Internship Report: Railway Wheels and Axel Manufacturing
Internship Report: Railway Wheels and Axel Manufacturing
ON
ACKNOWLEDGEMENT
This Internship would not have been possible without the support of many people.
Firstly, we wish to express my heartfelt gratitude to
Sri.NATRAJ (PRINCIPAL), BANGALORE INSTITUTE OF TECHNOLOGY
who permitted us for this internship and was also abundantly helpful and offered a
valuable assistance, support and guidance.
We would also like to thank Sri.M.C.JAGATH (HOD OF THE INDUSTRIAL
ENGINEERING MANAGEMENT) who was abundantly helpful and offered a
valuable assistance support and guidance.
We would also express my great many thanks to Sri.T. SURESHA (SSE/TTC
Electrical) & Sri. M.G.SUNIL ,Sri.D.SANJEEVA RAO (SSE/TTC Mechanical),
for their valuable and constructive suggestions during planning and development of
this internship. Willingness to spend time so generously has been much appreciated.
Without their co-operation & assistance this internship would not be successful.
We would like to express out deep gratitude to Sri. M. R. SHIRISH (TechnicianAxel dept.)forhis recommendations on this Internship.
We would like to extend my thanks to the Supervisors / Technicians / operators of
RAIL WHEEL FACTORY who helped us to complete the internship and enabling us
to visit their offices to observe their daily operations and guided us in all the way.
ABSTRACT
Indian Railways is the largest railway network in Asia. The wheels and axles for the
entire Indian railways is manufactured and supplied by RWF (Rail Wheel Factory)
Yelahanka, Bangalore, previously known as the Wheel and Axle Plant.
This report contains the brief procedure carried out in Rail Wheel Factory to produce
rail wheels and axles. It contains all the process which are carried out to make the
wheels and axle. The materials required for the productions, processing & also the test
carried out on the components are such that they do not undergo any damages during
working.
Overview
The Indian Railways are one of the largest in the world under a single
management. They employ the largest manpower as compared to
any other enterprise in the country. They also own the heaviest
assets and rail track length of over 1lakh kilometres and are
operating the railways with nearly 5,300 locomotives, 39,000
passenger vehicles and 3.5lakh freight cars. The size and magnitude
of the railways can be better appreciated when we realize that their
Railways run more than 1.5lakh train kilometres every day carrying
nearly 1crore passengers and nearly 67lakh tons of originating
freight dally, there by earning over Rs.4,500crores of revenue per
annum.
While on the one hand the Railways have been striving hard to meet
the transport needs of the country and to provide more and more
amenities, they have also been struggling to improve the health of
the railways and to rehabilitate its aging assets. To achieve the
astronomical results of performance mentioned above, it is
imperative that the railways explore all possibilities of the country
becoming self-sufficient in all inputs. Not only for repairs and
rehabilitation of the aging rolling stock but also for manufacturing
additional rolling stock to meet the increasing demands as the
requirements of wheel and axle are also increasing. These are two of
the heaviest components of the Railway Wagons and coaches, which
play the most crucial role towards safety.
products (the wheels, axles and wheel sets) are precisely engineered
with
little scrap for human errors; rigid quality control and latest MIS for
production planning and control.
It has a planned capacity to manufacture 70,000 wheels of different
sizes, 23,000 axles and to assemble 23,000 wheel sets. It employs
over 2000 personnel and has an annual turnover of about 82crores.It
is an ISO 9001: 2000 and ISO 14001 certified unit for its business
processes. It has claims to the best productivity figures among
comparable industries. It has a very high level of automation in its
manufacturing facilities and has an enviable information technology
setup.The task involved in putting up this plant at a huge investment
adopting the latest technology was really stupendous and it is a
matter very great pride not only for the railway men but also for the
whole of the Nation that with the help Of Indian Engineers, workers
and Industry it has been possible to cast the first wheel In about 3
years time from the date of laying of the foundation stone.
After detailed study, It was decided to adopt "Cast Steel Technology"
for the manufacture of Wheel through the controlled pressure
pouring technique developed by M/s. Griffin Wheel Co., USA and the
"Long Forging Technology" for the manufacture of Axles, which has
been mastered by M/s. GFM, Austria (Europe) A great advantage in
adopting the Griffin Technology Is that the arising of scrap wheels,
axles, rail and heavy sections of steel from the railways own system
can be recycled to produce new wheels.
CONTENTS
WHEEL SHOP
MELTING SHOP
-
Ladle Pre-heating
Furnace
Furnace Charging
Melting
Re-carburising
Decarburising
Tapping of the metal
JOHN MOHR PIT
SPECTRO LAB
MOULDING SHOP
- Pressure Pouring
- Mould Splitting
- Hot Wheel Klin
- Sprue Wash
- Hub Stamping
- Hub Cutting
HEAT TREATMENT OF WHEELS
- Normalising
- Rim Quenching
- Tempering
- Hub Cooling
- Air cooling
WHEEL FINAL PROCESSING SHOP
- Apex Grinding
- Wheel Cleaning Machine
- Magna Glow Testing
- Ultrasonic Inspection
- Hardness Test
- Warpage Testing
- Hub Boring
- Final Inspection
AXEL SHOP
FORGING SHOP
- Billet Cutting
- Rotary Heat Furnace
- Forging
- End Cutting
- Stamping
- Normalising
- Water Quenching (only for some axels)
- Intermediate Cooling
- Tempering
- Air Cooling
MACHING SHOP
CNC Machine
CNC Station1: End Miliing, Centering & Cup
Turing
CNC Station2: Rough Turing
CNC Station3: Drilling, Reaming & Tapping
CNC Station4: Smooth Turning
CNC Station5 : Grinding
Ultrasonic test of axels
Magnetic particle testing
PRODUCTION
Rail Wheel Factory is mainly divided into two major shops, i.e. The
Wheel Shop and The Axle Shop.
WHEEL SHOP
The wheel shop is the shop where the scrap steel is melted and
wheels are prepared.
RWF manufactures cast
steel wheels by a
controlled pressure
pouring process. In this process, the raw material used is pedigree
scrap (old used wheel sets, axles etc, rejected as unfit for use by
the Railways). The scrap steel is melted in Ultra High Frequency
Electric Arc furnace. The correct chemistry of molten metal steel is
established through a Spectrometer. The wheels are eventually
getting cast in the graphite moulds, which are pre-heated and
sprayed. After allowing for a pre-determined setting time the mould
is spilt and the risers are automatically separated from the cast
wheel.
The wheel is then subjected to various heat treatments. The
wheel undergoes the process of cleaning, checking, peening and
various stages of inspections. The wheel produced by this
process requires no machining except the precession boring of
heats central hole (hub) where the axle has to be fitted.
There are different varieties and sizes of wheels produced in RWF
depending on its use, like Box Wagon, Wagon and ICF etc. All these
wheels are prepared in the same manner but differ in their
dimensions.
In Rail Wheel Factory, the wheel shop is divided into 3 departments.9
They are:
1) Melting shop
2) Moulding shop
3) Wheel Finishing and Processing Shop (WFPS)/Cleaning
1) MELTING SHOP:
Ladle preheating:
-
FURNACE
The furnace used in RWF for melting is ELECTRIC ARC FURNACE.
An electric arc furnace (EAF) is a furnace that heats charged
material by means of an electric arc.Industrial electric arc furnace
temperatures can be up to 1,800 C (3,272F). High thermal
efficiency, rapid heating, close temperature control and strict
atmosphere are few characteristics of the furnace that lead to
the production of good quality metal.
FURNACE CHARGING
The charge for Electric Arc Furnaces contains non-ferrous and ferrous
charge
Melting
Working:
Charge scrap wheels or metal cakes/skull or risers with the help
of magnet (2-2.5MT approximately)
The electrodes are lowered down. On supplying the necessary
current and voltage, an arc is produced between the electrode
and the charge material.
The initial arcing of the furnace is started on low tap (219 Volts)
with longer arcs so that the side scrap will melt fast and to
protect the roof. This is done for one minute.
The gap between the electrode and charge is maintained by
regulating the movement of electrodes so that the arc remains
between them and continuously melting the charge material. The
flux melts and forms a slag that floats on the surface of the
liquid metal. The slag prevents oxidation, refines the metal
Re-carburising of metal:
Keep the required quantity of graphite powder ready in small
quantities, filled in gunny bag; maintain the bath temperature
around 1640 Celsius minimum. Lower the electrode column into the
molten bath, such that the electrode is just inside the bath.
Introduce the graphite powder into the molten bath, near the
electrode column through the slag door. Push the cake fallen on door
inside the furnace metal bath by rabble. Put on the powder in
whichever tap is required. After 3-4 minutes of arcing, mix the bath
thoroughly using metallic rabbles. Insure that the bath is uniform
and no graphite powder is floating on the top of the bath. Take the
sample with the slag pre coated spoon from deep inside the bath.
After 3-4 min take one more sample in the similar way.
Decarburising of metal:
The temperature of the metal must be maintained around 16301640
Celsius. Coat the front end of oxygen pipe with furnace slag. Insert
the slag coated oxygen lancing pipe into the bath through the slag
door and blow the bath with oxygen at 5-6kg/cm depending on the
carbon to be reduced. After the oxygen blowing add 10-15kg of Ferro
silicon to take care of high oxidised metal, when necessary. Add 3040kgs of Ferro manganese or silicon manganese to raise manganese
level in the bath and to take care of extra oxygen in the metal. Put
on power. Mix the bath thoroughly with the rabble. After 3-4 min of
arcing, take the sample from deep inside the bath for test. Again
after 3-4 min take another check sample. The ladles are then taken
into JMP from where the metal is poured into the cope and drag
assembly for casting.
Tapping of Molten Metal
RWF uses ladle which has a capacity of 23.5 ton metal. The
refactory used is 25 mm fire clay bricks to IS 8 specification as
safety layer and 115 mm 70% High Alumina brick to
specification.
Ladle is lifted from LPH(ladle pre heat station).
The temperature is checked twice before tapping the heat.
In
the
normal
conditions,
without
ladle
delay,
1690-1695 C temperature is considered for tapping (when the
ladle preparation is over in ten minutes time and final
analysis is received within ten minutes)
O2 is used to open the tap hole from the tap hole inside. If the
tap hole does not open in time, oxygen pipe is used for tap
hole opening from the slag door side.
While tapping, care is required to see that only metal comes
out of the tap hole initially and not with the slag. This can be
done by tilting the furnace till the metal level is above the tap
hole.
Ladle should be centred properly at the tapping station so that
the metal stream strikes the centre of the ladle. Metal stream
directed onto the sides wall may cause sidewall erosion and
sidewall punctures.
Ladle lip is prepared and the ladle sidewall should be inspected
thoroughly after lowering the ladle at the slag off station (SOS)
JHON MOHR PIT
Once the slag is taken out and the chemical composition of the
SPECTRO LAB:
There are 4 stages through which the chemical composition of the
sample can be determined, they are:
Excitation
Radiation
Refraction
Harness
Inetrpretation of results
Moulding Shop
In this part of the wheel shop the molten metal is poured into the
mould box consisting of the cope and drag assembly, later the caste
wheel is separated from cope and drag assembly and is made to
undergo certain heat treatment process.
CASTING:
such
occasions,
pouring station.
Sprue Wash:
After the controlled air cooling the wheel coming out of the kiln
is at a temperature of about 400-600 degree Celsius. It contains a
little part of the runner and riser which is not removed during
splitting.
The part must be removed before the further cleaning of the wheel.
- There are three sprue wash stations and one chipping station.
- The ideal temperature at sprue wash is 425 C to 550 C. The hot
wheel kiln damper opening/closing should be adjusted accordingly.
- 25 mm dia copper coated graphite electrode is used for Sprue
wash. The electrode is required to be held correctly into the jaws of
the holder. A gap of 6 to 8 should be maintained between the
holder jaws and arcing point.
- Cracks can appear in sprue area of wheel if wheel is too hot or too
cold.Optimum temperature before sprue wash is 425C to 550C.
- If, wheel temperature is less than 380 C at sprue wash because of
delay, the wheel is off loaded. After hub cutting the wheel is
sprue ground
- At the last sprue wash station, after the spruce wash is
over, the stopper pipe is cut and the wheel is discharged after
chipping.
The station has a pneumatically activated arm having serration
cut in and also having a wire brush to dislodged and clean the
deposited metal. After the chipping operator completes the last
wheel of any heat and that wheel is hub stamped, he switches off
the power to hub stamping. The hub cutting operator now changes
the heat no. in the hub stamping machine.
- Eventually Sprue wash stations will be replaced with sprue
grinding machines because of a no. of advantages like:
Better surface finish
Less environmental hazardous.
More automation.
Less wheel defect and less wheel off load for
machining.
Hub stamping:
- After chipping the wheel is made horizontal with drag side up
and released on the conveyer.
- In the hub stamping, heat no. is hot punched on the back hub.
- Depth of punching is normally 1.5 mm.
Hub Cutting:
The centre portion of the wheel, where the axle fits in, need to be
bored in order to remove the casted portion from the wheel. This is
done by up cutting process. The hole is initially bored for a
diameter lesser than required during this process using Hub
Cutting Machine. Hence the process is also called Hub cutting
process.
- Hub cutting is done in four nos. hub cutters available. Hub cutters
1 & 2 are mechanical type. The diameter of bore is adjusted
through the cam provided.
- Hub cutter 3 & 4 are CNC type.
- Wheel temperature before hub cutting should be above 265 C. If
due to any reason wheel becomes cold, the wheel is offloaded
without hub cutting.
- Before hub cutting, the pilot hole is thoroughly cleaned up to the
end of dome on cope side.
- The top face of back hub is cleaned with a wire brush to take out
spray material and blown with compressed air.
- Wheel is centered properly with the centering device of the
machine before starting hub cutting.
1) NORMALISING FURNANCE(NF)
The first process in heat treatment is normalising. In normalising the
wheel is heated beyond upper critical temperature and soaked at
that temperature.
Normalizing is a technique used to provide uniformity in grain
size and composition throughout an alloy and to remove or release
internal stresses.
The term is often used for ferrous alloys that have been austenitized
and then cooled in open air. Normalizing not only produces pearlite,
but also bainite sometimes martensite, which gives harder and
stronger steel, but with less ductility for the same composition than
full annealing.
The other internal features os the furnace are:
Normalising furnace has 7 zonesZones 1,2,3-------pre-heating zone temp:940 C
Zones 4,5,6,7.soaking zones temp:970 C
Burners are used to heat the air because if we supply cold air into
the furnace i.e.to the wheel cracks are formed ,hence air is
heated before heating the wheel.
60 HP Blowers seen in zones 3,4,5,6,7
Apart from this automising blowers are used which split the diesel
through the 4 holes of the burner.
Recuperator .used for heating the air and for mimising the
fuel consumption.It is seen at the top of the furnace.
Dilusion blowers dillusion takes place when the flue gases
in the recuperator
Nose cooling blower..this is usually found at the end of the
charging and discharing conveyerwhich prevents the heat from
coming out the furnace
The furnace is made of refractive material (steel) which can with
stand high heat.the furnace is mounted on earth(web plate or
floating ring) which inturn rotates the furnace.the earth rotates
with the help of rack and pinion gears mounted on both the
sides of the furnace. Even rollers are also used for rotating the
furnace.These are called as hearth supporting rollers ,there are
48 outside and 48 inside.
Wheels are loaded into and removed from the furnace with the
help of charging and discharging arms which are operated
hydraulically.
Inside the furnace the wheels are placed on the PEDESALS .There
are 48 pedesals inside and 48 pedesals outside , which can
accommodate 90 wheels and remaining 3 are left for charging
and discharging ..
Here the diesel along with the compressed air is used for
generating the flame.The diesel is pumped through diesel
motor.There is also a diesel flow meter outside the furnace which
indicates how much litres of fuel are consumed for each
zones.Thermocouple is used for controlling the the temperature.
There are water troughs provided inside and outside the furnace
which acts like sealing.
The normalizing process takes about one and half hours for each
wheel.
An induced draft fan 100HP blower is used to remove the
exhaust .There 2 chimneys to release the exhaust into the air
..one with direct connection form the furnace and the other
one from the recuperator.The solid wastes are collected in the
dust collector,which filters to separate the ash contents which are
later recycled and thus avoiding air pollution.
Following time limit is followed:
Any wheel should be soaked at requisite temperature.
Total hold up of the wheel in the soaking should not be
quenchers
is
4) HUB COOLING:
On discharge from Draw Furnace, the wheel goes through
hub cooling. There are three coolers and every wheel is
cooled in all the stations. Hub cooling is done to ensure a
favourable
residual stress
pattern
in the
hub (mildly
compressive stress).
Following parameters are maintained during hub cooling
a) APEX GRINDING:
First operation on the wheel is apex grinding. Here any fine
moulds at apex of the flange which is the parting line
between cope and drag, is ground. For this purpose wheel is
given 1.25 rotations, time required is 45 secs.
- After this process, the steel balls that fall to the ground under
gravity are raised by the elevator and loaded into the tank, thus
they are reused again.
c) Magna GlowTEST:
After this steel blasting, the wheel is made to
undergo two tests namely Ultra Sonic test and Magna glow test.
Only those wheels passed in these test are sent to further processing
and the wheels with defects are sent back to machining accordingly.
The rejected wheels are sent to scrap yard and is recycled.
- This is one of the testing conducted on the wheels for detecting
surface cracks. - The magnetic or magna powder (ionic oxide)
mixed with the water is passed on the wheels which acts as a
fluroscence. Using the magnetic boom, the wheel is rotated in
360 degrees and the UV light (lower range) is passed on the
wheels , if there are any defects the fluroscence gets collected
in these cracks and appears as a straight line in the presence of
the UV rays. Also these defects are marked using the chalk.
- Wheels
having minor
defects
on plate
like crack,
inclusions
of slag, refractory, sand, graphite, asbestos or
spray which can be easily removed through surface grinding
are sent to grinding like. If grinding operation up to a depth
of 3 mm is not likely to remove the defect, the wheel is marked
for machining. The wheels are sent for magna glow testing
again.
passing the sound waves along the rim of the wheel for 1 rotation of
the wheel, if cracks are present then the sound waves will deflected.
The computer shows thespecific readings like the wheel length
(mm), no. of rotations of the wheel and the actual length of the
wheel etc. Also some graphs showing the specifications of the 6
propes. The UT machine is set in the automatic mode.
e) Brinell Hardness Testing:
Brinell hardness test is used to determine the hardness of the wheel
by applying a load of 3000kg and it is done for about 1015 secs.
The hardness number is shown on the display and the required value
is between277 to 323. The machine is operated phenumaticallyand
the rim of the wheel is also subjected to grinding in the brinell
hardness testing machine.
f) Warpage :
It is an automatic machine used to measure the flatness of the
surface of the wheels with the help of the 4 point plate and the cycle
time is 1wheel/min.
- The wheels during casting and heat treatment process
remains at high temperature. Wheels are kept horizontally on
war page stations back side up. Four nos. laser transducers
check the war page at back flange.
- During this high temperature there are chances of wheel
undergoing
a little bending. But this bending of wheels
above certain limits is undesirable for the working of the
wheel.
- The War paging process includes the balancing of the wheels
from which the defects relating to the shape of the wheels can
be detected.
- If the detected defects in the shape like bending of wheels etc.
are more than the limiting value, wheels are rejected.
Permissible war page is 1 mm.
g) Peaning Machine:
Then wheels pass through war page stations to penning
machine.This machine is used for fine finishing and polishing of the
there 2 motors placed on both the cope and the drag face of the
wheel and the steel balls are used for peaning the wheel which
blasted at a very high intensity compared to the steel balls used in
the cleaning machine. The duration of the process is about 3156
secs. Wheel is penned on the plate area, both cope and drag
sides to improve fatigue life. Through shot peening, the skin of
wheel plate is stretched beyond yield and thereby residual
compressive stress is imparted on skin layer.Shot peening is the
most economical and effective method of producing and making surface
residual compressive stresses to increase the product life of treated metal
partsto exhibit high wear and fatigue resistance
h) Hub Boring:
,MNow the wheel is taken up for hub boring. This is the
rough boring operation carried out on the wheel before it is sent
into assembly
shop.
During hub
cutting, the
centre hole
generated is of a smaller
diameter when compared to the required diameter.
This hole need to be enlarged for the axle to fit in. This hole
enlarging is done by the boring process.
- A square shaped carbide 5 point cutter tool is used for this
operation.
- The loading and discharging of the wheels is done through the
wheel loading manipulator which consists of 3 arms at 120
degree each .
- The manipulator is driven through the servo meter which is
connected to the inline gear box to transmit the power and the
gear box is a 3-stage reduction by means of planetary gear
arrangement .
- The wheel is mounted on the the chuck which rotates at 120
rpm against the stationary tool. The chuck is rotated using the
spindle motor which is belt driven.
- The boring is done for about 1.5 mins/wheel and is CNC
operated and represents the vertical lathe machine.
- The hole of 5-10 mm lesser than the axle wheel seat diameter
is
produced during this process i.e though the dia. of axel is
i) Inspection:
The wheels after boring are diverted to the inspection
section , where the inspection is done on the wheels by noting down
the respective wheel no. and the heat number. If the wheels pass the
inspection they are given a white seal P and sent to the wheel set.
If they fail they are given a yellow seal XC on them and sent to
machining section .
During the inspection they usually check for the
distance from the hub hole to the end of the wheel plate using a hub
length tool. The usual value lies between 430 to 431mm, if the wheel
satisfies these values the section pass the wheels by putting the
RDTY BOC OK on them. And if they cross this value then the
wheels are sent for machining. Apart from this other parameters are
also checked using the following tools :
AXLE SHOP
The second unit of RWF is axle shop where the railway axles are
produced. An axle is a cylindrical rod on which the wheels of
locomotives are seated and hence helps to maintain the distance
between the 2 wheels.
RWF buys high-quality vacuum degassed steel blooms from
large-scale steelmakers. Axles are manufactured from billets cut
from the blooms. These blooms are forged in a precision longforging machine supplied from M/s GFM, Austria. The billets are
heated in a rotary hearth furnace to forging temperatures. Billets
then forged in axles on a special purpose long forging machine.
The forged axles are gas cut to required length. The axles are heat
treated through various heat treatment process. The physical
properties are confirmed before machining of the axles. The forged
axles are machined on various machines. The operations include
end machining, rough turning, finish turning, machining centers,
grinding and burnishing.
The railway axle is a long thick cylindrical rod made up of alloy
steel and weighs about 500 kg, The axles mainly consists of 4
parts namely Body ,Wheel seat, Dust guard and Journal. Major
portion of the axle is the body whose length is fixed and is equal
the distance to be maintained between two parallel wheels. Hence
the length of the body which is the centre portion of the axle varies
The portion of the axle where the wheels of the train is fixed is
the wheel seat. The diameter and the length of the wheel seat are
completely based on the diameter of the bore in the wheel and its
thickness. The curved portion in between the wheel seat and the
journal is the dust guard. The two ends of the axle are after the
dust guard is called the journal.
The journal is the main portion which is required in a perfect
smooth finished surface state. The bearings of the train wheels
occupy this place.
In RWF the axle shop is divided into three portions where different
operations are performed on the axle.
The three portions are :
1) Forging shop:
The blooms are cut and are given the shape of
axle by forging and later heat treated in the forging shop.
2) Machining shop:
The axles to the required dimensions are
machined in the machining shop. Certain tests done to check
cracks.
3) Assembly shop:
The finished axles are assembled along with wheels in the
assembly shop.
52
Bloom Cutting
RWF makes axles for locomotives, coaches, wagons, crane &
EMUs. Axle blooms are
procured from market.
To avoid
wastage, blooms
are procured in multiple length of unit billet
length for each type of axle.
The long bar with square cross section called Blooms are cut
into small length pieces called Billets by Gas cutting. The fuel used
is Oxygen + LPG Gas (Propane gas). The gas flame with a
pressure of about 10 bar is directed on the work piece and cutting
action is performed. The cutting is based on length to weight ratio.
The blooms are of different types:
1) ICF axel bloom .287 sq.m & length 810m.
2) Diesel axel bloom340 sq.m & length 1230mm.
3) BOX N axel blooms..300sq.m & length 925mm.
Heating:
Blooms are heated in Rotary Hearth Furnace before being fed into
forging machine. Rotary Hearth Furnace is a two shell structure,
one outer and another inner. It is oil fired type.
The billets after being cut must be heated so that it can be
forged. The Rotary Health Furnace having four zones namely Preheating zone, heating zone, soaking zone 1 and soaking zone 2 is
used for heating the billets to a temperature of about 1185 - 1200
degree Celsius.
The billet first enters the pre-heating zone where the heating
process begins. Further it moves to the heating zone.
In the soaking zone 1 and 2 is the spread to the core of the work
piece. The fuel used is High Speed Diesel (HSD). The pressure
inside the RHF is set to 10 bar. The temperature of the flue gas
coming out of RHF is
around 600 degree Celsius.
The hearth carrying billets rotates in all the 4 zones. The capacity of
the hearth is 80 billets.
The furnace is fitted with 20 burners, fume extraction system,
water troughs, measuring instruments etc. Gas fumes extracted
from the furnace is used to preheat the incoming air in recuperator
unit. Billets are charged and discharged with charging and
discharging machine.
1)
FORGING SHOP
Forging is a manufacturing process involving the shaping of
metal using localized compressive forces. Forging is often
classified according to the temperature at which it
is
performed: "cold", "warm", or "hot" forging.
Forged parts can range in weight from less than a kilogram to 580
metric tons. Forged parts usually require further processing to
achieve a finished part.
Today, forging
is a
major
world-wide industry
that has
significantly contributed to the development of the manufacturing
cycles.
Forging can produce a piece that
cast or machined part. As the
forging process, its internal grain
shape of the part. As a result, the
the part, giving rise to a
characteristics.
In RWF the axle are produced by forging process. Here the long
blooms are cut into small piece called billets which are later given
the shape of the axle by forging.
Forging, because of its inherent improvement in the grain
size and introduction of uninterrupted grain flow in the finished
Component has the following advantages:
Greater toughness and strength.
Reduction of weight of the finished part.
Saving in the material.
END CUTTING:
While forging the metal, the top layer of axle ends flows along the
surface of the axle and gets collected at the ends in the forms of
fish tail and as a result piping is formed.
To eliminate this tailed structure piping and in order to maintain the
exact length of the axle, the ends of the axle are cropped using an
oxygen + high propane type end cutting machine.
Approximately 58 kgs of metal is taken out in this cutting.
The forged axles arrive from the conveyor of the Forging Machine
furnace.
AXLE QUENCHING:
Not all types of axles require quenching. Only a few types of diesel
axles are quenched in quenching agent (polymer oil) and this is
called Polymer Quenching.
The axles requiring quenching are brought in a batch of 5 axle to the
quench elevator. The elevator then carries the axles to the
quenching tank and brings back the axles after dipping them in the
polymer quench ant for pre- determined duration, generally 30 min.
Quenching is defined as sudden cooling of heated steel (metal) by
dipping in cooling agent or spraying cooling agent in order to obtain
the work piece in a stable state which induces certain properties
like hardness etc to the work piece material. A mixture of polymer
oil and water in the ratio 1:20 is used as quenching agent in forging
shop of RWF.
INTERMEDIATE COOLING :
Normalised/quenched axle is air cooled on intermediate cooling
bed (ICB) from 860 C to 300 C before being fed into tempering
furnace.
ICB is a hydraulically operated walking beam
having two fixed beams and one moving beam.
conveyor system,
TEMPERING:
Axle from Intermediate cooling bed goes to tempering done at a
temperature of 650 C. Tempering has a capacity to hold 118 axle.
The axle movement is similar to that of normalising furnace. It is
necessary to return towards equilibrium after quench hardening,
by heating the
steel
to a
temperature below
the critical
temperature. This is tempering. Tempering also reduces the internal
stresses in the axles which may have induced during heating,
forging or quenching.
Machining Shop:
The axle coming out of Forging Chamber are of dimension
greater than required, only rough shape and have very rough
surface. These axles cannot be used directly. Hence in order to
obtain exact dimensional, required shape and a perfect surface finish
machining has to be carried out.
Machining is any of various processes in which a piece of raw
material is cut into a desired final shape and size by a controlled
material-removal process.
The many processes that have this common theme, controlled
material removal, are today collectively known as subtractive
manufacturing, in distinction from processes of controlled material
addition, which are known as additive manufacturing. Exactly
what the "controlled" part of the definition implies can vary, but it
almost always implies the use of machine
tools (in addition to just power tools and hand tools).
Metal cutting is a process of removing a layer of material from
the metal blank by means of a tool, which is harder than the metal
being cut. The layer of metal is removed is called as chip and this
removal is due to plastic deformation or controlled fracture in the
metal blank.
The material is removed from both the edged simultaneously i.e. the
turning operation makes use of 2 tool at the same time in order to
reduce the time of operation.
In Rail Wheel Factory (RWF) axle machining shop rough turning is
done by both CNC lathes and conventional lathe. In the CNC lathe
the feed, the motion of the tool spindle/holder for each type of axle
is programmed and fed into the computer which guides the cutting
operation.
Various parameters like length of the axle, feed, diameter of the
axle, speed of rotation etc can be adjusted and altered by the
operator as and when required.
A tracer placed in the carriage traces the template, tool carriage and
hence the tool moves along the same shape ,hence the required
shape is obtained on the axle.
Each parameter like feed, speed, carriage movement etc can be
controlled by the operator. The process can also be automated and
can be stopped and adjusted at any point of time.
CNC STATION 3 Drilling, Reaming & Tapping
After rough turning of the axle, threaded holes are drilled at the two
ends surfaces in order to fix the bearing to the axle.
Drilling: Drilling is a machining operation of producing a cylindrical
hole in a solid work piece by means of a revolving tool called the
Drill bit. Drill bit is also called as twist drill since it has sharp twisted
edges formed around a cylindrical body. In operation, the drill bit is
held in the chuck of the machine and rotated by a spindle at high
speed. With the help of the hand wheel or by automatic means, the
drill bit is forced to move against the rigidly clamped work piece. The
hole is generated by the sharp cutting edges of the rotating drill bit
while the excess material removed (chips) gets curled and escapes
through the helical grooves provided in the drill bit .Since the cutting
action takes place inside the work piece, lot of heat is generated:
this may cause damage to the tool as well as the work piece. Hence
coolant is used to reduce the heat. Both the ends are drilled at the
same time.
Reaming: Reaming is the operation of finishing a previously drilled
hole to bring it to an exact size and to improve the surface finish of
the hole. The operation is earned out using a multi tooth revolving
tool caller Reamer, which consists of a set of parallel straight or
helical cutting edges along the length of the cylindrical tool. This
operation is carried out at a speed lower than drilling in order to
obtain a good surface finish.
Tapping: Tapping is the operation of producing internal threads in a
previously drilled hole by means of a tool called tap. The tap has
threads cut on its periphery and is hardened to improve its
properties. The threads cut on the tap form the replica of the threads
to be produced in the work piece. To generate a specific size thread
in the work piece, a hole with diameter smaller than the size of the
tap is first drilled using twist drill. To perform the tapping operation,
the tool is held rigidly in the spindle and is rotated at a speed less
than drilling operation. The rotating tap is fed slowly in the hole of
the work piece to cut the material and produce threads.
Operations are carried out simultaneously on both sides. A
continuous supply of coolant is required in order to reduce the heat
production and wash away the chips.
CNC Station 4-Smooth Turning:
The roughly finished axle in the previous station is now given a good
surface finish by turning operation. A six edged carbide tool is fixed
in the tool holder and is fed against the rotating work piece. The
feed given is very less in order to obtain the perfect finish. The axle
dimensions are same as required dimensions, with tolerance of
about 3-5 microns. These operations give finishing to the body of
axle, while the dust guard and the journal is finished by the Grinding.
Station 5-Grinding:
The journal is the most important part of the axle since this bearing
is seated on it. Hence the journal is given a perfect finish. This is
done by grinding. Here Centre less Grinding is done. The shape of
the grinding wheel is same as that of the axles, dust guard and
journals shape. Hence for different axles different grinding wheel
must be used. Two wheels are kept on both the ends to finish both
the sides of the axles. They operate one after the other. In operation
the work piece comes near to the wheel and gets fixed. Now the
high speed grinding wheel approaches the axle due to which very
fine material layer is removed from the work piece due to the action
Advantages
Sensitive to both surface and subsurface discontinuities.
Rapid Flaw Detection: Ideal for quickly locating surface and sub-surface flaws and
discontinuities in ferromagnetic material like Iron, Nickel, Cobalt, and related alloys.
Highly Adaptable: Ideal for inspection of irregular parts.
Assembly Shop
The assembly of wheel sets is done on a highly automated wheel
assembly complex. The wheel seat size of the axles is measured
on an automated measuring unit and the dimensions are
transferred to two wheel borers. Paired wheels are custom bored
as per the wheel seat size to get correct interference fit. The
wheels are then pressed on axle in a 300 T Wheel press.
In assembly shop, the wheel seat diameter is sent to a Measuring
Stationwhere it is exactly measured to each axle and wheel for the
particular axle is centre bored to the measured axles wheel seat
diameter by the vertical boring machine using octagon shaped tool.
After the smooth surface finish boring operation the two wheels for
one particular axle are sent for pressing.
The two wheels are hydraulically pressed on a Mounting Press , so
that the two wheels sit on the wheel seat of the axle by using
pressing machine one wheel after the other. This combination of two
wheels and an axle is called Wheel Set.
The pressure to be applied on the wheel for pressing each wheel
varies on different properties. Castor oil is applied on the axle during
pressing in order to reduce the pressure on the axle. The pressure
applied is recorded in the form of a graph.
The wheel sets obtained is measure by various gauges (e.g. Offset
gauge).
In case the distance between wheels is to be altered or any other
minor corrections need to be done is corrected by damping machine.
Once the wheel set is inspected, it is painted to prevent the surface
of the axle from rusting and the journal is covered and then
transported to place where rest of the body parts of the train is
manufactured.
Testing Lab
Welds, casts and forgings are tested for one or more following purposes To access numerically the fundamental mechanical properties like
ductility, malleability, toughness etc.
To determine data i.e. force deformation values to draw conclusion
upon which engineer can base his design.
To determine the surface and sub surface defects in the parts.
To check chemical composition.
To determine suitability of the material for a particular application.
Tests on these can be broadly classified as Destructive Tests- These tests are conducted inside the Metallurgical
lab (M-LAB)
After the test is conducted the material or sample is destructed i.e. it
breaks or remains no use for further use.
E.g.- Tensile Test.
Non Destructive Tests- These tests are conducted inside the
industry , for example, brinell hardness test , ultrasonic test etc.
SA component does not break in this test. It can also be used for its
purpose even after testing.
E.g.- Ultra Sonic Testing.
The M-LAB has three sections :
Physical lab
Chemistry lab
Refactory lab
Physical lab:
1. Closure Test
2. Hardness Test
3. Tensile Test
4. Yield Strength
5. Elongation
6. Reduction in Area
7. Gain structure
8. Impact Test
9. Izod Test
10. Charpy Test
11. Ultrasonic Test & Magnetic Particle Testing
Chemistry lab:
In this lab various tests are conducted on the raw materials which are used in the
melting shop such as calcium lime, ferro manganese, ferro silicon, coke, etc.
REFACTORY LAB:
In this lab the basic refactory materials such as the refactory
bricks used in the walls of the electric furnace and the high alumina
bricks used in the ladle are tested. One of the test conducted is
Refractiveness Under Load (RUL) TEST.
HMT LATHES
BOMBAY LATHE
CENTRE LATHE
MILLING MACHINE
UNIVERSAL MIILING MACHINE
COPYING TYPE MILLING MACHINE
VERTICAL KEYWAY SLOTING MACHINE
GRINDING MACHINE
VERTICAL DRILLING MACHINE
TEST ROOM:
Here the testing of the hydraulic cylinders,
hydraulic pumps & control valves are done according
to the required specifications like:
Hydraulic cylinders:
- Flow measurement
- Presuure
- Leakage
Hydraulic pumps:
- Internal leakage
- Capacity
- Flow rate
TOOL ROOM:
Here the foam tools (both cope & drag foam
tools)are made which are later sent to the mould
repair shop (MRS).These tools are used for removing
the erosion which are formed on the cope and drag
box due to the repeated moulding.