IEEE-PES PSRC Report On Design and Testing of Selected System Integrity Protection Schemes
IEEE-PES PSRC Report On Design and Testing of Selected System Integrity Protection Schemes
I. INTRODUCTION
System Separation
Shunt Capacitor Switching
Tap-Changer Control
SVC/STATCOM Control
Turbine Valve Control
HVDC Controls
Power System Stabilizer Control
Discrete Excitation
Dynamic Braking
Generator Runback
Bypassing Series Capacitor
Black-Start or Gas-Turbine Start-Up
AGC Actions
Busbar Splitting
SIPS often are the last line of defense for preventing the
protected power system or portions of the system from
cascading outages. The proper design, documentation, and
testing of SIPS is the basis for reliable and accurate operation
of such schemes. For some SIPS, their design and/or testing
have been studied extensively over the years, such as the
under-frequency load shedding scheme [3], out-of-step
tripping [4], etc., while other SIPS (e.g. generator rejection,
load rejection, etc.), which are also in wide use in power
systems [1], are less studied.
This IEEE/PES PSRC report, Design and Testing of
Selected System Integrity Protection Schemes, was developed
to provide practical design examples for five widely used
SIPS: (1) Generator rejection; (2) Load rejection; (3) Adaptive
load mitigation; (4) Dynamic braking; and (5) System
separation.
The report includes information in two main areas: the high
level general considerations in SIPS design and testing, and
more detailed specific design considerations and the testing for
the selected five SIPS design and application examples.
II. GENERAL CONSIDERATIONS IN SIPS DESIGN AND TESTING
Although SIPS are typically different from each other
because their applications are specific to special requirements,
there are some considerations in their design and testing that
are generally common to them all. The report has included the
Centralized Processor B
Centralized Processor A
Processor 1
Switch
Processor 2
Processor 3
Switch
Router
Router
III. Mitigation
1. Generation/load level monitoring
2. Generation Tripping/load shedding
Substation #N (SIPS B)
Substation #N (SIPS A)
Substation #1 (SIPS B)
Substation #1 (SIPS A)
Generation
or
Load
Relay
Relay
with
Logic
Relay
Switch
Router
Switch
Router
Telecommunications
Network A
Telecommunications
Network B
Communications Requirements
Communications are used by SIPS to acquire data from
distant locations for the central controller where the decision
for any action is made. Communications are also used to send
SIPS control commands to the field to execute the mitigation
action. In order to assure power system stability, SIPS signals
executable test cases that confirm how well the SIPS satisfies
the requirements at any given time or under any specific
conditions. A test plan needs to be developed in order to build
a suite of executable tests that define and verify the
functionality requirements, providing a fast and objective way
to assess the performance of the tested function. It is important
to include in this test plan the simulation of common events
and conditions for which the SIPS should not operate,
particularly when the consequences of false operation are
harmful to the system or costly. This process should start
together with the design of the SIPS and follow through at
each step until the detailed test plan for the SIPS and each of
its components is defined. These tests can then be executed
regularly to ensure that functional modifications or firmware
upgrades do not unintentionally change previously verified
functionality.
An effective functional testing practice involves the
definition of guidelines for using functional testing
technologies effectively (based on the users protection testing
philosophy), and then the implementation and integration of
those guidelines into the asset management system.
To achieve effective system testing, the user or
manufacturer must not only have a defined practice for its use,
but that practice must be implemented and integrated into the
engineering process so that it can be used consistently and
regularly across the organization. The definition of the
functional tests will be part of the design and testing
documentation of the SIPS. At the time when the functionality
of every single element of the SIPS is designed, it must be
specified how it is going to be tested.
Utility Documents
The design and testing of SIPS may need to follow the
requirements of reliability coordination authorities in addition
to utilitys own guidelines. Individual utilities have also
developed whitepapers and internal guidelines about the SIPS
for their own use. These documents should be consulted and
the requirements should be followed in the SIPS design,
documentation, and testing guidelines to ensure compliance
where they are implemented.
stability problems.
The generator rejection design example provided in this
report is for a four unit coal-fired electrical generating plant
(the Plant) located in the western United States. The plant has
the capacity of a net output of 2120 MW, and it is remote from
the load and connected to a transmission network by three long
345 kV and two 230 kV transmission lines. When the
transmission path is being operated at the path load transfer
limit and a transmission line in the path is lost, the generation
at the Plant must be reduced to maintain the transient stability
of the power grid. To arrest the transient power swing
following the clearing of the line fault from dropping the
voltage below 0.3 per unit, a SIPS that trips generating units at
the Plant is deployed.
Load rejection
Load rejection is a protection system designed to trip load
following an event or disturbance that causes supply-load
unbalances that may lead to a wide area disturbance. Load
rejection SIPS typically are designed to keep a system or subsystem in parallel with the remaining parts of the system in
case of the loss of a major supply to the affected power system
area. Load rejection differs from the automatic underfrequency load shedding, since one of SIPS main goals is to
prevent the separation of an area of the system before the
change of frequency can result in the operation of the underfrequency relays.
The load rejection SIPS design example provided in this
report is for a transmission system in northern Chile. The load
reject scheme is used to maximize the use of the transfer
capability of the power flow between station A-B and B-C as
shown in Fig. 2. The scheme disconnects loads automatically
in order to adjust to the remaining operating line capacity
(using adjusted n-1 safety criterion).
LINE 9
(REMOTE)
E1 = V + ITOTAL*X
SUBSTATION C
SUBSTATION D
SUBSTATION B
LINE 5
LINE 4
MONITORING
SUBSTATION A
345 KV
BUS
LINE 6
138 KV BUS
ITOTAL
68-1
AUXILIARY
TRANSFORMER
5/12.5 A
LINE 1
68-2
LINE 2
LINE 3
Dynamic braking
A dynamic brake is a resistive shunt type load that is
switched onto the power system briefly to help maintain
transient stability once a disturbance has occurred. For the
design example in this report, application of a dynamic brake
is used to enhance transient angular stability between adjacent
systems allowing one system to benefit from the other systems
remotely located renewable power sources [5]. When first
installed, availability of this three-phase 1400 MW braking
scheme was thought to increase power transfer capability by
900 MW.
The dynamic braking scheme is applied to a system which
also has several other SIPS schemes in operation at any time.
Using dynamic braking scheme avoids the need for equivalent
generation reduction amounts using a gen rejection scheme
when the system is in export mode. The brake is applied at a
single location adjacent to large hydroelectric generation units
V. ACKNOWLEDGMENT
This paper is based on the report created by IEEE Power
System Relaying Committee working group C15 and is
available at http://www.pes-psrc.org. The content of the report
is a collective effort of many industry members from IEEE
PSRC. The authors acknowledge contributions by the Working
Group members that have made this report [2] possible:
[2]
[3]
[4]
[5]
BIOGRAPHIES
Jonanth Sykes (SM) is Manager of System Protection at
Pacific Gas and Electric Company in
Oakland California. Jonathan graduated
from the University of Arizona in 1982,
is a Professionally Licensed Electrical
Engineer, and has 30 years of
engineering experience in System
Protection. He is active on several
committees in the Western Electric
Coordinating Council and is past
Chairman of the North American Electric Reliability
Corporation System Protection and Control Subcommittee.
Jonathan has authored and co-authored papers for conferences
and publications and is an active senior member of IEEE and
regularly contributes to the Power System Relay
Committees. Jonathan has been involved in EHV protection
and control for over 15 years and established standards in
EHV relaying and SPS/RAS design and implementation.
Jonathan has been active in NERC and WECC standards
interpretation and development and is a subject matter expert
in the interpretation of various protection and critical
infrastructure related standards.