CDC UP Risk Management Practices Guide
CDC UP Risk Management Practices Guide
PRACTICES GUIDE
RISK MANAGEMENT
Document Purpose
The purpose of this document is to provide guidance on the practice of Risk Management and to
describe the practice overview, requirements, best practices, activities, and key terms related to these
requirements. In addition, templates relevant to this practice are provided at the end of this guide.
Practice Overview
Project risk must be identified, managed, and addressed throughout the project in order for the project to
be successful. Risk management plays an important role in maintaining project stability and efficiency
throughout the project life cycle. It proactively addresses potential obstacles that may arise and hinder
project success and/or block the project team from achieving its goals. Project risk can be anything that
threatens or limits the goals, objectives, or deliverables of a project. Project risk is present in all projects
and may have one or more causes and, if it occurs, one or more impacts.
PROCESS
Project risk management is an iterative process that begins in the early phases of a project and is
conducted throughout the project life cycle. It is the practice of systematically thinking about all possible
outcomes before they happen and defining procedures to accept, avoid, or minimize the impact of risk on
the project.
Types of risk that are considered during this process are:
Financial risk such as investments, funding, capital expenditure, etc.
UP Version: 11/30/06
Page 1 of 7
The Capital Planning and Investment Control (CPIC) process focuses specifically on the following types
of risk areas:
Schedule
Initial Costs
Life-cycle Costs
Technical Obsolescence
Feasibility
Reliability of Systems
Dependencies/Interoperability
Surety Considerations
Future Procurements
Project Management
Overall Project Failure
Organizational/Change Management
Business
Data/Information
Technology
Strategic
Security
Privacy
Project Resources
Effective risk management accomplishes:
Identification of risk
Evaluation and prioritization of identified risks
Assignment of risk owners
Development of risk response plans
Tracking and reacting accordingly
Monitoring and controlling risks
Project teams should hold meetings to identify risk and to define an appropriate strategy for dealing with
those risks. These activities are documented and used in the development of a Risk Management Plan
(RMP). The RMP describes the approach and processes for assessing and controlling risks in the project.
PMI PMBOK defines a RMP as a document that describes how project risk management will be
structured and performed on the project. It is contained in or is a subsidiary plan of the Project
Management Plan (PMP). During the creation of the RMP a prioritization process follows the identification
of risk whereby the risks with the greatest potential impact are prioritized first.
Page 2 of 7
Page 3 of 7
Impact
Based on the probability and impact assessments of each risk, the project manager may map the risks
using red/green/yellow color-coding.
H _______ _______ _______
Green: LL (Low Probability, Low Impact), LM (Low Probability, Medium
M
Impact), ML (Medium Probability, Low Impact)
Yellow: LH (Low Probability, High Impact), MM (Medium Probability,
L
Medium Impact), HL (High Probability, Low Impact)
Red: MH (Medium Probability, High Impact), HM (High Probability
L
M
H
Probability
Medium Impact), HH (High Probability, High Impact)
Additional advanced risk analysis techniques exist outside the scope of this document. These techniques
can be further researched by the reader, if needed, and include techniques such as:
Process Assessment
Probability and Impact Analysis
Probability Distributions
Sensitivity Analysis
Decision Tree Analysis
Modeling and Simulation
Risk Response Planning
Risk response planning includes the identification and assignment of one or more persons to take
responsibility for each identified risk and defines the actions to be taken against that risk through the
development of measures and action plans to respond to risk should it occur. PMI PMBOK defines Risk
Response Planning as the process of developing options and actions to enhance opportunities and to
reduce threats to project objectives. Risk response actions may include:
Mitigation Risk mitigation involves taking early action to prevent or reduce the likelihood of risk.
Contingency Contingency plans define actions to be taken in response to identified risk triggers in
hopes of reducing potential project impact from identified risk.
Transfer Risk transfer involves shifting the responsibility/ownership of the risk to another party. This is
typically done by purchasing insurance against the type of risk.
UP Version: 11/30/06
Page 4 of 7
Page 5 of 7
functionality, performance, reliability, availability, resources, etc. For C&A information security
risk requirements refer to http://intranet.cdc.gov/ociso/. For NIST risk requirements refer to
SP-800-30 located at http://csrc.nist.gov/publications/nistpubs/.
o Risk Analysis Summarize the probability of risk occurrence and assess the likelihood of
the risk occurring. Summarize the potential impact of the risk on the projects objectives.
Based on the probability and impact assessments for each risk, map the risks using
red/green/yellow color-coding.
o Qualitative Risk Analysis Summarize the probability of occurrence for each identified risk
based on an assessment by the project manager, with input from the project team.
o Quantitative Risk Analysis Summarize the probability and impact assessments of each
risk, the project manager may map the risks using red/green/yellow color-coding.
o Response Summarize the techniques and actions that will be taken to respond to identified
risks. Prioritize risk based on identified qualitative and quantitative characteristics. Define risk
thresholds and assign oversight responsibility of the risk to team members. Identify the risk
symptoms and triggers and then document mitigation and contingency plans, risk transfer,
avoidance, and/or acceptance strategies.
o Risk Monitoring, Controlling, and Reporting Summarize how risk will be monitored and
reported throughout the projects life.
Tools and Practices Summarize any tools that will be used to log and track risk and risk status
updates, where the tools are located, where information will be stored, etc. Summarize processes
defined specifically for the purpose of risk management such as how risk will be evaluated,
measured, reported on, etc.
Best Practices
The following best practices are recommended for Project Risk Management:
Identify Early Identify potential project risks as early in the project life cycle as possible.
Document these initially identified risks in the project charter and clearly communicate their
potential consequences to project sponsors and stakeholders.
Identify Continuously Continually identify and reevaluate project risk. When new risk is
identified communicate updates as needed.
Analyze Analyze the potential impact of identified project risk. Repeat this analysis process
throughout the project life cycle, make updates, and communicate changes as needed.
Reprioritize As risks are continually analyzed throughout the project life cycle, reprioritize risks
as potential project impact adjusts to changing project events.
Define and Plan - Define risk thresholds and triggers, mitigation strategies, and contingency
plans. The greater probability of occurrence and/or impact on project goals, the more detailed this
information should be.
Communicate Communicate regularly regarding risk status and changes in the level or overall
project risk. Solicit feedback from project team members and stakeholders regarding known risk
and the prospects of unknown risk. Store the risk management log in a location accessible to the
project team so that, if necessary, anyone can obtain updates at any time.
Update Update the risk management log on a regular basis, both informally and formally.
Educate Educate the entire project team and stakeholders on risk management and encourage
them to actively identify, communicate, and mitigate risk.
Practice Activities
For software development projects the following practice activities are appropriate:
Identify Identify project risk.
Evaluate/Analyze Analyze identified risks and evaluate potential impact on project goals.
Prioritize Prioritize risks based on probability of occurrence and potential impact on project
goals.
UP Version: 11/30/06
Page 6 of 7
Practice Attributes
This section provides a list of practice attributes to help project teams determine when and how
development of a Project Risk Management Plan impacts a project.
Practice Owner
Criteria
Estimated Level of
Effort
Prerequisites
Practice
Dependencies
Practice Timing in
Project Life Cycle
Templates/Tools
Additional
Information
Key Terms
Follow the link below to for definitions of project management terms and acronyms used in this document.
http://www2.cdc.gov/cdcup/library/other/help.htm
Related Templates/Tools
Below is a list of template(s) related to this practice. Follow the link below to download the document(s).
http://www2.cdc.gov/cdcup/library/matrix/default.htm
UP Version: 11/30/06
Page 7 of 7