Marsa Al Seef Clause 8.3 Progamme Update (As On 23 Oct 2015) Summary
Marsa Al Seef Clause 8.3 Progamme Update (As On 23 Oct 2015) Summary
Phase 1
Actual/Forecast
Start
Finish
% Complete
Variance
21-10-15 28-10-15
Comments
Overall Phase
Basements/Foundations
31-Mar-15
27-Jul-15
31-Mar-15
16-Jul-15
100%
100%
11
Superstructure
7-May-15
8-Oct-15
12-Apr-15
28-Sep-15
100%
100%
19-Apr-15
13-Jan-16
9-Apr-15
3-May-16
5%
7%
-111
Tenant Access
3-Nov-15
28-Feb-16
0%
0%
-117
1-Dec-15
31-Jan-16
14-Mar-16
8-Jun-16
0%
0%
-129
Marine Works
31-Mar-15
30-Sep-15
4-Apr-15
11-Feb-16
50%
53%
-134
6-Jun-15
27-Dec-15
9-Nov-15
24-May-16
0%
0%
-149
Phase 2
Actual/Forecast
Start
Finish
% Complete
Variance
21-10-15 28-10-15
Comments
Overall Phase
Basements/Foundations
25-Apr-15
11-Apr-16
19-Sep-15
1-Oct-16
2%
3%
-173
Superstructure
6-Jun-15
28-May-16
29-Oct-15
16-Nov-16
0%
0%
-172
6-May-15
8-Oct-16
16-Dec-15
25-Mar-17
0%
0%
-168
20-Oct-16
0%
0%
-70
1-May-17
0%
0%
-169
Tenant Access
Commissioning & Handover
11-Aug-16
21-Mar-16
13-Nov-16
17-Aug-16
Marine Works
2-May-15
8-Dec-15
25-Apr-15
31-May-16
40%
44%
-175
16-Jul-15
11-Apr-16
14-Nov-15
31-Aug-16
0%
0%
-142
Phase 3
Actual/Forecast
Start
Finish
% Complete
Variance
21-10-15 28-10-15
Comments
Overall Phase
Shoring, Piling & Excavation
Works
11-Jun-15
7-Jul-16
31-Jul-15
1-Dec-16
1%
1%
-147
Basements/Foundations
14-Nov-15
28-Jul-16
3-Apr-16
21-Dec-16
1%
1%
-146
Superstructure
2-Apr-16
1-Oct-16
29-Sep-16
21-Feb-17
0%
0%
-143
3-Mar-16
17-Jan-17
27-Sep-16
27-Jun-17
0%
0%
-161
24-Apr-17
0%
0%
-144
Tenant Access
Commissioning & Handover
1-Dec-16
26-Jul-16
16-Feb-17
18-Dec-16
5-Aug-17
0%
0%
-170
Marine Works
26-May-15
25-Jul-16
26-May-15
17-Nov-16
20%
27%
-115
10-Oct-15
6-Aug-16
28-Nov-15
17-Dec-16
0%
0%
-133
Phase 4
Overall Phase
Shoring, Piling & Excavation
Works
Basements/Foundations
Superstructure
MEP, finishes & External Works
Actual/Forecast
Start
Finish
% Complete
Variance
21-10-15 28-10-15
18-Apr-15
21-Oct-15
11-Apr-15
13-Jan-16
0%
0%
-84
15-Jul-15
29-Feb-16
19-Aug-15
22-Jun-16
0%
0%
-114
15-Aug-15
13-Jul-16
13-Sep-15
15-Nov-16
0%
0%
-125
23-Jul-15
5-Jul-16
25-Apr-16
29-Oct-16
0%
0%
-116
20-Mar-17
0%
0%
-123
Tenant Access
17-Nov-16
18-Jan-16
22-Feb-17
15-Jun-16
21-Jun-17
0%
0%
-119
Marine Works
28-Jul-15
24-Dec-15
24-Oct-15
6-Mar-16
0%
0%
-73
25-Oct-15
31-Dec-16
13-Dec-15
19-Apr-17
0%
0%
-109
Actual/Forecast Dates are from updated Clause 8.3 Programme (Rev. 02) updated as on 23 October 2015
Comments
* Relocation of Storm water pumping main, 132 kV cable, 300 Dia. Water
main, Etisalat & Hortculture is delayed on account of approved NOC from
various authorities.
*Delay
in relocation of above services resulted in suspension of shoring works &
disrupted piling progress.
*Absence of
Finalized detailed design, revised design delaying procurement, engineering &
construction works
*Notice to Proceed, DM & RTA approved Design & NOC's yet to be received
*Delayed due to absence of Design NOC & approved ROW
Baseline
Start
Finish
TIS
Approval
Design NOC's
Current Master Plan Approval
Receive Approvals
Updated Affection Plans
Apply for Building Permits
Phase 1
Phase 2
Apply for Revised building Permits (Additions)
Phase 4
Phase 3 (Part A)
Apply for revised Master Plan Assessment
Apply for Revised Approvals
Apply for Revised Building Permits (Additions)
Phase 3 (Part B)
9/13/2015
Scheduled
Start
Finish
9/24/2015
9/30/2015
10/15/2015
10/15/2015
10/15/2015
11/15/2015
11/15/2015
11/15/2015
11/15/2015
12/15/2015
12/15/2015
12/15/2015
5/15/2016
5/15/2016
6/15/2016
Variance
Comments