Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure

This document discusses transportation and lifting lessons learned from past projects. It focuses on the transportation of an EWT module and lifting of a flare tower. For the EWT, transportation was delayed by 2.5 days due to breakdown and incorrect measurements. Lifting of the flare tower was also delayed by 2 weeks as the lifting lugs were fabricated on site instead of beforehand, and lifting began inside the site instead of at the planned location. The document provides details of cargo dimensions, vessels, lifting plans and lessons on ensuring spare parts, accurate measurements, and fabrication considerations are in place.

Uploaded by

engineeringyusuf
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
124 views32 pages

Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure

This document discusses transportation and lifting lessons learned from past projects. It focuses on the transportation of an EWT module and lifting of a flare tower. For the EWT, transportation was delayed by 2.5 days due to breakdown and incorrect measurements. Lifting of the flare tower was also delayed by 2 weeks as the lifting lugs were fabricated on site instead of beforehand, and lifting began inside the site instead of at the planned location. The document provides details of cargo dimensions, vessels, lifting plans and lessons on ensuring spare parts, accurate measurements, and fabrication considerations are in place.

Uploaded by

engineeringyusuf
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 32

Prepared by

Muhammad Shafif bin Mohd Saleh


This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

Introduction

Transportation and lifting study is essential element to ensure safe

handling of properties throughout the operation

Critical lesson learnt during KMSE transportation and lifting campaign

are transportation of EWT and lifting of the flare tower.

Lesson learnt will highlight the processes involved during the

engineering stage and the load out/lifting operation.

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

Scope of work
Transportation of EWT module
Lifting and installation of flare tower

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

EWT transportation
The EWT transportation commence from Westport

Fabrication Yard and transported to West Port Jetty by


Multi Axle Trailer.
At the West Port wharf/jetty 2 units mobile crane was
used for lifting complete with lifting gears according to
lifting plans
The transport route leads from Port Klang through the
Street of Malacca towards MMHE jetty at Pasir
Gudang.

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

Cargo description
PRINCIPAL
DIMENSION
LENGTH = 9.105 M
BREADTH = 8.307 M
HEIGHT = 9.948 M
WEIGHT = 100 TON

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

Vessel and Barge Detail


Barge

: MUHIBBAH B29

Year Built : 2007


Length Overall : 54.869m (180ft)
Breadth (Moulded) : 15.24m (50ft)
Depth (Moulded) : 3.048m (10ft)
Design draught : 2.86m
Deadweight : 1634.952 t
Lightship : 330.10 tons
Deck loading : 15 t/m

Tug Boat : TROPICAL EAGLE

Year Built : 1987


Length Overall : 25.5m
Breadth (Moulded) : 8.1m
Depth (Moulded) : 4m
GRT : 209
NRT : 63
Flag : Singapore
Class : BV
BHP : 2 x 962 KW

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

COG (option 1)

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

Barge Muhibbah B29: Arrangement

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

Advantages
1. Less piping work at MMHE
2. Transport EWT in its complete form
Disadvantages
1. High COG will reduce stability of the barge
2. Fabricate foundation for transportation not economic

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

COG (option2)

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

Barge Muhibbah B29: Arrangement

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

Advantages
1. Easy and safe handling
2. Low COG result on better stability of the barge
Disadvantages
1. Extra piping work at MMHE

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

Transportation EWT
What was supposed to happen?
Transportation of EWT module from fabrication yard to Westport
shall take 1 hour

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

What actually happen?


Transport to Westport delayed for 2 days
Cometto breakdown due to hydraulic failure
EWT width wrongly measured by transporter.

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

What can we learn from this?


Route survey shall be done as per actual dimension
2. Ensure transporter prepare spare parts for their
equipment along the operation.
3. Selection of fabrication yard must consider the
location of the fabrication yard to the means of
transportation
1.

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

Lifting flare tower


The lifting of flare tower had been executed at in front

of DD1 and DD2 area with 1 no. of Floating Crane and 1


supporting crane (by MMHE).
The installation of flare tower had been executed at
quay8 with 1 no. of Floating Crane
Engineering of Lift Concepts to its final installation
location.

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

Cargo description
PRINCIPAL
DIMENSION
LENGTH = 55.00 M
BREADTH = 10.156M
HEIGHT = 8.4M
WEIGHT = 83.32 TON

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

Crane
Crane 1 : POE Giant 6 Offshore Floating Crane, 500MT

with 70.104 m. boom length (Aux. hook).


Crane 2 : Supporting Crane (MMHE proposed use LLC
No 3 for supporting Crane)

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

Lifting sequence

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

Lifting of flare tower


What was supposed to happen?
Flare tip installed before lifting operation
Flare tower padeye supposed to be install at fabrication yard
Lifting from transporter barge supposed to be done in front of DD1 and

DD2
Lifting commence once flare tower arrive at MMHE

What actually happen?

Flare tip installed after lifting operation


Lifting padeye fabricated at MMHE
Initial lifting had been execute inside DD2
Lifting campaign delay for 2 weeks

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

What can we learn from this?


Install flare tip after completion of installation of flare
tower to ease lifting operation
2. Use crane that able to turn 360 to avoid space limit
3. Reduce crane radius as much as possible to maximize
crane capacity
4. Ensure no additional steel work on the module after load
out from fabrication yard
5. Load out from fabrication yard shall synchronize with
lifting campaign perfectly
1.

This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..

THANK YOU