Critical Installation Elements
Critical Installation Elements
First Edition
State of Montana
Department of Environmental Quality
Underground Storage Tank Section
July 2004
INTRODUCTION
The critical installation requirements contained in this document will no longer appear on
installation and closure permits issued by the department. These requirements remain integral to
the installation and closure processes and must be followed whenever they are applicable.
This document does not replace or supplement industry standards for installing USTs. Its
purpose is to highlight critical installation elements that the Department of Environmental
Quality has historically felt a need to stress or clearly communicate. This document is not
comprehensive but rather is a compilation of commonly used permit conditions.
Administrative Rules of Montana (ARM), Title 17, Chapter 56 sets forth performance standards
for new underground storage tank systems. This document highlights certain industry standards
for UST installations as outlined by API Recommended Practice 1615, PEI/RP 100-2000, and
other standards of design and construction delineated by ARM 17.56. These rules may be
accessed at http://www.deq.state.mt.us/dir/legal/Chapters/Ch56-toc.asp.
I) PRELIMINARY CONSIDERATIONS
A) Legal
Work must comply with Montana Underground Storage Tank regulations, permit
conditions, department-adopted referenced standards, manufacturer specifications, and
all other state and local requirements.
B) Local Coordination
Owner and installer must contact the local fire official and the State Fire Marshal at
(406) 444-2050 regarding installation of aboveground tanks and components, which
are regulated by the Uniform Fire Codes and the Montana Fire Codes. Owner and
installer must also contact the local Planning Department for new installations
regarding local requirements.
C) Source Water Protection Districts
When installing an underground storage tank system, the owner and installer must
contact the applicable source water protection district regarding local requirements.
D) Notification
Notify DEQ at (406) 444-5300 at least one week before starting work. Provide permit
and facility numbers. If this project is the site of an active petroleum release and
excavation is required, you must also contact the case manager at (406) 841-5000 at
least one week before starting work.
E) Permit Modification
Permit modification is required by DEQ for any changes from the permitted proposal.
Call (406) 444-0495 for any permit modification, including a change of installer.
F) Suspected Contamination
Contact the department at 1-800-457-0568 within 24 hours if suspected contamination
(soil staining, soil odors, sheen on water, detectable head space concentrations, lab
analysis over DEQ action levels, holes in tanks or piping, or any unusual operating
conditions) is discovered, regardless of the suspected source. If a ppm meter is
available, collect dual samples and conduct a vapor headspace test on the sample not
being submitted to the lab.
G) Release Detection Equipment Performance Claims
The department authorizes equipment for UST system installation that has been tested
and evaluated by the National Work Group on Leak Detection Evaluation
(NWGLDE). The primary goal of NWGLDE is the creation of a list of release
Rev. 7/04
detection products that have undergone third party evaluations adhering to specified
engineering criteria. The list is a compilation of underground storage tank and piping
leak detection system evaluations that have met certain criteria developed by the
NWGLDE and the performance requirements established by Title 17, Chapter 56,
Sub-Chapter 4 of Administrative Rules of Montana.
If equipment not listed by NWGLDE is proposed, then the installer must submit
(with the permit application) a written performance claim substantiating the
performance and the manner in which the claim was justified or tested by the
equipment manufacturer or installer (ARM 17.56.409).
H) Setback Distances
No part of an underground tank system may be located less than 3 feet from a
property line.
Dispensers must be at least 10 feet from the building and property lines.
The end of the stretched hose must be at least 5 feet from any building openings
(windows, doors, or basement or crawl space wells), and all portions of the vehicle
being fueled must be on the property.
Accurate distances for these setbacks must be provided on the redlined drawing if
different from the previously submitted site plan.
I)
Rev. 7/04
Rev. 7/04
vi) Backfill
Pea gravel bedding and backfill must be washed and naturally rounded 1/8" to 3/4"
with no more than 3% passing a 3/8 sieve. Alternative backfills must be approved
by the manufacturer before installation.
vii) Flex Connectors
Install flex connectors in the product and vapor recovery piping at the tank,
base of dispensers, and anywhere a direction change of 30 degrees or more
occurs with less than a 4' straight run on either side of it.
Flex connectors in contact with soil must be protected from corrosion by heat
shrink sleeves, watertight boots, or STI coating and anodes.
Flex connectors must be UL listed for hydrocarbons.
Flex connectors exposed to the atmosphere must be fire rated.
viii) Pipe Leak Detection Equipment
Liquid sensors must be installed in all tank turbine sumps where there is piping
between the turbine housing and the leak detector housing.
For continuous interstitial monitoring of double-walled piping, interstitial
monitoring liquid sensors must be installed in all product-piping sumps and must
be approved for use with the LD panel
Liquid sensors and pressurized line leak detectors must:
Sound a continuous alarm that is responded to within 1 hour, 24 hours a day,
seven days a week, 365 days a year; or,
Close a solenoid valve at the tank if product is detected in any sump; or,
De-energize the turbine.
ix) Vent Lines
Vent risers must extend a minimum of 3 over roofs and adjacent structures.
If free standing, vents must extend a minimum of 12 aboveground.
Flex connectors must be installed in the rigid vent piping at the tank, base of
vent riser, and anywhere a direction change of 30 degrees or more occurs
with less than a 4' straight run on either side of it.
Vent piping must slope at least 1/8 per foot back to the tank without any
sags or traps.
x) Master-Slave Dispenser Installation
A master and slave dispenser arrangement with single-walled piping utilizing
mechanical line leak detectors must be installed with a continuous (no solenoids or
check valves) piping system from the submersible pump to the satellite dispenser.
Rev. 7/04
C) Cathodic Protection
The addition of corrosion protection to new or
existing installations is the addition of an
impressed current system, anodes, heat shrink
sleeves, non-corrodible offset sleeves, watertight
boots or STI coating.
i) Impressed Current Installation Procedures
Anodes must be located as shown on the corrosion protection design
proposal.
Anodes cannot be repositioned more than 2' laterally to accommodate
underground obstructions. Any repositioning beyond this requires prior
review and approval from the department (406) 444-5300.
Anodes must be located 10-15 feet from the tank for optimum current and ion
distribution. Location outside of this area requires prior review and approval
from the department (406) 444-5300.
The centerline of the vertical anodes must be at least as deep as the centerline
of the tank. Horizontal anodes must be placed at or below the centerline of
the tank or the historical frost line, whichever is deeper.
Wires must be placed below the surface concrete or asphalt with aggregate or
other cushioning material between the wires and the concrete or asphalt. If
there is no concrete or asphalt present, wires must be at least 24" below the
surface. Wires may not be placed directly in concrete.
Anodes must have coke breeze backfill placed at least 6" below the anode, 6"
above the anode, and completely filling the interstitial space around the
anode without any voids.
Any below-grade connection must be coated with either a waterproof or STI
approved type coating.
Soil potentials must be provided after cathodic protection is installed. After
the UST system has reached equilibrium, and within 6 months, a qualified
corrosion protection tester must perform a comprehensive corrosion
protection test according to department criteria.
ii) Magnesium Anode Installation Procedures
Anodes cannot be repositioned more than 2' laterally to accommodate
underground obstructions. Repositioning beyond this requires prior
department review and approval.
Except for spike anode installation, the centerline of the anodes must be
below the historical frost line.
Any below-grade connection must be coated with either a waterproof or STIapproved coating.
Wires must be placed below the surface concrete or asphalt with aggregate or
other cushioning material between the wires and the concrete or asphalt. If
there is no concrete or asphalt present, wires must be at least 24" below the
surface. Wires may not be placed directly in concrete.
Rev. 7/04
Rev. 7/04
Rev. 7/04