Islanding Scheme Operation: A Project Report On
Islanding Scheme Operation: A Project Report On
PROJECT REPORT ON
Manager,JSWECE
CERTIFICATE
This is to certify that this is a bonafide record of project
work entitled
ISLANDING SCHEME OPERATION
Carried Out by
Arunkumar K- 0511PGD09
Arunachalam R- 0511PGD12
Pramod Kumar Pandey- 0511PGD44
Ranjit M- 0511PGD49
Sriram V- 0511PGD62
In partial fulfillment of the requirement for the award of
Post Graduate Diploma in Thermal Power Plant
Engineering
(P.G.D.C.)
Offered by
Mr. S. Kartikeyan
Mr. Mahalingaswamy
Mr.
Prashanthkumar C
(AGM)
Manager)
JSWECE, Toranagallu
Toranagallu
JSWECE ,Torangallu
(Manager)
JSWECE , Torangallu
(Dy.
JSWECE,
ACKNOWLEDGEMENT
(Manager,
Electrical
Maintenance,SBU-1)
Mr.Ramakrishna
(Manager,Electrical
CONTENTS:
1. Introduction
2. Generating units on Islanding
3. Benefits of Islanding
4. Detection of Islanding
5. Modes of Operation
6. SLD for different modes with conditions
7. Particulars of different modes
8. Consequences of Islanding
9. Post Islanding operation
10. Load distribution table
4
INTRODUCTION
The power systems operated by the utilities in
developing countries like India suffer from a large gap
between
demand
and
generation,
inadequate
transmission capacity, and non-uniform location of the
load centers and generating stations. Occurrences of
faults in such systems, in most of the cases, end up
with the worst consequences (i.e., complete blackout).
A blackout can be prevented in real time through
controlled segregation of a system into a number of
viable islands together with generation and/or load
shedding. This is called System islanding.
Definition of Islanding: Islanding is a process in which a
generator continues to supply power to a particular load
5
DETECTION OF ISLANDING
Detection of islanding is done by three different relays
namely under voltage relay, under-frequency relay and
rate of change of frequency relay which senses the
voltage and the frequency in the islanding bus BUS-2.
The voltage and the frequency setting of these relays are
selected such that these settings are lesser than that of
the generator under-voltage and under-frequency setting
so that the generator will not go for trip and the system
enters into islanding mode.
Islanding is considered as detected in the following
conditions:
1. Voltage magnitude of islanding bus drops to
8
MODES
MODE-5
MODE-4
MODE-3
MODE-1
OPTIONS
1
2
3
4
5
6
7
8
9
SBU-I
118
118
118
118
118
0
118
0
0
CPP-I
65
65
0
65
0
65
0
65
65
Max
109
84
109
0
84
109
0
109
95
Mi
n
85
55
85
0
55
95
0
05
55
LOAD SHEDDING
Net Gen.
Ma
x
292
267
227
183
202
174
118
174
160
Mi
n
268
238
203
183
173
160
118
70
120
JSWSL
LOAD
270
205
205
170
170
170
118
118
118
Max
22
62
22
13
32
4
0
56
42
Min
-2
33
-2
13
3
-10
0
2
2
10
2. Mode 4:
Case - 1
a) CPP-2 Net generation < 85MW
b) CPP-2 Net generation > 55 MW
c) CPP-1 Generation >70MW
d) JSWEL Island Unit Healthy
e) Island detected.
65MW
Case -2
a) CPP-2 Net generation >90MW
b) CPP-1 Generation < 65MW
c) JSWEL Island Unit Healthy
d) Island detected.
11
0 MW
3. Mode 3:
Case - 1
a) CPP-2 Net generation < 55 MW
b) CPP-1 Generation >70MW
c) JSWEL Island Unit Healthy
d)Island detected.
65 MW
Case -2
a) CPP-2 Net generation < 85MW
b) CPP-1 Generation < 65MW
c) JSWEL Island Unit Healthy
12
Case-3
a) JSWEL Island Unit Trip.
b) CPP-1 Generation >70MW
c) CPP-2 Net generation >90MW.
d) CPP-2 Net generation <109MW
e) Island Detected.
65MW
4. Mode 1:
Case - 1
a) CPP-2 Net generation < 55 MW
13
Case -2
a) CPP-2 Net generation > 55MW
b) CPP-1 Generation >70MW
c) JSWEL Island Unit Trip
d) Un Healthy of Mode-3, Case-3
e) Island Detected
65 MW
Case-3
a) JSWEL Island Unit Trip.
b) Healthy of Mode-3, Case-3
14
85MW<CPP-2<109MW
55MW<CPP-2<85MW
In
20
LOAD DISTRIBUTION:
21
COMMUNICATION FAILURE:
CONTINGENCY LOGICS
If the OFC communication links fail in one or more
places, it puts the entire scheme at risk. So, for backup,
22
24