.38m
and 3.18m for North and South bound respectively) at the first crossing
According to the available information, MWA tunnel at the first crossing is of 2.5m
internal diameter steel lining with 150mm segmental ring and at the second crossing MWA
tunnel is of 2.5m diameter segmental ring with lightly reinforced concrete lining.
In preliminary stage 3 assessment, based on the predicted subsurface profile using the
method described in earlier section, structural assessment of water main was carried out and
results were compared with structural capacity of water tunnel calculated from the material
properties indicated in the construction drawings provided by MWA. As bending moment
induced in the water tunnel was considered critical parameter in assessing the damage which
is governed by both maximum settlement and curvature of the water tunnel further assessment
was proposed.
488
To carry out back-calculation using monitoring data obtained from the settlement
arrays (settlement points, extensometer data) at first 3 locations before reaching to
MWWA water tunnel near Rama IV Rachadapisek intersection, to determine the
volume loss and relationship between surface and subsurface settlement as well as
best estimation of subsurface K value and subsurface settlement profile at water
tunnel level.
To perform beam-on-elastic foundation analysis using the subsurface settlement
profile obtained from above item (1) to determine bending moment likely to occur in
MWWA water tunnel.
To compare the result obtained from above item with allowable values.
To establish the final trigger values based on above comparison.
To confirm the settlement profile of last array is within the alert level of final trigger
value.
Figure 9 Position of MWA water tunnel in relation to MRT tunnels (clear distance are 1.5m
and 2m for North and South bound respectively) at the second crossing
For the first location of MRT-MWA tunnel crossing, target ground loss from tunnel
operation was set at 0.5%, whereas ground loss based on allowable movement curvature of
water tunnel derived from predicted pattern of subsurface settlement was 0.65%. Backcalculated ground loss derived from the monitoring data of rod-extensometer placed at the
crown of MWA water tunnel was within target value. In addition to the preliminary
assessment based on prediction of subsurface settlement using empirical formulas, a detailed
soil-structure interaction was analyzed by experience geotechnical engineers of Tokyu
Construction Company Limited using 2-dimensional FEM considering behavior of tunnel
boring by earth pressure balance (EPB) method. Stress relief from the effect of cutter-head,
tail void and over-cut from EPB tunnel boring was considered in the analyses. Adding ground
movement due to consolidation caused by disturbance from tunnel operation surface and
subsurface settlement were predicted by finite element analysis. Detailed parameters and
assumption made in analysis was presented in the published paper of Sakai & Sugden (2000).
After the successful passing of both tunnels at the first MWA crossing, another trial area
tunneling was planned to further determine the ground movement associated with various
tunneling parameters well before reaching to more critical crossing after Sam Yan station.
Tunnel section between Silom and Samyan station, in which soil profile similar to that of
second crossing was selected and comprehensive instrumentation program was established to
489
monitor surface and subsurface settlement as well as horizontal movement of the ground at
depth.
8. COMPARISON OF PREDICTION AND ACTUAL MONITORING RESULTS
The monitored ground deformation due to station box construction and bored tunneling were
compared with the predicted values for one of the station and tunnel sections to evaluate the
performance of the actual operation.
8.1 Ground Movement Induced by Excavation Works
The monitored wall deflections and ground settlement induced due to station constructions
works were within the design prediction. Adopted top-down method in excavation works of
station boxes utilizing rigid diaphragm wall extensively propped by stiff permanent slabs, was
the key factor contributed in minimizing associated ground movement and disturbance to
adjacent buildings and structures. Figure 10 shows the comparison of monitored wall
deflections with predicted values at final stages of station construction.
0
10
20
30
40
50
60
-10
70
100
95
95
Reduced Level (m)
-10
100
90
85
80
75
70
10
20
30
40
50
60
70
90
85
80
75
70
Deflection (mm )
Deflection (mm )
A mber_Co ncourse
Red_Co nco urse
M o nitored_Conco urse
A mber_B ase
Red_B ase
M onito red_B ase
Figure 10 Diaphragm wall deflection showing predicted trigger levels and monitored data for
final excavation stages to concourse and base slab level
The comparison of monitored and predicted ground settlement profile resulting from
station excavation is presented in Figure 11.
S urf a c e S e t t le m e nt P ro f ile B e hind D / Wa ll R e s ult ing f ro m S t a t io n
B o x E xc a v a t io n
20
10
0
-10
-1
-4
-9
-20
-4
-4
-2 -1
-2
-4
-15
-17
-22
-30
-30
-40
-50
-32
DW_East
-60
DW_West
-70
-60
-50
-40
-30
-20
-10
10
20
30
40
50
60
D is t a nc e , m
Initial Reading
M easured-End o f Ro o f Exc.
Figure 11 The comparison of monitored and predicted ground settlement profile resulting
from station excavation works
490
Monitored
-60
-25
-20
-15
-10
-5
Predicted
SB
NB
-70
10
15
20
25
D is t a nc e , m
Figure 12 Predicted and observed ground settlement profile due to tunnel boring
Distance (m)
10
20
30
40
50
60
70
80
-10
Settlement _ NB Tunnel
-30
Settlement_SB Tunnel
Total Settlement
-50
491
90
The M.R.T Chaloem Ratchamongkhon Line, one of the most modern underground mass
transit systems in the region was successfully completed and has been in operation for over 1
year. Ground movement prediction and the detailed stage assessment carried out in the M.R.T
Chaloem Ratchamongkhon Line are presented. The measured ground and associated
movement of the buildings and structures were within predicted values. All deep excavation
works and tunneling were successfully completed without any significant damages to the
adjacent buildings and structures. Well organized plan, systematic approach of observational
method to achieve control values backup by extensive instrumentation and close co-operation
among relevant personnel were the key factors contributed to successful completion of the
project. The purpose of this paper however is not to extol success but to provide a set of
technical guidelines for ground movement prediction and building damage risk assessment of
deep excavation and tunneling works in Bangkok subsoil which may partly serve as a
reference for the future underground mass transit system projects in urban area of Bangkok.
Successful completion of the first MRT project in Bangkok marked the practicality of wellexecuted deep excavation works and tunneling by EPB method in protecting the sensitive
urban environment.
10. ACKNOWLEDGEMENT
The authors wish to express their appreciation to Mass Rapid Transit Authority (MRTA) for
permission to publish this paper. The authors would like to thank Construction Supervision
Consultants (CSC 1 Consortium) and Project Management Consultant (MPMC) for their
cooperation. Valuable advice and support given by Dr. D. J. Maconochie (CSC Consortium)
and Mr. A. J. Polley (former geotechnical advisor, Sindhu Maunsell Consultants) are
gratefully acknowledge.
11. REFERENCES
Boscarding, M.D. and Cording, E.G. (1989), Building Response to Excavation-Induced
Settlement. Journal of Geotechnical Engineering, ASCE, 115;1;1-21
Bowels J.E (1988) Foundation Analysis and Design, 4th Edition, McGRAW-Hill International
Book Company, Singapore, 1988
Burland, J.B., and Wroth, C.P. (1974), Settlement of Buildings and Associated Damage.
SOA Review, Conference on Settlement of Structures, Cambridge, Pentech Press.
London, pp. 611-654
Burland J.B., Broms J.B. and de Mello VFB (1977), Behavior of Foundations and Structures,
SOA Report Session 2, Proceedings of 9th International Conference, SMFE, Tokyo,
2:495-546
Clough, G.W., and ORourke, T.D., (1990), Construction Induced Movements of In-situ
Walls, ASCE Geotechnical Special Publication No. 25, pp. 439-470
Clough C.W. and T.D. ORourke (1990), Deep Excavation and Tunneling, 7th ICSME,
Mexico City
492
JV BCKT, (1997) Geotechnical Interpretation Report (GIR) for MRTA Initial System UGS, Bangkok
Mair, R.J., Taylor, R.N., and Burland, J.B., (1996), Prediction of Ground Movements and
Assessment of Risk of Building Damage. Geotechnical Aspects of Underground
Construction in Soft Ground, pp. 712-718, Balkema, Rotterdam
OReilly M.P and New B.M (1982), Settlements above tunnels in United Kingdom their
magnitude and prediction, Tunneling 82, pp. 173-181, London, IMM
Peck R.B. , (1969) Deep Excavation and Tunneling in Soft Ground, 7th ICSME, Mexico City,
State of the Art 3, 225-290
Petros P. Xanthakos (1995) Bridge Substructure and Foundation Design, Prentice Hall
PTR, USA, 1995
493
495
497
OPENING
OPENING
OPENING
498
SIRIPONG ROAD
OPENING
OPENING
OPENING
SHOP-HOUSES
SHOP-HOUSES
DINGSOR ROAD
OPENING
SHOP-HOUSES
OPENING
MAHUNNOP ROAD
I-5
I-4
N O R T H D -W A L L
I-6
EAST D-WALL
WEST D-WALL
PH A S E 2
S H E E T PIL E
124 m
S ee d etails in (b )
I-3
I-1
PH A S E 1
S O U T H D -W A L L
I-2
78 m
(a)
D IA P H R A G M W A L L
RC BUTTRESS
BARRETTE
W ALE BEAM
0 .3 0
T IE B E A M
P IL E C A P
SLA B
(b)
+0.20 ROOF SLAB
0.00
CAPPING
BEAM
RC BUTTRESS
G.W.L
2
SOFT CLAY
-9m
-12m
TIE
BEAM
2
WALE
BEAM
SOFT CLAY
DIAPHRAGM
WALL (tip=-16m)
MEDIUM CLAY
STIFF CLAY
-15m
-16m
-20m.
FOUNDATION PILES
DIA. 600mm (tip=-20m)
BARRETTE
(tip=-20m)
-20m.
499
establishing the design principles and sequence of construction. The architectural and utility
aspects of the project called for the design of the basement with a number of openings from
the ground surface to the final basement slab level to facilitate the ventilation system as
shown in figure 2.
Hence the roof slab can not be physically utilized as bracing in most of the area where
the diaphragm wall is to be acting as a cantilever retaining wall in the permanent stage. It was
analyzed in the preliminary analyses that the deflection of the diaphragm wall of 0.60 m width
would be large if it was to be fully cantilevered. As the project is located in a sensitive area,
ground movement induced by large deflection was unfavorable. It was therefore decided to
use buttress to minimize the diaphragm wall deflection as shown in figure 2.
Diaphragm Walls Barrettes and Bored Piles Construction
Diaphragm wall having 600mm width founded at 16m below ground level (B.G.L) was
constructed simultaneously with dry-processed bored piles of diameter 600mm with toe depth
20m below ground level. Barrettes having same toe depth as bored piles were installed at 8m
spacing along with diaphragm wall panels. Sheet pile wall (14m deep) was used as a
temporary retaining wall at the boundary of Phase 1 and 2 as shown in Fig. 3.
Subsoil Condition and Design Parameters
Typical subsoil profile at the site is characterized by thick Bangkok soft clay layer at the
top followed by thin layer of medium clay, and stiff clay layers.
Undrained Shear Strength (kN/m2)
10
15
20
Soft clay
35
Stiff clay
Very Stiff clay
50
150
20
40
60
SPT N-Value (blows / ft)
200
5.00
15.00
20.00
25.00
Medium Dense
Sand
30.00
35.00
40.00
40
45
100
25
30
50
0.00
0
5
Dense sand
45.00
50.00
Su BH-1
Su BH-3
SPT BH-1
SPT BH-3
500
Su BH-2
Design (Su)
SPT BH-2
Design (SPT)
80
Undrained shear strength (Su) and SPT N-value obtained from 3 SI boreholes were
plotted and design line was derived as shown in Fig. 3. The design soil parameters are
tabulated in Table 1.
Table 1. Design soil parameters
Soil Type
Depth
(m)
Su
(kN/m2)
Soft clay
s
(kN/m3)
Eu
(kN/m2)
0-9
16.50
18
7000
9 12
17.50
30
19250
12 15
19.00
60
45000
15 - 26
19.50
80
60000
Medium clay
Stiff Clay
Very stiff clay
HORIZONTAL STRUT
SLAB
D-WALL
RAKING STRUT
D-WALL
BARRETTE
-16m
BERM
BORED PILE
-20m
Fig. 4. Tender stage bracing system diaphragm wall was designed with soil-berm and 2
struts support (horizontal bracing and raker)
Value Engineering Option for Phase 1
Value engineering review of the temporary works was undertaken by the contractors
new in-house design engineering team prior to the commencement of Phase 1 excavation
works. Rigorous attention to detail of the design concept and constructability was made in the
pre-construction discussions between design engineers and construction team.
501
The main objectives for value engineering options were to minimize the material and
construction sequence involved in temporary works so as to accelerate the excavation time
thereby saving overall costs. without compromising the safety aspect.
After conducting a
series of re-analyses with different conditions major modifications were made : (1) To lower
the first strut level to 1.8m from the original tender stage design level 1.0m (2) To use only
1 temporary strut, omitting second level raking strut with the provision of sloping soil berm
against diaphragm walls. Soil berm was to remove after completion of base slab construction
in the majority of area minimizing the elapsed time of partially un-strutted diaphragm wall
between temporary strut and the final excavation level. Modified bracing system of Phase 1 as
an outcome of value engineering review is illustrated in Fig. 5.
HORIZONTAL STRUT
SLAB
HORIZONTAL STRUT
SLAB
BERM
D-WALL
RAKING STRUT
BARRETTE
-16m
SHEET PILE
-20m
-20m
BORED PILE
Fig. 5.
-14m
-16m
502
actual deflection of diaphragm wall reaches maximum acceptable limit), the observational
method was implemented on the followings basis.
Reviewed the design parameters together with critical conditions posed on sites as well as
most critical stage in excavation and basement construction work
Predicted the performance of diaphragm wall with most probable as well as most
unfavorableconditions and parameters.
Established the trigger criteria based on predicted diaphragm wall deflection
Predefined the practical contingency plan for most unfavorable conditions where wall
deflection reaches trigger levels
Set out the instrumentation program with the consideration of above factors
Monitored the performance of diaphragm wall. Compared the monitoring results with the
predicted and trigger values and reassessed
Implemented the contingency measures if monitoring result reaches action level of trigger
values
Figure 6 shows the predicted diaphragm wall lateral displacement or deflection of
Phase 1 (east, west and south diaphragm wall) at two conditions together with trigger levels
and tender stage prediction. It should be noted that the diaphragm wall deflection was
predicted to be maximum or most critical after removing the horizontal temporary strut.
Cum. Displacement , mm.
0
0
2
20
NORMAL
40
60
ALARM
80
100
ACTION
MOST
PROBABLE
PREDICTION
Depth, m.
6
MOST
UNFAVORABLE
PREDICTION
8
10
12
14
16
18
20
Tender Stage
Prediction with buttress :
Alarm Trigger Level
Prediction without buttress
Action Trigger Level
503
504
20
NORMAL
40
60
80
ALARM
100
ACTION
4
MOST
UNFAVORABLE
PREDICTION
Depth, m.
6
8
10
12
14
Stage 1
Stage 2
Stage 3
Stage 4
Stage 5
Tender Stage
16
18
20
Fig. 7. Phase 1 East Wall-Monitored diaphragm wall deflection at different stages with
trigger levels
505
20
40
60
80
100
0
NORMAL
ALARM
ACTION
4
6
MOST UNFAVORABLE
PREDICTION
Depth, m.
Stage 1
10
Stage 2
Stage 3
12
Stage 4
14
Stage 5
Tender Stage
16
18
20
Fig. 8. Phase 1 South Wall - Monitored diaphragm wall deflection at different stages with
trigger levels
Deflection profile of South diaphragm wall which braced against temporary sheet pile
wall at Phase 1 and 2 boundaries is presented in Fig. 8. As can be seen in Fig. 8, South
diaphragm wall deflection is significantly higher than that of east wall, which is likely to be
caused by the fact that South diaphragm wall is braced with more flexible sheet pile wall.
description of stages shown in the legend of Fig. 7 and 8 is summarized in Table 2.
Table 2. Description of stages shown in Fig. 7 & 8
Stage
Description
1
Excavate to 4m
Removal of berm
506
Fig. 9. Phase 1 excavation work in progress with historical Buddhist temple Wat Suthat in
background (Phase 2 area was being used as car parking space)
Modification of Phase 2 Bracing System
Monitoring results of the Phase 1 excavation work provided an ample opportunity to
review the design assumption, fine tune the parameters used in the analysis of the diaphragm
wall for the Phase 2 and made modification of construction sequence. The major
modifications are : (1) Removal of soil-berm at East and West diaphragm wall in shorter
duration than that of Phase 1, and (2) Using raking struts instead of horizontal strut for North
diaphragm wall a shown in Fig. 10.
HORIZONTAL STRUT
SLAB
COMPLETED PHASE 1
STRUCTURE
RAKING STRUT
SLAB
D-WALL
BERM
D-WALL
BARRETTE
-16m
BERM
-16m
-20m
-20m
EAST & WEST D-WALL
507
20
NORMAL
40
60
ALARM
80
100
ACTION
MOST PROBABLE PREDICTION
2
4
Depth, m.
6
MOST UNFAVORABLE
PREDICTION
8
Stage 1
10
Stage 2
12
Stage 3
Stage 4
14
Stage 5
16
18
20
Fig. 11 Phase 2 East Wall - Monitored diaphragm wall deflection at different stages with
trigger levels
With assurance of diaphragm wall performance from monitoring results of Phase 1,
original plan of using horizontal struts for North diaphragm wall was modified by using
raking struts instead. As can be seen in Fig. 12, deflection of North diaphragm wall (with
raking strut support) is significantly higher than that of East diaphragm wall (with horizontal
508
strut support). The main reason of larger movement of north diaphragm wall is due to the fact
that it was supported only by the berm for the long period (about 52 days) before completion
of raking struts so that soil-berm became soften during the long elapsed un-strutted period.
Time-dependent deflection pattern due to softening and deformation of soft clay can be
observed in North diaphragm wall as illustrated in Fig. 13. North diaphragm wall moved
progressively toward excavation before completion of raking struts (at 52 days) as can be seen
in Fig. 14.
Table 3. Description of stages shown in Fig. 11 & 12
Stage East Diaphragm wall
North Diaphragm wall
1
Excavate to 2.2m and installed
Excavate to 2.2m at d-wall, and to 6.6m
temporary strut
with sloping berm
2
3
4
Excavate to 4m
Excavate to 6.6m with berm
Removal of berm
20
40
60
80
NORMAL
100
ALARM
120
140
ACTION
2
4
Depth, m.
6
MOST UNFAVORABLE
PREDICTION
8
10
12
14
16
18
Stage 1
Stage 2
Stage 3
Stage 4
Alarm Trigger Level
Action Trigger Level
Prediction without buttress
20
Fig. 12. Phase 2 North Wall - Monitored diaphragm wall deflection at different stages with
trigger levels
509
Fig. 13. View of buttress-support diaphragm wall prior to temporary bracing removal
Cum. Displacement , mm.
0
20
40
60
80
0
2
4
Depth, m.
6
8
10
12
14
16
18
0 days
30 days
52 day
56 days
74 days
Prediction
20
Fig. 14. Phase 2 Time dependent wall deflection of North diaphragm wall diaphragm wall
was supported only by soil-berm for 52 days before completion of raker installation.
Implementation of Contingency Plan
Since deflection of North diaphragm wall (Phase 2) approached action trigger levels,
monitoring frequency was increased and the following contingency measures were
510
implemented on site.
Poured 15cm thick 1m wide lean concrete on the top of the berm along North diaphragm
wall to provide bearing-effect
Installed additional king-post and diagonal struts attached to the raking struts to provide
more rigid support against diaphragm wall
Soil-berm was removed locally in bays followed by construction of wale beam, tie beam
and buttress as shown in Fig. 15.
TIE BEAM CONSTRUCTED IN BAYS
TEMPORARY WALER
BUTTRESS
DIAGONAL STRUT
DIAPHRAGM WALL
TEMPORARY KING-POST
CAPPING BEAM
RAKER
BERM
TEMPORARY
STEEL BEAM
PILE
CAP
TED
PLE
COM
B
SLA
Fig. 16. View of raker and soil-berm support soil-berm was removed locally bay by bay
511
Fig. 17. View of buttress-support diaphragm wall after removal of temporary bracing
Time and Cost Saving from Value Engineering Options and the Application of
Observational Method
Significant cost and time saving were achieved from the value engineering option coupled
with observational method implemented for both Phase 1 and 2. The major savings were
achieved by less operation and material utilized in the following elements of temporary works.
Cancellation of 2nd level raking struts against diaphragm wall for both phases
Modification of bracing system using raking struts with soil-berm support instead of
horizontal struts for North diaphragm wall in Phase 2
512
important element in implementing the observational method. This case study reveals that a
thin permanent diaphragm wall coupled with effective design and construction method
supplemented by the observational method and robust monitoring program could offer a
logistically and financially attractive solution in construction of underground car park without
disturbing the environment in the prominent historical area of Bangkok.
CONTRACT 1 OF MRTA CHALOEM RATCHAMONGKHON LINE PROJECT
Observational method was applied mainly in building and structure damage assessment
in this Bangkok very first mass transit system project. The M.R.T Chaloem Ratchamongkhon
Line is the first underground mass transit system project in Bangkok developed by the Mass
Rapid Transit Authority (MRTA) of Thailand. Total length of the underground structure is
21.5km, comprises of 16 km of twin single-track bored-tunnel, a total of 4 km long18 cutand-cover stations, a twin 1.5km long cut-and-cover approach tunnel to Depot and other
associated structures. The project was commenced in late 1996 and opened for the public in
2004. The Contract No. 1, Underground Structure South - southern portion of this initial
system comprising 9 km of twin 6m outside diameter bored tunnels, nine underground
stations and cut-and-cover depot approach tunnel, was awarded to the Joint Venture BCKT
consisting of Bilfinger + Berger Bauaktiengesellschaft, Ch Karnchang Public Company
Limited, Kumagai Gumi Company Limited and Tokyu Construction Company Limited. The
project was commenced in late 1996, successfully completed and opened for the public in
2004.
One of the major challenges of the Contract No. 1was the need of stacked-alignment for
a major portion of twin bored-tunnel underneath Rama IV road, one of the busiest roads of
Bangkok, which called for a stacked configuration at 3 stations, Lumpini, Si Lom and Sam
Yan. This requirement led the contractor to design and construct the deepest underground
structures of Bangkok at Si Lom Station - four-floor stacked-station of 32m deep right under
the existing flyover and adjacent to a number of sensitive structures. Deep excavation and
bored tunneling works in congested urban environment of Metropolitan Bangkok requires a
systematic process of ground movement prediction, building risk damage assessment and
protection.
Subsoil Condition along Contract 1 Alignment
Similar to other localities in Bangkok, a typical subsoil profile along the tunnel
alignment is characterized by the alternating layers of clay and sand deposits as shown in
Figure 18. Weathered crust of 2 m thick is commonly found as the top layer. In urban areas
of Bangkok, this layer is covered by fill material. Soft to very soft, highly compressible dark
gray marine clay lies beneath weathered crust or fill. Depending on the location, this layer
extends up to 12-16 m. About 2 m thick medium clay layer can be observed between soft
clay and underlying stiff clay. Generally stiff Clay layer occurs directly underneath medium
clay and its depth goes up to 22 m. Below stiff clay layer, first sand layer of 5-8 m thickness
can be found. This first sand layer, however, is absent in some areas. Stiff to hard clay layer
underlies first sand and it is found to be about 5 m thick. Second sand layer generally occurs
at depths between 45 to 65 m.
513
Figure 18. Generalized soil profile along the tunnel alignment and stations
514
To record pre-construction status of all buildings and structures within the influence
zone. The records included were age of building, building type, storey height,
expected foundation types, visible defects supported by sketches and photographs as
appropriate
To utilize the information collected from the building / structure condition survey in
the assessment of the buildings and evaluate sensitive structures with respect to
construction aspects and monitoring
Expected foundation types of different buildings were classified based on the height,
number of floors and age of the buildings. Building survey information was also used to
identify the types of instrumentation required.
Building Damage Assessment and Observational Method
Process of Stage-Assessment is shown in figure 20. After carrying out the initial
assessment of potential building damage, it was recognized that without applying the
515
observational method, the result obtained from assessment process could be conservative for
some buildings and could be underestimated for others. For example, the settlement estimated
in Second Stage Assessment shown in above diagram was based on surface movement. For
the buildings located in close proximity to the excavation founded on piles, it was considered
that subsurface settlement may be more critical. Stage 2 Assessment was then further
extended by Additional Stage 2 Assessment in which the variation of settlement trough shape
and magnitude with depth were considered in identifying the risk of building damage.
Settlement of the buildings due to the excavation works were predicted assuming the green
filed condition. Neglecting restraints from foundation and structure, it was assumed that
buildings follow the ground settlement trough at foundation level (estimated pile tip level).
However, if the building is supported by deep foundations, assessment result could be too
conservative.
Stage 1
< 10mm
No further
assessment
>10mm
Stage 2
< slight
No further
assessment
> slight
Additional Stage 2
< slight
No further
assessment
> slight
Stage 3
Detailed Assessment
(building structural check, consider building stiffness, Soil-structure interaction)
516
D-wall
Do = 2.5 HE
D O = HW + W
Surface settlement trough
volume, V To
Sio
S WO
W
Total deflected
shape volume, V O
Sub-surface settlement
trough volume, VTy
Settlement
influence zone
deflected volumn V y at depth (H w- Y)
Swy
Siy
HW
HE
Dy
S WO
4V O
DO
S io SWO *
DO
D
DY Y * O
HW
VTY VY *
VTO
VO
517
Table 4
type
Summary of risk category obtained from two different methods and foundation
Estimated
Distance
Risk category by
Risk category by
Block
Pile Length
to edge
maximum tensile
chart of Boscarding
of wall
strain
stories
Type
Masonry /
Without
With
Without
With
pile
pile
pile
pile
7-14m
18m
7-14m
17.5m
7-14m
32m
< 6m
2m
50m
8m
Concrete
Masonry /
Concrete
Masonry /
Concrete
Masonry /
Concrete
37
RC
The predicted degree of damage of the buildings using simplified chart is more critical
than that of maximum tensile strain method as can be seen in above table. According to the
results obtained from of simplified chart, predicted degree of damage was higher if buildings
were assumed to be with piled foundation rather than without piled foundation.
In order to justify the most probable condition assumed in building damage assessment
and to take necessary actions if monitoring results reveal most unfavorable conditions (i.e.
ground movement induced by deflection of diaphragm wall reaches maximum acceptable
limit), observational method was implemented on the followings basis.
Reviewed the building condition survey record paying particular attention to the type of
foundation and existing visible defects
Predicted the ground movement based on the calculated diaphragm wall deflection
Performed structural assessment based on the predicted ground movement (for Stage 3
assessed buildings)
Established the trigger criteria based on the magnitude of ground movement (maximum
settlement and differential settlement between foundations or structural columns)
Predefined the practical contingency plan for most unfavorable conditions where
ground movement reaches trigger levels (ground movement was derived using simple
approach based on diaphragm wall deflection described in earlier section)
Set out the instrumentation program with the consideration of above factors.
Strictly controlled the construction sequence assumed and defined in design and if
necessary changed or modified the sequence
518
Monitored the performance of retaining wall both diaphragm wall (for station boxes)and
sheet pile walls (for station entrance structures) . Compared the monitoring results with
the predicted and trigger values and reassessed
Monitored the building settlement. Compared the monitoring results with the predicted
and trigger values and reassessed
Implemented the contingency measures if monitoring result reaches action level of trigger
values
Monitoring results obtained from early stage of the project were used to reassess the potential
damage of the buildings and structures. Some buildings of critical condition were put in Stage
3 assessment requirement and assessed by structural analysis using detailed structural survey
information as basic data. By simulating the differential settlement of the building predicted
from Additional Stage 2 Assessment, development of moment and shear in the main structural
members were determined with the use of structural analysis software. Computed moment
and shear were assessed in comparison with the capacity of the structural members estimated
from collected building condition survey and detailed structural survey data. The process
involved in structural assessment can be summarized below.
519
Data Taken
From
Sh1
Sh2
(mm) (mm)
Settlement
Prediction
Actual
Monitoring Data
L
(m)
Angular Distortion
31
24
18.6 0.0004
31*
24*
18.6
0.0004
*
Sv1
Sv2
L
(m)
Risk
Degree of
Category
Damage
48
23
25
18.60
0.0013
slight
53
14
39
18.60
0.0020
slight
*Predicted horizontal movement was used in computing horizontal strain for actual
miniotring data.
From the above table, following conclusions may be made.
Predicted angular distortion broadly agrees with that of actual monitoring data. Hence,
settlement prediction and assumed effective depth of piled foundation is fairly reasonable.
The settlement of actual monitroing data is slightly higher than that of prediction. This
may be due to the additional settlement caused by diaphragm wall panel construction
which influence zone might have extended to 15m from the diaphragm wall (equivalent
distance to bottom of soft clay level ).
520
To carry out back-calculation using monitoring data obtained from the settlement arrays
(settlement points, extensometer data) at first 3 locations before reaching to MWWA
water tunnel near Rama IV Rachadapisek intersection, to determine the volume loss
and relationship between surface and subsurface settlement as well as best estimation of
subsurface K value and subsurface settlement profile at water tunnel level.
To compare the result obtained from above item with allowable values.
To establish the final trigger values based on above comparison.
To confirm the settlement profile from actual monitoring of last array is within the alert
level of final trigger value.
Figure 21. Position of MWA water tunnel in relation to MRT tunnels (clear distance are
3.38m and 3.18m for North and South bound respectively) at the first crossing
521
Figure 22. Position of MWA water tunnel in relation to MRT tunnels (clear distance are 1.5m
and 2m for North and South bound respectively) at the second crossing
For the first location of MRT-MWA tunnel crossing, target ground loss from tunnel
operation was set at 0.5%, whereas ground loss based on allowable movement curvature of
water tunnel derived from predicted pattern of subsurface settlement was 0.65%.
Back-calculated ground loss derived from the monitoring data of rod-extensometer placed at
the crown of MWA water tunnel was within target value. In addition to the preliminary
assessment based on prediction of subsurface settlement using simple empirical formulas, a
detailed soil-structure interaction was analyzed using 2-dimensional FEM considering
behavior of tunnel boring by earth pressure balance (EPB) method. Stress relief from the
effect of cutter-head, tail void and over-cut from EPB tunnel boring was considered in the
analyses. Adding ground movement due to consolidation caused by disturbance from tunnel
operation surface and subsurface settlement were predicted by finite element analysis.
Detailed parameters and assumption made in analysis was presented in the published paper of
Sakai & Sugden (2000).
After the successful passing of both tunnels at the first MWA crossing, another trial area
tunneling was planned to further determine the ground movement associated with various
tunneling parameters well before reaching to more critical crossing after Sam Yan station.
Tunnel section between Silom and Samyan station, in which soil profile similar to that of
second crossing was selected and comprehensive instrumentation program was established to
monitor surface and subsurface settlement as well as horizontal movement of the ground at
depth.
The observed ground movement induced by tunneling works were within predicted
values. Well organized plan, systematic approach of observational method to achieve control
522
values backup by extensive instrumentation and close co-operation among relevant personnel
were the key factors contributed to successful completion of EPB tunneling particularly in the
most sensitive points at MWA water tunnel crossings. The monitored subsurface settlement
data from extensometer and predicted settlement trough of assumed ground loss 1% ground
settlement profile of the first MWA tunnel crossing is presented in Figure 23.
Distance (m)
10
20
30
40
50
60
70
80
90
-10
Settlement _ NB Tunnel
-30
Settlement_SB Tunnel
Total Settlement
-50
523
REFERENCES
Boscarding, M.D. and Cording, E.G. (1989),
524
with
Suchatvee Suwansawat
525
the
S. Suwansawat
Department of Civil Engineering, King Mongkut Institute of Technology-Lad Krabang, Bangkok, Thailand
[email protected]
Z. Z. Aye
Abstract: Works of the first Bangkok Underground MRT project involved the largest diameter shield tunneling and the deepest diaphragm wall excavation ever attempted in Bangkok subsoils. The design-built contracts required the design and construction to avoid
damages to existing buildings, thus the Observational Method was adopted and large amount of instrumentation for monitoring of
ground movements was integrated as important component of the works. The ground and building movement data associated with the
shield tunneling and station excavation are interpreted and the findings are briefly presented. Tunnel volume loss in the EPB shield
tunneling was typically in the range of 0.5-2.5% while the maximum ground surface settlement above the tunnel was typically 20-60
mm. The magnitude of ground movement varied with the face pressure used in the shield driving. The settlement trough width parameter was i = 0.5-0.6 Z for tunneling in clay layers and < 0.4Z for tunneling in the underlying sand layer. Maximum lateral deflection in
braced mode of the diaphragm wall in the station excavation was in the range of 0.05-0.4% of the excavation depth. A similar range
was observed for the maximum ground surface settlement adjacent to the wall. There were only limited cases of damages to adjacent
buildings, which occurred only to small sized buildings founded on short piles.
INTRODUCTION
527
lined water main tunnels at two locations, and removal and underpinning of piled foundations of four canal bridges.
Prior to the start of the MRT construction, there had been numerous shield tunneling and deep excavation works for both
building construction and utilities development. However, underground works of the MRT project marked the largest tunnel diameter and the deepest excavation ever attempted in Bangkok
subsoils. Thus great caution must be paid to the design and implementation of the works for safety assurance of the works and
success of the project development.
Control of ground movement and preventing damages to adjacent structures from the excavation was the key for the success
for the project. The Observation Method design was adopted for
that purpose. A comprehensive instrumentation program for
monitoring of ground movements and responses of concerned
structures was carried out as an important component of the contracts. The monitoring data served as indices for control of works
and safety assurance during construction as well as allowed for a
better understanding on the ground movement behavior induced
by EPB shield tunneling and deep excavation with diaphragm
wall in the stratified Bangkok soils.
2
SUBSOIL CONDITIONS
hard clay and dense sand existing to a great depth. The subsoil
condition is relatively uniform through out the city area. The soft
clay layer generally extends from the ground surface to a depth of
12 to 15 m. The soft clay which is known as Bangkok soft clay
has high water content (70-120%). The underlying stiff clay layer
has much better engineering properties than the soft clay and is
an ideal medium for tunnelling within. Below the stiff clay layer
is a layer of fine to medium, dense to very dense, silty to clayey
sand. The sand is normally saturated but the piezometric pressure has been considerably drawn down as a result of excessive
deep well pumping in the past 60 years. Presently, the piezometric head in the sand layer is mostly at 21-24 m below the ground
surface. The condition is beneficial to tunnelling and deep excavation works. Fig. 1 shows subsoil stratigraphy along the MRT
alignment. Although most of the tunnel alignment is placed in the
stiff clay layer, some shallow sections have roof in the overlying
soft clay and some of the deep alignment was excavated in the
underlying sand layer.
TUNNEL EXCAVATION
PRACHARAT BAMPHEN
SUTTHISARN
RATCHADA
LAT PHRAO
PHAHONYOTHIN
MO CHIT
KAMPHEANG PHET
BANG SU
10
10
20
20
30
30
40
40
50
50
60
60
20+000
21+000
22+000
23+000
24+000
25+000
26+000
FILL
DENSE SAND
528
27+000
28+000
29+000
30+000
STATION
TUNNELLING HORIZON
STATION EXCAVATION
Excavation of the 18 stations was made by the top-down construction using 1-m-thick concrete diaphragm walls. Tips of the
wall usually extend to the depth of 35 - 40 m below the ground
surface (Fig. 2) to satisfy load bearing and uplift resistance requirements as well as to provide ground water cutoff in the first
sand layer. The distinct difference in depth of embedment of the
wall below the excavation level between the two contracts was
partly due to the difference in the adopted design criteria. Construction period of each station from utility relocation to architectural finishes was usually around 45 months- 6 months of piling
and diaphragm wall construction and 18 months of excavation
and casting of station floors and walls.
OBSERVATIONAL METHOD
The contract required that the design and construction methods limit ground movements from tunneling and station excavation to avoid damage to adjacent structures and buildings.
The Observational Method was then adopted for the control of
work. It involved the followings.
-
Monitoring of settlements arising from works must be carried out. Comprehensive instrumentation program was required as a part of the contract.
529
-60.0
-80.0
-100.0
-120.0
-140.0
-160.0
-180.0
Stacked Tunnels
Side-by-SideTunnels
tion, the trough expanded and shifted toward the second tunnel.
However the centerline of the trough was normally skewed toward the first excavated tunnel.
In the Bangkok MRT tunneling, the shifted distance of the
centerline of the trough from centerline of the twin tunnels (a)
observed at 24 monitoring arrays ranged from 0.03-0.58 of the
distance between the two tunnel centerlines (d). The mean a/d is
0.16. The width of the settlement trough observed after the excavation of the twin tunnels in the project was about 6 to 12 m for
the vertically-stacked tunnels and 10 to 17 m for the side-by-side
twin tunnels.
A plot is made between relationship between the settlement
trough width parameter (i) and tunnel depth (z), Fig.7. Most of
the data points fall within the range of i = 0.5Z to 0.6Z for tunnels located in both the stiff clay and soft clay layers and i < 0.4Z
for tunnels in sand layer. This is in agreement with the observation of OReilly & New (1982) for tunneling in UK.
Ground settlement array no. 26-AR-001
Zone 26
Ratchada - Lat Phrao
Second tunnel
excavation (NB)
ground loss 0.61%
NB
SB
-20 m.
Stiff clay
-20 m.
NB
Stiff clay
First tunnel
excavation (SB)
ground loss 0.43%
Soft clay
Soft clay
SB
Sand
10.5 m.
40
Second tunnel
excavation (NB)
ground loss 0.80%
NB
SB
Stiff clay
-26 m.
Single tunnel
35
-15 m.
Twin tunnel
i = 0.3Z
i = 0.4Z
i = 0.5Z
i = 0.6Z
30
Depth, Z (m)
First tunnel
excavation (SB)
ground loss 0.69%
Dense sand
25
20
15
10
5
0
10
15
20
530
Extensometer installation in
South contract
Extensometer
cal/empirical approach (e.g. Verruijt & Booker, 1996; Loganathan & Poulos, 1998; etc.) and the numerical approach (e.g. FEM
PLAXIS, FDA FLAC, etc.) were investigated (Tavaranum,
2003). For the first approach, it was found that the method of Loganathan & Poulos (1998) method generally can give reasonable
fits to subsurface settlement pattern with field data for both single
and twin tunnels cases (8 out of 12 sections). The gap parameter,
g, from back calculation was in the range of 20-60 mm (Timpong, 2002). Reasonable prediction was also offered by the Verruijt & Booker (1996)s method. However, they could not sufficiently give reasonable prediction of lateral ground movement for
cases of excavation with high face pressures, where outward
ground movement occurred (6 out of 12 sections).
Extensometer installation in
North contract
Inclinometer
casing
Extensometer
Soft Clay
Inclinometer
casing
Soft Clay
Stiff Clay
Tunnel
Stiff Clay
3 - 6 m.
Tunnel
20
40
60
80
100
120
-50
-40
Settlement (mm)
The lateral displacements of ground beside the tunnel were observed at 12 locations along the alignment. The instruments were
placed at distance of 0.20-2.6 m from the tunnel wall. Most of the
measurements showed a similar pattern of the lateral ground
movement which can be divided into two different depth zones,
i.e. above and below the level of the tunnel arch. Above In the
upper zone zone, the ground displaced towards the tunnel with
the maximum displacement Fig. 6 Effect of presence of piled
foundation on shape of settlement trough occurring in the lower
area of the soft clay layer. The inward displacement within this
depth zone continued to increase after the passage of the shield
tail.
In the lower zone, two patterns of the lateral ground displacement were observed. In most cases,, inward movement toward
the tunnel was observed. The magnitude was smaller than those
occurring above the tunnel roof. At few sections where high face
pressure was used in the shield tunnelling, the ground showed
outward movement (Fig. 11). The movement ceased after the
passage of the shield tail. This clearly indicates the effect of the
applied face pressure in the EPB shield tunneling in Bangkok
soils.
Studies were made to investigate applicable methods for prediction of the ground in shield tunnelling. Both the analyti-
-30
-20
-10
Soft clay
25-M E-3/08
-2.02 m.
25-M E-3/07
-5.15 m.
25-M E-3/06
-8.32 m.
25-ME-3/05 - 11.45 m.
10
-15 m.
20
-18.5 m.
30
Stiff clay
Shield passing
6 .24 m.
25-ME-3/04 - 14.58 m.
25-ME-3/03 - 17.71 m.
531
140
of the Bangkok subsoils for the analysis. The results show that
for the soft/medium clay the modulus, Eu should be around 500
Su, where Su is undrained shear strength. For other soil layers
underlying the soft clay, the values are:
- 1st Stiff Clay
Eu = 700 N
- Clayey Sand & Sandy/Silty Clay Eu = 900 N
- 2nd Hard Clay
Eu = 1600 N
- 3rd Hard Clay
Eu = 2500 N
Made ground
-5
Soft clay
Zone 1
Zone 2
SOUTH CONTRACT
Zone 3
-20
-25
0.0
Clayey sand
A. 2D before the shield face
B. 1D before the shield face
C. at the shield face
D. 0.5D behide the shield face
E. at the shield tail
F. 2D behide the shield face
G. 3D behide the shield face
H. 4D behide the shield face
-4
-2
1.0
1.5
2.0
5
10
15
20
25
30
35
Cantilever mode (H=1.6m-4.0m)
Braced mode-stiff soil (H=12.4m-16.7m)
0.5
Stiff clay
Excavation Depth, H (m)
-15
Ground movements associated with the excavation of the 18 stations of the project were closely monitored with systematic instrumentation programs. The monitoring data provided useful information to capture the typical characteristics of lateral ground
movement and settlement in the areas adjacent to the controlled
deep excavation using diaphragm wall in Bangkok subsoil. The
station boxes were generally 230 m long by 25 m wide with excavation depths of 20-30 m. Hooi (2002) conducted comprehensive review and interpretation of the monitoring data. The results
showed the ratio of maximum lateral wall displacement to the excavation depth at various stages of excavation as shown in Fig.
12. For the cantilever mode occurring in the first stage of excavation (H = 1.6 m 4.0 m), the dHmax/H = 0.20 - 1.60 %. For the
braced wall mode, the ratio dHmax/H = 0.05 0.60% while excavating in soft clay layer (H = 6.5 m 10.8 m). The wall deflection in the braced wall mode while excavating in the stiff clay or
sand layers (H = 12.4 m 32.6 m) showed dHmax/H = 0.05
0.40%. The observed ground settlement adjacent to the excavation walls is summarized in Fig. 13. The ratio of the maximum
settlement to excavation depth is high in the first stage cantilever
excavation mode. After the excavation advanced down to the
braced mode in either the soft clay layer or the underlying stiff
clay layer, the ratio of the maximum settlement to excavation
depth (dVmax/H) was in the range of 0-0.3%. The observed
width of settlement zone (D) is large, up to 7 D/H for braced
mode with 4 D/H for braced mode with excavation base soft clay
and reducing to 4 D/H in deeper stiff clay or sand. The influence
zone of the diaphragm wall excavation is smaller than that suggested by Peck (1969) for braced excavation using soldier
piles/sheet piles. Since the FEM design analyses used for all station excavations of the MRT followed linear elasto-plastic soil
property, back-analyses based upon the monitoring data were
made to determine the appropriate corresponding modulus values
Depth (m)
-10
NORTH CONTRACT
Distance from excavation/Maximum excavation depth, D/H
2
3
4
5
6
7
8
10
0
0.1
0.2
A
B
0.3
0.4
0.5
I
II
III
0.6
Cantilever mode (H=1.6m-4.0m)
532
-1.5 m.
Soft clay
6 to 14 m
-15 m.
14 to 30 m.
-22 m.
15 to 22 m
-40 m.
Buildings on foundation
Type 1
Type 2
Type 3
Type 4
80
70
60
50
40
30
20
10
0
0
10
20
30
40
50
60
70
5. The observed subsurface settlements and lateral displacements could generally be reasonably fitted with the prediction
by the analytical methods of Verruijt & Booker (1996) and
Loganathan & Poulos (1998). However, the prediction was
poor for lateral ground movements in case where lateral outward ground movement occurred.
80
90
80
CONCLUSIONS
1. EPB shield tunneling for the first Bangkok MRT was successfully completed with the average advance rate of each
shield of 60-70 m/week. Similarly, the deep excavation using diaphragm wall of the 18 stations were completed without major difficulties.
70
60
7. Settlement of adjacent buildings induced by ground movement from the MRT excavation showed clear correlation with
building heights which reflects depth of piled foundations.
50
40
30
20
REFERENCES
10
0
0
10
20
30
40
50
60
No. of storey
533
Hooi Kah Yeng 2002. Ground Movements Associated with Station Excavations of the First Bangkok MRT Subway. M.S.
Thesis, AIT, Bangkok.
Loganathan N. & Poulos H.G., 1998. Analytical prediction for
tunneling-induced ground movement in clays. J. Geotech.
Engrg ASCE, 124, no. 9, pp.846-856.
Mair R.J., Gunn M.J. & OReilly M.P., 1981, Ground movement
around Shallow Tunnels in Soft Clay, Proceedings of The
10th Conference on Soil Mechanics and Foundation Engineering, Stockholm, Vol.1, pp. 323-328
OReilly, M.P. & New B.M., 1982. Settlements above Tunnels in
United Kingdom-Their Magnitude and Prediction, Tunnelling82, pp 173-181.
Peck, R.B., 1969. Deep Excavation in Soft Ground, Proc. 7th International Conference on Soil Mechanics and Foundation
Engineering, State of the Art Volume, pp 225-290.
534
and
Exhibition
on
Noppadol Phienwej
535
Abstract: The M.R.T Chaloem Ratchamongkhon Line is the first underground mass transit system project in Bangkok developed by
the Mass Rapid Transit Authority (MRTA) of Thailand. This paper presents the methods adopted in prediction of tunneling induced
ground movement and associated building damage risk-assessment carried out for the Contract No. 1 of the M.R.T Chaloem Ratchamongkhon Line constructed in congestive urban area. Application of observational method in managing risk of damage to the existing
buildings and structures are also reported.
1 INTRODUCTION
Geotechnical risk is one of the key elements of the technical and
financial risk in most of the major construction projects. Though
engineers use adequate factor of safety and taking account of
other risk factors in design and construction process, systematic
approach of risk assessment and management is not commonly
applied in most of the projects.
Tunneling works and deep excavation works pose a high degree of geotechnical risk that needs to be identified, assessed,
minimized and managed. Deep excavation and tunneling works
generally interact with natural ground and incorporating their
characteristics as structural elements of their own stability. This
interaction is more significant in tunneling projects than in other
civil engineering projects particularly in congestive urban area.
In this paper, process of geotechnical risk assessment in Bangkok
first underground mass transit project is presented.
2. GEOTECHNICAL RISK MANAGEMENT
Geotechnical risk is the risk to construction project originated
from the ground condition. In general case, once risk have been
identified and assessed, to manage the risk fall into one or more
of the following major categories.
Eliminate or avoid
Transfer
Mitigate
Tolerate
Unfortunately, ground-related risks are not often practical to
completely avoid or transfer. However, systematic approach,
control and management can minimize the risk if not entirely
eliminate. CIRIA Report 185 outlined the four fundamental
stages of risk management as follows ;
Hazard identification : where hazards are identified and documented in a register via experience of similar projects, brainstorming, structured interviews etc.
537
CHALOEM
RATCHA-
The M.R.T Chaloem Ratchamongkhon Line is the first underground mass transit system project in Bangkok developed by
the Mass Rapid Transit Authority (MRTA) of Thailand. Total
length of the underground structure is 21.5km, comprises of 16
km of twin single-track bored-tunnel, a total of 4 km long18 cutand-cover stations, a twin 1.5km long cut-and-cover approach
tunnel to Depot and other associated structures. The project was
commenced in late 1996 and opened for the public in 2004. The
Contract No. 1, Underground Structure South - southern portion
of this initial system comprising 9 km of twin 6m outside diameter bored tunnels, nine underground stations and cut-and-cover
depot approach tunnel, was awarded to the Joint Venture BCKT
538
Fig. 3. Generalized soil profile along the tunnel alignment and stations of Contract No. 1 (Phienwej et. al. 2006)
4. SUBSOIL CONDITION ALONG CONTRACT 1 ALIGHMENT
Similar to other localities in Bangkok, a typical subsoil profile
along the tunnel alignment is characterized by the alternating
layers of clay and sand deposits. Figure 3 shows the generalized
soil profile along the tunnel alignment of the Contract No.1.
Weathered crust of 2 m thick is commonly found as the top layer.
In urban areas of Bangkok, this layer is covered by fill material.
Soft to very soft, highly compressible dark gray marine clay lies
beneath weathered crust or fill. Depending on the location, this
layer extends up to 12-16 m. About 2 m thick medium clay layer
can be observed between soft clay and underlying stiff clay.
Generally stiff Clay layer occurs directly underneath medium
clay and its depth goes up to 22 m. Below stiff clay layer, first
sand layer of 5-8 m thickness can be found. This first sand layer,
however, is absent in some areas. Stiff to hard clay layer underlies first sand and it is found to be about 5 m thick. Second sand
layer generally occurs at depths between 45 to 65 m. As can be
seen in Figure 3, tunnel alignment is located mainly in stiff clay
layer. Tunnels were bored in the first sand layer before reaching
to Queen Sirikit Center station and deeper sections between Bon
Kai (Khlong Toey station) and Hua Lamphone stations.
5. STATION BOX CONSTRUCTION AND TUNNELLING
WORKS
Cast-in-place rigid diaphragm walls were used as permanent retaining structures for all stations and some entrance structures
and ventilation buildings. Most of the entrance and ventilation
buildings were excavated by sheet pile walls. Tip levels of diaphragm wall ranges from 19m (at Hua Lamphong station) to 39m
(at Sam Yan and Silom stations) for the final excavation depths
of 15m to 31m. Excavated down to 31 below existing ground
level at Silom station marked the deepest excavation supported
by diaphragm wall in Bangkok. Top-down construction method
was used for all stations having stanchions for vertical support
and skeleton slabs as bracing during bulk excavation of station
boxes (Figure 4).
539
540
To record pre-construction status of all buildings and structures within the influence zone. The records included were
age of building, building type, storey height, expected foundation types, visible defects supported by sketches and photographs as appropriate
Geotechnical
Risk Management
OM
Identify Risk
Risk of damage to building
Analysed Degree
of Risk
(Building Damage Category)
Construction Control
Monitoring & Review
Trigger Criteria
Exceeds
Control
Yes
No
Implement
Planned Action
Fig. 8. Flowchart showing the OM process involved in Building Damage Risk Assessment
Stage 1
< 10mm
No further
assessment
>10mm
Stage 2
No further
assessment
< slight
> slight
Additional Stage 2
< slight
No further
assessment
> slight
Stage 3
Detailed Assessment
(building structural check, consider building stiffness, Soil-structure interaction)
541
Process of Stage-Assessment is shown in figure 9. After carrying out the initial assessment of potential building damage, it
was recognized that without applying the observational method,
the result obtained from assessment process could be conservative for some buildings and could be underestimated for others.
For example, the settlement estimated in Second Stage Assessment shown in above diagram was based on surface movement.
For the buildings located in close proximity to the excavation
founded on piles, it was considered that subsurface settlement
may be more critical. Stage 2 Assessment was then further extended by Additional Stage 2 Assessment in which the variation
of settlement trough shape and magnitude with depth were considered in identifying the risk of building damage. Settlement of
the buildings due to the excavation works were predicted assuming the green filed condition. Neglecting restraints from foundation and structure, it was assumed that buildings follow the
ground settlement trough at foundation level (estimated pile tip
level). However, if the building is supported by deep foundations, assessment result could be too conservative.
10. PREDICTION OF GROUND MOVERMENT INDUCED
BY TUNNELLING WORK AND RISK ASSESSMENT
10.1 Prediction of surface settlement
The Gaussian normal distribution curve developed by Peck
(1969), OReilly and New (1982) was used to estimate the
ground settlement induced by a single tunnel.
10.2 Stage 1 Assessment
Fig. 10. Distribution of surface and subsurface settlement induced by tunnel boring.
.
542
The risk of damage to the building in terms of magnitude of building slope with reference to the limiting values specified by various researchers.
The following assumptions were made in the conservative
approach of Stage 3 assessment.
K = [0.14+0.26(1-z/z0)] / (1-z/z0)
By substituting K values for K in equation derived from
Gaussian normal distribution curve the subsurface settlement at
required depth can be calculated.
0
-10
-20
Surface_Settlement_NB Tunnel
Surface_Settlement_SB Tunnel
-30
Surface_Settlement_Total
-40
-50
-60
Table 1. Summary of risk category determination based on Boscarding and Cording (1989)
NB_TUNNEL CENTER
-70
0
10
20
30
40
50
60
70
80
Distance (m)
Data Taken
From
CL_NB
CL_SB
15
12/11/99 12:00
10
04/01/00 12:00
19/01/00 12:00
25/01/00 21:00
26/01/00 06:00
-5
26/01/00 09:00
-10
26/01/00 15:00
26/01/00 12:00
26/01/00 18:00
Settlement, m
-15
27/01/00 00:00
-20
27/01/00 03:00
27/01/00 06:00
-25
27/01/00 09:00
27/01/00 12:00
-30
Settlement
Prediction
Actual
Monitoring
Data
Sv1
(mm)
Sv2
(mm)
(mm)
L
(m)
48
23
25
18.6
0.0013
2 / slight
53
14
39
18.6
0.0020
2 / slight
Angular Distortion
S
27/01/00 15:00
-35
27/01/00 21:00
-40
28/01/00 03:00
-45
29/01/00 12:00
28/01/00 12:00
31/01/00 12:00
-50
02/02/00 12:00
-55
09/02/00 12:00
02/03/00 12:00
-60
05/04/00 12:00
-65
Predicted
-70
-25
-20
-15
-10
-5
10
15
20
25
Distance, m
Fig. 12. Actual settlement profile monitored at fully instrumented location in comparison with prediction
10.5 Stage 3 Assessment
The method used in Stage 3 Assessment of the buildings in tunnel zone was based on the superimposed predicted subsurface
settlement trough induced by twin tunnels.
Based on the pre-construction state building condition survey
and detailed structural survery, the method for damage
assessment was selected. Two main approaches were applied.
Type of Damage
Cracking in walls Structural Damage
and partitions
1/300 to 1/500
1/150
1. Skempton and
Macdonald
2. Meyerhof
1/500
1/250
1/500
1/500
1/200
1/150
543
Factor of safety of each structural members were determined base on predicted differential settlement of
the buildings.
A series of assessment were performed to determine
the critical differential settlement causing structural instability of the members or differential settlement at
limiting factor of safety.
Trigger values were established based on above results.
Based on the trigger values and the actual building
condition and response in conjunction with monitoring
data, the most sensitive structural members were protected, mainly by strengthening approach.
To carry out back-calculation using monitoring data obtained from the settlement arrays (settlement points, extensometer data) at first 3 locations before reaching to
MWWA water tunnel near Rama IV Rachadapisek intersection, to determine the volume loss and relationship between surface and subsurface settlement as well as best estimation of subsurface K value and subsurface settlement
profile at water tunnel level.
To compare the result obtained from above item with allowable values.
To establish the final trigger values based on above comparison.
To confirm the settlement profile from actual monitoring of
last array is within the alert level of final trigger value.
Fig. 13. Position of MWA water tunnel in relation to MRT tunnels (clear distance are 3.38m and 3.18m for North and South
bound respectively) at the first crossing.
Fig. 14. Position of MWA water tunnel in relation to MRT tunnels (clear distance are 1.5m and 2m for North and South bound
respectively) at the second crossing
For the first location of MRT-MWA tunnel crossing, target
ground loss from tunnel operation was set at 0.5%, whereas
ground loss based on allowable movement curvature of water
tunnel derived from predicted pattern of subsurface settlement
was 0.65%. Back-calculated ground loss derived from the monitoring data of rod-extensometer placed at the crown of MWA water tunnel was within target value. In addition to the preliminary
assessment based on prediction of subsurface settlement using
simple empirical formulas, a detailed soil-structure interaction
was analyzed using 2-dimensional FEM considering behavior of
tunnel boring by earth pressure balance (EPB) method. Stress relief from the effect of cutter-head, tail void and over-cut from
EPB tunnel boring was considered in the analyses. Adding
ground movement due to consolidation caused by disturbance
from tunnel operation surface and subsurface settlement were
predicted by finite element analysis. Detailed parameters and assumption made in analysis was presented in the published paper
of Sakai & Sugden (2000).
544
10
20
30
40
50
60
70
80
90
-10
Settlement _ NB Tunnel
-30
Settlement_SB Tunnel
Total Settlement
-50
REFERENCES
Boscarding, M.D. and Cording, E.G. (1989), Building Response
to Excavation-Induced Settlement. Journal of Geotechnical
Engineering, ASCE, 115;1;1-21
Burland, J.B., and Wroth, C.P. (1974), Settlement of Buildings
and Associated Damage. SOA Review, Conference on Settlement of Structures, Cambridge, Pentech Press. London,
pp. 611-654
Burland J.B., Broms J.B. and de Mello VFB (1977), Behavior of
Foundations and Structures, SOA Report Session 2, Proceedings of 9th International Conference, SMFE, Tokyo, 2:495546
Clayton C. R. I (2001), Managing Geotechnical Risk, Improving
Productivity in UK Building and Construction, Institute of
Civil Engineers and Thosmas Telford Ltd. UK
Clough, G.W., and ORourke, T.D., (1990), Construction Induced Movements of In-situ Walls, ASCE Geotechnical
Special Publication No. 25, pp. 439-470
Clough C.W. and T.D. ORourke (1990), Deep Excavation and
Tunneling, 7th ICSME, Mexico City
Graftio H. (1936), Some Features in Connection with the Foundation of Svir 3 Hydro-electric Power Development, Proceedings of the first international conference in Soil Mechanics, Cambridge, Mass., 1, pp. 284-290
JV BCKT, (1997) Geotechnical Interpretation Report (GIR) for
MRTA Initial System - UGS, Bangkok
Mair, R.J., Taylor, R.N., and Burland, J.B., (1996), Prediction of
Ground Movements and Assessment of Risk of Building
Damage. Geotechnical Aspects of Underground Construction
in Soft Ground, pp. 712-718, Balkema, Rotterdam
OReilly M.P and New B.M (1982), Settlements above tunnels in
United Kingdom their magnitude and prediction, Tunneling
82, pp. 173-181, London, IMM
Peck R.B. , (1969) Deep Excavation and Tunneling in Soft
Ground, 7th ICSME, Mexico City, State of the Art 3, 225-290
Peck, R. B. [1969]. Advantages and limitations of the observational method in applied soil mechanics, Geotechniques 19,
No.2, pp. 171-187
Phienewej N., Photayanuvat C., Suwansawat S., Mcconochie D.,
(2006) Geotechnical Aspects in Design and Construction of
Chaloemratchamongkhon Underground MRTA, Bangkok,
Proceedings of the International Symposium on Underground
Excavation and Tunneling, Urban Tunnel Construction and
Protection of Environment, EIT, Bangkok, Thailand, , pp.
271-279
Powderham, A. J. [1996]. An overview of the observational method : development in cut and cover and bored tunneling
projects, The Observational Method in Geotechnical Engineering, The institute of civil engineers, Thomas Telford Publishing, London, pp. 7-24
Zaw Zaw Aye , Dhiraj Karki and Christian Schulz [2006].
Ground Movement Prediction and Building Damage RiskAssessment for the Deep Excavations and Tunneling Works
in Bangkok Subsoil, Proceedings of the International Symposium on Underground Excavation and Tunneling, Urban Tunnel Construction and Protection of Environment, EIT, Bangkok, Thailand, , pp. 281-297
545
547
3119
ABSTRACT
Tunneling adjacent to an existing pile group may induce additional force,
bending moment and settlement of a pile. Moreover, it may cause load redistribution
and differential settlement in a pile group. In this paper, the construction of a water
diversion tunnel with an outside diameter (D) of 5.55 m constructed in Bangkok is
reported. The tunnel was constructed in very stiff clay using an earth pressure
balance shield with a cover-to-diameter ratio of 4.5 and very close to a pile group.
The pile group was located within a distance of 1D from the tunnel springline.
Tunneling induced ground responses were measured by using surface settlement
points, extensometers and inclinometers. To investigate the influence of tunnelling
on the pile group, a three-dimensional, elasto-plastic, coupled-consolidation
numerical analysis was also conducted to simulate the pile group responses.
Observed ground responses and computed changes of horizontal effective stress and
excess pore water pressure around piles are reported. Redistribution of pile shaft
resistance, load transfer in the pile group and pile head settlements are investigated.
INTRODUCTION
Tunneling adjacent to an existing pile group may induce additional bending moment,
cause redistribution of axial force in each pile and load transfer in a pile group. Any
stress change in the ground due to tunnelling is the main concern to engineers in
evaluating capacity and additional settlement of a pile group.
Chen et al. (1999) and Lee & Ng (2005) carried out numerical analyses to
study the influence of tunneling on adjacent pile. They found that negative skin
friction was induced along the pile shaft as a result of stress relief. Tunneling
adjacent to a pile group was also studied by Pang et al. (2005) and Cheng et al.
(2007). It is reported that the maximum bending moment induced in a pile occurs at
the tunnel axis in the transverse direction of tunnel advancement while no significant
bending moment occurs in the longitudinal direction.
In this paper, monitored soil displacements due to a 5.5m diameter shield
tunnelling adjacent to a pile group are reported and compared with computed finite
element results. The capacity and settlement of the pile group due to the tunneling
are also investigated.
549
3120
THE SITE
Figure 1a shows plan of tunnel alignment and adjacent pile groups of elevated
railways. The layout of instrumentation is also shown in the Figure. Various
instruments were installed to observe tunneling induced ground displacement and
structural response. Three surface settlement points (S1, S2 and S3), two
extensometers (Ex1 and Ex2) and one inclinometer tube (I1) were installed to
measure ground response. Two pier settlement points (C1 and C2) were mounted on
pier to measure pier settlement. The monitored data is interpreted from BMA flood
diversion tunnel project: Sansaeb Canal and Ladprao Canal Section (Lim et. al,
2009). The total length of tunnel in this project is about 5 km.
Figure 1b shows a typical soil profile of the study area. The first upper layer
is 12 m thick soft clay. Below it is the succession of medium stiff clay of 3 m, stiff
clay of 5 m, very stiff clay of 14 m and stiff clay of 14 m thick layers. A 12 m very
dense sand layer underlies the clay layer. A water diversion tunnel with an outer
diameter (D) of 5.55 m was constructed in very stiff clay at cover-to-diameter ratio
(C/D) of 4.5 using an earth pressure balance shield machine. The tunnel alignment is
very close to a (22) pile group with center to center of pile spacing 3 m. The outer
diameter and length of the shield are 5.70 m and 8.05 m, respectively. The diameter
of each concrete bored pile is 1.0 m. The length of piles is 60 m and pile toes are
embedded in very dense sand layer. All four piles are rigidly connected with 1.8 m
thick pile cap. The clear distance between the nearest pile and the tunnel springline is
3.65 m. The tunnel axis depth is approximate at the middle of pile length.
Instrumentation
(a)
t 71 R
umvi
Sukh
(b)
3.00
0.00 m
oad
.6
18
C2
13
8
.3
4.35 I1
S2
S3
Scale:
10
S1
20
C1
Sukhumvit Road
3.65
Ex2
Shield advancing
-34.0 m
Very
stiff
clay
Stiff
clay
-48.0 m
Very
dense
sand
S2
-3.0 m
Ex1&Ex2
-12.0 m
-15.0 m
-12.0 m Medium
-15.0 m stiff clay
Stiff
-20.0 m clay
Inclinometer
Ex1
C1
Soft
clay
-20.0 m
3.65
-27.55 m
5.55 m
I1
-40.50 m
4- 1.0 m
Concrete pile
-60.0 m
SECTION A
Figure 1. (a) Plan of study area and lay out of instrumentation (b) sectional view
A-A and soil profile
NUMERICAL ANALYSIS
To investigate the influence of tunnelling on the pile group, a three-dimensional,
elasto-plastic, coupled-consolidation numerical analysis was carried out using Finite
Element program ABAQUS (Hibbitt et al., 2008).
550
3121
50 m
Y=0
40 m
(b)
Excavated
diameter,
VL = 2.5%
(c) 18000 kN
P2
P4
P3
70 m
Tunnel
axis
Tunnel axis
3m
P1
3m
Final tunnel
diameter
5.55 m
Note:
1.0 m
Beam
element
Direction of shield advancement
Plane of symmetry
Figure 2. (a) Geometry of finite element mesh (b) tunnel excavation simulation
(c) detail of piles and pile cap
551
3122
()
18
19
20
19.5
35
()
6
'
0.15
0.15
0.15
0.15
0.15
E
(kPa)
1,200
5,000
7,000
6,000
40,000
552
3123
from depth 23 m to 40 m. When the shield reaches the monitoring section (i.e., Y=0
m), computed results show an abrupt soil displacement towards the shield. In
contrary to the measured data, when the shield passed at 25 m (i.e., Y=25 m) beyond
the monitoring section, a slight additional horizontal displacement towards the shield
occurs. The differences between measured and computed results may be caused by
tail void grouting is not simulated in the FEA. Therefore, outward movement in FEA
as the shield advances beyond the monitoring section does not occur. It can be
noticed that, the computed ground horizontal movement from FEA can reasonably
capture the measured ground response at the depth of tunnel axis. However, there is a
significant difference between computed and measured ground response near the
ground surface. Large measured horizontal ground displacement may be triggered
by other activities rather than tunneling such as surcharge induced by heavy traffic
load near the inclinometer tube.
-15
-10
-5
10
15
20
Shield distance, Y
Measured (Y=-10m)
10
Measured (Y=0m)
15
Computed (Y=-10 m)
Measured (Y=25m)
Computed (Y=0m)
20
Computed (Y=25m)
25
30
35
Depth (m)
-20
40
Tunnel
axis depth
I1
-Y
+Y
45
553
3124
Maximum reduction and increment in load on pile head of P1 and P2 is 0.8% and
1.2%, respectively.
Pile head settlement and pier tilting. Figure 4b illustrates the computed results of
pile head settlement against shield advancement. In addition to effects of tunneling,
the observed pier settlement was highly influenced by other factors such as vibration
induced by heavy traffic and the elevated train. Furthermore, pier settlement was
barely noticeable by conventional surveying instrument. Therefore, the measured
pier settlement result is not reported in this paper. Maximum computed pile head
settlement occurs at P3 since significant shaft resistance reduction in this pile occurs
when the shield is approaching to the monitoring section. Moreover, load at pile head
on P3 is almost constant (see Figure 4a). Pile head settlement in P1 and P2 is almost
equal although different mechanism is developed. Pile head settlement in P1 would
be mainly caused by reduction of horizontal effective stress and development of
negative shaft resistance which is discussed in following section. Elastic shortening
due to increase of load at pile head would be the major cause of pile head settlement
in P2. The reduction of load at pile head in P4 is higher than in P3 (see Figure 4a).
Therefore, minimum pile head settlement is induced on P4. Tunneling induced pier
settlement is about 1.3 mm. The differential settlement in the pile group causes the
pier to tilt in the longitudinal direction of the tunnel axis toward P3. The maximum
inclination of the pier becomes 1:12,500 when the shield is 5 m away from the
monitoring section (Y = -5 m). In addition, the computed differential settlement
between two piers is 1:27,000 at the end of tunnel driving (the distance between two
piers is 35 m). Those computed results are considered very small for the
serviceability limit state criteria.
Shield distance, Y (m)
(a)
P (%)
1.0
0.5
-20
-10
P2
P3
10
20
30
+Y
0.0
-0.5
-1.0
P1
P3
-10
10
20
30
P4
P1
-Y
0.0
p (mm)
1.5
(b)
P2
P4
0.5
1.0
Avg. 1.3 mm
1.5
Figure 4 (a) Changes of computed load at pile head (b) induce pile head
settlement
Mobilized shaft resistance. Figure 5 shows computed mobilized unit shaft
resistance of P1, P2, P3 and P4, during shield advancement. The significant change
of shaft resistance occurs in P1 as shown in Figure 5a. Mobilized shaft resistance
decreases significantly at depth 13 to 24 m. Negative shaft resistance develops in P1
when the shield reaches at the monitoring section and advances further, indicating
that soil settles more than pile at depth 12 to 25 m. To maintain load equilibrium in a
pile, mobilized shaft resistance in P1 below the tunnel axis increases. The change of
mobilized shaft resistance in P2 is the lowest as shown in Figure 5b. Negative shaft
554
3125
resistance did not develop in P2, which suggests that impact of tunneling on P2 is the
smallest. It is suggested that tunneling influence zone is about 1.5D from the tunnel
axis. P3 and P4 respond to the shield advancement in the same trend as shown in
Figure 5c and 5d, respectively. The only difference that can be noticed is significant
change occurs in P3 when the shield is at 5 m away from the monitoring section. The
significant change in P4 occurs when the shield is at 5 m beyond the monitoring
section. In other words, the maximum reduction of shaft resistance on each pile
occurs when the shield face is slightly beyond the pile.
(a)
0
5
10
Depth (m)
15
-10
-5
P1
fs (kPa)
0
10
(b)
15 -5
Initial
Y=-5m
Y=0m
Y=5m
Y=25m
fs (kPa)
10
15 -5
P2
(c)
P3
fs (kPa)
10
15 -5
(d)
fs (kPa)
5
10
15
P4
20
Tunnel
axis
25
30
35
40
45
P2
P3
-Y
P4
P1
+Y
Figure 5 Computed mobilized unit shaft resistance of (a) P1 (b) P2 (c) P3 (d) P4
Induced axial force and bending moment in pile. Figure 6a illustrates computed
tunneling induced axial force in each pile when shield is at 5m ahead of monitoring
section. The maximum induced axial force occurs in P1 at the depth of tunnel axis.
The trend of induced axial force distribution of P2, P3 and P4 is similar to P1. The
differences of magnitude of induced axial force are due to development of negative
shaft resistance in P1 (see Figure 5a). It can be noticed that minimum induced axial
force occurs in P2 as a result of minimum reduction of unit shaft resistance (see
Figure 5b).
Figure 6b shows the distribution of computed bending moment of each pile in
longitudinal direction of the tunnel axis (Mx). Maximum Mx occurs in P1 when the
shield is at 5 m beyond the pile (Y = 5 m). The bending moment (Mx) causes every
pile to bulge in the same direction as the shield advancement at the depth of tunnel
axis. Bending moment in each pile extends to depth 50 m, which is about 4D below
the tunnel axis.
Figure 6c illustrates the distribution of computed bending moment of each
pile in transverse direction of tunnel axis (My). Maximum My occurs in P1 when the
shield is at 5 m beyond the pile. The bending moment (My) causes the pile to bulge
towards the shield due to stress relief around the shield. By comparing bending
moment of a pile in 2 directions, My is significantly larger than Mx due to higher
555
3126
stress reduction around the shield in transverse direction than in the longitudinal
direction.
The ultimate bending moment capacity of a reinforced concrete bored pile
with diameter 1.0 m is approximate between 1,000 and 1,400 kN.m, given the
reinforcement ratio is 0.5% of the pile section. Therefore, maximum computed
induced bending moment in P1 is only about 20% of its capacity.
(a)
-100
0
(b)
Fx (kN)
0
100
200
400 -100
300
Mx (kN.m)
-50
20
Depth (m)
(c)
50 -100
My (kN.m)
0
100
200
P1
P2
P3
P4
10
30
40
P2
P4
P3
Sign
convention
for Mx
+
Tunnel
axis
+
Sign
convention
for My
P1
50
+Y
-Y
60
Figure 6 Computed (a) induced axial load distribution (b) bending moment in
longitudinal direction, Mx (c) bending moment in transverse direction, My in
each pile due to tunneling
Changes of horizontal effective stress and induced excess pore water pressure.
Figure 7a shows changes of computed normalized horizontal effective stress
(h/h0) with respect to shield advancement. In this study, coupled-consolidation
analysis is conducted which allows both volume and pore water pressure to change
during tunnel advancement. Soil elements around piles at the depth of tunnel axis are
selected to be investigated. As the shield reaches between Y = -10 to -5 m, h/h0
of P1, P2 and P4 increases. This is caused by horizontal effective stress relief around
the shield. Subsequently, arching effect or stress redistribution occurs on soil element
in front of the shield and causes outward movement from the shield. The measured
horizontal ground displacement confirmed the explanation of stress redistribution.
When the shield advances further and reaches at Y= -5 to 3 m, h/h0 suddenly
drops due to stress relief around the shield. Horizontal effective stress around piles
slightly increases when the shield advances beyond the monitoring section (Y = 3 to
25 m). This is due to stress redistribution behind the shield causing a slight outward
movement at the piles. The highest change of h/h0 occurs at P1 with the highest
increment h/h0 of 1% and the maximum reduction h/h0 of -3%. The
tunneling impact in terms of changes of horizontal effective stress on P2 is the lowest
as expected.
556
3127
Figure 7b shows changes of excess pore water pressure at the depth of tunnel
axis which has a similar trend to h /h0. When the shield approaches to the
monitoring section (Y = -20 to -10 m), u/u0 around every pile increases. It indicates
contractive behavior of soil around piles due to stress redistribution induced by
tunnel driving. When the shield reaches at Y= 3 m, u/u0 abruptly decreases to
minimum then it gradually rebounds when the shield advances beyond the
monitoring section. The dilative behaviour suggests that the resultant horizontal
displacement of soil around each pile is towards the shield. The maximum change of
u/u0 occurs on P1 whereas the minimum occurs on P2. The difference of h/h0
and u/u0 among P2, P3 and P4 is not significant. It indicates that the influence zone
of tunneling extends to P1 only.
(a)
-20
-10
1
0
-1
P1
10
20
30
-20
-10
10
20
30
1
0
-1
-2
-2
P2
-3
P3
-3
P4
-4
-4
(b)
u/u0 (%)
'h/'h0 (%)
P2
P4
P3
P1
-Y
+Y
Figure 7. Changes of computed (a) horizontal effective stress and (b) excess pore
water pressure of soil element at depth of tunnel axis
CONCLUSIONS
Based on field observations and computed results, the following conclusions may be
drawn. Within the pile group, P1, P2, P3 and P4 denote the closest, the farthest, the
front and the rear pile to the tunnel, respectively.
1. The maximum measured transverse horizontal ground displacement was 0.2%D
(i.e., 15 mm) at depth of the tunnel axis when the shield was at the monitoring
section. When the shield was approaching to the monitoring section, outward soil
movement away from the shield was observed due to stress redistribution. As the
shield reached the monitoring section, an abrupt change of inward horizontal
ground displacement toward the shield was observed as a result of stress relief
around the shield.
2. The influence zone of load transfer and pile head settlement are computed when
the shield advances from 1D (tunnel diameter) away from the center of the pile
group to 1D beyond the center of pile group. As the shield advances towards the
pier, computed pile load at P2 increases because it is the least affected one by
shaft resistance reduction due to tunneling. On the other hand, loads at pile head
of P1, P2 and P3 decrease because of load re-distribution within the pile group.
The maximum pile head settlement occurs on P3 causing the pier to tilt in the
longitudinal direction of tunnel towards P3.
557
3128
558