Frustration Revision Notes
Frustration Revision Notes
Contracts are often silent on the position of the parties in the event that something happens subsequent to
the formation of a contract which renders its performance literally impossible, or only possible in a very
different way from that originally contemplated. The doctrine of frustration operates to excuse from further
performance where: (1) it appears from the nature of the contract and the surrounding circumstances that
the parties have contracted on the basis that some fundamental thing or state of things will continue to exist,
or that some particular person will continue to be available, or that some future event which forms the basis
of the contract will take place; and (2) before breach, an event in relation to the matter stipulated in head (1)
above renders performance impossible or only possible in a very different way from that contemplated.
In more recent times, five propositions have been set out as the essence of the doctrine.
* the doctrine of frustration has evolved to mitigate the rigour of the common law's insistence on literal
performance of absolute promises so as to give effect to the demands of justice, to achieve a just and
reasonable result, to do what is reasonable and fair, as an expedient to escape from injustice where such
would result from enforcement of a contract in its literal terms after a significant change in circumstances.
* the effect of frustration is to kill the contract and discharge the parties from further liability under it, so
that the doctrine cannot be lightly invoked but must be kept within very narrow limits and ought not to be
extended.
* the effect of frustration is to bring the contract to an end forthwith, without more and automatically.
* the essence of frustration is that it should not be due to the act or election of the party seeking to rely
upon it, but due to some outside event or extraneous change of situation.
* that event must take place without blame or fault on the side of the party seeking to rely upon it; nor
does the mere fact that a contract has become more onerous allow such a plea. The mere fact that the
parties apparently treated a contract as remaining in force until a late stage in their dispute does not
conclusively rule out a plea of frustration.
FRUSTRATION OVERVIEW
The doctrine of frustration operates in situations where it is established that due to subsequent change in
circumstances, the contract is rendered impossible to perform, or it has become deprived of its commercial
purpose by an event not due to the act or default of either party.
Frustration is not to be confused with initial impossibility, which may render the contract void ab initio. See
Couturier v Hastie (1856) 5 HL Cas 673 (Handout on Mistake).
TESTS FOR FRUSTRATION
There are two alternative tests for frustration:
(1) The implied term theory, as in:
Taylor v Caldwell (1863) 3 B&S 826.
Lord Loreburn explained in FA Tamplin v Anglo-Mexican Petroleum [1916] 2 AC 397, that the court:
' can infer from the nature of the contract and the surrounding circumstances that a condition which
was not expressed was a foundation on which the parties contracted Were the altered conditions such
that, had they thought of them, the parties would have taken their chance of them, or such that as sensible
men they would have said "if that happens of course, it is all over between us".'
(2) The radical change in the obligation test. This was adopted by the majority of the House of Lords in:
Davis Contractors v Fareham UDC [1956] AC 696.
In National Carriers v Panalpina [1981] AC 675, Lord Wilberforce was reluctant to choose between the
theories. He took the view that they merged one into the other and that the choice depends upon "what is
most appropriate to the particular contract under consideration".
EXAMPLES OF FRUSTRATION
A) DESTRUCTION OF THE SPECIFIC OBJECT
ESSENTIAL FOR PERFORMANCE OF THE CONTRACT
The destruction of the specific object essential for performance of the contract will frustrate it. See:
Taylor v Caldwell (1863) (above).
B) PERSONAL INCAPACITY
Personal incapacity where the personality of one of the parties is significant may frustrate the contract:
Condor v The Baron Knights [1966] 1 WLR 87
Phillips v Alhambra Palace Co [1901] 1 QB 59
Graves v Cohen (1929) 46 TLR 121
FC Shepherd v Jeromm [1986] 3 All ER 589.
C) THE NON-OCCURENCE OF A SPECIFIED EVENT
The non-occurence of a specified event may frustrate the contract. Compare the leading cases:
Krell v Henry [1903] 2 KB 740
Herne Bay Steamboat Co v Hutton [1903] 2 KB 683.
BP v HUNT
In December 1957 the Libyan government granted the defendant a concession to explore for, and extract,
oil in a specified area in the Libyan desert. In June 1960 the defendant, who did not have the knowledge,
equipment or resources to develop the concession himself, entered into a contract with the plaintiff, a major
oil company. The contract, known in the oil industry as a farm-in agreement, was contained in two
documents, namely a 'letter agreement' and an operating agreement, whereby the defendant agreed to assign
to the plaintiff a half share in the oil concession in consideration for which the plaintiff undertook to
explore, develop and operate the whole of the concession entirely from its own resources and at its own
expense and to make down payments in cash and oil to the defendant as 'farm-in' contributions. Under the
agreement, if and when oil was discovered in commercial quantities the operating expenses were thereafter
to be shared and (by s 9(e) of the operating agreement) the plaintiff was to be entitled to take and receive as
reimbursement for the defendant's share of the development expenses and its farm-in contributions threeeighths of the defendant's half share of the oil produced until the plaintiff had received a quantity equal to
125% in value of its farm-in contributions and half its initial investment in the oil field. Clause 6 of the
letter agreement provided that the defendant would not be personally liable to repay the sums advanced to
his account in accordance with s 9(e) of the operating agreement and that the plaintiff was to look for
reimbursement solely from the defendant's share of the oil. The main risk of failure in the combined
venture was therefore to be borne by the plaintiff and not the defendant. The plaintiff spent considerable
sums of money in exploration and development of the concession which proved extremely successful in
that recoverable oil in commercially worthwhile quantities was found and from July 1967 production
increased considerably. However, on 7 December 1971, following a revolution in Libya, the Libyan
government expropriated the plaintiff's half share in the concession and on 11 June 1973 it also
expropriated the defendant's half share. Both parties received inadequate compensation. The plaintiff
brought an action against the defendant alleging that the agreement had been frustrated on 7 December
1971 as a result of the expropriation by the Libyan government of the plaintiff's half share in the concession
and claiming, inter alia, such sums as the court considered just under s 1(3) of the Law Reform (Frustrated
Contracts) Act 1943 in respect of the benefit obtained by the defendant by reason of the plaintiff's
performance of the contract prior to its frustration. The defendant contended that the 1943 Act did not apply
because the contract was not governed by English law and had not been frustrated; alternatively he crossclaimed for an award under the 1943 Act.
Following interlocutory proceedings in which it was held that the contract was governed by English law,
the trial judge found that the contract had been frustrated and awarded the plaintiff two principal sums
($US15,575,823 and 8,922,060) under s 1(3) of the 1943 Act and interest thereon from 14 June 1974, the
date when the plaintiff made it clear to the defendant that it was going to bring a claim against him. The
judge rejected the defendant's claim under the 1943 Act.
The defendant appealed to the Court of Appeal, contending that cl 6 of the letter agreement absolved him
from liability to pay the plaintiff anything and that if he was liable the judge had assessed his liability on
the wrong basis and had ordered him to pay too much. By a cross-appeal, the plaintiff also challenged the
basis on which the judge made his assessment of the amount awarded. The Court of Appeal dismissed the
appeal and the cross-appeal holding that the plaintiff was entitled to be reimbursed under s 1(2) and (3) of
the 1943 Act.
The defendant appealed to the House of Lords, contending (i) that the terms of the contract, in particular cl
6 of the letter agreement and s 9(e) of the operating agreement, were intended to apply whether or not the
contract was frustrated and therefore under s 2(3) of the 1943 Act the operation of the Act was excluded by
the terms of the contract, (ii) that it would be unjust in the circumstances to make an award under the 1943
Act, (iii) that if the judge was right to make an award under the 1943 Act he was wrong to order in addition
the payment of interest on the sums awarded, because sums recoverable under the 1943 Act were not 'any
debt or damages' within s 3(1) of the Law Reform (Miscellaneous Provisions) Act 1934, and (iv) if interest
was to be awarded it ought not to have been ordered to be paid from 14 June 1974 but from the date the
amounts of the principal sums were assessed by the judge at the hearing, because before that date there was
no debt that could attract interest. In the House of Lords, the defendant conceded that the contract had been
frustrated on 7 December 1971 and, since it was governed by English law, that the rights and liabilities of
the parties to it depended on the application of the 1943 Act to the particular circumstances of the case.
Furthermore he conceded that, if the judge had been right to order him to pay the plaintiff any principal
sums at all, the sums ordered to be paid were not excessive.
Held: The appeal would be dismissed for the following reasons:
(1) There was nothing in the express terms of the contract, in particular in cl 6 of the letter agreement or s
9(e) of the operating agreement, or in the surrounding circumstances, to indicate that the parties when they
made the contract contemplated the frustration of it by political risks or that, having such risks in
contemplation, they included in the contract any provision which expressly or by necessary implication
took effect in the event of such risks materialising so as to make s 2(3) of the 1943 Act apply and thus make
it inconsistent with the provisions of the contract for the defendant to be ordered to make any payment
under that Act to the plaintiffs. Furthermore, there were no other circumstances in the case which would
make it unjust, within s 1(2) or (3) of the 1943 Act, to make such an award. It followed therefore that the
judge was entitled to make an award under the 1943 Act.
(2) The words 'any debt or damages' in s 3(1) of the 1934 Act, in the context in which they occurred, were
very wide and covered any sum of money which was recoverable by one party from another either at
common law or in equity or under a statute such as the 1943 Act. Accordingly the judge had power to order
the payment of interest on the principal sums awarded by him.
(3) There was no general rule that, whenever the amount of any debt or damages payable by one party to an
action to the other party could not be ascertained until judgment was given, the court could not, in the
exercise of its discretion, award interest from a date earlier than the date of judgment, since to apply such a
rule would be inconsistent with the express terms of s 3(1) of the 1934 Act, and in many cases, for example
in the case of a claim on a quantum meruit, would lead to serious injustice against a successful plaintiff.
Accordingly, since the judge had express power under s 3(1) to award interest from any date between the
date when the cause of action arose, ie 7 December 1971, when the contract was frustrated, and the date of
judgment, ie 30 June 1978, his decision to award interest from the date when the defendant first became
fully aware of the plaintiff's intention to bring a claim against him was an entirely proper exercise of his
discretion and, having exercised his discretion in that way, an appellate court could not interfere with it.