Rise
Rise
This thesis looks at how vertical shafts can be constructed in unstable soil and rock. It is intended that
it expands the scope of shaft construction by integrating many fields of expertise and looking at how
we can combine our experience.
Because I have an Australian background my search for a research project began there, to build
contacts and experience in the Australian environment. The thesis first got off the ground in november
2003 when Dr. Bamford of Melbourne University responded with the potential of projects
approaching the field of mining engineering. As the thesis progressed, it became apparent that Dr.
Bamford would always be extremely helpful anytime progress threatened to slow.
Through Dr. Bamford the Melbourne based company Australian Mining Consultants (AMC) were
involved, where Max Lee and Warren Peck proposed the wall-support problem for raise-boring.
Throughout the project Warren was a considerable help, ensuring consistent meetings and generously
supplying a lot of helpful data. Max was often out in the field, but because of this, his involvement
always guaranteed plenty of practical out-in-the-field problems and solutions.
In the Netherlands Bert Everts and professor van Tol were very supportive of the overseas project,
even though it did not always coincide with the research they are normally involved in. They assisted
in gaining financial support from the Kivi (The Royal Institution of Engineers in the Netherlands) and
in keeping me on track in the final stretch of the project. Dominique Ngan-Tillard, who was always
very busy, nevertheless always managed to make time for me. With her knowledge of rock mechanics
she was an important bridge between the overseas and local part of my research.
This research has shown that pre-reinforcement, blind hole drilling and remote excavation can all be
viable alternatives to conventional drilling and blasting. I hope that, as a result of my work, other
students may investigate these alternatives in more detail. More importantly, I hope that smart and
responsible mining companies will then be inclined to consider these alternatives.
My thanks go out to all those that have helped me with this work.
Preface
Preface
Contents
Preface
Contents
List of Figures
Index of Tables
Introduction
Document Structure
Abstract
1.Analysis of the raiseboring method
1
3
6
8
9
10
12
13
Introduction
History
Elements of a mine
Raiseboring & shaft sinking
Geological Conditions
AMC Consultants
Aim
Problems
Safety
Cost
Wall and back instability
Current limits
Non-entry method
Limited Diameter
Bottom-end access
Groundwater
Muck removal
Drilling versatility
Range of application
Mine ventilation and ore passes
Tunnel access shafts
Other applications
13
13
13
14
16
17
18
19
19
19
20
21
21
21
21
22
22
23
24
24
24
26
28
Introduction
Down-the-hole shaft sinking methods
Conventional drilling and blasting
Shaft-boring machine with mucking
V-mole with pilot-hole
Down-the-hole lining methods
Rock bolting and meshing
Cast-in-place lining
Forepoling or Boodex method
Pre-cast lining segments
Remote shaft sinking methods
Blind Hole Drilling
The Shaft-cutting machine (SCM) or Excavation
Remote lining methods
Floated pre-cast lining segments
Caisson sinking
Remote shotcreting
Raiseboring methods
Horadiam method
Pre-reinforcement for Raiseboring
Grout treatment
Grout mini-piles
Contents
28
29
29
30
31
32
32
32
32
33
34
34
36
37
37
37
39
40
40
42
42
44
Secant piles
Diaphragm walls
Freezing
Calyx drill
45
46
46
47
3.Assessment of methods
49
Varying geologies
Workers in shafts
49
52
54
Excavation mechanisms
Augering
Excavation
Caisson-style lining
Skin friction
Conclusion
54
54
54
55
55
56
57
Introduction
Description
Cuttings Removal
Lining
Cost
Limitations
57
58
59
60
61
62
65
Introduction
Drilling methods
Secant Piles
Jet grouting
Rotary percussive DTH-drilling
MUD-support
Dry-rock-drilling
Odex
Abrasive water-jet-cutting
Drilling Accuracy
Measuring and correcting deflections
The grouting process
The purpose of grouting
Quality of grouting
Grouting and groundwater
Grout flow
Grout wash
Hot bitumen grouting
Grouting and joints
Small joints
Filled joints
Hydrofracturing
Cavities and large fractures
Conclusion
65
66
66
66
67
67
68
68
69
70
70
73
73
73
76
76
76
77
78
78
79
79
80
80
7.Stability of shafts
84
Instability problems
Empirical methods for assessing shaft stability
The Q-System
Adaptations for raisebored shafts
Analytical methods for assessing shaft stability
Shaft in isotropic horizontal stress field (Lams Problem)
Shaft in anisotropic horizontal stress field (Kirsch Solution)
Wedge Analysis
Block Theory
Application to shafts
84
84
84
84
86
86
87
90
90
91
Preface
8.Results
Introduction
Reviewed methods
Guidelines for use
Conclusion
Recommendations for further research
Bibliography
Glossary
Appendix A Database of Shaft Construction Examples
Appendix B List of experts consulted
Contents
93
94
95
96
97
98
100
100
101
107
108
110
112
120
123
127
List of Figures
Figure 1 - Overview of the report
11
Figure 2 - The problem of wall instability encountered in soft soil/rock due to fractures and weathering,
during raiseboring.
12
Figure 3 Picture of typical mine development and its' elements
13
[Hartman & Mutmansky 2002]
13
Figure 4 Drilling and blasting a shaft
14
Figure 5 Overview of the raiseboring process.
15
Figure 6 - Sign near ventilation shafts in outback Australia. It shows one of the safety issues with
vertical shafts. It is also dangerous to work in shafts because of the chance of rockfall from
overhead
16
Figure 7 - The problem of wall instability that is encountered in soft soil/rock due to fracturing and
weakness of the strata. This is a typical Australian situation, but similar circumstances exist
in Scandinavia, South Africa and China.
17
Figure 8 - Fatalities in Metal and Non-metal mining in the U.S. [Courtesy MSHA]
19
Figure 9 - Looking down what was intended as a round ventilation shaft. Overbreak has occured along
two intersecting fracture planes.
20
Figure 10 - Diameter versus depth for existing drilled shafts [Bell 1988]
21
Figure 11 - Typical shaft dimensions and geological conditions for different shaft types. (Typical
minimum and maximum dimensions are shown in brackets)
25
Figure 12 - Overview of construction methods grouped by location and direction of the construction
activities.
28
Figure 13 Shaft sinking through conventional drilling and blasting
29
Figure 14 Shaft sinking with a shaft boring machine and mucking
30
Figure 15 Shaft sinking with a V-mole where
31
Figure 16 Tunnelling example of forepoling in fractured rock in Greece [courtesy of the Geoegineer
Website, D. Zekkos]
33
Figure 17 Typical drill patterns used for forepoling ahead of the face in a vertical shaft.
33
Figure 18 - Composite pre-cast liners ready for floating into a mud-filled shaft.
33
Figure 19 Large diameter blind hole drilling.
34
Figure 20 Shaft sinking with a shaft cutting machine (SCM) down the shaft and mucking.
36
Figure 21 Shaft sinking from the surface by excavation with a crane or boom.
36
Figure 22 - Boom type excavator used to build a tunnel entry shaft in Abu-Dhabi
36
Figure 23 - Composite pre-cast liners ready for floating into a mud-filled shaft.
37
Figure 24 - Jack-down lining performed by Marin through soft clays. Pipes used for lubrication and
grouting can be seen running along the outside of the lining
37
Figure 25 - Wall lining through sinking of a caisson - open front excavation
38
Figure 26 - Detail of fibrecrete nozzle
39
Figure 28 - Horadiam method
40
Figure 29 - Horadiam method
40
Figure 30 - Calyx drill
47
Figure 31 retrieved segment of core from calyx drill
47
Figure 33 - Headframe for shaft drilling
57
Figure 34 - Composite lining elements which will be welded together as they are floated into the shaft.
59
Figure 35 - Drill pipes and the airline-nozzle [left] which is lowered through the pipes.
59
Figure 36 - Detail of drill-pipe flanges and connection bolts. To transmit the drill torque and carry the
weight of pipes and cutterhead they are thick and are made from high-grade steel.
59
Figure 37 - Settling ponds for drilling mud
60
Figure 38 Measuring borehole deviation: azimuth and inclination.
70
Figure 39 - Deflection caused by hard, dipping layers known as 'rat-holing'
70
Figure 40 - Improved accuracy through multi-shot survey
71
Figure 41 Mechanisms of grouting for increasing stability
75
Figure 42 - Crosshole radar tomography to find flow paths
76
Figure 43 - Penetration of hot bitumen in water-filled joints.
77
Preface
List of Figures
Index of Tables
Table 1 - Overview of problems and limits in shaft construction
Table 2 Types of shaft that will be facilitated in this study, including typical shaft dimensions
Table 3 - Shaft sinking methods: Drilling and Blasting
Table 4 - Shaft sinking methods: Shaft Boring Machine
Table 5 - Shaft sinking methods: V-mole with pilot-hole
Table 6 - Shaft sinking methods: Blind Hole Drilling
Table 7 - Shaft sinking methods: shaft excavation and shaft cutting machines
Table 8 - Horadiam method
Table 9 - Pre-reinforcement: Grout treatment
Table 10 - Pre-reinforcement: Grout Mini-piles
Table 11 - Pre-reinforcement: Secant piles
Table 12 - Pre-reinforcement: Diaphragm walls
Table 13 - Local and economic factors that influence the shaft design method.
Table 14 (Hydro)geological and design parameters that influence shaft construction
Table 15 Level of safety of each construction method.
Table 16 - Blind Hole Drilling guidelines [Zeni 2004, Weber]
Table 17 - Secant pile guidelines [134. Herrenknecht AG.]
Table 18 - Rotary percussive DTH-hammer drilling guidelines [88. Roger Nylund, 2004]
Table 19 Odex drilling guidelines [62. Verfel 1989]
Table 20 - Guidelines for troubleshooting drilling accuracy problems. Solid bullets indicate survey
systems that are susceptibile to errors.
Table 21 - Rules to ensure effective grouting
Table 22 Ensuring the quality of grouting
Table 24 - Detecting and preventing problems with grout flow and grout wash
Table 25 Guidelines for grout penetration
Table 26 - Application of hydrofracturing
Preface
22
27
29
30
31
35
36
41
43
44
45
46
49
51
53
64
66
67
68
72
81
81
82
83
83
Introduction
Getting access to underground area's is a useful construction activity for many human activities. Each
year we use over 500 megatons of metals in our everyday life, which has all been mined from pits and
underground ore deposits sometimes as deep as 3000m. To gain access to these deep deposits requires
an efficient method of construction of vertical shafts to get there, to transport men and equipment, to
carry fresh air and to carry the ore out.
Besides mining we also use shafts to transport water through damsites, for transportation purposes
through tunnels in urban areas and to store chemical and radioactive waste. Research into shaft
construction has always been limited but is now becoming of increasing importance. Because ore
bodies are becoming depleted, shafts are being constructed ever deeper and in ever more challenging
geologies. Secondly, unsafe practices that endanger the lives of men working in shafts have become
unacceptable.
This research looks into ways of constructing vertical shafts in area's with soft and weak overburden
that have been uneconomical previously. The focus is on ways to reinforce soft soils and soft and
fractured rock. Without further treatment such geologies normally cause collapse of the shaft.
The research looks at construction methods within the confines of increased safety demands, low cost
and varying geology and hydrology.
During the research, no single obvious solution became apparent for reinforcing weak geologies.
However it became clear that there are a great number of different geologies which can each be
tackled with specifically tailored construction methods.
The result of this research is an insight and methodology for determining how to best construct shafts
in weak overburden. A decision schematic now allows mining and construction companies to take
informed decisions at an early stage. Expert experience, examples and literature have been used to
generate design criteria and quick-and-easy models.
Although it should be noted that detailed research and local experience is always necessary when
designing and constructing shafts, this report should reduce risks and help decide on optimal shaft
construction methods early on, prior to detailed design.
Introduction
Document Structure
This report is built up in a number of research stages.
In the first chapter, an analysis of the raiseboring method is given. The problems and limits of current
practice are analyzed and the aim of the research is set. The different types of shafts are identified
along with their demands on dimensions and stability.
Then the various methods of vertical shaft construction are researched. Current methods, innovations
and methods from other fields are investigated. This was done under guidance of Australian Mining
Consultants and Melbourne University. During this period in Australia an examples database was
started, and many experts were consulted in regard to their experience with shaft construction
methods.
In chapter three, the wide array of methods is assessed. To be able to do this, the geological conditions
that affect shaft construction are analysed. With these constraints in hand, the methods are evaluated
and three are identified for detailed research.
Chapter four describes methods of excavating relatively shallow shafts with continuous cutting
machines.
Chapter five details Blind Hole Drilling which is a method derived from oil-well type drilling. A site
visit was made in the Springvale shaft thanks to Zeni Drilling.
Chapter six looks into forms of pre-reinforcement. These are methods where lining or reinforcement is
constructed prior to excavation, such as grouting and diaphragm walls. This research was continued in
the Netherlands where the knowledge of deep foundations and geotechnical modeling is extensive.
In Chapter seven shaft stability is discussed, and also the way in which shaft stability is affected by the
different construction methods. Empirical and analytical methods are demonstrated so they can be
used to compare methods.
The concluding chapter presents a decision model for determining the best construction method in
varying geologies. Alongside this, recommendations for further research are presented. Furthermore
the experts consulted and the examples database are shown in the appendices.
The structure of the report is also given schematically in Figure 1.
10
Preface
3. Assessement of Methods
poor
Literature
Experts
Existing methods
Examples from
other fields
good
Abandon
Further Research
4. Shaft Cutting Machines
5. Blind Hole Drilling
6. Pre-reinforcing with piles
7. Methods for
evaluating stability
8. Expert System
Decision schematic
Examples database
Experts database
Conclusions
Introduction
11
Abstract
Minesites require ventilation shafts and ore passes to gain access to resources. As ore becomes
depleted, methods for constructing deeper and cheaper vertical shafts are required. Also, increasing
safety demands mean the risk of having workers down shafts is becoming unacceptable.
Raiseboring is a common method used to
create ventilation and ore shafts for secondary
mine openings. Lengths usually range from
200-800m, with diameters up to 7m.
The raiseboring process works by boring a
pilot hole to an existing horizontal shaft, were
a reamer is installed. This reamer is pulled
back up to the surface creating the shaft. The
method is efficient because clippings fall
down the shaft and can be left there or easily
collected. More importantly there are no men
down the shaft.
Raiseboring
machine
Shaft
5m
Problematic
weathered rock can
stand up only 1-3m
Soil/rock breaches
into borehole
In layers of soft soils or highly fractured rock, Figure 2 - The problem of wall instability
the raiseboring method becomes unsuitable.
encountered in soft soil/rock due to fractures and
weathering, during raiseboring.
The weathered rock caves into the hole,
jamming and possibly damaging the reamer,
sometimes even causing collapse of the entire shaft. This thesis looks into cost-effective and safe
methods of constructing ventilation shafts through weak rock.
Analyzing the potential methods has resulted in an impression of the suitability of each method in
different conditions. Three areas have been selected for further research.
Blind-hole drilling, with the shaft filled to the top with mud to stabilize the walls is a safe,
innovative method. However the method can be restricted in its application because of large
transportation and setup costs, limited thrust and problems with existing mine openings.
Remote shaft cutting machines (similar to road-headers) can be dropped into the shaft, or a
similar microtunneling machine or a boom-mounted cutter. A wide range of lining methods can be
applied to line the shaft as drilling progresses, of which the most suited are remote shotcreting,
floating in a lining and caisson sinking. This low-investment method may be suitable for
traversing the weak overburden, leaving the remainder of the shaft to be raisebored, but the
method is not suited to deep layers of weak rock.
At first glance grouting of a ring of mini-piles, or localised grouting in weak layers, is a method
with high potential as it enables raiseboring in most situations. However previous cases have
shown the method to be ineffective, with collapses both South African and Australian mineshafts.
Problem areas are i) inaccurate measurement and positioning of grout; ii) dispersion of grout due
to groundwater flow; iii) grout not getting into small clay-filled joints and escaping into wide
fractures.
The thesis concludes with a method diagram to assist mining companies in selecting suitable
construction methods at an early stage.
12
Preface
History
Elements of a mine
Mines are used to access and recover
ore bodies which are made into
minerals. Australia is a leading country
in the field of mining, recovering large
amounts of gold, copper, zinc, iron and
aluminium.
There are two main types of ore
access, open pit (or surface mining)
and underground mining. Open pit
mines are used where ore is near the
surface. Underground mines are used
to gain access to deep ore bodies, or
ore bodies where the surface mining
operation has depleted the ore reserves
near the surface.
Ore bodies with different properties,
are mined in different ways. The
development method used depends on
many factors: host rock strength, ore
strength, ore grade, thickness and
dipping angle of ore bodies, etc. In
longwall or stope and pillar mining
Figure 3 Picture of typical mine development and its' elements
large areas of ore are mined out
[Hartman & Mutmansky 2002]
underground, leaving walls or pillars
to support the overhang. In block caving, chunks of the ore body are collapsed into underground areas
using controlled blasting. The fragmented ore tumbles into the shafts where it can be hauled out. Cut
and fill stoping is used in near-verical ore-bodies that are susceptible to collapse. It is mined out in
layers and backfilled to support the overhanging rock, before moving to the next level.
13
Whichever method is used, underground mining requires vertical shafts. These shafts can have many
purposes. The primary shaft is usually large (6-12m diameter) and is used to get workers and
equipment into and out of the mine, for ore haulage and for utilities like electricity and water.
Generally the bottom level of the mine has some sort of ore transport system that brings the ore to the
primary shaft where it can be lifted to the surface. This is called the haulage level. By building 3-8m
diameter vertical shafts to this haulage level, ore can fall naturally down towards it and transported
further. These shafts are called ore passes.
Because of the heat from the earths core, deep underground mines can become very hot. This heat,
combined with moisture, makes working
conditions underground very harsh. To allow a
workforce to function effectively, cold and dry
air should be circulated through the mine. To
this end ventilation shafts are constructed to the
surface with big blowers to pump the air. This
also helps to remove hazardous dust or even
hazardous gasses from the drilling and blasting
of the ore bodies. Ventilation shafts and ore
passes should have a round, smooth surface to
reduce wall friction.
Sometimes extra secondary openings are
constructed as a mine develops, because it
becomes uneconomical to carry the ore all the
way to the primary haulage shaft. A second
haulage shaft is constructed near to new ore
bodies.
Because of the need for access openings, ore
passes and ventilation shafts, a safe and
economical method of vertical shaft
construction is a vital part of mine
development.
14
workers and equipment had to be hauled out of the hole before each blast. Conventional drilling and
blasting is still the most common method of shaft sinking used to date, although work is now carried
out from separate blasting and lining platforms.
Raiseboring
machine
RBM
Pilot hole
300mm
1
Pilot hole drilled to
depths of up to 1000m
Shaft
6000mm
Reamer is pulled
up and clippings
fall down shaft
Existing drift
Looking to optimize this process, mining engineers went in search of continuous machines to speed up
shaft sinking. This is where shaft boring and drilling came into practice. Shaft boring machines were
constructed, but these had problems in removing the cuttings. The tailings would clutter and thereby
damage the cutting head and haulage couldnt keep up with drilling. Also maintaining verticality with
a boring machine was an issue.
Later on the V-mole was designed which had the cuttings fall down a pilot-hole and used a sloped
cutting head to transport them away from the cutters. Because of the pilot-hole guiding it, the V-mole
was also easier to keep on the vertical. However the problem still remained of needing shaft access
underground to remove the cuttings. This led to the adaptation of drilling rigs from the oil industry. In
the beginning these rigs were limited in the torque and pressure they could apply to the cutting face,
and thus diameters were initially only small. This method is known as blind hole drilling or shaft
drilling.
Alongside the development of shaft boring machines, engineers had another growing concern, which
was mine safety. Looking for ways to get mine-workers out of dangerous shafts, raiseboring was
invented and developed into a successful technique between 1960 and 1970.
Raiseboring uses a small diameter drill rod, around 200-300mm, to drill a pilot hole down to the
required depth of the shaft which can be drilled up to around 1200m. The raiseboring technique
15
assumes there is already existing shaft access at the bottom of the shaft. Once the pilot hole has been
drilled to the desired depth, a reamer of up to 6m diameter is attached to the drill rod. The reamer is
then pulled back up to the surface, creating a round shaft. The pilot hole is used to let the clippings fall
down the shaft by means of gravity, where ore can be collected
and other rock can be used as backfill in old mine cavities.
The raiseboring technique has some major advantages
compared to traditional shaft sinking methods.
Safety. There are never any men down the shaft (except
to fit the reamer).
Speed. Because it is continuous and because muck
automatically falls down the shaft, speeds of up to
30m/day can be achieved.
Smooth. Because no blasting is used, the shaft walls
are very smooth. A smoother shaft is more stable, and
has less wall friction, making it ideal for ventilation
shafts.
Mainly because of the advantage in safety, raiseboring has become a popular method used around the
world. However there are some restrictions to its application which will be discussed in the next
section.
Geological Conditions
Australia has a very specific geology which is largely determined by the absence of a glacial period in
its history. This means the bedrock is commonly covered by a thick layer of overburden which has
been built up over as long as five million years. Deep weathering is common in the rock, leaving
highly fractured, deeply weathered zones. It is common for these most unstable zones to be just above
the bedrock as this is where most of the leaching and weathering through groundwater flow has taken
place. From an engineering point of view this leads to a difficult situation where the most unstable
layers are the hardest to get to.
In South Africa karstic (limestone) zones are common. Although overburden layers are not necessarily
as old, this leads to the same sort of situation where weathered zones (even entire cavities) can occur at
deep locations underground.
16
In practice it is not very practical to look at the geology of such large regions, as each site always has
its individual geology. However it is useful to understand such large scale differences in geology.
Take for example a tunnel access shaft to be constructed in urban areas. Typical of urban areas, such
as the Netherlands, is the close proximity of rivers and the coast. This means alluvial and fluvial
deposits cover any igenous or metamorphic rock. The behaviour of this geology is determined by soils
and clays which consist of individual particles low cohesion and high porosity compared to rock. Also
water levels can be much higher than in remote mining locations. It should be clear that this location
requires an entirely different
engineering approach.
AMC Consultants
Max Lee and Warren Peck of AMC
Consultants Pty Ltd have supervised
this thesis, helping out with advice
and supplying case examples where
possible. AMC is well known in
Australia for providing a broad range
of Mining Engineering,
Geotechnical, Geological and
Corporate consulting services to the
exploration, mining and financial
services industries.
Raiseboring
machine
40-80m
soft,
deeply
weathered
rock.
Problematic
weathered rock can
stand up only 2-3m.
Soil/rock breaches
into borehole
Shaft
AMC has an international customer
6000mm
base and the scope of their work
includes engineering, ore reserves,
feasibility studies, due diligence
project reviews, valuation of
Figure 7 - The problem of wall instability that is encountered in
soft soil/rock due to fracturing and weakness of the strata. This is a
companies and projects, technical
typical Australian situation, but similar circumstances exist in
research and advice to management. Scandinavia, South Africa and China.
AMC maintains a policy of
independence from exploration and mining interests and complete confidentiality of client
information. Extensive records of mining costs, performances and productivities are maintained as a
basis for engineering, due diligence and feasibility studies.
AMC agreed to support this research thesis looking at stability problems encountered during the
raiseboring of shafts. AMC invited me to use a civil engineering approach, applying any experience
from foundation engineering, tunnelling and off-shore around the world that might seem useful.
17
Aim
During the construction of raiseboring shafts in Australia, problems have been encountered because of
the thick layer of overburden. Because there is no possible access to the shaft beneath the reamer, it is
not possible to immediately construct a lining. When the reamer passes through the weathered zone,
both the back of rock above the raiseborer, as well as the walls, become unstable and slip into the
reaming zone. The instability is due to either low strength of the overburden, extensive jointing or
both.
This causes many problems:
Overbreak along the shaft wall, which will later require grouting and rockbolting.
Jamming and potential destruction of the reaming head.
Breakage of the drill rods and loss of the reaming head.
Deformations at the surface and even entire collapse of the shaft.
This thesis will look at solving the problem of wall and back instability during raiseboring.
Thesis aim:
Find a cost-effective and safe method for construction of raisebored shafts through
low strength and/or highly-fractured overburden.
During exploration of methods that are currently in use around the world it will become clear that
raiseboring may not be the single solution for contruction vertical shafts. The scope of research will
include other methods that may be more effective than raiseboring.
In the following section the problems any construction method should overcome will be discussed
any new methods or adaptations should overcome these problems.
Besides the stability of the walls, there are other limits which currently apply to current raiseboring
practice; if the range of these restrictions can also be widened, new shafts may become feasible along
the way.
18
Problems
Safety
Safety is an important issue in mining. Figure 8 from the Mine Safety and Health Administration of
the United States shows how fatalities in mining have continously been reduced. Australian mining
shows a similar trend with less than ten fatalities a year, and is quickly pushing to the forefront of
mining safety.
Unfortunately vertical shafts are one of the most dangerous places of a minesite.
This can best be illustrated by the simple words of an experienced geologist :
People fall in them
Tools and rocks fall down them, on top of the people in them.
The great advantage of the raiseboring method is its high level of safety.
During raiseboring the only time men are actually in the shaft is for changing the reamer or bits on the
reamer. This mine access is always planned carefully, and prevented altogether whenever possible (for
example by using extra long life bits that prevent having to change the reamer during the raise).
Any devised construction alternative will ideally prevent any need to have mineworkers in the shafts,
as with current raiseboring practice. This is referred to as remote construction.
Also a mechanical drilling method, that does not make use of blasting, is preferred. This is because
there is no sudden impact and because the excavation is smoother and thus inherently more stable.
Figure 8 - Fatalities in Metal and Non-metal mining in the U.S. [Courtesy MSHA]
Cost
The construction of the vertical shaft must be cheap. Civil engineering practice is generally aimed at
long-term structures for urban zones; mining engineering however, has a more remote, low-cost and
19
temporary character. This means elaborate civil engineering solutions quickly become too expensive
for mining. On the other hand the remoteness of minig locations means excessive deformations are
rarely a problem, unlike in civil engineering practice.
Low cost is a vital key to a successful construction method.
Generally this means using low-cost machines that are re-usable and easy to set up. Shaft boring
machines and V-moles, as we will see later, are typically high-investment machines usually not suited
to simple shafts in remote locations.
In the majority of cases, high construction costs are a consequence of :
high capital investments with long periods till payback
the large amount of labour involved
Therefore an automated, continuous process with a high development rate is essential to cutting costs.
In all potential solutions the penetration rate forms a key indicator of the total shaft cost.
Not only the walls, but also the back (the overburden above the reamer, also referred to as crest or
crown) can become unstable. This can sometimes be prevented by maintaining constant pressure on
the back by keeping the reamer close to the back.
There are generally two reasons for instabilities: The first is the presence of incohesive and weak
material like running sands, clays and deeply weathered soft rock. The other is instability due to
intensive jointing and fracturing, sometimes made worse by water pressure or soft filling (such as clay
gouge) in the joints.
20
These instability problems should be addressed. Bartons Q-system [90. Barton 1974] will be used
incorporating stress reduction factor (SRS) [91. Kirsten 1984] can be used to test stability of the back
(or crest) and walls. Several adaptations for vertical shafts in raise boring [89. McCracken 1996] will
be adopted.
Current limits
Non-entry method
The shaft under the raiseborer cannot be accessed, because of the instable walls and back overhanging
the shaft. In some areas, where the rock has some standup-time, the raiseborer is quickly pulled to the
surface. Even then no workmen can access the shaft because it is unstable. In this case the shaft is first
lined by using a remote fibrecreting machine dropped into the shaft. Because estimating timedependant behaviour is a very unpredictable task, remote fibrecreting can be a dangerous exercise if
the stand-up time is critical.
A method of construction that prevents the necessity for having men in the shaft, like raiseboring,
greatly increase it's level of safety.
Limited Diameter
The maximum diameter that can be
drilled in one pass is determined
mainly by the drilling torque and
the face pressure that can be
applied to the reaming head.
Torque and pressure are in turn
limited by the bearing capacity of
the drill rods. Because reaming is
directed upwards, the weight of the
reamer and drill rods works
adversely, limiting raiseboring
diameters to a maximum of around
7m. Such dimensions would be
done in two or even three stages.
Figure 10 - Diameter versus depth for existing drilled shafts [Bell 1988]
There are some cases where it useful to create shafts with larger dimensions such as when shafts are
used as ore-passes or access shafts. Generally 3-4m is a comfortable diameter for most ventilation
shafts, but with greater depths larger diameter ventilation shafts will be needed. South African mines
at depths over 1000m already require ventilation shafts of 6 m diameter.
Bottom-end access
To attach the reamer to the drill rods at the bottom of the shaft, there must be an existing drift to get to
the foot of the shaft. This, in combination with the restricted diameter, is why raiseboring is generally
used for ventilation shafts or ore-passes, rather than primary mine openings. Although for the purposes
21
of this study, underground access is assumed, shaft sinking methods from the surface would have
added value over raiseboring
Table 1 - Overview of problems and limits in shaft construction
Groundwater
A ventilation shaft should generally be kept relatively dry. In most situations in Australia, the watertable is generally very low (-50m or a few meters above bedrock) and it is also highly saline. On one
hand this means construction of the shaft may be easier; limited flows can easily be pumped from the
shaft. On the other hand it rules out some construction methods such as ground freezing. Dry rock
cannot be frozen, and high flow rates which inhibit freezing result from raising the water table.
Also high flow rates are encountered around many bedrock zones because of pumping activities
around existing mines or aquifers. In this case flow rates may be so high that it is not possible to pump
the shaft dry. In such cases it would be useful to find a construction method that also limits the flow of
water into the shaft. Ventilation shafts should be kept especially dry because a moist shaft supplies
humid air that greatly affects the climate in the shafts.
It should also be noted that high water inflows through joints greatly affect the stability of the rock
mass. In general it would be useful to find construction alternatives that can not only be used with a
low groundwater table, but also in unfavourable conditions like high groundwater flow rates or a high
water heads.
Muck removal
Raiseboring uses gravity to remove the drill cuttings from the shaft. Once down the bottom of the
shaft, the conventional mining equipment (used for mining the ore) can be used to remove the muck.
This is a common and efficient practice for raiseboring, however in some alternate methods muck
removal is often the single factor limiting progress.
22
Drilling versatility
Raiseboring allows accurate drilling up to around 45 degrees, depending on how easily the muck
passes through the shaft, and it allows drilling from within a shaft with limited headroom. A
raiseboring machine can be used many times with different reaming heads in varying diamters and
geologies. Any alternate methods should attempt to maintain this versatile nature of raiseboring.
23
Range of application
Mine ventilation and ore passes
To assess the different methods, the typical case AMC and other mining companies in Australia are
interested in, will be described below. This is a common weak-overburden shaft that might be
required for mining in Australia. A typical ventilation shaft would require a diameter of around three
metres, however increasing depths of mining require increasingly large ventilation shafts.
Also ore-passes, although less common, would require larger diameters over 5m. Open cut or
conventional drill and blast are generally used on shallow shafts up to 100m. Most shafts built today
are up to 500m length, with problems of high temperature and long haulage distances for deeper
shafts. Although uncommon, depths up to 1000m are considered because of the need to access
deepening ore-bodies.
It is hard to describe overburden because of the multitude of rock conditions that can be encountered.
In Australian minesites the thickness of the overburden generally ranges between 30 to 100m, with
problem areas consisting of highly weathered sandstones and mudstones, slates and shales, extremely
weathered granidiorites, etc. Also several layers of quartzite veining are taken into account as it is not
uncommon for hard, abrasive layers to intercept weaker ones causing problems with cutter or drill bit
wear.
In Australia because of existing mine-workings the groundwater table is generally very low. Existing
mine activity usually implies water is already
being pumped leading to high
groundwater flow rates. Also the groundwater is typically highly saline which affects freezing and
grouting characteristics.
The range of situations in mining, with the most typical dimensions in bold, are given on the left side
of Figure 11. Ventilation shafts and ore passes are not the only application for vertical shafts. Other
applications will also be considered in the scope of this project. However differing applications also
have different requirements.
Primary shafts for mine access are similar to ventilation shafts for mining, but much larger in
diameter. They cannot be raisebored because there is no bottom-end access to the shaft, and alternative
methods are required.
24
Because of the long life of tunnels and the large number of people that use them, they should be much
less susceptable to leakage, damage and collapse, also in the long term.
Except for mountain-passes, tunnels are generally be built in densely populated urban areas. This
means surrounding structures can easily be damaged by deformations, leading to tight limits for
surface deformation. Also it is common for urban areas to have developed in alluvial or coastal
deposits, leading to a sedimentary lithology consisting of clay, peat and sand rather than rock. In this
case the water table is usually near the surface and pumping is limited or prohibited completely. This
is a typical situation in the Netherlands.
Ventilation shafts
Ore passes
Mine access shafts
Penstocks
Waste disposal
Water treatment
Overburden
50m
(30-100m)
Ventilation
Shafts
3m
(1,5 - 6m)
Total length
300m
(100-1000m)
Overburden
Slates, shales,
Highly weathered
sandstones and
siltstone,
Total length
50m
(20-200m)
Shaft
2m
(1-3m)
Fluvial deposits
Soft to medium
clays and peats,
medium sands
Shaft
10m
(5-20m)
Fluvial
deposits
20m
(0-50m)
Total length
30m
(10-50m)
Metamorphic layer
Dense sands.
Very stiff clay
Bedrock
SW-MW
Basalts/
Requires
Granites robust and
impermeable
lining
Rock with
impermeabilities/
jointing
Ore passes
5m
(3-7m)
Access
shafts
7m
(5-10m)
Figure 11 - Typical shaft dimensions and geological conditions for different shaft types. (Typical minimum and
maximum dimensions are shown in brackets)
25
The dimensions of tunnel access shafts also differ from mineshafts. From a cost perspective a tunnel
will be constructed as close to the surface as possible, leading to shaft lengths of 50 metres at most, but
more commonly around 20 metres. The diameter required for safely evacuating commuters in a tunnel,
or allowing access for emergency workers is generally much greater than for mineshafts, ranging from
anywhere between 5-20 metres. Tunnel access shafts that are longer than they are deep have wall
support systems based on resistence of the toe of the wall (such as sheet piles) hence these shafts will
not be discussed in this thesis. TBM entry and exit shafts will not be discussed because of the length
required to fit the machine is much greater than the depth. The specifics of the tunnel access shafts that
wil be discussed are shown on the right in Figure 11.
Other applications
Penstocks are shafts used for discharging water through dams. Mostly a turbine will be constructed in
the shaft for generating hydro-electric power, but penstocks also exist simply for redistribution of
water. Penstocks are generally around two metres in diameter and between 20-200m long, depending
on the distance the water should travel. Again raiseboring is a useful alternative as bottom-end access
is available (at the bottom side of the dam) and because a smooth, round shaft is created, reducing
friction. Penstocks should always be lined because they should be impermeable and they should be
able to withstand the high water pressures.
Similar to penstocks are wastewater treatment shafts and chemical and radioactive waste disposal
plants. For these shafts a safe, impermeable lining is vital. Also sufficient depth is important for the
filtration of wastewater in the case of treatment shafts, and to prevent chemical or radioactive waste
from affecting surface soil and groundwater in waste disposal shafts. Penstocks, wastewaer and waste
disposal shafts are also shown in Figure 11.
A few very specific shafts have been constructed for special needs. For example to access the
underground Superconducting Super Collider in Texas. Shafts were constructed up to around 80m
depth in both small and large diameters (up to 20m).
Shafts that will not be included in the scope of this research are water wells, sewer shafts and shafts
for extracting geothermal power. These shafts are generally small in diameter (and remain unlined)
and are drilled with efficient technologies driven by the oil industry.
Some foundations for very large civil engineering jobs such as coastal bridges and off-shore platforms
also use shaft drilling technology. Although drilling methods are sometimes similar, the purpose is
entirely different. Foundation shafts are designed solely to transfer immense vertical and horizontal
stresses to the subsurface and not for gaining access to deep locations. These shafts will not be
considered in this study.
26
Table 2 Types of shaft that will be facilitated in this study, including typical shaft dimensions
Shaft type
Main demands
Diam.
Depths
Scope of work
Mining ventilation
3
(1,5-6)
300
(50-1500)
Primary scope
5
(3-7)
300
(50-1500)
Secondary scope
7
(5-10)
300
(50-1500)
Secondary scope
Penstocks
Narrow, smooth,
impervious
2
(1-3)
50
(20-200)
Secondary scope
Chemical/ radioactive
waste dumps
Deep, totally
impervious
2
(1-3)
100
(20-300)
Secondary scope
Water-treatment shafts
Impervious, deep
2
(1-3)
50
(20-100)
Secondary scope
Shallow, large,
impervious, safe,
little deformations
10
(5-20)
20
(10-50)
Secondary scope
Access to supercollider
Impervious, safe
7
(5-10)
50
(40-80)
Secondary scope
Impervious, deep,
narrow
0.8
(0.5-1)
40
(20-200)
Secondary scope
Horizontal, little
deformations, safe,
impervious
1.2
(1-3)
(5-5000)
Outside scope:
Horizontal drilling is
well developed.
Bearing of loads
1.4
(0.6-2)
30
(10-60)
Water pits
Very narrow,
pervious, cheap
0.3
(0.1-1)
30
(8-350)
Outside scope:
Tiny diameter has
different mechanics
27
Shaft Construction
Down-the-hole
construction
Drilling & Blasting
Shaft Boring Machine
V-Mole
Remote
Construction
Blind Hole Drilling
Shaft Cutting Machine
Shaft Excavation
Post-reinforcement
Rock-bolting/meshing
Cast-in-place lining
Pre-cast lining segments
Forepoling (or Boodex)
Raiseboring
Raiseboring
Horadiam method
Excavation
methods
Pre-reinforcement
Grout minipiles
Grout treatment
Secant piles
Diaphragm walls
Freezing
Wall support
methods
Figure 12 - Overview of construction methods grouped by location and direction of the construction activities.
28
Drilling and
charging
Blasting
Mucking
Disadvantages
Examples
Range of application
Key Aspects
Alternative applications
gedefinieerd.
29
Sinking of
entry-shaft for
SBM assembly
boring
mucking
30
Drilling of Sinking of
pilot hole entry-shaft
Assembly of
V-mole and
boring
gedefinieerd.
31
Cast-in-place lining
It is possible to cast concrete rings as the shaft sink progresses. This is commonly done in combination
with a V-mole or shaft boring machine. Generally temporary rock bolts and mesh are still required
close to the cutting head. Then, on a second floor of the shaft boring machine, an L-shaped casing is
positioned which is then filled from a hose transporting concrete from a surface plant. This method
provides a smooth, watertight and permanent lining for the shaft. The casing can be reinforced to cope
with horizontal stresses (i.e. ring-shaped reinforcement) making the casing elements more economical,
and in this case the reinforcement is well protected by the concrete. Some attention should be given to
connecting the elements with rubber profiles to prevent water inflows.
Unfortunately this method is discontinuous, with many men down the hole. The safety of the workmen
is usually fair because they generally work under the cover of the shaft boring machine cage. Also the
robustness of the lining system means there is practically no chance of rock-fall or collapse from
above. The first metres of lining are the most unsafe in their application.
This method has been used a number of times in Europe, in combination with an SBM or V-mole. The
Lummerschied shaft [Haas & Schneider, 1991] in west Germany was safely enlarged to a diameter of
8,2m.
32
In the case of Soilmec, the method uses Tubex technology to drill a ring of piles about 12 metres long
at a slight incline around the tunnel face. The ring formes an umbrella to support the next nine metres
of shaft excavation, before a new ring of piles was installed. The
method is slow because of the many piles that need to be
consecutively driven, resulting in only 15-20 m a week. However it
does form a safe barrier ahead of the excavation process for workers
to operate more safely.
The method described
above is typical for
tunnelling, but has also
been used vertically for
shaft drilling. The
limited length of piles
means the forepoling
or Boodex machine has
to be used from within
the shaft along with
conventional drilling
and blasting or
mechanical excavation
for the removing rock
and soil.
gedefinieerd.
33
34
system, a spinning disk to apply shotcrete, developments by a company called Jetcrete have produced
impressive results. [L. Newnham, R.O.C., 2003]
Table 6 - Shaft sinking methods: Blind Hole Drilling
Disadvantages
Examples
Range of
application
Key Aspects
Adaptations
gedefinieerd.
35
Shaft
cutting
mucking
Shaft
cutting
excavation
Examples
Range of application
Key Aspects
Adaptations
36
+ semi-continuous operation
+ quick and effective
- restricted depth and rock strength
- potentially workmen are required in the shaft for excavation,
cuttings loading and haulage
Supercollider, USA (Atlas Excavation Inc, USA)
CANADA (Montala)
Tas, AUS. (Mancala)
Short shafts or pre-sinks (d<25m)
Soft soil/rock <4 UCS
Speed of mucking
With (hydro)fraise, higher rock strength can be excavated
Excavation mounted on the lining (Alimak-style) with
excavation/lining stages
From the shaft bottom with a road-header type excavator
Caisson sinking
Wall elements that are smaller than the shaft diameter can be dropped into the shaft as it progresses, or
upon completion. However, this means the shaft must be supported by mesh or drilling fluids during
construction. As an alternative, it may be possible in the future, to push down a lining as work
progresses, in combination with shaft excavation, and only lubricate behind the shaft wall.
Wall elements are added from the top avoiding the
need for any workers down the shaft, and providing
easy access to the work. A slipform lining can be
used, allowing a continuous poor of concrete, or
pre-cast elements can be added piece by piece.
Horizontal rings of reinforcement can easily be
installed to withstand horizontal pressures. Because
the horizontal pressures increase as the shaft goes
down, the amount of reinforcement can be scaled to
the expected loads.
However, as the hole deepens, wall friction will
continuously increase, until the casing will not slide
down any further. A raisebore-style machine with
an anchored foundation plate should be used to jack
the lining downwards. Even so, the friction at
greater depth will determine the potential of this
method. By undercutting the shaft, the toe friction
gedefinieerd.
37
can be overcome, and by excavating a slightly larger diameter than the final lining, the contact friction
along the outside of the lining can also be reduced. In rocky geologies the excavation will cause some
relaxation of the overburden and this may push against the lining with considerable pressures. This is
the main problem involved in jacking the lining.
To solve this, some additional measures may be applied:
Use of mud or drilling fluid to lubricate between the
shaft wall and rock.
Use of a series of steel cables that are unrolled from
the bottom of the shaft as it proceeds downwards.
[van Dijk, Almeraris & Rice, 2001]
Use of waterjets to decrease effective stress,
lubricate the wall and push aside any obstructions.
In soils the additional problem arises of a blow-out into
the shaft bottom or high water inflows through water
bearing strata. Some form of closed shield needs to be
devised to prevent this.
Figure 25 - Wall lining through sinking of a
caisson - open front excavation
38
Remote shotcreting
gedefinieerd.
39
Raiseboring methods
The raiseboring method requires drilling of a small diameter pilot hole to the required depth. In the
second stage a reamer is attached and drawn back to the surface. Because it is not possible to apply
any wall support beneath the reamer, raiseboring requires special adaptations in unstable overburden.
The group of remote lining operations that can be carried out from the surface before drilling starts
will be referred to as pre-reinforcement. In many cases, such as freezing, a more permanent lining may
also be needed.
Raiseboring can only be carried out through unstable overburden, if pre-reinforcement is applied or if
another method is used to create a pre-sink through the weathered portion of the raise. Alternatively
the more risky horadiam method may be used.
Horadiam method
The Horadiam method is a specific method that is used in Western Australia where the top layer
consists of silcrete. This soil type is partially cemented and thereby very stable compared to layers
beneath it.
The method works by first drilling a small pilot hole and using a raiseboring machine to ream it out to
the maximum stable diameter. This usually means the hole is drilled out to the full diameter through
stable rock, and that drilling is stopped for the instable areas near the surface. For this area, one of two
methods may be applied:
An Alimak climber is installed from below. This machine can climb up to the crest from below along a
steel monorail that is installed as work progresses. It is a very dangerous method because workmen in
the Alimak are always working beneath an open rock face. As work progresses rock bolts and mesh
are applied to stabilise the shaft. Because of the pilot hole there is space for rock to expand on blasting
this makes the blasting process quick and less destructive.
The slightly safer method is to perform stepwise-benching from above. Workers are lowered into the
shaft on a working platform and drill and blast holes into the areas of the shaft that need to be
enlarged. Again the expansion space of the pilot hole makes blasting light and easy. After blasting
workers are again lowered into the shaft to apply mesh and rock-bolting or shotcrete.
Drilling of Raise
Pilot Hole Boring
Stepwise benching
(Drilling, blasting
& reinforcing)
40
Drilling of Raise
Pilot Hole Boring
Alimak raising
(Drilling, blasting &
reinforcing)
The Horadiam method creates an unsafe scenario for workmen for the last portion of the shaft, and
also provides a rougher final shaft. Nevertheless this method is popular in Western Australia because
raiseboring can be applied efficiently through most of the shaft and the unstable area's tackled
conventionally. Also shafts can easily be made larger in diameter than with simply raiseboring.
In Stawell a similar method was used where a small, stable hole was grouted after construction. In this
way, grout penetrates around the hole and thereby stabilises it.
In stages the hole was enlarged and grouted again, until the final diameter was achieved.
Unfortunately both these methods are limited to area's where the soil or rock has some stability (the
small diameters are stable) and some standup time (the time it takes to apply mesh, rock-bolting and/or
shotcrete after each blast)
Table 8 - Horadiam method
Horadiam method
Advantages
Disadvantages
Examples
Range of application
Key Aspects
Adaptations
gedefinieerd.
41
42
Grout Mini-piles
Advantages
Disadvantages
Examples
Range of application
Key Aspects
Adaptations
+ allows raiseboring
+ quick and effective
- limited depth
- questionable effect on stability
- no-way-back method
Longos Gold Mine, Paracale, PHILIPPINES (Multi-urethanes)
Freestate, S.A. (Rodio)
Fractured and weathered rock, with unfilled or open joints
Areas with low-moderate groundwater flow rates
Drilling accuracy: good initial survey, calibrated surveying tools
Good grout penetration: suitable joints, quality control
Limiting grout wash: avoid high-pressure aquifers, groundwater flows
Navi-drill can be used for more accurate drilling
Grout types: cement, ultrafine cement, chemical grouts. polyurethanes
Reducing flow: fast-setting grouts, hot bitumen, water relief holes
gedefinieerd.
43
Grout mini-piles
A different form of grouting is where a concentric ring of mini-piles is constructed around the shaft
perimeter. This method is suited to areas where the rock stability is determined by jointing rather than
weathering. The grout columns intersect potential shear planes and the reinforcement keeps the planes
together. It is not intended that grout penetrates the joints to any considerable depth, so it is imply
poured into the bottom of the hole.
This method has been applied succesfully in Golden Grove in Western Australia, however in the
Callie mine, drilling accuracy was questionable hence the shaft was sunk conventionally and not
raisebored.
Table 10 - Pre-reinforcement: Grout Mini-piles
Grout Mini-piles
Advantages
Disadvantages
Examples
Range of application
Key Aspects
Adaptations
44
+ allows raiseboring
+ quick and effective
- limited depth
- questionable effect on stability
- no-way-back method
Callie, AUS
Golden Grove, AUS (Bachy)
Fractured but not soft rock
Areas with low groundwater flow rates
Piling Accuracy: good initial survey, calibrated surveying tools
Avoid reamer damage: User armoured grouts, not steel drill rods
Navi-drill can be used for more accurate drilling
Fibreglass armoured grouts instead of reinforcement
Secant piles
Down to limited depths, interconnecting columns can close groundwater flows and stop soft clays and
running sands from collapsing. They can be construted through jet-grouting or auger drilling a circular
pile wall.
Auger drilling is possible up to about 25m because greater depths jam the auger and may also lead to
such deflections that the secant piles no longer overlap. Roch strengths up to approximately 2MPa can
be tackled using the auger drill. Piles can be supported with fluid or a casing and filled with concrete
or mix-in-place additives.
Oscillating Cassagrande type piles can reach depths of roughly 35 metres where a hydrofraise is
used for stiff clays, soft rock and boulders. To be able to drill secant piles, bentonite fluid should be
used instead of casing, which means the method approaches that of diaphragm walls.
gedefinieerd.
45
Diaphragm walls
Diaphragm walls are constructed by digging rectangular trenches under support of bentonite fluild
using a large mucking crane or hydrofraise. In the case of shaft sinking the diaphragm walls are
constructed before raiseboring in several segements around the perimeter of the proposed shaft. Often
round casagrande piles are first excavated at the segment intersection to function as guides for the
excavation proces.
The method is only useful for large diameters, because otherwise the volume of drilling mud is greater
than for simply blind hole boring. A simple volume criterion can be used to see if a slurry trench can
be useful, for example assuming a thickness of 0.8m of the diaphragm wall and a distance of 0.8m
outside the shaft perimeter, a diaphragm wall uses less bentonite fluid at diameters of about 5m or
greater. [137. Puller 2003]
It should also be noted that diaphragm walls form the danger of blow-out when constructed near to
existing mine workings, or areas with large underground cavities.
Table 12 - Pre-reinforcement: Diaphragm walls
Diaphragm walls
Advantages
Disadvantages
Examples
Range of application
Key Aspects
Adaptations
Freezing
Instead of creating a grout curtain wall, an freezing provides an alternative method to harden the
ground. This is common practice in Germany, North America and Canada. The primary factor
affecting ground freezing is the speed of groundwater flow. Other factors are water temperature and
salinity of the groundwater. Groundwater flows are usually limited in greenfield sites, but existing
mine developments usually have some form of groundwater pumping in effect. Because of the heat
transport that accompanies groundwater flow, it will cost extra time to freeze the groundwater, and it
may even be impossible to create a complete ice curtain.
The problem with groundwater flow is increased if the groundwater table is very low. To create a
frozen curtain wall at low depths, the groundwater table should be raised. Unfortunately the raising of
46
the groundwater table implies groundwater flows away from the shaft, making freezing difficult. The
flow rate may be limited in soil strata because of the large amount of pore space partial saturation
will be enough to strengthen the soil. In fractured rocks full saturation will be required, and pumping
will induce high flow velocities, making freezing impossible.
The accuracy needed for freezing is lower than for grouting, because the ice wall spreads around the
drill pipes. Accuracies of 1,5 %, achievable by good drilling contractors, are sufficient for around 50m
depth. For depths greater than 100m, steerable Navi-drilling technologies are used to achieve the
desired accuracy.
Installation of piles around a 4m diameter shaft to 100m depth with approximately still groundwater
would take around 10-15 weeks for freezing, plus 5-10 additional weeks required for raiseboring and
permanent lining. [Freezewall Inc., 2004]
The freezing operation can reduce the effectiveness of
raiseboring as soft soils become hard because of the ice
formation. This results in low penetration rates and excessive
cutter wear. Frozen clays resulted in 50% greater torque required
than through shales and gypsum. Ice formation along the walls
of the pilot hole can inhibit the movement of the drill rods within
the pilot hole. Warm air blown through the annulus to melt the
ice along this surface along with scraping off by rotating and
reaming the drill strings can prevent this buildup, but slows the
drilling process. [87. Walsh 1991]
Calyx drill
For small shaft diameters up to 3 metres, doublewalled core-drills or calyx-drills have been
developed and used that are even suited to mediumhard rock. These use mud flushing through the
annulus and mud between the shaft and the wall for
added lubrication. The drill excavates a hollow core
leaving much the same result as with blind hole
drilling, but with significantly less energy.
Only one company is known to date that produces
this size core-drill.
gedefinieerd.
47
3. Assessment of methods
Varying geologies
At first it was assumed a solution was necessary to extend the possibilities of raiseboring through
instable overburden. However, on examining this method, a fundamental problem with raiseboring
presents itself: the shaft is constructed bottom-up. This severely limits the potential of raiseboring.
Firstly, only shafts with bottom-end access can be constructed. This is not always available, for
example when creating primary access shafts or when a tunnel or adit is not ready in time for the shaft.
However this is not the biggest issue that is raised by bottom-up construction.
More importantly, it makes many construction methods used to stabilise the shaft impossible. When
progressing downwards, drilling muds, shaft lining, mesh and bolting, fibrecreting and so forth can be
used. Bottom-up construction doesn't allow access to the shaft to apply any of these methods. This is
why, when looking at constructing shafts through unstable overburden, the scope has been expanded
to allow for top-down construction.
Table 13 - Local and economic factors that influence the shaft design method.
Influence on design
- design choices
Remoteness of location
Legislation
It would be a severe shortfall if blind drilling and mechanical excavation methods were excluded from
the possible set of solutions simply because they are not raiseboring.It should be made clear that many
different methods are plausible, but that it depends on many factors, which solution is optimal. While
looking at the methods used the factors that determine if a method is effective, have been noted. These
factors are shown in Table 13. Where possible, tests are indicated which may be used to quantify
them.
49
Besides conditions implied by design or geology, some conditions are enforced by local and economic
factors. These may be implied by government, by the availability of equipment and the attitude of
mining companies and contractors. They are listed in Table 14.
50
SYMBOL
UNIT
TEST
NOTES ON TESTING
Triaxial
Abrasion test
Siever's miniature drill
test
Geological conditions
Rock Drillability
-Unc. Compressive Strength
-Abrasion Value
-Siever's J-Value
UCS
AV
SJ
MPa
-
DRI
Rock penetrability
-Sand density or clay plasticity
-Presence of rock/gravel/boulders
Dr / PI
kN/m
CPT/SPT
Rock/soil stability
-Degree of weathering
-Unc. Compressive Strength
-Cohesion [soils]
-Tensile strength [rock]
UCS
c
q;u
[I-V]
MPa
MPa
MPa
- Soil/rock elasticity
MPa
Triaxial,
Seismic velocity
Rock fracturing
-Number of joints
J;n
Core samples,
Seismic velocity/amp
J;r
J;a
SRF
-Joint roughness
-Joint alteration i.e. filling
-Dip angle of shear zones/ in situ
stresses/ intersecting joint sets
-Depth of weak
layers/overburden
-Sensitivity to alteration
Related to
UCS/Abrasion
[78 Goodman]
CCBO Overcoring,
Hydraulic fracturing
1,3
MPa
C;v
q
Lugeon
m/s
wireline in borehole
Core samples,
thermal capacity
Packer test
2 borings with tracer
ppm
borehole sample
Design parameters
Diameter
Total depth
Shaft smoothness
Shaft inclination and azimuth
Access to bottom of shaft
Possible alternate locations
D
d
D
m
m
mm
Accepted size of
overbreak (i.e. for
laminar flow)
degrees
[y/n]
51
Workers in shafts
The initative to this work was the demand for a safe method of shaft construction through unstable
geologies. Of all safety aspects, there is a single key issue in shaft construction that outways all other
safety measures: The amount of time workmen are active inside the shaft.
For this reason any method that still requires workmen down the shaft is a poor one.
The methods discussed in the previous chapter are first assessed according to the amount of work that
is necessary in the shaft. Methods with a low or moderate safety will be abandoned, as shown in Table
15 .
Shaft excavation will be reviewed in more detail in chapter 4, as it forms an alternative to constructing
short pre-sinks without heavy equipment, where shafts are not long enough to install a complete blind
hole drilling rig. Also the development of remote controlled equipment means there may be room for
further development in this area in the future.
Blind Hole Drilling will be researched in further detail in chapter 5, because it appears to be able to
tackle nearly any geology effectively, yet it is one of the safest methods available.
Grout treatment and grout minipiles will be elaborated further in chapter 6. Grouting can be a very
cheap method, especially when used on localised targets. Also the understanding of the effect of
grouting is still poorly understood, leaving room for improvement and a desire for a better knowledge
base.
52
Method
Safety
Low.
Maintenance, reinforcement
Moderate
Shaft-boring machine
Moderate
Low
Cast-in-place lining
Lining.
Moderate
Lining.
Moderate
Forepoling/Boodex
Mod. high
Very high
Very high
None.
Very high.
Caisson lining
Very high.
Remote shotcreting
None.
Very high
Low (for
unstable
areas)
Very low
(for unstable
areas)
Raiseborer maintenance.
Final lining & watertighting.
Mod. high
Secant piles
Raiseborer maintenance.
Mod High
Diaphragm walls
Raiseborer maintenance.
High
Freezing
High
Calyx drill
High
Raiseboring
53
Excavation mechanisms
Augering
Augering refers to removal of soft plastic soils by applying torque to a helical blade, as shown in
Figure 32. The amount of torque that is necessary depends on the depth and diameter of the shaft. For
small diameters and limited depths this is a very competitive technique. Diameters up to 500 mm are
common, however diameters of approx. 2 m diameter are possible by more elaborate rigs. In the
Cannington area in Australia augers have also been used to hollow out a 6 m diameter shaft pre-sink
where smaller cores were removed from the greater circle. The maximum depth is about 22 m.
Augering is limited to low soil strength., although it can be combined by a diamond drill bit at the tip
to break moderately sized boulders. An obstruction may cause an auger to fail if its diameter is larger
than a third of the diameter of the auger.
Excavation
Excavation of the shaft can be
performed by full-face mechanisms
such as a microtunnelling machine
or a V-mole. However, these
systems have proven to be
inflexible and costly, and are being
replaced by non full-face machines.
Atlas Excavations has performed
extensive shaft sinking with a
small, down-the-hole excavation
machine which has fittings for
Figure 32 - Excavation of a shaft with a large diameter auger.
shovel, bucket tooth or hydraulic
hammer. This makes the machine extremely versatile. Such machines were used, for example, for
excavation of about thirty shafts for the Super Collider in the U.S. Unfortunately this machine requires
a controller, which makes it relatively unsafe for shaft sinking. As developments in underground
mining are going at the moment, this equipment will be controllable by computers from the surface
within the next decade, and this may be a promising alternative to the heavy equipment required for
blind hole drilling.
Shaft Sinkers inc. of India have developed a boom operated excavator for remote excavation of shafts.
This has the added advantage that the shaft can be excavated wet in areas with a high water table. For
54
depths of up to 30 m it is reasonable to consider a boom operated excavator, but legislation limits the
length of the boom to 22 m in some countries. In sandy soils wet excavation is an especially efficient
method.
An alternative to surface excavation in areas with a high water head is down-hole excavation under
pneumatic pressure. This method, where a caisson is sunk gradually as excavation proceeds from
inside, has serious health-and-safety hazards. The pneumatic system requires decompression of all
personell working at the bottom of the shaft. Hence this method is ralery used knowadays.
In all cases either an airline or fluid flushing can be used to get th e soil to the surface. The question
remains how to support the shaft wall in combination with a shaft cutting machine that excavates topdown.
Caisson-style lining
Skin friction
The top-down approach allows access to the shaft wall for applying support. It would be economical
and safe if it would be possible to insert prefabricated rings into the soil from the surface. This will be
referred to as caisson-style lining.
For soft plastic soils, it is most common to use steel lining elements which are pressed in to the soil
hydraulically. IHC Calland has the largest available equipment designed for off-shore construction
purposes. They have pushed steel tubes of up to 5 m diameter at least 20 m deep into soft marine soils.
In sands smaller diameters are possible, however as the relative density increase it becomes more
difficult to get the lining to penetrate. In sands it is common to use vibratory equipment which locally
liquifies the sand next to the steel lining. The following problems lead to jamming of pipes when
pushing them in to the ground :
Excessive skin friction as the length, diameter and soil density increases
Ovalisation of the lining
Elastic deformation of the lining as length increases. This makes it harder to vibrate or ram the
lining any further.
Determining the penetrability of sands is beyond the scope of this study, however extensive
knowledge is available from pile foundation engineering. A dynamic pile driving analysis could be
performed to determine if a casing could be driven into stiff sands.
Also it is generally excepted that the friction along a pile shaft is related to the in-situ vertical effective
stress and the friction angle between the lining and the soil as follows :
2
3
v 0 tan v 0 tan
The total resitance to skin friction can be derived by a simple summation of the area of the lining.
The following measures can be taken to reduce the shaft friction and thereby increase the depth
attainable by driving a lining :
55
Conclusion
Caisson-style sinking is a suitable alternative where soft soils and sands occur, along with high
phreatic levels. Dredging or wet excavation from a boom is a safe and economical way to get to
depths about 20 m. At greater depths, boom-length and skin friction start to restrict further progress.
The skin friction resistance and drivability of shaft elements can easily be analysed by analogous tools
designed for pile foundations.
56
57
Description
Blind hole drilling uses a cutter head similar to those used in raiseboring that is rotated from the
surface by drill rods. The hole is filled to the rim with drilling fluid, which can have clay or polymer
additives to make it cohesive and heavy so it will support the shaft wall. The fluid is also used to
transport rock cuttings from the bottom of the shaft, through the inside of the drill-rods.
The following steps are required to construct a shaft by the BHD method:
drill
rods
lining
grout
pump
tremie
pipe
lining
grout
58
Cuttings Removal
The transportation of rock cut from the surface is done by reverse circulation drilling. This means
drilling fluid from outside the shaft is pumped up through the
inside of the drill string. Generally a thin airline is lowered
down inside of the shaft with a nozzle at the bottom. Wirth
either uses a double walled drill string, where air is pumped
down the annulus between the outer and inner wall, or an
airline fastened to the
Figure 36 - Detail of drill-pipe flanges
outside of the
and connection bolts. To transmit the
drillpipe which has a
drill torque and carry the weight of pipes
and cutterhead they are thick and are
special connection at
made from high-grade steel.
each flange. This air
59
is pumped into the inner pipe reducing the density of the fluid. This creates a flow which is able to
carry pieces of rock up the pipe, some just smaller than the inner diameter of the drill pipe (up to
340mm).
At the top the fluids are collected in a retention basin, where cuttings are left to settle and drilling
fluids can be pumped off the top and reused. Reverse circulation was invented because the upward
flow in the inner pipe can carry cuttings better than the outer pipe (traditional forward circulation). The
inner cross section is small compared to the cross-section outside the pipe, resulting in high flow
speeds. This is necessary in big hole drilling where the diameters are so great that forward circulation
is impossible. Also chunks of rock tend not to jam easily because the diameter of the inner drill pipe is
relatively large being round (rather than when the annulus was used).
The air that is pumped inside the drill pipe lowers the density and thereby reduces the head. This is
why water or drilling fluid is required right up to the top of the shaft. The weight of the drilling fluid
drives the upward flow through the drill pipe.
This is an important restriction because it
means water, under high pressures, must
always be used.
Some rocks may dissolve or react with water,
resulting in significant loss of strength. As
well as this, the washing of clay and minerals
from fractures combined with high pore
pressure can make fractures turn into instable
shear planes.
Another danger of the pressure of the drilling
mud, is the risk of blow-out into nearby
Figure 37 - Settling ponds for drilling mud
cavities. Areas with washed out cavities or
existing mine openings may not be able to
withstand the high pressures of the mud. The shaft walls may suddenly burst into these openings
rapidly flushing the fluid away. This will stop the drilling progress, damage the shaft wall and
potentially cause the rest of the shaft to collapse. More importantly it will endanger peoples lives if
they are present in the adjacent mine openings.
Lining
The lining segments, each about 3m high, are generally pre-cast on site. The linings consist of a 2030mm steel outer ring with a layer of 100-200mm thick concrete poured inside. A thin ring is welded
to the outside of each segment to allow it to be lifted mechanically.
The lining is dropped down into the mud, with a plug at the bottom that is filled to the top with
concrete. This weight is necessary to stop the lining segments from floating in the drilling mud. As the
lining is floated in, each segmented is welded onto the previous one. A space of 100-200mm is
required between the shaft and the lining to stop it from jamming. It is very important for the success
of this stage that the shaft has been drilled as close to vertical as possible.
60
When the lining reaches the bottom, common drill rods around 72mm used for core-drilling are
lowered between the annulus behind the lining. The lining is carefully grouted from the bottom up,
creating a solid connection between the lining and the rock. The mud cannot be emptied until the grout
has hardened because fluids behind the lining compromise its strength, potentially causing it to
buckle. When the grout hardens it ensures stresses are transferred to the stiff rim of the lining through
arching. [70. Hunt, 2003]
For some deep shafts, where rock strength increases at greater depths, the drilling can be done in
stages. This way costly and thick drilling muds can be exchanged for water for the deeper section.
Because water is lighter and more viscous than muds, it makes cuttings removal easier. Also it lowers
the pressures at the bottom of deep shafts - reducing the chance of a blow-out. To be able to lower the
lining in the second stage, and grout behind it, the second section of the shaft must be drilled at a
smaller diameter than the inside diameter of the first.
Alternately blind hole drilling can be done without drilling fluids. In this case a pilot hole must be
drilled or raise bored, to allow for removal of the cuttings. This is not common practice.
The speed of drilling is generally limited by the weight at the cutting head. Pressure cannot be applied
to the cutting surface from above because this would cause the drill string to flex and the cutting head
would deviate from its vertical course. To achieve large diameters above 5m the shaft would be
drilled in more than one pass. A reamer would be used to enlarge the hole to the ultimate diameter of
up to 7m.
It should be noted that floated in lining only becomes strong once it is grouted up at the back this
transfers the horizontal pressures to the outsides through shear, unlike with fluids [Hunt et.al. 1995,
Casing collapse at the CT-8].
Cost
The cost of blind hole drilling is generally twice the cost of raise boring. The main costs of blind hole
drilling is the setup of the drilling equipment, can take up to 30 truckloads and four weeks. Once
drilling starts, costs per meter are only 20-30% higher than raise boring [Zeni 2004]. For remote
locations such as those in the Northern and Western deserts of Australia, pre-reinforcement options
tend to outweigh the high cost of setup. Despite the extra costs, there are many reasons why blind hole
drilling can still be the preferred method.
Firstly the liabilities of BHD are lower; for raise boring a reaming head must be positioned from the
bottom of the shaft, which is a very dangerous position to work from. For long shafts through hard
rock, the cutters become worn and damaged and must be changed, again putting workmen at risk.
In situations where soils or rock are unstable, raise boring requires a pre-sink. This pre-sink can be
done to about 20-30m below the surface by an excavation arm, but below this a working platform with
a protective cage is required. If the rock is hard, drilling and blasting is used, which is a dangerous and
cumbersome operation. This is where blind hole drilling starts getting an edge.
61
Often it is easy for mine planners to be able to have a shaft ready to go as underground workings reach
it. With raise boring the underground opening always has to be excavated first, and the cuttings
removed as the shaft is constructed. This can have significant economic disadvantages compared to
blind hole drilling.
Alternatively it is possible to combine raise boring and blind hole drilling. This way the unstable shaft
can be drilled by the more expensive blind hole drilling, and raise boring can be done for the
remainder of the shaft. This poses some difficulties.
It should be noted that it is not possible to raise bore first, then blind hole drill. The pilot hole will lose
the drilling muds, and as the blind hole drilling approaches the raise bored hole, the drilling muds will
suddenly be breach into the opening, causing shaft collapse.
The hole will have to be blind hole drilled first, then raise bored. This is possible, but three problems
arise during the raise boring:
Additional stabilizers are required because the drill strings are not supported by the pilot hole at
the top of the shaft. Although the drill strings are in tension, they may deflect because of the
torsion that is applied.
The foundation of the raiseboring machine is more complex. The shaft beneath the raise boring
machine means it is hard to transfer the vertical load to the ground beneath. Beams across the hole
are required which divert the load to a large area foundation.
The beams that cross the hole need to support very large vertical loads from the raise boring
machine. Because of this they may deflect op to 20mm, which means control of the raise boring
head becomes very difficult.
Eventually the costs of setup of both the blind hole drilling and raise boring machine may not
outweigh the costs of simply blind hole drilling all the way, but combinations of raiseboring and a
short pre-sink should always be considered in areas of weak overburden.
Limitations
With a common drill pipe diameter of 20, depths of 700-800m can be drilled, depending on rock
conditions. A smaller setup with 12 rods can reach 600m (and up to 3,5m diameter) rock conditions
permitting. At great depths drill strings start to get 1-2 rotations of windup. This is elastic
deformation of the drill pipe between the top where torque is applied and the resistance on the cutter
head at the bottom. Because rock is never completely homogenous, this can cause sudden spinning
followed by sticking of the cutter head, as the deformation travels up the shaft. The only solution for
this problem is a larger diameter drillpipe with better quality steel combined with heavier equipment.
Depth is hardly limited by the drilling fluids as it is usually possible to simply pump more air down
the nozzle. The increasing weight of the drill pipes is a bigger problem; it requires stronger drill pipe
with thicker flanges (or better quality steel) and larger equipment.
Diameter is still limited in blind hole drilling. Because the weight is supplied through gravity and not
through tension in the drill strings like in raiseboring, the thrust is limited, and thereby also the
diameter. A two-phase sink head or sumped cutterhead can be considered where thrust is a problem,
62
but these are still being developed for shaft drilling. An untried solution may be to place an anchor at
the end of a pilot hole, which can be tensioned and thereby apply thrust to the cutterhead.
Blind hole drilling applies large pressures to the surroundings. In the neighbourhoud of cavities and
existing mine openings this can form the danger of a blow-out. Generally a 20-30m barrier between
the shaft and neighbouring openings is considered quite substantial to support the fluid stresses (up to
30Mpa for very deep shafts). For soft coal seams which may be weaker and have high stresses, up to
50m may be required to support the standing head.
Uncemented sands, unstable weak rock and large water inflows are supported by the drilling mud. In
these cases bentonite is added which makes the mixture thixotropic and supports the shaft walls. This
must be balanced against keeping the drilling fluids viscous enough to easily transport the cuttings.
Some karstic limestones and similar rocks dissolve in the drilling mud and cause the walls to break
and dissolve. This can be solved by adding bentonite or polyacrilonite to the drilling mud which
makes the fluid thixotropic. This means it forms a solid cake around the outside of the fluid which
keeps the fluid together and stops it dissolving the walls. To prevent washing soluble clays potassium
chloride ions can be added (at around 20,000 p.p.m.). These form a molecular bond with the clays,
effectively hardening them. A simple test where core samples are dissolved in buckets of water with
various concentrations is sufficient to find out how much additive to use to stop solution of the clays.
The potassium chloride can cause some environmental problems where the chlorides cannot be
disposed of safely. Here a more expensive alternative is used (at about 10 p.p.m).
Areas of uncemented sand in combination with reactive clays can form a problem. This is because
bentonite is used to make a thixotropic solution which forms a cake and stabilizes the sand.
Bentonite consists mainly of smectite which is a reactive clay. This added clay prevents the addition of
potassium chloride, the additive that is used to prevent the solution of the reactive clays.
Open fractures can allow the drilling muds to escape. This is a problem that can be solved by using
sure-seal or other cellulose products, which are added to the drilling mud. Typical products such as
paper clippings or wood chips tend to get carried into the fractures by the high flow rates, where it
swells and blocks the hole.
Alternatively a ring of grout columns has been drilled to reduce the permeability of fractures, for
example in cases where shafts have been constructed near water catchment areas. The penetration of
drilling muds into the groundwater and surface retention basins can form an unacceptable
environmental hazard, restricting the use of blind hole drilling. Drilling with polymers or dry-drilling
combined with remote shotcreting may be an alternative in this case.
In Chapter 8 the rules for shaft drilling will be assessed and compared to other construction methods.
63
64
65
Drilling methods
Secant Piles
Secant piles are commonly drilled with an auger, which is a corkscrew shaped drill that transports
cuttings to the surface by rotation. In very soft rock, augers can be used with a drill bit at the tip. The
problem with augers is the limited torque that can be applied to the auger to overcome friction. In soft
clays augering works very well, but sands already start to become problem. As depth increases so does
the friction on the auger, reducing penetration rates until finally the auger refuses to pentrate any
further.
Table 17 - Secant pile guidelines [134. Herrenknecht AG.]
1
D A for auger diameters D A 300 mm
3
1
Maximum obstacle size (boulders etc..) D D A for auger diameters 300mm D A 800mm
4
Another important vulnerability of an auger is where boulders and solid obstacles occur, which also
jam the auger. As a guideline, drillers can use augers up to a depth of 22m for soil and rock strengths
up to 2MPa. By connecting two augers together, a depth of up to 44m may be possible in rock and
soils less than 1MPa.
This is obviously an uncommon geology especially in mineshafts as it is generally only encountered in
alluvial deposits or extremely weathered zones (e.g. karst). Generally any boulders cause problems
blocking the auger, as well as great depths because the friction increases with depth. If unstable clays
are encountered a casing can be used to support the shaft, which is driven by a vibrating block at the
same time as the auger drilling. In areas with only a few boulders, it may be viable to use jet-grouting.
Jet grouting
Although more expensive, jet-grouting has less problems with higher strength sands and gravel. Jetgrouting is suited to porous soils where the particles can be moved by a pressurised jet of air and
water. Areas with a large amount of large boulders should not be grouted as the boulders can stop
penetration of cement in their shadow.
Jet grouting is not very common in mining engineering because it is expensive, inappropriate to rocky
conditions, and error-prone at large depths.
66
MUD-support
For drilling in any soft soil or rock, some form of drilling fluid or 'mud' is used. The fluid cools the
drill bits, transports tailings back to the surface and, if necessary, supports the walls of the hole. When
extra stability of the hole is required, montmorillonite clays (bentonite) are added making the mix
thick, but reducing cuttings transport. Another important function of the clays is to form a filter cake
on the surface.
67
Often water flushing is adequate for small holes, except in soft or reactive clays and karstic geologies
that contain soluble rocks like gypsum and limestone. Also, situations where the in-situ stress is high
in one direction, and low in the other may require more than just water support, to prevent borehole
breakout.
Dry-rock-drilling
For reactive clays, gypsum and some limestones dry flushing can be used with air to support the walls.
Powermole or its Italian equivalent Technolgie Avanzate use this method on a regular basis, mainly
for directional drilling of pipelines (The PM903 system is used).
Dry-rock drilling, guidelines
Odex
Odex is a form of drilling with an eccentric drill bit, specifically tailored to drill through overburden.
Where ordinary drilling uses a casing only for the first few metres and uses drilling fluids to support
the hole, Odex uses a casing all the way down to the bedrock.
Odex is an eccentric bit that folds out of the casing by rotation, cutting a path just outside the diameter
of the casing. Because overburden can contain blocky and weathered rock that can jam the bit, the
Odex drill bit also has top bits that can drill backwards. When the rotation on the Odex bit is reversed,
it collapses so it can fit inside the casing and be lifted to the surface. This also allows the drill bit to be
exchanged for a hard-rock bit which allows drilling to proceed easily into the bedrock.
Table 19 Odex drilling guidelines [62. Verfel 1989]
68
Abrasive water-jet-cutting
In the interest of selective mining and mining through very hard rocks, significant research has been
done into cutting with water jets or jet-kerfing. Generally water-jet cutting has insufficient cutting
speed to be effective for large diameter shafts in soft rock.
Besides speed, the costs of water and abrasives used and the cost of replacing the water nozzles is far
too high. [117. Vijay 1992]
The use of water-jets in combination with drilling is quite useful as it removes tailings effectively.
However both drilling and cuttings transport through water-jets are highly complex mechanisms
description of these phenomena and how they collaborate requires extensive research. The
development of integrated drilling systems is being led by the exploration sector of the oil-industry.
[121. National Acacdemy of Sciences 1994]
Abrasice water-jet cutting/kerfing, guidelines
69
Drilling Accuracy
Measuring and correcting deflections
A vital part of succesful grouting is getting the grout into the areas that need reinforcing. This not
only means accurately surveying grouting operations, it also means drilling accurate geotechnical
investigation holes.
Firstly, this means grouting should be performed as close to the target as
possible, such as from completed mine activities close to the shaft.
However, having workmen down the shaft is a problem, so drilling grout
holes from the surface is preferred. Also this is more economical as it is
difficult to get large equipment into the shaft.
Accurate grouting is also necessary if raiseboring is to be performed after
drilling. An ventilation shaft in north-western Australia could not be
raisebored because reinforced grout piles had deflected inside the shaft
N
Azimuth
Inclination
70
Hard vein
(e.g. quartzite)
disrupting magnetic readings. This can be solved by moving the measuring tool away from drilling
equipment using non-magnetic aluminium extension pipes.
Such modern tools also contain three-component accelerometers rather than a graticule, which
provides for more accurate readings. Also it helps prevent error introduced by movement of the tool
during measurement. To provide more continuous operation, these tools may be used with a wireline,
to directly connect the measuring tool to the surface. This works well in conjunction with a Navidrill
or similar steerable drill that can then quickly adjust its direction with the help of a dogleg bend.
Reflex of Sweden also produce a multi-shot tool called Maxibor, which allows for quick measurement
as the tool travels down the hole. Rather than a single shot, Maxibor takes measurements up to as little
as 3m between, which is possible because it only
takes a few seconds to create an image. The system
should also be rotated between measurements to
average calibration mistakes in all directions.
One area of concern is where hard layers such as
quartzite veins intersect the borehole at an angle.
This is a typical location for deflections to occur
due to the phenomenon of rat-holing where the
drill bit is pushed away from its target, as shown in
Figure 39. Drilling should be performed with less
pressure on the bit when traversing these layers,
along with extra measurements so that deflections
can be quickly corrected.
survey
error
Common problems in measuring drilling accuracy are listed in Table 20. Calibration and initial survey
of equipment are by far the most common sources of borehole deflection. [139, 140. Reflex instrument
AB]
71
Poor centering of the down-the-hole Use 2-3 stabilisers. Check with photo.
tool in the hole.
Drilling equipment upsets magnetic Extend distance between survey tool and drill
readings
rods with up to 8m of aluminium rods
Rat-holing
Problem
Solution
Approximate error :
72
2%
2%
1%
,3%
Quality of grouting
To determine wether grouting will be effective, the factors that influence the result should be
identified It is important to get grout sufficiently far into joints and pores.
The distance grout can penetrate is determined by:
joint thickness, joint roughness and joint filling (clays gouge, etc)
initial normal pressure on the join
stiffness of the rock surrounding the join. Stiff rock can prevent fractures from opening. On the
other hand hydrojacking may allow opening of joints and further penetration.
filtration effects achieved by cement particles blocking holes
thickness of the grout mix (expressed by a Bingham fluid with viscosity and cohesion)
grout choosing the path of least resistance, instead of going into all cracks.
grouting pressure
reduction of grouting pressure due to hydrofracturing
The strength of the bond is dictated by:
Shrinkage called slump due to high water ratios, resulting in pore space
Dry powdery grout because of inadequate water .
Inadequate water occurs where :
o the grout is too thick
o The grout flow slows along the pore walls where friction is highest
o Absorption of water by dry rock
Additives like bentonite or superplasticizer (e.g. Intraplast) that weaken the grout
Dissolution of grouts due to groundwater wash.
Weathering after grouting due to in-situ water flows
Hydrofracturing causing new fractures
73
Accurate grout-control is needed for succesful grouting. Lugeon tests are a reliable way of testing the
permeability, and thereby the succesful penetration of grouting. During grouting accurate control is
necessary. [93. Lombardi 2003]
Firstly the grout mix should be closely monitored. Batches should be checked for proper mixing and
should not be too thin or too thick, in the form of measuring the Marsh flow time and the bleed. Also
samples should be kept and cured for triaxial testing to ensure the required strength is attained, taking
proper care to store the grouts in the same conditions (temperature and moisture) as where the grout is
injected. If insufficient strength is attained, water-cement ratio's may need to be adjusted, or the
amount of additives like superplasticizer or bentonite reduced.
Not only the mix, but also the grouting proces should be accurately controlled. It is recommended that
holes that may be clogged with clay, debris or drilling mud be flushed first with water. Also this wets
fracture surfaces making sure there is sufficient moisture for hydration of the cement. As grout pipes
may become clogged, it should be possible to flush them with water when necessary. In case of
flushing or if grouts do not meet quality standards, it should be possible te defer the flow of grout into
some sort of sump pit.
The flow rate and total amount of grout pumped should be monitored, as well as the grouting pressure
required. In case of large grout takes, the grout mix may be temporarily thickened to stop it
continuously disappearing into large fissures. When grout take starts to decrease, it should be readily
possible to lower the discharge of the grout pump accordingly, to prevent excessive grouting pressures
causing fracturing. Grout lines should be kept as short as possible so adjustments can be made
quickly. A return line allows deferring of poor grout and relaxation of pressures when necessary. It
may also be economical to defer a portion of grout into the next grout hole.
Finally, packer tests to determine the Lugeon value are the most practicable method of checking
grouting was succesful.
74
75
Borehole 3
Borehole 1
Borehole 2
Grout wash
Water flow has another effect on grouts, especially on cement grout. Water flushes the cement
particles, reducing the final strength, called grout wash. This occurs mainly during grouting while the
mix is hardening, but also in hardened grout where flow paths have not been completely blocked. In
the Stawell mine in south-eastern Australia, it is assumed the breaching of pressurized aquifers caused
strong water inflows that washed grout and later caused the shaft to collapse.
This problem is exceedingly difficult in the cross zone from weathered rock into bedrock. Close to the
hard rock zone, rocks are increasingly saturated and weathered, sometimes leading even to running
sands at the cross zone. Grout not only takes the path of least resistence, but can also be washed by
76
strong water flows across the bedrock. The Freestate mine 75 km SW of Johannesburf at 2.4m
diameter had high water inflows through dolerite layers. It was preconsolidated by a local grouting
company, but collapsed on excavation of the cross zone. All grouting efforts had been washed by
water flowing across the bedrock.
Some additives like quick hardeners can shorten the hardening time and reduce excessive grout wash.
The addition of bentonite kan keep the mix stable, controlling bleed, but this also weakens the
hardened grout. Bentonite works ineffectively for seawater inflows or other highly saline groundwater.
An alternative to quick-hardeners is the use of separate holes to concurrently inject sodium silicate.
Fast-gelling of the grout can be achieved because of the instant hardening when the two components
meet; this limits grout dilution and transport of grout away from the targeted areas.
77
insulated bulk containers with a temperature booster at the facility, capable of maintaining a high
temperature (180-225 deg Celcius). Pipes should be preheated with hot oil and much care should be
taken when handling the hot material..
[132. Naudts & Hooey]
There are several approaches to getting the grout to carry cement particles into narrow joints:
The particles are made smaller, e.g. ultrafine cements.
Superplasticizers are employed to disperse the colloids better. Particles drop from the solution less
easily.
The pressure is increased, in order to widen the joint.
Use of polyurethane or silicate grout, or hot bitumen, which does not contain suspended particles.
Superplasticizers have a secondary effect the reduction in viscosity reduces wall friction on the
grout. The pressure at the front of the grout remains higher, causing joints to open further and grout to
be pushed deeper into the joint. The most highly jointed zones are often the deeply weathered zones
just above the bedrock. Fortunately high-pressures can be applied to these zones because of the
significant ground cover (1-2MPa).
Poly-urethane grouts have proven effective because they have viscosity less than water and penetrate
well because of the high pressures applied due to the foaming action.
An example of effective grouting is Paracale in the Philippines where advanced grouting with both
local Portland cements as well as by water-activated polyurethane resins took place. High water flows
were limited by heavy localised pumping through 'relief'-holes. In earlier attempts in Paracle, grouting
had been ineffective before because of typical errors in quality control:
grout holes had not been flushed clean of drilling debris and mud infillings
lack of control because there was no hydrofacture presure testing done
grouting occurred in one pass rather than controlled stage-down grouting
grouting pressures were too high (7-14 MPa) for the weak, highly fractured ground conditions,
which eventually caused a blow-out of the shaft bottom.
[124. Ayugat et.al 1998]
78
Filled joints
Infill material can significantly reduce the shear strength of discontinuities. Soft materials such as clay
act as a lubricant between shear surfaces. Swelling clays are especially dangerous because they absorb
water and push apart joint surfaces so that nearly all internal friction is lost.
Theoretically clays can be washed from joints, but only at slow velocities of around 0.1 cm/s, and at
high pressures. Unfortunately clay usually fills the smaller joints, which, when washed, have higher
flow rates. Also hydrofracturing often limits the pressures that can be applied remove the joint filling.
[Verfel 1989 Rock Grouting & Diaphragm Wall Construction]
Treatment of clay fillings with cement, chemicals or bacteria that produce carbonates to improve
bonding is difficult. Penetration of joint filling with whatever particle can be in the order of weeks to
years.
Recent research in the Netherlands is looking at treatment of clay layers through electro-osmosis. The
aim in this case is to accelerate consolidation of clay layers and to create low strength foundations.
Through this method water is extracted from the clay and strengthened by drying. Because of the
complexity of clays and the remoteness of grouting it is hard to say if joint infill could be treated
succesfully by electro-osmosis.
At the very least clays that are to be treated should satisfy the following conditions:
Predominantly expansive forms of 2:1 clays such as smectites (e.g. montmorillonite) and poor
illite clays (e.g. vermicullite) that are sufficiently saturated. These are formed mostly from
sandstones and shales in high pH areas (where K+ and Al+3 cations are abundant).
Groundwater flows should be near zero, otherwise the driving current will be insufficient to
counteract flow.
Host rock needs to be non-porous. Porous rocks fill with water and have a high conductivity.
Electro-osmosis is worth further investigation as it may provide a solution to clay-filled joints that
cannot be grouted in any way. At the moment electro-osmosis is too uncontrollable to use effectively.
Hydrofracturing
Grout loss can also occur because hydrofracturing and hydrojacking opens extensive new flow paths.
It is important to conduct a hydrofracturing test, where water is pumped into the borehole through a
packer under increasing pressure. The maximum grouting (hydrofracturing) pressure can be found by
a sudden surge in water take, often accompanied by pressure drop.
There can also be a positive effect by hydrofracturing, although this is questionable. Hydrofracturing
creates new joints and thus also new weakness planes. It is common for hydrofracturing to occur in
vertical planes normal to the borehole wall. This means planes that dip towards the shaft are
intersected, which is a useful mechanism if it is hard to stengthen these joints directly. On the other
hand hydrofracture planes usually form parallel to the major principle stress, which is the exact
direction that a joint is most unstable. However, in weak rock where grout bonds are relatively strong
79
compared to rock strength, and where grouting is inhibired by clay gouge or extremely narrow joints,
this may be the only way to get grout to intercept fractures.
Conclusion
Grouting can be used to increase internal friction between joint surfaces. Other important effects of
grouting are blocking of water flow and increased cohesion.
There are abundant examples of shaft collapse after poor grouting operations. However, if grouting is
better understood, it forms a valuable, economical tool for reinforcement of shafts. The three most
common causes of collapse are:
Inaccurate positioning of grout
High groundwater flow
Poor penetration of grout
In this chapter we have seen that there are solutions for most of the problems that are encountered
during grouting. Accurate survey of grout holes and quality control of grouting operations is
fundamental. Grout wash can be tackled with appropriate countermeasures, such as the use of hot
bitumen grouting and pressure relief holes.
Poor penetration is more difficult to counteract, although reinforced minipiles that intersect joints are
an alternative. Grouting should not be applied when joints are blocked with infill material, and water
pressures also threaten shaft stability.
At the end of this chapter, a series of guidelines is given to ensure succesful grouting.
80
Establish that grouting will stabilise the shaft (See Chapter 7 Shaft Stability)
Ensure accurate positioning of grout holes (See Table 20)
Monitor and correct the quality of grouting (See Table 22)
Detect and prevent problems with grout flow and grout wash (See Table 23)
Detect and prevent problems with grout penetration (See)
Determine weather to grout above or below hydrofracturing pressure. (See
Table 25)
Do not attempt grouting where joints are blocked by soft infill material and water pressures
also threaten shaft stability. Consider freezing instead.
Table 22 Ensuring the quality of grouting
Grouting setup
Start a grout batch with water, to wet all rock surfaces and to attempt to push away joint fillings
Quickly increase grout thickness, to prevent open fractures from filling with water instead of
grout.
Grout quality control
Perform packer tests to determine Lugeon values before and after grouting.
Continuously check grout quality.
Check for proper mixing (lumps) and correct water cement ratios.
Beware of excessive water as it causies grout slump and insufficient strength
Beware of excessive cement as it causes poor penetration, cement filtration and poor
bonding.
Beware of using bentonite, super-plasticizers and quick hardeners, as it often results in
significant loss of grout strength.
Monitor grout viscosity by using a Marsch funnel
Monitor grout bleed to warn for an instable mix.
Take samples for triaxial testing. Keep these stored in similar temperature/humidity conditions
as the grout that is pumped underground.
81
Table 23 - Detecting and preventing problems with grout flow and grout wash
Detect grout flow problems with a packer test. High permeabilities and nearby pumping
activities indicate high risk of grout flowing from its target.
When in doubt, pockets of water should be detected by thermal imaging from the borehole.
When in doubt, high water flow rates and paths should be accurately detected by crosshole
radio tomography. Modelling is possible with a tools such as NAPSAC.
When losing grout into large cavities, thicken the grout and employ cellulose material.
Preventing grout flow problems
Open fissures can be recognised by large grout losses, and should be filled by thickening the
grout mix.
Large cavities will continue to lose grout, and should be blocked by adding cellulose material to
the grout mix. Cavities may also be backfilled seperately with sand and gravel mixes.
Continuous grout loss should be treated suspiciously, it may indicate an aquifer is washing the
grout. Detect aquifers by drilling extra core samples, using thermal imaging and/or radar
tomography.
82
Grout penetration
Grout selection:
Joints > 1 mm with normal portland cements
Joints > 0.1 mm with ultrafine cement grouts
Joints < 0.1 mm with polyurethane/silicate grouts
For wide and unfilled joints where water wash is a problem, use hot bitumen
For narrow and filled joints where water wash is a problem, use polyurethane foams
Grout at a small incline (20) if vertical joints are closely spaced and need grouting.
Generally grouting should occur at maximum pressure, but below hydrofracturing pressure
Table 25 - Application of hydrofracturing
Hydrofracturing generally creates extra weakness planes vertical and normal to the borehole
Apply hydrofracturing if weak planes dip toward the shaft and cannot be penetrated by grout
because they are extremely narrow or filled with clay gouge.
Only apply hydrofracturing if the strength of the cement bond is high compared to the in-situ
stresses. This usually means at shallow depths only.
Determine hydrofracture pressure with a packer by increasing pressure until sudden water loss
occurs accompanied by pressure drop.
83
7. Stability of shafts
Instability problems
Empirical methods for assessing shaft stability
The Q-System
Adaptations for raisebored shafts
84
85
86
87
88
89
Wedge Analysis
Block Theory
90
Application to shafts
91
92
93
Joint stability
94
Joint Orientation
95
Joint Roughness
96
Joint filling
97
Conclusions
98
99
8. Results
Introduction
100
Reviewed methods
101
102
103
104
105
106
107
Conclusion
108
109
110
111
Bibliography
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
112
P.R. Callow Shaft sinking for the Thomson Tunnel Stage 3 Application of a full face
rotary head shaft borer Fourth Australian Tunnelling Conference, Melbourne: ?pub?,
March 1981, p. 337-346
Morris J. Medd and Graham A. Speirs Breaking new ground Full face burn cutting in
hard rock shaft sinking World Mining Equipment, (October 1990): 14-20
Paul Richardson Blind Drilling Down Under Civil Engineering / ACSE (August 1985): 6668
James H. Allen The big hole gets bigger, Mining Engineering, November (1968): 58-63
Richards J. Robbins Advancing technology pushes back the frontiers Tunnels &
Tunnelling (May 1989): 48-58
P. Barendsen Mechanical drifting by the full-face method Tunnels & Tunnelling (July
1969): 89-93,141-144 B. Mason and M. Bishop Remote concrete spraying in shafts and
tunnels Tunnels & Tunnelling (September 1992): 43-45
Shani Wallis Tunnelling for tourists Tunnels & Tunnelling, (Autumn 1992): 27-30 [MU]
W.R. Dengler, W.M. Shaver, and R. Letourneau New technology in shaft sinking Tunnels
& Tunnelling, (December 1991): p23-27 [MU]
Descriptions of the Callie, Stawell, Bendigo, Pajingo, Mt Isa and Cannington minesites
given by Max Lee & Warren Peck: Australian Mining Consultants, level 19, 114 William
Street, Melbourne (2004) [AMC]
P.P. Jenkins, and T.G. Ball Reverse Circulation Coring Minerals and Mining Equipment,
pA17-21
Gu and B.Lin Application and abstraction of shaft drilling technique in coal mine
construction in China Mining Engineering (August 1993): 1084-1086 [MU]
Paolo Croce, Alessandro Flora, and Giuseppe Modoni Experimental Investigations of JetGrouting Foundations and Ground Improvement, p245-259
Li Li, Michael Aubertun, and Richard Simon Stability analyses of underground openings
using a multi-axial failure criterion Geo-engineering for underground facilities, p471-481
Alan James Catastrophic failure of a raise-boring machine during underground reaming
operations Engineering Failure Analyses 4.1 (1997): 71-80,
S. Keeble Alternative methods of Shaft Sinking through Water-Bearing Strata The Mining
Engineer (December 1990): 207-214
M.G. Kafarkis and S.W.Kan Characterisation of polyester grouts for ground control
Mining Engineering (September 1998): 69-74
Peter Hambach Uphill work for TBMs Tunnels & Tunnelling (April 1992): 42-44
Wilhelm J. Kogelmann Novel shaft sinking techniques Tunnels & Tunnelling (May 1992):
67-68
Bell Alternative methods of sinking & lining shafts Colliery Guard 236.10 (October
1988): 352-354
Colin Pigott The route to more efficient blind shaft drilling? Rapid Excavation and
Tunnelling Conference Proceedings Vol. 2. 2 vols. (New York:, June 1985): p975-991
Paul Richardson State of the art of big hole drilling Rapid Excavation and Tunnelling
Conference Proceedings Vol. 2. 2 vols. (New York: , June 1985) p992-1002
21. Wilhelm J. Kogelmann New road-header type continuous shaft sinking systems Rapid
Excavation and Tunnelling Conference Proceedings Vol.2, 2 vols. (Los Angeles: , 11-14
June 1989) p480-500
22. Stephen J. Navin, Jon Y. Kaneshiro, Larry J. Stout, and Gregory E. Korbin South Bay
tunnel outfall project, Rapid Excavation and Tunnelling Conference Proceedings (June
1995) p629-644
23. Michael McKenna, Daniel Traylor, Bernard Tarralle & Edwin Itzig-Heine Design and
construction of a deep, dual-cell slurry wall shaft in soft ground Proceedings of the Rapid
Excavation and Tunnelling Conference 2003, p368-382
24. NATM shafts case histories & cost benefits Rapid Excavation and Tunnelling
Conference Proceedings, (: ,1993) p307-323
25. Sinking of vertical shaft with sliding form Coal Science & Technology 3 (March 1991):
26. New technique of cementation curtain wall shaft sinking Coal Science & Technology 9
(September 1991)
27. Contact reaction mud and drop shaft lining Coal Science & Technology 7 (July 1993): 7
28. Shaft sinking in sliding overburden structure zone, Coal Science & Technology 22.1
(January 1994)
29. Wilhelm J. Kogelmann Continuous shaft sinking by selective-cut machines Glckauf
(Mining Reporter) 126.9/10 (May 1990): 431-433
30. Wollers Planning criteria when sinking shafts from the point of view of the shaft sinking
engineer Glckauf (Mining Reporter) 127.3/4 (Feb 1991): 98-
31. H.W. Toncheidt Shaft sinking by shaft boring machines without pipes Glckauf (Mining
Reporter) 125.13/14 (July 1989): 760-768
32. Computer aided blind shaft drilling operations Glckauf Forschungshefte 53.6 (December
1992): 254-257
33. Enlargement and Sinking of the Lummerschied shaft using a Shaft Boring Machine with
subsequent lining Mines Carrieres Les Techniques 73 (May 1991): 38-48
34. Comparison of the performance of high-speed water jets for selective mining International
Journal of Surface Mining & Reclamation 6.1 (1992): 1-9
35. K. Wollers Current development in conventional and mechanical shaft sinking in the
Federal Republic of Germany Proc. Conference on Shaft Engineering (Harrogate: , 5-7
June 1989) p375-378
36. Maynard Stenberg Navi-Drill/Welnav combination keeps pilot hole on course at Elura
Mining Engineering 42.8 (August 1990): 992-993
37. P. Sembenelli and G. Sembenelli Deep jet-grouted cut-offs in riverine alluvia for Ertan
cofferdams G. Sembenelli et.al. Journal of Geotechnical and Geoenvironmental
Engineering 125.2 (February 1999): 142-153
38. G.Galecki, ???other auth?? Method of trepanate drilling of deep and large diameter holes in
hard rocks Energy Sources Technology Conference and Exhibition (Huoston: Jan 26-30
1992).
39. M. Agus et.al. Influence of rock properties on waterjet performance Proceedings of the 7th
American Water Jet Conference. vol 1. 2 vols. ( : Seattle, Aug 28-31 1993) p427
40. Unusual solution for the slurry trench cutoff wall at Xiaolangdi International Journal on
Hydropower & Dams 5.1 (1998): 32-35
113
41. Classification of jointed rock with emphasis on grouting Tunnelling and Underground
Space Technology 7.4 (October 1992): 447-452
42. Pieter H. Fuykschot Vibration compensation of gravity sensing inclinometers in windtunnel
models Instrumentation in the Aerospace Industry : Proceedings of the International
SymposiumMay v42 (San Diego, CA, USA: 5-9 May 1996) p493-503
43. Technology news. Cutting machine replaces blasting in shaft-sinking project Mining
Engineering 46.4 (April 1995) 344
44. John H. Archibald, Arthur L. Miller, and George A. Savanick Self-propelled abrasive jet
reamer/miner for deviated boreholes in hard rock Proceedings Rapid Excavation and
Tunnelling Conference (Seattle, June 16-20 1991) p829-839
45. G. Pakes Developments in civil engineering tunneling Mining Technology 78.897 (May
1996): 127-130
46. S.K. Jain Drilled in caissons or shafts in soft rock of New York area Geotechnical
Engineering of Hard Soils Soft Rocks (A.A.Balkema: Athens, Greece, Sep 20-23 1993)
p961
47. David Martin Ring of success Tunnels and Tunnelling 22.9 (September 1990): 42-44
48. Anon. Directional accuracy using rotary drilling Journal of Offshore Technology 6.1
(February 1998): 28-30
49. K.A. Noy and J.G. Leonard New rate gyroscopic wellbore survey system achieves the
accuracy and operational flexibility needed for todays complex drilling challenges
Proceedings of the 1997 SPE/IADC Drilling Conference (Amsterdam, Neth.: Mar 4-6 1997):
p773-783
50. E.C. Drumm, W.F. Kane, and C.J. Yoon Application of limit plasticity to the stability of
sinkholes Engineering Geology 29.3 (Octoboer 1990): 213-225
51. Khaled M. Hassan and Michael W. O'Neill Side load-transfer mechanisms in drilled shafts
in soft argillaceous rock Journal of Geotechnical and Geoenvironmental Engineering 123.2
(February 1997): 145-151
52. Sam Spearing Superskins Mining Magazine 187.4 (October 2002): p164-165 [MU Internet
- Article A93351444 >> Cisti-Order number: CI-04482832]
53. James F. Archibald and David O. DeGagn Spray-on Lining Support in Canadian
Underground Mining A Research Summary CIM Bulletin 94.1050 (May 2001): 49-56
54. Improved forward support with Boodex Talking Technically (Ulf Linder for Atlas Copco:
2003) 17 http://www.tunnelbuilder.com/facedrilling/edition2pdf/page17.pdf
55. F. Verfel Rock grouting and diaphragm wall construction (Elsevier: Amsterdam, 1989)
56. Anon. Strengthening the case for grouting Tunnels and Tunnelling International 33.12
(Miller Freeman plc.: December 2001): 34-36
57. Dick Hattingh and Oliver Schwarz Chemical Grouting Glueckauf Mining Reporter 2
(Verlag Glueckauf GmbH: Essen, 1998): 37-42
58. F.K.Ewert Individual groutability of Rocks International Water Power and Dam
Construction 44.1 (Jan 1992): 23-30
59. G.A. Savanick and W.G. Krawza An abrasive water jet rock drill (Twin Cities Research
Centre, Bureau of Mines: Minneapolis, 1990)
60. X. Chen, C.P.Tan & C. Detournay The Impact of Mud Infiltration on Wellbore Stability in
Fractured Rock Masses Proceedings of the SPE/ISRM Rock Mechanics in Petroleum
Engineering Conference (Irving, Texas: 20-23 October 2002): p653-664
114
61. J.G. Dickens and P.J. Walker Use of distinct element model to simulate behaviour of drystone walls Structural Engineering Review 8.2-3 (Pergamon Press Ltd, Oxford: MayAugust 1996) 187-199
62. Gunnar Nord, The Boodex method - A way to overcome locally very poor ground
conditions in tunneling Proceedings of the Rapid Excavation and Tunnelling Conference
2003 p49-56
63. Steven Hunt, Roger Maurer and Steven Fradkin Experience with deep shaft construction in
Milwaukee Proceedings of the Rapid Excavation and Tunnelling Conference 2003 p336348
64. Deep shaft construction in unconsolidated material and water-bearing formations
Proceedings of the Rapid Excavation and Tunnelling Conference 2003 p349-359
65. Lake Mathews Outlet Facilities' shaft construction, Metropolitan Water District of Southern
California Proceedings of the Rapid Excavation and Tunnelling Conference 2003 p383-395
66. Hard rock tunneling stabilization using jet grouting techniques Proceedings of the Rapid
Excavation and Tunnelling Conference 2003 p494-499
67. Jacked box tunnelling creating large shallow openings beneath existing highways and
railways Proceedings of the Rapid Excavation and Tunnelling Conference 2003 p12351247
68. Leonard Schwer and Herbert Lindberg Finite element slideline approach for calculating
tunnel response in jointed rock International Journal for Numerical and Analytical Methods
in Geomechanics 16.7 (APTEK, Inc, San Jose, CA: July 1992) 529-540
69. V.M. Sharma Distinct element modelling in geomechanics (Balkema, Rotterdam: 1999)
70. E. Nonveiller Grouting Theory and Practice (Elsevier Science Publishers, Amsterdam
1989)
71. Richard Goodman Introduction to Rock Mechanics Second Edition (John Wiley and
Sons, New York: 1989)
72. Benjamin Cook & Richard Jensen Discrete Element Methods, numerical modeling of
discontinua (ASCE Geo-Institute, International Conference on Discrete Element Methods,
Santa Fe: 23-25 September 2002)
73. Geotechnical Special Publication 120 II (ASCE Geo-Institue, New Orleans: 10-12 February
2003)
74. William Morrison Grouting in deep flooded mines International Association of
Hydrological Sciences Publication 200 (IAHS Wallingford, Engl: 1991) p503-514
75. A.S. Derrington, Control of Water Discharge from Mine Ventilation Shafts 8th AusIMM
Underground Operators' Conference [electronic resource] : proceedings, growing our
underground operations : 29-31 July 2002, Townsville, Queensland. P31776. Bothma The rehabilitation of Impala No. 1A ventilation shaft Journal of The South
African Institute of Mining and Metallurgy 101.4 (July 2001): 177-182
77. Erhard Berger, Thomas Ahlbrecht, and Werner Bichler Sinking of the Primsmulde
ventilation shaft for Ensdorf colliery using the shaft bore technique Glueckauf Mining
Reporter 2003.1 (Verlag Glueckauf GmbH: January 2003) 13-20
78. William J. Maloney Blind drilling becoming an accepted technology for ventilation shafts
Mining Engineering 45.11 (Littleton, Colorado: November 1993) 1374-1376
79. John Zeni Ambitious endeavors in mechanized shaft construction: A case history of two
mine shaft projects in Australia Proceedings of the Rapid Excavation and Tunnelling
Conference 2001(Littleton, Colorado, U.S.: 2001): p171-177
115
80. A.R. Walsh, D.E. Hart, and Derek Maishman Shaft construction by raise boring through
artificially frozen ground Proceedings - Rapid Excavation and Tunnelling Conference 1991
(Seattle, WA: June 16-20 1991): p705-719
81. Rogar Nylund Oy Indau AB of Finland
82. McCracken and T. Stacey Geotechnical risk assessement for large-diameter raise-bored
shafts Transactions of the Institute for Mining and Metallurgy 1992?
83. N. Barton, R. Lieu, and J. Lunde Engineering Classification of rock masses for the design
of tunnel support Rock Mechanics VI (1974): p189-236
84. H.A.D. Kirsten The Combined Q-NATM System the design and specification of primary
tunnel support South African Tunnelling 6.1 (1984)
85. G. Lombardi Koelnbrein dam. An unusual solution for an unusual problem International
Water Power and Dam Construction 43.6 (June 1991): 31-34
86. G. Lombardi Grouting of Rock Masses Grouting and Ground Treatment (v1/2)
Proceedings of the 3rd International Conference (ASCE, Reston, Virginia: 2003): p164-197
87. Buddhima Indraratna, P.G. Ranjith , 2001, 'Laboratory Measurement of Two-Phase Flow
Parameters in Rock Joints Based on High Pressure Triaxial Testing', Journal of Geotechnical
and Geoenvironmental Engineering 127 530-542
88. Buddhima Indraratna, Naj Aziz, A. Dey , 2001, 'Behaviour of Joints Containing Clay Infill
Under Constant Normal Stiffness, with and without Bolting', Proceedings of the Institution
of Civil Engineers - Geotechnical Engineering, Vol 149, pp.259-267
89. G.E. Taylor, J.K. Cavey, and M.F. Roach Horizontal Grouting Beneath the Hollywood
Freeway. Los Angeles MetroRail C-311, Proceedings Rapid Excavation and Tunnelling
Conference (Las Vegas, Nevada, 1997): p73-81
90. Some effects of ellipticity on the fracturing and collapse behavior of a borehole
International Journal of Rock Mechanics and Mining Sciences 32.6 (September 1995):
p621-627
91. N. Phien-wej, U.B. Shresthal, and Ching-Yuan Ho Strength and displacements of model
infilled rock joints Developments in Geotechnical Aspects of Embankments, Excavations,
and Buried Structures (Asian Inst of Technology, Bangkok, Thail: 1991): p123-132
92. Shear strength of clay-filled bedding planes in limestones - back-analysis of a slope failure in
a phosphate mine, Israel
93. Y.H. Hatzor, and M. Levin Shear strength of clay-filled bedding planes in limestones back-analysis of a slope failure in a phosphate mine, Israel Geotechnical and Geological
Engineering 15.4 (December 1997): p263-282
94. Buddhima Indraratna, and Asadul Haque Shear behaviour of rock joints (Rotterdam :
Balkema, 2000)
95. Buddhima Indraratna, and A. Haque, Experimental and Numerical Modeling of Shear
Behaviour of Rock Joints GeoEng 2000 An International Conference on Geotechnical &
Geological Engineering. Volume 1, Invited Papers, CD ROMI (2000)
96. P.G. Ranjith, Buddhima Indraratna Coupled Air-Water Flow through Fractured
Sandstones GeoEng 2000 An International Conference on Geotechnical & Geological
Engineering. Volume 1, Invited Papers, CD ROMI (2000)
97. Ivan Carstensen Grouting and Drilling Services P.O.Box 151 Welshpool WA 6986 (2004)
98. Hermann Hamburger Application of Shaft Drilling in Civil Engineering Technical paper
presented at the International Shaft Drilling Technology, Las Vegas, April 1991 (Wirth
GmbH, Germany)
116
99. G. Mller Shaft Drilling Status and Potential Short Course Technical Paper presented at
Mechanical Excavation Techniques in Mine Development and Production, Golden,
Colorado, October 16-18, 1989 (Wirth, GmBH, Erkelenz, Germany)
100. Cyril Heever New Techniques in Deep pre-sinking of Mine Shafts Rapid Excavation and
Tunnelling Conference Proceedings 1991 p996-1003
101. Lawrence Nenham Director RUC Mining Contractors Pty Ltd. 2004
102. W. Weber Sizing of air-lift systems for drilling rigs Wirth GmBH, Erkelenz, Germany
103. A.S. Logan, D.OToole Shaft Assessment and Excavation Lessons from Rosebery Mine
Southern Upcast Shaft IX Australian Tunnelling Conference, Sydney, Australia 27-29
August 1996 p427-446
104. Gunder Homstvedt New Technology for Blind Hole Boring Rapid Excavation and
Tunnelling Conference Proceedings 1993 p169-180
105. Steven Hunt, Ronald Heuer, and Safdar Gill Casing collapse at the CT-8 dropshaft in
Milwaukee Rapid Excavation and Tunnelling Conference Proceedings 1995 p197-218
106. J.C. Zelanko and M.G. Karfakis Development of a Polyester-based Pumpable Grout
International Journal of Roch Mechanics and Mining Sciences 34.3/4 (Elsevier, UK, 1997)
595
107. V.B. Dubovskoi, V.G. Shilnikov, et.al. NI-2 Hole Inclinometer Soil Mechanics and
Foundation Engineering 40.3 (Plenum Publishing, May-June 2003) 104-108
108. Matthias Reich, Marcus Oesterberg, Hermilo Montes and Joachim Treviranus Straight
Down to Success: Vertical Drilling System for Top Hole and Subsalt Drilling Baker
Hughes INTEQ 2004
109. Zden?k Baant, Feng-Bao Lin, and Horst Lippmann Fracture Energry Release ans Size
Effect in Borehole Breakout International Journal for Numerical and Analytical Methods in
Geomechanics 17.1 (John Wiley & Sons Ltd, 1993)
110. M. Vijay Comparison of the performance of high-speed abrasive-entrained, cavitating and
plain jets for selective mining applications International Journal of Surface Mining and
Reclamation 6 (1992) 1-9
111. David Snow Packer Injection Test Data from Sites on Fractured Rock Lawrence Berkeley
Laboratories, LBL-10080, (1979), 15 p
112. Nick Barton TBM Tunnelling in jointed and faulted rock (A.A.Balkema: Rotterdam, 2000)
113. E.F. Matinhari Dams on deep foundations of weathered granite: solutions for reducing
under-seepage and prevention of piping failure (Delft, Masters Thesis: ITC Library, 1999)
114. National Academy of Sciences Drilling and Excavation Technologies for the Future
(National Acadamy Press: Wasington D.C., 1994)
115. Reuben H. Karol Chemical Grouting and Soil Stabilization Third Edition (Rutgers
University: New Brunswick, New Jersey, 2003)
116. Atlas-Copco Website, http://sg01.atlascopco.com/SGSite/Default.asp > Ground Engineering
Eq. > Dual Energy Percussion System (2004)
117. A.V. Ayugat Jr., J.H. Aquino and P. White Grouting and shaft sinking through waterbearing ground Multi-urethanes Homepage
http://www.multiurethanes.com/PDFfiles/pdf4.htm (1998)
118. Helen Anderson Chemical Rock Grouting An Experimental Study on Polyurethane
Foams (Chalmers University of Technology: Gteburg, Sweden, 1998)
119. sa Fransson and Gunnar Gustafson Characterization of Fractured Rock for Grouting
Design Using Hydrogeological Methods Grouting and Ground Treatment Proceedings of
117
120.
121.
122.
123.
124.
125.
126.
127.
128.
129.
130.
131.
132.
133.
134.
135.
118
the Third International Conference - vol. 2/2 (ASCE: Reston, Virginia, U.S., 2003) p10821088
PhD. S. Swedeborg and PhD. L.O. Dahlstrm Rock Mechanics Effects of Cement Grouting
in Hard Rock Masses Grouting and Ground Treatment Proceedings of the Third
International Conference - vol. 2/2 (ASCE: Reston, Virginia, U.S., 2003) p1089-1102
W.F. Heinz Mining Grouting: A Rational Approach Grouting and Ground Treatment
Proceedings of the Third International Conference - vol. 2/2 (ASCE: Reston, Virginia, U.S.,
2003) p1115-1129
Arthur. H. Walz, David. B. Wilson, Donald A. Bruce and James A. Hamby Grouted
Seepage Cutoffs in Karstic Limestone Grouting and Ground Treatment Proceedings of
the Third International Conference - vol. 2/2 (ASCE: Reston, Virginia, U.S., 2003) p11151129
Buddhima Indraratna and Asadul Haque Shear Behaviour of Rock Joints (Dept. of Civil,
Mining and Environmental Engineering, University of Wollongong / Balkema, Rotterdam:
2000)
Eric Landry, Daniel Lees and Alex Naudts "New Developments in Rock and Soil Grouting:
Design and Evaluation." Geotechnical News (September 2000) p38-44
Alex Naudts and Stephen Hooey "Hot Bitumen Grouting: The antidote for catastrophic
inflows" Grouting and Ground Treatment Proceedings of the Third International
Conference - vol. 2/2 (ASCE: Reston, Virginia, U.S., 2003) p1293-1303
Mine Safety and Health Administration Mining Fatality Statistics from 1911 through 2003
http://www.msha.gov/ > Fatality Charts > Metal/Non-metal (2004)
Minerals Council of Australia - The Safety and Health Performance Report of the Australian
Minerals Industry 2002 2003 http://www.minerals.org.au > Links > Information Centre >
Publications (2003)
Herrenknecht AG http://www.herrenknecht.com > Tunnelling Machines > Augering
machines (2002)
Howard Hartman and Jan Mutmansky Introductory Mining Engineering (John Wiley &
Sons, New Jersey, 2002) p282-283
BHP Billiton HSEC Repor 2003 Home http://www.bhpbilliton.com/ > Sustainable
Development > Reports > HSEC Report 2003 > Case Studies > Safety > 9. Dendrobium
Vent Shaft Innovation
[http://www.bhpbilliton.com/hsecReport/2003/caseStudies/cs_safety09.html]
Malcolm Puller Deep Excavations: a practical manual (Thomas Telford: London, 2003)
p450-519
Y. Obara, K. Kaneko and K. Sugawara Measurement of local stress and estimation of
regional stress http://www.asiaoceania.org/ > 2004 Abstract Listing > Solid Earth > 57OSE-M259 Asia Oceania Geosciences Society
Drill hole Deviation Survey Systems The art of straight holes http://www.reflex.se >
Downloads
Drill hole Deviation Survey Systems How Maxibor works http://www.reflex.se >
Downloads
Serco Assurance NAPSAC High performance package for modelling groundwater flow
and transport through fractured media http://www.sercoassurance.com/ Environmental
management > environmental assistance > NAPSAC
136. Rocscience Unwedge theory manual http://www.rocscience.com > Products > Excavation
design > Unwedge > Theory Manual
119
Glossary
Big hole drilling or
Blind hole Drilling
Boring
Clippings
Cuttings
Drilling
Fracture
Joint
Muck
Mucking
Mud
Overburden
Pre-reinforcement
Tailings
Shotcreting
Fibrecreting
Grout
120
Stepwise benching
Alimak raising
Fault
121
122
[m]
Total Depth
Location
Phreatic level /
Overburden type
Overburden depth
Contractor
Mining
company
[m]
[m]
Drilling
method
Stabilis.
method
Final lining
raiseboring
(in the end:
conventional
shaft sinking)
minipiling
remote fibrecreting
raiseboring
jet-grouting. Also
augering of walls
to 30m depth and
augering out of
inside 6m
diameter
remote shotcreting
b.h.drilling
bentonite drilling
fluids + steel
grouted up final
liner (steel?)
composite concrete
AMC /
Wellnavinc
Newmont
Callie, N.T.,
AUS
4.5
Soft to hard rock with narrow clayfilled jointing. Dry down to approx
70m. weathering. Some hard
quartzite veining.
120
AMC / Bachy
Soletanche
Cannington
Mine
Cannington,
Qld, AUS
60
Ardent /
Abergeldie
BP Billiton
North
Qoonyella,
Qld, AUS
3.15
110
Springvale,
Nsw, AUS
(4.3)
4.7
1 auqifer
ex.weath.sandstone, sand
67
367
b.h.drilling
polymer mud +
steel
Leinster,
W.a., AUS
(2.4
pilot)
7.0
48/76
805
presink to 48,
raiseboring
2.4m diam,
b.h.post-sink
to 80m
Horadiam on
rest of shaft.
Ardent /
Abergeldie
Coffey
Geosciences
WMC
Resources
Limited
500
123
Crinum
Colliery
Bowen
Coalfield,
Qld, AUS
North Selby
Coalfield
Yorkshire,
UK
Drilling
method
Stabilis.
method
Final lining
Cage of
reinforcement
>400
Bendigo,
Nsw, AUS
2.4
4.8
Frontier
Kemper
Construction
White
County Coal
Illinois, U.S.
Frontier
Kemper
Construction
White
County Coal
Illinois, U.S.
Potash
mining
(some
Uranium)
Saskatchewan
, CA
124
Total Depth
Location
Phreatic level /
Overburden type
Overburden depth
Contractor
Mining
company
6m
60
Two fast
flowing
aquifers
Moderate to hard
rock, alternated by
running sands.
42
257
9001100
Ground freezing
raiseboring
Extra grouted
cable dowels,
because drilling
was needed
anyway to check
for existing mine
workings
Notes:
One hole deviated
into the raise, but
was reamed
succesfully.
b.h.drilling
temporary lining
10mm thickness
steel can and
drilling mud
composite lining
102 2.46m tall x
3.86m o.d. x
210mm thick
composite concrete
segments
raiseboring
freezing
conventional
d&b /
excavation
and hoisting
freezing &
tubbing, cement
grouting
Lake Meed
Constructor
s,
subcontracto
r: Zeni
Las Vegas,
Nevada
Longos Mine
mainshaft
United
Paragon
Mining
Corp.
Paracale,
Camarines
Norte,
Philippines
Stawell
minesite
Stawell
Gold / WMI
Total Depth
6,510m
Lake Mead
Intake No. 2,
access shaft
Overburden depth
Location
Contractor
Mining
company
??
70+
??
grouting
257m
500
conventional
d&b /
excavation
and hoisting
76m
Phreatic level /
Overburden type
mostly below water table
soil, weathered rock in first metres
Drilling
method
Stabilis.
method
Final lining
reinforced cast-inplace concrete
Notes:
Abandoned in 1984 with water inflows >
850 GPM, Fixed with intensive downthe-shaft grouting, polyurethane
grouting and intense monitoring
403
125
Middelbult
and
Bosjesspruit
mines
(3 shafts)
Sasol
Minings
(RUC)
Dendrobium
Mine
BHP
Billiton
Dendrobium
Mine, NSW,
Australia
SoletancheBachy
Eastern
Harbour
Crossing,
Honk Kong
Freezewall
126
7,1m
Speckholzerh
eide, Holland
4,6m
Anonymous
example
4m
Phreatic level /
Overburden type
Shaft 1: Sandstones and siltstones
<100 MPa Shaft 2: some dolerite
areas with 1,4m blocks and a few
serpentine (dissolves in air) filled
zones
10m
Total Depth
Location
Overburden depth
Contractor
Mining
company
Stabilis.
method
Final lining
Raiseboring;
Concrete shaft placed to 10m depth
for weak overburden - Then
percussion holes drilled, grouted
and reinforced to 5m beneath
dolerite depth. (250mm diameter,
0,5m from shaft and 0,5m between
centres) - Also cable doweling (24
x 89mm diameters) on a 1,2m grid.
some flash
shotcrete to
stabilise serpentine
layers within 55
days of reaming.
Notes:
Biggest raisebored
shaft in the world
60m
some polyurethane
remote postgrouting
+/40m
hydrofraise
Diaphragm walls
72m
hydrofraise
Diaphragm walls
100m
90 &
173
Drilling
method
Company
Location
Subject
Warren Peck
Australian Mining
Consultants
Melbourne, Australia
Max Lee
Melbourne, Australia
Australian Mining
Consultants
Melbourne University
Melbourne, Australia
Civil tunneling
Wilhelm J.
Kogelmann
Nederland, Texas,
U.S.A.
Markel Hoffman
Mike Woof
World Mining
Equipment
www.wme.com
Juergen
Schauwecker
Deilmann-Haniel
company
SE Tecnologie
Avanzate
(Powermole)
Atlas Copco
Construction &
Mining Australia
Germany
Wheelers Hill,
Australia
Geotechnical
Engineering
Wellbore Navigation
Inc.
www.geotech.net.au
Deep Foundations
Institute (ASCE);
formerly Institute of
Shaft Drilling
Technology
Byrnecut Mining Pty
Ltd.
Seattle, U.S.A.
Kalgoorlie, Australia
Stanley Mining
Services
Malaga, Australia
Alan Halse
Nick Morgan
Steve Coughlan
Ortona, Italy
www.wellnavinc.com
Tustin, Canada
127
Mark Berry
Sharyn Dawson
Alain Dumont
www.dem.csiro.au
Kenmore, Australia
Assessement of ground
behaviour during mining
www.dem.csiro.au
Kenmore, Australia
www.dem.csiro.au
Kenmore, Australia
www.montali.com
Quebec, Canada
Bill Shaver
Dynatec Corporation,
mining services
division
www.dynatec.ca
Ontario, Canada
Alan Zeni
Zeni Drilling
Company
www.ardent
underground.com
Morgantown, United
States
Expert contractor:
Blind hole drilling.
D. Keward
Dosco Overseas
Engineering Ltd.
Newark, United
Kingdom
Dan O'Toole,
Delia Sidea
Bob Gee
Coffey Geosciences
Perth, Western
Australia
Rhodes, Australia
Mining Consultanti:
Expert horadiam technique
Expert Civil tunnelling
engineer. Head of AUCTA.
J. Donohoe
FreezeWall
www.moretrench.com
Rockaway, U.S.A.
Eric Downing
Walter Construction
AUCTA
Freysinet (Austress in
oz)
Soletanche-Bachy
Michael Cals
128
Wirth Europe
Vlizy , France
www.soletanchebachy.com
www.wirth-europe.de
Wirth Europe
www.wirth-europe.de
J.S. Redpath
www.jsredpath.com
Ontario, Canada
Henry Laas
Marius
Oosthuizen
www.murrob.com/RU
C/
South Africa
www.murrob.com/RU
C/
South Africa
Finland
Skansk
Sweden
Gunnar Nord
Atlas Copco
Sweden
Jol Jardine
Mechanised mining
services
Australia
Manfred
Voerckel
George Martin
karl Guilfoyle
Australia
Lombardi Engineering
Mark Berry
Minusio, Switzerland
www.reflex.se
Frontier Geo
www.frontiergeo.com
www.icefieldtools.co
m/docs/
www.bennetmg.co.uk
MG Bennet &
Associates Ltd
David Holton
Serco Assurance
W. Heinz
Rodio
Verstraeten
Funderingstechniek
Kjell Gustaffson
www.sercoassurance.c
om
Harwell Didcot,
United Kingdom
Freestate, South
Africa
www.fundex-group.nl
Oostburg, Netherlands
Expert on pre-reinforcement.
Extensive knowledge of shaft
collapses in South Africa
Expert on cut-and-cover
methods, shaft drilling in soft
soils.
129