APCBTMP TIMP Completion Document - Copy To DPUs - 16 Feb 10
APCBTMP TIMP Completion Document - Copy To DPUs - 16 Feb 10
Certificate
Handing over of Operation &
Maintenance Responsibilities of
Minor Irrigation Tank
to the Water User Association
Background
The Government of Andhra Pradesh initiated the process of providing to the farmers
benefiting from irrigation projects, substantive management role in the operation and
maintenance of the irrigation infrastructure. For this purpose, the Andhra Pradesh Farmers
Management of Irrigation System Act 1997 was enacted.
After the passage of the APFMIS Act 1997, I&CAD Department carried out minimum
rehabilitation of minor irrigation tanks and modernization of major irrigation projects for future
maintenance by Water Users Associations (WUAs). Performance evaluation of the WUAs
highlighted the need for greater investment in the institution building process for enabling the
WUAs in infrastructure management. This process has been initiated as part of the ongoing
sector reform process in tune with the observations of Mid Term Appraisal of the Xth plan
and observation of the Sub Group on Agriculture and Irrigation of National Development
Council. While new infrastructure creation is the main agenda of the Irrigation Department,
the reform process and facility management are the agenda of the CAD wing of the I& CAD
department under the flagship Jalayagnam program of the Government.
Water tax collection and plough back: In order to provide incentive to WUAs to take over
O&M responsibilities, the I&CAD Department initiated the process of ploughing back the
water tax collected to the WUAs. The Water Management committee under the chairmanship
of Chief Secretary suggested measures for simplification of the tax collection and plough
back procedures (vide IRRIGATION & C.A.D. [General.IV.2] DEPARTMENT G.O. No. 96
Dated: 08-06-2007).
The Andhra Pradesh Community Based Tank Management Project is taken up with the
assistance of the Government of India and the World Bank covering 3,000 tanks in 499
mandals of 21 districts with an approximate cost of Rs. 1,044 crores. The proposed project
development objective is for selected tank based producers to improve agricultural
productivity and water user associations to manage tank systems effectively. Key
performance indicators proposed to measure achievement of the project development
objective include: increase in area irrigated; improved water availability for tail-end
farmers; increase in agricultural (including livestock and fisheries) productivity and
production from tank systems; resources raised and operation and maintenance (O&M)
expenditures incurred by user groups.
SO (NGO)
details
SO CEO/
SO
Coordinat
or
Communi
ty
Organize
r
Agricultur
e
Coordinat
or
Work
Inspector
Declaration
……………………………………………………………………………………………………………………
……… (name of SO)
has been involved in the implementation of the APCBTMP from (date)
……………………………………………………. to (date)
……………………………………………………
As a Support Organization,
…………………………………………………………………………………………………………………..
has worked conscientiously to facilitate completion of the APCBTMP tasks as planned in
the TIMP in collaboration with the WUA and the DPU. All tasks have been completed as
per agreement between SO and the and the District Project Director, APCBTMP.
Technical
sanction Activity/Works Completed
# Comp Activity Units Quantity Cost (Rs. Quantity Cost (Rs. In Date
In lakhs) lakhs)
1 1. Capacity building
Notes
(d) Indicate height of bund, If bund height is more than 10m,proposals to be referred to
Dam safety panel for their technical input
All PGM equipment (water level & discharge measurement provisions, Raingauge,
(e) Water Level Indicator, and Stop Watch) and pipelines to groundwater users for
water sharing
6 Fingerlings stocked N
Owned Donated
Status rented / Monthly rent: Rs. ………………………
(Tick Yes or No
in column as relevant)
Items Records maintained by WUA Yes No Remarks
An up-to-date copy of “The Andhra
Pradesh Farmers Management of
APFMIS Irrigation Systems Act (Act 11 of 1997)
With Updated Amendments as on April
2007
Assets A statement of the assets and liabilities
Copies of audit reports and enquiry
Audit
reports
A map of the area of operation of the
Farmers Organisation along with map
of the structures and distributory
Maps & networks prepared in consultation with
Records the Irrigation Department
Map showing the localized/notified ayacut
Map showing the areas under irrigation not
falling within ayacut notified
Inventory Register
Register of vacant lands and building
Property Register of income on Miscellaneous
Register property
and
Records Register of Machinery
Membership Register and Records
Water Flows register and records
Others ….
APCBTM TIMP
P WUA manual
Documen
ts O&M Manual
PGM Process Book
PHM data record
Others …
Others …
All the works approved under the APCBTM Project have been completed by the
WUA and the Contractor. The WUA Works sub-committee has checked the
quantity and quality of the construction and has recommended payments for the
same.
As agreed in the MoU between WUA and DPD, we have contributed Rs. …….
……… ……………………… ……………………………………………………………………….…
in cash/kind towards cost of the Civil Works (5% of total cost of civil works).
We understand that the tank system will require regular operation and
maintenance comprising a number of activities and that the costs for these have
to be paid for through our contributions in cash and/or in kind. These activities
include:
Desilting (feeder channels, irrigation channels and if required tank bed)
Jungle clearance in the tank system
iii. Repairs to embankment, revetment, shutters, masonry and lining, waste
weir and surplus course
Cleaning and oiling of screw gears and gate groves
We will avoid:
vi. Damaging of sluice, tank bund, waste weir, irrigation canal, distribution
system, surplus course
vii. Unauthorized lowering and rising of tank bund and weir height
ii. Groundwater use by ayacutdars and those in the tank influence zone
Any such repair works are to be taken up as per the technical guidelines provided
by the Irrigation Department.
We will conduct an annual crop planning exercise to optimize use of the available
water in the tank so that water is shared equitably between all the stakeholders.
We will monitor the water inflow regularly to assess water quantity in the tank.
The TC member and farmers of each TC will discuss and plan the crops for each
survey number. The WUA Water Management Sub-committee shall consolidate
the water distribution plan in accordance with the demand of the farmers.
The Subcommittee will seek endorsement of plan from the WUA Management
Committee. The plan will be implemented through the lashkar (watermen).
Any dispute arising in water distribution will be resolved amicably. Anyone who
breaches the agreed water distribution plan will be suitably penalized by the WUA
Management Committee.
O&M Fund
We agree to contribute regularly to maintain a healthy Corpus Fund to meet all
the operation and maintenance expenses of the tank in the future. We will
maintain regular ledgers and accounts of the WUA as required.
2. Vice President
3. Executive
Committee
member
es
Witness President of Gram
1 Panchayat
Witness
SO Representative
2
Witness
DPU Representative
3
All the activities and works as proposed in the tank improvement management
plan (TIMP) under the Andhra Pradesh Community Based Tank Management
Project in
…………………………………………………………………………………………………………………………
The WUA Works Sub-Committee has verified the quantity and quality of the
works undertaken by the WUA and/or Contractor and have approved payment.
All due payments to WUA and Contractor have been paid.
The Water User Association has contributed its share to the Project as per
agreement and has created an O&M Fund for meeting future expenditures. The
WUA is ready to take over responsibilities of O&M of the tank.
The Support Organisation has facilitated the activities and prepared the required
documents for completion of the TIMP.
The District Project Director has provided the necessary technical inputs and
funds for the completion of the project. Any pending payment of bills for works
completed by the contractor is the responsibility of the District Project Director.
We, the undersigned, certify that the details provided in this document are true
to the best of our knowledge.