Applications of Vibro For Infra Structure Projects in India
Applications of Vibro For Infra Structure Projects in India
Vibro Techniques
for
Infrastructure
Projects in India
Rainer Wegner
Contract Manager,
Keller Grundbau GmbH, Germany
Dr. V. R. Raju
Director,
Keller Ground Engineering India Pvt Ltd, India
A. Vetriselvan
Engineering Manager,
Keller Ground Engineering India Pvt Ltd, India
Presented by
Keller Grundbau GmbH
Kaiserleistr. 44
D-63067 Offenbach
Tel. +69 8051 - 0
Fax +69 8051 - 244
E-mail [email protected]
www.KellerGrundbau.com
Abstract
Ground improvement is often required to stabilise weak soils for the construction of
major infrastructure projects. Deep vibratory techniques have found acceptance and
application worldwide as technically sound and cost effective ground improvement
methods. This paper describes the application of Vibro compaction for the construction of
breakwaters to a total length of 5 km for the Seabird Naval Base at Karwar, Karnataka and
the application of Vibro Replacement for the construction of two LNG tanks of 84m dia at
the Shell LNG terminal at Hazira, Gujarat. The paper explains the basic principles of the
two techniques, the methodology and quality control measures adopted.
1. INTRODUCTION
Large civil engineering projects are being executed in India in order to enhance the infrastructure
of the country. Infrastructure facilities have to be often built at sites where the soil conditions are
not ideal. The soils may vary from loose sands to soft clay deposits requiring treatment to improve
the shear strength and to reduce the liquefaction potential in the case that the selected area is
prone to seismic activity.
Rigid foundations such as piling present a solution but these are often expensive. In such
circumstances, ground improvement using Vibro techniques offers a proven and economical
solution.
This paper explains the application of Vibro techniques in two different soil conditions:
1. Vibro compaction methodology and its achieved results in the construction of a breakwater at
the Seabird naval base at Karwar and
2. Vibro Replacement (Vibro Stone Columns) process and its application in the construction of
two LNG tanks of 84 m diameter at the Shell LNG Terminal at Hazira.
2. VIBRO COMPACTION
Vibro compaction is a technique used to densify loose filled or formed granular soils having fines
contents generally in the range of upto 10% to 15% using depth vibrators. The vibrations are
produced by rotating a heavy eccentric weight with the help of an electrical motor within the
vibrator. The vibratory energy is used to rearrange the granular particle in a denser state.
The vibrator with extension tubes is allowed to penetrate into the soil with the help of vibratory
force and high pressure water jets. Once the vibrator reaches the required depth, the water jets
are stopped /reduced and the vibrator is pulled back in short steps, in each step the vibrator is
held for a predetermined time interval. During this time, inter granular forces between the particles are reduced which helps in rearranging the particles in a denser state. The process is repeated
up to required level to form a soil mass having improved shear strength and compressibility
parameters.
Water level
Break water
10 m
14 m
Fine sand
Sea Bed
(clay, soft silt)
2.4. Testing
CPT tests were carried out following a period of 7 days after compaction at every 50 m length
along the breakwater. The tests were conducted at the predetermined locations and were typically
at the centroid of the four compaction probes or at the mid point between two compaction
probes.
Typical pre and post compaction CPT test results are shown in Figure 3. The post compaction CPT
values were often found to be 2 to 3 times more than the pre compaction CPT Values.
Cone Resistance (MPa)
0
Pre CPT
10
Post CPT
11
Depth (m)
12
13
14
10
20
30
3. VIBRO REPLACEMENT
Vibro replacement is a technique used to improve cohesive soils such as silts and clays and
granular soils with high fines contents (>15 to 20%). In this method, columns made up of stone
are installed in the soft/loose soil using the depth vibrator. The vibrator is used to first create a
hole in the ground, which is then filled with coarse granular fill (stones) during withdrawal of
the vibrator. The stones are then laterally displaced into the soil following repenetration of the
vibrator. In this manner a column made up of well compacted stones with diameters typically
ranging between 800 mm and 1100 mm can be installed in the ground.
Two methods of installation namely the wet and dry methods are available for the installation of
the columns. In the wet method, water jets are used to create the hole and assist in penetration.
In the dry method the hole is created by the vibratory energy and a pull down force.
T1001
T1002
Inner Shell
Outer Shell
Double-Wall Tanks
160,000 m
16 m
Stone columns
Pumps
Pipe Rack
Pumps
105 m dia.
T1002
Tank
84 m dia.
T1001
Zone of improvement
Pipe route
3.2. Treatment
The 34 m high LNG tank imposes a static design load of 230 kPa. In addition a maximum peak
ground acceleration of 0.25 g is to be expected during a possible earthquake event.
Ground treatment was therefore required to
a) Increase the density of the soil and there by reduce the settlements of the tank
under the static load to within 120 mm.
b) Reduce the liquefaction potential in the sand layer by strengthening the subsoil and
also by providing effective drainage to prevent excess pore water pressure.
Vibro stone columns (Vibro Replacement) was selected to achieve the above objectives. The
coarse permeable material of the column allows rapid dissipation of excess pore water pressure.
The columns made up of highly compacted granular material act as a flexible reinforcement in the
soil to increase the overall shear strength of the treated soil. During the process of column
installation, sandy soil between the columns is densified.
3.3. Design
The responsibility of design and execution of stone column works was given to Keller.
Curve A in Figure 5 shows the required CPT for no liquefaction as per Stark & Olson (1995).
Curve B shows the existing Qc which is less than the theoretically required value. Ground
improvement works were designed using the Priebe method. The installation of well compacted
stone columns which are able to carry a large portion of the shear forces during an earthquake
results in a reduction in the requirement for the Qc value in the soil between the columns (now
shown by curve C).
As per the design, 1.0 m diameter columns on a square grid spacing of 2.4 m c/c to a depth of
16 m from the existing ground level were to be installed. The annular width of treatment was
extended beyond the tank edge by 10 m.
Cone Resistance (MPa)
0
Curve A - Required Qc with out SC
Curve B - Pre CPT
0
2.5
7.5
10
12.5
Depth (m)
15
17.5
20
10
15
20
CONCLUSIONS
Post compaction CPT testing has shown that Vibro Compaction is a reliable technique for the
offshore densification of loose sands at Karwar. Similar testing has also proven that Vibro
Replacement is able to mitigate liquefaction potential and reduce settlements to within tolerance
limits for large and settlement sensitive LNG tanks at Hazira.
In the case of the LNG tank foundation, Vibro Replacement has proven to be economical as
compared to conventional rigid foundations which require extensive reinforcement to counter
large horizontal forces in the event of an earthquake.
REFERENCES
Priebe, H. J. (1995), The Design of Vibro Replacement, Ground Engineering Vol 28, No 10.
Priebe, H. J. (1998), Vibro Replacement to Prevent Earthquake Induced Liquefaction,
Ground Engineering Vol 39, No 10.
Raju, V.R., Wegner. R., Godenzie. D. (1998), Ground Improvement using Vibro Techniques
Case Histories from S.E. Asia, Ground Engineering conference
Stark, T.D. and Olson, S.M. (1995), Liquefaction Resistance Using CPT and Field Case Histories,
Jl of Geotechnical Engineering, ASCE, 121.