Pa ge Fabrication Quality Assurance / Quality Control Plan [ProjectName] [ProjectNumber] ed le Se Version Version notes Initial issue Approved [QualityManagerName], Quality Manager documents provided by [CompanyName] disclose proprietary information as well as copyright information registered with the u.s. Patent and trademark office.

Uploaded by

P behera
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
208 views14 pages

1049 Essentials Steel Fabrication Welding Sample

Pa ge Fabrication Quality Assurance / Quality Control Plan [ProjectName] [ProjectNumber] ed le Se Version Version notes Initial issue Approved [QualityManagerName], Quality Manager documents provided by [CompanyName] disclose proprietary information as well as copyright information registered with the u.s. Patent and trademark office.

Uploaded by

P behera
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 14

Essentials Fabrication

Quality Plan Sample

Selected pages not a complete plan


Includes Standards and Forms for Structural Steel
Fabrication

Contact:
First Time Quality
410-451-8006

Pat
[Pick the date]

Questions? Call First Time Quality 410-451-8006

[ImagePlaceHolder]

[CompanyName]

Pa
ge

Fabrication
Quality Assurance/Quality Control Plan
[ProjectName]
[ProjectNumber]

ed

Version: 20150308

Effective Date: 20150308

le
Se

20150308

ct

Version

Version notes

Initial issue

Approved

_____________________________________________________
[QualityManagerName], Quality Manager

Documents provided by [CompanyName] disclose proprietary information as well as copyright information


registered with the U.S. Patent and Trademark Office. Please hold these documents in confidence and do
not share them with other organizations, even if you do not charge a fee. Submittal of documents does not
transfer copyright ownership.

Questions? Call First Time Quality 410-451-8006

PROJECT-SPECIFIC WELDING QUALITY PLAN


TABLE OF CONTENTS
A. [CompanyName] Quality Policy ........................................................................................................... 3
B. Key Elements of the Weld Quality Plan ................................................................................................ 4
C. Project Quality Coordination and Communication ............................................................................... 7
D. Project QC Personnel ......................................................................................................................... 11
Project QC Job Position Assignments ....................................................................................................... 11
Duties, Responsibilities, and Authority of QC Personnel .......................................................................... 11
Quality Responsibilities ............................................................................................................................ 11
Project QC Organization Chart ................................................................................................................. 14

E. Personnel Qualifications and Technical Certifications ........................................................................ 15

Pa
ge

Personnel Certification and Qualification Requirements ......................................................................... 16


Training ..................................................................................................................................................... 17
F. Qualification of Third Party Inspection/Testing Companies and Subcontractors and Suppliers .......... 19
Qualification of Testing Laboratories ....................................................................................................... 19
G. Weld Project Quality Specifications ................................................................................................... 21

ed

Compliance with Industry Welding Standards ......................................................................................... 21


Project - Specific Welding Procedure Standards ...................................................................................... 22
H. Material Traceability ......................................................................................................................... 28

ct

Identification of Lot Controlled Materials ................................................................................................ 28

le

I. Weld Inspection and Test Plan ............................................................................................................ 31

Se

Welding Inspection and Testing Standards .............................................................................................. 32


Control of Inspection, Measuring, and Test Equipment ........................................................................... 33
J. Welding Work Task Quality Inspections .............................................................................................. 36
Work Tasks Series of Inspections ............................................................................................................. 36
Daily Quality Control Report..................................................................................................................... 36
K. Quality Control of Corrections, Repairs, and Nonconformances ........................................................ 48
L. Project Completion Inspections .......................................................................................................... 50
M. Quality Assurance Surveillance ......................................................................................................... 52
N. Control of Quality Records and Documents ....................................................................................... 54
O. Servicing and Warranty ..................................................................................................................... 55

Page 2

[CompanyAddress1] [CompanyAddress2] [CompanyPhone] [CompanyPhone2]


Copyright

Questions? Call First Time Quality 410-451-8006

G. WELD PROJECT QUALITY SPECIFICATIONS


Fulfilling customer contract expectations is a primary objective of the [CompanyName] Quality System. To
ensure that customer expectations will be fulfilled, [CompanyName] clearly defines the requirements for
each contract before it is approved.
The Project Manager ensures that the information in customer contracts clearly defines customer
expectations and that the necessary details are provided to set requirements for fabrication.
[CompanyName] personnel and subcontractors and suppliers are accountable for compliance to
standards-based written specifications.
To achieve expectations reliably and consistently, specifications are clearly spelled out, not only for results
but also for processes. Specifications apply to materials, work steps, qualified personnel and
subcontractors and suppliers, safe work rules, and environmental work conditions.

Standards ensure that results are specified rather than left to discretionary practices.

Pa
ge

All [CompanyName] fabrication activities comply with generally accepted good workmanship practices
and industry standards.

COMPLIANCE WITH INDUSTRY WELDING STANDARDS

ed

Codes that may apply to this project include those listed below.

Regulatory Codes and Industry Standards

ct

Reference Standard
No.

Description

Minimum spacings and edge


distances for screws

AISI SG02-KIT

North American Specification for the Design of Cold-Formed Steel


Structural Members

Installation of bracing and


permanent bracing and bridging

CFSEI

Field Installation Guide for Cold-Formed Steel Roof Trusses

Installation of chimneys, vents, and


smokestacks

NFPA 211

Standard for Chimneys, Fireplaces, Vents, and Solid Fuel-Burning


Appliances

Framing and reinforcing openings


through a steel deck

SDI DDP

Deck Damage and Penetrations

Install high-strength bolts

Welding standards

AWS B2.1/B2.1M

Specification for Welding Procedure and Performance Qualification

Standard practices for structural


steel fabrication bound series of
standadards

AISC Code of Standard


Practice for Steel Buildings
and Bridges

AISC Code of Standard Practice for Steel Buildings and Bridges

Specification for steel fabrication for


structural steel buildings

AISC Specification for


Structural Steel Buildings

AISC Specification for Structural Steel Buildings

Structural steel joints

RCSC Specification for


Structural Joints Using
ASTM A325 or A490 Bolts

RCSC Specification for Structural Joints Using ASTM A325 or A490


Bolts

Se

le

Division

Reference Standard Title

RCSC's "Specification for Structural Joints Using ASTM A 325 or A


490 Bolts"

Page 21

[CompanyAddress1] [CompanyAddress2] [CompanyPhone] [CompanyPhone2]


Copyright

Questions? Call First Time Quality 410-451-8006

Standar design symbols

ANSI/AWS A2.4

Symbols

Standard terms

ANSI/AWS A3.0

Terms and Definitions

QA recommended practices

AWS Welding Quality


Assurance Guideline for
Fabricators (WQAG)

Welding Quality Assurance Guideline for Fabricators (WQAG)

Coating of steel

SSPC Steel Structures


Painting Manual, Volume I,
Good Painting Practice

Steel Structures Painting Manual, Volume I, Good Painting


Practice

Coating of steel

SSPC Steel Structures


Painting Manual, Volume II,
Systems and Specifications

Steel Structures Painting Manual, Volume II, Systems and


Specifications

Special provisions for seismic


applications

AISC Seismic Provisions for


Structural Steel Buildings

Seismic Provisions for Structural Steel Buildings

Detailing standards for the design of


structural steel details

AISC Detailing for Steel


Construction

Detailing for Steel Construction

Workmanship and techniques for


welded construction

AWS D1.1/D1.1M

Structural Welding Code Steel

Pa
ge

PROJECT - SPECIFIC WELDING PROCEDURE STANDARDS


The Quality Manager approves welding procedures before they can be used to fabricate metal.

ed

Welding procedures shall be qualified and approved, in accordance with the applicable AWS Welding
Code(s) or Specification(s) (i.e., D1.1., D1.5) or AWS B2.1, Specification for Welding Procedure and
Performance Qualification.
The welding procedure must identify the filler material.

Se

le

ct

When the governing AWS Welding Code(s) mandates that welding procedures be qualified by test, the
Welding Fabricator shall have PQRs that support the applicable WPSs. When prequalified WPSs or
Standard Welding Procedure Specifications (SWPSs) published by the AWS are permitted, PQRs are not
required.
The Quality Manager or Certified Welding Inspector (CWI) reviews and approves the welding procedure
before being used in production welding operations.
The WPSs and PQRs are controlled by the Quality Manager according by the document and record control
procedures specified in the relevant section of this Quality Manual.
The applicable WPSs shall be available to welders or welding operators during testing and production
welding.

Page 22

[CompanyAddress1] [CompanyAddress2] [CompanyPhone] [CompanyPhone2]


Copyright

Questions? Call First Time Quality 410-451-8006

Se

le

ct

ed

Pa
ge

Form N-1 Welding Procedure Specification Prequalification

Page 23

[CompanyAddress1] [CompanyAddress2] [CompanyPhone] [CompanyPhone2]


Copyright

Se

le

ct

ed

Pa
ge

Questions? Call First Time Quality 410-451-8006

http://www.aws.org/technical/forms/N-1.pdf

Page 24

[CompanyAddress1] [CompanyAddress2] [CompanyPhone] [CompanyPhone2]


Copyright

Questions? Call First Time Quality 410-451-8006

Se

le

ct

ed

Pa
ge

Form N-3 WPS QUALIFICATION TEST RECORD_ELECTROSLAG


and ELECTROGAS WELDING

http://www.aws.org/technical/forms/N-3.pdf

Page 25

[CompanyAddress1] [CompanyAddress2] [CompanyPhone] [CompanyPhone2]


Copyright

Questions? Call First Time Quality 410-451-8006

Se

le

ct

ed

Pa
ge

Form N-4 WELDER, WELDING OPERATOR, OR TACK WELDER


QUALIFICATION TEST RECORD

http://www.aws.org/technical/forms/N-4.pdf

Page 26

[CompanyAddress1] [CompanyAddress2] [CompanyPhone] [CompanyPhone2]


Copyright

Questions? Call First Time Quality 410-451-8006

Se

le

ct

ed

Pa
ge

Form N-9 STUD WELDING APPLICATION QUALIFICATION TEST


DATA

http://www.aws.org/technical/forms/N-9.pdf

Page 27

[CompanyAddress1] [CompanyAddress2] [CompanyPhone] [CompanyPhone2]


Copyright

Questions? Call First Time Quality 410-451-8006

H. MATERIAL TRACEABILITY
Products and materials are controlled to assure the use of only correct and acceptable items. Controls
include identification of the inspection status. Materials that require lot control traceability and the
method of traceability are listed on the Controlled Materials form included as an exhibit in this
subsection.

IDENTIFICATION OF LOT CONTROLLED MATERIALS


The Quality Manager determines types of project materials that require quality controls.
For each type of quality controlled material, the Quality Manager determines lot control traceability
requirements, if any, and specifies the means of lot identification. Identification methods may include
physical labels, tags, markings and/or attached certification documents.

Pa
ge

When lot controlled materials are received, the Superintendent verifies that materials have the specified
lot identifications.
The Superintendent maintains lot identification at all production phases from receipt, through production,
installation, or assembly, to final completion. Acceptable methods for preserving lot identification include
physically preserving observable lot identifications, recording the lot identification on a work task quality
inspection form or other work record, or collecting the physical lot identifier as a record along with
supplemented with location.

Se

le

ct

ed

If lot controlled materials are without lot identification, the Superintendent deems the materials as
nonconforming and segregates them and/or clearly marks them to prevent inadvertent use. The
Superintendent treats the material according to the company policy for nonconformances. Only the
Quality Manager can re-identify or re-certify the materials.

Page 28

[CompanyAddress1] [CompanyAddress2] [CompanyPhone] [CompanyPhone2]


Copyright

Questions? Call First Time Quality 410-451-8006

[CompanyName]
Controlled Materials Form
Version 20150308

Date

Lot Traceability
Requirements

Pa
ge

Intended Use
(if description is necessary)

[ProjectName]

ed

Material

ct

Contract Section/ Activity


ID

Preparer

le

[ProjectNumber]

Contract Name

Se

Contract ID

Page 29

[CompanyAddress1] [CompanyAddress2] [CompanyPhone] [CompanyPhone2]


Copyright

Method for identification of


Approved Inspection Status

Questions? Call First Time Quality 410-451-8006

[CompanyName]
Material Inspection and Receiving Report
Version 20150308

[ProjectNumber]

[ProjectName]
Stock/Part
No.

Supplier
Quantity
Received

Description

Bill of Lading No.

Condition

Marking

ed

Item No.

Purchase Order No.

Contract Name

Pa
ge

Contract ID

Listed items have been accepted by me or under my supervision

le

ACCEPTANCE

ct

Receiving Quality Control

Se

Conform to contract specifications EXCEPT as noted herein or on supporting documents.


Received in apparent good condition EXCEPT as noted

Signature of authorized person and date: _________________________________________________________________


EXCEPTIONS:

Page 30

[CompanyAddress1] [CompanyAddress2] [CompanyPhone] [CompanyPhone2]


Copyright

Accept

Conditional
Use

Date

Reject

Pa
ge

Questions? Call First Time Quality 410-451-8006

ed

For More Information:


Contact: FirstTimeQuality

le

ct

410-451-8006

Se

www.FirstTimeQuality.com

[email protected]

For More Information, contact: CaldeiraQuality, LLC First TimeQuality.


4104518006 www.firsttimequality.com [email protected]