Earned Value Management Explained
Earned Value Management Explained
EVM Measures
EVM consists of the following primary and derived data elements. Each data point value is based
on the time or date an EVM measure is performed on the project.
For example say we should have completed 800 pounds of work by today. We completed 600
worth of work. The BCWP is 600. The BCWS is 800. And if we actually paid 700 then (ACWP) =
700.
EVM Example
The best way to understand an EVM example is to solve it.
Problem: A project has a budget of 10M and schedule for 10 months. It is assumed that the
total budget will be spent equally each month until the 10th month is reached. After 2 months the
project manager finds that only 5% of the work is finished and a total of 1M spent.
Solution:
PV = 2M
EV = 10M * 0.05 = 0.5M
AV = 1M
CV = EV-AC = 0.5-1 = -0.5M
CV% = 100 * (CV/EV) = 100*(-0.5/0.5) = -100% overrun
SV = EV-PV = 0.5-2 = -1.5 months
EVM Benefits
EVM contributes to:
Preventing scope creep
Improving communication and visibility with stakeholders
Reducing risk
Profitability analysis
Project forecasting
Better accountability
Performance tracking