D70REV
D70REV
4,241,300
4,702,287
4,896,531
4,023,407
4,785,864
4,815,004
4,846,334
GBO,265,036
PI8,704,141
PI8,704,299
DEO,265,036
1,281,899 CANADA
Patented 1991
(OTHERS PENDING)
MACHINE SAFETY
All that is possible has been done to make this machine safe for the operators
and personnel in the machine's surrounding area.
WARNING
DO NOT OPERATE MACHINE UNLESS ALL
GUARDS ARE PROPERLY INSTALLED.
This machine should not be operated until the operating personnel have read and
understand this instruction manual and have been instructed on safety and
operation of this machine.
This machine should be shut down by the operator immediately and inform his
supervisor if he observes any unusual machine vibration, motion, or sounds.
Do not attempt repairs or adjustments without permission from supervisor.
The electrical, pneumatic and/or hydraulic circuits of this machine have been
designed to provide interlocks and safety precautions to eliminate risk of
injury to operators and personnel working around this machine and area.
Unauthorized alterations to these circuits may result in injury to personnel or
cause damage to the machine.
OPERATING PRECAUTIONS
WARNING
This machine includes a number of moving parts and assemblies under automatic
control.
Keep clear of moving parts while the machine is in operation.
Approaching too close to the machine during operation could result in injury or
even death.
WARNING
Whenever possible, shut off the machine to make component settings and
adjustments or performing maintenance duties.
When making checks or
adjustments which can be made only when the machine is powered, take extreme
pre- cautions to prevent unauthorized control operation while adjustments are
in progress.
WARNING
Never get under any conveyor while the unit is operating. Conveyors operate
under automatic control as well as pins, gates, arms, etc. which could cause
severe injury or death to personnel.
WARNING
The electrical power used to operate this equipment can cause severe injury or
death. Make sure that all power is disconnected and that disconnect switches
are tagged to prevent them from being energized while electrical connections
are being made.
WARNING
Grinder dust removal must be of adequate capacity such that hot rubber dust can
not accumulate and start machine fires causing possible body injury and machine
damage.
WARNING
Do not walk on conveyor rollers.
slippage could occur.
TABLE OF CONTENTS
SECTION
1.0
2.0
INTRODUCTION
PURPOSE
SPECIFICATIONS
SEQUENCE OF OPERATIONS
INITIAL INSTALLATION
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
UNLOADING
DELIVERY INSPECTION
LEVELING
SERVICES
LOADWHEEL ALIGNMENT
SETUP PROCEDURE FOR NON-CONTACT FRRO &
CONCENTRIC GRIND
THIRD (CENTER) GRINDER ADJUSTMENTS
FORCE CALIBRATION
RUNOUT CALIBRATION
3.0
OPERATION
4.0
5.0
GENERAL
ADJUSTMENTS FOR CHANGING TIRE SECTION WIDTH
ADJUSTMENTS FOR CHANGING TIRE BEAD DIAMETER
HARMONIC HIGH POINT MARKER POSITION
ADJUSTMENT
CONICITY POLARITY MARKER POSITION
ADJUSTMENT
ADJUSTMENTS
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
GENERAL
TIMER ADJUSTMENTS
LIMIT SWITCH ADJUSTMENTS
AIR PRESSURE REGULATOR ADJUSTMENTS
HYDRAULIC SYSTEM ADJUSTMENTS
CHUCK SPRAY MIST ADJUSTMENT
HIGH POINT MARKER ADJUSTMENTS
BEAD MARKER SETUP AND ADJUSTMENT
CONICITY POLARITY MARKER ADJUSTMENTS
LUBRICATION
6.1
6.2
6.3
6.4
6.5
7.0
MAINTENANCE
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
7.10
8.0
GENERAL
SKIM ADJUSTMENT (ELECTRICAL)
SKIM ADJUSTMENT (MECHANICAL)
SENSOR AIR PURGE
ELECTRONIC GRIND ADJUSTMENTS
ROUTINE GRINDER MAINTENANCE AND
INSPECTION
GRINDER SERVO VALVES
LOADWHEEL CARRIAGE SERVO POT AND
TACHOMETER
HYDRAULIC SYSTEM
PNEUMATIC SYSTEM
PNEUMATIC SYSTEM
8.1
8.2
9.0
LUBRICATION SCHEDULE
AIR LINE LUBRICATORS
CHUCK SPRAY MIST GENERATOR
LOADWHEEL CARRIAGE WAYS LUBRICATOR
RECOMMENDED LUBRICANTS
SPARE PARTS
9.1
9.2
9.3
ORDERING
STOCKING
GENERAL
LIST OF ILLUSTRATIONS
FIGURE
1.1
1.2
1.3
1.4
1.5
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.7A
2.8
2.9
2.10
2.11
2.12
4.1A
4.1B
4.2
4.3
4.4
4.5
4.6
HYDRAULIC UNIT
5.2
5.3A
5.3B
5.3C
5.4
BEAD MARKER
5.5
5.6
6.1
6.2
LUBRICATION SCHEDULE
7.3
8.1
8.2
8.3
8.4
8.5
8.6
LIST OF TABLES
TABLE
1-1
SPECIFICATIONS
2-1
2-2
5-1
5-2
6-1
7-1
1.0
1.1
INTRODUCTION - This technical manual provides installation, service, and
maintenance information for Tire Uniformity Optimizer (TUO), manufactured by
Akron Standard, an ITW Company.
This manual covers the TUO, including all of its options and alternates, so
that not all features described will be applicable to your particular machine.
Follow the correct procedure for your unit when using this manual. See both
D70 and D70 LTX supplements for options not covered in this manual.
1.2
PURPOSE - Your TUO machine is designed to do some or all of the
following:
1.
2.
3.
4.
5.
Test tires.
Determine correctable tire faults.
Correct the faults if possible.
Place grade identification marks on the tires.
Sort tires into either two or three categories for warehousing.
The unit can be operated in manual, semi-automatic, or automatic mode with the
manual mode being used mainly for machine setup and adjustment, checkout, and
troubleshooting.
During semi-automatic operation, the operator controls the
start of each cycle. In automatic operation, the machine controls the entire
operating cycle.
The main tire faults recognized by the machine are force variations and lack of
concentricity (runout).
Force variations are those defects which result
in"hard" and "soft" spots in the tire due to inconsistent wall thickness, ply
arrangement, and other deviations. Lack of concentricity is out-of-roundness
of the tread surface of the tire.
These faults are measured by the TUO.
Radial force variations and radial runout are corrected provided the tire can
be brought within acceptable limits.
Tire features are checked and corrections attempted while the tire is chucked,
inflated, and rotated at a slow rate of speed on the machine. All corrections
are made by grinding the tire to remove small amounts of rubber from tread
area.
1.3
SPECIFICATIONS - Specifications for the Tire Uniformity Optimizer are
listed in Table 1-1.
TABLE 1-1
SPECIFICATIONS
D70
D70 LT
D70 LTX
_______________________________________________________________________
Dimensions and Weight
Length
11'-6"
(3505 mm)
12'-5/8"
(3673 mm)
13'-1/2"
(3975 mm)
Width
11'-6"
(3505 mm)
11'-6"
(3505 mm)
11'-6"
(3505 mm)
Height
9'-6"
(2896 mm)
10'-0"
(3048 mm)
10'-8-1/2"
(3264 mm)
13" to 16-5"
13" to 16.5"
13" to 19.5"
(330.2-419.1 mm) (330.2-419.1 mm)(330.2-495.3 mm)
10" min with
adaptor
12"
(304.8 mm)
13-1/2"
(343. mm)
14-1/2"
(368.3 mm)
Max. Outside
Diameter
32"
(812.8 mm)
35-1/2"
(901.7 mm)
38.5"
(980. mm)
Min. Outside
Diameter
19.5
(495.3 mm)
22"
(558.8 mm)
22"
(558.8 mm)
10"
(254 mm)
11"
(279.4 mm)
12"
(304.8 mm)
150 lb
(68 kg)
150 lb
(68 kg)
150 lb
(68 kg)
80/80 psig
(552 kPa)
80/80 psig
(552 kPa)
55 psig
(380 kPa)
3000# Machine
55 psig
(380 kPa)
Services required
Electrical power
requirements
Air supply
Floor requirements
Level
Min. natural frequency
Max. vibrational
amplitude
Min. spring rate
Operating modes
4.
Chuck hydraulic cylinder drives lower adapter and rim upward to
engage tire, lifting in into engagement with a upper rim on the tire drive
spindle now being rotated. The male cone of the lower spindle shaft engages a
female cone of the upper shaft to achieve required alignment of parts.
5. Bead seat air pressure inflates the tire through upper spindle and
forces tire bead fully onto rims. Bead seat air pressure releases and pressure
reduces to normal, or test pressure.
6. DC motor driven ball screw advances loadwheel carriage so that the
loadwheel applies load to tire. Load as well as other forces are measured by
two or three (optional with tangential) axis loadcells mounted at the ends of
the loadwheel shaft.
7. Hydraulic cylinders move grinder to skim position and move runout
sensor assemblies against rotating tire when tire is rotating in clockwise
rotation. If non- contact probe type runout sensors are used, the sensors only
come near the tire.
8.
At this time, all force and runout measurements are made for
clockwise rotation, and only force measurement is made for counterclockwise
rotation, depending on sequence of operation.
All data is calculated and
displayed on computer output device (meters, CRT, or hard copy device), and the
first harmonic high point of the radial force variation is marked on the tire
sidewall.
9.While data is being displayed, the computer makes a grind or no-grind
decision by comparing actual measured correctable parameters (radial composite
and harmonic force variation, and radial runout) to preset limits.
10. If concentric (runout) grinding is required for either top or bottom
shoulders of tread, both shoulder grinders, which are already at the skim
position, will lock on the high point of the runout. Under hydraulic control,
both shoulder grinders will advance at a slow grinding rate, removing material
from shoulders of tire until both shoulder runouts fall below a preset limit.
11.If concentric grinding is required for center of tire tread, the third
(center) grinder, which is already at the skim position, will lock on the high
point of the runout. Under hydraulic control, the third grinder will advance
at a slow grinding rate to remove material from the center tread area of the
tire until center runout is within preset limits.
manual.
13.Upon completion of the grind, an appropriate grade is given to the
tire to be used for marking at machine exit station.
Grinders, runout probes,
and loadwheel retract from tire.
14.Air pressure is released from tire. When air pressure is less than 34
kPa (5 psi) strippers operated by a pneumatic cylinder strip, the tire from the
upper chuck rim, as chucking cylinder retracts to lower the tire, lower rim,
and adapter. Chuck lubricating device sprays lubricant on rims to facilitate
chucking of next tire.
15.Tire is deposited on center conveyor and lower rim pulls out of
engagement with lower tire bead.
Since centering arms are now retracted,
center conveyor is free to move tire toward delivery end
of conveyor.
Photoelectric eye senses that tire has passed completely onto exit conveyor and
signals for entry of new tire for testing.
16.Arms of exit gate have moved into position to prevent passage of tire
onto sorting conveyor.
With tires held in position by gate arms, the
pneumatically driven tire marking device applies one to four grading marks on
tire bead seat, using information derived from the computer. Conicity marker
applies spot of ink to tire sidewall in one of two colors to indicate positive
or negative conicity.
17. Sorting conveyor moves to the position required depending upon the
grade of the tire just checked. Arms of exit gate open, and tire is fed onto
sorting conveyor and is delivered to required location.
2.0
INITIAL INSTALLATION
2.1
UNLOADING - The machine is delivered completely assembled.
Largeeye
bolts are fitted in the top main casting so that the machine can be lifted by a
crane.
WARNING
Use a crane having a suitable
approximately 9090 kg (ten tons).
lifting
capacity.
The
machine
weighs
2.2
DELIVERY INSPECTION - Make a thorough visual check of the machine noting
any damage that may have occurred in transmit. Refer to the delivery checklist
in Table 2-1.
2.3
LEVELING - The machine must be installed on a level concrete foundation
in a vibration free area. Refer to Table 1-1 for floor requirements. When the
machine is in position, install the position, install the adjustable vibration
mounts under each foot pad. Check level of the machine on the horizontal face
of the top spindle rim flange using a machinist's level. Machine must be level
within .25 mm/m (.003"/ft.)
Adjust as indicated in Figure 2-1.
2.4
SERVICES - The services required to operate the machine are listed in
Table 2-2.
TABLE 2-1.
CHECK
FOR
CONNECTION LOCATION
Electric power
Machine ground
Air supply
Connect to three-way
hand valve located
directly behind electrical panel.
*Cooling water
supply
* Required only when machine has water-cooled hydraulic system. Water supply
and drain are eliminated when unit has air-cooled hydraulic system.
TABLE 2-2.
SERVICE
CONNECTION LOCATION
Shoulder grinder
vacuum dust
collector
Third grinder
vacuum dust
collector
WARNING
Shut off machine power before making adjustments. Tag control panel to prevent
accidental machine starting while adjustments are being made.
1.
Loadwheel Setup. The shaft alignment pins of the loadwheel were removed,
and the loadwheel is supported by two angle brackets. This is done to prevent
damage to the load cells during shipment.
a. Remove the bolts holding the loadwheel in place, but do not remove
the angle brackets.
b. Insert the alignment pins through the load cells.
CAUTION:
Do not pound on pins; use a small pry bar.
c.
provided.
Remove the angle brackets, and tighten the pins with the nuts
Adjust
2.Remove pin going through the load cell and through the loadwheel spindle
shaft. DO NOT POUND ON PINS
3.
4.
Slide the loadwheel load cell assembly away from casting, approximately
1/2", to clear keys behind load cell.
5.
The top load cell is installed using keys in the vertical as well as
horizontal slots.
6.
Install the bolts in the load cell and leave bolts slightly loose.
7.
Install the pin through load cell and loadwheel spindle shaft.
8.
9.
When tightening load cell bolts, or pins, or when installing support bracket,
make sure that no force is exerted on load cell.
CAUTION
Do not tighten nuts until the brackets are removed.
2.
A. Remove the upper rim from the spindle shaft, suing the jack provided
in the Calibration Kit for support.
NOTE
Install "V" Block with hand knob on checking adapter shaft before the checking
adapter is bolted to the rim mounting flange.
B. Secure the checking adapter to the upper rim
shown in Figure 2-2 and mount a dial indicator.
mounting flange as
NOTE
Do not remove upper spindle belt before aligning adaptor.
C. Rotate the spindle shaft slowly and observe any deviations on the
dial indicator.
Any deviation must be less that .005 mm (0.0002 in.) between
top and bottom readings.
D. If the adapter shaft is not concentric, slightly loosen the screws
holding the adapter in place. Tap the adapter with a rubber mallet to obtain
the desired readings.
3.
E.
F.
B. Connect a dial indicator to the fixture and position the dial against
the edge of the loadwheel. This is an arbitrary point on the bottom side of
the loadwheel.
C. Mark the loadwheel (with a wax pencil) at the point of the indicator
contact (Point A, Figure 2-3).
D.
Tighten the thumb screw to hold the fixture firmly against the
adapter shaft. Record the dial reading.
E.
Use handle to rotate the spindle and loadwheel so that the dial
indicator resets on the same arbitrary point on the loadwheel, except on the
opposite side of the machine (Point B, Figure 2-3).
F.
The two dial readings must not differ more than .005 mm (.0002
inch.)
G. Repeat the measurements two or three times to be certain the readings
are accurate.
If the measurements are not within tolerance, shim the load
cells as follows (see Figures 2-3 and 2-4):
1. If the dial reading A, Figure 2-3, is greater than the reading at
point B, shim the top load cell.
2. If the reading point B is greater than the reading at point A,
shim the bottom load cell.
NOTE
Shim thickness required should be 2/3 of the value of the differencein the
readings.
4.
Reinstall
above:
1. Adjust the loadwheel squareness to .005 mm (.0002 inch) (Refer to
Paragraph 2-5, Item 3).
2. Adjust the loadwheel parallelism to .005 mm (.0002 inch) (Refer
to Paragraph 2-5, Item 4).
3. Rotate the spindle
B.
1. Start by measuring the clockwise and counterclockwise lateral shifts for a tire with white sidewall up at 444. daN (1000 pounds)
radial load at least five times. Repeat this measurement again the same number
of times, but the white sidewall down.
2.Tabulate the data and average them to determine the individual
means for each of the lateral shifts.
3.
If the absolute value of the lateral shift clockwise white
sidewall up mean is within .5 daN (1 pound) of the absolute value of the
lateral shift counterclockwise white sidewall down mean, and the absolute value
of the lateral shift counterclockwise with the white sidewall up mean is within
.5 daN (1 pound) of the absolute value of the lateral shift clockwise with the
white sidewall down mean, the machine bias is set and no further adjustment is
necessary. This relation is expressed as follows:
__
LScw
wsw-up
__
LSccw
wsw-up
__
LSccw
>
1 pound
__
LScw
>
1 pound
wsw-down
wsw-down
= 1
wsw-up
__
LSccw
wsw-down
------------------------2
a. Tighten the four load cell cover screws. (May have come
shipment.)
This should have been done before mechanical
b.
computer) to zero.
c.Mount a dial indicator (A, Figure 2-6) near the bottom edge of
the loadwheel face.
d. Loosen the four bottom load cell mounting bolts. Watch for
alignment changes indicated on indicator A. Loosen the load cell pin nut.
e.
g.
2-7).
a. The Center Probe centerline may be changed 13 mm ( 1/2") up or
down from rim centerline as required by removing the probe and probe holder (1
and 2) from the right center guide (7) and loosening the two screws (11)
holding the right and left center guides (7 and 9) to the contour adjustment
fixture (6) and sliding the two pieces up or down accordingly.
Retighten
screws (11), and reassembly probe and probe holder (1 and 2) to the right
centerline guide (7).
b.
Shoulder Probes
1. Loosen socket head cap screws (12) for both upper and lower
probe holders (2) and slide both upper and lower probe brackets to the rear of
the machine or/and away from the tire.
2. Chuck up and inflate a tire of the size desired to be tested,
and advance free radial runout probes to cross over. (See instruction manual
for non-contact probes and machine operations manual).
WARNING
This runout unit, as well as the machine they are attached to include a number
of moving parts and assemblies under automatic control. Keep clear of moving
parts while machine is in operation.
Approaching too close to the machine
during operation could result in injury or even death.
WARNING
When making checks or adjustments which can be made only when the machine is
powered, taking extreme caution to prevent unauthorized control operation while
adjustments are in progress.
3. Adjust shoulder probe width using adjustment knob, item 22,
such that the two probes are pointing in area desired to be measured.
4. Once shoulder probes have been adjusted to proper width,
slide both upper and lower shoulder probes toward the tire until there is
approximately 10 mm (3/8") clearance between the end of the probe holder and
the shoulder of the tire. (Reference Figure 1) Secure upper and lower probe
holders using socket head cap screw, item 12.
2.
FRRO probe mechanical adjustment for one channel FRRO (Reference
Figure 2.7A) -The probe centerline may be changed 13 mm (1/2") up or down from the rim
centerline as required by loosening the two socket head cap screw (8) and
sliding the mounting plate (7) up or down screws, item 8.
3. FLRO Sensor Adjustment - To adjust the Free Lateral Runout (FLRO)
sensor, proceed as follows:
a. Loosen the mounting screws (2, Figure 2-8) that secure the FLRO
sensor to the base slide. Turn the adjusting knob (3) to raise the sensor to
its highest position.
b.
Ensure that the DCDT plunger stops are all the way back on both the shoulder
grinders (Figure 2-9) and the third (center) grinder (Figure 2-10) before
adjusting the skim.
c. To back off each shoulder grinder DCDT plunger stop, loosen the
adjusting knob (3, Figure 2-9) and slide the plunger stop (2) away from the
DCDT plunger (1) so that the stop will not contact the plunger as the grinder
moves inward to the skim position.
d.Place the GRINDER-NORMAL/SKIM selector to SKIM>
The shoulder
grinders will move to their skim positions, the third grinder will not.
e. When the shoulder grinders move to their skim positions, perform
the skim adjustment procedures described in paragraphs 7--2 and 7-3 if
non-contact type sensors are used.
For adjustment of non- contact probe
sensors, refer to the supplement.
f. With the shoulder grinders in the skim position, adjust the DCDT
plunger stops (2) so that the DCDT plunger (1) are depressed to approximately
mid- range. Tighten the adjusting knobs (3).
The
h. To back off the DCDT plunger stop of the third grinder, loosen
the adjusting screw (3, Figure 2- 10) and slide DCDT plunder stop (4) away from
DCDT plunger (5) so that the stop will not contact the plunder as the third
grinder is moved inward toward the skim position.
i.
m. If the skim is too light (the grinding wheel does not touch the
tire) move the probe away from the tire by loosening the probe mounting bolts
(item 8 on Figure 2-11) and turning the thumb wheel adjustment knob (item 9) to
position the probe such that the grinding wheel rotates slowly or
intermittently. Tighten the probe mounting bolts.
WARNING
Stop rotation to perform sensor position adjustment.
occur due to rotating and translating members.
n. If the skim is too heavy, (the grinding wheel rotates quickly and
is pressing on the tire) move the probe toward the tire by the method outlined
in the previous paragraph until the grinding wheel rotates slowly or
intermittenly. Be sure to tighten the probe mounting bolts.
o.
NOTE
For computer cell adjustments on GRIND RATE, MAXIMUM GRIND DEPTH and SPARK
TIME, See Computer Operations manual on editing.
2.7
THIRD (CENTER) GRINDER ADJUSTMENTS - Proper height and angle adjustments
were made at the factory prior to shipment, and further adjustment should be
unnecessary.
If adjustment should become necessary, proceed as follows (see
Figure 2-12):
1. Third Grinder Angle Adjustment:
a. When the third grinder is in the down position, the tire and
grinder wheel should be on the same centerline.
Adjust the height, if
necessary, as described in paragraph 2 below.
2.8
FORCE CALIBRATION
NOTE
calibration:
a.
When calibrating the radial channel, all cable and hanging
fixture must be parallel and square to the loadwheel, and all pulleys must be
free to turn so that frictional looses are at a minimum.
b. Before calibration, system power must be on for at lease one-half
hour for instruments to attain normal operating temperature.
c.Ambient temperature at the time of calibration should be within 12
(10 F) of ambient temperature at the time of any correlation test.
2.
procedure.
CAUTION
Remove all calibration fixtures from the load system before operating the
machine, or damage may result.
3.
a.
Install one hanging fixture on the loadwheel flange for the
addition of precision weights.
b.
procedure.
CAUTION
Remove all calibration fixtures
themachine, or damage may result.
2.9
from
the
load
system
before
operating
RUNOUT CALIBRATION
NOTE
The following instructions are for systems with contact-type sensors only. If
the machine is equipped with non- contact probe sensors, refer to the noncontact probe supplement manual.
1.
Precalibration Procedure - Note the following before performing
runout calibration:
a.
calibration procedure.
b. Before calibration, system power must be on for at lease one-half
hour for instruments to attain normal operating temperature.
c. Ambient temperature at the time of calibration should be within
12C (10F) of ambient temperature at the time of any correlation test.
d.
calibration.
NOTE
Perform section 2.6, 1, 2, an 3 for proper FRRO and FLRO mechanical adjustment
before performing runout sensor calibration.
1. With runout probes IN/OUT selector switch on IN, follow the steps
outlined in the Computer Maintenance Manual, on Runout Calibration. Add 2.5 mm
(.100") displacement by placing 2.5 mm (.100") thick gage blocks between the
runout sensors and tire.
3.0
OPERATION
See the Computer Operations Manual and Maintenance Manual for full details of
operating procedures.
4.0
4.1
GENERAL - The machine can handle tires with various bead diameters,
section widths, and outside diameters.
When changing from one tire size to
another, certain adjustments may have to be made.
The tread width must not
exceed the loadwheel when the tire is loaded.
4.2
ADJUSTMENTS FOR CHANGING TIRE SECTION WIDTH - The following changes may
have to be made for a tire of different section width, but of the same bead
diameter.
1. Tire Pressure - If a change intire pressure is required, it can be
made at the operator control panel.
2.
a. Chuck up a tire.
b. Unlock the vertical position clamps (3 and 4, Figure 4-1).
c. Use the ratchets (2 and 5) to position the grinding assemblies to
the desired vertical height or spacing when the grinders are skimming the tire.
d. Lock the final vertical position by tightening the positioning
clamps (3 and 4).
3.
Grinder Tilt:
a.
4.3
ADJUSTMENTS FOR CHANGING TIRE BEAD DIAMETER - The following changes may
have to be made for handling tires of a different bead diameter, and of the
same or different section width. Spread center conveyor first to clear bottom
rim flange by 13 mm (1/2").
1.
Use the jack provided in the calibration kit to support the upper
rim (6).
b. Remove the four mounting bolts (4) holding the upper rim (6) in
place and allow the rim to rest on the jack support plate.
c.
d.Remove the mounting bolts (2) around the tapered cone register of
the lower rim (1) and lift the lower rim out of the machine.
e.To install new size rims, refer to Figure 4-2.
f.Before installing and checking the rims, check that the O-rings (5
and 9) are in place. Also, ensure that the register surfaces
are clean.
g. Note the locating pin (7) (if used) on the upper rim.
all screws holding the top and bottom rims.
Tighten
h.Raise the lower rim against the upper rim under high hydraulic
pressure.
i.
l. Rotate the spindle and check the runout of both rims in the bead
seat area for lateral and radial runout.
NOTE
Maximum allowable runout is .025 mm (0.001 inch).
2. Stripping Wheel Adjustment - Whenever new sized rims are installed,
the stripping wheels must be adjusted. Turn the handwheel until the pointer on
the bead diameter scale indicator reads the same number as the bead size of the
rims.
WARNING
When changing bead diameters, insure stripper and center conveyor is adjusted
properly so not to damage rim flange when actuated.
3. Tire Centering Arms (Center Conveyor) - When changing to a different
diameter tire, the centering arms may need readjustment.
To adjust the
centering arms, turn the adjusting knob to add or remove cylinder stroke.
If either of
readjusted:
the
following
conditions
exist,
the
centering
arms
must
be
a. Centering Arms Compress the Tire - Open the centering arms until
the tire is not compressed.
b. Tire is more than 13 mm (1/2 inch ) from Centering Arms - Close
the centering arms toward, but not touching the tire.
4.
Computer - Select the correct tire code for the specific tire being
run.
4.4
HARMONIC HIGH POINT MARKER POSITION ADJUSTMENT - The position of the
harmonic high point marker pump must be adjusted vertically when changing the
size of the tire section width to ensure proper application of the ink mark.
The high point marker requires horizontal adjustment to compensate for changes
in the tire bead size. Proceed s follows:
1.
Vertical Positioning:
Horizontal Positioning:
NOTE
This position is only a suggestion; the marker may be set at another point if
customer requirements so dictate aslong as the marker nozzle is vertically
positioned 13 mm (1/2 inch) from the tire surface.
c.
4.5
CONICITY POLARITY MARKER POSITION ADJUSTMENT - The ink mark may be
adjusted in both the vertical and horizontal directions to accommodate changes
in tire diameters and section widths.
1.
Height Positioning - Reference Figure 4-5 for various height
positioning and adjust as follows:
a. Loosen the adjustment locking knob.
b. Use the height adjustment handwheel to slide the marker mechanism
to its maximum height and tighten the adjustment locking knob.
c. Place the desired size tire under the marking nozzles.
d.Loosen the adjustment locking knob and slide the marker nozzles to
a point near the bead of the tire.
NOTE
This position is only a suggestion and the marker may be set at another point
if customer requirements so dictate.
e. Tighten the horizontal adjustment knobs.
2.
Horizontal Positioning - Reference Figure 4-6 for horizontal
positioning and adjustment as follows:
a.
5.0
ADJUSTMENTS
5.1
GENERAL - The adjustments described in this section have all been made at
the factory and usually do not require readjustment except to correct a
malfunction or as the result of part replacement.
5.2
TIMER ADJUSTMENTS - All machine sequencing timers are contained in the
computer software. See Computer Operations Manual for common adjustment cells.
The carriage lube timer, located in the magnetics control panel should be set
to 120 minutes. There are no other external timers on the machine.
5.3
LIMIT SWITCH ADJUSTMENTS - Limit switches control various operating
limits of the unit.
Some of the switchesare preset; others are adjustable.
Table 5-1 lists the limit switches and indicates the required adjustments.
Switches are identified by the indicated designations.
5.4
AIR PRESSURE REGULATOR ADJUSTMENTS - Air pressure controls various
operations of the TUO.
Various pressures are required for the different
applications. These pressures are achieved through use of adjustable pressure
regulators. The regulators, their locations, and the pressure requirements are
given in Table 5-2.
5.5
HYDRAULIC SYSTEM ADJUSTMENTS - Many components of the TUO are actuated by
hydraulic pressures and flows. Hydraulic system adjustments are as follows:
1.
(Figure 5.1)
d. To adjust the FRRO and FLRO pressure; reset machine, and turn the
screw on the FRRO/FLRO pressure reducing valve and set for 2400 to 3400 kPa
9350 to 500 psig).
2.
Always
Always
NOTE
Be careful that baffle does not fall off screw.
5.
Use a high quality, clean lubricating solution Akron Standard
recommends - soap, water and rust inhibitor solution.
6. Close the shutoff valve to the bottom chuck spray nozzles for several
cycles or until the upper nozzles are spraying an excess mist.
7.Crack open the shutoff valve located below spray system to the bottom
nozzles and note the spray. If the mist is excessive, the baffle can be raised
slightly by turning the baffle screw one or two turns to the right.
8.If the unit fails to produce a spray mist, drain and clean the unit and
check the venturi tube for clogging or corrosion. Clean the venturi tube and
nozzle if necessary.
9. To adjust spray time, refer to Computer Operations Manual for common
adjustment cells.
5.7
HIGH POINT MARKER ADJUSTMENTS - The high point marker (Figure 5-3) is
designed to propel a small jet of ink from the nozzle of the marker onto the
sidewall area of the tire. The high point of the radial first harmonic force
of the tire is determined electronically by the computer. Ink is supplied from
a remote gravityfeed reservoir through a nylon tube to the marker mechanism.
The marker is designed to divert a percentage of the pump stroke pressure into
the ink feed tube, and back into the reservoir. This action produces adequate
agitation of the contents to keep pigmented inks in solution.
A positive
shutoff valve at the reservoir eliminates any dripping or leaking.
(NOTE:
Also used as a low point marker).
1. Adjusting Size of Ink Mark - The size of the ink mark is controlled
by adjusting the length of the pump stroke as follows:
a. Check reservoir for adequate ink supply. If necessary, add ink
(WS910-AF, available in gallon lots from Akron Standard) to fill reservoir.
Make sure reservoir shutoff valve is open.
b.Check for 550 kPa (80 psi) o the gauge at marker air regulator.
c.
d.
Depress (once) the HARM ANGLE MARKER CLEAR pushbutton and a
quantity of ink will spray onto the sidewall.
e. If the amount of ink is inadequate or excessive, turn the ink
mark size adjustment nut on the pump.
NOTE
The priming clip must be in place when making this adjustment.
f.
2.
b.
c.
d.
available from
e.
f.
g. Turn on the marker air regulator and adjust air pressure so that
the gauge indicates 80 psi.
h.
3. Priming the Marker Pump - Priming of the marker pump may be necessary
after a prolonged shutdown, and possibly whenever the ink reservoir supply is
replenished. To prime the pump, proceed as follows:
a.
b.
push-button.
d. When the marker is primed, reinsert the priming clip and the
marker is ready for operation.
4.
Mark Delay Adjustment - This adjustment concerns the
electro-mechanical lag of the marker system.
It is controlled only by the
computer and is dependent on the distance between the nozzle and tire (see
section 4.4), viscosity of the ink, stroke of the marker cylinder and the
amount of time it takes the marker solenoid to energize.
a. Select a tire whose radial peak force is approximately equal to
its radial harmonic force and is greater than 18 daN (40 lbs.)
b. Use a logic sequence to mark the high point of a tire in both
clockwise and counterclockwise directions.
c. With computer in manual operation, and HARMONIC POINT MARK SWITCH
ON, CHUCK UP, INFLATE, LOAD AND TEST A TIRE.
d.If the high point mark CW does not correspond with the high point
mark CCW, refer to the Computer Operations Manual for common adjustment cells
procedures.
5.8
BEAD MARKER SETUP AND ADJUSTMENT (Ref. Figure 5-4) - The bead marker is
designed to stamp a combination of upto 4 bars of paint onto the tire I.D. at
the bead.
Marking combinations are controlled by the computer and actuated
when:
a.
a.
Place desired tire in marking zone and actuated exit gate
centering solenoid 14 SOL manually.
WARNING
Exit gate will actuate in toward tire, rotational and translating motio could
cause injury. Insure clear distance from machine.
b. Push tire O.D. up against pivot arms and manually actuate all 4
bar marker solenoids 11, 12, 13, and 14 SOL. Bar rollers 93) will rotate and
advance to bead of tire (all four should contact).
WARNING
Marker arms (6) will rotate into position creating pinch points, keep hands
away from marker when actuating.
c.If bar rollers do not contact bead area of tire, remove pull pins
(4) from pivot arms (2) and adjust arms until bar rollers contact bead of tire.
Replace pull pins to nearest holes.
2.
b.Reinstall drain plug (7), open fill l id and fill reservoir with
paint until the large diameter of the drain plug and ink level indicator is
just covered.
c.
Akron Standard recommends water based Latex paint for bead markers use.
5.9
1.
Purpose of Marker - The conicity Polarity Marker is designed to
identify the
polarity of the measured conicity value by applying a spot of
colored ink on the sidewall of a tire when it reaches the marking station of a
TUO machine. Positive or negative conicity is determined electronically by the
computer.
Ink is supplied from remote gravity-feed reservoirs through nylon
tubing to the marker mechanisms. The markers are designed so that a percentage
of the pump stroke pressure is diverted into the ink feed tube, and back into
the reservoir. This action produces adequate agitation in the contents to keep
pigmented inks in solution.
A positive shutoff valve at each reservoir
eliminates any dripping or leaking.
2.
Specifications
Marker ------------------- Carco 3ES-454 Pumpomatic
Electrical Power ------------------------ 110 Volts
Pneumatic Power --------- 550-690 kPa (80-100 psig)
Size - 50.8 x 69.9 x 304.8 mm (2" x 2-3/4" x 12" approx.)
*Ink ------------------------------- Carco #WS910-AF
*CAUTION*
Using a substitute ink could cause clogging of the markers and result in
permanent damage. Use of any ink other than that specified will void the Carco
warranty. Ink is available in assorted colors from Akron Standard. 3.78 (one
gallon) of specified colors are furnished with each marker kit.
3.
Adjust the air supply to the solenoid valve(s) to 310 kPa (45
psi).
b.On initial start-up, or if changing colors of ink: remove the
priming clip "A" (see figure) and manually cycle the pump until ink is ejected,
by pressing the manual override on the top of the solenoid valve. Re-install
the priming clip.
c.
Adjust the stop nut "B" until the minimum volume of ink is
dispensed through the nozzle. Use the manual override for cycling during this
set-up.
the air pressure setting upward to eliminate a "tail" on the mark. The higher
the air pressure setting, the faster the ink is ejected, but the wear on the
anvil and pump piston is accelerated.
4. Maintenance The marker requires little or no maintenance other
than filling the ink reservoir or priming the pump.
5.
7.
Manual.
CAUTION
Using a sorting conveyor adjacent to the exit of the TUO could result in tire
jam at the conicity marker. If a conveyor is used, insure that the back of the
tire does not hit the marker when making its descent.
6.0
LUBRICATION
6.1
LUBRICATION SCHEDULE - The machine was completely lubricated prior to
shipment.
However, loss of lubricant may have occurred during transit and
installationof the machine.
Check for adequate lubrication before operating
the machine. Refer to Figure 6-2 for lubrication points, type of lubricant, and
frequency of application.
WARNING
Turn off the machine before performing lubrication procedures. Never attempt
to lubricate the machine while the operating cycle is in progress. Because of
the moving assemblies, this machine is potentially dangerous, and approaching
too close to the unit during operation could result in severe injury or death.
6.2
AIR LINE LUBRICATORS - Two air line lubricators are used on the machine.
These lubricators inject a small amount of oil into the air stream to lubricate
the various air cylinders. Check periodically and replenish oil as required.
For further information, refer to the lubricator manufacturer's data included
in this manual.
6.3
CHUCK SPRAY MIST GENERATOR - A lubricant spray mist generator is used to
lubricate the tire rims to ease the chucking and unchucking of the tire. Refer
to paragraph 5- 6 for adjustment procedures.
At the start of every shift,
check the lubricant level in the reservoir and fill if necessary.
Akron
Standard recommends soap, water, and rust inhibitor solution.
6.4
CAUTION
Do not operate the pump with an empty
reservoir.
2. The lubricator reservoir has a 5.4 kg (12 pound) capacity. This is
sufficient lubricant to last several months. An indicator rod (Figure 6-1) on
top of the reservoir is extended 178 mm (seven inches) when the reservoir is
full. When the rod extends two inches or less, the reservoir requires filling.
After filling, purge all air from the pump-to-reservoir lie; loosen the cock
vane provided to aid in purging. Refer to Figure 6-2 for type of lubricant and
frequency of inspection.
WARNING
Be careful when disassembling the reservoir for cleaning or repair.
which exerts 89 daN (200 pound force) is enclosed in the reservoir.
A spring
6.5
RECOMMENDED LUBRICANTS - Recommend hydraulic systems oils are listed in
Table 6-1.
TABLE 6-1.
SUPPLIER
TRADE NAME
Hytherm S-150
E. F. Houghton
Hydro-Drive HP 150
Nuto H-44
Harmony 43AW or Harmony 48AW
D.T.E. 24
D.T.E. 25
D.T.E. 26
Puropale - RX - Light
Tellus 927
Premium Grad H 15
Sun Oil
Texas Co.
Tidewater Oil Co.
Warren Refining & Chemical Co.
7.0
MAINTENANCE
7.1
GENERAL - There are several adjustment on the grinders; some are to be
checked daily or once per shift while others are made only when repair is
necessary.
WARNING
Extreme caution must be taken when making machine adjustments which require
power to be applied.
Tag the control panel to prevent accidental control
operation which could result in injury to the personnel making the adjustment.
Wheneverpossible, turn off the machine before making adjustments.
7.2
SKIM ADJUSTMENT (ELECTRICAL) (ALL GRINDERS) -- This adjustment should be
checked once per shift; readjust as required.
NOTE
Electrical skim adjustment must be performed in conjunction with concentric
grind setup (paragraph 2-6, 3).
1.
2.
3.
GRIND MODE
7.
Turn the SKIM potentiometer until the grinder motor timing belt
pulley rotates slowly or intermittently.
NOTE
The timing belt pulley can be seen by looking into the plexiglas
grinder motor.
cover on the
7-3.
7.3
1.
Shoulder Grinders - This adjustment was made at the factory;
readjustment should be infrequent.
Center Grinder:
Manual and
7.6
ROUTINE GRINDER MAINTENANCE AND INSPECTION - The most important item in
maintaining the grinders is to keep them free from any rubber dust buildup.
Other points to check are:
1.
required.
Replace wheel as
4.If the grinder spindle shaft shown signs of bearing failure or becomes
frozen, it is recommended that the spindle assembly be returned to Akron
Standard for reconditioning.
Remove the housing cover and loosen the drive
motor attachment to release the timing belt. Then remove the spindle assembly.
5.Inspect the grinders for proper lubrication and lubricate as required.
Refer to Figure 6-2 for type of lubricant and frequency of lubrication.
NOTE
The spindle assembly requires no additional lubrication as it is lubricated for
life.
7.7 GRINDER SERVOVALVES - Three servovalves are used on the machine to control
the hydraulic movement of the grinders.
a.
b.
c.
d.
e.
Insert Allen Wrench in the servovalve adjusting screw and rotate
until the grinder moves to mid-range of cylinder stroke.
f.
grinder.
g.
h.
i.
The servovalves are run at 6900 kPa (1000 psig) hydraulic pressure. Keep hands
away from moving grinder arms and linkage while making the servovalve null
adjustment.
2.
manual.
NOTE
Akron Standard does not recommend disassembly of the servovalves.
problems occur, return the servovalves to the manufacturer for repair.
If
7.8
LOADWHEEL CARRIAGE SERVO POT AND TACHOMETER - A small DC tachometer and
ten-turn potentiometer are used on the machine to help control the loadwheel
drive circuit.
The
tachometer also acts as a damper to reducer any servo
system oscillation. The servo pot signals to the computer the exact position
of the loadwheel. Refer to Figure 7-3 to locate the servo pot and tachometer.
1.Replacement and Calibration of Servo Pot:
a.
position.
b.Remove old pot, disconnect the wires, and place new pot in
Turn on machine and computer power.
c.
d.
e.
f.
g.
7.9
HYDRAULIC SYSTEM - The hydraulic system develops various pressures to
perform the following functions:
Raise and lower the chuck, hold chucks
engaged, operate the grinders and runout probes.
The hydraulic system
adjustments are outlined in Section 5.5. For further information on individual
hydraulic system components refer to the Akron Standard hydraulic system
drawings and the vendor data provided with this manual.
NOTE
Drain and replace the hydraulic oil filter every 4000 hours of machine
operation, or more frequently if required.
Refer to Table 6-1 for recommended
hydraulic oils.
1. Hydraulic System Flushing - If it is suspected that the hydraulic oil
has been exposed to dirt or contamination, the system must be flushed as
follows:
a.
This
servovalves.
NOTE
Wipe off the valve seating surface before mounting the servovalves.
2.Replacing Hydraulic Filter Elements - Two filters re used on the
hydraulic unit. Both are equipped with automatic dirt indicators. Check the
indicators periodically and replace the filter elements when the indicator
shows a dirty condition.
Replacement elements can be ordered from Akron
Standard.
Refer to recommended spare parts list for the correct element
number.
3.Motor Pump Alignment - Check quarterly, alignment between motor and
pump shafts. An indication of misalignment can usually be observed by a worn
coupling between motor and pump shafts.
7.10 PNEUMATIC SYSTEM
(NOTE: See Section 8.0 for a detailed explanation of the pneumatic system).
1.Air Pressure Regulators - The most common problem with regulators is
dirt. Check and clean each regulator periodically. Refer to the appropriate
vendor's data at the rear of this manual for disassembly and maintenance
information. Refer to Table 5-3 for air regulator settings.
2. Air Line Filters - Three filters are used on the pneumatic system:
one at the incoming main air supply (50 micron, located behind the magnetic
panel), one at the outlet of the accumulator) and one on the computer purging
system (a rigid metal strainer type, located on the side of the DTUOC). The
filters should be checked periodically for dirt and contamination.
Clean or
replace the filter elements as required. The computer purging filter can be
washed with kerosene,
blown dry with compressed air (about 30 psig) and
reused. use only kerosene to wash filter bowls; other cleaning solutions may
attack the polycarbon plastic bowls.
3.
Solenoid-Operated Air Valves - All solenoid valves should
beperiodically checked for proper operation. Dirt and defective solenoid coils
are the main cause of erratic operation or malfunction in solenoid valves.
Table 7-1 lists all solenoid valves used on the pneumatic system.
8.0
8.1
2.
3.
4.
5.
6.
7. Supplies air to air purge system for shoulder grinder sensor (contact
or non-contact), center grinder (contact or non-contact), radial runout sensors
(non- contact only) and lateral runout sensors (non-contact only).
Air supply - clean filtered air, 31.75 mm (1-1/4") diameter air line at
552 to 690 kPa (80 to 100 psig) @ .5 m3/min. (72 SCFM) minimum flow capacity.
8.2
deflation
2. Rotary Union - The air union provides ports for air flow and the
pressure monitoring sense tube while also yielding to rotation.
3. Sense Tube - This tube extends from the rotary union, up through the
spindle. It provides a true static sensing pressure to the inflation system.
4.Inflation Valve - A single solenoid (SOL 18B), three way, two position
normally open and spring returned is used to direct a large volume flow of air
to the tire from the supply or from the tire to the exhaust valve.
5.Exhaust Valve - A single solenoid (SOL 18), two way, two position,
normally open and spring returned valve is used to exhaust air from the tire
from bead seat pressure to approximately test pressure and to completely
deflate the tire.
6.
Test Pressure Valve - A single solenoid (SOL 17), two way, two
position, normally closed and spring returned valve is used to direct a
feedback pressure from the tire to the volume booster relay to correct
inflation pressure to within .7 kPa 0.1 psig).
7.Muffler - Used to disperse and quiet exhausting air from the tire.
8.Bead Seat Pressure Regulator - Bead seat pressure is adjusted using
this regulator. Set 70 kPa (10 psig) above desired test pressure.
9.
regulator.
10. Volume Booster Relay - Compares input from test pressure regulator to
on a one-to-one ratio and adjust it accordingly.
11.
12. Soft Seat Check Valve - Because of the large volume drained from the
accumulator during bead seat, this valve is used to stabilize the test pressure
supply portion of the system by preventing any test pressure air to flow back
into the accumulator.
13. Accumulator - A tank is used as a supply for the inflation valve
because of the large volume of air required for bead seat.
14. Supply Valve - Manually energized to supply air to pneumatic system.
15.Filter - Mechanical drain.
16.Supply Pressure Gauge - 0-861 kPa (0-125 psig).
17. Expansion Chamber - Used as a damper to prevent the frequency of the
air between the volume booster relay and test pressure valve from approaching
the natural frequency of the diaphram in the volume booster relay.
18. Test Pressure Air Gauge - Monitors the pre-set pressure from the test
pressure regulator.
19.Monitors the pre-set pressure from the bead seat regulator.
20. Tire Pressure Gauge - Monitors actual tire pressure (NOTE:
read 0 kPa (0 psig) at deflation).
The gauge
8.2.2 TIRE INFLATION THEORY OF OPERATION - The purpose of the tire inflation
system is to inflate a tire by seating the tire beads at a high pre-set
pressure 379 kPa (55 psig) maximum, then dropping this seat pressure down to a
pre-set test pressure 70 kPa (10 psig) below bead seat pressure and maintain it
within .7 kPa (0.1 psig) of the pre-set value. Operation is as follows:
1.Pre-set the desired test and bead seat pressures by adjusting the
regulators on the control box while monitoring these pressures on the test and
bead seat pressure gauges.
(NOTE:
Set bead seat pressure 70 kPa (10 psig)
above test pressure).
This provides the test and bead seat differential
pressure switches with a picking reference pressure. (NOTE: See Figure 8-2
for solenoid sequencing).
2. During tire inflation, SOL 18B of the inflation valve is energized
releasing a large volume of high pressure air from the accumulator and supply
line (see Figure 8- 3).
This air travels through the inflation valve and
rotary union and on through to the tire. As the pressure inside the tire and
sensing tube increases to 34 kPa (5 psig). PS-1 trips sending a signal to the
computer to confirm inflation. This pressure switch is used as a safety device
to prevent accidental unchucking of an inflated tire.
3.When tire pressure reaches the pre-set test pressure, PS-3 is tripped
but the signal is ignored and the tire pressure increases to the pre-set bead
seat pressure. PS-2 is now tripped at bead seat.
4. PS-2 then signals computer to de-energize SOL 18B of the inflation
valve thus releasing air through the inflation valve, exhaust valve and muffler
then finally to the atmosphere (see Figure 8-4).
5. As the tire and sensing tube pressure decrease to the desired pre-set
test pressure, PS-3 trips, thus signaling the computer to energize SOL 18A of
the exhaust valve and SOL 17 of the test pressure valve (see Figure 8-5). The
tire is approximately at the pre-set test pressure.
6. With SOL 17 of the test pressure valve energized, the volume booster
relay has two reference pressures to compare (see Figure 8-5): Port "A" from
the test pressure regulator and Port "B" from the sensing tube in the tire.
The volume booster relay compares these pressures and will adjust tire pressure
accordingly.
7.If the tire pressure is greater than the pre-set regulator pressure,
excess air will be expanded into the atmosphere by the volume booster relay.
If it is less than the pre-set test pressure, air will be allowed to flow from
the accumulator, through the volume booster relay and into the tire unit until
the pre-set test pressure is reached. The volume booster relay will hold this
tire pressure to within 0.1 psig of the pre-set value.
8. At deflation, all solenoids are de-energized (Figure 8- 6) with SOL
17-de-energized, an isolated system results between the accumulator, test
pressure valve and the bead seat and test pressure switches. Air is expelled
from the tire, through the inflation and exhaust valves where it is exhausted
into the atmosphere by the muffler.
NOTE:
When any emergency stop condition
energized, thus, deflation occurs.
is
encountered,
all
solenoids
are
de-
9.0
SPARE PARTS - This section is provided as a guide for ordering and
stocking replacement parts.
9.1 ORDERING - When ordering parts from Akron Standard, the following data
should accompany the order:
a.
b.
c.
d.
Quantity.
Part Description.
Akron Standard Part Number, Drawing and Item Number (as applicable).
Machine Serial Number.
9.2
STOCKING - The suggested spare parts are outlined in the following list.
This list is included with the objective of keeping the machine "down time" to
a minimum. Although a few of the parts may be available locally, it is often
faster and more economical to stock them in the plant.
Certain parts may
already be in stock as spares for other machines. Suggested spare parts should
be reviewed with this in mind.
9.3
GENERAL - The following lists of spare parts have been prepared to assist
in performing maintenance and repairs on the components and sub-assemblies of
the Tire Uniformity Optimizer. Note the following:
a.
Refer to the manufacturer's data at the backof this manual for
service to assemblies not manufactured by Akron Standard .
NOTE:
Parts marked * should be purchased for immediate stock.