05 - Short Circuit Strength of Power Transformers
05 - Short Circuit Strength of Power Transformers
Thomas A. Prevost
EHV-Weidmann Industries, Inc.
Abstract
One of the most important aspects of transformer design and manufacturing is assuring that the
transformer can withstand short circuit events in service. Design reviews and in some cases short circuit
type tests on the units themselves give the transformer purchaser assurance that the unit meets short circuit
withstand performance criteria when shipped. This paper deals with those factors which affect the short
circuit performance of transformers after shipment, throughout the life of the equipment.
Introduction
The transformer is a static device which is a critical component in the supply of energy via a
utilitys transmission and distribution grid. The transformer is exposed to atypical events throughout its
service life which it must have the capability to withstand in order to remain in service. One of the largest
causes of transformer failures is through faults or short circuits. A short circuit can result in severe radial
and axial forces which can damage the insulation integrity. Axial forces which result from short circuits
are controlled by the proper pre-loading of the transformer coils during manufacture. The windings are preloaded to a pressure which is at least as high as the maximum calculated axial short circuit force.(1) As long
as the transformer clamping system maintains pre-load pressure, the windings will remain tight during a
short circuit event and should therefore not sustain any damage, due to movement of the conductors.
In most transformers designed today, a rigid clamping system is utilized to compress the windings
to the specified pre-load value. Any change in the thickness of the materials in the winding and associated
end insulation will change the pressure on the winding. The thickness of the conductor material will not
change except for the thermal expansion and contraction during load cycles. The cellulose insulation
material, being organic, will change in thickness and elasticity over time resulting from the effect of
moisture, temperature, and aging. In order to maintain the short circuit integrity of a transformer it is
critical that the pre-load pressure on the windings be maintained. This paper discusses the various
parameters which affect the pressure on transformer windings over the life of a transformer in service.
Understanding these parameters will guide the transformer owner in deciding if taking maintenance steps
such as retightening of the windings should be taken.
Transformer Manufacturer
At the transformer factory a transformer is designed and manufactured to be capable of
withstanding the calculated highest short circuit force. The windings are dried and oil impregnated and then
loaded to a pressure which meets or exceeds the calculated short circuit force. In the United States the
standards do not dictate that all transformers be short circuit tested. However the standards do state that the
manufacturer is required to demonstrate that their design is capable of withstanding short circuit currents as
defined in IEEE/ANSI C57.12.00.
In most transformers designed today, a rigid clamping system is utilized to compress the windings
to the specified pre-load value. Because any reduction in the thickness of the materials in the winding and
associated end insulation will reduce the pressure on the winding the transformer manufacturer dries and
stabilizes the insulation during manufacturing.
An ideal insulating spacer material in the coil stack would have purely elastic behavior. Although
this is not practically attainable, it can be approached by the use of machined high density pressboard
which has been pre-stressed and stabilized in the transformer manufacturing process.(2) The manufacturing
process should include the following procedures in order to assure that the windings maintain the proper
pre-load forces:
Figure 1 demonstrates the change in thickness of transformerboard spacers during coil processing.
110
108
106
104
102
100
98
96
94
As-Is ( 6% m/c, 1
N/mm^2)
Compressed ( 6 %
m/c, 10 N/mm^2)
Effect of coil processing on the thickness of a 100 mm stack of Transformerboard spacer material.
Material was vacuum dried for 7 days at 0.5mbar under a load of 10 N/mm2
FIGURE 1
The pressure on the spacers was maintained through the use of springs. This test suggested that
there was additional shrinkage of the insulation material due simply to the oil impregnation process. This
phenomenon has been reported previously in literature. (2) A test series was performed to verify this
phenomenon.
copper 12 x 3, R 1 mm
Kraft paper insulation 1 mm
pressboard spacer 2 mm
40
25
25
Spacers (2 mm thick) interspersed with paper insulated copper conductor disk segments.
Apparent pressed area: 625 mm2.
FIGURE 2
These models were vacuum dried for seven days at 110 Deg. C while under a constant pressure of 10
N/mm^2. The models were then oil impregnated in a hot or ambient state with ambient or hot oil according
to the values given in Table 1.
Model Deg. C Oil Deg. C
25
25
80
25
25
80
80
80
Pressure
No Change
Decrease
Increase
No Change
TABLE 1
The test series demonstrated that the decrease in pressure noted during the oil impregnation of insulation
was due to the thermal contraction of the cellulose caused by the introduction of cooler transformer oil.(3)
4.5
4
3.5
3
2.5
2
1.5
1
0.5
0
-20
20
40
60
80
100
FIGURE 3
The pre-load pressure on transformer windings will change due to temperature variation. For the
transformer manufacturer it is best to pre-load the transformer at 30C to 50C in order to assure that the
windings have a proper pre-load force over the operating range of the transformer. This is particularly
important in climates where the ambient temperature can be quite low in order to avoid loss of correct preload pressure.
For transformers in service we can see from this relationship that the capability for a transformer
to withstand a short circuit can be different based on the temperature at which the short circuit occurred. If
the transformer is heavily loaded, thus running at a higher temperature the clamping pressure will be higher
thus giving the transformer a better chance of withstanding the short circuit forces without any dangerous
movement of the internal parts of the winding.
fo rc e (k N )
m o is tu r e (% )
7
6
5
4
3
4
3
2
2
1
1
0
0
0
10
20
30
m o d e l- 1 ( s p a c e r s )
40
tim e (h )
50
60
70
m o d e l- 2 ( s p a c e r s a n d c o n d u c to r s e g m e n ts )
m o is tu re
Clamping force and moisture content versus time for non-oiled models. After 24 hours at 23C
and 50% relative humidity, the specimens were dried under vacuum. The N/mm2-scale relates to
the apparent pressure area of 625 mm2.
FIGURE 4
100C
10
Air temperature
7
Board temperature
60C
Pressure
20C
0
0
10
Time (days)
11
100C
10
Air temperature
Board temperature
6
60C
Pressure
20C
0
0
10
Time (days)
The temperature of the aging vessels was cycled daily to simulate the load cycle that a typical
transformer might see. The temperature cycle for a 24 hour period composed of the constant temperature
(135C or 150C) for 19 hours, followed by a 2 hour cooling phase and then by a 3 hour heating phase.
The loss of effective aging time based on the Montsinger half value of 8 K was about 4 hours per
temperature cycle per day.(5)
The pressboard shows increasing shrinkage caused by loss of substance (CO2, CO, H2O) during
the aging of the cellulose and decrease in mechanical strength (due to decomposition of cellulose
molecules). The effect of aging on the thickness of pre-compressed cellulose board as a result of this
experiment is shown in (Figure 7). The extent of aging as measured by the DP is shown below. The
insulation material would be considered as being at its end of life if one assumes a DP value of 200 to be
the end of life.(6)
102
100
98
96
135 Deg. C
94
150 Deg. C
92
90
88
0
50
100
150
200
250
300
DP
Initial values
135oC
150oC
1190
164
152
The Degree of Polymerization was measured at the end of this aging study.
Conclusion
For a transformer to be capable of withstanding short-circuit events while in service it is critical that an
adequate clamping pressure be maintained on the windings. The manufacturer applies this pressure on the
windings before leaving the factory. It is important that the winding insulation is pre-stabilized during the
manufacturing process to prevent excessive pressure loss during the first load cycle once a transformer is
placed in service.
As a transformer ages two opposing phenomena occur in regards to the clamping pressure on the windings.
The aging process of the cellulose produces water which will increase the moisture content of the winding
insulation. This will tend to increase the clamping pressure. The aging of the winding insulation results in a
decrease in the thickness of the spacers over time which will decrease the pressure. It is unknown which
factor is prominent with respect to the clamping pressure. However, should a transformer, which has been
heavily loaded, be processed in the field for removal of moisture in the insulation it must be assumed that
the clamping pressure has diminished. For this reason the transformer owner should consider retightening
the transformer windings following field processing.
A transformer should be processed to remove moisture in the insulation before the windings are retightened
in the field. If the windings are tightened before field processing the insulation could have a high moisture
content. Field processing following tightening will result in shrinkage of the insulation material and the
clamping pressure applied during the retightening process will be reduced.
References
1.
K. Karsai, D. Keranyi, L. Kiss Large Power Transformers, Studies in Electrical and Electronics
Engineering. Elservier 1987 pp. 570-571.
2.
3.
C. Krause, W. Goetz, B. Heinrich, The Impact of Drying and Oil Impregnation Conditions and of
Temperature Cycles on the Clamping Force of Power Transformer Windings 2002 IEEE
International Symposium on Electrical Insulation.
4.
5.
6.
10