Performance Data Sheet4650
Performance Data Sheet4650
7-4
Teletorium
FUNCTION:
EQUIPMENT
(Special equipment e.g. Sound
system, oxygen pipes)
CRITICAL FACTORS:
(Special needs e.g. Acoustic
levels, access or views to other
spaces)
OTHER
Return to Table of Contents
8-1
Formula
Approximate
Estimate $
$/SF x gross SF
10% of A
8% of A
A+B+C
10% of D
3% of D
10% of D
D+E+F+G+H
As the design progresses the estimate will become more accurate, but it will always just
be the designers best guess. If the designer presents an estimate that is too high, then the
owner will make unnecessary cuts in the program, but if the estimate is too low, the
project may not be buildable when the bids are evaluated. Either way it is going to be
exiting on bid day. The market will define what the project is really going to cost, but
not necessarily what it is worth. Some bidders may be too busy and submit an inflated
bid, while others may be out of work and submit a very low bid to keep their workforce
employed.
In addition to this summary budget form, there are two other forms that are useful in
documenting the assumptions made in the detailed project estimates. The first form (SEE
PROJECT ESTIMATE UNIT COSTS) provides a guide for estimating the furnishing,
computer, telephone, and moving expenses. It also has unit costs for typical construction
elements, which can be used for small renovation estimates.
The second form (SEE PROJECT BUDGET) includes a summary of all project costs
from planning and design to moving and permits. Note that there are contingency
allowances for construction and telephone/data separate from the total project
contingency allowance.
9-1
code#
ITEM
1
1
D
D1
D2
D3
DEMOLITION:
LABOR
HOURLY
COST
REMOVE
CARPET
AND ACM
REMOVE VCT ACM
2
2
S
S1
S2
S3
Ff1
2
2
Ff2
Ff3
3
3
w
W1
3
3
3
W2
W3
W4
I
4
4
D
D1
D2
D3
D4
D5
D6
DOORS:
SOLID CORE DOOR
EXISTING FRAME
HOLLOW METAL
DOOR FRAME 3X7
DOOR LOCKSET
MORTISE
LOCK CYLINDER
ONLY W/PINS
LCN DOOR
CLOSURE
PANIC HARDWARE
5
5
C
C1
CEILING:
2X4 CEILING TILE
SITE:
CONCRETE
SIDEWALK 8'
BRICK PAVER
SIDEWALK 8'
ASPHALT
PAVEMENT 1" + 2"
CARPET LEVEL
LOOP GLUE DOWN
26 OZ.
VINYL BASE
VCT 12X12
WALLS:
SHEET ROCK
WALLS 8'
GWB SOFFIT
GWB OVER CMU
TOILET PARTITION
NYLON
UNIT
COST
UNITS
25
HR
SF
SF
4.00
SF
$-
10.00
LF
$-
1.30
SF
$-
20.00
SY
$-
1.50
1.80
LF
SF
$$-
30.00
LF
$-
6.00
1.00
19.00
LF
SF
SF
$$$-
200.00
EA
$-
200.00
EA
$-
200.00
DOOR
$-
50.00
EA
$-
100.0
DOOR
$-
150.0
DOOR
$-
2.50
SF
$-
9-2
# OF
UNITS
ITEM
TOT.$
SUB
TOT.
GROUP
code#
ITEM
UNIT
COST
UNITS
# OF
UNITS
ITEM
TOT.$
3.00
SF
$-
7.00
LF
$-
5.00
8.00
LF
LF
$$-
100.00
EA
$-
50.00
150.00
EA
EA
$$-
W/GRID
6
6
P
P1
P2
6
6
P3
P4
7
7
EE
EE1
7
7
EE2
EE3
EE4
PAINT:
PAINT 2 COATS
INSIDE LATEX
PAINT 2 PIECE
WOOD BASE
PAINT CHAIR RAIL
PAINT CROWN
MOLD 2 COATS
ELECTRICAL:
2X4 LIGHT FIXTURE
DEEP CELL
PARABOLIC
DUPLEX OUTLET
RECESSED DOWN
LIGHT
FIRE ALARM Dormitory
FIRE ALARM - Office
8
8
M
ME1
ME2
ME3
9
9
9
pl
PL1
PL2
PL3
PL4
10
10
M
M1
10
M2
MOVING:
5 MAN MOVING
CREW W/ VAN
TRUCK
2 CF BOOK BOXES
11
11
CF
CF1
FURNISHING:
CLASSROOM
MECHANICAL:
A/C SYSTEMS (400
sf/ton)`
FAN COIL
ONLY(PIPE EXTRA)
HVAC CEILING
GRILLES
PLUMBING:
NEW TANK TOILET
NEW FLUSH VALVE
TOILET
NEW LAV W/ DELTA
FAUCET
NEW URINAL
W/FLUSH VALVE
EA
EA
4000.00
TON
$-
400.00
EA
$-
30.00
EA
85.00
100.00
EA
EA
130.00
EA
215.00
EA
1000.00
DAY
$-
0.70
EA
$-
120.00
EA
$-
9-3
SUB
TOT.