DRC - Nyumba Ya Akiba Cement Plant - ESIA Summary
DRC - Nyumba Ya Akiba Cement Plant - ESIA Summary
PROJECT:
COUNTRY:
Team Leader
:
Team Members :
Project
Team
Sectorial Director :
Regional Director :
Division Manager :
T. TURNER
M. KANGA
M. NIANG
Page 2
Department: OPSM
Table of Contents
1
Introduction .................................................................................................................... 3
Page 3
1 Introduction
Nyumba Ya Akiba SARL (NYA), a joint venture between Lucky Cement Pakistan and Groupe
Rawji DRC, proposes to construct a 3,000 tonnes per day clinker and 3,580 tonnes per day cement
manufacturing facility, limestone quarry and associated facilities in Bas-Congo Province of DRC.
The project was approved by local authorities in 2011, following an Environmental Impact
Assessment (EIA) by an accredited local consultant, OEMS. Subsequently, an Environmental and
Social Impact Assessment (ESIA) for lender approval was submitted in March 2013 by the
Pakistani consulting firm ECTECH. Gaps in this ESIA relative to the requirements of international
funders were identified via an independent environmental and social due diligence (ESDD) by
ERM on behalf of the lenders.
To address these gaps, NYA appointed SRK Consulting (SRK) in June 2013 to prepare an updated
ESIA and Environmental and Social Management Plan (ESMP) for the Nyumba Project (the
project), in line with good international industry practice (GIIP) based on AfDB, the IFC
Performance Standards and other lender requirements. Key findings relating to this ESIA update,
are therefore included in this Executive Summary.
Page 4
Layout
The project will consist of a cement production plant, limestone quarry, and associated facilities, as
shown on the preliminary site layout drawing (see Erreur ! Source du renvoi introuvable.). The
cement plant will be supplemented by limestone and clay from mining concessions located
approximately 1.5 km north of the cement plant site. An access road linking the plant to the N1, and
a haul road between the quarry and plant (following an existing track), will be constructed, as well
as a power line, linking the project to the national energy grid. The total footprint area of the project
will be approximately 150 ha (boundary of concession area).
The Key Components of the Project include: (i) Cement plant (annual production capacity 1.18
Million tpa); (ii) Limestone quarry; (iii) Overburden storage facility; (iv) 220 KV powerline (6 km
long) to an existing substation; (v) Employee accommodation camps (for 300 personnel); (vi)
Waste management facility; (vii) Access and haul roads; (viii) Railway connection to the national
rail network; (ix) Auxiliary facilities (water management infrastructure, package sewage treatment
plant, explosives store, etc.).
While the final locations and design of certain infrastructure, including the overburden storage
facility, waste management facility, and water management infrastructure, have not been
determined, potential locations for some of these are indicated on Erreur ! Source du renvoi
introuvable., based on a high level sensitivity analysis by SRK. The final locations and design of
these facilities will however depend on the outcomes of further site-specific investigations.
Page 5
finalised). Raw material (limestone, laterite and clay) extraction will involve: (i) Stripping of
overburden by excavators; (ii) Excavation of the limestone deposit using mechanical drills and
blasting; (iii) Loading of the raw materials from the quarry onto dump trucks for transportation to
the plant along the haul road over a distance of 1.5 km. As the quarry depth increases, dewatering
of the pit will be required to remove groundwater inflows. This could potentially amount to
substantial volumes of pit water being discharged. The quality and quantity of this water are still to
be confirmed via further studies.
Page 6
Figure 2: Site locality map showing quarry, plant and associated infrastructure (including existing infrastructure
Page 7
Cement production
NYA has selected FLSmidth (FLS) of Denmark as the design engineering and procurement
contractor for the cement plant. The cement manufacturing process involves six steps, as shown
diagrammatically in Erreur ! Source du renvoi introuvable.:
1.Raw material preparation, blending and storing: Raw material transported from the quarry
will be crushed, blended in the required proportions and stockpiled in a storage area before
being conveyed to the Raw Mix Proportioning Station.
2.Raw material proportioning and grinding: The blended material will be mixed with other
additives and transferred to the Raw Mill for grinding. After grinding, the Raw Meal will be
transferred to the Blending Silo for storage and further blending.
3.Pre-Heater Phase: Meal from the Blending Silo will be fed into a preheater, from where it will
pass through Cyclones and Feed Pipes and finally through a Pre Calciner before feeding into the
Kiln.
4.Kiln Phase: The Calcined Raw Meal passes through a rotating Kiln and is subjected to
temperatures of 1450C, causing it to be converted to clinker.
5.Cooling: The clinker drops into a cooler at the discharge end of the Kiln, cooling it to 65C +
ambient temperature, before being discharged to the Clinker Storage Yard.
6.Clinker Grinding: The clinker is transferred from the Clinker Storage Yard to the Cement
Proportioning Station. Clinker is withdrawn and Gypsum (Calcium Sulphate) added to it,
followed by transfer of the mix to the Grinding Mill for fine grinding before being transferred to
the Cement Silos for storing.
7.Packing and Transport: The ground cement will be stocked into silos before being transferred
to two packing plants for packaging into 50 kg bags for dispatch. The project will primarily
service the local cement market, supplemented by exports to neighbouring countries.
Page 8
materials, sample preparation, chemical analysis and physical testing will take place in the on-site
laboratory. While the plant will operate 24 hours a day, certain components such as the crushers,
will operate during daylight hours only.
Environmental controls: Various dust control measures, including filters, are included in the plant
design to minimise dust emissions during cement manufacturing.
Fuel: Coal fuel for the cement plant will be imported from South Africa via ship, and transported
from Matadi Port to the site via either by road or preferably by rail. For this purpose, a railway
siding on the western side of the plant has been included in the design.
Power and Water supply: Power for the project will be sourced from the DRC national electricity
grid, with generators available at the plant for emergency supply to essential equipment. This will
not however be sufficient to maintain operation of the plant. Raw water supply will be obtained
from either the rivers in the area, or groundwater sources. Where possible, process water will be
recycled.
Page 9
Page 10
medicinal plants, grazing for livestock, and potable water. Many of the resources in the area are
depleting due to pressure from unsustainable agricultural practises.
5. Project alternatives
Various alternatives have/ are being considered as part of the project process. The no-go
alternative would perpetuate dependency on cement imports into DRC and is not considered
further. Project site alternatives within Bas Congo were limited by requirement for close proximity
to reserves of quality limestone, clay and laterite, transport routes, as well as the national power
grid. Within the site, high-level environmental screening was carried out which influenced the
location of the overburden stockpile, waste management facility and haul road alignment. Surface
Page 11
and groundwater studies have been commissioned by NYA and layout plans may require
amendment in line with findings.
Sub-surface open cast mining and underground mining were considered as mining method
alternatives, with sub-surface open cast mining being selected as the most safe and economical
approach. Chosen cement production technology is state of the art Best Available Technology
(BAT) for environmental controls and energy efficiency. Water-saving dry process technology and
open recirculating cooling systems are being implemented. Energy-saving is being achieved
through choice of vertical roller mills, as well as 5-stage preheater with pre-calciner. Air pollution
control methods to be implemented include fabric filters and electrostatic precipitator (ESP)
technologies. Coal (to be imported) is preferred to HFO for clinker production based on cost. Raw
water for process cooling and domestic use is still under investigation, and will be sourced either
from surface water resources (the Yuku and Sanzikua rivers); or groundwater abstraction (possibly
linked to pit dewatering at the quarry).
A waste management facility (WMF) will be developed for non-mining waste including hazardous
waste from the project. Co-processing (incineration) or project-generated and local waste will
require feasibility assessment after commencement of operation before its viability is confirmed.
Co-disposal of waste with the overburden from the quarry is not being pursued, for reasons
including undetermined effects on groundwater. Process water at the cement plant will be recycled,
reducing the raw water requirement. Package sewage treatment plants have been chosen over septic
tank based on the improved treatment of sewage and larger numbers of employees which the system
can deal with.
Page 12
Table 1: Summary of impact significance ratings before and after implementation of recommended management measures
Impact Significance
Impact
groups
Identified impacts
Premanagement
Postmanagement
CONSTRUCTION PHASE
Biophysical impacts
Visual
Soils, land
capability &
land use
Impact VI1: Loss of sense of place affecting local communities due to site clearing and construction activities
Medium (-ve)
Low (-ve)
Impact SL1: Placement of project infrastructure, resulting in a transient loss of soil resource, and change in soil characteristics, land
capability and land use
Medium (-ve)
Medium (-ve)
Impact SL 2: Placement of permanent project infrastructure, resulting in a permanent loss of soil resource, and change in soil characteristics,
land capability and land use
Medium (-ve)
Medium (-ve)
Impact SL 3: Spillage of chemicals and seepage from waste resulting in permanent loss of soil resource, and change in soil characteristics,
land capability and land use
Medium (-ve)
Low (-ve)
Impact SL4: Site clearance resulting in a permanent loss of soil resource, and potential change in soil characteristics, land capability and
land use as a result of increased erosion
Medium (-ve)
Low (-ve)
Impact AQ1: Increase in PM10 emissions resulting from land clearing, earthworks, and vehicular movement
Low (-ve)
Low (-ve)
Impact AQ2: Increase in gas (SO2, NOx, CO and VOCs) emissions resulting from vehicle exhaust emission and biomass burning
Low (-ve)
Low (-ve)
Impact WR1: Chemical contamination of surface water resulting from accidental spills during transportation and handling, and seepage from
waste
Low (-ve)
Low (-ve)
Impact WR2: Sedimentation of surface water resulting from erosion and runoff from exposed surfaces and roads
Low (-ve)
Low (-ve)
Impact WR3: Contamination of groundwater resulting from seepage from sewage and other waste
Low (-ve)
Low (-ve)
Impact NV 1: Continuous noise impact on Mbemba Village resulting from night-time construction at the quarry
Low (-ve)
Low (-ve)
Impact NV 2: Air-blast noise impact on Mbemba Village resulting from blasting at the quarry during construction
Low (-ve)
Low (-ve)
Impact EB1: Loss of savanna habitat due to site clearing and earthmoving activities
Medium (-ve)
Low (-ve)
Impact EB2: Loss of forest habitat due to site clearing and earthmoving activities
Medium (-ve)
Low (-ve)
Impact EB3: Loss of aquatic habitat due to site clearing and earthmoving activities
Medium (-ve)
Low (-ve)
Air quality
Water
resources
Noise and
Vibration
Ecology &
Biodiversity
Page 13
Impact Significance
Impact
groups
Traffic
Identified impacts
Premanagement
Postmanagement
Impact EB4: Loss or disturbance of species of special concern due to site clearing and construction activities
Medium (-ve)
Low (-ve)
Impact EB5: Loss or degradation of ecological processes due to site clearing and construction activities
Medium (-ve)
Low (-ve)
Impact EB6: Fragmentation of habitats and ecological processes due to positioning of project infrastructure
Medium (-ve)
Low (-ve)
Impact EB7: Modification or degradation of aquatic habitats due to altered hydrological regimes and surface or groundwater quality
Medium (-ve)
Medium (-ve)
Impact EB8: Introduction of alien invasive plants due to site clearing and disturbance of vegetation
Medium (-ve)
Low (-ve)
Impact EB9: Impeded photosynthesis and transpiration rate of plants due to dust generation
Low (-ve)
Low (-ve)
Impact T1: Impact of construction related traffic on utilisation capacity on the N-1
Medium (-ve)
Low (-ve)
Medium (-ve)
Low (-ve)
Impact T3: Safety impacts on local communities and other road users due to increased road accident rates during construction
Medium (-ve)
Medium (-ve)
Medium (-ve)
Low (-ve)
Impact HS1: Increased chances of the spread of communicable diseases such as HIV/AIDS and STDs linked to influx of predominantly
male job-seekers and workers
Low (-ve)
Low (-ve)
Impact HS2: Increased pressure on healthcare infrastructure due to project related influx
Medium (-ve)
Low (-ve)
Impact HS3: Increased risk of accidents and injuries to communities from improved roads and additional traffic
Low (-ve)
Low (-ve)
HS4: The visible presence of DRC police within the project area, and their secondment as a subcontractor for the mine security
Low (-ve)
Low (-ve)
Impact LN1: Physical displacement of households residing at Yuku Village and the protection of vulnerable groups
High(-ve)
Medium(-ve)
Impact EC1: Local and regional benefits resulting from increased Revenue to Government
Low (+ve)
n/a
Low (+ve)
n/a
Socio-economic impacts
Population &
Demographic
movement
Health &
Safety
Land &
Natural
Resources
Economic
Impacts
Impact PD1: Influx of potential job seekers into the area and associated risks
Page 14
Impact Significance
Impact
groups
Cultural
Heritage
Resources
Ecosystem
Services
Identified impacts
Premanagement
Postmanagement
Impact EC3: Generation of direct, indirect and induced employment and income
Medium (+ve)
Medium (+ve)
Impact CH1: Indirect damage to Iron Age archaeological resources through land transformation activities
Medium(-ve)
Low(-ve)
Medium(-ve)
Low (-ve)
Impact ES1: Reduced availability of natural resources and ecosystem services to local communities
Medium (-ve)
Low (-ve)
Impact AQ3: PM10 emissions due to activities at the quarry and the vehicle entrainment of dust affecting air quality of nearby villages
Medium (-ve)
Low (-ve)
Impact AQ4: Dust emission from activities at the cement plant affecting air quality for nearby communities
Medium (-ve)
Low (-ve)
Impact AQ5: Gas (SO2, NOx and CO) emissions from activities at the cement plant affecting air quality for nearby communities
Medium (-ve)
Low (-ve)
Impact GH1: Increase in greenhouse gas emissions in the area resulting from the cement plant
Medium (-ve)
Low (-ve)
Impact NV3: Continuous noise resulting from daytime operations of the quarry, cement plant and associated infrastructure
High (-ve)
Low (-ve)
Impact NV4: Continuous noise resulting from night-time operations of the cement plant and associated infrastructure
Medium (-ve)
Medium (-ve)
Impact NV5: Air blast pressure and vibration resulting from blasting at the quarry
High (-ve)
Medium (-ve)
Impact EB10: Loss or disturbance of fauna species of special concern due to collisions and noise disturbance
Medium (-ve)
Medium (-ve)
Medium (-ve)
Low (-ve)
Medium (-ve)
Low (-ve)
Impact EB13: Modification or degradation of aquatic habitats due to pollution or nutrient loading
High (-ve)
Medium (-ve)
Impact EB14: Impeded photosynthesis and transpiration rate of plants due to dust generation
Medium (-ve)
Low (-ve)
Impact SL5: Chemical spills and release of contact water resulting in permanent loss of soil, and change in soil characteristics, land
capability and land use
Medium (-ve)
Low (-ve)
OPERATIONAL PHASE
Biophysical impacts
Air quality
Greenhouse
Gases
Noise and
Vibration
Ecology &
Biodiversity
Soils, land
capability &
Page 15
Impact Significance
Impact
groups
land use
Identified impacts
Premanagement
Postmanagement
Impact SL6: Operational activities causing increased erosion, resulting in a permanent loss of soil resource, and change in soil
characteristics, land capability and land use
Medium (-ve)
Low (-ve)
Impact WR4: Contaminated stormwater runoff from roads and other surfaces affecting surface and groundwater quality
High (-ve)
Low (-ve)
Impact WR5: Discharge of contaminated pit water to surface water resources, affecting downstream users
High (-ve)
Low (-ve)
Impact WR6: Risk of flooding of project infrastructure due to placement within the 1:100 year floodline
Medium (-ve)
Low (-ve)
Impact WR7: Dewatering of the quarry resulting in groundwater drawdown and reduced contribution to surface water baseflows and
wetlands, affecting users
High (-ve)
Medium (-ve)
Impact WR8: Stormwater inflows into the pit, reducing surface water flows and availability to users
High (-ve)
Medium (-ve)
Impact WR9: Raw water abstraction for the project reducing availability to other users
Medium (-ve)
Low (-ve)
Impact WR10: Seepage from waste affecting surface and groundwater quality
Medium (-ve)
Medium (-ve)
Impact WR11: Wastewater effluent discharge to streams, affecting water quality for downstream users
High (-ve)
Medium (+ve)
Impact WR12: Sinkhole formation resulting from dewatering of subsurface cavities, resulting in safety and structural stability risks
High (-ve)
n/a
Impact VI2: Loss of sense of place affecting local communities due to project infrastructure and illumination
Medium (-ve)
Low (-ve)
Impact T4: Impact on utilisation capacity on the N-1 affecting other road users
Medium (-ve)
Medium (-ve)
Medium (+ve)
n/a
Impact T6: Increased road accident rates and road safety of other road users
High (-ve)
Medium (-ve)
Impact EC4: Local and regional benefits resulting from increased Revenue to Government
Medium (+ve)
n/a
Impact EC5: Generation of direct, indirect and induced employment and income
High (+ve)
High (+ve)
Ecosystem
Services
Impact ES2: Reduced availability of natural resources and ecosystem services to local communities due to use by the project and impacts on
these resources
Low (-ve)
Low (-ve)
Population &
Demographic
Impact PD2: Influx of potential job seekers into the area and associated risks
Medium(-ve)
Low(-ve)
Water
Resources
Visual
Traffic
Socio-economic impacts
Economic
Impacts
Page 16
Impact Significance
Impact
groups
Identified impacts
Premanagement
Postmanagement
Movement
Impact HS5: Increased chances of the spread of communicable diseases such as HIV/AIDS and STDs linked to influx of predominantly
male job-seekers and workers
Low(-ve)
Low(-ve)
Impact HS6: Increased pressure on healthcare infrastructure due to project related influx
Medium(-ve)
Low(-ve)
Impact HS7: Increased risk of accidents and injuries to communities from improved roads and additional traffic
Low(-ve)
Low(-ve)
Impact HS8: The visible presence of Congolese police within the project area, and their secondment as a subcontractor for the mine security
Low(-ve)
Low(-ve)
Medium (+ve)
Medium (+ve)
Medium (-ve)
Low(-ve)
Impact EB17: Loss or disturbance of fauna species of special concern due to collisions and noise disturbance
Medium (-ve)
Low (-ve)
Impact EB18: Increased hunting/poaching of wildlife and loss of habitats for crop production
Medium (-ve)
Medium (-ve)
Impact WR13: Chemical contamination of surface water resulting from accidental spills during transportation and handling, and seepage
from waste
Low (-ve)
Low (-ve)
Impact WR14: Sedimentation of surface water resulting from erosion and runoff from exposed surfaces and roads
Low(-ve)
Low(-ve)
Impact WR15: Contamination of groundwater resulting from seepage from hazardous materials and waste
Low(-ve)
Low(-ve)
Soils, land
capacity &
land use
Impact SL7: Remediation of contaminated soils and demolition of project infrastructure, resulting in re-establishment of baseline soil
characteristics and land capability
Medium (-ve)
Low(-ve)
Air Quality
Impact AQ6: Increase in PM10 emissions resulting from land clearing, earthworks, and vehicular movement
Low(-ve)
Low(-ve)
Visual
Impact VI3: Dust generation and site disturbance due to earth moving and removal of project infrastructure, affecting the visual character for
communities
Medium(-ve)
Low(-ve)
Medium (-ve)
Medium (-ve)
Health &
Safety
Water
Resources
POST-CLOSURE PHASE
Ecology &
Biodiversity
Impact EB19: Increased hunting/poaching of wildlife and loss of habitats for crop production
Page 17
Impact Significance
Impact
groups
Identified impacts
Premanagement
Postmanagement
Water
Resources
Impact WR12: Pit lake formation due to inflow of ground and surface water, resulting in safety risks to animals and humans, and
environmental contamination
Low (-ve)
Low (-ve)
Soils, land
capacity &
land use
Impact SL8: Demolition and restoration of project infrastructure, resulting in re-establishment of baseline soil characteristics and land
capability
Medium (-ve)
Low (-ve)
Visual
Impact VI4: Re-establishment of baseline visual character due to rehabilitation of the site and removal of project infrastructure
Medium(-ve)
Medium(+ve)
Table 2: Mitigation and enhancement measures recommended to manage environmental and social impacts
Project Phase2
Impact
category1
DC
PC
Undertake stripping, stockpiling and stockpile management as per the Soil Management Plan (Section 9.5 of ESIA).
Revegetate and landscape disturbed areas as soon as possible, to reflect the surrounding topography and vegetation.
VI
Consider the use of screening tools such as dense vegetation where practical and appropriate to the surroundings.
VI, WR, EB
Clear vegetation in phases so that only those areas required for immediate development are cleared.
VI, WR
Implement the waste management plan for the project (Appendix 15).
VI
Use directional lighting in areas operating at night, if communities are affected by lighting.
VI, SL
Implement the Closure and Rehabilitation Plan as described in the report to support the proposed project.
SL
Implement livelihood restoration and compensation measures in areas where livelihood are impacted by the loss of agricultural lands.
VI Visual impacts; SL Soils, land capability and land use; AQ Air Quality; WR Water Resources; NV Noise and Vibration; EB Ecology and Biodiversity; T Traffic; PD Population and Demographic
Movement; HS Health and Safety; LN Land and Natural Resources; CH Cultural Heritage; EC Economic Impacts; ES Ecosystem Services; GH Greenhouse gases; SR Safety Risks
2
Page 18
Impact
category1
Project Phase2
Proposed Mitigation / enhancement measures
C
SL
Assist community members where livelihood impacted with establishing new agricultural areas on land of equal or better land capability.
SL, SR
The preparation of procedures to ensure that spillage during mobile equipment maintenance is minimized, and that only designated areas are used for this
purpose.
SL, EB, SR
The provision of appropriate secondary containment (to hold 110% of the stored volume) in areas where hydrocarbons, solvents and other potentially
hazardous materials are stored.
SL
Implement emergency preparedness and response measures plan as described in Section 9.6.
SL
Apply dust suppressants to sections of roads used routinely by vehicles that pass through and close to villages;
Locate stockpiles within site boundaries considering the location of potential sensitive receptors and the predominant wind direction;
Design road alignments to minimize travel distances and eliminate unnecessary traffic;
AQ, WR, VI
Cover vehicles carrying dusty materials to prevent materials being blown from the vehicles;
Set speed limits to minimize the creation of fugitive dust within the project boundary;
AQ, GH
AQ
Limit vehicle idling and keep vehicles well maintained to minimize particulate and gaseous emissions;
AQ
Where possible, biomass burning should be considered and a schedule should be maintained to allow for pollutants to disperse into the atmosphere in a short
amount of time;
AQ
AQ
Vegetation and soil should be removed together (mixed) so that the plant matter helps to hold the soil. Alternatively, vegetation can be stripped and
stockpiled and then spread over the newly made stockpiles of soil
AQ
Biomass burning should be conducted during the during the day and during the summer months;
AQ, WR, VI
Minimise vegetation clearing. As the quarry expands, clearing should not take place a long time in advance of quarrying. Planned planting of trees and
vegetation outside the quarry limits will minimize spreading of dust to surroundings
Where practical, rehabilitation of the quarry should be progressive i.e. it should be implemented as soon as a section is worked out
AQ, GH
DC
PC
Page 19
Impact
category1
Project Phase2
Proposed Mitigation / enhancement measures
C
AQ
Install spray bars, enclosure of transfer points or other means of control will be employed as necessary to ensure dust emissions from the crushing and
conveying systems is properly managed to meet emission and ambient air quality targets
AQ
Start-up conditions should be short as possible as this will reduce emissions during this process
AQ
Develop an emergency response plan for Mbamba village to include on-going training and drills with the villagers. Impacts are likely to occur when the
prevailing winds are towards the village during an upset condition.
AQ
Start-up should be delayed when the prevailing winds are towards the village.
WR
Where contaminants are transported along construction roads, emergency contaminant and mitigation measures must be developed to minimize impacts
should accidental spillages occur along the transport routes
WR
Equip all trucks and equipment carrying fuels or oil with spill response materials and train personnel in the use of such materials
WR, EB, SR
Store all potential sources of contamination in secure facilities with appropriate Storm Water management systems in place to ensure that contaminants are
not released to the water resource through Storm Water runoff
Use oil & silt traps to remove these types of contaminants from stormwater, and use designated areas for equipment servicing
WR
Construct access roads and infrastructure in a way that sensitive ecosystems are avoided;
WR, EB
Ensure that proper designs are prepared and implemented to manage stormwater runoff in a manner that minimizes sediment transport to the receiving water
resource and minimizes erosion along runoff channels.
WR
Prioritise construction of a properly lined and designed waste landfill site and sewage treatment system as early as possible
WR
Implement a stormwater management plan which will separate dirty water from clean water and divert run off from dirty areas to a pollution control dam
which should have a silt trap to settle any sediment
WR
Re-use water from the pollution control dam as a first resort. Only discharge after treatment and compliance with discharge limits can be demonstrated
WR
WR
Optimise water reuse and reclamation within the mining operations, to limit raw water abstraction
WR
Where practical, intercept clean ingress water as close as possible to its source in order to prevent or minimize water quality deterioration and to allow this
water to be pumped up to surface for appropriate use or discharge
WR
If possible, undertake dewatering upgradient of the quarry to keep the pit dry and prevent water quality deterioration.
WR
Discharge pumped underground water into a dam for treatment and possible re-use as a first priority rather than discharging into the surface water resource
DC
PC
Page 20
Impact
category1
Project Phase2
Proposed Mitigation / enhancement measures
C
WR
Undertake flood line study investigation to establish 1:100 year flood line
WR, SR
Locate plant, associated infrastructure, material storage areas and quarry outside the 1:100 year floodline
WR
Construct cut-off trenches and storm water control measures to contain the 1:100 year flood event
WR
WR
Ensure water supply for domestic and agricultural purposes to communities affected through dewatering activities
WR
If necessary, treat removed groundwater to a quality that is suitable for discharge to streams and agricultural use
WR
Monitor discharge water quality to ensure it is compliant with the necessary guidelines.
WR
Cut-off trenches to be installed around the pit perimeter to manage the extent of inflows (divert clean water away from the pit)
WR
Discharge treated effluent into streams to compensate for abstraction losses (provided it meets the quality criteria)
WR
Especially ensure the removal of nitrates from treated water as streams and rivers already contain elevated nitrate background concentrations;
WR
Water to be discharged need to comply with maximum concentrations of contaminants in waste water as per Article 66 of Congolese Law.
WR
Undertake monthly monitoring up-gradient and down gradient of the discharge point
WR
Design the waste landfill in accordance with the requirements (eg lining and cover) for the type of waste handled
WR
Cap waste landfill facility after closure to limit artificial recharge and seepage forming
WR
WR, EB,HS
Restrict access (and ingestion of pit water) by animals and humans by fencing the pit.
NV
NV
Restrict blasting at the quarry to afternoon hours 14:00 to 17:00 pm, or employ alternative techniques to avoid blasting.
NV
Change the alignment of the haul road to bypass Yuku Village (or relocate the village)
NV
Implement noise screening measures for the mills in the plant design (or relocate Mbamba village)
EB, ES
All cleared or degraded areas that do not form part of NYAs operations must be rehabilitated to a stable ecological state, as close to the pre-construction
condition as practically possible;
DC
PC
Page 21
Impact
category1
Project Phase2
Proposed Mitigation / enhancement measures
C
EB, ES
A Rehabilitation Plan to be developed and implemented (overseen by an appropriately qualified botanist/ecologist), with different objectives and
rehabilitation approaches established for each habitat/ecosystem.
EB, ES
A Biodiversity Action Plan to be developed to inform NYAs protection and management of biodiversity in the entire concession.
EB, ES
Gallery and Swamp forest to be avoided to the greatest practical extent possible (including road and powerline alignments);
EB, ES
A No-Go buffer of 50 m to be established around Gallery forest present in the north of the proposed overburden stockpile. No spoiling of material may be
undertaken upgradient of this Gallery Forest. No spoiling of material to take place to the west of the existing (most western) road to the proposed spoil site, to
avoid impacts to the extensive swamp and Swamp forest system west of the road;
EB, ES
The proposed haul road should be constructed via an upgrade of the existing road to the west of the current staff camp, as opposed to the development of a
new road through/over the Yuku River to the east of the camp;
EB, ES
Re-shaping of slopes near Gallery and Swamp forest to be avoided to the greatest practical extent possible;
EB, ES
Remaining Forest habitat that has been degraded must be restored to their pre-construction condition;
EB, ES
Construction in or near to wetlands, swamps, streams and rivers must be avoided to the greatest practical extent possible, including the road and powerline
alignments;
EB, ES
The plant, railway siding and haul road must not be moved any closer to the Kawenga wetland (immediately west of plant) and no construction or
earthmoving activities may take place within 50m of the wetland and the swamp surrounding it. The plant site must be fenced and no slope/bank
modifications may be conducted along the eastern boundary of the plant site;
EB, ES
A stormwater management plan must be developed for all project components to address stormwater run-off volumes, velocity, water quality to minimise
impacts on natural areas, focussing on minimising increased sedimentation of the wetlands and swamps,
EB, ES
The largest practically possible size of culvert/s to be installed at any stream/swamp crossings, particularly at the intersection of the proposed haul road and
current railway line, to minimise impacts on the hydrological regime and aquatic habitat loss
EB, ES
The alignment of the new powerline must avoid the southern catchment of the Mbamba wetland (immediately east of plant) to the greatest practical extent
possible;
EB, ES
A No-Go buffer of 100 m should be established around all other wetlands, with the exception of the proposed roads, where site clearing and bank
modification must be minimised the greatest practical extent possible;
EB, ES
Aquatic habitats and areas immediately adjacent to them that have been degraded during the construction phase must be restored to their pre-construction
condition;
EB, ES
Sessile fauna present at construction sites to be relocated by appropriate experts prior to the commencement of site clearing;
DC
PC
Page 22
Impact
category1
Project Phase2
Proposed Mitigation / enhancement measures
C
EB, ES
EB, ES
An environmental education training programme to be developed and implemented, including regular refresher sessions;
EB, ES
Effective penalties (e.g. fines) must be imposed for the hunting or harm to fauna by any staff;
EB, ES
No diversions or bank modifications to any of the rivers, streams, wetland and swamps must take place;
EB, ES
The ecological water requirements of the aquatic ecosystems should be determined. Water abstraction from any of the rivers and from groundwater must not
exceed levels that result in the ecological water requirements of the aquatic ecosystems being compromised. Abstraction from the wetlands and swamps must
not be allowed;
EB, ES
Natural fire regimes in the study area to be allowed to continue, or active management must be instituted to mimic natural regimes as advised in the
Biodiversity Action Plan.
EB, ES
A weir or gabion system must be constructed at the toe of the Kawenga and Mbamaba wetlands if increased run-off into these wetlands results in associated
erosion immediately downstream of these systems. The weirs must be constructed to maintain the natural water levels of the wetlands and must not facilitate
increased flow out of the wetlands;
EB, ES
A programme for the control of alien invasive plants in the concession to be developed and implemented as a component of the Biodiversity Action Plan.
EB, ES
Bird collision minimisation technologies (e.g. bird flappers) to be installed on the new powerline from the grid station at Kimpese to the plant to minimise
collisions. The most appropriate technology is to be determined by an experienced ornithologist;
EB,ES
The waste water treatment plant to be located at least 100m from all wetlands.
EB,ES
Areas immediately adjacent to important habitats (e.g. lacustrine wetlands, swamps, Gallery and Swamp Forest) that have been degraded must be restored to
their natural, pre-construction condition;
EB, ES
All other cleared or degraded areas that are not identified in the closure plan for alternative commercial use (e.g. utilise the plant site for a new factory) must
be rehabilitated to a stable ecological state as close to the pre-construction condition as practically possible.
EB, ES
NYAs social and labour plan to address the provision of sustainable, alternative livelihoods upon cessation of operations
Widening of the N-1 at the access road to allow for turning lanes and reduce the potential for accidents and congestion at this intersection.
Clear signage and traffic calming measures on the N-1 warning motorists of the intersection would reduce potential traffic safety impacts at this intersection.
Truck staging and/or rest area to enable trucks to exit the N-1 safely, and enable site staff to schedule deliveries in an orderly manner.
Provision of temporary on-site accommodation for construction personnel to limit the volumes of daily commuter traffic to the project site;
DC
PC
Page 23
Project Phase2
Impact
category1
Provision of dedicated buses for construction personnel not accommodated on the site to reduce daily commuter traffic to the project site;
NYA to specify maximum loads for shipping of equipment to site (size and weight).
A maintenance schedule for all vehicles directly under the control of NYA must be developed and implemented to ensure ongoing roadworthiness of
vehicles. Suppliers, contractors, and sub-contractors must be instructed to implement the same maintenance schedule
Random inspections for roadworthiness of all vehicles entering or leaving the site must be implemented
NYA management to pursue the revitalisation of the rail network with the relevant authorities.
Rest area for drivers should be implemented, and maximum driving hours per driver established and enforced.
PD
Optimise the use of local labour as far as practically possible as per the Labour and Human Resources Management Plan (Appendix 11).
PD
Develop a code of conduct with which contractors and their employees must comply. The code should deal with the interaction with local communities and
substance abuse among other things.
PD
Implement the Stakeholder Engagement Plan (Appendix 17) which clarifies the principles of engagement with community and other stakeholders, sets in
place appropriate liaison forums and describes the grievance management procedure to be adopted by NYA.
PD
Develop and communicate a clear and concise employment and recruitment policy to prevent opportunistic job seekers from settling in the area (Appendix
17)
Develop a comprehensive HIV/AIDS program to employees through employee wellness programmes which should include the following:
PD, HS
Awareness campaigns targeting project workers, senior management, contractors, sub-contractors and their spouses, communities near project facilities,
risk groups (commercial sex workers, truck drivers)
Prevention, voluntary counselling for HIV testing, as well as anti-retroviral treatment for employees and surrounding communities. There are already
HIV/AIDS programs developed by Kimpese Hospital, which NYA could potentially be involved in.
PD, HS
HS
Develop an MOU with the Local Healthcare Centres in Minkelo and Kimpese for service provision to the local workforce and their dependents
HS
Identify NGOs in the area that might support operations at the Minkelo Clinic and Kimpese Hospital, with special focus on refurbishment of key areas,
equipment and building maintenance, as well as, improved healthcare management information systems.
HS
Develop and implementation community development/sustainability plans to support infrastructure development in the area
HS, T
Awareness campaigns in neighbouring communities, particularly at Nkonda village, with a focus on school children and mothers, about risks related to traffic
DC
PC
Page 24
Project Phase2
Impact
category1
HS, T
Enforcement of speed limits and sanctions for any personnel found in violation of speed limits, including senior staff and contractors and sub-contractors
employees
HS, T
Appropriate signalling of moving heavy machinery, and escort vehicles where needed
HS, T
All drivers to be given safety education focussing on speed and conflicts between pedestrians and cyclists.
HS, T
Advanced warning signs including sirens to be erected at locations of high pedestrian and cyclist activity
HS
Develop a code of conduct for police personnel, especially in relation to handling community violence
HS
Proper screening of appointed security personnel to ensure they were not implicated in human rights abuses in the past
HS, EC
Monitor the use of violence by the mine security in instances of labour unrests
LN
Implementation and updating of the Resettlement Action Plan (RAP) (Appendix 18)
CH
CH
The work activities must be monitored to successfully mitigate any chance finds.
CH
A CHMP should be developed to manage and conserve the sites located on the periphery of the development footprint. This plan should include all sites
recorded in the project area and make provision for communication channels to follow in the case of chance finds, and ensure that the sites are monitored and
protected from any adverse development effects..
CH
Demarcate Site 36 (Nkondo Sacred Tree) prior to construction, facilitating preservation or accidental impact of the site by avoidance. In the case of Site 16
(Yuku Village cemetery) this will have to be agreed with by family members.
CH
If Site 16 (Yuku Village cemetery) is to be preserved in-situ the site will have to be fenced off with an access gate for family members.
GH
Implementation of GHG Management Plan (Appendix 14) including the development of a GHG inventory and ongoing programme of GHG emission
reduction initiatives
GH
SR
To reduce the risk of injury the Project will conduct blasting in accordance with international safety standards
Open pit blasting will be conducted using standard mining industry practices and procedures for securing personnel and equipment. This includes the
development and implementation of standard operating procedures, blasting rules and a safety management plan that:
SR
Delineates the danger zone associated with each blast and clear workers from this zone before, during and after each blast; and
DC
PC
Page 25
Project Phase2
Impact
category1
SR
Design hazardous material containment structures taking into consideration natural hazards and the implications of these on structural integrity of the
containment facilities.
SR
Pave fuel delivery and dispensing pump areas and design these areas to drain into the adjacent storage tank containment areas.
Develop and implement a Spill Prevention Control and Countermeasure Plan for the site.
SR, WR, SL
Standard international good practice will be followed with regard to storage and handling of hazardous materials.
SR
Occupational health and safety guidelines with regard to safe working conditions and the use of PPE will be adhered to
SR
Fire extinguishers will be available at storage areas for flammable substances, and a fire water system will be installed, servicing the plant and
accommodation areas.
EC
Stipulate in the Recruitment Plan mechanisms to employ local workers if applicants with the appropriate skills are available.
EC
EC
Work closely with the community before and during the project to identify and publicise skills and resources that the local community could provide.
Establish relevant mechanisms in the relevant social and labour plans.
Explore opportunities with local and regional businesses to diversify the local and regional economic base and local skill level, thereby providing workers
with opportunities for alternative employment. Initiatives in this regard should be undertaken throughout the project lifetime and include:
Develop a Grievance Procedure to capture and address grievances arising due to retrenchments and downscaling.
EC
EC, ES
Implement the Resettlement Action Plan and Sustainable Development Plan (Appendix 19 and 20) to maximise community resilience and ensure fair
compensation where resources are directly affected.
ES
The project must comply with GIIP for air emissions, water (stormwater and effluent) discharge quality and solid waste disposal
DC
PC
SRK Consulting: Project No: 463574 Updated ESIA for NYA Cement Project Executive Summary
Page 26
Figure 2 below indicates how the EMP and SMP interrelate in an overarching Environmental and Social Management
System (ESMS) framework. Table 3 summarizes mitigation and management measures for environmental and social
impacts from project activities for all project phases. Management measures contained in the main body of the
document cover soil, biodiversity, air quality and stormwater management, as well as closure planning. Stand-alone
plans have been developed to cover, labour and human resources, occupational health and safety, community health and
safety, greenhouse gas (GHG) emission, waste management, emergency preparedness and response, stakeholder
engagement, resettlement, as well as sustainable development.
Figure 2: Diagrammatic representation of the interrelationship between the Social Management Plan and the
Environmental Management Plan
SRK Consulting: Project No: 463574 Updated ESIA for NYA Cement Project Executive Summary
Plans to be
developed
further by
NYA prior to
construction
Page 27
To be
developed
prior to
closure
SRK Consulting: Project No: 463574 Updated ESIA for NYA Cement Project Executive Summary
Page 28
8. Monitoring Program
This section shall summarise the surveillance and monitoring activities proposed in the
Environmental and Social Management Plan prepared for the project. It shall identify the roles and
responsibilities of stakeholders in the implementation as well as the estimated cost of the activities.
Table 4 presents the environmental monitoring plan for construction and operation phases of the
project. Compliance with the environmental standards as prescribed by DRC Mining Regulations
and the IFC, EHS Guidelines are the criteria for all environmental parameters.
As monitoring is frequency-based, a detailed costing for implementation of the monitoring plan
cannot be provided. Estimated cost ranges are therefore provided in Table 5 based on the labour,
equipment and consumables typically required for projects of this nature, and NYAs organisational
structure.
Responsibilities of stakeholders in EMP/ SMP
NYA/borrower: (i) Implement the ESMS including the EMP /SMPP in accordance with national
legal requirements and international standards; (ii) Meet the requirements of lenders in covenant
documentation; (iii) Report to stakeholders on performance on a regular basis; (iv) Undertake
capacity building with local communities on environmental and social issues including rights and
responsibilities
Lenders: (i) Monitor NYA performance in relation to its covenants; (ii) Sanction poor performance
and non-compliance where appropriate; (iii) Implementing agencies.
Communities: (i) Monitor implementation of the ESMS by NYA; (ii) Actively participate in
stakeholder forums including any development foundations; (iii) Make use of the NYA grievance
mechanism to communicate issues with the company; (iv) Government specifically the DPEM
and Ministry of Environment; (v) Monitor legal compliance; (vi) Monitor the ESMP
implementation and review performance reporting; (vi) Ensure transparent and efficient decision
making on permit applications; (vii) Sanction poor performance and non-compliance where
appropriate through directives, penalties and fines.
SRK Consulting: Project No: 463574 Updated ESIA for NYA Cement Project Executive Summary
Page 29
Table 4: Environmental and social monitoring plan for the construction and operation phases of the project
Environmental
component
Monitoring parameters
Reference location/3
monitoring point
Project
Phase4
Implementin
g Body
Regulatory
Body
NYA
DRC Regional
Mining
Department
NYA
DRC Regional
Mining
Department
WATER:
Drinking Water
quality
3
4
1.
2.
Refer to Erreur ! Source du renvoi introuvable. for monitoring locations for surface water quality and flow and air quality.
Project phases abbreviated as follows: C = Construction; O = Operation
SRK Consulting: Project No: 463574 Updated ESIA for NYA Cement Project Executive Summary
Environmental
component
WATER:
Surface Water
Quality
Monitoring parameters
Reference location/3
monitoring point
1.
2.
3.
4.
5.
6.
7.
8.
9.
WATER:
Treated sewage
effluent quality
1.
2.
Page 30
Monthly
Project
Phase4
Implementin
g Body
Regulatory
Body
NYA
DRC Regional
Mining
Department
NYA
DRC Regional
Mining
Department
pH to be measured on site
If not using a commercially purchased preacidified container for the dissolved metals in
water, filtered metals- in-water samples should be
preserved
X
X
The quality standards published as an annexure to the Decree No 038/2003 refers to surface water quality and not necessarily discharge standards (Development Bank of Southern Africa, 2012)
SRK Consulting: Project No: 463574 Updated ESIA for NYA Cement Project Executive Summary
Environmental
component
Monitoring parameters
Reference location/3
monitoring point
Page 31
Project
Phase4
Implementin
g Body
Regulatory
Body
NYA
DRC Regional
Mining
Department
NYA
DRC Regional
Mining
Department
ECOLOGY:
rehabilitation of
disturbed habitats
(including forest
and aquatic
habitats)
Continuously
NYA
DRC Regional
Mining
Department
ECOLOGY:
Rehabilitation of
spoil areas
Continuously
NYA
DRC Regional
Mining
Department
ECOLOGY:
Flora and Fauna
NYA
DRC Regional
Mining
Department
WATER:
Groundwater
Quality
WATER:
Groundwater
quantity
If not using a commercially purchased preacidified container for the dissolved metals in
water, filtered metals- in-water samples should be
preserved
SRK Consulting: Project No: 463574 Updated ESIA for NYA Cement Project Executive Summary
Environmental
component
Monitoring parameters
Reference location/3
monitoring point
Page 32
Project
Phase4
C
WASTE
MANAGEMENT
WASTE
MANAGEMENT:
solid waste disposal
WASTE
MANAGEMENT
AIR QUALITY
(See section
Erreur ! Source
du renvoi
introuvable.)
AIR QUALITY
(See section
Erreur ! Source
du renvoi
introuvable.)
Continuously
Regulatory
Body
NYA
DRC Regional
Mining
Department
NYA
NYA
NYA
DRC Regional
Mining
Department
NYA
DRC Regional
Mining
Department
DRC Regional
Mining
Department
n/a
X
All the kiln / Preheater stack and
Vehicles
Implementin
g Body
SRK Consulting: Project No: 463574 Updated ESIA for NYA Cement Project Executive Summary
Environmental
component
Monitoring parameters
NOISE:
ambient continuous
noise
LAeq
(A-weighted
equivalent
continuous
sound pressure level)
TRAFFIC
Project
Phase4
C
Implementin
g Body
Regulatory
Body
NYA
DRC Regional
Mining
Department
NOISE:
blast noise
Reference location/3
monitoring point
Page 33
Monitor roadworthiness of
all
vehicles
(NYA,
contractors,
and
subcontractors) entering or
leaving the site.
Monitor speed limits on all
mine related traffic.
Continuous
NYA
DRC Regional
Mining
Department
X
n/a
X
NYA
SRK Consulting: Project No: 463574 Updated ESIA for NYA Cement Project Executive Summary
Environmental
component
Monitoring parameters
Visual inspection.
Monitoring criteria should be
established based on reference
areas and the post-mining land
use being re-established.
Reference location/3
monitoring point
Page 34
Project
Phase4
including Monthly
Inspect activities for the implementation of
mitigation
measures
including
soil
salvage/management, storm water controls, etc. Keep
record of inspections and areas visited; and
Inspect chemical
containment areas.
and
material
storage
Implementin
g Body
Regulatory
Body
n/a
NYA
area
Annual
Record total and new areas disturbed, volume of soil
salvaged, and areas where reclamation is complete;
SOILS:
Contamination and
erosion
CULTURAL
HERITAGE
GREENHOUSE
GASES
NYA
DRC Regional
Mining
Department
NYA
n/a
NYA
DRC Regional
Mining
Department
SRK Consulting: Project No: 463574 Updated ESIA for NYA Cement Project Executive Summary
Environmental
component
Monitoring parameters
Reference location/3
monitoring point
Page 35
Project
Phase4
C
RESETTLED
HOUSEHOLDS
Implementin
g Body
Regulatory
Body
NYA
DRC Regional
Mining
Department
NYA
DRC Regional
Mining
Department
ECONOMIC
DISPLACEMENT
RESETTLED
VULNERABLE
GROUPS
Monitor livelihoods of
resettled community,
particularly vulnerable
households (women, elderly,
children, disabled)
NYA
DRC Regional
Mining
Department
SUSTAINABLE
DEVELOPMENT
PLAN
Agreed development
initiatives
NYA
DRC Regional
Mining
Department
Progress in implementation
Evaluation of impacts
SRK Consulting: Project No: 463574 Updated ESIA for NYA Cement Project Executive Summary
Environmental
component
Monitoring parameters
Page 36
Reference location/3
monitoring point
Project
Phase4
C
COMMUNITY
AND HEALTH
AND SAFETY
Implementin
g Body
Regulatory
Body
NYA
DRC Regional
Mining
Department
NYA
DRC Regional
Mining
Department
NYA
DRC Regional
Mining
Department
NYA
DRC Regional
Mining
Department
All employees
Occupational Health and Safety Plan
(See Appendix 12)
CONSULTATION
AND
DISCLOSURE
CONTRACTOR
MANAGEMENT
SRK Consulting: Project No: 463574 Updated ESIA for NYA Cement Project Executive Summary
Environmental
component
Reference location/3
monitoring point
Monitoring parameters
Page 37
Project
Phase4
C
EMPLOYMENT
Regular
and
accessible
dissemination of the human
resources and employment
policy to interested and
affected communities
Implementin
g Body
Regulatory
Body
NYA
DRC Regional
Mining
Department
6-monthly
Feedback to community development forum
NYA
DRC Regional
Mining
Department
Quarterly
Meetings with key authorities dealing with health, local
infrastructure and mining
NYA
DRC Regional
Mining
Department
Adherence
Conventions
to
ILO
CONSULTATION
WITH
AUTHORITIES
The estimated cost for implementing the ESMP is estimated to USD 418,000 575,000 USD per annum (table 5). This cost will be covered by the
sponsor. In addition to this cost, NYA will finance the community development related activities (as listed under the complementary initiatives) for
SRK Consulting: Project No: 463574 Updated ESIA for NYA Cement Project Executive Summary
Page 38
an amount of 575,000 USD. It should be noted that this cost does not include those of the measures that will be included directly in the contractors
contract.
Table 5: Estimated potential cost ranges for implementation of the management plans outlined in Table 4
Item
Amount /
allocation
LABOUR
Sustainable Development Manager
Responsibilities:
Manage the support team of environmental, health and safety, and community coordinators to implement the ESMS.
Prepare monitoring reports for submission to the General Manager and to stakeholders and the DPEM.
Responsibilities:
Review and analysis of monitoring results and preparation of reports to management and stakeholders.
Planning of and carrying out of training programs for employees and contractors.
Obtaining and maintaining all necessary permits in liaison with the Manager Legal.
Responsibilities:
Sampling and data capture in accordance with the environmental / safety / social monitoring program and analysis of
results.
Assistance with the preparation of environmental / safety / social monitoring reporting and permit applications.
5% cost of
employment
SRK Consulting: Project No: 463574 Updated ESIA for NYA Cement Project Executive Summary
Page 39
10% cost of
employment
SRK Consulting: Project No: 463574 Updated ESIA for NYA Cement Project Executive Summary
Page 40
SRK Consulting: Project No: 463574 Updated ESIA for NYA Cement Project Executive Summary
Page 41
SRK Consulting: Project No: 463574 Updated ESIA for NYA Cement Project Executive Summary
Page 42
12. Conclusions
This ESIA update has (where possible within the given timeframes) filled the gaps identified by
ERM relating to the ESIA by ECTECH. Data gaps, particularly relating to surface and
groundwater, were identified and will be addressed before the project design and layout is finalised.
Potential impacts that may result from each phase of the project were identified and the significance
of each impact was rated (see Table 2 for summarised impact ratings both before and after the
implementation of the recommended mitigation or enhancement measures).
Based on this
assessment conducted using the available information, all potential impacts initially rated as a high
negative significance are expected to be mitigatable to a rating of medium or lower negative
significance with effective implementation of the management measures listed in Table 3.
A number of key actions and further studies for NYA to undertake prior to construction have been
highlighted in the ESIA. These relate to the following: (i) Finalisation of the project layout and
SRK Consulting: Project No: 463574 Updated ESIA for NYA Cement Project Executive Summary
Page 43
description (based on the results of additional studies); (ii) Gaps in baseline data; (iii) Finalisation
and implementation of Policy and management structure; (iv) Additional management plans
required.
For further information on the ESIA for the Nyumba Ya Akiba cement plant, please contact the
following persons:
NYA
SRK Consulting
M. Kurt Lonsway, Manager, Environment and Climate Change Division (ONEC-3), BP 323
- 1002 Tunis Belvdre, Tunisia. Tel.: +216 71 10 3313, Email: [email protected]