Specification For Foundation Fieldbu Essar
Specification For Foundation Fieldbu Essar
INDEX
CLAUSE DESCRIPTION PAGE
1 Scope 4
2 Conflicts and Deviations 4
3 References 4
4 Definitions 5
5 System Design 6
6 Wiring Design 7
7 Fieldbus Devices 12
8 Non-Device Element Selection 13
9 Host Requirements 15
10 Consideration For Detail Engineering 18
11 Documentation 18
12 Factory Acceptance Test (FAT) 20
13 Site Acceptance Test (SAT). 21
14 Installation and Checkout 21
15 Maintenance Shop Fieldbus System and Tools Level Update 21
16 Fieldbus Spare Parts and Revision Program 22
17 Foundation Fieldbus Training 22
Annexure A Fieldbus Glossary of Terms 25
1 SCOPE
The use of FOUNDATION Fieldbus based control system is to be followed in the Refinery expansion
project of Essar Oil Limited, Vadinar, Jamnagar.
This specification defines the requirement for design, specification, installation, configuration;
commissioning and maintenance for FOUNDATION Fieldbus based control systems.
The specification covers the minimum requirements for the design and installation of H1 Foundation
Fieldbus (FF) system based on 31.25 kbps physical layer as defined in ISA 50.02
This specification is intended for use by Detail engineering contractor and by Control System vendor for
integrated services.
FOUNDATION Fieldbus systems include instruments and host that covers all applications and aspects
of instrumentation and control.
A FOUNDATION Fieldbus based control system shall not be used for the following systems
Emergency Shutdown System
Fire and Gas System,
Burner Management System,
Compressor Anti-surge Control System
Close Loop Control with scan time faster than 300 msec.
Discrete Motor Monitoring & Control System
Complex Control loops with multiple maths function
Instruments commercially not available (Nucleonic Instruments)
Packages Control System
3 REFERENCES
3.1 Essar Engineering Centre References
3.2 Industry Codes and Standards
The International Society for Measurement and Control (Refer latest standards)
ISA 5.1
ISA 50.02, Part 2
FF-569 FOUNDATION
FF-816 FOUNDATION
FF-890 FOUNDATION
AG-163 FOUNDATION
AG-181 FOUNDATION
AG-140 FOUNDATION
FF 940 FOUNDATION
IEC61158-2
IEC60079-27
NFPA 70
Communication Profile
Digital data communication for measurement and control
fieldbus for use in Industrial control system Part 2 through Part
6
Electrical apparatus for explosive gas atmosphere Part-27:
Fieldbus intrinsically safe concept (FISCO) and Fieldbus nonincendive concept (FNICO)
National Electrical Codes (National Fire Protection
Association)
4 DEFINITIONS
All definitions of Fieldbus terms and acronyms used in this document can be found in appendix 'A'.
A typical fieldbus segment that shall consist of the following components, reference Figure 1:
H1 - Foundation Fieldbus Interface Card (Redundant)
FFPS - Foundation Fieldbus Power Supply (Redundant)
JB - Junction Box
BPS - Bulk power Supply (24 V DC) (Redundant)
FBB - Foundation Fieldbus Barrier
HPT - High Power Trunk
Fieldbus Devices, (e.g., transmitters, transducers, Temp Multiplexers etc.)
full implementation of 32 devices, 1900 m total cable length (Trunk + Spur) with type A cable, 100 m
maximum spur length without compromise, even when connecting to FISCO field devices.
The HPT design for intrinsically safe applications uses the Fieldbus barrier that is situated within an EEx e
enclosure taking its power from 2-wire field bus trunk and behaves like a 4 output EEx ia FISCO power
supply. As the trunk uses EEx e safety techniques for its protection, conventional fieldbus supplies can be
used, providing typical outputs in the region of 24-32V at 350 mA - 500 mA.
The use of conventional fieldbus supplies enables the provision of true redundancy for both the H1 host
and the power supplies, ensuring system availability in the case of failure. By using conventional fieldbus
supplies, Advanced Diagnostics on the fieldbus physical layer also becomes available, providing
predictive maintenance on a part of the installation that typically causes most problems.
The fieldbus barrier design concept shall ensure the following:
1. Intrinsic safety on the outputs (spurs)
2. Galvanic isolation between the non IS fieldbus segment (Trunk) and the IS fieldbus segment (spurs)
and between the output circuits. The Trunk is galvanically isolated from the outputs.
3. Fieldbus terminator connected at both end of the FF trunk.
FF design should be followed for all monitoring & Control loops. For skin temperature monitoring FF
multiplexer shall be used.
5.3 Basic Segment Loading Requirements
Note: Prior to defining Fieldbus segments, the process control strategy should be complete, the P&IDs
available, instruments selected, and instrument locations determined.
Redundant H1 Interface cards shall be used for all segments.
Each segment shall have an enabled backup Link Active Scheduler (LAS) in a field transmitter device.
Note: The preferred location of the backup LAS is in a monitoring only (i.e., not used for control) field
device.
The 'primary' LAS shall reside in the H1 interface card.
5.4 Segment Executions Time
The suggested number of devices per segment, for monitoring shall be limited to twelve (12) devices.
Each segment shall operate with a single specified macrocycle execution time. Multiple macrocycles shall
not be used on a single segment, even if available in a vendor's particular product.
The vendor's configuration software shall automatically allocate sufficient unscheduled (free
asynchronous) time as required by the vendor.
Notes: Function block execution frequencies must be compatible with both system loading and process
control objectives. The execution frequency of all function blocks contained within a single fieldbus
segment is defined by that segment's macrocycle time. This macrocycle time, which can typically range
from 250ms to several seconds (depending on the nature of the application), is configured for each
fieldbus segment. Some vendor's configuration products allow devices on the same segment to operate
at different macrocycle times.
However, backup LAS devices are not capable of managing these multiple macrocycles, so this feature
may not be used. The order of execution should be automatically determined by the vendor's
configuration software, based on the connections between function blocks on the fieldbus segment.
Note that the macrocycle contains unscheduled time required for non-deterministic bus communications,
such as alarm transmission, set point changes, etc. The vendor's recommended unscheduled time should
be allocated for each macrocycle. Note that the minimum may change based on how much bus required
communication is configured as deterministic. While it is hoped that the vendor's configuration software
will manage and maintain minimum unscheduled time, this is not necessarily true, and must be verified.
Network \ Segment Execution Time.
The network/segment macro cycles should match the DCS module execution times. Each
network/segment should operate with a single specified macro cycle execution time. Multiple macro
cycles shall not be used on a single network/segment without the approval of Client. Care should be to
ensure that the network does not become overloaded.
Use a default segment execution time of one (1) second unless otherwise approved by the Client. Further
guidance on segment times is given below.
Network/Segment Execution Time
The network/segment macro cycles should match the module execution times.
Macrocycle
The Macrocycle should have minimum of 50% unscheduled (free asynchronous) time. The unscheduled
time Calculation shall allow for spare capacity requirement. Therefore newly commissioned segment
should have minimum of 50% unscheduled time.
The suggested maximum numbers of devices per segment for the following listed execution times are as
Follows:
For segments with monitor only measurements, limit segment to twelve (12) devices. (10 in use +
2 Spare)
For loops requiring 1-second macrocycle time, limit segment to twelve (12) devices with 4 valves.
(6 TX+ 4 CV+ 2 SPARE)
For loops requiring 0.5-second macrocycle time, limit segment to six (6) devices with 2 valves. (2
TX+ 2 CV+ 2 SPARE)
For loops requiring 0.25-second macrocycle time, limit segment to three (3) devices with 1 valve.
(1 TX+ 1 CV+ 1 SPARE)
Typically
1 Second macro cycle time to be considered for all parameters other than temperature monitoring
2 Second macro cycle time to be considered for temperature monitoring points
Each macro cycle should have a minimum of 50% unscheduled time with allowances for spare
capacity Requirement
each segment with a 1 sec macro cycle time. As defined in the FF design spec, 10 devices are to
be considered per segment with 2 as future spare.
Generally, MUX will not be combined with other FF devices in the same segment, however, if a
situation arise where combination of FF devices and MUX would be required, the loading of the
devices shall follow the Segment macro cycle time of 1 second.
In such a case, there shall be 1 MUX + max of 6 other FF devices (Including 2 futures spare).
Accordingly the total cycle time would be 1 x 256 mSec + 6 x 40 mSec = 496 mSecs.
6 WIRING DESIGN
6.1 SEGMENT TOPOLOGY
The fieldbus installation shall use the 'tree', or 'combination' topology as shown in Figure-2. The spur and
daisy chain topology (i.e., routing the trunk directly through each device) shall not be used.
Notes: Components of fieldbus segments can be connected together in various architectures known as
topologies.The topology selected is usually driven by the physical device location in order to reduce
installation costs. Hence, plot plans are used in addition to P&ID's and instrument indexes in the
design of a fieldbus segment.
Most often, after the above design considerations are weighed, the following three topologies are used:
(See
Figure 2)
A tree topology is used when several related instruments are physically located close to
each other. A fieldbus junction box is located close to the instruments with spurs
extending from it to each instrument.
A spur topology is used when several related instruments are located in the same
direction from the host device but not necessarily close to each other. In this case, a
trunk line is extended from the host to the farthest instrument and spurs are extended
from it as it runs past each instrument. It is not to be followed.
A spur/tree topology is used when some combination of the above instrument locales
exists. Note that spurs are permitted to extend only from trunk lines and not from other
spur lines.
Daisy chain topology may appear to reduce total wiring run length and connection cost, but it has a
significant disadvantage. That disadvantage is maintainability and reliability downstream of each device.
When a device is removed from a daisy chain topology segment, all downstream devices are also
disconnected.
Trunk
Spur
To H1
Card
Tree Topology
Junction
Box (JB)
To H1
Card
Spur Topology
To H1
Card
Junction
Box
Combination
Topology
To H1
Card
Daisy-Chain
Topology
(JB) (JB) (JB) (JB)
(JB)
Do Not Use
total segment length is computed by adding the length of the main trunk line and all the spurs that extend
from it.
Do not use
6.2.2 Total Segment Length = Trunk + All Spurs
Note: The maximum length given is specified in the ISA 50.02 Fieldbus standard. The length of a
segment is limited by voltage drop and signal quality (i.e., attenuation and distortion).
6.3 SPURS
6.3.1 Only one (1) FOUNDATION Fieldbus (FF) device shall be connected to each spur.
6.3.2 Though the maximum spur length can be 120 meters (394 ft.) but 100 meters (max) is to be
considered for
design. The spur length is the length of the cable from the 'wiring block' to the FF device.
Note: A spur is a drop off of the main trunk line. The trunk is considered to be the main cable run and will
contain segment terminators at each end.
6.8.1 Circuit analysis shall be carried out for each fieldbus segment to determine the operating voltage at
each
device. The calculated voltage at the device shall exceed the devices minimum voltage rating by 4 volts,
(e.g., minimum Vdc required by device = 9 volts, therefore the calculated minimum voltage seen at the
device shall be 13 Vdc).The calculated voltage at each device shall be shown on the Instrument Segment
Diagram (ISD) or Bus Coupler Arrangement Drawing.
Commentary Notes: The additional 4-volts at each device have been specified as a spare power margin
for
future device additions to the segment.
Per the FOUNDATION fieldbus specification, field devices must sense a DC voltage between 9 and 32 volts
for
proper operation.
The power used by fieldbus devices varies by device type and manufacturer. Specific minimum voltage
and
current requirements are contained in the product specifications for each device. The voltage and current
requirement for each device shall be taken into consideration while conducting the circuit analysis of the
segment. A Fieldbus FOUNDATION certified device is required to be capable of operating at > 9 Vdc.
7 FIELDBUS DEVICES
7.1 Following are the minimum requirements for Field bus Devices.
7.1.1 The device shall satisfy the requirements of the Fieldbus Foundation specifications and shall have
FF
CHECKMARK. The Devices shall be certified for intrinsic safety EEx ia (ATEX or equivalent certification).
7.1.2 Foundation Field bus Device shall be certified as passing the ITK 4.61 or later and shall include
Device
Description (DD) and Common File Format (CFF) files.
7.1.3 The FF device and all function blocks shall be tested and certified by the vendor of the control
system Host.
7.1.4 The Devices shall be provided with Flash memory for downloading the revised firmware in future.
7.1.5 Function block shall be downloadable into the devices by the end user.
Wiring Block Wiring Block Wiring Block
Marshalling Panel
Satellite Building
Intermediate FF
Junction Box
FF Spur Junction Box
FF Device
1 Pair, Type A
Type A
Trunk
cable
Type A
Trunk
cable
FOUNDATION FIELDBUS EARTHING ARRANGEMENT
7.1.6 Capable of performing continuous diagnostics, including self test functions, to provide specific
diagnostic
information at the Man Machine Interface (MMI).
7.1.7 All Fieldbus instruments shall include menus and methods (wizards) to allow easy setup and
calibration
from the MMI.
7.1.8 FF Device shall have three support files .FFO, SYM and CCF which contain information necessary
to
configure the Host systems. The support files shall include two Device Description Files and one
Capability
File, as defined in Fieldbus Foundation specification FF-940. The capabilities file and DD files shall be
provided by the device vendor and shall not be downloaded from the Foundation Fieldbus website.
7.1.9 Device vendors shall provide DTM (Device Type Manager) files for all devices and shall develop
these file
where they are not available. The DTM files shall be compatible with the host DCS system using
FDT/DTM
technology.
7.1.10 Standard programmatic interface shall follow FDT Group 1.2 standards. Any revision to host
Operating
System or device DD shall not require changes to the DTM for EDD.
7.1.11 Most Foundation Fieldbus devices can be powered directly from the Fieldbus. The DC supply
voltage can
range from 9-32 Vdc. The transmitting device delivers 10 mA at 31.25 kbits/s into a 50 ohm equivalent
load
to create a 1.0 volt peak-to-peak voltage modulated on top of the direct current (DC) supply voltage.
7.1.12 Loss of power or disturbance to one power supply module shall not result in the reset of a field
device in any
circumstances.
7.1.13 In order to reduce commissioning time each field device must be pre configured by the
manufacturer as
indicated on the instrument datasheet.
7.1.14 Temperature multiplexers shall be with 8 input and the input can be RTD or T/C.
7.1.15 None of the device shall be polarity sensitive.
7.1.16 All field bus devices shall have capability to perform continuously their own self diagnostics to
check their
health state.
7.1.17 Where ever specified for FF devices (Transmitters installed on high columns and open area like
tank farms)
shall be provided with necessary surge protection device in the concerned spur in the JB.
8.2 Terminators
8.2.1 Each fieldbus segment must have exactly two terminators. The terminator in the field will be at the
end of
trunk. ( last FFB JB of the segment )
8.2.2 All terminators located in the field shall be installed in a junction box. No terminators shall be
installed in
the FF devices.
and duly certified. Separate DIN mounted Terminator shall be provided inside the enclosure if more than
one
FBB is in the segment.
8.4.11 Fieldbus Sement Device Allocation
Control Loops
FF Barrier
JB Size Critical
Level 1
Critical
Level 2
Critical
Level 3
Max.
Additional
Devices
Total
Spurs
Used
Available
Spares
1 None None 1 3 1
None 1 None 1 3 1
None None 1 1 3 1
1 FB
Junction
Box
( 4 Spur
Max) None None None 3 3 1
1 None None 4 6 2
None 1 None 4 6 2
None 1 1 2 6 2
None None 1 4 6 2
None None 2 2 6 2
None None 3 None 6 2
2 FB
Junction
Box
( 8 Spur
Max)
None None None 6 6 2
1 None None 7 9 3
None 1 None 7 9 3
None 1 1 5 9 3
None None 1 7 9 3
None None 2 5 9 3
None None 3 3 9 3
3 FB
Junction
Box
( 12 Spur
Max)
None None None 9 9 3
Note: Each Controller is taken as one analogue input and one analogue output. Due
allowance for additional loop devices will be required for cascade loops and split
ranged controller application.
8.5 Repeater
9 HOST REQUIREMENTS
9.1 Host FF Interoperability
9.1.1 All FF Host systems shall have completed Host Interoperability Support Testing (HIST) at
FOUNDATION
Fieldbus facilities, based on HIST Procedures document FF-569. FF Host systems shall support all
features
specified in the HIST.
9.1.2 A letter of conformance to the Host Interoperability System Test shall be provided to verify test
completion
and feature support.
9.1.3 All supported FF HIST features shall be integrated seamlessly into the existing control system's
engineering,
configuration, maintenance, and operations system.
9.1.4 The Host System supplier shall have an interoperability test laboratory setup to ensure that all third
party
devices used in the project have been successfully tested and certified with their system, reference
section
9.2 Host Control System Requirements
In addition to the FF requirements specified in this document, Host systems shall meet all requirements
specified in "Distributed Control Systems".
9.3 Host FF Feature Integration
All Host FF functions, including engineering, configuration, maintenance, and operational display
functions,
hall be integrated into a single, seamless Host system. Engineering, configuration, maintenance and
operational features shall apply consistently and seamlessly to conventional analog or discrete I/O, smart
HART and proprietary I/O, bus based I/O, and FF systems. Separate software tools, displays, or
procedures specific for FF and different from conventional - are not acceptable.
9.4 Host-To-Device Revision Download Capability
Hosts shall have the capability to download software revisions to F OUNDATION Fieldbus devices.
9.5 Host Configuration Features
9.5.1 Host FF configuration shall be consistent in method and 'look and feel' with conventional
configuration.
9.5.2 Internal mirror or shadow function blocks used by control systems to map FF function blocks to
internal
proprietary function blocks must be completely transparent to the configurator and operator. Single,
unique
and independent function block and parameter tag names must be used for both configuration and
operation.
Duplicate shadow blocks/parameters with tag names different from FF block/parameters are not
acceptable.
9.5.3 The Host FF configuration tool shall seamlessly and transparently integrate with, and maintain, the
master
configuration database. Saves, restores and partial downloads of the master control system database
shall
be seamlessly and transparently accomplished for both FF and conventional control strategies by the
same
configuration tool.
switching, must be supported by, and transparently integrated into the control system operation and
operating displays. Differences in operation or displays between FF devices or loops and conventional
loops
are not acceptable.
9.7.3 FF process alarms and device alerts must be supported by, and integrated into the control system.
Differences between conventional and FF alarm management and alarm displays are not acceptable.
9.7.4 FF trend data via trend objects shall be supported by the Host control system and transparently
integrated
into real-time and historic trends displays.
11 DOCUMENTATION
FOUNDATION Fieldbus system design requires the same documentation as conventional control system
designs. However, some documents must be altered for FOUNDATION Fieldbus
architecture.Documentation
alterations, additions, and deletions required for FF use are defined below .
defines how and why specific Fieldbus devices are assigned to segments. The philosophy shall include
consideration for segment loading constraints and multiple segments per H1 card. See section 5.7 for risk
assessment and segment loading criteria.
11.2 PIPING AND INSTRUMENTATION DIGRAMS (P&ID's)
11.2.1 Fieldbus instrumentation shall be shown on the P&ID as per Essar Engineering Centre standards
with the
following exceptions:
11.2.1.1Fieldbus instrument balloons shall be conventional, with the addition of a Foundation Fieldbus
indication on
the top right side of the instrument bubble, shown as: FF
11.2.1.2The line symbology for FF signal wiring shall be the standard 'dashed' electric signal per ISA 5.1.
11.2.1.3 The
control or logic function balloons shall be shown independent of the hardware in which it is contained.
Note: PID, selectors, or arithmetic function blocks shall be shown functionally on the P&ID, (i.e., not
shown as
shared balloons with the device they reside in).
11.2.1.3 The control or logic function balloons shall be independent of the hardware in which it is
contained.
Note: PID, selectors, or arithmetic function blocks shall be shown functionally on the PID, (i.e., not shown
as a
shared balloons with the device they reside in).
11.2.2 All functions within the same field device shall be tagged with the same number, with individual
function
lettering appropriate for the application.
Note: For example using a multi-variable Coriolis meter, the instrument tagging would be FT-1010, DT1010,
and TT-1010 for flow, density and temperature, respectively.
11.2.3 Multivariable Fieldbus transmitters (e.g., multiple process measurements from the same
transmitter) shall be
represented with connected instrument balloons.
17 FIELDBUS TRAINING
Control System Vendor (ISV) to provide FF training programs targeted for the following categories of
company
personnel:
Engineers(Overview, Maintenance, Advanced)
Operators (Overview)
Maintenance Supervisors (Overview, Maintenance)
Maintenance technicians (Overview, Maintenance)
17.2 Courses and course requirements shall include following, but not limited to:
Foundation Fieldbus Architecture
Foundation Fieldbus terminology
Segment components, power and wiring.
Foundation Fieldbus communication and bandwidth issues.
Review of fieldbus function blocks.
Device Description language review.
17.3 Foundation Fieldbus Maintenance courses shall be as follows:
Foundation Fieldbus Architecture
Foundation Fieldbus terminology
Detailed review of segment components, segment design, power, intrinsic safety and wiring.
Foundation Fieldbus Communication and Bandwidth issues.
Review of Foundation fieldbus blocks.
Device Description language review.
Maintenance tools and troubleshooting.
DD file maintenance and updating
Interface to AMS.
17.4 Foundation Fieldbus Advance course:
H1 datalink layer.
H1 Bus monitor.
H1 System management
Fieldbus message specifications
High Speed Ethernet.
Object Dictionary
Function Block application process.
Advanced Control Strategies
DD file maintenance and updating.
17.5 A training program based at the DCS suppliers facilities may be developed for engineers and
supervisors.
An on-site training program may be developed for the operators and maintenance technicians.
The ISV vendor shall supply quotation for an on-site FF training simulator for on-going FF training support
of
the FF system.
17.6 Training Stages
The ISV vendor to implement FF training in phases as described below:
Engineering Phase
Prior to FAT Phase
Prior to SAT Phase
Company personnel to be trained in each phase shall be indicated by Essar Oil.
Engineering phase and prior to FAT phase training will be held at FF vendor facilities.
Prior to SAT phase training will be held at site.
HSE Switch: An HSE Switch is standard Ethernet equipment used to interconnect multiple High
Speed Ethernet (HSE) devices such as HSE Linking Devices and HSE Field Devices
to form a larger HSE network.
Input/Output (I/O) Subsystem Interface: An Input/Output (I/O) Subsystem Interface is a device used to
connect
other types of communications protocols to a fieldbus Segment or Segments.
Interchangeability: Interchangeability is the capability to substitute a device from one manufacturer with
that of another manufacturer on a fieldbus network without loss of functionality or
degree of integration.
Interoperability: Interoperability is the capability for a device from one manufacturer to interact with
that of another manufacturer on a fieldbus network without loss of functionality.
J
K
Link: A Link is the logical medium by which H1 Fieldbus devices are interconnected. It is
composed of one or more physical segments interconnected by bus Repeaters or
Couplers. All of the devices on a link share a common schedule which is
administered by that link's current LAS.
Link Active Scheduler (LAS): A Link Active Scheduler (LAS) is a deterministic, centralized bus
scheduler that
maintains a list of transmission times for all data buffers in all devices that need to be
cyclically transmitted. Only one Link Master (LM) device on an H1 fieldbus Link can
be functioning as that link's LAS.
Link Master (LM): A Link Master (LM) is any device containing Link Active Scheduler (LAS)
functionality that can control communications on an H1 fieldbus Link. There must be
at least one LM on an H1 Link; one of those LM devices will be elected to serve as
LAS.
Link Objects: A Link Object contains information to link Function Block (FB) Input/Output (I/O)
parameters in the same device and between different devices. The Link Object links
directly to a Virtual Communications Relationship (VCR).
M
Network Management (NM): Network Management (NM) permits FOUNDATION Network Manager
(NMgr) entities
to conduct management operations over the network by using Network Management
Agents (NMAs). Each Network Management Agent (NMA) is responsible for
managing the communications within a device. The NMgr and NMA communicate
through use of the Fieldbus Messaging Specification (FMS) and Virtual
Communications Relationship (VCR).
Object Dictionary: An Object Dictionary (OD) contains all Function Block (FB), Resource Block (RB)
and Transducer Block (TB) parameters used in a device. Through these parameters,
the blocks may be accessed over the fieldbus network.
Physical Layer: The Physical Layer receives messages from the Communications Stack and converts
the messages into physical signals on the fieldbus transmission medium, and viceversa.
Q
Resource Block (RB): A Resource Block (RB) describes characteristics of the fieldbus device such as
the
device name, manufacturer and serial number. There is only one Resource Block
(RB) in a device.
Schedules: Schedules define when Function Blocks (FBs) execute and when data and status is
published on the bus.
Segment: A Segment is a section of an H1 fieldbus that is terminated in its characteristic
impedance. Segments can be linked by Repeaters to form a longer H1 fieldbus.
Each Segment can include up to 32 H1 devices.
Splice: A Splice is an H1 Spur measuring less than 1 m (3.28 ft.) in length.
Spur: A Spur is an H1 branch line connecting to the Trunk that is a final circuit. A Spur can
vary in length from 1 m (3.28 ft.) to 120 m (394 ft.).
Standard Function Block (FB): Standard Function Blocks (FBs) are built into fieldbus devices as
needed to achieve
the desired control functionality. Automation functions provided by Standard FBs
include Analog Input (AI), Analog Output (AO) and Proportional/Integral/Derivative
(PID) control. The Fieldbus Foundation has released specifications for 21 types of
Standard FBs. There can be many types of FBs in a device. The order and definition
of Standard FB parameters are fixed and defined by the specifications.
System Management (SM): System Management (SM) synchronizes execution of Function Blocks (FBs)
and the
communication of Function Block (FB) parameters on the fieldbus, and handles
publication of the time of day to all devices, automatic assignment of device
addresses, and searching for parameter names or "tags" on the fieldbus.
Terminator: A Terminator is an impedance-matching module used at or near each end of a
transmission line. Only two Terminators can be used on a single H1 segment.
Transducer Block (TB): A Transducer Block (TB) decouples Function Blocks (FBs) from the local
Input/Output (I/O) functions required to read sensors and command output hardware.
Transducer Blocks (TBs) contain information such as calibration date and sensor
type. There is usually one TB channel for each input or output of a Function Block
(FB).
Transmitter: A Transmitter is an active fieldbus device containing circuitry which applies a digital
signal on the bus.
Trunk: A Trunk is the main communication highway between devices on an H1 fieldbus
network. The Trunk acts as a source of main supply to Spurs on the network.
User Application: The User Application is based on "blocks," including Resource Blocks (RBs),
Function Blocks (FBs) and Transducer Blocks (TBs), which represent different types
of application functions.
User Layer: The User Layer provides scheduling of Function Blocks (FBs), as well as Device
Descriptions (DDs) which allow the host system to communicate with devices without
the need for custom programming.
Virtual Communication Relationship (VCR): Configured application layer channels that provide for the
transfer of
data between applications. FOUNDATION fieldbus describes three types of VCRs:
Publisher/Subscriber, Client/Server, and Source/Sink.
Virtual Field Device (VFD): A Virtual Field Device (VFD) is used to remotely view local device data
described in
the object dictionary. A typical device will have at least two Virtual Field Devices
(VFDs).
W
X
Y
Z