Ata 24
Ata 24
- 1681,3 Hz
- 110 VAC.
inside the IDG and the other is just before the GLC They are
called the 3-Hole Current TransformersThe GCUs use the CT outputs for protection
functions (differential current, overcurrent, overload, open circuit)
If FADEC ENG SPEED data are not available, the GCU uses the PMG frequency to
determine the input speed of the generator.
Point Of Regulation (POR) is located between the 3-hole CT and
the GLC.
Each Generator Control Unit (GCU) is supplied by the PMG from its
related IDG and, as a back-up, through the battery bus 301PP
The main functions of the GCU are:The GCU is a type 1 computer:
- control of the field excitation via the Generator Control Relay (GCR),
- voltage regulation via the Excitation Control and Regulation module,
- speed regulation through the ServoValve Relay (SVR),
- control of the Generator Line Contactor (GLC) via the Power Ready
Relay (PRR), the Bus Tie Contactor (BTC) and the AUX RELAY 1,
- control and protection of the IDG and the network.
interface with Centralized Fault Display System (CFDS) via the Ground
and Auxiliary Power Control Unit (GAPCU).
GEN 1 LINE P/BSW
In SMOKE configuration (red smoke light on) an activation of this P/BSW
opens the GLC but the generator stays energized to supply directly the
fuel pumps 1 LH and 1 RH side
Pin programming provides the GCU with the following
information:
- the aircraft type,
- the GCU position,
- the current limit for voltage regulation,
- the load limit.
In case of an absent FADEC speed signal to the GCU,
a back-up signal is provided by the engine master switch to inform
the GCU logic that the engine will shut down
435 1Hz, for at least 4 seconds, the GCU trips
the PRR and the GCR.452 n above FOR 160 milli sec gcu trips PRR AND THE GCR ,SV
R
The feeder cables are duplicated from the engine pylon to the forward
cargo compartment
A 6 hole CT monitors each cable. If an open cable
is detected, or if the ENG FIRE P/BSW is released out, the GCU trips
the GCR and the PRR. The GLC opens after the PRR trips.
The Differential Protection is based on the comparison of each phase of
the Line 3-hole CT and the CTs in the IDG. If a differential current flow
is above 50 10A for at least 60 milliseconds, the PRR and GCR are
tripped
Differential Protection circuit reset is done via the GEN P/BSW,
but it is limited to two attempts
The APU generator is not interchangeable with the Integrated Drive
Generators (IDGs).It can supply the entire electrical network
APU engine without a Constant
Speed Drive (CSD);
Power Control Unit (GAPCU).
The GAPCU receives fault data from GCU 1 and 2, on MIL-STD 1553
data links
The maintenance test can be performed only on ground with engine shut
down. It is initiated either:
- Automatically at each GAPCU power-up.
- Or manually from the MCDU.
On each engine, use the sight glass that is in the vertical position to
do the check of the oil level. If it is below the green band or above
the yellow band, do the oil servicing
Clogged filter indication is provided by a visual pop out indicator (the
DPI) mounted on the IDG. This indicator is installed opposite the
drive end of the IDG
ENGAGE THE IDG DISCONNECT MECHANISM
WITH THE DISCONNECT RESET RING BEFORE
YOU START THE ENGINE. IF NOT, YOU WILL
CAUSE DAMAGE TO THE GEAR TEETH, AT
ENGINE START.
YOU CAN DAMAGE THE DISCONNECT SOLENOID
BECAUSE OF OVERHEATING IF: YOU PUSH THE
IDG DISCONNECT P/BSW FOR MORE THAN 3
SECONDS. THERE MUST BE AT LEAST 60
SECONDS BETWEEN 2 OPERATIONS OF THE
SWITCH.
The IDG disconnection is irreversible in flight. Reconnection
of the system is then possible only on the ground
The generator operation
principle is identical to that of the main or auxiliary generation. The
generator output characteristics are:
- three phase 115/200V AC,
ITE SWTCH
FAULT LT GOES OFF.
BOTH AC BUS LOST:AC ESSEN SUPPLIED FROM AC ESSEN TRU
FUEL MAIN PUMP 1 LH AND RH ENG SUPPLIED FROM AC BUS 1
SMOKE CONFIRMED AVIO LINE FOR 5 MIN :GEN 1 LINE SMOKE P/BSW light comes on amber
on the EMERgency
ELECtrical PoWeR panel
If the APU GEN is lost due to
an overload on the ground, all galleys and cabin-related sub-buses are
off.
REFULLING ON BAT:supplied from normal network or via
MAINTenance BUS switch,- HOT BUS 701PP if no other power is available
During ten minutes (time delay in the 12 PR relay), the operator may
select any position on the mode select switch 3QU
If the operator does not switch off the refueling system, the relay 12PR
will cut off battery power supply to the refuel buses.
There are three identical Transformer Rectifiers (TRs): TR 1, TR 2 and
ESSential TR, each with 200 A :AC TO DC
There are two identical nickel-cadmium batteries of 20 cells each. If the
battery voltage is below 26.5V DC,23 AH EACH
BCL:ensure automatic battery connection for charging,
- protect the battery against thermal runaway and short-circuit,
- prevent complete discharging when the aircraft is on the ground.
In flight, in normal configuration, the batteries are isolated from
the network by its respective BCL.
Automatic switching
failure.
If TR 1 fails, TR 2
1 through DC BUS 2.
transferred from DC
DC BUS TIE class 2
is provided in case of TR 1 or TR 2
automatically supplies DC BAT BUS and DC BUS
The DC ESS BUS supply is automatically
BAT BUS to AC ESS BUS through the ESS TR. MG ON ECAM
failure